Meghalaya Stormwater Design Manual

About this draft

Status. This is Draft v1.0 of the Meghalaya Stormwater Design Manual. It was prepared by Neer as a proposed stormwater design standard for Meghalaya.

Not adopted. This Manual has not been adopted, notified or endorsed by the Government of Meghalaya, by its Governor, its Council of Ministers or its Legislative Assembly, or by any of its departments, local bodies or agencies. In particular, it has not been adopted, notified or endorsed by the Urban Affairs Department, the Meghalaya Urban Development Authority (MUDA), the Shillong Municipal Board (SMB) or the Tura, Jowai, Williamnagar, Resubelpara or Baghmara Municipal Boards, the Shillong Cantonment Board, Shillong Smart City Ltd, the New Shillong Township Development Authority (NSTDA), any Town Committee, or any other agency. Nor has it been adopted, notified or endorsed by the Khasi Hills, Jaintia Hills or Garo Hills Autonomous District Councils (KHADC, JHADC and GHADC), by any building authority of a District Council, such as the Khasi Hills Building and Structure Regulatory Authority (KHBSRA), or by any Dorbar Shnong, Rangbah Shnong, Nokma or other traditional institution. Where it names a body, such as the Water Resources Department, the Public Health Engineering Department (PHED), the Public Works Department (PWD), the Soil and Water Conservation Department, the Forest and Environment Department, the Revenue and Disaster Management Department, the Meghalaya State Pollution Control Board (MSPCB), the Meghalaya State Disaster Management Authority (MSDMA), the Meghalaya Basin Development Authority (MBDA), the Meghalaya State Wetlands Authority, the Flood Zoning Authority under the Meghalaya Flood Plain Zoning Act, 2026 (when it is constituted), the Meghalaya Energy Corporation Ltd (MeECL) or the Meghalaya Power Generation Corporation Ltd (MePGCL), a Deputy Commissioner or a district administration, the High Court of Meghalaya, the National Green Tribunal (NGT) or the Supreme Court, or a body of the Union, such as the Central Water Commission (CWC), the India Meteorological Department (IMD), the Central Ground Water Board (CGWB), the Central Pollution Control Board (CPCB), the North Eastern Space Applications Centre (NESAC), the National Highways Authority of India (NHAI) or the Ministry of Environment, Forest and Climate Change (MoEF&CC), or a research body such as Integrated Research and Action for Development (IRADe), it describes the role that body would have if the Manual were adopted. It does not say the body has agreed to that role. Citing a body's document does not make this Manual that body's document.

No legal force. Until a competent authority adopts it, with or without changes, this Manual has no legal force. Until then, the Meghalaya Building Bye-Laws 2021 as amended (the Bye-Laws 2021), the Meghalaya Town and Country Planning Act, 1973 (the MTCP Act), the Khasi Hills Autonomous District (Land Development and Building) Regulation, 2015 and the instruments of the other District Councils, the Town Committee Acts, the Meghalaya Municipal Act, 1973, the Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023 as amended (the Waterbodies Guidelines), the Meghalaya Flood Plain Zoning Act, 2026, the Shillong Master Plan 2041 and the other master plans, drainage schemes, orders of courts and tribunals and approval conditions in force continue to apply.

Meghalaya and the Sixth Schedule. Almost the whole State lies in three autonomous districts under the Sixth Schedule to the Constitution, and the power to regulate building and land is divided by area. The Bye-Laws 2021 apply to "all the Master Plan Areas, Municipal areas and Scheme Areas within the State", and name the "Authority" as "the Meghalaya Urban Development Authority / Autonomous District Councils as applicable". In those areas MUDA grants building permission and the Municipal Boards keep their own drains under the Municipal Act; the Shillong Cantonment Board acts in the Cantonment. Outside them, building and land are regulated by the District Councils, through the KHADC's Regulation of 2015 in the Khasi Hills, with permissions issued by the KHBSRA since 2020, as reported; the building instruments of the JHADC and the GHADC were not found [TBC]. Town Committees, Dorbar Shnongs and other traditional institutions act under the District Councils' rules. The CAG found that the Town Committees and census towns, "47 per cent of the total urban population", are "governed by the concerned ADCs" and not by the Urban Affairs Department, so nearly half of the urban population lies outside the reach of the Bye-Laws 2021. Who regulates where is disputed: the KHADC's Executive Committee rejected the Bye-Laws 2021 in October 2021 for encroaching on the Sixth Schedule areas, as reported, and its present position is not known [TBC]; this Manual states the dispute and takes no side. This Manual therefore names its "competent authority" by area, as Chapter 1 sets out. The Urban Affairs Department could make it a condition under the Bye-Laws 2021 by an amendment under section 74 of the MTCP Act; a District Council's Executive Committee could adopt it for its district by amending its own building regulation, as the KHADC made its Regulation of 2015; a Municipal Board could adopt parts of it as bye-laws; the Flood Zoning Authority, once constituted, could use its corridor maps; and the Forest and Environment Department could align the setbacks of the Waterbodies Guidelines with it. None has done so, and the Manual can reach an autonomous district only through its District Council. Most land in the State is held by communities, clans or private owners, not by the State, so this Manual secures drainage corridors and easements by agreement with the landholding institution (a Dorbar Shnong, a clan or an owner) where they are not State land, or reserves them in a master plan; it does not assume that land can be taken. The paragraphs of the Sixth Schedule were not read for this Manual and are not quoted; the division is described by its effect, from the Bye-Laws 2021, the KHADC's Regulation and the CAG's audit.

Names. Some places, rivers and gauges have more than one name or spelling in statutes, sources and on IMD and CWC stations:

  • Cherrapunji, Cherrapunjee and Sohra are the same place. IMD's station, with its record of 1,563.0 mm in 24 hours on 16 June 1995, is "Cherrapunji" (index 42515, rainfall data 1902–2012); the daily rainfall map of IMD's Meteorological Centre Shillong shows two gauges there, "Sohra" and "RKM Sohra". This Manual writes Sohra for the town and Cherrapunji for IMD's station and for the curve of IMD's national rainfall study (Das et al., 2022) that bears its name. Press reports give the 1995 fall as 1,563.3 mm; this Manual uses IMD's 1,563.0 mm;
  • Shillong (C.S.O.) (index 42516, rainfall data 1957–2012) is the Shillong station in IMD's tables of extremes, with a record of 273.2 mm in 24 hours on 25 June 1988. The CWC flood estimation report for subzone 2(b) prints Shillong (Obsy) and Upper Shillong as separate ordinary rain gauges, each with a fall of more than 400 mm on 20 June 1934, and a Shillong self-recording gauge, with 347 mm on 14–15 September 1960. They need not be one gauge, and the 347 mm, which falls inside IMD's period of record but exceeds IMD's maximum, is not used until the two are reconciled [TBC]. This Manual names the gauge each figure comes from;
  • CWC's flood estimation reports divide the State between two subzones. The plateau, the northern foothills and the Garo hills are in subzone 2(b), South Brahmaputra, whose revised report (No. SB-2(b)/R-4/44/99, March 2000) describes its area as "large parts of Assam and areas of Meghalaya, Nagaland and Arunachal Pradesh"; the southern escarpment facing Bangladesh, with Sohra, Mawsynram, Shella, Pynursla, Dawki and Baghmara, is in subzone 2(c), Barak, for which CWC has never published a report. The boundary on the report's plates runs west to east along the plateau, just south of Shillong and on or just north of Tura, as this Manual reads them. No part of the State is in subzone 2(a), North Brahmaputra, though Chapter 2 uses that report's ratios of short to 24-hour rain on the plateau. These subzones are not the four rainfall zones (ML-Z1 to ML-Z4) and seven hydrologic sub-areas (ML-A, ML-A1, ML-B, ML-B1, ML-C, ML-C1 and ML-D) that this Manual sets in Annex 2A, nor Zones 1 and 2 of a waterbody setback in Chapter 7, nor a "flood zone" under the Flood Plain Zoning Act, 2026, which that Act defines by "the maximum probable floods";
  • the FER for subzone 2(b) and other older sources use the districts of their time, Khasi & Jaintia Hills and Garo Hills, which were divided from the 1970s on. Today the State's districts are taken to be East Khasi Hills, West Khasi Hills, South West Khasi Hills, Eastern West Khasi Hills, Ri Bhoi, West Jaintia Hills, East Jaintia Hills and North, East, West, South and South West Garo Hills; this list was not confirmed against a current notification [TBC], and some sources count 11 districts. The State Language Act of 2005 names the districts of 2005, among them Jaintia Hills. IMD reports Meghalaya with Assam in its "Assam & Meghalaya" meteorological subdivision. A clause that names a district must be checked against the current list;
  • the rivers are spelt in several ways: Umiam is Umium in the FER; Umtru is also Umtrew; Digaru is Digru in the FER; Myntdu is also Myntudu; Jinjiram is also Jingiram; Umngot is also the Wah Umngot; Umkhrah is also the Wah Umkhrah, Umkhra and Wahumkhrah; and Umshyrpi is also the Wah Umshyrpi. Barapani is the Umiam reservoir and its surroundings, and the reservoir is called Umiam lake. The Umkhrah and the Umshyrpi join below Shillong as the Wah Roro (or Roro) before they enter Umiam lake. Nan Polok is the Khasi name of Ward's Lake in Shillong, and Pung Sajar Nangli that of Thadlaskein, near Mukhla in West Jaintia Hills, as reported; these natural, historic and sacred waters keep their own names in this Manual;
  • where a shared clause names the State's main city or its largest local body, this Manual names Shillong, the State capital, and the Shillong Municipal Board (SMB). SMB is a Municipal Board under the Meghalaya Municipal Act, 1973, not a corporation, and its area is only part of Greater Shillong: only parts of the Umkhrah and the Umshyrpi lie in it, and the rest is under the KHADC, as the State told the NGT in 2023; the Cantonment, the census towns, New Shillong and the 54 villages of the Shillong Planning Area lie outside it. The State has six Municipal Boards: Shillong, Tura, Jowai, Williamnagar, Resubelpara and Baghmara;
  • the State has four broad belts. The northern foothills of Ri Bhoi and the Garo Hills fall to the Brahmaputra plains, with valley fills and, on the north-western fringe of the Garo Hills and in the Jinjiram valley, thick alluvium whose water table lies 3–5 m below the ground. The Shillong plateau, of gneiss, quartzite and phyllite under thin red loams, carries Shillong, Mawphlang, Nongstoin, Mairang and, in the Jaintia uplands, Jowai. The southern escarpment drops from the plateau to the plains of Bangladesh over cavernous limestones, sandstones and coal measures; it holds the record-rainfall belt of Sohra and Mawsynram, and in the Jaintia Hills and parts of the Garo Hills it is honeycombed with rat-hole coal workings. The Garo hills to the west, of sandstone and shale, carry Tura and Williamnagar. The names describe regions, not administrative units;
  • many levels in the sources are not in metric or not on a stated datum. MePGCL publishes some reservoir levels in feet (1 ft = 0.3048 m): the full reservoir level of Umiam–Umtru Stage III is 2,230 ft and its maximum water level 2,235 ft, about 679.7 m and 681.2 m; the level of Umiam lake behind the Stage I dam is known only from the press, as "3,220 ft", and on no stated datum [TBC]. Other MePGCL reservoirs are given in metres, such as the full reservoir level of 618.00 m of the Myntdu–Leshka Stage I dam. CWC's levels at its sites in the State, in metres, were read only in transcriptions by SANDRP, such as the highest flood level of 73.47 m for the Umngot at Dawki on 28 May 2006, and no source read states their datum [TBC]. This Manual names the gauge, the unit and the datum with every level; and
  • in this Manual "the monsoon" and "the monsoon season" mean the wet season of 1 April to 31 October. That is not IMD's usage: IMD counts April and May as pre-monsoon months, and the south-west monsoon reaches the State in about the first week of June and withdraws in about mid-October. The Manual's season begins on 1 April because the April and May storms on the escarpment are among the State's largest (Chapter 2).

This Manual uses the first form and keeps the others where a title, a source or a station uses them. Some names of bodies and laws need a word of explanation:

  • the Meghalaya Building Bye-Laws 2021 (the Bye-Laws 2021) are the State's building rules, notified by the Urban Affairs Department under section 74 of the MTCP Act by Notification No. UAU.73/2016/Pt/402 of 9 March 2021 and published in the Gazette of Meghalaya of 25 March 2021. They have been amended at least eight times, from 2024 to May 2026, and the amendments are numbered inconsistently: two instruments are each called "(Amendment)" and two "Second Amendment", and the notification of 15 January 2025 amends "the Meghalaya Building Bye-Law, 2024". This Manual cites each amendment by its notification number and date, and clauses as "the Bye-Laws 2021 (as amended), B1(vii)" or "Section I(a), cl. 3". The earlier bye-laws of 2011 were made by MUDA. MBBL 2016, in Chapters 1 and 10, is the national Model Building Bye-Laws of 2016, not the State's bye-laws;
  • the Meghalaya Town and Country Planning Act, 1973 (the MTCP Act) is the Assam Town and Country Planning Act, 1959 as adapted, as the State's notifications cite it; MUDA is the Authority under it, and the Urban Affairs Department notifies the bye-laws and the master plans. The Shillong Master Plan 2041 (SMP 2041) was notified by No. UAU.76/2022/Pt.I/74 of 27 November 2024, as cited in its amendment of 29 October 2025, and covers a planning area of 288.5 km², with NESAC's Risk Informed GIS Based Master Plan report of May 2023; no "Shillong Master Plan 2035" was found, and this Manual does not cite one. A draft risk-informed master plan for Tura was published for objections on 16 February 2024;
  • the Meghalaya Municipal Act, 1973 is the Assam Municipal Act, 1956 as adapted, amended by the Meghalaya Municipal (Amendment) Act, 2021. It vests "all public streams, channels, water-courses, springs tanks, reservoirs" and the public drains and sewers within municipal limits in the Board (section 62). Its penalties for unauthorised drains are ₹25 and ₹50;
  • the Khasi Hills Autonomous District (Land Development and Building) Regulation, 2015 was made by the KHADC's Executive Committee by Notification No. DC.II/Genl/31/2015/9 of 4 August 2015, under the United Khasi-Jaintia Hills District (Establishment of Town Committee) Act, 1960, and extends to the whole Khasi Hills Autonomous District. It sets a duty to protect "catchment areas, water sources, spring sheds, streams and rivers" (section 15) and makes rainwater harvesting mandatory in all existing and new buildings (section 36). The Bye-Laws 2021 list the three Town Committee Acts, of 1960, 1975 and 1950, among their Acts;
  • the Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023 were issued by the Forest and Environment Department by No. FOR/CC/29/2019/Pt/688 of 25 August 2023, on the High Court's direction in a public interest case on the cleanliness of Umiam lake (PIL 10 of 2019), and amended in February 2024 and July 2026. They are executive guidelines. They bind building permissions under the Bye-Laws 2021, which refer to them since 2024; elsewhere they are to be implemented "in such manner as may be prescribed", and nothing prescribed was found. Their setbacks are measured from "the mean high flood level of a water body observed in the past ten years", and their "waterbody" excludes streams whose bed was dry for at least 240 days in each of the past ten years, which takes in most jhoras (Chapter 7). The High Court's interim bar on building within 50 m of a waterbody (24 May 2023) ended when the case was closed on 19 February 2024; this Manual does not cite it as a rule. The amendment of 2024 dates the Guidelines "18th July, 2023"; this Manual uses the gazetted date, 25 August 2023;
  • the Meghalaya Flood Plain Zoning Act, 2026 provides for a Flood Zoning Authority, surveys, notified flood zones and restrictions that "shall prevail" over other laws. Its Bill was read in the Gazette of 23 February 2026; the Act, as Act No. 4 of 2026 assented to on 6 March 2026, is known only from a search snippet of the State's law site [TBC]. No constitution of the Authority, rules or zone notification was found, and this Manual treats no zone as notified;
  • MSDMA is the State's disaster management authority, under the Revenue and Disaster Management Department; the District Disaster Management Authorities are written in full. The Meghalaya State Wetlands Authority was constituted on 1 November 2017; no wetland notified under Rule 4 of the Wetlands (Conservation and Management) Rules, 2017 and no Ramsar site in the State was found. MBDA runs the State's spring-shed programme;
  • the Water Resources Department holds the rivers and flood works, ran the floodplain zonation study of the Umkhrah and other stretches, and is named in this Manual as the State groundwater agency, through the committees that issue groundwater no-objection certificates; the State has no groundwater Act, and CGWB's North Eastern Region office at Guwahati keeps the observation wells. PHED supplies water and has been the nodal department for sanitation outside municipal areas since 2023. The PWD keeps the State's roads and their drains and culverts, and NHAI and the National Highways and Infrastructure Development Corporation Ltd (NHIDCL) the national highways;
  • MeECL and its generating company MePGCL operate the Umiam–Umtru dams, the New Umtru dam and the Myntdu–Leshka dam (MLHEP); their guidelines for gate operation say that notice of releases is "not practicable" and that warnings go by siren, telephone or SMS;
  • the High Court of Meghalaya (HC) and the NGT have shaped the State's rules on waterbodies, river pollution and mining. The NGT's case on Shillong's rivers (OA 192 of 2022) produced the State's action-taken report of 21 March 2023 that this Manual cites, and its order of 17 April 2014 (OA 73 of 2014) stopped rat-hole mining across the State; the Supreme Court decided the appeals from it on 3 July 2019 (Civil Appeal 10720 of 2018). This Manual cites court and tribunal orders with their status; and
  • Meghalaya has no tehsils. Where a shared clause names a revenue subdivision, this Manual uses the Community and Rural Development (C&RD) block. A district is headed by a Deputy Commissioner (DC). In the Sixth Schedule areas most land records are held by the District Councils, the Dorbar Shnongs and the clans, not by the State's revenue staff (Chapter 7).

Where a shared clause calls for the local language on a sign, a form field or a basin name, this Manual writes "Khasi or Garo". English is the official language of the State and the language of this Manual (Meghalaya State Language Act, 2005, Act 10 of 2005, section 3). Under section 4 of that Act, Khasi is an associate official language in the East Khasi Hills, West Khasi Hills, Jaintia Hills and Ri Bhoi districts, and Garo in the East, West and South Garo Hills districts, as the districts were in 2005. The Meghalaya Official Languages Ordinance, 2026 reportedly makes English, Khasi and Garo official languages and repeals the 2005 Act, while one outlet reports that the associate status is kept; the sources conflict, and the Ordinance was not read [TBC]. So in this Manual "Khasi or Garo" means the language of the district: signs and flood-depth markers are bilingual by district, in Khasi and English in the Khasi and Jaintia Hills districts and in Garo and English in the Garo Hills districts (set by this Manual). Pnar, spoken in the Jaintia Hills, may be added there, though no official status for it was found; if the Ordinance is confirmed to make both languages official across the State, signs may carry all three. Khasi and Garo are both written in the Roman script, so where a shared clause says "script", it means the Roman spelling used in the district.

Some local words are used in the text, and are explained again where they first appear:

  • a pung (Khasi and Pnar: pond, pool or small lake; Garo: pokri) is this Manual's general term for a pond, a pool or a small lake. Singh's Khasi-English Dictionary (1906) gives "Pung, ka, n. a pool" and his English-Khasi Dictionary (1920) gives ka pung first for both "Pond" and "Pool"; the word also names Pung Sajar Nangli. Khasi and Pnar mark the plural with the article ki, not with an ending, so the English plural pungs is a convention of this Manual. The same spelling also means "a joint" (Singh, 1906). The Garo pokri (pond, tank, pool) is a false friend of the Khasi pukri, which means a well. This Manual writes detention pond for engineered storage and never calls a detention basin a sacred or community pung;
  • a nan (Khasi) is a tank, a built store of water, as in Nan Polok; in Pnar it is a small body of still water;
  • wah (Khasi and Pnar) is a stream or river, as in the Wah Umkhrah; um is water, the prefix of many river names (Umiam, Umkhrah, Umshyrpi); and umpohliew (Khasi) is a spring;
  • nur and muri (Khasi) are a channel, ditch or drain, muri also a culvert, and dooid (Pnar) is a drain that carries off rainwater or waste water;
  • chibima (Garo) is a river and chiring (Garo) a brook or stream; chi is water;
  • a law kyntang (Khasi) is a sacred grove, a patch of forest kept by custom; many lie at the heads of perennial streams, as reported;
  • a jhora is a small hill stream, in the local English of Shillong, as reported; it is not in the Khasi dictionaries read, and this Manual glosses it where it first appears in a chapter; and
  • a Dorbar Shnong is the village council of the Khasi and Jaintia Hills and a Rangbah Shnong its headman; the KHADC's rules on solid waste empower the Dorbar Shnong to fine polluters. A Nokma is the head of a Garo village, whose role in land and drainage was not researched for this Manual [TBC].

The dictionary page numbers behind these glosses were estimated from scanned text and are to be checked on the page images [TBC].

Some abbreviations have more than one meaning:

  • AMC is the antecedent moisture condition in Chapters 2 and 3; this Manual does not use it for any municipal body;
  • SMB is the Shillong Municipal Board, a Board and not a corporation. In other editions of this series and in some sources similar letters stand for other bodies; in this Manual SMB means only this one;
  • ADC is an Autonomous District Council: the KHADC, the JHADC or the GHADC. DC is a Deputy Commissioner;
  • "Bye-Laws 2021" is the Meghalaya Building Bye-Laws 2021 as amended, and "MBBL 2016" the national Model Building Bye-Laws 2016. Neither is the building rule of any other State;
  • HFL is the highest flood level recorded at a gauge, as CWC uses it. It is not a design level. The Bye-Laws 2021 use the words "Highest Flood Level" for the line above which a stilt floor on a sloping site must rise (B1(v)(b)), and the KHADC's forms ask for "the highest flood level (HFL) reached above the street"; no HFL has been published for Shillong's streams, and Chapter 7 says how this Manual finds one. No CWC site in the State has a warning level (WL) or a danger level (DL);
  • FRL (full reservoir level), MWL (maximum water level) and MDDL (minimum draw-down level) are used for MePGCL's reservoirs, in feet or metres as each guideline gives them;
  • FPZ is flood plain zoning, under the Flood Plain Zoning Act, 2026; and
  • SWD is a storm water drain.

The sense is clear from the context.

Use with care. Clauses and values may change after review. Designers remain responsible for their designs and for checking the data they use. Neer accepts no liability for decisions made on the basis of this draft.

Disclosure. Neer publishes the India Flood Atlas, a national map of modelled 1% AEP flood depth. Clause 6.11.3 names it as one example of a regional map that an Approving Authority may adopt for floor levels. The Manual does not require the Atlas; any map adopted under Clause 7.3.4 may be used.

Comments. Comments and corrections are welcome at info@neer.ai.

Preface

Meghalaya's towns flood, and fail, for three reasons. June 2022 showed the first, when Mawsynram recorded 1,003.6 mm in the 24 hours to 08:30 on 17 June, a June record in IMD's tables, and IMD found the month's rainfall over Assam and Meghalaya the highest since 1901; the hill towns showed the second, when the rains of 30–31 May 2025 brought landslides near National Highway 6 in Umling block that were linked to hill cutting, as reported; and Shillong shows the third every day, because it has no sewers, and its drains and jhoras carry its sullage into the Umkhrah and the Umshyrpi, which CPCB lists in Priority I of its polluted river stretches.

  1. Rainfall that outruns every national product. The State lies across two CWC subzones, and only one has a report. The revised report for subzone 2(b) (March 2000) covers the plateau, the northern foothills and the Garo hills; its plates give Shillong a 50-year day of about 560 mm, read by eye, which is 1.3 to 2 times every fall recorded at any Shillong gauge: IMD's record of 273.2 mm (25 June 1988), the 347 mm of the report's own self-recording gauge (1960) and the 415 mm and 437 mm of its ordinary gauges (20 June 1934). Its ratio of the 1-hour to the 24-hour rain, 0.48, the highest of any CWC report compared for this Manual, would give Shillong about 269 mm in an hour, 5.6 times the 48 mm that the self-recording gauge recorded in its largest hour. South of the plateau edge, the escarpment facing Bangladesh is in subzone 2(c), for which CWC never published a report, and the 2(b) plates draw no contour west of about 91.8°E. Yet that is where the rain is heaviest: Cherrapunji recorded 1,563.0 mm on 16 June 1995 and 985.5 mm on 13 September 1974, and its 48 hours of 15–16 June 1995, 2,493 mm, are reported as a world record. Its records in IMD's pre-monsoon months are each larger than the 50-year day that the 2(b) plates give anywhere in the Brahmaputra valley: 587.4 mm on 23 March 1994, 644.2 mm on 16 April 1990 and 812.0 mm on 25 May 1916. Sohra and Shillong are about 36 km apart, and their 24-hour records differ by more than five times. IMD's national set of rainfall intensity curves (Das et al., 2022) has a genuine panel for Cherrapunji, but its Shillong panel repeats a curve printed for many other cities, and the gridded rainfall of NIH-DHAARA gives Dawki a 50-year day of 1,423 mm, more than Mawsynram's. No hourly maximum for Cherrapunji or Mawsynram was found in any primary source, and the deaths of 2014 in the Garo Hills, where torrential rain on the night of 21 September was followed by 52 deaths by 28 September, and more than 60 by a later account, as reported, came with no rainfall measurement at all.
  2. Hill towns where water put into slopes, limestone or mine voids moves the ground, and jhoras narrowed by building and garbage that flood the valley floors. Shillong is built on the plateau's thin red loams over gneiss and quartzite, on slopes that the Shillong Master Plan's report divides into a "Regulated Slope" of 40–50° (3.2 km²) and a "Restricted Slope/No Construction Zone" above 50° (0.53 km²); the IRADe plan for Shillong records landslides at Laitumkhrah (2008), Happy Valley (2007), Lawsohtun, Mccabe Road, Bethesda and Arbuthnot, "very high" susceptibility along NH-40 and near the Umshyrpi, and, citing the Revenue and Disaster Management Department, about 22 deaths from landslides in 2014. The great earthquake of 12 June 1897 brought down a landslide at Sohra that is reported to have killed 600 people. On the escarpment and in the Jaintia Hills the ground is cavernous limestone, which CGWB describes as a "discontinuous aquifer in the cavernous limestones", and rat-hole coal workings, into which "smaller streams and rivers either disappear or have become seasonal", as reported; water put into such ground goes to caves and voids, not to an aquifer. In the valleys of Shillong, NESAC found that "Encroachment and clogging of channels are the main causes of flooding over Shillong", that "the water tops the banks along most of the streams", and that Polo Market, Pynthorbah, Nongrim Hills and Dhankheti are "highly potential for flash flood"; under the 15th Finance Commission 49,612 m³ of waste were removed from the Umkhrah. The Bye-Laws 2021 forbid building on slopes above 50° and limit cuts to 3.00 m, but no rule restricts soak pits or recharge on slopes, limestone or mine ground.
  3. Storm drains that are the sewerage. "The Shillong Planning Area has no sewerage system", NESAC records; septic tanks and soak pits take the sewage, and "the sullage from the kitchen and bathroom flows into the primary, secondary and natural drains and finally to the nearby rivers Wah Umkhrah in the north and Wah Umshyrpi in the south". MSPCB identified 32 outfalls, 20 on the Umkhrah and 12 on the Umshyrpi. In 2022–23 the biochemical oxygen demand reached 56 mg/L in the Umkhrah at Mawpdang and 59 mg/L in the Umshyrpi near the Law College, and the High Court found in 2023 that "Several of the rivers, including the Umkhrah in Shillong itself are carrying such contaminated water that they may not be fit even to step into". The Smart City proposal of 2016-17, as quoted in the IRADe plan, gives Shillong 148.91 km of drains that "drain directly into the Umkhrah and Umshyrpi rivers", coverage of "less than 75%" of the city and "sewerage mixing in drains" of "almost 100%"; the same plan's table of service levels gives a coverage of 85%, and the two conflict. Both rivers flow, as the Wah Roro, into Umiam lake, which the Expert Committee constituted on the High Court's order found "serves as a cesspool of the waste materials of Shillong". In the Jaintia Hills the rivers also carry acid: a joint committee found the Lukha "to have become acidic", naming cement plants, power plants, breweries and ferro-alloy units as sources, and acid drainage from the coal mines is reported in the Kopili, the Myntdu and the Lukha; the biochemical oxygen demand (BOD), on which CPCB lists its stretches, does not measure it.

Over all three lies a regulatory field divided by the Sixth Schedule. The Bye-Laws 2021 reach the master-plan, municipal and scheme areas only; nearly half of the urban population, in the Town Committees and census towns, lives under the District Councils, as the CAG found. The Waterbodies Guidelines keep building only 3 m from an urban stream up to 3 m wide and 6 m from a wider one, and exclude the streams that are dry for 240 days a year, which most jhoras are. The Flood Plain Zoning Act of 2026 has, as far as was found, no Authority, no rules and no notified zone. And no State, municipal or District Council document fixes a design storm, a return period or a runoff coefficient for any town's drains.

Behind all of this lie the State's reservoirs, lakes, pungs, springs and sacred groves, which set the level at the outfall and the quality of the water downstream. Umiam lake, impounded in 1965 behind the Umiam Stage I dam, has a water spread of about 10 km² at its full level, as reported, and a catchment given as 221.5 km² and as over 220 km², though one source gives 547 km² for the river at the dam; its gross capacity was reported as 179.757 million m³ in 1965 and 159.206 million m³ in 2004, as sediment filled it, and its level, reported only as "3,220 ft", has no stated datum. MePGCL began releases from it at 3,216.15 ft in August 2024 on an IMD warning, as reported. Below the plateau, the Myntdu–Leshka dam has a spillway for 12,000 m³/s on a catchment of 350 km², about nine times the flow per km² of the New Umtru spillway (3,820 m³/s on 1,020 km²) on the northern slope, a measure of the escarpment's floods. The State has no Ramsar site and no wetland notified under the Wetlands Rules; the High Court accepted in April 2025 a report that 225 water bodies had been ground-truthed, as reported. Springs and streams, not wells, supply most towns, and the counts of mapped springs conflict, at 1,000 and 1,400, as reported; the sacred groves that sit at many stream heads are counted differently by every source, and no statute protects a spring or a grove, though the KHADC's Regulation charges its institutions with protecting "spring sheds".

Design for Meghalaya therefore has to cover a wet season that begins with the storms of April and May, before the south-west monsoon reaches the State in about the first week of June, and that runs past its withdrawal in about mid-October to storms such as those of 11 October 1975 at Cherrapunji (594.0 mm) and 8 October 2004 at Shillong (262.0 mm), and the Garo Hills floods of 4–6 October 2024; it is this Manual's monsoon season, 1 April to 31 October. Large falls come outside it too, as on 18 February 1993 (376.9 mm) and 23 March 1994 (587.4 mm) at Cherrapunji, so design statistics use the annual maxima of every month. The normal annual rainfall in the CWC report is 2,425 mm at Upper Shillong and 2,253 mm at Shillong (Obsy); the annual totals of about 11,430 mm for Cherrapunji and 17,800 mm for Mawsynram that CGWB quotes give no source or period and are not used as normals. There is no snow. Underground, every assessed unit of the State is safe, and the State draws 3.55% of its extractable groundwater (2022) or 4.60% (2024, as reported); there is "acute shortage of water during the summer as the major part of rainfall is lost as surface run-off", as CGWB found, so rainwater is worth storing for the dry season, not putting into the slopes.

National guidance sizes public drains but does not control the runoff that new building adds. This Manual makes stormwater a condition of development approval. Every development above a modest size must:

  • hold frequent rainfall on site, in tanks for use in the dry season, and in the ground only where the ground can safely take it;
  • release the large storms no faster than the undeveloped land did, or slower where catchments already flood; and
  • show that its outfall still works when the receiving jhora, stream, river, pung or reservoir is high, when a dam upstream is releasing, or when a drain is choked with debris and garbage.

The Manual also sets how public drains, hill roads and their drains, jhoras, streams, rivers, pungs, reservoirs, springs and their recharge areas, outfalls and basin-wide master plans are designed, and how drains in steep catchments are protected against debris, sediment and garbage, so that private sites and public works aim at the same standard.

The Manual draws on leading stormwater standards from India and abroad. Each is adapted to Meghalaya's wet season of April to October, with its pre-monsoon storms and its June storms against the plateau and the southern escarpment; to the record-rainfall belt of Sohra and Mawsynram, where no CWC report applies; to the Umkhrah and the Umshyrpi, which join as the Wah Roro and flow into Umiam lake, and the Umiam–Umtru dams below it; to the Myntdu below the Myntdu–Leshka dam; to the Umngot at Dawki and the other rivers that flow south to Bangladesh; to the Ganol of Tura, the Simsang of Williamnagar and the Jinjiram of the Garo plains; to the jhoras of the hill towns; to the alluvium of the Garo foothills, the valley fills of Ri Bhoi, the thin red loams over the gneiss of the plateau, the cavernous limestones of the escarpment and the coal measures of the Jaintia and Garo coalfields; to the pungs, springs and sacred groves; and to towns built on community and clan land, whose roads and houses lie across the natural lines of drainage on the slopes.

  1. National base. The CPHEEO Manual on Storm Water Drainage Systems (2019). This Manual builds on it and sets higher standards where it allows a State to do so. IRC road-drainage codes, including IRC:SP:42-2014 on hill roads, and the NDMA urban flood guidelines are also used. The drainage chapter of the IRC's hill road manual, IRC:SP:48, was not read for this Manual.
  2. Overall structure. Kansas City Metro APWA Section 5600 (Version 2025.01), the most recent comprehensive regional standard. It supplies the preserve, retain, detain, convey and maintain sequence and the required retention volume.
  3. Design rainfall. The CWC Flood Estimation Report for subzone 2(b), South Brahmaputra (revised, March 2000), as the interim source for the foothills, the plateau outside Shillong and the Garo hills. It rests on 14 gauged catchments, of which two, the Digaru and the Dudhnai, rise in Meghalaya, and its ratio of short to 24-hour rain was built from six recording gauges, Shillong's and five in the Assam valley; this Manual uses that ratio in the northern foothills only, and on the plateau and in the Garo hills uses the lower ratios of the CWC report for subzone 2(a), which still lie above every ratio recorded on the plateau. Inside the Shillong Planning Area it does not use the plate: the design day there comes from IMD's Shillong series, and is not less than the largest fall printed for any Shillong gauge, 437 mm, at 1% AEP. On the southern escarpment, where subzone 2(c) has no report and the plates no contour, the Cherrapunji curve of IMD's national study (Das et al., 2022) is the interim design rainfall, and every cross-drainage structure and outfall of more than 1 km² there needs a site-specific study. The design day is checked against the largest reliable days recorded nearby, but only within the same sub-area and not across a ridge or the plateau edge, so that Sohra's record never sets Shillong's design. NIH-DHAARA is reported beside the design value on the plateau and in the northern foothills only, and IMD's Shillong panel is not used.
  4. Monsoon practice. The PUB Singapore Code of Practice on Surface Water Drainage (7th ed., 2025), for the fixed-coefficient route for small sites and drainage reserves. Malaysia's MSMA 2 (2012), for monsoon design storms and simplified on-site detention.
  5. Runoff reduction and treatment. The Georgia Stormwater Management Manual (2016), for runoff reduction and downstream analysis. CIRIA C753 The SuDS Manual (2015), for the treatment train. The Mile High Flood District criteria manual, for outlet and storage design.
  6. Local rules. The Meghalaya Building Bye-Laws 2021 and their amendments to 7 May 2026; the MTCP Act; the Shillong Master Plan 2041 with NESAC's report of May 2023, and the draft master plan for Tura (2024); the KHADC's Regulation of 2015; the Meghalaya Municipal Act, 1973 and its amendment of 2021; the Waterbodies Guidelines of 25 August 2023 and their amendments of 13 February 2024 and 6 July 2026; the Bill of the Meghalaya Flood Plain Zoning Act, 2026; the Meghalaya State Language Act, 2005; the Wetlands (Conservation and Management) Rules, 2017 and the State's notification of 1 November 2017 constituting the State Wetlands Authority; and the orders of the High Court of Meghalaya in PIL 10 of 2019, of the NGT in OA 192 of 2022 and OA 73 of 2014, and of the Supreme Court of 3 July 2019. This Manual follows them or, where disclosed, makes them stricter. The building instruments of the JHADC and the GHADC were not found; the gazetted text of the Flood Plain Zoning Act, the Official Languages Ordinance, 2026 and the Sixth Schedule itself were not read; the KHADC's present position on the Bye-Laws 2021 is not known; and the CAG's report number was not confirmed. Every rule cited must be checked against the current text.

Why this Manual is needed

India has no uniform stormwater design standard. The CPHEEO Manual on Storm Water Drainage Systems (2019) is the country's first manual dedicated to storm water drainage, but it is advisory. The Ministry of Housing and Urban Affairs lists it among advisory guidelines and treats urban flooding as a matter for State Governments and urban local bodies. None of the national rules or State building rules reviewed for this Manual makes runoff control a condition of building approval, and neither does the Model Building Bye-Laws 2016.

The national documents leave key values open, or give different answers.

  • Return periods. CPHEEO recommends 5 years for drains in Class I cities and 2 years elsewhere, and lets a State committee adopt higher values. A 2023 CPHEEO presentation shows a different table. IRC:SP:50-2013 suggests 1–2 years for urban road drains; IRC:SP:42-2014 suggests 5–25 years for road drains and 10–50 years for culverts, by class of road and size of culvert. An engineer designing a drain in Meghalaya can cite 1, 2, 5, 10 or 25 years, depending on the code chosen.
  • Detention. CPHEEO describes limiting peak outflow to pre-development rates as general practice. It uses no "shall" and names no storm frequencies.
  • Climate. The NDMA Urban Flooding Guidelines (2010) call for detention and retention facilities and for rainfall curves adjusted for climate change, but give no sizing rule or return period. The State Action Plan on Climate Change of 2015, as quoted in the IRADe plan, projects 10–15% more precipitation in East Khasi Hills by 2050 and about 3% more in the Garo Hills, but gives no factor for design; its second edition (2023–2030) was not read.
  • Design rainfall. No national document gives design rainfall that a designer can apply directly to a given town. Each project chooses its own source. The CWC report for subzone 2(b) (2000) covers only the northern part of the State, and its plates read about twice every record at Shillong; its 1-hour ratio of 0.48, built mostly from gauges on the Brahmaputra plains, gives an hour at Shillong more than five times the largest recorded there; and the escarpment, where the rain is heaviest, is in subzone 2(c), which has no report at all. IMD's 2022 national set of rainfall intensity curves has panels for Cherrapunji and Shillong: Cherrapunji's is its own, with a 50-year day of about 1,440 mm read by eye, but Shillong's repeats a curve printed for many other cities. The one design statement found for Shillong, in RMSI's multi-hazard assessment of 2019 as quoted in the IRADe plan, takes its rainfall from CWC's Brahmaputra Basin PMP Atlas (2014), a source of probable maximum precipitation, not of design storms; neither the assessment nor the atlas was obtained.

Meghalaya has no drainage design standard of its own. Research for this Manual found no standard, IDF relationship or circular of the Urban Affairs Department, MUDA, SMB or any other Municipal Board, the PWD, the Water Resources Department or any District Council that fixes a return period, a runoff coefficient or a design rainfall for town storm drains; the Bye-Laws 2021 say only that drainage "shall be as per National Building Code 2016". No IDF relationship with published constants was found for any station in the State. The Shillong Master Plan's report maps flash-flood and landslide susceptibility, finding 4.67% of the planning area highly and 1.01% very highly susceptible to flash floods, and proposes decentralised treatment of waste water, but sizes no drain. The Water Resources Department has resubmitted a detailed project report for embankments and channel works on the Umkhrah and the Umshyrpi after the Brahmaputra Board returned the first, as reported; the RMSI study of floodplain zonation of the Umkhrah and other stretches, begun in June 2021 and 80% complete by March 2023, has not been published; and the State's river works since 2022 have been led by pollution orders, not by flood capacity. These are projects and studies, not a State standard. This Manual is offered as a technical companion to the Bye-Laws 2021 and the MTCP Act, the master plans, the KHADC's Regulation of 2015 and the other District Councils' instruments, the Waterbodies Guidelines, the Flood Plain Zoning Act, 2026 and the Municipal Act: it supplies the design storm, detention, slope, water-level and buffer values that they leave open. It has not been adopted by the Urban Affairs Department, MUDA, any District Council or any other body. In particular:

  • The building rules require rainwater harvesting, but size nothing. Table G1 of the Bye-Laws 2021 requires rainwater harvesting for every plot category and use, "Ground water recharge for covered area more than 3000 sqft" on larger residential plots, and soft cover of 10% or 20% of the plot, and G2.1.2 rebates 10% of the permission fee for rainwater harvesting with recycling; the KHADC's Regulation makes "storing of water runoff including rainwater in all existing and new buildings" mandatory and asks plans to show "the system of storm water drainage along with points of collection of rain water" (section 36). Neither gives a storage volume or a rate per m² of roof. No rule requires on-site detention, limits peak runoff or sets a design storm; the nearest are the Bye-Laws' measures for hazard-prone areas, inserted in 2024, that "Construction should not obstruct existing surface drainage courses" and that diversion ditches and swales direct runoff "into designated sediment basins" (Section I(b)), and the KHADC's call for "Semi-pervious ground cover … as paving wherever possible";
  • The slope rules stop building, not infiltration. The Bye-Laws 2021 forbid building on slopes above 50° and limit building on 40–50° (Section I(a), 2024), limit earth cutting to 3.00 m, or 6.00 m to the crest of a reinforced concrete wall, with a report of the Geological Survey of India beyond that (B1(vii)), and ask for "good drainage facilities to prevent excessive saturation of sub-surface formations" (Section I(b)); the KHADC's Regulation sets the same 3 m and 6 m. But no rule restricts soak pits, recharge pits or infiltration trenches on slopes, on limestone or over mine workings, and the recharge that Table G1 asks of larger plots applies on the slopes of Shillong and the limestone of Sohra as on the Garo plains;
  • The setbacks are small, and they leave out the jhoras. The Waterbodies Guidelines, as amended in 2024, keep building 3 m from an urban stream up to 3 m wide and 6 m from a wider one; this Manual reads the amendment of 2024 as having cut the setback outside municipal and cantonment areas from 5 m and 10 m to the same 3 m and 6 m [TBC]. Rural streams have setbacks of 10–30 m, reduced in 2026 from up to 50 m, and lakes and ponds 10 m, 20 m or 50 m by area, with a regulated zone four times the setback around lakes and along rural streams. The distances are measured from "the mean high flood level of a water body observed in the past ten years", a field mark, not a modelled flood; and a stream whose bed was dry for 240 days in each of the past ten years is not a "waterbody" at all, which leaves most jhoras unprotected. The Bye-Laws' own 2.40 m from a stream was replaced in 2024, the High Court's interim 50 m ended in February 2024, and the 50 m and 300 m zones that the Expert Committee recommended around Umiam lake, and the 50 m and 100 m buffers of NESAC's report, are recommendations, not rules;
  • The floodplain law has no zones yet. The Flood Plain Zoning Act, 2026 defines a "flood zone" as "the area which is required to carry the flow of the maximum probable floods", without a return period, and lets the Authority's restrictions prevail over other laws, with permission deemed granted after 90 days; no Authority, rules or zone notification was found. The Bye-Laws 2021 forbid building on land "liable to flooding" without protection, and set a stilt floor at least 1.20 m above the Highest Flood Level on a sloping site, but no HFL has been published for Shillong's streams. This Manual offers a technical method for drawing a design flood line and corridors (Chapter 7); it does not replace any zone that the Authority notifies, a line that a master plan draws or a court orders, and where such a line binds and is wider, it governs; and
  • No document sets the river, jhora or reservoir level for which an outfall is designed. CWC has seven level-monitoring sites in the State and no forecasting site, and none has a warning or danger level; its highest flood levels, such as 73.47 m for the Umngot at Dawki (28 May 2006) and 47.0 m for the Myntdu at Kharkhana (23 April 1995), were found only in transcriptions, on no stated datum, and two of them fall before the south-west monsoon. The Umkhrah, the Umshyrpi, the Umiam and the jhoras of the towns are ungauged. MePGCL gives some of its reservoir levels in feet and others in metres, and the level of Umiam lake behind the Stage I dam is known only from the press. Highest flood levels are records, not design levels.

So each agency and each local body interprets the central manual its own way. SMB and the other Municipal Boards, MUDA, the Cantonment Board, NSTDA, the District Councils and the KHBSRA, the Town Committees and the Dorbar Shnongs, the PWD, NHAI and NHIDCL, the Water Resources Department, PHED, MePGCL, Shillong Smart City Ltd, their consultants and funding agencies fill the gaps differently. No rule divides the drains between them: in Shillong a jhora may be SMB's drain for part of its length and run on community land under the KHADC for the rest, take the drainage of a PWD road and the sullage of a whole locality, and end in Umiam lake, which MePGCL controls; only part of the Umkhrah and the Umshyrpi lies within SMB's limits. In the autonomous districts outside the master-plan, municipal and scheme areas the Bye-Laws 2021 do not apply at all, and the Waterbodies Guidelines apply only "in such manner as may be prescribed". And a reviewer has no common basis against which to check a design.

What this Manual does about it. It turns those open choices into one State standard:

  • one source and method for design rainfall across the State, in four rainfall zones and seven hydrologic sub-areas, with a checked station analysis to govern where one exists; the 2(b) plates and ratios in the northern foothills; the plates with the lower 2(a) ratios on the plateau and in the Garo hills; IMD's Shillong record, with floors above every recorded fall, in place of the plate inside the Shillong Planning Area; the Cherrapunji curve on the southern escarpment, where subzone 2(c) has no report, with site-specific hydrology for every crossing and outfall of more than 1 km²; and a check of the design day against the largest reliable days recorded nearby that never crosses a ridge or the plateau edge (Chapter 2);
  • named return periods for every drainage element (Chapters 2 and 6);
  • a required pre- versus post-development rule for private sites (Chapter 4);
  • a required tailwater check for outfalls to jhoras, streams, rivers, pungs and reservoirs, against a design river or lake level: CWC's highest flood levels where they exist, MePGCL's reservoir levels, converted from feet where they are given in feet, and its release reaches, and, on the ungauged streams and jhoras of the towns, surveyed flood marks and a 1% AEP study that allows for debris and garbage; and, on the valley floors of Shillong that flood when the Umkhrah rises, a check with the outfall closed (Chapter 5);
  • a design flood line, and corridors and setbacks along jhoras, streams and rivers and around pungs, lakes, reservoirs and springs, proposed by this Manual for use where nothing wider binds, with a corridor at least 15 m from the top of bank on every natural channel draining 8 ha or more, whether or not the Waterbodies Guidelines count it as a waterbody, and the Guidelines' setbacks, the regulated zones and any notified flood zone wherever those are wider; corridor land that is not State land secured by agreement with its landholding institution (Chapter 7);
  • no deliberate infiltration on slopes steeper than 10°, on colluvium, fill or slide debris, in mapped landslide zones, or above a cut slope or retaining wall, unless a geotechnical certificate allows it; none at all, with no exception, on limestone, over coal workings or near caves and sinkholes; recharge only on the tested alluvium of the Garo foothills and the valley fills of Ri Bhoi; roof runoff to storage for the dry season, as the building rules already require, with its overflow to lined drains; the recharge areas of springs above town intakes kept free of paving and road runoff; and the interception of dry-weather flow before every outfall to the Umkhrah, the Umshyrpi, the Wah Roro and Umiam lake, where drains carry sewage (Chapter 8);
  • debris racks and traps, allowances for sediment, garbage and blockage, energy dissipation in steep drains, and hill-road drainage that never discharges onto an unprotected slope (Chapters 6 and 9), with drains, jhoras, inlets, racks and culverts cleared and certified ready by 31 March, before the April storms, cleared again by 31 May before the south-west monsoon and by 15 November after it, and standby kept from 1 April to 31 October (Chapter 10); and
  • basin-wide master plans, so that the agencies that share a basin, including the District Councils for the parts that lie in their areas, plan together (Chapter 11).

It uses the route the CPHEEO manual itself provides: a State may adopt standards higher than the national values (CPHEEO 2019, Table 4.1, Note 2). A Municipal Board, the Urban Affairs Department in a master plan or the bye-laws, or a District Council in its own building regulation can still adopt a stricter standard (Chapter 1).

Sources: CPHEEO (2019) Part A §4.4–4.5 and Table 4.1; CPHEEO presentation to CSE (August 2023); IRC:SP:50-2013 §6; IRC:SP:42-2014 cl. 7.1.4 and 8.5.1; NDMA (2010) Urban Flooding Guidelines, para 6.6.2; MoHUA Model Building Bye-Laws (2016); Meghalaya Building Bye-Laws, 2021, Notification No. UAU.73/2016/Pt/402 of 9 March 2021 (Gazette of Meghalaya No. 12, Part IIA, 25 March 2021), A1.2, A2.5, A2.7, A2.8(j), B1, B1.1, B2(ii)(c), C12, D4.2, Section G and Table G1, and the amendments No. UAU.73/2016/Pt/55 of 29 February 2024 (Section I), No. UAU.73/2016/Pt.III/76 of 19 November 2024, No. UAU.73/2016/Pt.VIII/191 of 15 January 2025, No. UAU.73/2016/Pt.VII/97 of 18 June 2025, No. UAU.110/2020/208 of 13 August 2025, No. UAU.73/2016/Pt.III(A)/70 of 21 October 2025 (B10), No. UAU.73/2016/Pt VIII-A/22 of 19 December 2025 and No. UAU.73/2016/Pt.VIII/203 of 7 May 2026; Shillong Master Plan 2041, notification No. UAU.76/2022/Pt.I/74 of 27 November 2024 as cited in No. UAU.76/2022/Pt.I/186 of 29 October 2025; NESAC, Formulation of Risk Informed GIS Based Master Plan, Shillong Planning Area (Ver 1.0, May 2023); Tura draft master plan notice No. UAU.76/2022/129 of 16 February 2024; Khasi Hills Autonomous District (Land Development and Building) Regulation, 2015, KHADC Notification No. DC.II/Genl/31/2015/9 of 4 August 2015, ss. 15, 34, 35, 36 and 40; Meghalaya Municipal Act, 1973, ss. 62, 190, 204–206, and the Meghalaya Municipal (Amendment) Act, 2021 (Act No. 4 of 2021); Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023, No. FOR/CC/29/2019/Pt/688 of 25 August 2023 (Gazette Part IIA, 7 September 2023, with the Expert Committee report), as amended by No. FOR/CC/29/2019/1140 of 13 February 2024 and No. FOR/CC/29/2019/Pt/771 of 6 July 2026; Meghalaya Flood Plain Zoning Bill, 2026 (Gazette Extraordinary Part V, 23 February 2026, No. LB.43/LA/2026/2); Meghalaya State Language Act, 2005 (Act No. 10 of 2005), ss. 3–4; Forest and Environment Department notification No. ENV.1/2007/Pt/110 of 1 November 2017 (State Wetlands Authority); High Court of Meghalaya, PIL No. 10 of 2019, In Re: Cleanliness of Umiam Lake, orders of 24 May 2023, 19 July 2023 and 19 February 2024; NGT OA 192/2022, State action-taken report of 21 March 2023 and CPCB–MSPCB Joint Committee report of 28 February 2023; minutes of the stakeholder meeting on the Wah Umkhrah, Wah Umshyrpi and Wah Umkhen, 14 April 2023, and the Chief Secretary's presentation; Supreme Court, State of Meghalaya v. All Dimasa Students Union, CA No. 10720 of 2018 (3 July 2019); CAG, Performance Audit on Solid Waste Management in Urban Areas of Meghalaya (2017-18 to 2021-22), executive summary; CPCB, Polluted River Stretches for Restoration of Water Quality (September 2025); IRADe/NMHS, Disaster Resilience Action Plan, Shillong, IRADe-PR-73(2020); CWC, Flood Estimation Report for South Brahmaputra subzone 2(b) (Revised), No. SB-2(b)/R-4/44/99 (March 2000), Table 4.1, Annexes 4.1 and 4.2 and Plates 8–10, read by eye, and Flood Estimation Report for North Brahmaputra subzone 2(a) (NB/18/1991); CWC, Regional Flood Estimation Report page (archived 20 March 2024); IMD, Extremes of Temperature and Rainfall for Indian Stations (up to 2012); IMD, Monthly Climate Summary, June 2022; Das et al. (2022), MAUSAM 73(4); NIH-DHAARA (queried 14 November 2026); CGWB, Dynamic Ground Water Resources of Meghalaya 2022; MePGCL gate-operation guidelines for Umiam–Umtru Stages III and IV, New Umtru and Myntdu–Leshka Stage I; U Nissor Singh, Khasi-English Dictionary (1906) and English-Khasi Dictionary (1920); D. S. Nengminza, The School Dictionary Garo to English (7th ed., 1978); Sajeki Passah, Pnar–English Dictionary (2013); CWC levels as transcribed by SANDRP (2018); reports of the floods of 2014, 2022, 2024, 2025 and 2026, of the KHADC's position on the Bye-Laws, of the Official Languages Ordinance, 2026, of Umiam lake and of springs and sacred groves (press and secondary sources).


How to use this Manual

Clauses and commentary. Numbered clauses (for example 4.5.2) are the requirements of this Manual and use "shall". Paragraphs headed Commentary explain the reason for a clause and cite its precedent. They are guidance, not requirements. Where a value has no direct precedent elsewhere, the commentary says so and explains why this Manual sets it.

Return periods. Storms are described both by annual exceedance probability (AEP) and by return period. For example, "1% AEP (100-yr)" means a storm with a 1-in-100 chance of being equalled or exceeded in any year.

Illustrative values. Worked examples and figures marked "Illustrative — not design values" show method and scale only. Design values come from the sources set in Chapter 2.

Annexes and forms. Each chapter lists the annexes and forms it relies on. They follow the chapters, grouped by chapter, and hold the forms to submit, worked examples, templates, model text and standard drawings. Annexes that need data not yet collected are marked To be prepared. They say what they will contain, and the clause that depends on them states the rule that applies in the meantime.

Figures. All figures are original drawings prepared for this Manual. Where a figure follows a published concept, its caption credits the source.

Where to start.

If you are… Read first
A developer or architect Chapter 1 (does it apply?), Chapter 4 (what to provide), Chapter 10 (what to submit)
A design engineer Chapters 2–6, then 8 and 9
A local body or approving authority Chapters 1, 10 and 11
A planner or waterbody manager Chapters 7 and 11

Contents

Ch Title Annexes and forms
1 Policy, Applicability and Adoption Annexes 1
2 Design Rainfall and Design Storms Annexes 2
3 Hydrologic Methods Annexes 3
4 Site Runoff Control: Retention and Detention Annexes 4
5 Downstream and Tailwater Analysis Annexes 5
6 Minor and Major Drainage Systems Annexes 6
7 Waterbodies, Pungs (Ponds and Lakes) and Setbacks Annexes 7
8 Water Quality and Recharge Annexes 8
9 Hydraulic Design of Structures Annexes 9
10 Submittals, Review, Operation & Maintenance and Enforcement Annexes 10
11 Basin and City Stormwater Master Plans Annexes 11

List of tables

TableTitle
1.1Differences between Tier A and Tier B authorities
1.2Policy supplement: adoptable alternatives S-1 to S-5
1.3Relationship with other instruments
1.4Roles and responsibilities under this Manual
1.5Working assignment of drainage elements under this Manual
2.1Design return periods (summary)
2.2Interim climate factors
2.3Illustrative scale of the mixed-frequency rule (not design values)
3.1Permitted hydrologic methods
3.2Runoff coefficient C (for AEP of 10% or more frequent)
3.3Frequency factor Cf
3.4Manning's n for sheet flow (USDA SCS TR-55, 1986, Table 3-1)
3.5Runoff curve numbers, AMC II, Ia = 0.2S (USDA SCS TR-55, 1986, Tables 2-2a and 2-2c)
4.1Design storms to be routed for detention sizing
4.2Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
4.3Tier B permissible site discharge and site storage requirement (template)
4.3AFixed release coefficients (provisional)
5.1Design tailwater levels for tidal outfalls
5.2Joint-probability cases for tidal and riverine outfalls
6.1Design AEPs for conveyance (matches Clause 2.4)
6.2Street flow limits
6.3Flow hazard limits for streets and overland flow paths
6.4Combined flood hazard vulnerability classes (reproduced for reference)
6.5Inlet clogging factors (share of clean capacity assumed lost)
6.6Manning's n for design (from CPHEEO 2019)
6.7Minimum freeboard in open and covered drains
6.8Maximum spacing of manholes on straight pipe runs
6.9Minimum drainage reserve width (adopted from PUB Singapore)
7.1Fixed-width setback where no 1% AEP extent is available
8.1Pollutants of concern, sources and primary controls
8.2Required Level of Service for sites that are not redevelopment
8.3BMP Value Ratings and suitability in Meghalaya
9.1Entrance loss coefficients ke (outlet control, full or partly full)
9.2Maximum permissible mean velocities in channels
9.3Riprap classes and apron dimensions (HEC-14)
9.4Minimum internal size of manholes
9.5Minimum IS 456 exposure classes for Meghalaya locations
10.1Submittal stages and linked approvals
10.2Forms used in submittals
10.3Minimum owner inspection frequencies
10.4Graduated enforcement response
11.1Minimum data and surveys for a BSMP
11.2Minimum levels of service
1A.1Tier A authorities as defined in Clause 1.6.1
1A.2Register of Tier A authorities (layout)
1B.1Flood-sensitive catchments listed in Clause 4.5.3.2
1B.2Attributes of the flood-sensitive catchment layer (layout)
1C.1Alternatives adopted by this resolution
1D.1Schedule: alternatives adopted (layout)
2A.1Benchmark comparison of design depths (layout)
2A.2Rainfall zones (layout)
2B.1Ratios P(t)/P(24h) by zone (layout)
2B.2Fixed-interval adjustment factors (Clause 2.6.3)
2C.1Grid-to-point factors (layout)
2D.1Cumulative fraction of storm depth against cumulative fraction of storm time (layout, one table per zone, duration class and quartile)
2E.1Retention depth P_R by zone (layout)
3A.1Soil series to HSG lookup (layout)
3A.2Seasonal high water table, by mapping unit (layout)
3B.1Supplementary land covers, AMC II (layout)
3B.2CN calibration catchments (layout)
3C.1Problem 3C-1 solution
3C.2Problem 3C-2 solution
3C.3Problem 3C-3 solution
3C.4Problem 3C-4 solution
3C.5Problem 3C-5 stage–storage–discharge relationship
3C.6Problem 3C-5 routed outflow
3C.7Benchmark results to be reported by the applicant
3D.1Calibrated peak rate factors (layout)
3E.1SUH relationships by subzone (layout)
3E.2Worked example outline (layout)
4A.1Attributes of the shallow-groundwater zone layer (layout)
4B.1Contents of Annex 4B and their status
4B.2Tier B PSD and SSR (layout of Table 4.3)
4B.3Retention credit factor C_R (layout)
4B.4Largest orifice diameter (mm) for a permissible discharge at a given head (Cd = 0.60, free discharge)
4B.5Fixed release coefficients C_10 and C_2 (provisional, Table 4.3A)
4C.1Inputs (Illustrative — not design values)
4C.2Design rainfall depths, mm (Illustrative — not design values)
4C.3Curve numbers and abstractions (Illustrative — not design values)
4C.4Storm runoff depth Q, mm (Illustrative — not design values)
4C.5Unit hydrograph parameters (Illustrative — not design values)
4C.6Stage–storage–discharge, trial outlet (Illustrative — not design values)
4C.7Routing of the 100-yr 72-hour storm through the trial outlet, around the peak (Illustrative — not design values)
4C.8Routing of the 100-yr 72-hour storm through the trial outlet, hourly (Illustrative — not design values)
4C.9Results for the trial outlet (120 mm and 470 mm orifices) (Illustrative — not design values)
4C.10Stage–storage–discharge, revised outlet (Illustrative — not design values)
4C.11Results for the revised outlet (170 mm and 460 mm orifices) (Illustrative — not design values)
4C.12Retention credit by routing, revised outlet (Illustrative — not design values)
4C.13Outlet checks, revised outlet (Illustrative — not design values)
4C.14Summary of the revised design (Illustrative — not design values)
5A.1Use of the Annex 5A values in the design tailwater (Table 5.1)
5A.2Tidal datums, surge and still-water levels by coastal segment (layout)
5B.1Water bodies named in Chapter 5
5B.2Attributes of the Annex 5B layers (layout)
5C.1Inputs (Illustrative — not design values)
5C.2Outfall-closed check results (Illustrative — not design values)
5C.3Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
5C.4Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
5C.5Summary (Illustrative — not design values)
6A.1Interim requirements for inlets until Annex 6A is published (from Chapters 6 and 9)
6A.2Register of standard inlet types (layout)
6A.3Capacity on grade (layout; one table per inlet type)
6A.4Capacity in a sag (layout; one table per inlet type)
6B.1Sediment allowances already set by Chapter 6 (provisional, to be calibrated)
6B.2Sediment yield by land use and drain type (layout)
6B.3Calibration of the sediment allowance (layout)
6C.1Dimensions on the standard drawings and their source clauses
7A.1Attribute fields of the waterbody inventory (WB_POLY)
7A.2Code lists
7A.3Attribute fields of structures (WB_STRUCT)
7B.1Fixed-width setback by waterbody class (alternative S-3)
7B.2Source buffers cited in Clause 7.4.6 (KC APWA 5600, 2006, §5605.3)
7C.1Rule levels by period (to be completed for each tank)
7C.2Outlet settings by level (to be completed for each tank)
7C.3Triggers and actions (to be completed for each tank)
7D.1Hold points for desilting and restoration works
7E.1Waterbodies
7E.2Water, springs, streams and channels
7E.3Land, forest and institutions
7E.4Terms not yet verified
8A.1Water quality rainfall depths by zone (layout)
8A.23-month ARI intensity by duration (layout)
8B.1Required LoS for redevelopment (layout)
8B.2Worked example: composite VR (illustrative)
8B.3Composite VR of treatment trains (layout)
8C.1Monitoring site register (layout)
8C.2Event record (layout; parameters of Clause 8.13.2)
8C.3Performance summary and proposed VR (layout)
8D.1Pretreatment (all BMPs)
8D.2Bioretention and rain gardens (Figure 8.2)
8D.3Vegetated swales
8D.4Vegetated filter strips
8D.5Permeable pavement
8D.6Infiltration trenches and basins (Figure 8.3)
8D.7Wet ponds (extended wet detention)
8D.8Constructed wetlands
8D.9Gross pollutant traps and outfall screens
8D.10Oil-grit separators
8D.11Infiltration and recharge criteria (all infiltrating BMPs)
8D.12Bioretention filter media and layers
8D.13Indicative plants for bioretention, swales and filter strips
8D.14Indicative plants for constructed wetlands and wet ponds
8D.15Species not to be planted
8E.1Selection of measures (Clause 8.12.3)
8E.2ESC timing and inspection (Clauses 8.12.2 and 8.12.5)
9A.1HDS-5 inlet-control coefficients for common inlets
9A.2Inputs for the worked example
9A.3Critical depth and specific head (D = 1.2 m)
9A.4Inlet-control headwater
9A.5Outlet-control headwater
9A.6Governing headwater and checks
9A.7Riprap apron sizing
9A.8Summary of the worked example (Illustrative — not design values)
9B.1Dimensions and rules on the standard drawings and their source clauses
9C.1Pump station design checklist
9C.2Control levels (values to be set in design)
10A.1Calculator inputs
10A.2Calculations the calculator shall perform
10B.1Layers
10B.2Attributes of SW_FAC (facilities)
10B.3Attributes of SW_OUTF (outfalls)
10B.4Attributes of SW_CATCH (catchments)
10B.5Attributes of SW_FLOW and SW_CONV (flow paths and conveyance)
10B.6Metadata (SW_META)
10B.7Facility type codes (FAC_TYPE)
10B.8Status codes (STATUS)
10B.9Inspection result codes (INSP_RES)
10C.1Access dimensions set by the Manual
10C.2Access dimensions not set by the Manual (to be confirmed in design)
10D.1Contents of an O&M plan
10D.2Retention and infiltration (soakaways, trenches, bioretention, permeable paving)
10D.3Surface detention basin or multi-use open space area
10D.4Underground or podium detention tank, gravity outlet
10D.5Pumped detention, pumps and controls
10D.6Flap or tide gate, non-return valve
10D.7Gross pollutant trap or first-flush device
10D.8Private drains and inlets
11A.1Deliverables
11B.1Basins named in Clause 11.3.3 (provisional)
11B.2Attributes of the basin boundary layer (layout)
11C.1Depth–damage curve (layout, one table per building type)
11D.1Items to be published

List of figures

FigureTitle
1.1Stormwater management hierarchy
1.2Applicability decision flowchart
2.1Design rainfall source hierarchy and adjustments
2.2Design hyetographs
2.3From design rainfall source to design storm
3.1Selection of hydrologic method
3.2Time of concentration: flow segments along the longest flow path (schematic)
3.3SCS-CN runoff depth versus rainfall depth
3.4Two-step continuous simulation: starting tank level (schematic)
3.5Pre- and post-development hydrographs
4.1Pre-development 10-yr, post-development 100-yr uncontrolled, and detained hydrographs (illustrative)
4.2Detention storage stack and multi-stage outlet (schematic)
4.3Fixed-coefficient route: release caps, storage by the mass-curve method and two-stage outlet (schematic)
5.1Extent of downstream analysis
5.2Tidal outfall section with flap gate and design tailwater levels
5.3Tide-locked outfall timeline (illustrative)
6.1Minor and major drainage in a kerbed street
6.2Gutter spread, inlet interception and clogging
6.3Drain sections: freeboard, sediment allowance and access
6.4Drainage reserve: cross-section (schematic)
6.5Coastal band: floor level stack and extent of the band (schematic)
7.1Waterbody setback zones
7.2Compensatory storage by elevation band (schematic)
7.3A plateau town: its jhoras, stream, pung and spring. A town on a ridge with lined drains and sediment traps falling through jhoras to a stream (wah), a spring (umpohliew) above the town's intake with its protected recharge area and no drains across it, a sacred grove (law kyntang) at the stream head, a pung with an outlet kept clear of sewage by dry-weather interception, the stream running on to a reservoir, the Manual's corridor along the stream, and the escarpment edge with limestone and mine voids where no infiltration is allowed
8.1Treatment train
8.2Bioretention cell
8.3Infiltration trench
9.1Culvert hydraulics: inlet control and outlet control
9.2Riprap apron at a pipe or culvert outlet (schematic)
9.3Stormwater pump station: wet well, screens, levels and outfall
10.1Submittal, review and approval workflow
10.2Construction hold points from approval to handover
10.3Maintenance cycle and responsibility
11.1Basin master plan process
11.2BSMP model schematic
6C.1Covered roadside drain with removable covers
6C.2Access and junction chamber on a covered drain
6C.3Kerb inlet with silt sump
8E.1Silt fence: section and plan (schematic)
8E.2Sediment basin with surface dewatering outlet: section (schematic)
8E.3Stabilised construction exit: plan and section (schematic)
8E.4Drain inlet protection (schematic)
9B.1Culvert headwalls, wingwalls and cut-off walls
9B.2Straight vertical drop structure
9B.3Trash rack at a conduit entrance
9B.4Detention outlet riser and emergency spillway

Abbreviations

Abbreviation Meaning
ABC Waters Active, Beautiful, Clean Waters (PUB Singapore's design guidelines)
ADC Autonomous District Council (the KHADC, JHADC or GHADC)
AEP Annual exceedance probability
AIDR Australian Institute for Disaster Resilience
AMC Antecedent moisture condition
AMRUT Atal Mission for Rejuvenation and Urban Transformation
APWA American Public Works Association
ARF Areal reduction factor
ASABE American Society of Agricultural and Biological Engineers
ASTM ASTM International (standards)
AWS Automatic weather station
BOD Biochemical oxygen demand
BRE Building Research Establishment (UK)
BSMP Basin Stormwater Master Plan
Bye-Laws 2021 The Meghalaya Building Bye-Laws 2021, as amended
C&RD Community and Rural Development (a C&RD block is the subdivision of a district used in this Manual)
CAG Comptroller and Auditor General of India
CGP Construction General Permit (US EPA)
CGWA Central Ground Water Authority
CGWB Central Ground Water Board
CN Curve number (SCS/NRCS method)
COD Chemical oxygen demand
CPCB Central Pollution Control Board
CPHEEO Central Public Health and Environmental Engineering Organisation
CSE Centre for Science and Environment
CWC Central Water Commission
DC Deputy Commissioner
DEWATS Decentralised wastewater treatment systems
DL / WL Danger level / warning level (CWC; no site in Meghalaya has them)
DPR Detailed project report
DWF Dry-weather flow
EIA Environmental impact assessment
EN European Standard (Norme Européenne)
EPD Environmental Protection Division (Georgia, United States)
ESC Erosion and sediment control
ETP Effluent treatment plant
EV1 Extreme value type I (Gumbel) distribution
FAR Floor area ratio
FEPCC Flood Estimation Planning and Coordination Committee (CWC)
FER Flood Estimation Report (CWC)
FPZ Flood plain zoning (under the Meghalaya Flood Plain Zoning Act, 2026)
FRL / MWL / MDDL Full reservoir level / maximum water level / minimum draw-down level
FRP Fibre-reinforced plastic
FSSTP Faecal sludge and septage treatment plant
GHADC Garo Hills Autonomous District Council
GWRA Ground water resource assessment (CGWB)
HAT / MHWS Highest astronomical tide / mean high water springs (coastal terms; not applicable in Meghalaya)
HC High Court of Meghalaya
HEP Hydro-electric project
HFL High flood level (the highest level recorded at a gauge)
HGL Hydraulic grade line
HSG Hydrologic soil group
HY-8 FHWA's culvert hydraulic analysis program
IDF Intensity–duration–frequency
IIT Indian Institute of Technology
IMD India Meteorological Department
IMDAA Indian Monsoon Data Assimilation and Analysis (a regional reanalysis)
IRADe Integrated Research and Action for Development
IRC Indian Roads Congress
ISO International Organization for Standardization
IST Indian Standard Time
JHADC Jaintia Hills Autonomous District Council
KC Kansas City (Kansas City Metro APWA Section 5600)
KHADC Khasi Hills Autonomous District Council
KHBSRA Khasi Hills Building and Structure Regulatory Authority (of the KHADC)
KLD Kilolitres a day
LiDAR Light detection and ranging (laser survey)
MBBL 2016 Model Building Bye-Laws 2016 (MoHUA; not the State's bye-laws)
MBDA Meghalaya Basin Development Authority
MeECL Meghalaya Energy Corporation Ltd
MePGCL Meghalaya Power Generation Corporation Ltd (operator of the Umiam–Umtru, New Umtru and Myntdu–Leshka dams)
MLD Million litres a day
MLHEP Myntdu–Leshka Hydro Electric Project
MoEF&CC Ministry of Environment, Forest and Climate Change
MoHUA Ministry of Housing and Urban Affairs
MSDMA Meghalaya State Disaster Management Authority
MSPCB Meghalaya State Pollution Control Board
MTCP Act The Meghalaya Town and Country Planning Act, 1973
MUDA Meghalaya Urban Development Authority
NAQUIM National Aquifer Mapping and Management programme (CGWB)
NDMA National Disaster Management Authority
NEEPCO North Eastern Electric Power Corporation
NESAC North Eastern Space Applications Centre
NGT National Green Tribunal
NH National Highway
NHAI National Highways Authority of India
NHIDCL National Highways and Infrastructure Development Corporation Ltd
NIH National Institute of Hydrology, Roorkee
NIT National Institute of Technology
NMHS National Mission on Himalayan Studies
NOC No-objection certificate
NPDES National Pollutant Discharge Elimination System (United States)
NRSC National Remote Sensing Centre
NSTDA New Shillong Township Development Authority
NWIA National Wetland Inventory and Assessment (ISRO)
OA Original Application (NGT)
OBPS Online Building Permission System
OGC Open Geospatial Consortium
ORG Ordinary rain gauge
PHED Public Health Engineering Department
PIL Public interest litigation
PSD Permissible site discharge
PWD Public Works Department, Meghalaya
RDSO Research Designs and Standards Organisation (Railways)
RMSE Root-mean-square error
RRC River Rejuvenation Committee (Forest and Environment Department)
RRV Required retention volume
RWH Rainwater harvesting
SANDRP South Asia Network on Dams, Rivers and People
SAPCC State Action Plan on Climate Change
SH State highway
SIPMIU the Urban Affairs Department's project unit in Shillong, headed by a Project Director (expansion [TBC])
SLA Sea-level allowance (coastal term; not applicable in Meghalaya)
SMB Shillong Municipal Board
SMP 2041 Shillong Master Plan 2041
SoI Survey of India
SRRG Self-recording rain gauge
STP Sewage treatment plant
SUH Synthetic unit hydrograph (CWC)
SW monsoon South-west monsoon (in IMD's sense; about the first week of June to mid-October in Meghalaya)
SWA Meghalaya State Wetlands Authority
SWD Storm water drain
SWM Solid waste management
TBC To be confirmed: a fact or value not yet found in a source
TCPO Town and Country Planning Organisation (MoHUA)
TR-55 Technical Release 55 (USDA SCS/NRCS)
UH Unit hydrograph
ULB Urban local body (in Meghalaya, a Municipal Board)
USACE US Army Corps of Engineers
UT Union Territory
UTM Universal Transverse Mercator
VR Value rating (of a BMP treating the WQv)
WQv Water quality volume
WSUD Water-sensitive urban design