Chapter 8Water Quality and Recharge
8.1 Purpose and scope
8.1.1 This chapter sets the requirements for the quality of stormwater leaving a site or a public drainage system, and for groundwater recharge. It covers:
- (a) the water quality volume (WQv) and the water quality design flow;
- (b) the treatment train, and the selection and design of best management practices (BMPs);
- (c) the criteria for infiltration and recharge;
- (d) the exclusion of sewage and dry-weather flow from storm drains;
- (e) gross pollutant traps, first-flush treatment and screens at outfalls to waterbodies;
- (f) how rainwater harvesting (RWH) fits with retention and detention;
- (g) erosion and sediment control during construction; and
- (h) monitoring.
8.1.2 This chapter applies to every development and public work to which Chapter 4 applies (Chapter 1). Clauses 8.9 (sewage) and 8.12 (construction erosion and sediment control) apply to every development that needs a building permit or layout approval, and to every public drainage work, whatever its size.
8.1.3 Retention under Chapter 4 is the first and preferred form of water quality control. Runoff retained on site is treated in full. The rest of this chapter applies to the part of the WQv that is not retained.
8.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Water quality volume (WQv) | The runoff volume that must be retained or treated, from the water quality rainfall depth (Clause 8.4). |
| Water quality rainfall depth (P_wq) | The greater of the retention depth (Annex 2E, Clause 2.10) and the 24-hour 3-month ARI depth (Annex 8A). |
| 3-month ARI depth | The 24-hour rainfall depth equalled or exceeded on average four times a year, from a partial-duration series of the long-term daily record. |
| Water quality design flow (Q_wq) | The peak flow from the 3-month ARI storm, used to size flow-through devices and diversion structures (Clause 8.4.5). |
| Runoff coefficient for WQv (Rv) | The volumetric runoff coefficient for small storms, Rv = 0.05 + 0.009·I. |
| BMP | A best management practice: a structural or non-structural measure that reduces pollutant loads or runoff volume. |
| Treatment train | Two or more BMPs in series, from source to site to regional scale (Clause 8.5). |
| Pretreatment | A BMP that removes coarse sediment, litter and oil before runoff reaches a filter or infiltration BMP. |
| First flush | The early part of a runoff event, which usually carries the highest concentrations of sediment, litter and oil. |
| Gross pollutant trap (GPT) | A device that captures litter, plastics, vegetation and coarse sediment, typically above about 5 mm. |
| Dry-weather flow (DWF) | Flow in a storm drain when it has not rained for at least 72 hours. In a separate storm system, DWF is evidence of sewage, sullage, groundwater infiltration or illicit discharge. |
| Cross-connection | Any pipe, channel or opening that lets sewage or sullage (grey water from kitchens, bathrooms and laundries) enter a storm drain. |
| Infiltration facility | A facility designed to store runoff below the ground surface, or in a depression, and let it soak into the soil: infiltration trenches and basins, unlined bioretention, permeable pavement with an open base, soakaways, recharge pits and recharge wells. |
| Seasonal high groundwater table | As defined in Clause 3.10.2: the highest level in the SW monsoon season. |
| Hotspot | A land use with a high risk of spills or contaminated runoff (Clause 8.8.8). |
| Level of Service (LoS) / Value Rating (VR) | The scoring system of Clause 8.6, from the MARC/APWA BMP Manual (2012). |
8.3 Objectives and pollutants of concern
8.3.1 Stormwater treatment under this Manual shall aim to:
- (a) remove litter, plastics and other gross pollutants before they reach a waterbody;
- (b) remove suspended sediment, and the metals, nutrients and oil carried on it;
- (c) keep sewage and sullage out of storm drains and waterbodies;
- (d) recharge groundwater where soils and groundwater depth allow, without polluting it; and
- (e) prevent erosion and sediment discharge during construction.
8.3.2 The design shall address the following pollutants for every site, and the hotspot pollutants of Clause 8.8.8 where they apply:
Table 8.1 — Pollutants of concern, sources and primary controls
| Pollutant | Main sources in Uttarakhand towns | Primary control |
|---|---|---|
| Gross pollutants (plastics, litter, vegetation) | Streets, markets, open dumping in drains | Source collection; GPTs and screens (Clause 8.10) |
| Suspended sediment | Construction sites, unpaved roads and verges, road wear, drain silt | Erosion and sediment control (Clause 8.12); pretreatment; filtration |
| Oil, grease and fuel | Roads, parking, fuel stations, workshops, bus depots | Oil-grit separators at hotspots; bioretention |
| Pathogens and organic load (BOD) | Sewage and sullage cross-connections, animal waste | Exclusion and DWF interception (Clause 8.9) |
| Nutrients (N, P) | Sewage, fertiliser, food waste, detergents | Exclusion; bioretention; wetlands |
| Heavy metals | Roads, roofs, industrial yards | Filtration; sedimentation |
Commentary. Gross pollutants and sewage come first in Clause 8.3 because they dominate the pollution of urban waterbodies in Uttarakhand, and because no treatment BMP works for long if they are not removed. CPHEEO (2019) notes that Indian drains carry night soil, urine and food waste (Part A §9.5). In its WSUD procedure it lists TSS, total nitrogen, total phosphorus and gross pollutants as the key pollutants (Part A Ch. 10). AMRUT 2.0 funds the harvesting of rainwater "through storm water drains into water body (which is not receiving sewage/effluent)" (Lok Sabha unstarred question AU1419), which only works if sewage is first kept out of the drains.
8.4 Water quality volume and design flow
8.4.1 Water quality rainfall depth. The water quality rainfall depth is:
P_wq = max (P_ret, P_3m)
where:
- P_ret = the retention depth for the site's zone (Annex 2E, Clause 2.10), mm; and
- P_3m = the 24-hour 3-month ARI depth for the site's zone (Annex 8A), mm.
8.4.2 Water quality volume. The WQv shall be computed as:
WQv = (P_wq / 1000) × Rv × A
where:
- WQv is in m³;
- A = the contributing area, m²;
- Rv = 0.05 + 0.009·I; and
- I = the impervious percentage of the contributing area (0–100), after the connectivity rules of Clause 3.9.
The Rv form above may be used only for sites under 0.5 ha and under the Tier B simplified method (Clause 4.14). This is the same limit as for the retention volume (Clause 4.4.2). For all other sites the WQv shall be computed with the SCS-CN method, as the retention volume is: WQv (m³) = 10 × Q_wq × A, where Q_wq (mm) is the SCS-CN runoff from P_wq for each sub-area and A is in ha.
8.4.3 Climate factor. The climate factor of Clause 2.8 shall not be applied to P_wq. P_ret and P_3m are frequency statistics of ordinary rainfall, not AEP design depths.
8.4.4 WQv met by retention. The volume retained on site under Chapter 4 counts toward the WQv in full. Where the retained volume is equal to or greater than the WQv, no further treatment is required for that area, except:
- (a) pretreatment of inflows to each retention facility (Clause 8.5.3);
- (b) hotspot controls (Clause 8.8.8); and
- (c) the outfall requirements of Clause 8.10, where the site discharges to a waterbody.
8.4.5 Water quality design flow. Flow-through devices (swales, filter strips, oil-grit separators, GPTs) and diversion weirs for off-line BMPs shall be sized for Q_wq. Q_wq shall be computed from the 3-month ARI intensity at the time of concentration of the contributing area:
- (a) by the Rational Method, where Chapter 3 allows it (a single element draining no more than 16 ha); or
- (b) as the peak of a hydrograph method using the 3-month ARI 24-hour depth with the alternating-block pattern of Clause 2.9.1.
8.4.6 Bypass. Flows above Q_wq shall bypass flow-through and off-line treatment devices without washing out the material already captured. The bypass shall be part of the minor or major system (Chapter 6).
8.4.7 Drawdown. Where the WQv is held in an extended-detention BMP (wet pond, constructed wetland or dry extended-detention basin), it shall be released over 24–48 hours (Chapter 4).
Commentary. The WQv depth is the runoff from the 3-month ARI storm or the retention depth, whichever is greater. The 3-month ARI is the Malaysian water quality design storm (MSMA 2, 2012). The Malaysian 2008 checklist gave its depth as about 40 mm and said it captures 90% or more of 24-hour storm runoff volume (DID, 2008). The Uttarakhand value must be computed (Annex 8A). Georgia sets its WQv as the runoff from 1.2 inches (about 30 mm), the depth that covers 85% of storms in an average year, and requires 80% removal of the average annual post-development TSS load (GSMM 2016, Vol 1, Standard #4). Kansas City's water quality storm is the 1.37-inch (about 35 mm) event that produces up to 90% of the runoff from all 24-hour storms in a year (MARC BMP Manual, 2012).
The Rv formula is from the MARC/APWA BMP Manual (2012), which computes WQv = P × Rv with Rv = 0.05 + 0.009·I. Rv is used instead of the SCS curve number because the CN method greatly understates runoff from small storms on pervious ground. Not applying the climate factor (Clause 8.4.3) has no direct precedent; this Manual does so because it treats P_wq like the retention depth, as a statistic of ordinary rainfall. Bypass of larger flows and the 24–48 hour drawdown follow Chapter 4; MARC (2012) required at least 40 hours of extended detention of the WQv.
Illustrative — not design values. For a 1.0 ha site with 80% impervious cover and an assumed P_wq of 50 mm:
- Rv = 0.05 + 0.009 × 80 = 0.77
- WQv = (50 / 1000) × 0.77 × 10,000 = 385 m³
8.5 Treatment train and pretreatment
8.5.1 Treatment train. Water quality control shall be designed as a treatment train, in the order shown in Figure 8.1:
- (a) source controls on the plot: roof runoff to RWH, rain gardens, permeable paving, disconnection of impervious areas, and silt traps at inlets;
- (b) site controls: bioretention, swales, filter strips, infiltration, oil-grit separators at hotspots, wet ponds and extended detention; and
- (c) regional controls, for public drainage: GPTs and DWF interceptors at outfalls, constructed wetlands at tank inlets, and regional ponds.
8.5.2 A development shall meet the WQv on site, through (a) and (b). Regional controls under (c) may count toward a development's WQv only where a regional facility treating the same runoff has been built under a notified basin plan (Clause 7.11).
8.5.3 Pretreatment. Every bioretention cell, infiltration facility, permeable pavement receiving run-on, wet pond and constructed wetland shall have pretreatment at each concentrated inflow. Pretreatment shall be a sediment forebay, grass filter strip, silt trap or proprietary device that holds at least 10% of the WQv of its contributing area, or that is sized for Q_wq for flow-through devices.
8.5.4 Pretreatment shall be accessible for cleaning without entering or disturbing the main BMP.
Commentary. The treatment train follows CPHEEO (2019, Part A §10.2.3, SuDS treatment train) and CIRIA C753 The SuDS Manual (2015). It is also the order of priorities of this Manual: preserve, retain, detain, convey (Chapter 1). The 10% forebay volume has no Indian precedent; it is a common sizing rule for forebays in US manuals. In Uttarakhand, unpaved verges, construction sites and drain silt deliver a heavy sediment load. Bioretention and infiltration facilities without pretreatment clog, often within a year or two.
Figure 8.1 — Treatment train: source, site and regional controls before the receiving waterbody, with sewage and dry-weather flow kept out of the system. Original drawing for this Manual, adapted from CIRIA, The SuDS Manual (C753), 2015, and MARC/APWA, Manual of Best Management Practices for Stormwater Quality, 2012.
8.6 BMP selection: Level of Service and Value Rating
8.6.1 Method. In Tier A areas, the BMPs for each site shall be selected by the Level of Service (LoS) method of this Clause. In Tier B areas, the simplified route of Clause 8.6.5 may be used.
8.6.2 Required Level of Service. For a site that is not redevelopment, the required LoS depends on the change in curve number (ΔCN) from pre- to post-development (Chapter 3):
Table 8.2 — Required Level of Service for sites that are not redevelopment
| ΔCN | Impact | Required LoS |
|---|---|---|
| 17 or more | High | 8 |
| 7 to 16 | Moderate | 7 |
| 4 to 6 | Low | 6 |
| 1 to 3 | Minimal | 5 |
For redevelopment (existing impervious cover of 20% or more of the site), the required LoS shall be taken from Annex 8B.
8.6.3 Value Rating. Each BMP treating the WQv has a Value Rating (VR) from Table 8.3. The site's composite VR is the area-weighted average of the VRs of the BMPs serving each part of the site. Treatment trains get a composite VR under Annex 8B. The composite VR shall be equal to or greater than the required LoS.
8.6.4 Conditions for a Value Rating. A BMP earns its VR only if:
- (a) it is sized for the WQv (or Q_wq for flow-through devices) of the area credited to it;
- (b) it meets the design requirements of Clause 8.7 and, for infiltration, Clause 8.8; and
- (c) it has pretreatment under Clause 8.5.3.
8.6.5 Tier B simplified route. In Tier B areas, the requirement of Clause 8.6.3 is deemed met where the whole WQv of the site is either:
- (a) retained on site under Chapter 4; or
- (b) treated by a bioretention cell, rain garden or infiltration facility designed under Clauses 8.7 and 8.8, with pretreatment.
Table 8.3 — BMP Value Ratings and suitability in Uttarakhand
| BMP | VR (MARC 2012) | Main pollutants removed | Volume reduction / recharge | Doon Gravels, bhabar fans, river sands | Laterite / hard rock | Terai, Siwalik mudstone or hill colluvium / high water table | Uttarakhand notes |
|---|---|---|---|---|---|---|---|
| Native vegetation (preserved) | 9.25 | All | High | Suited | Suited | Suited | Counts only for preserved, undisturbed area |
| Rain garden / infiltration | 9.0 | Sediment, metals, oil, nutrients | High | Suited if 1.0 m separation met | Conditional (test) | Not suited | Mosquito control: drain within 48 h |
| Bioretention | 8.5 | Sediment, metals, oil, nutrients | Medium–high (unlined); low (lined) | Suited | Suited, with underdrain | Lined, with underdrain | Media source and phosphorus content to be specified |
| Permeable pavement | 7.5 | Sediment, metals, oil | Medium–high | Suited | Conditional | Lined only | Not where run-on carries heavy silt |
| Extended detention wetland | 7.0 | Sediment, nutrients, metals | Low | Conditional (water balance) | Suited | Suited | Good at tank inlets (Clause 7.9.7) |
| Media / sand filter | 6.0 | Sediment, metals | Low | Suited | Suited | Suited (lined) | Needs frequent cleaning |
| Extended wet detention (wet pond) | 5.0 | Sediment, metals, some nutrients | Low | Conditional (water balance) | Suited | Suited | Dry-season water balance (Clause 8.7.8) |
| Vegetated filter strip | 5.0 | Sediment | Low–medium | Suited | Suited | Suited | Mostly as pretreatment |
| Native vegetation swale | 4.0 | Sediment, oil | Low–medium | Suited | Suited | Suited | Not where Q_wq velocity is high |
| Extended dry detention | 4.0 | Coarse sediment | Low | Suited | Suited | Suited | Combine with detention (Chapter 4) |
| Proprietary / hydrodynamic devices | 3.0–5.0 | Coarse sediment, oil, litter | None | Suited | Suited | Suited | VR from verified test data only |
| Signage (public education) | +0.25 | — | — | — | — | — | Added to composite VR |
The VR column is from the MARC/APWA BMP Manual (2012), Table 4.4. The suitability columns and notes have no direct precedent and are set by this Manual.
Commentary. The LoS and VR method is from the MARC/APWA Manual of Best Management Practices for Stormwater Quality (2012), Tables 4.2 and 4.4. The VRs combine a water quality score, based on effluent TSS concentrations in the International Stormwater BMP Database, with scores for volume reduction, temperature, and oils and floatables. The method suits Uttarakhand for two reasons. It rewards volume reduction and preservation, which also serve recharge. It can also be checked by a reviewer without water quality modelling. Its weakness is that the scores come from US data. Uttarakhand stormwater carries more litter and more sewage than the US runoff behind the scores (CPHEEO 2019, §9.5), so this Manual requires GPTs and DWF exclusion separately (Clauses 8.9 and 8.10) and does not let a VR stand in for them.
8.7 BMP design summaries
8.7.1 General. Each BMP shall be designed to the requirements below and to Annex 8D (BMP design sheets). The dimensions given are recommended starting values where marked; the designer shall justify any departure. Every BMP shall be designed for safe passage of flows above Q_wq (Clause 8.4.6) and shall have access for maintenance (Chapter 10).
8.7.2 Bioretention and rain gardens (Figure 8.2).
- (a) Surface ponding depth not more than 300 mm above the mulch, with an overflow at the maximum ponding level.
- (b) Surface ponding drained within 48 hours.
- (c) Filter media 600–900 mm deep: an engineered sandy loam with low fines and low phosphorus content (Annex 8D), with a 50–75 mm mulch layer.
- (d) A transition (choker) layer and a gravel drainage layer below the media.
- (e) A perforated underdrain where the design infiltration rate of the native soil (Clause 8.8.4) is below the rate needed to meet (b), or where the cell is lined.
- (f) Unlined cells shall meet the infiltration criteria of Clause 8.8. Cells that cannot meet them, and cells at hotspots, shall be lined.
- (g) Plants: native or naturalised species tolerant of both waterlogging and long dry spells.
8.7.3 Vegetated swales.
- (a) Trapezoidal or parabolic section, with side slopes no steeper than 1V:3H.
- (b) Longitudinal slope 0.5% to 4%, with check dams where steeper.
- (c) Flow depth at Q_wq not more than the height of the grass, and velocity at Q_wq not more than 0.3 m/s.
- (d) The 1% AEP flow (or the bypass) shall not erode the swale (Chapter 9 permissible velocities).
- (e) Where longitudinal slopes are below 1% or the subsoil is poorly drained, an underdrained ("dry") swale with filter media.
8.7.4 Vegetated filter strips.
- (a) Receive sheet flow only, with a level spreader where flow arrives concentrated.
- (b) Length in the direction of flow at least 5 m, and slope 1% to 8%.
- (c) Used mainly as pretreatment for bioretention, infiltration and swales.
8.7.5 Permeable pavement.
- (a) Run-on from impervious areas not more than twice the permeable area, and no run-on from unpaved or eroding areas.
- (b) Base reservoir of clean, open-graded aggregate, sized to hold its share of the WQv in its voids.
- (c) An open base (infiltrating) only where Clause 8.8 is met; otherwise lined with an underdrain, and then counted as filtration only.
- (d) Structural design for the traffic loading by the road authority's standards.
- (e) Not at hotspots, and not where the surface will be resurfaced with impermeable material.
8.7.6 Infiltration trenches and basins (Figure 8.3).
- (a) Pretreatment under Clause 8.5.3 in every case.
- (b) Trenches filled with clean washed aggregate, with a void ratio confirmed by test, wrapped in geotextile on the sides and top, on a sand base.
- (c) An observation well to the base of each trench.
- (d) Storage volume = WQv (or the retention volume of Chapter 4, where greater) held in the voids; emptied within 72 hours at the design infiltration rate.
- (e) An overflow to the minor or major system at grade.
- (f) Not brought into service until the contributing area is stabilised (Chapter 10).
8.7.7 Wet ponds (extended wet detention).
- (a) A permanent pool of at least the WQv, plus extended detention of the WQv above the pool, released over 24–48 hours.
- (b) A sediment forebay at each inlet (Clause 8.5.3).
- (c) Length-to-width ratio of the flow path at least 3:1, with no short-circuiting.
- (d) Permanent pool depth 1.0–2.5 m, with a safety bench (Clause 7.9.4).
- (e) A dry-season water balance (Clause 8.7.8).
- (f) The detention storage of Chapter 4 may sit above the extended detention level.
8.7.8 Water balance for permanent pools. Wet ponds and wetlands shall be shown, by a monthly water balance using IMD rainfall and pan evaporation, to keep at least 50% of the permanent pool volume (or the minimum wetland depth) through the driest year in 10. They shall not be topped up with groundwater, potable water or sewage. Where the balance fails, a dry extended-detention basin or a constructed wetland with a smaller permanent pool shall be used instead.
8.7.9 Constructed wetlands.
- (a) An inlet sedimentation pond (forebay) followed by a shallow vegetated macrophyte zone.
- (b) Extended detention of the WQv above the normal water level, released over 24–48 hours, with an extended detention depth not more than 0.5 m.
- (c) A flow path length-to-width ratio of at least 3:1, with deep zones across the flow path to spread the flow.
- (d) A high-flow bypass so that floods do not scour the macrophyte zone.
- (e) Where built at a tank inlet, the wetland shall sit within the tank's setback but outside its waterspread, and its storage shall not be counted as tank storage.
8.7.10 Gross pollutant traps.
- (a) Sized to treat Q_wq, with all flows up to the 1% AEP passing without washing out captured material.
- (b) Capture of gross pollutants down to about 5 mm.
- (c) Head loss included in the hydraulic grade line of the drain (Chapter 9), with the screen assumed 50% blocked.
- (d) Storage for captured material sized for the cleaning interval of the O&M plan, and not less than the 3-monthly cleaning of Chapter 10.
- (e) Vehicle access for cleaning by suction or grab.
8.7.11 Oil-grit separators.
- (a) Required at the hotspots of Clause 8.8.8 that involve fuel or oil: fuel stations, vehicle workshops and washing bays, bus and truck depots, and parking areas of more than 50 spaces.
- (b) Sized for Q_wq, with a high-flow bypass.
- (c) Not to be used as the only treatment: they shall be followed by a filtering BMP where the site needs a VR above 5.
8.7.12 Silt traps and catch pits.
- (a) At every inlet that receives runoff from unpaved ground, and at the inlet of every drain discharging to a BMP or waterbody.
- (b) A sump at least 300 mm below the outlet invert.
- (c) Silt traps are pretreatment only and earn no VR.
Commentary. The design summaries draw on the MARC/APWA BMP Manual (2012), the Georgia Stormwater Management Manual (2016, Vol 2), CIRIA C753 The SuDS Manual (2015) and PUB Singapore's ABC Waters Design Guidelines. The dimensions are typical of those manuals but have not been calibrated in Uttarakhand. Three local issues drive changes from the source manuals:
- Mosquitoes. Dengue is endemic in Uttarakhand. Surface ponding in bioretention and rain gardens must drain within 48 hours (Clause 8.7.2(b)), well inside the time mosquito larvae need to develop. This is consistent with the 24–48 hour WQv drawdown of Clause 8.4.7.
- Dry seasons. Most of Uttarakhand's rain falls in the south-west monsoon: the State's normal is 1,326.1 mm a year, of which about 78% falls from June to September and July and August alone bring nearly 53%, with about 10% from March to May, 9% in the winter months of December to February, from western disturbances, and 3% in October and November (IMD, Climate of Uttarakhand, normals of 1961–2010). The gauge normals differ more than the district normals: the outer ridge, at Nainital, Mussoorie, Rajpur and Dehradun, receives about 2,000 to 2,500 mm a year, and the rain-shadow valleys of the inner hills, at Srinagar, Joshimath and Pithoragarh, about 500 to 1,000 mm (IMD, gauge normals). The monsoon now sets in at Dehradun on about 20 June and at Roorkee on about 28 June, and withdraws from Roorkee by about 25 September and from Dehradun by about 27 September (IMD, new normal dates, 2020), but the largest late storms have come in October. From October to the monsoon, taals fall and springs weaken unless they are fed: Naini lake was reported 18 ft below its normal level in 2017 and at a five-year low in 2025 (as reported), and the number of functional springs in the Almora region is reported to have fallen from 360 to 60 over 150 years (NITI Aayog, 2018). In the towns the feed of a drain or pond in the dry months is often sewage, because the raos and nalas carry it (Clause 8.9, Commentary). A wet pond or constructed wetland whose water balance (Clause 8.7.8) cannot keep its permanent pool through the dry months on its own catchment's runoff is not to be used; in the hill towns, where Clause 8.8.1 bars infiltration on the slopes and there is little flat land, the practical forms are lined bioretention with an underdrain, swales on gentle ground, storage for use, and lined extended dry detention, and above about 1,500 m every BMP is also checked for frost, snow and ice from December to March. Clause 8.7.8 applies to BMPs, which shall not be topped up with sewage; taals, khals, recharge flats, springs and wetlands are waterbodies under Chapter 7 and are not to be used as treatment for a development. Wet ponds that dry out turn into stagnant pools or are used for dumping. Clause 8.7.8 requires a water balance and bans topping up with sewage, which is a common practice for keeping urban ponds "full".
- Litter and silt. GPTs and silt traps are treated as essential, not optional, because Uttarakhand drains carry heavy litter and silt loads. The 50% blockage factor for screens matches the grate clogging factor of Chapter 6.
The 50-space threshold for oil-grit separators, the 5 mm GPT capture size, the 0.3 m/s swale velocity and the other dimensions in this Clause have no direct precedent and are set by this Manual.
Figure 8.2 — Bioretention cell (rain garden) in section: pretreatment, surface ponding, filter media, transition and gravel layers, underdrain, overflow, and the 1.0 m separation to seasonal high groundwater for an unlined cell. Original drawing for this Manual, adapted from MARC/APWA, Manual of Best Management Practices for Stormwater Quality, 2012, and CIRIA, The SuDS Manual (C753), 2015.
8.8 Infiltration and recharge criteria
8.8.1 Groundwater separation. An infiltration facility is permitted only where the seasonal high groundwater table is at least 1.0 m below the base of the facility. There is no exception in Uttarakhand, which has no coastal sand areas (Clause 8.8.9). For this Clause the seasonal high groundwater table is the highest post-monsoon level (September to November), and in the terai, where the deeper aquifers are confined and wells flow at the surface, the higher of that level and the level to which a flowing well near the site rises. Uttarakhand needs opposite rules in its three belts, and Clause 8.8.1 applies with the following. (i) Recharge first on the Doon Gravels and the bhabar. On the Doon Gravels of the Dehradun valley and the bhabar fans along the foot of the hills (Bhagwanpur and part of Bahadrabad in Haridwar district, Haldwani, Ramnagar, Kotdwar and Tanakpur), where the water table lies tens of metres down (40 to 75 m below ground in the bhabar of Nainital district, CGWB) and the gravels take water readily, recharge, with pretreatment, is the first means of meeting retention wherever this Clause is met. The bhabar is the intake of the terai's artesian aquifers, whose flowing zone is shrinking (CGWB, 2016), and Bahadrabad, Bhagwanpur, Haldwani and Kashipur were the State's semi-critical blocks in the assessments of 2020 and 2022 (CGWB). (ii) No infiltration on hill slopes. The hill infiltration rule of Clause 4.11 applies to every facility under this Chapter: no deliberate infiltration practice (soakaway, soak pit, recharge pit, shaft or well, infiltration trench, unlined bioretention, or permeable paving with an exfiltrating base) shall be built or credited on natural ground sloping more than 10°; on a mapped landslide or creep zone, or within the landslide-prone setting of bye-law 4.4(IV)–(V); on colluvium, slide debris or moraine, whatever its slope; or upslope of a cut slope or retaining wall within a distance of twice the height of the cut or wall — unless a geotechnical certificate by a qualified geotechnical engineer or engineering geologist shows that the added water will not destabilise the slope. Roof water there goes to the storage tank of bye-law 6.5, and its overflow, with all other runoff, is led by lined drains through a sediment trap to a stable natural channel (or, in a lake town, to the lake through a trap), never onto an unprotected slope; the exception for roof water in Clause 8.11.3(c) does not apply, and no infiltration is credited toward retention or the WQv. Water put into a hill slope raises the pore pressure in the colluvium and can carry its fines away: seepage from drains and from the wastewater of buildings is named among the causes of the slides along the Balia Nala below Naini lake (2022 study), the Mishra Committee asked in 1976 for the soak pits of Joshimath to be closed, and the infiltration of rain and wastewater was named among the causes of its subsidence in 2023 (both as reported). (iii) No infiltration in the terai where the water is within 1 m. In the terai of Udham Singh Nagar and Haridwar, where the water table stands about 1 to 7 m below ground in Udham Singh Nagar and more than 2,000 artesian wells were counted in five of its blocks (CGWB), no infiltration facility, recharge pit, recharge well or recharge shaft shall receive runoff of any kind where the seasonal high water table is within 1 m of the ground, where the ground is waterlogged, or where wells flow at the surface; the exception for roof water in Clause 8.11.3(c) does not apply there, no infiltration is credited, and retention is met by storage for use and by detention under Chapter 4 (bye-law 6.5 already exempts waterlogged areas from rainwater harvesting). Elsewhere in the terai this Clause applies on a test at the site. (iv) Springs and lake recharge areas. Within the recharge area of a naula, dhara or other spring used for drinking water, as a hydrogeologist maps it, and on the recharge flat of a taal, such as Sukhatal for Naini lake, only roof water and runoff that has passed a filtering BMP may be infiltrated, where item (ii) allows any infiltration at all; road runoff, sewage and septic effluent never are, no infiltration facility is placed within the 10 m of a spring kept by bye-law 4.4(III), and a recharge flat is kept open and unpaved (Clause 7.5). (v) Quality. In the assessment of 2024, nitrate exceeded 45 mg/L in about 17% of the samples (Almora, Dehradun, Haridwar, Nainital and Udham Singh Nagar), arsenic exceeded 10 µg/L in about 4% (Almora, Haridwar and Udham Singh Nagar), uranium exceeded 30 µg/L at one place in Haridwar and fluoride exceeded 1.5 mg/L at one place in Almora, all at "sporadic locations" (CGWB). In Haridwar and Udham Singh Nagar districts a recharge well or shaft is used only after a check of the groundwater quality at the site, water drawn back from a recharged aquifer is tested before any drinking use, and no sewage-laden or industrial runoff is led to any recharge structure anywhere. Where recharge is through a well or shaft into fractured rock or deep gravel, a hydrogeologist's report shall confirm the depth to water, the receiving zone, and that no drinking-water well or spring within 30 m will be harmed. The 10° trigger, the distance of twice the wall height, the 1 m limit in the terai and these conditions are set by this Manual; no Uttarakhand rule on infiltration or soak pits on slopes was found. The seasonal high groundwater table shall be determined under Clause 3.10.2.
8.8.2 Other separation. The base of an infiltration facility shall also be at least 1.0 m above bedrock or any impermeable layer, unless the facility is designed to recharge a fractured or weathered rock aquifer under Clause 8.8.10.
8.8.3 Infiltration tests. The infiltration rate shall be measured at the proposed base level of the facility:
- (a) by a double-ring infiltrometer test (ASTM D3385) for basins, bioretention and permeable pavement;
- (b) by a falling-head borehole or trial-pit soakage test (for example BRE Digest 365) for trenches, soakaways, recharge pits and recharge wells;
- (c) with at least 2 tests per facility, and at least 1 test per 100 m² of infiltration base area or per 50 m of trench length; and
- (d) by a person competent in geotechnical testing, with the results reported on the Infiltration Test Record (Form 8-2).
Tests made in the dry season shall be reported with the groundwater level at the time of test and the seasonal high level of Clause 8.8.1.
8.8.4 Design infiltration rate. The design infiltration rate is the measured rate divided by a safety factor:
- (a) 2.0 where the tests meet Clause 8.8.3(c) and the results vary by no more than a factor of 2; and
- (b) 3.0 otherwise.
8.8.5 Minimum rates.
- (a) Full infiltration (no underdrain) only where the design rate is at least 13 mm/h.
- (b) Partial infiltration, with an underdrain, where the design rate is 3 mm/h to 13 mm/h. Only the volume that infiltrates within 72 hours is credited as retention.
- (c) No infiltration credit where the design rate is below 3 mm/h.
8.8.6 Setbacks for infiltration facilities. Infiltration facilities receiving runoff from roads, parking or other paved surfaces shall be at least:
- (a) 3 m from building foundations, and 5 m from a basement;
- (b) 1.5 m from a property boundary, unless the neighbour agrees in writing;
- (c) 30 m from a drinking-water well or borewell;
- (d) 15 m from a septic tank or soak pit; and
- (e) 6 m from the crest of a slope steeper than 1V:3H, unless a geotechnical report shows the slope remains stable.
Roof-only runoff to recharge structures is subject to (a) and (b) only, and to Clause 8.11.3.
8.8.7 Drawdown and verification. Every infiltration facility shall empty within 72 hours at the design rate (Chapter 4), and shall be tested after construction (Clause 10.9.3).
8.8.8 Hotspots. Runoff from the following shall not be infiltrated without treatment, and shall not be infiltrated at all where (d) or (e) applies:
- (a) fuel stations;
- (b) vehicle workshops, washing bays, and bus and truck depots;
- (c) industrial yards and loading areas where hazardous materials are handled or stored;
- (d) solid waste transfer stations and landfill areas; and
- (e) land known or suspected to be contaminated.
Treatment for (a) to (c) shall include an oil-grit separator and a lined filtering BMP before any infiltration.
8.8.9 Sandy coastal aquifers. This Clause applies only to coastal sand aquifers. Uttarakhand has none, so the Clause has no effect in the State; it is kept only so that the clause numbers stay unchanged. The Doon Gravels, the bhabar fans and the sands and boulders of the river beds are not coastal sand areas: Clause 8.8.1 applies there in full, and the reduced separation of item (d) does not. In coastal sand areas:
- (a) infiltration is the preferred means of meeting retention and the WQv wherever Clause 8.8.1 is met;
- (b) storm drains shall not be designed to lower the groundwater table: inverts below the seasonal high groundwater table shall be watertight, with no weep holes or subsoil drains that discharge groundwater to the outfall, unless a hydrogeological report shows no harm to the freshwater aquifer;
- (c) no long-term pumping of groundwater into storm drains shall be approved (for example basement dewatering); and
- (d) in notified coastal sand areas, roof-only runoff may be infiltrated with a separation of not less than 0.5 m to the seasonal high groundwater table, provided a groundwater mounding check shows that the mound stays at least 0.3 m below the facility base and does not reach adjacent foundations or basements. No other runoff may use this reduced separation;
- (e) where neither the 1.0 m separation nor clause (d) can be met, the site shall use surface retention that does not infiltrate below ground (for example shallow vegetated depressions, disconnection of roofs onto lawns, and reuse), and detention under Chapter 4.
8.8.10 Laterite and hard-rock areas. In laterite and hard-rock terrain (for example the quartzite, phyllite, slate, schist, limestone and granite of the Lesser and Higher Himalaya, as around Mussoorie, Nainital, Almora, Pithoragarh, Tehri and Srinagar, where groundwater is held in the weathered veneer, in fractures and in perched bodies and comes out at springs (CGWB), and the Siwalik sandstone, mudstone and conglomerate of the outer hills; on any slope in these areas the hill limits of Clause 8.8.1 apply first):
- (a) tests shall be made at the facility base, below any surface crust or hardpan;
- (b) recharge into weathered or fractured rock is permitted only for roof runoff, or for runoff that has passed through a filtering BMP, because fractures give little treatment; and
- (c) infiltration on or above slopes shall be checked for slope stability.
8.8.11 Delta clays and black cotton soils. In the terai of Udham Singh Nagar and Haridwar where the seasonal water table is within about 1 m of the ground, the ground is waterlogged or wells flow at the surface, the silted beds of taals, khals and talabs, the Siwalik mudstone, and the clayey colluvium and slide debris of the hills, and in expansive black cotton soils:
- (a) infiltration facilities will usually fail Clause 8.8.5 and need not be tested where the soil survey (Chapter 3) shows HSG D; and
- (b) where infiltration is used near buildings on expansive soils, the setback of Clause 8.8.6(a) shall be doubled.
Commentary. The 1.0 m groundwater separation is a core requirement of this Manual. The other values in this Clause (the 1.0 m bedrock separation, test numbers, safety factors, minimum rates and setbacks) are typical of US and UK practice and have no Uttarakhand precedent. The well setback in Clause 8.8.6(c) applies to runoff from paved surfaces, not to roof water. Uttarakhand RWH practice routes roof water into open wells and recharge wells, and Clause 8.11 keeps that practice.
No statewide map of hydrologic soil groups for Uttarakhand, and no measured infiltration rate for the Doon, the bhabar, the terai or a hill slope, was found, and every infiltration design needs the tests of Clause 8.8.3; the geology, depths and categories below are from the CGWB's assessments, brochures and aquifer-mapping reports for the State. About 85% of the State is mountainous and underlain by hard rock, where groundwater is held in the weathered veneer and in fractures and comes out at springs whose discharge in the Lesser and Central Himalaya ranges from 60 to 600 litres a minute; the other 15% is the bhabar and the terai (CGWB, 2024). The Doon valley is filled with the Doon Gravels, "boulders and pebbles embedded in sandy and silty matrix", "highly porous" with a hydraulic conductivity of 13 to 583 m a day and the water 20 to 125 m below ground (CGWB, Dehradun, 2011). The bhabar, a belt of coalesced boulder fans 4 to 20 km wide along the foot of the hills, is "the main intake area" of the plains' aquifers, with the water table 40 to 75 m down and up to 173.71 m at Haldwani (CGWB, Nainital, 2010), and it covers most of Bhagwanpur block and part of Bahadrabad in Haridwar district (CGWB, Haridwar). Below the spring line the terai, 8 to 25 km wide and sloping at less than 1%, is mostly clay with sand beds, the water stands about 1 to 7 m below ground, and more than 2,000 artesian wells flow in five blocks of Udham Singh Nagar (CGWB, Udham Singh Nagar); its flowing zone is shrinking, by 5 to 7 km in the east, and the CGWB names the clearing of the bhabar forests that recharge it and the multiplying of shallow tube wells as possible causes (aquifer mapping, 2016). The State draws 53.54% of its extractable groundwater, with 4 of its 20 assessment units semi-critical (CGWB, 2024); Bahadrabad, Bhagwanpur, Haldwani and Kashipur were the semi-critical blocks in the assessments of 2020 and 2022, all of them on or below the bhabar. Water quality is mostly good, but at "sporadic locations" nitrate exceeded 45 mg/L in about 17% of the samples of 2024, arsenic exceeded 10 µg/L in about 4% (Almora, Haridwar and Udham Singh Nagar), uranium exceeded 30 µg/L at one place in Haridwar and fluoride exceeded 1.5 mg/L at one place in Almora (CGWB, 2024). In the hills the springs are the water supply: government water schemes depend on springs for about 70% of their sources in Chamoli district, 84% in Ghaat block and about 87% in Rikhnikhal (GBPNIHE, 2019), and the number of functional springs in the Almora region is reported to have fallen from 360 to 60 over 150 years (NITI Aayog, 2018); a Spring and River Rejuvenation Authority was reported constituted in 2025 and to have treated 929 water sources (as reported), but no constitution order was found. Water put into a hill slope is a hazard as well as a resource: seepage from drains and the wastewater of buildings, raising the pore pressure of the perched water, is named among the causes of the slides along the Balia Nala below Naini lake (2022 study); the Mishra Committee asked in 1976 for the soak pits of Joshimath to be closed; and an IIT Roorkee study of the subsidence of 2023 named infiltration of rain and wastewater as a likely cause (both as reported). This Manual's interim soil groups follow from these: the Doon Gravels and bhabar fans A, the terai C (D where the water table is within about 1 m), the Ganga alluvium B to C, Siwalik regolith C (D on mudstone), and hill colluvium, slide debris and moraine designed as D with no infiltration credit on slopes (Chapter 3). The State therefore needs opposite rules in its three belts. On the Doon Gravels and the bhabar, recharge comes first, with pretreatment, because they feed the plains' aquifers. On the hill slopes, no water is put into the ground on purpose, under the hill infiltration rule of Clause 4.11, which Clause 8.8.1 applies. In the terai, where the water is within 1 m or flows at the surface, no infiltration is used, and retention is met by storage for use and detention. Everywhere, runoff from roads and open land goes to surface systems and never directly to a recharge well, borewell or shaft (Clause 8.11.3(b)), and arsenic, nitrate and uranium are checked where Clause 8.8.1 says so. Clause 8.8.9 has no effect in Uttarakhand, which has no coast.
Figure 8.3 — Infiltration trench in section: pretreatment sump, aggregate-filled trench in geotextile, observation well, overflow, the 1.0 m minimum separation to the seasonal high groundwater table, and setbacks to wells and foundations. Original drawing for this Manual, adapted from the Georgia Stormwater Management Manual, 2016 (Vol 2), and CIRIA, The SuDS Manual (C753), 2015.
8.9 Sewage cross-connections and dry-weather flow
8.9.1 No sewage in storm drains. No sewage or sullage (grey water from kitchens, bathrooms and laundries), septic tank effluent, or trade effluent shall be connected to, or discharged into, any storm drain, by any pipe, channel or opening.
8.9.2 Condition of approval. Before the completion certificate, the Applicant shall show, by a dye or smoke test witnessed by the Authority or the sewerage agency, that every sewage and sullage outlet on the site discharges to a sewer or to an approved on-site system, and that none discharges to a storm drain. Any existing cross-connection on the site shall be removed as a condition of approval, including on redevelopment and on additions to existing buildings.
8.9.3 Where no sewer exists. Where no sewer is available, sewage and sullage shall go to an approved on-site or decentralised treatment system. The treated effluent of such a system may be discharged to a storm drain only with the written consent of the Uttarakhand Environment Protection and Pollution Control Board (UEPPCB) and the drain owner.
8.9.4 Public drains: DWF survey. Every ULB in a Tier A area shall survey its storm drain outfalls to waterbodies for dry-weather flow at least once a year, before the SW monsoon, and record:
- (a) the outfalls with DWF;
- (b) the estimated DWF rate; and
- (c) the upstream sources found by tracing, CCTV, dye or smoke testing.
The results shall be published in the register of Clause 10.17.
8.9.5 DWF interception. Until the sources are removed, every outfall to a waterbody that carries DWF shall have a DWF interceptor that:
- (a) diverts the DWF to a sewer or a treatment plant;
- (b) does not reduce the capacity of the storm drain for the minor or major event (Chapter 6), with its weir or diversion head losses included in the hydraulic design (Chapter 9);
- (c) has a screen ahead of the diversion; and
- (d) is not a substitute for removing the source connections.
8.9.6 Sewage overflows. No new sewage overflow, emergency bypass or pumping station overflow shall be designed to discharge into a storm drain or waterbody, except where the sewerage agency shows that no alternative exists, and then only with screening and with the overflow frequency stated.
Commentary. The prohibition of sewage connections and the removal of existing cross-connections as a condition of approval are core requirements of this Manual, and Clause 1.10.3 allows no variance from them. Sewage in storm drains is the single largest water quality problem of urban drainage in Uttarakhand. It defeats every other measure in this chapter: BMPs designed for stormwater are overloaded, GPTs fill with sludge, and the receiving tanks and channels become sewage lagoons. CPHEEO (2019) notes that Indian drains carry night soil and urine (Part A §9.5). DWF interception (Clause 8.9.5) is an interim measure. It protects the waterbody while the sources are traced and removed, but it can become permanent if the source work is not done, which is why the annual survey and publication of Clause 8.9.4 are required. The annual survey frequency is set by this Manual.
In Uttarakhand the raos and nalas carry the sewage, and the State's answer has been interception and diversion (I&D) at the drain mouth under Namami Gange. On the Rispana in Dehradun, 187 of the 208 drains have I&D works, 19 more now reach the sewers and 2 are clean forest streams; the I&D project for the Rispana and the Bindal, sanctioned in 2021, tapped 200 drains with 22.34 km of sewers, sending the Rispana's drains to two 20 MLD treatment plants at Mothrowala and the Bindal to the 68 MLD plant; and the floods of 16 and 17 September 2025 damaged 83 of those I&D structures (Uttarakhand Peyjal Nigam, affidavit of December 2025 in NGT O.A. 417/2022). Statewide, the CPCB monitored 200 drains carrying about 1,891 MLD, of which 114 were completely tapped, 13 partly tapped and 70 untapped before the monsoon of 2025, and it lists the Rispana, the Bindal Rao, the Rambha at Rishikesh and the Kalyani at Rudrapur among "rivers reported as drains" (as quoted in a submission of 12 March 2026 in NGT O.A. 200/2014). The CAG found in 2017 that 47 of the 111 nallas identified in the Ganga towns of Uttarakhand had been tapped, with 26.292 MLD of sewage still falling into the river (Report No. 39 of 2017; its Report No. 1 of 2018 counts 65 of 112 still to be tapped). The adapted Municipal Acts were not read for any power to require separate drains for sewage and rain-water [TBC]. Every I&D structure on a rao or nala is a DWF interceptor under Clause 8.9.5, and Clause 8.9.5(b) applies to it in full: it is sized from the measured dry-weather flow of its drain, does not reduce the drain's capacity for the minor and major events or raise the flood level behind it, and passes the storm flow above its capacity on down the drain to the river, never to the treatment plant or back into the colonies. On a rao or gadhera, where a flash flood carries boulders and can destroy it, an interceptor and its chamber are also placed above the 25-year flood line of the reach where one is notified, or otherwise protected against the scour and debris of the 1% AEP flood (Chapter 9), with the bypass shown to pass that flood; this condition is set by this Manual.
8.10 Outfalls to waterbodies: first flush, gross pollutant traps and screens
8.10.1 Requirement. Every new storm drain outfall to a waterbody, and every existing outfall on a drain that is rebuilt, widened or extended, shall have:
- (a) a GPT designed under Clause 8.7.10; and
- (b) first-flush treatment: treatment of the WQv (or Q_wq) of the contributing catchment by the BMPs of Clause 8.7, either on the contributing sites or at the outfall.
8.10.2 Where treatment at the outfall is impracticable. Where land is not available at a public outfall, first-flush treatment may be provided by:
- (a) a proprietary first-flush or hydrodynamic device sized for Q_wq; or
- (b) a treatment wetland or forebay within the waterbody setback (Clause 7.5.1(b)), outside the waterspread.
8.10.3 Screens and trash racks. Screens at outfalls, culvert inlets and pump sumps shall:
- (a) be designed with 50% blockage for hydraulic capacity;
- (b) have an overflow or bypass path so that a fully blocked screen does not flood property;
- (c) have bar spacing chosen for the hazard: closer spacing for litter capture, wider spacing where blockage would cause flooding; and
- (d) be cleanable from a safe platform, with vehicle access.
8.10.4 Existing outfalls. Each ULB shall prepare a programme to fit GPTs and DWF interceptors to its existing outfalls to waterbodies, starting with outfalls to tanks used for drinking water supply and to notified wetlands (Clause 7.12), and shall report progress in the register of Clause 10.17.
Commentary. This Manual requires first-flush treatment and gross pollutant traps at outfalls to waterbodies. Gross pollutants are the most visible form of pollution in Uttarakhand waterbodies, and plastics also block drains and culverts, which links water quality to flooding. The 50% screen blockage matches the grate clogging factor of Chapter 6. Clause 8.10.3(c) warns against fine screens on large drains, which block in the first hour of a storm and cause the flooding they were meant to prevent.
8.11 Rainwater harvesting integration
8.11.1 RWH mandate continues. The rainwater harvesting required by the Uttarakhand Building Construction and Development Bye-laws 2011 (bye-law 6.5, which makes rainwater harvesting mandatory for every permitted construction with a ground coverage of 125 m² or more, except in areas with a waterlogging problem, with storage of at least 2.0 m³ up to 250 m² of coverage, 3.5 m³ up to 400 m², and 0.5 m³ more for each further 50 m² or part of it, reduced to one-third of that storage on a plot of more than 400 m² where groundwater recharge is provided by a bore well, recharge pit, well or trench, and confirmed on the building plan before approval; that storage is about 8 to 16 mm of rain over the covered area) continues to apply, subject to the limits of Clause 8.8.1 (Chapter 1). This Clause sets how RWH structures are counted under this Manual.
8.11.2 Three different functions. The designer shall keep apart, on the drawings and in the calculations:
- (a) harvesting: storage for use (sumps and tanks);
- (b) recharge: recharge pits, trenches, shafts and wells that put water into the ground; and
- (c) detention: storage with an orifice outlet that is empty at the start of a storm (Chapter 4).
8.11.3 Recharge structures.
- (a) Roof runoff may be led to recharge wells, open wells, recharge pits and shafts after a filter or settling chamber.
- (b) Runoff from roads, parking and other paved areas shall not be led directly into any well, borewell or recharge shaft. It may be recharged only through an infiltration facility that meets Clause 8.8, with pretreatment.
- (c) Recharge structures shall meet the groundwater separation of Clause 8.8.1, measured from the base of the pit or the bottom of the filter media, except recharge wells that receive filtered roof water only.
8.11.4 Credit toward retention and WQv. A recharge structure counts toward the retention volume of Chapter 4 and the WQv only where:
- (a) its infiltration rate has been tested under Clause 8.8.3;
- (b) it empties within 72 hours at the design rate; and
- (c) it has pretreatment.
A harvesting sump counts toward retention only where its contents are used, by a demand stated in the drainage report, within 72 hours (Chapter 4).
8.11.5 No credit as detention. RWH storage does not count as detention unless it is a dedicated volume that is empty when a storm arrives, with an outlet. RWH sumps are assumed full at the start of every SW monsoon (JJAS) design storm (Chapter 4).
8.11.6 Overflow. Every RWH structure shall have an overflow that discharges at grade to the site drainage, never onto a neighbouring plot or into a sewer.
8.11.7 Surface-runoff recharge in public spaces. Recharge trenches, shafts and percolation pits in roads, medians, parks and other public spaces shall meet Clause 8.8 in full, including the hotspot rules for roads with heavy traffic, and shall have a GPT or silt trap at each inlet.
Commentary. The rule that RWH storage does not count as detention is set in Chapter 4. Uttarakhand's building rules make rainwater harvesting mandatory, but none of them sets a detention rule. Bye-law 6.5 of the Bye-laws 2011 requires it, except in areas with a waterlogging problem, for every permitted construction with a ground coverage of 125 m² or more, as a storage of at least 2.0 m³ up to 250 m² of coverage, 3.5 m³ up to 400 m², and 0.5 m³ more for each further 50 m² or part of it; on a plot of more than 400 m² where groundwater recharge is provided by a bore well, recharge pit, well or trench, one-third of that storage suffices; the provision must be shown on the building plan before approval, and the drainage and storage works do not count in the ground coverage (compilation of 2015–2019). The storage is about 8 to 16 mm of rain over the covered area, and the marginal 0.5 m³ per 50 m² is 10 mm. Structures for rainwater harvesting, conservation and storage, including underground tanks, are among the works exempt from permission, and the open area over a basement may carry a recharge well (bye-law 5.6(vi)). A draft revision of the bye-laws, the "Amendment 2017" hosted by MDDA, would have applied harvesting to plots above 100 m² and made recharge mandatory on plots of 500 m² and more, with recharge wells at least 10 m from any structure handling sewage or industrial waste water, but it is not found notified. The Uttarakhand Ground Water (Regulation and Control of Development and Management) Act, 2016, whose section 20 would have let an authority order harvesting for recharge, was repealed in 2017 (Act No. 11 of 2017), so the State has no groundwater law with a harvesting mandate, and the Central Ground Water Authority's guidelines of 2020, as amended in 2023, apply to extraction (CGWB, 2024). Enforcement is by plan approval and drives: MDDA's Vice-Chairman ordered harvesting in residential projects to be improved within a week in June 2024, and the authority said that approved maps often show provisions that were not built (as reported); and the CAG found that Dehradun Smart City's integrated drainage works made no provision for storm-water reuse (CAG, 2025). The rules set no test of the recharge pit, no protection of the aquifer from road runoff, no storage to be empty before a storm, and no limit on recharge pits on slopes. On the Doon Gravels and the bhabar, and in the semi-critical blocks of Bahadrabad, Bhagwanpur, Haldwani and Kashipur, recharge is the main function of harvesting (Clause 8.11.2(b)); on hill slopes, landslide and creep zones, colluvium, slide debris and moraine, and in the terai where the water table is within 1 m, harvesting is for storage and use, and the recharge pit of bye-law 6.5(III) is not used unless Clause 8.8.1 allows it, so the one-third reduction of storage, which depends on recharge, is not taken there under this Manual (Clause 8.8.1). RWH serves water supply and recharge. It is usually full, or its soil saturated, by the time a July to September monsoon burst or cloudburst against the outer Himalaya, or a late-season storm such as that of October 2021 arrives after weeks of rain, which is why it cannot be counted as detention.
Clause 8.11.3(b) has no direct precedent; this Manual sets it because road runoff carries oil, metals and pathogens. A recharge shaft or borewell bypasses the soil that would otherwise filter it and delivers it straight to the aquifer that supplies wells nearby. The CGWB Manual on Artificial Recharge of Ground Water (2007) gives recharge structure types and filter designs; this Manual adds the source-water restrictions.
8.12 Construction-stage erosion and sediment control
8.12.1 ESC plan. Every development with land disturbance of 0.1 ha or more, and every public drainage or road work, shall have an Erosion and Sediment Control (ESC) plan, approved with the drainage report. It shall show:
- (a) the sequence of clearing, earthworks and stabilisation;
- (b) the area exposed at each stage;
- (c) the measures of Clause 8.12.3, with their locations and sizes;
- (d) the protection of infiltration and retention areas (Chapter 10);
- (e) stockpile, concrete washout and fuel storage locations; and
- (f) the inspection and maintenance schedule.
8.12.2 Monsoon timing. Earthworks shall be planned so that:
- (a) the area exposed during the SW monsoon (June to September) is as small as practicable;
- (b) all completed earthworks are stabilised by vegetation, mulch, matting or paving by 31 May; and
- (c) any area exposed between 15 June and 31 October has sediment controls in place before it is cleared.
8.12.3 Measures.
- (a) Silt fences along the downslope edge of disturbed areas receiving sheet flow, with the area draining to each fence limited as set in Annex 8E.
- (b) Sediment traps for concentrated flow from disturbed areas of up to 2 ha.
- (c) Sediment basins for disturbed areas of more than 2 ha. The storage volume below the outlet shall be at least the greater of the runoff from the 50% AEP (2-yr) 24-hour storm and 250 m³ per hectare of drainage area, with a dewatering outlet that draws water from the surface.
- (d) Inlet protection at every existing drain inlet that receives runoff from the site.
- (e) Stabilised construction exits, with wheel washing where vehicles enter public roads.
- (f) Stockpiles outside Zone 1 of any waterbody setback (Chapter 7), at least 10 m from any drain, and covered during the SW monsoon.
- (g) Dewatering discharges passed through a sediment basin, settling tank or filter bag, never pumped directly into a drain or waterbody.
- (h) Concrete washout in a lined pit, never into a drain.
8.12.4 Design storm for temporary works. Temporary ESC measures use the rainfall of Chapter 2 with a climate factor of 1.0 (Clause 2.8.2).
8.12.5 Inspection. ESC measures shall be inspected weekly and within 24 hours after every heavy-rainfall event (as defined in Chapter 10), repaired within 48 hours, and cleaned when half full of sediment.
8.12.6 Removal. Temporary measures shall be removed only after the area draining to them is stabilised. Sediment shall be removed from any permanent facility used for sediment control before its as-built survey (Chapter 10).
Commentary. The 0.1 ha threshold is the applicability threshold of Chapter 1. The sediment basin volume of 250 m³/ha is the US EPA Construction General Permit minimum of 3,600 ft³ per acre drained, converted to SI (US EPA, 2022 CGP); the CGP allows the alternative of the 2-year, 24-hour runoff. This Manual requires the greater of the two, because Uttarakhand's 2-year 24-hour depths are high and construction sites are commonly left exposed through the SW monsoon. The 2 ha division between traps and basins, the 31 May stabilisation date, the 10 m stockpile distance and the inspection frequency have no direct precedent and are set by this Manual. The 31 May date matches the pre-monsoon deadline of Chapter 10. Construction sediment is a direct flood hazard as well as a pollutant: it fills drains, culverts and tanks, and in Uttarakhand sediment, not sewage alone, is the dominant pollutant of the hill drains: the State's slopes are steep, its soils skeletal and erodible, road and building works leave cut slopes and loose spoil, and the rivers carry heavy loads (about 7.88 million tonnes of suspended sediment a year in the Bhagirathi at Devprayag, as reported). In a hill town the silt, gravel and debris settle in the lake at the end of the drains, such as Naini lake, on the recharge flats that feed it, where dumped debris has reduced Sukhatal's recharge (NITI Aayog, 2018), and in the barrage ponds, such as the Gaula barrage, reported silted with debris and boulders upstream (as reported). Solid waste adds to the load: the CAG found most of the State's dump sites near national highways or rivers, with waste flowing into them (Report No. 4 of 2024). In the hills the outlet of a sediment basin or trap under Clause 8.12 discharges to a lined drain or a stable channel and never onto an unprotected slope, and no sediment basin or trap is designed to infiltrate where Clause 8.8.1 bars infiltration; in a lake catchment, a construction site also keeps its sediment out of every drain that reaches the lake.
8.13 Monitoring
8.13.1 Outfall monitoring. Each Tier A authority shall monitor water quality at a representative set of its outfalls to waterbodies, including every outfall to a drinking-water tank or notified wetland. Monitoring shall include:
- (a) dry-weather sampling (Clause 8.9.4), at least once a year before the SW monsoon; and
- (b) wet-weather sampling of at least three events each SW monsoon at a set of index outfalls.
8.13.2 Parameters. At minimum: TSS, BOD, COD, faecal coliform, total nitrogen, total phosphorus, oil and grease, and, for industrial catchments, heavy metals. Results shall be compared with the CPCB water quality criteria for the designated best use of the receiving waterbody.
8.13.3 Gross pollutant records. The mass or volume of material removed from each GPT and screen at each cleaning shall be recorded in the O&M records (Chapter 10).
8.13.4 BMP performance monitoring. The State Stormwater Technical Committee shall run a BMP performance calibration programme and shall revise Table 8.3 and Annex 8C from its results.
8.13.5 Publication. Monitoring results shall be published in the register of Clause 10.17.
Commentary. No Uttarakhand programme of stormwater quality monitoring was found during research for this Manual, and CPHEEO (2019) sets no Indian targets. The monitoring in Clause 8.13 is the minimum needed to calibrate Table 8.3 and to show whether DWF interception and source removal are working. The parameter list follows the key pollutants named in CPHEEO's WSUD procedure (TSS, nitrogen, phosphorus and gross pollutants), with BOD and faecal coliform added because of sewage contamination. The monitoring frequencies are set by this Manual.
8.14 Submittal requirements
Every drainage report under this chapter shall include:
- the Water Quality Sheet (Form 8-1): P_ret, P_3m and P_wq; the WQv and Q_wq for each drainage area; the volume retained under Chapter 4; and the BMP serving each area;
- for Tier A: the LoS calculation (ΔCN, required LoS) and the composite VR (Clause 8.6);
- the design of each BMP to Clause 8.7 and Annex 8D, with pretreatment;
- for infiltration and recharge: the Infiltration Test Record (Form 8-2), the seasonal high groundwater level and its source, the design rate, the drawdown time, and the setbacks of Clause 8.8.6;
- the sewage and sullage connection plan and the dye or smoke test record of Clause 8.9.2;
- the GPT and first-flush design for any outfall to a waterbody (Clause 8.10);
- the RWH layout, separating harvesting, recharge and detention (Clause 8.11); and
- the ESC plan (Clause 8.12).
8.15 Review and update
8.15.1 This chapter shall be reviewed with the rest of the Manual (Chapter 1). Table 8.3 shall also be reviewed when the calibration programme of Clause 8.13.4 reports, and in any case within 5 years of notification.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A: Engineering Design (§9.5, Ch. 10). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- Mid-America Regional Council and Kansas City Metro Chapter APWA (2012). Manual of Best Management Practices for Stormwater Quality (Tables 4.2–4.6). https://www.marc.org/sites/default/files/2022-05/Best_Management_Practices_for_Stormwater_Quality.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01; MARC factsheet and Supplement. https://www.marc.org/document/apwa-5600-manual-factsheet ; https://www.marc.org/document/apwa-stormwater-standards-supplement
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, 2016 Edition, Vols 1–2. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd Edition. https://did.sarawak.gov.my/web/attachment/show/?docid=clRsMlRycU1lNnFRcnl3eDZnNkJMdz09OjpY0au0UPvQ9zUHVWRMbCKX
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- CIRIA (2015). The SuDS Manual (C753). London: CIRIA.
- PUB, Singapore's National Water Agency. Active, Beautiful, Clean Waters Design Guidelines (current edition).
- Central Ground Water Board (2007). Manual on Artificial Recharge of Ground Water. Ministry of Water Resources, Government of India.
- US Environmental Protection Agency (2022). NPDES Construction General Permit (sediment basin sizing).
- ASTM D3385. Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer.
- BRE Digest 365. Soakaway Design. Building Research Establishment, UK.
- Government of Uttarakhand, Housing Department. Uttarakhand Building Construction and Development Bye-laws/Regulations, 2011 (Amendment 2015), compilation of 2015–2019 (bye-laws 2.x exempt works, 5.6(vi) and 6.5) (Chapter 7 references); and the draft Amendment 2017 (clause 9), hosted by MDDA and not seen notified.
- Government of Uttarakhand. Uttarakhand Ground Water (Regulation and Control of Development and Management) Act, 2016 (Act No. 12 of 2016) and its Repeal Act, 2017 (Act No. 11 of 2017). http://web.archive.org/web/20240413135305id_/https://www.highcourtofuttarakhand.gov.in/files/Ground_Water_(Regulation_and_Control_of_Development_and_Management)_Repeal_Act,_2017.pdf
- Central Ground Water Board. Dynamic Ground Water Resources & Ground Water Quality of Uttarakhand, 2024 (brochure, December 2024), https://web.archive.org/web/20250329005750id_/https://cgwb.gov.in/cgwbpnm/public/uploads/documents/1742294726543197566file.pdf ; categorisation of assessment units, GWRA 2020 and 2022; ground water level bulletin, January 2025; district brochures for Dehradun (2011), Nainital (2010), Udham Singh Nagar and Hardwar (2009); aquifer mapping reports for Udham Singh Nagar (2016) and Haridwar (draft).
- NITI Aayog (2018). Report of Working Group I: Inventory and Revival of Springs in the Himalayas for Water Security. https://nmhs.org.in/w/pdf/publication/Niti%20Ayog/doc1.pdf
- G.B. Pant National Institute of Himalayan Environment (2019). Water at a glance: Uttarakhand (dependence of water schemes on springs; read in part). https://www.gbpihed.gov.in/PDF/Publication/Water_at_a_glance_UK_2019.pdf
- Uttarakhand Peyjal Nigam. Affidavit in NGT O.A. 417/2022, Niranjan Bagchi v. State of Uttarakhand (December 2025): interception and diversion of the drains of the Rispana and the Bindal; damage of 16 and 17 September 2025 (Chapter 7 references).
- Applicant's submission of 12 March 2026 on the affidavits of the State of Uttarakhand and the CPCB in NGT O.A. 200/2014, M.C. Mehta v. Union of India (quoting the CPCB's report of 6 January 2026 on drains, tapping and treatment plants). https://www.greentribunal.gov.in/sites/default/files/news_updates/Submission%20by%20Applicant%20State%20of%20UK%20and%20CPCB%20in%20OA%20NO%20200%20OF%202014%20M%20C%20Mehta%20Vs%20UOI%20and%20Ors.pdf
- Comptroller and Auditor General of India. Report No. 39 of 2017, Performance Audit of Namami Gange, Chapter 8 (compliance with the High Court's judgment in Uttarakhand; nallas tapped), https://www.cag.gov.in/uploads/download_audit_report/2017/Chapter_8_Compliance_to_Hon%E2%80%99ble_Uttarakhand_High_Court_Judgement_of_Report_No.39_of_2017_-_Performance_Audit_on_Ministry_of_Water_Resources,_River_Development_&_Ganga_Rejuvenati.pdf ; Report No. 1 of 2018 (Uttarakhand); Report No. 4 of 2024 (solid waste management); and Report No. 2 of 2025 (Namami Gange, Uttarakhand; seen only as reported).
- India Meteorological Department. Climate of Uttarakhand (Climatological Summaries of States; normals of 1961–2010); and new normal dates of onset and withdrawal of the southwest monsoon (2020) (Chapter 7 references).
- Studies of slopes and infiltration: a study of the landslides of the Balia Nala, Nainital, Arabian Journal of Geosciences (2022), https://doi.org/10.1007/s12517-022-09742-8 ; Gupta, V. et al. (2016), Natural Hazards 80: 863–877; reports of the Mishra Committee of 1976 and of the IIT Roorkee study of Joshimath (2023) (seen in secondary sources, such as Down To Earth, https://www.downtoearth.org.in/news/urbanisation/joshimath-sinking-over-50-of-joshimath-high-risk-area-finds-iit-roorkee-92389).
- Reports of the Spring and River Rejuvenation Authority (2024–2026) and of MDDA's enforcement of rainwater harvesting (2024) (secondary). https://thenewsmill.com/2025/05/uttarakhand-government-constitutes-spring-and-river-rejuvenation-authority-to-revive-water-sources/ ; https://pioneeredge.in/?p=154180
- Parliament reply AU1419 on AMRUT 2.0 admissible components. https://eparlib.sansad.in/bitstream/123456789/2988692/1/AU1419_tzCIvw.pdf
Annexes and forms
| Annex / Form | Content |
|---|---|
| 8A | 3-month ARI 24-hour depth and IDF by zone |
| 8B | Redevelopment LoS table and treatment-train composite VR |
| 8C | Uttarakhand BMP performance calibration |
| 8D | BMP design sheets, media specification, plant lists |
| 8E | Erosion and sediment control standard details |
| Form 8-1 | Water Quality Sheet |
| Form 8-2 | Infiltration Test Record |
Commentary. CPHEEO (2019) is the only Indian manual that covers stormwater quality in any detail. Its Chapter 9 reproduces US event mean concentrations, but cautions that "in an Indian context the values would be much higher" because drains receive night soil, urine and food waste, and it sets no Indian numeric criteria (CPHEEO 2019, Part A §9.5). Its Chapter 10 describes water-sensitive urban design, LID and SuDS treatment trains (CPHEEO 2019, Part A Ch. 10). This chapter turns that guidance into requirements. It follows the treatment approach of the MARC/APWA BMP Manual (2012), now merged into APWA 5600 (2025.01), with the Malaysian 3-month ARI water quality storm (MSMA 2, 2012) and the Georgia water quality volume (GSMM, 2016) as tropical and US benchmarks.