Draft v1.0 prepared by NEER. Not adopted by the Government of Assam, any Autonomous Council, authority or local body, and has no legal force. About this draft

Annexes to Chapter 5Downstream and Tailwater Analysis

These annexes support Chapter 5. Annex 5C is a worked example of the outfall-closed check of Clause 5.10, for the illustrative facility of Annex 4C. Annexes 5A and 5B need tidal, surge, survey and river data that this draft does not yet contain; each lists what the chapter already sets, gives the intended layout and states the interim rule of Chapter 5 that applies until it is published. Forms 5-1 and 5-2 are the submittal forms required by Clause 5.14. They are draft forms and have no statutory status.


Annex 5A — Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment

Supports Clauses 5.7, 5.9, 5.10, 5.11 and 5.12 of Chapter 5.

5A.1 Table 5A.1 shows how the values of this annex enter the design tailwater levels of Table 5.1. The sea-level allowance is set by Clause 5.7.4 and does not depend on this annex.

Table 5A.1 — Use of the Annex 5A values in the design tailwater (Table 5.1)

Design case Tailwater Annex 5A values used Chapter value
Minor-system design MHWS + SLA MHWS SLA ≥ +0.3 m (Clause 5.7.4)
Major-system and storage design HAT + surge + SLA HAT; 10% AEP surge (Clause 5.7.3(a)) SLA ≥ +0.3 m
Joint case (Clause 2.12(b)) 1% AEP still-water level + SLA 1% AEP still-water level (Clause 5.7.3(b)) SLA ≥ +0.3 m
Datum conversion Chart datum to project datum Offset from chart datum to the Survey of India datum (Clause 5.7.2(b)) —

Not prepared for Assam. Assam has no coast, so no outfall in the State has a tidal tailwater, and this annex has no Assam content (Clause 5.1.4). Its tables are kept, empty, so that the annex and table numbers match the other editions of this Manual. Rows F1 to F7 of Form 5-1 are entered as "not applicable", and the tailwater is derived under rows F8 to F10; for a river-locked outfall, row F10 records the sluice, the CWC gauge and its datum, the lock and the pump-down of Clause 5.8.5(a), and for an outfall to a beel, pukhuri or pond, its starting level and surveyed stage–storage relation under Clause 5.8.5(e).

Table 5A.2 — Tidal datums, surge and still-water levels by coastal segment (layout)

Coastal segment Reference port and tide-table edition MSL (m CD) MHWS (m CD) HAT (m CD) CD to Survey of India datum (m) 10% AEP surge (m) 1% AEP still-water level (m CD) Wave set-up (m), open-sea outfalls Sources
                   
                   
                   

Annex 5B — Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map

Supports Clauses 5.2, 5.3, 5.8 and 5.13 of Chapter 5.

5B.1 Table 5B.1 lists the water bodies that Chapter 5 already names. It is not complete: the annex will add the extents of each reach, the other rivers, canals and mouths of the State, and a map.

Table 5B.1 — Water bodies named in Chapter 5

Water body Region Listed as Clause
Brahmaputra at Dibrugarh, Neamatighat (Jorhat), Tezpur, Guwahati (DC Court), Goalpara and Dhubri Brahmaputra valley Riverine outfall reaches through WRD embankment sluices; highest levels 106.48 m (Dibrugarh, 3 September 1998), 87.37 m (Neamatighat, 11 July 1991), 66.59 m (Tezpur, 27 August 1988), 51.46 m (Guwahati, 21 July 2004), 37.43 m or 37.35 m (Goalpara, 1954 or 2004; 37.43 m applies) and 30.36 m or 30.37 m (Dhubri, 1988 or 2019; 30.37 m applies); danger levels 105.70, 85.04, 65.23, 49.68, 36.27 and 28.62 m; CWC levels as reported, datum [TBC]; lock the 72-hour storm and while the river stays above the sill, not less than 7 days without a stage record 5.8.1, 5.8.5
Bharalu and Bahini to the Bharalumukh sluice Guwahati (Bharalu basin) Major drain and river-locked outfall; the Bahini rises in Meghalaya at Umtyrnga and becomes the Bharalu at Jonali; catchment ≈120 km² (≈10.94 km² or ≈11 km² of city drainage, conflict); 72 m³/s by gravity, 7 m³/s of pumps (2008, as reported; present capacity [TBC]); Natun Bazar sluice on the Bahini; carries sewage (Clause 8.9) 5.2, 5.8.1, 5.8.5
Mora Bharalu, Deepor Beel and the Khanajan, with the Basistha and the Kalmani Guwahati (Dipar basin) Major drains and receiving storage; Deepor Beel ≈10.1 km² all year, up to ≈40.1 km² in floods (as reported), stage–storage [TBC]; starts full; Ramsar site and sanctuary, no project credit for its storage; outlet by the Khanajan to the Brahmaputra; Mora Bharalu reported at 45 m³/s 5.2, 5.8.1, 5.8.5
Silsako basin and the ADB Bahini works Guwahati (Silsako basin) Receiving storage; 59,000 m³ retention pond with a 1.6 m³/s pump station and +7.8 m³/s in three pumping stations (ADB, 2025), counted only when commissioned and confirmed by GMDA; starts full 5.8.5
Bondajan with the Noonmati pump house; the Lakhimijan Guwahati Major drains; Noonmati 4 × 1,000 L/s and an older 2 × 1,700 L/s (as reported), pumped inflow included; WRD dewatering pumps credited only where confirmed permanent 5.2, 5.8.5
DTP drain past Larua Jamira beel to the Sessa sluice Dibrugarh Major drain and river-locked outfall; 32.053 km; capacities 105.50, 142.97 and 61.11 m³/s by reach; tailwater not less than 97.50 m at the sluice, beel full and drain flowing full (ADB IEE, 2017; datum [TBC]); carries sewage 5.2, 5.8.1, 5.8.5
Barak at Annapurnaghat (Silchar) and Badarpurghat Barak valley Riverine outfall reaches behind the Barak embankment; highest levels 21.84 m (1 August 1989) and 18.48 m (11 September 2007), danger levels 19.83 and 16.85 m (as reported); 2022 peak 21.59 m after the Bethukandi cut; breach check; Silchar's outfall channels [TBC] 5.8.1, 5.8.5
Kushiyara at Karimganj; the Dhaleswari and the Katakhal (Hailakandi) Barak valley Riverine outfall reaches; Karimganj highest level 16.57 m (10 June 2010), danger level 14.94 m (as reported); Hailakandi levels [TBC] 5.8.1, 5.8.5
Jia Bharali, Subansiri, Burhidihing, Dikhow, Kopili, Beki, Manas, Puthimari and Pagladiya at their CWC sites Brahmaputra valley Riverine outfall reaches; levels as listed in Clause 5.8.5(d) (as reported), the Kopili at Dharamtul 58.09 m (21 July 2004, CWC bulletins); Manas at Mathanguri 100.28 m or 102.28 m (102.28 m applies) [TBC]; lock not less than 72 hours without a stage record; Kopili outfalls designed for the river's pH 5.8.1, 5.8.5
Digaru at Sonapur, Kulsi and Krishnai (Dudhnai) Kamrup, Goalpara (from Meghalaya) Riverine outfall reaches; level-monitoring sites with no published level (as reported) [TBC]; modelled or surveyed flood level required; the Meghalaya edition governs the reaches in Meghalaya 5.8.1, 5.8.5
Ranganadi, Subansiri, Kopili, Manas and Umtru below their dams North bank; Kopili and Umtru basins Release reaches; Ranganadi release 1,412.57 m³/s (2017, as quoted); Umtru 3,820 m³/s (New Umtru spillway); Lower Subansiri, Kopili HEP and Kurichu releases [TBC]; release before, during and after the storm; lock not less than 72 hours 5.8.3, 5.8.5
Ranganadi (NEEPCO), Lower Subansiri (NHPC), Kopili (NEEPCO, Khandong), Kurichu (Bhutan) and New Umtru (Meghalaya) dams Upstream of Assam's reaches Releases and gate operation to be included in river levels (operating rules and release records [TBC]); no credit for warnings, drawdown or attenuation 5.8.3, 5.8.5
Beels, pukhuris, jans and retention ponds that receive town drains, among them Borsola, Sorusola and the scheduled water bodies of every Master Plan area Statewide Receiving storage; full to the outlet at the start; surveyed stage–storage [TBC]; storage belongs to the system; interception and screens before any outfall that carries sewage 5.8.5
Juris and hill streams of the Guwahati fringe (Bahini above Jonali, Basistha, Kalmani, Khanapara–Jorabat streams), of the Karbi and Dima Hasao hills and of the north-bank bhabar fans; the Jinjiram from the Garo hills Guwahati fringe; hill districts; north bank Hill streams; ungauged; 1% AEP study with bulking and blockage and surveyed flood marks; invert at least 0.5 m above the highest surveyed bed; silt trap at the hill–plain break; lock not less than 24 hours 5.2, 5.8.1, 5.8.5
Drains of GMC, GMDA, the Municipal Corporations and Boards, the Development Authorities, PWD and NHAI 1.0 m wide or more; WRD drainage-scheme channels Assam Major drains; WRD permission under the 1953 Act through an embankment or sluice; owner's consent, design water level and flap gate 5.2, 5.8.5
River mouths subject to sand-bar closure None in Assam Not applicable (Clause 5.1.4) 5.13.1

To be prepared. This annex will list and map (a) the major drains of each basin plan, (b) the riverine outfall reaches where backwater shall be modelled, with their upstream and downstream limits and the source of their design flood levels, and (c) the river mouths and creek inlets subject to seasonal sand-bar closure, with the most recent pre-monsoon bar crest levels and any WRD mouth-maintenance programme. It needs WRD river and canal records, design and recorded flood levels, reservoir operating rules, mouth-condition, dredging and bar-cutting records and pre-monsoon bar surveys (WRD), the drain inventories of GMC and other local bodies, basin stormwater master plans (Chapter 11), and base mapping from the Survey of India and NRSC. Until it is published: every river, WRD canal, the Bharalu and the Bahini, the Mora Bharalu, the Basistha, the Kalmani, the Khanajan, the Bondajan and the Lakhimijan in Guwahati, the DTP drain of Dibrugarh to the Sessa, every channel of a WRD drainage scheme and every drain that discharges through a sluice in an embankment, any drain built or held by GMC, GMDA, a Municipal Corporation, a Municipal Board, a Development Authority, PWD or NHAI with an internal width of 1.0 m or more, and every jan, juri or other natural channel that drains 8 ha or more and every tidal creek is a major drain (Clause 5.2); the water bodies of Table 5B.1 are riverine outfall reaches (Clause 5.8.1); and the mouths of the coastal States' rivers (there is none in Assam) are assumed closed at the start of the monsoon unless the Water Resources Department certifies otherwise (Clause 5.13.2).

Table 5B.2 — Attributes of the Annex 5B layers (layout)

Field Content Unit or format
feature_id Unique identifier text
name Name of the drain, river, canal, creek or mouth text
category Major drain; riverine outfall reach; mouth subject to sand-bar closure text
clause Clause of Chapter 5 under which it is listed text
reach_limits Upstream and downstream limits of the reach text
design_flood_level_source WRD design or highest recorded flood level, or hydraulic model (Clause 5.8.2) text
reservoir_release Upstream reservoir or tank and its operating rule, where any (Clause 5.8.3) text
bar_crest_level Most recent pre-monsoon bar crest level, for mouths m (Survey of India datum)
mouth_programme WRD mouth-maintenance programme and certification (Clause 5.13.2) text
source Source agency and date text
geometry Line (drains and reaches) or point (mouths) line / point

Annex 5C — Worked example: outfall-closed check for a site on the hill fringe of south Guwahati draining to the Bahini

Supports Clauses 5.9, 5.10, 5.11 and 5.12 of Chapter 5 and Clause 4.6.6 of Chapter 4.

Illustrative — not design values. This example applies the outfall-closed check of Clause 5.10 to the revised detention facility of Annex 4C. The site, its levels and its receiving drain are invented to show the method. No tidal level is used: the tide enters only through the illustrative statements in Table 5C.1 about whether the receiving drain is above or below the site outlet.

Inputs

5C.1 The site is the 2.0 ha flood-sensitive site of Annex 4C, on the hill fringe of south Guwahati. It discharges through its own outlet chamber and a flap gate to a public storm drain that joins the Bahini, whose level rises when the stream comes down from the Khasi hills in spate and stays up while the Bharalu below it is held behind the closed Bharalumukh sluice, so Clause 5.10.1 applies to the facility. To show the method, this example uses the two 6-hour lock windows of Clause 5.10.3, as the coastal editions of this Manual do. In Assam an outfall to a hill stream whose invert is below its design level is closed for the storm and the stream's recession, and for not less than 24 hours; a river-locked outfall, such as every outfall in the Bharalu basin at Bharalumukh, is closed for the whole 72-hour storm and for as long as the Brahmaputra stays above the sill, not less than 7 days where no stage record has been analysed, and its stored volume is pumped down within 48 hours with the gate still shut; an outfall to a release reach is closed for not less than 72 hours; and an outfall below the design level of a full beel, pukhuri or pond is closed for the whole storm, under Clause 5.8.5. In each of those cases the facility must store or pump the volume of the longer closure, up to the whole storm volume (Clause 5.9.4); that needs more storage, or pumping, than this example shows. The routing, the volume balance of Clause 5.10.4 and the assessment are the same. The public drain's own outfall to the Bahini would also need the debris rack, the bulking factor and the silt trap of Clause 6.3.6 and an invert above the range of bed movement of Clause 5.8.5(f); and on a natural slope of more than 10° the facility itself would be a lined tank, not an infiltrating basin (Clause 4.11 (hill rule)).

Table 5C.1 — Inputs (Illustrative — not design values)

Item Value Basis
Facility Revised facility of Annex 4C: 2,500 m² plan area, vertical walls; 170 mm orifice at the floor; 460 mm orifice, invert 0.53 m Annex 4C, Table 4C.14
Storm 1% AEP, 48 h, peak day last, AMC III; 72 h also run Clause 5.10.2
Inflow Post-development 1% AEP hydrographs of Annex 4C (48 h: 8,420 m³; 72 h: 9,468 m³) Annex 4C
Receiving drain levels at the connection, J1, J2 and J3 Below the site outlet invert (from the drain owner's model) Illustrative input
Receiving drain during each lock window Backs up above the site outlet invert, so the site cannot discharge Illustrative input; Clause 5.10.3(b)
Flap gate on the site outlet Set 0.15 m below the orifice inverts in the outlet chamber, so that outside the lock windows its opening head and head loss do not affect the orifice control Illustrative input; to be confirmed from the certified curve (Clause 5.11.2)
Lock windows Two of 6 h each, starts 12.4 h apart (semi-diurnal tide) Clause 5.10.3(a)
Pumps None —

5C.2 Cases of Table 5.2. Because the receiving drain stays below the site outlet in J1, J2 and J3 (Table 5C.1), those cases give the free-outfall results of Annex 4C: in J2 the 1% AEP maximum water level is 1.17 m (2,913 m³), and in J3 (10% AEP, 48 h) it is 0.77 m. R1 and R2 do not apply, because the site does not drain to a river. J4, the outfall-closed check, is worked below.

Lock windows (Clause 5.10.3)

5C.3 The peak 1-hour block of the final 24 hours of the 48-hour storm is 35:35–36:35 h, with 98.2 mm (the 1-hour depth of Table 4C.2). Two runs are made:

  • Run A: the first window is centred on that block: 33:05–39:05 h; the second starts 12.4 h later: 45:29–51:29 h.
  • Run B: the first window starts at that block: 35:35–41:35 h; the second: 47:59–53:59 h.

For the 72-hour storm, every time is 24 h later.

5C.4 Gravity discharge is zero inside each window. Outside the windows the outlet discharges through the orifices of Table 4C.10. The routing is the same level-pool routing as in Annex 4C.

Results

Table 5C.2 — Outfall-closed check results (Illustrative — not design values)

Storm Run Lock windows (h:min) Maximum stage (m) Maximum storage (m³) Time of maximum (h:min) Largest release after a window (L/s)
1% AEP, 48 h A 33:05–39:05; 45:29–51:29 2.01 5,019 39:05 566
1% AEP, 48 h B 35:35–41:35; 47:59–53:59 2.10 5,238 41:35 584
1% AEP, 72 h A 57:05–63:05; 69:29–75:29 2.00 5,012 63:05 565
1% AEP, 72 h B 59:35–65:35; 71:59–77:59 2.09 5,233 65:35 584

Run B of the 48-hour storm governs. The first window closes the outlet just as the storm peak arrives, so the whole peak is stored. The second window arrives when the facility has drained to about 0.7 m, below the Stage 2 orifice, and adds little.

5C.5 Volume balance (Clause 5.10.4). Table 5C.3 gives the balance for Run B. The outflow in each period is found by continuity: outflow = storage at start + inflow − storage at end.

Table 5C.3 — Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)

Period (h:min) Inflow (m³) Gravity outflow (m³) Pumped (m³) Storage at start (m³) Storage at end (m³)
0:00–35:35, before window 1 3,817 2,213 0 0 1,604
35:35–41:35, window 1 3,634 0 0 1,604 5,238
41:35–47:59, between windows 941 4,423 0 5,238 1,756
47:59–53:59, window 2 28 0 0 1,756 1,784
After 53:59 0 1,784 0 1,784 0
Total 8,420 8,420 0 — —

Check for window 1: V_inflow = 3,634 m³ ≤ V_storage available + V_pumped + V_gravity = (5,238 − 1,604) + 0 + 0 = 3,634 m³. The facility therefore needs 5,238 m³ of storage, which the routing confirms.

Table 5C.4 — Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)

Time (h) Inflow (L/s) Outlet Outflow (L/s) Stage (m) Storage (m³)
24 20 Open 18 0.18 445
28 39 Open 24 0.25 621
32 59 Open 32 0.36 906
34 85 Open 37 0.47 1,166
36 286 Closed 0 0.78 1,944
38 106 Closed 0 1.73 4,321
40 66 Closed 0 1.96 4,904
42 51 Open 529 1.79 4,472
44 42 Open 204 0.87 2,181
46 37 Open 49 0.74 1,854
48 33 Open 47 0.70 1,756
50 0 Closed 0 0.71 1,784
54 0 Closed 0 0.71 1,784
56 0 Open 43 0.58 1,459
60 0 Open 32 0.37 921
66 0 Open 16 0.16 397
72 0 Open 7 0.06 162

Assessment

5C.6 Clause 5.10.4(a). The facility of Annex 4C reaches 1.17 m in J2, and its spillway crest is at 1.35 m (Annex 4C). In the outfall-closed check the stage reaches 2.10 m, so the spillway would operate. The facility of Annex 4C fails the check.

5C.7 Remedy. Pumping (Clause 5.12) does not help here: during the lock windows the receiving drain is itself closed, and pumping into it would raise its level, which Clause 5.12.3 does not permit. The remedy is more storage. Keeping the plan area of 2,500 m² and the outlets of Annex 4C:

  • the facility must hold 5,238 m³, to a stage of 2.10 m;
  • the spillway crest is set above that stage, with the 0.15 m clearance recommended in Clause 4.9.3: 2.25 m;
  • with the 4.0 m spillway of Annex 4C (head 0.30 m), the maximum level with the spillway flowing is 2.55 m, and with 0.3 m freeboard the top of the walls is at least 2.85 m above the floor.

The outfall-closed check therefore governs the storage: 5,238 m³ against 2,913 m³ from the release-rate checks, about 80% more. A larger plan area would make the facility shallower; the outlet, caps and drawdown would then have to be re-checked, because the stage–discharge relationship changes.

5C.8 Release after the lock. When the first window ends, the stored water is released under a head of about 2 m, at up to 584 L/s. This is above the 100-yr cap of 356 L/s. Clause 5.10.4 allows this, because the release reaches a drain that has itself just reopened, and requires it to be included in the J4 run of the downstream analysis (Clauses 5.4 and 5.9) and reported on Form 5-1, Section H.

5C.9 Drawdown after the storm (Clause 5.10.5). The J1 tidal curve stays below the site outlet (Table 5C.1), so the drawdown of Annex 4C applies: 45.3 h for 90% of the 10-yr storage with the low-flow orifice 50% blocked, within the 48-hour limit of Clause 4.7. In Run B, 90% of the maximum J4 storage is released 22.6 h after the maximum.

5C.10 Other requirements.

  • The flap gate on the site outlet is inspected and operated before 31 March each year and after every event in which it closed against a storm flow (Clause 5.11.5).
  • The deeper facility is checked for flotation with groundwater at the design groundwater level; in the flood plains of the Brahmaputra and Barak valleys, the char and chapori lands, the beel and pukhuri margins and the land behind embankments without piezometer readings that level is existing ground level (Clauses 4.12.1 and 4.12.3).
  • The fence and signs of Annex 4C apply to the deeper facility (Clause 4.15).

Table 5C.5 — Summary (Illustrative — not design values)

Item Value
Governing case J4, 1% AEP 48-hour storm, Run B (first window starting at the peak 1-hour block)
Storage required 5,238 m³ (Annex 4C release-rate design: 2,913 m³)
Maximum stage 2.10 m, with 2,500 m² plan area
Spillway crest 2.25 m
Top of walls ≥ 2.85 m above the floor
Largest release after a lock window 584 L/s, to be included in the downstream J4 run
Drawdown Annex 4C result applies: 45.3 h with the low-flow orifice 50% blocked

Form 5-1 — Downstream and Tailwater Report

Supports Clauses 5.3 to 5.14 of Chapter 5.

Draft form — Assam Stormwater Design Manual, Draft v1.0. One report for each project. Sites of less than 0.5 ha that meet Clause 5.3.4 may submit Form 5-2 instead, where the Authority accepts it. Attach the plans, model files and hydrographs referred to.

A. Project

Table 5F.1 — Form 5-1: project

Field Entry
A1. Project name, applicant and location  
A2. Project type: site under Chapter 4; drainage project under Chapter 6; regional detention or tank restoration (Clause 5.1.2)  
A3. Site or project area (ha) and outfalls  
A4. Site Runoff Control Report reference (Form 4-1), where applicable  

B. Extent of the analysis (Clause 5.3; Clause 5.14, item 1)

Table 5F.2 — Form 5-1: analysis points

Point Location Type (Clause 5.3.3 (a) to (e)) Contributing catchment (ha) Project area as % of it
         
         
         

Table 5F.3 — Form 5-1: end point

Field Entry
B1. End point and reason: 10% point, tank or pukhuri, or major drain or the sea (Clause 5.3.1 (a) to (c))  
B2. Where the end point is a tank or pukhuri: change in maximum water level (m) and in surplus-weir discharge (m³/s); continuation below the weir if the level rises (Clause 5.3.2)  
B3. Plan of the analysis extent, showing the site, each point with its contributing area and percentage, and the end point (attach)  

C. Model (Clause 5.4.4; Clause 5.14, item 2)

Table 5F.4 — Form 5-1: model

Field Entry
C1. Software and version; hydrologic and hydraulic methods (Clause 5.4.4)  
C2. Network schematic, with the survey sources for drains and crossings (attach)  
C3. Land use and CN of off-site areas (present land use)  
C4. Upstream detention included, with evidence that it is built, maintained and documented  
C5. Calibration or validation evidence, where available  
C6. Scenarios run: existing, with project, and future where the Authority requires it (Clause 5.4.1)  
C7. Storms run: AEPs and durations, AMC and areal reduction (Clause 5.4.3)  

D. Results at each analysis point (Clause 5.4.2; Clause 5.14, item 3)

Complete one row for each analysis point, AEP and duration. E = existing; P = with project.

Table 5F.5 — Form 5-1: results by analysis point

Point AEP Duration (h) Peak flow E / P (m³/s) Time to peak E / P (h) Maximum water level E / P (m) Peak velocity E / P (m/s) Duration of inundation E / P (h)
               
               
               

E. Acceptance (Clause 5.5; Clause 5.14, item 4)

Table 5F.6 — Form 5-1: acceptance criteria

Criterion Met at every point? Where not met, the remedy adopted (Clause 5.5.3)
E1. 1% AEP water level rise ≤ 10 mm at buildings, lowest openings and carriageways (Clause 5.5.1(a))    
E2. No building newly flooded; no building or road newly failing the Chapter 6 limits (Clause 5.5.1(b))    
E3. Peak flow not above existing at the minor-system AEP of each element or at 1% AEP (Clause 5.5.1(c))    
E4. Velocity in lined channels within the lining limit, 3.0 m/s maximum (Clause 5.5.1(d))    
E5. Velocity in unlined channels, 50% and 10% AEP, not increased by more than 10% (Clause 5.5.1(e))    
E6. Change in duration of road closure on arterial or emergency routes (Clause 5.5.2)    
E7. Timing exception requested (Clause 5.5.4)? Give the conditions met    

F. Tailwater derivation (Clauses 5.6 to 5.8; Clause 5.14, item 5)

Table 5F.7 — Form 5-1: tailwater derivation

Field Entry
F1. Tide-table edition and port, or port authority source (Clause 5.7.2(a))  
F2. MHWS, HAT and MSL (m above chart datum)  
F3. Connection from chart datum to the Survey of India benchmark and the project datum: offset (m) and source (Clause 5.7.2(b))  
F4. Estuary, creek or canal outfall: levels used and any evidence for a departure from open-coast levels (Clause 5.7.2(c))  
F5. 10% AEP surge and 1% AEP still-water level: values, source, method and record length (Clause 5.7.3)  
F6. Wave set-up, for outfalls facing the open sea (Clause 5.7.3(d))  
F7. SLA (m), at least +0.3 m; design life; sensitivity run at twice the SLA for design lives over 50 years (Clause 5.7.4)  
F8. Non-tidal tailwater: receiving-system level and source (Clauses 5.6.2, 5.6.3)  
F9. River levels and sources; reservoir or tank releases included (Clauses 5.8.2, 5.8.3)  
F10. River-locked outfalls, Guwahati, dyke-protected and bowl towns, tributaries and release reaches, beels and pukhuris, hill streams, and drains of other bodies: for a river-locked outfall, the operator of each sluice, gate and pumping station identified (WRD or the local body), gate sills, embankment, dyke or wall crest, installed capacity, operating levels and sluice-closing level obtained, with every level tied to the datum of the nearest CWC or WRD gauge and the operator named; 1% AEP river level at the outfall from a model, and not below the highest recorded level at the nearest CWC gauge transferred to the outfall (Dibrugarh 106.48 m, Neamatighat 87.37 m, Tezpur 66.59 m, Guwahati (DC Court) 51.46 m, Goalpara 37.43 m, Dhubri 30.37 m, Annapurnaghat 21.84 m, Badarpurghat 18.48 m, Karimganj 16.57 m, or the tributary levels of Clause 5.8.5(d)), with the profile or interpolation used; 10% AEP river level, not below the danger level transferred; the datum of each CWC level confirmed or flagged; drain, jan or beel behind the gate routed with its whole catchment (including any part in Meghalaya) and present storage, starting full to its outlet, pumping confirmed available (permanent pumps only, not more than installed capacity less the largest pump), pumps operable at the design river level; the lock (the whole 72-hour storm and while the river stays above the sill, from the stage record used, or not less than 7 days on the Brahmaputra, the Barak and the Kushiyara and 72 hours on a tributary) and the pump-down to the starting level within 48 hours with the gate shut; gate-failure and breach checks; for Guwahati, the basin (Bharalu, Dipar, Silsako, Foreshore, North Guwahati or Kalmoni), the Bharalumukh pumps confirmed by WRD, the Noonmati and Bondajan pumped inflows, the Deepor Beel level and the Brahmaputra level at the Khanajan's outfall, and any ADB or other works counted only once commissioned and confirmed; for Dibrugarh, the Sessa sluice tailwater not below 97.50 m with Larua Jamira beel full and the drain flowing full, and its datum; for Silchar, the Annapurnaghat level and the breach check with the enclosed area filled to the Barak level; for a release reach, the operator's consent, levels in writing (feet converted at 1 ft = 0.3048 m, datum stated), the largest recorded release (Ranganadi 1,412.57 m³/s; Umtru 3,820 m³/s) or the spillway capacity, placed before, during and after the storm, and a lock of not less than 72 hours, with no warning, drawdown or attenuation credited; for a Kopili outfall, the river's pH; for a beel, pukhuri, jan or pond, its outlet level, surveyed monsoon water line, surveyed stage–storage relation, starting level and design level, and the interception and screens before it; for a hill stream, the 1% AEP study with the rainfall of its sub-area (the Guwahati catchment rule of Clause 2.3.6(c)(i) where it applies), the bulking and blockage of Clause 6.3.6, the surveyed flood marks and their sources, the bed survey and range of bed movement, the invert at least 0.5 m above the highest surveyed bed level, the scour depth of the foundation, the silt trap at the hill–plain break, and a lock of not less than 24 hours; WRD's permission under the Assam Embankment and Drainage Act, 1953 (ss.15 and 16); owner's consent (GMC under s.242 of the 1969 Act; a Municipal Corporation under ss.171 and 177 of the 2022 Act; PWD, NHAI, GMDA or another body; the District Council in an Autonomous District), permitted rate, design water level or computed channel level, and flap gate; and the byelaw 26(ix)/44(ix) setbacks, the water-bodies law, the Hill Land Act, the Master Plan riverfront strip and the byelaw 45(c) flood level checked (Clause 5.8.5)  

G. Joint cases (Clause 5.9; Clause 5.14, item 6)

Table 5F.8 — Form 5-1: joint-case results

Case Rainfall Tailwater used (m, project datum) Applies? Governing result (storage, level, pipe size or pump capacity)
J1        
J2        
J3        
J4        
R1        
R2        

H. Outfall-closed check (Clause 5.10; Clause 5.14, item 7)

Table 5F.9 — Form 5-1: outfall-closed check

Field Entry
H1. Reason the check applies (Clause 5.10.1)  
H2. Storm: AEP, 48 h and 72 h, AMC III (Clause 5.10.2)  
H3. Lock duration and basis: default of two 6-hour windows, or site study (Clause 5.10.6); extension for sand-bar closure (Clause 5.13.5)  
H4. Lock windows of the two runs (start and end times) (Clause 5.10.3(d))  
H5. Maximum stage in each facility, against its 1% AEP maximum water level (Clause 5.10.4(a))  
H6. Maximum stage in the minor and major systems, against the Chapter 6 limits (Clause 5.10.4(b))  
H7. Property connections: surcharge level, or non-return valves fitted (Clause 5.10.4(c))  
H8. Stage hydrographs (attach)  
H9. Drawdown after the storm under the J1 tidal curve, and pumping where needed (Clause 5.10.5)  

Table 5F.10 — Form 5-1: volume balance for each lock window (Clause 5.10.4)

Period Inflow (m³) Gravity outflow (m³) Pumped (m³) Storage at start (m³) Storage at end (m³)
Before window 1          
Window 1          
Between windows          
Window 2          
After window 2          

I. Gates and valves (Clause 5.11; Clause 5.14, item 8)

Table 5F.11 — Form 5-1: schedule of flap gates, tide gates and non-return valves

Location Type Size (mm) Invert (m, project datum) Certified head–discharge data (reference) Stop-log or penstock (outfalls > 600 mm)
           
           

J. Pumped outfalls (Clause 5.12; Clause 5.14, item 9)

Table 5F.12 — Form 5-1: pumped outfalls

Field Entry
J1. Reason pumping is needed (Clause 5.12.1)  
J2. Duty capacity (m³/s) at the static head for the J2 tailwater; standby capacity (Clause 5.12.2)  
J3. Effect on the receiving water level (Clause 5.12.3)  
J4. Power supply: two independent supplies, or standby generation with 72 h of fuel; automatic changeover (Clause 5.12.4)  
J5. Level of electrical panels, controls, generators and fuel, against the higher of the 1% AEP flood level + 0.5 m and HAT + surge + SLA + 0.5 m (Clause 5.12.5)  
J6. Discharge arrangement (Clause 5.12.6); controls, alarms and logging (Clause 5.12.7); screens (Clause 5.12.8)  

K. Sand bar (Clause 5.13; Clause 5.14, item 10)

Table 5F.13 — Form 5-1: sand-bar assumption

Field Entry
K1. River mouth or creek inlet concerned  
K2. Mouth assumed closed, or open with WRD certification attached (Clause 5.13.2)  
K3. Bar crest level from the most recent pre-monsoon survey (m) and the closed-mouth tailwater (Clause 5.13.3)  
K4. Extension of the lock duration, where required (Clause 5.13.5)  

L. Inspection and maintenance (Clause 5.14, item 11)

Table 5F.14 — Form 5-1: inspection and maintenance

Field Entry
L1. Gate and valve inspection before 31 March and after closure events (Clause 5.11.5)  
L2. Pump test runs before 31 March (Clause 5.12.9)  
L3. Other requirements for the maintenance plan (Chapter 10)  

M. Statement by the registered professional (Clause 10.6)

I state that this report has been prepared under Chapter 5 of the Assam Stormwater Design Manual (Draft v1.0), that the results reported are reproduced by the models submitted, and that every departure from Chapter 5 is listed with its reason. The Professional Design Certificate (Form 10-3) is attached.

Table 5F.15 — Form 5-1: statement by the registered professional

Field Entry
Name  
Qualification and registration number  
Empanelment number, where Clause 10.6.1 requires it  
Organisation  
Signature  
Date  

Draft form — Assam Stormwater Design Manual, Draft v1.0.


Form 5-2 — Simplified Downstream Statement (small sites)

Supports Clause 5.3.4 of Chapter 5.

Draft form — Assam Stormwater Design Manual, Draft v1.0. For sites of less than 0.5 ha. The Authority may accept this statement in place of the full analysis only where every answer in Section B is "Yes". Otherwise submit Form 5-1.

A. Site

Table 5F.16 — Form 5-2: site

Field Entry
A1. Project name, applicant and location  
A2. Site area (ha), less than 0.5 ha  
A3. Receiving public drain: name or reference, type and size  
A4. Site Runoff Control Report reference (Form 4-1)  

B. Conditions (Clause 5.3.4)

Table 5F.17 — Form 5-2: conditions

Condition Yes / No Evidence
B1. The receiving public drain has documented capacity for its minor-system design flow (Chapter 6)    
B2. No flood-prone location is recorded within 500 m downstream of the site outfall. Records checked: local body, GMC, ASDMA, WRD (Clause 5.3.3(d))    
B3. The site does not drain to a tidal or backwater-affected outfall    

C. Route plan

Table 5F.18 — Form 5-2: attachments

Attachment Attached?
C1. Plan of the drainage route from the site outfall for 500 m downstream, with the receiving drain and any recorded flood-prone locations  
C2. Copy or reference of the drain capacity record  

D. Statement

I state that the site meets the conditions of Clause 5.3.4 as shown above, and that the records listed have been checked.

Table 5F.19 — Form 5-2: statement

Field Entry
Name  
Qualification and registration number  
Signature  
Date  

Draft form — Assam Stormwater Design Manual, Draft v1.0.