Chapter 4Site Runoff Control: Retention and Detention
4.1 Purpose and scope
4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:
- (a) the order in which runoff-control measures are to be applied (Clause 4.3);
- (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
- (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
- (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
- (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
- (f) regional detention and fee-in-lieu (Clause 4.13);
- (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
- (h) public safety (Clause 4.15).
4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (rain or roof water harvesting under rule 78(4) of the CGBVN 1984, as amended on 17 February 2009, on buildings on plots above a threshold reported as 500 m² (the amendment substitutes the figures "500" and "300" in the sub-rule, and the threshold is to be confirmed [TBC]), by the options of Appendix ढ (N), with a penalty of up to ₹1,000 a year for every 100 m² of built-up area where the system is not built and maintained; and, for the buildings of State departments and their undertakings, the General Administration Department order of 31 May 2016; the rules are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.
4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.
4.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Retention | Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall. |
| Retention depth | The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E). |
| Required retention volume (RRV) | The runoff volume from the retention depth over the post-development site (Clause 4.4.2). |
| Detention | Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5. |
| Retention credit | The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume. |
| Permissible site discharge (PSD) | The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha. |
| Site storage requirement (SSR) | The detention storage required per hectare of site under the simplified method of Clause 4.14. |
| Multi-stage outlet | An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2). |
| Drawdown time | Time from the peak stored volume until the stated fraction of that volume has been released. |
| Emergency spillway | A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment. |
| Freeboard | Vertical distance between the maximum design water level and the embankment crest or other critical level. |
| Flood-sensitive catchment | A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4. |
| Authority | The approving authority under Chapter 1 (the Director of Town and Country Planning, or an officer authorised by the Director, who grants development permission for land in a planning area under the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973, and the Municipal Corporation, Nagar Palika Parishad or Nagar Panchayat that grants building permission under the CGBVN 1984; NRDA in Nava Raipur Atal Nagar, as a Special Area Development Authority under that Adhiniyam; or a development authority constituted under that Adhiniyam, where it grants that permission [TBC], as applicable). |
| Tier A / Tier B | Adoption tiers defined in Chapter 1. Tier A: Raipur Municipal Corporation (RMC), every approving authority within the planning area of Raipur under the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973, including the Directorate of Town and Country Planning where it grants development permission, RDA in its schemes and the Nagar Palika Parishads and Nagar Panchayats in that area; NRDA in Nava Raipur Atal Nagar; every other Municipal Corporation constituted under the Municipal Corporation Act 1956 as adapted in Chhattisgarh, among them those of Bilaspur, Durg, Bhilai, Bhilai-Charoda, Risali, Birgaon, Rajnandgaon, Korba, Raigarh, Jagdalpur, Ambikapur, Dhamtari and Chirmiri; and the Directorate of Town and Country Planning where it grants development permission within the planning area of a Municipal Corporation. Tier B: Nagar Palika Parishads and Nagar Panchayats. |
4.3 Order of measures
4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:
- Preserve. Keep existing waterbodies, talabs, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
- Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
- Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
- Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).
4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.
Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.
4.4 Retention
4.4.1 Requirement
The site shall retain the RRV. Retention shall be achieved by one or more of the following:
- infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
- rainwater reuse that is drawn down by a demonstrated non-potable demand;
- green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.
The limits of Clause 4.4.4 apply.
4.4.2 Computation of the RRV
RRV (m³) = 10 × Q_R × A
where:
- Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
- A (ha) is the area of the site that drains to the outfall.
Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.
The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.
Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.
4.4.3 Verification
Retention by infiltration shall be supported by:
- (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
- (b) a design infiltration rate of no more than half of the measured rate; and
- (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).
Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.
Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.
4.4.4 Limits on retention
4.4.4.1 Infiltration practices shall not be used:
- where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
- on contaminated land;
- within the setbacks from foundations, wells and septic systems set in Chapter 8; or
- on fill, unless tested after placement.
4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.
4.4.5 Drawdown of retention
Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.
4.4.6 Retention credit: definition and computation
4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.
4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:
- (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
- (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
- (c) once it is full, route its overflow to the detention facility; and
- (d) size the detention for the residual hydrograph.
The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.
4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:
V_credit = C_R × RRV_provided
where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.
4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.
Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Chhattisgarh, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.
The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).
This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).
4.4.7 Preservation credit
Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:
- they are protected by a registered covenant or dedication; and
- their runoff is not concentrated onto impervious surfaces.
This lowers both the RRV and the detention required. No other preservation credit applies.
4.5 Release-rate criteria
4.5.1 General
4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.
4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.
4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.
4.5.2 Standard catchments
For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:
Q_post(T, d) ≤ 0.9 × Q_pre(T, d)
4.5.3 Flood-sensitive catchments
4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:
Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).
Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).
4.5.3.2 The flood-sensitive catchments are:
- (a) Raipur's low colonies on the Kharun nalas: the catchments of the nalas and drains of Raipur and Birgaon that discharge to the Kharun, with the talabs on them, and the low-lying colonies of the city that drain to them and flood in heavy rain, whose outfalls are held up when the Kharun is high;
- (b) Bilaspur on the Arpa: the land of Bilaspur that drains to the Arpa below the Bhaisajhar barrage, including Sarkanda and the other low colonies of the river's banks;
- (c) Durg–Bhilai on the Seonath nalas: the land of Durg, Bhilai, Bhilai-Charoda and Risali that drains to the Seonath (Shivnath) through the Shankar and Pulgaon nalas and the other nalas of the twin cities;
- (d) Korba below Bango and Darri: the land of Korba that drains to the Hasdeo below the Minimata Bango dam and the Hasdeo barrage at Darri, whose outfalls are held up when the dams release;
- (e) Raigarh–Sarangarh in the Hirakud backwater: the land of Raigarh and Sarangarh that drains to the Kelo, the Mand or the Mahanadi within reach of the backwater of the Hirakud reservoir;
- (f) Jagdalpur on the Indravati: the land of Jagdalpur that drains to the Indravati, whose outfalls are held up when the river is above its CWC warning level; and
- (g) any catchment notified under Clause 4.5.4.
The boundaries shall be those mapped in Annex 4A.
4.5.4 Notification of further flood-sensitive catchments
4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:
- (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
- (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
- (c) an outfall to a talab, lake, reservoir or barrage pond held at or above its full level, such as the talabs of Raipur and the lakes of Nava Raipur, or an outfall that is held up by a river in flood or by releases from dams and barrages upstream, such as the Kharun at Raipur, the Arpa below the Bhaisajhar barrage at Bilaspur, the Hasdeo below Bango and Darri at Korba, the Mahanadi below Gangrel, the Indravati at Jagdalpur or the Hirakud backwater at Raigarh and Sarangarh, for part of the SW monsoon (Chapter 5);
- (d) loss of more than a quarter of the mapped tank and talab storage in the catchment since the earliest available survey; or
- (e) a basin master plan that relies on limiting site discharge.
4.5.4.2 The procedure shall be:
- The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
- The State-level technical committee constituted under Chapter 1 reviews the note.
- The draft notification and map are published for public comment for at least 60 days.
- The Government notifies the catchment and the map is added to Annex 4A.
- The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.
4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.
Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The Raipur entry follows the Kharun and the city's record. Raipur's nalas are linked to the Kharun "through eight big canals" (as reported), and the river set a new highest level of 281.68 m at Pathardihi on 29 August 2020, 2.47 m above its level of 1994, on the day the district had about 160 mm of rain (CWC, as transcribed by SANDRP; as reported); no warning or danger level is published for it. In the city's storm-drainage plan under AMRUT the drain network covered 49% of the city, about 480 km of drains were pucca, "Capacity of drain is not sufficient In rainy season most of the drains are overflowed", and 11 road stretches flooded two or three times a year; the plan proposed ₹1,191 crore of drainage works but stated no return period, intensity or runoff coefficient (Raipur Municipal Corporation, service level improvement plan, 4 November 2015), and the CAG's audit of AMRUT in the State, for the years to March 2022, covers water supply, sewerage and parks and never mentions drains. On 30 June 2007, when 297.0 mm fell at Raipur (IMD), more than 6,000 people were moved from low-lying parts of the city (as reported); on 4–5 July 2026 Adarsh Nagar (Mowa), DD Nagar, Shankar Nagar, Tatibandh and the Fafadih and Gudhiyari underpasses were under water and five ponds overflowed into the homes of Chaubey Colony (as reported); and in September 2026 the Kharun overtopped the road at Mahadev Ghat (as reported). The city's ponds have shrunk from about 130 to about 40 (as reported). The Bilaspur entry follows the Arpa. Bilaspur lies on the river below the Bhaisajhar barrage (full reservoir level 302.000 m, WRD); on 4 September 2025 the colonies from Sarkanda to Abhishek Vihar "turned into sprawling water bodies", and in July 2026 more than 400 houses were flooded after a fall reported as 28 cm in 24 hours by one paper and as 415.6 mm by another; the conflict is unresolved, and the city has no IMD station in the extremes table to test it [TBC]. The special area authority for the Arpa riverfront, whose development plan was approved in 2014, was largely sidelined after orders of the High Court in 2019, and no other line along the river was found. The Durg–Bhilai entry follows the Seonath nalas: the Shankar and Pulgaon nalas carry most of Durg's sewage to the Seonath, and the NGT ordered the treatment plants on them finished within six months (16 January 2026, as reported); in Bhilai, water hyacinth from the drains of the steel-plant township blocked the Junwani and Kosanala culverts in 2025 (as reported); and in the flood of September 2026 764 people were rescued in Durg and about 200 houses were inundated (as reported). The Korba entry follows the Hasdeo. The town lies below the Minimata Bango dam (spillway capacity 24,000 m³/s) and the Hasdeo barrage at Darri (19,820 m³/s) (CWC, National Register of Large Dams, 2009); when Bango released about 30,000 cusecs through six gates and Darri about 20,000 cusecs on 24–26 August 2024, houses were flooded in Motisagarpada, Seetamani and Imliduggu (as reported), and the Hasdeo set new highest levels at Katghora (313.58 m, 20 July 2026) and Bangodam (303.5 m, 17 August 2026) (as reported). Korba holds the record of 358.0 mm in 24 hours on 12 August 2004 (IMD), and its coalfield and ash dykes add sediment and breach hazards (Commentary to Clause 4.1). The Raigarh–Sarangarh entry follows the Hirakud backwater, which partly submerges 33 villages in Chhattisgarh and damaged villages on both sides of the border in 2011 (as reported); the Kelo overflowed in Raigarh on 14 August 2019, and the Mahanadi at Surajgarh and the Mand at Kurubhata set their highest levels, 201.06 m and 220.4 m, in August 2020 (as reported); Raigarh recorded 360.9 mm on 10 July 1958 (IMD). The backwater's extent within the State at Hirakud's full level has not been mapped [TBC]. The Jagdalpur entry follows the Indravati, the only river in the State with published CWC warning and danger levels found, 539.49 m and 540.80 m: it stood at 541.65 m, above danger, on 29 July–8 August 2019 (CWC), and set a new highest level of 544.891 m, 4.09 m above danger, on 26 September 2026 (as reported), while the floods of 25–28 August 2025 in the Bastar division killed eight people (as reported). Its upstream dams are in Odisha. Dhamtari, Rajim and Arang below Gangrel, Rajnandgaon, Ambikapur and Kanker are candidates for notification under Clause 4.5.4. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.
4.5.5 Minimum outlet and short-duration 2-yr checks
4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.
4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:
- size the low-flow orifice as the smallest opening that meets Clause 4.7; and
- report the resulting 2-yr exceedance for those durations.
The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.
Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next SW monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).
4.5.6 Constrained redevelopment sites
4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:
- (a) the existing site is at least 60% impervious, as surveyed before demolition;
- (b) the site is 1 ha or less; and
- (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.
New development on undeveloped land is never eligible.
4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:
- (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
- (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
- (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).
4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:
- (a) paid into the ring-fenced account of the basin in which the site lies;
- (b) spent only on regional detention or on restoring talab or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
- (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.
Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with WRD agreement.
4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.
Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as the old city of Raipur round Budha Talab, or the old cores of Bilaspur, Durg, Rajnandgaon and Raigarh, there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.
4.6 Detention sizing procedure
4.6.1 Method
Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.
4.6.2 Steps
- Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
- Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
- Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
- Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 1 July to 30 September on kanhar or dorsa paddy lowland, talab-draining and valley-floor sites, at all times in catchments draining to a reservoir or barrage pond, the Hirakud backwater, a mine void or a river at or above its CWC warning level, and at other sites and times after a 5-day total of more than 53 mm, AMC II otherwise).
- Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
- Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
- Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
- Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
- Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
- Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
- Size the emergency spillway and set freeboard (Clause 4.9).
- Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).
4.6.3 Storms to be routed
Every facility shall be routed for the full matrix:
Table 4.1 — Design storms to be routed for detention sizing
| AEP | Durations (h) | AMC |
|---|---|---|
| 50% (2-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 10% (10-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 1% (100-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.
4.6.4 Initial conditions
Each run shall start with:
- detention storage empty, down to the invert of the lowest outlet;
- any permanent pool full;
- retention practices empty, except as limited by Clause 4.11; and
- RWH storage full (Clause 4.11).
The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.
4.6.5 Multi-stage outlet design
4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:
- Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
- Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
- Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
- Emergency spillway: separate from the primary outlet (Clause 4.9).
Stages may be combined where routing shows that every cap is met.
4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).
4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.
4.6.6 Tailwater on the outlet
The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:
- for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
- for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).
Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.
4.6.7 Illustrative example
Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a colony draining to the Kharun in Raipur. They are not NIH-DHAARA values and must not be used for design.
Inputs:
- Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
- Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
- Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
- 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
- Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
- Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
- Storage: vertical-walled, 2,500 m² plan area.
- Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
- Stage 1: 170 mm orifice at the invert.
- Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
- Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.
Results (discharges in L/s; storage in m³):
Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
| Duration (h) | 2-yr pre | 2-yr post, detained | 10-yr pre | 10-yr post, detained | 100-yr post, uncontrolled | 100-yr post, detained | 100-yr storage used | 10-yr drawdown, 50% blocked (h) |
|---|---|---|---|---|---|---|---|---|
| 1 | 4 | 15 | 51 | 28 | 922 | 42 | 1,426 | 31.3 |
| 2 | 14 | 20 | 84 | 34 | 961 | 79 | 1,911 | 32.1 |
| 3 | 19 | 22 | 104 | 37 | 981 | 139 | 1,999 | 32.8 |
| 6 | 32 | 25 | 150 | 41 | 1,010 | 194 | 2,154 | 34.2 |
| 12 | 127 | 30 | 302 | 46 | 1,074 | 276 | 2,512 | 39.0 |
| 24 | 149 | 32 | 327 | 49 | 1,081 | 320 | 2,766 | 45.3 |
| 48 | 173 | 34 | 349 | 82 | 1,087 | 343 | 2,913 | 44.8 |
| 72 | 180 | 34 | 356 | 84 | 1,089 | 343 | 2,911 | 44.7 |
How to read it:
- 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
- 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
- Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
- Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
- Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.
The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.
Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).
Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).
4.7 Drawdown
4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.
4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).
4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).
4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.
Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Chhattisgarh storage must hold multi-day volumes. It is still short enough that a basin filled by one SW monsoon depression will have most of its volume back before the next, which in late June and early July 2001 (365.0 mm at Jashpurnagar and 298.0 mm at Raigarh on 30 June, 281.8 mm at Narayanpur on 6 July and 497.8 mm at Charama on 9 July, IMD) followed within days.
4.8 Outlet structures
4.8.1 General. Primary outlets shall be:
- unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
- accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
- built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).
4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.
4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:
- have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
- have a clear open area at least 10 times the area of the opening it protects;
- be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
- be removable or hinged for cleaning; and
- for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.
4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).
4.8.5 Outlet barrels. Outlet barrels through embankments shall:
- be at least 300 mm in diameter (Chapter 6);
- have watertight joints;
- have a filter diaphragm or seepage collars over the length within the embankment; and
- have an energy-dissipating outfall (Chapter 9).
4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.
Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.
Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).
4.9 Emergency spillway, freeboard and embankment safety
4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:
- with the primary outlet assumed fully blocked;
- with the facility full to the spillway crest at the start of the storm; and
- with at least 0.3 m freeboard from the maximum water level to the embankment crest.
4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:
- endanger life;
- flood a habitable building or critical facility; or
- close an arterial road.
High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.
4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.
4.9.4 Spillway location. The spillway shall be:
- on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
- discharging to the 1% AEP overland flow path of Chapter 6; and
- placed so that its flow does not reach a building.
4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.
4.9.6 Embankments.
- (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
- (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
- (c) Embankments shall have:
- a crest width of at least 3 m;
- compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
- no trees or large shrubs.
- (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.
4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.
Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.
4.10 Facility types
4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.
4.10.2 Underground tanks and vaults.
- (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
- (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
- (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
- (d) The tank shall be ventilated.
- (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
- (f) Flotation and groundwater ingress shall be checked under Clause 4.12.
4.10.3 Rooftop detention.
- (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
- (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
- (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.
4.10.4 Podium and landscape-deck detention.
- (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
- (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.
4.10.5 Parking-lot detention.
- (a) It is permitted only on surface parking. Ponding depth shall not exceed:
- 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
- zero on accessible routes, ramps and pedestrian crossings; and
- zero in the 10% AEP storm on fire-tender access routes.
- (b) Signs shall warn that the area floods.
- (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).
4.10.6 Multi-use detention (parks, playfields, open space reservation).
- (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
- (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
- (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
- (d) The depth and slope limits of Clause 4.15 apply.
- (e) Play equipment and seating shall be placed above the 10% AEP level.
4.10.7 Ponds and wet basins.
- (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
- (b) Only storage above the permanent pool counts as detention.
Commentary.
- The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
- The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
- Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
- Using open space for multi-use detention fits the CGBVN 1984, under which layouts keep community open space (Rule 47; the Chhattisgarh percentage was not seen [TBC]) and integrated townships keep at least 10% of their area as gardens and playgrounds (Appendix ण, as amended in 2019), and the draft green-building rule of 2017 would have kept at least 20% of the recreational open space unpaved (draft rule 79-C, final text not found [TBC]). Nava Raipur Atal Nagar was planned with its parks as carriers of storm water to its lakes (as reported), and its development plan asks that rain water from the storm drains be stored in dug or natural lakes and depressions (Naya Raipur Development Plan-2031, §10.3.2). A detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires. Four kinds of land are not open space for this purpose. A talab or dabri on the land is preserved under step 1 of Clause 4.3.1 and modelled as a water surface (Clause 3.3.2(e)) that starts at its full level (Clause 3.12.5), so only its flood storage above that level can count, and only as Chapter 7 allows; village tanks over which the community exercised rights of irrigation or nistar vest in the State (Chhattisgarh Land Revenue Code 1959, section 251), their encroachment is proceeded against as unauthorised occupation (section 248), as at the ponds of Baloda under the NGT's order of 14 November 2024 in O.A. 78/2024, and public tanks vest in the Municipal Corporation (section 82 of the Municipal Corporation Act 1956, as adapted in Chhattisgarh [TBC]). Land in a buffer is not spare land either: the line 50 m from the highest flood level of a wetland, which the State Wetland Authority has applied to halt works at Karbala Talab and to probe a project at Narhaiya Talab in Raipur, and to have NRDA withdraw tenders beside the Jhanjh wetland in Nava Raipur (2025, as reported); the Kopra Jalashay Ramsar site at Bilaspur; and the distances of Rule 50 from water bodies and watercourses, 9 m and 15 m in the inherited 1984 text, whose Chhattisgarh wording is to be confirmed [TBC]. Land in the hydraulic corridor of a nala, talab or river under Chapter 7 is corridor or flood land already: water reaches it first, so it is not counted as detention for the development beside it (Chapter 7). And a mine void, pit lake, ash pond or ash dyke on or beside the land is not open space or storage for the site unless the lessee and DGMS, or for an ash pond its operator, agree in writing and its levels are surveyed (Commentary to Clause 4.1).
4.11 Rainwater harvesting versus detention accounting
4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.
4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.
4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:
- (a) the detention zone lies wholly above the RWH overflow level;
- (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
- (c) no pump, valve or user action can hold water in the detention zone; and
- (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.
Only the volume between the RWH overflow level and the detention overflow level counts as detention.
4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the SW monsoon season.
4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of rule 78(4) of the CGBVN 1984 and its Appendix ढ (N), the General Administration Department order of 31 May 2016 for government buildings, the rainwater harvesting required in integrated townships (Appendix ण of the CGBVN 1984) and in Nava Raipur Atal Nagar (Naya Raipur Development Plan-2031, §10.3.2), any area notified under the Chhattisgarh Ground Water (Management and Regulation) Act 2022 once it is in force, any condition of a development or building permission, or any rainwater harvesting rule or direction of an approving authority.
Commentary. RWH in Chhattisgarh rests on rule 78(4) of the CGBVN 1984, which sets out the planning standards for rainwater harvesting (Housing and Environment Department, letter No. 2940/1445/32/2009 of 23 November 2009) and was amended on 17 February 2009 (notification No. 318/1193/32/2006, Gazette p. 124(10)). The amendment substitutes the figures "500" and "300" in sub-rule (4), without saying for what ("नियम 78 के उपनियम (4) में अंक '500' तथा अंक "300" प्रतिस्थापित किया जावे", as printed), and adds clause (क): if the owner does not build and maintain the rainwater harvesting system as provided, the Authority may impose a penalty of up to ₹1,000 a year for every 100 m² of built-up area. The Chhattisgarh text of the sub-rule before or after 2009 was not read, so its threshold is not known: a Rajya Sabha answer of 8 July 2019 reports that rule 78(4) makes rain or roof water harvesting mandatory "for all types of buildings having plot size more than 500 sq. mt." in towns with planning areas notified under the 1973 Adhiniyam, which fits "500" as the plot threshold, but what "300" refers to is unknown [TBC]. The options are set out in Appendix ढ (Appendix N). The 2009 amendment replaced the pebbles of ढ-2 with a filter of fine stone over 50% of the depth at the bottom and fine sand over 20% in the middle, and added ढ-4: an underground storage tank, dug as needed in the marginal open space of the house, into which rain water is also led, with a tap to draw the water for washing clothes, cleaning floors and the garden, and, in premises of 100 dwelling units, a tank under a plant that treats the used water; options ढ-1 and ढ-3 were not read [TBC]. Integrated townships must provide rainwater harvesting (Appendix ण, 2008), Nava Raipur makes it "mandatory at individual development level" (Naya Raipur Development Plan-2031, §10.3.2), and the draft green-building rule of 2017 would have required it on every plot of more than 100 m² (draft rule 79-C, 30 March 2017), but whether that draft was made final was not found [TBC]. For government buildings, the General Administration Department ordered on 31 May 2016 that every building of a department or its undertakings under construction with a roof of more than 1,500 sq ft (about 139 m²) shall have rainwater harvesting, and every existing building with a pucca roof of more than 5,000 sq ft (about 465 m²) shall be given it, from the department's own budget (order No. F 9-22/2016/1/5). The Chhattisgarh Ground Water (Management and Regulation) Act 2022 lets the State enforce rainwater harvesting and recharge in notified over-exploited and critical blocks and stressed urban areas (section 7), but no notification bringing it into force or notifying an area was found [TBC]. Raipur Municipal Corporation is reported to require at least 50 rainwater harvesting pits in each township, and the district acted in 2016 against 18 builders and 7 industrial units that had not built them (as reported). None of these rules sets a storage volume, an infiltration test or a depth to the water table, requires a tank to be empty before a storm, or restricts recharge on clay, karst, mine ground or contaminated aquifers. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:
- An RWH storage tank or sump, including the underground tank of Appendix ढ-4 and the tanks built under the order of 31 May 2016, is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2), because after the July rains it is full. A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
- An RWH tank counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing or washing, demonstrated under Clause 4.4.3; watering a garden is not a continuous use in the monsoon. The tank is then modelled under Clause 4.4.6 like any other retention practice.
- The pits, filter beds and recharge structures of Appendix ढ, and the pits that Raipur requires in townships, count as retention only where they meet Clause 4.11.4: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume.
- The community open space of a layout (Rule 47), the open space of an integrated township and the unpaved area of the draft green-building rule are pervious area. They enter the post-development run as pervious land under Clause 3.9.2 and get no further credit as retention or detention unless they are built and tested as an infiltration practice.
- Recharge first where the aquifer is stressed. Groundwater use is moderate statewide, at a stage of extraction of 47.32% in the 2024 assessment, with 120 of the 146 blocks safe, 21 semi-critical, 5 critical and none over-exploited, but the critical blocks lie in the Seonath plain and include Dharsiwa, round Raipur, at 93.51%, with Gurur, Nawagarh, Bemetara and Berla, and the blocks of Durg and Dhamdha are semi-critical (CGWB, Dynamic Ground Water Resources of Chhattisgarh 2024; a press report that no block was critical in 2026 is unverified [TBC]). In these urban blocks, retention shall be provided by recharge before reuse or detention wherever site tests allow, through a silt trap, a filter and a first-flush diverter ahead of the recharge structure, and with a hydrogeologist's check of the target zone.
- No infiltration practice on kanhar. No pit, trench, filter bed, basin or recharge structure shall be founded on or in kanhar, which takes water through its cracks only while it is dry and almost none once they close (Clause 3.7.2). The RWH of rule 78(4) may still be met on such a site by a storage tank under Appendix ढ-4, which is credited only as the second bullet allows.
- A cavity check in the limestone belt. The Chandi and Charmuria limestones of the Raipur–Durg–Rajnandgaon belt, which supply Raipur's groundwater, are officially described as "Karstified and Cavernous", with field permeabilities of 4–65 m/day and solution cavities filled with clay (CGWB, 2024; CGWB, Rajnandgaon brochure); sinkholes and borehole cavities near Raipur are reported but not confirmed by the Geological Survey [TBC]. In this belt, an infiltration or recharge practice is credited only after a cavity check below its base, by probe holes or a geophysical survey, and only with the pre-treatment above, because runoff that reaches a cavity enters the aquifer with almost no filtering and can wash out the clay that fills it.
- No recharge credit on wet or disturbed ground. On the kanhar and dorsa paddy lowlands, the floodplains, the talab and reservoir margins, the Hirakud backwater and the other land of Clause 4.12.1, and wherever the seasonal high water table is within the 1.0 m separation of Clause 4.4.3, no recharge or infiltration practice earns retention credit; detention, conveyance and reuse govern there. No recharge or infiltration practice shall be built on an overburden dump or other mine-disturbed ground, on or beside an ash pond or ash dyke, or within the dewatering zone of a working mine, such as the drawdown of about 1.2 km round the Kusmunda and Gevra pits at Korba (as reported), where the water would be pumped out again or would wet unstable ground, and none within 50 m of the edge of a mine void without a geotechnical check.
- Fluoride, arsenic and nitrate. Fluoride above 1.5 mg/l was found in 14 of 783 samples, in Janjgir-Champa, Kanker, Korba, Koriya, Mahasamund, Raigarh, Rajnandgaon and Surajpur districts; arsenic in samples from Korba, Koriya and Raigarh and in the wells of Kaudikasa in the Ambagarh Chowki block, formerly of Rajnandgaon district; and nitrate above 45 mg/l in 11.5% of samples, in 20 districts including Raipur, Durg and Bilaspur (CGWB factsheet, December 2024; CGWB studies of Ambagarh Chowki). In these districts the hydrogeologist's check shall report the fluoride, arsenic and nitrate of the target aquifer before a recharge bore or shaft is credited, and untreated runoff shall not be put into a bore or shaft there; retention is then provided by surface infiltration through a soil or filter layer, or by detention and reuse (Chapter 8).
- Everywhere, road and parking runoff shall be recharged only through a surface infiltration practice with a filter, such as a vegetated basin or trench, never directly into a bore or well, and runoff from a nala that carries sewage, as most of Raipur's and Durg's nalas do, shall not be recharged at all.
On kanhar and the paddy lowlands a recharge pit drains slowly or not at all in the SW monsoon, and in the Seonath plain a sump is full after the first heavy rain. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH sumps are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives. The recharge-first rule for the stressed urban blocks, the bar on infiltration practices on kanhar, the cavity check in the limestone belt, the bars on mine-disturbed ground, ash ponds and dewatering zones, the 50 m distance from a mine void, the fluoride, arsenic and nitrate checks and the pre-treatment and road-runoff rules are set by this Manual; no Chhattisgarh rule on where recharge may or may not be credited was found.
4.12 High-groundwater and sandy coastal sites
4.12.1 Design groundwater level. Each site in the kanhar and dorsa paddy lowlands of the Chhattisgarh plain, where the water table rises close to the surface in the monsoon, the floodplains of the Kharun, the Seonath, the Arpa, the Hasdeo, the Kelo, the Mahanadi and the Indravati and their tributaries, the beds and margins of the talabs, reservoirs and barrage ponds, among them the talabs of Raipur and the lakes of Nava Raipur, and the Hirakud backwater at Raigarh and Sarangarh, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the SW monsoon, from:
- (a) site piezometer readings over at least one full June–November season; or
- (b) where (a) is not available, the higher of the CGWB or Water Resources Department record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, nala, talab, reservoir or mine void.
For the flotation check of 4.12.3 at sites in the kanhar and dorsa paddy lowlands, the talab and river floodplain margins and the Hirakud backwater, where (a) is not available, the DGWL shall be taken as existing ground level.
4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:
- (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
- (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.
4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:
- with the facility empty;
- with groundwater at the DGWL; and
- for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.
The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.
4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.
4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.
4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.
Commentary. Chhattisgarh is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the State, and saline groundwater is rare (electrical conductivity above 3,000 µS/cm in 2 of 783 samples; CGWB factsheet, December 2024), so the exposure provisions of 4.12.5 apply only where a test at the site shows it, or where the facility is in contact with mine water or ash-pond water whose chemistry has not been tested. The water table of the plain is several metres down before the monsoon but rises close to the surface after it: in 2023, 52% of the State's observation wells stood at 5–10 m before the monsoon, and about 76% within 5 m after it, 17.6% of them within 2 m (CGWB, Dynamic Ground Water Resources of Chhattisgarh 2024); in Raipur district the post-monsoon depth was 0.87–7.05 m (CGWB district brochure, about 2007). The kanhar and dorsa paddy lowlands, the floodplains of the Kharun, the Seonath, the Arpa, the Hasdeo, the Kelo, the Mahanadi and the Indravati, the margins of the talabs, lakes, reservoirs and barrage ponds, and the Hirakud backwater at Raigarh and Sarangarh are the wet cases. There an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when a river in flood, a reservoir or barrage pond at its full level, a talab or a flooded mine void raises the water table beside it; in the Gondwana coalfields groundwater can also stand under flowing (artesian) conditions (CGWB, 2024). The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, nala, talab, reservoir or mine void where that is higher than the well record, and on the paddy lowlands, the talab and river floodplain margins and in the Hirakud backwater it is taken as existing ground level for the flotation check unless piezometers show otherwise. The June–November monitoring season of 4.12.1(a) is set by this Manual to cover the SW monsoon and the post-monsoon high that the CGWB measures in November: a reading taken in May or June, when most wells are at 5–10 m, understates the design level. No monsoon water-table depths for individual town sites in Raipur, Durg–Bhilai, Bilaspur, Korba or Raigarh were obtained [TBC]. The factor of 1.2, the 0.5 m allowance and the "ground level" default for the lowlands, the floodplain margins and the Hirakud backwater have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Chhattisgarh were found during research.
4.13 Regional detention and fee-in-lieu
4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:
- (a) a regional detention facility identified in the plan; or
- (b) a fee-in-lieu paid toward restoration of talab or tank storage identified in the plan.
4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:
- (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
- (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
- (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the SW monsoon. Storage below FTL that is held for irrigation or supply through June to September shall not be credited.
- (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
- (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
- (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.
4.13.3 Fee. The fee-in-lieu shall be computed as:
Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)
The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.
4.13.4 Ledger. The Authority shall keep a public ledger of:
- detention volume credited to each regional facility;
- volume delivered; and
- fees received and spent.
Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.
Chhattisgarh has no tank or lake Act, and no talab, lake or reservoir in its cities was found to be operated for flood control under a documented rule [TBC]. Village tanks over which the community exercised rights of irrigation or nistar have vested in the State since 6 April 1959 (Chhattisgarh Land Revenue Code 1959, section 251), and encroachment on them is proceeded against as unauthorised occupation (section 248): after the NGT ordered the Collector to remove encroachments from ponds recorded in the revenue record at Baloda (order of 14 November 2024 in O.A. 78/2024), the Tahsildar began proceedings under that section. Public tanks vest in the Municipal Corporation under the Municipal Corporation Act 1956, but the same Act, in its Madhya Pradesh text, also lets the Commissioner require a private tank to be filled or drained (sections 82 and 202, as adapted in Chhattisgarh [TBC]), so a private talab can be lost by order, and this Manual prefers desilting and inlet screening to filling. Raipur is a city of talabs: about 130 ponds were reported in 2001 and about 37–40 remain, over about 69 ha, all of them reported in 2015 to be "polluted and heavily silted" (as reported). The State Wetland Authority ordered all the water bodies of Raipur district surveyed on 8 May 2023, but only Karbala Talab is reported to have been surveyed (as reported). Nava Raipur Atal Nagar was planned round a network of natural reservoirs, among them the Sendh, Jhanjh and Khandawa lakes, fed by storm-water channels and parks, and its development plan asks that storm water be stored in dug or natural lakes and depressions (Naya Raipur Development Plan-2031, §10.3.2); yet the State Wetland Authority had to direct NRDA to withdraw tenders for plots and residences beside the Jhanjh wetland (3 March 2025, as reported). The State's only Ramsar site is Kopra Jalashay near Bilaspur, 210 ha, a reservoir of WRD built in 1993 whose overflow runs by the Ghonga to the Maniyari and the Seonath, designated on 8 August 2025 according to the Ramsar Information Sheet and announced in December 2025 (as reported). The State's regional storage is of five kinds: the talabs and dabris of the towns and villages, such as Budha Talab and Telibandha in Raipur; the lakes and reservoirs of Nava Raipur; the dams, reservoirs and barrages of WRD, among them Ravishankar Sagar (Gangrel), Minimata Bango and the Hasdeo barrage at Darri, Kharang, Maniyari, Kelo, Kumhari and Pendrawan, the Arpa Bhaisajhar and Mongra barrages and the barrages on the Mahanadi; the voids and pit lakes of the coalfields and the ash ponds of the power stations; and the river floodplains. Four points follow:
- A talab on the record may not be a working talab. No inventory of the talabs within RMC or the other Municipal Corporations, with their beds, bunds and outlets, was found [TBC]. A talab is credited only after a survey shows its bed, bund and outlet, and only for the storage above its full level.
- The reservoirs and barrages are not spare capacity for a site. They are held for irrigation, supply and industry through the monsoon, so their storage below full level is not credited (Clause 4.13.2(c)); their releases are set by WRD for the whole basin, as when Gangrel opened all 14 gates in September 2026 (as reported); and the Hirakud reservoir, whose backwater reaches Raigarh and Sarangarh, is operated by Odisha, and was opened at Chhattisgarh's request in August 2020 and September 2024 (as reported). Storm water spilled to a reservoir or barrage pond, or to a river below one, uses capacity that is operated for the whole basin; it can be relied on only with the written agreement of WRD for a stated flow and level.
- A mine void, pit lake or ash pond is not regional storage. A void can attenuate runoff, but water raised against an unstable high wall or into old workings is a hazard, and the lessee and DGMS control it; an ash pond is held behind a dyke whose breaches at Korba in 2024–2026 sent ash slurry onto fields and into the Hasdeo (as reported). Either is used only with the written consent of the lessee and DGMS, or of the operator for an ash pond, and with its water level, spill level and spill path surveyed (Clause 5.8.5(e)), and it is never assumed to have free storage.
- No rule dividing natural nalas from municipal drains was found [TBC]. Until one is made, this Manual treats rivers, dams, reservoirs, barrages and canals as WRD's; the nalas, drains and public tanks within the limits of a Municipal Corporation, Nagar Palika Parishad or Nagar Panchayat as that body's; the roads, drains and lakes of Nava Raipur as NRDA's; the drains of the Bhilai Steel Plant township as SAIL's; village tanks vested under section 251 as the Collector's; mine drains, voids and pit lakes as the lessee's and ash ponds and dykes as the power company's; and Kopra Jalashay and any wetland the State Wetland Authority treats as protected as within that Authority's remit (Commentary to Clause 6.9). This is the Manual's working assignment, not a statutory one.
The first point is the basis of condition 4.13.2(c) in Chhattisgarh. A talab gives flood storage only above its full level, unless a notified operating rule commits it to be lowered before the SW monsoon. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.
4.14 Simplified methods for small sites
4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.
4.14.2 Method.
- Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
- Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
- Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
- Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
- Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
- Complete Form 4-2 (Tier B site sheet).
Table 4.3 — Tier B permissible site discharge and site storage requirement (template)
| Zone (Annex 2A) | HSG | Imperviousness | PSD 2-yr (L/s/ha) | PSD 100-yr (L/s/ha), standard | PSD 100-yr (L/s/ha), flood-sensitive | SSR (m³/ha), standard | SSR (m³/ha), flood-sensitive |
|---|---|---|---|---|---|---|---|
| CG-Z1 Mahanadi plain: CG-A Raipur–Durg–Bhilai–Rajnandgaon plain (Seonath–Kharun, limestone) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| CG-Z1 Mahanadi plain: CG-B Bilaspur–Mungeli–Kawardha (Arpa–Maniari–Hamp) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| CG-Z1 Mahanadi plain: CG-C Korba–Janjgir–Champa–Raigarh (Hasdeo–Mand–Kelo coalfields) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| CG-Z1 Mahanadi plain: CG-D South-east plain (Dhamtari–Mahasamund–Gariaband–Rajim) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| CG-Z2 Bastar plateau: CG-E Bastar plateau and Godavari frontage | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| CG-Z3 Northern hills: CG-F Northern hills (Surguja–Koriya–Jashpur) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
Worked example (illustrative — not design values).
A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:
- PSD 100-yr = 356 / 2.0 = 178 L/s/ha
- SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
- PSD 2-yr ≈ 17 L/s/ha
Then:
- Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
- 100-yr release: 178 × 0.4 = 71 L/s.
- 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
- Layout options:
- a 400 m² underground tank 1.5 m deep; or
- 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
- Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
- RWH sumps are additional, and are assumed full (Clause 4.11).
Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.
4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:
- (a) the site counts tank or waterbody storage in its design (Chapter 7);
- (b) any part of the site lies within a waterbody setback (Chapter 7); or
- (c) the site drains to a tank cascade whose storage is counted in a downstream design.
The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.
4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:
Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A
where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.
Table 4.3A — Fixed release coefficients (provisional)
| Hydrologic soil group | C_10 | C_2 |
|---|---|---|
| A (sandy, well drained) | 0.05 | 0.02 |
| B | 0.08 | 0.03 |
| C | 0.15 | 0.08 |
| D (clay, poorly drained) | 0.25 | 0.15 |
Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).
4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):
V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]
V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]
where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).
4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.
4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.
Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).
Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the Chhattisgarh plain, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.
The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.
4.15 Safety, fencing and multi-use
4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):
- (a) maximum depth in the 10% AEP storm: 0.45 m;
- (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
- (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
- (d) no vertical drop greater than 0.3 m within the storage area or at its edge.
4.15.2 Wet basins. Permanent pools shall have:
- a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
- an emergent planting fringe that deters entry.
4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:
- has a vertical wall or headwall drop greater than 0.6 m;
- exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
- contains an outlet structure with an opening larger than 300 mm that is not grated.
4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.
4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Hindi and English stating that the area floods during rain, and a depth marker at the deepest point.
4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.
4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.
Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.
4.16 Basis: why peak matching alone fails
Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.
- Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
- Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
- Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
- Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
- Closed outfalls. In Chhattisgarh, the governing failure is volume with no outlet when a river, reservoir or talab downstream is high, and on the plain it lasts. Raipur drains to the Kharun, which on 29 August 2020 set a new highest level of 281.68 m at Pathardihi and stayed above its previous highest level for about 46 hours, while the Mahanadi at Kalma stayed above its previous highest level for about 110 hours (CWC, as transcribed by SANDRP); and in Chaubey Colony five ponds overflowed into homes on 4–5 July 2026 (as reported). The cities below dams and barrages drain to rivers whose levels are set by releases: Korba to the Hasdeo, when Bango released about 30,000 cusecs through six gates and the Darri barrage about 20,000 cusecs on 24–26 August 2024 and houses in the town were flooded (as reported); Dhamtari, Rajim and the villages along the Mahanadi to the river below Gangrel, which released about 55,000 cusecs through eight gates in early October 2025 and opened all 14 gates on 24–27 September 2026 (as reported); and Bilaspur to the Arpa below the Bhaisajhar barrage. Jagdalpur drains to the Indravati, which stood above its danger level of 540.80 m from 29 July to 8 August 2019 (CWC) and reached 544.891 m on 26 September 2026 (as reported), with dams upstream in Odisha. The low outfalls of Raigarh and Sarangarh lie within reach of the backwater of the Hirakud reservoir in Odisha, whose gates were opened at Chhattisgarh's request in August 2020 and September 2024 (as reported). No hourly record of how long a river, reservoir or talab in Chhattisgarh stays above a city's outfalls was obtained [TBC], and no document was found that sets a design river level for an outfall; Chapter 5 sets the design level and the closure to be assumed. A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.
The response in this Manual is layered:
- release below pre-development (Clause 4.5);
- retain the frequent storms (Clause 4.4);
- route long SW monsoon storms (Clause 4.6.3);
- prefer regional storage in the talab system (Clause 4.13); and
- check downstream and at the outfall (Chapter 5).
Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.
4.17 Submittal requirements
Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:
- the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
- the evidence for the order of measures under Clause 4.3.1;
- the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
- the retention credit computation (Clause 4.4.6);
- the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
- a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
- stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
- the drawdown calculation (Clause 4.7);
- outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
- the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
- the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
- the design groundwater level and flotation check (Clause 4.12);
- the downstream and tailwater report (Chapter 5, Form 5-1); and
- the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).
Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.
References (chapter)
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01 (approved 10 Dec 2025). https://kcmetro.apwa.org/wp-content/uploads/sites/23/2026/01/APWA-Section-5600_Storm-Drainage-Systems-Facilities.pdf
- Mid-America Regional Council (2025). APWA 5600 Stormwater Standards Policy Supplement (7 Nov 2025); APWA 5600 Manual factsheet. https://www.marc.org/document/apwa-stormwater-standards-supplement ; https://www.marc.org/document/apwa-5600-manual-factsheet
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.8, 5608.4). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- MARC / APWA (2012). Manual of Best Management Practices for Stormwater Quality. https://www.marc.org/sites/default/files/2022-05/Best_Management_Practices_for_Stormwater_Quality.pdf
- MARC. The Evolution of Regional Stormwater Design Standards (presentation; McEnroe 2005 results). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Volume 1. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- Urban Drainage and Flood Control District (now MHFD) (2012). Full Spectrum Detention Release Rate Memorandum. https://mhfd.specialdistrict.org/files/23cb85ce8/UDFCD_Full_Spectrum_Detention_Release_Rate_Memorandum.pdf
- Mile High Flood District. Urban Storm Drainage Criteria Manual, Volume 2 (Storage).
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- PUB Singapore (2024). On-site Detention Tank Technical Guide, Rev. 3; Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3 (16 Apr 2025). https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- Sydney Water (2020). On-site Stormwater Detention Guide (SW201). https://www.sydneywater.com.au/content/dam/sydneywater/documents/on-site-stormwater-detention-guide.pdf
- Upper Parramatta River Catchment Trust (2005). On-site Stormwater Detention Handbook, 4th ed.
- "On-site stormwater detention for Australian development projects: does it meet frequent flow management objectives?" Water Science and Engineering (2019). https://www.sciencedirect.com/science/article/pii/S1674237019300213
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Chhattisgarh Land Revenue Code, 1959, sections 237, 248 and 251 (Hindi text from a third-party copy). https://vidhijudicial.com/धारा-233-से-254-अध्याय-18-छत्तीसगढ़-भू-राजस्व-संहिता,-1959.html
- National Green Tribunal, Central Zone. O.A. 78/2024, Jagdish Prasad Devangan v. State of Chhattisgarh: order of 14 November 2024 and the factual and action-taken report of the District Magistrate, Janjgir-Champa (ponds of Nagar Panchayat Baloda; proceedings under section 248). https://www.greentribunal.gov.in/sites/default/files/news_updates/13.1.25%20OA%2078-24-REPORT.pdf
- Ramsar Convention. Ramsar Information Sheet, Kopra Jalashay (site 2583). https://rsis.ramsar.org/RISapp/files/RISrep/IN2583RIS_2512_en.pdf
- Reports on the State Wetland Authority's actions at Karbala Talab and Narhaiya Talab in Raipur and at the Jhanjh wetland in Nava Raipur (The Hitavada, 4 March, 27 July and 12 October 2025). https://www.thehitavada.com/Encyc/2025/3/4/CGSWA-intervenes-directs-NRANVP-to-withdraw-Jhanjh-Wetland-tenders.html ; https://www.thehitavada.com/Encyc/2025/7/27/toy-train-plan-in-narhaiya-talab-buffer-sparks-probe-by-cswa.html ; https://www.thehitavada.com/Encyc/2025/10/12/wetland-authority-halts-rs-15-cr-work-at-karbala-talab-over-rule-violations.html
- Reports and a study on the lakes of Raipur (Down To Earth, 2015; India Water Portal). https://www.downtoearth.org.in/coverage/in-srinagars-footsteps-48224 ; https://oldiwp.indiawaterportal.org/sites/default/files/iwp2/ninad_bodhankar_study_on_lakes_in_raipur.pdf
- Naya Raipur Development Authority (2008). Naya Raipur Development Plan-2031, Chapter 10, §10.3.2 (storage of storm water in lakes and depressions) (read from the Internet Archive copy of nayaraipur.gov.in).
- Water Resources Department, Government of Chhattisgarh. Daily tank gauge report of 10 October 2024. https://cgwrd.in/phocadownload/userupload/eedd4/Tank%20Gauge%2010-10-2024.pdf
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A (§8.5).
- Housing and Environment Department, Government of Chhattisgarh. Amendments to the Chhattisgarh Bhumi Vikas Niyam 1984 under section 85(1) read with section 24(3) of the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973: No. एफ 7-26/32/2008 of 17 December 2008 (integrated townships, Appendix ण); No. 318/1193/32/2006 of 17 February 2009, Gazette p. 124(10) (rule 78(4), Appendices ढ-2 and ढ-4); draft No. F 7-15/2016/32 of 30 March 2017 (draft rules 79-C to 79-G); No. F 7-27/2017/32 of 6 October 2018 (rules 73(3)(क) and 96, Appendix Q); and No. F 07-24/2019/32 of 29 April 2020 (read from Internet Archive copies of tcp.cg.gov.in). http://tcp.cg.gov.in:80/Circular/Bhoomi_Vikas_Niyam%20_1984_Amendment/dt-17-12-2008.PDF ; https://tcp.cg.gov.in/Circular/Bhoomi_Vikas_Niyam%20_1984_Amendment/Image0004.PDF ; https://tcp.cg.gov.in/Circular/Bhoomi_Vikas_Niyam%20_1984_Amendment/cg-BVN-amendment-6-10-2018.pdf ; https://tcp.cg.gov.in/Circular/Bhoomi_Vikas_Niyam%20_1984_Amendment/BVN-1984%20Amendment_29-4-20.pdf
- Summaries of the draft amendments of 12 September and 1 December 2025 (RULE/170/2025-HOUSING) and of the reclassification of land uses of October 2026 (TeamLease RegTech; Drishti; texts not read).
- Madhya Pradesh Bhumi Vikas Rules, 1984, rules 17, 50 and 51 (the inherited text, from a third-party copy; the Chhattisgarh text not read [TBC]). https://www.legitquest.com/act/madhya-pradesh-bhumi-vikas-rules-1984/D2B8
- Housing and Environment Department, Government of Chhattisgarh. Letter No. 2940/1445/32/2009 of 23 November 2009 on rainwater harvesting in government offices and housing (rule 78(4)). http://tcp.cg.gov.in:80/Circular/Circular/Final%20Circular/Rainwater%20Harvesting.pdf
- General Administration Department, Government of Chhattisgarh. Order No. F 9-22/2016/1/5, Naya Raipur, 31 May 2016 (rainwater harvesting in government buildings). http://tcp.cg.gov.in:80/Circular/General/rainwater%20harvesting.pdf
- Directorate of Town and Country Planning, Chhattisgarh. Letter No. 2507/नग्रानि/09 of 30 November 2009 (basements); report format No. 1680/TCR-2/नग्रानि./2011 of 23 June 2011 (rule 50); checklist No. 1569/स्टेनो/नग्रानि./2011 (WRD high flood point) (read from Internet Archive copies of tcp.cg.gov.in).
- Chhattisgarh regularisation of unauthorised development Act, 2002, section 7(1)(चार), Chhattisgarh Rajpatra of 26 April 2002 (read from the Internet Archive copy of tcp.cg.gov.in).
- Rajya Sabha. Reply of 8 July 2019 on rainwater harvesting (rule 78(4) of the Chhattisgarh Bhumi Vikas Niyam 1984; seen in a search summary).
- Chhattisgarh Ground Water (Management and Regulation) Act, 2022, sections 1(3), 2(u), 7 and 21. https://cgwrd.in/water-allotment-system/docs/20220712_Ground%20Water%20Act_English.pdf
- Central Ground Water Board (2024). Dynamic Ground Water Resources of Chhattisgarh, 2024, and factsheet of December 2024; district brochures for Raipur, Durg and Rajnandgaon.
- Naya Raipur Development Authority (2008). Naya Raipur Development Plan-2031, §10.3 (Storm Water Drainage) and Chapters 7–9 (road drainage) (read from Internet Archive copies of nayaraipur.gov.in).
- Raipur Municipal Corporation (2015). Sector-wise SLIP template: Storm Water Drainage (AMRUT), 4 November 2015 (read from the Internet Archive copy of nagarnigamraipur.nic.in).
- Comptroller and Auditor General of India. Audit Report on Performance and Compliance Audit for the year ended 31 March 2022, Government of Chhattisgarh, Chapter II, Implementation of AMRUT. https://cag.gov.in/uploads/download_audit_report/2022/9_Chapter_II-0687a1a6b75cdf5.10923258.pdf
- Chhattisgarh Environment Conservation Board. Report in NGT O.A. 593/2017, including the monthly progress report of January 2021 in O.A. 673/2018 (sewerage and treatment plants). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20CHHATTISGARH%20ENVIRONMENT%20CONSERVATION%20BOARD%20IN%20OA%20NO.%20593%20of%202017%20(PARYAVARAN%20SURAKSHA%20SAMITI%20&%20ANR.%20VS%20U.O.I.%20&%20ORS).pdf
- Ministry of Environment, Forest and Climate Change. Environmental clearance of 13 August 2024 for a coal mine (File No. J-11015/72/2016-IA.II(M)), used as the standard text of the coal-sector conditions on garland drains and settling sumps. https://mahagenco.in/Content/File_pdf/EnvClearance/2.EC_Gare%20Palma%20Sector%20II%20Coal%20Mine%20Project_13.08.2024.pdf
- Coal Mines Regulations, 2017, regulation 149, Danger from surface water (cited from search snippets; the Gazette text was not read) [TBC].
- Central Water Commission (2009). National Register of Large Dams (Chhattisgarh; spillway capacities) (read from the Internet Archive copy).
- India Meteorological Department (2015). Climate of Chhattisgarh (heaviest rainfall in 24 hours by district). https://imdpune.gov.in/library/public/Climate%20of%20%20Chhattisgarh.pdf
- Reports on Raipur's nalas and the Kharun (YourStory, 2017), on rainwater harvesting pits in Raipur (2016), on the Raipur floods of June 2007 and July 2026, on Bilaspur in September 2025 and July 2026, on the drains of the Bhilai Steel Plant township (July 2025), on the NGT's order on Durg's nalas of 16 January 2026, on the Bango and Darri releases of August 2024, on the Kelo at Raigarh in August 2019, on the Hirakud backwater, on the ash-dyke breaches at Korba in 2024–2026 (SANDRP; The Hitavada) and on the flood of September 2026. https://yourstory.com/2017/02/kharun-river-raipur/ ; https://indiaenvironmentportal.org.in/news-clippings/18-builders-7-industrial-units-in-raipur-district-to-face-action ; https://www.oneindia.com/2007/06/30/flood-hits-chhattisgarh-capital-6000-people-evacuated-1183210857.html ; https://www.thehitavada.com/Encyc/2026/7/6/heavy-monsoon-spell-exposes-civic-flaws-waterlogging-disrupts-traffic-sewage-enters-homes.html ; https://www.thehitavada.com/Encyc/2025/9/5/rain-exposes-bilaspurs-smart-city-claims.html ; https://www.thehitavada.com/Encyc/2025/7/13/Commissioner-issues-warning-to-BSP-over-poor-drain-cleaning-in-Township.html ; https://www.downtoearth.org.in/environment/daily-court-digest-major-environment-orders-january-20-2026 ; https://www.thehitavada.com/Encyc/2024/8/26/Hasdeo-Bango-Dam-projectin-Korba-put-on-high-alert.html ; https://business-standard.com/article/news-ani/kelo-river-overflows-in-raigarh-following-incessant-rainfall-119081401553_1.html ; https://dailypioneer.com/india/chhattisgarh-floods-eight-killed-16000-rescued
- Bureau of Indian Standards. IS 456:2000 Plain and Reinforced Concrete — Code of Practice.
- Government of India. Dam Safety Act, 2021.
- Chow, V.T., Maidment, D.R. and Mays, L.W. (1988). Applied Hydrology. McGraw-Hill (AMC conversion).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 4A | Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map |
| 4B | Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A) |
| 4C | Worked example (Tier A) with full routing tables |
| Form 4-1 | Site Runoff Control Report |
| Form 4-2 | Tier B Site Sheet |
| Form 4-3 | Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7) |
Commentary. No Indian national rule or Chhattisgarh rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". The building rules are the Chhattisgarh Bhumi Vikas Niyam 1984 (CGBVN 1984), the rules of 1984 that the State inherited from Madhya Pradesh in 2000, retitled and amended since by the Housing and Environment Department under section 85(1) read with section 24(3) of the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973. Unlike Madhya Pradesh, which replaced its rules in 2012, Chhattisgarh has kept and amended the 1984 rules: among the amendments read are those of 17 December 2008 (No. एफ 7-26/32/2008, integrated townships), 17 February 2009 (No. 318/1193/32/2006, which amends the rainwater harvesting rule, Commentary to Clause 4.11), 6 October 2018 (No. F 7-27/2017/32) and 29 April 2020 (No. F 07-24/2019/32), and a draft of 30 March 2017 (No. F 7-15/2016/32) on green buildings; drafts of 12 September and 1 December 2025 and a reclassification of land uses in October 2026 are reported but were not read [TBC]. No consolidated Chhattisgarh text of the rules was found, so the rules on definitions, site suitability (Rule 50), drains (Rule 51), plinth and basements were not read in their Chhattisgarh form [TBC]. None of the amendments read touches drainage, site levels or water bodies, apart from the forms of 2018. The drainage provisions that can be traced protect the building, the drain and the site, not the catchment. Rule 50 is still the State's rule on the unsuitability of a site: the T&CP Directorate's report format of 2011 asks whether a site is unsuitable under it, whether the land is a waterlogging area, and whether it lies beside a canal, nala or river and at what distance, and records the area left for nalas (letter No. 1680/TCR-2/नग्रानि./2011 of 23 June 2011). The inherited 1984 text of that rule bars building within 9 m of the highest water mark and, along a major watercourse, within "9 meters from average high flood mark or 15 meters from the defined boundary of water course, whichever is more" (r.50(b)), and on a site that is not properly drained or is incapable of being well drained (r.50(f)), while r.51 requires land within the curtilage to be "effectively drained by surface water drain or other means" if the Authority so requires; whether the Chhattisgarh text keeps these words and distances is to be confirmed [TBC]. The Directorate's checklist of 2011 asks, for land next to a nala, canal or river, for the no-objection of WRD or the Revenue Department and for "the high flood point" from WRD (No. 1569/स्टेनो/नग्रानि./2011), the only flood level found in the State's planning process. The amendment of 2018 added a plinth certificate (Rule 96), whose form checks location, setbacks and deviations but no level, and inspection forms that ask whether a "Nalah (Major Drain)" is adjacent to the plot and how far it is, "in rule" of the CGBVN 1984 with the rule number left blank, whether rainwater harvesting is installed "as per rule", and whether the drainage line is connected "up to final diposal" (Appendix Q). Integrated townships may not be sited on the bank of a perennial river or in an ecologically sensitive area (Appendix ण, 2008), and water sources are left out of their area (draft of 4 October 2018); and no unauthorised construction on the bed or edge of a reservoir or on a natural drain may be regularised (Chhattisgarh regularisation Act of 2002, section 7(1)(चार)). The draft green-building rule of 2017 would have asked for a reduction of hardscape on larger plots and an unpaved area of at least 20% of the recreational open space (draft rule 79-C); its final text was not found [TBC]. The Municipal Corporation Act 1956 and the Municipalities Act 1961, as adapted in Chhattisgarh, were not read in their Chhattisgarh form; their drainage and tank sections are cited from the Madhya Pradesh text of the same Acts (sections 82, 198, 203 and 204 of the 1956 Act), and their numbering in Chhattisgarh is to be confirmed [TBC]. None of these sets a design storm, a release rate, a storage volume or an overflow path, and no drainage design standard of UADD, T&CP or any Municipal Corporation stating a return period was found. The only explicit urban design storm in the State is in a city plan: the Naya Raipur Development Plan-2031 says that "5 years Maximum rainfall intensity should be taken for design of system", asks for river embankments "safe against 100 yrs frequency flood", road levels "at least 0.5 to 1.0 m above the observed high flood level" and road drainage to IRC: SP-50, and gives a chart of rainfall intensity against time of concentration for 2, 5, 10 and 50 years from IMD data for Raipur, with no equation or record length (§10.3, §10.3.1.1 and Chapters 7–9); it binds Nava Raipur only and is not a State standard. Raipur's drainage plan under AMRUT (2015) proposed ₹1,191 crore of works with no return period, intensity or runoff coefficient, and the CAG's audit of AMRUT in Chhattisgarh, for the years to March 2022, covers water supply, sewerage and parks and never mentions drains (Commentary to Clause 4.5). This Manual uses none of these values; its design storms come from Chapter 2. Basements are regulated, but not for flooding. The amendment of 2018 lets a basement be approved after a clear margin of 3 m from the plot boundary for a building up to 18 m high and 6 m above that (Rule 73(3)(क)), and in 2009 the Directorate required its own approval for basements below 10,000 sq ft because basement space was being misused; no Chhattisgarh rule restricts basements in low-lying or flood-prone land, sets a level for a basement ramp or opening, or keeps surface water out of a basement [TBC]. This Manual therefore adds its own requirements for every basement: no detention storage in a habitable basement (Clause 4.10.1); the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4); and no basement in Zone 2 (Clause 7.5.2). In the flood-sensitive catchments of Clause 4.5.3.2, in any catchment notified under Clause 4.5.4 and on the paddy lowlands, floodplains and backwater land of Clause 4.12.1, it recommends that no basement be permitted where the 1% AEP flood level stands above the surrounding ground; these are the Manual's proposals, not rules of the CGBVN 1984. Mine land is a drainage regime of its own. Mine drains are governed by the conditions of each environmental clearance and by DGMS, under whose Coal Mines Regulations 2017 the lowest point at which surface water could enter a mine is to stand at least 1.5 m above the highest flood level (regulation 149, as reported [TBC]); the coal-sector clearances size garland drains with "at least 50% safety margin over and above the peak sudden rainfall and maximum discharge", which is not a return period (standard coal-sector conditions, as read); mine dewatering round Korba draws the water table down over about 1.2 km from the Kusmunda and Gevra pits (as reported); and the ash dykes of the power stations at Korba have breached, at NTPC's Dhanras dyke in July 2024, at CSPGCL's Korba West dyke on 19 April 2026, with one death, and at BALCO's ash dam, whose slurry reached a nala and the Hasdeo (as reported). For any development on or beside mine land, an overburden dump or an ash pond this Manual therefore requires that: no development drain or overflow path discharges into an active mine; runoff from an overburden dump, an ash pond or dyke or other mine-disturbed ground passes through a sediment basin (Chapter 8) and a stable toe drain at the foot of the dump or dyke before it reaches any urban drain or outfall; overburden dumps, mine-disturbed ground and ash ponds are HSG D with no infiltration credit (Clause 3.7.2); a mine void or pit lake is not used as an outfall or as storage unless the lessee and DGMS agree in writing and its water level, spill level and spill path are surveyed, and an ash pond only with the operator's consent and a check of the dyke (Clause 5.8.5(e)); and the path of an ash-dyke breach is a hazard to be mapped, not a design inflow. These are the Manual's requirements, not conditions of any clearance. This chapter is written so that it can supply, as a technical companion to the CGBVN 1984 and the Municipal Acts, the design storm, release rates and storage volumes that they leave open; it has not been adopted for either purpose. In practice most city nalas in Chhattisgarh carry sewage: in January 2021 the State's pollution control board reported that only Bilaspur had a sewerage system, while Raipur's new treatment plants were to take the flow of its nalas through diversion weirs (CECB, report to the NGT), Raipur's sewage is reported to reach the Kharun "through eight big canals", and the NGT has ordered the plants on Durg's Shankar and Pulgaon nalas finished within six months (16 January 2026, as reported) (Clause 8.9). Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.