Chapter 6Minor and Major Drainage Systems
6.1 Purpose and scope
6.1.1 This chapter sets the level of service and the hydraulic criteria for the conveyance system that carries runoff from a development, a road or a public drainage scheme to a receiving waterway, tank or outfall. It covers:
- (a) the dual drainage concept: a minor system and a major system (Clause 6.3);
- (b) design return periods by land use and road class (Clause 6.4);
- (c) street hydraulics: spread, depth and flow hazard (Clause 6.5);
- (d) inlets, including clogging (Clause 6.6);
- (e) pipes and open and covered drains (Clause 6.7);
- (f) hydraulic grade line analysis (Clause 6.8);
- (g) overland flow paths, ponding at sags and building floor levels (Clauses 6.9 to 6.11);
- (h) culverts and road crossings (Clause 6.12); and
- (i) Punjab construction-practice requirements for covered drains, silt, solid waste, utilities and desilting access (Clause 6.13).
6.1.2 The detailed hydraulic design of individual structures (culverts, channels, energy dissipators, screens, pumps, gates, manholes) is in Chapter 9. Rainfall is in Chapter 2, runoff methods in Chapter 3, on-site storage in Chapter 4, tailwater in Chapter 5, waterbodies in Chapter 7 and water quality in Chapter 8.
6.1.3 This chapter applies to all public drains, all roads with kerbs or roadside drains, and all private drainage systems in developments that meet the applicability thresholds of Chapter 1. In Tier B local bodies, the simplified procedures and design aids referred to in Chapter 1 may be used for elements serving ≤ 16 ha, but the criteria of this chapter still apply.
6.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Minor system | Inlets, pipes, covered drains and open drains that carry runoff up to the minor design AEP of Table 6.1 without surcharge above the limits of Clause 6.8. |
| Major system | The surface flow paths (streets, overland flow paths, open channels, floodways and storage) that carry flow above the capacity of the minor system, up to the 1% AEP (100-yr) event. |
| Overland flow path | A defined surface route, in public land or a recorded easement, that carries major-system flow to a receiving waterway. |
| Spread (T) | Width of flow in the gutter and carriageway, measured from the face of the kerb. |
| Sag | A low point on a road or flow path from which water can leave only through an inlet or by ponding to an overflow level. A trapped sag has no surface overflow route. |
| Clogging factor | The fraction of an inlet's clean hydraulic capacity assumed lost to debris (Clause 6.6.3). |
| Hydraulic grade line (HGL) | The line joining the free-surface levels in a conduit system, or the piezometric levels where the system is under pressure. |
| Covered drain | A rectangular drain, usually beside a road, closed by cast-in-situ or precast cover slabs that form a footpath. |
| Sediment allowance | The depth or area of a drain or pipe assumed filled with silt when its design capacity is computed (Clause 6.7.8). |
| Check event | An AEP rarer than the design AEP at which the combined minor and major system must still meet the limits of Table 6.2. |
| High-density area | An area notified as such by the approving authority under Clause 6.4.4. |
| Class I area | An urban local body with a population of 1 lakh or more (the CPHEEO definition). |
6.3 The dual drainage concept
6.3.1 Every drainage system shall be designed as two systems that work together:
- (a) a minor system that carries the minor design flow of Table 6.1 below ground or in drains, keeping streets usable and spread within Table 6.2; and
- (b) a major system that carries all flow above the minor-system capacity, up to the 1% AEP (100-yr) flow, on the surface without entering buildings and within the depth and hazard limits of Clause 6.5.
6.3.2 Every element has a 1% path. Every inlet, sag, pipe, drain, culvert and storage element shall have an identified 1% AEP overland flow path to a receiving waterway, tank or outfall. The path shall be shown on the drainage plan (Clause 6.15).
6.3.3 Major-system design flow. The major system at any point shall carry the 1% AEP peak flow less the minor-system capacity at that point. The minor-system capacity used in this subtraction is the capacity of the inlets after the clogging factors of Clause 6.6.3, or the pipe capacity, whichever is less. At sags and at any location used to set building floor levels, the major system shall also be checked with the minor system fully blocked (Clause 6.10.3).
6.3.4 Rainfall and method. Design flows shall use the rainfall of Chapter 2 (including the climate factor of Clause 2.8) and the methods of Chapter 3:
- (a) the Rational Method only for catchments ≤ 16 ha and a single conveyance element. It shall not be used to accumulate flows down a network whose total catchment exceeds 16 ha;
- (b) a hydrograph method with hydraulic routing (for example SWMM, HEC-HMS with a hydraulic model, or an equivalent 1D/2D model) for networks above 16 ha and for any network with storage, pumping or a tidal outfall;
- (c) a minimum time of concentration of 10 minutes.
6.3.5 No transfer between catchments. Neither the minor nor the major system shall divert flow from one natural catchment to another unless the approving authority accepts a catchment-wide study showing no adverse effect.
6.3.6 Choe crossings and Kandi drains (sub-area PB-A). This clause applies to every element of the minor and major systems that receives runoff from the Shivalik hills or the Kandi, which in this Manual means land in sub-area PB-A of Annex 2A, any catchment whose natural ground slopes more than 10% on average, and any choe, rao, nadi, khad or other seasonal stream that comes down from the Shivaliks, wherever it runs, including the choes that cross SAS Nagar, Kharar, Zirakpur, Dera Bassi and New Chandigarh on their way to the Ghaggar. Such elements shall meet Clauses 6.4 to 6.14 and, in addition (all set by this Manual):
- (a) Debris racks and sediment traps. Every inlet, drain or pipe entrance and culvert that receives flow from 1 ha or more of unbuilt Shivalik or Kandi land (forest, scrub, grassland, bare or eroded slope, a quarried surface or a choe bed), or from a choe, rao or nadi whatever its catchment, shall have a debris rack or a sediment trap upstream of it, designed under Chapter 9 (Clause 9.8), with machine access and a place to stockpile what it catches that is not a slope, a choe bed or a drain. With 50% of the rack blocked, the element it protects shall still pass its design flow, and the overflow route shall not send the flow onto a building or an unprotected slope. Racks and traps shall be cleared by 15 June and, in sub-area PB-A, again after the monsoon by 31 October (Chapter 10). The volume of a sediment basin is to be set in Chapter 9 [TBC].
- (b) Bulking factor. The design flow of every channel, drain, pipe, culvert and crossing that receives flow from such a catchment shall be the clear-water peak flow of Chapters 2 and 3, with Clause 2.3.6(i) for the Kandi and Shivalik catchments, multiplied by a bulking factor of 1.25, for the minor design flow, the check event and the 1% AEP flow; elsewhere the factor is 1.0. The factor applies to capacity, freeboard and velocity; it does not apply to the runoff volume used for storage (Chapter 4). A larger factor shall be used where a sediment study of the catchment gives one.
- (c) Blockage. The blockage check of Clause 6.12.4 shall assume 50% of the inlet area blocked for every culvert and pipe entrance with a span or diameter below 3.0 m, and 20% for larger ones, whether or not a debris rack is provided. Grate inlets keep the clogging factor of Table 6.5, and kerb openings on grade take the sag value of 20%.
- (d) Sediment and minimum velocity. Drains and pipes that receive flow from such a catchment, or that run across the Kandi fans of sub-area PB-A, shall reach a velocity of at least 1.0 m/s at the minor design flow, in place of the minimum of Clause 6.7.3(a). Where the gradient does not allow it, a sediment trap shall be provided upstream and the sediment allowance of Clause 6.7.8 doubled (Clause 6.7.4). Every town drain that takes the flow of a choe, or of a catchment under item (a), shall have a sediment trap where it takes it, so that the sand the choe carries settles where it can be removed and not in the drain.
- (e) Steep drains and steep streets. Where the gradient of a drain gives a velocity above the limits of Clause 6.7.3(b), or a Froude number above 0.8, at the design flow, the drain shall be a lined chute, a stepped channel or a series of drop structures designed under Chapter 9 for the bulked flow of item (b), with the freeboard of Table 6.7 for steep channels and an energy dissipator at every change to a flatter gradient and at the outlet. On a street steeper than 5%, grate-only inlets shall not be used, and inlets shall be placed by the calculation of Clause 6.6.4 with the bypass flows of a steep gutter; on a street steeper than 10%, the flow shall be intercepted by transverse grated channels or kerb inlets at a spacing that keeps the street flow within the limits of Table 6.3 in the check and 1% AEP events.
- (f) Choe beds and choe crossings. No choe, rao or nadi bed shall be narrowed, filled, covered, decked, built over or diverted by a development, a road, a drain or a boundary wall, and no structure shall be placed in it, other than a crossing, outfall or protection work designed under this clause with the written consent of WRD (Clause 5.8.5(h)); where the choe is notified under section 38 of the Punjab Canal and Drainage Act 2023, or under section 55 of the Northern India Canal and Drainage Act 1873, the notified limits apply as well. Every culvert, causeway and bridge on a choe shall pass the bulked 1% AEP flow of item (b) with the blockage of item (c) without raising the upstream level above the floor levels of Clause 6.11, and a causeway shall be treated as closed to traffic whenever it is overtopped. Every outfall to a choe shall have its invert at least 0.5 m above the highest bed level surveyed within 50 m downstream, shall enter in the direction of flow, and shall have an erosion-resistant apron and scour protection designed under Chapter 9 (Clause 5.8.5(e)).
- (g) Foothill roads as the minor system. In sub-area PB-A, and on any road elsewhere that crosses a choe or a Kandi catchment, the drainage of a road is the minor system for the land above it as well as for the road. Every road and street there shall have, as works of the road's owner, PWD (B&R), NHAI or the local body:
- (i) a lined catch-water drain above every cut slope where the land above drains towards the road, discharging to a natural channel or a cross-drainage work and not over the cut;
- (ii) lined side drains on the hill side (IRC:SP:42-2014, cl. 8.5.1);
- (iii) a cross-drainage work at every choe, rao and nadi, and culverts or scuppers at intervals such that no side drain exceeds its capacity at the design AEP of Table 6.1 with the factors of items (b) and (c);
- (iv) at the outlet of every scupper, culvert and side drain on the valley side, a lined chute, cascade or pipe carrying the flow to a stable natural channel, with an energy dissipator, so that road runoff is never discharged onto an unprotected slope, fill, retaining wall or the land of a building below;
- (v) culverts of at least the size of Clause 6.12.5, designed under Clause 6.12 and not less than IRC:SP:42-2014 cl. 7.1.4 requires for the road; where the drainage provisions of IRC:SP:48-1998, the Hill Road Manual, which were not read for this Manual [TBC], are stricter than this item, they apply; and
- (vi) no muck, spoil, quarry waste or excavated material from the construction, widening or maintenance of the road placed in or beside a choe, rao, nadi or other line of natural drainage, or on a slope from which a storm can carry it into one.
- (h) Sloping sites. On a site where the land above drains towards a building, its cut or its retaining wall, the runoff of that land shall be intercepted above them by a lined diversion drain sized for the minor design flow of Table 6.1 from the land above it, with the factors of items (b) and (c), with a 1% AEP flow path that does not pass through or against the building. It shall discharge to a public drain or a stable natural channel as item (g)(iv) requires, not onto the slope below. Roof and paved-area runoff on such a site follows the hill infiltration rule of Clause 4.11.
Commentary. The CPHEEO (2019) manual defines major and minor systems in its glossary but gives no return period for the major system. APWA 5600 (2006, 5601.8) requires the system to convey the 1% peak and, where in-system capacity is less, an overflow system to carry the remainder. Clause 6.3.3 subtracts only the clogged inlet capacity, not the full pipe capacity, because in practice the pipes cannot take more water than the inlets admit. The fully-blocked check at sags has no direct precedent; this Manual sets it because of the Amritsar experience that drains under footpaths are often silted or blocked by solid waste when the heaviest rain arrives (CPHEEO 2019 Part A, Ch 1 and 2, Figures 1.2 and 2.1 on solid waste dumping in drains). The prohibition on inter-catchment transfer follows the DID Malaysia 2008 submission checklist, which prohibits inter-catchment diversion. Clause 6.3.6 is set by this Manual for the Shivalik fringe and the Kandi of Punjab, on the model of the clause that the Himachal Pradesh edition sets for its hills, because the criteria of this chapter assume clear water on gentle ground, and the water of a choe is not clear. The Kandi below the Shivaliks "is traversed by numerous small and big seasonal streams called choes and is prone to flashy floods", and "About 40% of this rain water gets wasted in floods" (WRD, Kandi Area Development); the plain there slopes about 16 m per kilometre, decreasing westwards (CGWB, Hoshiarpur district report). Hoshiarpur district alone has "more than 100 choes", which "originate from Shivalik slopes and take shape of wide channels after entering the foothill plains" and leave "thick deposits of sand and silt" (District Environment Plan, Hoshiarpur). The same choes cross the sectors of SAS Nagar and Chandigarh on their way to the Ghaggar: the Phase 11 area of SAS Nagar is reported to flood when the Lakhnaur choe is not cleared (as reported); villagers beside a new sector road told GMADA that "the village Abadi area is seven feet lower than the level of stream (Nadi) area", and the assessment recommended that GMADA "not disturb the natural passage of 'Nadi' or allied tributaries" and recalculate the nadi's runoff "as per proposed landuse" (GMADA, social impact assessment for sector roads 92 and 92-Alpha, 2021); the NGT has recorded that debris in the N-Choe is "shrinking size of drain causing serious apprehension of flood" (OA 736/2022, as quoted by CPCB, 2024); and the Punjab portion of the Patiala ki Rao was found "heavily encroached by squatters" with "rampant illegal construction even deep inside the Nadi/Choe" (Local Commissioner's report of 8 January 2024 in CWP 5901/2017). That is why item (f) forbids narrowing, filling or covering a choe bed, whatever the choe is called and whoever maintains it: the rule matches the notification of 4 March 2013 on the Patiala ki Rao, which authorises action against any construction in, or covering of, the nadi, and the Punjab Land Preservation (Chos) Act 1900, under which the State may regulate the clearing, quarrying and cultivation of notified Kandi land (s.4, as quoted). The clause does not ask for the concrete channelisation of choes, and it does not forbid it: WRD has channelised and lined choes, among them the Sirhind choe below the siphon of the Bhakra Main Line and the N-Choe in IT City (WRD), and Hoshiarpur's choes have been channelised "to avoid any disaster caused by over flooding" (District Environment Plan, Hoshiarpur); such a work is a work of WRD under Clause 5.8.5(h), and item (f) requires only that what a development puts across or beside a choe passes the choe's bulked flood. No Indian guidance on bulking factors, debris racks or sediment basins was found during research [TBC], so each number in Clause 6.3.6 is an interim value with a stated reason, the same as in the Himachal Pradesh edition. The 1 ha trigger for a rack or trap reflects the short time of concentration on the Shivalik slopes and the Kandi fans, so that even a small unbuilt slope delivers sand, gravel and leaves to an inlet in the first burst of a storm. The bulking factor of 1.25 is the factor for a flow that carries a fifth of its volume as sediment (bulking factor = 1 / (1 − sediment fraction by volume)): about the most that a drain can carry and still behave as a water flood; it is to be replaced by a sediment study of the Kandi choes as soon as one is made [TBC]. The 3.0 m limit in item (c) doubles the core's 1.5 m because sand, gravel and branches block openings that leaves and plastic do not. The 1.0 m/s minimum in item (d) replaces the 0.6 m/s of CPHEEO, which is based on carrying fine sand of 0.09 mm, because the choes carry coarse sand and gravel, and the sediment trap where a town drain takes a choe keeps that sand out of the town's drains. The 0.5 m clearance of an outfall invert above the highest surveyed bed in item (f) allows for the bed to rise in a single flood, which is how an outfall to a choe is buried. Few streets in the State are steep, but those of Pathankot, Dhar Kalan and the Shivalik townships are, and on a 10% street the hazard limit of 2.0 m/s is reached when sheet flow on a concrete surface is only about 30 mm deep, which is why item (e) takes the flow off steep carriageways. IRC:SP:42-2014 (cl. 8.5.1) already treats hill roads differently: their side drains are lined because "rolling stones cause high friction", and "culverts are required at closer intervals compared to those in plain areas"; item (g) applies the same to the foothill roads of PWD (B&R), NHAI and the local bodies, and adds that their runoff shall never be discharged onto an unprotected slope, because water discharged onto a slope raises its pore pressure (Chapter 4, Clause 4.11). The clearance of sand and debris after the monsoon, by 31 October, follows from the same evidence: a choe that has left its sand at a crossing in September has blocked it for the next storm, and a storm can come in October, as in 1955.
6.4 Design return periods
6.4.1 The minor system, roads and crossings shall be designed for the AEPs of Table 6.1. Where both a land-use row and a road-class row apply to an element, the rarer AEP (longer return period) governs.
Table 6.1 — Design AEPs for conveyance (matches Clause 2.4)
| Element | Design AEP (return period) | Check event | Basis |
|---|---|---|---|
| Minor system: Ludhiana, Amritsar, Jalandhar, Patiala and SAS Nagar (Mohali) core and other high-density areas | 10% (10-yr) | 1% (100-yr) overland path | This Manual (see Commentary) |
| Minor system: other Class I areas | 20% (5-yr) | 1% overland path | This Manual; CPHEEO Table 4.1 |
| Minor system: other areas | 50% (2-yr) | 1% overland path | This Manual; CPHEEO Table 4.1 |
| Arterial road drainage and crossings | 2% (50-yr) for arterials that are notified evacuation or emergency routes; 4% (25-yr) for other arterials | Next higher AEP: 1% for a 2% design; 2% for a 4% design | This Manual (25–50-yr); split set by this Manual |
| Collector road drainage and crossings | 4% (25-yr) | 2% (50-yr) | This Manual |
| Local road drainage and crossings | 10% (10-yr) | 4% (25-yr) | This Manual |
| Road underpasses and other trapped sags on public roads | 2% (50-yr) | 1% (100-yr) | This Manual (Clause 6.10.5) |
| Airports, railway stations, power stations and other critical infrastructure | 1% (100-yr) in Class I areas; 2% (50-yr) elsewhere | — | CPHEEO 2019 Table 4.1 |
| Major (overland) system, every element | 1% (100-yr) | — | This Manual |
| Building floor levels | 1% level + 0.5 m freeboard | — | This Manual (Clause 6.11) |
6.4.2 Check events. At the check event of Table 6.1, the combined minor and major system shall carry the check-event flow within the 1% AEP limits of Table 6.2 and without water entering any building. The 1% overland path requirement of Clause 6.3.2 applies in addition to the check event.
6.4.3 Higher standards. An approving authority may adopt a rarer AEP for any element, including through the high-powered committee route in Note 2 of CPHEEO Table 4.1. It shall not adopt a more frequent AEP than Table 6.1.
6.4.4 High-density areas. The approving authority shall notify, by map, the high-density areas to which the 10% AEP minor-system standard applies. Until it does, the 10% AEP standard applies to:
- (a) the walled city of Amritsar, about 877 acres (3.55 km²) at a density of 300 to 550 persons per acre (Amritsar Smart City bid 07/ASCL/2018-19, 2018), and the old cores of Ludhiana, Jalandhar, Patiala and Bathinda: the older, densely built area within each Municipal Corporation that the applicable master plan identifies as the walled city, old city or core, outside the urban estates and sectors planned since, with the boundary of each to be confirmed by the Municipal Corporation, DLG and HUD [TBC]; and the village abadis (the Lal Lakir) that lie inside the sectors of SAS Nagar (Mohali), with the boundary to be confirmed by GMADA and the Municipal Corporation SAS Nagar [TBC];
- (b) in every other Municipal Corporation, Municipal Council or Nagar Panchayat, the area that the applicable master plan identifies as the old town, walled city, core or central bazaar, and the abadi (Lal Lakir) of every village that has been taken into the built-up area; and
- (c) any area in a Tier A body where the master plan permits a floor space index above the base value for the zone.
6.4.5 Retrofit. Where an existing drain cannot practicably be enlarged to the Table 6.1 AEP, the shortfall shall be made good by upstream storage (Chapter 4), regional storage (Chapter 7) or an improved major-system path. The approving authority shall record the residual level of service.
Commentary. The values in Table 6.1 match the Clause 2.4 summary and add rows for underpasses and critical infrastructure. They exceed the CPHEEO (2019) national advisory minimums of 5-yr for Class I cities and 2-yr elsewhere (CPHEEO Part A, Table 4.1). Note 2 of that table allows a State committee to adopt higher values. The 10-yr tier for high-density areas follows Gupta (IIT Bombay), who recommends "1 in 10 year for residential-high density", and Malaysia's MSMA 2, which uses 10-yr minor and 100-yr major systems for link houses, apartments, commercial and industrial land. The road values resolve a conflict in Indian codes. IRC:SP:50-2013 recommends 1–2 years for urban road drains. IRC:SP:42-2014 suggests 25 years for urban roadside drains and a check flood at the next higher return period. APWA 5600 (2006) uses 50-yr for arterial, 25-yr for collector and 10-yr for residential street crossings. Table 6.1 adopts the APWA tiers and the IRC:SP:42 check-flood concept. Splitting arterials into 50-yr evacuation routes and 25-yr others has no direct precedent and is set by this Manual. The 50-yr standard for underpasses is likewise set by this Manual, because an underpass is a trapped sag where the failure mode is deep water on a live carriageway. The default high-density areas in Clause 6.4.4 are set by this Manual and apply until the approving authority notifies a map.
6.5 Street hydraulics: spread, depth and flow hazard
6.5.1 Gutter flow. Flow in a triangular kerb-and-gutter section shall be computed with the modified Manning (Izzard) equation:
Q = (Ku / n) · Sx^(5/3) · SL^(1/2) · T^(8/3)
where Q is the gutter flow (m³/s), Ku = 0.376 (SI), n is the Manning roughness of the gutter (Table 6.6), Sx is the cross slope (m/m), SL is the longitudinal slope (m/m) and T is the spread (m). Composite and depressed gutter sections shall be analysed by the methods of FHWA HEC-22 (4th edition, 2024).
6.5.2 Spread and depth limits. Street flow shall not exceed the limits of Table 6.2.
Table 6.2 — Street flow limits
| Road class | Minor design event (Table 6.1) | Check event and 1% AEP event |
|---|---|---|
| Arterial | Spread shall leave at least one through lane in each direction clear of water. No flow across the crown. | Depth ≤ 150 mm at the crown and ≤ 350 mm at the deepest point; hazard limits of Clause 6.5.3 |
| Collector | Spread T ≤ 3 m. No flow across the crown except at a sag intersection. | As above |
| Local | Spread T ≤ 3 m. Flow shall not overtop the kerb. | As above |
| All classes, at intersections | Cross-flow over the crown ≤ 0.03 m³/s at sag intersections and superelevation transitions; none at mid-block sags. | As above |
6.5.3 Flow hazard limits. In the check event and the 1% AEP event, the product of depth (D, m) and velocity (V, m/s) of street and overland flow shall not exceed the limits of Table 6.3.
Table 6.3 — Flow hazard limits for streets and overland flow paths
| Location | Required hazard class (Table 6.4) | Limits |
|---|---|---|
| Carriageways of all roads | H2 or better | D·V ≤ 0.6 m²/s; D ≤ 0.35 m (Table 6.2); V ≤ 2.0 m/s |
| Footpaths, pedestrian crossings, school, hospital and transit-stop frontages | H1 | D·V ≤ 0.3 m²/s; D ≤ 0.3 m; V ≤ 2.0 m/s |
| Notified evacuation and emergency routes | H1 | D·V ≤ 0.3 m²/s; D ≤ 0.3 m; V ≤ 2.0 m/s |
| Overland flow paths in public open space or easements, away from roads | H3 or better, with warning signs | D·V ≤ 0.6 m²/s; D ≤ 1.2 m; V ≤ 2.0 m/s |
Table 6.4 — Combined flood hazard vulnerability classes (reproduced for reference)
| Class | Description | D·V limit (m²/s) | Depth limit D (m) | Velocity limit V (m/s) |
|---|---|---|---|---|
| H1 | Generally safe for vehicles, people and buildings | ≤ 0.3 | 0.3 | 2.0 |
| H2 | Unsafe for small vehicles | ≤ 0.6 | 0.5 | 2.0 |
| H3 | Unsafe for vehicles, children and the elderly | ≤ 0.6 | 1.2 | 2.0 |
| H4 | Unsafe for vehicles and people | ≤ 1.0 | 2.0 | 2.0 |
| H5 | Unsafe for vehicles and people; buildings vulnerable to structural damage | ≤ 4.0 | 4.0 | 4.0 |
| H6 | Unsafe for vehicles and people; all buildings vulnerable to failure | > 4.0 | — | — |
Source: AIDR Guideline 7-3, Technical flood risk management guideline: Flood hazard (2014), Tables 1 and 2, modelled after Smith and Wasko (2012).
6.5.4 Depth and velocity for Clause 6.5.3 shall be taken from the gutter-flow calculation for simple sections, or from a 1D or 2D hydraulic model where flow leaves the kerb-and-gutter section.
Figure 6.1 — Minor and major drainage in a kerbed street. Original drawing for this Manual, adapted from Kansas City Metro APWA, Section 5600 (2006, 5601.8) and FHWA, HEC-22 Urban Drainage Design Manual (4th ed., 2024).
Commentary. The Izzard form of Manning's equation with Ku = 0.376 is used both in FHWA HEC-22 and in the CPHEEO (2019) manual (Part A, Example 5.5, where the constant is written Kc = 0.376). The arterial spread rule (one lane clear) and the 3 m spread for local and collector streets are close to the APWA 5600 (2006, 5604.2) limit of 12 ft (3.66 m) from the back of kerb in each outside lane. The cross-flow limit of 0.03 m³/s is the SI equivalent of the APWA limit of 1.0 cfs at intersection sumps and superelevation transitions, with no cross-flow at mid-block sumps. The 150 mm and 350 mm depth limits are close to the APWA 5600 limits for 1% overflow at road crossings (7 in, about 180 mm, at the crown; 14 in, about 360 mm, at the deepest point). Mumbai's criterion of no flooding above 15 cm (IRC:SP:50-2013, §6.4.1) is a local precedent for the 150 mm crown value.
The hazard classes of Table 6.4 are the combined hazard curves published by the Australian Institute for Disaster Resilience (AIDR Guideline 7-3, 2014), which are modelled after Smith and Wasko (2012). Requiring H2 or better on carriageways means the 1% depth limit of 350 mm (Table 6.2) governs the depth, and the D·V product controls fast, shallow flow on steep streets. H2 is described as "unsafe for small vehicles". Two-wheelers are the dominant vehicles on Punjab streets, so the 1% event must be treated as a road-closure event on all roads except notified evacuation routes, which must meet H1. The assignment of hazard classes to locations in Table 6.3 has no direct precedent and is set by this Manual.
6.6 Inlets
6.6.1 Inlet types. Inlets may be kerb-opening inlets, grate inlets, combination inlets (a grate with a kerb opening) or slotted and trench drains. On public streets:
- (a) kerb-opening or combination inlets shall be used, unless the approving authority accepts grate-only inlets for a specific location;
- (b) inlet openings shall be set at road level, with a gutter depression where practicable, so that water is not held on the carriageway by a raised kerb or footpath;
- (c) grates in carriageways, cycle lanes and footpaths shall be of a bicycle- and pedestrian-safe pattern (Chapter 9, Clause 9.11).
6.6.2 Inlet capacity. The clean capacity of inlets on grade and in sags shall be computed by the methods of FHWA HEC-22 (4th edition, 2024), or from tested ratings published by the manufacturer for the exact grate and kerb-opening geometry. The empirical kerb-inlet equations of CPHEEO (2019) Part A §5.6.2 may be used as a cross-check only.
6.6.3 Clogging factors. The design capacity of every inlet shall be its clean capacity reduced by the clogging factors of Table 6.5:
Table 6.5 — Inlet clogging factors (share of clean capacity assumed lost)
| Inlet type | On grade | In a sag |
|---|---|---|
| Grate | 50% | 50% |
| Kerb opening | 10% | 20% |
| Combination | Apply the grate and kerb factors to each part separately | Apply the grate and kerb factors to each part separately |
Design capacity = (1 − clogging factor) × clean capacity.
6.6.4 Inlet spacing. Inlets shall be located by a sequential calculation that starts at the top of each gutter run. At each inlet, the intercepted flow is computed, and the bypass flow is added to the gutter flow arriving at the next inlet. Spacing shall be such that the spread limits of Table 6.2 are met everywhere in the minor design event. In addition:
- (a) inlet spacing shall not exceed 30 m on kerbed roads, whatever the calculation gives;
- (b) inlets shall be provided at every sag, immediately upstream of pedestrian crossings and intersections, upstream of bridge decks and superelevation transitions, and at the end of every gutter run;
- (c) bypass flow from the last inlet of a run shall not be passed onto a road of a higher class or into private land.
6.6.5 Sag inlets. At a sag on a kerbed road:
- (a) the sag inlet's design capacity (after clogging) shall be not less than the total minor design flow arriving at the sag;
- (b) flanking inlets shall be placed on each side of a sag on any road where ponding could spread beyond the Table 6.2 limits, and at every underpass;
- (c) the ponding at the sag shall comply with Clause 6.10.
6.6.6 Inlet connections. The pipe connecting an inlet to the main drain shall have a diameter of at least 300 mm and shall be laid at a gradient that gives at least 0.9 m/s at the inlet's design flow.
6.6.7 Silt sumps. Every inlet chamber on a public road shall have a silt sump at least 300 mm deep below the invert of its outlet pipe, accessible for cleaning from the surface.
Figure 6.2 — Gutter spread, inlet interception and clogging. Original drawing for this Manual, adapted from FHWA, HEC-22 Urban Drainage Design Manual (3rd ed., 2009; 4th ed., 2024) and CPHEEO, Manual on Storm Water Drainage Systems (2019).
Commentary. The clogging factors are more severe than the APWA 5600 (2006, 5604.2) rating of sump inlets at 80% of theoretical capacity (a 20% reduction), because grates in Punjab streets are routinely blinded by plastic and leaves. CPHEEO (2019) Part A shows solid waste dumped in drains as a primary cause of drain failure (Figures 1.2 and 2.1). APWA 5600 (2006) allows only kerb-opening inlets on public streets; Clause 6.6.1(a) is less strict because combination inlets are useful on flat roads. The 30 m maximum spacing and the treatment of combination inlets in Table 6.5 have no direct precedent and are set by this Manual. Roads on the Punjab plains, where the river slopes "seldom exceed 0.38 m per km" (CWC, Flood Estimation Report for subzone 1(e)), are flat, which shortens the calculated spacing anyway; on the steep streets of the Shivalik fringe gutter flow runs fast and passes inlets by, which Clause 6.3.6(e) deals with. A fixed cap stops a single blocked inlet from leaving a long dry gutter run. The 300 mm silt sump is set by this Manual. It matches the 0.3 m sump shown on the CPHEEO catch-basin detail (CPHEEO 2019, Figure 5.9).
6.7 Pipes and open and covered drains
6.7.1 Uniform flow. Pipe and drain capacity shall be computed with Manning's equation:
V = (1/n) · R^(2/3) · S^(1/2); Q = A · V
where V is the mean velocity (m/s), n is the Manning roughness (Table 6.6), R is the hydraulic radius (m), S is the friction slope (m/m), A is the flow area (m²) and Q is the discharge (m³/s). Where backwater from a tailwater, a junction or a structure affects the water level, a gradually varied flow (standard step) or hydraulic network model shall be used, and the HGL requirements of Clause 6.8 apply.
6.7.2 Manning roughness. Design values of n shall be taken from Table 6.6. For concrete pipes and masonry or concrete drains, the design value shall be not less than the "fair" or "rough" condition value listed, to allow for sediment, biofilm and ageing.
Table 6.6 — Manning's n for design (from CPHEEO 2019)
| Material | Condition | n (CPHEEO) | Minimum design n in this Manual |
|---|---|---|---|
| Cement concrete pipe (collar joints) | Good / fair | 0.013 / 0.015 | 0.015 |
| Spun concrete pipe (RCC, PSC) with S/S joints | Manufacturer's design value | 0.011 | 0.013 |
| HDPE / uPVC pipe | — | 0.010 | 0.011 |
| Plastic (smooth), asbestos cement | — | 0.011 | 0.011 |
| Concrete drain, steel trowelled / wood trowelled | — | 0.014 / 0.015 | 0.015 |
| Sand and cement plaster | — | 0.015 | 0.015 |
| Brick masonry | Good / rough | 0.015 / 0.017 | 0.017 |
| Masonry | Bad condition | 0.020 | 0.020 |
| Rubble set in cement | — | 0.017 | 0.017 |
| Earth channel | Regular, good / ordinary | 0.020 / 0.025 | 0.025 |
| Earth channel | With stones and weeds / poor | 0.030 / 0.035 | 0.035 |
| Earth channel | Partly obstructed by debris or weeds | 0.050 | 0.050 |
| Gutter: concrete | — | 0.013 | 0.013 |
| Gutter: hot-mix asphalt | — | 0.015 | 0.015 |
| Gutter: sprayed seal | — | 0.018 | 0.018 |
Source of the CPHEEO column: CPHEEO (2019) Part A, Table 5.1 (itself from the CPHEEO Manual on Sewerage and Sewage Treatment Systems, 2013) and Table 5.8 (gutters).
6.7.3 Velocity limits. At the minor design flow:
- (a) minimum (self-cleansing) velocity: 0.6 m/s in open and covered drains and 0.9 m/s in pipes;
- (b) maximum velocity: 3.0 m/s in lined drains and in pipes, unless the drain or pipe is designed as a chute under Chapter 9. CPHEEO permits up to 6.0 m/s in plastic or plastic-lined pipes in hilly regions; this may be used in Pathankot and Dhar Kalan on the Shivalik fringe, Talwara, Nangal and Anandpur Sahib and other hill towns with the approving authority's agreement;
- (c) maximum velocity in unlined and vegetated channels: Chapter 9, Table 9.2;
- (d) the Froude number of flow in open and covered drains shall not exceed 0.8 at the design flow, unless the drain is designed for supercritical flow under Chapter 9.
6.7.4 Gradient. Each pipe and drain shall be laid at a gradient that achieves Clause 6.7.3(a). Where flat terrain or a fixed outfall level makes this impossible, the designer shall:
- (a) report the velocity achieved;
- (b) double the sediment allowance of Clause 6.7.8; and
- (c) provide access for mechanical desilting at the spacing of Clause 6.13.2.
6.7.5 Pipe flow condition. Pipes shall be sized so that the minor design flow does not exceed the pipe-full capacity. The greater discharge that a circular pipe carries at about 0.95 of its depth shall not be relied on.
6.7.6 Minimum sizes.
- (a) Pipes: 300 mm internal diameter; 450 mm for public mains.
- (b) Open drains: bed width 0.3 m.
- (c) Covered public drains (drains closed by cover slabs): clear internal width 0.6 m and clear internal depth 0.6 m.
6.7.7 Cover to pipes. Pipes shall have at least 0.6 m of cover to finished level, and at least 0.9 m under carriageways unless a structural design for the traffic load is submitted. Where the seasonal high groundwater table is within 1 m of the pipe crown, the pipe shall be checked for flotation with the pipe empty (CPHEEO 2019, Table 11.2) and anchored where necessary.
6.7.8 Sediment allowance. The design capacity of open drains, covered drains and pipes of 600 mm diameter or more shall be computed with the following depth of sediment at the invert:
- (a) open and covered drains: the greater of 75 mm and 10% of the clear internal depth;
- (b) pipes of 600 mm diameter or more: 5% of the internal diameter;
- (c) pipes below 600 mm: no allowance, but Clause 6.7.3(a) shall be met.
The Manning n for the reduced section shall be that of the drain material in Table 6.6.
6.7.9 Freeboard in open and covered drains. At the minor design flow, the water surface (computed with the sediment allowance) shall be below the top of the drain wall, or below the soffit of the cover slab in a covered drain, by at least the freeboard of Table 6.7.
Table 6.7 — Minimum freeboard in open and covered drains
| Drain | Minimum freeboard | Source |
|---|---|---|
| Bed width up to 300 mm | 100 mm | CPHEEO 2019 Table 5.3 (from IRC:SP:50-2013) |
| Bed width 300–900 mm | 150 mm | CPHEEO 2019 Table 5.3 |
| Bed width 900–1,500 mm | 300 mm | CPHEEO 2019 Table 5.3 |
| Wider drains and engineered channels, Q < 3 m³/s | 450 mm | CPHEEO 2019 Table 5.12 (from IS 7784 (Part 1): 1993) |
| Q 3 to < 30 m³/s | 600 mm | As above |
| Q 30 to < 300 m³/s | 900 mm | As above |
| Q 300 to < 3,000 m³/s | 1,200 mm | As above |
| Q ≥ 3,000 m³/s | 1,500 mm | As above |
| Any roadside drain | Not less than 150 mm | IRC:SP:42-2014 |
| Steep (supercritical) channels | Equal to the flow depth | CPHEEO 2019 §5.3.2 |
At bends, the freeboard shall be measured from the water level on the outside of the bend, including the superelevation Δy = V²T / (2 g rc), where T is the top width and rc the centreline radius (CPHEEO 2019, Eq. 5.29).
6.7.10 Bends and junctions.
- (a) The centreline radius of a bend in a drain shall be at least 3 times the drain width (CPHEEO 2019 §5.3.3). In engineered channels it shall be at least 2 times the top width and not less than 30 m (CPHEEO 2019 Table 5.11).
- (b) Where drains meet, a junction sump shall be provided with an internal width of at least twice the width of the outgoing drain. Incoming drains shall enter at less than a right angle to the outgoing flow, and the outgoing invert shall be below the sump floor so that water does not stand in the sump (CPHEEO 2019 §5.3.4).
6.7.11 Manholes and access chambers on pipes. Manholes shall be provided at every junction, change of size, alignment or gradient, and at the head of every pipe. Spacing on straight runs shall not exceed Table 6.8.
Table 6.8 — Maximum spacing of manholes on straight pipe runs
| Pipe diameter | Maximum spacing |
|---|---|
| 300–600 mm | 40 m |
| 700–1,000 mm | 100 m |
| 1,050–1,400 mm | 150 m |
| 1,500 mm and above | 300 m |
Source: CPHEEO 2019 Table 11.5. Manhole sizes, drops and covers: Chapter 9, Clause 9.12.
Figure 6.3 — Drain sections: freeboard, sediment allowance and access. Original drawing for this Manual, adapted from CPHEEO, Manual on Storm Water Drainage Systems (2019), Tables 5.3 and 5.12, and IRC:SP:50-2013.
Commentary. The n values are those of CPHEEO (2019) Table 5.1. The higher minimum design values have no direct precedent; this Manual sets them because CPHEEO notes that the 0.011 value for spun pipes "may be taken as given by the manufacturer". That is a clean-pipe value, and Punjab drains carry heavy silt and solid waste. The 0.6 m/s minimum velocity is CPHEEO's (Table 5.2), based on carrying 0.09 mm sand (§5.3.1). The 0.9 m/s value for pipes is stricter, because a silted pipe cannot be cleaned as easily as an open drain. The 3.0 m/s maximum is from CPHEEO Table 5.2 (WPCF/ASCE 1982). The Froude limit of 0.8 is from CPHEEO §5.3, which advises avoiding critical flow because the water surface becomes unstable.
The 0.6 m × 0.6 m minimum for covered drains has no direct precedent and is set by this Manual. A covered drain narrower than this cannot be desilted by hand or by small machines through a cover opening, and silted, inaccessible drains were a recurring finding after the floods of Punjab's older cities: in Amritsar the open Ganda Nallahs were converted to double-barrel pipes, and a 2011 PWSSB report found the south-east storm sewer of the walled city "75%" silted with garbage (as quoted in the Amritsar Smart City bid, 2018); and in Jalandhar, where storm drains serve about 5% of the city, the rain is "largely discharged in to the sewer network", resulting in "choking of the pipes" and "back flow of the sewerage water" (Master Plan Jalandhar report). The 0.6 m minimum cover is the value used in the CPHEEO (2019) worked pipe-design computation sheet (Part A, Chapter 5). The 0.9 m cover under carriageways is set by this Manual.
The sediment allowance values (75 mm or 10% for drains, 5% for large pipes) are set by this Manual. No Indian standard sets a sediment allowance for design. Amritsar's experience is that drains run partly full of silt for much of the year, so a capacity computed for a clean section overstates the real capacity.
The CPHEEO freeboard table (Table 5.3) prints the first row as "Beyond 300 mm bed width". Read with the second row ("Beyond 300 mm & up to 900 mm"), the first row must mean "up to 300 mm"; Table 6.7 is written that way. The CPHEEO manhole spacing table (Table 11.5) gives overlapping ranges (700–1,050 mm and 1,000–1,400 mm); Table 6.8 removes the overlap by assigning 1,050 mm to the 150 m class.
6.8 Hydraulic grade line
6.8.1 HGL analysis. For every pipe and covered-drain network, the designer shall compute the HGL for the minor design event and for the check event, starting at the outfall and working upstream. The analysis shall include friction losses and losses at junctions, manholes, bends, inlets, outlets and gates.
6.8.2 Starting water level. The starting (tailwater) level at the outfall shall be the higher of:
- (a) the tailwater level of Chapter 5: mean high water springs (MHWS) plus the sea-level allowance of +0.3 m for minor-system design at tidal outfalls, and the level in the receiving drain, river or tank for the coincident event at other outfalls; and
- (b) the level computed at the outlet pipe from the critical depth and the pipe diameter, (dc + D)/2, where the receiving water is lower.
6.8.3 Minor-event limit. In the minor design event, the HGL shall be at least 0.3 m below the rim of every inlet and the cover level of every manhole and access chamber.
6.8.4 Check-event and 1% limit. In the check event and the 1% AEP event, the HGL may rise above the inlet rims. Water that leaves the minor system shall then be carried by the major system within the limits of Table 6.2 and shall not enter any building. Manholes that can surcharge above ground in these events shall have bolted or locked covers (Chapter 9, Clause 9.12).
6.8.5 Structure losses. Losses at manholes and junctions shall be computed by the energy-based access-hole method of FHWA HEC-22 (2009 or 2024 edition), or by an equivalent method in an approved hydraulic model. A simplified loss-coefficient method (h = K V²/2g) with coefficients from HEC-22 may be used for Tier B networks below 16 ha.
6.8.6 Invert and soffit levels. Where pipe size increases at a manhole, the soffits (crowns) of the incoming and outgoing pipes shall be matched, or the outgoing soffit set lower. The outgoing invert shall not be higher than the lowest incoming invert. Vertical drops in manholes shall follow Chapter 9, Clause 9.12.
6.8.7 Gates and valves. The head loss through flap gates and non-return valves in the open position shall be included in the HGL (Chapter 9, Clause 9.10).
6.8.8 Private connections. Building drainage that connects to a public drain whose 1% HGL is above the building's lowest drainage fitting shall have a non-return valve.
Commentary. The 0.3 m clearance between the minor-event HGL and the inlet rim is set by this Manual. It keeps a margin for losses that a model underestimates, and it stops water from bubbling out of inlets in the event the system is designed for. In Punjab most town drains end in a drain of WRD, in a river held high for days behind a dhussi bandh, in a choe, or in a pumped sump (Clause 5.8.5). In Amritsar the city's storm sewers end in the Tung Dhab and City Outfall drains of WRD, which end in the Hudiara drain (Amritsar Smart City bid, 2018), and the walled-city sewers were designed to surcharge in their manholes in the 2-year storm; in Ludhiana the city's drains end in the Buddha Nallah, whose level is set by its own narrowed reaches and by the Sutlej at Walipur Kalan; and in Jalandhar the rain is "largely discharged in to the sewer network", which chokes and backs up (Master Plan Jalandhar report). A drain whose HGL is started from a free outfall, or computed one length at a time without the receiving drain, its narrowest reach or the river level, fails in exactly that way. An HGL computed from the outfall, with the tidal tailwater of Chapter 5, exposes those errors at design stage. The MHWS plus 0.3 m starting level is from CPHEEO (2019) Table 6.2. The access-hole method is described in HEC-22 from the 2009 edition onward.
6.9 Major system: overland flow paths, easements and drainage reserves
6.9.1 Streets as the primary major system. Streets shall be graded so that the 1% AEP major-system flow is carried along the road reserve to a receiving waterway without being trapped, except at sags designed under Clause 6.10.
6.9.2 Overland flow paths outside streets. Where a major-system path leaves the road reserve, it shall be:
- (a) in public land, in the open space of a layout, or in an easement recorded on the layout approval and the title;
- (b) at least as wide as the 1% AEP flow top width plus 0.5 m on each side, and not less than 3.0 m;
- (c) kept free of buildings, compound walls, fences, fill, stored materials and planting that would obstruct flow;
- (d) graded to a continuous fall with no sag that lacks an outlet; and
- (e) within the hazard limits of Table 6.3.
6.9.3 Compound walls. A compound wall or fence shall not be built across a mapped overland flow path. Where a wall must cross one, it shall have openings with a total area that passes the 1% AEP flow with a 50% blockage, without raising the upstream water level above the limits of this chapter.
6.9.4 Access along open drains. Open drains with a top width of 2 m or more shall have a maintenance access strip at least 3.5 m wide along one bank, connected to a public road at intervals of not more than 500 m.
6.9.5 Supply channels, surplus courses and tanks. Tank supply channels and surplus courses are part of the major system and shall be protected under Chapter 7.
6.9.6 Drainage reserves. A drainage reserve is a strip of land, including the drain, kept free of buildings so that the drain can be maintained, widened and used as a flood path. A drainage reserve shall be provided:
- (a) along every public drain or channel with an internal width of 1.0 m or more that runs through or along a layout or site being developed or redeveloped;
- (b) along every drain or channel shown in an adopted Basin Stormwater Master Plan (Chapter 11), at the width of the future drain in that plan; and
- (c) along every new public drain with an internal width of 1.0 m or more built by a public body.
6.9.7 Width. The reserve shall be not less than the width in Table 6.9, measured from the drain's internal width W. The width is based on the required drain size (for a planned drain, the size in the master plan), not the existing size. Where the access strip of Clause 6.9.4 is wider than the margin in Table 6.9, the wider governs.
Table 6.9 — Minimum drainage reserve width (adopted from PUB Singapore)
| Internal width of drain, W | Open drain | Closed (covered) drain |
|---|---|---|
| 1.0 m to 1.2 m | 3.0 m | W + 0.6 m |
| more than 1.2 m to 3.0 m | W + 2.6 m | W + 1.6 m |
| more than 3.0 m to 4.5 m | W + 3.5 m | W + 1.6 m |
| more than 4.5 m to 6.0 m | W + 4.5 m | W + 3.0 m |
| more than 6.0 m to 9.0 m | W + 6.0 m | W + 3.0 m |
| more than 9.0 m to 25.0 m | W + 7.5 m | W + 3.0 m |
| more than 25.0 m | W + 12.0 m | W + 3.0 m |
For an open drain, the larger part of the margin shall be on the side used for maintenance access.
6.9.8 Use and protection.
- (a) The reserve shall be shown as a separate plot on the layout or site plan and transferred to the Approving Authority free of cost, as roads and open space reservations are. Where the drain is a WRD channel, the reserve is transferred to WRD.
- (b) No building, compound wall, fence, ramp, step, fill or other structure shall be built in the reserve. Compound walls and boundary fences shall stand outside it.
- (c) The access strip in the reserve shall be level and continuous, and connected to a public road. Bollards or posts and chains may be used at entrances to keep out vehicles other than maintenance vehicles.
- (d) Where the reserve is not fenced off, its edge shall be marked with concrete markers at not more than 50 m spacing.
- (e) Services shall cross under the drain, with at least 1.0 m clearance below the invert, or over it on an approved structure. Services shall not run along the reserve inside the drain section.
- (f) A structure within 2 m of the edge of the reserve shall be designed to remain stable when the drain is excavated to 1.0 m below its invert. The design shall be signed by a qualified structural engineer.
- (g) The reserve counts toward the site's open space requirements only where the Approving Authority's rules allow it; it does not reduce any setback required by Chapter 7.
Figure 6.4 — Drainage reserve along an open drain: reserve width from Table 6.9, no-structure zone, access strip on the maintenance side, the 1.0 m service clearance below the invert and the 2 m stability-check zone (Clauses 6.9.6 to 6.9.8). Original drawing for this Manual, adapted from PUB Singapore, Code of Practice on Surface Water Drainage (7th ed., with Addendum No. 3, 2025), clauses 5.1, 5.3, 9.6 and 9.7 and Appendix 1.
Commentary. Drainage reserves follow Singapore, where "the width of a drainage reserve is based on the required drain size" and the reserve is set aside as a separate plot, "kept free of all encumbrances" (PUB Code of Practice on Surface Water Drainage, 7th ed. with Addendum No. 3, 2025, cl. 1.1). Table 6.9 reproduces PUB's Appendix 1 widths. Clauses 6.9.8(b) to (f) follow PUB clauses 5.1 (no structure within a drain or drainage reserve), 5.3 and 5.3.1 (stability for excavation 1.0 m below the invert; engineer's calculations within 2 m of the reserve), 9.6 (level, continuous access, with bollards or posts and chains) and 9.7 (markers at a maximum of 50 m). The 1.0 m clearance for services crossing under a drain is from PUB's development-plan guidance. In Punjab, buildings and compound walls are often built up to the edge of a drain, so it cannot be widened or desilted by machine. Reserving the land when a plot is developed or redeveloped is the cheapest time to secure it, because widening later needs land acquisition. Basing the width on the master-plan drain size (6.9.6(b)) protects the land a future drain will need. Punjab has no statutory reserve width along a drain, choe or nala. Neither building instrument sets a setback from any river, nallah, choe, pond or canal: the Punjab Urban Planning and Development Building Rules 2021 set setbacks by the height of the building and the Uniform Zoning Plan only (PUDBR 2021 (as amended), r.26), and require the plans to show the "methods of disposal of waste water, sewerage and storm water" and the "surroundings up to a distance of fifteen metres" (r.11); the Punjab Municipal Building Bye-Laws 2018 require only that, on a large project, "The inlet and outlet point of natural drain system should be maintained with adequate size of channel" (PMBBL 2018 (as amended), Table 15.1, item 1). The sections of the Punjab Municipal Corporation Act 1976 and the Punjab Municipal Act 1911 that vest drains in a municipality or bar building over them were not read [TBC]. The only instrument found that draws a line along a channel is section 38 of the Punjab Canal and Drainage Act 2023 (Punjab Act 11 of 2023), which carries over section 55 of the Northern India Canal and Drainage Act 1873: the State may notify limits along "any river, stream or drainage-channel" within which an obstruction is prohibited or is to be removed, and the reach so notified "shall be held to be a drainage-work", from which the Divisional Canal Officer may have an obstruction removed (s.39), and to construct or alter a drainage work, or to alter the flow of a river or stream so as to endanger one, is an offence punishable with a fine of ₹5,000 to ₹50,000 or imprisonment of up to six months (s.52). WRD reports 393 of 869 drains, choes and rivers notified under section 55 (WRD website), and the press 514 of 935 notified under the 2023 Act (as reported); no list of the notified drains and no notification giving a width was found [TBC]. WRD's method, which it described to CWC in 2024, is to compute the 100-year flood by Gumbel's method and the waterway by Lacey's formula and to notify that area, in which "no construction is to be allowed" (Chief Engineer, Drainage-cum-Mining & Geology, 2 May 2024); but the one floodplain zone found, on the Sutlej in Ferozepur and Tarn Taran districts (4 March 2024), was declared as the land between the embankments, about 4.5 km apart, although the Lacey width of the 100-year flood of 5,34,441 cusecs is 0.58 km (WRD affidavit in NGT OA 303/2023), and the NGT found "no material … indicating the exercise for demarcating the flood plain zone" (order of 14 March 2024, as quoted). Two lines have been drawn on particular channels. Along the Patiala ki Rao, notified under section 55 on 4 March 2013 against construction in or covering of the nadi, the High Court's Local Commissioner reported pillars "measuring 200 Ft." apart fixed in Chandigarh and still pending on the Punjab side (report of 8 January 2024 in CWP 5901/2017): a court-monitored width for one choe, not a norm of WRD. Along the Buddha Nallah, a road built by the Municipal Corporation Ludhiana is alleged before the NGT to have cut the channel's width "from 58 feet to 35 feet" (OA 327/2025): an allegation, cited as one, not a finding. The Master Plan Jalandhar report proposes that no construction be allowed within at least 200 m of the Chitti Bein "untill concrete bandh is constructed", except for a 30 m buffer zone from its bank, and a 30 m strip of plantation along the Black (Kala Sanghian) Bein (13.8.6 and 13.8.7): plan proposals, whose notified status was not seen. The NoC of the drainage wing for projects "within the 150-metre radius" of a water body was announced by the Water Resources Minister on 20 September 2023 (as reported), but no order was found, and this Manual does not apply it [TBC]. WRD has stated that no notified drain may be realigned "without prior permission/NOC from competent authority of Water Resources Department" (NGT OA 279/2024). None of these gives a reserve width along a drain. This Manual therefore gives the reserve a width, as its own proposal and not as a statutory width: a hydraulic corridor made up of the reserve of Table 6.9, based on the drain size needed to carry the design flow (Clause 6.9.7), the access strip of Clause 6.9.4 on the access bank, and, along a choe, rao, nadi, bein or natural drain, or a drain of WRD, that drains 8 ha or more, the setbacks of Clause 7.4 measured from its top of bank, with a Zone 1 of at least 15 m; where a 1% AEP flood extent has been mapped, it governs Zone 2, and where a notification under section 38 (or section 55), a floodplain zone or a court has set a wider line, such as the Sutlej floodplain zone in Ferozepur and Tarn Taran districts or the 200 ft pillared width of the Patiala ki Rao, that line applies for as long as it binds (Chapter 7). The corridor is to be superseded by a notification under section 38 of the Punjab Canal and Drainage Act 2023 where one exists. For this Manual, every nala, choe, rao, nadi and bein that drains 8 ha or more is a natural channel under Clause 7.4.1(b), whoever maintains it and whether or not it is lined, piped or covered, and land recorded in the revenue (khasra) records as a nala, choe, rao, chhappar, toba or dhab is part of the channel or waterbody whatever its present use (set by this Manual). The corridor is set by this Manual. It should be shown in the master plans under the Punjab Regional and Town Planning and Development Act 1995, in the layouts of PUDA, GMADA, GLADA and the other development authorities and in the plans sanctioned under PMBBL and PUDBR, with the khasra map and WRD's list of notified drains overlaid, rather than made a new NoC.
The reserve matters because the drains of Punjab's towns are divided among owners, and no rule divides them. WRD's Drainage-cum-Mining & Geology wing holds the rivers, choes, notified drains and dhussi bandhs, among them the Buddha Nallah in Ludhiana and the Tung Dhab and City Outfall drains in Amritsar, which are "maintained by drainage division of Irrigation department" (Amritsar Smart City bid, 2018); WRD's canal wing holds the canals, distributaries and watercourses; PUDA and the development authorities build the sector drains of their urban estates and schemes, as GMADA does with the storm sewer under the sector roads 92 and 92-Alpha of SAS Nagar (GMADA, 2021); the Municipal Corporations, Councils and Nagar Panchayats, under DLG, hold the street drains and sewers within their limits; PWSSB and PMIDC build drains and sewers for the local bodies, PMIDC as the State's nodal agency for AMRUT and for the Buddha Nallah project (CAG Report No. 7 of 2021; PMIDC, 2020); the Smart City companies of Ludhiana, Jalandhar and Amritsar build storm-drain works in their areas (CAG Report No. 7 of 2021); PWD (B&R) and NHAI hold the drains of their roads; the chhappars belong to the Gram Panchayats as shamlat land, under the Department of Rural Development and Panchayats; the Department of Soil and Water Conservation builds check dams in the Kandi; and land closed under the Punjab Land Preservation (Chos) Act 1900 is administered by a department not confirmed during research [TBC]. The Punjab Canal and Drainage Act 2023 excludes from a "drainage work" the "removal of sewage from towns, villages or any other habitat" (s.2(7)). No rule dividing the drains of WRD from those of the local bodies or the development authorities was found during research. For the purposes of this Manual, and until the State issues such a rule [TBC], the drains are assigned as follows: rivers, choes, raos, nadis and beins, every drain notified under section 38 (or section 55), every drain that WRD maintains, including the Buddha Nallah, the Tung Dhab, City Outfall and Hudiara drains, the Kala Sanghian drain, the Sakki/Kiran, Patti and Kasur nallahs and the Chand Bhan drain, and the dhussi bandhs, flood embankments and river-training works, to WRD's Drainage-cum-Mining & Geology wing; canals, branches, feeders, distributaries, minors, kassis and watercourses, with their siphons and escapes, to WRD's canal wing; the sector and scheme drains of an urban estate or scheme to PUDA or the development authority (GMADA, GLADA or another) until they are transferred to the local body; the public drains, street drains and sewers within a Municipal Corporation, Municipal Council or Nagar Panchayat to that body, under DLG; drains built by PWSSB, PMIDC or a Smart City company to the body for which they were built, on completion; road drains, culverts and cross-drainage works to PWD (B&R) or NHAI on their roads; chhappars and village drains to the Gram Panchayat; check dams in the Kandi to the Department of Soil and Water Conservation, and the Kandi low dams to WRD; and land closed under the Punjab Land Preservation (Chos) Act 1900 to the department that administers it [TBC], with the choes through it under WRD (set by this Manual). Under Clause 6.9.8(a), the reserve along a WRD drain is transferred to WRD. Where a channel's status is disputed, the corridor follows the channel and not its name: the Buddha Nallah is both a seasonal tributary of the Sutlej and the trunk drain of Ludhiana, the N-Choe leaves Chandigarh as a choe and reaches the Ghaggar as the Pachisdhara drain (CPCB, 2024), and a complaint about the "N-Choe" near Manauli was found by WRD to concern the Jagatpura drain (NGT OA 279/2024). No design return period was found for any drain in the State other than two project choices, both of 2 years: the trunk storm sewers of the walled city of Amritsar (Amritsar Smart City bid, 2018) and the rejuvenated Buddha Nallah (PMIDC, 2020); and under AMRUT no storm-drain work was done up to 2020 (CAG Report No. 7 of 2021). Until a Basin Stormwater Master Plan is adopted (Clause 6.9.6(b)), the required drain size of Clause 6.9.7 is the size computed by the designer under this chapter. This Manual does not prescribe a lined or an unlined section. It requires the section to meet the velocity limits of Clause 6.7.3 and Chapter 9, and a reserve wide enough for an unlined or vegetated section is a reserve that keeps both options open.
Commentary. Requirements 6.9.2(b)–(e), 6.9.3 and 6.9.4 have no direct precedent and are set by this Manual. Compound walls around individual plots are almost universal in Punjab and are one of the most common ways that overland flow paths get blocked. The 50% blockage assumption for wall openings is set to match the grate clogging factor of Clause 6.6.3. The 3.5 m access width is set by this Manual, sized for a small excavator or desilting vehicle. For comparison, APWA 5600 (2006, 5608.4) requires a 15 ft (about 4.6 m) maintenance access strip for detention facilities.
6.10 Ponding at sags and low points
6.10.1 Minor event. At every sag, the minor design flow shall be removed by inlets (after clogging) with ponded spread within Table 6.2.
6.10.2 1% AEP event. At every sag:
- (a) the ponded depth shall not exceed 350 mm at the deepest point of the carriageway;
- (b) a surface overflow route shall be provided (for example over a lowered kerb and footpath into a designated overland flow path), so that the ponding level cannot rise above the overflow level; and
- (c) building floor levels around the sag shall comply with Clause 6.11.
6.10.3 Fully-blocked check. At sags, the 1% AEP ponding level shall also be computed with the minor system fully blocked and all flow leaving by the surface overflow route. Floor levels around the sag shall be set from the higher of the two ponding levels.
6.10.4 Trapped sags. Where a sag has no surface overflow route, the inlets and conduits (after clogging) shall carry the 1% AEP flow, and the approving authority shall agree the arrangement.
6.10.5 Road underpasses. Underpasses and other trapped sags on public roads shall:
- (a) be drained by a minor system (with pumping under Chapter 9, Clause 9.9, where gravity drainage is not possible) designed for the 2% AEP (50-yr) flow, checked at the 1% AEP flow;
- (b) have flanking inlets at both approaches to intercept flow before it reaches the low point;
- (c) be protected from inflow from surrounding streets by raised approach crests where practicable; and
- (d) have depth markers and automatic warning or closure signals that operate at 150 mm depth on the carriageway.
Commentary. The fully-blocked check, the trapped-sag rule and the underpass requirements have no direct precedent and are set by this Manual. No record of a flooded underpass in a Punjab city, with its depth and duration, was found during research [TBC]. Jalandhar's master plan report lists only two underpasses in the city, one under the main railway line and one on the bypass road, and proposes more under the same railway (Master Plan Jalandhar report), and the urban floods of 1 to 3 September 2025 in SAS Nagar, Ludhiana, Jalandhar and Amritsar were reported without depths (as reported). The requirements are set so that the underpasses now being built under the railways and highways of the State do not repeat the failures recorded in the cities of other States. Clause 6.10.5(d) links the 150 mm crown depth limit of Table 6.2 to the point at which traffic should stop.
6.11 Building floor levels
6.11.1 The lowest habitable floor, and every opening through which water could enter a building (doors, ventilators, basement ramps, lift pits and service entries), shall be at least 0.5 m above the 1% AEP flood level.
6.11.2 The 1% AEP flood level is the highest of:
- (a) the 1% AEP major-system water level in the street or overland flow path next to the building (Clauses 6.9 and 6.10, including the fully-blocked check at sags);
- (b) the 1% AEP flood level of any river, channel, tank or waterbody (Chapter 7); and
- (c) the 1% AEP level with the tailwater of Chapter 5; and
- (d) where the Approving Authority has adopted a 1% AEP flood depth map under Clause 7.3.4, the ground level at the plot plus the mapped 1% AEP depth.
6.11.3 Default where no level has been computed. For a plot below the Chapter 1 thresholds, or where no 1% AEP level has been computed for the plot, the lowest habitable floor and openings shall be at least the higher of:
- (a) 0.65 m above the highest crown level of the road on which the plot fronts; and
- (b) where an adopted 1% AEP flood depth map covers the plot, the ground level plus the mapped 1% AEP depth plus 0.5 m.
The Approving Authority may adopt a regional map, such as a State-approved map or a published national map of modelled 1% AEP flood depth (for example the India Flood Atlas), until a local study replaces it. A map that does not model storm surge shall not be used in place of Clause 6.11.6.
6.11.4 Basements. The crest of every basement ramp and the sill of every basement opening shall meet Clause 6.11.1. Basement drainage shall be pumped to the surface drain through a non-return valve.
6.11.5 Services. Electrical panels, transformers, standby generators, lift machinery and pumps that serve a building shall meet Clause 6.11.1.
6.11.6 Coastal band. The coastal band is the land within 500 m landward of the High Tide Line along the sea front, as defined by the CRZ Notification, 2019, with the High Tide Line as demarcated in the approved Coastal Zone Management Plan. Where the Survey of India Hazard Line lies further inland than 500 m, the band extends to the Hazard Line. Within the coastal band, in addition to Clauses 6.11.1 to 6.11.5:
- (a) the lowest habitable floor and every opening shall also be at least 0.5 m above the coastal flood level, which is the 1% AEP still-water level (Clause 5.7.3(b), Annex 5A) plus twice the sea-level allowance of Clause 5.7.4 (so at least 0.6 m), because buildings have a design life of more than 50 years (Clause 5.7.4(c));
- (b) where the plot fronts the open beach, the coastal flood level shall include wave set-up from a site study;
- (c) no habitable room, electrical service room or plant listed in Clause 6.11.5 shall be placed in a basement; and
- (d) every basement opening, ramp crest and ventilation opening shall meet Clause 6.11.6(a).
Clause 6.11.6 does not authorise any construction that the CRZ Notification prohibits. Where both apply, the stricter governs.
Figure 6.5 — Coastal band: the minimum floor level built up from the 1% AEP still-water level, twice the sea-level allowance, wave set-up where the plot fronts the open beach and 0.5 m freeboard; and the extent of the band, to 500 m from the High Tide Line or to the Hazard Line where it lies further inland (Clause 6.11.6). Original drawing for this Manual, adapted from the CRZ Notification, 2019 (para 1(i) and Annexure IV) and PUB Singapore, Code of Practice on Surface Water Drainage (7th ed.), cl. 2.1.1.
Commentary. The 0.5 m freeboard above the 1% AEP level follows the DID Malaysia 2008 checklist (platform and lowest floor at 100-yr ARI + 0.5 m). It is more than the APWA 5600 (2006, 5601.8 A2) requirement of 1 ft (about 0.3 m) above the 1% stage. The 0.65 m default in Clause 6.11.3 is derived from the other limits of this chapter, not separately sourced: the 1% water level at the crown may be up to 150 mm (Table 6.2), plus the 0.5 m freeboard. It has no direct precedent and applies to plots where no flood level exists. URDPFI (2015) also links minimum plinth levels to flood frequency in its flood-plain zoning, which is covered in Chapter 7.
Clause 6.11.3(b) lets a small plot use a mapped 1% AEP depth where no local study exists, instead of guessing from the road level alone. Modelled national maps are coarse (about 30 m), and most model rainfall and river flooding but not storm surge, which is why 6.11.3 keeps the road-crown check and Clause 6.11.6 sets a separate coastal rule.
The coastal band of Clause 6.11.6 uses the 500 m line of the CRZ Notification, 2019 (G.S.R. 37(E), para 1(i): "the land area from High Tide Line ... to 500 meters on the landward side"), because every coastal authority already maps it and it needs no new survey. The Hazard Line, demarcated by the Survey of India to show the extent of flooding and shoreline change, extends the band where it lies further inland (CRZ Notification, 2019, Annexure IV). The band takes the coastal level from the joint-case still-water level of Chapter 5 rather than from the rainfall map. The higher standard reflects the setting: a coastal flood rises with the sea, cannot be drained while the tide is up, and will rise further with the sea. Singapore takes the same approach with a fixed minimum platform level of 4.0 m above datum on its southern coast and 4.5 m on its northern coast, whatever the rainfall flood level (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 2.1.1). Each coastal State's tide and surge levels vary too much along its coast for one fixed level, so this Manual uses the computed still-water level instead. Using twice the sea-level allowance applies the sensitivity case of Clause 5.7.4(c) as the design case, because a building, unlike a drain, cannot easily be raised later. The basement restriction in 6.11.6(c) is set by this Manual: a basement in the coastal band fills from the sea as well as from rain, and cannot be pumped out to a tide-locked outfall. Punjab has no coast, no High Tide Line and no Coastal Regulation Zone, so the coastal band is empty in the State and Clause 6.11.6 does not apply there. Clauses 6.11.3 and 6.11.4 matter instead. The two building instruments of the State set different plinths. In municipal areas the plinth shall be "not less than 450 mm from the surrounding ground level", and the building sited so "that adequate drainage of the site is assured" (PMBBL 2018 (as amended), cl. 5.2.1.1); outside them and in the schemes of PUDA and the development authorities, a residential plot's plinth is 900 mm "from the crown of adjoining road in front", and other buildings' "450mm or as specified by competent authority" (PUDBR 2021 (as amended), r.3(A)). Both keep surface water out of basements in words only: PMBBL requires that "surface drainage does not enter the basement", that the basement be safe "in relation to underground water table/spring level", and that a basement's sewage be pumped "to avoid any risk of the sewerage or sludge heading back into the basement" (PMBBL 2018, cl. 4.23(vi) to (viii)); PUDBR bars a basement in a "No construction Zone" or "Master Plan Green area", sets the ceiling of a first basement 0.9 m to 1.2 m above the average surrounding ground, and requires that "Adequate arrangement shall be made that surface drainage does not enter the basement" (PUDBR 2021, r.30(5)(iii) and (iv)). Neither sets a level related to a flood, and no amendment touching these provisions was found [TBC]. Clause 6.11.3, which sets the lowest habitable floor and every opening 0.65 m above the road crown where no flood level has been computed, and Clause 6.11.4, which applies the same level, or 0.5 m above the 1% AEP flood level, to the crest of every basement ramp and the sill of every basement opening, are set by this Manual. The PUDBR plinth of 900 mm above the road crown meets the 0.65 m of Clause 6.11.3; the PMBBL plinth of 450 mm is measured from the surrounding ground, not the road, and can be lower than it, so in municipal areas Clause 6.11.3 is the stricter and the two can be met together by building to it. In the waterlogged south-west, the Sirowal belt and the bet lands a basement also lies in the groundwater, and the flotation check of Clause 4.12.3 applies to it. Within limits notified under section 38 of the Punjab Canal and Drainage Act 2023 (or section 55 of the 1873 Act), in the Sutlej floodplain zone of Ferozepur and Tarn Taran districts and along the Patiala ki Rao, the lines of Chapter 7 also apply.
6.12 Culverts and road crossings
6.12.1 Design AEP. A culvert or bridge that carries a road over a drain or waterway shall pass the design AEP flow of Table 6.1 for that road class without overtopping the road, and with the headwater limits of Chapter 9, Clause 9.4. Where the waterway is a State highway or national highway crossing, the design AEP shall also be not less than that of IRC:SP:42-2014 §7.1.4 for the span. The rarer AEP governs.
6.12.2 Check event and 1% AEP. At the check event and at the 1% AEP event, the crossing and the road together shall pass the flow:
- (a) with overtopping depth ≤ 150 mm at the road crown and ≤ 350 mm at the deepest point of the road;
- (b) within the hazard limits of Table 6.3;
- (c) with no overtopping at all of arterial roads that are notified evacuation routes; and
- (d) without raising the 1% AEP flood level at any upstream building or property boundary above the level for the existing condition, unless the affected owners and the approving authority agree.
6.12.3 Where overtopping is not permitted. Overtopping in the 1% AEP event is permitted only where the structure span is less than 6 m and the 1% AEP peak flow is not more than 7 m³/s, unless a guard rail is installed downstream of the overtopping section. Otherwise, the crossing shall pass the 1% AEP flow without overtopping.
6.12.4 Blockage check. The 1% AEP check shall be repeated with a blocked inlet:
- (a) 50% of the inlet area blocked for culverts with a span or diameter below 1.5 m; and
- (b) 20% blocked for larger culverts.
The results of this check shall meet Clause 6.12.2(a) and (d).
6.12.5 Minimum size. Culverts under public roads shall be at least 900 mm in diameter, or 900 mm × 900 mm for box culverts.
6.12.6 Hydraulic design. Culvert hydraulics, including inlet and outlet control, tailwater, road overtopping and outlet protection, shall follow Chapter 9, Clauses 9.4 and 9.6.
Commentary. The design AEPs are those of Table 6.1. The overtopping limits are the street-depth limits of Table 6.2. The span and flow threshold in Clause 6.12.3 is the SI conversion of APWA 5600 (2006): overtopping allowed only where the structure span is under 20 ft and the 1% peak is 250 cfs or less, unless a downstream guard fence is installed. IRC:SP:42-2014 (§7.1.4) sets 25-yr for NH/SH culverts up to 2 m span and 50-yr for 2–6 m spans. The blockage percentages in Clause 6.12.4 and the 900 mm minimum size have no direct precedent and are set by this Manual. The 50% value matches the grate clogging factor.
6.13 Punjab construction-practice requirements
6.13.1 Covered roadside drains. Where a roadside drain is covered by slabs that form a footpath:
- (a) it shall be designed as an open channel with the freeboard of Table 6.7 measured to the soffit of the cover slab, and its HGL shall meet Clause 6.8 measured to the footpath and inlet levels;
- (b) road runoff shall enter through openings in the drain wall at road level (Clause 6.6.1(b)), each with a silt sump (Clause 6.6.7), at the spacing of Clause 6.6.4;
- (c) footpath runoff shall enter through slots or grated openings in the cover, not by ponding on the footpath; and
- (d) the clear section shall meet Clause 6.7.6(c).
6.13.2 Removable covers and access openings. Covered drains shall have:
- (a) removable cover panels at not more than 10 m centres, each at least 0.6 m long and spanning the full clear width, with recessed lifting points, liftable by two workers or by a hand-operated lifting device, and flush with the footpath;
- (b) access chambers with a clear opening of at least 0.6 m × 0.6 m at every junction, bend and change of section, and at not more than 30 m centres on straight runs; and
- (c) covers rated for the traffic or pedestrian load at their location (Chapter 9, Clause 9.11).
6.13.3 Silt traps. In addition to the inlet sumps of Clause 6.6.7, silt trap chambers shall be provided:
- (a) upstream of every culvert under an arterial road;
- (b) upstream of every pump station and detention facility; and
- (c) at every outfall to a tank, river or other waterbody (with the gross pollutant trap required by Chapter 8).
Each silt trap shall be sized to hold the sediment expected between scheduled cleanings, using the sediment yield in Annex 6B, and shall be reachable by a desilting vehicle.
6.13.4 Garbage and gross pollutant screens. Screens shall be provided where an open drain enters a covered drain, a pipe or a culvert, and at outfalls under Chapter 8. Each screen shall:
- (a) be designed under Chapter 9, Clause 9.8;
- (b) have a bypass or overflow, so that a fully blinded screen does not flood properties or the road beyond the limits of this chapter; and
- (c) be checked hydraulically with 50% of its area blocked.
6.13.5 No building over drains. No structure other than an approved crossing or a removable cover shall be built over a public drain. Shop frontages, ramps and steps that cross a drain shall be removable or shall leave access openings that meet Clause 6.13.2.
6.13.6 Utilities. No water main, sewer, power or telecom cable, gas pipe or duct shall be laid along, or pass through, the flow area or freeboard of any drain. A utility that must cross a drain shall:
- (a) cross above the cover soffit or below the drain invert, inside a sleeve; and
- (b) be shown on the drainage plan with its level.
Where an existing utility crossing obstructs a drain, its area shall be deducted from the drain section, with a 50% blockage allowance for the debris it traps, until the utility is relocated. The utility owner shall relocate it when the drain is rebuilt.
6.13.7 Sewage. No sewage connection is permitted to a storm drain (Chapter 8). Covered drains shall be built with sealed joints where they run next to sewers.
6.13.8 Edge protection. Open drains deeper than 1.0 m beside a footpath, a carriageway or a public open space shall have railings or barriers. Open drains of any depth shall not be left uncovered across a footpath.
6.13.9 As-built levels. The as-built invert levels of every public drain, pipe and manhole shall be surveyed and submitted (Chapter 10). Inverts shall be within ±15 mm of design. An HGL re-check shall be submitted where they are not.
6.13.10 Desilting. Public drains shall be desilted before the south-west monsoon each year, as set out in Chapter 10.
Commentary. Clause 6.13 has no direct precedent; this Manual sets it on the basis of Punjab practice. Most urban drains in the State are covered roadside drains under footpaths. They are often built with continuous cast-in-situ slabs and few openings, so they cannot be cleaned and fill with silt and solid waste within a season. CPHEEO (2019) notes that uncovered channels "are prone to the dumping of garbage" (Part A, Ch 2), which is why the drains are covered. Covering without access openings simply moves the problem out of sight. NDMA (2010) recommends that pre-monsoon desilting be complete by 31 March. In Punjab the south-west monsoon normally sets in at Jalandhar on 26 June, at Patti on 28 June and at Ludhiana on 1 July, and normally withdraws from all three on 21 September; by 1 October it has withdrawn from most of the State (IMD, new normals, Pai et al., 2020). Paddy is transplanted from 1 to 9 June, district by district (as reported), so the plains are wet before the monsoon arrives, and large storms fall in June: Patiala recorded 160.6 mm on 8 June 2000 (IMD). So Clause 6.13.10 refers to the south-west monsoon, and Chapter 10 requires the desilting of drains, choes and chhappars to be complete by 15 June; the gates, flap gates on the dhussi-bandh outfalls, pumps, siphon crossings, inlets and choe crossings are certified ready and test-run by 25 June (Clauses 5.11.5 and 5.12.9), before the normal onset everywhere in the State; and pumps and gates stay on standby until 15 October, because the State's storm of record fell on 4–5 October 1955, after the normal withdrawal, and the dams were still spilling into September in 2023 and 2025. In sub-area PB-A the sand and debris that the choes leave at crossings, culverts and inlets are cleared again after the monsoon, by 31 October (Clause 6.3.6(a)). No State order fixes a date for drain cleaning (as reported): the customary target is 30 June, set in 2023 by the Chief Minister for "cleansing of waterways" and in 2026 by the Minister for Local Government for sewer desilting in Ludhiana and by the Deputy Commissioner of Kapurthala for drains, sewers and storm systems (all as reported), and 30 June is later than the normal onset at Jalandhar and Patti. These dates are therefore set by this Manual.
Neither building instrument protects a drain, choe or nala from being covered or built over. The Punjab Municipal Building Bye-Laws 2018 require only that, on a large project, "The inlet and outlet point of natural drain system should be maintained with adequate size of channel" (PMBBL 2018, Table 15.1, item 1), and the Punjab Urban Planning and Development Building Rules 2021 require the plans to show the "methods of disposal of waste water, sewerage and storm water" (PUDBR 2021, r.11); the sections of the Punjab Municipal Corporation Act 1976 and the Punjab Municipal Act 1911 on municipal drains were not read [TBC]. Natural drains, choes and the drains of WRD are open channels with a drainage reserve (Clause 6.9), and should not be covered, decked or built over; within limits notified under section 38 of the Punjab Canal and Drainage Act 2023 the Divisional Canal Officer may have an obstruction removed (s.39), and the 2013 notification on the Patiala ki Rao authorises action against any construction in, or "covering" of, the nadi. Covered drains silt: in Amritsar the Ganda Nallahs were converted to double-barrel pipes, and a 2011 PWSSB report found the south-east storm sewer "75%" silted with garbage (as quoted in the Amritsar Smart City bid, 2018). Where a drain is covered, Clause 6.13.2 applies to it in full.
Clause 6.13.7 is not yet the practice. Punjab's largest urban drains carry sewage and industrial effluent: the Buddha Nallah takes about 700 MLD of treated and untreated wastewater to the Sutlej (River Rejuvenation Committee, 2025), and before its confluence its BOD was 161 mg/l, its COD 456 mg/l and its suspended solids 328 mg/l in April 2024, against the general standards of 30, 250 and 100 mg/l (CPCB reply in NGT OA 327/2025); in Amritsar the road-side drains "are connected to the sewerage system typically at the road junctions, thus making the sewerage system as combined system" (Amritsar Smart City bid, 2018). The Punjab Canal and Drainage Act 2023 excludes the "removal of sewage from towns, villages or any other habitat" from a drainage work (s.2(7)), so sewage has no lawful place in a drain of WRD, and the Building Rules forbid an absorption pit from having an outlet into "any sewer, storm water, drain or surface drain" (PUDBR 2021, r.45(8)). Clause 8.9 sets how dry-weather flow in storm drains is surveyed and intercepted until the connections are removed, including the rule that interception shall not reduce the capacity of the drain (Clause 8.9.5(b)).
The 10 m and 30 m spacings and the ±15 mm tolerance have no direct precedent and are set by this Manual. Clause 6.13.6 responds to the common sight of water mains and cables running through drains. Each one traps debris and reduces the section. Mechanical cleaning through cover openings, rather than manual entry, is assumed throughout, consistent with the Prohibition of Employment as Manual Scavengers and their Rehabilitation Act, 2013.
6.14 Outfalls
6.14.1 Outfalls shall be designed for the tailwater conditions of Chapter 5. Outfalls below the 1% AEP still-water level shall have flap or tide gates or non-return valves (Chapter 5 and Chapter 9, Clause 9.10).
6.14.2 Outfall protection and energy dissipation shall be designed under Chapter 9, Clause 9.6. Outfalls to tanks and waterbodies shall also meet Chapters 7 and 8.
6.15 Submittal requirements
Every conveyance submittal shall include a Conveyance Design Report (Form 6-1) containing:
- a catchment plan showing sub-catchments, the minor system, inlet locations and the major-system overland flow paths for the 1% AEP event (Clause 6.3.2);
- the land-use and road-class AEP adopted for each element (Table 6.1), and the high-density area status;
- design flows, with the rainfall sheet of Chapter 2 and the method of Chapter 3;
- gutter spread, depth and D·V checks for the minor, check and 1% events (Tables 6.2 and 6.3);
- an inlet schedule with clean capacity, clogging factor, design capacity and bypass flow (Clause 6.6);
- pipe and drain design tables with n, velocity, sediment allowance and freeboard (Clause 6.7);
- HGL profiles for the minor and check events, with the tailwater used (Clause 6.8);
- sag ponding levels, including the fully-blocked check (Clause 6.10);
- a floor-level schedule for every building (Clause 6.11);
- culvert and crossing calculations (Clause 6.12 and Chapter 9); and
- a utilities-crossing schedule and access-opening layout for covered drains (Clause 6.13).
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Volume I, Part A: Engineering Design. Tables 4.1, 5.1, 5.2, 5.3, 5.8, 5.11, 5.12, 6.2, 11.2, 11.5; §5.3, §5.6.2, Fig. 5.9. https://www.mohua.gov.in/static/uploads/2025/10/8a2456c722036d78c72a698898ef846d.pdf
- PUB Singapore (2018, with Addendum No. 3, April 2025). Code of Practice on Surface Water Drainage, 7th edition. Clauses 1.1, 2.1.1, 5.1, 5.3, 9.6, 9.7 and Appendix 1 (Drainage Reserve Requirements). https://www.pub.gov.sg/-/media/PUB/PDF/Code-of-Practices-and-Submission-Guidelines/Surface-Water-Drainage/Code-of-Practice-on-Surface-Water-Drainage.pdf
- Indian Roads Congress (2013). IRC:SP:50-2013, Guidelines on Urban Drainage (First Revision). https://law.resource.org/pub/in/bis/irc/irc.gov.in.sp.050.2013.pdf
- Indian Roads Congress (2014). IRC:SP:42-2014, Guidelines on Road Drainage (First Revision). https://law.resource.org/pub/in/bis/irc/irc.gov.in.sp.042.2014.pdf
- Bureau of Indian Standards. IS 7784 (Part 1): 1993, Code of practice for design of cross drainage works, Part 1: General features (as cited in CPHEEO 2019 Table 5.12).
- Federal Highway Administration (2024). Urban Drainage Design Manual, Hydraulic Engineering Circular No. 22, 4th edition, FHWA-HIF-24-006. (3rd edition 2009, FHWA-NHI-10-009.)
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.8, 5604.2, 5608.4). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf ; and Version 2025.01 (Dec 2025).
- Australian Institute for Disaster Resilience (2014). Australian Disaster Resilience Guideline 7-3: Technical flood risk management guideline: Flood hazard. Tables 1 and 2. https://knowledge.aidr.org.au/media/1891/guideline-7-3-technical-flood-risk-management.pdf
- Smith, G.P. and Wasko, C.D. (2012). Australian Rainfall and Runoff Revision Project 15: Two-dimensional modelling in urban and rural floodplains. Engineers Australia.
- Ball, J. et al. (eds) (2019). Australian Rainfall and Runoff: A Guide to Flood Estimation, Book 6 (Chapters 6 and 7). Commonwealth of Australia (Geoscience Australia).
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management; and (2012) Urban Stormwater Management Manual for Malaysia (MSMA), 2nd edition.
- Gupta, K. Return Period and Rainfall Intensity for Drainage Design in India. IIT Bombay. https://www.civil.iitb.ac.in/~kgupta/drainagedesign.pdf
- Amritsar Smart City Limited (2018). Bid No. 07/ASCL/2018-19, Performance Based Management Contract for Construction of Trunk Storm Water Drainage & Allied Works, Strengthening and Rehabilitation of Sewer Network … at Walled City Amritsar, November 2018, Section V, 1.1–1.6 and 2.3.2 (the 2-year return period, the 15-minute minimum time of concentration and manhole surcharge; the walled city's area and density; the combined road-side drains; the outfalls by the Tung Dhab and City Outfall drains to the Hudiara drain; the PWSSB finding of 2011 on silt). https://www.amritsarcorp.com/NoticePDF/RFP_07_ASCL_2018-19.pdf
- Punjab Municipal Infrastructure Development Company (2020). Rejuvenation of Buddha Nallah at Ludhiana: Feasibility Report, January 2020 (the 2-year design of the Nallah). https://pwssb.punjab.gov.in/wp-content/uploads/2020/03/Buddha-Nallah-Feasibility-Report.pdf
- Comptroller and Auditor General of India. Performance Audit on Efficacy of implementation of the 74th Constitutional Amendment Act, Government of Punjab, Report No. 7 of 2021, Table 4.6 and Appendix 4.2 (AMRUT storm water drainage; the storm-water items of the Smart City projects of Ludhiana, Jalandhar and Amritsar). https://cag.gov.in/webroot/uploads/download_audit_report/2021/Report%20No.%207%20of%202021%20Govt.%20of%20Punjab_PA-062e0dc92d20019.93581063.pdf ; and Audit Report on Local Bodies for the period ended March 2023, Government of Punjab, Report No. 1 of 2026 (the storm-drain works of the Municipal Council Amloh). https://cag.gov.in/en/audit-report/details/124559
- Department of Housing and Urban Development, Punjab. Master Plan Jalandhar report (Local Planning Area Jalandhar, Vision 2031), 9.3, 13.8.6, 13.8.7 and 13.9.3 (storm-water coverage of 5% of the city; the Chitti Bein and the Black Bein), read through an archived copy of a GMADA-hosted file; its notified status was not seen. http://web.archive.org/web/20230726152616id_/https://www.gmada.gov.in/sites/default/files/documents/Jal_rpt_2011.pdf
- Greater Mohali Area Development Authority (2021). Report of Social Impact Assessment & SIMP: Master Plan Sector Dividing Road 92 & 92 Alpha for Disposal of Storm Sewer, SAS Nagar (the village abadi "seven feet lower than the level of stream (Nadi) area"; the recommended "City Drainage Plan"), read through an archived copy. http://web.archive.org/web/20250707200848id_/https://gmada.gov.in/sites/default/files/documents/2.%20(E)%2092%20%26%2092%20Alpha%20Road%20for%20Storm%20Water%20Disposal.pdf
- Reply of the Nagar Panchayat Naya Gaon in NGT O.A. 180/2026, Sumitra Negi v. State of Punjab, with the Local Commissioner's fourth periodic report of 8 January 2024 in CWP 5901/2017, Shamsher Singh v. State of Punjab (the Patiala ki Rao). https://www.greentribunal.gov.in/sites/default/files/news_updates/Reply%20on%20behalf%20of%20R%206%20Nagar%20Panchayat%20Naya%20Gaon%20in%20OA%20No%20180%20of%202026%20Sumitra%20Negi%20Vs%20State%20of%20Punjab%20and%20Ors.pdf
- Central Pollution Control Board, reply of 13 October 2025 in NGT O.A. 327/2025, Public Action Committee v. State of Punjab (the width of the Buddha Nallah; its quality before the Sutlej, April 2024). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPLY%20BY%20R-7%20CPCB%20IN%20OA%20NO.%20327%20of%202025%20Public%20Action%20Committee%20through%20its%20Member%20Er%20Kapil%20Dev%20Vs%20The%20State%20of%20Punjab%20through%20the%20Principal%20Secretary%20Department%20of%20Water%20Resources.pdf ; and Punjab Pollution Control Board, short reply in NGT O.A. 413/2025 with the proceedings of the River Rejuvenation Committee of 28 October 2025. https://www.greentribunal.gov.in/sites/default/files/news_updates/SHORT%20REPLY%20BY%20PPCB%20IN%20OA%20NO.%20413%20of%202025%20ABHISHT%20KUSUM%20GUPTA%20VS%20UNION%20OF%20INDIA%20AND%20ORS..pdf
- Water Resources Department, Punjab. Kandi Area Development (the choes of the Kandi; the 12 low dams), read through an archived copy; and Department of Environment and Climate Change, Punjab, District Environment Plan, Hoshiarpur (the "more than 100 choes"; their sand and silt). https://decc.punjab.gov.in/wp-content/uploads/2021/11/DEP-Hoshiarpur.pdf ; and Central Ground Water Board, Hoshiarpur district report (the Kandi slope of 16 m per km). https://cgwb.gov.in/sites/default/files/2022-10/hoshiarpur_district.pdf
- India Meteorological Department (2020). Press release of 15 May 2020, New normal dates of onset/progress and withdrawal of southwest monsoon (Pai et al.), Table 2 (Jalandhar, Patti, Ludhiana). https://internal.imd.gov.in/press_release/20200515_pr_804.pdf ; and Extremes of Temperature and Rainfall for Indian Stations (up to 2012), Punjab pages (Patiala, 11 July 1993 and 8 June 2000; Ludhiana, 4 October 1955). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Indian Roads Congress (1998). IRC:SP:48-1998, Hill Road Manual (drainage provisions not read for this Manual [TBC]).
- Press reports on the urban floods of 1–3 September 2025 in SAS Nagar, Ludhiana, Jalandhar and Amritsar; on the Phase 11 area of SAS Nagar and the Lakhnaur choe (The Tribune); on the pre-monsoon targets of 30 June set by the Chief Minister in 2023 (Daily Pioneer), https://www.dailypioneer.com/2023/state-editions/punjab-cm-orders-completion-of-flood-protection-work--cleansing-of-waterways-by-jun-30.html , by the Minister for Local Government in 2026 for Ludhiana (5 Dariya News) and by the Deputy Commissioner of Kapurthala in 2026 (Newswav); and on the paddy transplanting dates of 2025 under the Punjab Preservation of Subsoil Water Act 2009.
- National Disaster Management Authority (2010). National Guidelines: Management of Urban Flooding.
- MoHUA / TCPO (2015). URDPFI Guidelines, Volume I.
- Ministry of Environment, Forest and Climate Change (2019). Coastal Regulation Zone Notification, 2019, G.S.R. 37(E), 18 January 2019. Para 1(i) and Annexure IV. https://crz.elaw.in/crz2019.html
- Department of Local Government, Punjab. Punjab Municipal Building Bye-Laws, 2018, Notification No. CTP(LG)/2018/3548 of 22 November 2018, under s.201(1) of the Punjab Municipal Act 1911 and s.399(2) of the Punjab Municipal Corporation Act 1976, 4.23, 5.2.1 and Table 15.1, read through an archived copy; amended by Notification No. LG/CTP(LG)/2019/3977 of 31 December 2019. http://web.archive.org/web/20190713054359id_/http://lgpunjab.gov.in:80/upload/5bfb9b6b8b129Final%20PMBBL,%2022-11-2018.pdf
- Department of Housing and Urban Development, Punjab. Punjab Urban Planning and Development Building Rules, 2021, G.S.R. 144/P.A.11/1995/Ss.180 and 43/2021 of 31 August 2021 (Punjab Government Gazette, 10 September 2021), r.1(3), r.3(A), r.11, r.26, r.30(5) and r.45, with the corrigendum of 16 March 2022 and the Amendment Rules 2022 (G.S.R. 23, 29 March 2022), read through the PPCB copy; the amendments of 2026 were reported and not read, and none was found to touch these rules [TBC]. "PUDBR" is an abbreviation set by this Manual. http://web.archive.org/web/20221222012900id_/https://ppcb.punjab.gov.in/sites/default/files/2022-07/Building%20Rules-2021.pdf
- The Punjab Canal and Drainage Act, 2023 (Punjab Act No. 11 of 2023), ss.2(7), 38, 39, 52 and 61, PRS copy; commencement notification not found [TBC]. https://prsindia.org/files/bills_acts/acts_states/punjab/2023/Act11of2023-Punjab.pdf ; and the Northern India Canal and Drainage Act, 1873, s.55, for notifications issued before the 2023 Act came into force.
- Department of Irrigation, Punjab. Notification No. 4/8/2013-iw(3)26573/1 of 4 March 2013 under section 55 of the Northern India Canal and Drainage Act 1873 (the Patiala ki Rao), as annexed to the reply of the Nagar Panchayat Naya Gaon in NGT O.A. 180/2026; and the Sutlej floodplain zone in Ferozepur and Tarn Taran districts, notified on 4 March 2024, as described in WRD's affidavit in NGT O.A. 303/2023 (the Gazette text was not read [TBC]).
- The Punjab Municipal Corporation Act, 1976 (Punjab Act 42 of 1976) and the Punjab Municipal Act, 1911 (Punjab Act 3 of 1911): their sections on municipal drains were not read [TBC].
- Water Resources Department, Punjab. Report of the Executive Engineer, Drainage-cum-Mining & Geology Division, SAS Nagar, of 11 October 2024 in NGT O.A. 279/2024 (drain realignment and the NoC of WRD).
- Press report on the NoC of the drainage wing within 150 m of a water body, announced on 20 September 2023 (The Tribune, "Now, get NoC for construction near water bodies", 20 September 2023); no order was found.
- Government of India. The Prohibition of Employment as Manual Scavengers and their Rehabilitation Act, 2013.
Annexes and forms
| Annex / Form | Content |
|---|---|
| 6A | Standard inlet types for Punjab with capacity curves (on grade and sag) |
| 6B | Sediment yield for silt-trap sizing and calibration of the sediment allowance |
| 6C | Standard drawings: covered roadside drain with removable covers, access chamber, inlet with silt sump |
| Form 6-1 | Conveyance Design Report checklist |
Commentary. Punjab's drains have been designed to no stated standard, or to a low one, and with no plan for floods larger than the drain. No storm-drain design standard of the State, of PWSSB, PMIDC, PUDA, GMADA or GLADA, or of any Municipal Corporation was found during research. The two design return periods found are project choices: the trunk storm sewers of the walled city of Amritsar were designed for "a return period of once in two years", with a "Minimum time of concentration … 15 mins", and "the surcharging inside the manhole has been allowed (without flooding)" so that pipe sizes could be kept small enough for the narrow lanes (Amritsar Smart City bid 07/ASCL/2018-19, 2018); and the rejuvenation of the Buddha Nallah in Ludhiana was designed "considering 2 year return period with reduced run-off within the city reach due to active storm water detention" (PMIDC feasibility report, 2020). Under AMRUT, "No work was done" on storm water drainage in the State up to September 2020 "due to shortage of funds and priority to cover water supply and sewerage" (CAG Report No. 7 of 2021). In Jalandhar "only about 5% of the city area is covered under the storm water network", 11.53 of 93.41 km², and "the rain water is largely discharged in to the sewer network", choking it (Master Plan Jalandhar report). The storms these drains face are far larger than a 2-year storm: Patiala recorded 356.5 mm in a day on 11 July 1993 and Ludhiana 354.3 mm on 4 October 1955 (IMD), and on 1 to 3 September 2025 SAS Nagar, Ludhiana, Jalandhar and Amritsar flooded within the city in rain for which no depths were reported (as reported). Where the drains overflow, the water runs along the roads and collects in the low streets and village abadis, because the roads are the only path left, and the natural channels that should carry the overflow have been narrowed or built over: the Punjab portion of the Patiala ki Rao was found "heavily encroached by squatters" with "rampant illegal construction even deep inside the Nadi/Choe" (Local Commissioner's report of 8 January 2024 in CWP 5901/2017), a road along the Buddha Nallah is alleged before the NGT to have cut its width "from 58 feet to 35 feet" (OA 327/2025), and villagers told GMADA that "the village Abadi area is seven feet lower than the level of stream (Nadi) area" beside a new sector road in SAS Nagar (GMADA, social impact assessment for sector roads 92 and 92-Alpha, 2021). The drains are also divided among owners: the Municipal Corporations, Councils and Nagar Panchayats, PUDA and the development authorities, the Smart City companies, PWSSB and PMIDC as builders, PWD (B&R) and NHAI, the Gram Panchayats and WRD all build or hold drains and receiving waters in the same town, and no rule divides them (see the Commentary to Clause 6.9). Fixing the rainfall (Chapter 2) is only half the answer. The other half is a second, surface-level system that carries the flows the pipes cannot, without flooding buildings. That is the dual drainage concept of this chapter, taken from Kansas City Metro APWA Section 5600 (5601.8, Levels of Service), which requires every element to have a 1% AEP overflow path.