Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Nagaland the failure is one of missing criteria, of an old building rule whose force is in doubt, and of land that no building rule reaches. No document stating a design return period, intensity or runoff coefficient for the storm drains of any town was found. The building rule is the Nagaland Building Bye-Laws 2012 (Urban Development Department; made under sections 479 and 481 of the Nagaland Municipal Act 2001 (Act No. 10 of 2001) and continued by section 143(2) of the Nagaland Municipal Act, 2023 (Act No. 9 of 2023)), as amended; their notification number, date and gazette reference are not printed in the copy hosted by the Kohima Municipal Council (KMC) [TBC], and they commence "on a date to be notified" (1(iii)) [TBC]. They extend to Master Plan areas, to Municipal Council and Town Council areas and to other notified local-body areas (1(ii)), and their "Authority" is the Municipal and Town Councils, including "a Local Authority or officer authorized" (2(i)). Whether they are applied is disputed: the savings clause keeps them in force "in so far as it is not inconsistent" with the 2023 Act (this Manual's reading), an officer of NSDMA said in 2024 that "the 2012 byelaws have not been implemented" (as reported), and the CAG wrote that "In Nagaland, however, no Rules and Bye-laws have been framed as of date" (Audit Report for the year ended 31 March 2023, Local Governments, in a paragraph on the internal controls of the urban local bodies); the three statements do not reconcile [TBC]. A draft Nagaland Building Bye-Laws 2026, said to follow the Draft National Building Bye-Laws 2026, is reported "in the final stages" (as reported) and has not been notified. The bye-laws already ask for much of what a drainage submittal needs, and this chapter hooks into them. Bye-law 4 asks for a site plan on which, on sloping ground, "the slope shall be indicated either with contour lines or spot levels to facilitate convenience for graphical study of drainage pattern of the site", showing "The position of rainwater drains, wastewater drains from kitchen and bathroom, the soil pipe from tank to soak pit" and the "Proposed method of drainage or disposal of rain water, waste water": the drainage sheet of Stage 2 goes with it. Bye-law 9(A)(ii) deems a permit sanctioned if no decision is made within 30 days, without authorising anything "against the terms of lease or titles of the land", so the drainage review must fit inside those 30 days: the 5 working days of the completeness check and the 15 of the first review (Clause 10.7) come to about four calendar weeks, which fit only if the drainage report is complete and lodged with the building application, and a resubmittal does not fit, so the Stage 0 meeting and the preliminary study of Stage 1 should precede the application (this Manual's reading of Clause 10.7.6). Bye-law 21 lets the Authority restrict the height of earth cutting and the width of terraces and "direct owner to construct such protective measures like retaining wall", and refuse permission if the owner does not agree: the slope-drainage conditions of this Manual (catch drains, toe drains, silt traps and no infiltration above a cut, Clause 4.11, hill rule) are attached there. Bye-law 22 makes height depend on structural design certified by the "Structural Engineer/Geo-technical Expert on Record", with a Structural Design Review Panel for taller buildings (22(ii)), and the Second Amendment (2024) asks for "a geotechnical report vetted by the Department of Geology and Mining" in notified areas (s.17A, as summarised by TeamLease); a geotechnical certificate under Clause 4.11 travels with them. Bye-law 39 requires rooftop rainwater harvesting "included in the building plans" of new buildings on plots of 100 m² and more, with a "Storage tank with provision for drawing water and spill over", but sets no volume, so the storage of Clause 4.11 is shown on the same plans. The Fourth Amendment (No. MA-22/2024/382; dated 30 June 2026 in one summary against a "2025" title, a conflict) defines a Building Plan Approval Committee and sets up a Building Byelaws Review Committee under the Municipal Affairs Department as the "competent authority" for review, amendment and relaxation (ss.33A–33B, as summarised by TeamLease). An Online Building Permission System is reported to have held a "first joint session" (as reported); its status is not known [TBC]. Bye-law 5 refuses a site only for liquefaction or storm surge, with no landslide, slope or flood test, and the bye-laws set no stream, spring or drain setback, no slope limit, no flood plinth and no runoff limit. In a Master Plan area, development needs the permission of the Authority under section 13 of the Nagaland Town and Country Planning Act, 1966, but no plan for Kohima or Dimapur has been notified, so none is yet required; in a Town Planning Scheme under the Fourth Amendment Act, 2025, the urban local body issues a commencement certificate, deemed granted after two months (s.14K). Land is the other hook. Most land is held by villages, clans and individuals under customary law, protected by Article 371A; "no transfer of immovable property shall be affected without the consent of the Village Council" (Nagaland Village Council Act, 1978, s.15(1)(g)), the oldest part of Kohima is Kohima Village, and the Secretariat area "is said to be a part of Kohima village and does not form part of Kohima municipal area" (ADB, project administration manual, 2022). A drain carried across another's land to "the nearest nulla or gorge or fallow land" needs the landowner's written permission (bye-law 20(ii)). So the land that a drain, corridor, storage or outfall needs is secured by agreement with the Village Council or the landowners, by donation, or by reservation in a Master Plan or Town Planning Scheme, and never taken by this Manual; on village land outside the bye-laws' reach this chapter is guidance for the Village Council unless it takes the Manual into a Village Development Scheme or a resolution of its own. Two fields of the forms read differently here: the "NBBL 2012 registration number" of Form 10-3 and the "NBBL 2012 registration" of Clause 10.6.1's commentary, because the bye-laws name a "Structural Engineer/Geo-technical Expert on Record" (22) but no registration scheme for designers was found [TBC], so the registration or licence under which the Authority accepts the signatory is entered there; and the "survey numbers, village" of Form 10-6, because customary land has no survey numbers in the State's records, so the recognised village under section 3 of the Village Council Act and the description of the land in the Village Council's or landowner's record are entered (this Manual's reading). Every stormwater item in this chapter is therefore written so that the engineer or architect on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the site plan and drainage details of bye-law 4, the earth-cutting directions of bye-law 21, the certificates of bye-law 22 and the rainwater harvesting plans of bye-law 39, within the 30 days of bye-law 9(A)(ii), and at completion. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Nagaland Building Bye-Laws 2012 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the NBBL 2012 steps a Nagaland applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for the whole State, which lies between 93°20′ E and 95°15′ E (Nagaland statistics portal, as quoted), inside zone 46N (90°–96° E), so that no project needs another zone (this Manual's reading; pages that place the State at "96°–98°E" are wrong)), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of any gauge on the Dhansiri, the Chathe and the Diphu at Dimapur (no State gauge level or datum was found [TBC]), of the reservoir levels of NEEPCO's Doyang dam (quoted in metres of reservoir water level, RWL, on a datum not stated [TBC]), of the CWC sites on the reaches in Assam where a check against them is needed (not stated in any source found [TBC]), and of the flood marks surveyed on ungauged streams, nullahs and ponds used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Nagaland has no design return period, design storm, runoff coefficient or drain standard for the storm drains of any town, and none was found in any document of the Urban Development Department (UDD), the Municipal Affairs Department, the Kohima or Dimapur Municipal Council, Kohima Smart City Development Ltd (KSCDL), PWD or the Water Resources Department. The NBBL 2012 refer to the National Building Code and the Indian Standards for structure only. Kohima's "storm water drainage phase 1 has been completed", with Rs 107 crore sanctioned (Elets eGov, March 2018, as reported), but no return period, intensity–duration–frequency relation or runoff coefficient for it was seen; Kohima Smart City's "Sustainable urban drainage system including Re-use" (₹41.52 crore) and "Rain water harvesting" (₹18.84 crore) stood at "DPR Completed" with nothing spent (CAG, Audit Report for the year ended 31 March 2022, Appendix 2.2.1(A)); and the terms of reference of the ADB's Nagaland Urban Infrastructure Development Project ask for designs "in keeping with Indian national standards and guidelines" without stating a return period or runoff coefficient. Road drains follow IRC:SP:42-2014 and, on hill roads, IRC:SP:48. The rainfall studies do not supply a design storm either. No intensity–duration–frequency relation with constants was found for any Nagaland station; IMD's national study (Das et al., 2022) has no panel for Kohima or Dimapur; the only Nagaland station in IMD's Extremes is Kohima (42527, rain data 1948–2012), whose 24-hour record of 322.0 mm on 6 June 1985 is 1.46 times the next Kohima day and 2.4 times the largest fall of the State's own Kohima gauge in 1997–2022 (134.2 mm), and is to be confirmed by IMD [TBC]; that gauge's fit gives 133 mm in a day at 50 years (Dabral, 2025), against about 240–280 mm on Plate 9 of the CWC Flood Estimation Report for subzone 2(b), so the station series, the plate and the record disagree. Subzone 2(b) covers the plain and the central and northern ranges, the south-western hills lie in subzone 2(c), for which CWC has published no Flood Estimation Report, and the eastern ranges lie outside every plate. The State's design values are therefore those of Chapter 2: the 2(b) plates in sub-areas NL-A, NL-B and NL-B1, with the Kohima record as a floor within 25 km of the gauge until IMD rules on it (Clause 2.3.6(c)(i) and (h)), the adjoining edition's western-hills table in NL-D (Clause 2.3.6(c)(ii)), and the boundary values or NIH-DHAARA, whichever is higher, in NL-C (Clause 2.3.6(c)(iii)); and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Nagaland calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UDD:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by UDD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the NBBL 2012 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UDD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the approval of the Water Resources Department (WRD) for a work on, or a discharge to, a river or embankment in its charge, among them the Dhansiri, the Chathe and the Diphu, the consent of the Municipal Council or Town Council to connect a drain to a public drain vested in it (Nagaland Municipal Act, 2023, s.119), the written permission of the landowner for a drain carried across another's land to "the nearest nulla or gorge or fallow land" (NBBL 2012, bye-law 20(ii)), the consent of the Village Council to any transfer of village land that a drain, corridor or storage needs (Nagaland Village Council Act, 1978, s.15(1)(g)), the consent of PWD (R&B), PWD (NH) or NHIDCL for a discharge to a side drain, catch-water drain or culvert of one of their roads, the consent of the Nagaland Pollution Control Board (NPCB) for a discharge that carries effluent, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example UDD or KSCDL for a drain they have built and not yet handed over to the ULB), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Nagaland because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Nagaland extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Nagaland has no dated State or municipal order fixing pre-monsoon desilting: Dimapur's drain-cleaning drive "started in January and would continue based on urgency", a report identifying flood-prone areas was submitted in March 2025, and the major drains got priority because it was "impossible to clean every drain" (as reported); the district disaster authority's monsoon meeting at Kohima stressed clearing drains in all colonies, with no date (as reported). The drains are run by many hands, and no notification divides them (this Manual's reading): the Municipal and Town Councils for the public drains, streams and tanks vested in them (Nagaland Municipal Act, 2023, s.119); PWD (R&B) for the drains and culverts of State roads, and PWD (NH) and NHIDCL for the national highways, NH-29 among them, where a short-term maintenance contract covers "drain clearances and, slide removal works" (Gauhati High Court, Kohima Bench, order of 9 September 2026 in PIL(Suo Moto)/2/2019); UDD as executing agency for the storm drains built under AMRUT, JNNURM and the ADB's urban infrastructure project, until it hands them over; KSCDL for the Smart City works in Kohima; WRD for the rivers and embankments; PHED for sewers, the Dimapur sewage treatment plant and septage, and PHED (Urban) for village drainage under the Swachh Bharat Mission (Gramin); the Soil and Water Conservation Department for catchment treatment, such as that of the Dzuma for flood and bank erosion (State affidavit to the National Green Tribunal, 12 December 2023); and the Village Councils for the lanes, drains and springs on village land, inside towns as well as outside, under their duty "to supervise proper maintenance of water supply, roads, … sanitation" (Nagaland Village Council Act, 1978, s.12(1)). A DMC administrator called Dimapur's drains "orphans" (2019, as reported); DMC cleans them with a dedicated crew and submits AMRUT drainage projects that UDD tenders (as reported). The interception and diversion works on Kohima's four major drains, which take the waste water to "Retention Ponds" for treatment (the same affidavit), and the septage plants of the Dimapur Municipal Council (30 KLD) and the Kohima Municipal Council (90 KLD), with 13 cesspool vehicles, need their own maintenance, and their screens trap the same garbage as the storm drains. The one large gated structure is run by rules made for another purpose: NEEPCO operates the Doyang dam for power, and its release protocol and warning thresholds were not found [TBC]; in July 2025 an "alert sounded over rise in Doyang's water level" (headline, as reported). No operating rule for any gate or pumping station in a Nagaland town, linking it to a river level, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 March) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Nagaland, the pre-monsoon inspection of flap gates, penstocks, non-return valves, debris racks, screens, silt traps, debris basins, culvert inlets and any pumped facility, including the gates, where any exist, on the outfalls of the Hospital, Dhobi and Lengrijan Nullahs and the other drains of the Dimapur–Chümoukedima plain to the Dhansiri, the Chathe and the Diphu and on outfalls to the Doyang reservoir or its release reach, with the desilting of every drain, nullah and channel, the clearance of inlets, culverts, racks, silt traps and slide debris, and the pump duty and gate seal tests, shall be completed by 31 March, with earthworks and cut slopes stabilised by the same date; gates, flap gates and any pumped facilities, with their standby power, shall be certified ready on the same date, with every gate on an outfall to a river or reservoir operated through its full travel, because the season of this Manual begins on 1 April and the floods of the Dimapur plain begin in May. Gates, pumps, their standby power and racks shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to the Doyang release reach until NEEPCO's releases have ended, if that is later. Inlets, culverts, debris racks, silt traps and the mouths of the nullahs shall be cleared again by 15 May, of the silt, slide debris and garbage of the April and early-May storms, before the May floods of the plain, and every public drain, nullah, inlet, rack, trap, basin and culvert in every town shall be cleared of the silt, slide debris and garbage of the season by 15 November. WRD's own works on rivers and embankments keep WRD's calendar.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December. The monsoon season of this Manual, 1 April to 31 October, is bracketed: the pre-monsoon months of April and May, when Dimapur's flood season begins, the south-west monsoon from its normal onset at Dimapur on 4 June to its withdrawal on 14 October, and the late part of October after the withdrawal. December to February is marked as the dry works window, and March and November as months with storms outside the season. Lanes show routine inspections; the desilting of drains and nullahs, the clearance of inlets, culverts, racks, silt traps and slide debris, the pre-monsoon inspection, the readiness of gates, flap gates and any pumps and the Form 10-7 declaration, all by 31 March; standby of gates, pumps and racks from 1 April to 31 October; a mid-season clearance by 15 May, before the May floods of the Dimapur plain; a post-season clearance by 15 November; inspections after heavy rainfall in any month; the reporting year from 1 April to 31 March; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Monsoon season of this Manual: 1 Apr–31 Oct Dry: works window Dry Storms Storms Pre-monsoon storms South-west monsoon, 4 Jun–14 Oct Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 Mar 15 May 31 Oct 15 Nov Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 Mar: drains and nullahs desilted; inlets, culverts, racks, traps and slide debris cleared; inspection; gates and pumps ready. 1 Apr–31 Oct: standby. By 15 May: inlets, culverts, racks, traps and nullah mouths cleared again. By 15 Nov: post-season clearance. After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including March and November storms) Annual declaration Form 10-7 Form 10-7 by 31 Mar, closing the reporting year (1 Apr–31 Mar): Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one season, 1 Apr–31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 March, 15 May, 31 October and 15 November are fixed (set by this Manual). December–February is the works window. Pre-monsoon months at Kohima: mean 106 mm in April and 179 mm in May (NSCCC, 1981–2022); 24-h records 74.8 mm (11 April 1965) and 76.0 mm (18 May 1995) (IMD). Dimapur's flood season begins in May (NSDMA). South-west monsoon: normal onset at Dimapur 4 June, withdrawal 14 October (IMD normals, 2020). Late-season storm: Kohima 140.0 mm on 19 October 2001. Outside the season: Kohima 75.2 mm on 27 March 1994 and 87.0 mm on 7 November 1971 (all IMD).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October: the pre-monsoon months of April and May, and the south-west monsoon from its normal onset at Dimapur on 4 June (2 June in 1901–1940) to its withdrawal on 14 October (9 October before; 1971–2019) (IMD, new normal dates of onset and withdrawal, 2020, Table 2; IMD gives no Kohima row). The monsoon in IMD's sense does not begin in April; the season of this Manual does, for four reasons. Kohima's rain rises steeply from April: its monthly means for 1981–2022 are 106.27 mm in April, 179.40 mm in May, 268.70 mm in June, 349.82 mm in July, 327.53 mm in August, 256.13 mm in September and 133.04 mm in October (NSCCC, Rainfall Kohima), and March to May bring about 19% of the year (sum computed for this Manual, about 1,744 mm). Dimapur's flood season starts in May: NSDMA lists the town's vulnerable areas for "May–Sep" (assessment of the Dimapur urban flood), CGWB finds that the monsoon "persists from May to September" in Dimapur district, Dabral (2025) that the State's rain falls "over a period of 6 months (May to October)", and the Deputy Commissioner called a Dimapur flood of May 2025 "man-made", with "drains desilting still on" (headline, as reported). Kohima's April and May falls are modest by its own record, 74.8 mm in 24 hours on 11 April 1965 and 76.0 mm on 18 May 1995, against 322.0 mm on 6 June 1985 and 221.2 mm on 23 August 1971 (IMD, Extremes), so the early deadline is set by the plain's May floods and by the slope and earth works that must be finished and stabilised before the season, not by large April falls. And NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual keeps that date, as the other North-East editions of this series do. No Nagaland order fixing a date for desilting was found: Dimapur's drain clearance "started in January and would continue based on urgency" into late May, with a mass social work on 31 May (as reported), the town's urban councils said it was "impossible to clean every drain" (as reported), and no deadline was reported for Kohima. The research's own suggestion, completion by 30 April, is not used: 31 March is earlier and keeps the North East on one calendar. December to February is the works window. This Manual therefore takes 31 March for the desilting of drains, nullahs and channels, the clearance of inlets, culverts, racks, silt traps and slide debris, the pre-monsoon inspection, the annual declaration, the BSMP annual report, the stabilisation of completed earthworks and cut slopes, and the readiness of gates, flap gates and any pumps, with no later readiness date. WRD's own works on rivers and embankments keep WRD's calendar. Here Nagaland's record moves one date of the North-East calendar: the Assam edition, like the plateau edition to the west, clears inlets and traps a second time by 31 May, but Dimapur's clearance campaign running into late May was overtaken by the May 2025 flood, so a clearance due by 31 May would fall in the storms it is meant to precede; inlets, culverts, racks, silt traps and the mouths of the nullahs are therefore cleared again by 15 May, as in the adjoining edition to the south, after the April and early-May storms and before the plain's May floods. Storms continue after the withdrawal: Kohima recorded 140.0 mm on 19 October 2001 (IMD), so gates, pumps and racks are kept on standby to 31 October (Figure 10.3). Storms also come outside the season, 75.2 mm on 27 March 1994, 49.0 mm on 27 February 2001 and 87.0 mm on 7 November 1971 at Kohima (IMD), and a fall of 277 mm at Wokha is listed for "12.02.1906" in the CWC Flood Estimation Report for subzone 2(b), a February date that is implausible and unconfirmed; design statistics use annual maxima from all months, the drains fill with silt, slide debris and garbage during the season, and every town clears its drains a second time by 15 November. The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Nagaland cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Nagaland drainage show up only in the first monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Nagaland Building Bye-Laws 2012 were made and continue in force and from the municipal Acts. The graduated steps are set by this Manual. In Nagaland the statutes give the local bodies a duty over their drains and weak means to enforce it, and the courts and the National Green Tribunal have begun to act where the rules do not. The NBBL 2012 carry the strongest drainage power: "Notwithstanding any of the provisions contained in these Bye-Laws, no building shall be allowed to be constructed, which will obstruct the natural flow of drain. The Authority shall have the power to cause the free flow of public drains" (bye-law 23); appeals lie under Chapter VIII of the Nagaland Town and Country Planning Act, 1966 (bye-law 31). The Nagaland Municipal Act, 2023 vests in the Municipality "all public sewers and drains, channels, tunnels, culverts and water courses in, alongside or under any street" and "all public tanks, streams, reservoirs and wells", "notwithstanding anything contained in any other law" (s.119(1)), although drainage, storm water and water supply are not among the obligatory functions of section 61; the Government's rules may carry a fine of up to ₹5,000 for a breach (s.137), a nominal sum against the cost of a blocked nullah or a flooded colony; and a Municipal or Town Council may make regulations (s.138) that take effect only once "approved by the Government and published in the Official Gazette" (s.139), and none on drainage was found. The Act levies no tax on land and buildings (s.124), and the CAG found "No Property Tax in the State" (Audit Report for the year ended 31 March 2023, Local Governments), so the councils have little revenue of their own for maintenance, and only seven of the eighteen functions of the Twelfth Schedule had been transferred to them, solid waste management alone in full (the same report). In a Master Plan area the Nagaland Town and Country Planning Act, 1966 forbids development "except with the permission of the Authority" (s.13), but no plan for Kohima or Dimapur has been notified. The audits show how works fail without enforcement: in the Kohima Smart City Mission "only eight works were completed, another six works were ongoing … while the remaining 47 works had not yet been taken up" of 61 prioritised works, "none of the eight completed projects could provide the facilities featured as essential", and the sustainable drainage and rainwater harvesting projects had not passed the project report (CAG, Audit Report for the year ended 31 March 2022); and the Executive Engineer of PHED (Urban), Dimapur Division, made a "fraudulent payment of ₹90.54 lakh without actual execution of 2,338 metres of drainage works in 18 villages" under the Swachh Bharat Mission (Gramin) (CAG, Audit Report for the year ended 31 March 2020, para 2.3). The tribunal and the court supervise what the rules leave open. Before the National Green Tribunal in O.A. No. 673 of 2018 the State reported that the Dhansiri's pollution comes from "sewage drainage from Dimapur City, improper disposal of solid waste into the drains and industrial effluents", that the 25.43 MLD sewage treatment plant at Dimapur was "made fully functional on 14.1.2023", and that the Dhansiri was moved from Priority I to Priority III in September 2023 (affidavit in E.A. No. 35 of 2023, 12 December 2023); the Gauhati High Court, Kohima Bench, supervises NH-29 in PIL(Suo Moto)/2/2019, where the maintenance of the highway's drains and the removal of slides are recorded (order of 9 September 2026), and has directed the declogging of drains on the Kigwema–Mao road (as reported). On village land the Village Council deals with internal administration by customary law and enforces "orders passed by the competent authority on the village as a whole" (Nagaland Village Council Act, 1978, ss.14 and 15(1)(e)); it is not bound by this Manual unless it takes it up. This shows that a rule without routine enforcement does little, and that the step that acts on the professional who signs, not only on the owner, is the one this State's weak penalties most need. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river at the nearest gauge with a named datum, which for the Dhansiri, the Chathe and the Diphu at Dimapur means a State gauge or a staff gauge set up and levelled for the purpose, since none with a published datum was found [TBC], or the level of the receiving pond, with any reading published in the press kept apart and never mixed with the CWC levels of the reaches in Assam; for an ungauged stream or nullah, which includes the Dzuna, the Dzucha, the Dzu and the Sano Ru in Kohima, the flood marks surveyed after the event and the gravel, slide debris and garbage deposited at crossings, racks and culverts; the state of every flap gate, penstock, debris rack, screen, silt trap, debris basin and pumping station on the outfall and on the drain upstream of it, with the volume of debris and garbage removed from each, the hours each pump ran and any loss of power; and the gate openings, inflows and releases of the Doyang dam where it sets the receiving level, with the times of any warning NEEPCO gave;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), NSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Nagaland's floods and landslides have been counted more often than they have been reviewed, and the counts conflict. NSDMA's assessment of the Dimapur urban flood tabulates the floods of 11–24 September 2008 at Dobhinalla, Super Market, Nagarjan, Burma Camp, Walford, Sachu Colony, Nagagaon, Khermahal, Netaji Colony, Naharbari and the airport area; of 2019, with 3 deaths and 13 areas submerged; and of 2021-22, with 1,265 people affected; a press account of October 2019 gives 13–17 villages submerged and 2 deaths (as reported), a conflict. In the statewide floods and landslides of July–September 2018 the tolls changed through the season, 10 deaths in early August, at least 11 and more than 3,000 families displaced from 532 villages in 11 districts by 2 September, and about 12 in other accounts, with an interim request of ₹219 crore and damage put at "around ₹800 crore"; Kiphire was cut off for two weeks and Tobu, Pungro, Tenzing and Noklak were supplied by air (all as reported). The landslide near Pherima on NH-29 on 3 September 2024 killed six people (as reported), the heavy rain of 8–15 September 2025 washed out Pagla Pahar again and destroyed the Chümoukedima–Seithekema bridge (as reported, citing NSDMA), the floods of July 2025 killed three people at Dimapur and Niuland (as reported), and the landslide at Defence Colony in Mon town on 19 July 2026 killed 8, 9 or 10 people by different counts (as reported); reports of landslides at Mon in July 2025 and July 2026 overlap and are kept apart here. NSDMA's final tolls for 2018, 2024, 2025 and 2026 were not found [TBC]. For most of these events no gauge value was published: no IMD rainfall for any of them is in the research, only press values such as 121.0 mm at AWS Jalukie on 14 September 2025 and 137 mm in Mon district in July 2026, and IMD's own Kohima record of 322.0 mm on 6 June 1985 is unconfirmed [TBC]. No review of any flood in a Nagaland town, and no record of flood extents, depths or durations kept by any Municipal Council, Town Council or District Disaster Management Authority, was found beyond NSDMA's list of Dimapur's flooded localities and its photograph of the submergence of 12 June 2023. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Nagaland's drainage record is public: the NBBL 2012 on the Kohima Municipal Council's website; the Nagaland Municipal Act, 2023 and its amendment of 2024, the Nagaland Town and Country Planning Act, 1966 with its Fourth Amendment Act, 2025, and the Nagaland Land (Requisition and Acquisition) Act, 1965 in the Department of Land Records and Survey's compendium; the Nagaland Village Council Act, 1978 with its amendments; NSDMA's assessment of the Dimapur urban flood; the ADB's documents for the Nagaland Urban Infrastructure Development Project, with the drainage terms of reference; the State's affidavit to the National Green Tribunal on the Dhansiri; CPCB's list of polluted river stretches (2025); the High Court's orders on NH-29; the CAG's audits of the Kohima Smart City Mission, of PHED's drainage works in Dimapur and of the local governments; NSCCC's Kohima rainfall series; the Meteorological Centre Kohima's daily rainfall summary; and IMD's station extremes and monsoon normals. Much else could not be found in the public domain: the notification of the NBBL 2012 and the gazetted texts of their amendments; the draft Nagaland Building Bye-Laws 2026; the Draft Kohima Master Plan 2030, the draft GIS-based master plan for the Greater Dimapur Planning Area and any drainage chapter in them; the design basis of any storm drain, including the Kohima storm-drainage works, the AMRUT and Smart City projects and the project's drainage reports; any gauge level or datum on the Dhansiri, the Chathe or the Diphu at Dimapur; NEEPCO's release protocol and levels for the Doyang dam on a named datum; the hourly archive of the State's automatic weather stations; IMD's ruling on the Kohima record of 1985; NSDMA's official tolls; and an inventory of the gates, racks, screens and culverts of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)