Annexes to Chapter 5Downstream and Tailwater Analysis
These annexes support Chapter 5. Annex 5C is a worked example of the outfall-closed check of Clause 5.10, for the illustrative facility of Annex 4C. Annexes 5A and 5B need tidal, surge, survey and river data that this draft does not yet contain; each lists what the chapter already sets, gives the intended layout and states the interim rule of Chapter 5 that applies until it is published. Forms 5-1 and 5-2 are the submittal forms required by Clause 5.14. They are draft forms and have no statutory status.
Annex 5A — Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment
Supports Clauses 5.7, 5.9, 5.10, 5.11 and 5.12 of Chapter 5.
5A.1 Table 5A.1 shows how the values of this annex enter the design tailwater levels of Table 5.1. The sea-level allowance is set by Clause 5.7.4 and does not depend on this annex.
Table 5A.1 — Use of the Annex 5A values in the design tailwater (Table 5.1)
| Design case | Tailwater | Annex 5A values used | Chapter value |
|---|---|---|---|
| Minor-system design | MHWS + SLA | MHWS | SLA ≥ +0.3 m (Clause 5.7.4) |
| Major-system and storage design | HAT + surge + SLA | HAT; 10% AEP surge (Clause 5.7.3(a)) | SLA ≥ +0.3 m |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA | 1% AEP still-water level (Clause 5.7.3(b)) | SLA ≥ +0.3 m |
| Datum conversion | Chart datum to project datum | Offset from chart datum to the Survey of India datum (Clause 5.7.2(b)) | — |
Not prepared for Punjab. Punjab has no coast, so no outfall in the State has a tidal tailwater, and this annex has no Punjab content (Clause 5.1.4). Its tables are kept, empty, so that the annex and table numbers match the other editions of this Manual. Rows F1 to F7 of Form 5-1 are entered as "not applicable", and the tailwater is derived under rows F8 to F10; for a site with no defined outfall, row F10 records the 72-hour design volume and the overflow path instead (Clause 5.8.5(g)).
Table 5A.2 — Tidal datums, surge and still-water levels by coastal segment (layout)
| Coastal segment | Reference port and tide-table edition | MSL (m CD) | MHWS (m CD) | HAT (m CD) | CD to Survey of India datum (m) | 10% AEP surge (m) | 1% AEP still-water level (m CD) | Wave set-up (m), open-sea outfalls | Sources |
|---|---|---|---|---|---|---|---|---|---|
Annex 5B — Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map
Supports Clauses 5.2, 5.3, 5.8 and 5.13 of Chapter 5.
5B.1 Table 5B.1 lists the water bodies that Chapter 5 already names. It is not complete: the annex will add the extents of each reach, the other rivers, canals and mouths of the State, and a map.
Table 5B.1 — Water bodies named in Chapter 5
| Water body | Region | Listed as | Clause |
|---|---|---|---|
| Sutlej from the Bhakra dam to the Ropar headworks | Nangal, Anandpur Sahib, Rupnagar | Riverine outfall reach below a dam; no CWC gauge; Bhakra releases included (permissible level 1,680 ft, technical limit 1,690 ft, as reported); flow of about 2.4 lakh cusecs at Ropar (1988) and 1.79 lakh cusecs (July 2023), as reported; gauge zero [TBC]; flood marks of 2019, 2023 and 2025 + 0.5 m; lock of at least 7 days | 5.8.1, 5.8.3, 5.8.5 |
| Sutlej from the Ropar headworks to Harike | Ludhiana, Phillaur, Shahkot | Riverine outfall reach behind dhussi bandhs; no CWC gauge; 10% AEP level not below the level for 3,00,000 cusecs at Harike, or the 1988 Ropar flow above Harike, routed; flood marks + 0.5 m; breaches of August 2019 (Janian Chahal, Gidderpindi, Mandala); lock of at least 7 days | 5.8.1, 5.8.5 |
| Sutlej from Harike to Hussainiwala and the border | Tarn Taran, Ferozepur | Riverine outfall reach; floodplain zone notified 4 March 2024 between the embankments; 100-year discharge 5,34,441 cusecs (WRD); Harike 3,35,030 cusecs, 686.50 ft u/s, and Hussainiwala 3,02,508 cusecs, 646.50 ft u/s, on 3 September 2025 (as reported); "High Flood" above 3,00,000 cusecs at Harike; gauge zeros [TBC]; lock of at least 7 days | 5.8.1, 5.8.5 |
| Beas from the Pong dam to Harike | Talwara, Mukerian, Kapurthala district | Riverine outfall reach below a dam; Pong releases included (largest about 1.49 lakh cusecs, 2023, as reported; FRL 1,390 ft, permissible 1,394 ft and technical limit 1,410 ft reported); lock of at least 7 days | 5.8.1, 5.8.3, 5.8.5 |
| Ravi below Ranjit Sagar, Shahpur Kandi and Madhopur | Pathankot, Gurdaspur, Dera Baba Nanak | Riverine outfall reach below dams; Ranjit Sagar FRL 527.91 m (also reported as 1,731 ft), Shahpur Kandi maximum 405 m; Ranjit Sagar releases of August 2025 conflict (about 1 lakh and 2.21 lakh cusecs reported), the higher applying; Madhopur gate failure of 27–28 August 2025 as a stress case; dhussi bandh breaches of 2025; border reach; lock of at least 7 days | 5.8.1, 5.8.3, 5.8.5 |
| Chakki Khad; Swan | Pathankot; Anandpur Sahib | Shivalik rivers; no gauge level found; bulked 1% AEP study; lock of at least 72 hours | 5.8.1, 5.8.5 |
| Ghaggar at Mubarakpur, Bhankharpur and Dera Bassi | SAS Nagar district (Dera Bassi, Zirakpur) | Riverine outfall reach; no CWC gauge; 1.22 lakh cusecs reported at Bhankharpur against a stated capacity of 70,000 cusecs; model inflow not below 2.40 m³/s/km²; Haryana's Panchkula floodplain zone upstream; lock of at least 72 hours | 5.8.1, 5.8.5 |
| Ghaggar below the Patiala district boundary | Patiala, Samana, Moonak, Khanauri, Makraud Sahib, Sardulgarh | Riverine outfall reach; no CWC gauge; Khanauri 753 ft (13 July 2023) and 754.2 ft (15 July 2023), danger mark reported as 748, 752 and 753 ft (conflict); Sarala Kalan danger about 16 ft; Sardulgarh danger 20 ft (all as reported); gauge zeros [TBC]; breaches of 1993, 2010 and 2023; Haryana reach downstream; lock of at least 7 days | 5.8.1, 5.8.5 |
| N-Choe, Sukhna Choe, Patiali-ki-Rao, Jayanti Devi ki Rao, Lakhnaur choe | SAS Nagar, Zirakpur, Kharar, New Chandigarh; Chandigarh (Supplement S01) | Choes to the Ghaggar; ungauged; bulked 1% AEP study and flood marks + 0.5 m; invert 0.5 m above the highest surveyed bed; Patiala ki Rao notified under section 55 (4 March 2013) with 200 ft pillars ordered (court-monitored); lock of at least 72 hours | 5.8.1, 5.8.5 |
| Badi Nadi and Chhoti Nadi | Patiala | Nadis to the Ghaggar; capacities not found [TBC]; lock of at least 72 hours, or that of the Ghaggar where it backs them up | 5.8.5 |
| Choes of the Kandi, among them those of Hoshiarpur, Garhshankar and Balachaur, and the Sirhind choe | Sub-area PB-A; Fatehgarh Sahib | Choes; "more than 100" in Hoshiarpur district; sand and silt; Sirhind choe passes under the Bhakra Main Line by a siphon; Clause 6.3.6 applies; lock of at least 72 hours | 5.8.5 |
| Buddha Nallah | Ludhiana | Major drain of WRD, 47.55 km, to the Sutlej at Walipur Kalan; 2-year rejuvenation design (PMIDC, 2020), not a bound; about 700 MLD of wastewater; width alleged reduced from 58 ft to 35 ft (OA 327/2025); level computed with the Sutlej at Walipur Kalan; drain lock, or the Sutlej lock where the river backs it up | 5.2, 5.8.5 |
| Tung Dhab and City Outfall drains; Hudiara drain | Amritsar | Major drains of WRD; the Hudiara drain enters Pakistan near village Lalo; level beyond the border outside Indian control; junction level from the Indian side; lock of at least 7 days | 5.2, 5.8.5 |
| Kala Sanghian drain, Chitti Bein, Kali Bein | Jalandhar, Kapurthala | Major drains and beins to the Sutlej and the Beas; flow-augmentation figures only, no flood capacity found [TBC]; Chitti Bein high flood level reported as "generally 12'" at the Chaheru railway bridge (Master Plan Jalandhar report) | 5.2, 5.8.5 |
| Sakki/Kiran, Patti and Kasur nallahs; Chand Bhan drain and diversion drain; other WRD and notified drains | Majha; the south-west | Major drains of WRD; design discharges not found [TBC]; drain lock of at least 72 hours | 5.2, 5.8.5 |
| Depressions, chhappars and pumped drains of the south-west | Sub-area PB-F (Bathinda, Sri Muktsar Sahib, Fazilka, Abohar, Faridkot) | No outfall or pumped outfall; 72-hour design volume; permanent pumps less the largest; pumping credited only under WRD's consent while the receiving drain is full; no infiltration credit where the October water table is within 3 m | 5.8.5 |
| Sirhind canal, Bhakra Main Line, Sirhind and Rajasthan feeders, SYL canal, Narwana branch, and the other canals, distributaries, minors and kassis of WRD | Punjab | Not drainage outfalls; WRD's written consent required; siphons and canal banks modelled as controls; SYL and Narwana branch breaches at Rajpura (2023); Hansi–Butana siphon at Samana | 5.8.5 |
| Drains of WRD, PUDA, GMADA, GLADA and the other development authorities, Municipal Corporations, Municipal Councils and Nagar Panchayats 1.0 m wide or more | Punjab | Major drains; owner's consent, design water level and flap gate | 5.2, 5.8.5 |
| Bhakra and Pong dams (BBMB); Ranjit Sagar and Shahpur Kandi dams; Ropar, Harike, Hussainiwala and Madhopur headworks; Kandi low dams | Himachal Pradesh (Bhakra, Pong); Pathankot district (Ranjit Sagar, Shahpur Kandi, Madhopur); Rupnagar, Tarn Taran and Ferozepur districts (Ropar, Harike, Hussainiwala); sub-area PB-A (low dams) | Releases and gate operation to be included in river levels (operating rules and release records [TBC]) | 5.8.3, 5.8.5 |
| River mouths subject to sand-bar closure | None in Punjab | Not applicable (Clause 5.1.4) | 5.13.1 |
To be prepared. This annex will list and map (a) the major drains of each basin plan, (b) the riverine outfall reaches where backwater shall be modelled, with their upstream and downstream limits and the source of their design flood levels, and (c) the river mouths and creek inlets subject to seasonal sand-bar closure, with the most recent pre-monsoon bar crest levels and any WRD mouth-maintenance programme. It needs WRD river and canal records, design and recorded flood levels, reservoir operating rules, mouth-condition, dredging and bar-cutting records and pre-monsoon bar surveys (WRD), the drain inventories of MC Ludhiana and other local bodies, basin stormwater master plans (Chapter 11), and base mapping from the Survey of India and NRSC. Until it is published: every river, WRD canal, the Buddha Nallah, the Tung Dhab and City Outfall drains and the Hudiara drain, the Kala Sanghian drain and the Chitti and Kali Beins, the Sakki/Kiran, Patti and Kasur nallahs, the Chand Bhan drain and its diversion drain, every choe, rao and nadi, every drain notified under section 38 of the Punjab Canal and Drainage Act 2023 or section 55 of the Northern India Canal and Drainage Act 1873, any drain of WRD, and any drain maintained by PUDA, GMADA, GLADA or another development authority, a Municipal Corporation, a Municipal Council or a Nagar Panchayat with an internal width of 1.0 m or more and every tidal creek is a major drain (Clause 5.2); the water bodies of Table 5B.1 are riverine outfall reaches (Clause 5.8.1); and the mouths of the coastal States' rivers (there is none in Punjab) are assumed closed at the start of the SW monsoon unless WRD certifies otherwise (Clause 5.13.2).
Table 5B.2 — Attributes of the Annex 5B layers (layout)
| Field | Content | Unit or format |
|---|---|---|
| feature_id | Unique identifier | text |
| name | Name of the drain, river, canal, creek or mouth | text |
| category | Major drain; riverine outfall reach; mouth subject to sand-bar closure | text |
| clause | Clause of Chapter 5 under which it is listed | text |
| reach_limits | Upstream and downstream limits of the reach | text |
| design_flood_level_source | WRD design or highest recorded flood level, or hydraulic model (Clause 5.8.2) | text |
| reservoir_release | Upstream reservoir or tank and its operating rule, where any (Clause 5.8.3) | text |
| bar_crest_level | Most recent pre-monsoon bar crest level, for mouths | m (Survey of India datum) |
| mouth_programme | WRD mouth-maintenance programme and certification (Clause 5.13.2) | text |
| source | Source agency and date | text |
| geometry | Line (drains and reaches) or point (mouths) | line / point |
Annex 5C — Worked example: outfall-closed check for a site on a choe draining to the Ghaggar in SAS Nagar (Mohali)
Supports Clauses 5.9, 5.10, 5.11 and 5.12 of Chapter 5 and Clause 4.6.6 of Chapter 4.
Illustrative — not design values. This example applies the outfall-closed check of Clause 5.10 to the revised detention facility of Annex 4C. The site, its levels and its receiving drain are invented to show the method. No tidal level is used: the tide enters only through the illustrative statements in Table 5C.1 about whether the receiving drain is above or below the site outlet.
Inputs
5C.1 The site is the 2.0 ha flood-sensitive site of Annex 4C. It discharges through its own outlet chamber and a flap gate to a public storm drain that joins a choe in SAS Nagar (Mohali), which runs on to the Ghaggar; the choe's level rises when it runs full of sand-laden water from the Shivaliks and when the Ghaggar is high, so Clause 5.10.1 applies to the facility. To show the method, this example uses the two 6-hour lock windows of Clause 5.10.3, as the coastal editions of this Manual do. In Punjab an outfall to a choe has a lock of at least 72 hours under Clause 5.8.5(e), an outfall to the Ghaggar below the Patiala district boundary or to the Sutlej, the Beas or the Ravi below the dams a single lock of at least 7 days under Clause 5.8.5(a) to (c), an outfall to a WRD drain that is full a drain lock of at least 72 hours under Clause 5.8.5(i), and a site with no defined outfall must hold the 72-hour design volume of Clause 5.8.5(g), so in each of those cases the facility must store or pump the whole storm volume (Clause 5.9.4); that needs more storage, or pumping, than this example shows. The outfall invert is also set at least 0.5 m above the highest surveyed bed of the choe within 50 m downstream (Clause 5.8.5(e)). The routing, the volume balance of Clause 5.10.4 and the assessment are the same.
Table 5C.1 — Inputs (Illustrative — not design values)
| Item | Value | Basis |
|---|---|---|
| Facility | Revised facility of Annex 4C: 2,500 m² plan area, vertical walls; 170 mm orifice at the floor; 460 mm orifice, invert 0.53 m | Annex 4C, Table 4C.14 |
| Storm | 1% AEP, 48 h, peak day last, AMC III; 72 h also run | Clause 5.10.2 |
| Inflow | Post-development 1% AEP hydrographs of Annex 4C (48 h: 8,420 m³; 72 h: 9,468 m³) | Annex 4C |
| Receiving drain levels at the connection, J1, J2 and J3 | Below the site outlet invert (from the drain owner's model) | Illustrative input |
| Receiving drain during each lock window | Backs up above the site outlet invert, so the site cannot discharge | Illustrative input; Clause 5.10.3(b) |
| Flap gate on the site outlet | Set 0.15 m below the orifice inverts in the outlet chamber, so that outside the lock windows its opening head and head loss do not affect the orifice control | Illustrative input; to be confirmed from the certified curve (Clause 5.11.2) |
| Lock windows | Two of 6 h each, starts 12.4 h apart (semi-diurnal tide) | Clause 5.10.3(a) |
| Pumps | None | — |
5C.2 Cases of Table 5.2. Because the receiving drain stays below the site outlet in J1, J2 and J3 (Table 5C.1), those cases give the free-outfall results of Annex 4C: in J2 the 1% AEP maximum water level is 1.17 m (2,913 m³), and in J3 (10% AEP, 48 h) it is 0.77 m. R1 and R2 do not apply, because the site does not drain to a river. J4, the outfall-closed check, is worked below.
Lock windows (Clause 5.10.3)
5C.3 The peak 1-hour block of the final 24 hours of the 48-hour storm is 35:35–36:35 h, with 98.2 mm (the 1-hour depth of Table 4C.2). Two runs are made:
- Run A: the first window is centred on that block: 33:05–39:05 h; the second starts 12.4 h later: 45:29–51:29 h.
- Run B: the first window starts at that block: 35:35–41:35 h; the second: 47:59–53:59 h.
For the 72-hour storm, every time is 24 h later.
5C.4 Gravity discharge is zero inside each window. Outside the windows the outlet discharges through the orifices of Table 4C.10. The routing is the same level-pool routing as in Annex 4C.
Results
Table 5C.2 — Outfall-closed check results (Illustrative — not design values)
| Storm | Run | Lock windows (h:min) | Maximum stage (m) | Maximum storage (m³) | Time of maximum (h:min) | Largest release after a window (L/s) |
|---|---|---|---|---|---|---|
| 1% AEP, 48 h | A | 33:05–39:05; 45:29–51:29 | 2.01 | 5,019 | 39:05 | 566 |
| 1% AEP, 48 h | B | 35:35–41:35; 47:59–53:59 | 2.10 | 5,238 | 41:35 | 584 |
| 1% AEP, 72 h | A | 57:05–63:05; 69:29–75:29 | 2.00 | 5,012 | 63:05 | 565 |
| 1% AEP, 72 h | B | 59:35–65:35; 71:59–77:59 | 2.09 | 5,233 | 65:35 | 584 |
Run B of the 48-hour storm governs. The first window closes the outlet just as the storm peak arrives, so the whole peak is stored. The second window arrives when the facility has drained to about 0.7 m, below the Stage 2 orifice, and adds little.
5C.5 Volume balance (Clause 5.10.4). Table 5C.3 gives the balance for Run B. The outflow in each period is found by continuity: outflow = storage at start + inflow − storage at end.
Table 5C.3 — Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Period (h:min) | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| 0:00–35:35, before window 1 | 3,817 | 2,213 | 0 | 0 | 1,604 |
| 35:35–41:35, window 1 | 3,634 | 0 | 0 | 1,604 | 5,238 |
| 41:35–47:59, between windows | 941 | 4,423 | 0 | 5,238 | 1,756 |
| 47:59–53:59, window 2 | 28 | 0 | 0 | 1,756 | 1,784 |
| After 53:59 | 0 | 1,784 | 0 | 1,784 | 0 |
| Total | 8,420 | 8,420 | 0 | — | — |
Check for window 1: V_inflow = 3,634 m³ ≤ V_storage available + V_pumped + V_gravity = (5,238 − 1,604) + 0 + 0 = 3,634 m³. The facility therefore needs 5,238 m³ of storage, which the routing confirms.
Table 5C.4 — Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Time (h) | Inflow (L/s) | Outlet | Outflow (L/s) | Stage (m) | Storage (m³) |
|---|---|---|---|---|---|
| 24 | 20 | Open | 18 | 0.18 | 445 |
| 28 | 39 | Open | 24 | 0.25 | 621 |
| 32 | 59 | Open | 32 | 0.36 | 906 |
| 34 | 85 | Open | 37 | 0.47 | 1,166 |
| 36 | 286 | Closed | 0 | 0.78 | 1,944 |
| 38 | 106 | Closed | 0 | 1.73 | 4,321 |
| 40 | 66 | Closed | 0 | 1.96 | 4,904 |
| 42 | 51 | Open | 529 | 1.79 | 4,472 |
| 44 | 42 | Open | 204 | 0.87 | 2,181 |
| 46 | 37 | Open | 49 | 0.74 | 1,854 |
| 48 | 33 | Open | 47 | 0.70 | 1,756 |
| 50 | 0 | Closed | 0 | 0.71 | 1,784 |
| 54 | 0 | Closed | 0 | 0.71 | 1,784 |
| 56 | 0 | Open | 43 | 0.58 | 1,459 |
| 60 | 0 | Open | 32 | 0.37 | 921 |
| 66 | 0 | Open | 16 | 0.16 | 397 |
| 72 | 0 | Open | 7 | 0.06 | 162 |
Assessment
5C.6 Clause 5.10.4(a). The facility of Annex 4C reaches 1.17 m in J2, and its spillway crest is at 1.35 m (Annex 4C). In the outfall-closed check the stage reaches 2.10 m, so the spillway would operate. The facility of Annex 4C fails the check.
5C.7 Remedy. Pumping (Clause 5.12) does not help here: during the lock windows the receiving drain is itself closed, and pumping into it would raise its level, which Clause 5.12.3 does not permit. The remedy is more storage. Keeping the plan area of 2,500 m² and the outlets of Annex 4C:
- the facility must hold 5,238 m³, to a stage of 2.10 m;
- the spillway crest is set above that stage, with the 0.15 m clearance recommended in Clause 4.9.3: 2.25 m;
- with the 4.0 m spillway of Annex 4C (head 0.30 m), the maximum level with the spillway flowing is 2.55 m, and with 0.3 m freeboard the top of the walls is at least 2.85 m above the floor.
The outfall-closed check therefore governs the storage: 5,238 m³ against 2,913 m³ from the release-rate checks, about 80% more. A larger plan area would make the facility shallower; the outlet, caps and drawdown would then have to be re-checked, because the stage–discharge relationship changes.
5C.8 Release after the lock. When the first window ends, the stored water is released under a head of about 2 m, at up to 584 L/s. This is above the 100-yr cap of 356 L/s. Clause 5.10.4 allows this, because the release reaches a drain that has itself just reopened, and requires it to be included in the J4 run of the downstream analysis (Clauses 5.4 and 5.9) and reported on Form 5-1, Section H.
5C.9 Drawdown after the storm (Clause 5.10.5). The J1 tidal curve stays below the site outlet (Table 5C.1), so the drawdown of Annex 4C applies: 45.3 h for 90% of the 10-yr storage with the low-flow orifice 50% blocked, within the 48-hour limit of Clause 4.7. In Run B, 90% of the maximum J4 storage is released 22.6 h after the maximum.
5C.10 Other requirements.
- The flap gate on the site outlet is inspected and operated before 25 June each year and after every event in which it closed against a storm flow (Clause 5.11.5).
- The deeper facility is checked for flotation with groundwater at the design groundwater level; in the waterlogged south-west (Sri Muktsar Sahib, Fazilka, Faridkot and the waterlogged parts of Bathinda), the Sirowal belt below the Kandi, and the bet (floodplain) lands of the Sutlej, Beas, Ravi and Ghaggar without piezometer readings that level is existing ground level (Clauses 4.12.1 and 4.12.3).
- The fence and signs of Annex 4C apply to the deeper facility (Clause 4.15).
Table 5C.5 — Summary (Illustrative — not design values)
| Item | Value |
|---|---|
| Governing case | J4, 1% AEP 48-hour storm, Run B (first window starting at the peak 1-hour block) |
| Storage required | 5,238 m³ (Annex 4C release-rate design: 2,913 m³) |
| Maximum stage | 2.10 m, with 2,500 m² plan area |
| Spillway crest | 2.25 m |
| Top of walls | ≥ 2.85 m above the floor |
| Largest release after a lock window | 584 L/s, to be included in the downstream J4 run |
| Drawdown | Annex 4C result applies: 45.3 h with the low-flow orifice 50% blocked |
Form 5-1 — Downstream and Tailwater Report
Supports Clauses 5.3 to 5.14 of Chapter 5.
Draft form — Punjab Stormwater Design Manual, Draft v1.0. One report for each project. Sites of less than 0.5 ha that meet Clause 5.3.4 may submit Form 5-2 instead, where the Authority accepts it. Attach the plans, model files and hydrographs referred to.
A. Project
Table 5F.1 — Form 5-1: project
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Project type: site under Chapter 4; drainage project under Chapter 6; regional detention or tank restoration (Clause 5.1.2) | |
| A3. Site or project area (ha) and outfalls | |
| A4. Site Runoff Control Report reference (Form 4-1), where applicable |
B. Extent of the analysis (Clause 5.3; Clause 5.14, item 1)
Table 5F.2 — Form 5-1: analysis points
| Point | Location | Type (Clause 5.3.3 (a) to (e)) | Contributing catchment (ha) | Project area as % of it |
|---|---|---|---|---|
Table 5F.3 — Form 5-1: end point
| Field | Entry |
|---|---|
| B1. End point and reason: 10% point, tank or chhappar, or major drain or the sea (Clause 5.3.1 (a) to (c)) | |
| B2. Where the end point is a tank or chhappar: change in maximum water level (m) and in surplus-weir discharge (m³/s); continuation below the weir if the level rises (Clause 5.3.2) | |
| B3. Plan of the analysis extent, showing the site, each point with its contributing area and percentage, and the end point (attach) |
C. Model (Clause 5.4.4; Clause 5.14, item 2)
Table 5F.4 — Form 5-1: model
| Field | Entry |
|---|---|
| C1. Software and version; hydrologic and hydraulic methods (Clause 5.4.4) | |
| C2. Network schematic, with the survey sources for drains and crossings (attach) | |
| C3. Land use and CN of off-site areas (present land use) | |
| C4. Upstream detention included, with evidence that it is built, maintained and documented | |
| C5. Calibration or validation evidence, where available | |
| C6. Scenarios run: existing, with project, and future where the Authority requires it (Clause 5.4.1) | |
| C7. Storms run: AEPs and durations, AMC and areal reduction (Clause 5.4.3) |
D. Results at each analysis point (Clause 5.4.2; Clause 5.14, item 3)
Complete one row for each analysis point, AEP and duration. E = existing; P = with project.
Table 5F.5 — Form 5-1: results by analysis point
| Point | AEP | Duration (h) | Peak flow E / P (m³/s) | Time to peak E / P (h) | Maximum water level E / P (m) | Peak velocity E / P (m/s) | Duration of inundation E / P (h) |
|---|---|---|---|---|---|---|---|
E. Acceptance (Clause 5.5; Clause 5.14, item 4)
Table 5F.6 — Form 5-1: acceptance criteria
| Criterion | Met at every point? | Where not met, the remedy adopted (Clause 5.5.3) |
|---|---|---|
| E1. 1% AEP water level rise ≤ 10 mm at buildings, lowest openings and carriageways (Clause 5.5.1(a)) | ||
| E2. No building newly flooded; no building or road newly failing the Chapter 6 limits (Clause 5.5.1(b)) | ||
| E3. Peak flow not above existing at the minor-system AEP of each element or at 1% AEP (Clause 5.5.1(c)) | ||
| E4. Velocity in lined channels within the lining limit, 3.0 m/s maximum (Clause 5.5.1(d)) | ||
| E5. Velocity in unlined channels, 50% and 10% AEP, not increased by more than 10% (Clause 5.5.1(e)) | ||
| E6. Change in duration of road closure on arterial or emergency routes (Clause 5.5.2) | ||
| E7. Timing exception requested (Clause 5.5.4)? Give the conditions met |
F. Tailwater derivation (Clauses 5.6 to 5.8; Clause 5.14, item 5)
Table 5F.7 — Form 5-1: tailwater derivation
| Field | Entry |
|---|---|
| F1. Tide-table edition and port, or port authority source (Clause 5.7.2(a)) | |
| F2. MHWS, HAT and MSL (m above chart datum) | |
| F3. Connection from chart datum to the Survey of India benchmark and the project datum: offset (m) and source (Clause 5.7.2(b)) | |
| F4. Estuary, creek or canal outfall: levels used and any evidence for a departure from open-coast levels (Clause 5.7.2(c)) | |
| F5. 10% AEP surge and 1% AEP still-water level: values, source, method and record length (Clause 5.7.3) | |
| F6. Wave set-up, for outfalls facing the open sea (Clause 5.7.3(d)) | |
| F7. SLA (m), at least +0.3 m; design life; sensitivity run at twice the SLA for design lives over 50 years (Clause 5.7.4) | |
| F8. Non-tidal tailwater: receiving-system level and source (Clauses 5.6.2, 5.6.3) | |
| F9. River levels and sources; reservoir or tank releases included (Clauses 5.8.2, 5.8.3) | |
| F10. Rivers, the Hudiara drain, choes, canals, south-west depressions and WRD drains (Clause 5.8.5): for every level, the gauge, its unit (ft or m), its gauge zero and the levelled tie to the project datum and a Survey of India benchmark, with WRD's or BBMB's confirmation (no CWC level exists in Punjab); for a river outfall through a dhussi bandh, operator of each gate and pumping station identified, gate sills, bandh crest, installed capacity, operating levels and gate-closing level obtained; 1% AEP river level from a Gumbel 100-year flood and a model (not less than 5,34,441 cusecs on the Ferozepur–Tarn Taran reach of the Sutlej), and not below the surveyed 2019, 2023 and 2025 flood marks + 0.5 m; 10% AEP level not below the level for 3,00,000 cusecs at Harike (or the 1988 Ropar flow above Harike); on the Ghaggar, model inflow not below 2.40 m³/s/km², level not below 754.2 ft at Khanauri + 0.5 m, 10% AEP level not below the highest reported danger mark (753 ft at Khanauri), and whether the level was coordinated through WRD with Haryana; drain behind the bandh routed with its whole catchment and present storage, permanent pumps only, not more than installed capacity less the largest pump, operable at the design river level; river lock of not less than 7 days (Sutlej, Beas and Ravi below the dams; Ghaggar below the Patiala district boundary; Hudiara drain) or 72 hours (upper Ghaggar, choes, Chakki Khad, Swan), covering the whole storm, and its source; gate-failure and breach checks; the design storm with the largest recorded release of the dam or headworks above (the higher of conflicting reports), placed before, during and after the storm; for a reservoir or pond outfall, the level used (Ranjit Sagar 527.91 m, Shahpur Kandi 405 m, Pong 1,410 ft, each + 0.5 m); the Madhopur 2025 stress case and its result; for the Buddha Nallah, its level with all inflows and dry-weather flow and the Sutlej at Walipur Kalan; for Amritsar, the junction level of the Tung Dhab and Hudiara drains; for a choe, the bulked 1% AEP study, crossings blocked, flood marks + 0.5 m, invert at least 0.5 m above the highest bed surveyed within 50 m downstream; for a canal, WRD's written consent (or none: no discharge), full supply level, permitted rate and flap gate, and every siphon, culvert and canal bank modelled as a control with the breach check; for a site with no defined outfall, the 72-hour design volume, the storage below its overflow and its emptying time, the level of any shared depression or chhappar with and without the project and its starting level, and the overflow path traced to public land; for a pumped outfall, the pumping credited under WRD's consent while its drain is full, and no infiltration credit where the October water table is within 3 m; for a WRD or other drain, the owner's consent and permitted rate, design water level or computed level with all its inflows, present condition and narrowest section, the lowest reported capacity or width, proposed works not counted, and the drain lock of not less than 72 hours; WRD's consent, whether the outfall lies within limits notified under section 38 (or section 55), and the court and plan lines checked (Clause 5.8.5) |
G. Joint cases (Clause 5.9; Clause 5.14, item 6)
Table 5F.8 — Form 5-1: joint-case results
| Case | Rainfall | Tailwater used (m, project datum) | Applies? | Governing result (storage, level, pipe size or pump capacity) |
|---|---|---|---|---|
| J1 | ||||
| J2 | ||||
| J3 | ||||
| J4 | ||||
| R1 | ||||
| R2 |
H. Outfall-closed check (Clause 5.10; Clause 5.14, item 7)
Table 5F.9 — Form 5-1: outfall-closed check
| Field | Entry |
|---|---|
| H1. Reason the check applies (Clause 5.10.1) | |
| H2. Storm: AEP, 48 h and 72 h, AMC III (Clause 5.10.2) | |
| H3. Lock duration and basis: default of two 6-hour windows, or site study (Clause 5.10.6); extension for sand-bar closure (Clause 5.13.5) | |
| H4. Lock windows of the two runs (start and end times) (Clause 5.10.3(d)) | |
| H5. Maximum stage in each facility, against its 1% AEP maximum water level (Clause 5.10.4(a)) | |
| H6. Maximum stage in the minor and major systems, against the Chapter 6 limits (Clause 5.10.4(b)) | |
| H7. Property connections: surcharge level, or non-return valves fitted (Clause 5.10.4(c)) | |
| H8. Stage hydrographs (attach) | |
| H9. Drawdown after the storm under the J1 tidal curve, and pumping where needed (Clause 5.10.5) |
Table 5F.10 — Form 5-1: volume balance for each lock window (Clause 5.10.4)
| Period | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| Before window 1 | |||||
| Window 1 | |||||
| Between windows | |||||
| Window 2 | |||||
| After window 2 |
I. Gates and valves (Clause 5.11; Clause 5.14, item 8)
Table 5F.11 — Form 5-1: schedule of flap gates, tide gates and non-return valves
| Location | Type | Size (mm) | Invert (m, project datum) | Certified head–discharge data (reference) | Stop-log or penstock (outfalls > 600 mm) |
|---|---|---|---|---|---|
J. Pumped outfalls (Clause 5.12; Clause 5.14, item 9)
Table 5F.12 — Form 5-1: pumped outfalls
| Field | Entry |
|---|---|
| J1. Reason pumping is needed (Clause 5.12.1) | |
| J2. Duty capacity (m³/s) at the static head for the J2 tailwater; standby capacity (Clause 5.12.2) | |
| J3. Effect on the receiving water level (Clause 5.12.3) | |
| J4. Power supply: two independent supplies, or standby generation with 72 h of fuel; automatic changeover (Clause 5.12.4) | |
| J5. Level of electrical panels, controls, generators and fuel, against the higher of the 1% AEP flood level + 0.5 m and HAT + surge + SLA + 0.5 m (Clause 5.12.5) | |
| J6. Discharge arrangement (Clause 5.12.6); controls, alarms and logging (Clause 5.12.7); screens (Clause 5.12.8) |
K. Sand bar (Clause 5.13; Clause 5.14, item 10)
Table 5F.13 — Form 5-1: sand-bar assumption
| Field | Entry |
|---|---|
| K1. River mouth or creek inlet concerned | |
| K2. Mouth assumed closed, or open with WRD certification attached (Clause 5.13.2) | |
| K3. Bar crest level from the most recent pre-monsoon survey (m) and the closed-mouth tailwater (Clause 5.13.3) | |
| K4. Extension of the lock duration, where required (Clause 5.13.5) |
L. Inspection and maintenance (Clause 5.14, item 11)
Table 5F.14 — Form 5-1: inspection and maintenance
| Field | Entry |
|---|---|
| L1. Gate and valve inspection before 25 June and after closure events (Clause 5.11.5) | |
| L2. Pump test runs before 25 June (Clause 5.12.9) | |
| L3. Other requirements for the maintenance plan (Chapter 10) |
M. Statement by the registered professional (Clause 10.6)
I state that this report has been prepared under Chapter 5 of the Punjab Stormwater Design Manual (Draft v1.0), that the results reported are reproduced by the models submitted, and that every departure from Chapter 5 is listed with its reason. The Professional Design Certificate (Form 10-3) is attached.
Table 5F.15 — Form 5-1: statement by the registered professional
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Empanelment number, where Clause 10.6.1 requires it | |
| Organisation | |
| Signature | |
| Date |
Draft form — Punjab Stormwater Design Manual, Draft v1.0.
Form 5-2 — Simplified Downstream Statement (small sites)
Supports Clause 5.3.4 of Chapter 5.
Draft form — Punjab Stormwater Design Manual, Draft v1.0. For sites of less than 0.5 ha. The Authority may accept this statement in place of the full analysis only where every answer in Section B is "Yes". Otherwise submit Form 5-1.
A. Site
Table 5F.16 — Form 5-2: site
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Site area (ha), less than 0.5 ha | |
| A3. Receiving public drain: name or reference, type and size | |
| A4. Site Runoff Control Report reference (Form 4-1) |
B. Conditions (Clause 5.3.4)
Table 5F.17 — Form 5-2: conditions
| Condition | Yes / No | Evidence |
|---|---|---|
| B1. The receiving public drain has documented capacity for its minor-system design flow (Chapter 6) | ||
| B2. No flood-prone location is recorded within 500 m downstream of the site outfall. Records checked: local body, MC Ludhiana, PSDMA, WRD (Clause 5.3.3(d)) | ||
| B3. The site does not drain to a tidal or backwater-affected outfall |
C. Route plan
Table 5F.18 — Form 5-2: attachments
| Attachment | Attached? |
|---|---|
| C1. Plan of the drainage route from the site outfall for 500 m downstream, with the receiving drain and any recorded flood-prone locations | |
| C2. Copy or reference of the drain capacity record |
D. Statement
I state that the site meets the conditions of Clause 5.3.4 as shown above, and that the records listed have been checked.
Table 5F.19 — Form 5-2: statement
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Signature | |
| Date |
Draft form — Punjab Stormwater Design Manual, Draft v1.0.