Draft v1.0 prepared by NEER. Not adopted by the Government of Chhattisgarh or any authority or local body, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, talab and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Chhattisgarh's cities have drainage proposals but, with one exception, no published drainage plan with a design standard. The exception is Nava Raipur: the Naya Raipur Development Plan-2031 (NRDA, 2008) divides the new capital into four catchments along its four main streams, which it keeps, asks that the existing channels be rehabilitated and that "5 years Maximum rainfall intensity should be taken for design of system" (§10.3.1.1), that any river embankment be safe against a 100-year flood, that roads stand at least 0.5–1.0 m above the observed high flood level and follow IRC SP-50, and that rainwater from the storm drains be stored in dug or natural lakes and depressions; it gives a chart of intensity against time of concentration for 2, 5, 10 and 50 years from IMD data for the Raipur region, read only by eye, and the new city's 55 reservoirs, Sendh, Jhanjh and Khandawa among them, are reported as its storage (as reported). This is the only explicit urban design storm in the State, and it is a plan for one city, not a State standard. Raipur's storm drainage plan under AMRUT (RMC, 2015) records drains covering 49% of the city, about 480 km of pucca drains, 11 road stretches flooding two or three times a year and drains "not sufficient" in capacity, and proposes ₹1,191 crore of works, but states no return period or intensity; AMRUT in the State then funded no drainage, and a ₹222.22 crore urban flood risk project for Raipur under the NDMA's programme, approved on 1 October 2025, has been reported without its criteria (as reported). Raipur's development plan, the Raipur Development Plan (Revised) 2021, was approved on 5 April 2008, and the revised plan to 2031, presented in 2022 with an emphasis on water bodies, has not been found approved. In Bilaspur the Arpa Special Area Development Authority's development plan to 2033, approved on 10 February 2014, was largely sidelined after the High Court's orders of January 2019, when the State dropped the Authority's permission for land sale, building and development. Bhilai's township is planned and drained by Bhilai Steel Plant (SAIL) through its Town Services, beside the drains of the Bhilai and Risali Municipal Corporations, with no published division of the drains between them. No published document sets a design return period for the storm drain network of any other Chhattisgarh city. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by UADD, the Housing and Environment Department, T&CP, NRDA, RDA, any Municipal Corporation, Bhilai Steel Plant, WRD or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, city nalas that reach the Kharun, the Seonath, the Arpa and the Hasdeo while barrage and dam releases hold them high, nalas that carry sewage to their outfalls and into the talabs, talabs filled or encroached, as in Raipur, where about 40 remain of the 130 or more once reported, catchments changed by mine voids, overburden dumps and ash ponds in the coalfields, and single drains split between a Municipal Corporation, NRDA, Bhilai Steel Plant, WRD and the coal and power companies, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Chhattisgarh: to a State of plains, plateau and hills whose city nalas run to rivers held by dams and barrages, as in Raipur, where the nalas and talabs drain to the Kharun, at Durg and Bhilai on the Seonath below the Mongra barrage, at Bilaspur on the Arpa at the Bhaisajhar barrage, at Korba on the Hasdeo below Minimata Bango and the Darri barrage, and at Raigarh on the Kelo, with the Hirakud backwater reaching the low outfalls of Raigarh and Sarangarh districts and the Indravati at Jagdalpur setting a new high flood level in 2026; to a planned capital, Nava Raipur, drained to a network of lakes and reservoirs on the only explicit urban design storm in the State; to talabs filled or encroached, of which Raipur keeps about 40 of the 130 or more once reported, and to a Wetland Authority that now enforces a 50 m line around them; to the coalfields and power stations of Korba, Raigarh and Surguja, where mine voids, overburden dumps and ash dykes change the catchments and their hazards; to nalas that carry sewage, intercepted by weirs at Raipur's new treatment plants and under orders of the Tribunal at Durg; to drains vested in the Municipal Corporations, the drains and lakes of NRDA, the Bhilai Steel Plant township and the rivers, dams and barrages of WRD, without an order that divides the natural nalas from the municipal drains; to a State with no floodplain zoning law and no notified flood zone; to a State with no published design return period for the drains of any city other than Nava Raipur; to hard-rock and karst aquifers critical under Raipur's Dharsiwa block and the Seonath plain, with a water table near the surface after the monsoon; and to a south-west monsoon and Bay of Bengal depressions whose recorded days exceed the 100-year depths of the CWC plates, 370.3 mm at Raipur on 4 August 1910 and 392.0 mm at Rajnandgaon on 21 September 1965 (IMD).


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 No basin delineation has been published for any Chhattisgarh city. For the urban areas where the evidence identifies them, the basins are at least the following:

  • Raipur, Kharun: the catchments of Raipur and Birgaon that drain to the Kharun through the city's nalas, with the city's talabs (Budha Talab, Telibandha, Karbala, Narhaiya, Maharajbandh and the others) as storage, the diversion weirs of the Chandanidih, Kara and Nimora treatment plants and the anicut at Mahadev Ghat in the 1D network, their sewage interceptions mapped (Clause 8.9.5), and the level of the Kharun at Pathardihi as the boundary condition;
  • Nava Raipur: the four catchments of the four main streams of the Naya Raipur Development Plan-2031, with the city's lakes and reservoirs, Sendh, Jhanjh and Khandawa among them, as storage and outfall, the 50 m line of the State Wetland Authority shown, and the river that receives each stream as the boundary condition;
  • Durg and Bhilai: the catchments of Durg, Bhilai, Risali and Bhilai-Charoda that drain to the Seonath, with the Shankar and Pulgaon nalas and the drains of the Bhilai Steel Plant township in the 1D network, their sewage interceptions mapped, and the Seonath level below the Mongra barrage as the boundary condition;
  • Bilaspur, Arpa: the catchments of Bilaspur that drain to the Arpa, with the pond level and releases of the Arpa Bhaisajhar barrage as boundary conditions and Kopra Jalashay, west of the city, shown with its catchment;
  • Korba, Hasdeo: the catchments of Korba that drain to the Hasdeo below the Darri barrage, with the releases of Minimata Bango and Darri as inflows and the levels at Bangodam and Katghora as boundary conditions, the outfall-closed case a design case, mine voids shown as storage only where the lessee and DGMS consent and their levels and spills are surveyed, overburden dumps as sediment sources, and the breach flow paths of the ash dykes of Dhanras, the Hasdeo Thermal Power Station and BALCO shown as hazards;
  • Raigarh, Kelo: the catchments of Raigarh that drain to the Kelo below the Kelo dam, with the levels of the Mahanadi and the Mand and of the Hirakud backwater as boundary conditions for the low outfalls of Raigarh and Sarangarh districts; and
  • Jagdalpur, Indravati: the catchments of Jagdalpur that drain to the Indravati, with the level at CWC's Jagdalpur site (warning 539.49 m, danger 540.80 m, high flood level 544.891 m) as the boundary condition and the outfall-closed case a design case.

Other Tier A bodies, among them Rajnandgaon, Dhamtari, Ambikapur and Chirmiri, shall define their basins in the first BSMP that covers them. Where WRD, CWC, DGMS, the State Wetland Authority or a court has a high flood level, a full reservoir level, a line around a talab or wetland, or an operating rule for a dam, barrage, sluice or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, river levels, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, river, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Chhattisgarh a single nala can pass through several hands on its way to a river. The Municipal Corporation Act 1956 and the Municipalities Act 1961, as adapted from the Madhya Pradesh Acts, vest the public drains and tanks of a city in its local body (their Chhattisgarh texts were not read); NRDA plans and builds the drains and lakes of Nava Raipur; Bhilai Steel Plant drains its township, whose drains Bhilai Municipal Corporation has had to warn it to clean (2025, as reported); tanks recorded for irrigation or nistar vest in the State, under the Collector (Land Revenue Code 1959, s.251); WRD holds the rivers, dams, barrages and reservoirs; and the coal companies and power stations hold the drains, voids, dumps and ash ponds on their land. No rule divides the natural nalas from the municipal drains (as this Manual reads the record). The nalas carry sewage across these boundaries: in January 2021 Bilaspur was the only city with a sewerage system, and the new plants in Raipur take the flow of the nalas through diversion weirs (CECB); Durg's sewage reaches the Seonath through the Shankar and Pulgaon nalas (National Green Tribunal, 2026, as reported); and about 40% of Bilaspur's sewage was expected to remain untreated even after its new plants (High Court, 2025, as reported). This clause makes the basin the planning unit, so that one model carries each nala from its head to the river whoever owns each reach, and so that the interception works are tested against the capacity of the nalas they tap (Chapter 8, Clause 8.9.5).


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For the basins of a city with a Municipal Corporation: the Municipal Corporation (in Raipur, RMC; elsewhere the Corporations of Bilaspur, Durg, Bhilai, Bhilai-Charoda, Risali, Birgaon, Rajnandgaon, Korba, Raigarh, Jagdalpur, Ambikapur, Dhamtari and Chirmiri), in which the public drains and tanks vest under the Municipal Corporation Act 1956 as adapted in Chhattisgarh, jointly with T&CP, which prepares the development plan into which the BSMP is carried (Clause 11.9); either may prepare the plan as UADD directs. In Nava Raipur the Lead Authority is NRDA, the Special Area Development Authority under the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973, for the whole of its area and its lakes and reservoirs. Where a basin extends beyond the Corporation, the other local bodies, RDA and NRDA in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1); a basin that drains from Raipur into Nava Raipur, or the reverse, has one BSMP.
  • No order dividing the natural nalas from the municipal drains, or the drains of the local bodies from the rivers, dams and barrages of WRD, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: WRD for the rivers, dams, barrages and reservoirs and their gates and releases, among them Gangrel, Minimata Bango, the Hasdeo barrage at Darri, the Mongra and Arpa Bhaisajhar barrages, Kharang and the Kelo dam; the coal company or other lessee, with DGMS, for the mine voids, pit lakes, overburden dumps, garland drains and sediment basins within its lease, and the power company (NTPC, CSPGCL, BALCO or another) for its ash ponds, ash dykes and their breach flow paths; the Chhattisgarh State Wetland Authority for notified wetlands, for the 50 m lines of the talabs and wetlands it treats as protected and, with WRD as its managing authority, for Kopra Jalashay, the State's Ramsar site; the Municipal Corporation, Nagar Palika Parishad or Nagar Panchayat for the drains, nalas and public tanks vested in it; NRDA in Nava Raipur; Bhilai Steel Plant for the drains of its township, until the responsibility for them is settled with the Municipal Corporations; RDA and the Chhattisgarh Housing Board for the drains of their schemes until they are handed over; the Collector for the tanks vested in the State under s.251 of the Land Revenue Code 1959 in the parts of a basin outside municipal limits; and PWD and NHAI for the drains of their roads.
  • In Tier B bodies: the Lead Authority is named by UADD. Basins draining to a common river reach, reservoir or talab may be grouped into one district-level plan.

The Chhattisgarh State Wetland Authority shall be consulted on every BSMP whose basin drains to a talab or wetland it treats as protected or to Kopra Jalashay; CGSDMA and the district administration on every BSMP; the Chhattisgarh Environment Conservation Board on every BSMP that proposes works on a nala that carries sewage to a river or talab, or that receives runoff from a mine, a dump or an ash pond; and, for a basin whose outfall lies on a river shared with Odisha, such as the Mahanadi below the State's barrages or within the Hirakud backwater, or the Indravati, the water resources department of that State, through WRD.

WRD shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, talab, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls, rivers, reservoirs, barrages and mine voids The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the receiving river at the nearest CWC gauge and its recorded peaks (on the Indravati at Jagdalpur a warning level of 539.49 m, a danger level of 540.80 m and a high flood level of 544.891 m, 26 September 2026; on the Kharun at Pathardihi a high flood level of 281.68 m, 29 August 2020, with no warning or danger level found; CWC levels, as reported), with any local gauge kept as a separate series; for outfalls to reservoirs, barrage ponds and talabs, the full reservoir level, maximum water level and spillway and sluice data from WRD or the custodian (for example the full reservoir levels of 302.000 m for the Arpa Bhaisajhar barrage, 337.150 m for the Mongra barrage and 233.000 m for the Kelo dam in WRD's tank gauge report of 10 October 2024), naming which is used; the release records of Gangrel, Minimata Bango, the Hasdeo barrage at Darri, Kharang and the barrages on the Seonath, the Arpa and the Mahanadi; the extent of the Hirakud backwater inside the State; for any mine void proposed as storage, the lessee's survey of its level, spill and highwall stability, with the consent of DGMS; the breach flow paths of ash dykes mapped by their owners; WRD's high flood points given for land next to a nala, canal or river, the lines of rule 50 of the Chhattisgarh Bhumi Vikas Niyam 1984 once confirmed, and the 50 m line of the State Wetland Authority where they bind; and the sluices, flap gates, interception weirs, anicuts, check dams, lake outlets and pumping stations on the outfalls, with their capacities and operating rules
Rainfall and levels All available rain gauges (IMD, including its observatories at Raipur (since 1901) and Raipur (Mana) airport, its stations at Jagdalpur, Pendra Road, Ambikapur, Raigarh, Durg, Champa, Jashpurnagar, Kanker and Rajnandgaon, and the automatic weather stations and rain gauges reported by the Meteorological Centre Raipur; the district and tehsil rain gauges of the State, whose records IMD tabulates in the Climate of Chhattisgarh; the rain and river gauges of CWC and of WRD, including those at its dams and barrages; the agrometeorological observatory of Indira Gandhi Krishi Vishwavidyalaya at Raipur; and any gauges kept by the Municipal Corporations, NRDA and the Smart City companies) and water-level records, including those for the 4 August 1910 (Raipur's record day of 370.3 mm, rainfall only), August 2020 (the Kharun at Raipur and the upper Mahanadi), August 2025 (the Bastar division) and September 2026 (statewide, with the Indravati at Jagdalpur and the Kharun at Raipur) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the Chhattisgarh plain, where slopes are gentle (0–5% across Nava Raipur, NRDA) and the kanhar and dorsa lowlands, the talabs and the floodplains of the Kharun, the Seonath and the Arpa decide where water stands, and around the margins of Raipur's talabs and Nava Raipur's lakes and reservoirs, where the line 50 m from the highest flood level that the State Wetland Authority enforces decides what may be built, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 4 August 1910 (Raipur's record day of 370.3 mm, rainfall only), August 2020 (the Kharun at Raipur and the upper Mahanadi), August 2025 (the Bastar division) and September 2026 (statewide, with the Indravati at Jagdalpur and the Kharun at Raipur) events are the best calibration data Chhattisgarh has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and talab storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but not measured. In law the tanks of Chhattisgarh are largely public: village tanks on land with rights of irrigation or nistar vested in the State on 6 April 1959 (Land Revenue Code 1959, s.251), the Collector may set land apart for tanks for nistar (s.237), and encroachment on a pond recorded in the land records is removed as unauthorised occupation (s.248), as at Baloda in 2024–25 under the National Green Tribunal's order (O.A. 78/2024); within a city the public tanks vest in the local body under the Municipal Corporation and Municipalities Acts as adapted (their Chhattisgarh texts were not read); and the State Wetland Authority bars works within 50 m of the highest flood level of the talabs and wetlands it treats as protected (as reported). Kopra Jalashay near Bilaspur, a 210 ha reservoir built in 1993 and managed by WRD, is the State's first Ramsar site (designation date 8 August 2025 in the Ramsar information sheet; announced in December 2025, as reported). The losses are visible all the same: Raipur, a city of talabs, is reported to have had about 130 ponds or more, of which about 40 remain over about 69 ha, all polluted and silted (as reported; the counts conflict); a directive of 8 May 2023 to survey every water body in Raipur district was reported to have been carried out only at Karbala Talab (as reported); and the State Wetland Authority found works at Karbala Talab within 50 m of its highest flood level and stopped them (2025, as reported). Beyond the cities lie the talabs, bandhs and dabris of the villages, and the farm ponds dug under the State's schemes. No survey of the storage of any talab or reservoir inside a Municipal Corporation was found, and no level or capacity has been published for any of Raipur's talabs or Nava Raipur's lakes.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Chhattisgarh with a design factor was found; the State Action Plan on Climate Change (2014) is summarised as finding falling monsoon totals, while the maximum 1- and 5-day rainfalls at stations of the Mahanadi plain are reported to have risen over 1971–2021 (as reported); and station records, 370.3 mm at Raipur on 4 August 1910, 392.0 mm at Rajnandgaon on 21 September 1965, 358.0 mm at Korba on 12 August 2004 and 337.0 mm at Durg on 15 June 2004 (IMD), exceed the 100-year 24-hour depths of the CWC plates there (this Manual's reading), which is a reason to keep the factors, not to reduce them.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 4 August 1910 (Raipur's record day of 370.3 mm, rainfall only), August 2020 (the Kharun at Raipur and the upper Mahanadi), August 2025 (the Bastar division) and September 2026 (statewide, with the Indravati at Jagdalpur and the Kharun at Raipur) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two tanks in cascade with surplus course; a 1D drain network linked to a 2D surface grid; a river or canal reach with an inter-basin link; an outfall with a flap gate and pumps; and a river or lake level boundary. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) River / receiving water 1 S1 S2 S3 2 Upper tank Lower tank start level start level 3 2D surface 5 4 River / canal (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Tanks and ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers and canals (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Sluices, flap gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary River (CWC or WRD gauge) or lake level (MWL or FTL + surcharge), per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and talabs with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: talabs, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: sluices and flap gates on the outfalls to the Kharun, the Seonath, the Arpa, the Hasdeo, the Kelo and the Indravati, pumping stations and the storage behind them where an outfall can be closed by a river in flood, a barrage pond or the Hirakud backwater, interception weirs that take the dry-weather flow of the nalas of Raipur and Durg to the sewage treatment plants without taking their storm capacity, sediment basins and toe drains below overburden dumps and mine sites, and the operating rules of the gates of Gangrel, Minimata Bango, the Hasdeo barrage at Darri, Kharang and the Mongra and Arpa Bhaisajhar barrages that set the receiving levels, agreed with WRD;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Raipur, CWC flood forecasts and river stages at its sites, among them the Indravati at Jagdalpur against its warning and danger levels, notice of releases from Gangrel, Minimata Bango, the Hasdeo barrage at Darri, the Mongra and Arpa Bhaisajhar barrages and Kharang to the towns and villages downstream, and the district flood control rooms), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge in the critical and semi-critical blocks of the Seonath plain, Dharsiwa (Raipur), Durg and Dhamdha among them, where the Chandi and Charmuria limestone that supplies Raipur is karstified and cavernous, the shallow post-monsoon water table, within 5 m in about three wells in four, kanhar clays that take no recharge once wet, mine dewatering in the Korba coalfield, and the quality of the groundwater, with fluoride and nitrate in parts of the State and arsenic at Ambagarh Chowki, and of the rivers, reservoirs and talabs that the runoff reaches (Chapter 8);
  • effect on downstream basins and the receiving river, reservoir or talab; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because many of Chhattisgarh's city outfalls are closed or limited in the wettest weeks, and because conveyance on its own has not kept up. The Kharun at Pathardihi stood above its 1994 mark for about 46 hours in August 2020 and overtopped the road at Mahadev Ghat in 2024 and 2026, Gangrel opened all 14 of its gates in September 2026, Minimata Bango and the Darri barrage released together onto Korba in August 2024 (as reported), and the Hirakud backwater reaches into the State in the east. Raipur once held its runoff in its talabs, and of the 130 or more reported in the city about 40 remain, over about 69 ha (as reported; the counts conflict), while Nava Raipur was planned on the opposite principle, with its storm drains and parks leading to its lakes and reservoirs (NRDA, 2008). Conveyance alone has not served: Raipur's plan of 2015 found its drains insufficient in capacity and choked, and proposed to reach full coverage by 2020 (RMC, 2015), but its low colonies and underpasses flooded again in July 2026 (as reported). The storms are large for drains with no stated design basis: IMD has recorded 370.3 mm in a day at Raipur (4 August 1910), 392.0 mm at Rajnandgaon (21 September 1965) and 358.0 mm at Korba (12 August 2004), above the 100-year 24-hour depths of the CWC plates there (IMD; this Manual's reading). Conveyance upgrades on their own move water faster to an outfall that the Kharun, the Seonath, the Arpa, the Hasdeo or the Indravati in flood, a barrage pond or reservoir held at its full level, or the Hirakud backwater may close, or that is limited by the capacity of its sluice, interception weir or pumping station. Groundwater in Chhattisgarh calls for recharge on the Seonath plain and for care everywhere. The State's stage of extraction was 47.32% in 2024, with 120 of its 146 blocks safe, 21 semi-critical and 5 critical, among them Dharsiwa in Raipur district at 93.51% and Gurur, Nawagarh, Bemetara and Berla nearby; Durg, Dhamdha and Rajnandgaon were semi-critical (CGWB, 2024); a press report that no block was critical in 2026 has not been verified. About 87% of the State is hard rock, and the Chandi limestone that supplies Raipur, with the Charmuria limestone of the same belt, is described as "Karstified and Cavernous" (CGWB), so recharge there reaches the aquifer fast, with whatever the runoff carries, and needs a cavity check. But the post-monsoon water table stands within 5 m of the ground in about 76% of wells (CGWB, 2023), so recharge on the kanhar and dorsa lowlands adds to waterlogging. Quality limits recharge too: fluoride exceeds 1.5 mg/l in samples from eight districts and nitrate exceeds 45 mg/l in about 11% of samples, arsenic is found at Kaudikasa in Ambagarh Chowki block and in samples from Korba, Koriya and Raigarh (CGWB), and in the Korba coalfield mine dewatering draws the water table down around the pits (as reported). The Ground Water (Management and Regulation) Act 2022 would let the State enforce recharge in notified critical blocks and stressed urban areas, but no notification bringing it into force has been found. The rainwater harvesting rule of the Bhumi Vikas Niyam asks for recharge pits or storage above a plot threshold reported as 500 m² (rule 78(4) and Appendix ढ, as amended in 2009; threshold [TBC]) without regard to the depth of the water table or the ground. This is why recharge, waterlogging, karst, mine-disturbed ground and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the development plans approved by the State under s.19 of the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973, among them the Raipur Development Plan (Revised) 2021 and the plan that replaces it and the development plan of Durg–Bhilai; the plans of the Special Area Development Authorities under the same Adhiniyam, among them the Naya Raipur Development Plan-2031 and the Arpa special-area development plan 2033 where it still applies; and the layouts given development permission under them and under the Chhattisgarh Bhumi Vikas Niyam 1984. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Chhattisgarh draws few water lines by rule, and the widest it has come from the Wetland Authority. Rule 50 of the Chhattisgarh Bhumi Vikas Niyam 1984 is still the rule on land unsuitable for development, but its Chhattisgarh text was not read: as made in 1984 it bars building within 9 m of the highest water mark, or, by a major watercourse, within 9 m of the average high flood mark or 15 m of its defined boundary, whichever is more, without defining either mark, and these lines are not confirmed for Chhattisgarh [TBC]. T&CP's checklist asks, for land next to a nala, canal or river, for the no-objection of WRD or the Revenue Department and for WRD's high flood point (2011); integrated townships may not be sited on the bank of a perennial river and may not count water sources in their area (Appendix ण, 2008 and 2018); and construction on the bed or edge of a reservoir or on a natural drain may not be regularised (regularisation Act 2002, s.7(1)). Since 2018 the site-inspection form records whether a major nala is near the plot and its distance, for compliance with the Niyam, but no form or rule asks how a flood edge is drawn. Tanks recorded for nistar vest in the State (Land Revenue Code 1959, s.251), and encroachment on them is removed as unauthorised occupation (s.248), as at Baloda under the National Green Tribunal's order of 2024. The State Wetland Authority treats wetlands larger than 2.25 ha as deemed wetlands and bars works within 50 m of their highest flood level, the line it applied at Karbala and Narhaiya talabs in Raipur and at the Jhanjh wetland in Nava Raipur in 2025 (as reported), though no list of notified wetlands has been found. In Nava Raipur the Development Plan asks for river embankments safe against a 100-year flood and roads 0.5–1.0 m above the observed high flood level (NRDA, 2008). There is no floodplain zoning law, no notified flood zone and no WRD demarcation of the floodplain of any river in the State. These are watercourse, tank and wetland lines, not drainage-flood lines; the hydraulic corridor and setback zones of Chapter 7 are this Manual's proposal, and where the lines of the Niyam or the 50 m wetland line bind and are wider, they apply. A BSMP gives the development plans the 1% AEP drainage-flood map, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Chhattisgarh Bhumi Vikas Niyam 1984 already require community open space in layouts (rule 47; the Chhattisgarh percentage was not seen), at least 10% of an integrated township as gardens and playgrounds (Appendix ण, as amended) and rainwater harvesting under rule 78(4), and the Naya Raipur Development Plan-2031 asks that rainwater from the storm drainage system be stored in dug or natural lakes and depressions and makes rainwater harvesting mandatory for every development (§10.3.2), but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Chhattisgarh building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report