Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Meghalaya the failure is one of missing criteria and of an approval system split by the Sixth Schedule. No document of the Urban Affairs Department, MUDA, a Municipal Board, a District Council, PWD or the Water Resources Department stating a design return period, intensity or runoff coefficient for the storm drains of any town was found; the Bye-Laws 2021 leave drainage to the National Building Code 2016 (D4.2, D5.6), and Shillong's 148.91 km of drains, which "drain directly into the Umkhrah and Umshyrpi rivers", covered "less than 75%" of the city with "sewerage mixing in drains … almost 100%" (Smart City Proposal 2016-17, as quoted in the IRADe/NMHS plan, whose own service-level table gives 85% coverage, a conflict). The approval route shapes this chapter. The Bye-Laws 2021 (Notification No. UAU.73/2016/Pt/402 of 9 March 2021, under s.74 of the Meghalaya Town and Country Planning Act, 1973, as amended to May 2026) apply only to "all the Master Plan Areas, Municipal areas and Scheme Areas within the State" (A1.2), and their "Authority" is "the Meghalaya Urban Development Authority / Autonomous District Councils as applicable" (A2.5); permissions are applied for through the Online Building Permission System, in force since 2025 (Section J, 13 August 2025). The Bye-Laws already ask for much of what a drainage submittal needs: a site plan showing "Surface drains, position and sizes of septic tank and soak pit in cubic dimensions" and rainwater harvesting, a roof plan "indicating drainage and roof slope", and for large projects a services and utilities plan with the "drainage and storm water disposal system"; a soil report from a geotechnical expert where the soil is weak (B1(vi)); cuts of not more than 3.00 m, or 6.00 m to the crest of an RCC wall, with a report of the Geological Survey of India beyond 6.00 m (B1(vii)); a stilt at least 1.20 m above the Highest Flood Level on sloping sites beside a stream or river (B1(v)(b)); the drainage and sediment measures of Section I(b) in hazard-prone areas, among them diversion ditches and swales "into designated sediment basins" and silt fences (2024); and the setbacks and regulated zones of the Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023 (B2(ii)(c) and Section I(f), 2024). Outside those areas, which hold the Town Committee and census-town areas, "47 per cent of the total urban population", governed by the District Councils (CAG, performance audit on solid waste management, 2017-18 to 2021-22), building is regulated in the Khasi Hills by the KHADC's Land Development and Building Regulation, 2015, with permissions issued by its building authority, the KHBSRA, since 2020 (as reported) on Forms I (application), II (commencement) and III (completion); its drawings show "the highest flood level (HFL) reached above the street in front of the building" and "adequate arrangements for proper drainage, sewerage and surface drains", and s.36 requires the plans to "indicate the system of storm water drainage along with points of collection of rain water". The building instruments of the JHADC and the GHADC were not found [TBC]. The two regimes are disputed: the Urban Affairs Department is reported to have notified the three District Councils to implement building bye-laws outside the municipalities on 1 February 2019 (number not found), and the KHADC's Executive Committee is reported to have "outright rejected" the Bye-Laws 2021 on 25 October 2021 as encroaching on Sixth Schedule areas (as reported; present status not known [TBC]); this Manual takes no side. Inside municipal limits no building may be put up without the Board's sanction (Meghalaya Municipal Act, 1973, s.171), and no drain may be led into a Board drain or water-course without its written consent (s.204). The Meghalaya Flood Plain Zoning Act, 2026 lets the Flood Zoning Authority require its permission for activities in notified restricted zones, deemed given if not refused within 90 days (s.12, as read in the Bill), but no Authority, rule or zone has been found. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a design storm. Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the drawings that the Bye-Laws 2021 already require through the Online Building Permission System, beside the site plan with its surface drains and soak pits and with the Section I(b) measures; in the Khasi Hills, with the KHADC's Forms I–III, where the storm-drainage layout of s.36 is the hook for the simplified drainage plan of this chapter, if the District Council adopts the Manual; where cuts exceed 6.00 m, with the report of the Geological Survey of India, which shall then also confirm that no runoff is put into the ground (Clause 4.11); and at completion. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Meghalaya Building Bye-Laws 2021 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the Bye-Laws 2021 steps a Meghalaya applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for almost all of the State, and 45N west of 90° E, a strip about 18 km wide in West and South West Garo Hills that includes the Mahendraganj–Hallidayganj area (this Manual's reading; town coordinates not verified [TBC]); Tura, Williamnagar and Baghmara lie in 46N, Phulbari, Tikrikilla and Ampati are to be confirmed against Survey of India coordinates [TBC], and a project that crosses 90° E uses one zone for all its layers and states which), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC level-monitoring sites on the receiving rivers (not stated in any source found), of the reservoir levels of MePGCL (published in metres for Myntdu–Leshka, New Umtru and Umiam–Umtru Stage IV, and in feet for Umiam–Umtru Stage III, converted at 0.3048 m per foot), and of the flood marks surveyed on ungauged streams, jhoras, pungs and lakes used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Meghalaya has no notified design return period or design storm for its urban drains, and no document of the Urban Affairs Department, MUDA, a Municipal Board, a District Council, PWD, the Water Resources Department or Shillong Smart City Ltd stating a return period, a runoff coefficient or a drain standard was found; the Bye-Laws 2021 refer drainage to the National Building Code 2016 (D4.2, D5.6). The only drainage method found is that of RMSI's multi-hazard assessment of Shillong (2019), which used the IMD station at Shillong, design rainfall "adopted from the Brahmaputra Basin PMP Atlas developed by the Central Water Commission (CWC, 2014) using data from 1957-2010" and the rational formula (as quoted in the IRADe/NMHS plan; the report and the atlas were not obtained [TBC]); the plan itself recommends the "Upgradation of the existing drains" and desilting, without a design storm. The rainfall studies do not supply one either. No intensity–duration–frequency relation with constants was found for any Meghalaya station; the "Eastern" constants of Ram Babu and others repeat the "Central" ones and are not used; IMD's national study (Das et al., 2022) has a genuine panel for Cherrapunji but a Shillong panel that repeats the generic curve of most other cities, which is not used; and the 2(b) plate of the CWC Flood Estimation Report reads about 560 mm in 24 hours at 50 years at Shillong, 1.3 to 2 times every fall recorded there (273.2 mm on 25 June 1988 at Shillong (C.S.O.), IMD; 347 mm in 1960 at the self-recording gauge and 437 mm at Upper Shillong in 1934, CWC). The storms on record exceed anything the drains were built for: 1,563.0 mm in 24 hours at Cherrapunji on 16 June 1995 (IMD), 1,003.6 mm at Mawsynram on 17 June 2022 (IMD's June record), and 48 mm in one hour at the Shillong self-recording gauge on 15 September 1960 (CWC), the only hourly value on record in the State. The southern escarpment lies in subzone 2(c) (Barak), for which CWC has published no Flood Estimation Report. The State's design values are therefore those of Chapter 2: the 2(b) report in the northern foothills, on the plateau outside the Shillong Planning Area and in the Garo hills, the Shillong rule of Clause 2.3.6(c)(i) within it, and the Das et al. (2022) Cherrapunji curve on the escarpment (Clause 2.3.6(f)), and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Meghalaya calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or Urban Affairs:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by Urban Affairs and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the Bye-Laws 2021 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the Urban Affairs list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the approval of the Water Resources Department for a work on, or a discharge to, a river or flood-protection work in its charge, among them the Umkhrah and the Umshyrpi, the consent of MePGCL for a work that drains to Umiam, Kyrdemkulai, Nongkhyllem, New Umtru or Myntdu–Leshka or to a reach below one of their dams, the written consent of the Municipal Board to connect a drain to a Board drain or water-course (Meghalaya Municipal Act, 1973, s.204), the views of the Forest and Environment Department, or of the authority that implements the Meghalaya Waterbodies (Conservation and Protection) Guidelines, 2023 in the area, for a work in the setback or regulated zone of a waterbody, and of the Meghalaya State Wetlands Authority for a work in or next to a wetland, the permission of the Flood Zoning Authority for an activity in a restricted zone, once one is notified under the Meghalaya Flood Plain Zoning Act, 2026 (none has been; the Act deems permission given if it is not refused within 90 days), the groundwater no-objection certificate of the District Level or State Level Committee on ground water, on which the Water Resources Department serves, for a well or abstraction, the consent of PWD (Roads), NHAI or NHIDCL for a discharge to a side drain, catch-water drain or culvert of one of their roads, the consent of MSPCB for a discharge that carries effluent, the consent of the District Council, or of the Dorbar Shnong under the District Council's rules, for a work on a jhora or village drain outside municipal limits, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example the Shillong Cantonment Board, NSTDA in New Shillong [TBC] or Shillong Smart City Ltd until its drains are handed over), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Meghalaya because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Meghalaya extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Meghalaya has no dated State order fixing pre-monsoon desilting: the IRADe/NMHS plan for Shillong recommends "Desilting to avoid flooding during monsoons" by PWD and the Shillong Municipal Board (2020), without a date. The drains are run by several hands, and no rule divides them: the Municipal Boards for the drains, public streams, springs and tanks vested in them within municipal limits (Meghalaya Municipal Act, 1973, s.62); PWD (Roads), and NHAI and NHIDCL on NH-6 and the Shillong–Dawki road, for the road drains and culverts, which carry much of the runoff of the hill towns; the Shillong Cantonment Board in the Cantonment, where "each house in the civil areas of cantonment has their own septic tank" (State action-taken report to the National Green Tribunal, 2023); NSTDA in New Shillong [TBC]; the District Councils, and the Dorbar Shnongs under their rules, for the village drains and jhoras outside municipal limits, only parts of the Umkhrah and the Umshyrpi lying within the Shillong Municipal Board's area and the rest under the KHADC (the same report); the Water Resources Department for the rivers and flood works; PHED, nodal for sanitation outside the municipalities since 2023; and Shillong Smart City Ltd for its works, among them rainwater harvesting at 52 locations and "in-situ Nallah Treatment Technology" (as reported). The waste traps, stone bunds and in-situ treatment of five drains entering the Umkhrah, built since 2022 (the same report), need their own maintenance. The gates that matter most are run by rules made for other purposes: the reservoirs of MePGCL are operated for power, and their gate-operation guidelines for Umiam–Umtru Stages III and IV, New Umtru and Myntdu–Leshka say that, because the reservoirs are small and gates open often "during Monsoon as well as during Non-monsoon period", notice of releases is "not practicable" and warnings are given by siren, telephone or SMS; no guideline was found for Umiam Stage I, where releases were begun in August 2024 at 3,216.15 ft on an IMD warning (as reported). No operating rule for any sluice, flap gate or pumping station in a Meghalaya town, linking it to a stream level, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 March) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Meghalaya, the pre-monsoon inspection of sluices, flap gates, non-return valves, debris racks, solid-waste traps, sediment traps, debris basins, culvert inlets and pumped facilities, including the gates on outfalls to Umiam lake and the other reservoirs, pungs and lakes and on outfalls that the Umkhrah and the Umshyrpi in Shillong, the Umngot at Dawki or the Jinjiram on the Garo plains can close, with the desilting and the clearance of debris, garbage and slide material from every drain, jhora, inlet, rack, trap, basin and culvert and the pump duty and gate seal tests, shall be completed by 31 March; inlets, trash and debris racks, culverts, outfall gates and pumped facilities, with their standby generators, shall be certified ready on the same date, with every gate on an outfall to a river or reservoir operated through its full travel, because the season of this Manual begins on 1 April and the storms of April and May are among the State's largest. Pumps, their standby power, gates and racks shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to a reservoir of MePGCL or to a reach below one of its dams until the releases have ended, if that is later. Racks, culverts, sediment traps and jhora inlets shall be cleared again by 31 May, of the debris and garbage of the April and May storms, before the south-west monsoon arrives, and every public drain, jhora inlet, rack, trap, basin and culvert in every town shall be cleared of the sediment, slide debris and garbage of the season by 15 November.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December. The monsoon season of this Manual, 1 April to 31 October, is bracketed: the pre-monsoon storms of April and May, the south-west monsoon from about the first week of June to about mid-October, and the late part of October after the withdrawal. December to February is marked as the dry works window, and March and November as months with storms outside the season. Lanes show routine inspections; desilting, the clearance of debris, garbage and slide material, the pre-monsoon inspection, the readiness of inlets, racks, culverts, gates and pumps and the Form 10-7 declaration, all by 31 March; standby of pumps, gates and racks from 1 April to 31 October; a mid-season clearance by 31 May; a post-season clearance by 15 November; inspections after heavy rainfall in any month; the reporting year from 1 April to 31 March; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Monsoon season of this Manual: 1 Apr–31 Oct Dry: works window Dry Storms Storms Pre-monsoon storms South-west monsoon Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 Mar 31 May 31 Oct 15 Nov Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 Mar: desilting; debris, garbage and slide material cleared; inspection; inlets, racks, culverts, gates and pumps ready. 1 Apr–31 Oct: standby. By 31 May: mid-season clearance of racks, culverts, traps and jhora inlets. By 15 Nov: post-season clearance. After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including March and November storms) Annual declaration Form 10-7 Form 10-7 by 31 Mar, closing the reporting year (1 Apr–31 Mar): Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one season, 1 Apr–31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 March, 31 May, 31 October and 15 November are fixed (set by this Manual). December–February is practically dry. Pre-monsoon storms: Cherrapunji 644.2 mm in 24 h on 16 April 1990 and 812.0 mm on 25 May 1916. The south-west monsoon arrives about the first week of June and withdraws about mid-October. Late-season storms: Cherrapunji 594.0 mm on 11 October 1975; Shillong 262.0 mm on 8 October 2004. Outside the season: Cherrapunji 587.4 mm on 23 March 1994 and 332.2 mm in November 1917; Shillong 138.2 mm on 16 November 2007 (all IMD).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October, and its first two months bring some of the State's largest storms: Cherrapunji recorded 644.2 mm in 24 hours on 16 April 1990 and 812.0 mm on 25 May 1916 (IMD, Extremes), more than the 50-year 24-hour depth of any plains State; CWC's high flood levels on the Myntdu at Kharkhana (47.0 m, 23 April 1995) and the Umngot at Dawki (73.47 m, 28 May 2006) fall on pre-monsoon dates (CWC levels as transcribed by SANDRP, as reported); the CWC Flood Estimation Report for subzone 2(b) finds the rainfall "spread over a period of eight months, i.e. from March to October", with thunderstorms in April and May and "May rainfall … more than the September rainfall"; and the floods and landslides of 30–31 May 2025 struck 86 villages in 10 districts before the monsoon arrived (as reported). NDMA (2010) sets 31 March for pre-monsoon desilting nationally, and this Manual keeps that date; the 31 May deadline of the mountain editions of this series would leave the April and May storms uncovered. December to February is "practically dry" (the same report) and is the works window. No dated State or municipal order fixing a deadline for desilting was found; the IRADe/NMHS plan for Shillong recommends desilting "to avoid flooding during monsoons" (2020), without a date. This Manual therefore takes 31 March for desilting and the clearance of debris, garbage and slide material, the pre-monsoon inspection, the annual declaration and the readiness of inlets, racks, culverts, gates and pumps, with no later readiness date. The south-west monsoon itself arrives about the first week of June: the old IMD normal date for Shillong is 1 June (as reported; IMD's revised normals for Shillong were not read [TBC]), and in 2026 the monsoon reached "substantial parts" of the North East on 7 June, "two days later than its normal" (as reported). Racks, culverts, sediment traps and jhora inlets are therefore cleared again by 31 May, after the April and May storms and before the onset. The monsoon withdraws from Meghalaya about mid-October (expected by 14 October in 2025 and reported for the North East on 15 October 2026, as reported), but storms continue after it: Cherrapunji recorded 594.0 mm on 11 October 1975 and Shillong 262.0 mm on 8 October 2004 (IMD), and the Garo Hills floods of 4–6 October 2024 drowned three people at Dalu (as reported); pumps, gates and racks are therefore kept on standby to 31 October (Figure 10.3). Large falls also come outside the season, 587.4 mm on 23 March 1994 and 376.9 mm on 18 February 1993 at Cherrapunji, and 332.2 mm there in November 1917 and 138.2 mm at Shillong on 16 November 2007 (IMD), and the jhoras fill with sediment, slide debris and garbage during the season, so every town clears its drains a second time by 15 November. The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Meghalaya cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Meghalaya drainage show up only in the first monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Meghalaya Building Bye-Laws 2021 are made and from the municipal Acts. The graduated steps are set by this Manual. In Meghalaya the courts and the National Green Tribunal have become the working regulators of the streams and lakes, and the District Councils and the Dorbar Shnongs act where the State's rules do not reach. The High Court, in In Re: Cleanliness of Umiam Lake (PIL No. 10 of 2019), barred any construction "within 50 metres of the high-water mark of the relevant waterbody without the express previous leave of this Court" (24 May 2023), found the waterbody guidelines of July 2023 to "fall woefully short" and "more of a formality", observing that "Several of the rivers, including the Umkhrah in Shillong itself are carrying such contaminated water that they may not be fit even to step into" (19 July 2023), and closed the PIL on 19 February 2024 once the amended Waterbodies Guidelines were taken on record, so the 50 m bar has ended. The Tribunal, on the report "Poison flowing in Shillong's rivers", directed that "the raw fecal matter is not discharged into fresh water streams and Umkhrah and Umshyrpi rivers" (O.A. No. 192 of 2022, 22 November 2022), and the State reported fencing, waste traps, in-situ treatment of five drains and on-site treatment plants (action-taken report, 21 March 2023) and undertook to ring-fence ₹109 crore for liquid and solid waste (letter of 22 December 2023); the Tribunal also supervises the polluted stretches (O.A. No. 673 of 2018) and stopped rat-hole mining throughout the State on 17 April 2014 (O.A. No. 73 of 2014), after which the Supreme Court allowed mining on private and community land subject to leases and mining plans under the MMDR Act (C.A. No. 10720 of 2018, 3 July 2019). The statutes carry weak powers. The Meghalaya Municipal Act, 1973 lets a Board require an owner "to improve bad drainage" within 15 days (s.190), have land within 100 ft of a drain drained (s.206) and demolish a drain led into a Board drain or water-course without consent, but the fines are nominal: up to ₹50 for such a drain (s.204) and up to ₹25 for letting sewage run onto a road or into a roadside drain (s.205). The Shillong Municipal Board inspected 1,169 households along the Umshyrpi and the Wahumkhrah and served notices on 47 under s.201 and the Environment (Protection) Act, 1986, with a fine of ₹500 a day for faulty septic tanks, and told the public not to discharge untreated sewage into drains and water bodies (notice No. SMB/PW/40/2023/10 of 17 February 2023). The Bye-Laws 2021 are enforced through the building permission and the completion stage. Outside the municipalities the District Councils' rules apply: the KHADC's Solid Waste Management Rules, 2022 empower the Dorbar Shnong to fine polluters (as recorded in the minutes of the meeting on the Wah Umkhrah, Wah Umshyrpi and Wah Umkhen, 14 April 2023), the KHADC told all headmen not to discharge "untreated waste, faecal matter and garbage" into the two rivers (notice of 13 March 2023, as recited in the action-taken report), and its Land Development and Building Regulation, 2015 makes the Executive Committee, the Town Committee and the Dorbar Shnong responsible for keeping development from damaging "catchment areas, water sources, spring sheds, streams and rivers", with restoration at the polluter's cost (s.15). The Meghalaya Flood Plain Zoning Act, 2026 provides a fine of up to ₹10,000 and ₹500 a day for breaching a notified restriction (s.13, as read in the Bill), but no zone has been notified. The CAG's performance audit of solid waste management in urban areas (2017-18 to 2021-22) found that no Municipal Board, and neither the JHADC nor the GHADC, had framed bye-laws under the Solid Waste Management Rules 2016, while the KHADC had notified its Solid Waste Management Act, 2020 in February 2022 (report number [TBC]); no audit of storm drainage or flood works in Meghalaya was found. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river at the nearest CWC level-monitoring site (the Umngot at Dawki, the Umnohryngkew at Therriaghat, the Myntdu at Kharkhana, the Bugi at Dimapara or the Dareng at Sibbari, none of which has a warning or danger level) or of the receiving reservoir, pung or lake, with the level of a MePGCL reservoir as the operator records it, converted from feet where so published, and, where it is gauged, at the outfall, each on a named datum, with any reading of a local gauge kept apart from the CWC levels; for an ungauged stream or jhora, which includes the Umkhrah and the Umshyrpi in Shillong, the flood marks surveyed after the event and the boulders, slide debris and garbage deposited at crossings, racks and culverts; the state of every sluice, flap gate, debris rack, solid-waste trap, sediment trap, debris basin and pumping station on the outfall and on the drain upstream of it, with the volume of debris and garbage removed from each, the hours each pump ran and any loss of power; and the gate openings and releases of any MePGCL dam that sets the receiving level, such as Umiam–Umtru Stages III and IV, New Umtru or Myntdu–Leshka, with the times of its siren, telephone or SMS warnings;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), MSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Meghalaya's floods and landslides have been counted more often than they have been reviewed, and the counts conflict. In the Garo Hills floods and landslides that followed the torrential rain of 21 September 2014, 52 deaths were reported by 28–29 September and more than 60 in a later account, with damage put at more than ₹1,500 crore and over 200 villages submerged by the Brahmaputra and the Jinjiram, in what was called the "worst natural calamity that struck the state in the past century" (all as reported); no rainfall measurement for the event was found. In June 2022, when Mawsynram recorded 1,003.6 mm in the 24 hours to 08:30 on 17 June and the rainfall over Assam and Meghalaya was the highest since 1901 (IMD), 13 deaths were reported on 17 June and 32 or 34 since 1 April, depending on the date of the count (as reported). The floods and landslides of 30–31 May 2025 affected 86 villages in 10 districts and killed six people, by MSDMA's count as reported; the Garo Hills floods of 4–6 October 2024 killed 15 by 6 October, three of them drowned at Dalu and seven in a landslide at Hatiasia Songma (as reported); and the collapse of the Shillong–Dawki road at Laitlyngkot and the Umngot flood at Dawki in June 2026 came with no rainfall value published (as reported). The IRADe/NMHS plan for Shillong tabulates the flash flood of July 2019 at Polo, Forest Colony and Mawlai after "more than 72.2 mm of rain on 9th July 2019", five deaths and 1.5 lakh people affected in July 2020, and 13 deaths in September 2020, and cites the Revenue and Disaster Management Department for "approximately 22 deaths" from landslides in 2014. MSDMA's official tolls for 2014, 2022 and 2025 were not found [TBC]. No review of any flood in a Meghalaya town, and no record of flood extents, depths or durations kept by any Municipal Board, District Council or MSDMA, was found, and for most of these events no gauge recorded the rain. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Much of Meghalaya's drainage record is public: the Bye-Laws 2021 and their amendments on the Urban Affairs Department's website; the Waterbodies Guidelines, the KHADC's Land Development and Building Regulation, 2015, the Flood Plain Zoning Bill, 2026 and the notification of the State Wetlands Authority in the Gazette of Meghalaya; the consolidated Meghalaya Municipal Act, 1973; NESAC's report for the risk-informed master plan of the Shillong Planning Area, the amendment of the Shillong Master Plan 2041 and the notice of the draft master plan for Tura; the State's action-taken report and the joint committee's report to the National Green Tribunal on the Shillong rivers, the minutes of the meeting of 14 April 2023 on their restoration and the Chief Secretary's presentation with its water-quality table; the High Court's orders on Umiam lake; CPCB's list of polluted river stretches (2025); the executive summary of the CAG's audit of solid waste management; the IRADe/NMHS plan for Shillong; MePGCL's gate-operation guidelines; and IMD's station extremes and monthly summaries. Much else could not be found in the public domain: the notified text of the Shillong Master Plan 2041 and any drainage chapter; the gazetted text of the Flood Plain Zoning Act, 2026, the constitution of the Flood Zoning Authority and any zone; the building instruments of the JHADC and the GHADC, the KHBSRA's own rules and the notification of 1 February 2019 on the District Councils' role; RMSI's floodplain zoning study of the Umkhrah and other stretches and its multi-hazard assessment of Shillong; the design basis of any storm drain, including the Smart City and AMRUT works and the Water Resources Department's project report for the Wahumkhrah and the Umshyrpi; CWC's site sheets and gauge datums; the levels and gate rules of Umiam Stage I; MSDMA's operating procedures for urban floods and its official tolls; the number of the CAG's report; and an inventory of the gates, racks, waste traps and pumping stations of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)