Annexes to Chapter 5Downstream and Tailwater Analysis
These annexes support Chapter 5. Annex 5C is a worked example of the outfall-closed check of Clause 5.10, for the illustrative facility of Annex 4C. Annexes 5A and 5B need tidal, surge, survey and river data that this draft does not yet contain; each lists what the chapter already sets, gives the intended layout and states the interim rule of Chapter 5 that applies until it is published. Forms 5-1 and 5-2 are the submittal forms required by Clause 5.14. They are draft forms and have no statutory status.
Annex 5A — Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment
Supports Clauses 5.7, 5.9, 5.10, 5.11 and 5.12 of Chapter 5.
5A.1 Table 5A.1 shows how the values of this annex enter the design tailwater levels of Table 5.1. The sea-level allowance is set by Clause 5.7.4 and does not depend on this annex.
Table 5A.1 — Use of the Annex 5A values in the design tailwater (Table 5.1)
| Design case | Tailwater | Annex 5A values used | Chapter value |
|---|---|---|---|
| Minor-system design | MHWS + SLA | MHWS | SLA ≥ +0.3 m (Clause 5.7.4) |
| Major-system and storage design | HAT + surge + SLA | HAT; 10% AEP surge (Clause 5.7.3(a)) | SLA ≥ +0.3 m |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA | 1% AEP still-water level (Clause 5.7.3(b)) | SLA ≥ +0.3 m |
| Datum conversion | Chart datum to project datum | Offset from chart datum to the Survey of India datum (Clause 5.7.2(b)) | — |
Not prepared for Nagaland. Nagaland has no coast, so no outfall in the State has a tidal tailwater, and this annex has no Nagaland content (Clause 5.1.4). Its tables are kept, empty, so that the annex and table numbers match the other editions of this Manual. Rows F1 to F7 of Form 5-1 are entered as "not applicable", and the tailwater is derived under rows F8 to F10; for an outfall to a Dimapur nullah or the plain's rivers, row F10 records the gauge and the danger-mark stage used, the model and the flood marks of Clause 5.8.5(a), each with its datum; for a hill stream, the study, the flood marks and the bed survey of Clause 5.8.5(b); and for the Doyang reservoir or its release reach, NEEPCO's levels and release records, or the interim values of Clause 5.8.5(c), with their source and datum.
Table 5A.2 — Tidal datums, surge and still-water levels by coastal segment (layout)
| Coastal segment | Reference port and tide-table edition | MSL (m CD) | MHWS (m CD) | HAT (m CD) | CD to Survey of India datum (m) | 10% AEP surge (m) | 1% AEP still-water level (m CD) | Wave set-up (m), open-sea outfalls | Sources |
|---|---|---|---|---|---|---|---|---|---|
Annex 5B — Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map
Supports Clauses 5.2, 5.3, 5.8 and 5.13 of Chapter 5.
5B.1 Table 5B.1 lists the water bodies that Chapter 5 already names. It is not complete: the annex will add the extents of each reach, the other rivers, canals and mouths of the State, and a map.
Table 5B.1 — Water bodies named in Chapter 5
| Water body | Region | Listed as | Clause |
|---|---|---|---|
| Hospital Nullah, Dhobi Nullah and Lengrijan Nullah, Dimapur | Dimapur–Chümoukedima plain (Dimapur) | Major drains and outfall reaches to the Dhansiri; carry waste water as well as storm water (Clause 8.9); no gauge or published level [TBC]; both failure cases (river low with drains blocked; river high with outfalls backed up); design tailwater the higher of the 1% AEP model level and the danger-mark stage of the nearest State gauge (not yet surveyed [TBC]), checked at the highest surveyed flood mark; lock not less than 72 hours; pump-down within 48 hours; no gate or operator found [TBC]; reaches heavily encroached (as reported) | 5.2, 5.8.1, 5.8.5 |
| Dhansiri at Dimapur, and the old Dhansiri channel | Dimapur–Chümoukedima plain | Riverine outfall reach; no CWC site in Nagaland; "crossed the danger mark" in September 2025 (as reported), level and datum [TBC]; WRD's Dhansiri flood-forecasting model in progress (as reported); structures on the old channel not counted as channel | 5.8.1, 5.8.5 |
| Chathe through Chümoukedima and Dimapur | Dimapur–Chümoukedima plain and the Tsiedukhru foothills | Riverine outfall reach; rises near Medziphema and Chümoukedima and joins the Dhansiri in Assam (NPCB); above the danger mark in September 2025 (as reported), level and datum [TBC]; undercuts NH-29 at Pagla Pahar (as reported) | 5.8.1, 5.8.5 |
| Diphu at Dimapur | Dimapur–Chümoukedima plain | Riverine outfall reach; flows south to north and meanders into the Dhansiri in the Dimapur valley (CGWB); no gauge level found [TBC] | 5.8.1, 5.8.5 |
| Dzuna, Dzucha, Dzu and Sano Ru (Sanuo Ru), Kohima | Central ranges (Kohima) | Major drains and hill streams; ungauged, no published flood level [TBC]; 1% AEP study with bulking and blockage and surveyed flood marks; outfall at least 0.5 m above the highest surveyed bed level; lock the storm and the recession, not less than 24 hours; polluted stretches below the town (NPCB; the Sanuo Ru in Priority V, CPCB 2025); four interception and diversion projects on Kohima's major drains (Clause 8.9) | 5.2, 5.8.1, 5.8.5 |
| Streams of the other hill towns: Mokokchung, Wokha, Zunheboto, Tuensang, Mon, Phek, Kiphire, Peren, Longleng | Central, northern, eastern and south-western ranges | Hill streams; ungauged; as for the Kohima streams; the streams that leave the ranges at the foot of the Tsiedukhru range need the silt trap of Clause 6.3.6(m) | 5.2, 5.8.1, 5.8.5 |
| Doyang reservoir and the Doyang below the dam, past Runchan and Liphi | Wokha district | Reservoir outfalls and release reach; NEEPCO operator; storages at 333.0 m and 324.0 m RWL as quoted, in conflict with SANDRP's figures, datum [TBC]; interim reservoir tailwater 333.5 m [TBC]; release of 5,977 m³/s (spillway capacity, as reported) until NEEPCO gives a recorded release [TBC]; lock not less than 72 hours and for the release's duration (2018: about 215 hours, as reported); release scenarios, not notices; hazard-first channel shift at Runchan | 5.8.1, 5.8.3, 5.8.5 |
| Dhansiri (S) at Golaghat and Numaligarh; Doyang at Gelabil; Dikhow at Sivasagar and Bihubar; Disang at Nanglamoraghat and Desangpani | Assam, downstream of the State | CWC sites, all in Assam (SANDRP's transcription, as reported; datum [TBC]); the Assam edition governs those reaches; a lower bound on a model's downstream boundary only; Numaligarh 80.16 m (3 August 2018) or 80.18 m (2 August 2018), the higher used where a boundary needs one | 5.8.1, 5.8.5 |
| Jhanji and the other rivers that leave the State into Assam | Northern ranges | Riverine outfall reaches; no CWC site in Nagaland; modelled or surveyed flood level required [TBC]; the Assam edition governs the reaches downstream | 5.8.1, 5.8.5 |
| Tizu and Zungki | Eastern ranges (Phek, Kiphire, Meluri, eastern Tuensang) | Hill streams and rivers; no gauge and no CWC site; drain to the Chindwin in Myanmar; modelled and surveyed flood levels; no downstream boundary across the border [TBC] | 5.8.1, 5.8.5 |
| Barak headwaters (Peren, Jalukie, Tening; the south face of Kohima at Jakhama and Viswema) | South-western hills | Hill streams; ungauged; the nearest CWC site, Chotebekra on the Barak (32.1 m, 31 July 1989, as reported), lies far downstream and is not a level for any Nagaland outfall | 5.8.1, 5.8.5 |
| Dzuma | Dimapur district | Dhansiri tributary under integrated catchment treatment "for flood and bank erosion" by the Soil and Water Conservation Department (NGT affidavit, 2023); hill stream or riverine reach by location; no level found [TBC] | 5.8.5 |
| Natural pond in Dr. Haralu Colony, Dimapur, and other ponds | Dimapur and statewide | Ponds as receiving storage; full to the outlet at the start of every storm; stage–storage [TBC]; owner's consent and, on village land, the Village Council's; dry-weather-flow interception before it (Clause 8.9); proposed by NSDMA for retention; not a detention pond | 5.8.5 |
| Shilloi lake and Dzüdu lake | Location to be confirmed [TBC] | Named, with the Doyang reservoir, as priority wetlands (as reported); no town outfall to either was found; levels [TBC]; item (f) and Chapter 7 apply to any outfall | 5.8.5 |
| Drains of the Municipal and Town Councils, UDD, KSCDL, PWD, PWD (NH) and NHIDCL 1.0 m wide or more; village drains and streams on village land | Nagaland | Major drains; owner's written consent (the Municipality's for drains vested in it under s.119 of the 2023 Act; the Village Council's on village land), design water level and flap gate; the landowner's written permission for a drain across another's land (NBBL 2012, bye-law 20(ii)) | 5.2, 5.8.5 |
| River mouths subject to sand-bar closure | None in Nagaland | Not applicable (Clause 5.1.4) | 5.13.1 |
To be prepared. This annex will list and map (a) the major drains of each basin plan, (b) the riverine outfall reaches where backwater shall be modelled, with their upstream and downstream limits and the source of their design flood levels, and (c) the river mouths and creek inlets subject to seasonal sand-bar closure, with the most recent pre-monsoon bar crest levels and any WRD mouth-maintenance programme. It needs WRD river and canal records, design and recorded flood levels, reservoir operating rules, mouth-condition, dredging and bar-cutting records and pre-monsoon bar surveys (WRD), the drain inventories of KMC and other local bodies, basin stormwater master plans (Chapter 11), and base mapping from the Survey of India and NRSC. Until it is published: every river, WRD canal, the Hospital, Dhobi and Lengrijan Nullahs of Dimapur, the old Dhansiri channel and the Chathe and the Diphu at Dimapur and Chümoukedima, the Dzuna, the Dzucha, the Dzu and the Sano Ru through Kohima, the Doyang below the Doyang dam, any drain built or held by a Municipal Council or Town Council, KSCDL, UDD, PWD, PWD (NH) or NHIDCL with an internal width of 1.0 m or more, and every stream, ravine or other natural channel that drains 8 ha or more, whether or not it is lined, piped or covered and every tidal creek is a major drain (Clause 5.2); the water bodies of Table 5B.1 are riverine outfall reaches (Clause 5.8.1); and the mouths of the coastal States' rivers (there is none in Nagaland) are assumed closed at the start of the monsoon unless the Water Resources Department certifies otherwise (Clause 5.13.2).
Table 5B.2 — Attributes of the Annex 5B layers (layout)
| Field | Content | Unit or format |
|---|---|---|
| feature_id | Unique identifier | text |
| name | Name of the drain, river, canal, creek or mouth | text |
| category | Major drain; riverine outfall reach; mouth subject to sand-bar closure | text |
| clause | Clause of Chapter 5 under which it is listed | text |
| reach_limits | Upstream and downstream limits of the reach | text |
| design_flood_level_source | WRD design or highest recorded flood level, or hydraulic model (Clause 5.8.2) | text |
| reservoir_release | Upstream reservoir or tank and its operating rule, where any (Clause 5.8.3) | text |
| bar_crest_level | Most recent pre-monsoon bar crest level, for mouths | m (Survey of India datum) |
| mouth_programme | WRD mouth-maintenance programme and certification (Clause 5.13.2) | text |
| source | Source agency and date | text |
| geometry | Line (drains and reaches) or point (mouths) | line / point |
Annex 5C — Worked example: outfall-closed check for a hillside colony in Kohima draining to the Dzuna
Supports Clauses 5.9, 5.10, 5.11 and 5.12 of Chapter 5 and Clause 4.6.6 of Chapter 4.
Illustrative — not design values. This example applies the outfall-closed check of Clause 5.10 to the revised detention facility of Annex 4C. The site, its levels and its receiving drain are invented to show the method. No tidal level is used: the tide enters only through the illustrative statements in Table 5C.1 about whether the receiving drain is above or below the site outlet.
Inputs
5C.1 The site is the 2.0 ha flood-sensitive site of Annex 4C. It discharges through its own outlet chamber and a flap gate to a public storm drain that runs down a ravine to the Dzuna in Kohima, "a small river and a natural drain flowing in a west to east direction before meeting River Dzu" (NPCB), whose level rises when the stream runs full in a monsoon storm and whose bed and crossings collect gravel, slide debris and garbage, so Clause 5.10.1 applies to the facility. To show the method, this example uses the two 6-hour lock windows of Clause 5.10.3, as the coastal editions of this Manual do. In Nagaland an outfall to a hill stream such as the Dzuna whose invert is below its design level is closed for the design storm and the stream's recession, and for not less than 24 hours, and for the whole storm where no hydrograph of the stream has been computed; an outfall backed up by the Dhansiri, the Chathe or the Diphu on the Dimapur–Chümoukedima plain, and an outfall to the Doyang below its dam, has a single lock of at least 72 hours, and on the Doyang for as long as the release lasts; and an outfall below the design level of the Doyang reservoir or of a pond is closed for the whole storm, under Clause 5.8.5. In each of those cases that lasts longer than the windows used here, the facility must store or pump the volume of the longer closure, up to the whole storm volume (Clause 5.9.4); that needs more storage, or pumping, than this example shows. The routing, the volume balance of Clause 5.10.4 and the assessment are the same. The public drain's own outfall to the Dzuna would also need the debris rack, the bulking factor and the solid-waste trap of Clause 6.3.6 and an invert above the range of bed movement of Clause 5.8.5(b); the public drain, like most in the town, may carry sullage under bye-law 20(ii)–(iii) of the Nagaland Building Bye-Laws 2012, so the site's connection has the non-return valve of Clause 6.3.6(c); and on a slope in Kohima the facility itself would be a lined tank, not an infiltrating basin (Clause 4.11 (hill rule)).
Table 5C.1 — Inputs (Illustrative — not design values)
| Item | Value | Basis |
|---|---|---|
| Facility | Revised facility of Annex 4C: 2,500 m² plan area, vertical walls; 170 mm orifice at the floor; 460 mm orifice, invert 0.53 m | Annex 4C, Table 4C.14 |
| Storm | 1% AEP, 48 h, peak day last, AMC III; 72 h also run | Clause 5.10.2 |
| Inflow | Post-development 1% AEP hydrographs of Annex 4C (48 h: 8,420 m³; 72 h: 9,468 m³) | Annex 4C |
| Receiving drain levels at the connection, J1, J2 and J3 | Below the site outlet invert (from the drain owner's model) | Illustrative input |
| Receiving drain during each lock window | Backs up above the site outlet invert, so the site cannot discharge | Illustrative input; Clause 5.10.3(b) |
| Flap gate on the site outlet | Set 0.15 m below the orifice inverts in the outlet chamber, so that outside the lock windows its opening head and head loss do not affect the orifice control | Illustrative input; to be confirmed from the certified curve (Clause 5.11.2) |
| Lock windows | Two of 6 h each, starts 12.4 h apart (semi-diurnal tide) | Clause 5.10.3(a) |
| Pumps | None | — |
5C.2 Cases of Table 5.2. Because the receiving drain stays below the site outlet in J1, J2 and J3 (Table 5C.1), those cases give the free-outfall results of Annex 4C: in J2 the 1% AEP maximum water level is 1.17 m (2,913 m³), and in J3 (10% AEP, 48 h) it is 0.77 m. R1 and R2 do not apply, because the site does not drain to a river. J4, the outfall-closed check, is worked below.
Lock windows (Clause 5.10.3)
5C.3 The peak 1-hour block of the final 24 hours of the 48-hour storm is 35:35–36:35 h, with 98.2 mm (the 1-hour depth of Table 4C.2). Two runs are made:
- Run A: the first window is centred on that block: 33:05–39:05 h; the second starts 12.4 h later: 45:29–51:29 h.
- Run B: the first window starts at that block: 35:35–41:35 h; the second: 47:59–53:59 h.
For the 72-hour storm, every time is 24 h later.
5C.4 Gravity discharge is zero inside each window. Outside the windows the outlet discharges through the orifices of Table 4C.10. The routing is the same level-pool routing as in Annex 4C.
Results
Table 5C.2 — Outfall-closed check results (Illustrative — not design values)
| Storm | Run | Lock windows (h:min) | Maximum stage (m) | Maximum storage (m³) | Time of maximum (h:min) | Largest release after a window (L/s) |
|---|---|---|---|---|---|---|
| 1% AEP, 48 h | A | 33:05–39:05; 45:29–51:29 | 2.01 | 5,019 | 39:05 | 566 |
| 1% AEP, 48 h | B | 35:35–41:35; 47:59–53:59 | 2.10 | 5,238 | 41:35 | 584 |
| 1% AEP, 72 h | A | 57:05–63:05; 69:29–75:29 | 2.00 | 5,012 | 63:05 | 565 |
| 1% AEP, 72 h | B | 59:35–65:35; 71:59–77:59 | 2.09 | 5,233 | 65:35 | 584 |
Run B of the 48-hour storm governs. The first window closes the outlet just as the storm peak arrives, so the whole peak is stored. The second window arrives when the facility has drained to about 0.7 m, below the Stage 2 orifice, and adds little.
5C.5 Volume balance (Clause 5.10.4). Table 5C.3 gives the balance for Run B. The outflow in each period is found by continuity: outflow = storage at start + inflow − storage at end.
Table 5C.3 — Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Period (h:min) | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| 0:00–35:35, before window 1 | 3,817 | 2,213 | 0 | 0 | 1,604 |
| 35:35–41:35, window 1 | 3,634 | 0 | 0 | 1,604 | 5,238 |
| 41:35–47:59, between windows | 941 | 4,423 | 0 | 5,238 | 1,756 |
| 47:59–53:59, window 2 | 28 | 0 | 0 | 1,756 | 1,784 |
| After 53:59 | 0 | 1,784 | 0 | 1,784 | 0 |
| Total | 8,420 | 8,420 | 0 | — | — |
Check for window 1: V_inflow = 3,634 m³ ≤ V_storage available + V_pumped + V_gravity = (5,238 − 1,604) + 0 + 0 = 3,634 m³. The facility therefore needs 5,238 m³ of storage, which the routing confirms.
Table 5C.4 — Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Time (h) | Inflow (L/s) | Outlet | Outflow (L/s) | Stage (m) | Storage (m³) |
|---|---|---|---|---|---|
| 24 | 20 | Open | 18 | 0.18 | 445 |
| 28 | 39 | Open | 24 | 0.25 | 621 |
| 32 | 59 | Open | 32 | 0.36 | 906 |
| 34 | 85 | Open | 37 | 0.47 | 1,166 |
| 36 | 286 | Closed | 0 | 0.78 | 1,944 |
| 38 | 106 | Closed | 0 | 1.73 | 4,321 |
| 40 | 66 | Closed | 0 | 1.96 | 4,904 |
| 42 | 51 | Open | 529 | 1.79 | 4,472 |
| 44 | 42 | Open | 204 | 0.87 | 2,181 |
| 46 | 37 | Open | 49 | 0.74 | 1,854 |
| 48 | 33 | Open | 47 | 0.70 | 1,756 |
| 50 | 0 | Closed | 0 | 0.71 | 1,784 |
| 54 | 0 | Closed | 0 | 0.71 | 1,784 |
| 56 | 0 | Open | 43 | 0.58 | 1,459 |
| 60 | 0 | Open | 32 | 0.37 | 921 |
| 66 | 0 | Open | 16 | 0.16 | 397 |
| 72 | 0 | Open | 7 | 0.06 | 162 |
Assessment
5C.6 Clause 5.10.4(a). The facility of Annex 4C reaches 1.17 m in J2, and its spillway crest is at 1.35 m (Annex 4C). In the outfall-closed check the stage reaches 2.10 m, so the spillway would operate. The facility of Annex 4C fails the check.
5C.7 Remedy. Pumping (Clause 5.12) does not help here: during the lock windows the receiving drain is itself closed, and pumping into it would raise its level, which Clause 5.12.3 does not permit. The remedy is more storage. Keeping the plan area of 2,500 m² and the outlets of Annex 4C:
- the facility must hold 5,238 m³, to a stage of 2.10 m;
- the spillway crest is set above that stage, with the 0.15 m clearance recommended in Clause 4.9.3: 2.25 m;
- with the 4.0 m spillway of Annex 4C (head 0.30 m), the maximum level with the spillway flowing is 2.55 m, and with 0.3 m freeboard the top of the walls is at least 2.85 m above the floor.
The outfall-closed check therefore governs the storage: 5,238 m³ against 2,913 m³ from the release-rate checks, about 80% more. A larger plan area would make the facility shallower; the outlet, caps and drawdown would then have to be re-checked, because the stage–discharge relationship changes.
5C.8 Release after the lock. When the first window ends, the stored water is released under a head of about 2 m, at up to 584 L/s. This is above the 100-yr cap of 356 L/s. Clause 5.10.4 allows this, because the release reaches a drain that has itself just reopened, and requires it to be included in the J4 run of the downstream analysis (Clauses 5.4 and 5.9) and reported on Form 5-1, Section H.
5C.9 Drawdown after the storm (Clause 5.10.5). The J1 tidal curve stays below the site outlet (Table 5C.1), so the drawdown of Annex 4C applies: 45.3 h for 90% of the 10-yr storage with the low-flow orifice 50% blocked, within the 48-hour limit of Clause 4.7. In Run B, 90% of the maximum J4 storage is released 22.6 h after the maximum.
5C.10 Other requirements.
- The flap gate on the site outlet is inspected and operated before 31 March each year and after every event in which it closed against a storm flow (Clause 5.11.5).
- The deeper facility is checked for flotation with groundwater at the design groundwater level; in the Dhansiri, Chathe and Diphu flood plains of the Dimapur–Chümoukedima plain, with the auto-flow zone round Dhansiripar, land below the 1% AEP flood level of those rivers, and the pond and reservoir margins without piezometer readings that level is existing ground level (Clauses 4.12.1 and 4.12.3).
- The fence and signs of Annex 4C apply to the deeper facility (Clause 4.15).
Table 5C.5 — Summary (Illustrative — not design values)
| Item | Value |
|---|---|
| Governing case | J4, 1% AEP 48-hour storm, Run B (first window starting at the peak 1-hour block) |
| Storage required | 5,238 m³ (Annex 4C release-rate design: 2,913 m³) |
| Maximum stage | 2.10 m, with 2,500 m² plan area |
| Spillway crest | 2.25 m |
| Top of walls | ≥ 2.85 m above the floor |
| Largest release after a lock window | 584 L/s, to be included in the downstream J4 run |
| Drawdown | Annex 4C result applies: 45.3 h with the low-flow orifice 50% blocked |
Form 5-1 — Downstream and Tailwater Report
Supports Clauses 5.3 to 5.14 of Chapter 5.
Draft form — Nagaland Stormwater Design Manual, Draft v1.0. One report for each project. Sites of less than 0.5 ha that meet Clause 5.3.4 may submit Form 5-2 instead, where the Authority accepts it. Attach the plans, model files and hydrographs referred to.
A. Project
Table 5F.1 — Form 5-1: project
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Project type: site under Chapter 4; drainage project under Chapter 6; regional detention or tank restoration (Clause 5.1.2) | |
| A3. Site or project area (ha) and outfalls | |
| A4. Site Runoff Control Report reference (Form 4-1), where applicable |
B. Extent of the analysis (Clause 5.3; Clause 5.14, item 1)
Table 5F.2 — Form 5-1: analysis points
| Point | Location | Type (Clause 5.3.3 (a) to (e)) | Contributing catchment (ha) | Project area as % of it |
|---|---|---|---|---|
Table 5F.3 — Form 5-1: end point
| Field | Entry |
|---|---|
| B1. End point and reason: 10% point, tank or pond, or major drain or the sea (Clause 5.3.1 (a) to (c)) | |
| B2. Where the end point is a tank or pond: change in maximum water level (m) and in surplus-weir discharge (m³/s); continuation below the weir if the level rises (Clause 5.3.2) | |
| B3. Plan of the analysis extent, showing the site, each point with its contributing area and percentage, and the end point (attach) |
C. Model (Clause 5.4.4; Clause 5.14, item 2)
Table 5F.4 — Form 5-1: model
| Field | Entry |
|---|---|
| C1. Software and version; hydrologic and hydraulic methods (Clause 5.4.4) | |
| C2. Network schematic, with the survey sources for drains and crossings (attach) | |
| C3. Land use and CN of off-site areas (present land use) | |
| C4. Upstream detention included, with evidence that it is built, maintained and documented | |
| C5. Calibration or validation evidence, where available | |
| C6. Scenarios run: existing, with project, and future where the Authority requires it (Clause 5.4.1) | |
| C7. Storms run: AEPs and durations, AMC and areal reduction (Clause 5.4.3) |
D. Results at each analysis point (Clause 5.4.2; Clause 5.14, item 3)
Complete one row for each analysis point, AEP and duration. E = existing; P = with project.
Table 5F.5 — Form 5-1: results by analysis point
| Point | AEP | Duration (h) | Peak flow E / P (m³/s) | Time to peak E / P (h) | Maximum water level E / P (m) | Peak velocity E / P (m/s) | Duration of inundation E / P (h) |
|---|---|---|---|---|---|---|---|
E. Acceptance (Clause 5.5; Clause 5.14, item 4)
Table 5F.6 — Form 5-1: acceptance criteria
| Criterion | Met at every point? | Where not met, the remedy adopted (Clause 5.5.3) |
|---|---|---|
| E1. 1% AEP water level rise ≤ 10 mm at buildings, lowest openings and carriageways (Clause 5.5.1(a)) | ||
| E2. No building newly flooded; no building or road newly failing the Chapter 6 limits (Clause 5.5.1(b)) | ||
| E3. Peak flow not above existing at the minor-system AEP of each element or at 1% AEP (Clause 5.5.1(c)) | ||
| E4. Velocity in lined channels within the lining limit, 3.0 m/s maximum (Clause 5.5.1(d)) | ||
| E5. Velocity in unlined channels, 50% and 10% AEP, not increased by more than 10% (Clause 5.5.1(e)) | ||
| E6. Change in duration of road closure on arterial or emergency routes (Clause 5.5.2) | ||
| E7. Timing exception requested (Clause 5.5.4)? Give the conditions met |
F. Tailwater derivation (Clauses 5.6 to 5.8; Clause 5.14, item 5)
Table 5F.7 — Form 5-1: tailwater derivation
| Field | Entry |
|---|---|
| F1. Tide-table edition and port, or port authority source (Clause 5.7.2(a)) | |
| F2. MHWS, HAT and MSL (m above chart datum) | |
| F3. Connection from chart datum to the Survey of India benchmark and the project datum: offset (m) and source (Clause 5.7.2(b)) | |
| F4. Estuary, creek or canal outfall: levels used and any evidence for a departure from open-coast levels (Clause 5.7.2(c)) | |
| F5. 10% AEP surge and 1% AEP still-water level: values, source, method and record length (Clause 5.7.3) | |
| F6. Wave set-up, for outfalls facing the open sea (Clause 5.7.3(d)) | |
| F7. SLA (m), at least +0.3 m; design life; sensitivity run at twice the SLA for design lives over 50 years (Clause 5.7.4) | |
| F8. Non-tidal tailwater: receiving-system level and source (Clauses 5.6.2, 5.6.3) | |
| F9. River levels and sources; reservoir or tank releases included (Clauses 5.8.2, 5.8.3) | |
| F10. The Dimapur nullahs and the plain's rivers, hill streams, the Doyang reservoir and its release reach, the Assam reaches, the Tizu and the Barak headwaters, ponds, and drains of other bodies: for an outfall on the Dimapur–Chümoukedima plain, the nullah and the river it reaches (Dhansiri, Chathe, Diphu or the old Dhansiri channel), the gauge and the danger-mark stage used, with its datum and its tie to a Survey of India benchmark, or a statement that none has been surveyed; the 1% AEP model with the rainfall of Clause 2.3.6, AMC and the channel as surveyed net of encroachment, silt, waste and vegetation; the surveyed flood marks (2008, 2019, June 2023, September 2025 or later) and their sources; the low-river case with the drains blocked and the high-river case with the outfalls backed up; the operator of each gate, flap gate and pumping station, sills, bank or wall crest, installed capacity, operating levels and gate-closing level, or a statement that none exists; drain behind the gate routed with its whole catchment and present storage, pumping confirmed available (permanent pumps only, not more than installed capacity less the largest pump), pumps operable at the design level; the lock (the whole 72-hour storm, not less than 72 hours with no gravity discharge where a gate would shut, or longer from a stage record) and the pump-down within 48 hours; gate-failure check; for a hill stream (the Dzuna, Dzucha, Dzu, Sano Ru or another), the 1% AEP study with the bulking, blockage and solid-waste rules of Clause 6.3.6, the surveyed flood marks and their sources, the receiving system confirmed by survey, the bed survey and range of bed movement, the invert at least 0.5 m above the highest surveyed bed level, the scour depth of the foundation, the energy dissipator, confirmation that no outfall discharges onto an unprotected slope, to a spring or above a supply intake, and the lock (storm plus recession, not less than 24 hours); for the Doyang reservoir, NEEPCO's written levels, rating and datum, or the interim tailwater of 333.5 m [TBC], the reservoir starting at 333.0 m, outfall below the tailwater treated as closed for the whole of the 72-hour storm, no gate operation, drawdown, notice or attenuation credited; for the release reach, the design storm and the 72-hour storm with the largest recorded release, or 5,977 m³/s until NEEPCO gives one, placed before, during and after the storm, the lock (not less than 72 hours, and for the release's duration, about 215 hours as in 2018, where the outfall is below the release level) and the channel-shift hazard; for a river leaving the State, the Assam-site level (Numaligarh 80.18 m where a check level is needed) used only as the model's downstream boundary; for the Tizu, the Zungki or the Barak headwaters, the model and flood marks and the boundary used; for a pond, the owner's and, on village land, the Village Council's consent, the outlet level surveyed, the stage–storage relation, the routed level and the dry-weather interception before it; WRD's consent for work in or on a river; owner's consent for a drain of another body (the Municipality's under s.119 of the 2023 Act; PWD, PWD (NH) or NHIDCL; UDD or KSCDL; the Village Council), the landowner's written permission for a drain across another's land (bye-law 20(ii)), permitted rate, design water level or computed channel level, and flap gate; and the lines checked (no statutory line; bye-law 23; NSDMA's 0.75–3.0 m proposal noted, not applied; the corridor of Clause 7.4) (Clause 5.8.5) |
G. Joint cases (Clause 5.9; Clause 5.14, item 6)
Table 5F.8 — Form 5-1: joint-case results
| Case | Rainfall | Tailwater used (m, project datum) | Applies? | Governing result (storage, level, pipe size or pump capacity) |
|---|---|---|---|---|
| J1 | ||||
| J2 | ||||
| J3 | ||||
| J4 | ||||
| R1 | ||||
| R2 |
H. Outfall-closed check (Clause 5.10; Clause 5.14, item 7)
Table 5F.9 — Form 5-1: outfall-closed check
| Field | Entry |
|---|---|
| H1. Reason the check applies (Clause 5.10.1) | |
| H2. Storm: AEP, 48 h and 72 h, AMC III (Clause 5.10.2) | |
| H3. Lock duration and basis: default of two 6-hour windows, or site study (Clause 5.10.6); extension for sand-bar closure (Clause 5.13.5) | |
| H4. Lock windows of the two runs (start and end times) (Clause 5.10.3(d)) | |
| H5. Maximum stage in each facility, against its 1% AEP maximum water level (Clause 5.10.4(a)) | |
| H6. Maximum stage in the minor and major systems, against the Chapter 6 limits (Clause 5.10.4(b)) | |
| H7. Property connections: surcharge level, or non-return valves fitted (Clause 5.10.4(c)) | |
| H8. Stage hydrographs (attach) | |
| H9. Drawdown after the storm under the J1 tidal curve, and pumping where needed (Clause 5.10.5) |
Table 5F.10 — Form 5-1: volume balance for each lock window (Clause 5.10.4)
| Period | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| Before window 1 | |||||
| Window 1 | |||||
| Between windows | |||||
| Window 2 | |||||
| After window 2 |
I. Gates and valves (Clause 5.11; Clause 5.14, item 8)
Table 5F.11 — Form 5-1: schedule of flap gates, tide gates and non-return valves
| Location | Type | Size (mm) | Invert (m, project datum) | Certified head–discharge data (reference) | Stop-log or penstock (outfalls > 600 mm) |
|---|---|---|---|---|---|
J. Pumped outfalls (Clause 5.12; Clause 5.14, item 9)
Table 5F.12 — Form 5-1: pumped outfalls
| Field | Entry |
|---|---|
| J1. Reason pumping is needed (Clause 5.12.1) | |
| J2. Duty capacity (m³/s) at the static head for the J2 tailwater; standby capacity (Clause 5.12.2) | |
| J3. Effect on the receiving water level (Clause 5.12.3) | |
| J4. Power supply: two independent supplies, or standby generation with 72 h of fuel; automatic changeover (Clause 5.12.4) | |
| J5. Level of electrical panels, controls, generators and fuel, against the higher of the 1% AEP flood level + 0.5 m and HAT + surge + SLA + 0.5 m (Clause 5.12.5) | |
| J6. Discharge arrangement (Clause 5.12.6); controls, alarms and logging (Clause 5.12.7); screens (Clause 5.12.8) |
K. Sand bar (Clause 5.13; Clause 5.14, item 10)
Table 5F.13 — Form 5-1: sand-bar assumption
| Field | Entry |
|---|---|
| K1. River mouth or creek inlet concerned | |
| K2. Mouth assumed closed, or open with WRD certification attached (Clause 5.13.2) | |
| K3. Bar crest level from the most recent pre-monsoon survey (m) and the closed-mouth tailwater (Clause 5.13.3) | |
| K4. Extension of the lock duration, where required (Clause 5.13.5) |
L. Inspection and maintenance (Clause 5.14, item 11)
Table 5F.14 — Form 5-1: inspection and maintenance
| Field | Entry |
|---|---|
| L1. Gate and valve inspection before 31 March and after closure events (Clause 5.11.5) | |
| L2. Pump test runs before 31 March (Clause 5.12.9) | |
| L3. Other requirements for the maintenance plan (Chapter 10) |
M. Statement by the registered professional (Clause 10.6)
I state that this report has been prepared under Chapter 5 of the Nagaland Stormwater Design Manual (Draft v1.0), that the results reported are reproduced by the models submitted, and that every departure from Chapter 5 is listed with its reason. The Professional Design Certificate (Form 10-3) is attached.
Table 5F.15 — Form 5-1: statement by the registered professional
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Empanelment number, where Clause 10.6.1 requires it | |
| Organisation | |
| Signature | |
| Date |
Draft form — Nagaland Stormwater Design Manual, Draft v1.0.
Form 5-2 — Simplified Downstream Statement (small sites)
Supports Clause 5.3.4 of Chapter 5.
Draft form — Nagaland Stormwater Design Manual, Draft v1.0. For sites of less than 0.5 ha. The Authority may accept this statement in place of the full analysis only where every answer in Section B is "Yes". Otherwise submit Form 5-1.
A. Site
Table 5F.16 — Form 5-2: site
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Site area (ha), less than 0.5 ha | |
| A3. Receiving public drain: name or reference, type and size | |
| A4. Site Runoff Control Report reference (Form 4-1) |
B. Conditions (Clause 5.3.4)
Table 5F.17 — Form 5-2: conditions
| Condition | Yes / No | Evidence |
|---|---|---|
| B1. The receiving public drain has documented capacity for its minor-system design flow (Chapter 6) | ||
| B2. No flood-prone location is recorded within 500 m downstream of the site outfall. Records checked: local body, KMC, NSDMA, WRD (Clause 5.3.3(d)) | ||
| B3. The site does not drain to a tidal or backwater-affected outfall |
C. Route plan
Table 5F.18 — Form 5-2: attachments
| Attachment | Attached? |
|---|---|
| C1. Plan of the drainage route from the site outfall for 500 m downstream, with the receiving drain and any recorded flood-prone locations | |
| C2. Copy or reference of the drain capacity record |
D. Statement
I state that the site meets the conditions of Clause 5.3.4 as shown above, and that the records listed have been checked.
Table 5F.19 — Form 5-2: statement
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Signature | |
| Date |
Draft form — Nagaland Stormwater Design Manual, Draft v1.0.