Annexes to Chapter 11Basin and City Stormwater Master Plans
These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.
Annex 11A — BSMP terms of reference template
Supports Clauses 11.1 to 11.12 of Chapter 11.
Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.
11A.1 Background and purpose
- The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Nagaland Stormwater Design Manual.
- The BSMP shall (Clause 11.1.2):
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service for each part of the drainage system;
- (c) identify, cost and rank the works, storage and land needed to reach that level of service;
- (d) identify land to be reserved in the statutory land-use plan for regional storage, pond and tank restoration and major flow paths;
- (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
- (f) recommend catchments for notification as flood-sensitive.
- The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).
11A.2 Client, partners and study area
- Client: [Lead Authority] (Clause 11.4.1).
- Partners: WRD, wherever the basin includes a river, canal or tank under its control, and [other local bodies, the Municipal Affairs Department or UDD, NSDMA] (Clause 11.4.1).
- Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
- Links to other basins: [for example the receiving river, stream, nullah, pond or reservoir corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).
11A.3 Team
- The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
- The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.
11A.4 Tasks
Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.
Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):
- (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
- (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
- (c) waterbodies: every tank, pond, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
- (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
- (e) outfalls, rivers, streams, nullahs, ponds and the Doyang reservoir: outfall invert levels, on a named datum, against a surveyed level of the receiving river at the outfall (there is no CWC site in Nagaland, and no State gauge level for the Dhansiri, the Chathe or the Diphu at Dimapur was found), with the danger-mark stage and the highest surveyed flood mark at each nullah outfall, any local gauge kept as a separate series and any conflict between published values stated; for ungauged streams, the Dzuna, the Dzucha, the Dzu and the Sano Ru among them, surveyed flood marks and the 1% AEP level with its sediment, debris and garbage; for outfalls to the Doyang reservoir and its release reach, NEEPCO's levels, spillway and gate data and release records, and ponds at their surveyed spill levels; the landslide, debris and flash-flood hazards above the basin; and flap gates, penstocks, debris racks, screens, silt traps, debris basins and any pumping stations on the outfalls, with their capacities and operating rules;
- (f) rainfall and water levels: all available records (IMD, including its station at Kohima (42527) and the network reported daily by the Meteorological Centre Kohima, whose letterhead address is in Dimapur: the IMD stations at Kohima, Dimapur, Peren, Mokokchung, Wokha, Zunheboto, Tuensang, Kiphire, Phek and Mangkolemba, automatic weather stations and automatic rain gauges, among them AWS Dimapur, AWS Kohima, AWS Jalukie and ARG Medziphema, the automatic weather stations of NSDMA and of the Krishi Vigyan Kendras, and the agro-meteorological field unit at Jharnapani (types and record lengths [TBC]); the daily gauge of the Directorate of Soil and Water Conservation at Kohima (1997–2022); the ordinary gauge at Wokha listed in the CWC Flood Estimation Report for subzone 2(b); the rain and reservoir records of NEEPCO at the Doyang dam [TBC]; and any gauges or sensors kept by the Municipal Councils, KSCDL, WRD for its Dhansiri flood-forecasting model (as reported) and NSDMA [TBC]), including the 11–24 September 2008 (the Dimapur floods at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Khermahal, Netaji Colony and the airport area, NSDMA, with no rainfall value found), July–September 2018 (the statewide floods and landslides, with the gates of the Doyang dam open from 27 July to 5 August and an inflow of "over 1150 cum/sec" on 31 July, NEEPCO as reported by SANDRP, and only press values of rain, 95 mm at Wokha on 8 July among them), 2019 (the Dimapur floods, with 3 deaths and 13 areas submerged by NSDMA's count and 2 deaths in October in a press account, a conflict, and no rainfall value found), 12 June 2023 (the submergence of Dimapur recorded by NSDMA, with no rainfall value found), July 2025 (the floods of Dimapur and Niuland, with daily values of 95.5 to 122 mm on 4–7 July in one account and 31.5 mm at Dimapur on 6 July in another, as reported, a conflict) and 14 September 2025 (the Chathe and the Dhansiri above the danger mark at Dimapur, with 59.0 mm at Dimapur, 105.0 mm at ARG Medziphema and 121.0 mm at AWS Jalukie, as reported quoting the Meteorological Centre Kohima) events;
- (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
- (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
- (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
- (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.
Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.
Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).
Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the 11–24 September 2008 (the Dimapur floods at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Khermahal, Netaji Colony and the airport area, NSDMA, with no rainfall value found), July–September 2018 (the statewide floods and landslides, with the gates of the Doyang dam open from 27 July to 5 August and an inflow of "over 1150 cum/sec" on 31 July, NEEPCO as reported by SANDRP, and only press values of rain, 95 mm at Wokha on 8 July among them), 2019 (the Dimapur floods, with 3 deaths and 13 areas submerged by NSDMA's count and 2 deaths in October in a press account, a conflict, and no rainfall value found), 12 June 2023 (the submergence of Dimapur recorded by NSDMA, with no rainfall value found), July 2025 (the floods of Dimapur and Niuland, with daily values of 95.5 to 122 mm on 4–7 July in one account and 31.5 mm at Dimapur on 6 July in another, as reported, a conflict) and 14 September 2025 (the Chathe and the Dhansiri above the danger mark at Dimapur, with 59.0 mm at Dimapur, 105.0 mm at ARG Medziphema and 121.0 mm at AWS Jalukie, as reported quoting the Meteorological Centre Kohima) events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.
Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).
Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.
Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on the springs and streams that supply the hill towns and villages, of which 2,361 have been inventoried in 1,025 settlements (as reported), and their recharge areas above the intakes, which this Manual keeps free of paving and of infiltrated road runoff, the stability of hill slopes on the Disang and Barail shales, where water put into colluvium, fill or slide debris raises the pore pressure, recharge on the tested piedmont sands and gravels of the Dimapur–Chümoukedima plain, the only ground where it is allowed (Clause 4.11, recharge rule), although every assessment unit in the State is safe (stage of extraction 4.72%, GWRA 2024, as quoted), the shallow water table and the auto-flow zone of the plain, and the quality of the groundwater, which carries iron above the desirable limit in 23.52% of the dug-well samples of the Dimapur valley (CGWB), and of the streams, nullahs, ponds and the Doyang reservoir that the runoff reaches; effect on downstream basins and the receiving river, stream, nullah, pond or reservoir; and who benefits.
Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).
Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).
Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).
Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.
Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.
Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).
11A.5 Deliverables
Table 11A.1 — Deliverables
| No. | Deliverable | Task | Due (months from start) |
|---|---|---|---|
| D1 | Inception report, data inventory and survey plan | 1 | [ ] |
| D2 | Data report and data sets (Annex 11D) | 2 | [ ] |
| D3 | Model build report and model files | 3 | [ ] |
| D4 | Calibration and validation report | 4 | [ ] |
| D5 | Scenario results, hazard maps and level-of-service assessment | 5, 6 | [ ] |
| D6 | Options report, with basin inputs for site design | 7, 8 | [ ] |
| D7 | Draft BSMP with draft CIP, for consultation | 9–12 | [ ] |
| D8 | Final BSMP, consultation log, approval package and open-data release | 13 | [ ] |
11A.6 Ownership and publication
All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.
Annex 11B — Basin lists and boundaries for Tier A bodies
Supports Clauses 11.3 and 11.4 of Chapter 11.
To be prepared. This annex will contain the list of basins for every Tier A body, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs the list of Tier A bodies (Annex 1A), a DEM of the accuracy of Clause 11.5.1, flown again over the Dimapur–Chümoukedima plain, the Doyang release reach and the slide-prone slopes after any large flood or landslide, the drain network of every drain-owning body (the Kohima and Dimapur Municipal Councils and the other local bodies, UDD for the drains it has built and not handed over, KSCDL, PWD (R&B), PWD (NH) and NHIDCL, PHED, and the Village Councils for the lanes and drains on village land), a drain register giving every reach its owner, its land status (village, clan, individual, municipal or State), whether it carries sullage or septic overflow, and its outfall, the rivers and embankments of WRD, the Doyang reservoir with NEEPCO's levels, spillway, gates and release records on a stated datum, the ponds with their spill levels, the springs and their recharge areas above the town intakes, and the landslide, debris and flood hazards mapped by NSDMA and the District Disaster Management Authorities (other likely sources: Survey of India, CWC, CGWB, NIH, UDD's master-plan maps, the Land Resources Department's spring inventory and the Village Councils' own records). No basin map of any Nagaland town was found. Until the annex is published, the basins of Dimapur (the Hospital, Dhobi and Lengrijan Nullahs; the Chathe; the Diphu and the old Dhansiri channel; the airport area), Kohima (the Dzuna, Dzucha and Dzu and the Sano Ru; the south face towards the Barak), the NH-29 corridor from Chümoukedima to Kohima, the Doyang reservoir and its release reach, Mon town, Peren and Jalukie, and the Dzuma named in Clause 11.3.3 are at least those named there; other Tier A bodies define their basins in their first BSMP (Clause 11.3.3); on the hazard-first sites of Clause 2.3.6(i) the hazard screening of Clause 11.3.3 comes first; and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP.
Table 11B.1 — Basins named in Clause 11.3.3 (provisional)
| Tier A body or area | Basin | Note from Chapter 11 |
|---|---|---|
| Dimapur (DMC, with UDD; Village Councils for village land, if adopted) | Catchments of the Hospital, Dhobi and Lengrijan Nullahs to the Dhansiri | Outfall-closed cases under the interim design tailwater (Clause 5.8.5(a)); river low and river high both modelled; NSDMA's vulnerable areas shown; reaches carrying sullage and reaches on village land marked |
| Chümoukedima and Dimapur (DMC, with the Chümoukedima local body [TBC]) | Catchment of the Chathe from Medziphema and Chümoukedima through Dimapur | Danger-mark stage and highest surveyed flood mark as boundary; colonies flooded in September 2025 |
| Dimapur (as above) | Catchments draining to the Diphu and the old Dhansiri channel | Auto-flow zone round Dhansiripar mapped |
| Dimapur (as above) | Airport area on the "Sugar Mill Nallah" | As for the nullahs |
| Kohima (KMC, with UDD; Kohima Village Council for village land, if adopted) | Catchments of the Dzuna and the Dzucha to the Dzu, and of the Sano Ru | Four drains under interception and diversion in the 1D network; KMC, Kohima Village and Secretariat areas marked; surveyed flood marks and 1% AEP level with debris and garbage as boundary |
| Kohima (as above) | South face, with Jakhama and Viswema, towards the Barak headwaters | Sub-area NL-D rainfall (Clause 2.3.6(c)(ii)); local survey as boundary |
| NH-29, Chümoukedima to Kohima | Catchments crossing NH-29, with Pagla Pahar and Pherima | Slides of 2024 and 2025 and the river-cut toe mapped; hazard screening first |
| Doyang reservoir and release reach | Catchments draining to the reservoir and to the reach below the dam, to the State border | NEEPCO's levels on a named datum [TBC]; largest recorded release, or spillway capacity, as boundary (Clause 5.8.5(c)); hazard screening first |
| Mon town | Catchments of Mon town | Landslide of July 2026 mapped; hazard screening first |
| Peren and Jalukie | Catchments on the Barak headwaters | Sub-area NL-D; local survey as boundary |
| Dzuma | Catchment of the Dzuma, a tributary of the Dhansiri | Integrated catchment treatment of the Soil and Water Conservation Department |
| Mokokchung and other councils (Tier B) | To be defined in the first BSMP | Clause 11.3.3 |
Table 11B.2 — Attributes of the basin boundary layer (layout)
| Field | Type | Content |
|---|---|---|
| BASIN_ID | Text | Basin identifier |
| NAME_EN, NAME_LOC | Text | Basin name in English and the local language |
| TIER_A | Text | Tier A body or bodies in the basin |
| OUTFALL | Text | Outfall to the sea, river or major waterbody (Clause 11.2) |
| AREA_KM2 | Real | Basin area, km² |
| LEAD_AUTH | Text | Lead Authority (Clause 11.4.1) |
| PARTNERS | Text | Partners, including WRD where it applies |
| LINKS | Text | Diversions to and from other basins (Clause 11.3.2) |
| BSMP_STAT | Text | None / in preparation / draft published / approved |
| BSMP_DATE | Date | Date of approval of the current BSMP |
| REVIEW_DUE | Date | Date of the next review (Clause 11.11.2) |
Annex 11C — Depth–damage curves for Nagaland building types
Supports Clause 11.8.2 of Chapter 11.
To be prepared. This annex will contain depth–damage curves for the main building types of Nagaland cities, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the 11–24 September 2008 (the Dimapur floods at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Khermahal, Netaji Colony and the airport area, NSDMA, with no rainfall value found), July–September 2018 (the statewide floods and landslides, with the gates of the Doyang dam open from 27 July to 5 August and an inflow of "over 1150 cum/sec" on 31 July, NEEPCO as reported by SANDRP, and only press values of rain, 95 mm at Wokha on 8 July among them), 2019 (the Dimapur floods, with 3 deaths and 13 areas submerged by NSDMA's count and 2 deaths in October in a press account, a conflict, and no rainfall value found), 12 June 2023 (the submergence of Dimapur recorded by NSDMA, with no rainfall value found), July 2025 (the floods of Dimapur and Niuland, with daily values of 95.5 to 122 mm on 4–7 July in one account and 31.5 mm at Dimapur on 6 July in another, as reported, a conflict) and 14 September 2025 (the Chathe and the Dhansiri above the danger mark at Dimapur, with 59.0 mm at Dimapur, 105.0 mm at ARG Medziphema and 121.0 mm at AWS Jalukie, as reported quoting the Meteorological Centre Kohima) floods (Department of Land Records and Survey and NSDMA damage assessments, insurers), and replacement costs (Public Works Department schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.
Table 11C.1 — Depth–damage curve (layout, one table per building type)
| Depth of water above floor level (m) | 0 | 0.25 | 0.5 | 1.0 | 1.5 | 2.0 | 3.0 |
|---|---|---|---|---|---|---|---|
| Structure damage (% of replacement cost) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Contents damage (% of contents value) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Building type, source and year of costs | ______ |
11C.1 Use in option assessment
Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:
EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))
The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.
Annex 11D — BSMP data and model publication standard
Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.
11D.1 What is published, and when
Table 11D.1 — Items to be published
| Item | Format | At draft (Clause 11.10.1) | At approval (Clause 11.10.2) |
|---|---|---|---|
| BSMP report, with the level-of-service assessment and options | Searchable PDF | Yes | Yes, final |
| Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) | GeoTIFF rasters; extents also as GeoPackage polygons | Yes | Yes |
| Capital Improvement Programme | CSV and PDF | Draft | Yes |
| Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate | GeoPackage and CSV | Yes | Yes |
| Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, river, nullah, pond and reservoir levels, slope, debris and garbage hazards and outfall structures, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) | GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) | Summary | Yes, except security-sensitive asset details |
| Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log | Native format, zipped | No | Yes |
| Calibration and validation report | Searchable PDF | Yes | Yes |
| Consultation log of comments and responses | PDF or CSV | — | Yes |
11D.2 Formats and references
- (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
- (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 river datums of any gauge on the Dhansiri, the Chathe and the Diphu at Dimapur (no State gauge level or datum was found [TBC]), of the reservoir levels of NEEPCO's Doyang dam (quoted in metres of reservoir water level, RWL, on a datum not stated [TBC]), of the CWC sites on the reaches in Assam where a check against them is needed (not stated in any source found [TBC]), and of the flood marks surveyed on ungauged streams, nullahs and ponds shall be stated in every data set that carries levels.
- (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
- (d) Hazard map files shall be named
<basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for exampledzuna_d_1_depth.tif. - (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.
11D.3 Metadata
Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.
11D.4 Withholding and personal data
- (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
- (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.
11D.5 Licence, viewer and versions
- (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
- (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
- (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
- (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).
Form 11-1 — Annual implementation report
Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.
Draft form — Nagaland Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each monsoon season, by 31 March (Clause 11.11.3).
Table 11F.1 — Form 11-1, Section A: Basin and plan
| No. | Field | Entry |
|---|---|---|
| A1 | Basin; Lead Authority; partners | ______ |
| A2 | BSMP version and date of approval | ______ |
| A3 | Reporting year (1 April to 31 March) | ______ |
| A4 | Date of publication (by 31 March) and web address | ______ |
Table 11F.2 — Form 11-1, Section B: CIP progress
| CIP rank | Work | Agency | Cost in CIP (₹) | Spent this year (₹) | Spent to date (₹) | Status | Expected completion |
|---|---|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)
| Regional facility or tank | Volume credited to sites (m³) | Volume delivered (m³) | Fees received (₹) | Fees spent (₹) | Fees held, with year received |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
| Basin total: volume owed and delivered | ______ | ______ | ______ | ______ | ______ |
Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))
| No. | Item | Planned | Done | Date completed |
|---|---|---|---|---|
| D1 | Desilting of drains and canals (length, km; volume, m³) | ______ | ______ | ______ |
| D2 | Tank and pond desilting and restoration (tanks, number; storage restored, m³) | ______ | ______ | ______ |
| D3 | Gate tests (number of gates) | ______ | ______ | ______ |
| D4 | Pump station duty tests (number of stations) | ______ | ______ | ______ |
| D5 | Tank operating rules reviewed with the custodian (number) | ______ | ______ | ______ |
| D6 | Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) | ______ | ______ | ______ |
Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service
| Event (dates) | Rainfall compared with the design depths (Clause 10.16.2(a)) | Level-of-service element (Table 11.2) | Location | Met (yes / no) | Event report reference (Clause 10.16.2) |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off
| No. | Field | Entry |
|---|---|---|
| F1 | Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) | ______ |
| F2 | Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) | ______ |
| F3 | Next 10-year review due (date) | ______ |
| F4 | Officer of the Lead Authority: name, designation, signature, date | ______ |