Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, pukhuri and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Assam town; the comprehensive drainage master plan for Guwahati, which is to cover six river basins surveyed by DGPS and drone (State affidavit, February 2026, as reported), is under revision. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:
- Guwahati, Bharalu–Bahini: the catchment of the Bahini from its head in Meghalaya to Jonali and of the Bharalu from Jonali to the sluice at Bharalumukh, with the Noonmati basin and its diversion by pumping to the Bondajan, the whole catchment modelled with the design rainfall of the Guwahati catchment rule (Clause 2.3.6(c)(i)), the sluice at Natun Bazar, the ADB pumping stations and retention pond and the outfall-closed case at Bharalumukh as a design case (Clause 5.8.5(b)), the drains carrying sewage to the Bharalu's outfalls in the 1D network, and the Brahmaputra at Guwahati (DC Court), danger level 49.68 m and high flood level 51.46 m (CWC, as transcribed by SANDRP, as reported; datum not stated), as the boundary;
- Guwahati, Mora Bharalu–Deepor Beel–Khanajan and Silsako: the catchments of the Basistha and the Kalmani and of the Mora Bharalu to Deepor Beel and on through the Khanajan to the Brahmaputra, with the beel's stage–storage, once surveyed [TBC], its perennial spread of about 10.1 km² and up to 40.1 km² in floods (as reported) and its draft eco-sensitive zone shown; and the Silsako basin, with the retention basin to which part of the Bahini's runoff is to be diverted and pumped out (ADB, 2025);
- Guwahati, the other ADB basins: the Dipar, Foreshore, North Guwahati and Kalmoni basins (ADB, initial environmental examination, 2017), North Guwahati on the north bank under the 2(b) rainfall of Clause 2.3.6(b), each to its outfall on the Brahmaputra;
- Guwahati hill fringe: the streams that come down from the hills to the south at Khanapara and Jorabat, with their silt traps at the hill–plain break (Clause 6.3.6(m)) and the cut slopes, quarries and landslide ground above them mapped, and the hazard-first rule below;
- Dibrugarh, DTP drain to the Sessa: the town behind the DTP dyke and its drain of 32.053 km past the Larua Jamira beel to the Sessa, with the beel full and the drain flowing full at the start of the storm and the flood level of 97.50 m at the outfall sluice (ADB, 2017) as the boundary, and the Brahmaputra at Dibrugarh, danger level 105.70 m and high flood level 106.48 m (as reported), on the dyke side;
- Silchar, behind the Barak embankment: the bowl of the town, with its outfall channels and any pumps, once surveyed [TBC], the Barak at Annapurnaghat, danger level 19.83 m and high flood level 21.84 m (as reported), and the breach path of the Bethukandi cut of 2022 and its flood marks as calibration evidence;
- Karimganj, Hailakandi and Badarpur: the towns on the Kushiyara and the Barak, with the Kushiyara at Karimganj, danger level 14.94 m and high flood level 16.57 m, and the Barak at Badarpurghat, 16.85 m and 18.48 m (as reported), as boundaries, under the Barak valley rule of Clause 2.3.6(c)(ii);
- Palasbari–Mirza: the channels and wetland whose blocking and filling the High Court has examined as "artificial floods" (PIL/53/2023);
- North-bank towns on release and flash-flood reaches: North Lakhimpur on the Ranganadi, Dhemaji, the Subansiri reach and Tezpur on the Jia Bharali, with the largest recorded release, or the spillway capacity until the operator gives one, as the boundary (Clause 5.8.5(d)), and the bhabar fans above them mapped;
- Dhubri and Goalpara: the towns on the lower Brahmaputra, with the Brahmaputra at Dhubri (high flood level 30.36 m in 1988, or 30.37 m in 2019, a conflict) and at Goalpara (37.43 m in 1954 or 37.35 m in 2004, a conflict) (as reported), and, at Dhubri, the record check of Clause 2.3.6(h);
- Majuli and the char lands: under the hazard-first rule below; and
- Haflong and Diphu: the hill towns, Haflong on the 2(b)/2(c) line, with landslide ground mapped and the hazard-first rule below.
Hazard first (set by this Manual). On active char and chapori land and eroding banks, in the breach path of an embankment, in a reach below a dam, on the bhabar fans and avulsing streams of the northern foothills, on the landslide ground of the Guwahati hills and the hill districts and on cut hill slopes, the BSMP begins with a hazard screening (Clause 2.3.6(i)), made with the flood and landslide maps of ASDMA where they exist [TBC], the Hilly Area Zone of the Master Plan for Guwahati 2025, the hazard maps that byelaw 120 asks the Master Plans to carry once they are made, and WRD's records of its embankments, sluices and breaches, and states whether each part of the basin lies in the path of the hazard. The scale is large: riverbank erosion is reported at more than 4.27 lakh ha since 1950 or about 3.86 lakh ha since 1954 (both as reported, a conflict); the Ranganadi released 1,412.57 m³/s in 2017 (as quoted from a report of IIT Guwahati for ASDMA); and landslides killed four at Nizarapar and Boragaon on 14 June 2022 and three at Bonda on 31 May 2025 (as reported). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to hold a channel on active char land or to carry a breach, a debris flow or a landslide. Other Tier A bodies and the other Municipal Corporations and Boards define their basins in the first BSMP that covers them. Where CWC, WRD, a master plan, an operator of a dam or a court has a high flood level, a gate-closing level, a flood line or an operating rule for a dam, sluice or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Assam a single channel passes through many hands, and often across the State's border, on its way to a river. The Bahini rises at Umtyrnga in Meghalaya and runs 9.29 km to Jonali, where it becomes the Bharalu, which runs 6.2 km to the Brahmaputra at Bharalumukh; the catchment is about 120 km², roughly half hills and half plains, of which about 10.94 km² drains the city (PCBA action plan for the Bharalu, as quoted; about 11 km² in a press account, a conflict); the Bahini is "cut off by a sluice at Natun Bazar" (the same plan), and the Mora Bharalu, a channel "abandoned by the Bharalu river" (Assam's progress report to the National Green Tribunal, August 2020), carries water and sewage to Deepor Beel, which drains to the Brahmaputra through the Khanajan. ADB divides the city into "six drainage basins … Bharalu Basin, Dipar Basin, Silsako Basin, Foreshore Basin, North Guwahati Basin, and Kalmoni Basin" and finds that "The wetlands and other water bodies in GMA collectively act as the receptors of storm water during the monsoons" (initial environmental examination, 2017). No notification assigns the Bharalu, the Mora Bharalu or the Bahini to one owner (this Manual's reading of the record): GMC desilts them, WRD runs the sluice and the pumps at their outfalls, PWD holds the roadside drains, GMDA builds new drainage and protects the scheduled water bodies, and the Railways, OIL, NHAI and the Army keep their own drains (ADB, 2025; press reports), and ADB names "fragmented institutional responsibilities" as the core problem. The law already treats the channels as part of the water bodies: the Assam Urban Water Bodies (Preservation and Conservation) Bill, 2024 defines a water body to include "all natural water channels (that are inflow or out flow channels into or from the waterbody)" (s.2(d)), and the Hill Land Act of 2006 counts "a drainage system, feeding channel" among its ecological sites (s.2(d)(ii)). Dibrugarh shows the same at town scale: its DTP drain runs 32.053 km past the Larua Jamira beel to the Sessa, receiving the town's sewage on the way (ADB, 2017). This clause makes the basin the planning unit, so that one model carries each channel from its head in the hills, across the State's border where it rises there, to the river, through every sluice and pump, whoever owns each reach.
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of the Guwahati Metropolitan Area (the area of the Master Plan for Guwahati 2025, 328 km², on both banks): GMDA, which plans the area, builds new drainage, protects the scheduled water bodies and is the project implementation unit of the ADB-funded Bahini works, jointly with GMC, which keeps the municipal drains and desilts the Bharalu, the Mora Bharalu, the Basistha, the Bahini and the Lakhimijan (as reported); the BSMP is taken into the Master Plan and its Zoning Regulations (Clause 11.9). For Dibrugarh and Silchar: the Dibrugarh Municipal Corporation and the Silchar Municipal Corporation, in which the public drains vest and which must provide a safe and sufficient outfall for storm water (Assam Municipal Corporation Act, 2022, ss.171 and 173), each jointly with the Development Authority of its Master Plan area (names [TBC]) and with T&CP, which prepares the Master Plans and the drainage master plans of the towns outside the Guwahati Metropolitan Area. Each role is the one the body would have if the Manual were adopted. Where a basin extends beyond the Corporation's limits or the Master Plan area, the other local bodies and Gaon Panchayats in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No order dividing the city's channels among GMC, GMDA, PWD and WRD was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: WRD, through its Embankment Officers, for the rivers, the embankments and the sluices in them, the drainage schemes, the sluice and pumps at Bharalumukh, the dewatering pumps at the Bharalu, the Mora Bharalu and the Bondajan and the desilting of the Bondajan (as reported); GMC and the other Municipal Corporations and Boards for the municipal drains and the channels they desilt; GMDA for new drainage, the Bahini works, the Silsako retention basin and the scheduled water bodies in its area; PWD for the roadside drains, and NHAI for those of the national highways; the Railways, OIL, the Army and the other owners of drains for their own; and, for the scheduled water bodies outside the GMDA area, the District Level Committee under the Assam Urban Water Bodies (Preservation and Conservation) Act, 2024. Each town keeps the drain register of Chapters 1 and 6, which gives every reach its owner.
- ASDMA, with the District Disaster Management Authority, for the flood, erosion and landslide hazards that a BSMP must show (Clause 11.3.3).
- In the other Municipal Corporations and Boards, the Development Authorities and Tier B bodies: the Lead Authority is named by DoHUA. In an Autonomous District (the Bodoland Territorial Region, Karbi Anglong and West Karbi Anglong, and Dima Hasao), the Lead Authority is the District Council or the authority it designates, only where the Council has notified that the byelaws or this Manual apply (none has). Basins draining to a common river reach or sluice may be grouped into one district-level plan.
WRD shall also be a partner in every BSMP whose outfall passes through one of its embankments or sluices; ASDMA and the Deputy Commissioner shall be consulted on every BSMP; the State Level Committee under the Act of 2024, and in the GMDA area GMDA as chair of the District Level Committee, on every BSMP that proposes works in or next to a scheduled water body; the Environment and Forest Department and the Assam State Wetlands Authority on every BSMP whose basin drains to Deepor Beel or another wetland; PCBA on every BSMP that proposes works on a drain that carries sewage, among them the Bharalu; the Guwahati Jal Board on every BSMP in the area of its sewerage project; the operator of any dam that sets the receiving level, NEEPCO for the Ranganadi and the Kopili and NHPC for the Lower Subansiri, on every BSMP whose outfall lies on a release reach; and, for a basin whose streams rise across the State's border, such as the Bahini, the Basistha and the Kalmani, the authorities of the neighbouring State through WRD, since the rain on the part of the catchment beyond the border is part of the design storm (Clause 2.3.6(c)(i)).
The Water Resources Department (WRD) shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, pukhuri, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, rivers, embankments, sluices and pumps | The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the receiving river at the nearest CWC site (for example the Brahmaputra at Guwahati (DC Court), danger level 49.68 m and high flood level 51.46 m, and the Barak at Annapurnaghat, 19.83 m and 21.84 m; CWC levels as transcribed by SANDRP, as reported, with the datum not stated) and its recorded peaks, with any WRD or local gauge kept as a separate series and any conflict between published values stated; embankment crest levels and the location of every sluice in the embankments of WRD, with its sill, gate type, closing level and operating rule; the pumping stations on the outfalls, with their installed and working capacities, sump volumes and standby power; the stage–storage of every beel and retention pond that receives the outfall, starting full to its outlet; past breaches and cuts of the embankments and the land they flooded; the release records of any dam that sets the receiving level; and the char and chapori land, eroding banks and bhabar fans in and below the basin |
| Rainfall and levels | All available rain gauges (IMD, including the Regional Meteorological Centre Guwahati and its stations in Extremes, among them Guwahati (Borjhar) (42410), Dibrugarh (Mohanbari) (42314), Tezpur (42415), North Lakhimpur (Lilabari) (42309), Dhubri (42404) and Dhubri (Rupsi) (42406), Silchar (42619) and Silchar (Kumbhigram) (42620), Haflong (42522), Lumding (42523), Chaparmukh, Golaghat, Goalpara, Gohpur, Rangia, Tangla and Majbat; the self-recording gauges at Guwahati, Nowgong (Nagaon), Dibrugarh, Chabua and Jorhat used for the CWC Flood Estimation Report for subzone 2(b); the river gauges of CWC; the rain gauges of WRD, among them Chandmari and Beltola in Guwahati; the Guwahati city gauges reported in 2026, the City ARG, AAU-HRS, Gauhati University and SIRD Khanapara (owners, logging intervals and archives [TBC]); and any gauges or sensors kept by GMC, GMDA, ASDMA or Guwahati Smart City Ltd [TBC]) and water-level records, including those for the 31 May 2025 (111 mm in 24 hours at Guwahati (Borjhar), the highest May day on record there, with 120 mm and 99.6 mm given in other outlets, and three deaths in a landslide at Bonda, as reported), 14 June 2022 (84.6 mm at Chandmari and 88 mm at Beltola, gauges of WRD, against about 10 mm at Borjhar and 46 mm for the city, so that the gauges of one city differed about nine-fold in one storm, and four deaths in the landslide at Nizarapar and Boragaon, as reported), 20 April 2026 (117.4 mm at the airport, the April record, 215.9 mm at SIRD Khanapara, 134 mm at Gauhati University and 126.5 mm at the City ARG overnight, as reported, with no hourly values found), June 2022 at Silchar (the Barak entering the town through the cut in its embankment at Bethukandi, with the Barak at Annapurnaghat peaking at 21.59 m on 21 June and 251.20 mm in Cachar on 19 June, both as quoted from the Cachar district report, and no hourly rainfall in the town found) and June 2014 (the Guwahati floods, with seven flash-flood deaths and four electrocutions, CAG Report No. 4 of 2019, and no rainfall value found) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the floodplains of the Brahmaputra and the Barak, behind the embankments of Dibrugarh, Silchar and the other embanked towns, on the char and chapori land and in the beel basins, where slopes are gentle, the rivers back up and a closed sluice ponds the land behind it, and where a raised road, an embankment or a dumped fill can turn an overflow from one part of a town to another, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 31 May 2025 (111 mm in 24 hours at Guwahati (Borjhar), the highest May day on record there, with 120 mm and 99.6 mm given in other outlets, and three deaths in a landslide at Bonda, as reported), 14 June 2022 (84.6 mm at Chandmari and 88 mm at Beltola, gauges of WRD, against about 10 mm at Borjhar and 46 mm for the city, so that the gauges of one city differed about nine-fold in one storm, and four deaths in the landslide at Nizarapar and Boragaon, as reported), 20 April 2026 (117.4 mm at the airport, the April record, 215.9 mm at SIRD Khanapara, 134 mm at Gauhati University and 126.5 mm at the City ARG overnight, as reported, with no hourly values found), June 2022 at Silchar (the Barak entering the town through the cut in its embankment at Bethukandi, with the Barak at Annapurnaghat peaking at 21.59 m on 21 June and 251.20 mm in Cachar on 19 June, both as quoted from the Cachar district report, and no hourly rainfall in the town found) and June 2014 (the Guwahati floods, with seven flash-flood deaths and four electrocutions, CAG Report No. 4 of 2019, and no rainfall value found) events are the best calibration data Assam has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and pukhuri storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Assam's storage is in its beels and wetlands more than in tanks; it has no irrigation tank cascades, and its pukhuris are mostly the dug tanks of towns and villages. The National Wetland Atlas puts the State's wetlands at 764,372 ha, 9.74% of its area (SAC, 2011, as quoted; the counts of wetlands in different sources conflict and are not used); the Fisheries Department's register listed 2,072 beels of 71,843.5 ha in 2021–22, and later 447 registered and 1,625 unregistered beels, a change in the way they are counted (as quoted). Deepor Beel is the State's only Ramsar site (site 1207, designated 19 August 2002, as listed), its sanctuary of 2009 was restored on appeal and its denotification stayed by the High Court (5 April 2024), and its eco-sensitive zone has been notified only in draft (about 148.9 km² in 2021 and 38.84 km² in 2025, as reported). The Son Beel in Karimganj, the largest in the State, is given as 3,458 ha in a study of 2024 and as 4,388 ha dry and 9,800 ha full elsewhere, a conflict; the Chandubi is reported to have shrunk from 203.2 ha in 1997 to 186.5 ha in 2007. The Assam State Wetlands Authority was constituted by Notification No. FRM.10/2010/Pt/16 of 1 November 2018 (as listed), but no wetland has been found notified under rule 4 of the Wetlands Rules, 2017. Guwahati's scheduled water bodies, Sarusola, Borsola, Silsako and land near Deepor Beel, are listed by dag number in the schedules of the 2008 Act, which the Bill of 2024 repeals (s.22; the enacted text was not read [TBC]); the Bill extends scheduling to all notified Master Plan areas. No survey of the stage–storage of Deepor Beel or of any other beel or pukhuri in a town was found [TBC].
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Assam has been adopted with a design factor; the Assam State Action Plan on Climate Change 2.0 is reported to project that "extreme rainfall events will increase by 5–38 per cent", and a minister to have given 38% by about 2050 relative to 1971–2000 (as reported; the plan text was not read [TBC]); the NAPCC portal lists a change in annual rainfall of +0.97 to +3.04% for 2011–2040 (RCP 4.5 and 8.5, as quoted); IMD's analysis for 1989–2018 is reported to find decreasing trends in each month from June to September, while a study of 26 locations for 1981–2017 found increasing pre-monsoon and monsoon trends, a conflict; and Guwahati set new April (2026) and May (2025) daily records (as reported), which is a reason to keep the factors, not to reduce them; and on the hill fringe of Guwahati, in the hill districts and below the dams the hazard screening of Clause 11.3.3 is made in every scenario.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 31 May 2025 (111 mm in 24 hours at Guwahati (Borjhar), the highest May day on record there, with 120 mm and 99.6 mm given in other outlets, and three deaths in a landslide at Bonda, as reported), 14 June 2022 (84.6 mm at Chandmari and 88 mm at Beltola, gauges of WRD, against about 10 mm at Borjhar and 46 mm for the city, so that the gauges of one city differed about nine-fold in one storm, and four deaths in the landslide at Nizarapar and Boragaon, as reported), 20 April 2026 (117.4 mm at the airport, the April record, 215.9 mm at SIRD Khanapara, 134 mm at Gauhati University and 126.5 mm at the City ARG overnight, as reported, with no hourly values found), June 2022 at Silchar (the Barak entering the town through the cut in its embankment at Bethukandi, with the Barak at Annapurnaghat peaking at 21.59 m on 21 June and 251.20 mm in Cachar on 19 June, both as quoted from the Cachar district report, and no hourly rainfall in the town found) and June 2014 (the Guwahati floods, with seven flash-flood deaths and four electrocutions, CAG Report No. 4 of 2019, and no rainfall value found) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and pukhuris with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: pukhuris, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: sluices, flap gates and penstocks on the outfalls through the embankments of the Brahmaputra, the Barak and their tributaries, with the storage and pumping behind them sized for the outfall-closed durations of Chapter 5, among them the sluice and pumps at Bharalumukh, the Noonmati–Bondajan diversion and the pumping stations and retention pond of the Bahini works in Guwahati, the outfall sluice of Dibrugarh's DTP drain to the Sessa and the outfalls of Silchar behind the Barak embankment; standby power and fuel for the whole closure; screens and silt traps where drains that carry sewage and garbage enter a pump sump, a gate or a beel; silt traps and debris racks at the hill–plain break, where the streams of the Guwahati hills and the hill districts enter the towns; the interception and screening of dry-weather flow before every outfall to a beel or scheduled water body (Chapter 8, Clause 8.9); and the operating rules of the sluices of WRD, agreed with WRD;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts from the Regional Meteorological Centre Guwahati, CWC flood forecasts and river stages at its sites on the Brahmaputra, the Barak, the Kushiyara and their tributaries against their warning and danger levels, the daily flood reports of ASDMA, level gauges with alarms in the Bharalu, the Mora Bharalu and the other city channels at their sluices and pumping stations, and warnings before releases from the dams on the Ranganadi, the Subansiri and the Kopili, whose release rules and warning procedures were not found [TBC]), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge, which is credited only on tested ground outside the floodplain and hill rules, the bhabar fans, the river terraces above the 1% AEP level and the hill-foot colluvium of Guwahati (Clause 4.11, recharge rule), waterlogging where the water table lies within 2 m of the surface, as CGWB found after the monsoon in almost every district, the stability of the Guwahati hills and the hill districts, where water put into colluvium or fill raises the pore pressure, and the quality of the shallow aquifer in the districts with arsenic or fluoride above the limits (Chapter 8);
- effect on downstream basins and the receiving river, jan or beel; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because Assam's town outfalls are closed for days or weeks when the river is high, and the storage left is in beels and low land that the towns are filling. When the sluice at Bharalumukh is closed, the Bharalu's pumps were reported in 2008 to pass 7 m³/s against 72 m³/s by gravity, so the city's drains can empty only as fast as the pumps run, and every cubic metre that cannot be pumped must be stored; Dibrugarh's drainage design accordingly assumes "that the beel is full and the drain is also flowing full" at its outfall sluice (ADB, 2017), and the ADB-funded Bahini works build a retention pond of 59,000 m³ and divert runoff to a retention basin at Silsako to be "gradually pumped out to the Brahmaputra River" (ADB, 2025). The beels are the towns' storage, and the law already says so: a water body is "the area or areas of land where the rain water accumulates and act as natural or storm water reservoir" (Guwahati Waterbodies (Preservation and Conservation) Act, 2008, s.2(e); kept in s.2(d) of the Bill of 2024 that repeals it). They are being lost: Deepor Beel spreads over about 10.1 km² all year and up to 40.1 km² in floods, and is reported to have shrunk by "about 35% since 1991", though other figures conflict (as reported); the water area of the Urpad Beel in Goalpara fell from 4.84 km² in 2003 to 3.38 km² in 2023 (as reported); and among the causes of Guwahati's waterlogging ADB lists the "encroachment of low-lying land", filled swamps and "indiscriminate cutting and quarrying of hill slopes for filling up of low lying areas" (2017). On the floodplain, where the water table is near the surface in the monsoon, storage means a lined pond or a beel kept at its outlet level, never a pond that soaks into the ground (Clause 4.11, floodplain rule); the 5 m³ of storage for every 100 m² of roof that byelaw 114 asks for, held as storage under Clause 4.11, and the dry sump of byelaws 74(ii) and 110(h), designed as detention under Chapter 4, are the first of it. Conveyance upgrades on their own move water faster to an outfall that the Brahmaputra, the Barak or a tributary in flood closes at its sluice for days or weeks, to a beel or retention pond that a closed sluice holds full, or to an outfall limited by the capacity of its sluice or pumping station, as at Bharalumukh, where the pumps were reported in 2008 to pass 7 m³/s against 72 m³/s by gravity with the gates open. Groundwater in Assam calls for storage and restraint, not recharge. It is not short: the stage of extraction was 22% in CGWB's assessment for 2007, with no over-exploited, critical or semi-critical unit, and is quoted at 12.61% for 2024 (as quoted; the columns of the source are unlabelled). It is shallow: in March 2022, before the monsoon, the water level in Assam was "mostly in the range of 2-5 mbgl (57.43%)", with 20.27% of wells within 2 m, and in November 2022 89.13% of wells were within 5 m and 45.96% within 2 m; in Kamrup (Metro) the range was 1.39–4.08 m in March, 0.2–2.76 m in August and 1.29–2.64 m in November; waterlogged and waterlogging-prone areas were found after the monsoon in "almost all the districts of Assam", "due to high rainfall, shallow water level and a poor ground water draft in the vast flood plains" (CGWB, Ground Water Year Book, North Eastern Region, 2022-23). The rising Brahmaputra "reduces the rate of percolation" (ADB, 2017). Its quality limits what can be put into it: arsenic above the limit in isolated pockets of Barpeta, Goalpara, Golaghat, Karbi Anglong, Kokrajhar, Lakhimpur, Sibsagar, Nalbari and Karimganj (as quoted from a Lok Sabha answer of February 2025), fluoride above the limit in parts of Goalpara, Kamrup, Karbi Anglong, Nagaon, Golaghat and Karimganj (as quoted from CGWB), and iron on the north bank (CGWB, 2007). The Assam Ground Water Control and Regulation Act, 2012 allows the State Ground Water Authority to notify areas and direct rainwater harvesting there on premises of 100 m² or more (ss.5(2) and 19), but no area has been notified and the Authority's constitution was not confirmed [TBC]. The percolation pits of Appendix VI of the Unified Byelaws 2022 therefore sit in saturated ground for much of the season they are meant to serve. This is why waterlogging, recharge only on the ground that can take it (Clause 4.11, recharge rule), slope stability and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plan for Guwahati 2025 and its Zoning Regulations under the GMDA Act, 1985, and the Master Plan 2045 once it is notified; the Master Plans and Zoning Regulations of the other towns under the Assam Town and Country Planning Act, 1959; the hazard maps that byelaw 120 of the Unified Byelaws 2022, as amended in 2024, asks the Master Plans to carry; the schedules of water bodies under the Assam Urban Water Bodies (Preservation and Conservation) Act, 2024; in an Autonomous District, the plans and rules of the District Council, if the District Council adopts the Manual; and the layouts and buildings permitted under them. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Assam draws its water lines in its byelaws and Master Plans, and has no floodplain zoning law. The Unified Byelaws 2022 set the minimum distance of any building "from the edge of natural drainage channels": 15 m from a river "as marked in the plan"; 10 m from the Bharalu, the Mora Bharalu and the Bondajan; 6 m from other channels; 15 m from the notified water bodies "Deepar Beel, Silsako Waterbody"; 6 m from "Other notified water bodies (Sarusola, Barsola etc.)"; 10 m from other large ponds and water bodies "as marked in the plan"; and, for minor drains and small ponds not marked in the plan, the ordinary building setbacks (byelaw 26(ix), repeated as byelaw 44(ix) [numbering read from the OCR layout; TBC: confirm against a clean copy]). The table names only Guwahati's channels and beels although the byelaws are statewide, and "as marked in the plan" ties its rows to the Master Plan maps (this Manual's reading). The Authority may refuse a site "near a water body or water course" that the development may contaminate or divert, or a site "likely to be inundated" without satisfactory drainage, or "a filled up tank or low lying" site (byelaw 44(iii) [TBC]); multistoreyed buildings are excluded from areas "on or abutting natural drainage channels" and "wetlands" (byelaw 117); and since 2024 the Master Plans are to map the "natural hazard prone areas where construction is not permitted" (byelaw 120). The Master Plan for Guwahati 2025 classifies "All notified forest, water bodies, rivers etc." as Eco-Sensitive Zone, and its modification schedule forbids construction "within a distance of 15m from river bank" on the riverfront from Sonaram High School to the Kamakhya foothills. The Assam Urban Water Bodies (Preservation and Conservation) Bill, 2024 asks the District Level Committee to "ensure no construction zone within a buffer around the Water Bodies as prescribed in the Notified Master Plan and Assam Unified Building Construction (Regulation) Bye law, 2022" (s.5); that buffer is the byelaw table. The plinth is to be "0.3 m higher than the highest recorded flood level as fixed by the local authority" (byelaw 45(c)), but no such level was found for any town [TBC]. Under the Assam Embankment and Drainage Act, 1953 no one may build on, remove or alter an embankment or drain in a notified area without permission (s.16), but no setback from an embankment was found [TBC]. Assam has not enacted a floodplain zoning law (as quoted from PIB); a proposed Assam Flood Plain Zoning Bill was reported to have been reviewed by the Chief Minister on 5 November 2026 (a single report, unverified), and is not law. The flood-prone area is 31.50 lakh ha, 40% of the State, by the figure of the Rashtriya Barh Ayog as quoted by the CAG (Report No. 5 of 2018), or 31.05 lakh ha, 39.58%, on WRD's website (as quoted); both figures are in use. Where a byelaw line, a Master Plan line or a scheduled water body governs, it applies; this Manual adds the hydraulic corridor and setback zones of Chapter 7, with a Zone 1 of at least 15 m from the top of bank on every natural channel draining 8 ha or more and round every beel and pukhuri, and a Zone 2 to the 1% AEP extent plus 10 m, the line that reaches furthest from the water governing, as this Manual's proposal; it equals the byelaw for rivers, Deepor Beel and Silsako and is stricter elsewhere (Chapter 7), and Zone 1 land that is patta land is reserved in the Master Plan or secured by agreement, not taken. A BSMP gives the Master Plans the 1% AEP drainage-flood map and the buffer widths of Chapter 7 as an input to the hazard maps of byelaw 120, not as a notification under it. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Unified Byelaws 2022 already reserve 20% of every plot for trees and greenery (byelaw 111) and 30% of a plot in hilly areas for vegetation (byelaw 110(k)), require 60% of the open space to be landscaped, half of it unpaved and the rest in permeable pavers "to allow rain water to percolate" (byelaw 92, as amended in 2024), and ask for rainwater harvesting on every building (byelaw 114) and a dry sump "capable of holding rain water during peak monsoon" on flood-liable and hilly plots (byelaws 74(ii) and 110(h)), but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on the floodplain, where the water table is near the surface in the monsoon, it is a shallow lined storage that drains to the outfall, never an infiltration basin (Clause 4.11). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Guwahati Metropolitan Development Authority. Master Plan for Guwahati 2025 and Zoning Regulation 2025, Assam Gazette Extraordinary No. 198, 9 July 2009 (in operation from 7 July 2009; corrigenda No. 199 of 10 July 2009 and No. 62 of 16 March 2010), with the Report Part II, Land Use Zoning & Development Control Regulation, and the Schedule of Modification of Master Plan 2025 (undated). https://gmda.assam.gov.in/
- Gauhati High Court. PIL/14/2024, North East Eco Development Society v. State of Assam, orders of 23 September 2024 and 26 May 2025 (comprehensive drainage master plan; hill cutting). https://livelaw.in/pdf_upload/gau-hc-water-logging-562406.pdf
- Asian Development Bank (2025). Assam Urban Sector Development Project (57262-001): report and recommendation of the President and project administration manual (Bahini works; design and monitoring framework). https://www.adb.org/sites/default/files/project-documents/57262/57262-001-rrp-en.pdf
- Asian Development Bank (2017). Assam Urban Infrastructure Investment Program, Tranche 2 (42265-025): initial environmental examinations for the Guwahati subprojects (six drainage basins) and for the outfall of the Dibrugarh DTP drain.
- Department of Housing and Urban Affairs, Assam (c. 2016). Town wise status of fund release for preparation of drainage master plan; and an undated drainage master plan status sheet (as quoted).
- Pollution Control Board, Assam. Action Plan for the Bharalu River (Priority I) (catchment; outfalls; sewage loads). https://www.pcbassam.org/RRC%20Action%20Plan%20Final/Priority%20I/Action%20plan_Bharalu.pdf
- Central Ground Water Board (2023). Ground Water Year Book 2022-23, North Eastern Region, Technical Series D No. 12/2022-23 (depth to water in Assam and Kamrup (Metro)); and Assam State Profile (2007). https://cgwb.gov.in/cgwbpnm/public/uploads/documents/17032376731214418851file.pdf
- Comptroller and Auditor General of India. Report No. 5 of 2018, Report No. 4 of 2019 and Report No. 2 of 2024 (Government of Assam). https://cag.gov.in/
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Assam Urban Water Bodies (Preservation and Conservation) Bill, 2024, as introduced: ss.2(d), 3–8, 15, 16 and 22 (enacted as Assam Act XXV of 2024, as cited; the enacted text and the Rules of 2025 were not read). https://prsindia.org/files/bills_acts/bills_states/assam/2024/Assam_Urban_Water_Bodies_Bill_2024.pdf
- Guwahati Waterbodies (Preservation and Conservation) Act, 2008 (Assam Act XX of 2008), s.2(e) and Schedules I–IV. https://www.ielrc.org/content/e0845.pdf
- Government of Assam, Department of Housing and Urban Affairs. Assam Unified Building Construction (Regulation) Byelaws, 2022 (Gazette No. 688, 15 October 2022), as amended in 2024 (Gazette No. 667, 20 November 2024): byelaws 26(ix), 44(iii), 44(ix), 45(c), 74, 92, 110, 111, 114, 117 and 120.
- Assam Embankment and Drainage Act, 1953 (Assam Act I of 1954), s.16; Assam Hill Land and Ecological Sites (Protection and Management) Act, 2006 (Assam Act V of 2007), s.2(d); Assam Ground Water Control and Regulation Act, 2012 (Assam Act XVI of 2012), ss.5(2) and 19; Assam Town and Country Planning Act, 1959 (Assam Act II of 1960).
- Government of Assam, Environment and Forest Department. Notification No. FRM.10/2010/Pt/16 of 1 November 2018 constituting the Assam State Wetlands Authority (as listed).
- Gauhati High Court. PIL/53/2023, Khanindra Kalita & 8 Ors v. State of Assam, order of 6 September 2024; PIL 18/2023, Pramod Kalita & 2 Ors v. State of Assam, I.A.(C) 924/2024, order of 5 April 2024.
- Space Applications Centre (2011). National Wetland Atlas: Assam (area and share only, as quoted).
- Central Water Commission (1991, 2000). Flood Estimation Reports for subzones 2(a) and 2(b); and South Asia Network on Dams, Rivers and People (2019), transcription of CWC site data for North East India. https://sandrp.in/2019/10/02/overview-of-cwcs-flood-forecasting-sites-2019-north-east-india/
- IIT Guwahati for ASDMA (2018). Final report with annexures (Ranganadi release of 2017, as quoted).
- The Sentinel, Assam Tribune, EastMojo, NE Now, News Arena, Drishti IAS, IndiaSpend and other sources (2008–2026). Reports of the Haskoning DHV plan and its revision, the Tahal report, the ₹1,459 crore project, the Deepor Beel and Urpad Beel areas, the Chandubi, the registered beels, the erosion figures, the floodplain zoning Bill and the floods and landslides of 2022 and 2025 (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Assam building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Assam's towns have master plans, drainage projects and court-supervised studies, but no published storm-drainage master plan with a design storm. The Master Plan for Guwahati 2025 and its Zoning Regulations, published by GMDA in Assam Gazette Extraordinary No. 198 of 9 July 2009 "for operation with effect from 07/07/2009", cover 328 km² (the old metropolitan area of 262 km² and 66 km² added), put "All notified forest, water bodies, rivers etc." in an Eco-Sensitive Zone and, in a later modification, take their slope classes "from a conceptual guideline derived from a study by IIT(G) in the planning and design of drainage in hilly areas" (the study was not seen), but set no design storm and size no drain; the draft Master Plan 2045, released early in 2024, has not been finally notified (as reported). Guwahati is on its second drainage master plan. The storm-drainage report prepared by Tahal in 2008 was not built (as reported), and the CAG found no action taken against the consultants for "defective DPRs for Storm Water Drainage Project for Guwahati City" (Report No. 2 of 2024). Under the supervision of the Gauhati High Court, GMDA engaged Haskoning DHV by order of 21 August 2024 to prepare a "GIS-based Comprehensive Drainage Master Plan and Detailed Project Report (DPR) for Guwahati City" within nine months (PIL/14/2024, order of 23 September 2024); the State told the Court in February 2026 that it was "expected to be completed by April 2026", and the minister later directed the consultants to revise the plan and the project report for the Bahini–Bharalu basin (both as reported), so in November 2026 the plan is under revision, not final. Outside Guwahati, DoHUA's town drainage master plans were "prepared before 2015 as per previous FPS system" and await revision to CPHEEO's guideline of 2015, with drafts for Tinsukia (11 May 2015), Silapathar and Margherita, Sonari's finalised, Dibrugarh's held up by a "shortage of fund" and Goalpara's "Final hydraulic design work … in progress" (DoHUA, status sheet, c. 2016); a later undated sheet puts Dibrugarh and Silchar at the "final stage" and Jorhat's as "prepared" (as quoted); "The Directorate of Town and Country Planning has started preparing drainage master plans for all major towns in the state" (ADB, 2025); no design criteria appear in any of these documents read. At basin scale, the Brahmaputra Board's master plans for the Brahmaputra (Part I) and the Barak (Part II) were approved in 1997 (as quoted), for the rivers rather than the towns. The first funded works with storage are the ADB-funded Bahini works in Guwahati, with 4.1 km of diversion channels, 4.7 km of drains, 7.8 m³/s of added pumping in three stations and a retention pond of 59,000 m³ with a pumping station of 1.6 m³/s, against a target of avoiding inundation "from a 1-in-5-year storm or lower return period" in 434 ha of the Bahini basin (ADB, 2025), and a project of ₹1,459 crore for the Bahini and the Bharalu was announced in May 2026 (as reported). "Assam's stormwater drainage network in ULBs covers only about 30% of the required areas" (ADB, 2025). This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by DoHUA, T&CP, GMDA, GMC, any other Municipal Corporation, Municipal Board or Development Authority, any District Council, WRD, ASDMA, the Brahmaputra Board or any other body, and it does not replace the plan that Haskoning DHV is preparing for GMDA. A site-level manual cannot fix basin-level problems: lost tank storage, beels and low land filled for building, as round Deepor Beel and Silsako in Guwahati and in the wetland at Palasbari, hill streams that bring the silt of cut hill slopes down into the Bharalu and the other city channels, drains that are the sewers of towns without sewerage and carry their sewage to the beels and the rivers, outfalls that a sluice closes for days or weeks when the river is high, so that the town drains only as fast as its pumps run, and single channels split between GMC, GMDA, PWD, WRD and other owners, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Assam, the first floodplain-river State of the North East in the series: to towns that sit below the high stage of the Brahmaputra or the Barak, behind about 4,474 km of embankments, and drain through sluices and pumps into rivers that are often higher than the town, so that the outfall is normally closed in the monsoon; to beels, pukhuris and jans (jan, Assamese জান: a stream or natural drainage channel, often the outlet of a beel) that the law already treats as storm-water reservoirs and channels, and that are being filled; to a city, Guwahati, whose hill streams, each a juri (Assamese জুৰি: a small hill stream) at its head, rise across the State's southern border and bring down the silt of cut hill slopes; to drains that are the sewers of towns with no sewerage; to two CWC subzones that read the rainfall differently across one river and a third, the Barak valley, that no CWC report covers; to a water table near the surface on the floodplains, where infiltration is not credited; to char and chapori land, eroding banks, embankment breach paths and dam-release reaches, where no drain is the answer; to drains split among GMC, GMDA, PWD, WRD and others with no notification dividing them; and to the Sixth Schedule districts, where the byelaws do not apply unless a District Council chooses, so that a BSMP begins with the river and the hazard, not the storm alone (Clause 11.3.3).