Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Chhattisgarh the failure is one of missing criteria and of drains that have not kept up. No document of UADD, T&CP, a Municipal Corporation or a development authority stating a design return period, intensity or runoff coefficient for the storm drains of a city was found, except NRDA's 5-year criterion for Nava Raipur (Chapter 11). Raipur's own plan of 2015 found that the "Capacity of drain is not sufficient" and that "In rainy season most of the drains are overflowed", with drains covering 49% of the city against a benchmark of 100%, and proposed ₹1,191 crore of drainage works to reach full coverage by 2020, without stating a design basis (RMC, 2015); no source shows that target met, and the CAG's audit of AMRUT in the State (year ended March 2022) does not mention drains at all. The approval route shapes this chapter. Chhattisgarh did not replace the rules it inherited from Madhya Pradesh in 2000: it still amends the Chhattisgarh Bhumi Vikas Niyam 1984, made under s.85(1) read with s.24(3) of the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973 and amended by the Housing and Environment Department, among others by notifications No. 318/1193/32/2006 of 17 February 2009 (rainwater harvesting), No. F 7-27/2017/32 of 6 October 2018 and No. F 07-24/2019/32 of 29 April 2020, none of which adds a drainage, site-level or detention rule; drafts of September and December 2025 and a reclassification of land uses in October 2026 have been reported but not read. The base and consolidated texts of the Niyam as they stand in Chhattisgarh were not found. Rule 50 is still the rule on land unsuitable for development: T&CP's report format asks whether the land is unsuitable under rule 50, whether it is waterlogged and how far it lies from a canal, nala or river, and its checklist asks, for land next to a nala, canal, river or watercourse, for the no-objection of WRD or the Revenue Department and WRD's high flood point (T&CP Directorate letters of 2011); but the 9 m and 15 m lines of the 1984 text as made in Madhya Pradesh (9 m from the highest water mark, or, by a major watercourse, 9 m from the average high flood mark or 15 m from its defined boundary, whichever is more) are not confirmed for Chhattisgarh [TBC]. Construction on the bed or edge of a reservoir or on a natural drain may not be regularised (Chhattisgarh Act of 2002 on the regularisation of unauthorised development, s.7(1), as enacted; whether later Acts kept the bar was not checked). Development permission is given by T&CP under the Adhiniyam, and building permission by the Municipal Corporation (in Raipur, RMC), Nagar Palika Parishad or Nagar Panchayat under the Municipal Corporation Act 1956 and the Municipalities Act 1961, as adapted in Chhattisgarh; in Nava Raipur, NRDA (now the Nava Raipur Atal Nagar Vikas Pradhikaran) is a Special Area Development Authority under the same Adhiniyam, and delegated most of its powers under ss.69 to 69-ग of that Adhiniyam to its Chief Executive Officer by notification No. 4066 of 23 May 2022; and the works of State departments and local authorities need T&CP's concurrence under ss.27 and 28 (Housing and Environment Department letter of 23 November 2009). The 2018 amendment added a plinth-level check and a plinth certificate (rule 96), whose form checks location, setbacks and deviations but no level or drainage item, a site-inspection form that asks whether a major nala ("Nalah (Major Drain)") is adjacent to the plot and, if so, its nearest distance, the proposal to comply with the Niyam, and a completion form that asks whether rainwater harvesting is installed as per rule and whether the drainage line is connected to final disposal. Rainwater harvesting is required under rule 78(4), by the systems of Appendix ढ (N), and the Authority may levy a penalty of up to ₹1,000 a year per 100 m² of built-up area where a system is not built and kept up (amendment of 17 February 2009); the plot threshold is reported as 500 m² (Rajya Sabha answer of 2019), but the 2009 amendment substitutes the figures "500" and "300" in the rule without saying which is the threshold, and the rule text was not read [TBC]. Integrated townships must provide rainwater harvesting and a sewage treatment plant (Appendix ण, 2008). A draft green-building rule of 2017 (rule 79-C) would have required rainwater harvesting on plots above 100 m² and kept at least 20% of recreational open space unpaved, but its final text was not found. State buildings fall under the General Administration Department's order No. F 9-22/2016/1/5 of 31 May 2016, which makes rainwater harvesting compulsory for buildings under construction of every department and undertaking with roofs above 1,500 sq ft, and requires it on existing buildings with pucca roofs above 5,000 sq ft. The Chhattisgarh Ground Water (Management and Regulation) Act 2022 lets the State enforce rainwater harvesting and recharge in notified critical blocks and stressed urban areas, but it comes into force only on a date the State notifies, and no such notification has been found. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a "zero runoff" condition. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the layout at development permission, with the building plan, at the plinth-level inspection, where the distance to the nearest major nala is already recorded, and with the rainwater harvesting at completion. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Chhattisgarh Bhumi Vikas Niyam 1984 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the CGBVN 1984 steps a Chhattisgarh applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (44N statewide, including Jashpur Nagar and the eastern part of Jashpur district, which lie in zone 45N), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC gauges on the receiving rivers, of WRD's dam, barrage, reservoir and tank levels and of the levels of the lakes and reservoirs of Nava Raipur, and, for an outfall to a mine void, of the lessee's mine survey used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Chhattisgarh has no notified design return period or design storm for its urban drains. The only explicit urban design storm in the State is in the Naya Raipur Development Plan-2031 (NRDA, 2008), which says that "5 years Maximum rainfall intensity should be taken for design of system" (§10.3.1.1), asks that any river embankment be safe against a 100-year flood, keeps roads 0.5–1.0 m above the observed high flood level, follows IRC SP-50 for road drainage, and gives a chart of rainfall intensity against time of concentration for 2, 5, 10 and 50 years prepared from IMD data for the Raipur region (Figure 10.1 of the Plan), with no equation, record length or method; it is a plan for one city, not a State standard. Raipur's storm drainage plan under AMRUT (RMC, 2015) records coverage of 49%, about 480 km of pucca drains and 11 road stretches that flood two or three times a year, and proposes ₹1,191 crore of works, but states no return period, intensity or runoff coefficient; and AMRUT in the State funded water supply, sewerage and septage and green spaces, so the CAG's audit of it (year ended March 2022) does not mention drains at all. The design basis of the Raipur Smart City drainage works and of the drains of Bilaspur, Durg, Bhilai, Korba and the Bhilai Steel Plant township was not found. These figures are history, not a design basis. IMD's national IDF study (Das et al. 2022) has no Chhattisgarh station, the constants for Raipur in an older IMD study (Ram Babu et al., 1979) have been seen only in a search snippet and are unverified, and no station IDF with usable constants has been published for any Chhattisgarh city; the NRDA chart can be read only by eye. The short bursts on record, 79 mm in an hour at Kanker (26 June 1974) and 80 mm at Jagdalpur (CWC), lie below the 1-hour values that the CWC ratios give, while the 24-hour records, 370.3 mm at Raipur on 4 August 1910 and 392.0 mm at Rajnandgaon on 21 September 1965 among them, exceed the 100-year depths of the CWC plates (IMD; this Manual's reading). The State's design values are therefore those of the CWC Flood Estimation Reports for subzones 3(d), 3(g), 3(f), 1(d) and 3(c), with the interim provisions of Chapter 2, and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Chhattisgarh calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or T&CP:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by T&CP and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the CGBVN 1984 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the T&CP list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the permission of WRD for a work on, or a discharge to, one of its rivers, dams, barrages, reservoirs, tanks or canals, among them Gangrel, Minimata Bango, the Hasdeo barrage at Darri, the Mongra and Arpa Bhaisajhar barrages, Kharang, the Kelo dam and Kopra Jalashay, the permission of the Commissioner or Chief Municipal Officer to connect to a municipal drain or to build over one (Municipal Corporation Act 1956 and Municipalities Act 1961, as adapted in Chhattisgarh), the concurrence of T&CP that a work of a State department or local authority needs (Nagar Tatha Gram Nivesh Adhiniyam 1973, ss.27 and 28), the views of the Chhattisgarh State Wetland Authority on a work within 50 m of the highest flood level of a talab or wetland that it treats as protected, and its approval for a regulated activity in a notified wetland or at Kopra Jalashay, the consent of the Collector for a work on a tank vested in the State (Land Revenue Code 1959, s.251), the consent of the lessee and of DGMS that this Manual requires for any discharge to a mine void or pit lake or for a drain that crosses a mining lease, the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example NRDA in Nava Raipur, or Bhilai Steel Plant in its township), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Chhattisgarh because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 May date is set by this Manual to fall before the south-west monsoon (June–September), when most Chhattisgarh extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Chhattisgarh has no State order fixing a date for pre-monsoon desilting: no order of UADD, RMC or CGSDMA with a date was found, and no State disaster management plan or urban flood plan of CGSDMA was found. After the Raipur floods of July 2026 residents blamed inadequate desilting and drains narrowed by encroachment, and RMC's Commissioner was reported angered by garbage-choked drains (as reported). The drains are run by several hands: the Municipal Corporations, Nagar Palika Parishads and Nagar Panchayats for the municipal drains; NRDA in Nava Raipur; Bhilai Steel Plant's Town Services in its township, which the Commissioner of Bhilai Municipal Corporation warned in July 2025 over uncleaned township drains after a 15 June deadline was missed (as reported); WRD for the rivers, dams and barrages; and the coal companies on their leases, whose clearance conditions require garland drains and sumps to be desilted regularly (MoEFCC, clearance for Gare Palma Sector II, 2024). The rivers are run by dam operation: Gangrel's release of October 2025 was preceded by alerts to 72 riverside villages (as reported); the gates of Hirakud in Odisha were opened at Chhattisgarh's request in August 2020 and September 2024, and in August 2022 the State was reported to have opened its barrages on the Mahanadi before informing Odisha (as reported). No operating rule for any sluice, flap gate, interception weir or pumping station in a Chhattisgarh town, linking it to a river stage, a dam or barrage release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 May; 25 May in Bastar) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Chhattisgarh, the pre-monsoon inspection of sluices, flap gates, non-return valves and pumped facilities, including the sluices and gates on outfalls to reservoirs, barrage ponds and talabs and on outfalls that the Kharun, the Seonath, the Arpa, the Hasdeo, the Kelo, the Indravati or the Hirakud backwater can close, with the pump duty and gate seal tests, shall be completed by 31 May, and in the Bastar division by 25 May; these facilities, with their standby generators, shall be certified ready by 10 June, the normal onset date used by IMD Raipur and before the new normal onsets of 11–17 June, with every gate on an outfall to a river or reservoir operated through its full travel. Pumps, their standby power and the gates shall then be kept on monsoon standby, with the monthly test run, until 20 October, and in the Bastar division until 31 October, after the normal withdrawal of 7–15 October, and at an outfall to a river regulated by a dam or barrage upstream until the releases from the dam have ended and the river at the governing gauge has fallen below its danger level where one is published, if that is later.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December with the south-west monsoon (mid-June to early October) shaded, and the onset period from 10 to 17 June and the withdrawal period from 7 to 15 October shaded more lightly. Lanes show routine inspections, the pre-monsoon inspection and desilting of every facility with the Form 10-7 declaration by 31 May (desilting by 25 May in the Bastar division), the readiness of sluices, flap gates, pumps and standby generators by 10 June, pumps and gates on standby to 20 October (31 October in the Bastar division), inspections after heavy rainfall, and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) South-west monsoon Onset Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 May 10 Jun 20 Oct Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 May (Bastar 25 May): desilting, pump and gate tests. By 10 Jun: sluices, gates, pumps ready. To 20 Oct (Bastar 31 Oct): standby After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert Annual declaration Form 10-7 Form 10-7 lodged by 31 May: Tier A facilities; pumped, gate and regional facilities anywhere Authority At least every 2 years (every year if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% random sample of others each year → facility register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one monsoon to 20 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 May, 10 June and 20 October are fixed (in the Bastar division, 25 May for desilting and 31 October for standby). Normal onset 10 June (State, IMD Raipur) to 17 June (Bilaspur); normal withdrawal 7 October (Pendra Road) to 15 October (State, IMD Raipur) (IMD).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 May deadline is set by this Manual for the onset of the south-west monsoon in the second and third weeks of June: IMD Raipur uses 10 June as the normal onset for the State, and the new normals are 11–13 June at Jagdalpur, 14 June at Kondagaon, 16 June at Raipur and Pendra Road and 17 June at Bilaspur (IMD, 1961–2019 normals); the monsoon set in on 12 June in 2020 and entered the State through Sukma on 8 June in 2024 (IMD Raipur). Large falls come in June: 365.0 mm at Jashpurnagar on 30 June 2001, 337.0 mm at Durg on 15 June 2004 and 297.0 mm at Raipur on 30 June 2007 (IMD). The south of the State is wetter earlier, with the onset at Jagdalpur from 11 June and 207.0 mm at Bailadila on 11 May 1990 (IMD), so this Manual sets 25 May in the Bastar division. No State or municipal deadline for desilting was found; this Manual takes 31 May for desilting, the pre-monsoon inspection and the annual declaration. NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 31 May so that dry-season work can be finished. Sluices, flap gates, pumps and their standby generators must in addition be certified ready by 10 June, the earliest normal onset. The normal withdrawal runs from 7 October at Pendra Road and 9 October at Raipur to 12–14 October at Jagdalpur (IMD, 1971–2019 normals), and IMD Raipur uses 15 October; 21 of the 100 storms and depressions that affected the State from 1891 to 2014 came in October, on more southerly tracks across Bastar, and October storms are on record, 228.1 mm at Pendra Road on 8 October 1994, 206.0 mm at Ambikapur on 1 October 1961 and 148.6 mm at Raipur on 8 October 1900 (IMD); pumps and gates are therefore kept on standby to 20 October, and to 31 October in the Bastar division (Figure 10.3), and at an outfall to a river regulated by a dam or barrage until the releases have ended and the river has fallen below its danger level, if that is later. The post-event inspections of Table 10.3 cover storms at any time of year.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Chhattisgarh cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 10 June to 20 October (31 October in the Bastar division), after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Chhattisgarh drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Chhattisgarh Bhumi Vikas Niyam 1984 are made and from the municipal Acts. The graduated steps are set by this Manual. In Chhattisgarh the courts, the National Green Tribunal and the State Wetland Authority have become the working regulators of the rivers, tanks and nalas. The Tribunal's Central Zone bench directed the Collector of Janjgir-Champa to remove encroachments from ponds recorded in the land records at Baloda (order of 14 November 2024 in O.A. 78/2024), and the Tahsildar proceeded against the encroachers under s.248 of the Chhattisgarh Land Revenue Code 1959 (report of 27 December 2024); in January 2026 it ordered that the treatment plants for Durg's sewage, carried to the Seonath by the Shankar and Pulgaon nalas, be finished within six months (as reported). The High Court, hearing the pollution of the Arpa, recorded that about 40% of Bilaspur's sewage would remain untreated after the new plants (January 2025, as reported), and in May 2026 called the pollution of the Kharun, the Seonath and the Arpa a "systematic failure" (as reported); after its orders of 22 January 2019 in WPC 25/2016 and 2696/2016, the State decided that the permission of the Arpa Special Area Development Authority would no longer be needed to sell, build on or develop land in Bilaspur (Housing and Environment Department letter of 14 February 2019). The State Wetland Authority halted works at Karbala Talab in Raipur within 50 m of its highest flood level (September 2025), ordered a probe into a toy-train plan in the buffer of Narhaiya Talab (2025) and directed NRDA to withdraw its tenders for plots beside the Jhanjh wetland in Nava Raipur (March 2025) (as reported). Rainwater harvesting has been enforced case by case: 18 builders and 7 industrial units in Raipur district faced action for not building it (2016), and RMC directed builders to provide at least 50 recharge pits in each township (as reported). The statutes carry real powers: the Authority may levy up to ₹1,000 a year per 100 m² of built-up area on an owner who does not build and keep up rainwater harvesting (Bhumi Vikas Niyam, rule 78(4), as amended in 2009); construction on the bed or edge of a reservoir or on a natural drain may not be regularised (regularisation Act 2002, s.7(1)); tanks recorded for nistar vest in the State (Land Revenue Code, s.251), and unauthorised occupation of them is met by summary eviction (s.248); and the Municipal Corporation and Municipalities Acts, as adapted in Chhattisgarh, carry the drainage and tank powers of the Madhya Pradesh Acts from which they come (their Chhattisgarh texts were not read). This shows that a rule without routine enforcement does little, and that where the State has not drawn a line the courts, the Tribunal and the Wetland Authority have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river (the Kharun at Pathardihi, the Seonath, the Arpa, the Hasdeo at Bangodam or Katghora, the Kelo, the Mahanadi at Rajim, Kalma or Surajgarh, or the Indravati at the CWC site at Jagdalpur) or of the receiving reservoir, barrage pond or talab, and, where it is gauged, at the outfall, each on a named datum, with any reading of a local gauge kept apart from the CWC levels; the state of every sluice, flap gate, interception weir and pumping station on the outfall and on the drain upstream of it, with the hours each pump ran and any loss of power; and the gate openings and releases of any dam or barrage that sets the receiving level, such as Gangrel, Minimata Bango, the Hasdeo barrage at Darri, the Mongra or Arpa Bhaisajhar barrage, Kharang or the Kelo dam, with the level of the Hirakud reservoir where its backwater reaches the outfall;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), CGSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Chhattisgarh's floods have been recorded by IMD, CWC and the press rather than examined by technical reviews. Raipur's record day, 370.3 mm on 4 August 1910, is the highest in the observatory's record since 1901 (IMD); on 30 June 2007 Raipur recorded 297.0 mm and more than 6,000 people were moved from its low-lying areas (IMD; as reported). On 28–29 August 2020 a Bay depression brought 282.7 mm to Akaltara (IMD Raipur), the Kharun at Pathardihi, the Mahanadi at Kalma and Surajgarh and the Mand at Kurubhata set new high flood levels (CWC levels, as reported), 11,942 houses were damaged and 219 relief camps were opened (as reported). On 25–28 August 2025 floods in the Bastar division killed eight people and damaged about 495 houses and 16 culverts and bridges (as reported). In July 2026 Raipur's underpasses and low colonies were flooded and five ponds overflowed into homes, with no depth of rain reported (as reported), and Bilaspur was reported to have received 28 cm in a day in one source and 415.6 mm in another, a conflict that IMD has not resolved. On 24–27 September 2026 floods across the State killed eight people and affected 22,377 people in 571 villages, all 14 gates of Gangrel were opened, the Kharun overflowed at Mahadev Ghat and the Indravati at Jagdalpur set a new high flood level (as reported). The records of the past are larger still: 392.0 mm at Rajnandgaon on 21 September 1965, 358.0 mm at Korba on 12 August 2004 and 337.0 mm at Durg on 15 June 2004 (IMD). No review of any flood event, and no record of flood extents, depths or durations kept by any Municipal Corporation, NRDA or CGSDMA, was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Chhattisgarh's drainage records are public, though most of the State's websites could be read only in archived copies: the amendments of 2018 and 2020 to the Chhattisgarh Bhumi Vikas Niyam 1984, the General Administration Department's order on rainwater harvesting of 31 May 2016 and the approval notifications of the Raipur and Arpa development plans (on the T&CP website); chapters of the Naya Raipur Development Plan-2031 and Raipur's AMRUT storm drainage plan of 2015; the Ground Water (Management and Regulation) Act 2022 and WRD's daily tank gauge reports; the CAG's audit of AMRUT; the reports of CECB and the district administration to the National Green Tribunal; IMD's Climate of Chhattisgarh and the monsoon reports of the Meteorological Centre Raipur; CGWB's groundwater assessments; and the Ramsar information sheet for Kopra Jalashay. Much else could not be found in the public domain: the consolidated text of the Bhumi Vikas Niyam; the Chhattisgarh texts of the Municipal Corporation and Municipalities Acts; NRDA's drainage report, lake levels and development regulations; the design basis of any storm drain in Raipur, Bilaspur, Durg, Bhilai or Korba; the approval of a revised Raipur development plan; any State disaster management or urban flood plan; warning and danger levels for any CWC site in the State except Jagdalpur; the operating rules of WRD's dams and barrages; an inventory of the sluices, interception weirs and pumping stations of any town; any notification bringing the Ground Water Act into force; the list of wetlands under the State Wetland Authority; and the texts of the High Court's orders on the Arpa and the Kharun. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate