Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Punjab the failure is one of missing criteria, and of conditions checked only for rainwater harvesting. No document of HUD, DTCP, DLG, PUDA, GMADA, GLADA, PWSSB, PMIDC or a Municipal Corporation stating a design return period for urban storm drains was found; the only urban figures on record are the 2-year choices of two projects (Clause 10.4, Commentary). The approval route shapes this chapter, and it runs through two instruments by territory. In the municipal areas of the Municipal Corporations, Municipal Councils and Nagar Panchayats, PMBBL 2018 (DLG notification No. CTP(LG)/2018/3548 of 22 November 2018, under s.201(1) of the Punjab Municipal Act 1911 and s.399(2) of the Punjab Municipal Corporation Act 1976) requires the plinth to be at least 450 mm above the surrounding ground and the building sited "that adequate drainage of the site is assured" (cl. 5.2.1.1), a complete rainwater harvesting proposal with the building plans of every plot of 100 m² or more (cl. 10.1), and inspection by a municipal Rainwater Harvesting Cell before a completion certificate or a service connection is given (cl. 10.6). Outside municipal limits, and in the urban estates and schemes of PUDA and the development authorities, PUDBR 2021 (HUD, G.S.R. 144 of 31 August 2021, under ss.180 and 43(2) of the PRTPD Act 1995) requires the plans to show "methods of disposal of waste water, sewerage and storm water" and the surroundings to 15 m (r.11), a rainwater harvesting design "prepared and certified by an Engineer dealing with civil work" (r.40), a certificate in Form H before drainage is brought into use (r.44(5)) and an application in Form L to connect to a public sewer (r.45), before the completion and occupation certificates (r.14 and r.23). In both instruments the open parking of group housing is to be of permeable materials, basements are to be built so that surface drainage does not enter them (PUDBR r.30(5)(iv)(e); PMBBL cl. 4.23(vii)), and the larger projects keep the inlet and outlet points of the natural drainage (PMBBL Table 15.1; PUDBR r.43, by reference to MoEFCC S.O. 3999(E)). Outside the building instruments, an obstruction within limits notified under s.38 of the Punjab Canal and Drainage Act 2023 needs WRD's permission, a notified drain may not be realigned "without prior permission/NOC" of WRD (OA 279/2024), and a rainwater harvesting scheme earns PWRDA's water-conservation credits only once PWRDA approves it (Directions 2023, cl. 2.7); a no-objection of WRD's drainage wing for projects within 150 m of a water body was announced by the Water Resources Minister on 20 September 2023 (as reported), but no order making it was found, and this Manual does not treat it as a rule. Village chhappars (ਛੱਪੜ; toba ਟੋਭਾ; ponds) are the common land of the Gram Panchayats, and no rule ties a building approval to them. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a setback from a drain, choe, river, canal or pond: PUDBR's setbacks run by building height only (r.26). Every stormwater item in this chapter is therefore written so that the architect or engineer on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the building plan, at the Form H and Form L stages and at the completion and occupation certificates. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Punjab Municipal Building Bye-Laws 2018 and the Punjab Urban Planning and Development Building Rules 2021 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the PMBBL/PUDBR steps a Punjab applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N, which contains the whole State, from 29°33′ to 32°32′ N and from 73°53′ to 76°56′ E), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of WRD's headworks and drain gauges and of BBMB's reservoir levels for Bhakra and Pong (published in feet, on gauge zeros to be confirmed [TBC], and converted at 0.3048 m per foot), of the Ranjit Sagar and Shahpur Kandi levels published in metres, and of the flood marks surveyed on ungauged choes, raos and drains used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Punjab has no notified design return period or design storm for its urban drains: no standard of PWSSB, PMIDC, PUDA, GMADA, GLADA, a Municipal Corporation or a Smart City company was found. Two project choices are on record. Amritsar Smart City Ltd's bid for the trunk storm sewers of the walled city (No. 07/ASCL/2018-19, November 2018) adopted "a return period of once in two years", a minimum time of concentration of 15 minutes and surcharge "inside the manhole … (without flooding)", and PMIDC's feasibility report for the Buddha Nallah (January 2020) designed the channel "considering 2 year return period with reduced run-off within the city reach due to active storm water detention"; neither states a design intensity or a design discharge in the sections read. WRD's own numbers serve other purposes: it zones floodplains on the 100-year flood computed by Gumbel's method, with the waterway by Lacey's formula (Chief Engineer Drainage to CWC, 2 May 2024), and it sizes rooftop rainwater harvesting on government buildings for 40 mm/h with runoff coefficients of 0.8–0.9 for roofs, 0.6–0.7 for paved and 0.1–0.2 for green areas, which is a recharge figure and not a drain design storm. Under AMRUT, Punjab did no storm-water drainage work up to September 2020, "due to shortage of funds and priority to cover water supply and sewerage" (CAG, Report No. 7 of 2021). These figures are history, not a design basis; the return periods of Table 2.1 apply instead. In IMD's national IDF study (Das et al. 2022) the only Punjab panel, Amritsar, repeats a generic curve and is not used, and no station IDF has been published for any Punjab station. The State's sub-daily design values are therefore those of the CWC Flood Estimation Reports for subzone 1(e) and zone 7, with the interim short-storm floors and the 24-hour record check of Clause 2.3.6, which raises the 24-hour depths near Ludhiana, Patiala, Amritsar and Bathinda well above the plates. Form 2-1 and Form 10-2 therefore carry the whole design basis of each submission. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Punjab calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or DLG:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by DLG and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the PMBBL/PUDBR registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the DLG list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the prior permission or no-objection of WRD for an outfall to, or a work on or across, one of its rivers, choes, drains, dhussi bandhs or regulators, among them the realignment of a notified drain (WRD report before the National Green Tribunal, OA 279/2024), or for an obstruction within limits notified under s.38 of the Punjab Canal and Drainage Act 2023, or under s.55 of the Northern India Canal and Drainage Act 1873 for a notification made before the 2023 Act came into force, such as the Patiala ki Rao in Kharar tehsil (2013) and the Sutlej floodplain zone in Ferozepur and Tarn Taran (2024), the written consent of WRD for any discharge to a canal, distributary or minor, the consent of BBMB for a work that drains to a reservoir or channel in its charge, the approval of PWRDA for a rainwater harvesting scheme that is to earn water-conservation credits (PWRDA Directions 2023, cl. 2.7), the permission needed under the Punjab Land Preservation (Chos) Act 1900 for clearing, quarrying or cultivation in an area regulated under its s.4 (the administering department to be confirmed [TBC]), the views of the Punjab State Wetlands Authority for a work in or next to a Ramsar site such as Harike, Kanjli, Ropar or Keshopur-Miani, the consent of the Gram Panchayat for a work that drains to, or encroaches on, a chhappar on its common land, the consent of PWD (B&R) or NHAI for a discharge to a drain or culvert of one of their roads, the consent of the body that owns the receiving drain where that body is not the Authority (for example GMADA, GLADA, PUDA or another development authority in its scheme), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 15 June each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Punjab because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 15 June date is set by this Manual to fall before the south-west monsoon (June–September), when most Punjab extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Punjab runs its monsoon season through the State Flood Control Board, chaired by the Chief Minister, which reviews drain cleaning and embankment works and in 2023 ordered flood-protection works and the cleaning of waterways finished by 30 June (as reported), and through district flood works under the Deputy Commissioners. The draft State Disaster Management Plan (c. 2011) says that streams "should be desilted properly before the onset of monsoons every year" but sets no date, and no current State plan or urban flood plan of PSDMA was found. On the rivers, choes and drains the works are WRD's: its Drainage Administration reports about 1,800 km of flood embankments, 3,800 river-training works and 7,200 km of drains; in 2025 it reported 601 of 850 drains cleaned over 4,766 km (as reported); and for the 2024 monsoon its SAS Nagar division listed 19 flood-protection works costing ₹1,091.40 lakh (public notice of 26 June 2024). For the town drains the orders found are local and dated by ministers and Deputy Commissioners: a target of 30 June 2026 for Ludhiana's sewers, 47% of 220 km being desilted by mid-June, and the same date in Kapurthala (as reported). The rivers are run by the dams and headworks: BBMB sets the releases from Bhakra and Pong, whose permissible levels are given as 1,680 ft and 1,390 ft (with higher "technical" limits also quoted), Harike's discharge above 3,00,000 cusecs is classed as "High Flood", and the gates of the Madhopur headworks failed on 27–28 August 2025 (all as reported). No operating rule for any regulator, sluice, flap gate or pumping station in a Punjab town, linking it to a river stage, a BBMB release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 15 June) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Punjab, the pre-monsoon inspection of regulators, sluices, flap gates on the outfalls through the dhussi bandhs, non-return valves, siphons and culverts under canals, choe crossings and pumped facilities, including the pumps at underpasses and in the depressions of the south-west, with the desilting of drains, choes and chhappars and the pump duty and gate seal tests, shall be completed by 15 June; these facilities, with their standby generators, shall be certified ready by 25 June, before the normal onset reaches Jalandhar (26 June) and Patti (28 June), with every gate on an outfall to a river or a WRD drain operated through its full travel. Pumps, their standby power and the gates shall then be kept on monsoon standby, with the monthly test run, until 15 October, and at an outfall to the Sutlej, the Beas, the Ravi or the Ghaggar until BBMB's releases from Bhakra and Pong have ended and the river at the governing WRD gauge has fallen below its danger mark, if that is later. In sub-area PB-A, and on every drain with an undeveloped Shivalik catchment, every public culvert, causeway, choe crossing, inlet and sediment trap shall be cleared a second time, of the sand, gravel and debris of the monsoon, by 31 October.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December with the south-west monsoon shaded from the normal onset at Jalandhar (26 June) and Ludhiana (1 July) to the normal withdrawal of 21 September, the withdrawal from most of Punjab by 1 October shaded more lightly, and the first half of October marked for late storms such as that of 4–5 October 1955. Thin bands mark paddy transplanting from 1 to 9 June and the winter western disturbances from December to April. Lanes show routine inspections; desilting of drains, choes and chhappars with the pre-monsoon inspection and the Form 10-7 declaration by 15 June; regulators, flap gates on dhussi-bandh outfalls, pumps, siphon crossings and choe crossings certified ready by 25 June; pumps and gates on standby to 15 October; a post-monsoon clearance of sand and debris from choe crossings, culverts and inlets in sub-area PB-A by 31 October; inspections after heavy rainfall; and Authority inspections. A dotted line marks the customary 30 June target, which falls after the onset at Jalandhar and is not used. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) South-west monsoon Onset ▸ 4–5 Oct 1955 Winter western disturbances (Dec–Apr) ◂ Paddy transplanting 1–9 Jun Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 15 Jun 25 Jun 15 Oct 31 Oct 30 Jun: customary target, later than onset at Jalandhar; not used Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 15 Jun: desilting of drains, choes and chhappars; pump and gate tests. By 25 Jun: regulators, flap gates on dhussi-bandh outfalls, pumps, siphon and choe crossings ready. To 15 Oct: standby. PB-A: sand and debris cleared from choe crossings by 31 Oct After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including October and winter storms) Annual declaration Form 10-7 Form 10-7 lodged by 15 June: Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one monsoon to 15 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 15 June, 25 June, 15 October and 31 October are fixed, all set by this Manual (no State order fixes a date). Normal onset 26 June (Jalandhar), 28 June (Patti), 1 July (Ludhiana); normal withdrawal 21 September; out of most of Punjab by 1 October (IMD, new normals). Late storms follow the withdrawal (354.3 mm at Ludhiana, 4 October 1955; IMD); winter western disturbances bring heavy falls from December to April.

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 15 June) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 15 June deadline is set by this Manual for the onset of the south-west monsoon in the last days of June: under IMD's new normals the monsoon reaches Jalandhar on 26 June, Patti on 28 June and Ludhiana on 1 July (Pai et al., IMD, 2020), so the onset lies inside the calendar season of June–September rather than at its start, and heavy falls come before it, such as 160.6 mm at Patiala on 8 June 2000 (IMD). The plains are wetted before the monsoon too, because paddy is transplanted from 1, 5 or 9 June by district under the Punjab Preservation of Subsoil Water Act 2009 (2025 schedule, as reported). No State order fixing a date for drain cleaning was found: ministers and Deputy Commissioners set 30 June in most years, as for the flood works of the State Flood Control Board in 2023 and the sewer desilting of Ludhiana and the drain cleaning of Kapurthala in 2026, and WRD's desilting of river sites missed a 30 June deadline in 2026 and was extended to 30 September (all as reported). 30 June falls after the normal onset at Jalandhar and Patti, so this Manual does not use it and takes 15 June for the desilting of drains, choes and chhappars, the pre-monsoon inspection, the annual declaration and the BSMP report. NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 15 June so that dry-season work can be finished. Regulators, flap gates on the outfalls through the dhussi bandhs, pumps, siphon crossings, inlets and choe crossings must in addition be certified ready by 25 June, before the onset reaches Jalandhar. The normal withdrawal is 21 September at all three stations, and "By 1st October, monsoon withdraws from most areas of … Punjab" (IMD), but the storm of record came after it, on 4–5 October 1955, with 354.3 mm at Ludhiana (IMD), as did the September storms of 1950, 1958, 1962, 1988 and 1995, and BBMB's reservoirs were still spilling in late August and September of 2023 and 2025 (as reported); pumps and gates are therefore kept on standby to 15 October (Figure 10.3), and at an outfall to the Sutlej, the Beas, the Ravi or the Ghaggar until the releases have ended. The choes of the Kandi leave "thick deposits of sand and silt" (District Environment Plan, Hoshiarpur), so in sub-area PB-A culverts, causeways, inlets and choe crossings are cleared of sand and debris a second time, by 31 October. Western disturbances bring large falls in winter and before the monsoon, 119.6 mm at Ludhiana on 4 January 1911, 115.0 mm there on 9 December 1997 and 144.2 mm at Patiala on 16 April 1983 (IMD), and the post-event inspections of Table 10.3 cover storms at any time of year. The reporting year of Forms 10-7 and 11-1 runs from 1 June to 31 May, so that each report covers one monsoon and the dry-season works after it (set by this Manual). All these dates are this Manual's; none is a State order.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Punjab cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 15 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Punjab drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Punjab Municipal Building Bye-Laws 2018 and the Punjab Urban Planning and Development Building Rules 2021 are made and from the municipal Acts. The graduated steps are set by this Manual. In Punjab the courts have become the working regulators of choes, ponds, floodplains and drains. The Punjab and Haryana High Court directed the clearing and demarcation of the Patiala ki Rao (Shamsher Singh v. State of Punjab, CWP 5901/2017, 2 June 2017), and its Local Commissioner found the Punjab portion "heavily encroached" and the pillars marking a width of "200 Ft." still pending on the Punjab side in January 2024, though fixed in Chandigarh; contempt proceedings are pending (COCP 1105/2023), and an embankment along the same rao is sought in Ram Lal v. State of Punjab (CWP-PIL 79/2025). The High Court ordered encroachments on village ponds removed within six months and PPCB to monitor their water (suo motu, 2020, as reported), after the Supreme Court held village commons protected (Jagpal Singh v. State of Punjab, 28 January 2011, as reported). The National Green Tribunal found "no material … indicating the exercise for demarcating the flood plain zone" of the Sutlej in Ferozepur and Tarn Taran (OA 303/2023, order of 14 March 2024, as quoted), has heard that a road built by MC Ludhiana cut the width of the Buddha Nallah "from 58 feet to 35 feet" (OA 327/2025), and has been told by WRD that no notified drain may be realigned without its permission (OA 279/2024). The statutes carry real powers: within limits notified under s.38 of the Punjab Canal and Drainage Act 2023 the Divisional Canal Officer may remove an obstruction (s.39) and no compensation is due for an illegal structure (s.45), and damaging, altering or building a drainage work, or altering the flow of a river or stream, is an offence punishable with a fine of ₹5,000 to ₹50,000 or imprisonment of up to six months (s.52); under PMBBL 2018 the municipal Rainwater Harvesting Cell inspects before a completion certificate or a service connection is given and verifies every building of more than 1,000 m² each year, with a 10% random survey below that (cl. 10.6); under PUDBR 2021 drainage may not be brought into use without the certificate in Form H (r.44(5)); and PWRDA may penalise the non-maintenance of a recharge structure with ₹10,000 to ₹1,00,000, by the size of the unit (Directions 2023). The enforcement sections of the Punjab Municipal Corporation Act 1976, the Punjab Municipal Act 1911 and the PRTPD Act 1995 were not read, and are to be confirmed [TBC]. CAG found that no storm-water drainage work had been done under AMRUT in Punjab up to September 2020 (Report No. 7 of 2021), and an excess release of ₹1.33 lakh of performance security on four works of the Municipal Council Amloh, two of them for "Laying storm water drain", which it called "record tampering and fraud" (Report No. 1 of 2026); no CAG audit of urban storm drainage, of WRD's drainage works or of flood control in Punjab was found. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river at the nearest gauge of WRD's headworks or of BBMB (for the Sutlej at Ropar, Harike or Hussainiwala; for the Ravi at Madhopur; for the Beas below Pong; for the Ghaggar at Bhankharpur, Sarala Kalan, Khanauri or Sardulgarh), or of the receiving WRD drain, and, where it is gauged, at the outfall, each with its gauge zero and a named datum, levels read in feet converted at 0.3048 m per foot, and never a CWC danger level; for an ungauged choe, rao or nallah, the flood marks surveyed after the event and the sand and debris deposited at crossings; the state of every regulator, sluice, flap gate, siphon or culvert under a canal and pumping station on the outfall and on the drain upstream of it, including those on the dhussi bandhs, with the hours each pump ran and any loss of power; any breach of a dhussi bandh or canal bank; and the releases from Bhakra, Pong, Ranjit Sagar and Shahpur Kandi and the gate operations at the headworks that set the receiving level;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), PSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Punjab's floods have been counted in figures that do not agree, and examined by the courts and the press rather than by technical reviews. On 4–5 October 1955, after the monsoon's normal withdrawal, a single storm put 300–500 mm in a day on many stations of Majha, Doaba and central Malwa, 354.3 mm at Ludhiana (IMD), and the draft State Disaster Management Plan records 6,27,000 houses damaged that year. Ludhiana PAU recorded 338.0 mm and Kapurthala 284.2 mm on 24 September 1988, and Patiala 356.5 mm on 11 July 1993 (IMD); the area flooded in those years is given as 9,221.2 and 9,757.4 km² in the press, quoting official data, but as 741 and 7,977 km² in the table of the draft State plan, figures that conflict. On 8–10 July 2023 Ropar recorded 35 cm in the 24 hours to 08:30 on 10 July (IMD press release), and the Ghaggar rose to 754.2 ft at Khanauri against a danger mark given as 748 ft, with 752 and 753 ft also reported, and breached in Sangrur and Mansa (as reported); the State reported 41 deaths in July (as reported), while the Union's provisional figure for all the year's hydro-meteorological events is 77 (MHA). In August–September 2025 the Ravi, the Beas, the Sutlej and the Ghaggar flooded together, Harike passed 3,35,030 cusecs on 3 September, the Madhopur gates failed, dhussi bandhs breached in Ajnala and Ramdass, and SAS Nagar, Ludhiana, Jalandhar and Amritsar flooded on 1–3 September (all as reported); the deaths are given as 56 (State bulletin of 16 September 2025, as reported), 40 (Rajya Sabha reply of 3 December 2025, as reported) and 28 (MHA, provisional). The station falls of August–September 2025, the deaths and area of 1955 and the official figures for 2019 were not found. No technical review of any of these events, no post-disaster needs assessment for 2023 or 2025, and no record of flood extents, depths or durations kept by any Municipal Corporation or development authority was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Punjab's drainage records are public: PUDBR 2021 with its corrigendum and 2022 amendment (in PPCB's circular copy), PMBBL 2018 and its 2019 amendment (in archived copies of the DLG website), the Punjab Canal and Drainage Act 2023 and the Punjab Water Resources (Management and Regulation) Act 2020 (in PRS copies), the PWRDA Directions 2023, the replies and reports that WRD, HUD, PPCB, CPCB and the local bodies have filed before the National Green Tribunal, CAG's Reports No. 7 of 2021 and No. 1 of 2026, the draft State Disaster Management Plan, WRD's archived Drainage Administration and Kandi Area Development pages, PMIDC's feasibility report for the Buddha Nallah, Amritsar Smart City's bid for its walled-city storm sewers, GMADA's impact study for the storm-sewer road of Sectors 92 and 92-Alpha, the Jalandhar master plan report and CGWB's groundwater assessments. Much else could not be found in the public domain: the notification bringing the 2023 Act into force and any rules under it; the list of notified drains (393 of 869 by WRD's page, 514 of 935 by a press report) and the text, with widths, of any notification under s.38 or s.55; any order on the 150 m drainage-wing no-objection announced in 2023; any urban drain design standard of PWSSB, PMIDC, PUDA, GMADA or GLADA; GMADA's "City Drainage Plan"; the drainage chapters of the Ludhiana and other master plans; the gauge zeros, danger marks and rating curves of WRD's gauges; the operating rules of the headworks and of the town gates and pumps; an inventory of the regulators, sluices, flap gates and pumping stations of any town; a current State Disaster Management Plan; any wetland notified under the Wetlands Rules 2017; and the texts of the Punjab Municipal Corporation Act 1976, the Punjab Municipal Act 1911 and the PRTPD Act 1995 as applied to drains, which were not read. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)