Annexes to Chapter 5Downstream and Tailwater Analysis
These annexes support Chapter 5. Annex 5C is a worked example of the outfall-closed check of Clause 5.10, for the illustrative facility of Annex 4C. Annexes 5A and 5B need tidal, surge, survey and river data that this draft does not yet contain; each lists what the chapter already sets, gives the intended layout and states the interim rule of Chapter 5 that applies until it is published. Forms 5-1 and 5-2 are the submittal forms required by Clause 5.14. They are draft forms and have no statutory status.
Annex 5A — Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment
Supports Clauses 5.7, 5.9, 5.10, 5.11 and 5.12 of Chapter 5.
5A.1 Table 5A.1 shows how the values of this annex enter the design tailwater levels of Table 5.1. The sea-level allowance is set by Clause 5.7.4 and does not depend on this annex.
Table 5A.1 — Use of the Annex 5A values in the design tailwater (Table 5.1)
| Design case | Tailwater | Annex 5A values used | Chapter value |
|---|---|---|---|
| Minor-system design | MHWS + SLA | MHWS | SLA ≥ +0.3 m (Clause 5.7.4) |
| Major-system and storage design | HAT + surge + SLA | HAT; 10% AEP surge (Clause 5.7.3(a)) | SLA ≥ +0.3 m |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA | 1% AEP still-water level (Clause 5.7.3(b)) | SLA ≥ +0.3 m |
| Datum conversion | Chart datum to project datum | Offset from chart datum to the Survey of India datum (Clause 5.7.2(b)) | — |
Not prepared for Sikkim. Sikkim has no coast, so no outfall in the State has a tidal tailwater, and this annex has no Sikkim content (Clause 5.1.4). Its tables are kept, empty, so that the annex and table numbers match the other editions of this Manual. Rows F1 to F7 of Form 5-1 are entered as "not applicable", and the tailwater is derived under rows F8 to F10; for an outfall to a jhora (झोरा; a natural watercourse), row F10 records the study, the flood marks, the bed survey and the check of the jhora to the next confluence or trained reach of Clause 5.8.5(a); for a valley-floor outfall, the CWC level, the surveyed October 2023 flood mark and the post-2023 bed survey of Clause 5.8.5(b); and for an outfall to a reservoir reach, the operator's levels and their datum, or the interim rule, of Clause 5.8.5(c).
Table 5A.2 — Tidal datums, surge and still-water levels by coastal segment (layout)
| Coastal segment | Reference port and tide-table edition | MSL (m CD) | MHWS (m CD) | HAT (m CD) | CD to Survey of India datum (m) | 10% AEP surge (m) | 1% AEP still-water level (m CD) | Wave set-up (m), open-sea outfalls | Sources |
|---|---|---|---|---|---|---|---|---|---|
Annex 5B — Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map
Supports Clauses 5.2, 5.3, 5.8 and 5.13 of Chapter 5.
5B.1 Table 5B.1 lists the water bodies that Chapter 5 already names. It is not complete: the annex will add the extents of each reach, the other rivers, canals and mouths of the State, and a map.
Table 5B.1 — Water bodies named in Chapter 5
| Water body | Region | Listed as | Clause |
|---|---|---|---|
| Jhoras of the ridge towns: Pakyong, Namchi, Ravangla, Gyalshing, Pelling, Soreng and others | Statewide | Major drains; ungauged, no published flood level [TBC]; free outfall with energy dissipation; 1% AEP study with bulking and blockage and surveyed flood marks; check of the jhora to the next confluence or trained reach (s.187 of the Municipalities Act); outfall at least 0.5 m above the highest surveyed bed level; lock (where the invert is below the design level) the storm plus recession, not less than 24 hours; no outfall within 15 m of a dhara | 5.2, 5.8.1, 5.8.5 |
| Jhoras of Gangtok, the Rani Khola and the Roro Chu | Gangtok | Major drains and city streams; ungauged, no published flood level [TBC]; item (a) rule with the SK-B rainfall; Zone III sewerage of Gangtok for "Pollution abatement of Rani chu through Ro-Ro Chu" (Clause 8.9); whether the Rani Khola is the scheduled "Rongni chu" of the 1988 Act is a NEER reading to be confirmed | 5.2, 5.8.1, 5.8.5 |
| Teesta (Tista) at Chungthang, Mangan, Dikchu, Singtam, Rangpo and Melli | Mangan, Gangtok, Pakyong and Namchi districts | Riverine outfall reach and GLOF corridor; scheduled river no. 1 (1988 Act); CWC sites Khanitar (HFL 297.7 m, 1974; 298.4 m, 4 October 2023) and Melli (225.5 m vs 228.0 m, 4 October 2023, conflict; 228.0 m for a check), as reported, datums [TBC]; no CWC level at Rangpo [TBC]; bed raised about 2–7.4 m in October 2023; design tailwater the higher of the CWC level and the surveyed October 2023 flood mark, or a model; inverts above the post-2023 bed; flap gates; lock the whole 72-hour storm, not less than 72 hours; assets sited above the 2023 flood and aggradation level | 5.8.1, 5.8.5 |
| Rangit (Rangeet) at Jorethang and the CWC site at Majitar | Namchi district; State border | Riverine outfall reach; scheduled river no. 2; Majitar HFL 279.29 m (17 October 1985, as reported), to be resurveyed; valley-floor rule of Clause 5.8.5(b); lower reach on the State border, where the West Bengal edition governs | 5.8.1, 5.8.5 |
| Rongni Chu at Ranipool and the CWC site at Singtam | Gangtok district | Riverine outfall reach; scheduled river no. 14; Singtam danger level 355.09 m and HFL 356.09 m (undated, as reported); Ranipool active, no HFL; valley-floor rule of Clause 5.8.5(b) | 5.8.1, 5.8.5 |
| Dik Chu at the CWC site at Bakcha | Sikkim | Riverine outfall reach; active site, no HFL (as reported); model and surveyed flood marks | 5.8.1, 5.8.5 |
| Lachen Chu and Lachung Chu, to Chungthang | Mangan district (SK-C) | GLOF corridors; screened under Clause 2.3.6(i); no drain sized for a GLOF; site-specific study for every outfall of more than 1 km²; assets sited above the 2023 flood and aggradation level and outside any mapped GLOF path | 2.3.6, 5.8.5 |
| Maney Khola | East Sikkim | Major drain; a former polluted stretch, delisted, and the State's model river for bathing quality (Clause 8.9); item (a) or (b) rule as its setting requires | 5.8.1, 5.8.5 |
| Reservoirs of Teesta-III (under restoration), Teesta-V, Teesta-VI, Chuzachen, Dikchu, Rongnichu, Jorethang, Tashiding and Rangit-III, and the reaches below them | Teesta and its tributaries | Reservoir outfalls and release reaches; no FRL, MWL, spillway rating or release rule found [TBC]; operator's levels in writing (data, not an approval); until then sited above the October 2023 flood mark, or the surveyed shore line or spillway crest + 0.5 m; release: largest recorded, else spillway capacity, else unattenuated 1% AEP inflow; releases, not notices; the High Court's safety direction of 1 March 2021 | 5.8.1, 5.8.3, 5.8.5 |
| Teesta below Melli and the Rangit's lower reach | State border | The West Bengal edition governs those reaches; its levels bound the model's downstream boundary only | 5.8.5 |
| Khecheopalri lake (Khachoedpalri) | Sikkim | Sikkim's first Ramsar site (February 2025, as reported; area figures conflict and none is cited); no town's drains named as discharging to it; no outfall without its custodian's consent (Chapter 7) | 5.8.5 |
| Pokharis that receive a town's drains | Statewide | None named in the sources [TBC]; spill level plus head; start full to the outlet; custodian's consent; debris, waste and sediment traps; no sewage; never a glacial lake | 5.8.5 |
| Drains and jhoras of the Gangtok Municipal Corporation and the other urban local bodies, GSCDL, the Roads and Bridges Department (PWD), NHIDCL, BRO, WRD, PHED and RMDD, 1.0 m wide or more | Sikkim | Major drains; owner's consent (ss.172, 187 and 189 of the Municipalities Act within municipal areas), design water level and flap gate; jhoras outside municipal limits or on forest land have no named owner | 5.2, 5.8.5 |
| River banks of the scheduled rivers (1988 Act, s.29) | Statewide | Forest Department's consent for any work in the bank; the bank is 60 m or the high-flood-level line, whichever is less (a maximum) | 5.8.5 |
| River mouths subject to sand-bar closure | None in Sikkim | Not applicable (Clause 5.1.4) | 5.13.1 |
To be prepared. This annex will list and map (a) the major drains of each basin plan, (b) the riverine outfall reaches where backwater shall be modelled, with their upstream and downstream limits and the source of their design flood levels, and (c) the river mouths and creek inlets subject to seasonal sand-bar closure, with the most recent pre-monsoon bar crest levels and any WRD mouth-maintenance programme. It needs WRD river and canal records, design and recorded flood levels, reservoir operating rules, mouth-condition, dredging and bar-cutting records and pre-monsoon bar surveys (WRD), the drain inventories of GMC and other local bodies, basin stormwater master plans (Chapter 11), and base mapping from the Survey of India and NRSC. Until it is published: every river, WRD canal, the Rani Khola and the Roro Chu below Gangtok and the jhoras that feed them, the jhoras of Pakyong, Namchi, Ravangla, Gyalshing, Pelling, Soreng and the other ridge towns, every drain that discharges through a flap gate on the valley floors of Rangpo, Singtam, Melli, Majitar, Jorethang or Dikchu, any drain built or held by the Gangtok Municipal Corporation or another urban local body, GSCDL, the Roads and Bridges Department (PWD), NHIDCL, BRO, WRD, the Public Health Engineering Department (PHED) or the Rural Management and Development Department (RMDD) with an internal width of 1.0 m or more, and every jhora, khola or other natural channel that drains 8 ha or more, whether or not it has been trained and every tidal creek is a major drain (Clause 5.2); the water bodies of Table 5B.1 are riverine outfall reaches (Clause 5.8.1); and the mouths of the coastal States' rivers (there is none in Sikkim) are assumed closed at the start of the monsoon unless the Water Resources Department certifies otherwise (Clause 5.13.2).
Table 5B.2 — Attributes of the Annex 5B layers (layout)
| Field | Content | Unit or format |
|---|---|---|
| feature_id | Unique identifier | text |
| name | Name of the drain, river, canal, creek or mouth | text |
| category | Major drain; riverine outfall reach; mouth subject to sand-bar closure | text |
| clause | Clause of Chapter 5 under which it is listed | text |
| reach_limits | Upstream and downstream limits of the reach | text |
| design_flood_level_source | WRD design or highest recorded flood level, or hydraulic model (Clause 5.8.2) | text |
| reservoir_release | Upstream reservoir or tank and its operating rule, where any (Clause 5.8.3) | text |
| bar_crest_level | Most recent pre-monsoon bar crest level, for mouths | m (Survey of India datum) |
| mouth_programme | WRD mouth-maintenance programme and certification (Clause 5.13.2) | text |
| source | Source agency and date | text |
| geometry | Line (drains and reaches) or point (mouths) | line / point |
Annex 5C — Worked example: outfall-closed check for a hillside colony in Gangtok draining to a jhora
Supports Clauses 5.9, 5.10, 5.11 and 5.12 of Chapter 5 and Clause 4.6.6 of Chapter 4.
Illustrative — not design values. This example applies the outfall-closed check of Clause 5.10 to the revised detention facility of Annex 4C. The site, its levels and its receiving drain are invented to show the method. No tidal level is used: the tide enters only through the illustrative statements in Table 5C.1 about whether the receiving drain is above or below the site outlet.
Inputs
5C.1 The site is the 2.0 ha flood-sensitive site of Annex 4C, a hillside colony in Gangtok draining to a jhora (flood-sensitive catchment (a) of Clause 4.5.3.2, Gangtok's jhoras to the Rani Khola and the Roro Chu). It discharges through its own outlet chamber and a flap gate to a public storm drain that runs down a lined chute to the jhora, whose level rises over the drain's outlet when the jhora runs full in a storm and stays up while the storm and its recession last, so Clause 5.10.1 applies to the facility. To show the method, this example uses the two 6-hour lock windows of Clause 5.10.3, as the coastal editions of this Manual do. In Sikkim an outfall to a jhora whose invert is below its design level is closed for the design storm and the jhora's recession, and for not less than 24 hours, and for the whole storm where the 48- and 72-hour storms are run; an outfall on the valley floor of the Teesta, the Rangit or the Rongni Chu below the design tailwater of its river is held at that tailwater for the whole 72-hour storm and closed for not less than 72 hours; an outfall to a release reach below a hydropower dam is closed for not less than 72 hours; and an outfall below the design level of a reservoir or a pokhari is closed for the whole storm, under Clause 5.8.5. In each of those cases that lasts longer than the windows used here, the facility must store or pump the volume of the longer closure, up to the whole storm volume (Clause 5.9.4); that needs more storage, or pumping, than this example shows. The routing, the volume balance of Clause 5.10.4 and the assessment are the same. The public drain's own outfall to the jhora would also need the energy dissipator, the check of the jhora to the next confluence or trained reach and the invert above the range of bed movement of Clause 5.8.5(a), and the debris rack and the bulking factor of Clause 6.3.6; and on Gangtok's slopes, on natural ground steeper than 10°, on colluvium or fill, or in stability zones 3 to 6, the facility itself would be a lined tank, not an infiltrating basin, and its overflow would go to a lined drain, never onto the slope (Clause 4.11 (hill rule)).
Table 5C.1 — Inputs (Illustrative — not design values)
| Item | Value | Basis |
|---|---|---|
| Facility | Revised facility of Annex 4C: 2,500 m² plan area, vertical walls; 170 mm orifice at the floor; 460 mm orifice, invert 0.53 m | Annex 4C, Table 4C.14 |
| Storm | 1% AEP, 48 h, peak day last, AMC III; 72 h also run | Clause 5.10.2 |
| Inflow | Post-development 1% AEP hydrographs of Annex 4C (48 h: 8,420 m³; 72 h: 9,468 m³) | Annex 4C |
| Receiving drain levels at the connection, J1, J2 and J3 | Below the site outlet invert (from the drain owner's model) | Illustrative input |
| Receiving drain during each lock window | Backs up above the site outlet invert, so the site cannot discharge | Illustrative input; Clause 5.10.3(b) |
| Flap gate on the site outlet | Set 0.15 m below the orifice inverts in the outlet chamber, so that outside the lock windows its opening head and head loss do not affect the orifice control | Illustrative input; to be confirmed from the certified curve (Clause 5.11.2) |
| Lock windows | Two of 6 h each, starts 12.4 h apart (semi-diurnal tide) | Clause 5.10.3(a) |
| Pumps | None | — |
5C.2 Cases of Table 5.2. Because the receiving drain stays below the site outlet in J1, J2 and J3 (Table 5C.1), those cases give the free-outfall results of Annex 4C: in J2 the 1% AEP maximum water level is 1.17 m (2,913 m³), and in J3 (10% AEP, 48 h) it is 0.77 m. R1 and R2 do not apply, because the site does not drain to a river. J4, the outfall-closed check, is worked below.
Lock windows (Clause 5.10.3)
5C.3 The peak 1-hour block of the final 24 hours of the 48-hour storm is 35:35–36:35 h, with 98.2 mm (the 1-hour depth of Table 4C.2). Two runs are made:
- Run A: the first window is centred on that block: 33:05–39:05 h; the second starts 12.4 h later: 45:29–51:29 h.
- Run B: the first window starts at that block: 35:35–41:35 h; the second: 47:59–53:59 h.
For the 72-hour storm, every time is 24 h later.
5C.4 Gravity discharge is zero inside each window. Outside the windows the outlet discharges through the orifices of Table 4C.10. The routing is the same level-pool routing as in Annex 4C.
Results
Table 5C.2 — Outfall-closed check results (Illustrative — not design values)
| Storm | Run | Lock windows (h:min) | Maximum stage (m) | Maximum storage (m³) | Time of maximum (h:min) | Largest release after a window (L/s) |
|---|---|---|---|---|---|---|
| 1% AEP, 48 h | A | 33:05–39:05; 45:29–51:29 | 2.01 | 5,019 | 39:05 | 566 |
| 1% AEP, 48 h | B | 35:35–41:35; 47:59–53:59 | 2.10 | 5,238 | 41:35 | 584 |
| 1% AEP, 72 h | A | 57:05–63:05; 69:29–75:29 | 2.00 | 5,012 | 63:05 | 565 |
| 1% AEP, 72 h | B | 59:35–65:35; 71:59–77:59 | 2.09 | 5,233 | 65:35 | 584 |
Run B of the 48-hour storm governs. The first window closes the outlet just as the storm peak arrives, so the whole peak is stored. The second window arrives when the facility has drained to about 0.7 m, below the Stage 2 orifice, and adds little.
5C.5 Volume balance (Clause 5.10.4). Table 5C.3 gives the balance for Run B. The outflow in each period is found by continuity: outflow = storage at start + inflow − storage at end.
Table 5C.3 — Volume balance, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Period (h:min) | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| 0:00–35:35, before window 1 | 3,817 | 2,213 | 0 | 0 | 1,604 |
| 35:35–41:35, window 1 | 3,634 | 0 | 0 | 1,604 | 5,238 |
| 41:35–47:59, between windows | 941 | 4,423 | 0 | 5,238 | 1,756 |
| 47:59–53:59, window 2 | 28 | 0 | 0 | 1,756 | 1,784 |
| After 53:59 | 0 | 1,784 | 0 | 1,784 | 0 |
| Total | 8,420 | 8,420 | 0 | — | — |
Check for window 1: V_inflow = 3,634 m³ ≤ V_storage available + V_pumped + V_gravity = (5,238 − 1,604) + 0 + 0 = 3,634 m³. The facility therefore needs 5,238 m³ of storage, which the routing confirms.
Table 5C.4 — Stage hydrograph, 1% AEP 48-hour storm, Run B (Illustrative — not design values)
| Time (h) | Inflow (L/s) | Outlet | Outflow (L/s) | Stage (m) | Storage (m³) |
|---|---|---|---|---|---|
| 24 | 20 | Open | 18 | 0.18 | 445 |
| 28 | 39 | Open | 24 | 0.25 | 621 |
| 32 | 59 | Open | 32 | 0.36 | 906 |
| 34 | 85 | Open | 37 | 0.47 | 1,166 |
| 36 | 286 | Closed | 0 | 0.78 | 1,944 |
| 38 | 106 | Closed | 0 | 1.73 | 4,321 |
| 40 | 66 | Closed | 0 | 1.96 | 4,904 |
| 42 | 51 | Open | 529 | 1.79 | 4,472 |
| 44 | 42 | Open | 204 | 0.87 | 2,181 |
| 46 | 37 | Open | 49 | 0.74 | 1,854 |
| 48 | 33 | Open | 47 | 0.70 | 1,756 |
| 50 | 0 | Closed | 0 | 0.71 | 1,784 |
| 54 | 0 | Closed | 0 | 0.71 | 1,784 |
| 56 | 0 | Open | 43 | 0.58 | 1,459 |
| 60 | 0 | Open | 32 | 0.37 | 921 |
| 66 | 0 | Open | 16 | 0.16 | 397 |
| 72 | 0 | Open | 7 | 0.06 | 162 |
Assessment
5C.6 Clause 5.10.4(a). The facility of Annex 4C reaches 1.17 m in J2, and its spillway crest is at 1.35 m (Annex 4C). In the outfall-closed check the stage reaches 2.10 m, so the spillway would operate. The facility of Annex 4C fails the check.
5C.7 Remedy. Pumping (Clause 5.12) does not help here: during the lock windows the receiving drain is itself closed, and pumping into it would raise its level, which Clause 5.12.3 does not permit. The remedy is more storage. Keeping the plan area of 2,500 m² and the outlets of Annex 4C:
- the facility must hold 5,238 m³, to a stage of 2.10 m;
- the spillway crest is set above that stage, with the 0.15 m clearance recommended in Clause 4.9.3: 2.25 m;
- with the 4.0 m spillway of Annex 4C (head 0.30 m), the maximum level with the spillway flowing is 2.55 m, and with 0.3 m freeboard the top of the walls is at least 2.85 m above the floor.
The outfall-closed check therefore governs the storage: 5,238 m³ against 2,913 m³ from the release-rate checks, about 80% more. A larger plan area would make the facility shallower; the outlet, caps and drawdown would then have to be re-checked, because the stage–discharge relationship changes.
5C.8 Release after the lock. When the first window ends, the stored water is released under a head of about 2 m, at up to 584 L/s. This is above the 100-yr cap of 356 L/s. Clause 5.10.4 allows this, because the release reaches a drain that has itself just reopened, and requires it to be included in the J4 run of the downstream analysis (Clauses 5.4 and 5.9) and reported on Form 5-1, Section H.
5C.9 Drawdown after the storm (Clause 5.10.5). The J1 tidal curve stays below the site outlet (Table 5C.1), so the drawdown of Annex 4C applies: 45.3 h for 90% of the 10-yr storage with the low-flow orifice 50% blocked, within the 48-hour limit of Clause 4.7. In Run B, 90% of the maximum J4 storage is released 22.6 h after the maximum.
5C.10 Other requirements.
- The flap gate on the site outlet is inspected and operated before 31 March each year and after every event in which it closed against a storm flow (Clause 5.11.5).
- The deeper facility is checked for flotation with groundwater at the design groundwater level; in the Teesta and Rangit valley floors and river terraces (at Rangpo, Singtam, Melli, Majitar and Jorethang), land below the 1% AEP flood level or on the river bed raised by the flood of October 2023, the pokhari and reservoir margins, and the seepage zones below springs (dhara) on slopes without piezometer readings that level is existing ground level (Clauses 4.12.1 and 4.12.3).
- The fence and signs of Annex 4C apply to the deeper facility (Clause 4.15).
Table 5C.5 — Summary (Illustrative — not design values)
| Item | Value |
|---|---|
| Governing case | J4, 1% AEP 48-hour storm, Run B (first window starting at the peak 1-hour block) |
| Storage required | 5,238 m³ (Annex 4C release-rate design: 2,913 m³) |
| Maximum stage | 2.10 m, with 2,500 m² plan area |
| Spillway crest | 2.25 m |
| Top of walls | ≥ 2.85 m above the floor |
| Largest release after a lock window | 584 L/s, to be included in the downstream J4 run |
| Drawdown | Annex 4C result applies: 45.3 h with the low-flow orifice 50% blocked |
Form 5-1 — Downstream and Tailwater Report
Supports Clauses 5.3 to 5.14 of Chapter 5.
Draft form — Sikkim Stormwater Design Manual, Draft v1.0. One report for each project. Sites of less than 0.5 ha that meet Clause 5.3.4 may submit Form 5-2 instead, where the Authority accepts it. Attach the plans, model files and hydrographs referred to.
A. Project
Table 5F.1 — Form 5-1: project
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Project type: site under Chapter 4; drainage project under Chapter 6; regional detention or tank restoration (Clause 5.1.2) | |
| A3. Site or project area (ha) and outfalls | |
| A4. Site Runoff Control Report reference (Form 4-1), where applicable |
B. Extent of the analysis (Clause 5.3; Clause 5.14, item 1)
Table 5F.2 — Form 5-1: analysis points
| Point | Location | Type (Clause 5.3.3 (a) to (e)) | Contributing catchment (ha) | Project area as % of it |
|---|---|---|---|---|
Table 5F.3 — Form 5-1: end point
| Field | Entry |
|---|---|
| B1. End point and reason: 10% point, tank or pokhari, or major drain or the sea (Clause 5.3.1 (a) to (c)) | |
| B2. Where the end point is a tank or pokhari: change in maximum water level (m) and in surplus-weir discharge (m³/s); continuation below the weir if the level rises (Clause 5.3.2) | |
| B3. Plan of the analysis extent, showing the site, each point with its contributing area and percentage, and the end point (attach) |
C. Model (Clause 5.4.4; Clause 5.14, item 2)
Table 5F.4 — Form 5-1: model
| Field | Entry |
|---|---|
| C1. Software and version; hydrologic and hydraulic methods (Clause 5.4.4) | |
| C2. Network schematic, with the survey sources for drains and crossings (attach) | |
| C3. Land use and CN of off-site areas (present land use) | |
| C4. Upstream detention included, with evidence that it is built, maintained and documented | |
| C5. Calibration or validation evidence, where available | |
| C6. Scenarios run: existing, with project, and future where the Authority requires it (Clause 5.4.1) | |
| C7. Storms run: AEPs and durations, AMC and areal reduction (Clause 5.4.3) |
D. Results at each analysis point (Clause 5.4.2; Clause 5.14, item 3)
Complete one row for each analysis point, AEP and duration. E = existing; P = with project.
Table 5F.5 — Form 5-1: results by analysis point
| Point | AEP | Duration (h) | Peak flow E / P (m³/s) | Time to peak E / P (h) | Maximum water level E / P (m) | Peak velocity E / P (m/s) | Duration of inundation E / P (h) |
|---|---|---|---|---|---|---|---|
E. Acceptance (Clause 5.5; Clause 5.14, item 4)
Table 5F.6 — Form 5-1: acceptance criteria
| Criterion | Met at every point? | Where not met, the remedy adopted (Clause 5.5.3) |
|---|---|---|
| E1. 1% AEP water level rise ≤ 10 mm at buildings, lowest openings and carriageways (Clause 5.5.1(a)) | ||
| E2. No building newly flooded; no building or road newly failing the Chapter 6 limits (Clause 5.5.1(b)) | ||
| E3. Peak flow not above existing at the minor-system AEP of each element or at 1% AEP (Clause 5.5.1(c)) | ||
| E4. Velocity in lined channels within the lining limit, 3.0 m/s maximum (Clause 5.5.1(d)) | ||
| E5. Velocity in unlined channels, 50% and 10% AEP, not increased by more than 10% (Clause 5.5.1(e)) | ||
| E6. Change in duration of road closure on arterial or emergency routes (Clause 5.5.2) | ||
| E7. Timing exception requested (Clause 5.5.4)? Give the conditions met |
F. Tailwater derivation (Clauses 5.6 to 5.8; Clause 5.14, item 5)
Table 5F.7 — Form 5-1: tailwater derivation
| Field | Entry |
|---|---|
| F1. Tide-table edition and port, or port authority source (Clause 5.7.2(a)) | |
| F2. MHWS, HAT and MSL (m above chart datum) | |
| F3. Connection from chart datum to the Survey of India benchmark and the project datum: offset (m) and source (Clause 5.7.2(b)) | |
| F4. Estuary, creek or canal outfall: levels used and any evidence for a departure from open-coast levels (Clause 5.7.2(c)) | |
| F5. 10% AEP surge and 1% AEP still-water level: values, source, method and record length (Clause 5.7.3) | |
| F6. Wave set-up, for outfalls facing the open sea (Clause 5.7.3(d)) | |
| F7. SLA (m), at least +0.3 m; design life; sensitivity run at twice the SLA for design lives over 50 years (Clause 5.7.4) | |
| F8. Non-tidal tailwater: receiving-system level and source (Clauses 5.6.2, 5.6.3) | |
| F9. River levels and sources; reservoir or tank releases included (Clauses 5.8.2, 5.8.3) | |
| F10. Jhoras, valley-floor rivers, reservoirs and release reaches, GLOF corridors, the West Bengal reaches, pokharis, and drains of other bodies: for a jhora (Clause 5.8.5(a)), the 1% AEP study with the rainfall of Clause 2.3.6 for the sub-area (SK-B for Gangtok), AMC, the bulking and blockage of Clause 6.3.6, the channel as surveyed net of encroachment, silt, slide debris and waste, the surveyed flood marks and their sources, the energy dissipator and the lined path to the jhora, the check of the jhora to the next confluence or trained reach (capacity with bulking, velocity, bank stability) and its result, the stability zone of the outfall and of the reach, the bed survey and range of bed movement, the invert at least 0.5 m above the highest surveyed bed level, the scour depth of the foundation, confirmation that no outfall lies within 15 m of a dhara or on its recharge area, and the lock where the invert is below the design level (storm plus recession, not less than 24 hours); for valley-floor land (Clause 5.8.5(b)), the highest recorded CWC level at the nearest site (Khanitar 298.4 m; Melli 228.0 m used for a check, with 225.5 m recorded beside it; Singtam 356.09 m; Majitar 279.29 m; Rangpo none) transferred to the outfall, the surveyed October 2023 flood mark and its source, the model on the post-2023 bed where neither exists or where it gives a higher level, every level with its gauge, date, datum and tie to the named CWC site and a Survey of India benchmark; the 10% AEP river level (danger level where reported, else the design level); the post-2023 bed survey and the invert at least 0.5 m above the highest surveyed post-2023 bed; the flap gate, its owner from the drain and jhora register, sill and closing level; the hillside-burst case with the river low and the multi-day case with the river at the design tailwater; drain behind the gate routed with its whole catchment, hill catchments included, and present storage, pumping confirmed available (permanent pumps only, not more than installed capacity less the largest pump), pumps operable at the design river level; the river at the design tailwater for the whole 72-hour storm, the outfall closed for not less than 72 hours, or longer from a stage record, and its source; pump-down within 48 hours; gate jammed open or buried checked; for a reservoir (Clause 5.8.5(c)), the operator's MWL or FRL plus design-flood surcharge in writing with its datum, or the interim rule (sited above the October 2023 flood mark, or the surveyed shore line or spillway crest + 0.5 m), the outfall below the tailwater treated as closed for the whole of the 72-hour storm, the reservoir starting at FRL, and no gate operation, drawdown, release notice or reservoir attenuation credited; for a release reach, the design storm and the 72-hour storm with the largest recorded release, or the spillway capacity, or the unattenuated 1% AEP inflow until the operator gives either, placed before, during and after the storm, and, below Chungthang, the reported October 2023 inflow of about 10,000 m³/s recorded as the cascade, not a design release; for a GLOF corridor (Clause 5.8.5(d)), the screening of Clause 2.3.6(i), the surveyed October 2023 flood and aggradation level at the site, any mapped GLOF path and its source, and confirmation that every asset stands above that level and outside that path; for an outfall near the State border (Clause 5.8.5(e)), the West Bengal edition's level used only as the model's downstream boundary; for a pokhari (Clause 5.8.5(f)), the custodian's consent, the surveyed spill level plus head, the start full to the outlet, the debris, waste and sediment traps before it, and confirmation that it is not a glacial lake; owner's consent (WRD for works in or on a river; the Forest Department for a scheduled river's bank; the urban local body for its drains and jhoras; the Roads and Bridges Department (PWD), NHIDCL or BRO for a road drain; for a jhora outside municipal limits or on forest land, no named owner recorded and the landholder's and Forest Department's consent), permitted rate, design water level or computed channel level, and flap gate; and the lines checked (the 1988 Act's river bank, 60 m or the high-flood-level line, whichever is less; any closure under s.32; any jhora limits notified under s.173 of the Municipalities Act, none found) (Clause 5.8.5) |
G. Joint cases (Clause 5.9; Clause 5.14, item 6)
Table 5F.8 — Form 5-1: joint-case results
| Case | Rainfall | Tailwater used (m, project datum) | Applies? | Governing result (storage, level, pipe size or pump capacity) |
|---|---|---|---|---|
| J1 | ||||
| J2 | ||||
| J3 | ||||
| J4 | ||||
| R1 | ||||
| R2 |
H. Outfall-closed check (Clause 5.10; Clause 5.14, item 7)
Table 5F.9 — Form 5-1: outfall-closed check
| Field | Entry |
|---|---|
| H1. Reason the check applies (Clause 5.10.1) | |
| H2. Storm: AEP, 48 h and 72 h, AMC III (Clause 5.10.2) | |
| H3. Lock duration and basis: default of two 6-hour windows, or site study (Clause 5.10.6); extension for sand-bar closure (Clause 5.13.5) | |
| H4. Lock windows of the two runs (start and end times) (Clause 5.10.3(d)) | |
| H5. Maximum stage in each facility, against its 1% AEP maximum water level (Clause 5.10.4(a)) | |
| H6. Maximum stage in the minor and major systems, against the Chapter 6 limits (Clause 5.10.4(b)) | |
| H7. Property connections: surcharge level, or non-return valves fitted (Clause 5.10.4(c)) | |
| H8. Stage hydrographs (attach) | |
| H9. Drawdown after the storm under the J1 tidal curve, and pumping where needed (Clause 5.10.5) |
Table 5F.10 — Form 5-1: volume balance for each lock window (Clause 5.10.4)
| Period | Inflow (m³) | Gravity outflow (m³) | Pumped (m³) | Storage at start (m³) | Storage at end (m³) |
|---|---|---|---|---|---|
| Before window 1 | |||||
| Window 1 | |||||
| Between windows | |||||
| Window 2 | |||||
| After window 2 |
I. Gates and valves (Clause 5.11; Clause 5.14, item 8)
Table 5F.11 — Form 5-1: schedule of flap gates, tide gates and non-return valves
| Location | Type | Size (mm) | Invert (m, project datum) | Certified head–discharge data (reference) | Stop-log or penstock (outfalls > 600 mm) |
|---|---|---|---|---|---|
J. Pumped outfalls (Clause 5.12; Clause 5.14, item 9)
Table 5F.12 — Form 5-1: pumped outfalls
| Field | Entry |
|---|---|
| J1. Reason pumping is needed (Clause 5.12.1) | |
| J2. Duty capacity (m³/s) at the static head for the J2 tailwater; standby capacity (Clause 5.12.2) | |
| J3. Effect on the receiving water level (Clause 5.12.3) | |
| J4. Power supply: two independent supplies, or standby generation with 72 h of fuel; automatic changeover (Clause 5.12.4) | |
| J5. Level of electrical panels, controls, generators and fuel, against the higher of the 1% AEP flood level + 0.5 m and HAT + surge + SLA + 0.5 m (Clause 5.12.5) | |
| J6. Discharge arrangement (Clause 5.12.6); controls, alarms and logging (Clause 5.12.7); screens (Clause 5.12.8) |
K. Sand bar (Clause 5.13; Clause 5.14, item 10)
Table 5F.13 — Form 5-1: sand-bar assumption
| Field | Entry |
|---|---|
| K1. River mouth or creek inlet concerned | |
| K2. Mouth assumed closed, or open with WRD certification attached (Clause 5.13.2) | |
| K3. Bar crest level from the most recent pre-monsoon survey (m) and the closed-mouth tailwater (Clause 5.13.3) | |
| K4. Extension of the lock duration, where required (Clause 5.13.5) |
L. Inspection and maintenance (Clause 5.14, item 11)
Table 5F.14 — Form 5-1: inspection and maintenance
| Field | Entry |
|---|---|
| L1. Gate and valve inspection before 31 March and after closure events (Clause 5.11.5) | |
| L2. Pump test runs before 31 March (Clause 5.12.9) | |
| L3. Other requirements for the maintenance plan (Chapter 10) |
M. Statement by the registered professional (Clause 10.6)
I state that this report has been prepared under Chapter 5 of the Sikkim Stormwater Design Manual (Draft v1.0), that the results reported are reproduced by the models submitted, and that every departure from Chapter 5 is listed with its reason. The Professional Design Certificate (Form 10-3) is attached.
Table 5F.15 — Form 5-1: statement by the registered professional
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Empanelment number, where Clause 10.6.1 requires it | |
| Organisation | |
| Signature | |
| Date |
Draft form — Sikkim Stormwater Design Manual, Draft v1.0.
Form 5-2 — Simplified Downstream Statement (small sites)
Supports Clause 5.3.4 of Chapter 5.
Draft form — Sikkim Stormwater Design Manual, Draft v1.0. For sites of less than 0.5 ha. The Authority may accept this statement in place of the full analysis only where every answer in Section B is "Yes". Otherwise submit Form 5-1.
A. Site
Table 5F.16 — Form 5-2: site
| Field | Entry |
|---|---|
| A1. Project name, applicant and location | |
| A2. Site area (ha), less than 0.5 ha | |
| A3. Receiving public drain: name or reference, type and size | |
| A4. Site Runoff Control Report reference (Form 4-1) |
B. Conditions (Clause 5.3.4)
Table 5F.17 — Form 5-2: conditions
| Condition | Yes / No | Evidence |
|---|---|---|
| B1. The receiving public drain has documented capacity for its minor-system design flow (Chapter 6) | ||
| B2. No flood-prone location is recorded within 500 m downstream of the site outfall. Records checked: local body, GMC, SSDMA, WRD (Clause 5.3.3(d)) | ||
| B3. The site does not drain to a tidal or backwater-affected outfall |
C. Route plan
Table 5F.18 — Form 5-2: attachments
| Attachment | Attached? |
|---|---|
| C1. Plan of the drainage route from the site outfall for 500 m downstream, with the receiving drain and any recorded flood-prone locations | |
| C2. Copy or reference of the drain capacity record |
D. Statement
I state that the site meets the conditions of Clause 5.3.4 as shown above, and that the records listed have been checked.
Table 5F.19 — Form 5-2: statement
| Field | Entry |
|---|---|
| Name | |
| Qualification and registration number | |
| Signature | |
| Date |
Draft form — Sikkim Stormwater Design Manual, Draft v1.0.