Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Assam the failure is one of missing criteria and of drains split among many hands. No document of DoHUA, T&CP, GMDA, GMC, any other Municipal Corporation or Board, PWD or WRD stating a design return period, intensity or runoff coefficient for the storm drains of any town was found. The CAG found storm-water drainage in the test-checked ULBs covering "3 to 37 per cent only" of the need, and GMC's data on storm-water drainage "not available as it was involved with works of drain desilting only", although it spent ₹32.57 crore on desilting from 2013–14 to 2017–18 (Report No. 4 of 2019); it found GMDA "not functioning as per the spirit" of its Act, with "very few technical staff", and no action against the consultants for "defective DPRs for Storm Water Drainage Project for Guwahati City" (Report No. 2 of 2024). ADB puts the stormwater drainage of the State's ULBs at "only about 30% of the required areas" and names the cause: "fragmented institutional responsibilities involving multiple institutions, such as the Guwahati Metropolitan Development Authority (GMDA), Public Works Department, and Water Resources Department" (report and recommendation of the President, 2025). The approval route shapes this chapter. Since the Assam Building Construction (Regulation) (Amendment) Act, 2022 (Assam Act XXVII of 2022), one Act and one set of byelaws cover every notified Master Plan area: GMDA or another Development Authority grants the planning permit "as per the provisions of Master Plan and Zoning Regulations", and GMC, another Municipal Corporation, a Municipal Board or a Gaon Panchayat the building permit under the byelaws (s.6, amending s.2); the occupancy certificate follows, and GMC already checks rainwater harvesting there, with penalties up to its revocation (as reported); the time for a permit was cut from 45 to 30 days in 2024 (as reported). The Unified Byelaws 2022 already ask for much of what a drainage submittal needs: a "Detailed drainage plan for both internal and external required to be constructed upto the available permanent/pucca drain of municipal/other authority" and the "detail provisions made for conservation and harvesting of rain water" on the plans (byelaw 94); the rainwater structures of Appendix VI "shown in plans while applying for planning permission"; on hill sites a topographic survey with proposed ground levels and erosion measures (110(a)) and earthwork and slope-stability calculations vetted by an approved third party (110(f)); on sites liable to flood and in hilly areas a "dry sump (including design calculation) in all individual plots, capable of holding rain water during peak monsoon" (byelaws 74(ii) and 110(h)); a plinth "0.3 m higher than the highest recorded flood level as fixed by the local authority" (45(c)), although no local authority's level was found for any town [TBC]; and the "Improvement of drains up to the nearest outlet point … as directed by the Authority", with an "Additional 25% of the cost of improvement at PWD rate" as a penalty if it is not done (101(vi)). The Act defines a "drain-surface water" as one "used or constructed to use solely for conveying to any drain any rain water" (s.2(20)). An outfall through an embankment or sluice needs the permission of WRD under the Assam Embankment and Drainage Act, 1953 (ss.15 and 16); a scheduled water body, the committees of the Assam Urban Water Bodies (Preservation and Conservation) Act, 2024; a guard wall or house on hill land in a Designated Area, the Advisory Committee under s.14 of the Assam Hill Land and Ecological Sites (Protection and Management) Act, 2006; and a well in a notified area, the State Ground Water Authority under the Assam Ground Water Control and Regulation Act, 2012, under which no area has yet been notified. The byelaws do not extend to the Autonomous Districts unless a District Council notifies that they apply (byelaw 1(2)), and no such notification was found [TBC]. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a design storm, and the dry sump's "design calculation" has no method to follow. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the competent authority for the area can check it with the drawings the Unified Byelaws 2022 already require: the drainage plan of byelaw 94 to the pucca drain, the Appendix VI plans and the dry-sump calculation, which Chapter 4 supplies, at the planning permit; the hill-site survey and third-party slope checks of byelaw 110 at the building permit; the permission of WRD for any outfall through an embankment or sluice; and the occupancy certificate at completion. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Assam Unified Building Construction (Regulation) Byelaws 2022 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the Unified Byelaws 2022 steps an Assam applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for State-wide work and nearly every project, and 45N only for a project wholly west of 90° E, a strip of Dhubri, South Salmara-Mankachar and western Kokrajhar and Goalpara districts that includes Dhubri town at about 89.98° E (this Manual's reading; district boundaries and coordinates to be confirmed against Survey of India data [TBC]); at most a sliver of Tinsukia district east of 96° E would fall in 47N [TBC] and is mapped in 46N, and a project uses one zone for all its layers and states which), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC flood-forecasting and level-monitoring sites on the Brahmaputra, the Barak, the Kushiyara and their tributaries (not stated in any source found [TBC]), of the gauges of WRD and of its embankment crests, sluice sills and gate-closing levels, and of the flood marks surveyed on ungauged channels, beels and pukhuris used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Assam has no notified design return period or design storm for its urban drains. The town drainage master plans of DoHUA were "prepared before 2015 as per previous FPS system" and await revision to the CPHEEO guideline of 2015 (DoHUA, status of drainage master plans, c. 2016), and no design criteria appear in any of their documents read; Guwahati's storm-drainage report by Tahal (2008) was not built (as reported); the comprehensive drainage master plan that Haskoning DHV is preparing for GMDA was under revision, not final, in November 2026 (as reported); and Dibrugarh's DTP drain was designed by a "rainfall based approach … The peak discharge computed by rational method", with no return period given (ADB, 2017). The first design values found in an official Assam document are those of the ADB-funded Bahini works: inundation "from a 1-in-5-year storm or lower return period avoided in 434 ha of frequently flooded areas of Bahini Basin", with "Inundation areas of 693 ha during the design storm of 65.72 mm hour" (ADB, project administration manual, 2025); the duration behind 65.72 mm per hour and its return period are not stated, and the 616-ha baseline of the same table differs from the 693 ha [TBC]. A 1-in-5-year target is below the 10% AEP that Table 2.1 sets for minor drains in high-density areas, so a design that uses it reports it on Form 2-1 and meets this Manual's AEPs. A research model has simulated about 34 m³/s for a 2-hour, 5-year storm in a proposed outfall system for Guwahati (EGU abstract, 2026), research only. The rainfall studies do not supply a design storm either. No intensity–duration–frequency relation with published constants was found for any Assam station; IMD's national study (Das et al., 2022) prints panels for Guwahati and Dibrugarh (Mohanbari), but both repeat a generic curve and are not used; NIH-DHAARA's depths exceed every IMD 24-hour record at Guwahati, Dibrugarh, Tezpur, North Lakhimpur and Silchar and are reported for comparison only; and the two CWC Flood Estimation Reports that cover the State disagree, the report for subzone 2(a) giving a 1-hour ratio of 0.260 on the north bank and the report for subzone 2(b) 0.48 on the south bank, while the Barak valley lies in subzone 2(c), for which CWC has published no report. The storms on record exceed the screening values: Guwahati's self-recording gauge took 163 mm in 3 hours and 179 mm in 6 hours on 18 July 1978, above the 3- and 6-hour depths that the 2(b) ratios give on the city's 50-year plate value, and Nowgong's 427 mm in 24 hours on 3–4 September 1978 (CWC, Flood Estimation Report for subzone 2(b), Annex 4.2), and SIRD Khanapara recorded 215.9 mm overnight on 20 April 2026 (as reported). The State's design values are therefore those of Chapter 2: the plates and ratios of the two reports by sub-area (Clause 2.3.6(c) and (f)), the Guwahati catchment rule of Clause 2.3.6(c)(i), the Barak valley rule of Clause 2.3.6(c)(ii) and the short-storm floors of Clause 2.3.6(g), and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). An Assam calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or T&CP:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by T&CP and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the Unified Byelaws 2022 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the T&CP list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the permission of WRD, through its Embankment Officer, for any work that cuts, crosses, alters or discharges through an embankment, sluice or drain under the Assam Embankment and Drainage Act, 1953 (ss.15 and 16), or for a work on a river in its charge, the permission of the Commissioner to make or alter a drain leading into a drain vested in the Corporation (Gauhati Municipal Corporation Act, 1969, s.242) or of the Municipal Corporation or Board under the Assam Municipal Corporation Act, 2022 (ss.173–177) or the Assam Municipal Act, 1956, the permission of the Authority for any use of a plot scheduled under the Assam Urban Water Bodies (Preservation and Conservation) Act, 2024 (Unified Byelaws 2022, land-use note added in 2024) and the approval of the State Level Committee for any change that diminishes a water body or alters its character (ss.3 and 15 of the Bill; the enacted section numbers [TBC]), the prior approval of the Advisory Committee for a guard wall or a house on hill land in a Designated Area (Assam Hill Land and Ecological Sites (Protection and Management) Act, 2006, s.14), the permit or direction of the State Ground Water Authority in an area notified under the Assam Ground Water Control and Regulation Act, 2012 (none has been notified), the consent of PWD or NHAI for a discharge to a side drain or culvert of one of their roads, the consent of PCBA for a discharge that carries effluent, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (in Guwahati, GMDA, GMC, PWD, WRD, the Railways or another owner of drains), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Assam because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Assam extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Assam has no dated State or municipal order fixing pre-monsoon desilting. In Guwahati, GMC's cleaning of nearly 550 drains was "expected to begin from mid-February" in 2026, desilting procedures "issued in February 2025" are said to have been "largely ignored", and the Mayor said that the work "will be completed before the monsoon" (all as reported). The drains are run by several hands, and no notification divides them: under a working split of 2022, GMC desilts the Bharalu, the Mora Bharalu, the Basistha, the Bahini and the Lakhimijan with their primary and secondary drains; WRD desilts the Bondajan and installs and maintains the dewatering pumps at the Bharalu, the Mora Bharalu and the Bondajan; and PWD cleans about 263 roadside drains (all as reported); GMDA builds new drainage, excavates Silsako and is the project implementation unit of the ADB-funded Bahini works (ADB, 2025); and the Railways, OIL, NHAI, the Army and others keep their own drains (as reported). In March 2025, 21 monitoring committees of the District Disaster Management Authority were reported to oversee the desilting in Guwahati (as reported). GMDA treats about 15 MLD at Silsako "with bacterial dosing" before release to the Brahmaputra (State report to the National Green Tribunal, 9 October 2024, as quoted), so the retention ponds that hold storm water mixed with sewage need their own operating rules. In the other Municipal Corporations the public drains vest in the Corporation, which must provide "a safe and sufficient outfall … for effectual drainage and proper discharge of storm-water and sewage" (Assam Municipal Corporation Act, 2022, ss.171 and 173); the Gauhati Municipal Corporation Act, 1969 lets the Commissioner set up "reservoirs, sluices, engines and other works" (s.231(2)) but sets no comparable outfall duty (s.232 is permissive). The gates that matter most are WRD's: the sluices in its embankments, 98 major and 545 minor in March 2017 (CAG), are closed and opened by its staff, but no operating rule of WRD for any sluice, linking it to a river stage, and no record of how long its sluices stay closed in a monsoon were found [TBC]; Dibrugarh's outfall sluice is to be rebuilt as "two numbers of radial automatic sluice" (ADB, 2017), whose operating rule was not found. The dams upstream are operated for power: the Ranganadi project released 1,412.57 m³/s in 2017 (as quoted from a report of IIT Guwahati for ASDMA), and the release rules and warning procedures of the Ranganadi, the Lower Subansiri and the Kopili projects were not found [TBC]. No operating rule for any sluice, flap gate or pumping station in an Assam town, linking it to a river stage, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 March) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Assam, the pre-monsoon inspection of sluice gates, flap gates, non-return valves, screens, silt traps and pumped facilities, including the gates and pumps on outfalls through the embankments of WRD and to the Brahmaputra, the Barak and the beels, with the desilting of every drain, nala (a built drain) and jan (Assamese জান: a stream or natural drainage channel, often the outlet of a beel), the clearance of inlets, silt traps, screens and hill-stream traps, and the pump duty and gate seal tests, shall be completed by 31 March; sluice gates, flap gates and pumped facilities, with their standby power and fuel, shall be certified ready on the same date, with every gate on an outfall to a river or beel operated through its full travel, by or with WRD where the gate is in its charge, because the season of this Manual begins on 1 April and the storms of April and May are among the State's largest. Pumps, their standby power, gates and screens shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to a river until the river at the governing CWC site has fallen below its danger level and the gates have been reopened, if that is later. Inlets, silt traps, screens and hill-stream traps shall be cleared again by 31 May, of the silt, debris and garbage of the April and May storms, before the south-west monsoon arrives, and every public drain, nala and jan, inlet, trap and screen in every town shall be cleared of the silt and debris of the season, and its silt depths surveyed, by 15 November.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December. The monsoon season of this Manual, 1 April to 31 October, is bracketed: the pre-monsoon storms of April and May and the south-west monsoon from about the first week of June, whose withdrawal date for Assam was not obtained. December to February is marked as the dry works window, and March (in the Barak valley) and November as months with storms outside the season. Lanes show routine inspections; the desilting of drains and jans, the clearance of inlets, silt traps and screens, the pre-monsoon inspection, the readiness of sluice gates, flap gates, pumps and standby power and the Form 10-7 declaration, all by 31 March; standby of pumps, gates and screens from 1 April to 31 October; a mid-season clearance by 31 May; a post-season clearance by 15 November; inspections after heavy rainfall in any month; the reporting year from 1 April to 31 March; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Monsoon season of this Manual: 1 Apr–31 Oct Dry: works window Dry Storms (Barak) Storms Pre-monsoon storms South-west monsoon Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 Mar 31 May 31 Oct 15 Nov Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 Mar: drains and jans desilted; inlets, silt traps and screens cleared; inspection; sluice and flap gates, pumps and standby power ready. 1 Apr–31 Oct: standby. By 31 May: mid-season clearance of inlets, silt traps, screens and hill-stream traps. By 15 Nov: post-season clearance. After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including March and November storms) Annual declaration Form 10-7 Form 10-7 by 31 Mar, closing the reporting year (1 Apr–31 Mar): Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one season, 1 Apr–31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 March, 31 May, 31 October and 15 November are fixed (set by this Manual). December–February is practically dry (CWC). Pre-monsoon storms: Dhubri (Rupsi) 479.3 mm in 24 h on 28 May 1989 and Dibrugarh (Mohanbari) 231.5 mm on 10 May 1996 (IMD). The south-west monsoon arrives about the first week of June; its withdrawal date for Assam was not obtained [TBC]. Late-season storms: Haflong 237.1 mm on 30 October 1959; Dhubri (Rupsi) 220.0 mm on 4 October 1958. Outside the season: Silchar 245.4 mm on 29 March 1922; Haflong 234.2 mm and Silchar 174.2 mm on 9 November 1955 (all IMD).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October, and its first two months bring some of the State's largest storms: four of the seventeen Assam station records of 24-hour rainfall in IMD's Extremes are May storms, Dibrugarh (Mohanbari) 231.5 mm (10 May 1996), Dhubri (Rupsi) 479.3 mm (28 May 1989), Rangia 217.0 mm (29 May 1977) and Silchar 290.3 mm (30 May 1893), Haflong's May value of 248.2 mm (10 May 1958) is 80% of its record (ratio computed for this Manual), and Silchar's wettest month on record is May (1,314.2 mm in 1883) (IMD). April brings storms too: Guwahati's April record of 116.5 mm (6 April 2004, IMD) was beaten on 20 April 2026, when the airport recorded 117.4 mm, SIRD Khanapara 215.9 mm, Gauhati University 134 mm and the City ARG 126.5 mm overnight, and a woman died after falling into an open roadside drain on the night of 19 April (all as reported); Chaparmukh's pre-monsoon record is 193.2 mm on 23 April 1982 (IMD). The CWC Flood Estimation Report for subzone 2(b) finds that "The rainfall is generally spread over a period of eight months, i.e. from March to October", that at Guwahati and Nowgong "May rainfall is more than the September rainfall. Similarly, April rainfall is more than October rainfall", and that "The winter season from December to March is practically dry"; December to February is the works window. NDMA (2010) sets 31 March for pre-monsoon desilting nationally, and this Manual keeps that date. A deadline of 30 April, which the research for this edition first suggested for the Brahmaputra valley, would leave the April storms uncovered, and the Barak valley has storms in March (Silchar 245.4 mm on 29 March 1922, IMD); one date applies statewide, the same as in the neighbouring North-East edition of this series, because Guwahati's hill streams rise across the State's southern border and the catchments that cross it are cleared and inspected on one calendar. No Assam order fixes a date for drains (Clause 10.11, Commentary). The dates of WRD in the press are for embankment works, not for drains: the Chief Minister's target of 30 April 2018 for embankment repairs, which was missed, "no permanent work … from May 15 to October, only temporary work", and works to be "concluded before the month of May" (2021) (all as reported); that calendar is WRD's for its embankments, while this Manual's 31 March covers the drains, sluice gates, flap gates and pumps of the drainage system. This Manual therefore takes 31 March for desilting, the clearance of inlets, silt traps and screens, the pre-monsoon inspection, the annual declaration and the readiness of gates, pumps and standby power, with no later readiness date. The south-west monsoon arrives about the first week of June: its normal onset over the North East is about 5 June (as reported), and IMD's revised normals are reported to put Guwahati at 2–4 June (as quoted in a summary of IMD's press release). Inlets, silt traps, screens and hill-stream traps are therefore cleared again by 31 May, after the April and May storms and before the onset. The date of the monsoon's withdrawal from Assam was not obtained [TBC], but storms continue to the end of October: Haflong 237.1 mm (30 October 1959), Dhubri (Rupsi) 220.0 mm (4 October 1958), Dhubri 186.2 mm (2 October 2012) and Guwahati 160.9 mm (15 October 1991) (IMD); pumps, gates and screens are therefore kept on standby to 31 October (Figure 10.3), and the research's suggestion of a post-monsoon check by 30 September is not used, because standby and the after-event inspections run to 31 October. Large falls also come outside the season, Haflong 234.2 mm and Silchar 174.2 mm on 9 November 1955 (IMD), and the drains fill with silt during the season, so every town clears its drains a second time, and surveys their silt depths, by 15 November. The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Assam cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Assam drainage show up only in the first monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Assam Unified Building Construction (Regulation) Byelaws 2022 are made and from the municipal Acts. The graduated steps are set by this Manual. In Assam the courts and the National Green Tribunal have become the working regulators of the city's drains and beels. The Gauhati High Court, in PIL/14/2024 on Guwahati's waterlogging, recorded the engagement of Haskoning DHV by order of 21 August 2024 to prepare a "GIS-based Comprehensive Drainage Master Plan and Detailed Project Report (DPR) for Guwahati City" within nine months (order of 23 September 2024) and found on 26 May 2025 that "hill cutting is still going on"; in PIL/53/2023 it appointed an Advocate Commissioner after builders were said to have blocked channels and filled wetland at Palasbari, causing "artificial floods" (6 September 2024); in PIL 18/2023 it directed the State not to denotify the Deepor Beel sanctuary (5 April 2024); and in the Silsako eviction appeals it was reported to say "Once it is a water body you have to move out" (2023, as reported). The Tribunal has dealt with dumping near Deepor Beel (O.A. No. 472 of 2018, order of 11 February 2020), the polluted river stretches, among them the Bharalu (O.A. No. 673 of 2018), and the State's sewage gap (O.A. No. 606 of 2018). The statutes carry real terms of imprisonment but mostly nominal fines. Under the Assam Embankment and Drainage Act, 1953, cutting through an embankment or drain, or opening, shutting or obstructing a sluice without authority, is punishable with up to three years and ₹1,000 (s.15(ii)), and so is building on, removing or altering an embankment or drain in a notified area without permission, with removal at the offender's cost (s.16); the fine is nominal by today's values, the imprisonment is not, and the cut at Bethukandi in 2022, for which a police case was registered and one arrest made (as reported), is such an offence (this Manual's reading). Under the Assam Hill Land and Ecological Sites (Protection and Management) Act, 2006, earth cutting on a hill or altering an ecological site in a Designated Area is punishable with up to six months or ₹5,000 (s.19), nominal, and no Designated Area was found [TBC]. The water-bodies law is the strongest: the Guwahati Waterbodies (Preservation and Conservation) Act, 2008 provided up to three years or ₹50,000 (s.6), and the Assam Urban Water Bodies (Preservation and Conservation) Bill, 2024, which repeals it (s.22), provides up to three years or ₹1 lakh or both, with restoration of the water body "to its original status and shape" (s.16); the enacted text of the Act of 2024 was not read [TBC]. Under the Gauhati Municipal Corporation Act, 1969 the Commissioner may pull down any building erected over a drain vested in the Corporation (s.239), no one may make or alter a drain leading into one without permission (s.242), and no building within one hundred feet of a municipal drain may be occupied until it is drained to it (s.244); the fines under the Act were not read [TBC]. The Unified Byelaws 2022 add their own lever, the 25% penalty on the cost of drain improvement not carried out (byelaw 101(vi)), and GMC's drive on rainwater harvesting from 20 June 2025 threatened the revocation of occupancy certificates and the sealing of premises, while builders were reported to "conveniently flout" the rules and their association to call the Appendix VI structures "faulty" (all as reported). The CAG found that the State "relied on short term measures to avert flood problems without adopting long term solutions" (Report No. 5 of 2018), that GMC had no storm-drainage data (Report No. 4 of 2019) and that GMDA was "not functioning as per the spirit" of its Act (Report No. 2 of 2024). This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the stage of the receiving river (the Brahmaputra, the Barak, the Kushiyara or a tributary) at the nearest CWC site, against its warning, danger and high flood levels, and, where it is gauged, at the outfall and inside the embankment, each on a named datum, with any reading of a WRD or local gauge kept apart from the CWC levels; the times at which each sluice and flap gate on the outfall and on the drain upstream of it closed and reopened, the level in the receiving beel or retention pond, the hours each pump ran, any loss of power and the fuel used; any breach or cut of an embankment, with its time and the level the water reached inside it; and the releases of any dam that set the receiving level, such as the Ranganadi, Lower Subansiri or Kopili projects, with the times of the warnings given;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), ASDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Assam's floods have been counted more often than they have been reviewed, and the counts conflict, differing in whether landslides, storms and lightning are included. In 2022, the worst flood season in a decade, more than 88 lakh people were affected, with 54.57 lakh in 32 districts on 23 June, and the deaths are given as about 181, 195 or 197 (all as reported); Silchar was under water for about 11 days, or "about a week" in another account, after the Barak entered through the cut embankment at Bethukandi, and a police case was registered over the breach of 23 May (as reported). In Guwahati, the floods of June 2014 caused seven flash-flood deaths and four electrocutions (CAG, Report No. 4 of 2019); on 14 June 2022 four people died in a landslide at Nizarapar and Boragaon; on 31 May 2025 three died in a landslide at Bonda; and on 19 April 2026 a woman died after falling into an open roadside drain (all as reported). The season of 2024 affected 24,20,722 people in 30 districts at its peak about 5 July and killed 117 by 27 July, that of 2025 111 by 30 August, and that of 2026 105 by 17 August, with 11,45,109 people affected in 25 districts between 29 April and 3 August (all as reported). ASDMA's daily flood reports list the rivers above their danger levels (on 4 July 2024, the Brahmaputra at Neamatighat, Tezpur, Guwahati, Goalpara and Dhubri, the Barak, the Kushiyara at Karimganj and others, none above its high flood level), but ASDMA's official tolls for these seasons were not obtained [TBC]. No review of any flood in an Assam town, and no record of flood extents, depths or durations kept by GMC, GMDA, another Municipal Corporation or Board, or ASDMA, was found. The rainfall record shows why reviews need more than one gauge: on 14 June 2022 the gauges of WRD at Chandmari and Beltola recorded 84.6 mm and 88 mm while Borjhar recorded about 10 mm (as reported), and on 20 April 2026 the gauges of one city ranged from 117.4 mm to 215.9 mm (as reported). NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Much of Assam's drainage record is public: the Unified Byelaws 2022 and their amendment of 2024, the Guwahati Building Construction (Regulation) Byelaws, 2014 and the gazette of the Master Plan for Guwahati 2025 with its zoning report and modification schedule, on GMDA's website; the Acts on the website of the Legislative Department and in PRS's copies, among them the building Act and its amendment of 2022, the Gauhati Municipal Corporation Act, 1969, the Assam Municipal Corporation Act, 2022, the Assam Embankment and Drainage Act, 1953, the Hill Land Act of 2006, the groundwater Act of 2012 and the Urban Water Bodies Bill, 2024; the CAG's reports of 2018, 2019 and 2024; the High Court's orders in PIL/14/2024, PIL/53/2023 and PIL 18/2023 and the Tribunal's orders on Deepor Beel; ADB's report and recommendation, project administration manual and environmental examinations for Guwahati and Dibrugarh; PCBA's action plan for the Bharalu; JICA's evaluation of the Guwahati sewerage project; CGWB's Ground Water Year Book for the North Eastern Region; DoHUA's status sheet of the town drainage master plans; ASDMA's daily flood reports; and IMD's station extremes and the two CWC Flood Estimation Reports. Several of these were read only from archived copies, because the State's websites refused connections while this edition was prepared. Much else could not be found in the public domain: the comprehensive drainage master plan for Guwahati and the project reports for the Bahini and the Bharalu; Tahal's report of 2008; the town drainage master plans themselves; the modification of the Master Plan 2025 of 25 March 2025 and the drainage and wetland chapters of the draft Master Plan 2045; the enacted Urban Water Bodies Act, its schedules and its Rules of 2025; the Designated Areas under the Hill Land Act; the constitution of the State Ground Water Authority; the text of the GMDA Act, 1985; any notification by a District Council applying the byelaws; CWC's site sheets and gauge datums; an inventory of WRD's sluices with their sills and operating rules; the present capacity of the pumps at Bharalumukh; the stage–storage of Deepor Beel; the archives of the Guwahati city gauges; and ASDMA's official tolls. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)