Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the AMCBR/SD&SM steps a Mizoram applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for the whole State, which lies within 21°58′–24°35′ N and 92°15′–93°29′ E (Lallawmzuali and Muniyan, 2024), inside zone 46N (90°–96° E), so that no project needs another zone (this Manual's reading)), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC level-monitoring sites on the receiving rivers (not stated in any source found), of the reservoir levels of the Tuirial dam published by NEEPCO in metres (datum not stated) and of Serlui B (not found), and of the flood marks surveyed on ungauged lui, rivers and dils used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Mizoram has no notified design return period or design storm for its urban drains, and no document of UD&PA, the Aizawl Municipal Corporation, the Lunglei Municipal Council, PWD, PHED, IWRD or Aizawl Smart City Ltd stating a return period, a runoff coefficient, an intensity–duration–frequency relation or a rule for the time of concentration was found. The documents found for the Aizawl tranche of the ADB's North Eastern Region Capital Cities Development Investment Program cover water supply and sewerage, not storm drainage (as summarised), and no storm-drain project of Aizawl Smart City Ltd was found. The building regulations defer to the National Building Code (2005, "as amended from time to time" since the 2019 amendment) and, for landslide hazards, to IS 14458 and IS 14496 (Part 2) (AMCBR Annexure F). SD&SM 2017 fixes the geometry of terrace swales, interceptor drains, down-drains and building-pad gradients (reg. 27) and asks an engineered application for "A map showing the drainage area and the estimated runoff of the area served by any drains" (reg. 6), but sets no design storm, return period or runoff coefficient; it leaves the "hydrology and hydraulic calculations" to licensed civil engineers (Schedule I). The master plan found Aizawl's drains "silted up frequently due to insufficiency in the hydraulic design", with 67% of the Aizawl Urban Area served by kutcha drains, 18% by none and only 15% by pucca drains. Road drains follow IRC:SP:42-2014 and IRC:SP:48. The rainfall studies do not supply a design storm either. No Mizoram station is in IMD's Extremes (data to 2012), so no official 24-hour record exists for any town; the only peer-reviewed frequency study (Lallawmzuali and Muniyan, MAUSAM, 2024) fits monthly and annual totals only; IMD's national study (Das et al., 2022) has no Mizoram panel; and the whole State lies in CWC subzone 2(c), for which CWC has published no Flood Estimation Report. The largest daily falls known are press values: 148 mm at Aizawl in one day, probably 12 June 2018 (this Manual's reading of the report's date), and 130 mm at Chawngte in October 2025 (both as reported). The State's design values are therefore those of Chapter 2: NIH-DHAARA in every sub-area, with the statewide floor of Clause 2.3.6(c)(i), the Barak-valley floors of Clause 2.3.6(c)(ii) in sub-areas MZ-A and MZ-A1, the 72-hour factor of Clause 2.3.6(e) and the interim ratios of Clause 2.3.6(f), and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Mizoram calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UD&PA:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by UD&PA and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the AMCBR/SD&SM registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UD&PA list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where the approval of the Irrigation and Water Resources Department (IWRD) for a work on, or a discharge to, a river or flood work in its charge, or a direction of WARDMA under the Mizoram Water Resources (Management and Regulation) Act, 2024 outside the Autonomous District Councils' areas, the consent of NEEPCO for a work that drains to the Tuirial reservoir or to the reach below its dam, and of the State's power department for Serlui B [TBC], the written permission of the Aizawl Municipal Corporation, or of the Lunglei Municipal Council in its area, to connect a drain to a municipal drain or to lead one into any water-course (Mizoram Municipalities Act, 2007, ss.295 and 296), the views of the Environment, Forest and Climate Change Department (EF&CC) for a work in a riverine reserve or a wetland, the prior approval of the Mizoram River Protection Authority for a work in a River Conservation Zone, only if the Mizoram (Protection of Rivers) Ordinance, 2023 (Ordinance No. 1 of 2023) and Bill, 2023, whose enactment was not confirmed, are in force and a zone has been notified (neither is confirmed), the consent of PWD, or of the national-highway agency, for a discharge to a side drain, catch-water drain or culvert of one of their roads, the consent of MPCB for a discharge that carries effluent, the consent of the Village Council for a work on a village drain outside the municipalities, the views of the Village or Local Water Resources Committee for a work that drains towards an identified water source such as a tuikhur, the consent of the District Council for a work in an Autonomous District Council area, if the District Council adopts the Manual, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example PHED or SIPMIU for a sewer), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Mizoram because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Mizoram extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. Mizoram has no dated State order fixing pre-monsoon desilting: the Master Plan for Aizawl: Vision 2030 says only that "drains need to be cleaned every year before the onset of monsoon", and found that only 8% of the villages in its area have open drains with regular maintenance, 40% periodic maintenance and 52% none at all. No notification divides the drains among their owners (this Manual's reading), and they are run by several hands: the Aizawl Municipal Corporation, with its Local Councils, for the public drains and the drains along public streets, which vest in it (Mizoram Municipalities Act, 2007, s.289(1)); PWD in practice for the side drains of the State roads, which were never devolved to the Corporation (CAG), although the same drains vest in the Corporation on the statute, an overlap this Manual states and does not resolve; the national-highway agencies for NH-6 and the other national highways; PHED and SIPMIU for the sewers and the Chite sewage treatment plant; the Lunglei Municipal Council in Lunglei; the Village Councils for village drains, a duty the State may assign to them ("Sanitation and drainages", Mizoram (Village Councils) Act, 2025, s.15(1)(q)); and, in the Autonomous District Council areas, the District Councils and their Village Councils [TBC]. Owners maintain the terrace swales, interceptor drains and down-drains built under a site development permit (SD&SM 2017, reg. 27). The Roadmap to Stability (Landslide Policy Committee for Aizawl City, 2014) asked PHED to "Create an office within the Public Health Engineering Department to design and build, monitor and repair or improve drainage systems", and said that the Corporation "should have controlling authority for all developmental activities (Roads, Drainage, quarries etc.) within AMC area"; whether either was done was not found [TBC]. The gates that matter most are run for other purposes: the Tuirial dam is operated by NEEPCO for power, and no rule linking its releases, or those of Serlui B, to warnings for the reaches below was found [TBC]. No operating rule for any flap gate, check dam or pumping station in a Mizoram town, linking it to a river level, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 31 March) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use open space area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Mizoram, the pre-monsoon inspection of flap gates, non-return valves, debris racks, sediment traps, debris basins, culvert inlets and any pumped facilities, including the gates on outfalls that the Tlawng, the Khawthlangtuipui at Tlabung or another valley river can close, with the desilting and the clearance of debris, garbage and slide material from every drain, lui inlet, catch-pit, rack, trap, basin and culvert, the clearance of the terrace swales, interceptor drains and down-drains of SD&SM reg. 27, the inspection and clearance of the weep holes and subsurface drains of retaining walls, and the pump duty and gate seal tests, shall be completed by 31 March; racks, culverts, flap gates and any pumped facilities, with their standby power, shall be certified ready on the same date, because the season of this Manual begins on 1 April and storms come in April. Flap gates, racks and any pumps shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to the Tuirial reservoir or to a reach below the Tuirial or Serlui B dam until the releases have ended, if that is later. Drains, terrace swales, interceptor drains, racks, culvert inlets and catch-pits shall be cleared again by 30 April, of the debris, garbage and slide material of the April storms, before the May storms that brought the State's deadliest dated rain events, and every public drain, lui inlet, rack, trap, basin and culvert in every town shall be cleared of the sediment, slide debris and garbage of the season by 15 November, with a survey of the cut slopes, terraces and retaining walls above them, so that the drains are clear for the post-monsoon cyclones of October to December.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October, and its first two months bring the State's deadliest dated rain events: the Laipuitlang–Ramhlun Venglai rockslide in Aizawl (11 May 2013 by the press and the AGU Landslide Blog, 15 May 2013 by one paper), the Melthum–Hlimen quarry collapse in Cyclone Remal (28 May 2024) and the 598 landslides of 24 May–3 June 2025 (DM&R figures, as reported). April storms shut schools in five to nine districts on 27–28 April 2026, with 70.5 mm at Serchhip and 55 mm at Hnahthial (as reported). CGWB finds "heavy rainfall during May to late September" (Lunglei booklet), and the Agriculture Department's project report for NAFCC "high rainfall during May to September" (2016). NDMA (2010) sets 31 March for pre-monsoon desilting nationally, and this Manual keeps that date, as the other North-East editions of this series do. December to February is the works window. No Mizoram order fixing a date for desilting drains or readying slope drains, racks and gates was found; the Master Plan for Aizawl: Vision 2030 says only that "drains need to be cleaned every year before the onset of monsoon". This Manual therefore takes 31 March for desilting and the clearance of debris, garbage and slide material, the clearance of the terrace swales, interceptor drains and down-drains of SD&SM reg. 27, the inspection and clearance of the weep holes and subsurface drains of retaining walls, the pre-monsoon inspection, the annual declaration and the readiness of racks, culverts, flap gates and any pumps, with no later readiness date. The research's suggestion of 15 April for slope drains and weep holes is not used, because the Manual's season begins on 1 April and the April storms of 2026 came on 27–28 April. The normal onset and withdrawal dates of the south-west monsoon at Aizawl were not obtained [TBC]; in 2026 the monsoon reached Mizoram about 6 June (as reported). Here Mizoram's own record moves one date. The other North-East editions of this series clear racks, culverts and inlets a second time by 31 May, or by 15 May, but the earliest of the State's dated deadly May events fell on 11 May (Laipuitlang, 2013), so a clearance due by 15 May could come after it, and one due by 31 May after all three. Drains, terrace swales, interceptor drains, racks, culvert inlets and catch-pits are therefore cleared again by 30 April, after the April storms and before every dated May disaster in the record. Storms continue after the season: the same 2016 report finds that "the cyclones of the Post Monsoon season (October to December) are more intense than those of Pre-Monsoon season (April & May)", and Chawngte had 130 mm in a day in October 2025, "highest in the region" (as reported). Flap gates, racks and any pumps are therefore kept on standby to 31 October (Figure 10.3), and every town clears its drains a second time, and surveys its cut slopes, terraces and retaining walls, by 15 November. The research's 30 November is not used: 15 November, the series' date, clears the drains before most of the cyclone window rather than after it. The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Mizoram towns make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Mizoram drainage show up only in the first monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Aizawl Municipal Corporation Building Regulations 2012 and the Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations 2017 are made and from the municipal Acts. The graduated steps are set by this Manual. In Mizoram the courts and the National Green Tribunal have become working regulators of slopes and streams, while the statutes carry powers that are little used on record. The Gauhati High Court (Aizawl Bench), in a suo motu public-interest case on a letter of the INTACH Mizoram Chapter, directed in July 2024 that "no new construction activity shall henceforth be allowed on either side of the Bawngkawn – Durtlang (Leitan) road", kept the Corporation's approvals beyond the first floor "in abeyance" and exempted retaining walls built to prevent landslides, quoting the master plan's "development on slope more than 36 degree should be strongly discouraged" (as reported; the case number was not found [TBC]); the same Court quashed the Riverine Reserved Forest notification of 1965 on 27 January 2021, and the State's appeal was dismissed as withdrawn on 9 November 2022 (as reported). The Tribunal supervises sewage and polluted stretches: in O.A. No. 593 of 2017 and O.A. No. 673 of 2018 MPCB reported the trial run of the Chite sewage treatment plant from 6 February 2021, a River Rejuvenation Committee, and a compensation regime adopted on 5 May 2020 under which "no compensation has been levied till date" (MPCB report, February 2021); in O.A. No. 606 of 2018 the State reports its sewage and treatment capacity every six months. The statutes give the Corporation the powers this chapter needs, but no record of their use on drainage was found, so they are untested: all drains in the municipal area, "whether private or public, shall be under the survey and control of the Board of Councillors" (Mizoram Municipalities Act, 2007, s.290); the Corporation cleanses them (s.291) and may drain a sudden water-logging across private land without notice (s.294); a private drain may enter a municipal drain only with the Chairman's written permission (s.295), and no drain may be led into a municipal drain or any water-course without written consent (s.296); the Corporation may require foul water to be drained apart from rain water (s.298); the State may take control of "imperfect, inefficient or unsuitable" drainage works (s.299); and no structure may be built over a municipal drain, culvert or storm-water channel, on pain of a fine of up to ₹500 and ₹100 a day (s.300). A regulation made under the Act may provide fines of up to ₹1 lakh, with ₹1,000 a day after conviction (s.374), but whether the AMCBR or SD&SM do so was not checked [TBC]. SD&SM 2017 makes "The owner … responsible for maintaining drainage facilities installed under their permit" (reg. 27), with no inspection regime stated, so the duty is nominal until someone inspects it. The AMCBR work through the permit: OBPAS, which since 2023 "shall return" any proposal not as per the regulations and the master plan, and, since 2025, an Occupancy Certificate issued after an inspection within 7 working days and only once excess materials are removed from public roads; of 15,162 OBPAS applications from June 2018 to 1 April 2024, 7,159 were valid and 6,214 had expired (CAG). The Mizoram Water Resources (Management and Regulation) Act, 2024 provides penalties of up to 3 months or ₹10,000 for a first offence and 6 months or ₹25,000 for a later one, with the Deputy Commissioner as penal authority (s.20), but the notifications constituting MISWARC and WARDMA were not found [TBC] and the Act does not extend to the Autonomous District Councils, so for drainage it is nominal so far. The Mizoram (Village Councils) Act, 2025 lets a Village Council declare an area "unsafe site for house construction for mitigation of landslide" with the approval of the District Disaster Management Authority, and adopt and enforce model building bye-laws "as may be framed by the State Government" (s.13(6)), but no model bye-laws were found, so building control for drainage outside the municipalities is untested; in the Lai, Mara and Chakma Autonomous District Councils none of these Acts applies, and no District Council instrument on building or drainage was found. The CAG's Report No. 1 of 2025 found that "regular inspection of landslide prone areas and research studies have not been conducted", that there was "no Action Plan for checking unplanned urbanisation", that automated landslide monitoring "envisaged in the State Plan since 2015" had not been set up, that the National Building Code for seismic zone V was "yet to be adopted in the sampled Lawngtlai and Mamit districts", and that none of the measures IIT suggested for the Durtlang BSUP complex after its collapse of 2 July 2019 was carried out; no audit of storm drainage in Mizoram was found. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) the level of the receiving river at the nearest CWC level-monitoring site, where there is one (Sairang on the Tlawng, or Turial on the Tuirial, the only site with a published high flood level, 149.0 m on 17 June 1995; no site in the State has a warning or danger level), or of the Tuirial reservoir as NEEPCO records it, each on a named datum, and, where it is gauged, at the outfall; for an ungauged lui, river or dil, such as the Chite lui and the Ser lui in Aizawl and the Khawthlangtuipui at Tlabung, the flood marks surveyed after the event and the boulders, slide debris and garbage deposited at crossings, racks and culverts; the state of every flap gate, debris rack, sediment trap, debris basin, check dam and pumping station on the outfall and on the drain upstream of it, with the volume of debris and garbage removed from each and the hours any pump ran; the slides, slope failures and blocked down-drains, interceptor drains and weep holes in the catchment of the outfall, located on the landslide hazard maps; and the gate openings and releases of the Tuirial or Serlui B dam where they set the receiving level;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), MSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Mizoram's landslides and floods have been counted more often than they have been reviewed, and the counts conflict. In Cyclone Remal on 28 May 2024 the tolls were reported rising through the day, to 29 dead in Aizawl district with 7 missing by 29 May; a later report gave 15 dead at the Melthum–Hlimen quarry and 5 at Hlimen, another 34 killed in seven Aizawl areas, and the State's toll was put at 27 to 29 (all as reported). The Laipuitlang–Ramhlun Venglai rockslide is dated 11 May 2013 by the press and 15 May 2013 by one paper, and killed 17 by that paper's count or 8 by another review. For 24 May–3 June 2025 DM&R counted 598 landslides, five dead, 171 houses damaged and 257 road blockages (as reported). The Tlabung flood of June 2017 submerged about 350 houses in the sub-division by one count, or 9 fully and more than 60 partly by the district officials' (as reported). Over 2017-18 to 2021-22 landslides affected 661 villages and killed 41 people, and floods affected 434 villages and killed 12 (CAG, Report No. 1 of 2025). Heavy rain brought landslides to Aizawl, Champhai, Lawngtlai and Hnahthial in August 2026 with no casualties, and a landslide at Vairengte in September 2026 killed one boy (both as reported). DM&R's final tolls for these events were not obtained [TBC]. No review of any landslide or flood in a Mizoram town, and no record of flood extents, depths or durations kept by the Aizawl Municipal Corporation, the Lunglei Municipal Council or MSDMA, was found, and for most of these events no gauge recorded the rain: the rainfall at Aizawl in Cyclone Remal is not known, and the 20 mm at Mizoram University in IMD's release of 28 May 2024 is for an unclear window. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. Much of Mizoram's drainage record is public: the Aizawl Municipal Corporation publishes on its website the AMCBR and their amendments, SD&SM 2017, the Mizoram Municipalities Act, 2007 and the Local Council Rules, the Master Plan for Aizawl: Vision 2030, the draft zonal regulations of 2015 and the Roadmap to Stability; the Village Councils Act, 2025, the Water Resources Act, 2024 and the Rivers Ordinance and Bill, 2023 are in the State's published texts; the CAG's Report No. 1 of 2025, the State's and MPCB's reports to the National Green Tribunal, CPCB's list of polluted river stretches (2025), CERC's order on the Tuirial project, CGWB's State profile and district booklets, and IMD's daily rainfall list for the Meteorological Centre Aizawl are online. Much else could not be found in the public domain: the approval notification of the Master Plan for Aizawl: Vision 2030 and its Map 8.3 of proposed drains, which is in the plan but was not extracted [TBC]; the final gazette of the 2019 amendment of the AMCBR and any amendment of SD&SM 2017; the Landslide Hazard Maps of the Corporation and MIRSAC's atlas as published layers; any building or drainage instrument of the Lunglei Municipal Council or of the Lai, Mara and Chakma Autonomous District Councils, and the model building bye-laws of the Village Councils Act; the notifications constituting MISWARC, WARDMA and MSDMA, and whether the Rivers law was enacted; the design basis of any storm drain, including the Smart City and AMRUT works; the daily and hourly records of any Mizoram rain gauge with its start year; CWC's site sheets and gauge datums; the maximum water level, spillway data and release rules of the Tuirial dam and any level of Serlui B; DM&R's final tolls; and an inventory of the gates, racks, check dams and drains of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Government of Mizoram, Urban Development and Poverty Alleviation Department. Aizawl Municipal Council Building Regulations, 2012 (now the Aizawl Municipal Corporation Building Regulations, 2012), Notification No. B.13017/8/2012-UD&PA of 20 December 2012 (Mizoram Gazette Extraordinary Vol. XLII, Issue No. 4, 10 January 2013): regs. 1(2), 4–5, 5(5)(v), 5(6)(iv), (viii) and (ix), 26(2), 33 and 37, Annexure F; as amended by the Amendment Regulations of 2019 (No. B.13017/8(2)/2018-UD&PA; public notification of 10 April 2019; final gazette not read [TBC]), 2023 (No. B.13017/8/2021-UD&PA/Pt of 14 August 2023, Gazette Extraordinary Vol. LII, Issue No. 459, 28 August 2023; OBPAS) and 2025 (No. B.13017/8/2021-UD&PA/Loose of 21 November 2025; Occupancy Certificate, Chapter VIIIA, Annexure B-I), with the Corporation's circular No. P.11011/1/2025-AMC(BW) of 20 January 2026. https://amcmizoram.com/uploads/files/amc-building-regulations_21042017023756.pdf
- Government of Mizoram, Urban Development and Poverty Alleviation Department. Aizawl Municipal Corporation (Site Development and Slope Modification) Regulations, 2017, No. B.13017/75/2016-UD&PA of 4 April 2017 (Gazette Extraordinary Vol. XLVI, Issue No. 161, 11 April 2017): regs. 1, 4–6, 14 and 24–29, Form 1, Schedule I. https://amcmizoram.com/uploads/files/Site%20Development_27062019101258.pdf
- The Mizoram Municipalities Act, 2007 (Act No. 6 of 2007), consolidated to the Fourth Amendment (2015): ss.1(2), 80, 288–300, 371 and 374; and the Mizoram Municipalities (Ward Committee and Local Council) Rules, 2010 (No. B.13017/21/2008-UD&PA, 2 November 2010). https://amcmizoram.com/uploads/files/THE%20MIZORAM%20MUNICIPALITIES%20ACT,%202007_11062018034305.pdf
- The Mizoram (Village Councils) Act, 2025 (Act No. 7 of 2025; Gazette Extraordinary Vol. LIV, Issue No. 178, 20 March 2025): ss.1(2), 2(29), 13(6), 14(6) and 15(1). https://prsindia.org/files/bills_acts/acts_states/mizoram/2025/Act7of2025MZ.pdf
- The Mizoram Water Resources (Management and Regulation) Act, 2024 (Act No. 1 of 2024; No. H.12018/273/2023-LJD (IWR) of 15 March 2024): ss.1, 2(1)(i), 3–12, 14, 16, 20 and 24. https://prsindia.org/files/bills_acts/acts_states/mizoram/2024/Act1of2024MZ.pdf
- The Mizoram (Protection of Rivers) Ordinance, 2023 (Ordinance No. 1 of 2023) and Bill, 2023 (Bill No. 70 of 2023 as printed), whose enactment was not confirmed: s.15. https://prsindia.org/files/bills_acts/bills_states/mizoram/2023/Billno68of2023MZ.pdf
- Aizawl Development Authority (2012). Master Plan for Aizawl: Vision 2030, prepared by the Department of Architecture and Regional Planning, IIT Kharagpur (drainage, 8.3; its approval notification was not found [TBC]). https://amcmizoram.com/uploads/files/Master%20Plan%20For%20Aizawl%20Vision%20-%202030_18032019040050.pdf
- Landslide Policy Committee for Aizawl City (2014). Roadmap to Stability: Actions to Reduce the Landslide Risk in Aizawl, with technical support from GeoHazards International. https://amcmizoram.com/uploads/files/AMC%20Roadmap%20to%20Stability_15012019035648.pdf
- Comptroller and Auditor General of India. Report No. 1 of 2025 (Social, Economic, Revenue Sectors and Local Government, Government of Mizoram, year ended 31 March 2023): performance audits on disaster preparedness and management and on the 74th Amendment. https://cag.gov.in/ag/aizawl/en/audit-report/details/122595
- Government of Mizoram. Six-monthly progress report to the National Green Tribunal in O.A. No. 606 of 2018, January–June 2025 (liquid waste, as on 31 August 2025); and the Mizoram Pollution Control Board's report in O.A. No. 593 of 2017 and O.A. No. 673 of 2018 (February 2021). https://www.greentribunal.gov.in/
- Lallawmzuali and Muniyan (2024). Probability analysis of annual and monthly rainfall in Mizoram. MAUSAM 75(3), 815–822. https://metnet.imd.gov.in/docs/mausamdocs/175317_F.pdf
- Central Electricity Regulatory Commission. Order in Petition No. 125/MP/2021 (NEEPCO, Tuirial HEP). https://www.cercind.gov.in/2023/orders/125-MP-2021.pdf
- Government of Mizoram, Agriculture Department (2016). Detailed Project Report: Sustainable agriculture development in the state of Mizoram, for the National Adaptation Fund for Climate Change (rainfall season; cyclones). https://moef.gov.in/uploads/2017/08/Mizoram.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (no Mizoram station); and Das, S.K. et al. (2022), Isopluvial analysis and intensity–duration–frequency curves for different cities in India, MAUSAM 73(4), 887–898 (no Mizoram panel).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- Gauhati High Court (Aizawl Bench). Suo motu public-interest case on the letter of the INTACH Mizoram Chapter (order reported 23 July 2024; case number not found); and the judgment of 27 January 2021 on the Riverine Reserved Forest notification of 1965, with Writ Appeal No. 8 of 2021 (dismissed as withdrawn, 9 November 2022) (as reported).
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (Chite and Tuikual streams, Priority II; Lawibual stream, Priority III; Tuipui, Priority V).
- Central Ground Water Board, North Eastern Region. Ground Water Information Booklet, Lunglei District (rainfall season).
- Indian Roads Congress (2014). IRC:SP:42-2014, Guidelines on Road Drainage, §8.5.1 (hill roads); and IRC:SP:48 (hill roads). https://law.resource.org/pub/in/bis/irc/irc.gov.in.sp.042.2014.pdf
- South Asia Network on Dams, Rivers and People (2018). Overview of CWC's flood monitoring and forecasting in North East India (transcription of CWC site data). https://sandrp.in/2018/08/05/overview-of-cwcs-flood-monitoring-forecasting-in-north-east-india/
- AGU Landslide Blog (11 May 2013); EastMojo, Down To Earth, PTI, ThePrint, India Today NE, Deccan Herald, DT Next, Tribune, Eastern Mirror, Morung Express, Business Standard, IndiaLegalLive and All India Radio (2013–2026). Reports of the Laipuitlang rockslide, the Tlabung floods of 2017, 2019 and 2023, the storms of June 2018, Cyclone Remal and its tolls, the storms of May–June 2025, the Directorate of Geology and Mineral Resources' finding on improper drainage, NH-6 at Hunthar, the High Court's order on the Bawngkawn–Durtlang road, the April 2026 storms, the August and September 2026 landslides and the monsoon's arrival in 2026 (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Mizoram the failure is one of missing criteria and of an approval system that reaches one city. No document of UD&PA, the Aizawl Municipal Corporation, the Lunglei Municipal Council, PWD, PHED or IWRD stating a design return period, intensity or runoff coefficient for the storm drains of any town was found, and the Master Plan for Aizawl: Vision 2030 found 67% of the Aizawl Urban Area with kutcha drains, 18% with none and 15% with pucca drains. The approval route shapes this chapter. Both the AMCBR and SD&SM apply only to the Corporation's area (AMCBR reg. 1(2)). A building permit is applied for through the Corporation's online building permission system, OBPAS, in use since June 2018 and made the route by the 2023 amendment, which "shall return" any proposal not as per the regulations and the master plan; the Local Council's no-objection certificate goes with the application (AMCBR regs. 4–5; SD&SM Form 1). The AMCBR already ask for much of what a drainage submittal needs: a site plan showing "sewerage and surface drains, position and sizes of septic tank and soak pit" (reg. 5(5)(v)), a roof plan "indicating drainage and roof slope" (reg. 5(6)(iv)), "site development and permanent structures like retaining wall, surface drain" (reg. 5(6)(viii)), a rainwater harvesting facility (regs. 5(6)(ix) and 33), roofs drained "at ground level by pipe" with no spout into the road or a neighbour's compound (reg. 26(2)(b)), and a surface drain or closed conduit "of adequate capacity to the nearest public drain" (reg. 37(ii)). SD&SM 2017 adds a site development permit "in addition to a building permit" (reg. 5(1)), on two tracks: regular site development, on Form 1 with a site plan, cut and fill quantities, title and the Local Council's no-objection certificate, "allowed ONLY in zones of Low landslide hazard"; and engineered site development, required in mapped Moderate, High and Very High hazard zones, on unmapped ground of 24° or more, for cuts of 3 m or more, for works above 200 m³ and for works that support a structure, with a geotechnical report, "Detailed plans of all surface and subsurface drainage devices", "A map showing the drainage area and the estimated runoff of the area served by any drains" and "A drainage plan, including elevations of floors with respect to finish site grade" (reg. 6); its Schedule I makes licensed civil engineers competent for "Design of drainage structures, including hydrology and hydraulic calculations". Since the 2025 amendment, ordinary buildings "on plots measuring less than 93 square meters and located within low and moderate geo-hazard zones" may be self-certified by empanelled technical personnel, with a declaration of compliance with "the Aizawl Landslide Hazard Map" (Annexure B-I and form C-IV), and the Occupancy Certificate follows an inspection within 7 working days. A private drain may be connected to a municipal drain only with the written permission of the Chairman (Mizoram Municipalities Act, 2007, s.295), and no drain may be led into a municipal drain or any water-course without written consent (s.296). Outside the Corporation's area no building regulation was found: none for the Lunglei Municipal Council [TBC]; the Village Councils may declare unsafe sites for house construction with the District Disaster Management Authority's approval and are to enforce model building bye-laws once the State frames them (Mizoram (Village Councils) Act, 2025, s.13(6); none found); WARDMA may direct rainwater harvesting outside the Autonomous District Councils (Mizoram Water Resources (Management and Regulation) Act, 2024, s.16(2)(ix)); the Mizoram River Protection Authority would approve works in a River Conservation Zone only if the Mizoram (Protection of Rivers) Ordinance, 2023 (Ordinance No. 1 of 2023) and Bill, 2023, whose enactment was not confirmed, are in force and a zone has been notified (neither is confirmed); and in the Lai, Mara and Chakma Autonomous District Councils no building or drainage instrument was found, beyond notices of the Chakma District Council on no-objection certificates of the Kamalanagar Town Planning Committee and on roadside construction, known from their titles (as reported). No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a design storm. Every stormwater item in this chapter is therefore written so that the licensed civil engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Corporation can check it, if it adopts the Manual, with the drawings that the AMCBR and SD&SM already require through OBPAS: the Stage 1 and Stage 2 submittals of Table 10.1 go with the building permit and, where one is needed, the engineered site development permit, whose runoff map and drainage plan are the hook for the drainage report of this chapter, and the regular-track Form 1 is the hook for the simplified drainage plan; a self-certified plot of less than 93 m² carries a simplified drainage declaration, covering roof storage, the connection to the public drain and the hill rule of Clause 4.11, signed by the empanelled technical person; Stage 4 goes with the Occupancy Certificate inspection; and drain connections go with the permission of ss.295 and 296. This chapter is the process.