Chapter 4Site Runoff Control: Retention and Detention
4.1 Purpose and scope
4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:
- (a) the order in which runoff-control measures are to be applied (Clause 4.3);
- (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
- (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
- (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
- (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
- (f) regional detention and fee-in-lieu (Clause 4.13);
- (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
- (h) public safety (Clause 4.15).
4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (a complete rainwater harvesting proposal with the building plans for every plot of 100 m² or more, and for group housing, public, commercial and industrial buildings of every size, in municipal areas under PMBBL 2018 (as amended), cl. 10.1 and Table 10.1, with recharge for plots of more than 500 m² (cl. 10.5); and rainwater harvesting for residential plotted and public or institutional buildings above 250 m², for commercial, mixed-use and industrial buildings above 100 m² and for group housing of every size, outside municipal limits and in development-authority schemes, under PUDBR 2021 (as amended), r.40; the rules are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.
4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.
4.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Retention | Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall. |
| Retention depth | The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E). |
| Required retention volume (RRV) | The runoff volume from the retention depth over the post-development site (Clause 4.4.2). |
| Detention | Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5. |
| Retention credit | The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume. |
| Permissible site discharge (PSD) | The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha. |
| Site storage requirement (SSR) | The detention storage required per hectare of site under the simplified method of Clause 4.14. |
| Multi-stage outlet | An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2). |
| Drawdown time | Time from the peak stored volume until the stated fraction of that volume has been released. |
| Emergency spillway | A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment. |
| Freeboard | Vertical distance between the maximum design water level and the embankment crest or other critical level. |
| Flood-sensitive catchment | A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4. |
| Authority | The approving authority under Chapter 1 (the Municipal Corporation, Municipal Council or Nagar Panchayat that sanctions building plans under PMBBL 2018 within its municipal limits; PUDA, GMADA, GLADA or the other development authority in its urban estates and schemes under PUDBR 2021; and the competent authority under PUDBR 2021 elsewhere outside municipal limits, whose definition in the Rules was not read [TBC], as applicable). |
| Tier A / Tier B | Adoption tiers defined in Chapter 1. Tier A: the Municipal Corporation Ludhiana (MC Ludhiana), with GLADA and every other approving authority within GLADA's area; the Municipal Corporation SAS Nagar (Mohali), with GMADA and every other approving authority within GMADA's area, among them the local bodies of Zirakpur and Kharar and the authority for New Chandigarh; every other Municipal Corporation constituted under the Punjab Municipal Corporation Act 1976, among them those of Amritsar, Jalandhar and Patiala (13 at March 2023 by the CAG, with Barnala reported as the fourteenth; list [TBC]), with every other approving authority within its limits; and, wherever they lie, PUDA and the development authorities in their urban estates and schemes. Tier B: Municipal Councils and Nagar Panchayats. |
4.3 Order of measures
4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:
- Preserve. Keep existing waterbodies, chhappars, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
- Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
- Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
- Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).
4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.
Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.
4.4 Retention
4.4.1 Requirement
The site shall retain the RRV. Retention shall be achieved by one or more of the following:
- infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
- rainwater reuse that is drawn down by a demonstrated non-potable demand;
- green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.
The limits of Clause 4.4.4 apply.
4.4.2 Computation of the RRV
RRV (m³) = 10 × Q_R × A
where:
- Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
- A (ha) is the area of the site that drains to the outfall.
Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.
The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.
Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.
4.4.3 Verification
Retention by infiltration shall be supported by:
- (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
- (b) a design infiltration rate of no more than half of the measured rate; and
- (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).
Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.
Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.
4.4.4 Limits on retention
4.4.4.1 Infiltration practices shall not be used:
- where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
- on contaminated land;
- within the setbacks from foundations, wells and septic systems set in Chapter 8; or
- on fill, unless tested after placement.
4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.
4.4.5 Drawdown of retention
Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.
4.4.6 Retention credit: definition and computation
4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.
4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:
- (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
- (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
- (c) once it is full, route its overflow to the detention facility; and
- (d) size the detention for the residual hydrograph.
The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.
4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:
V_credit = C_R × RRV_provided
where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.
4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.
Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Punjab, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.
The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).
This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).
4.4.7 Preservation credit
Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:
- they are protected by a registered covenant or dedication; and
- their runoff is not concentrated onto impervious surfaces.
This lowers both the RRV and the detention required. No other preservation credit applies.
4.5 Release-rate criteria
4.5.1 General
4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.
4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.
4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.
4.5.2 Standard catchments
For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:
Q_post(T, d) ≤ 0.9 × Q_pre(T, d)
4.5.3 Flood-sensitive catchments
4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:
Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).
Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).
4.5.3.2 The flood-sensitive catchments are:
- (a) Ludhiana on the Buddha Nallah: the catchment of the Buddha Nallah and of the city drains that join it, through its city reach to its outfall to the Sutlej at Walipur Kalan;
- (b) SAS Nagar–Zirakpur–Kharar–Dera Bassi–New Chandigarh on the Shivalik choes: the land of those towns that drains to the choes and raos that come from the Shivaliks and from Chandigarh, among them the N-Choe, the Patiala ki Rao (Patiali-ki-Rao), the Sukhna Choe, the Jayanti Devi ki Rao and the Lakhnaur choe, and to the Ghaggar at Bhankharpur;
- (c) Patiala–Rajpura–Samana on the Nadis and the Ghaggar: the land of those towns that drains to the Badi and Chhoti Nadi of Patiala and to the Ghaggar, including the land held up behind the canal crossings of their drains;
- (d) the Ghaggar towns of Sangrur and Mansa: Moonak, Khanauri, Makraud Sahib and Sardulgarh, and the land that drains from them to the Ghaggar;
- (e) Jalandhar–Kapurthala–Phagwara on the Beins and the Sutlej: the land of those towns that drains to the Kali Bein, the Chitti Bein and the Kala Sanghian drain, and the land along the Sutlej at Phillaur and Shahkot;
- (f) Amritsar on the Tung Dhab–Hudiara outfall: the walled city and the land of the city that drains to the Tung Dhab drain and the City Outfall drain and through them to the Hudiara drain;
- (g) Pathankot–Gurdaspur–Dera Baba Nanak on the Ravi: the land of those towns that drains to the Ravi, the Chakki Khad and the other khads, including the land behind the dhussi bandh of the Ravi;
- (h) the Kandi towns of Hoshiarpur, Garhshankar, Mukerian and Talwara: the land of those towns that drains to the Kandi choes, and the land along the Beas below Pong;
- (i) Rupnagar–Nangal–Anandpur Sahib on the Sutlej and the Swan: the land of those towns that drains to the Sutlej below Bhakra and to the Swan;
- (j) Ferozepur and the Harike–Hussainiwala reach: the land of Ferozepur and of the towns along the Sutlej from Harike to Hussainiwala that drains to the river through outfalls in its dhussi bandhs;
- (k) the waterlogged south-west: Bathinda, Sri Muktsar Sahib, Fazilka, Abohar and Faridkot, and the land that drains from them to the WRD drains or to pumped outfalls; and
- (l) any catchment notified under Clause 4.5.4.
The boundaries shall be those mapped in Annex 4A.
4.5.4 Notification of further flood-sensitive catchments
4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:
- (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
- (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
- (c) an outfall that is closed by a flap gate or regulator in a dhussi bandh when the receiving river is high, as on the Sutlej at Rupnagar, Ludhiana, Phillaur, Shahkot and Ferozepur, the Beas at Mukerian and the Ravi at Dera Baba Nanak, that is held up by the Ghaggar in flood, as at Dera Bassi, Patiala, Samana, Moonak, Khanauri and Sardulgarh, that depends on pumping, as in the depressions of the waterlogged south-west, or that discharges to a WRD drain that runs full, such as the Buddha Nallah, the Tung Dhab and Hudiara drains or the Chitti Bein, for part of the SW monsoon (Chapter 5);
- (d) loss of more than a quarter of the mapped tank and chhappar storage in the catchment since the earliest available survey; or
- (e) a basin master plan that relies on limiting site discharge.
4.5.4.2 The procedure shall be:
- The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
- The State-level technical committee constituted under Chapter 1 reviews the note.
- The draft notification and map are published for public comment for at least 60 days.
- The Government notifies the catchment and the map is added to Annex 4A.
- The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.
4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.
Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The list of Clause 4.5.3.2 is this Manual's proposal; no Punjab body has named any of these catchments as flood-sensitive, and each entry follows the evidence below. The Ludhiana entry follows the Buddha Nallah, the State's largest urban drainage problem: a channel of 47.55 km that leaves the city for the Sutlej at Walipur Kalan, whose rehabilitation was designed "considering 2 year return period with reduced run-off within the city reach due to active storm water detention" (PMIDC, feasibility report, January 2020), with no design discharge found [TBC]; it carries about 700 MLD of treated and untreated wastewater (River Rejuvenation Committee, 28 October 2025, in the PPCB reply in NGT O.A. 413/2025), and a road built along it is alleged to have cut its width "from 58 feet to 35 feet" (NGT O.A. 327/2025). Ludhiana holds the State's storm of record, 354.3 mm on 4 October 1955, and recorded 286.8 mm on 5 September 1995, while Ludhiana PAU recorded 338.0 mm on 24 September 1988 (IMD, Extremes); flash floods were reported in Ludhiana, SAS Nagar, Jalandhar and Amritsar on 1–3 September 2025, with no depths recorded (as reported). The SAS Nagar entry follows the choes. They rise in the Shivaliks and in Chandigarh, where 302.2 mm fell in 24 hours on 9 July 2023 (IMD), and cross the sectors to the Ghaggar: Phase 11 of SAS Nagar floods when the Lakhnaur choe is not cleared (as reported); the villagers of Chappar Chiri Khurd and Landran told GMADA's social impact assessment for the storm sewer of sector roads 92 and 92-Alpha that "the village Abadi area is seven feet lower than the level of stream (Nadi)" (GMADA, 2021); a notification of 4 March 2013 under section 55 of the Northern India Canal and Drainage Act 1873 authorised WRD's Executive Engineer at Rupnagar to prevent any construction in the Patiala ki Rao or covering of it, yet the Punjab reach was "heavily encroached", and the pillars that the High Court's proceedings require to mark its 200-ft width were in place in Chandigarh but pending in Punjab in January 2024 (Local Commissioner's report of 8 January 2024 in CWP 5901/2017); and WRD lists the re-alignment and channelisation of the N-Choe over RD 4,943–8,128 m in IT City (Sector 101) among its projects, at ₹22.43 crore (WRD, Drainage Administration). The Ghaggar at Bhankharpur is reported with a "full capacity" of 70,000 cusecs, against a flow of about 1.22 lakh cusecs reported for July 2023 (as reported; the two figures conflict). The Patiala entry follows the storm of 11 July 1993, 356.5 mm at Patiala (IMD), and the Nadis, whose revamp of 8.3 km of the Badi Nadi and 4.9 km of the Chhoti Nadi at ₹208.33 crore was discussed in 2025 (as reported); the recording gauge at Patiala measured 93 mm in one hour on 21 July 1982 and 153 mm in three hours (CWC zone 7 report, Annex 4.4); breaches of the SYL canal and the Narwana branch flooded Rajpura in 2023, and the Hansi–Butana siphon on the Ghaggar is blamed for ponding at Samana (as reported). The Ghaggar entry for Sangrur and Mansa follows July 2023, when the river at Khanauri reached 753 ft on 13 July, "the highest-ever", and 754.2 ft on 15 July, against a danger mark reported as 748 ft (752 and 753 ft are also reported, and the gauge datum was not found [TBC]), and breached at Moonak, Khanauri, Banarasi, Makraud Sahib and Phullad and, in Mansa district, at Budhlada and Sardulgarh (as reported); the channel is reported as "588 ft wide from Khanauri to Makraud Sahib", narrowing to 190 ft from Makraud Sahib to Kadail (as reported), and in 1993 Mansa and Sangrur were flooded by "congested" drainage (as reported). The Jalandhar entry follows the Beins and the river. Only "about 5% of the city area is covered under the storm water network" and the rain "is largely discharged in to the sewer network" (Master Plan Jalandhar report, Vision 2031, 9.3); the same report puts the high flood level of the Chitti Bein at the Chaheru railway bridge at "generally 12'", with water spreading about 200 m, and proposes to widen the Bein from 40–60 ft to "atleast 80'-100'" (13.8.7); Kapurthala, 19 km from Jalandhar by NEER's reading, recorded 284.2 mm on 24 September 1988 (IMD); and in August 2019 the Sutlej breached the dhussi bundh at Shahkot (Janian and Janian Chahal), at Gidderpindi near Sultanpur Lodhi and at Mandala, flooding more than 150 villages in Kapurthala and Jalandhar districts (as reported). The Amritsar entry follows the walled city, 3.55 km² at 300–550 persons an acre, whose trunk storm sewers were designed for "a return period of once in two years", with a minimum time of concentration of 15 minutes and surcharge in the manholes "allowed (without flooding)", and whose road-side drains "are connected to the sewerage system typically at the road junctions, thus making the sewerage system as combined system" (Amritsar Smart City bid 07/ASCL/2018-19, 2018); the city drains by the Tung Dhab and City Outfall drains of WRD to the Hudiara drain, which runs into Pakistan, so its outfall level is set outside Indian control (same source; Chapter 5); Amritsar recorded 308.4 mm on 22 September 1962 (IMD). The Pathankot–Gurdaspur entry follows August 2025, when gates of the Madhopur headworks on the Ravi jammed on 27 August and one was washed away on 28 August, under a flow reported as "less than 2 lakh cusec", and the Ravi breached the dhussi bundh in the Ajnala–Ramdass area and submerged Kartarpur Sahib across the border (as reported); the recording gauge at Madhopur measured 100 mm in one hour on 16 September 1975 and 329 mm in 24 hours on 23–24 July 1974 (CWC zone 7 report, Annex 4.4). The Kandi entry follows the choes: Hoshiarpur district has "more than 100 choes", which "originate from Shivalik slopes and take shape of wide channels after entering the foothill plains" and leave "thick deposits of sand and silt" (Hoshiarpur District Environment Plan), and Garhshankar recorded 470.0 mm on 31 July 1976 (IMD, Climate of Punjab); below Pong, the reservoir took a record inflow of about 7.3 lakh cusecs on 14 August 2023 and stood at 1,399.65 ft on 15 August (as reported; the reservoir's full, permissible and technical levels are reported variously as 1,390, 1,394 and 1,410 ft). The Rupnagar entry follows July 2023, when Ropar recorded 35 cm in the 24 hours to 08:30 on 10 July and Nangal 28 cm in the 24 hours to 08:30 on 9 July (IMD press releases), the Ropar figure above the district's heaviest day of 310.4 mm in 1951 (IMD, Climate of Punjab), and the Ropar headworks passed about 1.79 lakh cusecs, against 2.4 lakh in 1988 (as reported); WRD lists flood-management works on the Swan, down to its confluence with the Sutlej near Anandpur Sahib, at ₹284.98 crore (WRD, Drainage Administration). The Ferozepur entry follows the river: at Harike "discharge above 3,00,000 cusecs falls under the High Flood category", and 3,35,030 cusecs passed it on 3 September 2025, with 3,02,508 cusecs at Hussainiwala (as reported); the Sutlej floodplain zone of Ferozepur and Tarn Taran districts, notified on 4 March 2024 on a 100-year flow of 5,34,441 cusecs, was declared as the land between the embankments, about 4.5 km apart (WRD affidavit in NGT O.A. 303/2023); and in the floods of 1988 Ferozepur was reported as the worst-hit district, with 2,054 km² flooded (as reported; the draft State Disaster Management Plan's table gives a much smaller area for that year, and the two are not reconciled). The south-west entry follows the water table and the outfalls: the shallowest wells in the State were at Abohar (0.79 m, June 2019) and Kot Bhai in Sri Muktsar Sahib district (0.53 m, October 2019) (CGWB and WRD, 2020); Bathinda's storm-water pumping stations are reported to be "connected to the existing sewer system" and its waterlogging is chronic (as reported); and the Bhatinda rain gauge recorded 256.1 mm on 18 August 1964 (IMD, Climate of Punjab). Moga, Barnala, Malerkotla, Batala, Khanna and Tarn Taran, and the towns on the Kali Bein at Sultanpur Lodhi, are candidates for notification under Clause 4.5.4. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.
4.5.5 Minimum outlet and short-duration 2-yr checks
4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.
4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:
- size the low-flow orifice as the smallest opening that meets Clause 4.7; and
- report the resulting 2-yr exceedance for those durations.
The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.
Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next SW monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).
4.5.6 Constrained redevelopment sites
4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:
- (a) the existing site is at least 60% impervious, as surveyed before demolition;
- (b) the site is 1 ha or less; and
- (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.
New development on undeveloped land is never eligible.
4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:
- (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
- (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
- (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).
4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:
- (a) paid into the ring-fenced account of the basin in which the site lies;
- (b) spent only on regional detention or on restoring chhappar or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
- (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.
Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with WRD agreement.
4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.
Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as the walled city of Amritsar, the old cores of Ludhiana, Jalandhar, Patiala and Bathinda, or the village abadis inside the sectors of SAS Nagar, there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.
4.6 Detention sizing procedure
4.6.1 Method
Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.
4.6.2 Steps
- Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
- Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
- Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
- Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 15 June to 30 September under paddy or other ponded fields in sub-areas PB-B to PB-F and on the bet lands of the Sutlej, Beas, Ravi and Ghaggar, from 1 July to 31 October in PB-F and the Sirowal belt where the October water table is within 3 m, and at other sites and times after a 5-day total of more than 53 mm, AMC II otherwise).
- Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
- Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
- Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
- Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
- Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
- Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
- Size the emergency spillway and set freeboard (Clause 4.9).
- Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).
4.6.3 Storms to be routed
Every facility shall be routed for the full matrix:
Table 4.1 — Design storms to be routed for detention sizing
| AEP | Durations (h) | AMC |
|---|---|---|
| 50% (2-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 10% (10-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 1% (100-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.
4.6.4 Initial conditions
Each run shall start with:
- detention storage empty, down to the invert of the lowest outlet;
- any permanent pool full;
- retention practices empty, except as limited by Clause 4.11; and
- RWH storage full (Clause 4.11).
The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.
4.6.5 Multi-stage outlet design
4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:
- Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
- Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
- Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
- Emergency spillway: separate from the primary outlet (Clause 4.9).
Stages may be combined where routing shows that every cap is met.
4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).
4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.
4.6.6 Tailwater on the outlet
The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:
- for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
- for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).
Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.
4.6.7 Illustrative example
Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a sector draining to a choe in SAS Nagar (Mohali). They are not NIH-DHAARA values and must not be used for design.
Inputs:
- Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
- Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
- Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
- 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
- Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
- Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
- Storage: vertical-walled, 2,500 m² plan area.
- Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
- Stage 1: 170 mm orifice at the invert.
- Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
- Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.
Results (discharges in L/s; storage in m³):
Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
| Duration (h) | 2-yr pre | 2-yr post, detained | 10-yr pre | 10-yr post, detained | 100-yr post, uncontrolled | 100-yr post, detained | 100-yr storage used | 10-yr drawdown, 50% blocked (h) |
|---|---|---|---|---|---|---|---|---|
| 1 | 4 | 15 | 51 | 28 | 922 | 42 | 1,426 | 31.3 |
| 2 | 14 | 20 | 84 | 34 | 961 | 79 | 1,911 | 32.1 |
| 3 | 19 | 22 | 104 | 37 | 981 | 139 | 1,999 | 32.8 |
| 6 | 32 | 25 | 150 | 41 | 1,010 | 194 | 2,154 | 34.2 |
| 12 | 127 | 30 | 302 | 46 | 1,074 | 276 | 2,512 | 39.0 |
| 24 | 149 | 32 | 327 | 49 | 1,081 | 320 | 2,766 | 45.3 |
| 48 | 173 | 34 | 349 | 82 | 1,087 | 343 | 2,913 | 44.8 |
| 72 | 180 | 34 | 356 | 84 | 1,089 | 343 | 2,911 | 44.7 |
How to read it:
- 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
- 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
- Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
- Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
- Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.
The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.
Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).
Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).
4.7 Drawdown
4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.
4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).
4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).
4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.
Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Punjab storage must hold multi-day volumes. It is still short enough that a basin filled by one SW monsoon depression will have most of its volume back before the next, which in July 2023 at Ropar (27 cm in the 24 hours to 08:30 on 9 July and 35 cm in the 24 hours to 08:30 on 10 July, IMD press releases) followed within days.
4.8 Outlet structures
4.8.1 General. Primary outlets shall be:
- unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
- accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
- built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).
4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.
4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:
- have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
- have a clear open area at least 10 times the area of the opening it protects;
- be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
- be removable or hinged for cleaning; and
- for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.
4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).
4.8.5 Outlet barrels. Outlet barrels through embankments shall:
- be at least 300 mm in diameter (Chapter 6);
- have watertight joints;
- have a filter diaphragm or seepage collars over the length within the embankment; and
- have an energy-dissipating outfall (Chapter 9).
4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.
Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.
Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).
4.9 Emergency spillway, freeboard and embankment safety
4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:
- with the primary outlet assumed fully blocked;
- with the facility full to the spillway crest at the start of the storm; and
- with at least 0.3 m freeboard from the maximum water level to the embankment crest.
4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:
- endanger life;
- flood a habitable building or critical facility; or
- close an arterial road.
High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.
4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.
4.9.4 Spillway location. The spillway shall be:
- on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
- discharging to the 1% AEP overland flow path of Chapter 6; and
- placed so that its flow does not reach a building.
4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.
4.9.6 Embankments.
- (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
- (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
- (c) Embankments shall have:
- a crest width of at least 3 m;
- compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
- no trees or large shrubs.
- (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.
4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.
Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.
4.10 Facility types
4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.
4.10.2 Underground tanks and vaults.
- (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
- (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
- (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
- (d) The tank shall be ventilated.
- (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
- (f) Flotation and groundwater ingress shall be checked under Clause 4.12.
4.10.3 Rooftop detention.
- (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
- (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
- (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.
4.10.4 Podium and landscape-deck detention.
- (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
- (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.
4.10.5 Parking-lot detention.
- (a) It is permitted only on surface parking. Ponding depth shall not exceed:
- 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
- zero on accessible routes, ramps and pedestrian crossings; and
- zero in the 10% AEP storm on fire-tender access routes.
- (b) Signs shall warn that the area floods.
- (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).
4.10.6 Multi-use detention (parks, playfields, open space reservation).
- (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
- (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
- (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
- (d) The depth and slope limits of Clause 4.15 apply.
- (e) Play equipment and seating shall be placed above the 10% AEP level.
4.10.7 Ponds and wet basins.
- (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
- (b) Only storage above the permanent pool counts as detention.
Commentary.
- The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
- The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
- Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
- Using open space for multi-use detention fits the building instruments. PMBBL 10.4 requires public open spaces of more than 500 m² to have "arrangements for complete utilization and capture of storm water", including "Artificial or natural Storage of storm water runoff from larger sites"; PMBBL 10.5 makes recharge mandatory for parks, parking, plazas and playgrounds; and for buildings of 5,000–20,000 m² of built-up area at least 20% of the recreational open space is to be unpaved (PMBBL 11.2.1(iv) and Table 15.1; PUDBR r.43). It also fits the recommendation of GMADA's social impact assessment for the storm sewer of sector roads 92 and 92-Alpha that the authority "not disturb the natural passage of 'Nadi' or allied tributaries" (GMADA, 2021). A detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires. Two kinds of land are not open space for this purpose. A chhappar (ਛੱਪੜ; toba ਟੋਭਾ; pond), toba or dhab on or beside the land is Panchayat common land (shamlat) under the Punjab Village Common Lands (Regulation) Act 1961, protected against encroachment by the Supreme Court in Jagpal Singh v. State of Punjab (2011) and by the High Court's order of 2020 to remove encroachments from village ponds (as reported); it is preserved under step 1 of Clause 4.3.1 and modelled as a water surface (Clause 3.3.2(e)) that starts at its overflow level (Clause 3.12.5), so only its flood storage above that level can count, only as Chapter 7 allows and only with the Gram Panchayat's consent. And land within the limits of a reach notified under section 38 of the Punjab Canal and Drainage Act 2023 (or section 55 of the 1873 Act), such as the Patiala ki Rao and its pillared 200-ft width, the Sutlej floodplain zone of Ferozepur and Tarn Taran, the bet land between a river and its dhussi bandh, and land in the hydraulic corridor of a drain, choe or water body under Chapter 7 are corridor or flood land already: water reaches them first, so they are not counted as detention for the development beside them (Chapter 7).
4.11 Rainwater harvesting versus detention accounting
4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.
4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.
4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:
- (a) the detention zone lies wholly above the RWH overflow level;
- (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
- (c) no pump, valve or user action can hold water in the detention zone; and
- (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.
Only the volume between the RWH overflow level and the detention overflow level counts as detention.
4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the SW monsoon season.
4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of Chapter X (cl. 10.1–10.6) and Table 10.1 of PMBBL 2018 (as amended) in municipal areas, r.40 of PUDBR 2021 (as amended) outside them and in development-authority schemes, the environmental conditions of PMBBL Chapter 15 and of PUDBR r.43 (MoEFCC S.O. 3999(E) of 9 December 2016), any condition of a building plan, completion certificate or occupation certificate, any direction of PWRDA under section 15(2)(ix) of the Punjab Water Resources (Management and Regulation) Act 2020, or any rainwater harvesting rule or direction of an approving authority.
Commentary. RWH in Punjab is required by two instruments, with different thresholds, and each number belongs to its instrument; there is no single "Punjab threshold". In municipal areas, "All buildings having a plot size of 100 sq.m. or more, while submitting the building plans for sanction, shall mandatorily include the complete proposal of rainwater harvesting" (PMBBL 2018 (as amended), cl. 10.1); Table 10.1 applies this to residential plots of 100 m² and above, with the emphasis on storage and reuse, and to group housing, public, commercial, mixed-use and industrial buildings of every plot size; public open spaces of more than 500 m² are to capture and use their storm water (cl. 10.4); recharge is to be mandatory for every building on a plot of more than 500 m² and for parks, parking, plazas and playgrounds (cl. 10.5); and each municipality is to constitute a Rainwater Harvesting Cell, inspect the structures "before issuing Completion Certificates or NOCs for service connections", verify every building above 1,000 m² each year and survey 10% of the smaller ones at random (cl. 10.6). The bye-laws add that rainwater "can be harvested to the extent of 55,000 liters per 100sq. meters area per year from rooftops" (cl. 10.1), about 550 mm a year by NEER's arithmetic, a description and not a sizing rule, and the amendment of 31 December 2019 makes buyers of additional FAR comply with "Rain Water Harvesting and requirements of National Building Code (NBC)-2016". Outside municipal limits and in the schemes of the development authorities, PUDBR 2021 (as amended), r.40 requires rainwater harvesting for residential plotted and for government, semi-government and institutional buildings "Above 250 sq.mt.", for commercial, mixed-use and industrial buildings "Above 100 Sq.mt.", and for group housing of "All plot sizes", with industrial units "not to inject contaminated water into recharge structures" and recharge structures kept away from sewer lines, septic tanks, soak pits and landfill; the design "shall be prepared and certified by an Engineer dealing with civil work". Earlier thresholds of 400 m² (a 2010 amendment of the PUDA rules) and 500 square yards (the 2013 rules) are reported (as reported), and a Lok Sabha reply quotes "above 200 sq. yds." for the municipal bye-laws (as quoted, [TBC]); none of them is current. Both instruments also say, for group housing, that "Concrete paving to be avoided and permeable materials are to be used [for] all open parking spaces", which is Punjab's only rule on permeable paving. Neither instrument sets a storage volume, a design storm, an infiltration test or a depth to the water table, so the RWH Cell's inspection and the engineer's certificate have no stated standard; the tests of Clauses 4.4.3 and 4.11.4 can supply one. WRD's own design for the recharge structures of government roofs uses 40 mm/h ("Hourly Rainfall Intensity is typically 25 to 30 mm/hr for Punjab and Haryana. For safer side we assumed it to be 40 mm/hr"), with one injection well and filter chamber "safe for a roof top area of 900 sqm" (WRD, rooftop rainwater harvesting proposal); that is a figure for sizing a recharge structure, not a design storm for a drain, and this Manual does not use it as one. PWRDA's Directions of 2023 make rainwater harvesting voluntary for the users they cover and reward it: a user with an approved scheme earns water-conservation credits, one for each cubic metre conserved, worth a rebate of ₹2.50 against the groundwater charges of ₹4–22/m³ (Directions 2.7, 4.6 and 4.7), and the Act empowers PWRDA to direct "water conservation and groundwater recharge, including rain water harvesting" (Punjab Water Resources (Management and Regulation) Act 2020, section 15(2)(ix)). A design under this chapter therefore states the recharge volume of each practice in m³ a year, so that the owner can use it in an application for credits; this is a link, not a mandate, and this Manual gives no credit of its own for it. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:
- An RWH storage tank or sump is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2). A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
- An RWH tank counts toward the retention requirement of Clause 4.4 only if it holds at least 20 litres for every square metre of the roof that drains to it, and then only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing or garden watering, demonstrated under Clause 4.4.3; it is then modelled under Clause 4.4.6 like any other retention practice. The 20 L/m² minimum, about 20 mm over the roof, is set by this Manual, because neither PMBBL nor PUDBR sets a volume; it follows the minimum capacity of 20 litres per square metre of roof-top area set for roof-top storage by the Himachal Pradesh Town and Country Planning Rules 2014 (Appendix 6), the nearest precedent found. Where recharge earns no credit (below), reuse is the practical way to earn retention.
- Recharge pits, trenches, shafts, wells and bores, including the recharge wells of PMBBL Table 10.1 and PUDBR r.40 and the recharge bores of the environmental conditions, count as retention only where they meet Clause 4.11.4: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, read from the October (post-monsoon) record (Clause 3.10.2), and the credit is found by routing under Clause 4.4.6, not by deducting their volume.
- Recharge depends on the ground, and Punjab has three kinds. The State draws far more groundwater than is recharged, at a stage of extraction of 156.87% in 2024, with 115 of its 153 assessment units over-exploited (CGWB, Dynamic Ground Water Resources of Punjab 2024), and the area where the water lay deeper than 10 m in June grew from 14.9% in 1989 to 68% in 2019; yet in the south-west the water was within 1.5 m of the surface at Abohar and Kot Bhai in 2019, and "Water logging conditions exist in some parts of south-western districts" (CGWB and WRD, 2020). The credit for recharge therefore follows the ground and the seasonal high (October) water table at the site, from Clause 3.10.2 or Clause 4.12.1, under three rules, all set by this Manual:
- (a) the Kandi recharge belt: recharge first, with sediment control. On the boulder–gravel fans and choe beds of sub-area PB-A, where "deep water levels are recorded in Kandi belt" (CGWB and WRD, 2020) and the stage of extraction is lower than in the central districts (Hoshiarpur 102%, Ropar 100% and Pathankot 53%, against 211% at Ludhiana and 301% at Sangrur, by district in GWRA-2020), retention shall be provided by recharge before reuse or detention wherever site infiltration tests allow, through pre-treatment, a silt trap ahead of every pit, shaft or well, and the 1.0 m separation above the October water table, and with the sand and silt of the choes kept out of every recharge structure by the sediment control of Chapter 8; the Kandi low dams and WRD's 410 check dams on rivers and nallahs are recharge structures of the same kind at basin scale (WRD reply in NGT O.A. 694/2023). On the Shivalik slopes themselves the hill infiltration rule below applies instead;
- (b) the central over-exploited plains: recharge encouraged, with quality protection. In sub-areas PB-B, PB-C, PB-D and PB-E, and in the parts of PB-F where the water table is deep, recharge is the default where the October water table is deeper than 10 m below ground, and earns credit with: first-flush diversion and a filter ahead of every structure; roof water only to an injection well, bore or shaft; road, parking, yard and industrial runoff only through a surface infiltration practice with a filter, such as a vegetated basin or trench, and never directly into a well, bore or shaft (following PUDBR r.40's "not to inject contaminated water into recharge structures"); no runoff from a drain that carries sewage; every recharge structure away from sewers, septic tanks, soak pits and landfill (PUDBR r.40), and outside the 30 m within which PUDBR r.45(7) keeps septic tanks and absorption pits from wells, sources and streams used for drinking; and a quality screen: where the groundwater at the site, from a sample or the nearest CGWB or WRD well, exceeds 30 ppb of uranium, 45 mg/L of nitrate, 1.5 mg/L of fluoride, 10 ppb of arsenic or an EC of 3,000 µS/cm, the limits used in GWRA-2024, recharge earns credit only after a check by a hydrogeologist that it will not spread the contaminant towards a drinking-water well. Uranium above 30 ppb was found in 32.6% of the samples of the 2024 assessment, nitrate above 45 mg/L in 12.58%, fluoride above 1.5 mg/L in 13.77%, arsenic above 10 ppb in 4.85% and EC above 3,000 µS/cm in 6.72% (CGWB, GWRA-2024), and the CGWB notes that "Groundwater at Shallow depth is largely contaminated caused by surface water pollution" (CGWB and WRD, 2020). Between 3 m and 10 m below ground, recharge earns credit only after a site check of the water table, by a piezometer read in October or by a hydrogeologist, shows that the practice will not raise the water table to within 3 m of the surface at the site or its neighbours, and that the groundwater below is not saline;
- (c) the south-west waterlogged belt, the Sirowal and the bet lands: no infiltration. In sub-area PB-F wherever the October water table is within 3 m of the surface, as in parts of Sri Muktsar Sahib, Fazilka, Faridkot, Bathinda and Ferozepur, in the Sirowal belt below the Kandi, and on bet land within the seasonal flood level of the Sutlej, Beas, Ravi or Ghaggar, the soil is HSG D for design (Clause 3.7.2), no recharge or infiltration practice earns retention credit whatever a test shows, and no soakaway, recharge pit, shaft or well, or permeable paving with an exfiltrating base, shall be built for the purposes of this chapter; RWH there is storage and reuse, saline groundwater (EC up to 8,320 µS/cm at Abohar; CGWB and WRD, 2020) is not a recharge target, and detention, conveyance and pumped outfalls carry the design, with the design groundwater level at ground level (Clause 4.12.1). Where PMBBL or PUDBR requires a recharge well on such a site, it is built as the instrument requires, lined above the water table and fed only with filtered roof water, but it is not counted. The maps are those of the CGWB and WRD for October, not June.
- Hill infiltration rule (Clause 4.11). No deliberate infiltration practice (soakaway, soak pit, recharge pit, shaft or well, infiltration trench, or permeable paving with an exfiltrating base) shall be built or credited on natural ground sloping more than 10° in the Shivalik hills of sub-area PB-A (the Pathankot–Dhar Kalan hills, the Mukerian–Dasuya, Hoshiarpur and Garhshankar Shivaliks, the Anandpur Sahib–Nangal Shivaliks and the Kharar–Mullanpur hills), or upslope of a cut slope or retaining wall within a distance of twice the height of the cut or wall, unless a geotechnical certificate by a qualified geotechnical engineer or engineering geologist shows that the added water will not destabilise the slope. On such sites roof runoff goes to rainwater storage, with overflow to a lined drain that discharges through a sediment trap to a stable natural channel or choe, never onto an unprotected slope. The 10° trigger is set by this Manual; the Shivalik slopes are of sandstone and clay, and runoff from them reaches the choes within minutes.
- Permeable paving on the open parking of group housing, which both instruments require, is pervious area in the post-development run (Clause 3.9.2). It earns credit as retention only where it is built and tested as an infiltration practice under rule (a) or (b); under rule (c), and under the hill rule, it is built with a lined, non-exfiltrating base and an underdrain.
- The unpaved area of the environmental conditions (at least 20% of the recreational open space) and the pervious open space of a layout are pervious area. They enter the post-development run as pervious land under Clause 3.9.2 and get no further credit as retention or detention unless they are built and tested as an infiltration practice.
In the waterlogged belt, the Sirowal and the bet lands, a recharge pit drains slowly or not at all in the SW monsoon, and a sump is full after the first heavy rain. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH sumps are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives. The three recharge rules, the 10 m and 3 m thresholds, the site check in between, the quality screen, the 20 L/m² minimum for reuse credit, the hill infiltration rule and the pre-treatment and road-runoff rules are set by this Manual; no Punjab rule on where recharge may or may not be credited was found.
4.12 High-groundwater and sandy coastal sites
4.12.1 Design groundwater level. Each site in the waterlogged south-west of sub-area PB-F of Annex 2A (Sri Muktsar Sahib, Fazilka, Faridkot and the waterlogged parts of Bathinda and Ferozepur), the land along the Rajasthan and Sirhind feeders, the Sirowal belt below the Kandi in sub-area PB-A, the bet (floodplain) lands of the Sutlej, Beas, Ravi and Ghaggar, and the beds and margins of chhappars, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the SW monsoon, from:
- (a) site piezometer readings over at least one full June–November season; or
- (b) where (a) is not available, the higher of the CGWB or WRD (or PWRDA) record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, choe, bein, drain, canal or chhappar.
For the flotation check of 4.12.3 at sites in the waterlogged south-west (Sri Muktsar Sahib, Fazilka, Faridkot and the waterlogged parts of Bathinda), the Sirowal belt below the Kandi, and the bet (floodplain) lands of the Sutlej, Beas, Ravi and Ghaggar, where (a) is not available, the DGWL shall be taken as existing ground level.
4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:
- (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
- (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.
4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:
- with the facility empty;
- with groundwater at the DGWL; and
- for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.
The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.
4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.
4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.
4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.
Commentary. Punjab is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the State. The exposure provisions of 4.12.5 apply where groundwater at a site is saline or brackish, which in the south-west it often is: the EC of groundwater exceeded 3,000 µS/cm in 6.72% of the samples of the 2024 assessment, with hot spots in Bathinda, Faridkot, Fazilka, Ferozepur, Mansa, Sri Muktsar Sahib, Nawanshahr, Patiala and SAS Nagar (CGWB, GWRA-2024); "About 15-25% of the groundwater is saline/alkaline" in Sri Muktsar Sahib, Bathinda, Mansa and Sangrur districts, and the EC reached 8,320 µS/cm at Abohar (CGWB and WRD, 2020). The State's groundwater runs to both extremes. Depths ranged from 0.79 m to 65.10 m below ground in June 2019 and from 0.53 m to 67.27 m in October 2019, and about 21–22% of the State had water deeper than 30 m (same source). Where it is deep, infiltration is the best retention and should be used, subject to the three recharge rules of the Commentary to Clause 4.11, the 1.0 m separation of Clause 4.4.3 and Chapter 8. The waterlogged south-west, the Sirowal and the bet lands are the opposite case. There the water table is within a few metres of the surface and rises through the monsoon, fed in the south-west by seepage from the Rajasthan and Sirhind feeders (as reported), so an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when the Sutlej or the Ghaggar is high and the river raises the water table of the bet land beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, choe, bein, drain, canal or chhappar where that is higher than the well record, and in the waterlogged south-west (Sri Muktsar Sahib, Fazilka, Faridkot and the waterlogged parts of Bathinda), the Sirowal belt below the Kandi, and the bet (floodplain) lands of the Sutlej, Beas, Ravi and Ghaggar the flotation check takes ground level unless piezometers show otherwise. The June–November monitoring season of 4.12.1(a) is set by this Manual to cover the SW monsoon and the post-monsoon high: the CGWB and WRD read their wells in June and October, the October reading is the shallowest in the waterlogged belt (0.53 m at Kot Bhai in October 2019, against 0.79 m at Abohar in June), and the share of the State with water within 1.5–5 m rose from about 14% in June to about 17% in October (CGWB and WRD, 2020), so a reading taken in June understates the design level. No monsoon water-table depths for individual town sites in Bathinda, Sri Muktsar Sahib, Fazilka or Faridkot were obtained [TBC]. The factor of 1.2, the 0.5 m allowance and the "ground level" default for the waterlogged south-west, the Sirowal and the bet lands have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Punjab were found during research.
4.13 Regional detention and fee-in-lieu
4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:
- (a) a regional detention facility identified in the plan; or
- (b) a fee-in-lieu paid toward restoration of chhappar or tank storage identified in the plan.
4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:
- (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
- (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
- (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the SW monsoon. Storage below FTL that is held for irrigation or supply through June to September shall not be credited.
- (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
- (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
- (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.
4.13.3 Fee. The fee-in-lieu shall be computed as:
Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)
The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.
4.13.4 Ledger. The Authority shall keep a public ledger of:
- detention volume credited to each regional facility;
- volume delivered; and
- fees received and spent.
Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.
Punjab has no pond Act, no pond authority and no working tank cascade [N; unverified]. Its regional storage is of three kinds: the village chhappars (ਛੱਪੜ; toba ਟੋਭਾ; pond), tobas and dhabs, which are Panchayat commons; the low dams and check dams of the Kandi; and the drains, embankments and canals of WRD. Village ponds are shamlat land under the Punjab Village Common Lands (Regulation) Act 1961; the Supreme Court ordered illegally occupied pond land restored to the Gram Panchayat in Jagpal Singh v. State of Punjab (28 January 2011), and the High Court directed in July 2020 that encroachments on village ponds be removed within six months and that PPCB monitor their water (as reported); restoration is a programme of the Department of Rural Development and Panchayats, on the Seechewal, Thapar and PPCB models (as reported). No spatial-plan or building approval in Punjab was found to require the consent of any pond body. Three points follow:
- A pond on a list may not be what the list says. About 15,000 ponds in about 13,500 villages are in the cleaning programme of April 2025 (as reported); the first census of water bodies counted 16,012 in Punjab, 1,578 of them encroached (as reported); and many chhappars are combined basins that take the village sullage all year, so that the Comptroller and Auditor General found that a choked screening chamber at the pond-treatment works of the Gram Panchayats of Punnawal and Bhalwan, in Dhuri block, had led to the "discharge of untreated wastewater into the drain" (CAG Report 1 of 2026). A chhappar is credited only after a survey shows its bed, bank and outlet, only for the storage above its overflow level, only where its sullage is intercepted and treated ahead of it (Chapter 8), and only with the Gram Panchayat's consent.
- The Kandi dams are regional detention only where they are run as such. WRD reports 12 low dams completed in the Kandi, with "Flood attenuation" among their benefits, and 410 check dams on rivers and nallahs (WRD, Kandi Area Development; WRD reply in NGT O.A. 694/2023), and the Kandi choes, "prone to flashy floods", fill them with sand and silt. A low dam or check dam is the kind of regional storage that Clause 4.13 can credit once it is identified in a basin master plan (Chapter 11), surveyed for its present capacity, given an operating rule under Chapter 7 and desilted on a schedule; until then it starts full (Clause 3.12.5) and gives no credit.
- A drain or canal of WRD, or the bet land of a river, is not regional storage. The Buddha Nallah was designed for a 2-year storm and already carries about 700 MLD of wastewater (PMIDC, 2020; River Rejuvenation Committee, 2025), the Tung Dhab and Hudiara drains end in Pakistan, the Ghaggar has breached its banks in 1993, 2010 and 2023 (as reported), the bet land between a river and its dhussi bandh is the river's own flood land, and a canal is a barrier, not a receiving system. Storm water spilled to any of them uses capacity that the drain or river needs for its whole basin; it can be relied on only with the written consent of WRD, for a stated flow and level (Chapter 5).
The first point is the basis of condition 4.13.2(c) in Punjab. A chhappar gives flood storage only above its overflow level, unless a notified operating rule commits it to be lowered before the SW monsoon. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.
4.14 Simplified methods for small sites
4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.
4.14.2 Method.
- Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
- Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
- Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
- Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
- Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
- Complete Form 4-2 (Tier B site sheet).
Table 4.3 — Tier B permissible site discharge and site storage requirement (template)
| Zone (Annex 2A) | HSG | Imperviousness | PSD 2-yr (L/s/ha) | PSD 100-yr (L/s/ha), standard | PSD 100-yr (L/s/ha), flood-sensitive | SSR (m³/ha), standard | SSR (m³/ha), flood-sensitive |
|---|---|---|---|---|---|---|---|
| PB-Z1 Shivalik–Kandi: PB-A Shivalik foothills and Kandi (Pathankot–Talwara–Hoshiarpur–Garhshankar–Nangal–Anandpur Sahib–Rupnagar–Mullanpur) | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| PB-Z2 Northern and central plains: PB-B Majha–Doaba north (Gurdaspur–Batala–Jalandhar–Kapurthala–Phagwara–Nawanshahr) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| PB-Z2 Northern and central plains: PB-C Central Sutlej–Ghaggar belt (Ludhiana–Khanna–SAS Nagar–Zirakpur–Rajpura–Patiala–Fatehgarh Sahib) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| PB-Z3 Western and Malwa plains: PB-D Majha west and the border (Amritsar–Tarn Taran–Patti–Ferozepur–Zira) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| PB-Z3 Western and Malwa plains: PB-E Malwa centre (Sangrur–Barnala–Malerkotla–Moga–Mansa) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| PB-Z4 South-west: PB-F South-west sands, waterlogging and salinity (Bathinda–Sri Muktsar Sahib–Malout–Fazilka–Abohar–Faridkot) | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
Worked example (illustrative — not design values).
A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:
- PSD 100-yr = 356 / 2.0 = 178 L/s/ha
- SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
- PSD 2-yr ≈ 17 L/s/ha
Then:
- Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
- 100-yr release: 178 × 0.4 = 71 L/s.
- 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
- Layout options:
- a 400 m² underground tank 1.5 m deep; or
- 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
- Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
- RWH sumps are additional, and are assumed full (Clause 4.11).
Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.
4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:
- (a) the site counts tank or waterbody storage in its design (Chapter 7);
- (b) any part of the site lies within a waterbody setback (Chapter 7); or
- (c) the site drains to a tank cascade whose storage is counted in a downstream design.
The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.
4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:
Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A
where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.
Table 4.3A — Fixed release coefficients (provisional)
| Hydrologic soil group | C_10 | C_2 |
|---|---|---|
| A (sandy, well drained) | 0.05 | 0.02 |
| B | 0.08 | 0.03 |
| C | 0.15 | 0.08 |
| D (clay, poorly drained) | 0.25 | 0.15 |
Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).
4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):
V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]
V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]
where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).
4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.
4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.
Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).
Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the Ludhiana–Patiala plain, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.
The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.
4.15 Safety, fencing and multi-use
4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):
- (a) maximum depth in the 10% AEP storm: 0.45 m;
- (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
- (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
- (d) no vertical drop greater than 0.3 m within the storage area or at its edge.
4.15.2 Wet basins. Permanent pools shall have:
- a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
- an emergent planting fringe that deters entry.
4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:
- has a vertical wall or headwall drop greater than 0.6 m;
- exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
- contains an outlet structure with an opening larger than 300 mm that is not grated.
4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.
4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Punjabi and English stating that the area floods during rain, and a depth marker at the deepest point.
4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.
4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.
Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.
4.16 Basis: why peak matching alone fails
Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.
- Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
- Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
- Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
- Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
- Closed outfalls. In Punjab, the governing failure is volume with no outlet when the receiving water is high. The towns of the plains drain through outfalls in the dhussi bandhs of the Sutlej, the Beas, the Ravi and the Ghaggar, or to WRD drains that end in them, and a flap gate closes when the river rises. The rivers rise for days, not hours: at Harike "discharge above 3,00,000 cusecs falls under the High Flood category", and the headworks passed about 2.73 lakh cusecs on 26 August 2025 and 3,35,030 cusecs on 3 September 2025 (as reported); the Ghaggar at Khanauri stood above its danger mark, reported as 748 ft, from 13 to 15 July 2023, reaching 754.2 ft, with breaches left open after it (as reported); and the Pong reservoir took a record inflow of about 7.3 lakh cusecs on 14 August 2023 and then released for weeks (as reported). The dams give warning of the river but none of a local burst: BBMB's release notices from Bhakra and Pong come hours to days ahead, and a local storm can coincide with a high river, as when the storm of 8–10 July 2023 put 35 cm on Ropar in the 24 hours to 08:30 on 10 July (IMD press release) while the Ropar headworks passed about 1.79 lakh cusecs (as reported). The Central Water Commission has no flood site in Punjab, and the gauges used are WRD's and BBMB's, in feet, with gauge zeros not found [TBC]. The Buddha Nallah ends in the Sutlej at Walipur Kalan, and its rehabilitation was designed for a 2-year storm (PMIDC, 2020), so when the river is high the storm runoff of the city backs up in the city reach. Amritsar drains by the Tung Dhab and City Outfall drains of WRD to the Hudiara drain, which enters Pakistan, so the level at its outfall is outside Indian control (Amritsar Smart City bid, 2018). In the waterlogged south-west many depressions have no gravity outlet at all and drain only by pumping. And the canals are a barrier, not an outlet: a canal, distributary or minor takes no storm water without WRD's written consent, and the siphons and culverts that carry the drains under the canals control the flood level upstream of them (Chapter 5). A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.
The response in this Manual is layered:
- release below pre-development (Clause 4.5);
- retain the frequent storms (Clause 4.4);
- route long SW monsoon storms (Clause 4.6.3);
- prefer regional storage in the chhappar system (Clause 4.13); and
- check downstream and at the outfall (Chapter 5).
Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.
4.17 Submittal requirements
Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:
- the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
- the evidence for the order of measures under Clause 4.3.1;
- the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
- the retention credit computation (Clause 4.4.6);
- the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
- a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
- stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
- the drawdown calculation (Clause 4.7);
- outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
- the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
- the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
- the design groundwater level and flotation check (Clause 4.12);
- the downstream and tailwater report (Chapter 5, Form 5-1); and
- the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).
Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.
References (chapter)
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01 (approved 10 Dec 2025). https://kcmetro.apwa.org/wp-content/uploads/sites/23/2026/01/APWA-Section-5600_Storm-Drainage-Systems-Facilities.pdf
- Mid-America Regional Council (2025). APWA 5600 Stormwater Standards Policy Supplement (7 Nov 2025); APWA 5600 Manual factsheet. https://www.marc.org/document/apwa-stormwater-standards-supplement ; https://www.marc.org/document/apwa-5600-manual-factsheet
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.8, 5608.4). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- MARC / APWA (2012). Manual of Best Management Practices for Stormwater Quality. https://www.marc.org/sites/default/files/2022-05/Best_Management_Practices_for_Stormwater_Quality.pdf
- MARC. The Evolution of Regional Stormwater Design Standards (presentation; McEnroe 2005 results). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Volume 1. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- Urban Drainage and Flood Control District (now MHFD) (2012). Full Spectrum Detention Release Rate Memorandum. https://mhfd.specialdistrict.org/files/23cb85ce8/UDFCD_Full_Spectrum_Detention_Release_Rate_Memorandum.pdf
- Mile High Flood District. Urban Storm Drainage Criteria Manual, Volume 2 (Storage).
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- PUB Singapore (2024). On-site Detention Tank Technical Guide, Rev. 3; Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3 (16 Apr 2025). https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- Sydney Water (2020). On-site Stormwater Detention Guide (SW201). https://www.sydneywater.com.au/content/dam/sydneywater/documents/on-site-stormwater-detention-guide.pdf
- Upper Parramatta River Catchment Trust (2005). On-site Stormwater Detention Handbook, 4th ed.
- "On-site stormwater detention for Australian development projects: does it meet frequent flow management objectives?" Water Science and Engineering (2019). https://www.sciencedirect.com/science/article/pii/S1674237019300213
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Supreme Court of India (2011). Jagpal Singh v. State of Punjab, Civil Appeal arising out of SLP(C) No. 3109 of 2011, judgment of 28 January 2011 (village common land and ponds; cited from its summary). https://api.sci.gov.in/jonew/judis/37417.pdf
- Reports on the order of the Punjab and Haryana High Court of July 2020 on encroachments on village ponds (Hindustan Times, 16 July 2020). https://www.pressreader.com/india/hindustan-times-amritsar/20200716/281702617018140
- Reports on the pond-cleaning programme of the Department of Rural Development and Panchayats (The Tribune, 21 April 2025; Department of Information and Public Relations, Punjab) and on the first census of water bodies (The Tribune, 4 November 2024). https://www.tribuneindia.com/news/punjab/aap-govt-sanctions-rs-4573-crore-for-cleaning-15000-ponds-in-13500-punjab-villages ; https://ipr.punjab.gov.in/en/press-releases/hq-press-releases/minister-tarunpreet-sond-hits-ground-zero-to-inspect-ponds-cleaning-drive ; https://www.tribuneindia.com/news/punjab/process-to-notify-water-bodies-on-all-encroachments-to-go/amp
- Comptroller and Auditor General of India (2026). Audit Report on Local Bodies for the period ended March 2023, Government of Punjab, Report No. 1 of 2026, Chapter III (pond-based wastewater treatment works of Gram Panchayats). https://cag.gov.in/en/audit-report/details/124559
- Water Resources Department, Punjab. Kandi Area Development Administration (low dams; choes), and reply of 10 February 2024 in NGT O.A. 694/2023 (check dams and recharge works): see the References of Chapter 3.
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A (§8.5).
- Department of Local Government, Punjab (2018). Punjab Municipal Building Bye-Laws, 2018, notification No. CTP(LG)/2018/3548 of 22 November 2018: 1.1–1.3, 2.3, 2.44, the definition of parking, 3.10.7, 4.23, 5.2.1, 5.16, Chapter X (10.1–10.6, Table 10.1), 11.2.1 and Chapter 15 (Tables 15.1–15.3) (read from the Internet Archive copy). http://web.archive.org/web/20190713054359id_/http://lgpunjab.gov.in:80/upload/5bfb9b6b8b129Final%20PMBBL,%2022-11-2018.pdf
- Department of Local Government, Punjab (2019). Amendment to the Punjab Municipal Building Bye-Laws, 2018, notification No. LG/CTP(LG)/2019/3977 of 31 December 2019 (read from the Internet Archive copy); the amendment of 9 August 2023 (independent floors) is known from DLG's list only. http://web.archive.org/web/20200926062809id_/http://lgpunjab.gov.in/upload/documentation/5e18013e68c4bPMBBL-2020.pdf
- Department of Housing and Urban Development, Punjab (2021). Punjab Urban Planning and Development Building Rules, 2021, notification No. G.S.R. 144/P.A.11/1995/Ss.180 and 43/2021 of 31 August 2021 (Punjab Government Gazette, 10 September 2021), with the corrigendum of 16 March 2022 and the Amendment Rules, 2022 (G.S.R. 23 of 29 March 2022): r.1, r.2, r.3(A), r.11, r.26, r.30, r.40, r.43–r.45 and r.51–r.53 (read from the copy circulated by PPCB). http://web.archive.org/web/20221222012900id_/https://ppcb.punjab.gov.in/sites/default/files/2022-07/Building%20Rules-2021.pdf
- Reports on the withdrawal of the Punjab Unified Building Rules, 2025, on 27 April 2026 (The Tribune). https://www.tribuneindia.com/news/punjab/punjab-withdraws-2025-building-rules-reverts-to-old-system/
- Ministry of Environment, Forest and Climate Change (2016). Notification S.O. 3999(E) of 9 December 2016 (environmental conditions for buildings and construction), as applied by PUDBR r.43 and PMBBL Chapter 15.
- The Punjab Canal and Drainage Act, 2023 (Punjab Act No. 11 of 2023), Punjab Government Gazette (Extraordinary), 27 December 2023: sections 1(3), 2, 5, 38, 39, 41, 45, 51, 52 and 61 (PRS copy). https://prsindia.org/files/bills_acts/acts_states/punjab/2023/Act11of2023-Punjab.pdf
- The Northern India Canal and Drainage Act, 1873 (Central Act VIII of 1873), sections 3 and 55–57 (repealed in its application to Punjab by section 61 of the 2023 Act). https://thc.nic.in/Central%20Governmental%20Acts/Northern%20India%20Canal%20and%20Drainage%20Act,%201873..pdf
- The Punjab Water Resources (Management and Regulation) Act, 2020 (Punjab Act No. 2 of 2020), sections 3, 14, 15, 16 and 17 (PRS copy). https://prsindia.org/files/bills_acts/acts_states/punjab/2020/Act%20No.%202%20of%202020%20Punjab.pdf
- Punjab Water Regulation and Development Authority (2023). Punjab Ground Water Extraction and Conservation Directions, 2023, notification of 27 January 2023: 2.7, 3.1, 4.6 (Table 4.2) and 4.7. https://faolex.fao.org/docs/pdf/IND221379.pdf
- Water Resources Department, Punjab. Rooftop Rainwater Harvesting schemes for Ground Water Recharge at roof tops of various Government Buildings across Punjab (project report, costed at CSR-2020; read from the Internet Archive copy). http://web.archive.org/web/20240828204347id_/https://irrigation.punjab.gov.in/sites/default/files/Proposal%20RWH.pdf
- Water Resources Department, Punjab (2024). Affidavit in NGT O.A. 303/2023, Karnvir Thamman v. State of Punjab (Sutlej floodplain zone, Ferozepur and Tarn Taran, notified 4 March 2024; letter of the Chief Engineer, Drainage-cum-Mining & Geology, to CWC of 2 May 2024). https://www.greentribunal.gov.in/sites/default/files/news_updates/AFFIDAVIT%20BY%20GOVT.%20OF%20PUNJAB%20IN%20OA%20NO.%20303%20OF%202023%20Karnvir%20Thamman%20VS%20State%20of%20Punjab%20&%20Ors.pdf
- Nagar Panchayat Naya Gaon (2026). Reply of 5 June 2026 in NGT O.A. 180/2026, Sumitra Negi v. State of Punjab, with the notification of 4 March 2013 under section 55 of the 1873 Act (Patiala ki Rao) and the Local Commissioner's report of 8 January 2024 in CWP 5901/2017. https://www.greentribunal.gov.in/sites/default/files/news_updates/Reply%20on%20behalf%20of%20R%206%20Nagar%20Panchayat%20Naya%20Gaon%20in%20OA%20No%20180%20of%202026%20Sumitra%20Negi%20Vs%20State%20of%20Punjab%20and%20Ors.pdf
- Central Pollution Control Board (2025). Reply of 13 October 2025 in NGT O.A. 327/2025, Public Action Committee v. State of Punjab (Buddha Nallah: quality before the Sutlej confluence, April 2024; width of the channel). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPLY%20BY%20R-7%20CPCB%20IN%20OA%20NO.%20327%20of%202025%20Public%20Action%20Committee%20through%20its%20Member%20Er%20Kapil%20Dev%20Vs%20The%20State%20of%20Punjab%20through%20the%20Principal%20Secretary%20Department%20of%20Water%20Resources.pdf
- Punjab Pollution Control Board (2025). Short reply in NGT O.A. 413/2025, Abhisht Kusum Gupta v. Union of India, with the proceedings of the River Rejuvenation Committee of 28 October 2025. https://www.greentribunal.gov.in/sites/default/files/news_updates/SHORT%20REPLY%20BY%20PPCB%20IN%20OA%20NO.%20413%20of%202025%20ABHISHT%20KUSUM%20GUPTA%20VS%20UNION%20OF%20INDIA%20AND%20ORS..pdf
- Punjab Municipal Infrastructure Development Company (2020). Rejuvenation of Buddha Nallah, Ludhiana — Feasibility Report, January 2020. https://pwssb.punjab.gov.in/wp-content/uploads/2020/03/Buddha-Nallah-Feasibility-Report.pdf
- Amritsar Smart City Limited (2018). Bid No. 07/ASCL/2018-19, Trunk Storm Water Drainage and Allied Works … at Walled City Amritsar, Section V, 1.1–1.6 and 2.3.2. https://www.amritsarcorp.com/NoticePDF/RFP_07_ASCL_2018-19.pdf
- Greater Mohali Area Development Authority (2021). Report of Social Impact Assessment and SIMP: Master Plan Sector Dividing Road 92 & 92 Alpha for Disposal of Storm Sewer, SAS Nagar (read from the Internet Archive copy). http://web.archive.org/web/20250707200848id_/https://gmada.gov.in/sites/default/files/documents/2.%20(E)%2092%20%26%2092%20Alpha%20Road%20for%20Storm%20Water%20Disposal.pdf
- Master Plan Jalandhar report (LPA Jalandhar, Vision 2031): 9.3 and 13.8.5–13.9.3 (notification status not seen; read from the Internet Archive copy of the file hosted by GMADA). http://web.archive.org/web/20230726152616id_/https://www.gmada.gov.in/sites/default/files/documents/Jal_rpt_2011.pdf
- Comptroller and Auditor General of India (2021). Performance Audit on Efficacy of implementation of the 74th Constitutional Amendment Act, Government of Punjab, Report No. 7 of 2021, Chapter 4 and Appendix 4.2 (AMRUT; Smart City storm-water works). https://cag.gov.in/webroot/uploads/download_audit_report/2021/Report%20No.%207%20of%202021%20Govt.%20of%20Punjab_PA-062e0dc92d20019.93581063.pdf
- Water Resources Department, Punjab. Drainage Administration page (projects, including the N-Choe re-alignment in IT City and the Swan flood works): see the References of Chapter 3.
- Department of Science, Technology and Environment, Punjab. District Environment Plan, Hoshiarpur (choes). https://decc.punjab.gov.in/wp-content/uploads/2021/11/DEP-Hoshiarpur.pdf
- Town and Country Planning Department, Government of Himachal Pradesh. Himachal Pradesh Town and Country Planning Rules, 2014, consolidated to 2022, Appendix 6 (minimum roof-top storage of 20 litres per square metre; cited as precedent only). https://tcp.hp.gov.in/Application/uploadDocuments/rule/Rule20221126_160623.pdf
- Reports on the announcement of 20 September 2023 of a drainage-wing NoC for construction within 150 m of a water body (The Tribune, 20–21 September 2023); no notification or order was found.
- Reports on the Ravi and the Madhopur headworks, August 2025 (SANDRP), on the Pong and Bhakra dams in August 2023 (SANDRP), on the Harike and Hussainiwala headworks, 3 September 2025 (Babushahi), and on the Ghaggar at Khanauri, July 2023 (The Tribune; Down To Earth). https://sandrp.in/2025/08/29/aug-2025-ravi-flood-damages-madhopur-barrage-gates-in-punjab/ ; https://sandrp.in/2023/08/21/no-dispute-about-role-of-pong-and-bhakra-dams-in-punjab-aug-2023-floods/ ; https://www.babushahi.com/view-news.php?id=210079 ; https://www.tribuneindia.com/news/punjab/ghaggar-flows-5-ft-above-danger-mark-in-sangrur-525383 ; https://www.downtoearth.org.in/news/natural-disasters/a-dead-ghaggar-and-its-tributaries-wrought-havoc-in-haryana-early-july-here-is-how-90671
- Reports on the 2019 Sutlej breaches (PTC News) and on the 1988 and 1993 floods (The Tribune, 11 July 2023). https://www.ptcnews.tv/work-on-plugging-500-feet-wide-jania-chahal-breach-completed-jalandhar ; https://www.tribuneindia.com/news/punjab/redux-of-1988-1993-flooding-no-lessons-learnt-524523
- Bureau of Indian Standards. IS 456:2000 Plain and Reinforced Concrete — Code of Practice.
- Government of India. Dam Safety Act, 2021.
- Chow, V.T., Maidment, D.R. and Mays, L.W. (1988). Applied Hydrology. McGraw-Hill (AMC conversion).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 4A | Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map |
| 4B | Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A) |
| 4C | Worked example (Tier A) with full routing tables |
| Form 4-1 | Site Runoff Control Report |
| Form 4-2 | Tier B Site Sheet |
| Form 4-3 | Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7) |
Commentary. No Indian national rule or Punjab rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". Punjab controls building through two instruments, divided by territory. Inside the limits of every Municipal Corporation, Municipal Council and Nagar Panchayat the Punjab Municipal Building Bye-Laws 2018 (PMBBL) apply, made by DLG (notification No. CTP(LG)/2018/3548 of 22 November 2018) under section 201(1) of the Punjab Municipal Act 1911 and section 399(2) of the Punjab Municipal Corporation Act 1976 (PMBBL 1.3), and amended on 31 December 2019 and, for independent floors, on 9 August 2023 (as listed by DLG). Outside municipal limits, and in the urban estates and other schemes of the development authorities, the Punjab Urban Planning and Development Building Rules 2021 (PUDBR, an abbreviation set by this Manual) apply, made by HUD under section 180 read with section 43(2) of the Punjab Regional and Town Planning and Development Act 1995 (G.S.R. 144 of 31 August 2021), except within the Lal Lakir of village abadi, Cantonment Boards and protected archaeological sites (PUDBR r.1(3)); they were corrected on 16 March 2022 and amended on 29 March 2022, and the amendments reported for 2026 were not read, none of them being reported to touch rainwater harvesting, the plinth, basements or drainage [TBC]. The Punjab Unified Building Rules 2025, which would have replaced both, were withdrawn on 27 April 2026, restoring the two instruments (as reported), and are not cited. The drainage provisions of both protect the building and the drain, not the catchment. The building plan shows "methods of disposal of waste water, sewerage and storm water" and the surroundings up to fifteen metres (PUDBR r.11); open parking is kept level with the crown of the road "except for the slopes required for natural drainage of the area" (PMBBL, definition of parking); the plinth is sited "that adequate drainage of the site is assured", at least 450 mm above the surrounding ground (PMBBL 5.2.1.1), or 900 mm "from the crown of adjoining road in front" on residential plots and "450mm or as specified by competent authority" for other buildings (PUDBR r.3(A) and r.30(1)); roof water is carried away from the building, and the municipality may require the rain-water pipes to be led to a covered channel and the road gutter (PMBBL 5.16.1); rainwater harvesting is required (Commentary to Clause 4.11); and for buildings of 5,000–20,000 m² of built-up area the environmental conditions require that "The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water" and that the unpaved area be at least 20% of the recreational open space (PMBBL 11.2.1(iv) and Table 15.1; PUDBR r.43, by reference to MoEFCC S.O. 3999(E) of 9 December 2016). PMBBL 10.4 comes nearest to detention: public open spaces of more than 500 m² "shall have arrangements for complete utilization and capture of storm water", including "Artificial or natural Storage of storm water runoff from larger sites". None of these sets a design storm, a release rate, a storage volume or an overflow path, and neither instrument sets any setback from a river, nallah, choe, pond or canal (PUDBR r.26 sets setbacks by building height only). The parent municipal Acts were not read, and their sections on drains and drain connections are not known to this Manual [TBC]. The lines that do exist come from a statute and the courts. Under section 38 of the Punjab Canal and Drainage Act 2023 (Punjab Act 11 of 2023), as under section 55 of the Northern India Canal and Drainage Act 1873 that it repeals in Punjab (section 61), the State may notify limits within which no obstruction of a river, stream or drainage channel may be formed, and the reach "shall be held to be a drainage-work"; whether the 2023 Act has been brought into force was not confirmed [TBC]. WRD computes such lines from the 100-year flood by Gumbel's method and the waterway by Lacey's formula, and states that in the 100-year area "no construction is to be allowed" (Chief Engineer, Drainage-cum-Mining & Geology, to CWC, 2 May 2024); the Sutlej floodplain zone of Ferozepur and Tarn Taran districts, notified on 4 March 2024, was declared as the land between the embankments, about 4.5 km apart, although the Lacey waterway was 0.58 km (WRD affidavit in NGT O.A. 303/2023). The Patiala ki Rao has a section 55 notification of 4 March 2013 and pillars marking a 200-ft width set in the High Court's proceedings, a case-specific width and not a WRD norm (CWP 5901/2017). The Master Plan Jalandhar report proposes no construction within at least 200 m of the Chitti Bein "untill concrete bandh is constructed", except a 30 m buffer zone from the bank, and a 30 m plantation strip along the Black (Kala Sanghian) Bein (13.8.6–13.8.7), the only numeric river setback found in a Punjab plan text, a plan proposal whose notified form was not seen [TBC]. A drainage-wing NoC for projects within 150 m of a water body was announced by the Water Resources Minister on 20 September 2023 (as reported), but no notification or order was found, and this Manual does not apply it. The hydraulic corridor of Chapter 7, with its Zone 1 floor of at least 15 m, and the setback zones of that chapter are this Manual's proposal, to be superseded by a notification under section 38 where one exists; the notified limits and the court lines apply where they bind and are wider. The design norms in use are history, to be replaced. No State or municipal storm-drain standard was found. The Amritsar Smart City bid of 2018 adopted for the walled-city trunk sewers "a return period of once in two years", a minimum time of concentration of 15 minutes and surcharge in the manholes "(without flooding)" (bid 07/ASCL/2018-19); the Buddha Nallah was designed for a 2-year return period "with reduced run-off within the city reach due to active storm water detention" (PMIDC, 2020); WRD sizes the recharge structures of government roofs for 40 mm/h, with runoff coefficients of 0.8–0.9 for roofs, 0.6–0.7 for paved areas and 0.1–0.2 for green areas, which is a recharge-structure figure and not a design storm for drains (WRD, rooftop rainwater harvesting proposal); and under AMRUT, "Storm Water Drainage — No work was done … due to shortage of funds" up to September 2020 (CAG Report 7 of 2021). These are project choices, not State standards, and this Manual uses none of them. Basements are regulated, and more firmly than in most States, but not for flooding. "Adequate arrangement shall be made that surface drainage does not enter the basement" (PUDBR r.30(5)(iv)(e); PMBBL 4.23(vii)); the basement's waste water is pumped to the sewer, not connected directly, "to avoid any risk of the sewerage or sludge heading back into the basement" (PMBBL 4.23(viii)); its structural safety is certified "in relation to underground water table/spring level" (PMBBL 4.23(vi)); the ceiling of a first basement stands 0.9–1.2 m above the average surrounding ground (PUDBR r.30(5)(iv)(d)); and no basement is allowed in a "No construction Zone" or "Master Plan Green area" or any other restricted zone "under the provision of any other Act" (PUDBR r.30(5)(iii)), under which a reach notified under section 38 could, by NEER's reading, count. No rule sets the level of a basement ramp or opening against a flood level. This Manual therefore adds its own requirements for every basement: no detention storage in a habitable basement (Clause 4.10.1); the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4); and no basement in Zone 2 (Clause 7.5.2). The same rule sets the lowest habitable floor and every opening at least 0.5 m above the 1% AEP flood level (Clause 6.11.1). These levels are stricter than the plinth of either instrument, which is measured from the road crown or the surrounding ground and not from any flood level, and the difference is disclosed: a PMBBL plinth of 450 mm above the surrounding ground meets Clause 6.11.1 only where the 1% AEP level stays at least 50 mm below the ground beside the building, and a PUDBR plinth of 900 mm above the crown of the road meets it only where that level is no more than 0.4 m above the crown (NEER's arithmetic); on a street that floods 0.5 m deep, neither does. In the flood-sensitive catchments of Clause 4.5.3.2 and in any catchment notified under Clause 4.5.4, this Manual recommends that no basement be permitted where the 1% AEP flood level stands above the plinth that the applicable instrument requires; and in the waterlogged south-west (Sri Muktsar Sahib, Fazilka, Faridkot and the waterlogged parts of Bathinda), the Sirowal belt below the Kandi, and the bet (floodplain) lands of the Sutlej, Beas, Ravi and Ghaggar, where the water table is within 3 m of the surface, that a basement be permitted only as a watertight structure checked against flotation with the groundwater at ground level (Clauses 4.12.1 and 4.12.3). These are the Manual's proposals, not rules of PMBBL or PUDBR. This chapter is written so that it can supply, as a technical companion to the two instruments, the sizing for the storm-water disposal that PUDBR r.11 already requires to be shown on the plans and the "adequate size of channel" that Table 15.1 leaves open; a competent authority (for example DLG for municipal building approvals or HUD for PUDBR) could adopt it for either purpose, and none has. In practice the storm drains carry sewage. The Buddha Nallah, before its confluence with the Sutlej, measured BOD 161 mg/l, COD 456 mg/l and TSS 328 mg/l in April 2024, against general discharge standards of 30, 250 and 100 mg/l (CPCB reply in NGT O.A. 327/2025); the roadside drains of Amritsar's walled city are joined to the sewers (Amritsar Smart City bid, 2018); and the rain in Jalandhar "is largely discharged in to the sewer network" (Master Plan Jalandhar report, 9.3), although the Canal and Drainage Act excludes "removal of sewage from towns, villages or any other habitat" from its drainage works (section 2(7)). Clause 8.9 deals with that dry-weather flow. Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.