Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, dil and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Mizoram town. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:
- Aizawl east, Chite lui: the catchment of the Chite lui to the Tuirial, with its tributaries, the Chanmari, Ramthar, Mirawng, Tlak, Bangla, Taite, Bethlehem veng, Lawibual, Hmawngkawn, Zemabawktuikhur, Zuangtui and Kawmthlang lui, and the Muthi and Tuipawl lui that also drain the east of the city (Master Plan for Aizawl: Vision 2030); the destructive reaches named in the plan shown, the Chite sewage treatment plant and the Priority II stretch of the Chite stream in the 1D network, and surveyed flood marks and the 1% AEP level of the lui with its sediment, debris and garbage as the boundary condition, since no lui has a gauge;
- Aizawl west, Ser lui: the catchment of the Ser lui to the Tlawng, with its streamlets, the Ramri, Tuikal, Vai and Zawngkawt lui, and the Khatla, Tuikual, Vaivakawn and Chanmari west lui, "the worst destructive streams and nullahs" of the west (the same plan), with the same boundary conditions;
- Aizawl, hazard areas within these basins: the Hlimen–Melthum quarry belt on the city's southern edge, the Hunthar Veng sinking area and the cuts of NH-6 at Hunthar, and Durtlang with the Bawngkawn–Durtlang road, each mapped with its debris paths in whichever of the two basins it drains to [TBC];
- Sairang, Tlawng: the catchments of Sairang that drain to the Tlawng, with the CWC level-monitoring site at Sairang (no high flood level published) and surveyed flood marks as the boundary, and the outfall-closed case a design case (Clause 5.8.5(c));
- Bairabi and Vairengte, northern valley floors: the catchments of the two towns in sub-area MZ-A1, with surveyed flood marks of the receiving rivers as the boundary for at least the 72-hour storm, the adjoining Barak-valley rule of the series governing the reaches downstream;
- Tlabung, Khawthlangtuipui: the catchments of Tlabung that drain to the Khawthlangtuipui, in sub-area MZ-D1, with the river at its surveyed flood level as the boundary for not less than 72 hours (Clause 5.8.5(d)), the floods of June 2017 and July 2019 as calibration evidence, and no downstream Indian control;
- Lunglei town: the catchments of Lunglei and the lui that receive them, whose names and outfalls are to be confirmed in the first BSMP [TBC];
- Serchhip town: the catchments of Serchhip, 89.2% of whose area is steeper than 30° (this Manual's arithmetic on MIRSAC's slope classes), with the lui that drain towards the Mat [TBC];
- Champhai town and the Champhai flats: the catchments of the town and the paddy flats of sub-area MZ-C1, draining towards the Tiau, with surveyed flood marks as the boundary and the Myanmar reaches beyond any Indian gauge;
- Siaha and Lawngtlai: the catchments of the two Autonomous District Council towns in sub-area MZ-D, through the District Councils only, if they adopt the Manual; and
- Tuirial release reach: the catchments that drain to the Tuirial below the NEEPCO dam, with the largest recorded release or, until NEEPCO gives one, the spillway capacity, as the boundary (Clause 5.8.5(e)).
Hazard first in every sub-area (set by this Manual). In every sub-area of Annex 2A, because the State's binding stormwater hazard is the landslide that drainage starts, every BSMP begins with a hazard screening for landslides, debris flows, quarry faces, sinking ground, river floods on valley-floor land and dam releases, made with the Corporation's Landslide Hazard Maps and MIRSAC's zonation where they exist, the inventories of MSDMA and DM&R where they exist [TBC], and NEEPCO's release reach below the Tuirial dam, and uses site-specific hydrology in place of a CWC report, which subzone 2(c) does not have (Clause 2.3.6(b), (c) and (i)), with the 72-hour storm of Clause 2.3.6(e) as well as the short storms. The record is why: "more than 71 per cent of the total area is in Very High to Moderate Hazard Zone", and landslides in 2017-18 to 2021-22 affected 661 villages and killed 41 people (CAG, Report No. 1 of 2025); a team of the Directorate of Geology and Mineral Resources found that "two-thirds of large-scale landslides … were due to improper drainage" (2022-23, as reported); and the State's deadliest dated rain events, Laipuitlang in 2013, Cyclone Remal in 2024 and the storm of 24 May–3 June 2025, were landslides, not floods. The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, no water is put into the ground on hill ground (Clause 4.11, hill rule), and no work in the CIP is sized to carry a debris flow or a landslide. Other towns define their basins in the first BSMP that covers them. Where CWC, NEEPCO, a master plan or a court has a high flood level, a reservoir level, a line or an operating rule for a dam, gate or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Mizoram a single lui passes through many hands on its way from a ridge to a river. Aizawl drains east to the Tuirial through the Chite lui, which takes "more than two-third of eastern portion" of the city with its tributaries, the Chanmari, Ramthar, Mirawng, Tlak, Bangla, Taite, Bethlehem veng, Lawibual, Hmawngkawn, Zemabawktuikhur, Zuangtui and Kawmthlang lui, and through the Muthi and Tuipawl lui; and west to the Tlawng through the Ser lui and its streamlets, the Ramri, Tuikal, Vai and Zawngkawt lui (Master Plan for Aizawl: Vision 2030). The same lui are at once storm drains, sewers and the feeders of rivers that supply the city: CPCB placed the Chite stream "near SIPMIU's STP to Armed Veng" and the Tuikual stream in Priority II of its polluted river stretches (2025), and the master plan finds septic effluent finding its way "through drains and cross drains to the rivers, which are the sources of water supply". Along one lui the public drains and the drains of public streets vest in the Aizawl Municipal Corporation (Mizoram Municipalities Act, 2007, s.289(1)), the side drains of State roads are PWD's in practice and those of NH-6 the national-highway agencies', the sewers and the Chite sewage treatment plant are PHED's and SIPMIU's, the natural channel and any riverine reserve fall to EF&CC and the Land Revenue and Settlement Department (this Manual's reading), and below the city the lui crosses Village Council land. Beyond the towns the rivers leave the State: the Tlawng, the Tuirial and the Tuivai north to the Barak plain, the Khawthlangtuipui south-west to Bangladesh, the Chhimtuipui south to Myanmar, and the Tiau, on the eastern border, into Myanmar (this Manual's reading); in the south the Lai, Mara and Chakma Autonomous District Councils lie outside the municipal, village-council and water-resources Acts alike. No rule divides the lui from the municipal drains (as this Manual reads the record). This clause makes the basin the planning unit, so that one model carries each lui from its head on the ridge to the river or reservoir whoever owns each reach, and so that the sewage it carries is separated before it reaches the river (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of the Aizawl Development Plan Area: the Aizawl Municipal Corporation, in which the public drains and the drains of public streets vest (Mizoram Municipalities Act, 2007, s.289(1)) and whose Board of Councillors makes the AMCBR and SD&SM (s.371), with its Local Councils, jointly with the Urban Development and Poverty Alleviation Department (UD&PA), which holds master planning for urban areas and into whose plans, the Master Plan for Aizawl: Vision 2030 and the zonal and ward plans that are to follow it, the BSMP is taken (Clause 11.9). For the basins of Lunglei: the Lunglei Municipal Council, with UD&PA. Each role is the one the body would have if the Manual were adopted. Where a basin extends beyond the municipal limits, the Village Councils of the villages it crosses are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No order dividing the lui and natural streams from the municipal drains, or the drains of the local bodies from the rivers and reservoirs, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: IWRD for the rivers and their flood works; the Aizawl Municipal Corporation and the Lunglei Municipal Council for the drains that vest in them; PWD for the side drains, catch-water drains and culverts of the State roads, and the national-highway agencies for those of NH-6 and the other national highways, with the spoil of their works; PHED and SIPMIU for the sewers and the Chite sewage treatment plant; NEEPCO for the Tuirial reservoir, its levels and its releases, and the State's power department for Serlui B; EF&CC and the Land Revenue and Settlement Department for the natural lui and any riverine reserve (this Manual's reading); the Village Councils for the village drains outside the municipalities; and MSDMA, with DM&R, the Corporation's Landslide Hazard Maps and MIRSAC's zonation, for the mapping of landslide, debris and sinking hazards that a BSMP must show.
- In the notified towns without an urban local body, Serchhip, Champhai and Kolasib among them (this Manual's reading of the CAG's count of 13 such towns), and in other Tier B bodies: the Lead Authority is named by UD&PA, with the Village Councils of the town; in an Autonomous District Council area, Siaha and Lawngtlai among them, it is the District Council, only if the District Council adopts the Manual (none has). Basins draining to a common river reach or reservoir may be grouped into one district-level plan.
MSDMA and the Deputy Commissioner shall be consulted on every BSMP; NEEPCO on every BSMP whose basin drains to the Tuirial reservoir or to a reach below its dam, and the State's power department for Serlui B; EF&CC on every BSMP whose basin includes a riverine reserve or a wetland; MPCB on every BSMP that proposes works on a lui or drain that carries sewage, among them the Chite, Tuikual and Lawibual streams; the Village or Local Water Resources Committee on every BSMP whose basin holds a tuikhur or other identified water source; the landholders, or the Village Council, on every BSMP that needs private land or land held under a land pass for a corridor or storage, which is reserved in the master plan or secured by agreement; and, for a basin whose outfall lies on a river that flows on to the Barak plain, such as the Tlawng, the Tuirial or the Tuivai, the water resources department of the adjoining State, through IWRD.
The Irrigation and Water Resources Department (IWRD) shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, dil, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, lui, rivers, dils and reservoirs | The datum of every level named; on valley-floor land, outfall invert levels against the high flood level of the receiving river at the nearest CWC level-monitoring site where there is one (Turial on the Tuirial, 149.0 m on 17 June 1995, the only one published; no site in the State has a warning or danger level; CWC levels as transcribed by SANDRP, as reported, with the datum not stated), and elsewhere against surveyed flood marks, with any local gauge kept as a separate series; for the free outfalls of the ridge towns, the Chite lui and the Ser lui in Aizawl among them, the bed and bank profile of the receiving lui to the next confluence, its debris and garbage lines and the 1% AEP flood level with its sediment, debris and garbage; for outfalls to the Tuirial reservoir or to the reaches below the Tuirial and Serlui B dams, NEEPCO's full reservoir level (90.5 m) and minimum drawdown level (68.0 m), the maximum water level and the spillway and release data, and the levels of Serlui B from the State's power department [TBC], naming which is used; dils at their surveyed spill levels; the landslide hazard zones of the Aizawl Municipal Corporation's Landslide Hazard Maps and MIRSAC's zonation, slopes above 60°, quarries active and disused, the Hunthar Veng sinking area and the debris paths below cut slopes, fills and retaining walls; and the flap gates, debris racks, sediment traps, debris basins, check dams and any pumping stations on the outfalls, with their capacities and operating rules |
| Rainfall and levels | All available rain gauges (IMD, including the ordinary gauges of its Meteorological Centre Aizawl and at Lengpui, neither of which is in IMD's Extremes, and its automatic weather stations at Mizoram University, Kolasib, Champhai, Khawzawl, Serchhip, Hnahthial, Saiha and Chawnhu (record lengths [TBC]); the automatic rain gauges and weather stations listed under Mz-SWIC, about 30 sites (the operator's name is not expanded in the source; start years and logging intervals [TBC]); the State Meteorological Centre of the Directorate of Science and Technology, whose series runs from the 1980s to 2021 (gauge list not seen [TBC]); the ordinary gauges of the Agriculture Department at Serchhip, North Vanlaiphai, Lunglei, Haulawng and Tlabung; the rain gauges of CWC, among them Bairabi, Dapchhuah, Mat-1, Tlabung, Tuichawng, Tuipui D and Shitlangpui, and its level-monitoring sites at Sairang and Turial; the reservoir records of NEEPCO at the Tuirial dam [TBC]; and any gauges or sensors kept by the Aizawl Municipal Corporation, MSDMA or IWRD [TBC]) and water-level records, including those for the 28 May 2024 (Cyclone Remal: the collapse at about 6 a.m. of a disused stone quarry between Melthum and Hlimen and other slides in Aizawl, with tolls reported rising to 29 dead in Aizawl district, with 7 missing, by 29 May, and given later as 15 at the quarry and 5 at Hlimen, or 34 in seven Aizawl areas, and 27–29 for the State, all as reported; the rainfall at Aizawl on 27–28 May 2024 was not found, and the 20 mm at Mizoram University in IMD's release of 28 May is for an unclear window), 24 May–3 June 2025 (598 landslides, five dead, 171 houses damaged and 257 road blockages, with Champhai 209, Serchhip 116, Khawzawl 75, Lunglei 61 and Aizawl 21, DM&R figures as reported; Serchhip 104.6 mm, Kolasib 98.3 mm and Aizawl 97.4 mm on one day whose date is not fixed, as reported; no IMD series for the storm was found), June 2018 (148 mm at Aizawl in one day, probably 12 June, and 677 mm in Serchhip district in 1–13 June, ten dead in landslides on 5 June, houses flooded at Tiperabagh, Serhuan and Tlabung and families stranded at Sairang, all as reported), July 2019 (about 400 houses flooded by the Khawthlangtuipui at Tlabung, 150 of them in the town, and three killed in the State, as reported; no rainfall value was found) and June 2017 (the Khawthlangtuipui flood at Tlabung, with about 350 houses submerged in the sub-division by one count, or 9 fully and more than 60 partly by another, and 8–10 dead, as reported; no rainfall value was found) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the valley floors and river terraces at Sairang, Bairabi, Vairengte, Chawngte and Tlabung and on the Champhai flats, where the rivers back up over gentle slopes, and on the margins of dils and reservoirs, where a raised road, a dumped fill or a low wall can turn an overflow from one side of a valley floor to the other, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 28 May 2024 (Cyclone Remal: the collapse at about 6 a.m. of a disused stone quarry between Melthum and Hlimen and other slides in Aizawl, with tolls reported rising to 29 dead in Aizawl district, with 7 missing, by 29 May, and given later as 15 at the quarry and 5 at Hlimen, or 34 in seven Aizawl areas, and 27–29 for the State, all as reported; the rainfall at Aizawl on 27–28 May 2024 was not found, and the 20 mm at Mizoram University in IMD's release of 28 May is for an unclear window), 24 May–3 June 2025 (598 landslides, five dead, 171 houses damaged and 257 road blockages, with Champhai 209, Serchhip 116, Khawzawl 75, Lunglei 61 and Aizawl 21, DM&R figures as reported; Serchhip 104.6 mm, Kolasib 98.3 mm and Aizawl 97.4 mm on one day whose date is not fixed, as reported; no IMD series for the storm was found), June 2018 (148 mm at Aizawl in one day, probably 12 June, and 677 mm in Serchhip district in 1–13 June, ten dead in landslides on 5 June, houses flooded at Tiperabagh, Serhuan and Tlabung and families stranded at Sairang, all as reported), July 2019 (about 400 houses flooded by the Khawthlangtuipui at Tlabung, 150 of them in the town, and three killed in the State, as reported; no rainfall value was found) and June 2017 (the Khawthlangtuipui flood at Tlabung, with about 350 houses submerged in the sub-division by one count, or 9 fully and more than 60 partly by another, and 8–10 dead, as reported; no rainfall value was found) events are the best calibration data Mizoram has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and dil storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule matters in Mizoram less for tanks than for the few places that hold water: its reservoirs, its few dils, its valley floors and its springs; it has no irrigation tank cascades. The Tuirial reservoir of NEEPCO has a full reservoir level of 90.5 m and a minimum drawdown level of 68.0 m (CERC, Petition No. 125/MP/2021), and the levels of Serlui B were not found [TBC]; no survey of their sedimentation was found [TBC]. The best-known dils are Palak Dil, the Pala Wetland in Siaha district, in the Mara Autonomous District Council's area, Ramsar site No. 2484, designated on 31 August 2021 according to its Ramsar information sheet (as quoted) and announced on 26 July 2022 (as reported), a site of 1,850 ha with a water body of about 135 ha (as quoted); and Tam Dil, 6 km from Saitual, rebuilt as a fishery reservoir by the Fisheries Department (as reported; area not found). The Master Plan for Aizawl: Vision 2030 puts rivers, streams and water bodies at 585 ha, 3.83% of its area, places springs, ponds, lakes and wetlands in its "W" use zone and recommends stopping the dumping and earth filling of water bodies; the Mizoram Water Resources (Management and Regulation) Act, 2024 counts "springs, ponds, lakes, tanks, traditional water harvesting structures, wells" among "community water resources" (s.2(1)(i)), and "tuikhur" is defined in law as "any place wherein water supply is obtained" (Mizoram (Village Councils) Act, 2025, s.2(29)). No State Wetland Authority notification, no notified wetland other than the Ramsar site, no inventory of Aizawl's tuikhur and no survey of the storage of any dil or of any valley floor was found [TBC].
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Mizoram has been adopted with a design factor; the Agriculture Department's project report for NAFCC (2016), citing a "State remote sensing center report", projects "nearly 25% increase in rainfall" in some districts and a rise of "about 26%" in the number of yearly extreme rainfall events, which is a statement of frequency, not of intensity, and is not used as a factor; the State Action Plan on Climate Change itself was not read [TBC]; and in every sub-area the 72-hour storm of Clause 2.3.6(e) and the hazard screening of Clause 11.3.3 are run in every scenario, because the State's landslide storms last for days.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 28 May 2024 (Cyclone Remal: the collapse at about 6 a.m. of a disused stone quarry between Melthum and Hlimen and other slides in Aizawl, with tolls reported rising to 29 dead in Aizawl district, with 7 missing, by 29 May, and given later as 15 at the quarry and 5 at Hlimen, or 34 in seven Aizawl areas, and 27–29 for the State, all as reported; the rainfall at Aizawl on 27–28 May 2024 was not found, and the 20 mm at Mizoram University in IMD's release of 28 May is for an unclear window), 24 May–3 June 2025 (598 landslides, five dead, 171 houses damaged and 257 road blockages, with Champhai 209, Serchhip 116, Khawzawl 75, Lunglei 61 and Aizawl 21, DM&R figures as reported; Serchhip 104.6 mm, Kolasib 98.3 mm and Aizawl 97.4 mm on one day whose date is not fixed, as reported; no IMD series for the storm was found), June 2018 (148 mm at Aizawl in one day, probably 12 June, and 677 mm in Serchhip district in 1–13 June, ten dead in landslides on 5 June, houses flooded at Tiperabagh, Serhuan and Tlabung and families stranded at Sairang, all as reported), July 2019 (about 400 houses flooded by the Khawthlangtuipui at Tlabung, 150 of them in the town, and three killed in the State, as reported; no rainfall value was found) and June 2017 (the Khawthlangtuipui flood at Tlabung, with about 350 houses submerged in the sub-division by one count, or 9 fully and more than 60 partly by another, and 8–10 dead, as reported; no rainfall value was found) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and dils with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: dils, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: energy dissipators, stepped chutes, drop structures and protected outfalls wherever a drain or down-drain reaches a lui, so that none discharges onto an unprotected slope, with the receiving lui stabilised to the next confluence where the check of Clause 5.8.5(a) shows it eroding; debris racks, sediment traps and debris basins where lui enter culverts and covered drains, with ramps for the machines that empty them, and the check dams proposed in the Master Plan for Aizawl: Vision 2030 where a BSMP confirms them; flap gates and penstocks on the outfalls of the valley floors and terraces to the Tlawng at Sairang and Bairabi and to the Khawthlangtuipui at Tlabung, with storage or pumping behind them where a river in flood can close an outfall; the interception and screening of dry-weather flow before the outfalls to the Chite, Tuikual and Lawibual streams and the Tuipui, to any dil and above any tuikhur (Chapter 8, Clause 8.9); and the release rules of the Tuirial and Serlui B dams that set the receiving levels, agreed with NEEPCO and the State's power department;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by its Meteorological Centre Aizawl, rainfall alarms from the automatic gauges of IMD and Mz-SWIC, level gauges with alarms on the Khawthlangtuipui at Tlabung and on the valley rivers at Sairang and Bairabi, which have none today, warnings from NEEPCO before releases from the Tuirial dam [TBC], the automated landslide monitoring "envisaged in the State Plan since 2015" and not yet set up (CAG), and the District Disaster Management Authorities), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on the springs (tuikhur) and spring-fed water points that supply the villages and part of the towns, and their catchments above the water points, which this Manual keeps free of paving and of infiltrated road runoff (the spring rule of Chapter 8), the stability of hill slopes, where water put into shale, colluvium, fill or slide debris raises the pore pressure, as SD&SM 2017 warns and the slides of Hlimen and Laipuitlang show, recharge on tested valley alluvium and river terraces, the only ground where it is allowed (Clause 4.11, recharge rule), although groundwater is barely drawn (stage of extraction 3.52% in 2011, CGWB, and 3.95% in 2024, as quoted), and the quality of the springs, lui, rivers, dils and reservoirs that the runoff reaches, several of which carry sewage (Chapter 8, Clause 8.9) (Chapter 8);
- effect on downstream basins and the receiving river, stream (lui), dil or reservoir; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Storage comes first in Mizoram for a different reason than on the plains: there is little flood storage left to restore on the ridges, but every litre held on a site is a litre that does not run down a cut slope or into a lui already "turbulent with high velocities of currents during the monsoon season" and "very destructive" (Master Plan for Aizawl: Vision 2030), and on the valley floors at Tlabung, Sairang and Bairabi the outfalls are closed while the rivers are high. On hill ground storage means a lined tank or a paved terrace, never a pond that soaks into the ground (Clause 4.11, hill rule). The storage of at least 25 litres per m² of roof that Clause 4.11 sets, where the AMCBR require "a suitable rain water harvesting facility … in all buildings" (reg. 33) without a volume, is the first of it, and it also serves supply: 27.16% of households in the Aizawl Urban Area use rain water (the same plan), and PHED's supply was reported at 44 litres per head per day, with 35% unaccounted for (as reported; date not fixed). The master plan's eight proposed check dams, below Zuangtui, Sakawrtuichhun, Government Complex, Mission Vengthlang, Tlangnuam, Saikhamakawn, Melthum and Hlimen, would hold sediment and debris as well as water, and are confirmed or replaced by the BSMP. Concrete channels alone will not serve on a lui that carries garbage, boulders, slide debris and sewage. The storms are large for drains with no stated design basis: 148 mm fell at Aizawl in one day, probably 12 June 2018, and 677 mm in Serchhip district in 1–13 June 2018 (as reported), and the 50-year 72-hour depth of NIH-DHAARA's Aizawl cell is 318.9 mm. Conveyance upgrades on their own move water faster to a steep lui whose bed and banks erode and slide with the debris and garbage it carries, to an outfall on a valley floor that the Tlawng, the Khawthlangtuipui or another river in flood may close, or to a reach below the Tuirial or Serlui B dam whose level the releases set. Groundwater in Mizoram calls for storage and the protection of springs, not recharge. The stage of groundwater extraction was 3.52% in 2011, with "Areas Notified for Regulation of ground water development: NIL" (CGWB, State profile), and 3.95% in 2024, with all 26 assessed units safe (CGWB, as quoted); in Lunglei district "Ground water is used for drinking purpose only" and no water-level trend is available "due to lack of ground water abstraction" (CGWB). Little rain enters the ground: the shale, siltstone and sandstone ridges of the Surma group are "characterized by low permeability and infiltration" and act as a "run off zone" (CGWB, Lunglei). The towns' water comes from rivers, roofs and springs: "the main source of water supply for Aizawl is from Tlawng River", 27.16% of households in the Aizawl Urban Area use rain water and 1.01% spring water (Master Plan for Aizawl: Vision 2030, Table 8.2), and "Mizoram is an abode of springs" (CGWB), whose yields of "3,000 to 20,000 liters per day" in January to March sustain the dry season (CGWB, Lunglei). The springs are under strain: "Urbanisation has led to drying up of traditional water sources, like tuikhur" (as reported), and spring-shed work is reported under a GIZ-supported study of 20 springs, with the Forest Department as nodal agency for a pilot of 100 springs, and by NEIDA and the Tata Trusts in Serchhip and Lunglei districts (all as reported); no count of Aizawl's tuikhur was found [TBC]. Water put into the ground on the hills does harm: SD&SM 2017 names "increasing the amount of groundwater penetrating into slopes" among the causes of slope instability, and the Roadmap to Stability (2014) asked for the elimination of "all septic tanks, leach fields and soak pits within Aizawl City". No State groundwater Act was found; the Mizoram Ground Water (Control and Regulation) Bill, 2023 is known by its title page only. The Mizoram Water Resources (Management and Regulation) Act, 2024 has IWRD "promote rain water harvesting to augment ground water recharge" (s.14(1)(b)(viii)); on hill ground this Manual reads that duty as storage and reuse, not recharge (Clause 4.11). This is why springs and their catchments, slope stability, recharge on the only ground that can take it, and the quality of the water the runoff reaches are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plan for Aizawl: Vision 2030, against which OBPAS checks every proposal (its approval notification was not found [TBC]), and the zonal and ward development plans that are to follow it, whose regulations were sent to the Government on 17 May 2023 and had not been approved by September 2023 (CAG), with the AMCBR and SD&SM; the master plans of other urban areas and notified towns that UD&PA prepares, among them any plan for the Lunglei Development Planning Area, known by the title of its notification [TBC]; in the Autonomous District Council areas, any plan or regulation of the District Council, if the District Council adopts the Manual; and the layouts and buildings permitted under them. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Mizoram's water lines are drawn by plan, by regulation and by court, and none of them is a statutory stream setback. The Master Plan for Aizawl: Vision 2030 recommends "a 15 meters wide green buffer on both sides" of the major drainage channels, which is a recommendation of the plan, and keeps an 800 m green belt on either side of the Tlawng "as per the Mizo District (Forest) Act, 1955, section 14 read with section 21"; the legal basis of that belt, the Riverine Reserved Forest notification of 1965, was quashed by the Gauhati High Court on 27 January 2021, and a notification of April 2021 reported to set an 800 m restricted zone was not read (as reported), so this Manual never treats 800 m as statutory and does not use it. SD&SM 2017 requires that "the riverine reserve shall be maintained" for plots beside natural streams (reg. 28), without defining it, keeps excavated material off "drainage courses or riverine reserves" (reg. 29), and asks site plans to show "flood hazard areas as designated and defined by Aizawl Municipal Corporation" (reg. 6), but no such area has been designated. River Conservation Zones under the Mizoram (Protection of Rivers) Ordinance, 2023 (Ordinance No. 1 of 2023) and Bill, 2023, whose enactment was not confirmed, would bar construction and the obstruction or diversion of a watercourse without the State Authority's approval, but none has been notified. The AMCBR keep septic tanks and soak pits 15 m from "a water source" (reg. 33), and the slope lines are firmer than the stream lines: no site development permit above 60° (SD&SM reg. 14), engineered site development in Moderate, High and Very High hazard zones and from 24° where unmapped, and the master plan's "SL" zone of slopes above 36° and "areas adjacent to major drainage lines", with its "W" zone for rivers, streams, springs, ponds, lakes, wetlands and water catchment areas; the plan leaves detailed hazard zoning, "no development zone" included, to the zonal development plans, which were not yet approved in September 2023 (CAG). The State told the National Green Tribunal that "Mizoram being a hilly state, there is no flood plain zone in the catchment area" (MPCB, in O.A. No. 593 of 2017 and O.A. No. 673 of 2018), yet the Khawthlangtuipui flooded Tlabung in 2017, 2019 and 2023, families were stranded at Sairang in 2018, and Bairabi on the Tlawng and Champhai on the Tiau are reported among the lowland flood towns (all as reported), so the statement does not hold on those valley floors; no flood plain zoning law was found. Where a notified line or a master-plan line governs, it applies; elsewhere the corridor of Chapter 7 applies as this Manual's proposal, stricter than any statute: a Zone 1 of not less than 15 m from the top of bank of every channel draining 8 ha or more, measured on an incised lui whose bank is a slope steeper than 10° from the crest of that slope, and a Zone 2 to the 1% AEP extent plus 10 m, whichever is wider, for new development and redevelopment approved under the Manual, with Zone 1 land that is private or held under a land pass reserved in the master plan or secured by agreement, not taken, and in an Autonomous District Council area only through the District Council [TBC]. A BSMP gives the master plan, the zonal plans and UD&PA the 1% AEP map of valley-floor land and the lui corridors, with the debris paths and landslide hazard zones beside them, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the AMCBR require a suitable rainwater harvesting facility in every building (regs. 5(6)(ix) and 33) and, since 2025, offer incentives for rainwater harvesting and the "Reduction of Hardscape" on plots above 100 m², SD&SM 2017 makes every site developed downhill of another carry the uphill site's drainage "in a safe manner to the nearest practicable drainage way" (reg. 27), and the Master Plan for Aizawl: Vision 2030 keeps "Around 52% of total urban area" under non-urban uses, among them water bodies and undevelopable sloping land, but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on hill ground it is a lined tank or a shallow paved terrace that drains to a lined drain, never an infiltration basin (Clause 4.11, hill rule). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Aizawl Development Authority (2012). Master Plan for Aizawl: Vision 2030, prepared by the Department of Architecture and Regional Planning, IIT Kharagpur (drainage, 8.3; check dams, 4.9.12; hazard zoning, 12.3; water supply, Table 8.2; its approval notification was not found [TBC]). https://amcmizoram.com/uploads/files/Master%20Plan%20For%20Aizawl%20Vision%20-%202030_18032019040050.pdf
- Aizawl Municipal Corporation. Draft Aizawl Municipal Corporation (Master Plan and Strategic Zonal/Ward Development Plan) Regulations, 2015 (draft). https://amcmizoram.com/uploads/files/draft-master-plan-and-strategic-zonal-ward-development-plan_21042017103706.pdf
- Landslide Policy Committee for Aizawl City (2014). Roadmap to Stability: Actions to Reduce the Landslide Risk in Aizawl, with technical support from GeoHazards International (surface runoff actions). https://amcmizoram.com/uploads/files/AMC%20Roadmap%20to%20Stability_15012019035648.pdf
- Comptroller and Auditor General of India. Report No. 1 of 2025 (Government of Mizoram, year ended 31 March 2023): hazard zones, landslide losses 2017-18 to 2021-22, the Hunthar Veng sinking area, the Durtlang BSUP collapse, and the zonal and ward plan regulations. https://cag.gov.in/ag/aizawl/en/audit-report/details/122595
- Central Ground Water Board, North Eastern Region. Ground Water Scenario of Mizoram (State profile) and Ground Water Information Booklets for Lunglei and Serchhip districts (stage of development; springs; hydrogeology); with the assessment of 2024 (as quoted).
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (Chite and Tuikual streams, Priority II). https://dste.py.gov.in/ppcc/pdf/Laboratory/PRS-2025.pdf
- Central Electricity Regulatory Commission. Order in Petition No. 125/MP/2021 (NEEPCO, Tuirial HEP: reservoir levels, dam and spillway). https://www.cercind.gov.in/2023/orders/125-MP-2021.pdf
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Government of Mizoram, Urban Development and Poverty Alleviation Department. Aizawl Municipal Corporation Building Regulations, 2012 (as amended to 2025), regs. 5(6)(ix) and 33; and Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017, regs. 1, 6, 14 and 27–29.
- The Mizoram Municipalities Act, 2007 (Act No. 6 of 2007), s.289; The Mizoram Water Resources (Management and Regulation) Act, 2024 (Act No. 1 of 2024), ss.2(1)(i) and 14; The Mizoram (Village Councils) Act, 2025 (Act No. 7 of 2025), ss.1(2), 2(29) and 15(1); and the Mizoram (Protection of Rivers) Ordinance, 2023 (Ordinance No. 1 of 2023) and Bill, 2023, whose enactment was not confirmed.
- Mizoram Pollution Control Board. Report in O.A. No. 593 of 2017 and O.A. No. 673 of 2018 before the National Green Tribunal (February 2021) ("no flood plain zone"). https://www.greentribunal.gov.in/
- Ramsar Convention. Ramsar Information Sheet for Pala Wetland, site No. 2484 (as quoted).
- Agriculture Department, Government of Mizoram (2016). Detailed Project Report for the National Adaptation Fund for Climate Change (rainfall projections, as quoted from a State remote sensing report). https://moef.gov.in/uploads/2017/08/Mizoram.pdf
- NIH-DHAARA (National Institute of Hydrology), IMDAA dataset, queried 14 November 2026 (Aizawl cell).
- South Asia Network on Dams, Rivers and People (2018). Overview of CWC's flood monitoring and forecasting in North East India (transcription of CWC site data). https://sandrp.in/2018/08/05/overview-of-cwcs-flood-monitoring-forecasting-in-north-east-india/
- EastMojo, Down To Earth, Senhri Journal, PTI, Morung Express, Business Standard and other regional sources (2017–2026). Reports of the Tlabung floods, the June 2018 storms, the springs and tuikhur of Aizawl, PHED's supply, the spring-shed programmes, Tam Dil, the Pala Wetland's announcement, the Tuirial dam-break study and the Directorate of Geology and Mineral Resources' finding on improper drainage (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Mizoram building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. No Mizoram town has a published storm-drainage master plan with a design storm. The Master Plan for Aizawl: Vision 2030, prepared for the Aizawl Development Authority by the Department of Architecture and Regional Planning of IIT Kharagpur (Chief Minister's message of 11 September 2012), is the only city plan found; OBPAS checks every proposal against it (AMCBR, 2023 amendment), but its approval notification was not found, and a date of March 2013 given in one source is unverified [TBC]. Its drainage chapter describes and proposes; it does not design. It finds that "67% of Aizawl Urban Area is having kutcha drains and 18% are without any drainage system at all. Only 15% of the area is provided with pucca drains"; that there is "no major water logging in Aizawl as it is situated in sloppy ground", yet 33% of the Aizawl W-I area is water-logged "for several days or for hours", which it blames on solid waste in the roadside drains; that drains are "silted up frequently due to insufficiency in the hydraulic design"; and that only 8% of the villages in the plan area have drains with regular maintenance. It proposes that the existing drainage alignments be made permanent and the natural drainage protected "with treatment facilities at the outfall points", a network of drains and catchments on its Map 8.3, which was not extracted [TBC], and eight check dams, below Zuangtui, Sakawrtuichhun, Government Complex, Mission Vengthlang, Tlangnuam, Saikhamakawn, Melthum and Hlimen; it sets no design storm, return period or runoff coefficient and sizes no drain. The zonal and ward development plans that are to carry its hazard zoning were not yet in force: their regulations were sent to the Government on 17 May 2023 and had not been approved by September 2023 (CAG), and the draft regulations of 2015 remain a draft. The Roadmap to Stability (Landslide Policy Committee for Aizawl City, 2014) asked PHED to "Adopt and implement a five year capital outlay plan to design and construct facilities to capture and transport rain and waste water away from exposed hillslopes and ejected at locations that will not saturate potentially unstable slopes", and to "eliminate all septic tanks, leach fields and soak pits within Aizawl City"; no such plan was found [TBC]. No storm-drainage project of the ADB, Aizawl Smart City Ltd or AMRUT was found, and no plan of any kind was found for Lunglei beyond a Development Planning Area notification known by its title [TBC]. No published document sets a design return period for the storm drains of any Mizoram town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by UD&PA, the Aizawl Municipal Corporation, the Lunglei Municipal Council, PHED, IWRD, MSDMA, any Village Council or District Council, or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, slopes that open drains, soak pits and uncontrolled discharges saturate until they slide, as at Laipuitlang in 2013 and on the Melthum–Hlimen quarry face in Cyclone Remal in 2024, drains that are kutcha or absent over 85% of the Aizawl Urban Area and end in steep lui that are "turbulent with high velocities of currents during the monsoon season", drains that carry the sullage and septic effluent of towns with one sewered catchment to the Chite and Tuikual streams and on to the rivers that supply them, river floods on the few valley floors, Tlabung, Sairang and Bairabi among them, and single lui split between the Aizawl Municipal Corporation, PWD, the national-highway agencies, the Village Councils and, in the south, the District Councils, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Mizoram, the series' fifth North-East edition and its steepest: to towns built on ridges and slopes, Aizawl on ridges between the Tlawng and Tuirial valleys with no valley floor of its own, where the binding stormwater hazard is the landslide that drainage starts rather than the flood, and where drains end in steep lui; to a few valley floors and river terraces, Tlabung, Sairang, Bairabi, Vairengte, Chawngte and the Champhai flats, that flood from rivers in a State officially said to have no flood plain; to a State that lies wholly in CWC subzone 2(c), for which CWC has published no Flood Estimation Report, and in which no rain gauge has a published 24-hour record, so that NIH-DHAARA with the floors of Clause 2.3.6 is the design source everywhere; to ground that will not take water, the Surma-group shales and siltstones that CGWB calls a "run off zone", where water is drawn from springs (tuikhur) and roofs rather than wells; to drains that are the sewers of towns with one sewered catchment; to a slope regulation that fixes the geometry of swales, interceptor drains and down-drains but gives no design storm, in one city only; to three legal geographies, the municipalities, the Village Council areas and the Lai, Mara and Chakma Autonomous District Councils, which no State building, water-resources or rivers law reaches; and to a wet season whose deadliest storms come in May, before the south-west monsoon, so that in every basin a BSMP begins with the hazard, not the storm (Clause 11.3.3).