Draft v1.0 prepared by NEER. Not adopted by the Government of Meghalaya, any District Council, authority or local body, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, pung and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Meghalaya's towns have master plans, hazard maps and river projects, but no published storm-drainage master plan with a design storm. The Shillong Master Plan 2041 was notified by No. UAU.76/2022/Pt.I/74 of 27 November 2024 (as cited in its amendment, No. UAU.76/2022/Pt.I/186 of 29 October 2025, whose text was read); its notified text was not obtained [TBC]. NESAC's report for it covers a planning area of 288.5 km² (174 km² in the plan of 1991–2011), the Shillong urban agglomeration and 54 villages, "drained mainly by the upstream reaches of Wah Umiam, Wah Umkhen, and Wah Tamdong"; it maps flash-flood susceptibility (very low 18.38% of the area, low 55.44%, medium 20.5%, high 4.67% and very high 1.01%), finds that "Encroachment and clogging of channels are the main causes of flooding over Shillong" and that "Polo Market, Pynthorbah, Nongrim hills, Dhankheti is a highly potential for flash flood", records that the planning area "has no sewerage system", projects wastewater in 2041 of 10.35 MLD in the Board area, 18.28 MLD in the census towns, 0.97 MLD in the Cantonment and 6.52 MLD in the villages and proposes decentralised treatment (DEWATS), but sets no design storm and sizes no drain (NESAC, 2023). The draft risk-informed master plan for Tura (notice No. UAU.76/2022/129 of 16 February 2024) covers 54.65 km² bounded by the Ringrey stream, the Ganol river and the Rongkhon stream, with 0.58 km² of water bodies, and has no drainage design either; the earlier plans, Shillong 1991–2011, Tura 1990–2001 and Jowai 1991–2001, are listed by the Urban Affairs Department. River work in Shillong has been led by pollution rather than capacity: in-situ treatment of five drains, on-site treatment plants and waste traps on the Umkhrah under the Tribunal's supervision (State action-taken report, 21 March 2023), and an invitation of 2018 for project reports on seven polluted stretches favouring "low-cost, decentralized, wetland-based bio-treatment systems". The Water Resources Department is reported to have resubmitted a project report for embankments and channel improvement on the Wahumkhrah and the Umshyrpi "to prevent flash floods" after the Brahmaputra Board returned the first (as reported; not read), and the floodplain zonation of the Umkhrah and other stretches awarded to RMSI in June 2021 was "80%" complete in March 2023 (the same report) but has not been published, so the flood it maps is not known [TBC]. No published document sets a design return period for the storm-drain network of any Meghalaya town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by the Urban Affairs Department, MUDA, any Municipal Board, any District Council or its building authority, the Water Resources Department, MePGCL, MSDMA or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, jhoras and streams narrowed by building and clogged with garbage, whose overflow floods the valley floors of Shillong, at Polo, Pynthorbah, Nongmynsong, Mawlai and Dhankheti, with nearly every heavy downpour, slopes that open drains and soak pits saturate, as in the landslide localities of Shillong along NH-40 and the Umshyrpi, drains that carry the sewage of a city with no sewers to the Umkhrah and the Umshyrpi and on to Umiam lake, drains that end in reservoirs or in reaches below the dams of MePGCL, and single streams split between a Municipal Board, PWD, a District Council and the Dorbar Shnongs of the villages they cross, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Meghalaya, the first North-East hill State in the series and its first under the Sixth Schedule: to towns in three settings, the plateau towns, Shillong, Jowai and Nongstoin among them, built on slopes where open drains and soak pits saturate the ground and where jhoras narrowed by building and garbage flood the valley floors; the escarpment settlements of Sohra, Mawsynram, Shella and Dawki, in the world's wettest belt, on limestone and above gorges, where landslides and debris decide more than the design storm; and the towns of the Garo hills and plains, Tura, Williamnagar, Baghmara, Dalu, Phulbari and Tikrikilla, on rivers that back up; to two CWC subzones, of which the southern has no Flood Estimation Report, and rainfall records five times apart within 40 km, 1,563.0 mm in 24 hours at Cherrapunji and 273.2 mm at Shillong (IMD); to drains that are the sewerage of a city with no sewers and that carry it to the Umkhrah, the Umshyrpi and Umiam lake, a reservoir run for power by MePGCL; to a regulatory field split between MUDA and the Municipal Boards in the master-plan and municipal areas and the District Councils and Dorbar Shnongs elsewhere, on land that is mostly community, clan or private; to setbacks of 3 m and 6 m from urban streams that leave most jhoras out, and a Flood Plain Zoning Act with no zone yet; to springs and sacred groves that supply and protect the towns' water, and karst and mine voids into which no water may be put; and to a wet season that begins with the storms of April and May, so that on the escarpment and below the dams a BSMP begins with the hazard, not the storm (Clause 11.3.3).


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 No basin delineation has been published for any Meghalaya town. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:

  • Shillong, Umkhrah and Umshyrpi: the catchments of the Umkhrah and the Umshyrpi to their junction as the Wah Roro and on to Umiam lake, with the valley floors of Polo, Pynthorbah, Nongmynsong, Mawlai, Forest Colony, Dhankheti and Nongrim Hills as outfall-closed cases (Clause 5.8.5(a)), NESAC's high and very-high flash-flood classes and the landslide localities along NH-40 and the Umshyrpi shown, the five drains that carry 42% of the Umkhrah's pre-monsoon discharge and the 32 outfalls of the two rivers in the 1D network, the stretches under the Board and under the KHADC marked, and surveyed flood marks and the 1% AEP level with its sediment, debris and garbage as the boundary condition, since neither river has a gauge;
  • Shillong, Umkhen and Wah Tamdong: the catchments of the planning area that drain east to the Umkhen, its eastern boundary, and to the Wah Tamdong (NESAC), with the same boundary conditions;
  • Umiam lake shore and the Umiam–Umtru reaches: the catchments that drain to Umiam lake and to the reaches below the dams of Stages III and IV and New Umtru, down the 9.80 km of the Umtru to Byrnihat, with the level of the lake, once MePGCL states it on a named datum [TBC], and the largest recorded releases as boundary conditions;
  • Jowai, Myntdu headwaters: the catchments of Jowai that drain to the headwaters of the Myntdu, with the limestone, cave and mine-void areas of sub-area ML-B1 mapped, and a local survey of flood marks as the boundary, since the CWC site at Kharkhana is far downstream, and the release reach of Myntdu–Leshka below the dam to the Bangladesh border;
  • Sohra, Mawsynram and Shella, escarpment: the catchments of the escarpment settlements of sub-area ML-C, under the hazard-first rule below;
  • Dawki, Umngot: the catchments of Dawki that drain to the Umngot, with the high flood level at CWC's Dawki site (73.47 m, 28 May 2006; datum not stated) and a surveyed flood mark of June 2026 as the boundary, and the outfall-closed case a design case;
  • Tura, Ganol: the catchments of Tura that drain to the Ganol and to the Ringrey and Rongkhon streams, which bound the draft master-plan area, with surveyed flood marks as the boundary;
  • Williamnagar, Simsang: the catchments of Williamnagar that drain to the Simsang, with a surveyed level of the river as the boundary;
  • Baghmara and Dalu, south Garo rivers: the catchments of the two towns, with the high flood levels of the Bugi at Dimapara (29.75 m) and the Dareng at Sibbari (20.34 m) where they apply, a survey of the Simsang at Baghmara, and the floods of October 2024 at Dalu as calibration evidence;
  • Garo foothill plains, Jinjiram and Krishnai: the catchments of Phulbari, Tikrikilla and the other plains towns that drain to the Jinjiram and the Krishnai, with river backwater as the boundary for at least the 72-hour storm and the Assam edition governing the Brahmaputra reaches; and
  • Nongpoh–Umling, NH-6 and the Umlew: the catchments along NH-6 that drain to the Umlew and the other streams of Ri-Bhoi, with the slides of the hill cuts of 2025 mapped.

Hazard first on the southern escarpment (set by this Manual). In sub-areas ML-C (Southern escarpment) and ML-C1 (South Garo slopes) of Annex 2A, and in any basin below a mapped landslide zone, a debris fan, a mine-spoil dump, a karst sink or a reservoir release reach, the BSMP begins with a hazard screening for landslides, debris flows, flash floods, karst collapse and dam releases, made with MSDMA's inventories where they exist [TBC], the susceptibility maps of NESAC and the IRADe/NMHS plan, and MePGCL's release reaches, and uses site-specific hydrology in place of a CWC report, which subzone 2(c) does not have (Clause 2.3.6(c)(ii) and (i)), with the duration check of Clause 6.3.6(j). The escarpment's floods are of another order: the spillway of Myntdu–Leshka Stage I is rated for 12,000 m³/s from 350 km², about 34 m³/s per km² (MePGCL; ratio computed for this Manual), Cherrapunji has recorded 1,563.0 mm in 24 hours (IMD) and 2,493 mm in 48 hours on 15–16 June 1995 (a world record, as reported, used only as a stress case), and the earthquake of 12 June 1897 is reported to have killed about 600 people in a landslide at Sohra (as reported). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow or a landslide. Other Tier A bodies and the other Municipal Boards define their basins in the first BSMP that covers them. Where CWC, MePGCL, a master plan, the Flood Zoning Authority or a court has a high flood level, a reservoir level, a flood line or an operating rule for a dam, gate or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, river levels, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, river, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Meghalaya a single stream passes through many hands, and through the Sixth Schedule line, on its way to a river. In Shillong the Umkhrah and the Umshyrpi are at once storm drains, sewers and the feeders of a reservoir: the drains and jhoras carry the city's sullage and septic overflow to 32 outfalls, 20 on the Umkhrah and 12 on the Umshyrpi (MSPCB, as minuted on 14 April 2023), five drains entering the Umkhrah "account for 42% of Umkhrah's pre-monsoon discharge" (the Chief Secretary's presentation, April 2023), and the two rivers join as the Wah Roro before flowing into Umiam lake, which the Expert Committee found "serves as a cesspool of the waste materials of Shillong" (2023). Only parts of the two rivers lie in the Shillong Municipal Board's area, "and remaining stretch falls under jurisdiction of Khasi Hills Autonomous District Council" (State action-taken report to the National Green Tribunal, 21 March 2023), which asked the Board to prepare a geo-referenced map dividing them; the drains in the Board's area are the Board's (Meghalaya Municipal Act, 1973, s.62), its road drains PWD's or NHAI's, the Cantonment's the Cantonment Board's, the village drains and jhoras the District Council's and the Dorbar Shnongs', and the lake MePGCL's. Most of the drainage lines of the planning area are "first, second, and third order reaches" (NESAC, 2023), and most jhoras fall outside the Waterbodies Guidelines, which exclude streams whose bed is dry for 240 days a year (para 2(e)). Beyond Shillong the rivers leave the State: the Umtru, the Digaru, the Jinjiram and the Kopili north to Assam, and the Umngot, the Myntdu, the Kynshi and the Simsang south to Bangladesh. No rule divides the jhoras and natural streams from the municipal drains (as this Manual reads the record). This clause makes the basin the planning unit, so that one model carries each jhora from its head on the ridge to the river or reservoir whoever owns each reach, whether or not the Guidelines treat it as a waterbody, and so that the sewage it carries is separated before it reaches the river or the lake (Chapter 8, Clause 8.9.5).


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For the basins of the Shillong Planning Area: the Shillong Municipal Board (SMB), in which the drains, public streams and springs within its limits vest (Meghalaya Municipal Act, 1973, s.62), jointly with MUDA, the Authority under the Bye-Laws 2021 in the master-plan area, and the Urban Affairs Department, which notifies the Shillong Master Plan 2041 into which the BSMP is taken (Clause 11.9); and, for the parts of the planning area under the Khasi Hills Autonomous District Council, the KHADC or its building authority, if the District Council adopts the Manual. Each role is the one the body would have if the Manual were adopted. The Shillong Cantonment Board and NSTDA in New Shillong [TBC] are partners for their areas. For the basins of Tura: the Tura Municipal Board with MUDA in the Tura master-plan area. Where a basin extends beyond the Board's limits or the planning area, the District Council, the Dorbar Shnongs of the villages it crosses and the other local bodies in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
  • No order dividing the jhoras and natural streams from the municipal drains, or the drains of the local bodies from the rivers and reservoirs, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: the Water Resources Department for the rivers and their beds, banks and flood works, among them the Umkhrah and the Umshyrpi, for which it has proposed embankments and channel improvement (as reported); the Municipal Board for the drains, public streams, springs and tanks within its limits; the District Council, and the Dorbar Shnong under the District Council's rules, for the village drains and jhoras outside municipal limits (the Nokma-led villages of the Garo Hills were not researched [TBC]); Shillong Smart City Ltd for the drains of its works, until handed over in writing; PWD (Roads) for the side drains, catch-water drains and culverts of the State roads, and NHAI and NHIDCL for those of NH-6 and the Shillong–Dawki road, with the spoil of their works; PHED for sanitation outside the municipalities; MePGCL for Umiam, Kyrdemkulai, Nongkhyllem, New Umtru and Myntdu–Leshka, their reservoir levels and releases; the Soil and Water Conservation Department for catchment treatment; the Forest and Environment Department and the Meghalaya State Wetlands Authority for the setbacks of the Waterbodies Guidelines, Umiam lake and the other wetlands; and MSDMA, with NESAC's susceptibility maps, for the mapping of landslide, flash-flood and debris hazards that a BSMP must show.
  • In the other Municipal Boards (Jowai, Williamnagar, Resubelpara and Baghmara) and in Tier B bodies: the Lead Authority is named by the Urban Affairs Department, and in a District Council's area by the District Council, if it adopts the Manual. Basins draining to a common river reach or reservoir may be grouped into one district-level plan.

MSDMA and the Deputy Commissioner shall be consulted on every BSMP; MePGCL on every BSMP whose basin drains to a reservoir or to a river below a dam; the Forest and Environment Department on every BSMP whose basin drains to Umiam lake or another waterbody with a setback or regulated zone; MSPCB on every BSMP that proposes works on a drain or stream that carries sewage or effluent, among them the Umkhrah, the Umshyrpi, the Wah Roro and the streams of the coal belt; the District Council and the Dorbar Shnongs on every BSMP that needs community, clan or private land for a corridor or storage, which is secured by agreement with the landholding institution; and, for a basin whose outfall lies on a river that flows into Assam, such as the Umtru below Byrnihat, the Digaru or the Jinjiram, Assam's water resources department, through the Water Resources Department.

The Water Resources Department shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, pung, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls, rivers, streams, jhoras, reservoirs, pungs and lakes The datum of every level named; outfall invert levels against the high flood level of the receiving river at the nearest CWC level-monitoring site, where there is one (73.47 m on the Umngot at Dawki, 47.0 m on the Myntdu at Kharkhana, 20.62 m on the Umnohryngkew at Therriaghat, 29.75 m on the Bugi at Dimapara and 20.34 m on the Dareng at Sibbari; no site in the State has a warning or danger level; CWC levels as transcribed by SANDRP, as reported, with the datum not stated), with any local gauge kept as a separate series; for the Umkhrah and the Umshyrpi in Shillong and the other ungauged streams and jhoras, surveyed flood marks, the debris and garbage lines of past floods and the 1% AEP flood level with its sediment, debris and garbage; for outfalls to reservoirs, the maximum water level, full reservoir level and spillway and gate data from MePGCL, converted from feet where so published (for example Myntdu–Leshka Stage I, 618.00 m; New Umtru, full reservoir level 130.10 m and maximum water level 132.78 m; Umiam–Umtru Stage III, 2,230 ft and 2,235 ft, about 679.7 m and 681.2 m; Stage IV, 503.00 m; Umiam Stage I, 3,220 ft in the press only, on an unknown datum [TBC]), naming which is used, and pungs and lakes at their surveyed spill levels; the release records of the MePGCL dams; the landslide, flash-flood and debris hazards above the basin from the susceptibility maps of NESAC and the IRADe/NMHS plan and from MSDMA where mapped, the karst, cave and mine-void areas, and the mine-spoil dumps; and the sluices, flap gates, debris racks, solid-waste traps, sediment traps, debris basins and pumping stations on the outfalls, with their capacities and operating rules
Rainfall and levels All available rain gauges (IMD, including its observatories at Cherrapunji and Shillong (C.S.O.) and the gauges reported by the Meteorological Centre Shillong, among them Tikrikilla, Resubelpara, Barapani, MeECL Lumjingshai, Shillong, Williamnagar, Nongstoin, Tura, Mawphlang, Mawkyrwat, Mawsynram, Sohra, RKM Sohra, Khliehriat, Baghmara, Shella and Ratacherra (types and record lengths [TBC]); the Shillong self-recording gauge and the ordinary gauges at Shillong (Obsy), Upper Shillong and Dalu used for the CWC Flood Estimation Report for subzone 2(b); the river gauges of CWC; the agro-meteorological station of the ICAR Research Complex for NEH Region at Umiam [TBC]; the rain and reservoir records of MePGCL at its dams [TBC]; and any gauges or sensors kept by the Municipal Boards, Shillong Smart City Ltd, MSDMA and the Water Resources Department [TBC]) and water-level records, including those for the 15–17 June 2022 (1,003.6 mm at Mawsynram in the 24 hours to 08:30 on 17 June, IMD, with 811.6 or 811.2 mm and 972 mm reported at Sohra and NH-6 cut by slides, as reported), 9 July 2019 (more than 72.2 mm at Shillong, with the flash floods of Polo, Forest Colony and Mawlai, as tabulated in the IRADe/NMHS plan), 21–22 September 2014 (the floods and landslides of the Garo Hills after the rain of the night of 21 September, with 52 deaths reported by 28–29 September and more than 60 in a later account, and more than 200 villages under the Brahmaputra and the Jinjiram, as reported, for which no rainfall measurement was found), 4–6 October 2024 (the floods at Dalu and the landslide at Hatiasia Songma in the Garo Hills, as reported, with no rainfall value found), 30–31 May 2025 (the flash flood at Sumer Latara and the landslides of the Umling block near NH-6, as reported, with no rainfall value found) and June 2026 (the collapse of the Shillong–Dawki road at Laitlyngkot and the Umngot flood at Dawki, as reported, with no rainfall value found) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the valley floors of Shillong along the Umkhrah and the Umshyrpi, where the water tops the banks of channels narrowed by encroachment, on the Garo foothill plains of Phulbari and Tikrikilla on the Jinjiram and the Krishnai, where slopes are gentle and the rivers back up, on the river terraces and floodplains below the dams of MePGCL, and on the pung, lake and reservoir margins, where a raised road, a dumped fill or a low wall can turn an overflow from one side of a valley floor to the other, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 15–17 June 2022 (1,003.6 mm at Mawsynram in the 24 hours to 08:30 on 17 June, IMD, with 811.6 or 811.2 mm and 972 mm reported at Sohra and NH-6 cut by slides, as reported), 9 July 2019 (more than 72.2 mm at Shillong, with the flash floods of Polo, Forest Colony and Mawlai, as tabulated in the IRADe/NMHS plan), 21–22 September 2014 (the floods and landslides of the Garo Hills after the rain of the night of 21 September, with 52 deaths reported by 28–29 September and more than 60 in a later account, and more than 200 villages under the Brahmaputra and the Jinjiram, as reported, for which no rainfall measurement was found), 4–6 October 2024 (the floods at Dalu and the landslide at Hatiasia Songma in the Garo Hills, as reported, with no rainfall value found), 30–31 May 2025 (the flash flood at Sumer Latara and the landslides of the Umling block near NH-6, as reported, with no rainfall value found) and June 2026 (the collapse of the Shillong–Dawki road at Laitlyngkot and the Umngot flood at Dawki, as reported, with no rainfall value found) events are the best calibration data Meghalaya has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and pung storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Meghalaya's storage is in its reservoirs, its few lakes and pungs, its valley floors and its springs more than in tanks; it has no irrigation tank cascades. Umiam (Barapani), impounded in 1965, has a water spread of about 10.148 km² at its full level and has lost part of its capacity to sediment (as reported); Ward's Lake (Nan Polok) in Shillong and Thadlaskein (Pung Sajar Nangli) near Mukhla are its best-known lake and pung (as reported). The Meghalaya State Wetlands Authority was constituted on 1 November 2017 under the Wetlands Rules 2017 (Notification No. ENV.1/2007/Pt/110), but no wetland has been found notified under Rule 4 and the State has no Ramsar site; in 2025 the High Court accepted a report that 225 water bodies had been ground-truthed, 66 of them lakes and ponds, 25 tanks and ponds and 9 reservoirs and barrages, and that none qualified as a Ramsar site (as reported). The Expert Committee annexed to the Waterbodies Guidelines circulated "inclusion and exclusion lists of water bodies" to the Deputy Commissioners (2023), and the Guidelines exclude ponds and streams whose bed is dry for 240 days in each of the past ten years (para 2(e)), so the jhoras that carry the hill runoff are outside them. The losses are visible in the water as well as at its edge: MSPCB found Umiam lake "Not satisfactory" at all four stations in June 2023, with cyanobacterial blooms each year and leachate from the Mawiong landfill reaching it (Expert Committee, 2023). No survey of the storage of any pung or lake, or of any floodplain inside a Municipal Board's limits, was found.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Meghalaya has been adopted with a design factor; the State Action Plan on Climate Change (2015), as quoted in the IRADe/NMHS plan for Shillong, projects more precipitation in every district, 10–15% more in East Khasi Hills by 2050 and about 3% more in the Garo Hills (the passage's east–west wording is inconsistent as printed), and its second version (2023–2030) was not read [TBC]; the trend of Shillong's daily maximum over 1985–2003 is a non-significant increase; the rainfall of June 2022 over Assam and Meghalaya was the highest since 1901 (IMD), while the monsoon of 2026 was 60% below normal in Meghalaya (as reported), which is a reason to keep the factors, not to reduce them; and in sub-areas ML-C and ML-C1 the duration check of Clause 6.3.6(j) and the hazard screening of Clause 11.3.3 are made in every scenario.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 15–17 June 2022 (1,003.6 mm at Mawsynram in the 24 hours to 08:30 on 17 June, IMD, with 811.6 or 811.2 mm and 972 mm reported at Sohra and NH-6 cut by slides, as reported), 9 July 2019 (more than 72.2 mm at Shillong, with the flash floods of Polo, Forest Colony and Mawlai, as tabulated in the IRADe/NMHS plan), 21–22 September 2014 (the floods and landslides of the Garo Hills after the rain of the night of 21 September, with 52 deaths reported by 28–29 September and more than 60 in a later account, and more than 200 villages under the Brahmaputra and the Jinjiram, as reported, for which no rainfall measurement was found), 4–6 October 2024 (the floods at Dalu and the landslide at Hatiasia Songma in the Garo Hills, as reported, with no rainfall value found), 30–31 May 2025 (the flash flood at Sumer Latara and the landslides of the Umling block near NH-6, as reported, with no rainfall value found) and June 2026 (the collapse of the Shillong–Dawki road at Laitlyngkot and the Umngot flood at Dawki, as reported, with no rainfall value found) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two pungs in cascade with an overflow course; a 1D drain network linked to a 2D surface grid; a jhora and stream (wah) reach with an inter-basin link; an outfall with a flap gate and pumps; and a river or reservoir stage boundary (a free outfall to a gorge, a reservoir level, or river backwater on the Garo plains). Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) River / reservoir 1 S1 S2 S3 2 Upper pung Lower pung start level start level 3 2D surface 5 4 Jhora and stream (wah) (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Pungs, ponds and lakes Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Jhoras and streams (wah) (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Sluices, flap gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary River or reservoir stage, per Ch. 5: free outfall to a gorge; reservoir (MWL or FRL + surcharge); river backwater (Garo plains) Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and pungs with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: pungs, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: flap gates and penstocks on the outfalls of the valley floors of Shillong to the Umkhrah and the Umshyrpi, of Dawki to the Umngot and of the Garo plains towns to the Jinjiram and the Krishnai, and on the outfalls of the Umiam lake shore, with storage or pumping behind them where a stream in flood or a reservoir held near its full level can close an outfall; debris racks, solid-waste traps, sediment traps and debris basins where jhoras and streams from the hills enter the towns and at every drain outfall to the Umkhrah, the Umshyrpi, the Wah Roro and Umiam lake, with ramps for the machines that empty them, and the removal of garbage and slide debris from the jhoras; drop structures, chutes, energy dissipators and protected outfalls where steep drains reach a jhora or river, never an unprotected slope; the interception and screening of dry-weather flow, and the separation of sewage, before the outfalls to the Umkhrah, the Umshyrpi, the Wah Roro and Umiam lake (Chapter 8, Clause 8.9); and the release rules of the MePGCL dams that set the receiving levels, agreed with MePGCL;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Shillong, the siren, telephone and SMS warnings that MePGCL gives before releases from its dams, level gauges with alarms on the Umkhrah and the Umshyrpi in Shillong, which have no gauge today, and the district emergency operation centres of MSDMA), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on the springs and streams that supply most towns by gravity, and their recharge areas above the town intakes, which this Manual keeps free of paving and of infiltrated road runoff, the sacred groves at the heads of perennial streams, the stability of hill slopes, where water put into colluvium, fill or slide debris raises the pore pressure, as in the landslide localities of Shillong, the cavernous limestones and coal-mine voids of the escarpment and the Jaintia hills, where water put into the ground may go anywhere and no infiltration is allowed (Clause 4.11, karst and mine rule), recharge on the alluvium of the Garo foothill plains and the valley fills of Ri-Bhoi, the only ground where it is allowed, although every assessment unit in the State is safe (stage of extraction 3.55%, CGWB, 2022), and the quality of the groundwater, which carries iron above the drinking-water limit at Shillong and other places, and of the streams, reservoirs, pungs and lakes that the runoff reaches (Chapter 8);
  • effect on downstream basins and the receiving river, stream, jhora, reservoir or pung; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because many of Meghalaya's town outfalls are closed or limited in the wettest hours, and because the storage left is on valley floors and in jhora beds that the towns are filling. In Shillong the valley floors of Polo, Pynthorbah, Nongmynsong, Forest Colony and Mawlai flood "with nearly every heavy downpour" when the Wah Umkhrah overflows, a flooding attributed to "clogging of Wah Umkhrah and the decreasing width of the river due to human activities" (as reported; the same account is in the IRADe/NMHS plan), and NESAC found "a drastic reduction in channel capacities in most streams due to encroachments along their banks by buildings" (2023). Umiam lake, at the end of the city's rivers, is losing storage to sediment: its gross capacity is reported as 179.757 Mm³ in 1965, 167.069 Mm³ in 1990 and 159.206 Mm³ in 2004 (as reported). Concrete channels alone will not serve on a jhora that carries garbage, boulders and sewage, and on a hill slope, on limestone or over mine workings storage means a lined tank or a terrace, never a pond that soaks into the ground (Clause 4.11); the rainwater storage of at least 25 litres per m² of roof that Clause 4.11 sets, where the Bye-Laws 2021 and the KHADC's Regulation require rainwater harvesting without a volume, is the first of it, and it also serves the dry months, when the towns run short of water. The storms are large for drains with no stated design basis: Cherrapunji has recorded 1,563.0 mm in a day (16 June 1995) and Mawsynram 1,003.6 mm (17 June 2022), and even Shillong 273.2 mm (25 June 1988) (IMD). Conveyance upgrades on their own move water faster to an outfall that the Umkhrah or the Umshyrpi in flood, the Umngot at Dawki, the Jinjiram on the Garo plains, or Umiam lake or another reservoir held near its full level, may close, to a jhora or stream whose bed and banks shift with the boulders, slide debris and garbage it carries, or to an outfall limited by the capacity of its gate or pumping station. Groundwater in Meghalaya calls for storage and restraint, not recharge. Every assessment unit in the State is safe, with a stage of extraction of 3.55% in 2022 (CGWB) and 4.60% in 2024 (as reported), yet the State has "acute shortage of water during the summer as the major part of rainfall is lost as surface run-off", and its towns are supplied by gravity from "streams and springs" tapped at higher altitudes (CGWB, 2022). Little rain enters the ground: infiltration tests under the national aquifer mapping programme gave recharge of 4–5% of rainfall on weathered granite, quartzite and Tertiary rocks and 10–13% only on the alluvium and valley fills of Ri-Bhoi and the Jaintia hills (CGWB, 2022). Water put into the ground can do harm: on the slopes of Shillong, where the landslide localities named in the IRADe/NMHS plan lie, it raises the pore pressure; in the "discontinuous aquifer in the cavernous limestones" (CGWB, 2022) and in the rat-hole workings of the coalfields, into which streams are reported to "disappear" (as reported), it may go anywhere; and the groundwater of Shillong already carries 11.25 mg/l of iron (CGWB, 2022). The springs matter more than the wells: MBDA's spring-shed programme is reported to have mapped 1,000 springs in 11 districts, or to hold an inventory of 1,400 (both as reported; the counts conflict), and a State scheme for the revival of springs covers 306 springsheds under the National Adaptation Fund for Climate Change (as cited on the State's scheme page); many sacred groves stand near the sources of perennial streams (as reported). No State groundwater Act was found; abstraction needs the no-objection certificate of a District Level or State Level Committee on ground water. This is why springs and their recharge areas, slope stability, karst and mine voids, recharge on the only ground that can take it, and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the master plans of the master-plan areas notified under the Meghalaya Town and Country Planning Act, 1973, among them the Shillong Master Plan 2041 and, once notified, the risk-informed master plan for Tura, with their zoning regulations and the Bye-Laws 2021; in the autonomous districts outside those areas, the land-development and building regulations of the District Councils, among them the KHADC's Regulation of 2015, if the District Council adopts the Manual; the flood zones notified under the Meghalaya Flood Plain Zoning Act, 2026, once any are; and the layouts and buildings permitted under them. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Meghalaya draws its water lines by executive guideline and by bye-law, and has a floodplain Act with no zone yet. The Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023, as amended in 2024 and 2026, set setbacks from "the mean high flood level of a water body observed in the past ten years" (para 2(f)): 3 m from an urban stream up to 3 m wide and 6 m from a wider one (Appendix 3 as merged in 2024), 10 m to 30 m from rural streams by width and plot size (Appendix 2A, 2026), and 10, 20 or 50 m from lakes and ponds by area, with a regulated zone four times the setback for lakes and rural streams (para 7(1A)); they bind in the Bye-Laws areas (B2(ii)(c) and Section I(f), 2024), elsewhere only "in such manner as may be prescribed" (para 10(2)), and nothing prescribed was found; and they exclude seasonal streams whose bed is dry for 240 days in each of the past ten years (para 2(e)), which is most jhoras. The Bye-Laws 2021 bar the use of land "liable to flooding, except where protection measures are adopted" (B1.1(ii)), set a stilt 1.20 m above the Highest Flood Level on sloping sites beside a stream (B1(v)(b)), and leave the areas of "back flow in drains, inadequate drainage" to be "identified through local surveys in the development plan" (A2.37); the KHADC's Regulation of 2015 puts the "river edge" in a conservation zone where "No development should normally be allowed" (s.2.101). The Meghalaya Flood Plain Zoning Act, 2026 defines the flood zone as "the area which is required to carry the flow of the maximum probable floods", without a return period, and its restrictions "shall prevail" over other laws (ss.2(g) and 12(2), as read in the Bill), but no zone has been notified. The High Court's bar on building within 50 m of waterbodies ended when PIL No. 10 of 2019 was closed on 19 February 2024; the Expert Committee's "Restricted Zones of 50m + 300m" round Umiam lake and NESAC's "buffer as per NGT" along the Umkhrah and the Umshyrpi (no such order of the Tribunal for Shillong's streams was found), 50 m from the lake and 100 m from protected forests are recommendations, not rules. Where a notified flood zone or a master-plan line governs, it applies; elsewhere the hydraulic corridor and setback zones of Chapter 7, with a Zone 1 of at least 15 m on every channel draining 8 ha or more, the Guidelines' setbacks from the ten-year mean high flood level and the 1% AEP extent plus 10 m apply, whichever is wider, as this Manual's proposal, with the 1% AEP corridor as this Manual's reading of "maximum probable floods" and Zone 1 land that is community, clan or private secured by agreement with the landholding institution. A BSMP gives the master plans and the Flood Zoning Authority the 1% AEP drainage-flood map, including the jhoras that no guideline covers, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the Bye-Laws 2021 already require rainwater harvesting for every plot category and use, soft cover of at least 10% or 20% of the plot and, for new buildings in the City Centre Zone, 30% of the plot as open space with soft cover and landscaping (Table G1; D8.2), and ask for diversion ditches and swales that carry runoff into designated sediment basins (Section I(b)), and the KHADC Regulation 2015 asks for soft cover of 10–15% of the plot and for plans that show the storm-water drainage and the points where rainwater is collected (ss.35(iii) and 36), but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on a hill slope, on limestone or over mine workings it is a lined tank or a shallow terrace, never an infiltration basin (Clause 4.11). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

  • Central Ground Water Board, North Eastern Region, Guwahati (2022). Dynamic Ground Water Resources of Meghalaya (GWRA 2022): stage of extraction, hydrogeology (Table 1), rainfall infiltration factors from aquifer-mapping tests, groundwater quality; with the assessment of 2024 (as reported). http://web.archive.org/web/20250402124501/https://www.cgwb.gov.in/old_website/GW-Assessment/GWR-2022-Reports%20State/Meghalaya.pdf
  • North Eastern Space Applications Centre (2023). Formulation of Risk Informed GIS Based Master Plan, Shillong Planning Area, Ver. 1.0 (planning area; drainage; flash-flood and landslide susceptibility; sewage and sullage; DEWATS; buffer recommendations). https://megurban.gov.in/notifications/RiskInformedMasterPlans/Finalised%20Report%20-%20Shillong.pdf
  • Government of Meghalaya, Urban Affairs Department. Notification No. UAU.76/2022/Pt.I/186 of 29 October 2025 amending the Shillong Master Plan 2041 (Gazette, 13 November 2025), which cites its notification No. UAU.76/2022/Pt.I/74 of 27 November 2024; and notice No. UAU.76/2022/129 of 16 February 2024 of the draft risk-informed master plan for Tura. https://megpns.gov.in/gazette/2025/11/13-11-25-IIA.pdf
  • Government of Meghalaya. Action-taken report of 21 March 2023 in O.A. No. 192 of 2022 before the National Green Tribunal (river jurisdiction of the Shillong Municipal Board and the KHADC; waste removal and traps; RMSI's floodplain zonation study). https://www.greentribunal.gov.in/
  • Shillong Municipal Board. Minutes of the stakeholder meeting of 14 April 2023 on the Wah Umkhrah, Wah Umshyrpi and Wah Umkhen (32 outfalls), and the Chief Secretary's presentation, Restoration of Rivers (five drains; water quality). https://smb.gov.in/other_menu/new_projects/files/MoM%20_RestorationOfRivers.pdf
  • Integrated Research and Action for Development (2020). Disaster Resilience Action Plan, Shillong, IRADe-PR-73(2020), for NMHS (landslide localities; drains; flood events; the State Action Plan on Climate Change as quoted). https://nmhs.org.in/w/pdf/publication/Technical_Report/Dr.Rohit_Mangotra/Shillong_Disaster_Resilience_Action_Plan.pdf
  • Urban Affairs Department (2018). Expression of interest for detailed project reports for the restoration of seven polluted river stretches in Meghalaya. https://megurban.gov.in/adverts/EOI_river_restoration.pdf
  • Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
  • Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
  • Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
  • Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
  • Government of Meghalaya, Forest and Environment Department. Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023, Notification No. FOR/CC/29/2019/Pt/688 of 25 August 2023 (Gazette Part IIA, 7 September 2023), with the report of the Expert Committee (Umiam lake; lists of water bodies), as amended by No. FOR/CC/29/2019/1140 of 13 February 2024 and No. FOR/CC/29/2019/Pt/771 of 6 July 2026. https://megpns.gov.in/gazette/2023/09/07-09-23-IIA.pdf
  • Government of Meghalaya, Forest and Environment Department. Notification No. ENV.1/2007/Pt/110 of 1 November 2017 constituting the Meghalaya State Wetlands Authority (Gazette, 16 November 2017). https://megpns.gov.in/gazette/2017/11/16-11-17-IIA.pdf
  • The Meghalaya Flood Plain Zoning Bill, 2026 (Gazette Extraordinary Part V, 23 February 2026, No. LB.43/LA/2026/2), ss.2(g) and 12; enacted as the Meghalaya Flood Plain Zoning Act, 2026 (Act No. 4 of 2026, as cited in notification No. LL(B)14/2026/2; the Act's text was not read).
  • Government of Meghalaya, Urban Affairs Department. Meghalaya Building Bye-Laws, 2021 (as amended), A2.37, B1(v), B1.1, B2(ii)(c), Section I(f) and Table G1; and Khasi Hills Autonomous District Council, Land Development and Building Regulation, 2015, ss.2.101, 15, 35 and 36.
  • High Court of Meghalaya. In Re: Cleanliness of Umiam Lake v. State of Meghalaya, PIL No. 10 of 2019, orders of 24 May 2023 and 19 February 2024.
  • Meghalaya Power Generation Corporation Ltd. Guidelines for gate operation of Umiam–Umtru Stages III and IV, New Umtru HEP and Myntdu–Leshka HEP Stage I (levels, spillways, release reaches). https://meecl.nic.in/
  • Central Water Commission (2000). Flood Estimation Report for South Brahmaputra Subzone 2(b) (Revised), Report No. SB-2(b)/R-4/44/99; and India Meteorological Department, Extremes of Temperature and Rainfall for Indian Stations (up to 2012) and Monthly Climate Summary, June 2022.
  • South Asia Network on Dams, Rivers and People (2018). Overview of CWC's flood monitoring and forecasting in North East India (transcription of CWC site data). https://sandrp.in/2018/08/05/overview-of-cwcs-flood-monitoring-forecasting-in-north-east-india/
  • OhMeghalaya, The Shillong Times, Highland Post, India Water Portal, Down To Earth, BorderLens, PTI and other regional newspapers (2014–2026). Reports of the Water Resources Department's project report for the Wahumkhrah and the Umshyrpi, Umiam's sedimentation, Ward's Lake and Thadlaskein, the springs and sacred groves, the High Court's wetlands case of 2025, and the floods of 2014, 2022, 2024, 2025 and 2026 (secondary sources).

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Meghalaya building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report