Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, pond and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Nagaland's towns have draft master plans, a disaster authority's flood assessment and an externally funded drainage programme, but no storm-drainage master plan with a design storm anywhere. No master plan for Kohima or Dimapur has been notified under the Nagaland Town and Country Planning Act, 1966, as far as found (this Manual's reading): a Draft Kohima Master Plan 2030, with studies from 2008-09, covers peripheral villages such as Meriema and Chedema (as reported); a GIS-based master plan under AMRUT for the Greater Dimapur Planning Area, for the year 2041, reached stakeholder consultation on 10 February 2023 (as reported); the Second Amendment to the bye-laws (2024) refers to "the draft Master Plans for Kohima and Dimapur" (as summarised by TeamLease); and in April 2026 a State presentation on urban strategy noted "the absence of statutory master plans in most urban areas" (as reported). No drainage chapter was seen in any of them. The Act lets a master plan include a "Public utilities plan" (s.11(d)), and since the Fourth Amendment Act, 2025 an urban local body may prepare Town Planning Schemes whose contents include "drainage inclusive of sewerage, surface or sub-soil drainage and sewage disposal" and "The filling up or reclamation of low laying, swamp or unhealthy areas" (ss.14A–14K; 14F(g)); the second is the main statutory risk to ponds and low-lying storage, and the compensatory storage of Clause 7.6.4 applies to such reclamation. The ADB's Nagaland Urban Infrastructure Development Project (UDD as executing agency; project readiness financing approved on 10 March 2022) covers "urban roads and roadside drains, storm water drainage networks, and landslip protection" in Dimapur, Kohima, Chümoukedima, Mokokchung, Wokha, Mon, Tuensang and Zunheboto, and its terms of reference ask for flood control and drainage systems that "encompass the entire areas of the towns", using "rainfall runoff computational techniques", but state no return period or runoff coefficient. NSDMA's assessment of the Dimapur urban flood recommends immediate and annual desilting, the removal of encroachments, slope stabilisation, the repair of culverts such as the Walford culvert and the covering of drains, and, in the long term, "a mandatory buffer zone (0.75 – 3.0 meters) along drainage lines", "Utilizing Natural Ponds and Water Retention Areas" such as the "ancient natural pond in Dr. Haralu Colony", a plastic ban over five years, "phase-wise priority-based improvements in the drainage system (closed system)", door-to-door waste collection, "mandating rainwater harvesting in public buildings" and "increasing permeable surfaces"; these are an assessment's recommendations, and the buffer a proposal, not a rule. AMRUT's Mission Director said in 2019 that the department "focuses on storm water drains" and that "There is no comprehensive project for drains" (as reported). No published document sets a design return period for the storm-drain network of any Nagaland town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by the Urban Development Department (UDD), the Municipal Affairs Department, any Municipal or Town Council, any Village Council, WRD, NSDMA, NEEPCO, the ADB or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, nullahs narrowed by encroachment and choked with garbage and vegetation, which flood Dimapur's colonies both when they block and when the Dhansiri, the Chathe or the Diphu backs up into them, slopes that open drains, soak pits and blocked culverts saturate, as at Pherima on NH-29 in September 2024 (as reported), drains that carry the sullage of towns without sewers, as the bye-laws allow, to the Dhansiri, the Chathe and the Kohima streams, a reach below the Doyang dam whose level the releases set, and single streams split between a Municipal Council, PWD, NHIDCL and the Village Councils of the villages they cross, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Nagaland, the fifth North-East edition of this series and its first State under Article 371A: to a ridge-top capital and a foothill-plain commercial capital, Kohima, at about 1,444 m on Disang and Barail shales that slide, whose streams fall freely to ravines, and Dimapur, on the piedmont alluvium of the Dhansiri, whose three nullahs carry its storm water and waste water to a river that backs up into them; to hill towns, Mokokchung, Wokha, Zunheboto, Tuensang, Mon, Phek and Kiphire among them, on ridges and spurs where water put into the slope moves the ground; to a highway, NH-29, that fails at blocked culverts and at the river-cut toe of Pagla Pahar; to rainfall that the national products barely cover, a CWC subzone on its upland edge, the south-western hills in a subzone without a report and the eastern ranges outside every plate, and a capital whose own records disagree, 133 mm in a day at 50 years from the State's own gauge, 240–280 mm on the plate and 322.0 mm in IMD's record; to no CWC site in the State, and a reservoir, the Doyang, run for power by NEEPCO, whose releases set the level of the river below it; to drains that carry sullage by rule, under bye-laws made under a repealed Act and kept by a savings clause, with no setback, slope limit or flood plinth; to land held mostly by villages, clans and individuals under customary law, with Village Councils inside the towns as well as outside them, so that land for a drain or a corridor is secured by agreement, never taken; to springs that supply the towns and are reported to be drying; and to a wet season that begins with the April and May storms and the plain's May floods, so that on landslide ground and below the dam a BSMP begins with the hazard, not the storm (Clause 11.3.3).


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 No basin delineation has been published for any Nagaland town. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:

  • Dimapur, Hospital, Dhobi and Lengrijan Nullahs: the catchments of the three nullahs to their outfalls on the Dhansiri, with NSDMA's vulnerable areas (Dhobinala, Burma Camp, New Market, Bank Colony, Walford, Super Market, Nagarjan, Khermahal, Netaji Colony, Rail Colony, Niu Colony, Riverbelt Colony, Zeliangrong Colony, Sachu Colony, Police Colony, Holy Cross Area and Lengrijan) shown, the outfalls as outfall-closed cases under the interim design tailwater of Clause 5.8.5(a), both failure cases modelled (the river low with the nullahs blocked, and the river high with the outfalls backed up), and the drain register marking the reaches that carry sullage and the reaches on village land;
  • Chümoukedima and Dimapur, Chathe: the catchment of the Chathe from Medziphema and Chümoukedima through Dimapur, with the colonies flooded in September 2025 (Vilhume, SM, East Police, Namgalong, Ragailong and Kuda, as reported) and the river at its danger-mark stage and its highest surveyed flood mark as the boundary;
  • Dimapur, Diphu and the old Dhansiri channel: the catchments that drain to the Diphu and to the old Dhansiri channel, where structures are reported to affect about 200 families a year (as reported), with the auto-flow zone round Dhansiripar mapped;
  • Dimapur airport area: the catchment of the "Sugar Mill Nallah" and the external storm drain of the airport (as reported), with the same boundary as the nullahs;
  • Kohima, Dzuna, Dzucha and Dzu, and Sano Ru: the catchments of the Dzuna and the Dzucha to their confluence as the Dzu, and of the Sano Ru, with the four drains under interception and diversion and their retention ponds in the 1D network, the parts under the KMC, Kohima Village and the Secretariat area marked, the landslide ground on the Disang and Barail shales shown [TBC], and surveyed flood marks and the 1% AEP level with its sediment, debris and garbage as the boundary, since no stream has a gauge;
  • Kohima, south face: the catchments of the southern slopes of Kohima and of Jakhama and Viswema that drain towards the Barak headwaters, in sub-area NL-D, with the adjoining western-hills rainfall of Clause 2.3.6(c)(ii) and a local survey as the boundary;
  • NH-29, Chümoukedima to Kohima: the catchments that cross NH-29 from Chümoukedima to Kohima, with the river-cut toe of the Chathe at Pagla Pahar, the culverts at Pherima and the slides of 2024 and 2025 mapped;
  • Doyang reservoir and release reach: the catchments that drain to the Doyang reservoir and to the reach below the dam, through Runchan and Liphi to the Assam border, with the level of the reservoir once NEEPCO states it on a named datum [TBC] and the largest recorded release, or, until NEEPCO gives one, the spillway capacity, as boundary conditions (Clause 5.8.5(c));
  • Mon town: the catchments of Mon town, with the landslide of 19 July 2026 at Defence Colony mapped, under the hazard-first rule below;
  • Peren and Jalukie, Barak headwaters: the catchments of Peren and Jalukie, in sub-area NL-D, with a local survey as the boundary, since the nearest CWC site on the Barak is far downstream; and
  • Dzuma: the catchment of the Dzuma, a tributary of the Dhansiri under integrated catchment treatment "for flood and bank erosion" by the Soil and Water Conservation Department (State affidavit to the National Green Tribunal, 12 December 2023).

Hazard first on landslide ground and the release reach (set by this Manual). On the hazard-first sites of Clause 2.3.6(i), which include the landslide ground on the Disang and Barail shales of the ranges, the river-cut toe at Pagla Pahar, the Doyang release reach, the Dimapur nullahs and the old Dhansiri channel, and the foothill fans where hill streams leave the ranges, and in every basin below one of them, the BSMP begins with a hazard screening for landslides, debris flows, flash floods and dam releases, made with the inventories of NSDMA and the District Disaster Management Authorities and the landslide records of GSI and NRSC where they exist [TBC], and NEEPCO's release reach [TBC], and in sub-areas NL-C and NL-D uses site-specific hydrology in place of a CWC report, which neither has (Clause 2.3.6(b) and (c)(ii)–(iii)). The ground moves more than the design storm here: six people died near Pherima on 3 September 2024, at least 8 at Mon on 19 July 2026, and in 2018 the river below the Doyang dam shifted 50–100 m at Runchan (all as reported). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow or a landslide. Other Tier A bodies and the Tier B councils define their basins in the first BSMP that covers them. Where a master plan, a Town Planning Scheme, NEEPCO, WRD or a court has a flood level, a reservoir level, a line or an operating rule for a dam or gate, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, river levels, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, river, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Nagaland a single stream passes through many hands, and through land held in several ways, on its way to a river. In Kohima the Dzuna, "a small river and a natural drain flowing in a west to east direction before meeting River Dzu", the Dzucha, which joins it, the Dzu "formed after the confluence of River Dzuna and Dzucha Ru", and the Sano Ru, which "flows through the capital city Kohima" (NPCB), are at once storm drains and sewers: four interception and diversion projects on the town's major drains are to take the waste water to retention ponds for treatment (State affidavit to the National Green Tribunal, 12 December 2023), and the Sanuo Ru below the New Secretariat is in CPCB's Priority V (2025). The town's north and east faces drain towards the Doyang and the Dhansiri, a placing that rests on press and local sources and has not been confirmed by a hydrological authority, and its south face towards the Barak (this Manual's reading). The oldest part of Kohima is Kohima Village, under its Village Council, and the Secretariat area "is said to be a part of Kohima village and does not form part of Kohima municipal area" (ADB, project administration manual, 2022), so a stream that crosses the town crosses municipal land, village land and State land. In Dimapur the Hospital, Dhobi and Lengrijan Nullahs carry storm water and waste water to the Dhansiri, the Lengrijan along the State border, with slums on its banks (NSDMA), and the Chathe, which "originates near Medziphema/Chumukedima, flows through Dimapur" and "connects River Dhansiri in Assam" (NPCB), carries the sewage of Medziphema and Chümoukedima; the drains vest in the Municipal Council (Nagaland Municipal Act, 2023, s.119), the road drains are PWD's, PWD (NH)'s or NHIDCL's, the rivers WRD's, and the lanes and drains on village land the Village Councils'. Below them the rivers leave the State: the Dhansiri, the Doyang, the Dikhow, the Jhanji and the Disang north into Assam, the Tizu and the Zungki east to the Chindwin in Myanmar, and the Barak headwaters south-west. No rule divides the natural streams from the municipal drains, and no notification divides the drains among their owners (this Manual's reading). This clause makes the basin the planning unit, so that one model carries each stream and nullah from its head on the ridge to the river or reservoir whoever owns each reach, so that a drain register gives every reach an owner, a land status and an outfall, and so that the sewage it carries is separated before it reaches the river or a pond (Chapter 8, Clause 8.9.5).


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For the basins of Kohima: the Kohima Municipal Council (KMC), in which the public drains, streams and tanks within its limits vest (Nagaland Municipal Act, 2023, s.119), jointly with the Urban Development Department (UDD), which prepares the master plans and Town Planning Schemes into which the BSMP is taken (Clause 11.9), and, for the parts of a basin on village land, among them Kohima Village and the Secretariat area, the Village Council of each village, if it takes the Manual into a Village Development Scheme or a resolution of its own. Each role is the one the body would have if the Manual were adopted. KSCDL is a partner for its works until they are handed over. For the basins of Greater Dimapur: the Dimapur Municipal Council (DMC) with UDD, and with the local body of Chümoukedima [TBC] for the parts of a basin in its area. Where a basin extends beyond a council's limits, the Village Councils of the villages it crosses and the other local bodies in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
  • No notification dividing the natural streams from the municipal drains, or the drains among their owners, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: the Water Resources Department (WRD) for the rivers and their beds, banks and embankments, among them the Dhansiri, the Chathe and the Diphu; the Municipal or Town Council for the public drains, streams and tanks vested in it; the Village Council for the lanes, drains and springs on village land, inside or outside a town (Nagaland Village Council Act, 1978, s.12(1)), if it adopts the Manual; UDD for the storm drains built under AMRUT, JNNURM and the ADB's urban infrastructure project, and KSCDL for the Smart City works, until handed over in writing; PWD (R&B) for the side drains, catch-water drains and culverts of State roads, and PWD (NH) and NHIDCL for those of NH-29 and the other national highways, with the slide debris and spoil of their works; PHED for sewers, the Dimapur sewage treatment plant and septage; the Soil and Water Conservation Department for catchment treatment; NEEPCO as the operator of the Doyang dam, whose levels and releases a BSMP needs as data, not as an approving authority; and NSDMA, with the District Disaster Management Authorities, for the mapping of landslide, flood and debris hazards that a BSMP must show.
  • In Mokokchung and the Town Councils, which are Tier B: the Lead Authority is named by the Municipal Affairs Department, if the Manual is adopted. Basins draining to a common river reach or reservoir may be grouped into one district-level plan.

NSDMA and the Deputy Commissioner shall be consulted on every BSMP; NEEPCO on every BSMP whose basin drains to the Doyang reservoir or to the reach below its dam; the Nagaland Pollution Control Board (NPCB) on every BSMP that proposes works on a drain or stream that carries sewage, among them the Dhansiri, the Chathe, the Sano Ru and the Dzuna, Dzucha and Dzu; the Village Councils on every BSMP that crosses village land or needs village, clan or private land for a corridor, storage or outfall, which is secured by agreement with the Village Council or the landowners; and, for a basin whose outfall lies on a river that flows into Assam, such as the Dhansiri, the Chathe or the Doyang, Assam's water resources department, through WRD.

The Water Resources Department (WRD) shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, pond, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls, rivers, streams, nullahs, ponds and the Doyang reservoir The datum of every level named; outfall invert levels against a surveyed level of the receiving river at the outfall, since there is no CWC site in Nagaland and no State gauge level for the Dhansiri, the Chathe or the Diphu at Dimapur was found (the CWC levels at Golaghat, Numaligarh, Gelabil and Sivasagar are tens of kilometres downstream in Assam and are not tailwater for any Nagaland town), with the danger-mark stage and the highest surveyed flood mark at each outfall of the Dimapur nullahs, and any local gauge kept as a separate series; for the Dzuna, the Dzucha, the Dzu and the Sano Ru in Kohima and the other ungauged streams, surveyed flood marks, the debris and garbage lines of past floods and the 1% AEP flood level with its sediment, debris and garbage; for outfalls to the Doyang reservoir and its release reach, the levels, spillway and gate data and release records of NEEPCO on a named datum, naming which is used (the CERC data format quotes 220 MCM at 324.0 m RWL and 400 MCM at 333.0 m RWL, as quoted, while SANDRP gives a gross storage of 535 MCM and 216.5 MCM at 324.0 m, as reported, a conflict; spillway 5,977 m³/s, as reported); ponds at their surveyed spill levels; the landslide, debris and flash-flood hazards above the basin from the inventories of NSDMA and the District Disaster Management Authorities where they exist and the slide records of NH-29 [TBC]; and the flap gates, penstocks, debris racks, screens, silt traps, debris basins and any pumping stations on the outfalls, with their capacities and operating rules
Rainfall and levels All available rain gauges (IMD, including its station at Kohima (42527) and the network reported daily by the Meteorological Centre Kohima, whose letterhead address is in Dimapur: the IMD stations at Kohima, Dimapur, Peren, Mokokchung, Wokha, Zunheboto, Tuensang, Kiphire, Phek and Mangkolemba, automatic weather stations and automatic rain gauges, among them AWS Dimapur, AWS Kohima, AWS Jalukie and ARG Medziphema, the automatic weather stations of NSDMA and of the Krishi Vigyan Kendras, and the agro-meteorological field unit at Jharnapani (types and record lengths [TBC]); the daily gauge of the Directorate of Soil and Water Conservation at Kohima (1997–2022); the ordinary gauge at Wokha listed in the CWC Flood Estimation Report for subzone 2(b); the rain and reservoir records of NEEPCO at the Doyang dam [TBC]; and any gauges or sensors kept by the Municipal Councils, KSCDL, WRD for its Dhansiri flood-forecasting model (as reported) and NSDMA [TBC]) and water-level records, including those for the 11–24 September 2008 (the Dimapur floods at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Khermahal, Netaji Colony and the airport area, NSDMA, with no rainfall value found), July–September 2018 (the statewide floods and landslides, with the gates of the Doyang dam open from 27 July to 5 August and an inflow of "over 1150 cum/sec" on 31 July, NEEPCO as reported by SANDRP, and only press values of rain, 95 mm at Wokha on 8 July among them), 2019 (the Dimapur floods, with 3 deaths and 13 areas submerged by NSDMA's count and 2 deaths in October in a press account, a conflict, and no rainfall value found), 12 June 2023 (the submergence of Dimapur recorded by NSDMA, with no rainfall value found), July 2025 (the floods of Dimapur and Niuland, with daily values of 95.5 to 122 mm on 4–7 July in one account and 31.5 mm at Dimapur on 6 July in another, as reported, a conflict) and 14 September 2025 (the Chathe and the Dhansiri above the danger mark at Dimapur, with 59.0 mm at Dimapur, 105.0 mm at ARG Medziphema and 121.0 mm at AWS Jalukie, as reported quoting the Meteorological Centre Kohima) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the Dimapur–Chümoukedima plain along the Dhansiri, the Chathe and the Diphu, where slopes are gentle, the nullahs are encroached and the rivers back up into them, on the old Dhansiri channel and round Dhansiripar, where the water table reaches the ground, on the Doyang release reach below the dam, and on pond margins and the few flat benches of the ridge towns, where a raised road, a dumped fill or a low wall can turn an overflow from one side of a valley floor to the other, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 11–24 September 2008 (the Dimapur floods at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Khermahal, Netaji Colony and the airport area, NSDMA, with no rainfall value found), July–September 2018 (the statewide floods and landslides, with the gates of the Doyang dam open from 27 July to 5 August and an inflow of "over 1150 cum/sec" on 31 July, NEEPCO as reported by SANDRP, and only press values of rain, 95 mm at Wokha on 8 July among them), 2019 (the Dimapur floods, with 3 deaths and 13 areas submerged by NSDMA's count and 2 deaths in October in a press account, a conflict, and no rainfall value found), 12 June 2023 (the submergence of Dimapur recorded by NSDMA, with no rainfall value found), July 2025 (the floods of Dimapur and Niuland, with daily values of 95.5 to 122 mm on 4–7 July in one account and 31.5 mm at Dimapur on 6 July in another, as reported, a conflict) and 14 September 2025 (the Chathe and the Dhansiri above the danger mark at Dimapur, with 59.0 mm at Dimapur, 105.0 mm at ARG Medziphema and 121.0 mm at AWS Jalukie, as reported quoting the Meteorological Centre Kohima) events are the best calibration data Nagaland has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and pond storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but not measured. Nagaland's storage is in its ponds, its low land on the Dimapur plain, its springs and the Doyang reservoir more than in tanks; it has no irrigation tank cascades, so the tank clauses of this chapter apply to ponds, the Doyang reservoir and any impounded water. The first census of water bodies (reference year 2017-18) counted 1,432 water bodies in the State, 90.64% of them ponds, 94.13% privately owned and 145 in urban areas, with one reported encroached (as reported); 421 wetlands covering 215 km² are reported, with Shilloi lake, the Doyang reservoir and Dzüdu lake named as priority wetlands, and a State Wetland Authority whose nodal officer is reported to be the Principal Chief Conservator of Forests (all as reported; its constitution notice [TBC]). No wetland notified under Rule 4 of the Wetlands Rules, 2017 and no Ramsar site was found. In Dimapur NSDMA proposes to keep the "ancient natural pond in Dr. Haralu Colony" for retention. Town Planning Schemes may provide for "The filling up or reclamation of low laying, swamp or unhealthy areas" (Nagaland Town and Country Planning Act, 1966, s.14F(g)), the main statutory risk to ponds and low-lying storage, to which the compensatory storage of Clause 7.6.4 applies. The Doyang reservoir's storage is quoted as 400 MCM at 333.0 m RWL and 220 MCM at 324.0 m RWL (CERC data format for NEEPCO, as quoted), while SANDRP gives a gross storage of 535 MCM, a live storage of 370 or 400 MCM and 216.5 MCM at 324.0 m (as reported), a conflict this Manual does not resolve. No survey of the storage of any pond, or of the low land and floodplain inside any town, was found.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Nagaland has been adopted with a design factor; the Nagaland State Action Plan on Climate Change (2012 version, as summarised) projects higher rainfall at Kohima, Zunheboto and Phek and increases of 15% and 20% at Wokha and Tuensang, and the State Action Plan on Climate Change and Human Health 2022–27 projects more days of 100 mm in some districts, naming Phek and Tuensang (as summarised); a larger increase attributed to UNDP is quoted in the press without a primary source and is not used; NSCCC's Kohima series for 1981–2022 states no trend, and residents report less rain overall with more heavy-rain floods (as reported), which is a reason to keep the factors, not to reduce them; and on the hazard-first sites of Clause 2.3.6(i) the hazard screening of Clause 11.3.3 is made in every scenario.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 11–24 September 2008 (the Dimapur floods at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Khermahal, Netaji Colony and the airport area, NSDMA, with no rainfall value found), July–September 2018 (the statewide floods and landslides, with the gates of the Doyang dam open from 27 July to 5 August and an inflow of "over 1150 cum/sec" on 31 July, NEEPCO as reported by SANDRP, and only press values of rain, 95 mm at Wokha on 8 July among them), 2019 (the Dimapur floods, with 3 deaths and 13 areas submerged by NSDMA's count and 2 deaths in October in a press account, a conflict, and no rainfall value found), 12 June 2023 (the submergence of Dimapur recorded by NSDMA, with no rainfall value found), July 2025 (the floods of Dimapur and Niuland, with daily values of 95.5 to 122 mm on 4–7 July in one account and 31.5 mm at Dimapur on 6 July in another, as reported, a conflict) and 14 September 2025 (the Chathe and the Dhansiri above the danger mark at Dimapur, with 59.0 mm at Dimapur, 105.0 mm at ARG Medziphema and 121.0 mm at AWS Jalukie, as reported quoting the Meteorological Centre Kohima) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two ponds in cascade with an overflow course; a 1D drain network linked to a 2D surface grid; a reach of drains, nullahs and streams with an inter-basin link; an outfall with a flap gate and pumps; and a downstream boundary that is a free outfall to a ravine stream in the ranges, river backwater at a nullah outfall on the plain, or a reservoir release reach. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) River / reservoir 1 S1 S2 S3 2 Upper pond Lower pond start level start level 3 2D surface 5 4 Drains, nullahs and streams (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Ponds Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Drains, nullahs and streams (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Sluices, flap gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary Per Ch. 5: free outfall to a ravine stream in the ranges; river backwater at a nullah outfall on the plain; reservoir release reach (largest recorded release) Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and ponds with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: ponds, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: flap gates and penstocks on the outfalls of the Hospital, Dhobi and Lengrijan Nullahs and the other drains of the Dimapur–Chümoukedima plain to the Dhansiri, the Chathe and the Diphu, where a river in flood can close an outfall, with storage behind them, and pumping only where the outfall-closed check of Chapter 5 shows that storage alone cannot serve; screens, debris racks and silt traps at the mouths of the nullahs and where the hill streams leave the ranges for the plain; debris racks, silt traps and debris basins above the culverts of the hill towns, of NH-29 and of the other hill roads, with ramps for the machines that empty them; drop structures, chutes, energy dissipators and protected outfalls where steep drains reach a stream or ravine, never an unprotected slope; the interception and screening of dry-weather flow before the outfalls to the Dhansiri, the Chathe, the Sano Ru and the Dzuna, Dzucha and Dzu, and before any pond used as storage (Chapter 8, Clause 8.9); and release scenarios for the Doyang dam, agreed with NEEPCO, for the villages on the reach below it;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Kohima, the Dhansiri flood-forecasting model that WRD is building under the National Hydrology Project (as reported), warnings of the level of the Doyang reservoir and of releases from its dam under a protocol agreed with NEEPCO [TBC], level gauges with alarms on the Dhansiri, the Chathe and the Diphu at Dimapur, which have no published gauge today, and the alerts of NSDMA and the District Disaster Management Authorities), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on the springs and streams that supply the hill towns and villages, of which 2,361 have been inventoried in 1,025 settlements (as reported), and their recharge areas above the intakes, which this Manual keeps free of paving and of infiltrated road runoff, the stability of hill slopes on the Disang and Barail shales, where water put into colluvium, fill or slide debris raises the pore pressure, recharge on the tested piedmont sands and gravels of the Dimapur–Chümoukedima plain, the only ground where it is allowed (Clause 4.11, recharge rule), although every assessment unit in the State is safe (stage of extraction 4.72%, GWRA 2024, as quoted), the shallow water table and the auto-flow zone of the plain, and the quality of the groundwater, which carries iron above the desirable limit in 23.52% of the dug-well samples of the Dimapur valley (CGWB), and of the streams, nullahs, ponds and the Doyang reservoir that the runoff reaches (Chapter 8);
  • effect on downstream basins and the receiving river, stream, nullah, pond or reservoir; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because the outfalls of the Dimapur–Chümoukedima plain are closed or limited in the wettest hours, and because the storage left is in ponds and low land that a Town Planning Scheme may reclaim (Nagaland Town and Country Planning Act, 1966, s.14F(g)). The first State-level brief for urban storm drainage takes the other view: the terms of reference of the ADB's Nagaland Urban Infrastructure Development Project, for Dimapur, Kohima, Chümoukedima, Mokokchung, Wokha, Mon, Tuensang and Zunheboto, say that "drainage waters are to be removed to outside of the town limits to suitable disposal points. Ponding of water within the towns is to be avoided", that "Structures such as flood storages and retarding basins are only to be considered as a last resort and the main intent is to concentrate and remove flood waters by providing unimpeded routes", and that designs should "eliminate pondage even during short rainfall durations and low intensities", while "low impact development/green infrastructure … shall be duly explored". This Manual differs, for three reasons, and does not criticise the terms, which were written for a programme of works. First, Dimapur's outfalls back up from the Dhansiri, the Chathe and the Diphu, so removing water faster fills the nullahs sooner when the river is high (Clause 5.8.5(a)). Second, water removed "outside of the town limits" goes to the villages downstream and to the reaches in Assam, where the flood of 2018 at Golaghat followed the release from the Doyang dam (as reported; SANDRP and NEEPCO dispute the cause). Third, NSDMA's own recommendations for Dimapur include "Utilizing Natural Ponds and Water Retention Areas", such as the "ancient natural pond in Dr. Haralu Colony", and "increasing permeable surfaces". The Manual and the terms agree on low impact development; where a design under the project follows the terms, the designer states on the submittal which governs, and this Manual does not override a contract. In the ranges storage means a lined tank or a terrace, never a pond that soaks into the ground (Clause 4.11, hill rule); the rainwater storage of at least 25 litres per m² of roof that Clause 4.11 sets, where bye-law 39 of the NBBL 2012 requires harvesting without a volume, is the first of it, and it also serves the towns in the dry months, when Kohima's supply falls short. Conveyance upgrades on their own move water faster to a nullah outfall that the Dhansiri, the Chathe or the Diphu in flood may close, to a stream or ravine whose bed and banks shift with the gravel, slide debris and garbage it carries, to the Doyang release reach, whose level the dam's releases set, or to the villages and the reaches in Assam downstream. Groundwater in Nagaland calls for storage and restraint, not recharge. Every assessment unit in the State is safe, with a stage of extraction of 4.72% and all 52 units "Safe" (GWRA 2024, as quoted), and 2.13% in Kohima district (CGWB); a Nagaland groundwater act is reported to be "being implemented" (as reported), but no State observation-well network was found [TBC]. In the ranges little rain enters the ground: "due to hilly nature most of it goes as runoff", and CGWB excludes "hilly areas with slope greater than 20%" from its recharge computation for Kohima district (an assessment convention, not a rule), whose water stood 4.41–7.22 m below ground before the monsoon and 3.98–4.68 m after it. Water put into the ground there can do harm: on the Disang shale, "grey in colour and splintery", and in colluvium and fill it raises the pore pressure on slopes that slide, and the bye-laws ask that slopes be kept stable "by ensuring good drainage of water so that the saturation of the hill-slope is avoided" (NBBL 2012, Appendix A1(d)). On the Dimapur–Chümoukedima plain the ground is different: "The Quaternary sediments provide good scope for infiltration and recharge … The Tertiary rocks which form the structural hills and residual hill act as runoff zones" (CGWB, aquifer mapping of the Dimapur valley, 2013), and a pebble–boulder bed 4–50 m thick lies south of Rangapahar, Singrijan and Diphupar (CGWB booklet), but dug-well water stood 1.04–18.88 m below ground before the monsoon and 1.0–16.66 m after it (2013), with auto-flow zones round Dhansiripar, and iron exceeded the desirable limit in 23.52% of dug-well samples, none in deep tube wells. The towns' water is short all the same: in Kohima "only about 30% of municipal areas get regular supply" and the KMC distributes water by tanker (as reported), and average supply in the project towns is "1 hour per day" (ADB, 2022). The springs matter more than the wells: the Land Resources Department is reported to have inventoried 2,361 springs in 1,025 settlements, with about 4,600 more to do and a "Springshed Atlas of Nagaland" in preparation, and to have rejuvenated 105 springs serving 11,857 households in 95 villages; and springs are reported to be "drying up due to dev" (all as reported). This is why springs and their recharge areas, slope stability, recharge only on the tested ground of the plain (Clause 4.11, recharge rule), the shallow water table and groundwater quality are all assessment criteria, and why rainwater harvesting here means storage and reuse. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the master plans of the planning areas published under the Nagaland Town and Country Planning Act, 1966, once any is notified (the Draft Kohima Master Plan 2030 and the draft master plan for the Greater Dimapur Planning Area are drafts), with their "Public utilities plan" (s.11(d)); the Town Planning Schemes prepared by the urban local bodies under ss.14A–14K of that Act; the NBBL 2012 in the areas they cover; on village land, a Village Development Scheme under section 12(1) of the Nagaland Village Council Act, 1978, if the Village Council takes the BSMP into one; and the layouts and buildings permitted under them. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Nagaland draws no water line in law. No statute or bye-law found sets a setback from a stream, spring, pond or drain, and no floodplain zoning law or Bill was found (this Manual's reading). What exists is a bar on obstruction, "no building shall be allowed to be constructed, which will obstruct the natural flow of drain" (NBBL 2012, bye-law 23), in force where the bye-laws apply and without a width; road setbacks (bye-law 17); and a definition of "Natural Hazard Prone Areas" that takes the flood-prone areas of the CWC Flood Atlas "besides, other areas can be flooded under conditions of heavy intensity rains, inundation in depressions, back flow in drains, inadequate drainage, etc. as identified through local surveys in the development plan of the area" (bye-law 42(iii)), with a menu of flood-protection measures (Appendix A3). The bye-laws have no flood plinth, and no high flood level fixed by any local authority was found for any town [TBC]. NSDMA's "mandatory buffer zone (0.75 – 3.0 meters) along drainage lines" in Dimapur is a recommendation of an assessment report, not a rule. Town Planning Schemes may provide for "The filling up or reclamation of low laying, swamp or unhealthy areas" (Nagaland Town and Country Planning Act, 1966, s.14F(g), added by the Fourth Amendment Act, 2025), which can remove the storage this chapter relies on. Land is held mostly by villages, clans and individuals under customary law, protected by Article 371A, and "no transfer of immovable property shall be affected without the consent of the Village Council" (Nagaland Village Council Act, 1978, s.15(1)(g)). Where a master-plan line or a Town Planning Scheme governs, it applies; elsewhere the hydraulic corridor and setback zones of Chapter 7 apply as this Manual's proposal, with a Zone 1 of at least 15 m from the top of bank on every channel draining 8 ha or more, including the Dimapur nullahs and the Kohima streams, and round every pond, spring and reservoir the Manual covers, and a Zone 2 to the 1% AEP extent plus 10 m, whichever is wider; the 15 m is 5 to 20 times NSDMA's proposed drain buffer, and it applies to new development and redevelopment approved under this Manual, not to existing buildings. The corridor is a condition of building permission in ULB and Master Plan areas and a recommendation elsewhere, including on village land inside towns, and Zone 1 land that is village, clan or private land is secured by agreement with the Village Council or the landowners, by donation, or by reservation in a Master Plan or Town Planning Scheme, never taken by this Manual; where the State decides that land must be obtained compulsorily, that is under the Nagaland Land (Requisition and Acquisition) Act, 1965, whose s.3(1) covers "flood control and anti-erosion measures including embankment and drainage", at a Municipality's request (Nagaland Municipal Act, 2023, s.121), with compensation as the Kohima Bench held on 3 November 2026 (as reported); this Manual states that route and does not invoke it. A BSMP gives the master plans, the Town Planning Schemes and the local surveys of bye-law 42(iii) the 1% AEP drainage-flood map and the buffer widths of Chapter 7 that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the NBBL 2012 already require rooftop rainwater harvesting with a storage tank on new buildings on plots of 100 m² and more (bye-law 39), a site plan that shows the slope "to facilitate convenience for graphical study of drainage pattern of the site" and "the position of rainwater drains" (bye-law 4), and that no building obstruct "the natural flow of drain" (bye-law 23), and NSDMA's assessment of the Dimapur urban flood recommends "Utilizing Natural Ponds and Water Retention Areas" and "increasing permeable surfaces", but no rule sets a detention or peak-runoff limit; storage placed in a layout's open space builds on these, and because that land still serves as open space, the storage must stay usable as one, and on a hill slope or on shale it is a lined tank or a shallow terrace, never an infiltration basin (Clause 4.11, hill rule). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

  • Nagaland State Disaster Management Authority. Critical Assessment and Recommendation of Remedial Measures on Dimapur Urban Flood (with the District Disaster Management Authority, Dimapur, and the Dimapur Municipal Council; undated, uploaded September 2023) (nullahs; vulnerable areas; causes; recommendations; flood history; sewerage). https://web.archive.org/web/20240901051148/https://nsdma.nagaland.gov.in/sites/default/files/2023-09/Critical%20Assessment%20%26%20Recommendation%20of%20Remedial%20Measures%20on%20Dimapur%20Urban%20Flood_0.pdf
  • Asian Development Bank. Nagaland Urban Infrastructure Development Project (54166-001): project readiness financing report and project administration manual (Loan 6045, March 2022), terms of reference, Task 4, "Improving Overall Drainage Systems"; and Urban Development Department, NUIDP Introduction (August 2026). https://ewsdata.rightsindevelopment.org/files/documents/01/ADB-54166-001_YBR92el.pdf
  • The Nagaland Town and Country Planning Act, 1966 (Nagaland Act 4 of 1966), s.11, as amended, and the Nagaland Town and Country Planning (Fourth Amendment) Act, 2025 (Act No. 6 of 2025), ss.14A–14K. https://nagaland.gov.in/storage/actRules/jMXU5KJuxtktVu2WES5RkP3puVc7f6R3p3M5J2P0.pdf
  • The Nagaland Municipal Act, 2023 (Act No. 9 of 2023), ss.61, 119–121; and the Nagaland Land (Requisition and Acquisition) Act, 1965 (Act III of 1965), s.3(1), in the Department of Land Records and Survey's compendium. https://dlrs.nagaland.gov.in/wp-content/uploads/2025/01/Act_and_Rules.pdf
  • State of Nagaland. Affidavit filed on 12 December 2023 in E.A. No. 35 of 2023 in O.A. No. 673 of 2018 before the National Green Tribunal (the Dhansiri; the Dimapur STP; interception and diversion on Kohima's drains; septage; the Dzuma catchment). https://www.greentribunal.gov.in/
  • Central Ground Water Board, North Eastern Region. Aquifer Mapping … Dimapur Valley (July 2013) and Ground Water Information Booklets, Kohima and Dimapur districts; with the assessment of 2024 (as quoted).
  • Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
  • Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
  • Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
  • Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
  • Government of Nagaland, Urban Development Department. Nagaland Building Bye-Laws 2012 (as amended), bye-laws 17, 23, 39 and 42(iii), Appendices A1 and A3. https://kmc.nagaland.gov.in/wp-content/uploads/2023/12/Building-Bye-Laws.pdf
  • The Nagaland Village Council Act, 1978 (as amended), ss.12 and 15. https://faolex.fao.org/docs/pdf/ind94094.pdf
  • Nagaland Pollution Control Board. Revised Action Plan for rejuvenation of polluted river stretches, Priority III/IV/V (2019) (the Dzuna, Dzucha, Dzu, Sano Ru and Chathe); and Central Pollution Control Board (2025), Polluted River Stretches for Restoration of Water Quality.
  • Central Electricity Regulatory Commission. Data formats for NEEPCO's Doyang hydro-electric project, 2024–29 (reservoir levels and storage, as quoted). https://cercind.gov.in/
  • South Asia Network on Dams, Rivers and People (2018, 2019). Role of Doyang dam in bringing unprecedented floods in Golaghat and Overview of CWC's flood forecasting sites 2019: North East India (secondary sources). https://sandrp.in/
  • India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Kohima (42527); Meteorological Centre Kohima, Daily Weather Summary of Nagaland; and Nagaland State Climate Change Cell, Rainfall Kohima (1981–2022).
  • Eastern Mirror, Morung Express, Nagaland Post, IPR Nagaland, EastMojo and Down To Earth (2018–2026). Reports of the draft master plans for Kohima and Greater Dimapur, the urban strategy of 2026, the water bodies census, wetlands and springs, Kohima's water supply, the Doyang alerts and the floods and landslides of 2018–2026 (secondary sources).

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Nagaland building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report