Annexes to Chapter 5Downstream and Tailwater Analysis
These annexes support Chapter 5. Annex 5C is a worked example of the outfall-closed check of Clause 5.10, for the illustrative facility of Annex 4C. Annexes 5A and 5B need tidal, surge, survey and river data that this draft does not yet contain; each lists what the chapter already sets, gives the intended layout and states the interim rule of Chapter 5 that applies until it is published. Forms 5-1 and 5-2 are the submittal forms required by Clause 5.14. They are draft forms and have no statutory status.
Annex 5A — Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment
Supports Clauses 5.7, 5.9, 5.10, 5.11 and 5.12 of Chapter 5.
5A.1 Table 5A.1 shows how the values of this annex enter the design tailwater levels of Table 5.1. The sea-level allowance is set by Clause 5.7.4 and does not depend on this annex.
Table 5A.1 — Use of the Annex 5A values in the design tailwater (Table 5.1)
| Design case | Tailwater | Annex 5A values used | Chapter value |
|---|---|---|---|
| Minor-system design | MHWS + SLA | MHWS | SLA ≥ +0.3 m (Clause 5.7.4) |
| Major-system and storage design | HAT + surge + SLA | HAT; 10% AEP surge (Clause 5.7.3(a)) | SLA ≥ +0.3 m |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA | 1% AEP still-water level (Clause 5.7.3(b)) | SLA ≥ +0.3 m |
| Datum conversion | Chart datum to project datum | Offset from chart datum to the Survey of India datum (Clause 5.7.2(b)) | — |
Not prepared for Mizoram. Mizoram has no coast, so no outfall in the State has a tidal tailwater, and this annex has no Mizoram content (Clause 5.1.4). Its tables are kept, empty, so that the annex and table numbers match the other editions of this Manual. Rows F1 to F7 of Form 5-1 are entered as "not applicable", and the tailwater is derived under rows F8 to F10; for an outfall to a lui, row F10 records the study, the flood marks, the bed survey and the check of the lui to the next confluence of Clause 5.8.5(a) or (b), and for an outfall to the Tuirial or Serlui B reservoir, the operator's levels and their datum, or the interim level, of Clause 5.8.5(e).
Table 5A.2 — Tidal datums, surge and still-water levels by coastal segment (layout)
| Coastal segment | Reference port and tide-table edition | MSL (m CD) | MHWS (m CD) | HAT (m CD) | CD to Survey of India datum (m) | 10% AEP surge (m) | 1% AEP still-water level (m CD) | Wave set-up (m), open-sea outfalls | Sources |
|---|---|---|---|---|---|---|---|---|---|
Annex 5B — Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map
Supports Clauses 5.2, 5.3, 5.8 and 5.13 of Chapter 5.
5B.1 Table 5B.1 lists the water bodies that Chapter 5 already names. It is not complete: the annex will add the extents of each reach, the other rivers, canals and mouths of the State, and a map.
Table 5B.1 — Water bodies named in Chapter 5
| Water body | Region | Listed as | Clause |
|---|---|---|---|
| Lui of the ridge towns: Lunglei, Serchhip, Champhai, Kolasib, Siaha, Lawngtlai, Mamit, Khawzawl, Saitual, Hnahthial and others | Statewide | Major drains; ungauged, no published flood level [TBC]; free outfall with energy dissipation; 1% AEP study with bulking and blockage and surveyed flood marks; check of the lui to the next confluence; outfall at least 0.5 m above the highest surveyed bed level; lock (where the invert is below the design level) the storm plus recession, not less than 24 hours; no outfall within 15 m of a tuikhur or onto a quarry face | 5.2, 5.8.1, 5.8.5 |
| Chite lui (with its tributaries, and the Muthi and Tuipawl lui) to the Tuirial; Ser lui (with the Ramri, Tuikal, Vai and Zawngkawt lui) to the Tlawng | Aizawl | Major drains and city lui; ungauged, no published flood level [TBC]; item (a) rule with the MZ-B rainfall; the Chite and Tuikual streams CPCB Priority II and the Lawibual stream Priority III (Clause 8.9); eight check dams proposed in the master plan, not to raise any outfall level | 5.2, 5.8.1, 5.8.5 |
| Tlawng (Dhaleswari) at Sairang, Bairabi and the CWC site at Keitum | Aizawl, Kolasib, Lunglei districts | Riverine outfall reach; CWC level sites at Sairang (active hydrograph) and Keitum, no highest level printed [TBC]; no warning or danger level; modelled 1% AEP level and surveyed flood marks (June 2018 and later); valley-floor outfalls flap-gated, lock the whole 72-hour storm, not less than 72 hours; runs north to the Barak plain, where the adjoining edition governs | 5.8.1, 5.8.5 |
| Tiau at Champhai and Zokhawthar; the Champhai flats | Champhai district; Myanmar border | Riverine outfall reach and valley-floor land; no CWC level site; modelled level and flood marks (June 2025 and later); lock not less than 72 hours; no level across the border | 5.8.1, 5.8.5 |
| Kau (Tuichawng) at Chawngte; Tuichang and Tuichawng at their CWC sites; Tuipui at Bailley Bridge | Lawngtlai and Lunglei districts; Champhai district | Riverine outfall reaches; CWC level sites with no highest level printed [TBC]; modelled level and flood marks; lock not less than 72 hours on valley-floor land | 5.8.1, 5.8.5 |
| Khawthlangtuipui (Karnaphuli) at Tlabung | Lunglei district (MZ-D1) | Riverine outfall reach; river-flood town (June 2017, June 2018, July 2019, August 2023, as reported); no CWC level site listed; design for the river at flood level from a model and surveyed flood marks; flap gates; lock not less than 72 hours, longer where flood marks show it; runs into Bangladesh, no level across the border | 5.8.1, 5.8.5 |
| Tuirial (Sonai) reservoir of NEEPCO and the Tuirial below the dam | Kolasib district | Reservoir outfalls and release reach; FRL 90.5 m, MDDL 68.0 m, normal tailwater 30.7 m (CERC); tailwater 91.0 m (FRL + 0.5 m) until NEEPCO gives the MWL, datum [TBC]; CWC Turial gauge HFL 149.0 m (17 June 1995), not to be related to the reservoir levels [TBC]; release: largest recorded, else spillway capacity, else unattenuated 1% AEP inflow [TBC]; dam-break peak 3,035.34 m³/s (as reported) recorded, not a design release; NEEPCO's consent | 5.8.1, 5.8.3, 5.8.5 |
| Serlui B reservoir and the Serlui below the dam | Kolasib district | Reservoir outfalls and release reach; FRL and MWL not found [TBC]; operator's levels in writing, or the surveyed shore line or spillway crest + 0.5 m; release as for the Tuirial; the State power department's consent | 5.8.1, 5.8.3, 5.8.5 |
| Chhimtuipui (Kaladan) at the CWC's Sihthangpui site | Lawngtlai district; to Myanmar | Riverine outfall reach; no highest level printed [TBC]; no level across the border; model boundary far downstream with a sensitivity run | 5.8.1, 5.8.5 |
| Tuivai and the northern rivers where they leave the State | Northern border | Riverine outfall reaches; the adjoining Barak-valley edition governs the reaches downstream; its levels bound the model's downstream boundary only | 5.8.1, 5.8.5 |
| Palak Dil (Pala wetland) and Tam Dil | Siaha district (Mara Autonomous District Council area); near Saitual | Dil outfalls; no level found [TBC]; spill level plus head; custodian's consent (and the District Council's in its area); debris, waste and sediment traps; no sewage; no dil used as a detention pond; Palak Dil a Ramsar site (designated 31 August 2021 per its RIS; announced 26 July 2022, as reported) | 5.8.5 |
| Drains of the Aizawl Municipal Corporation, the Lunglei Municipal Council, Village Councils, PWD, PHED and the national-highway agencies 1.0 m wide or more; village drains and lui in the Autonomous District Council areas | Mizoram | Major drains; owner's consent (the Chairman's written permission, s.295, and the municipality's consent, s.296, of the Municipalities Act within municipal areas; PWD and the Corporation both on State roads in the Corporation's area), design water level and flap gate | 5.2, 5.8.5 |
| Tuirial and Serlui B dams | Tuirial, Serlui | Releases and gate operation to be included in river levels (release records and operating rules [TBC]); releases, not notices | 5.8.3, 5.8.5 |
| River mouths subject to sand-bar closure | None in Mizoram | Not applicable (Clause 5.1.4) | 5.13.1 |
To be prepared. This annex will list and map (a) the major drains of each basin plan, (b) the riverine outfall reaches where backwater shall be modelled, with their upstream and downstream limits and the source of their design flood levels, and (c) the river mouths and creek inlets subject to seasonal sand-bar closure, with the most recent pre-monsoon bar crest levels and any IWRD mouth-maintenance programme. It needs IWRD river and canal records, design and recorded flood levels, reservoir operating rules, mouth-condition, dredging and bar-cutting records and pre-monsoon bar surveys (IWRD), the drain inventories of the Aizawl Municipal Corporation and other local bodies, basin stormwater master plans (Chapter 11), and base mapping from the Survey of India and NRSC. Until it is published: every river, IWRD canal, the Chite lui and its tributary lui through eastern Aizawl and the Ser lui and its streamlets through western Aizawl, the lui of Lunglei and the other ridge towns, every drain that discharges through a flap gate on the valley floors of Sairang, Bairabi, Vairengte, Tlabung, Chawngte or the Champhai flats, any drain built or held by the Aizawl Municipal Corporation, the Lunglei Municipal Council, a Village Council, a District Council, PWD, PHED or a national-highway agency with an internal width of 1.0 m or more, and every lui or other natural channel that drains 8 ha or more and every tidal creek is a major drain (Clause 5.2); the water bodies of Table 5B.1 are riverine outfall reaches (Clause 5.8.1); and the mouths of the coastal States' rivers (there is none in Mizoram) are assumed closed at the start of the monsoon unless the IWRD certifies otherwise (Clause 5.13.2).
Table 5B.2 — Attributes of the Annex 5B layers (layout)
| Field | Content | Unit or format |
|---|---|---|
| feature_id | Unique identifier | text |
| name | Name of the drain, river, canal, creek or mouth | text |
| category | Major drain; riverine outfall reach; mouth subject to sand-bar closure | text |
| clause | Clause of Chapter 5 under which it is listed | text |
| reach_limits | Upstream and downstream limits of the reach | text |
| design_flood_level_source | IWRD design or highest recorded flood level, or hydraulic model (Clause 5.8.2) | text |
| reservoir_release | Upstream reservoir or tank and its operating rule, where any (Clause 5.8.3) | text |
| bar_crest_level | Most recent pre-monsoon bar crest level, for mouths | m (Survey of India datum) |
| mouth_programme | IWRD mouth-maintenance programme and certification (Clause 5.13.2) | text |
| source | Source agency and date | text |
| geometry | Line (drains and reaches) or point (mouths) | line / point |
Annex 5C — Worked example: outfall-closed check for a hillside colony in Lunglei town draining to a hill stream (lui)
Supports Clauses 5.9, 5.10, 5.11 and 5.12 of Chapter 5 and Clause 4.6.6 of Chapter 4.
Illustrative — not design values. This example applies the outfall-closed check of Clause 5.10 to the revised detention facility of Annex 4C. The site, its levels and its receiving drain are invented to show the method. No tidal level is used: the tide enters only through the illustrative statements in Table 5C.1 about whether the receiving drain is above or below the site outlet.
Inputs
5C.1 The site is the 2.0 ha flood-sensitive site of Annex 4C, a hillside colony in Lunglei town (flood-sensitive catchment (i) of Clause 4.5.3.2). It discharges through its own outlet chamber and a flap gate to a public storm drain that runs down a lined chute to a hill stream (lui), whose level rises over the drain's outlet when the lui runs full in a storm and stays up while the storm and its recession last, so Clause 5.10.1 applies to the facility. To show the method, this example uses the two 6-hour lock windows of Clause 5.10.3, as the coastal editions of this Manual do. In Mizoram an outfall to a lui whose invert is below its design level is closed for the design storm and the lui's recession, and for not less than 24 hours, and for the whole storm where the 48- and 72-hour storms are run; an outfall on valley-floor land below the design level of its river is closed for the whole 72-hour storm and not less than 72 hours; an outfall at Tlabung is closed for not less than 72 hours, and longer where flood marks show the Khawthlangtuipui held up for longer; an outfall to a release reach below the Tuirial or Serlui B dam is closed for not less than 72 hours; and an outfall below the design level of either reservoir is closed for the whole storm, under Clause 5.8.5. In each of those cases that lasts longer than the windows used here, the facility must store or pump the volume of the longer closure, up to the whole storm volume (Clause 5.9.4); that needs more storage, or pumping, than this example shows. The routing, the volume balance of Clause 5.10.4 and the assessment are the same. The public drain's own outfall to the lui would also need the energy dissipator, the check of the lui to the next confluence and the invert above the range of bed movement of Clause 5.8.5(a), and the debris rack and the bulking factor of Clause 6.3.6; and on Lunglei's slopes, on natural ground steeper than 10° or on Surma-group shale at any slope, the facility itself would be a lined tank, not an infiltrating basin, and its overflow would go to a lined drain, never onto the slope (Clause 4.11 (hill rule)).
Table 5C.1 — Inputs (Illustrative — not design values)
| Item | Value | Basis |
|---|---|---|
| Facility | Revised facility of Annex 4C: 2,500 m² plan area, vertical walls; 170 mm orifice at the floor; 460 mm orifice, invert 0.53 m | Annex 4C, Table 4C.14 |
| Storm | 1% AEP, 48 h, peak day last, AMC III; 72 h also run | Clause 5.10.2 |
| Inflow | Post-development 1% AEP hydrographs of Annex 4C (48 h: 8,420 m³; 72 h: 9,468 m³) | Annex 4C |
| Receiving drain levels at the connection, J1, J2 and J3 | Below the site outlet invert (from the drain owner's model) | Illustrative input |
| Receiving drain during each lock window | Backs up above the site outlet invert, so the site cannot discharge | Illustrative input; Clause 5.10.3(b) |
| Flap gate on the site outlet | Set 0.15 m below the orifice inverts in the outlet chamber, so that outside the lock windows its opening head and head loss do not affect the orifice control | Illustrative input; to be confirmed from the certified curve (Clause 5.11.2) |
| Lock windows | Two of 6 h each, starts 12.4 h apart (semi-diurnal tide) | Clause 5.10.3(a) |
| Pumps | None | — |
5C.2 Cases of Table 5.2. Because the receiving drain stays below the site outlet in J1, J2 and J3 (Table 5C.1), those cases give the free-outfall results of Annex 4C: in J2 the 1% AEP maximum water level is 1.17 m (2,913 m³), and in J3 (10% AEP, 48 h) it is 0.77 m. R1 and R2 do not apply, because the site does not drain to a river. J4, the outfall-closed check, is worked below.
Lock windows (Clause 5.10.3)
5C.3 The peak 1-hour block of the final 24 hours of the 48-hour storm is 35:35–36:35 h, with 98.2 mm (the 1-hour depth of Table 4C.2). Two runs are made:
- Run A: the first window is centred on that block: 33:05–39:05 h; the second starts 12.4 h later: 45:29–51:29 h.
- Run B: the first window starts at that block: 35:35–41:35 h; the second: 47:59–53:59 h.
For the 72-hour storm, every time is 24 h later.
5C.4 Gravity discharge is zero inside each window. Outside the windows the outlet discharges through the orifices of Table 4C.10. The routing is the same level-pool routing as in Annex 4C.
Results
Table 5C.2 — Outfall-closed check results (Illustrative — not design values)
| Storm | Run | Lock windows (h:min) | Maximum stage (m) | Maximum storage (m³) | Time of maximum (h:min) | Largest release after a window (L/s) |
|---|---|---|---|---|---|---|
| 1% AEP, 48 h | A | 33:05–39:05; 45:29–51:29 | 2.01 | 5,019 | 39:05 | 566 |
| 1% AEP, 48 h | B | 35:35–41:35; 47:59–53:59 | 2.10 | 5,238 | 41:35 | 584 |
| 1% AEP, 72 h | A | 57:05–63:05; 69:29–75:29 | 2.00 | 5,012 | 63:05 | 565 |
| 1% AEP, 72 h | B | 59:35–65:35; 71:59–77:59 | 2.09 | 5,233 | 65:35 | 584 |
Run B of the 48-hour storm governs. The first window closes the outlet just as the storm peak arrives, so the whole peak is stored. The second window arrives when the facility has drained to about 0.7 m, below the Stage 2 orifice, and adds little.
5C.5 Volume balance (Clause 5.10.4). Table 5C.3 gives the balance for Run B. The outflow in each period is found by continuity: outflow = storage at start + inflow − storage at end.
Table 5C.3 — Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Period (h:min) | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| 0:00–35:35, before window 1 | 3,817 | 2,213 | 0 | 0 | 1,604 |
| 35:35–41:35, window 1 | 3,634 | 0 | 0 | 1,604 | 5,238 |
| 41:35–47:59, between windows | 941 | 4,423 | 0 | 5,238 | 1,756 |
| 47:59–53:59, window 2 | 28 | 0 | 0 | 1,756 | 1,784 |
| After 53:59 | 0 | 1,784 | 0 | 1,784 | 0 |
| Total | 8,420 | 8,420 | 0 | — | — |
Check for window 1: V_inflow = 3,634 m³ ≤ V_storage available + V_pumped + V_gravity = (5,238 − 1,604) + 0 + 0 = 3,634 m³. The facility therefore needs 5,238 m³ of storage, which the routing confirms.
Table 5C.4 — Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Time (h) | Inflow (L/s) | Outlet | Outflow (L/s) | Stage (m) | Storage (m³) |
|---|---|---|---|---|---|
| 24 | 20 | Open | 18 | 0.18 | 445 |
| 28 | 39 | Open | 24 | 0.25 | 621 |
| 32 | 59 | Open | 32 | 0.36 | 906 |
| 34 | 85 | Open | 37 | 0.47 | 1,166 |
| 36 | 286 | Closed | 0 | 0.78 | 1,944 |
| 38 | 106 | Closed | 0 | 1.73 | 4,321 |
| 40 | 66 | Closed | 0 | 1.96 | 4,904 |
| 42 | 51 | Open | 529 | 1.79 | 4,472 |
| 44 | 42 | Open | 204 | 0.87 | 2,181 |
| 46 | 37 | Open | 49 | 0.74 | 1,854 |
| 48 | 33 | Open | 47 | 0.70 | 1,756 |
| 50 | 0 | Closed | 0 | 0.71 | 1,784 |
| 54 | 0 | Closed | 0 | 0.71 | 1,784 |
| 56 | 0 | Open | 43 | 0.58 | 1,459 |
| 60 | 0 | Open | 32 | 0.37 | 921 |
| 66 | 0 | Open | 16 | 0.16 | 397 |
| 72 | 0 | Open | 7 | 0.06 | 162 |
Assessment
5C.6 Clause 5.10.4(a). The facility of Annex 4C reaches 1.17 m in J2, and its spillway crest is at 1.35 m (Annex 4C). In the outfall-closed check the stage reaches 2.10 m, so the spillway would operate. The facility of Annex 4C fails the check.
5C.7 Remedy. Pumping (Clause 5.12) does not help here: during the lock windows the receiving drain is itself closed, and pumping into it would raise its level, which Clause 5.12.3 does not permit. The remedy is more storage. Keeping the plan area of 2,500 m² and the outlets of Annex 4C:
- the facility must hold 5,238 m³, to a stage of 2.10 m;
- the spillway crest is set above that stage, with the 0.15 m clearance recommended in Clause 4.9.3: 2.25 m;
- with the 4.0 m spillway of Annex 4C (head 0.30 m), the maximum level with the spillway flowing is 2.55 m, and with 0.3 m freeboard the top of the walls is at least 2.85 m above the floor.
The outfall-closed check therefore governs the storage: 5,238 m³ against 2,913 m³ from the release-rate checks, about 80% more. A larger plan area would make the facility shallower; the outlet, caps and drawdown would then have to be re-checked, because the stage–discharge relationship changes.
5C.8 Release after the lock. When the first window ends, the stored water is released under a head of about 2 m, at up to 584 L/s. This is above the 100-yr cap of 356 L/s. Clause 5.10.4 allows this, because the release reaches a drain that has itself just reopened, and requires it to be included in the J4 run of the downstream analysis (Clauses 5.4 and 5.9) and reported on Form 5-1, Section H.
5C.9 Drawdown after the storm (Clause 5.10.5). The J1 tidal curve stays below the site outlet (Table 5C.1), so the drawdown of Annex 4C applies: 45.3 h for 90% of the 10-yr storage with the low-flow orifice 50% blocked, within the 48-hour limit of Clause 4.7. In Run B, 90% of the maximum J4 storage is released 22.6 h after the maximum.
5C.10 Other requirements.
- The flap gate on the site outlet is inspected and operated before 31 March each year and after every event in which it closed against a storm flow (Clause 5.11.5).
- The deeper facility is checked for flotation with groundwater at the design groundwater level; in the valley floors and river terraces of the Tlawng, Tuirial and Khawthlangtuipui (at Sairang, Bairabi, Vairengte and Tlabung), the Champhai flats, the margins of dils and reservoirs, and the seepage zones below springs (tuikhur) on slopes without piezometer readings that level is existing ground level (Clauses 4.12.1 and 4.12.3).
- The fence and signs of Annex 4C apply to the deeper facility (Clause 4.15).
Table 5C.5 — Summary (Illustrative — not design values)
| Item | Value |
|---|---|
| Governing case | J4, 1% AEP 48-hour storm, Run B (first window starting at the peak 1-hour block) |
| Storage required | 5,238 m³ (Annex 4C release-rate design: 2,913 m³) |
| Maximum stage | 2.10 m, with 2,500 m² plan area |
| Spillway crest | 2.25 m |
| Top of walls | ≥ 2.85 m above the floor |
| Largest release after a lock window | 584 L/s, to be included in the downstream J4 run |
| Drawdown | Annex 4C result applies: 45.3 h with the low-flow orifice 50% blocked |
Form 5-1 — Downstream and Tailwater Report
Supports Clauses 5.3 to 5.14 of Chapter 5.
Draft form — Mizoram Stormwater Design Manual, Draft v1.0. One report for each project. Sites of less than 0.5 ha that meet Clause 5.3.4 may submit Form 5-2 instead, where the Authority accepts it. Attach the plans, model files and hydrographs referred to.
A. Project
Table 5F.1 — Form 5-1: project
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Project type: site under Chapter 4; drainage project under Chapter 6; regional detention or tank restoration (Clause 5.1.2) | |
| A3. Site or project area (ha) and outfalls | |
| A4. Site Runoff Control Report reference (Form 4-1), where applicable |
B. Extent of the analysis (Clause 5.3; Clause 5.14, item 1)
Table 5F.2 — Form 5-1: analysis points
| Point | Location | Type (Clause 5.3.3 (a) to (e)) | Contributing catchment (ha) | Project area as % of it |
|---|---|---|---|---|
Table 5F.3 — Form 5-1: end point
| Field | Entry |
|---|---|
| B1. End point and reason: 10% point, tank or dil, or major drain or the sea (Clause 5.3.1 (a) to (c)) | |
| B2. Where the end point is a tank or dil: change in maximum water level (m) and in surplus-weir discharge (m³/s); continuation below the weir if the level rises (Clause 5.3.2) | |
| B3. Plan of the analysis extent, showing the site, each point with its contributing area and percentage, and the end point (attach) |
C. Model (Clause 5.4.4; Clause 5.14, item 2)
Table 5F.4 — Form 5-1: model
| Field | Entry |
|---|---|
| C1. Software and version; hydrologic and hydraulic methods (Clause 5.4.4) | |
| C2. Network schematic, with the survey sources for drains and crossings (attach) | |
| C3. Land use and CN of off-site areas (present land use) | |
| C4. Upstream detention included, with evidence that it is built, maintained and documented | |
| C5. Calibration or validation evidence, where available | |
| C6. Scenarios run: existing, with project, and future where the Authority requires it (Clause 5.4.1) | |
| C7. Storms run: AEPs and durations, AMC and areal reduction (Clause 5.4.3) |
D. Results at each analysis point (Clause 5.4.2; Clause 5.14, item 3)
Complete one row for each analysis point, AEP and duration. E = existing; P = with project.
Table 5F.5 — Form 5-1: results by analysis point
| Point | AEP | Duration (h) | Peak flow E / P (m³/s) | Time to peak E / P (h) | Maximum water level E / P (m) | Peak velocity E / P (m/s) | Duration of inundation E / P (h) |
|---|---|---|---|---|---|---|---|
E. Acceptance (Clause 5.5; Clause 5.14, item 4)
Table 5F.6 — Form 5-1: acceptance criteria
| Criterion | Met at every point? | Where not met, the remedy adopted (Clause 5.5.3) |
|---|---|---|
| E1. 1% AEP water level rise ≤ 10 mm at buildings, lowest openings and carriageways (Clause 5.5.1(a)) | ||
| E2. No building newly flooded; no building or road newly failing the Chapter 6 limits (Clause 5.5.1(b)) | ||
| E3. Peak flow not above existing at the minor-system AEP of each element or at 1% AEP (Clause 5.5.1(c)) | ||
| E4. Velocity in lined channels within the lining limit, 3.0 m/s maximum (Clause 5.5.1(d)) | ||
| E5. Velocity in unlined channels, 50% and 10% AEP, not increased by more than 10% (Clause 5.5.1(e)) | ||
| E6. Change in duration of road closure on arterial or emergency routes (Clause 5.5.2) | ||
| E7. Timing exception requested (Clause 5.5.4)? Give the conditions met |
F. Tailwater derivation (Clauses 5.6 to 5.8; Clause 5.14, item 5)
Table 5F.7 — Form 5-1: tailwater derivation
| Field | Entry |
|---|---|
| F1. Tide-table edition and port, or port authority source (Clause 5.7.2(a)) | |
| F2. MHWS, HAT and MSL (m above chart datum) | |
| F3. Connection from chart datum to the Survey of India benchmark and the project datum: offset (m) and source (Clause 5.7.2(b)) | |
| F4. Estuary, creek or canal outfall: levels used and any evidence for a departure from open-coast levels (Clause 5.7.2(c)) | |
| F5. 10% AEP surge and 1% AEP still-water level: values, source, method and record length (Clause 5.7.3) | |
| F6. Wave set-up, for outfalls facing the open sea (Clause 5.7.3(d)) | |
| F7. SLA (m), at least +0.3 m; design life; sensitivity run at twice the SLA for design lives over 50 years (Clause 5.7.4) | |
| F8. Non-tidal tailwater: receiving-system level and source (Clauses 5.6.2, 5.6.3) | |
| F9. River levels and sources; reservoir or tank releases included (Clauses 5.8.2, 5.8.3) | |
| F10. Lui, valley-floor rivers, Tlabung, reservoirs and release reaches, dils, transboundary rivers, and drains of other bodies: for a lui (Clause 5.8.5(a) and (b)), the 1% AEP study with the rainfall of Clause 2.3.6 for the sub-area (MZ-B for Aizawl), AMC, the bulking and blockage of Clause 6.3.6, the channel as surveyed net of encroachment, silt, slide debris and waste, the surveyed flood marks and their sources, the energy dissipator and the lined path to the lui, the check of the lui to the next confluence (capacity with bulking, velocity, bank stability) and its result, the landslide-hazard-map class of the outfall and of the reach, the bed survey and range of bed movement, the invert at least 0.5 m above the highest surveyed bed level, the scour depth of the foundation, confirmation that no outfall lies within 15 m of a tuikhur, on its protected catchment or on a quarry face, any check dam or trap included in the model, and the lock where the invert is below the design level (storm plus recession, not less than 24 hours); for valley-floor land (Clause 5.8.5(c)), the 1% AEP river level from a model with a site study calibrated to CWC, NEEPCO or State gauges where they exist, any level obtained from CWC for the nearest gauge (Sairang, Keitum, Turial 149.0 m, Bailley Bridge Tuipui, Tuichang, Tuichawng, Sihthangpui) transferred to the outfall, the surveyed flood marks and their sources, every level with its datum and its tie to the named gauge and a Survey of India benchmark; 10% AEP river level (no warning or danger level exists: the design river level until a frequency analysis is accepted); the flap gate, its owner from the drain register, sill and closing level; drain behind the gate routed with its whole catchment, hill catchments included, and present storage, pumping confirmed available (permanent pumps only, not more than installed capacity less the largest pump), pumps operable at the design river level; single lock of the whole 72-hour storm, not less than 72 hours, or longer from the model or a stage record, and its source; gate jammed open checked; for Tlabung (Clause 5.8.5(d)), the model of the Khawthlangtuipui, the flood marks of June 2017, July 2019, August 2023 or later and residents' records, the downstream boundary and its sensitivity run, and the lock (not less than 72 hours, longer where the flood marks show it); for the Tuirial or Serlui B reservoir (Clause 5.8.5(e)), the operator's consent, its MWL or FRL plus design-flood surcharge in writing with its datum, or the interim level (Tuirial 91.0 m, FRL 90.5 m + 0.5 m; Serlui B the surveyed shore line or spillway crest + 0.5 m), the Turial gauge level recorded but not related to the reservoir levels, the outfall below the tailwater treated as closed for the whole of the 72-hour storm, the reservoir starting at FRL, and no gate operation, drawdown, release notice or reservoir attenuation credited; for a release reach, the design storm and the 72-hour storm with the largest recorded release, or the spillway capacity, or the unattenuated 1% AEP inflow until the operator gives either, placed before, during and after the storm, and the reported dam-break peak of 3,035.34 m³/s below the Tuirial dam and whether the outfall lies in its inundation extent; for a dil, the custodian's consent (and the District Council's in its area), the surveyed spill level plus head, and the debris, waste and sediment traps before it; for a river that leaves the State (Clause 5.8.5(f)), the model boundary and its sensitivity run, and for the northern rivers the adjoining edition's level used only as the model's downstream boundary; owner's consent (the Chairman's written permission under s.295 and the municipality's consent under s.296 of the Municipalities Act; PWD and the Corporation both on a State road in the Corporation's area; the national-highway agency; the Village Council; the District Council in its area), permitted rate, design water level or computed channel level, and flap gate; and the lines checked (SD&SM reg. 28 riverine reserve; riverine reserves under the Mizo District (Forest) Act, 1955 and any restriction of April 2021 confirmed with EF&CC; the master plan's 15 m buffer; any River Conservation Zone, only if the Rivers law is in force and a zone notified; AMCBR reg. 33's 15 m) (Clause 5.8.5) |
G. Joint cases (Clause 5.9; Clause 5.14, item 6)
Table 5F.8 — Form 5-1: joint-case results
| Case | Rainfall | Tailwater used (m, project datum) | Applies? | Governing result (storage, level, pipe size or pump capacity) |
|---|---|---|---|---|
| J1 | ||||
| J2 | ||||
| J3 | ||||
| J4 | ||||
| R1 | ||||
| R2 |
H. Outfall-closed check (Clause 5.10; Clause 5.14, item 7)
Table 5F.9 — Form 5-1: outfall-closed check
| Field | Entry |
|---|---|
| H1. Reason the check applies (Clause 5.10.1) | |
| H2. Storm: AEP, 48 h and 72 h, AMC III (Clause 5.10.2) | |
| H3. Lock duration and basis: default of two 6-hour windows, or site study (Clause 5.10.6); extension for sand-bar closure (Clause 5.13.5) | |
| H4. Lock windows of the two runs (start and end times) (Clause 5.10.3(d)) | |
| H5. Maximum stage in each facility, against its 1% AEP maximum water level (Clause 5.10.4(a)) | |
| H6. Maximum stage in the minor and major systems, against the Chapter 6 limits (Clause 5.10.4(b)) | |
| H7. Property connections: surcharge level, or non-return valves fitted (Clause 5.10.4(c)) | |
| H8. Stage hydrographs (attach) | |
| H9. Drawdown after the storm under the J1 tidal curve, and pumping where needed (Clause 5.10.5) |
Table 5F.10 — Form 5-1: volume balance for each lock window (Clause 5.10.4)
| Period | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| Before window 1 | |||||
| Window 1 | |||||
| Between windows | |||||
| Window 2 | |||||
| After window 2 |
I. Gates and valves (Clause 5.11; Clause 5.14, item 8)
Table 5F.11 — Form 5-1: schedule of flap gates, tide gates and non-return valves
| Location | Type | Size (mm) | Invert (m, project datum) | Certified head–discharge data (reference) | Stop-log or penstock (outfalls > 600 mm) |
|---|---|---|---|---|---|
J. Pumped outfalls (Clause 5.12; Clause 5.14, item 9)
Table 5F.12 — Form 5-1: pumped outfalls
| Field | Entry |
|---|---|
| J1. Reason pumping is needed (Clause 5.12.1) | |
| J2. Duty capacity (m³/s) at the static head for the J2 tailwater; standby capacity (Clause 5.12.2) | |
| J3. Effect on the receiving water level (Clause 5.12.3) | |
| J4. Power supply: two independent supplies, or standby generation with 72 h of fuel; automatic changeover (Clause 5.12.4) | |
| J5. Level of electrical panels, controls, generators and fuel, against the higher of the 1% AEP flood level + 0.5 m and HAT + surge + SLA + 0.5 m (Clause 5.12.5) | |
| J6. Discharge arrangement (Clause 5.12.6); controls, alarms and logging (Clause 5.12.7); screens (Clause 5.12.8) |
K. Sand bar (Clause 5.13; Clause 5.14, item 10)
Table 5F.13 — Form 5-1: sand-bar assumption
| Field | Entry |
|---|---|
| K1. River mouth or creek inlet concerned | |
| K2. Mouth assumed closed, or open with IWRD certification attached (Clause 5.13.2) | |
| K3. Bar crest level from the most recent pre-monsoon survey (m) and the closed-mouth tailwater (Clause 5.13.3) | |
| K4. Extension of the lock duration, where required (Clause 5.13.5) |
L. Inspection and maintenance (Clause 5.14, item 11)
Table 5F.14 — Form 5-1: inspection and maintenance
| Field | Entry |
|---|---|
| L1. Gate and valve inspection before 31 March and after closure events (Clause 5.11.5) | |
| L2. Pump test runs before 31 March (Clause 5.12.9) | |
| L3. Other requirements for the maintenance plan (Chapter 10) |
M. Statement by the registered professional (Clause 10.6)
I state that this report has been prepared under Chapter 5 of the Mizoram Stormwater Design Manual (Draft v1.0), that the results reported are reproduced by the models submitted, and that every departure from Chapter 5 is listed with its reason. The Professional Design Certificate (Form 10-3) is attached.
Table 5F.15 — Form 5-1: statement by the registered professional
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Empanelment number, where Clause 10.6.1 requires it | |
| Organisation | |
| Signature | |
| Date |
Draft form — Mizoram Stormwater Design Manual, Draft v1.0.
Form 5-2 — Simplified Downstream Statement (small sites)
Supports Clause 5.3.4 of Chapter 5.
Draft form — Mizoram Stormwater Design Manual, Draft v1.0. For sites of less than 0.5 ha. The Authority may accept this statement in place of the full analysis only where every answer in Section B is "Yes". Otherwise submit Form 5-1.
A. Site
Table 5F.16 — Form 5-2: site
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Site area (ha), less than 0.5 ha | |
| A3. Receiving public drain: name or reference, type and size | |
| A4. Site Runoff Control Report reference (Form 4-1) |
B. Conditions (Clause 5.3.4)
Table 5F.17 — Form 5-2: conditions
| Condition | Yes / No | Evidence |
|---|---|---|
| B1. The receiving public drain has documented capacity for its minor-system design flow (Chapter 6) | ||
| B2. No flood-prone location is recorded within 500 m downstream of the site outfall. Records checked: local body, the Aizawl Municipal Corporation, MSDMA, IWRD (Clause 5.3.3(d)) | ||
| B3. The site does not drain to a tidal or backwater-affected outfall |
C. Route plan
Table 5F.18 — Form 5-2: attachments
| Attachment | Attached? |
|---|---|
| C1. Plan of the drainage route from the site outfall for 500 m downstream, with the receiving drain and any recorded flood-prone locations | |
| C2. Copy or reference of the drain capacity record |
D. Statement
I state that the site meets the conditions of Clause 5.3.4 as shown above, and that the records listed have been checked.
Table 5F.19 — Form 5-2: statement
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Signature | |
| Date |
Draft form — Mizoram Stormwater Design Manual, Draft v1.0.