Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, chhappar and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Punjab's cities are spending on their drains, but no city drainage master plan with a design storm has been published. The Master Plan Ludhiana (2007–2031) was notified on 12 September 2008 under s.70(5) of the PRTPD Act 1995 (HUD reply before the National Green Tribunal, OA 1295/2024); its drainage chapter was not read. The Jalandhar master plan report (Vision 2031) found that "only about 5% of the city area is covered under the storm water network" (11.53 of 93.41 km²) and that rain is "largely discharged in to the sewer network"; it proposes widening the Chitti Bein, whose high flood level at the Chaheru railway bridge "is generally 12'", from 40–60 ft to "atleast 80'-100'", no construction within 200 m of it until a concrete bandh is built, except a 30 m buffer from the bank, and storm drainage as an "integral part of road development plans" (13.8.7 and 13.9.3; the notification status of the plan was not seen). GMADA's impact study for the 200-ft sector road of Sectors 92 and 92-Alpha, built "for Disposal of Storm Sewer" (2021), asks GMADA to "calculate / recalculate the 'Proposed Runoff Water of the Nadi Catchment Area'" and to make "strong provisions … in the 'City Drainage Plan'", a plan that was not found. The Buddha Nallah, 47.55 km from the Kum Link and Neelon drains near Ghumait to the Sutlej at Walipur Kalan, is being rebuilt on a 2-year design "with reduced run-off within the city reach due to active storm water detention" (PMIDC feasibility report, 2020), in a project sanctioned at ₹650 crore and awarded at ₹839.79 crore with its operation and maintenance (as reported); no design discharge for it was found. Amritsar Smart City's walled-city storm sewers (2018) were designed for a 2-year storm and outfall through WRD's Tung Dhab and City Outfall drains to the Hudiara drain, which flows on into Pakistan. Patiala's Badi Nadi (8.3 km) and Chhoti Nadi (4.9 km) are to be revamped for ₹208.33 crore (as reported). Under AMRUT, Punjab did no storm-water drainage work up to September 2020 (CAG, Report No. 7 of 2021). WRD zones the floodplains of rivers, choes and drains on the 100-year flood by Gumbel's method and Lacey's waterway, but its first zone, on the Sutlej in Ferozepur and Tarn Taran (4 March 2024), was drawn as the land between the embankments, about 4.5 km apart, against a computed Lacey width of 0.58 km (WRD affidavit, OA 303/2023). No published document sets a design return period for the storm drain network of any Punjab city; the only design floods found are WRD's 100-year river floods and the two 2-year project choices. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by HUD, DTCP, DLG, PUDA, GMADA, GLADA, any Municipal Corporation, WRD or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, town drains that outfall through the dhussi bandhs to the Sutlej, the Beas, the Ravi and the Ghaggar when the rivers are high, the Buddha Nallah and other WRD drains that carry sewage and industrial effluent, choes from the Shivaliks that carry sand onto the towns built on their fans and beds, as at SAS Nagar, drains that must pass under canals by siphons and culverts, village chhappars (ਛੱਪੜ; toba ਟੋਭਾ; ponds) filled, encroached or turned into sullage ponds, the depressions of the waterlogged south-west with no gravity outfall, single drains split between a Municipal Corporation, a development authority, WRD and a Gram Panchayat, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Punjab: to town outfalls through the dhussi bandhs to the Sutlej, the Beas, the Ravi and the Ghaggar, whose stage BBMB's releases from Bhakra and Pong, the dams on the Ravi and the headworks at Ropar, Harike, Hussainiwala and Madhopur set, and on which CWC has no flood sites; to the Buddha Nallah and the other WRD drains that receive the towns and carry their sewage and industrial effluent; to Amritsar, whose drains reach Pakistan through the Hudiara drain; to choes from the Shivaliks that carry sand onto the towns built on the Kandi fans, among them the choes that SAS Nagar shares with Chandigarh (Supplement S01); to canals that cross the drainage of the plains and are not receiving waters; to aquifers over-exploited across the centre of the State but standing near the surface in the south-west, the Sirowal and the bet lands; to street drains vested in the Municipal Corporations, Municipal Councils and Nagar Panchayats, sector drains in the schemes of PUDA, GMADA, GLADA and the other development authorities, rivers, choes and notified drains held by WRD and village chhappars on the common land of the Gram Panchayats, without an order that divides the drains between them; to a State whose floodplain lines are notifications under the Canal and Drainage Acts and widths fixed under court orders; to a State with no published design return period for the drains of any city; and to storms far beyond the 50-year depths of the CWC plates, 354.3 mm at Ludhiana on 4 October 1955 and 356.5 mm at Patiala on 11 July 1993 (IMD).


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 No basin delineation has been published for any Punjab city. For the urban areas where the evidence identifies them, the basins are at least the following:

  • Ludhiana, Buddha Nallah: the catchment of the Buddha Nallah from the Kum Link and Neelon drains near Ghumait through its upper reach, the 14 km city reach (RD 55,000–99,620 ft) and the outer reach to the Sutlej at Walipur Kalan, with the discharges of the city's STPs and the dyeing CETPs and the sewage interceptions mapped (Clause 8.9.5), the width disputed before the National Green Tribunal (OA 327/2025) surveyed, and the Sutlej level at the outfall, behind the dhussi bandh, as the boundary condition;
  • SAS Nagar–Zirakpur–Kharar–Dera Bassi–New Chandigarh, the Ghaggar choes: the catchments of the N-Choe, the Patiala ki Rao (Patiali-ki-Rao), the Sukhna Choe, the Jayanti Devi ki Rao and the Lakhnaur choe from the Shivaliks and Chandigarh to the Ghaggar at and below Bhankharpur, with the reaches in the Union Territory, the releases from Sukhna Lake and the cross-boundary rules of Supplement S01 as inflows and partners, the limits notified on the Patiala ki Rao in 2013 and its pillared width shown, GMADA's storm sewer on the sector road of Sectors 92 and 92-Alpha in the 1D network, sand bulking at every choe crossing, and the Ghaggar level as the boundary condition;
  • Patiala, the Nadis: the catchments of the Badi Nadi and the Chhoti Nadi through the city and of the Patiala Nadi to the Ghaggar, with the siphons and culverts that carry them under the canals as controls and the outfall-closed case a design case;
  • The Ghaggar towns of Patiala, Sangrur and Mansa districts: for Samana, Moonak, Khanauri, Makraud Sahib and Sardulgarh, the catchments that drain to the Ghaggar, with the river's narrowing from 588 ft to 190 ft below Makraud Sahib (as reported), the Hansi–Butana canal siphon on the Ghaggar near Samana as a control, the WRD gauges at Khanauri and Sardulgarh as boundary conditions, the breaches of 1993 and 2023 as calibration, and the Haryana reach downstream agreed through WRD;
  • Jalandhar–Kapurthala–Phagwara, the Beins: the catchments that drain to the Kali Bein, the Chitti Bein and the Kala Sanghian drain, with the Chitti Bein level at the Chaheru railway bridge, the Leather Complex CETP and the sewage interceptions mapped, and the Sutlej at Phillaur–Shahkot as the boundary condition;
  • Amritsar, Tung Dhab–Hudiara: the catchments of the walled city and the town that drain through the Tung Dhab and City Outfall drains to the Hudiara drain, with the joint level at the Tung Dhab–Hudiara junction as the boundary condition and the transboundary reach, whose levels are outside Indian control, treated as an uncertain boundary;
  • Pathankot, Chakki Khad: the catchments that drain to the Chakki Khad, which rises in Himachal Pradesh, and to the Ravi, with the releases from Ranjit Sagar and Shahpur Kandi and the level at the Madhopur headworks as boundary conditions and the gate failure of 2025 as a stress case;
  • Hoshiarpur and the Kandi towns, the choes: the catchments of the Hoshiarpur choes and of the choes that cross the Kandi at Garhshankar, Mukerian and Talwara, split at the break of slope above the Sirowal, with the Kandi low dams and check dams as storage, channel losses on the fans, and the Beas below Pong as the boundary condition where the choes reach it; and
  • The south-west drains: for Bathinda, Sri Muktsar Sahib, Fazilka, Abohar and Faridkot, the catchments that drain to the Chand Bhan drain and the other WRD drains of the south-west, and the depressions with no gravity outfall, with the capacity of the receiving drain as the boundary condition, the October water table as a design condition, and pumped outfalls with storage in the 1D network.

Other Tier A bodies, among them Moga, Barnala and Batala, shall define their basins in the first BSMP that covers them. Where WRD, BBMB or a court has a design flood level, limits notified under s.38 of the Punjab Canal and Drainage Act 2023 or s.55 of the 1873 Act, a fixed width or a line around a choe, or an operating rule for a dam, headworks, regulator or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, river levels, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, river, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Punjab a single drain can pass through several hands on its way to a river. The street drains and sewers of a town are the municipal body's, under the Punjab Municipal Corporation Act 1976 or the Punjab Municipal Act 1911, whose drain-vesting sections were not read [TBC], and PWSSB builds them in many towns; the sector drains of an urban estate or scheme are PUDA's or the development authority's until they are handed over (as this Manual reads the record); the rivers, the choes and the drains that WRD maintains are "canal" under the Punjab Canal and Drainage Act 2023, which includes "all drains, works, embankments and structures, connected with drains, maintained or controlled by the State Government" (s.2(1)(g)), while its "drainage work" excludes the "removal of sewage from towns, villages or any other habitat" (s.2(7)); WRD's Drainage Administration counts 869 drains, choes and rivers, of which it had notified 393 under s.55 of the 1873 Act (WRD; a press report of November 2024 gives 514 of 935); and the village chhappars are the common land of the Gram Panchayats. The Buddha Nallah shows the split: its length of 47.55 km is taken from the records of the Drainage department at Ludhiana (PMIDC, 2020), its 14 km city reach runs through MC Ludhiana, whose road along it is said to have narrowed it (OA 327/2025), and it receives the treated effluent of the city's STPs and of three dyeing CETPs. Other drains cross the State's boundaries: the N-Choe, the Sukhna Choe and the Patiala ki Rao cross between Chandigarh and SAS Nagar on their way to the Ghaggar, the Ghaggar runs on into Haryana, and the Hudiara drain into Pakistan. No rule divides WRD's drains from the drains of the municipal bodies and the development authorities (as this Manual reads the record). This clause makes the basin the planning unit, so that one model carries each drain from its head to the river whoever owns each reach, and so that the interception works are tested against the capacity of the drains they tap (Chapter 8, Clause 8.9.5).


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For the basins of a city with a Municipal Corporation: the Municipal Corporation (in Ludhiana, MC Ludhiana; in SAS Nagar, the Municipal Corporation SAS Nagar), jointly with the development authority of the area (in Ludhiana, GLADA; in SAS Nagar, GMADA; elsewhere the development authorities of Amritsar, Jalandhar, Patiala and Bathinda [TBC]), which plans and builds the drains of its urban estates and schemes; either may prepare the plan as the State directs, and HUD carries it into the master plan, with DLG for the municipal area (Clause 11.9). Where a basin extends beyond the Corporation, as from SAS Nagar to Zirakpur, Kharar and New Chandigarh, the other local bodies and the authority in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
  • No order dividing WRD's drains from the drains of the municipal bodies and the development authorities was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: WRD (Drainage-cum-Mining & Geology) for the rivers, the choes, the notified drains (among them the Buddha Nallah, the Tung Dhab, the City Outfall and Hudiara drains and the Chand Bhan drain), the dhussi bandhs, the regulators on them and the limits notified under s.38 of the Punjab Canal and Drainage Act 2023; WRD (canals) for the canals, distributaries and minors and the siphons and culverts that carry drains under them; the Gram Panchayat, with the Department of Rural Development and Panchayats, for the chhappars on its common land; the Punjab State Wetlands Authority for wetlands notified under the Wetlands Rules 2017; the Municipal Corporation, Municipal Council or Nagar Panchayat for its street drains and sewers; PUDA, GMADA, GLADA and the other development authorities for the drains of their estates and schemes until they are handed over; the Department of Soil and Water Conservation and WRD's Kandi Area Development wing for the check dams and low dams of the Kandi; and PWD (B&R) and NHAI for the drains of their roads.
  • In Tier B bodies: the Lead Authority is named by DLG, with HUD where the basin includes a scheme of PUDA or a development authority. Basins draining to a common river reach or WRD drain may be grouped into one district-level plan.

PSDMA and the district administration shall be consulted on every BSMP; BBMB on every BSMP whose outfall levels its releases from Bhakra and Pong set; PPCB on every BSMP that proposes works on a drain that carries sewage or industrial effluent, such as the Buddha Nallah and the Kala Sanghian drain; the Punjab State Wetlands Authority on every BSMP whose basin drains to a Ramsar site (Harike, Kanjli, Ropar, Keshopur-Miani, the Beas Conservation Reserve or Nangal); and, for a basin shared with the Union Territory of Chandigarh, the Chandigarh Administration and the Municipal Corporation Chandigarh as Supplement S01 sets out, and, for the Ghaggar downstream of the State, Haryana's Irrigation and Water Resources Department, through WRD.

WRD, through its Drainage-cum-Mining & Geology wing for rivers, choes, notified drains and dhussi bandhs and its canal wing for canals, shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, chhappar, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls, rivers, WRD drains, choes and canal crossings The datum of every level named, with the gauge zero of every WRD and BBMB gauge [TBC] and levels published in feet converted at 0.3048 m per foot; outfall invert levels against the levels of the receiving river at the nearest WRD headworks or BBMB gauge and its recorded peaks, never a CWC danger level, since CWC has no flood site in Punjab (as reported): for the Sutlej, the discharges and levels at the Ropar, Harike and Hussainiwala headworks, with Harike's "High Flood" band above 3,00,000 cusecs and 3,35,030 cusecs at 686.50 ft upstream on 3 September 2025 (as reported); for the Beas, the releases from Pong, whose full reservoir level is 1,390 ft (higher limits also quoted); for the Ravi, the releases from Ranjit Sagar (full reservoir level 527.91 m) and Shahpur Kandi and the record of the Madhopur headworks, whose gates failed in August 2025; for the Ghaggar, the WRD gauges at Bhankharpur, Sarala Kalan, Khanauri and Sardulgarh with their danger marks (at Khanauri 748 ft, with 752 and 753 ft also reported, against 754.2 ft on 15 July 2023, as reported) or surveyed marks of the July 2023 flood; for outfalls to WRD drains, the design discharge and design water level of the drain at the outfall from WRD; for choes, raos and nallahs, surveyed flood marks and bed levels and the 1% AEP level with its sand bulking; the limits notified under s.38 of the Punjab Canal and Drainage Act 2023 (or s.55 of the 1873 Act) and the widths fixed under court orders, such as the 200 ft pillared width of the Patiala ki Rao; and the regulators, sluices, flap gates, dhussi bandhs, siphons and culverts under canals and pumping stations on the outfalls, with their capacities and operating rules
Rainfall and levels All available rain gauges (IMD, including its observatories and stations at Ludhiana, Patiala, Amritsar, Ferozepore, Kapurthala, Bhatinda, Halwara and Adampur, its station at Chandigarh for SAS Nagar, and the automatic weather stations and rain gauges reported by the Meteorological Centre Chandigarh; the self-recording gauges at Madhopur, Patiala and Hoshiarpur used for the CWC Flood Estimation Report for zone 7; the observatories of Punjab Agricultural University at Ludhiana, Ballowal Saunkhri and Bathinda; the district and tehsil rain gauges of the State; the river, headworks and drain gauges of WRD and the rain and reservoir records of BBMB at Bhakra and Pong; and any gauges kept by the Municipal Corporations, GMADA, GLADA and the Smart City companies) and water-level records, including those for the 4–5 October 1955 (354.3 mm at Ludhiana on 4 October, IMD), 24 September 1988 (338.0 mm at Ludhiana PAU and 284.2 mm at Kapurthala, IMD), 11 July 1993 (356.5 mm at Patiala, IMD), 5 September 1995 (286.8 mm at Ludhiana, IMD), August 2019 (the Sutlej breaches at Shahkot, Gidderpindi and Mandala, as reported), 8–10 July 2023 (35 cm at Ropar in the 24 hours to 08:30 on 10 July, IMD, and the Ghaggar at 754.2 ft at Khanauri, as reported) and August–September 2025 (Harike at 3,35,030 cusecs on 3 September and the town floods of 1–3 September in SAS Nagar, Ludhiana, Jalandhar and Amritsar, as reported) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the bet lands of the Sutlej, the Beas, the Ravi and the Ghaggar between and behind the dhussi bandhs, across the flat canal-commanded plains, where river slopes seldom exceed 0.38 m per km (CWC Flood Estimation Report, subzone 1(e)) and canal banks, roads and paddy bunds hold water back, in the waterlogged depressions of the south-west, on the Kandi fans, where a road or a wall can turn a choe from one side of its fan to the other, and around the margins of the chhappars, where the line of the full level decides what may be built, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 4–5 October 1955 (354.3 mm at Ludhiana on 4 October, IMD), 24 September 1988 (338.0 mm at Ludhiana PAU and 284.2 mm at Kapurthala, IMD), 11 July 1993 (356.5 mm at Patiala, IMD), 5 September 1995 (286.8 mm at Ludhiana, IMD), August 2019 (the Sutlej breaches at Shahkot, Gidderpindi and Mandala, as reported), 8–10 July 2023 (35 cm at Ropar in the 24 hours to 08:30 on 10 July, IMD, and the Ghaggar at 754.2 ft at Khanauri, as reported) and August–September 2025 (Harike at 3,35,030 cusecs on 3 September and the town floods of 1–3 September in SAS Nagar, Ludhiana, Jalandhar and Amritsar, as reported) events are the best calibration data Punjab has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and chhappar storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been counted but not measured. Punjab has no pond statute and no pond authority (as this Manual reads the record): its village chhappars are common (shamlat) land under the Punjab Village Common Lands (Regulation) Act 1961, the Supreme Court has held such commons protected against encroachment (Jagpal Singh v. State of Punjab, 2011, as reported), and the High Court ordered encroachments on ponds removed within six months (2020, as reported); the Punjab Canal and Drainage Act 2023 gives water-user bodies the "use of village ponds and drains for irrigation purposes" (s.51). The counts do not agree: the first water-bodies census found 16,012 water bodies, 1,578 of them encroached, and the State's cleaning programme covers about 15,000 ponds in about 13,500 villages (both as reported). The chhappars are combined sullage and storm basins: they are restored on the Seechewal and Thapar models, which treat village sullage before it enters the pond (as reported), and CAG found a choked screening chamber at the pond treatment works of Punnawal and Bhalwan (Dhuri block) discharging untreated wastewater into the drain (Report No. 1 of 2026). The larger waters are protected as wetlands, though only in part: Harike, Kanjli, Ropar, Keshopur-Miani, the Beas Conservation Reserve and Nangal are Ramsar sites, but no wetland notified under rule 7 of the Wetlands Rules 2017 was found, and the Punjab State Wetlands Authority recommended 72 water bodies for notification in September 2025 (as reported). No survey of the storage of any chhappar inside a Municipal Corporation was found.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Punjab with a design factor was found; the State Action Plan on Climate Change 2.0 projects annual rainfall rising by 5.4–12.8% under RCP4.5 and RCP8.5, most in Gurdaspur and Hoshiarpur, but gives no projection of heavy rainfall, and its count of days above 100 mm per decade at its stations peaked in the 1980s and 1990s (8.3 and 8.0) and fell to 3.8 and 4.3 in the 2000s and 2010s; but the 24-hour records set after the CWC plates were drawn, 338.0 mm at Ludhiana PAU (1988), 356.5 mm at Patiala (1993) and 35 cm at Ropar (2023) (IMD), and the record inflow to Pong in August 2023 (as reported), are a reason to keep the factors, not to reduce them; in the central plains the 24-hour record check of Clause 2.3.6 is the larger correction.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 4–5 October 1955 (354.3 mm at Ludhiana on 4 October, IMD), 24 September 1988 (338.0 mm at Ludhiana PAU and 284.2 mm at Kapurthala, IMD), 11 July 1993 (356.5 mm at Patiala, IMD), 5 September 1995 (286.8 mm at Ludhiana, IMD), August 2019 (the Sutlej breaches at Shahkot, Gidderpindi and Mandala, as reported), 8–10 July 2023 (35 cm at Ropar in the 24 hours to 08:30 on 10 July, IMD, and the Ghaggar at 754.2 ft at Khanauri, as reported) and August–September 2025 (Harike at 3,35,030 cusecs on 3 September and the town floods of 1–3 September in SAS Nagar, Ludhiana, Jalandhar and Amritsar, as reported) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; two chhappars (village ponds) in cascade with an overflow course; a 1D drain network linked to a 2D surface grid; a river or WRD drain reach with a canal crossing by siphon; an outfall through a dhussi bandh with a flap gate and pumps; and a river stage boundary on an embanked river. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) Embanked river (dhussi bandh) 1 S1 S2 S3 2 Upper chhappar Lower chhappar start level start level 3 2D surface 5 4 River / WRD drain (1D) 6 Canal crossing (siphon) Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Chhappars and ponds Surveyed FTL, MWL, stage–storage, outlets, sullage inflow (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Rivers, drains and canals (1D) Sections ≤ 200 m apart and at every structure; siphons under canals as controls; diversions mapped (Cl. 11.3.2) 7 Outfall Flap gates and sluices in the dhussi bandh, pumps; joint and outfall-closed cases, Ch. 5 8 River stage boundary Embanked river: WRD or BBMB gauge (ft → m, gauge zero stated); gated outfall, Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and chhappars with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: chhappars, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: flap gates and sluices on the outfalls through the dhussi bandhs to the Sutlej, the Beas, the Ravi and the Ghaggar, with storage or pumping behind them where a river in flood can close an outfall, as on the Sutlej from Rupnagar and Ludhiana to Ferozepur and on the Ghaggar from SAS Nagar to Sardulgarh; storage and pumped outfalls for the depressions of the waterlogged south-west; the desilting, widening and protection of the WRD drains that receive the towns, among them the Buddha Nallah, the Tung Dhab and the Chitti Bein, and of the siphons and culverts that carry them under canals; sediment traps and choe crossings designed for sand where the Kandi choes enter the towns; interception works that keep sewage and industrial effluent out of the Buddha Nallah, the Kala Sanghian drain and the other storm channels without taking their storm capacity; the dhussi bandhs themselves; and the release and gate-operating rules of Bhakra, Pong, Ranjit Sagar and the Ropar, Harike, Hussainiwala and Madhopur headworks that set the receiving levels, agreed with WRD and BBMB;
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Chandigarh, notice of releases from Bhakra and Pong by BBMB and from Ranjit Sagar and Shahpur Kandi to the towns downstream, the discharges and levels reported by WRD at the Ropar, Harike, Hussainiwala and Madhopur headworks and at its gauges on the Ghaggar, since CWC has no flood sites in Punjab, and the district flood control rooms), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge where the water table is deep and over-exploited, as under Ludhiana, Jalandhar, Patiala, Sangrur, Moga and most of the central plains (115 of the State's 153 assessment units over-exploited, stage of extraction 156.87%; CGWB and WRD, 2024) and in the Kandi recharge belt of sub-area PB-A, waterlogging where the October water table is within 3 m, as in parts of Sri Muktsar Sahib, Fazilka, Faridkot and Bathinda, in the Sirowal and on the bet lands, and the quality of the groundwater, which is saline in much of the south-west and exceeds the limits for uranium, nitrate, fluoride or arsenic in parts of the State, and of the drains, beins, choes and chhappars that the runoff reaches (Chapter 8);
  • effect on downstream basins and the receiving river, WRD drain or choe; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because many of the outfalls of Punjab's towns are closed or limited in the wettest weeks. The Sutlej stood in the "High Flood" band at Harike, at 3,35,030 cusecs, on 3 September 2025, the Ghaggar stood above its danger mark at Khanauri from 13 to 15 July 2023, and Pong spilled for weeks after its record inflow in August 2023 (all as reported); a town drain through a dhussi bandh cannot discharge against such a river, and in the south-west many depressions have no gravity outfall at all. Within the towns, only about 5% of Jalandhar is covered by a storm-water network, and its rain goes largely to the sewers (Jalandhar master plan report). The State's storage has been lost, too: the first water-bodies census counted 16,012 water bodies in Punjab, 1,578 of them encroached (as reported), the State has sanctioned ₹4,573 crore for cleaning about 15,000 village chhappars (as reported), of which about 1,062 were reported dewatered and about 400 desilted; on the Kandi "About 40% of this rain water gets wasted in floods" (WRD, Kandi Area Development). The storms are large for drains designed for a 2-year storm or none: IMD has recorded 354.3 mm in a day at Ludhiana (4 October 1955), 356.5 mm at Patiala (11 July 1993) and 338.0 mm at Ludhiana PAU (24 September 1988), above the 50-year 24-hour depths of the CWC plates there (IMD; this Manual's reading). Conveyance upgrades on their own move water faster to an outfall that the Sutlej, the Beas, the Ravi or the Ghaggar in flood may close at its dhussi bandh, one limited by the capacity of its gate, its pumping station, the receiving WRD drain or a siphon under a canal, or a depression of the south-west that has no gravity outfall at all. Groundwater in Punjab calls for recharge over most of the State and forbids it in part of it. The State's stage of extraction was 156.87% in 2024, with 115 of its 153 assessment units over-exploited (CGWB and WRD), and the area where the June water table was deeper than 10 m grew from 14.9% of the State in 1989 to 68% in 2019 (CGWB and WRD, 2020); "deep water levels are recorded in Kandi belt". But "Water logging conditions exist in some parts of south-western districts": in June 2019 the water table stood 0.79 m below ground at Abohar, and about 15% of the State had it within 1.5–5 m, mostly in the south-west (CGWB and WRD, 2020); there, recharge adds to waterlogging. Quality limits recharge too: CGWB found uranium above 30 ppb in 32.6% of its samples, fluoride above 1.5 mg/L in 13.77%, nitrate above 45 mg/L in 12.58%, arsenic above 10 ppb in 4.85% and electrical conductivity above 3,000 µS/cm in 6.72% (2024), and says that "Groundwater at Shallow depth is largely contaminated caused by surface water pollution". The building instruments ask for recharge without regard to the depth of the water table (PMBBL 2018, cl. 10.5; PUDBR 2021, r.40; as this Manual reads them), PUDBR bars the injection of contaminated water in industrial areas (r.40), and PWRDA credits approved rainwater harvesting (Directions 2023, cl. 2.7). This is why recharge, waterlogging and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the master plans of the local planning areas notified under the Punjab Regional and Town Planning and Development Act 1995 (s.70(5)), among them the Master Plan Ludhiana (2007–2031) and the master plans of Amritsar, Jalandhar, Patiala, Bathinda and the SAS Nagar local planning area (the notification of each to be confirmed [TBC]), with the Unified Zoning Regulations of the master plans (as amended on 24 September 2021), and the layouts of the urban estates and schemes of PUDA, GMADA, GLADA and the other development authorities; and, for a plan that covers a river, choe or notified drain, with the limits notified under s.38 of the Punjab Canal and Drainage Act 2023 shown on it. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Punjab draws its water lines by notification in a few places and by court order elsewhere. Neither PMBBL 2018 nor PUDBR 2021 sets a setback from a river, nallah, choe, pond or canal. Section 38 of the Punjab Canal and Drainage Act 2023, which carries over s.55 of the 1873 Act, lets the State prohibit obstructions within notified limits along a river, stream or drainage channel; WRD's method is to notify the waterway of the 100-year flood, computed by Gumbel's method with Lacey's width, in which "no construction is to be allowed" (Chief Engineer Drainage to CWC, 2 May 2024), but its first zone, on the Sutlej in Ferozepur and Tarn Taran (4 March 2024), was drawn as the land between the embankments, and the National Green Tribunal found no material showing the zone demarcated (OA 303/2023); on the Patiala ki Rao a s.55 notification of 2013 is directed against any construction in or covering of the nadi, and pillars at a width of 200 ft are being fixed under the High Court's orders (CWP 5901/2017), a width for that case only. The Jalandhar master plan report proposes a 30 m buffer and a 200 m no-construction zone along the Chitti Bein and a 30 m plantation strip along the Kala Sanghian drain, plan proposals and not statutory buffers. A no-objection of WRD's drainage wing for projects within 150 m of a water body was announced in 2023 (as reported), but no order was found, and the Punjab Land Preservation (Chos) Act 1900 regulates clearing and quarrying in notified Kandi areas (s.4) without drawing a line along the choes. Punjab has no floodplain zoning Act (as reported), and no wetland has been notified under the Wetlands Rules 2017. These are river and waterbody lines, not drainage-flood lines; the hydraulic corridor and setback zones of Chapter 7 are this Manual's proposal, and where the s.38 limits or a court line bind and are wider, they apply. A BSMP gives the master plans the 1% AEP drainage-flood map, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because PMBBL 2018 already asks that public open spaces of more than 500 m² provide for the "complete utilization and capture of storm water", including "Artificial or natural Storage of storm water runoff from larger sites" (cl. 10.4), that the projects of its Chapter 15 keep the inlet and outlet points of the natural drainage with a channel of adequate size and leave at least 20% of the recreational open space unpaved (Table 15.1), and, with PUDBR 2021 (r.40), that the open parking of group housing be of permeable materials, but neither instrument sets a detention or peak-runoff rule; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one. Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 15 June). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Punjab building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report