Annexes to Chapter 11Basin and City Stormwater Master Plans
These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.
Annex 11A — BSMP terms of reference template
Supports Clauses 11.1 to 11.12 of Chapter 11.
Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.
11A.1 Background and purpose
- The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Mizoram Stormwater Design Manual.
- The BSMP shall (Clause 11.1.2):
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service for each part of the drainage system;
- (c) identify, cost and rank the works, storage and land needed to reach that level of service;
- (d) identify land to be reserved in the statutory land-use plan for regional storage, dil and tank restoration and major flow paths;
- (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
- (f) recommend catchments for notification as flood-sensitive.
- The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).
11A.2 Client, partners and study area
- Client: [Lead Authority] (Clause 11.4.1).
- Partners: IWRD, wherever the basin includes a river, canal or tank under its control, and [other local bodies, a planning authority or UD&PA, MSDMA] (Clause 11.4.1).
- Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
- Links to other basins: [for example the receiving river, stream (lui), dil or reservoir corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).
11A.3 Team
- The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
- The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.
11A.4 Tasks
Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.
Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):
- (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
- (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
- (c) waterbodies: every tank, dil, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
- (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
- (e) outfalls, lui, rivers, dils and reservoirs: outfall invert levels on valley-floor land, on a named datum, against the high flood level of the receiving river at the nearest CWC level-monitoring site (none in the State has a warning or danger level) or surveyed flood marks, with any local gauge kept as a separate series and any conflict between published values stated; for the free outfalls of the ridge towns, the bed and bank profile of the receiving lui to the next confluence and the 1% AEP level with its sediment, debris and garbage; for outfalls to the Tuirial reservoir or the reaches below the Tuirial and Serlui B dams, the full, minimum and maximum reservoir levels and the spillway and release data from NEEPCO and the State's power department, and dils at their surveyed spill levels; the landslide hazard zones, slopes above 60°, quarries, sinking areas and debris paths above the basin; and flap gates, debris racks, sediment traps, debris basins, check dams and pumping stations on the outfalls, with their capacities and operating rules;
- (f) rainfall and water levels: all available records (IMD, including the ordinary gauges of its Meteorological Centre Aizawl and at Lengpui, neither of which is in IMD's Extremes, and its automatic weather stations at Mizoram University, Kolasib, Champhai, Khawzawl, Serchhip, Hnahthial, Saiha and Chawnhu (record lengths [TBC]); the automatic rain gauges and weather stations listed under Mz-SWIC, about 30 sites (the operator's name is not expanded in the source; start years and logging intervals [TBC]); the State Meteorological Centre of the Directorate of Science and Technology, whose series runs from the 1980s to 2021 (gauge list not seen [TBC]); the ordinary gauges of the Agriculture Department at Serchhip, North Vanlaiphai, Lunglei, Haulawng and Tlabung; the rain gauges of CWC, among them Bairabi, Dapchhuah, Mat-1, Tlabung, Tuichawng, Tuipui D and Shitlangpui, and its level-monitoring sites at Sairang and Turial; the reservoir records of NEEPCO at the Tuirial dam [TBC]; and any gauges or sensors kept by the Aizawl Municipal Corporation, MSDMA or IWRD [TBC]), including the 28 May 2024 (Cyclone Remal: the collapse at about 6 a.m. of a disused stone quarry between Melthum and Hlimen and other slides in Aizawl, with tolls reported rising to 29 dead in Aizawl district, with 7 missing, by 29 May, and given later as 15 at the quarry and 5 at Hlimen, or 34 in seven Aizawl areas, and 27–29 for the State, all as reported; the rainfall at Aizawl on 27–28 May 2024 was not found, and the 20 mm at Mizoram University in IMD's release of 28 May is for an unclear window), 24 May–3 June 2025 (598 landslides, five dead, 171 houses damaged and 257 road blockages, with Champhai 209, Serchhip 116, Khawzawl 75, Lunglei 61 and Aizawl 21, DM&R figures as reported; Serchhip 104.6 mm, Kolasib 98.3 mm and Aizawl 97.4 mm on one day whose date is not fixed, as reported; no IMD series for the storm was found), June 2018 (148 mm at Aizawl in one day, probably 12 June, and 677 mm in Serchhip district in 1–13 June, ten dead in landslides on 5 June, houses flooded at Tiperabagh, Serhuan and Tlabung and families stranded at Sairang, all as reported), July 2019 (about 400 houses flooded by the Khawthlangtuipui at Tlabung, 150 of them in the town, and three killed in the State, as reported; no rainfall value was found) and June 2017 (the Khawthlangtuipui flood at Tlabung, with about 350 houses submerged in the sub-division by one count, or 9 fully and more than 60 partly by another, and 8–10 dead, as reported; no rainfall value was found) events;
- (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
- (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
- (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
- (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.
Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.
Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).
Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the 28 May 2024 (Cyclone Remal: the collapse at about 6 a.m. of a disused stone quarry between Melthum and Hlimen and other slides in Aizawl, with tolls reported rising to 29 dead in Aizawl district, with 7 missing, by 29 May, and given later as 15 at the quarry and 5 at Hlimen, or 34 in seven Aizawl areas, and 27–29 for the State, all as reported; the rainfall at Aizawl on 27–28 May 2024 was not found, and the 20 mm at Mizoram University in IMD's release of 28 May is for an unclear window), 24 May–3 June 2025 (598 landslides, five dead, 171 houses damaged and 257 road blockages, with Champhai 209, Serchhip 116, Khawzawl 75, Lunglei 61 and Aizawl 21, DM&R figures as reported; Serchhip 104.6 mm, Kolasib 98.3 mm and Aizawl 97.4 mm on one day whose date is not fixed, as reported; no IMD series for the storm was found), June 2018 (148 mm at Aizawl in one day, probably 12 June, and 677 mm in Serchhip district in 1–13 June, ten dead in landslides on 5 June, houses flooded at Tiperabagh, Serhuan and Tlabung and families stranded at Sairang, all as reported), July 2019 (about 400 houses flooded by the Khawthlangtuipui at Tlabung, 150 of them in the town, and three killed in the State, as reported; no rainfall value was found) and June 2017 (the Khawthlangtuipui flood at Tlabung, with about 350 houses submerged in the sub-division by one count, or 9 fully and more than 60 partly by another, and 8–10 dead, as reported; no rainfall value was found) events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.
Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).
Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.
Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on the springs (tuikhur) and spring-fed water points that supply the villages and part of the towns, and their catchments above the water points, which this Manual keeps free of paving and of infiltrated road runoff (the spring rule of Chapter 8), the stability of hill slopes, where water put into shale, colluvium, fill or slide debris raises the pore pressure, as SD&SM 2017 warns and the slides of Hlimen and Laipuitlang show, recharge on tested valley alluvium and river terraces, the only ground where it is allowed (Clause 4.11, recharge rule), although groundwater is barely drawn (stage of extraction 3.52% in 2011, CGWB, and 3.95% in 2024, as quoted), and the quality of the springs, lui, rivers, dils and reservoirs that the runoff reaches, several of which carry sewage (Chapter 8, Clause 8.9); effect on downstream basins and the receiving river, stream (lui), dil or reservoir; and who benefits.
Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).
Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).
Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).
Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.
Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.
Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).
11A.5 Deliverables
Table 11A.1 — Deliverables
| No. | Deliverable | Task | Due (months from start) |
|---|---|---|---|
| D1 | Inception report, data inventory and survey plan | 1 | [ ] |
| D2 | Data report and data sets (Annex 11D) | 2 | [ ] |
| D3 | Model build report and model files | 3 | [ ] |
| D4 | Calibration and validation report | 4 | [ ] |
| D5 | Scenario results, hazard maps and level-of-service assessment | 5, 6 | [ ] |
| D6 | Options report, with basin inputs for site design | 7, 8 | [ ] |
| D7 | Draft BSMP with draft CIP, for consultation | 9–12 | [ ] |
| D8 | Final BSMP, consultation log, approval package and open-data release | 13 | [ ] |
11A.6 Ownership and publication
All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.
Annex 11B — Basin lists and boundaries for Tier A bodies
Supports Clauses 11.3 and 11.4 of Chapter 11.
To be prepared. This annex will contain the list of basins for every Tier A body, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs the list of Tier A bodies (Annex 1A), a DEM of the accuracy of Clause 11.5.1, flown again over the valley floors and the slide-prone slopes after any large flood or landslide, the drain network of every drain-owning body (the Aizawl Municipal Corporation and its Local Councils, the Lunglei Municipal Council, PWD, the national-highway agencies, PHED and SIPMIU, and the Village Councils for the village drains), a drain register giving every reach its owner, the lui it reaches, its class on the landslide hazard maps and its outfall, the drains and catchments proposed on Map 8.3 of the Master Plan for Aizawl: Vision 2030 (not yet extracted [TBC]), the rivers and flood works of IWRD, the Tuirial and Serlui B reservoirs with their levels, spillways, gates and release rules on a stated datum, the dils with their spill levels, the springs (tuikhur) and their catchments above the water points, the quarries, active and disused, and the sinking areas, and the landslide hazard zones of the Corporation's Landslide Hazard Maps and MIRSAC's atlas (other likely sources: Survey of India, CWC, CGWB, NIH, MIRSAC, UD&PA's master-plan maps and the land records of the Land Revenue and Settlement Department). No basin map of any Mizoram town was found. Until the annex is published, the basins of Aizawl (the Chite lui to the Tuirial; the Ser lui to the Tlawng), with the hazard areas of Hlimen–Melthum, Hunthar Veng and Durtlang, and those of Sairang, Bairabi and Vairengte, Tlabung, Lunglei, Serchhip, Champhai and the Champhai flats, Siaha and Lawngtlai and the Tuirial release reach named in Clause 11.3.3 are at least those named there; other towns and bodies define their basins in their first BSMP (Clause 11.3.3); in every basin the hazard screening of Clause 11.3.3 comes first; and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP. For Annex 11C, the damage assessments of landslides and floods in Mizoram fall to the Disaster Management and Rehabilitation Department (DM&R), which "is responsible for prevention, preparedness, mitigation, response, relief and rehabilitation" (CAG) and whose counts the press reports, as for 24 May–3 June 2025, beside the land records of the Land Revenue and Settlement Department (this Manual's reading); DM&R's final counts for the calibration events were not obtained [TBC].
Table 11B.1 — Basins named in Clause 11.3.3 (provisional)
| Tier A body or area | Basin | Note from Chapter 11 |
|---|---|---|
| Aizawl Development Plan Area (the Aizawl Municipal Corporation, UD&PA) | Catchment of the Chite lui to the Tuirial, with its tributaries and the Muthi and Tuipawl lui | Free outfalls to steep lui (Clause 5.8.5(a) and (b)); Chite sewage treatment plant and Priority II stretch in the 1D network; surveyed flood marks and 1% AEP level with debris and garbage as boundary |
| Aizawl Development Plan Area (as above) | Catchment of the Ser lui to the Tlawng, with its streamlets and the Khatla, Tuikual, Vaivakawn and Chanmari west lui | As above |
| Aizawl Development Plan Area (as above) | Hazard areas within these basins: the Hlimen–Melthum quarry belt, Hunthar Veng and the NH-6 cuts, Durtlang and the Bawngkawn–Durtlang road | Hazard screening first; debris paths mapped; basin assignment [TBC] |
| Sairang | Catchments draining to the Tlawng | CWC Sairang site (no high flood level) and surveyed flood marks as boundary; outfall-closed case a design case (Clause 5.8.5(c)) |
| Bairabi and Vairengte (sub-area MZ-A1) | Catchments of the two towns | Surveyed flood marks for at least the 72-hour storm; the adjoining Barak-valley rule downstream |
| Tlabung (sub-area MZ-D1) | Catchments draining to the Khawthlangtuipui | River at surveyed flood level for not less than 72 hours (Clause 5.8.5(d)); June 2017 and July 2019 as calibration evidence |
| Lunglei (Lunglei Municipal Council, a Tier B body) | Catchments of the town and their receiving lui | Names and outfalls [TBC] |
| Serchhip | Catchments of the town draining towards the Mat | Hazard screening first; receiving lui [TBC] |
| Champhai town and the Champhai flats (sub-area MZ-C1) | Catchments draining towards the Tiau | Surveyed flood marks as boundary; no downstream gauge in Myanmar |
| Siaha and Lawngtlai | Catchments of the two towns | Through the District Councils only, if they adopt the Manual |
| Tuirial release reach | Catchments draining to the Tuirial below the NEEPCO dam | Largest recorded release, or the spillway capacity until NEEPCO gives one, as boundary (Clause 5.8.5(e)) |
| Other towns and bodies | To be defined in the first BSMP | Clause 11.3.3 |
Table 11B.2 — Attributes of the basin boundary layer (layout)
| Field | Type | Content |
|---|---|---|
| BASIN_ID | Text | Basin identifier |
| NAME_EN, NAME_LUS | Text | Basin name in English and Mizo |
| TIER_A | Text | Tier A body or bodies in the basin |
| OUTFALL | Text | Outfall to the sea, river or major waterbody (Clause 11.2) |
| AREA_KM2 | Real | Basin area, km² |
| LEAD_AUTH | Text | Lead Authority (Clause 11.4.1) |
| PARTNERS | Text | Partners, including IWRD where it applies |
| LINKS | Text | Diversions to and from other basins (Clause 11.3.2) |
| BSMP_STAT | Text | None / in preparation / draft published / approved |
| BSMP_DATE | Date | Date of approval of the current BSMP |
| REVIEW_DUE | Date | Date of the next review (Clause 11.11.2) |
Annex 11C — Depth–damage curves for Mizoram building types
Supports Clause 11.8.2 of Chapter 11.
To be prepared. This annex will contain depth–damage curves for the main building types of Mizoram towns, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the 28 May 2024 (Cyclone Remal: the collapse at about 6 a.m. of a disused stone quarry between Melthum and Hlimen and other slides in Aizawl, with tolls reported rising to 29 dead in Aizawl district, with 7 missing, by 29 May, and given later as 15 at the quarry and 5 at Hlimen, or 34 in seven Aizawl areas, and 27–29 for the State, all as reported; the rainfall at Aizawl on 27–28 May 2024 was not found, and the 20 mm at Mizoram University in IMD's release of 28 May is for an unclear window), 24 May–3 June 2025 (598 landslides, five dead, 171 houses damaged and 257 road blockages, with Champhai 209, Serchhip 116, Khawzawl 75, Lunglei 61 and Aizawl 21, DM&R figures as reported; Serchhip 104.6 mm, Kolasib 98.3 mm and Aizawl 97.4 mm on one day whose date is not fixed, as reported; no IMD series for the storm was found), June 2018 (148 mm at Aizawl in one day, probably 12 June, and 677 mm in Serchhip district in 1–13 June, ten dead in landslides on 5 June, houses flooded at Tiperabagh, Serhuan and Tlabung and families stranded at Sairang, all as reported), July 2019 (about 400 houses flooded by the Khawthlangtuipui at Tlabung, 150 of them in the town, and three killed in the State, as reported; no rainfall value was found) and June 2017 (the Khawthlangtuipui flood at Tlabung, with about 350 houses submerged in the sub-division by one count, or 9 fully and more than 60 partly by another, and 8–10 dead, as reported; no rainfall value was found) floods (Land Revenue and Settlement Department and MSDMA damage assessments, insurers), and replacement costs (Public Works Department schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.
Table 11C.1 — Depth–damage curve (layout, one table per building type)
| Depth of water above floor level (m) | 0 | 0.25 | 0.5 | 1.0 | 1.5 | 2.0 | 3.0 |
|---|---|---|---|---|---|---|---|
| Structure damage (% of replacement cost) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Contents damage (% of contents value) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Building type, source and year of costs | ______ |
11C.1 Use in option assessment
Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:
EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))
The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.
Annex 11D — BSMP data and model publication standard
Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.
11D.1 What is published, and when
Table 11D.1 — Items to be published
| Item | Format | At draft (Clause 11.10.1) | At approval (Clause 11.10.2) |
|---|---|---|---|
| BSMP report, with the level-of-service assessment and options | Searchable PDF | Yes | Yes, final |
| Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) | GeoTIFF rasters; extents also as GeoPackage polygons | Yes | Yes |
| Capital Improvement Programme | CSV and PDF | Draft | Yes |
| Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate | GeoPackage and CSV | Yes | Yes |
| Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, river, reservoir and dil levels, receiving-lui profiles, landslide, debris and garbage hazards and outfall structures, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) | GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) | Summary | Yes, except security-sensitive asset details |
| Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log | Native format, zipped | No | Yes |
| Calibration and validation report | Searchable PDF | Yes | Yes |
| Consultation log of comments and responses | PDF or CSV | — | Yes |
11D.2 Formats and references
- (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
- (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 river datums of the CWC level-monitoring sites on the receiving rivers (not stated in any source found), of the reservoir levels of the Tuirial dam published by NEEPCO in metres (datum not stated) and of Serlui B (not found), and of the flood marks surveyed on ungauged lui, rivers and dils shall be stated in every data set that carries levels.
- (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
- (d) Hazard map files shall be named
<basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for examplechite-lui_d_1_depth.tif. - (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.
11D.3 Metadata
Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.
11D.4 Withholding and personal data
- (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
- (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.
11D.5 Licence, viewer and versions
- (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
- (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
- (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
- (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).
Form 11-1 — Annual implementation report
Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.
Draft form — Mizoram Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each monsoon season, by 31 March (Clause 11.11.3).
Table 11F.1 — Form 11-1, Section A: Basin and plan
| No. | Field | Entry |
|---|---|---|
| A1 | Basin; Lead Authority; partners | ______ |
| A2 | BSMP version and date of approval | ______ |
| A3 | Reporting year (1 April to 31 March) | ______ |
| A4 | Date of publication (by 31 March) and web address | ______ |
Table 11F.2 — Form 11-1, Section B: CIP progress
| CIP rank | Work | Agency | Cost in CIP (₹) | Spent this year (₹) | Spent to date (₹) | Status | Expected completion |
|---|---|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)
| Regional facility or tank | Volume credited to sites (m³) | Volume delivered (m³) | Fees received (₹) | Fees spent (₹) | Fees held, with year received |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
| Basin total: volume owed and delivered | ______ | ______ | ______ | ______ | ______ |
Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))
| No. | Item | Planned | Done | Date completed |
|---|---|---|---|---|
| D1 | Desilting of drains and canals (length, km; volume, m³) | ______ | ______ | ______ |
| D2 | Tank and dil desilting and restoration (tanks, number; storage restored, m³) | ______ | ______ | ______ |
| D3 | Gate tests (number of gates) | ______ | ______ | ______ |
| D4 | Pump station duty tests (number of stations) | ______ | ______ | ______ |
| D5 | Tank operating rules reviewed with the custodian (number) | ______ | ______ | ______ |
| D6 | Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) | ______ | ______ | ______ |
Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service
| Event (dates) | Rainfall compared with the design depths (Clause 10.16.2(a)) | Level-of-service element (Table 11.2) | Location | Met (yes / no) | Event report reference (Clause 10.16.2) |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off
| No. | Field | Entry |
|---|---|---|
| F1 | Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) | ______ |
| F2 | Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) | ______ |
| F3 | Next 10-year review due (date) | ______ |
| F4 | Officer of the Lead Authority: name, designation, signature, date | ______ |