Draft v1.0 prepared by NEER. Not adopted by the Government of Mizoram, any District Council, Village Council, authority or local body, and has no legal force. About this draft

Chapter 1Policy, Applicability and Adoption


1.1 Purpose and objectives

1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Mizoram. It applies to private development and to public works, as set out in Clause 1.5.

1.1.2 The Manual has the following objectives:

  • (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
  • (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
  • (c) to size storage for the long-duration storms of the monsoon season, which in Mizoram fall for days on slopes of shale and loose soil (677 mm in Serchhip district in 1–13 June 2018, SANDRP, as reported; 598 landslides across the State in the storms of 24 May–3 June 2025, DM&R figures, as reported), and which, from the pre-monsoon storms of April and May, among them Cyclone Remal on 28 May 2024, to the post-monsoon cyclones of October to December, saturate the ground, set off landslides and keep the streams and valley rivers high, as well as for short-duration intensities;
  • (d) to design outfalls for the steep hill streams (lui) into which almost every town drains, among them the Chite lui, which takes "more than two-third of eastern portion" of Aizawl to the Tuirial, and the Ser lui and its streamlets, which take the west of the city to the Tlawng (Master Plan for Aizawl: Vision 2030), and which rise within the hour, run "turbulent with high velocities of currents during the monsoon season" and carry slide debris and garbage, so that most outfalls fall freely and must dissipate their energy; the rivers that stand high beside the valley floors and terraces, the Tlawng at Sairang, Bairabi and Vairengte, the rivers of the Champhai flats and the Kau and the Tuichawng at Chawngte; the Khawthlangtuipui (Karnaphuli) at Tlabung, a river-flood town whose houses were flooded in 2017, 2018, 2019 and 2023 (as reported); the reservoir of the Tuirial dam and the reaches below it and below the Serlui B dam, into which floods are released; and the rivers that leave the State for Bangladesh and Myanmar, the Karnaphuli, the Kaladan (Chhimtuipui) and the Tiau, on which no downstream level is available, including the case where the outfall is closed;
  • (e) to protect tanks (dils), marshes, rivers, supply channels and surplus courses as part of the drainage system;
  • (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
  • (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
  • (h) to make sure that facilities, once built, are maintained and remain effective.

1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building and site-development regulations that the Board of Councillors of the Aizawl Municipal Corporation makes under section 371 of the Mizoram Municipalities Act, 2007 and the Urban Development and Poverty Alleviation Department notifies (the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).

Commentary. Mizoram's disasters come from three sources, often together. The first, and the deadliest, is the landslide that rain and drainage set off on the slopes of the ridge towns. On 9 August 1992 a stone quarry at South Hlimen, on Aizawl's southern edge, collapsed in "unprecedented landslides" (Senhri Journal) that "claimed the lives of almost 100 people" (MIRSAC, 2013, citing earlier work); a chronology reports 30 bodies recovered and 68 feared buried in an unnamed Mizoram village in August 1992, which may be the same event (as reported; unverified). Landslides killed at least 25 people in 1995 (as reported), and the Bawngkawn and Vaivakawn slides of 1994 were studied geotechnically (MIRSAC, 2013). At about 3 a.m. on 11 May 2013 by the press and the AGU Landslide Blog, or on 15 May 2013 by one paper (conflict), a rockslide at Laipuitlang–Ramhlun Venglai in Aizawl, after "heavy rainfall, thunderstorm", destroyed 15 houses and brought a vacated PWD building down on nine; 17 bodies were exhumed and 8 people rescued by the paper's account, while another review gives 8 lives (Laldinpuia et al., 2013; as reported; conflict). The paper's volume of "about 8 Mm³" is implausible for a slide of 1,025 m² and is not used [U]. On 2 July 2019 three of the 20 blocks of a housing complex built under BSUP at Durtlang collapsed, killing 3 people and injuring 11, and 140 families were relocated; the rock bolts, wire nets and buttressed toe walls suggested in 2020 were not provided: "none of the suggestions were carried out" (CAG). From 2017-18 to 2021-22 landslides affected 661 villages, killed 41 people, injured 15 and damaged 219 km of road, and floods affected 434 villages and killed 12 (CAG). In 2022-23 a team of the Directorate of Geology and Mineral Resources inspected 55 locations and attributed two-thirds of the large landslides to "improper drainage" (as reported). On 28 May 2024, in Cyclone Remal, after heavy rain from 27 May, the disused quarry between Melthum and Hlimen collapsed at about 6 a.m., other slides struck Aizawl and NH-6 was cut at Hunthar. The tolls rose through the day: 10, then 23, then 29 dead in Aizawl district with 7 missing (29 May); one report gives 15 at the quarry site and 5 at Hlimen, a later report 34 killed in seven Aizawl areas, and the State toll is put at 27 to 29 by various counts (all as reported; conflict). In July 2024 slides on the Bawngkawn–Durtlang road led the High Court to freeze new construction on either side of it (as reported). Over 24 May–3 June 2025, 598 landslides killed five people, damaged 171 houses and blocked roads at 257 places, most of them in Champhai district (209), then Serchhip (116), Khawzawl (75), Lunglei (61) and Aizawl (21) (DM&R figures, as reported). Landslides in August 2026 struck Aizawl, Champhai, Lawngtlai and Hnahthial without casualties, and a landslide at Vairengte killed a boy and injured four people in September 2026 (as reported).

The second source is the river flood of the valley floors and terraces, which the State has described as absent: "Mizoram being a hilly state, there is no flood plain zone in the catchment area" (MPCB, report to the National Green Tribunal in OA 593/2017). Tlabung, on the Khawthlangtuipui, floods from its river. In June 2017 about 350 houses were reported submerged in the sub-division, against 9 fully and more than 60 partly submerged by district officials, with 8 to 10 dead and more than 1,500 families affected (as reported; conflict). In June 2018, when Serchhip district received 677 mm in 1–13 June and Aizawl 148 mm in one day, 100 houses were flooded at Tiperabagh, 70 at Serhuan and 30 at Tlabung, families were stranded at Sairang on the Tlawng, the cuts of NH-54 at Hunthar became unstable and ten people died in landslides on 5 June (SANDRP; as reported). In July 2019 about 400 houses, 150 of them in Tlabung town, were flooded, more than 350 families were evacuated and 3 people were killed across the State, and in August 2023, 40 families were evacuated at Tlabung (as reported). Bairabi on the Tlawng and Champhai on the Tiau flood too (as reported). The State's statement and these floods do not agree, and the statement does not hold beside the valley floors.

The third is the town drain itself. "67% of Aizawl Urban Area is having kutcha drains and 18% are without any drainage system at all. Only 15% of the area is provided with pucca drains"; the drains are "silted up frequently due to insufficiency in the hydraulic design"; and although "there is no major water logging in Aizawl as it is situated in sloppy ground", a third of Aizawl W-I is waterlogged "for several days or for hours", which the plan blames on solid waste in the roadside drains (Master Plan for Aizawl: Vision 2030). The same drains carry most of the city's sewage (Chapter 8). The final tolls of DM&R for these events were not obtained [TBC], and the tolls above differ in what they count and in the date of the report.

Missing design makes all three worse. No design storm, return period or drain standard was found for the drains of any town in the State, and the slope regulation of the Aizawl Municipal Corporation sets the geometry of terraces and drains but no design storm. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix; the slope source is answered by the siting, screening, infiltration and debris rules of Chapters 2, 4, 6 and 7, because no drain is sized to carry a slide, and the river source by the outfall checks of Chapter 5 and the corridors and floor levels of Chapters 6 and 7.

No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.


1.2 Stormwater management hierarchy

1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.

  1. Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
  2. Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
  3. Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
  4. Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).

1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.

1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.

Figure 1.1 — Stormwater management hierarchy Four stacked bars, widest at top: Preserve, Retain, Detain, Convey, with a Maintain bar underneath spanning all. A downward arrow shows the order of consideration; an upward arrow shows that credits from higher measures reduce lower ones. Order of consideration Credits reduce lower measures 1 PRESERVE Chapter 7 Keep tanks, wetlands, marshes, permeable soils, trees and flow paths 2 RETAIN Chapters 4, 8 Hold the Annex 2E depth on site: infiltrate, reuse, evaporate 3 DETAIN Chapters 4, 5 Store larger storms; release below pre-development peaks 4 CONVEY Chapters 6, 9 Minor system, plus a 1% AEP overland path MAINTAIN — underlies every measure Chapter 10 A measure that its owner cannot maintain earns no credit (Clause 1.2.2) Use a lower measure only for what the measures above it cannot practicably achieve (Clause 1.2.1).

Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).

Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Mizoram, the top two layers have a particular meaning. On the ridges what must be preserved first is the natural drainage of the slope: the lui that carry the towns' water to the rivers, the springs (tuikhur) from which the villages draw their water, the few dils, and the cover of forest and soil on slopes where "The soil in and around the city is young and in a loose state" (Master Plan for Aizawl: Vision 2030). The slope regulation of the Aizawl Municipal Corporation names the danger: "human activities such as slope cutting, filling, increasing the amount of groundwater penetrating into slopes, and disposing of sewerage and drainage onto slopes in a poorly controlled manner can greatly increase slope instability" (SD&SM, reg. 1). The law protects some of this. The master plan keeps "Around 52% of total urban area … under non-urban uses like Agriculture/Forest, Water Bodies, Undevelopable Slopped Lands" and recommends a 15 m green buffer on both sides of major drainage channels; the slope regulation keeps "the riverine reserve" beside natural streams, without defining it (reg. 28), and gives no permit above 60° (reg. 14); and the Mizoram Water Resources (Management and Regulation) Act, 2024 counts springs among the "community water resources" (s.2(1)(i)) that its Village and Local Water Resources Committees are to keep from pollution. Neither regulation sets a metric setback from a stream or a spring, and none of these instruments reaches the areas of the Autonomous District Councils. On hill ground the second layer changes. Retention there is storage and reuse, not infiltration: CGWB finds the shale ridges "characterized by low permeability and infiltration", a "run off zone" (CGWB, Lunglei), and every assessment unit of the State "Safe", with a stage of extraction of 3.52% in 2011 (CGWB, State profile) and 3.95% in 2024 (GWRA 2024, as quoted), so recharge is not a design objective. This Manual therefore bars deliberate infiltration on natural slopes of more than 10°, on the shale, siltstone and mudstone of the Surma group at any slope, on colluvium, fill, cut-spoil or slide debris, in a mapped Moderate, High or Very High landslide hazard zone and within twice the height of a cut or retaining wall upslope of it, unless a geotechnical certificate allows it, and in High and Very High hazard zones not at all (Clause 4.11, hill rule); allows recharge only on tested valley alluvium and river terraces, on flat ground above the 1% AEP flood level and where the water table is at least 2.0 m below ground (Clause 4.11, recharge rule); and keeps stormwater out of every tuikhur, with no storm outfall, soakaway or drain discharge within 15 m of it (the spring rule of Chapter 8) (all set by this Manual). Rainwater harvesting is supply: 27.16% of households in the Aizawl Urban Area use rain water (Master Plan for Aizawl: Vision 2030). On these slopes a drain that puts water into the ground can bring the slope down.


1.3.1 Notification. This Manual shall be given statutory effect by the Government of Mizoram through:

  • (a) an amendment to the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
  • (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.

1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.

1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.

1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.

Commentary. In Mizoram the drainage rule that binds a site is in a slope regulation, not in the building regulation, and this Manual cites the two as a pair, AMCBR/SD&SM. The first is the Aizawl Municipal Corporation Building Regulations, 2012 (UD&PA Notification No. B.13017/8/2012-UD&PA of 20 December 2012; Mizoram Gazette Extraordinary Vol. XLII, Issue No. 4, 10 January 2013), made as the Aizawl Municipal Council Building Regulations, as amended by the Amendment Regulations of 2019 (No. B.13017/8(2)/2018-UD&PA; the draft published for objections on 10 April 2019 was read, the final gazette was not [TBC]), 2023 (No. B.13017/8/2021-UD&PA/Pt of 14 August 2023, in force 28 August 2023, which renamed "Council" to "Corporation") and 2025 (No. B.13017/8/2021-UD&PA/Loose of 21 November 2025). The second is the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017 (No. B.13017/75/2016-UD&PA of 4 April 2017; Gazette Extraordinary Vol. XLVI, Issue No. 161, 11 April 2017), drafted with GeoHazards International for the Landslide Policy Committee for Aizawl City (as reported); whether they have been amended is not known [TBC]. Both are made by the Board of Councillors under section 371 of the Mizoram Municipalities Act, 2007, "after previous publication", and notified by UD&PA. Both apply only to "all the areas covered by the Aizawl Municipal Council" (AMCBR reg. 1(2)), and the 2012 Regulations "shall come into force on such date as the Aizawl Municipal Council may notify", a date not found [TBC]. No statewide building regulation was found, and no regulation of the Lunglei Municipal Council (LMC) was found [TBC].

The building regulation requires a site "properly drained or capable of being drained" and "not an active hazard-prone area such as landslide, subsidences, mass movement" (AMCBR reg. 21(ii), (iv)); plans that show "sewerage and surface drains, position and sizes of septic tank and soak pit", a roof plan "indicating drainage and roof slope", "site development and permanent structures like retaining wall, surface drain" and "provision for a suitable rain water harvesting facility" (regs. 5(5)(v), 5(6)(iv), (viii) and (ix)); a plinth that "may preferably be not less than 0.45 metre" so that drainage is assured, and roof water carried by rain gutters and closed conduits and "discharged at ground level by pipe", with "no spout … to drain into the road or public area or within the adjacent compound" (reg. 26(2)); a septic tank "with soak pit" for every water closet, not "within a radius of 15 metres from a water source", and "A suitable rain water harvesting facility … in all buildings" (reg. 33); and a closed conduit through a neighbour's land where "in the interest of public safety" water must cross it, and a drain or closed conduit "of adequate capacity to the nearest public drain" (reg. 37). Since 2023 the online building permission system (OBPAS) returns any proposal "not as per the provisions of the AMC Building Regulations, 2012 and the Master Plan for Aizawl, Vision-2030"; since 2025 rainwater harvesting and "Reduction of Hardscape" are incentives for plots above 100 m² (Chapter VIIIA), and empanelled technical personnel may self-certify ordinary buildings "on plots measuring less than 93 square meters and located within low and moderate geo-hazard zones" (Annexure B-I). The slope regulation requires a site development permit "in addition to a building permit" (SD&SM reg. 5(1)); an engineered track, with a geotechnical report, in the Moderate, High and Very High zones of the Landslide Hazard Maps, on unmapped slopes of 24° or more, for cuts of 3 m or more, for works of more than 200 m³ and for works that support a structure, "Regular site development" being "allowed ONLY in zones of Low landslide hazard"; no permit above 60° (reg. 14); and the drainage of the site (reg. 27): terraces at least 2 m wide at not more than 10 m vertical intervals on cut and fill slopes, with paved swales of at least 1 in 20, no single run of which "shall … collect runoff from a tributary area exceeding 400 square meters (projected horizontally) without discharging into a down drain"; paved interceptor drains along the top of every cut slope whose uphill drainage path exceeds 10 m; building pads graded at least 1 in 50 to approved drainage; "non-erosive downdrains"; and the duty of a site developed downhill to "convey drainage, sewage or seepage from the adjacent site uphill … in a safe manner to the nearest practicable drainage way". Its engineered plans show "the estimated runoff of the area served by any drains" (reg. 6(4)), and its Schedule I makes licensed civil engineers competent for "Design of drainage structures, including hydrology and hydraulic calculations". Neither regulation sets a design storm, return period, runoff coefficient, release rate or detention volume, a setback from a stream or spring, or a size for rainwater harvesting. The Commentary to Clause 1.1 says that the national Model Building Bye-Laws and the AMCBR/SD&SM "mandate RWH only": that is right for the 2012 Regulations (reg. 33), but the 2017 Regulations mandate no rainwater harvesting and do set the geometry of the site's drainage, though still no detention, peak-flow or design-storm rule (NEER reading). This Manual supplies what the slope regulation leaves to the engineer: the design storm, the intensity, the capacity check, the freeboard and the allowance for debris.

The route of Clause 1.3.1(a) therefore runs through the Board of Councillors and UD&PA. UD&PA could carry this Manual into amendments of AMCBR regs. 5(6), 26, 33 and 37 and SD&SM regs. 6 and 27, which the Board of Councillors would make under section 371 after previous publication and UD&PA would notify (Annex 1D); the Corporation could apply it through OBPAS, the site development permit and its own street drains, which vest in it (Municipalities Act, ss.288–289); the LMC could adopt the same through regulations of its own; and UD&PA could frame the model building bye-laws of section 13(6) of the Mizoram (Village Councils) Act, 2025 with a drainage annex. The Mizoram Urban and Regional Development Act, 1990 (Act 12 of 1990, amended in 2004) is known to this Manual by its title only (as listed) and is not the Act under which either regulation is made; Annex 1D names it only because the core text asks for the State's planning Act. The Master Plan for Aizawl: Vision 2030 was prepared by the erstwhile Aizawl Development Authority, "(now absorbed in AMC)" (CAG); no notification approving it was found, and a report that it was approved in March 2013 is unverified [TBC], yet OBPAS checks every proposal against it.

That route reaches only the Corporation's area. Mizoram has three legal geographies. (i) The municipalities. The Mizoram Municipalities Act, 2007 (Act No. 6 of 2007) "shall extend to the whole of the State of Mizoram except the area which has been or may hereafter be declared as, or included in, a Panchayat or a Village Council … but shall not extend to the Mizoram Tribal Areas, as referred to in PART III of the paragraph 20 of the Sixth Schedule" (s.1(2)); in practice it reaches the Aizawl Municipal Corporation and the LMC. (ii) The Village Council areas. The Mizoram (Village Councils) Act, 2025 (Act No. 7 of 2025; assent 12 March 2025; Gazette Extraordinary Vol. LIV, Issue No. 178, 20 March 2025), which replaced the Lushai Hills District (Village Councils) Act, 1953, "shall extend to the whole of Mizoram except the areas under the jurisdiction of the Municipalities and the Lai, Mara and Chakma Autonomous District Councils" (s.1(2)), and so reaches the villages and the notified towns that have no urban local body, 13 of them with 5,950 to 32,734 people (CAG). Its Village Councils "shall adopt and enforce the model building bye-laws as may be framed by the State Government" and, "subject to the approval of the concerned District Disaster Management Authority", "may declare certain area within their jurisdiction as unsafe site for house construction for mitigation of landslide" (s.13(6)); no model building bye-laws were found (NEER reading). (iii) The Autonomous District Councils. The Lai (Lawngtlai), Mara (Siaha) and Chakma (Kamalanagar and Chawngte) Autonomous District Councils of the Sixth Schedule, in the south, are excluded from both Acts, from the Mizoram Water Resources (Management and Regulation) Act, 2024 ("except the Autonomous District Councils") and from the Rivers Bill of 2023, and the provisions of the 74th Amendment "are not applicable in the Sixth Schedule areas" (CAG). No building or drainage regulation of any District Council was found. The Chakma District Council's requirement of a no-objection certificate from the Kamalanagar Town Planning Committee (2018), its notification on prior approval for roadside buildings (20 November 2020) and a provision of 2002 barring house construction "without the written permission from the Village Council" are known only from titles and snippets, the Lai Autonomous District Council (Land Holding and Settlement) Act, 2002 from a snippet, and nothing was found for the Mara District Council (as listed or summarised). This Manual does not quote the Sixth Schedule, which was not read for it; it describes the split by the extent clauses of the Acts and by the CAG.

What the Manual can reach outside the Corporation's area is therefore narrow: public works executed by the State's departments and agencies anywhere in the State, among them roads, culverts, drains, water supply, sewerage and flood works (Clause 1.5.1(b)); any body that adopts it; in the Village Council areas, the model building bye-laws of section 13(6) once the State frames them, and the Village Councils' declarations of unsafe sites with the approval of the District Disaster Management Authority; and in the areas of the Autonomous District Councils, nothing unless a District Council adopts it. A District Council could adopt it for its area by its own instrument, through its Executive Committee, as a District Council of another North-East State has made its own building regulation; none has. For a household outside the Corporation's area the Manual is guidance (Commentary to Clause 1.5). This Manual is a draft: neither the Government of Mizoram, UD&PA, the Aizawl Municipal Corporation, its Board of Councillors or its Local Councils, the LMC, any Village Council, the Lai, Mara or Chakma Autonomous District Council, nor any other authority has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.


1.4 Definitions

1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).

Term Meaning in this Manual
Approving Authority (the Authority) The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the competent authority for the area: in the area of the Aizawl Municipal Corporation, the Corporation, for the building permit, given through its online building permission system (OBPAS) under the Aizawl Municipal Corporation Building Regulations, 2012, for the site development permit that the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017 require "in addition to a building permit" (reg. 5(1)), for drain connections (sections 295 and 296 of the Mizoram Municipalities Act, 2007) and for its own drains and works, with its Local Councils for the no-objection certificates they give; in the area of the Lunglei Municipal Council (LMC), the LMC under the Mizoram Municipalities Act, 2007 (no building regulation of the LMC was found [TBC]); in a Village Council area, the Village Council, for building only once the State Government frames the model building bye-laws of section 13(6) of the Mizoram (Village Councils) Act, 2025 (none was found), and for the declaration of an unsafe site for house construction with the approval of the District Disaster Management Authority; the Urban Development and Poverty Alleviation Department (UD&PA) for the master plans of urban areas and notified towns; the Irrigation and Water Resources Department (IWRD) and the Water Resources Development and Management Authority (WARDMA), with the District and the Village or Local Water Resources Committees, for water resources under the Mizoram Water Resources (Management and Regulation) Act, 2024, outside the Autonomous District Councils; the Environment, Forest and Climate Change Department (EF&CC) for riverine reserves and wetlands; the Mizoram River Protection Authority in a River Conservation Zone, only if the Rivers law is in force and a zone has been notified (neither is confirmed); for a public work, the department that executes it (the Public Works Department (PWD), the Public Health Engineering Department (PHED), the IWRD or another works agency); and, in the area of the Lai, Mara or Chakma Autonomous District Council, the District Council (its Executive Committee) and its Village Councils, only if the District Council adopts this Manual (none has), or a department for its own works.
Applicant The owner, developer or department that seeks approval, and its successors in title.
Development Any building, layout, sub-division, road, paving or land-use change that requires approval under the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017 or that is executed as a public work.
Redevelopment Development on a site where impervious cover already exists.
Land disturbance Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5).
Impervious area Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats.
New or replaced impervious area Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced".
Retention Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4).
Detention Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4).
Rainwater harvesting (RWH) Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it.
Minor system Drains, pipes and inlets designed for the minor-system AEP of Chapter 6.
Major system The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6).
Pre-development condition Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3).
Flood-sensitive catchment The catchments of Aizawl east, the Chite lui and its tributaries down to the Tuirial; of Aizawl west, the Ser lui with the Khatla, Tuikual, Vaivakawn and Chanmari west lui, down to the Tlawng; of the Hlimen–Melthum quarry belt on Aizawl's southern edge; of Hunthar Veng and the NH-6 corridor at Aizawl; of Durtlang and the Bawngkawn–Durtlang road; of Sairang on the Tlawng; of Bairabi and Vairengte; of Tlabung on the Khawthlangtuipui; of Lunglei town; of Serchhip town; of Champhai town and the Champhai flats; of Siaha and Lawngtlai; and of the release reach below the Tuirial dam, and any catchment the Authority notifies (Chapter 4; Annex 1B).
Waterbody A river, stream, canal, tank (dil), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7).
Regional facility A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4).
Tier A / Tier B authority An Approving Authority classed under Clause 1.6.
Policy supplement The set of adoptable alternative clauses in Clause 1.7 and Annex 1C.
Drainage report The preliminary or final report required by Chapter 10.
Registered professional A person registered under the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6.
Compliance calculator The State-issued tool for computing and reporting compliance (Clause 10.5).
Maintenance declaration The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10).
Variance Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10).
Waiver Approval that a requirement does not apply to a site, on the grounds in Clause 1.10.
Notified Published by the Government or the State Stormwater Technical Committee in the Mizoram Gazette.
Competent authority for the area The body that grants permission for the site, or consents to the work, under the instrument that applies there: in the area of the Aizawl Municipal Corporation, the Corporation, for the building permit, given through its online building permission system (OBPAS) under the Aizawl Municipal Corporation Building Regulations, 2012, for the site development permit that the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017 require "in addition to a building permit" (reg. 5(1)), for drain connections (sections 295 and 296 of the Mizoram Municipalities Act, 2007) and for its own drains and works, with its Local Councils for the no-objection certificates they give; in the area of the Lunglei Municipal Council (LMC), the LMC under the Mizoram Municipalities Act, 2007 (no building regulation of the LMC was found [TBC]); in a Village Council area, the Village Council, for building only once the State Government frames the model building bye-laws of section 13(6) of the Mizoram (Village Councils) Act, 2025 (none was found), and for the declaration of an unsafe site for house construction with the approval of the District Disaster Management Authority; the Urban Development and Poverty Alleviation Department (UD&PA) for the master plans of urban areas and notified towns; the Irrigation and Water Resources Department (IWRD) and the Water Resources Development and Management Authority (WARDMA), with the District and the Village or Local Water Resources Committees, for water resources under the Mizoram Water Resources (Management and Regulation) Act, 2024, outside the Autonomous District Councils; the Environment, Forest and Climate Change Department (EF&CC) for riverine reserves and wetlands; the Mizoram River Protection Authority in a River Conservation Zone, only if the Rivers law is in force and a zone has been notified (neither is confirmed); for a public work, the department that executes it (the Public Works Department (PWD), the Public Health Engineering Department (PHED), the IWRD or another works agency); and, in the area of the Lai, Mara or Chakma Autonomous District Council, the District Council (its Executive Committee) and its Village Councils, only if the District Council adopts this Manual (none has). Where this Manual says "the Authority", the competent authority for the area is meant. This Manual reaches the area of an Autonomous District Council only through that District Council.
Municipal area; Village Council area; Autonomous District Council area The three legal geographies of the State. A municipal area is the area of the Aizawl Municipal Corporation or the Lunglei Municipal Council, to which the Mizoram Municipalities Act, 2007 extends (s.1(2)). A Village Council area is any other part of the State outside the three Autonomous District Councils, including the notified towns that have no urban local body, to which the Mizoram (Village Councils) Act, 2025 extends (s.1(2)). An Autonomous District Council area is the area of the Lai, Mara or Chakma Autonomous District Council under the Sixth Schedule to the Constitution, in the south of the State, which the municipal, village-council and water-resources Acts and the Rivers Bill of 2023 all exclude; no building or drainage regulation of a District Council was found for this Manual [TBC].
Building regulations; site development permit The Aizawl Municipal Corporation Building Regulations, 2012, as amended (AMCBR), and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017 (SD&SM), made by the Board of Councillors under section 371 of the Mizoram Municipalities Act, 2007 and notified by UD&PA, which apply in the area of the Aizawl Municipal Corporation only. A site development permit under SD&SM is required "in addition to a building permit" (reg. 5(1)), on a regular or an engineered track (Chapter 10).
Landslide Hazard Maps; hazard zone "The currently adopted version of the Aizawl Municipal Corporation Landslide Hazard Maps, created in 2014 or later to the standards adopted by the Landslide Policy Committee for Aizawl City" (SD&SM, definitions), and their Low, Moderate, High and Very High hazard zones. Outside the Corporation's area, the hazard zonation of MIRSAC for the town concerned, where one exists, is used in the same way (set by this Manual).
Lui A stream or river (Mizo; lui te, a small stream). A lui draining 8 ha or more is a natural channel under Chapter 7, whether or not it carries water all year. Most outfalls in the State discharge to a steep lui (Clause 5.8.5(a)).
Valley-floor land Land below the 1% AEP flood level of a river, in sub-areas MZ-A1 (Northern valley floors), MZ-C1 (Champhai flats) and MZ-D1 (Tlabung valley floor) of Annex 2A or elsewhere, such as Sairang on the Tlawng and Chawngte on the Kau and the Tuichawng, to which the valley-floor conditions of Chapters 2, 4, 5 and 7 apply (set by this Manual).
Land records; house sites; community land Land records and land use are with the Land Revenue and Settlement Department, also inside the Corporation's area (CAG); Village Councils allot house sites under the Mizoram (Village Councils) Act, 2025; land in the Autonomous District Council areas is under the District Councils [TBC]. Where this Manual reserves a drainage corridor, an easement or a regional facility site on private land or land held under a pass, it is reserved in the master plan or secured by agreement, not taken (set by this Manual).

Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).


1.5 Applicability

1.5.1 Who is covered. This Manual applies to:

  • (a) all development requiring planning permission, building permit or layout approval under the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017;
  • (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
  • (c) works executed by Central agencies or their contractors within Mizoram, to the extent that the Authority's approval or no-objection is required.

1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:

  • (a) land disturbance of 0.1 ha or more; or
  • (b) new or replaced impervious area of 500 m² or more.

1.5.3 RWH. The existing RWH mandate continues to apply under regulation 33 of the Aizawl Municipal Corporation Building Regulations, 2012, "A suitable rain water harvesting facility shall also be provided in all buildings", with plans that "include provision for a suitable rain water harvesting facility" (reg. 5(6)(ix)), in the area of the Aizawl Municipal Corporation, and with rainwater harvesting and "Reduction of Hardscape" offered as incentives, not conditions, for plots above 100 m² under Chapter VIIIA inserted in 2025, but with no storage volume or roof-area rate; the Site Development and Slope Modification Regulations, 2017 contain no rainwater harvesting rule, and no rainwater harvesting rule was found outside the Corporation's area, as now. This Manual does not change it.

1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:

  • (a) no sewage connection to a storm drain (Chapter 8);
  • (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
  • (c) waterbody setbacks and the no-fill zone (Chapter 7); and
  • (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).

1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.

1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.

1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.

1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:

  • (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
  • (b) linear road resurfacing that adds no impervious area.

Exempt development remains subject to the RWH mandate and to Clause 1.5.4.

1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.

Figure 1.2 — Applicability decision flowchart Flowchart for Clause 1.5: approval test, exemption test, size threshold test, and flood-sensitive catchment test, leading to the requirements that apply. Development or public work (Clause 1.5.1) Needs building-rules approval, or is it a public work? No Manual not triggered; other rules apply Yes Exempt under Clause 1.5.8? (single dwelling below the threshold, or road resurfacing that adds no impervious area) Yes Exempt from Chapters 4–5. RWH (where mandated) and Clause 1.5.4 still apply No Land disturbance ≥ 0.1 ha, or new or replaced impervious area ≥ 500 m² (Clause 1.5.2)? No Below threshold: RWH (where mandated) and Clause 1.5.4 apply Yes Chapters 4 and 5 apply: retention, detention, downstream and tailwater analysis (+ RWH, 1.5.4) In a flood-sensitive catchment (Annex 1B)? Yes Mixed-frequency rule; full methods only; no Policy Supplement alternatives No Standard rule: Q_post ≤ 0.9 × Q_pre Tier B: design-aid route may be used (Clause 1.7) Decision Chapters 4–5 requirements Chapters 4–5 do not apply

Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.

Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:

  • Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
  • Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
  • The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
  • MBBL 2016 makes recharge mandatory for buildings over 500 m².

The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Mizoram plots are small and the cumulative effect of many small plots is what fills Aizawl's drains. For small buildings in Mizoram, the AMCBR/SD&SM reach every building in the Corporation's area with a duty to provide "a suitable rain water harvesting facility" (AMCBR reg. 33), roof water "discharged at ground level by pipe" and not onto the road or a neighbour's compound (reg. 26(2)(b)), and, where site works are not exempt, the terraces, swales, interceptor drains and down-drains of SD&SM reg. 27. None of it sets a volume or a design storm, and the tank is full when the season's storm arrives, so none of it limits what leaves the plot. Since 2025 an ordinary building on a plot of less than 93 m² in a low or moderate geo-hazard zone may be self-certified by empanelled technical personnel (Annexure B-I), so the smallest plots are approved without a drainage review; Clause 1.5.4(b) applies to every building whatever its size for this reason. A small building on a hill slope is also where a soak pit does most harm: AMCBR reg. 33 asks for "a septic tank of appropriate capacity with soak pit" for every water closet, which on hazard slopes is the practice the Roadmap to Stability would eliminate; this Manual puts no stormwater into a soak pit and does not override reg. 33 (Table 1.3). Outside the Corporation's area no building rule was found, in a Village Council area or in the area of an Autonomous District Council, and there is no permit to which a small building's drainage could be tied. There the small-site method of Chapter 4 and the hill rule of Clause 4.11, no soak pit or soakaway on a slope of more than 10° or on the shale, roof water to storage and its overflow to a lined drain, never down an unprotected slope, are offered to the household, the village and the agencies that build as guidance, not as a condition of any permit, with the terrace, swale and down-drain geometry of SD&SM reg. 27 as the practical minimum on a slope.

Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.


1.6 Tiered adoption

1.6.1 Tier A authorities. The following are Tier A:

  • (a) the Aizawl Municipal Corporation, for its whole area: the only body in the State with building and site-development regulations, an online building permission system and licensed technical personnel (484 at March 2023; 15,162 applications on OBPAS from June 2018 to 1 April 2024; CAG).

1.6.2 Tier B authorities. All other Municipal Councils, Village Councils and Autonomous District Councils are Tier B.

1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:

Table 1.1 — Differences between Tier A and Tier B authorities

Item Tier A Tier B
Performance criteria (Chapters 2–9) Apply in full Apply in full
Hydrologic method for storage Hydrograph method (Chapter 3) Hydrograph method, or the design-aid route of Clause 1.7 where eligible
Compliance calculator (Clause 10.5) Required as a summary Required; may be the sole calculation on the design-aid route
Policy supplement alternatives (Clause 1.7) Only with State Stormwater Technical Committee concurrence May be adopted by council resolution
Technical review By the Authority By the Authority, with UD&PA regional support or an empanelled reviewer (Clause 10.7)
Flood-sensitive catchment rule Applies Applies

1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the Aizawl Development Plan Area of the Master Plan for Aizawl: Vision 2030, or is found by a post-event review (Clause 10.16) to need the full methods.

1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.

Commentary. Aizawl Municipal Corporation, with an online building permission system (OBPAS) since June 2018, 15,162 applications on it from June 2018 to 1 April 2024 and 484 licensed technical personnel at March 2023 (CAG), but no drain inventory or drainage design standard found for this Manual, in an urban area where "67% of Aizawl Urban Area is having kutcha drains and 18% are without any drainage system at all" (Master Plan for Aizawl: Vision 2030), and a Village Council in one of the notified towns that have no urban local body, even with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Aizawl.


1.7 Policy supplement: adoptable alternatives

1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.

1.7.2 The alternatives are:

Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5

No. Main-text requirement Adoptable alternative Eligibility
S-1 Storage sized by hydrograph method (Chapter 3) Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1)
S-2 Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule Any site outside flood-sensitive catchments
S-3 Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 (15 m from top of bank, or from the crest of the bank slope where an incised lui's bank is steeper than 10°) Waterbodies with no mapped 1% AEP extent
S-4 Downstream analysis by hydraulic model (Chapter 5) Screening checklist of downstream capacity and known flooding, with a model only where the screen fails Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall
S-5 On-site detention Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) Where a basin plan has been notified

1.7.3 Conditions on adoption.

  • (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
  • (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
  • (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
  • (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
  • (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).

Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.


1.8 Relationship with other instruments

1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.

Table 1.3 — Relationship with other instruments

Instrument Relationship
Aizawl Municipal Corporation Building Regulations, 2012 (AMCBR; UD&PA Notification No. B.13017/8/2012-UD&PA of 20 December 2012; Mizoram Gazette Extraordinary Vol. XLII, Issue No. 4, 10 January 2013), as amended by the Amendment Regulations of 2019 (No. B.13017/8(2)/2018-UD&PA; final gazette not read [TBC]), 2023 (No. B.13017/8/2021-UD&PA/Pt of 14 August 2023, in force 28 August 2023) and 2025 (No. B.13017/8/2021-UD&PA/Loose of 21 November 2025) Continue. They apply only to "all the areas covered by the Aizawl Municipal Council" (reg. 1(2)). They define "Drain" to include "open channel used for conveying surface water" (reg. 3(17)); require a site "properly drained or capable of being drained" and "not an active hazard-prone area" (21), drains and roof drainage on the plans (5(5)(v), 5(6)(iv), (viii)), a plinth of preferably not less than 0.45 m and roof water "discharged at ground level by pipe" (26(2)), a septic tank and soak pit not within 15 m of "a water source" and "A suitable rain water harvesting facility … in all buildings" (33), and a drain "of adequate capacity to the nearest public drain" (37); and list IS 14458 and IS 14496 (Part 2) "For Protection of Landslide Hazard" (Annexure F). The 2023 amendment makes OBPAS return a proposal "not as per the provisions of the AMC Building Regulations, 2012 and the Master Plan for Aizawl, Vision-2030"; the 2025 amendment makes rainwater harvesting and "Reduction of Hardscape" incentives for plots above 100 m², requires excess materials to be removed from public roads before an Occupancy Certificate, and allows self-certification of ordinary buildings on plots of less than 93 m² in low and moderate geo-hazard zones. They set no stream or spring setback, slope limit, detention, rainwater harvesting size or design storm. Reg. 33's soak pit conflicts on hazard slopes with the Roadmap to Stability and with Clause 4.11 (hill rule): this Manual puts no stormwater into a soak pit and does not override reg. 33. The design criteria of Chapters 2–6, the hill and recharge rules of Clause 4.11, the spring rule of Chapter 8 and the corridors of Chapter 7, whose Zone 1 is at least 15 m, are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the regulations, a master plan or a statute are stricter, they govern (Clause 1.3.3).
Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017 (SD&SM; No. B.13017/75/2016-UD&PA of 4 April 2017; Gazette Extraordinary Vol. XLVI, Issue No. 161, 11 April 2017; amendments not known [TBC]); the Corporation's Landslide Hazard Maps Continue in the Corporation's area. A site development permit is required "in addition to a building permit" (reg. 5(1)); engineered site development, with a geotechnical report, in the Moderate, High and Very High zones of the Landslide Hazard Maps, on unmapped slopes of 24° or more, for cuts of 3 m or more, works of more than 200 m³ and works that support a structure (reg. 4 and the permit tracks); no exemption "within three meters of any slope of 24 degrees or more"; no permit above 60° (reg. 14); plans showing drainage patterns, natural streams, riverine reserves and "flood hazard areas as designated and defined by Aizawl Municipal Corporation" (reg. 6), of which none was found (NEER reading); fill toes drained "with energy dissipaters" (reg. 25); setbacks that "may need to be increased for any required interceptor drains" and the control of "subsurface water, such as springs" (reg. 26); the terraces, swales, interceptor drains, down-drains, pad gradients and downhill conveyance of reg. 27, which this Manual treats as the minimum conveyance layer (Clause 6.3.6); "the riverine reserve shall be maintained" beside natural streams (reg. 28); and excavated material kept off "drainage courses or riverine reserves" (reg. 29). Schedule I makes licensed civil engineers competent for "hydrology and hydraulic calculations". It sets no design storm, return period or runoff coefficient; this Manual supplies them.
Mizoram Municipalities Act, 2007 (Act No. 6 of 2007; Fourth Amendment 2015); the Mizoram Municipalities (Ward Committee and Local Council) Rules, 2010 (No. B.13017/21/2008-UD&PA of 2 November 2010; bilingual) Continue in the municipal areas, the Aizawl Municipal Corporation and the Lunglei Municipal Council; the Act does not extend to Village Council areas or to "the Mizoram Tribal Areas, as referred to in PART III of the paragraph 20 of the Sixth Schedule" (s.1(2)). It vests "all public tanks, streams, reservoirs, and wells" and the drains, culverts and watercourses along streets in the municipality (s.80(b), (d)); makes it "provide and maintain a system of drainage or sewerage as well as a safe and sufficient outfall" (s.288); vests all public drains and drains along public streets in it, "whether made out of Municipal Fund or otherwise" (s.289(1)), with hand-over of sewers to a Government agency (s.289(3)); puts all drains "under the survey and control of the Board of Councillors" (s.290) and requires their cleansing (s.291); allows drainage across private land without notice "in the case of sudden water-logging" (s.294); requires the Chairman's written permission to connect a private drain (s.295) and consent before draining into a municipal drain or "any water-course" (s.296); lets the municipality require foul water to be drained "as distinct from rain-water" (s.298); gives the State control over "imperfect, inefficient or unsuitable" works (s.299); and forbids any structure over a municipal drain, culvert or storm-water channel (s.300). Regulations are made under s.371 "after previous publication". The Corporation's start is given as 1 July 2008 in the Act's preface and as 2010 by the CAG, upgraded on 15 October 2015 [U].
Mizoram (Village Councils) Act, 2025 (Act No. 7 of 2025; Gazette Extraordinary Vol. LIV, Issue No. 178, 20 March 2025), replacing the Lushai Hills District (Village Councils) Act, 1953 Continue in the Village Council areas, including the notified towns without an urban local body; the Act does not extend to the municipalities or the three Autonomous District Councils (s.1(2)). It defines "tuikhur" as "any place wherein water supply is obtained" (s.2(29), numbering inferred from the sequence); lets Village Councils "adopt and enforce the model building bye-laws as may be framed by the State Government" and declare unsafe sites for house construction with the approval of the District Disaster Management Authority (s.13(6)); and lists among their duties "Conserve water resources within the village area" (s.14(6)) and, as assigned, minor irrigation and watershed development, roads and culverts, "Sanitation and drainages" and artificial water bodies (s.15(1)). No model building bye-laws were found (NEER reading); this Manual could be offered as their drainage annex.
The Sixth Schedule areas: the Lai, Mara and Chakma Autonomous District Councils; the Lai Autonomous District Council (Land Holding and Settlement) Act, 2002 (known from a snippet); the Chakma District Council's notices on the Kamalanagar Town Planning Committee (2018), roadside approvals (20 November 2020) and house construction (2002) (known from titles and snippets) Continue in their areas. The State's municipal, village-council and water-resources Acts and the Rivers Bill of 2023 exclude them, and the 74th Amendment does not apply there (CAG). No building or drainage regulation of a District Council was found [TBC]. This Manual has no force there unless a District Council adopts it (Commentary to Clause 1.3).
Mizoram Water Resources (Management and Regulation) Act, 2024 (Act No. 1 of 2024; No. H.12018/273/2023-LJD (IWR) of 15 March 2024; Gazette Extraordinary Issue No. 197); the Mizoram State Water Policy 2020 (as named in the Act) Continue, "except the Autonomous District Councils" (s.1(2)). The Act counts "springs, ponds, lakes, tanks, traditional water harvesting structures, wells" among "community water resources" (s.2(1)(i)); sets up MISWARC and WARDMA (ss.3–6), District Water Resources Committees chaired by the Deputy Commissioner and Village and Local Water Resources Committees chaired by the Village Council President or Local Council Chairman, which are to "Prevent pollution of identified water sources" (ss.9–12); has the IWRD "promote rain water harvesting to augment ground water recharge" (s.14(1)(b)(viii)) and lets WARDMA direct "water conservation and groundwater recharge, including rain water harvesting" (s.16(2)(ix)); requires water-resources mapping within five years (s.17); and sets penalties, with the Deputy Commissioner as penal authority (s.20). On hill ground this Manual reads ss.14 and 16 as storage and reuse, not recharge (Clause 4.11). The constitution notifications of MISWARC and WARDMA were not found [TBC].
Mizoram (Protection of Rivers) Ordinance, 2023 (Ordinance No. 1 of 2023; assent 26 May 2023) and Bill, 2023 (Bill No. 70 of 2023 as printed), whose enactment was not confirmed Not cited as law. As printed, the Bill would extend to the State except the Autonomous District Councils; would provide for Protected Rivers and River Conservation Zones, inside which no construction, "obstruction or diversion of the water course or channel" or land pass would be allowed without the prior approval of a State River Protection Authority, with exemptions that include "bridges and culverts, check dams, waterholes" (s.15(1)); and would let the State regulate catchments "for the prevention of landslips or of the formation of ravines and torrents" and "for the maintenance of water supply in springs, streams and rivers" (s.16). No Protected River or River Conservation Zone is known to have been notified, and no Authority is known to have been constituted. If the law is in force and a zone is notified, its approval is needed in addition to this Manual's.
Mizo District (Forest) Act, 1955 (ss.14 and 21; known by citation); the riverine reserved forests Not cited as a buffer. A notification of 1965 under the Act declared the forest within half a mile on either side of 16 rivers a reserved forest; the High Court quashed it on 27 January 2021, the State's writ appeal was dismissed as withdrawn on 9 November 2022, a special leave petition was filed (outcome not found), a notification of the General Administration Department of April 2021, not read, is reported to set an 800 m restricted zone from mid-river with development by prior approval, and the Supreme Court issued notice over works in riverine reserved forests in April 2024 (all as reported). The master plan's 800 m green belt along the Tlawng rests on the Act and is not statutory law; this Manual does not use it (Chapter 7).
Master Plan for Aizawl: Vision 2030 (Aizawl Development Authority; IIT Kharagpur; Chief Minister's message of 11 September 2012); the draft Aizawl Municipal Corporation (Master Plan and Strategic Zonal/Ward Development Plan) Regulations, 2015; the Mizoram Urban and Regional Development Act, 1990 (Act 12 of 1990, amended 2004) and the Aizawl Development Authority Act, 2005 (titles as listed) Continue as the plan against which OBPAS checks every proposal (2023 amendment). No notification approving the plan was found, and a report of approval in March 2013 is unverified [TBC]; the Aizawl Development Authority that prepared it is "now absorbed in AMC" (CAG); and the zonal and ward plan regulations sent to the Government on 17 May 2023 were not approved by September 2023 (CAG). The plan covers the Aizawl Development Plan Area in ten planning zones; recommends a 15 m green buffer on both sides of major drainage channels; marks an "SL" zone of slopes above 36° and "areas adjacent to major drainage lines"; says "development on slope more than 36 degree should be strongly discouraged"; leaves the zoning of natural-hazard areas as "no development zone" to the zonal plans; records that "67% of Aizawl Urban Area is having kutcha drains and 18% are without any drainage system at all"; proposes eight check dams and "treatment facilities at the outfall points"; and says that "drains need to be cleaned every year before the onset of monsoon". It has no design storm. Master plans would show the flood-sensitive catchments, drainage reserves and regional facility sites of this Manual (Chapter 11).
Roadmap to Stability: Actions to Reduce the Landslide Risk in Aizawl (Landslide Policy Committee for Aizawl City, February 2014); MIRSAC's Atlas of Micro-level Landslide Hazard Zonation of Aizawl City and Selected Towns Inform this Manual. The Roadmap asks PHED to carry rain and waste water "away from exposed hillslopes" to places "that will not saturate potentially unstable slopes", to "eliminate all septic tanks, leach fields and soak pits within Aizawl City" and to set up a drainage office, and gives the Corporation "controlling authority for all developmental activities (Roads, Drainage, quarries etc.)"; its members include PHED, PWD, the Land Revenue and Settlement Department, DM&R, MIRSAC, the Geological Survey of India, Mizoram University, the Corporation and the Directorate of Geology and Mineral Resources. Its drainage actions are the hooks of Clause 4.11 and Chapter 9. The atlas is the only hazard zonation the CAG found (CAG).
Mizoram Official Language Act, 1974 (Act No. 3 of 1975), in effect from 1 August 1977 by a notification of 6 May 1996 (No. H.12017/14/90-LJD, read from a poor scan) Continue. Mizo is the official language; that English may also be used is known only as quoted (section not read). Signs and depth markers under this Manual are in Mizo and English (front matter).
Gauhati High Court (Aizawl Bench): the suo motu PIL on the Bawngkawn–Durtlang (Leitan) road (reported 23 July 2024) and the single-bench order of 23 November 2023 in a petition of 2020 (case numbers not found); the riverine reserved forest judgment of 27 January 2021 and Writ Appeal 8 of 2021; the Supreme Court's notice of April 2024 (all as reported) Apply where they bind; they are directions, not rules of this Manual. The High Court ordered that "no new construction activity shall henceforth be allowed on either side of the Bawngkawn – Durtlang (Leitan) road", kept the Corporation's approvals beyond the first floor "in abeyance", exempted retaining walls for landslide prevention and quoted the master plan's rule against development on slopes of more than 36° (as reported).
National Green Tribunal: OA 593/2017 and OA 673/2018 (MPCB's compliance report, February 2021); OA 606/2018 (the State's report for January–June 2025, liquid-waste table "as on 31st August, 2025") Apply where they bind. The State reports 51.81 MLD of sewage against treatment of 10 MLD "only for Aizawl city", the Chite treatment plant on trial from 6 February 2021, and the River Rejuvenation Committee and State Level Monitoring Committee; it told the Tribunal that "Mizoram being a hilly state, there is no flood plain zone in the catchment area", a statement that does not hold beside the valley floors (Commentary to Clause 1.1). Sewage in storm drains is dealt with in Chapter 8 (Clause 8.9).
Comptroller and Auditor General of India, Report No. 1 of 2025 (tabled 27 August 2025): the performance audits of disaster preparedness and of the 74th Amendment Inform this Manual. The audits find "more than 71 per cent of the total area is in Very High to Moderate Hazard Zone", no regular inspection of landslide-prone areas, "no Action Plan for checking unplanned urbanisation", the National Building Code for Seismic Zone V "yet to be adopted in the sampled Lawngtlai and Mamit districts", 15 of 18 functions devolved to the Corporation but not "Roads & Bridges, Water supply … and Fire Services", and land use still with the Land Revenue and Settlement Department. No audit of storm drains, AMRUT drainage or the Smart City's drains was found.
Groundwater: no State groundwater Act; the Mizoram Ground Water (Control and Regulation) Bill, 2023 (title page only) Continue. No State law regulating groundwater was found; "Areas Notified for Regulation of ground water development: NIL" (CGWB, State profile). Every assessment unit is "Safe" (stage of extraction 3.95%, GWRA 2024, as quoted), so recharge is not a design objective of this Manual (Clause 4.11, recharge rule). The IWRD is named in this Manual for groundwater records; no State observation-well network was found.
Environment (Protection) Act, 1986; Water (Prevention and Control of Pollution) Act, 1974; Wetlands (Conservation and Management) Rules, 2017; the Mizoram Pollution Control Board (MPCB) Continue. No State Wetland Authority notification was found [TBC]. Pala Wetland (Palak Dil) in Siaha district is a Ramsar site (Chapter 7). dils and springs are governed by Chapters 7 and 8.
Disaster Management Act, 2005; MSDMA, DM&R, the District Disaster Management Authorities and the Deputy Commissioners; the State Disaster Management Plan 2020 (as listed) Continue. The notification constituting MSDMA was not found [TBC]. No order of the State fixing a date for pre-monsoon desilting was found; the works calendar of Chapter 10 sets this Manual's dates, beginning with 31 March.
IRC:SP:42-2014, IRC:SP:48 (Hill Road Manual), IS 14458 (Parts 1–3) and IS 14496 (Part 2), and the practice of the PWD and the national-highway agencies on road and hill-road drainage Apply to the drainage of roads and hill roads, cross-referenced from Chapter 6, where they do not conflict with it; the drainage clauses of IRC:SP:48 were not read for this Manual [TBC].
CPHEEO Manual on Storm Water Drainage Systems (2019) Engineering reference. This Manual sets higher return periods under Clause 1.3.2.
NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF.
NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create.
IRC:SP:42-2014 and IRC:SP:50-2013 Apply to road drainage only where they do not conflict with Chapter 6.
MBBL 2016, Chapter 9 Model for RWH and for the inspection regime in Chapter 10.

Commentary. RWH in Mizoram is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the monsoon, because RWH sumps are usually full or the ground saturated by the time a June to August monsoon storm, such as that of mid-June 2018, arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.

Mizoram has slope rules but no drainage design. The Landslide Policy Committee for Aizawl City asked in 2014 that the Public Health Engineering Department "Adopt and implement a five year capital outlay plan to design and construct facilities to capture and transport rain and waste water away from exposed hillslopes and ejected at locations that will not saturate potentially unstable slopes", that it "eliminate all septic tanks, leach fields and soak pits within Aizawl City" and "Create an office within the Public Health Engineering Department to design and build, monitor and repair or improve drainage systems", and that the Corporation "should have controlling authority for all developmental activities (Roads, Drainage, quarries etc.) within AMC area" (Roadmap to Stability, 2014). The master plan proposes permanent drain alignments, "treatment facilities at the outfall points" and eight check dams, below Zuangtui, Sakawrtuichhun, the Government Complex, Mission Vengthlang, Tlangnuam, Saikhamakawn, Melthum and Hlimen (Master Plan for Aizawl: Vision 2030). No storm-drain project of Aizawl Smart City Ltd was found, and the documents found of the ADB's programme for Aizawl cover water supply and sewerage (as summarised). The CAG found that "regular inspection of landslide prone areas and research studies have not been conducted", that there is "no Action Plan for checking unplanned urbanisation" and that the automated landslide monitoring "envisaged in the State Plan since 2015" had not been set up (CAG, Report No. 1 of 2025). None of these states a design storm, and no development-control condition stops new plots from using up the capacity of the drains or putting water into the slopes. Linking Chapters 4–5 to approvals closes that gap.

The State's law holds some of the tools. The slope regulation sets the geometry of the site's drainage, limits what one swale run may drain to 400 m² and makes a site developed downhill carry the drainage from the site above (SD&SM reg. 27); the building regulation requires rainwater harvesting and a drain "of adequate capacity to the nearest public drain" (AMCBR regs. 33 and 37); the Municipalities Act vests the street drains in the Corporation, makes it "provide and maintain a system of drainage or sewerage as well as a safe and sufficient outfall" (s.288), lets it require foul water to be drained "as distinct from rain-water" (s.298) and forbids any structure over a municipal drain or storm-water channel (s.300); the Water Resources Act of 2024 sets up WARDMA and committees down to the village and the locality, whose duty includes "Prevent pollution of identified water sources"; and the Village Councils Act of 2025 lets Village Councils declare unsafe sites. The courts and the tribunal have acted too: the High Court froze new construction on either side of the Bawngkawn–Durtlang road in July 2024 and quashed the riverine reserve notification of 1965 in January 2021 (as reported), and the National Green Tribunal's supervision of sewage and polluted rivers (OA 593/2017, OA 673/2018 and OA 606/2018) produced the reports on which Chapter 8 draws. What the law lacks is a design standard. None of these instruments says which storm a drain or down-drain must carry, how much water a hill site may release or put into its slope, what a terrace swale must carry in a 10-year storm, how long a valley-floor outfall is closed by the river, or how far development stays from a lui; the 400 m² rule fixes an area, not a flow; and none applies in the areas of the Autonomous District Councils. This Manual's checks are framed as part of the building permit and the site development permit given by the competent authority for the area, not as a separate no-objection certificate. This Manual is offered as a technical companion to these instruments, to the Roadmap's drainage actions and to the orders of the courts and the tribunal: it supplies the design storm, detention, outfall, infiltration, hill-site drainage and corridor numbers they do not set, as a proposal for the Government, the Corporation and the other authorities to consider. Neither UD&PA, the Corporation, the LMC, PHED, PWD, the IWRD, any Village Council, any District Council nor any other body has adopted it.


1.9 Roles and responsibilities

1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.

Table 1.4 — Roles and responsibilities under this Manual

Agency Role under this Manual
Urban Development and Poverty Alleviation Department (UD&PA) Notifies the AMCBR/SD&SM that the Board of Councillors makes under section 371 of the Mizoram Municipalities Act, 2007, holds the master plans of urban areas and the town development plans (Allocation of Business Rules, 2019, as quoted by the CAG) and notifies towns. Would prepare, with the Corporation, the amendment of Clause 1.3.1(a) to AMCBR regs. 5(6), 26, 33 and 37 and SD&SM regs. 6 and 27; could frame the model building bye-laws of section 13(6) of the Mizoram (Village Councils) Act, 2025 with a drainage annex; would show flood-sensitive catchments, drainage reserves, the 1% AEP areas of the valley floors and regional facility sites in the master plans (Chapter 11), issue the model bye-law of Clause 1.3.1(b) and give regional support to Tier B authorities (Table 1.1).
Aizawl Municipal Corporation: its Board of Councillors, Local Councils and Ward Committees Gives building permits through OBPAS and site development permits under the AMCBR/SD&SM, holds the street drains of its area (s.289) and must "provide and maintain a system of drainage or sewerage as well as a safe and sufficient outfall" (s.288); its Local Councils give no-objection certificates and see that the regulations "are strictly observed" (AMCBR reg. 15). Could apply this Manual through OBPAS and the site development permit; would then require the drainage report of Chapter 10, check the hill rule of Clause 4.11 and the SD&SM drainage at the site inspections, apply the Manual to its own drains and works, keep the drain register of Table 1.5, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15).
Lunglei Municipal Council (LMC) The State's second urban local body (established November 2021; first election 29 March 2023, CAG); no building regulation of its own was found [TBC]. Could adopt this Manual through regulations of its own under the Municipalities Act; would then apply it as the Corporation does.
State Stormwater Technical Committee (Clause 1.3.2) Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12).
Village Councils Under the Mizoram (Village Councils) Act, 2025, "adopt and enforce the model building bye-laws as may be framed by the State Government" (none found) and declare unsafe sites for house construction with the approval of the District Disaster Management Authority (s.13(6)); "Sanitation and drainages", roads and culverts and "Conserve water resources within the village area" are among their duties (ss.14(6), 15(1)); they allot house sites. Could apply this Manual through the model bye-laws once framed, and use its screening of Clause 2.3.6(i) for unsafe-site declarations; would keep village drains and the catchments of tuikhur clear of stormwater outfalls.
Lai, Mara and Chakma Autonomous District Councils, their Executive Committees and Village Councils Govern their areas under the Sixth Schedule; the State's municipal, village-council and water-resources Acts and the Rivers Bill of 2023 do not extend to them, and no building or drainage regulation of theirs was found [TBC]. The Manual has no force in their areas unless a District Council adopts it. A District Council could adopt it for its area by its own instrument, through its Executive Committee; if it did, it would be the competent authority for the area there. None has. Palak Dil, a Ramsar site, lies in the Mara District Council's area.
Public Works Department (PWD) and the national-highway agencies (NHIDCL among them) Build and maintain the State roads and the national highways, with their side drains and culverts; roads were not devolved to the Corporation (CAG), and the PWD identifies unsafe buildings outside Aizawl (CAG). Would apply Chapter 6 and the hill-road rules of Clause 6.3.6 to their drains and never discharge a road drain onto an unprotected slope; NH-6 at Hunthar is the standing example.
Public Health Engineering Department (PHED) and the State Investment Programme Management and Implementation Unit (SIPMIU) PHED runs the water supply, the sewers, bio-digesters and community soak pits; SIPMIU built the 10 MLD sewage treatment plant at Chite and prepared the sewage plan "for Aizawl City and subsequently for the whole state" (MPCB). The Roadmap asks PHED for a drainage office and a five-year plan to carry rain and waste water "away from exposed hillslopes". Would keep sewer and storm networks separate where sewers are built and intercept sullage before storm outfalls (Chapter 8).
Irrigation and Water Resources Department (IWRD); the Mizoram State Water Resources Council (MISWARC), the Water Resources Development and Management Authority (WARDMA), the District Water Resources Committees and the Village and Local Water Resources Committees Under the Mizoram Water Resources (Management and Regulation) Act, 2024, outside the Autonomous District Councils: the IWRD's Chief Engineer is WARDMA's member secretary, the IWRD is to "promote rain water harvesting to augment ground water recharge" (s.14(1)(b)(viii)), WARDMA may direct "water conservation and groundwater recharge, including rain water harvesting" (s.16(2)(ix)), and the village and locality committees are to "Prevent pollution of identified water sources"; their constitution notifications were not found [TBC]. Would supply river levels and flood marks for Chapter 5, approve the site study of Clause 2.3.6(b) for rural rivers, read rainwater harvesting on hill ground as storage and reuse (Clause 4.11) and protect the catchments of tuikhur.
Environment, Forest and Climate Change Department (EF&CC); the Mizoram River Protection Authority (if constituted) EF&CC holds the riverine reserves and wetlands and is nodal for the spring-shed pilot (as reported). The Rivers Ordinance and Bill of 2023 would set up a River Protection Authority whose prior approval is needed in a River Conservation Zone; enactment, constitution and any zone are not confirmed. Would apply the corridors of Chapter 7 to riverine reserves; the Authority, if constituted, could use them.
Mizoram Pollution Control Board (MPCB) Reports to the National Green Tribunal on sewage and polluted rivers (OA 593/2017, OA 673/2018). Would receive the records of sewage found in storm drains under Chapter 8.
MSDMA, the Disaster Management and Rehabilitation Department (DM&R), the Land Revenue and Settlement Department, the Deputy Commissioners and the District Disaster Management Authorities DM&R "is responsible for prevention, preparedness, mitigation, response, relief and rehabilitation" (CAG) and reports the tolls of floods and landslides; the District Disaster Management Authorities approve the Village Councils' unsafe-site declarations; the Land Revenue and Settlement Department keeps the land records and administers land use, also inside the Corporation's area (CAG). Would supply the landslide and flood inventories used in the screening of Clause 2.3.6(i) and lead post-event reviews with the Authority (Clause 10.16).
Directorate of Geology and Mineral Resources, MIRSAC and the Landslide Policy Committee for Aizawl City The Directorate investigates landslides and attributed two-thirds of the large ones of 2022-23 to "improper drainage" (as reported); MIRSAC prepared the Atlas of Micro-level Landslide Hazard Zonation of Aizawl City and Selected Towns (CAG); the Committee set the standards of the Corporation's Landslide Hazard Maps (SD&SM). Would supply the hazard maps and inventories for Clause 2.3.6(i) and Clause 4.11.
NEEPCO (Tuirial hydroelectric project) and the State's power department (Serlui B) Operate the Tuirial and Serlui B dams. Would supply reservoir levels, release rules and release records in writing for Chapter 5 and the screening of Clause 2.3.6(i).
Aizawl Smart City Ltd Set up in November 2017 and incorporated in March 2018 (CAG); no storm-drain project of it was found. Would design any drainage works to this Manual from the dates of Clause 1.11 and hand them over under Clause 10.14.
Central Water Commission (CWC), a body of the Union Monitors levels at seven sites in the State, five inactive, with no forecasting site (as transcribed by SANDRP). Would supply its records for Chapter 5 and confirm whether a Flood Estimation Report for subzone 2(c) exists or is in preparation (Clause 2.3.6(b)).
Central Ground Water Board (CGWB), North Eastern Region, a body of the Union Assesses the State's groundwater (every unit "Safe") and published the district booklets on which Clause 4.11 rests. Would supply groundwater records with the IWRD.
IMD (Meteorological Centre Aizawl), the Directorate of Science and Technology (DST), the Agriculture Department and the operator of the Mz-SWIC gauges [U] Hold the rainfall records of Chapter 2 that are the first data requests of Clause 2.3.6(a). Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7).

Commentary. Stormwater in Mizoram is split, first, by the three legal geographies: the municipal areas, where the Board of Councillors makes the regulations, UD&PA notifies them and the Corporation grants permission; the Village Council areas, where no building rule has yet been framed; and the areas of the Lai, Mara and Chakma Autonomous District Councils, which none of the State's municipal, village-council, water-resources or river laws reaches. The split is then repeated among the bodies that drain the land: the Corporation for the street drains, which vest in it, the PWD for the drains of the State roads, which were never devolved, the national-highway agencies for NH-6 and NH-306, PHED and SIPMIU for the sewers and the Chite treatment plant, the IWRD and WARDMA for water resources, EF&CC and the Land Revenue and Settlement Department for the riverine reserves and land, NEEPCO for the Tuirial dam, and the courts and the tribunal, which have acted on the Bawngkawn–Durtlang road, the riverine reserves and the polluted lui. Aizawl shows why the split matters. The Chite lui is at once the trunk storm drain of two-thirds of the city's eastern part, the outfall of its one sewage treatment plant, a sewer for the rest of its catchment and a Priority II polluted stretch (CPCB, 2025), and the roadside drains that feed it vest in the Corporation on the statute (s.289(1)) while the PWD maintains the roads they run beside. No notification divides the drains of any Mizoram town among their owners (NEER reading). Until the State issues a rule [TBC], this Manual assigns the drainage elements as in Table 1.5, as Chapter 6 does for the drains themselves, and recommends that each town keep a drain register giving every reach its owner, the lui it reaches, its class on the landslide hazard map and its outfall (set by this Manual). The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers, and on private land or land held under a pass it is put into effect by reservation in the master plan or by agreement, not by acquisition.

Table 1.5 — Working assignment of drainage elements under this Manual

Element Assigned to
Public drains and drains along public streets in the Corporation's area the Aizawl Municipal Corporation (Mizoram Municipalities Act, 2007, ss.80(d), 288, 289(1), 290–291), with its Local Councils
Roadside drains of State roads and highways PWD in practice, because roads were not devolved (CAG), though on the statute the same drains vest in the Corporation (s.289(1)); the overlap is stated, not resolved
Drains of national highways The national-highway agencies
Natural lui and riverine reserves EF&CC and the Land Revenue and Settlement Department (NEER reading)
Sewers and the Chite sewage treatment plant PHED and SIPMIU (s.289(3) allows a hand-over to a Government agency)
Dams and their release reaches NEEPCO (Tuirial) and the State's power department (Serlui B) (NEER reading)
Village drains outside the municipalities The Village Council (Mizoram (Village Councils) Act, 2025, s.15(1)(q), "Sanitation and drainages", an assignable duty)
Drains in Lunglei town The Lunglei Municipal Council under the Municipalities Act (no regulation found [TBC])
Drains in the areas of the Autonomous District Councils The District Council and its Village Councils [TBC]

This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.


1.10 Variances and waivers

1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:

  • (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
  • (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.

1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Mizoram has no coast and no tidal reach, so no site in the State qualifies for this waiver. A site that drains to a river in flood beside a valley floor or terrace, such as the Khawthlangtuipui at Tlabung or the Tlawng at Sairang and Bairabi, to the Tuirial reservoir or its backwater, or to a release reach below the Tuirial or Serlui B dam, is in the outfall-closed condition of Chapter 5 whenever the receiving water is high, and detention is not waived for it; nor is it waived for a site because it drains to a steep lui, a gorge or down a slope.

1.10.3 No variance or waiver. No variance or waiver shall be granted for:

  • (a) a sewage connection to a storm drain;
  • (b) the lowest habitable floor level of Chapter 6;
  • (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7 (15 m from top of bank, or from the crest of the bank slope where an incised lui's bank is steeper than 10°), or any fill or construction in the no-fill zone of Chapter 7; or
  • (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.

1.10.4 Procedure.

  • (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
  • (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
  • (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
  • (d) A variance runs with the approval. It lapses if the approval lapses.

Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Mizoram the one statutory line that once ran along the rivers, the riverine reserved forest of 1965, half a mile either side of 16 rivers, was quashed by the High Court on 27 January 2021 (as reported), the 15 m green buffer along Aizawl's major drainage channels is a recommendation of the master plan only (Master Plan for Aizawl: Vision 2030), the slope regulation's "riverine reserve" is not defined (SD&SM reg. 28), and the State told the National Green Tribunal that "Mizoram being a hilly state, there is no flood plain zone in the catchment area" (MPCB, OA 593/2017) while Tlabung, Sairang and Bairabi flood from their rivers (as reported).


1.11 Transition provisions

1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).

1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.

1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.

1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.

1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.

Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).


1.12 Review and amendment

1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.

1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.

1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.


References (chapter)

Annexes and forms

Annex / Form Content
1A List of Tier A authorities, with the boundaries of the Aizawl Municipal Corporation and of the Aizawl Development Plan Area of the Master Plan for Aizawl: Vision 2030
1B Maps of flood-sensitive catchments
1C Policy Supplement: text of alternatives S-1 to S-5 and model council resolution
1D Model AMCBR/SD&SM amendment and model ULB bye-law
Form 1-1 Applicability Determination
Form 1-2 Variance / Waiver Request