Draft v1.0 prepared by NEER. Not adopted by the Government of Punjab or the Chandigarh Administration, and has no legal force. About this draft

Annexes to Chapter 3Hydrologic Methods

These annexes support Chapter 3. Annex 3C sets out benchmark test problems for software acceptance, and Forms 3-1 and 3-2 are the submittal forms required by Clause 3.17. Annexes 3A, 3B, 3D and 3E need survey, gauging or published report data that this draft does not yet contain; each gives the intended layout and the interim rule of Chapter 3 that applies until it is published. The forms are draft forms and have no statutory status.


Annex 3A — Punjab soil series to HSG lookup; seasonal high water table map

Supports Clauses 3.7 and 3.10 of Chapter 3.

To be prepared. This annex will contain (a) a lookup from each soil series mapped in Punjab to its hydrologic soil group (HSG), in both the drained and the undrained state, and (b) a map of the depth to the seasonal high groundwater table in the south-west monsoon (June–September). It needs NBSS&LUP and Punjab Remote Sensing Centre (PRSC) or Punjab Agricultural University (PAU) [TBC] series maps with their scales, measured saturated hydraulic conductivity and depth to an impermeable layer for each series, and observation-well records from the Central Ground Water Board and the Water Resources Department, supplemented by piezometers in the waterlogged south-west (Sri Muktsar Sahib, Fazilka, Faridkot and the waterlogged parts of Bathinda and Ferozepur), the land along the Rajasthan and Sirhind feeders, the Sirowal belt below the Kandi, the bet lands of the Sutlej, Beas, Ravi and Ghaggar, and the beds and margins of chhappars. Until it is published, use the interim rules of Chapter 3: assign HSG from measured saturated hydraulic conductivity and depth to an impermeable layer or water table by the criteria of NEH Part 630, Ch. 7 (Clause 3.7.2); verify it by site infiltration tests wherever retention relies on infiltration (Clause 3.7.3); take the seasonal high water table from site piezometers, trial pits or the nearest observation well (Clause 3.10.2); and assign HSG D wherever that level is within 0.6 m of the ground surface (Clause 3.10.1).

Table 3A.1 — Soil series to HSG lookup (layout)

Soil series District(s) Taxonomic class Surface texture Saturated hydraulic conductivity (mm/h) Depth to impermeable layer (m) HSG, drained HSG, undrained Source map and scale
                 
                 
                 

Table 3A.2 — Seasonal high water table, by mapping unit (layout)

Mapping unit or grid cell Observation wells used Years of June–September record Highest June–September level below ground (m) Within 0.6 m of ground (Clause 3.10.1)? Data source
           
           

Annex 3B — Punjab CN calibration and supplementary land covers (choe beds and Kandi scrub, paddy fields, saline-sodic fields, dune sand, chhappar beds)

Supports Clauses 3.8 and 3.15 of Chapter 3.

To be prepared. This annex will contain (a) curve numbers calibrated against observed rainfall and runoff in Punjab catchments, compared with the TR-55 values of Table 3.5, and (b) curve numbers for land covers that Table 3.5 does not list: the boulder, gravel and sand beds of the Kandi choes, and the scrub, grass and plantation on the Kandi fans and on the sandstone and clay of the Shivalik slopes of Pathankot, Hoshiarpur, Nawanshahr, Rupnagar and SAS Nagar; paddy fields, puddled and bunded from transplanting in early June, which stand under water at the start of a monsoon storm and spill over their bunds; the saline-sodic and waterlogged fields of the south-west, in Sri Muktsar Sahib, Fazilka, Faridkot and parts of Bathinda and Ferozepur, and the sodic patches of the old alluvium of Patiala, Sangrur and Mansa, which either stand under water at the start of a storm or shed it from a sealed, crusted surface; the dune sands and loamy sands of Bathinda, Fazilka, Abohar and Sri Muktsar Sahib, bare or under sparse crops; and the beds of chhappars, tobas and dhabs that are dry, silted or cultivated at the start of a storm. It needs paired rainfall–runoff records for small gauged catchments of known cover and soil, from WRD gauging sites, agricultural research stations and tank gauges, analysed by event and by antecedent moisture. Until it is published: the pre-development reference stays open space in good condition for every site (Clause 3.3.2), so these covers do not enter the pre-development run; for off-site existing conditions, use the nearest Table 3.5 or TR-55 cover row, including the cultivated rows (Clause 3.8.3(c)), and state the row chosen and the reason on Form 3-1; land under standing water at the start of the design storm is modelled as water surface with no losses (Table 3.5; Clause 3.10.4(b)). Any departure from these defaults requires calibration under Clause 3.15 (Clause 3.15.1(d)).

Table 3B.1 — Supplementary land covers, AMC II (layout)

Cover type HSG A HSG B HSG C HSG D Ia ratio Basis (catchments, events, years)
Boulder, gravel and sand bed of a Kandi choe, dry at the start of the storm            
Scrub, grass or plantation on a Kandi fan or on the sandstone and clay of the Shivalik slopes            
Paddy field, puddled and bunded, under standing water at the start of the storm (15 June–30 September)            
Paddy field after harvest or before puddling, bunds intact            
Waterlogged or saline-sodic field, south-west, above standing water or a water table within 1.5 m at the start of the storm            
Sodic patch with a crusted surface, old alluvium of Patiala, Sangrur and Mansa            
Dune or sandy plain, bare or under sparse crops, south-west            
Chhappar, toba or dhab bed, dry, silted or cultivated at the start of the storm            
Other (state)            

Table 3B.2 — CN calibration catchments (layout)

Catchment District Area (km²) Dominant HSG and cover Events used Table 3.5 CN Calibrated CN Calibrated ÷ Table 3.5
               
               

Annex 3C — Benchmark test problems for software acceptance

Supports Clauses 3.5, 3.6, 3.8, 3.9, 3.11, 3.12 and 3.16 of Chapter 3.

Purpose. Software not listed in Clause 3.16.1 shall reproduce the results of the five problems below (Clause 3.16.3). Each problem is fully specified and uses only the methods and tables of Chapter 3, so every answer can be checked by hand. The acceptance tolerance is ±5% on each tabulated result, the equivalence threshold of Clause 3.16.2; for closed-form results (Problems 3C-1 to 3C-4), software should agree to the rounding shown. The submittal shall report the software result next to each answer below.

Illustrative — not design values. The inputs (areas, intensities, rainfall depths, slopes and the basin) are chosen for testing only. They are not design data for any site.

Problem 3C-1 — Rational Method peak (Clause 3.5)

Inputs. A 2.0 ha catchment draining to one inlet: 1.2 ha concrete paving and roofs, C = 0.90 (Table 3.2, upper half of 0.80–0.95); 0.8 ha lawns on sandy soil, average slope, C = 0.15 (Table 3.2, upper half of 0.10–0.15). Design AEP 1% (100-yr). Rainfall intensity at Tc, including the climate factor: i = 120 mm/h.

Part (b): a separate 0.5 ha fully paved catchment, C = 0.90, design AEP 1%, i = 150 mm/h.

Table 3C.1 — Problem 3C-1 solution

Step Calculation Result
Composite C (Clause 3.5.4) (1.2 × 0.90 + 0.8 × 0.15) / 2.0 0.60
Frequency factor (Table 3.3) 1% AEP Cf = 1.25
C · Cf (≤ 1.0) 0.60 × 1.25 0.75
Peak flow (Clause 3.5.1) 0.75 × 120 × 2.0 / 360 Q = 0.500 m³/s
Part (b): C · Cf 0.90 × 1.25 = 1.125, capped at 1.0 (Clause 3.5.3) 1.00
Part (b): peak flow 1.00 × 150 × 0.5 / 360 Q = 0.208 m³/s

Problem 3C-2 — Time of concentration by the segment method (Clause 3.6)

Inputs. Pre-development flow path: sheet flow over greenfield, n = 0.15 (Clause 3.6.3), L = 30 m, S = 0.01; P2 (50% AEP 24-hour rainfall, no climate factor) = 80 mm. Shallow concentrated flow, unpaved, L = 200 m, S = 0.01. Channel flow, L = 400 m, bank-full velocity V = 1.0 m/s (given).

Table 3C.2 — Problem 3C-2 solution

Segment Calculation Travel time
Sheet flow (Clause 3.6.2(a)) 0.091 × (0.15 × 30)^0.8 / (80^0.5 × 0.01^0.4) = 0.2138 h 12.83 min
Shallow concentrated (Clause 3.6.2(c)) V = 4.918 × 0.01^0.5 = 0.4918 m/s; 200 / (3,600 × 0.4918) = 0.1130 h 6.78 min
Channel (Clause 3.6.2(d)) 400 / (3,600 × 1.0) = 0.1111 h 6.67 min
Tc (Clause 3.6.1; ≥ 10 min) 12.83 + 6.78 + 6.67 26.27 min
Lag (Clause 3.6.5) 0.6 × 26.27 15.76 min

Problem 3C-3 — SCS-CN runoff depth, AMC and Ia sensitivity (Clause 3.8)

Inputs. Pre-development reference on HSG C: CN = 74 at AMC II (Table 3.5), all pervious. Cumulative rainfall P = 100 mm; second case P = 25 mm.

Table 3C.3 — Problem 3C-3 solution

Case S (mm) Ia (mm) Runoff Q (mm), P = 100 mm Runoff Q (mm), P = 25 mm
(a) AMC II, Ia = 0.2S: S = 25,400 / 74 − 254 89.24 17.85 39.38 0.53
(b) AMC III, Ia = 0.2S: CN(III) = 23 × 74 / (10 + 0.13 × 74) = 86.75 38.80 7.76 64.93 —
(c) AMC II, Ia = 0.05S: S0.05 = 25.4 × 1.33 × (89.24 / 25.4)^1.15 143.31 7.17 36.49 1.97

Runoff is Q = (P − Ia)² / (P − Ia + S). Case (c) gives less runoff than case (a) at 100 mm but more at 25 mm, as Clause 3.8.5 and Figure 3.3 describe.

Problem 3C-4 — Separate vs composite impervious representation, and SCS unit hydrograph peak (Clauses 3.9 and 3.11.2)

Inputs, part (a). A site that is 50% directly connected impervious (CN 98) and 50% open space on HSG B (CNp = 61), AMC II, Ia = 0.2S, P = 25 mm.

Inputs, part (b). A sub-area of A = 2.5 km² with Tc = 1.0 h and computation interval Δt = 0.1 h.

Table 3C.4 — Problem 3C-4 solution

Step Calculation Result
(a) Impervious half (Clause 3.9.2) S = 5.18 mm, Ia = 1.04 mm; Q = 23.96² / (23.96 + 5.18) 19.70 mm
(a) Pervious half S = 162.39 mm, Ia = 32.48 mm > P 0 mm
(a) Area-weighted runoff, separate sub-areas 0.5 × 19.70 + 0.5 × 0 9.85 mm
(a) Composite CN (Clause 3.9.4) 61 + 0.50 × (98 − 61) 79.5
(a) Runoff with composite CN S = 65.50 mm, Ia = 13.10 mm; Q = 11.90² / (11.90 + 65.50) 1.83 mm
(b) Interval check (Clause 3.11.3(a)) 0.133 × 1.0 = 0.133 h ≥ Δt = 0.1 h satisfied
(b) Lag and time to peak (Clause 3.11.2) tL = 0.6 × 1.0 = 0.60 h; tp = 0.1 / 2 + 0.60 tp = 0.65 h
(b) Unit hydrograph peak, Q = 1 mm 0.208 × 2.5 × 1 / 0.65 qp = 0.800 m³/s per mm

Part (a) reproduces the comparison in the commentary to Clause 3.9 (about 9.9 mm vs 1.8 mm).

Problem 3C-5 — Level-pool (modified Puls) storage routing (Clause 3.12.1)

Inputs. A detention basin with vertical sides and plan area 500 m², with the stage–storage–discharge relationship of Table 3C.5. Triangular inflow hydrograph: 0 at t = 0, rising linearly to 0.50 m³/s at t = 30 min, falling linearly to 0 at t = 90 min. Basin empty at t = 0. Routing interval Δt = 10 min (600 s). No tailwater.

Table 3C.5 — Problem 3C-5 stage–storage–discharge relationship

Stage (m) Storage S (m³) Outflow O (m³/s)
0.0 0 0.00
0.5 250 0.05
1.0 500 0.10
1.5 750 0.15
2.0 1,000 0.20
2.5 1,250 0.25

Method. The storage-indication equation is (I1 + I2) + (2S1/Δt − O1) = (2S2/Δt + O2). The table gives O = S / 5,000 (S in m³, O in m³/s), so 2S/Δt + O = 17.667 O and 2S/Δt − O = 15.667 O, and each step is O2 = [(I1 + I2) + 15.667 O1] / 17.667. Software interpolating linearly in Table 3C.5 shall give the same result.

Table 3C.6 — Problem 3C-5 routed outflow

Time (min) Inflow I (m³/s) Outflow O (m³/s) Storage (m³) Stage (m)
0 0.0000 0.0000 0.0 0.000
10 0.1667 0.0094 47.2 0.094
20 0.3333 0.0367 183.3 0.367
30 0.5000 0.0797 398.4 0.797
40 0.4167 0.1226 612.8 1.226
50 0.3333 0.1511 755.7 1.511
60 0.2500 0.1670 835.2 1.670
70 0.1667 0.1717 858.6 1.717
80 0.0833 0.1664 832.1 1.664
90 0.0000 0.1523 761.5 1.523
120 0.0000 0.1062 531.1 1.062
180 0.0000 0.0517 258.3 0.517

Results. Peak outflow 0.172 m³/s at 70 min; peak storage 859 m³; peak stage 1.72 m. The inflow peak of 0.50 m³/s is reduced to 34% of its value.

Table 3C.7 — Benchmark results to be reported by the applicant

Problem Result Benchmark Software result Difference (%) Within ±5%?
3C-1 Q, main case (m³/s) 0.500      
3C-1 Q, part (b) (m³/s) 0.208      
3C-2 Tc (min) 26.27      
3C-3 Q, case (a), P = 100 mm (mm) 39.38      
3C-3 Q, case (b), P = 100 mm (mm) 64.93      
3C-3 Q, case (c), P = 100 mm (mm) 36.49      
3C-3 Q, case (c), P = 25 mm (mm) 1.97      
3C-4 Runoff, separate sub-areas (mm) 9.85      
3C-4 Runoff, composite CN (mm) 1.83      
3C-4 qp (m³/s per mm) 0.800      
3C-5 Peak outflow (m³/s) 0.172      
3C-5 Peak storage (m³) 859      

Annex 3D — Peak rate factor study for flat coastal land

Supports Clauses 3.11.5 and 3.15 of Chapter 3.

Not required in Punjab. Punjab is landlocked and has no flat coastal plain, so no land in the State meets Clause 3.11.5(a), and the standard factor 484 (PRF′ = 0.208) applies to all land (Clause 3.11.5). The waterlogged south-west, the bet lands of the rivers, the paddy plains and the land held behind canal banks and raised roads are flat but are not coastal plain; their slow response is represented by storage and backwater (Clauses 3.10.4 and 3.12, and rule (b) of the Commentary to Clause 3.7), not by a lower peak rate factor. The annex and the layout of Table 3D.1 are kept only so that the annex numbering is unchanged.

Table 3D.1 — Calibrated peak rate factors (layout)

Catchment Area (km²) Mean slope (m/m) Drainage condition Events used Calibrated PRF (US customary) PRF′ (SI) Range of applicability
               
               

Annex 3E — CWC SUH parameters for subzone 1(e) and zone 7, with worked example

Supports Clauses 3.4.3 and 3.11.4 of Chapter 3.

To be prepared. This annex will tabulate, for CWC subzone 1(e) (Upper Indo-Ganga Plains) and zone 7 (Western Himalayas), the regression relationships for the synthetic unit hydrograph parameters, the design storm duration, loss rate, base flow, areal reduction and time distribution, each with its reference to the Flood Estimation Report, and a worked example for one catchment. It needs the two CWC Flood Estimation Reports that cover Punjab, split at the Shivalik front: the Upper Indo-Ganga Plains subzone 1(e) report, approved at the 40th meeting of the Planning and Co-ordination Committee on 23–24 July 1984, whose design-office report number is not on the scanned copy read for this Manual [TBC], which "covers almost entire Haryana and Punjab" and here covers the plains and the Kandi piedmont, with Rupnagar on its boundary; and the Western Himalayas zone 7 report (No. WH/22/1994, November 1994), which names "parts of Punjab" and here covers Pathankot, Dhar Kalan, Sujanpur, Talwara, Nangal, Anandpur Sahib and the Shivalik hills of Hoshiarpur, Nawanshahr, Rupnagar and SAS Nagar (see the References of Chapter 3); with the 1(e) areal reduction rows for areas above 50 km² and its 24-hour time-distribution fractions, the zone 7 areal reduction factors for areas above 300 km² and for 24 hours, a cleaner copy of the zone 7 Plates 9 and 10 at Pathankot, whose Plate 10 is misregistered on the copy read, the loss rate of the zone 7 worked example, printed as 0.20 cm/h against the 0.5 cm/h the report recommends, and the boundary between the two reports at Dera Baba Nanak, Gurdaspur, Mukerian, Hoshiarpur, Anandpur Sahib and Rupnagar, read by eye from Plate 9 of the 1(e) report and still to be confirmed on the index maps of both reports [TBC], transcribed and checked against the published reports, and a catchment with physiographic parameters measured from survey or a DEM. Until it is published, take all SUH inputs directly from the applicable Flood Estimation Report (Clause 3.11.4(a)), apply the 24-hour design rainfall of Clauses 2.3.3(b) and 2.7.3 with the climate factor of Clause 2.8 (Clause 3.11.4(b)), report the SUH result alongside the HEC-HMS or SWMM result for the existing natural condition (Clause 3.11.4(c)), and, where the hydrograph model gives a lower 1% AEP peak, either justify it by calibration under Clause 3.15 or adopt the SUH peak (Clause 3.11.4(d)).

Table 3E.1 — SUH relationships by subzone (layout)

Parameter Symbol Unit Subzone 1(e) (Upper Indo-Ganga Plains) relationship Zone 7 (Western Himalayas) relationship
Peak discharge per unit area qp m³/s per km² qp = 2.030 (L/√S)^−0.649 qp = 1.048 tp^−0.178
Time from centre of unit rainfall to peak tp h tp = 1.858 qp^−1.038 tp = 2.498 (L·Lc/S)^0.156 (printed with S, not √S; see the note)
Width of UH at 50% of peak W50 h W50 = 2.217 qp^−0.990 W50 = 1.954 (L·Lc/S)^0.099
Width of UH at 75% of peak W75 h W75 = 1.477 qp^−0.876 W75 = 0.972 (L·Lc/S)^0.124
Width of rising limb at 50% of peak WR50 h WR50 = 0.812 qp^−0.907 WR50 = 0.189 W50^1.769
Width of rising limb at 75% of peak WR75 h WR75 = 0.606 qp^−0.791 WR75 = 0.419 W75^1.246
Base width of UH TB h TB = 7.744 tp^0.779 TB = 7.845 tp^0.453
Unit duration tr h 2 1
Design storm duration TD h TD = 1.1 tp, limited to 24 h TD = 1.1 tp (it gave the highest peak on all the gauged catchments)
Design loss rate — mm/h 3.0 (printed "3.0 mm per hour" and, in the worked example, 0.3 cm/h) 5 (printed "0.5 cm/hr"; "Designers can modify this value as per local conditions"); the worked example uses 0.20 cm/h "as recommended in para 3.5", which conflicts with para 3.5 [TBC]
Design base flow — m³/s per km² 0.05 (the average of 126 flood events in the range 0.01–0.09) 0.05 (27 of 45 events in the range 0.00–0.10)
Ratio of t-hour to 24-hour rainfall — — 50-yr: 1 h 0.340; 2 h 0.475; 3 h 0.560; 4 h 0.607; 5 h 0.647; 6 h 0.680; 9 h 0.770; 12 h 0.840; 15 h 0.890; 18 h 0.930; 24 h 1.000 10-yr, partial duration: 1 h 0.425; 3 h 0.600; 6 h 0.725; 9 h 0.790; 12 h 0.845; 15 h 0.895; 18 h 0.935; 24 h 1.000
Time distribution of rainfall — cumulative fraction Average curves of Fig. 12; the worked 12-hour storm puts 58% of the total in the first 2 hours, 74% by 4 hours, 86% by 6 hours, 92% by 8 hours and 95% by 10 hours; the 24-hour fractions were not transcribed [TBC] 3-h storm 0.73, 0.92, 1.00; 6-h storm 0.52, 0.69, 0.82, 0.91, 0.97, 1.00; 12-h storm 0.34, 0.49, 0.60, 0.67, 0.74, 0.81, 0.86, 0.90, 0.94, 0.96, 0.98, 1.00; 24-h storm 0.17, 0.27, 0.36, 0.43, 0.48, 0.53, 0.58, 0.63, 0.67, 0.70, 0.73, 0.76, 0.79, 0.82, 0.84, 0.86, 0.88, 0.90, 0.92, 0.94, 0.96, 0.98, 0.99, 1.00
Conversion of 1-day to 24-hour rainfall — factor 1.15 1.15
Areal reduction factor ARF — Table 6 of the report; at 50 km², 1 h 0.88, 3 h 0.92, 6 h 0.95, 12 h 0.96, 24 h 0.98, read by optical character recognition only, and the rows for larger areas incomplete in the reading [TBC]; the worked example uses 0.765 for 12 hours at 1,126 km² Annex 4.2: 50 km², 0.940 at 1 h, 0.964 at 3 h, 0.977 at 6 h, 0.9825 at 12 h; 100 km², 0.890, 0.929, 0.954, 0.965; 200 km², 0.8075, 0.862, 0.898, 0.935; 300 km², 0.7425, 0.800, 0.862, 0.905; the 24-hour column and the rows above 300 km² not read [TBC]
50-yr 24-hour point rainfall at Punjab towns (100-yr in brackets) — mm Plate 9 (Plate 10), read by eye within about one contour (interval 40 mm): SAS Nagar, Kharar and Zirakpur about 255–262 (280–289), beside the Chandigarh spot values of 262 (289); Hoshiarpur about 263, a spot value (280–292); Rupnagar, on the line, 240–260 (about 280); Ludhiana 240–255 (240–280), in a central cell of 240; Patiala and Rajpura about 240 (about 260); Gurdaspur, Batala and Kapurthala 240–260 (240–292); Amritsar and Tarn Taran about 220, between 200 and 240 (about 240); Sangrur and Sunam 220–240 (about 240); Ferozepur about 220 (about 240); Moga 200–240, of low confidence; Jalandhar about 200, inside a closed low loop of 180–220 (220–240, of low confidence); Fazilka and Sri Muktsar Sahib 160–180 (180–200); Bathinda and Abohar 150–160, inside a closed 160 cell with a spot value of 148 (about 180); Mansa 160–200 (180–200, of low confidence). Inside a closed low the value is the enclosing contour, never lower (Clause 2.3.6(c)). Bridge numbers printed beside crosses on the plates are not rainfall values Plate 9 (Plate 10), read by eye: Pathankot and Dhar Kalan about 320, on a poorly registered plate (320 or more on Plate 10, which is offset by about 0.1–0.2° on the copy read and is not used) [TBC]; Nangal and Anandpur Sahib about 280; the zone 7 plate gives about 280–320 at Hoshiarpur, which lies in 1(e) and uses it only as a sensitivity check (Clause 2.3.6(b))
Gauged catchments in Punjab — — Table 1 of the report, considered for the regression: the White Bein at bridge 20 on the Amritsar–Ludhiana line (2,426 km²; 1962, 1966, 1976–78); the Sunam Choe at bridge 181 on the Dhuri–Jakhal line (912 km²; 1963–66); the Patti Nalla at bridge 99(I) on the Jullundur–Amritsar line (297 km²; 1968–71); the Siswan at bridge 93(II) (141 km²; 1967–71) and the Sughrao at bridge 104(II) (105 km²; 1962–65), both on the Sirhind–Nangal Dam line and both Shivalik-foothill choes; and the Ghaggar at road bridge No. 2 on the border reach (1,126 km²; 1981–83), the worked example. Other Punjab bridge catchments in the table, among them the Kasur Nalla (743 km²), the Sareta drain, the Dhanaula drain, the Rahi–Beas, the Jassowal drain, the Nasrala and Kingerwala choes, the Dagru drain, the Kail Nala, the Budki Nadi and the Mudki drain, are listed but were not used, with remarks such as "floods unsuitable for U.G. analysis", "no floods" and "inadequate data" 2 of the 6 used: the Chakki Khad at bridge 232 on the Jalandhar–Pathankot line (657.86 km²; L 51.49 km, Lc 24.13 km, S 9.90 m/km; 1963–67), whose bridge is at Pathankot and whose catchment lies mainly in Kangra and Chamba in Himachal Pradesh; and a tributary printed as "Jhalum (Tri.)" at bridge 154 on the Sirhind–Nangal Dam line (43.82 km²; L 13.10 km, Lc 7.50 km, S 13.85 m/km; 1962–67)
Catchment area for which the relationships apply A km² 25–2,500, for "reasonably free catchments" with interception of not more than 20%; for "foothill catchments (steep slopes)" a "suitable increase" is to be given, by an amount the report does not state 25–1,000; not in snow-fed catchments
Report reference — — §3.9 (p. 42), §§3.11–3.12 (p. 57), text table (p. 61), Fig. 12, Table 1, Table 6, §§6.1–6.3, Plates 9 and 10 §§3.3–3.6, Annexes 3.1 and 3.2, §4.4.2, Annexes 4.1 to 4.4, worked example, Plates 9 and 10

Note: relationships as printed in the two CWC reports that cover Punjab (References of Chapter 3), read from scanned copies and checked against the page images except where marked. L is the length of the main stream in km, Lc the length to the point nearest the catchment centroid in km, S the equivalent slope in m/km and A the catchment area in km². Subzone 1(e) relates the peak to L/√S and derives tp from qp; zone 7 relates tp to L·Lc/S, printed without the square root that most subzone reports use, and the printed equations reproduce the report's own unit hydrograph only in that form. Each column shall be used only in its own area. Where each report applies. Subzone 1(e) "covers almost entire Haryana and Punjab" and notes that "The plains in the Punjab State are flat with the exception of Hoshiarpur tract where the general elevation varies between 300 m to 400 m"; the zone 7 report names "parts of Punjab" among the States it covers, drew on rain-gauge data from five Punjab districts and self-recording gauges in three, and marks Gurdaspur, Hoshiarpur and Rupar as "partly outside" the zone and Jullundar and Patiala as "fully outside". On Plate 9 of the 1(e) report, by NEER's reading within about 5–10 km, the boundary of zone 7 leaves the international border at Dera Baba Nanak, passes about 15 km north of Gurdaspur and north of Mukerian and Dasuya, about 0.25° north-east of Hoshiarpur and along the Shivalik front past Garhshankar and Balachaur, which are on the 1(e) side, then between Anandpur Sahib and Nangal, on the zone 7 side, and Rupnagar, which is on the line, and north-east of Chandigarh, keeping SAS Nagar, Kharar and Zirakpur in 1(e); Fazilka and Abohar are just inside 1(e), at most a sliver of the far south-west could fall in subzone 1(a), and subzone 1(f) does not reach the State [TBC]. Rupnagar reads both reports and takes the higher result, and a Kandi choe of 25 km² or more that rises in the Shivaliks is run with zone 7 as a sensitivity check (Clause 2.3.6(b)). Subzone 1(e). The report was derived from 23 gauged catchments (137 bridge-years), none urban. Its own worked example is the Ghaggar at road bridge No. 2 (30°24′ N, 76°44′ E), on the river's border reach near Ambala, below its course past Panchkula, SAS Nagar and Dera Bassi (by NEER's reading of the printed coordinates), 1,126 km² of "moderate steep slope", with L = 81.42 km, S = 5.14 m/km and L/√S = 35.91. The relationships give qp = 0.199 m³/s per km² and tp = 9.98 h, against the report's 0.198 and 10 h; TD = 1.1 tp = 11 h, rounded to 12 h; the 50-yr 24-hour point rainfall of 25.0 cm (Plate 9) × 0.84 (12-hour ratio) × 0.765 (areal reduction at 1,126 km²) = 16.06 cm; a loss of 0.3 cm/h and a base flow of 0.05 × 1,126 = 56.3 m³/s; and a 50-yr peak of 2,706 m³/s by the unit hydrograph, or 2,630 m³/s by the simplified formula, Q50 = K·A·R·S^0.324 / L^0.649 (K = 1.70 at 25 km² falling to 1.00 at 2,500 km², R the 50-yr TD-hour point rainfall in cm), both of which reproduce. That is about 2.40 m³/s per km², the yardstick for the Ghaggar as it enters Patiala and Sangrur districts. The five Punjab catchments of the regression were gauged for only 4–8 years each, and the two Shivalik-foothill choes among them, the Siswan and the Sughrao, for 4–5 years, so the relationships rest lightly on the Kandi. In Punjab they apply to the rural streams of 25–2,500 km² that enter the towns: the Ghaggar above Patiala and Sangrur; the White, Kali and Chitti Beins; the Sunam choe; the Patti, Kasur and Hudiara nallahs; and the Kandi choes that enter Hoshiarpur, Garhshankar, Kharar and SAS Nagar, with the "suitable increase" for foothill catchments, which the designer shall state and justify. The Sutlej, Beas and Ravi, whose catchments in the report run to 25,540, 5,859 and 4,667 km² (the Ravi to the Sakki Nala), are regulated by dams and headworks and are outside the relationships; the river levels they set are tailwater under Chapter 5. Zone 7. The report rests on six catchments of 44–658 km², with 2–5 years of record each in 1962–67 and 45 flood events, all near the southern edge of the zone: about 1% of it. Two of the six are Punjab bridges, the Chakki Khad at Pathankot and the tributary at bridge 154. For these the printed relationships give L·Lc/S = 125.5, tp ≈ 5.3 h, qp ≈ 0.78 m³/s per km², TB ≈ 17 h and TD ≈ 5.8 h for the Chakki Khad, and L·Lc/S = 7.09, tp ≈ 3.4 h, qp ≈ 0.84 m³/s per km², TB ≈ 14 h and TD ≈ 3.7 h for the tributary at bridge 154 (NEER's computation; yardsticks, not design values). The report itself warns that a design flood computed from these relations is not to be used "without verifying the results on the basis of alternate methods". Its worked example, the Banu Khad at bridge 629 in Himachal Pradesh, prints tp = 2.5 h where its equations give about 3.05 h, and applies a loss of 0.20 cm/h where para 3.5 recommends 0.5 cm/h; this Manual uses 0.5 cm/h and reads tp from the equations [TBC]. In Punjab the zone 7 relationships apply to the Chakki Khad and the other khads that enter Pathankot, and to the Swan and the Sutlej tributaries of 25–1,000 km² at Nangal and Anandpur Sahib. Both. Where a city catchment lies within the range, the SUH is computed only as the benchmark of its natural condition (Clause 3.11.4), and the city itself is designed by the methods of Clause 3.4. The design loss rates of 3.0 and 5 mm/h are φ-indices fitted to the monsoon floods of whole rural catchments; they are not the infiltration capacity of any soil and shall not be used to assign an HSG or to size an infiltration practice (Clause 3.7). The ratios are not to be used to derive intensities for durations shorter than the TD of the SUH without the short-storm floors of Clause 2.3.6(g): the 1(e) 1-hour ratio of 0.34 gives a 50-yr 1-hour depth of only about 82 mm at Patiala, where the recording gauge measured 93 mm in one hour on 21 July 1982, and the largest single-event ratios of the zone 7 report's Punjab recording gauges are 0.30 at Madhopur, 0.44 at Patiala and 0.59 at Hoshiarpur (NEER's arithmetic from Annex 4.4; at Madhopur and Patiala the largest hour and the largest day are different storms, so these are not event ratios in the strict sense).

Table 3E.2 — Worked example outline (layout)

Step Content Clause
1 Catchment area, main stream length, length to centroid and equivalent slope, from survey or DEM 3.11.4(a)
2 SUH parameters from Table 3E.1 and the plotted unit hydrograph 3.11.4(a)
3 Design storm duration, point and areal 24-hour rainfall with climate factor, time distribution 3.11.4(a), (b)
4 Effective rainfall after the design loss rate; convolution with the SUH; base flow added 3.11.4(a)
5 1% AEP peak compared with the HEC-HMS or SWMM peak for the existing natural condition 3.11.4(c), (d)

Form 3-1 — Hydrologic Calculation Summary

Supports Clauses 3.4, 3.6, 3.7, 3.8, 3.10–3.13, 3.15–3.17 of Chapter 3.

Draft form — Punjab Stormwater Design Manual, Draft v1.0. One form per submittal. Attach the documents listed in Section H.

A. Project

Table 3F.1 — Form 3-1: project

Field Entry
A1. Project name and applicant  
A2. Location (village or ward, survey numbers, district)  
A3. Site area (ha) and number of points of comparison (POCs)  
A4. Catchment class: standard (Clause 2.11.2) or flood-sensitive (Clause 2.11.3)  
A5. Design Rainfall Sheet reference (Form 2-1)  

B. Method and software (Clauses 3.4, 3.11, 3.12, 3.16)

Table 3F.2 — Form 3-1: method and software

Field Entry
B1. Purpose of each calculation (conveyance, storage, comparison, catchment study)  
B2. Contributing area for each purpose (ha or km²)  
B3. Method used and the row of Table 3.1 that permits it  
B4. Reason for the choice of method  
B5. Software and version; engine and version for packages built on SWMM or HEC (Clause 3.16.1, 3.16.2)  
B6. For other software: benchmark results of Annex 3C attached (Table 3C.7) and the 5% comparison of Clause 3.16.2  
B7. Runoff transform (Clause 3.11.1)  
B8. Computation interval Δt (h), with 0.133 Tc of the smallest sub-area and the hyetograph time step (Clause 3.11.3(a))  
B9. Storage routing and channel routing methods (Clauses 3.12.1, 3.12.2)  
B10. Dynamic-wave routing required? If yes, which condition of Clause 3.12.4  
B11. CWC SUH benchmark required (25–5,000 km², Clause 3.11.4)? Result reference  
B12. Continuous simulation required (Clause 3.13.1)? Record used and starting tank levels (Clause 3.13.5)  
B13. Calibration required (Clause 3.15.1)? Calibration report reference  

C. Soils and groundwater (Clauses 3.3.3(b), 3.7, 3.10)

Table 3F.3 — Form 3-1: soils and groundwater

Field Entry
C1. HSG source map, scale and lookup used (Clause 3.7.1, Annex 3A) or NEH Part 630, Ch. 7 assignment (Clause 3.7.2)  
C2. Infiltration tests: number, locations, depths, results (Clause 3.7.3)  
C3. Seasonal high water table: depth below ground and source (Clause 3.10.2)  
C4. Areas within 0.6 m assigned HSG D (Clause 3.10.1)  
C5. Disturbed pervious areas and HSG downgrade applied (Clause 3.3.3(b))  

D. Parameters by sub-area and condition (Clauses 3.3, 3.5, 3.8, 3.9; Clause 3.17 item 4)

Table 3F.4 — Form 3-1: parameters by sub-area and condition

Sub-area Condition (pre / post) Area (ha) Impervious: roofs / paved / roads (ha) DCIA (ha) Disconnected (ha) HSG CN, AMC II CN, AMC III (pervious part) C and Cf (if Rational) Tc (min)
                     
                     
                     

E. Time of concentration worksheet (Clause 3.6)

One worksheet per sub-area and condition.

Table 3F.5 — Form 3-1: time of concentration worksheet

Segment Flow type Surface and n (Table 3.4) L (m) S (m/m) P2 (mm) V (m/s) Tt (min)
1 Sheet         —  
2 Shallow concentrated       —    
3 Channel or pipe       —    
Tc (not less than 10 min)  

E1. Is the post-development Tc shorter than the pre-development Tc? If not, explain (Clause 3.6.6): ______

F. Rainfall and losses (Clauses 3.8.4, 3.8.5, 3.11.5, 3.12, 3.3.5)

Table 3F.6 — Form 3-1: rainfall, losses and starting levels

Field Entry
F1. AEPs and durations run; climate factor applied (Chapter 2)  
F2. AMC used for each duration (Clause 3.8.4)  
F3. Ia ratio for design runs; Ia = 0.05S sensitivity run made (Clause 3.8.5)  
F4. Peak rate factor used; if lower than 484, the Annex 3D value and the land it applies to (Clause 3.11.5)  
F5. Starting water level of each tank or waterbody, and its basis (Clauses 3.12.5, 3.13.5)  
F6. Off-site run-on: land use assumed for conveyance and for the comparison (Clause 3.3.5)  
F7. Incidental storage counted? If yes, the authority's acceptance (Clause 3.12.3)  

G. Departures

Table 3F.7 — Form 3-1: departures from Chapter 3

No. Clause departed from Value used in place of the Chapter 3 value Justification
1      
2      

H. Attachments (Clause 3.17)

Table 3F.8 — Form 3-1: attachments

Item Attached (yes / no / not applicable) Reference
H1. Catchment maps, pre- and post-development, with sub-areas, Tc flow paths, POCs and off-site run-on    
H2. HSG map, water-table data and infiltration test results    
H3. Parameter tables (Section D) and Tc worksheets (Section E)    
H4. Design Rainfall Sheet (Form 2-1) and hyetographs    
H5. Hydrograph tables and plots; stage–storage and stage–discharge tables; routed outflows; peak water levels    
H6. Form 3-2 for each POC    
H7. Calibration report (Clause 3.15)    
H8. Native model input and output files (Clause 3.16.4)    

I. Statement by the responsible engineer (Clause 3.17 item 10)

I state that the methods and parameters of Chapter 3 of the Punjab Stormwater Design Manual (Draft v1.0) have been used in this submittal, and that every departure is listed and justified in Section G.

Table 3F.9 — Form 3-1: statement by the responsible engineer

Field Entry
Name  
Qualification and registration number  
Organisation  
Signature  
Date  

Draft form — Punjab Stormwater Design Manual, Draft v1.0.


Form 3-2 — Pre- vs Post-Development Comparison

Supports Clauses 3.8.5, 3.11.5 and 3.14 of Chapter 3.

Draft form — Punjab Stormwater Design Manual, Draft v1.0. One form for each point of comparison (POC). Flows in m³/s, volumes in m³.

A. Point of comparison (Clause 3.14.2)

Table 3F.10 — Form 3-2: point of comparison

Field Entry
A1. POC identifier and location  
A2. Area draining to the POC: site (ha) and off-site run-on (ha)  
A3. Off-site run-on passes through site storage? (Clause 3.14.2(c))  
A4. Catchment class: standard (Clause 2.11.2) or flood-sensitive (Clause 2.11.3)  
A5. Tailwater applied, including joint cases of Clause 2.12 (Clause 3.14.9(c))  
A6. Flood-sensitive only: largest 10% AEP pre-development peak over all durations, the cap of Clause 2.11.3 (Clause 3.14.7)  
A7. Flood-sensitive only: 50% AEP pre-development peak at the pre-development critical duration (Clause 2.11.3)  

B. Peak flows (Clauses 3.14.7–3.14.10)

Limit: standard catchments 0.9 × Q_pre for the same AEP and duration (Clause 3.14.10(a)); flood-sensitive catchments the caps A6 (for 1% AEP) and A7 (for 50% AEP) (Clause 3.14.10(b)).

Table 3F.11 — Form 3-2: peak flows by AEP and duration

AEP Duration (h) AMC Q_pre Q_post, uncontrolled Q_post, routed Limit Met?
50% (2-yr) 1 II          
50% (2-yr) 2 II          
50% (2-yr) 3 II          
50% (2-yr) 6 II          
50% (2-yr) 12 III          
50% (2-yr) 24 III          
50% (2-yr) 48 III          
50% (2-yr) 72 III          
10% (10-yr) 1 II          
10% (10-yr) 2 II          
10% (10-yr) 3 II          
10% (10-yr) 6 II          
10% (10-yr) 12 III          
10% (10-yr) 24 III          
10% (10-yr) 48 III          
10% (10-yr) 72 III          
1% (100-yr) 1 II          
1% (100-yr) 2 II          
1% (100-yr) 3 II          
1% (100-yr) 6 II          
1% (100-yr) 12 III          
1% (100-yr) 24 III          
1% (100-yr) 48 III          
1% (100-yr) 72 III          

C. Volumes and storage (Clauses 3.14.8–3.14.10)

Table 3F.12 — Form 3-2: volumes and storage

AEP Governing duration (h) Runoff volume, pre Runoff volume, post uncontrolled Retention volume Detention storage required Peak water level in storage (m)
50% (2-yr)            
10% (10-yr)            
1% (100-yr)            

C1. Governing duration for storage, and the 24, 48 and 72 h results (Clause 3.14.10): ______

D. Sensitivity runs (Clauses 3.8.5, 3.14.11)

Table 3F.13 — Form 3-2: sensitivity runs

Run Governing storm (AEP, duration) Change in Q_post, routed (%) Change in required storage (%) Retention volume or WQv governing (Clause 3.8.5(c))
Ia = 0.05S        
Standard peak rate factor (only where a lower factor is used)       —

E. Associated checks (Clause 3.14.12)

Table 3F.14 — Form 3-2: associated checks

Check Result Reference in submittal
Drawdown times (Chapter 4)    
Minimum orifice and trash screen (Chapter 4)    
Emergency spillway (Chapter 4)    
Outfall-closed storage check (Chapter 5)    
Downstream analysis (Chapter 5)    

F. Statement by the responsible engineer

I state that this comparison has been made by the procedure of Clause 3.14, with the same design storms in the pre- and post-development runs, and that no runoff has been diverted from one natural catchment to another to meet the criterion (Clause 3.14.2(b)).

Table 3F.15 — Form 3-2: statement by the responsible engineer

Field Entry
Name  
Qualification and registration number  
Signature  
Date  

Draft form — Punjab Stormwater Design Manual, Draft v1.0.