Annexes to Chapter 1Policy, Applicability and Adoption
These annexes support Chapter 1. They hold the lists and maps that define where the Manual applies, the model text of the Policy Supplement and of the legal instruments that would give the Manual effect, and the two forms an Applicant files under Chapter 1. The Manual is a draft; it is not adopted by any government or agency: model legal text is offered for consideration by a competent authority and is not in force, and the forms are draft forms. An annex marked "To be prepared" states the data it needs and the rule to use until it is published (Clause 1.11.5).
Annex 1A — List of Tier A authorities, with the boundaries of the Municipal Corporations, of the planning area of Raipur and of the special area of Nava Raipur Atal Nagar
Supports Clauses 1.6.1 to 1.6.5 of Chapter 1.
1A.1 Clause 1.6.1 defines Tier A by class of authority. Table 1A.1 sets out the classes, and the authorities named in the clause, as Chapter 1 defines them. Every authority not in Table 1A.1 is Tier B (Clause 1.6.2).
Table 1A.1 — Tier A authorities as defined in Clause 1.6.1
| Item | Tier A authority | Clause |
|---|---|---|
| (a) | Raipur Municipal Corporation (RMC) | 1.6.1(a) |
| (b) | Every Approving Authority within the planning area of Raipur under the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973, including the Directorate of Town and Country Planning where it grants development permission, RDA in its scheme areas, and the Municipal Corporations, Nagar Palika Parishads and Nagar Panchayats of the area | 1.6.1(b) |
| (b) | NRDA, the Special Area Development Authority of Nava Raipur Atal Nagar under the 1973 Adhiniyam, in its special area | 1.6.1(b) |
| (c) | Every other Municipal Corporation (Nagar Palik Nigam) constituted under the Municipal Corporation Act, 1956 as adapted in Chhattisgarh: Bilaspur, Durg, Bhilai, Ambikapur, Jagdalpur, Korba, Rajnandgaon and Raigarh (named by the CAG among the State's 14 Municipal Corporations), and Bhilai-Charoda, Risali, Birgaon, Dhamtari and Chirmiri (to be confirmed [TBC]) | 1.6.1(c) |
| (c) | The Directorate of Town and Country Planning and every development authority constituted under the 1973 Adhiniyam, where it grants development permission within the planning area of a Municipal Corporation | 1.6.1(c) |
| — | A Tier B authority that opts into Tier A by council resolution, or that the Government notifies as Tier A | 1.6.4 |
1A.2 Whatever the tier, the design-aid route and the alternatives of Clause 1.7 are not available in a flood-sensitive catchment (Clause 1.6.5; Annex 1B).
To be prepared. This annex will contain the full list, by name, of every Municipal Corporation and every development authority in the State, and of every Approving Authority within the planning area of Raipur and the special area of Nava Raipur Atal Nagar, with the date from which each is Tier A, and the boundaries of those areas as a map and as a GIS layer. It needs the notified planning areas of the development plans under the 1973 Adhiniyam, among them the Raipur Development Plan (Revised) 2021, approved on 5 April 2008, and the Durg–Bhilai plan, and the special area of NRDA (T&CP, the Housing and Environment Department, NRDA); the scheme areas of RDA, whose constitution was not verified for this Manual, and of the other development authorities [TBC]; the current list and boundaries of the Municipal Corporations, Nagar Palika Parishads and Nagar Panchayats (the Urban Administration and Development Department; the CAG gives 14 Municipal Corporations and names nine of them, and the other five were not verified [TBC]); and the district and tehsil boundaries (Revenue and Disaster Management Department, Survey of India), many of which have changed since 2012 with the creation of new districts. Until it is published, the tier is decided by the classes in Clause 1.6.1 and recorded on Form 1-1, and the Authority confirms it at the pre-application stage (Clause 1.5.9).
Table 1A.2 — Register of Tier A authorities (layout)
| No. | Authority | Class (Municipal Corporation / Nagar Palika Parishad / Nagar Panchayat / Special Area Development Authority / development authority / Directorate of Town and Country Planning / other) | District | Basis (Clause 1.6.1(a), (b), (c) or 1.6.4) | Tier A from (date) | Notification or resolution reference |
|---|---|---|---|---|---|---|
| 1 | ||||||
| 2 | ||||||
| 3 |
1A.3 The Municipal Corporation, Raipur planning-area and Nava Raipur special-area boundary map shall be published as open data in a machine-readable format (Clause 10.17.4), with the date of the notification it shows.
Annex 1B — Maps of flood-sensitive catchments
Supports Clauses 1.4, 1.6.5 and 1.10.3(d) of Chapter 1, and Clauses 4.5.3 and 4.5.4 of Chapter 4.
1B.1 The flood-sensitive catchments are listed in Clause 4.5.3.2. Table 1B.1 repeats that list. The maps of this annex and the boundaries of Annex 4A are the same data set and shall be issued together.
Table 1B.1 — Flood-sensitive catchments listed in Clause 4.5.3.2
| Item | Catchment | Extent as described in Chapter 4 |
|---|---|---|
| (a) | Raipur's low colonies on the Kharun nalas | The catchments of the nalas and drains of Raipur and Birgaon that discharge to the Kharun, with the talabs on them and the low-lying colonies that drain to them. The city's sewage and storm water reach the Kharun through some eight large nalas (as reported), now intercepted by diversion weirs for the treatment plants at Chandanidih, Kara and Nimora (CECB, 2021); RMC recorded 11 road stretches that flood two or three times a year and drain coverage of 49% (RMC, 2015); in July 2026 Mowa, Shankar Nagar, Tatibandh, Chaubey Colony, where five ponds overflowed into homes, and the Fafadih and Gudhiyari underpasses were flooded (as reported). The Kharun at Pathardihi has a highest flood level of 281.68 m (29 August 2020) and no published warning or danger level (CWC data as transcribed by SANDRP) |
| (b) | Bilaspur on the Arpa | The land of Bilaspur that drains to the Arpa below the Arpa Bhaisajhar barrage (full reservoir level 302.000 m, WRD) and the Kharang reservoir at Khutaghat, including Sarkanda and the other low colonies of the river's banks, which flooded in September 2025 (as reported); a fall reported as 28 cm in 24 hours flooded the city in July 2026, and another report of 415.6 mm for the same storm is unresolved (as reported); no gauge level for the Arpa at Bilaspur was found [TBC] |
| (c) | Durg–Bhilai on the Seonath nalas | The land of Durg, Bhilai, Bhilai-Charoda and Risali that drains to the Seonath (Shivnath) through the Shankar and Pulgaon nalas and the other nalas of the twin cities, including the township drains of the Bhilai Steel Plant, whose blockage at the Junwani and Kosanala culverts was the subject of a warning by the Bhilai Municipal Corporation in July 2025 (as reported); the NGT ordered Durg's treatment plants on the Shankar and Pulgaon nalas finished within six months in January 2026 (as reported); the Mongra barrage upstream on the Seonath has a full reservoir level of 337.150 m (WRD); no gauge level for the Seonath at Durg was found [TBC] |
| (d) | Korba below Bango and Darri | The land of Korba that drains to the Hasdeo below the Minimata Bango dam (spillway capacity 24,000 m³/s) and the Hasdeo barrage at Darri (19,820 m³/s) (CWC, NRLD 2009); releases of about 30,000 cusecs through six gates of Bango and 20,000 cusecs at Darri flooded houses at Motisagarpada, Seetamani and Imliduggu in August 2024, and the Hasdeo set new highest levels at Katghora, 313.58 m, and Bangodam, 303.5 m, in July and August 2026 (as reported); the ash dykes of the power plants and the mine voids beside the river are flood hazards to map under Chapter 5 |
| (e) | Raigarh–Sarangarh in the Hirakud backwater | The land of Raigarh and Sarangarh that drains to the Kelo, the Mand or the Mahanadi within reach of the backwater of the Hirakud reservoir in Odisha, in which 33 villages of Chhattisgarh are reported to be partly submerged; the Kelo overflowed in Raigarh in August 2019, and the Mand at Kurubhata reached 220.4 m and the Mahanadi at Surajgarh 201.06 m in August 2020 (as reported); the Kelo dam above Raigarh has a full reservoir level of 233.000 m (WRD); the extent of the backwater within the State is not mapped [TBC] |
| (f) | Jagdalpur on the Indravati | The land of Jagdalpur that drains to the Indravati, whose CWC site has a warning level of 539.49 m and a danger level of 540.80 m (CWC advisories of 2019, seen as search extracts) and reached a new highest level of 544.891 m on 26 September 2026, above the 544.68 m of 9 July 1973 (as reported); the river rises in Odisha, where dams on its upper reaches regulate the flow reaching the city, and their releases were not researched for this Manual [TBC] |
| (g) | Notified catchments | Any catchment notified under Clause 4.5.4 |
To be prepared. This annex will contain a map of each catchment in Table 1B.1 at a scale fit for deciding whether a plot lies inside it, and the same boundaries as a GIS layer. It needs catchment boundaries drawn from a digital elevation model and the drain network (the Municipal Corporations of Raipur, Birgaon, Bilaspur, Durg, Bhilai, Bhilai-Charoda, Risali, Korba, Raigarh and Jagdalpur, the Bhilai Steel Plant for its township, Survey of India); the city drains and nalas with their outfalls, the interception weirs of the new treatment plants and their levels on a stated datum (the Municipal Corporations); the full reservoir levels, maximum water levels and gate-operation rules of Gangrel, Minimata Bango, the Hasdeo barrage at Darri, Kharang, the Arpa Bhaisajhar and Mongra barrages and the Kelo dam, and the levels of the Hirakud reservoir and its backwater within the State (WRD, and through it the Government of Odisha); the CWC levels, with warning and danger levels where they exist, on the Kharun at Pathardihi, the Hasdeo at Bangodam and Katghora, the Mand at Kurubhata, the Mahanadi at Surajgarh and the Indravati at Jagdalpur, and any gauge on the Arpa at Bilaspur and the Seonath at Durg; the talabs recorded in the revenue records (the Collectors); and the land flooded in 2007, 2020, 2024, 2025 and 2026 (the Collectors, CGSDMA, the Municipal Corporations). Nava Raipur Atal Nagar, whose streams and lakes NRDA planned as a storage network; Rajnandgaon on the Shivnath; Dhamtari and Rajim below Gangrel; Ambikapur; and the towns of the Bastar division flooded in August 2025 (as reported) are candidates for notification under Clause 4.5.4 once their catchment boundaries and flood record are documented [TBC]. The floodplains of the rivers, the 50 m line that the State Wetland Authority applies around wetlands and the village tanks vested in the State are governed by Chapter 7 and by the instruments that bind there rather than by this list. Until it is published, the Authority decides at the pre-application stage whether a site lies in a listed catchment, from the best boundary available, and the decision and its basis are recorded on Form 1-1 and in the drainage report (Clauses 1.5.9 and 1.11.5).
Table 1B.2 — Attributes of the flood-sensitive catchment layer (layout)
| Field | Content | Unit or format |
|---|---|---|
| catchment_id | Unique identifier | text |
| name | Catchment name | text |
| basis | Clause 4.5.3.2 item (a) to (f), or the notification under Clause 4.5.4 | text |
| notification_ref | Gazette notification number, where notified | text |
| notified_on | Date of notification | date |
| applies_from | Date from which the rule applies to applications (Clause 4.5.4.2, step 5) | date |
| boundary_source | Source and date of the boundary | text |
| area_km2 | Catchment area | km² |
Annex 1C — Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
Supports Clauses 1.6.3, 1.6.5 and 1.7.1 to 1.7.3 of Chapter 1.
Model text for consideration by a competent authority. Not in force. The text below shows how the Policy Supplement of Clause 1.7 could be written. It has no effect unless and until it is issued by the Government and adopted by an Approving Authority under Clause 1.7.3.
Part 1 — General provisions
P1.1 Scope. This Supplement sets out alternatives S-1 to S-5 to the requirements of the Chhattisgarh Stormwater Design Manual (the Manual) named in each alternative. An alternative applies within the area of an Approving Authority (the Authority) only from the date on which the Authority adopts it under P1.3.
P1.2 No lower criterion. No alternative lowers any criterion of the Manual. S-1 and S-2 are simplified methods for meeting the same criterion (Clause 1.7.3(a)).
P1.3 Adoption.
- (a) A Tier B authority adopts an alternative by council resolution in the form of Part 3, and sends a copy to the State Stormwater Technical Committee (the Committee) within 30 days of the resolution.
- (b) A Tier A authority adopts an alternative only after the Committee has concurred in writing.
- (c) The Authority publishes the alternatives it has adopted on its website and in the register of Clause 10.17.
P1.4 Retention. No alternative replaces the retention requirement (Annex 2E depth), except where fee-in-lieu under S-5 funds equivalent retention in the same basin (Clause 1.7.3(d)).
P1.5 Tables. The tables used by S-1, S-2 and S-3 are those issued by the Committee, and are reviewed with Chapter 2 of the Manual (Clauses 1.7.3(e) and 2.14). An alternative that depends on a table cannot be used until that table is issued.
P1.6 Record. An Applicant who uses an alternative states it on Form 1-1 and in the drainage report, with the resolution or concurrence under which it was adopted.
Part 2 — The alternatives
S-1 — Design-aid route for storage
S-1.1 Replaces: storage sized by a hydrograph method under Chapter 3.
S-1.2 Alternative: retention and detention volumes may be taken from the unit-storage tables issued for Annex 4B (m³ per ha, by rainfall zone, hydrologic soil group and impervious fraction) and the compliance calculator, by the method of Clause 4.14.2.
S-1.3 Eligibility: sites of 2 ha or less outside flood-sensitive catchments, and of 0.5 ha or less within them (Table 1.2; Clause 4.14.1).
S-1.4 Conditions: the post-development imperviousness used shall be that shown on the approved plans; the outlet, spillway, RWH accounting and safety provisions of Clause 4.14.2 apply; the compliance calculator may be the sole calculation (Table 1.1).
S-2 — Permissible site discharge (PSD)
S-2.1 Replaces: the release rate Q_post(T) ≤ 0.9 × Q_pre(T) computed for the site (Clause 2.11.2).
S-2.2 Alternative: the release rate for each AEP may be taken as the tabulated unit-area release rate for the site's zone and AEP, multiplied by the site area. The tabulated rates are derived from the 0.9 × Q_pre rule (Table 1.2).
S-2.3 Eligibility: any site outside a flood-sensitive catchment.
S-2.4 Conditions: storage is then sized to hold every duration of Clause 2.5.2 at the PSD; drawdown, minimum orifice and spillway rules of Chapter 4 apply unchanged.
S-3 — Fixed-width waterbody setback
S-3.1 Replaces: the waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7).
S-3.2 Alternative: where no 1% AEP extent is mapped, the setback shall be the fixed width for the class of waterbody in the table of Clause 7.4.6 (and Annex 7B), measured as in Clause 7.4.3.
S-3.3 Eligibility: waterbodies with no mapped 1% AEP extent.
S-3.4 Conditions: no setback under this alternative is less than the Zone 1 minimum of Clause 7.4.7 (Clause 1.10.3(c)); the no-fill zone of Chapter 7 applies; where a 1% AEP extent is later mapped and adopted, the mapped setback applies to new applications.
S-4 — Downstream screening checklist
S-4.1 Replaces: downstream analysis by hydraulic model under Chapter 5.
S-4.2 Alternative: the Applicant completes a screening checklist of downstream capacity and known flooding, covering at least the conditions of Clause 5.3.4: that the receiving public drain has documented capacity for its minor-system design flow (Chapter 6), and that no flood-prone location is recorded within 500 m downstream. A hydraulic model under Chapter 5 is required only where the screen fails.
S-4.3 Eligibility: sites of less than 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall.
S-4.4 Conditions: the checklist is signed by the registered professional who signs the drainage report (Clause 10.6); flood-prone locations are those recorded by the local body, the Collector and the District Disaster Management Authority, CGSDMA, the district flood control rooms, or WRD (Clause 5.3.3(d)).
S-5 — Fee-in-lieu toward regional storage
S-5.1 Replaces: on-site detention under Chapter 4.
S-5.2 Alternative: all or part of the detention requirement may be met by a fee-in-lieu toward a regional detention facility or restored talab or tank storage identified in the basin plan (Clause 4.13.1).
S-5.3 Eligibility: sites in a basin for which a basin plan has been notified (Table 1.2).
S-5.4 Conditions:
- (a) the conditions of Clause 4.13.2 apply, including interim on-site detention until the regional facility or restored tank is operational, and retention and WQv treatment on site;
- (b) the fee is computed under Clause 4.13.3 and held in the ring-fenced basin account;
- (c) the volume credited and the fee are entered in the public ledger of Clause 4.13.4; and
- (d) in a flood-sensitive catchment, fee-in-lieu is available only as allowed by Clause 1.10.3(d).
Part 3 — Model council resolution
Model text for consideration by a competent authority. Not in force.
Resolution No. ______ of ______ (name of Municipal Corporation (Nagar Palik Nigam) / Nagar Palika Parishad / Nagar Panchayat), dated ______
Subject: Adoption of alternatives under the Policy Supplement to the Chhattisgarh Stormwater Design Manual.
The Council, having considered the report of the Municipal Commissioner / Chief Municipal Officer dated ______, and noting that:
- (i) the Chhattisgarh Stormwater Design Manual and its Policy Supplement have been given effect by ______ (instrument and date);
- (ii) this local body is a Tier B / Tier A authority under Clause 1.6 of the Manual; and
- (iii) for a Tier A authority, the State Stormwater Technical Committee concurred on ______ (reference ______),
resolves:
- to adopt the following alternatives of the Policy Supplement within its area, under the conditions of Clause 1.7.3 of the Manual:
Table 1C.1 — Alternatives adopted by this resolution
| Alternative | Adopted (Yes / No) | Area to which it applies (whole area, or wards / zones) | Applies from (date) |
|---|---|---|---|
| S-1 Design-aid route | |||
| S-2 Permissible site discharge | |||
| S-3 Fixed-width setback | |||
| S-4 Downstream screening checklist | |||
| S-5 Fee-in-lieu |
- that no adopted alternative shall apply within a flood-sensitive catchment except as the Manual allows (Clause 1.6.5);
- that a copy of this resolution be sent to the State Stormwater Technical Committee within 30 days;
- that the adopted alternatives be published on the local body's website and entered in the register of Clause 10.17; and
- that this resolution be reviewed when the tables of Clause 1.7.3(e) are revised.
Mayor / President: ______ Municipal Commissioner / Chief Municipal Officer: ______ Date: ______
Annex 1D — Model CGBVN 1984 amendment and model ULB bye-law
Supports Clauses 1.3.1, 1.3.4, 1.11 and 1.12 of Chapter 1.
Model text for consideration by a competent authority. Not in force. The text shows one way the instruments of Clause 1.3.1 could be drafted. Rule and section numbers are left blank.
Drafting note D1D.1. The rule numbers of the Chhattisgarh Bhumi Vikas Niyam 1984 at which the new rule and the conditions would be inserted, and the enabling sections of the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973 and the municipal and panchayat Acts, are to be confirmed by the Government's legal advisers. None is stated here.
Part A — Model amendment to the Chhattisgarh Bhumi Vikas Niyam 1984
A.1 Short title and commencement.
- (1) These rules may be called the Chhattisgarh Bhumi Vikas (Stormwater Management) Amendment Rules, ______.
- (2) They shall come into force on the date six months after their publication in the Chhattisgarh Gazette (Rajpatra) (Clause 1.11.1).
A.2 Insertion of a new rule. After rule [______] of the land development rules made by the State Government under section 85(1) read with section 24(3) of the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973, the following rule shall be inserted:
Rule [______]. Stormwater management.
(1) Definitions. In this rule, "the Manual" means the Chhattisgarh Stormwater Design Manual as notified by the Government, with its annexes and amendments; other words have the meanings given in Clause 1.4 of the Manual.
(2) Application. This rule applies to every development for which planning permission, building permit or layout approval is required under these rules.
(3) Runoff control. Where a development, over its common plan of development, involves land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, the development shall comply with Chapters 4 and 5 of the Manual (retention, detention, downstream and tailwater analysis).
(4) Provisions for every development. Every development, whatever its size, shall comply with Clause 1.5.4 of the Manual: no sewage connection to a storm drain; floor levels; waterbody setbacks and the no-fill zone; and no obstruction of a drainage path.
(5) Exemptions. A single dwelling on its own plot below the thresholds of sub-rule (3), and linear road resurfacing that adds no impervious area, are exempt from sub-rule (3) but not from sub-rule (4) or the rainwater harvesting provisions of these rules.
(6) Conditions of approval. The competent authority shall not grant:
- (a) planning permission or layout approval, unless a preliminary drainage report under the Manual has been accepted;
- (b) a building permit, or permission to commence, unless the final drainage design has been accepted; or
- (c) a completion certificate, unless the as-built certificate has been accepted and the maintenance declaration has been registered, or the public assets have been handed over,
for a development to which sub-rule (3) applies (Manual, Clause 10.3).
(7) Certification. Drainage reports and designs shall be signed by a registered professional, and, where Clause 10.6.1 of the Manual so requires, by an empanelled Stormwater Design Professional.
(8) Rainwater harvesting. Nothing in this rule alters the rainwater harvesting provisions of these rules.
(9) Variances and waivers. The competent authority may grant a variance or waiver only on the grounds and by the procedure of Clause 1.10 of the Manual, and shall publish each decision.
(10) Transition. Applications filed complete before the commencement of this rule, and Tier B authorities, are governed by Clause 1.11 of the Manual.
Part B — Model ULB bye-law
B.1 Title and commencement. These bye-laws may be called the ______ (name of local body) Stormwater Management Bye-laws, ______. They come into force on ______.
B.2 Adoption of the Manual. The Chhattisgarh Stormwater Design Manual, as notified by the Government, applies to:
- (a) every development approved by the local body; and
- (b) every drainage, road, culvert, waterbody and flood-mitigation work executed by the local body, including its own drains and roads (Clause 1.3.1(b)).
B.3 Public works. Every detailed project report and contract for a work under B.2(b) shall require compliance with the Manual, from the dates in Clause 1.11 (Clause 1.3.4).
B.4 Tier and alternatives. The local body is a Tier ______ authority under Clause 1.6 of the Manual. The alternatives of the Policy Supplement adopted by the local body are listed in the Schedule, with the resolution under which each was adopted.
B.5 Submittals and review. Submittals shall be made in the stages of Clause 10.3 of the Manual and reviewed within the periods of Clause 10.7.
B.6 Maintenance, inspection and enforcement. Maintenance declarations, inspections, handover of public assets and enforcement shall follow Clauses 10.10 to 10.15 of the Manual.
B.7 Publication. The local body shall publish the registers and reports of Clause 10.17 of the Manual.
B.8 Review. These bye-laws shall be reviewed whenever the Manual is amended under Clause 1.12.
Table 1D.1 — Schedule: alternatives adopted (layout)
| Alternative | Resolution number and date | Committee concurrence (Tier A only) | Applies from | Area |
|---|---|---|---|---|
Form 1-1 — Applicability Determination
Supports Clauses 1.5.1 to 1.5.9 and 1.6 of Chapter 1, and Clause 10.3 of Chapter 10.
Draft form — Chhattisgarh Stormwater Design Manual, Draft v1.0. Lodged at the pre-application meeting (Stage 0) or with the preliminary drainage report (Stage 1), as Clause 10.3.2 requires.
Table 1F.1 — Form 1-1: Applicability Determination
| No. | Item (clause) | Entry |
|---|---|---|
| A. Applicant and site | ||
| A1 | Applicant (owner, developer or department) | ______ |
| A2 | Site address and survey numbers | ______ |
| A3 | Site coordinates (latitude, longitude) | ______ |
| A4 | Approving Authority (Clause 1.4) | ______ |
| A5 | Tier of the Authority: A / B (Clause 1.6; Annex 1A) | ______ |
| A6 | Approval sought: planning permission / building permit / layout approval / public work (DPR) | ______ |
| A7 | Type of development: building / layout / sub-division / road / paving / land-use change / other (Clause 1.4) | ______ |
| A8 | Stage at which this form is lodged: Stage 0 / Stage 1 (Clause 10.3) | ______ |
| B. Coverage (Clause 1.5.1) | ||
| B1 | Development requiring approval under the Chhattisgarh Bhumi Vikas Niyam 1984 — 1.5.1(a): Yes / No | ______ |
| B2 | Public work by a ULB, State department, board or State undertaking — 1.5.1(b): Yes / No | ______ |
| B3 | Work by a Central agency needing the Authority's approval or no-objection — 1.5.1(c): Yes / No | ______ |
| C. Areas over the common plan of development (Clauses 1.4, 1.5.5) | ||
| C1 | Phases, plots and sub-divisions included (one layout approval or one ownership) | ______ |
| C2 | Total site area (ha) | ______ |
| C3 | Land disturbance (ha) | ______ |
| C4 | Existing impervious area (m²) | ______ |
| C5 | New impervious area (m²) | ______ |
| C6 | Replaced impervious area, removed to subgrade and rebuilt (m²) | ______ |
| C7 | New plus replaced impervious area, C5 + C6 (m²) | ______ |
| C8 | Plot area for the RWH mandate (m²) (Clause 1.5.3) | ______ |
| D. Thresholds and exemptions | ||
| D1 | Land disturbance 0.1 ha or more — 1.5.2(a): Yes / No | ______ |
| D2 | New or replaced impervious area 500 m² or more — 1.5.2(b): Yes / No | ______ |
| D3 | Redevelopment (existing impervious cover on the site) — 1.5.6: Yes / No | ______ |
| D4 | Constrained redevelopment route of Clause 4.5.6 proposed: Yes / No | ______ |
| D5 | Linear public work: added impervious area per drainage catchment crossed given in Table 1F.2 — 1.5.7: Yes / No / not applicable | ______ |
| D6 | Exemption claimed — 1.5.8(a) single dwelling below the thresholds / 1.5.8(b) resurfacing with no added impervious area / none | ______ |
| D7 | RWH mandate applies (CGBVN 1984, Rule 78(4): building on a plot above the threshold, reported as 500 m² [TBC]; government building with a roof of more than 1,500 sq ft (new) or 5,000 sq ft (existing) (General Administration Department order of 31 May 2016)) — 1.5.3: Yes / No | ______ |
| E. Site conditions | ||
| E1 | Site in a flood-sensitive catchment (Annex 1B; Clause 4.5.3): No / Yes — name | ______ |
| E2 | Source of the catchment boundary used | ______ |
| E3 | 1% AEP level mapped or determinable for the site (Clause 1.5.4(b)): Yes / No; source | ______ |
| E4 | Waterbody on or adjoining the site (Clause 1.5.4(c); Chapter 7): No / Yes — name | ______ |
| E5 | Natural drainage path or major-system flow path crossing the site (Clause 1.5.4(d)): No / Yes | ______ |
| E6 | Site drains to a tidal outfall (Clause 10.3.2(d)): Yes / No | ______ |
| E7 | Variance, waiver, regional facility or fee-in-lieu proposed (Clause 10.3.2(c)): No / Yes — Form 1-2 attached | ______ |
| F. Determination | ||
| F1 | Result: (i) Chapters 4 and 5 apply, with Clause 1.5.4 and the RWH mandate; (ii) Clause 1.5.4 and the RWH mandate only (below thresholds); (iii) exempt under 1.5.8, Clause 1.5.4 and the RWH mandate still apply | ______ |
| F2 | Stage 0 mandatory under Clause 10.3.2: Yes (state item (a) to (d)) / No | ______ |
| F3 | Storage method: hydrograph method (Chapter 3) / design-aid route S-1 (Clause 1.7, where adopted and eligible) | ______ |
| F4 | Other Policy Supplement alternatives relied on (S-2 to S-5), with the adopting resolution | ______ |
| F5 | Tier B phased start applies (Clause 1.11.3): Yes / No | ______ |
| G. Declaration | ||
| G1 | I declare that the information above is correct and covers the whole common plan of development. Applicant: name, signature, date | ______ |
| G2 | Prepared by (registered professional, Clause 1.4): name, registration number, signature, date | ______ |
| H. For the Authority (Clause 1.5.9) | ||
| H1 | Determination confirmed / corrected | ______ |
| H2 | Corrections and reasons | ______ |
| H3 | Officer: name, designation, signature, date | ______ |
Table 1F.2 — Form 1-1: added impervious area by drainage catchment, linear works (Clause 1.5.7)
| Drainage catchment crossed | Chainage from – to | Added impervious area (m²) | 500 m² or more (Yes / No) | Storage location: right of way / regional facility |
|---|---|---|---|---|
Form 1-2 — Variance / Waiver Request
Supports Clause 1.10 of Chapter 1.
Draft form — Chhattisgarh Stormwater Design Manual, Draft v1.0. Lodged with the preliminary drainage report (Clause 1.10.4(a)), with one form for each requirement concerned.
Table 1F.3 — Form 1-2: Variance / Waiver Request
| No. | Item (clause) | Entry |
|---|---|---|
| A. Applicant and site | ||
| A1 | Applicant | ______ |
| A2 | Site address and coordinates | ______ |
| A3 | Form 1-1 reference and date | ______ |
| A4 | Tier of the Authority: A / B | ______ |
| A5 | Site area (ha) | ______ |
| A6 | Site in a flood-sensitive catchment: Yes / No | ______ |
| B. Request | ||
| B1 | Type: variance from a numeric requirement (1.10.1) / waiver of Chapter 4 detention (1.10.2) | ______ |
| B2 | Clause of the Manual concerned | ______ |
| B3 | Value required by the Manual | ______ |
| B4 | Value or arrangement proposed | ______ |
| C. Matters that cannot be varied or waived (Clause 1.10.3) — confirm that the request does not concern any of them | ||
| C1 | (a) a sewage connection to a storm drain | Not concerned: ______ |
| C2 | (b) the lowest habitable floor level of Chapter 6 | Not concerned: ______ |
| C3 | (c) a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or fill or construction in the no-fill zone of Chapter 7 | Not concerned: ______ |
| C4 | (d) retention in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7 | Not concerned: ______ |
| D. Variance: grounds (Clause 1.10.1(a)) | ||
| D1 | Site condition: high groundwater table / contaminated soil / rock / site too small for the required facility / other | ______ |
| D2 | Evidence (tests, surveys, plans), with references | ______ |
| D3 | Options assessed and why each is impracticable | ______ |
| E. Variance: equal performance or make-up (Clause 1.10.1(b)) | ||
| E1 | Downstream point used (Chapter 5) | ______ |
| E2 | Performance at that point with full compliance and with the variance (peak flows, water levels) | ______ |
| E3 | Or: shortfall made up by fee-in-lieu or off-site works in the same catchment — volume (m³), works or fee | ______ |
| F. Waiver of detention: grounds (Clause 1.10.2) | ||
| F1 | Site discharges directly to the sea / to a tidal reach with no flood-prone property downstream | ______ |
| F2 | Analysis showing that undetained flow does not worsen the outfall-closed condition of Chapter 5 — reference | ______ |
| F3 | Retention still provided in full: Yes | ______ |
| G. Attachments (Clause 1.10.4(a)) | ||
| G1 | Report certified under Clause 10.6 | ______ |
| G2 | Preliminary drainage report | ______ |
| H. Certification and declaration | ||
| H1 | Certified by (registered professional; empanelled professional where Clause 10.6.1 applies): name, registration or empanelment number, signature, date | ______ |
| H2 | Applicant: name, signature, date | ______ |
| I. For the Authority (Clause 1.10.4) | ||
| I1 | Referred to the State Stormwater Technical Committee (Tier B, site 1 ha or more): Yes / No; date | ______ |
| I2 | Decision: granted / granted with conditions / refused | ______ |
| I3 | Reasons and conditions | ______ |
| I4 | Entry number in the public register (Clause 10.17) | ______ |
| I5 | Note: a variance runs with the approval and lapses if the approval lapses (Clause 1.10.4(d)) | — |
| I6 | Officer: name, designation, signature, date | ______ |