Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Sikkim the failure is one of missing criteria, of one old building rule whose drainage clauses carry no numbers, and of land that no building rule reaches. No document of the Urban Development Department (UDD; the Urban Development and Housing Department, UD&HD, until about 2020), the Gangtok Municipal Corporation (GMC), any other urban local body, Gangtok Smart City Development Ltd (GSCDL), the Water Resources Department (WRD) or the Roads and Bridges Department (PWD) stating a design return period, intensity, runoff coefficient or drain standard for the storm drains of any town, or a standard for training a jhora (झोरा; a natural watercourse or ravine stream), was found. The building rule is the Sikkim Building Construction Regulations, 1991 (UD&HD Notification No. 29(202)UD&HD/90/295, 19 March 1991, made under section 7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985), as amended in 2000 and 2001 (No. GOS/UD&HD/6(294)2001, 16 October 2001); a Sikkim Building Construction (Amendment) Regulation, 2022 is reported to have been published on 12 April 2023 (as reported), was not read, and may change what follows [TBC]. The regulations "extend to all the notified areas in Sikkim" (reg. 1(2)), and the 1985 Act requires prior permission for any construction in a notified area (s.7(1)); the list of notified areas was not found [TBC], and land outside them has no building permission under the regulations. Inside Gangtok, building-plan approval passed from UD&HD to the GMC's Town Planning Cell in 2017, still under the 1991 Regulations (GMC's counter-affidavit in O.A. No. 5 of 2022 before the National Green Tribunal; the transfer notification was not seen [TBC]); how approval is shared between UDD and the other urban local bodies, seven or nine of them as the sources differ, was not found [TBC]. The regulations already contain the steps a drainage submittal needs, and this chapter hooks into them. The application goes in Forms I and II (reg. 4), with a site plan showing the "position of sewer line, water main pipe line, electricity line" (reg. 5(f)) and a blue-print plan showing the "drainage including connection to main outlet and the slopes of the roof" and the "sanitary/plumbing layout … drainage system … sewerage disposal system/septic tank and soak pit" (reg. 6): the drainage sheets of Stages 1 and 2 go with them. The decision is given in Form III or IV within 120 days of the application (reg. 9(i)), which is the overall time limit within which the review periods of Clause 10.7 run (Clause 10.7.6). The Construction Order is "the permission to start the building after approval of Blue Print Plan and demarcation" (reg. 3(1)(g)), and the State's notices stop Construction Orders and earth excavation in each monsoon (6 May to 30 September in 2019; 1 June to 30 September in 2020), so the earthworks of Stage 3, and the drainage that protects them, must be programmed outside the ban. Form III holds a refundable security of ₹5,000 "to meet the expenses for lifting of building materials/spoils … dumped at road side including drain … and also effect repair to damages to the road including drainage system" (cl. 15), which Clause 10.15.4 extends to the works of this Manual. No occupation certificate may be issued "if the drain has not been provided to main outlet/jhora or if the septic tank/soak pit has not been properly built/connected/ventilated" (reg. 13(iii)): the as-built certificate of Stage 4 is the measured form of that test. Height is set by the stability zone of the site (reg. 17(i)), and the Mines and Geology Department's zones of 2021 (Notification No. 17/DMG/20-21, 19 March 2021) are reviewed on conditions that include "Training of untrained Jhora and maintenance at regular intervals which is located adjacent to the plot" and "Proper channelization of surface runoff by providing catchment drains especially during the rainy seasons and connect it to natural waterways/Jhora", so the jhora training of Clause 6.3.6(m) and the catchment drains of this Manual are what a zone review checks. The Government may relax any provision for a building of the Government or a registered organisation (reg. 39, 2001), and has done so on "the merit of the case to engineered structures", as for the GSCDL car park at Gangtok, approved for "a 4+7 storeys building subject to confirmation of a Geotechnical investigation and Report" (GMC's counter-affidavit); a relaxation in a stability zone of 3 or more travels with the geotechnical certificate of Clause 4.11. The Sikkim Municipalities Act, 2007 sets up a second route, a permit system run by the Municipality (Chapter XXXII: "No person shall undertake any building activity without obtaining" a permit, s.271), with Advocates, Architects, Construction Engineers and Structural Engineers on Record registered "in the books of the Municipality" in a manner to be prescribed (ss.266–267) and rules that may cover "infrastructure in relation to building activity" (s.287); no rules under it were found, and whether any Municipality applies it in place of the 1991 Regulations is not clear [TBC], so where it is applied the same drainage sheets go with the permit. Where a drain or outfall serves a sewage treatment plant or carries effluent, the consent of the Sikkim State Pollution Control Board (SSPCB) is needed, as for the plant at Tathangchen (consent-to-operate application 548294, 20 September 2025). The regulations ask for a plinth drain "leading to the road side drain or to adjoining permanent drains or jhora" (reg. 25(iv)) and roof gutters and down pipes of a "design and capacity that the water will neither spill out of them nor leak through them" (reg. 21), but none asks for a drainage report, limits peak runoff, requires on-site detention or rainwater harvesting, sets a design storm or draws a line from a jhora, a khola (खोला; a river or large stream), a dhara (धारा; a spring or spring spout) or a pokhari (पोखरी; pond, lake or tank). Two fields of the forms read differently here. The "SBCR 1991 registration number" of Form 10-3, the "SBCR 1991 registration" of Clause 10.6.1's commentary and the registration "under the Sikkim Building Construction Regulations, 1991" in the model criteria of Annex 10E refer to a register the regulations do not set up: the 1991 Regulations, as read, register no professionals, and the only register found is the Municipality's register of persons on record under the Municipalities Act (ss.266–287), with no rules made [TBC], so the registration or licence under which the Authority accepts the signatory (the Council of Architecture for an architect, or the Municipality's register where one is kept) is entered there. And the "survey numbers, village, sub-division, district" of Form 10-6 are entered as the land records of the Land Revenue and Disaster Management Department give them, in which the unit that the form calls a village is the revenue block (this Manual's reading [TBC]). Land is the last hook. A jhora on public land other than forest land within a municipal area already vests in the Municipality, which "shall protect any jhora, whether on a public land or on a private land" (Municipalities Act, s.172), and the river bank of a scheduled river is under the Forest Department "as if it were a forest" (Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988, s.29(9)); private land that a drain, corridor, storage or outfall needs is secured by agreement with the owner or by donation, or reserved in a development plan once the Sikkim Town and Country Planning Act, 2024 (enacted in 2024 and amended in 2025, not yet commenced) is brought into force, and never taken by this Manual. On land outside every notified and municipal area this chapter is guidance, except for public works and for any body that applies the Manual. Every stormwater item in this chapter is therefore written so that the architect or engineer who signs the plans can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the competent authority for the area (the GMC in Gangtok; UDD or the urban local body that approves plans in another notified area [TBC]; the Forest Department for the river bank of a scheduled river; the department or agency that executes a public work) can check it with the site plan and blue-print plan of regs. 5 and 6, in the time of reg. 9(i), against the stability zone of the site, and at the occupation certificate of reg. 13(iii). This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Sikkim Building Construction Regulations, 1991 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the SBCR 1991 steps a Sikkim applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (45N for the whole State, which spans roughly 88.0°–88.9° E, inside zone 45N (84°–90° E), so that no project needs another zone (this Manual's reading; the State's extreme longitudes are to be confirmed against Survey of India [TBC])), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC level-monitoring sites on the Teesta, the Rangit and the Rongni Chu, Khanitar, Melli, Singtam and Majitar among them (not stated in any source found [TBC]), of the reservoir levels of NHPC and the other hydropower operators (not found [TBC]), and of the flood marks of October 2023 and the post-2023 river beds surveyed at the outfalls and on ungauged kholas, jhoras and pokharis used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Sikkim has no notified design return period or design storm for its urban drains, and no document of UDD, the GMC, any other urban local body, GSCDL, WRD or the Roads and Bridges Department stating a return period, a runoff coefficient, a time-of-concentration rule or a standard for drains or jhora training was found; the 1991 Regulations' drainage clauses (regs. 6, 13(iii), 21 and 25(iv)) carry no numbers. The works that exist convey: GSCDL's "Construction of drainage and jhora training works" in several Gangtok constituencies, put at about ₹13.41 crore (as reported), and the stormwater drains of about 60 km of roads in seven towns under the ADB-funded Sikkim Integrated Urban Development Project (SIUDP, 57230-001; ADB, due-diligence report, December 2024); no design storm was seen for either. A Lok Sabha reply gives the national fallback that where records are lacking "rainfall intensity is usually taken in the range of 12 to 20 mm/hr" (as quoted), far below every Sikkim value, and it is not used; road drains follow IRC:SP:42-2014 and IRC:SP:48. The rainfall studies do not supply a design basis either. No intensity–duration–frequency relation with constants and no recording-gauge ratio was found for any Sikkim station; the only Gangtok "IDF" (Wangsu, Isaac and Tirkey, 2022, for the Ranikhola watershed) disaggregates daily data and reports a July "peak intensity" of 259.785 mm/h, which is not usable; IMD's national study (Das et al., 2022) has no Sikkim panel; and the plates of the CWC Flood Estimation Report for subzone 2(a) draw no contour north of Gangtok, while the State's own records exceed them: 310.3 mm in 24 hours at Gangtok on 30 May 1975 (IMD, Extremes), against a 100-year plate band of 240–320 mm there, and 504.2 mm at Singhik on 12 May 1981 and 400.8 mm at Dikchu on 25 August 1969 (the same report, Table 7), where the plate implies 200–240 mm at 50 years. NIH-DHAARA is lower still in the north, 121–183 mm at 50 years in the cells of Lachung, Lachen, Chungthang and Mangan (tool output, 14 November 2026). The State's design values are therefore those of Chapter 2: the 2(a) plates in sub-areas SK-A and SK-B (Clause 2.3.6(c)(i)), the Gangtok record within 25 km east of the Teesta (Clause 2.3.6(h)), the Singhik record floor in sub-area SK-B1 (Clause 2.3.6(c)(ii)) and the plate's last values carried north in sub-area SK-C (Clause 2.3.6(c)(iii)), with the hazard screening of Clause 2.3.6(i) on the Teesta valley floor and in the GLOF corridors, and each submission must state its own design basis on Form 2-1. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Sikkim calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UDD:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by UDD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the SBCR 1991 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UDD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the approval of the Water Resources Department (WRD) for a work on, or a discharge to, a river or a river or jhora work in its charge, the permission of the Forest Department for a work in the river bank of a scheduled river, which is under its administrative control "as if it were a forest", or in a slip reserve or road reserve (Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988, s.29), the consent of the Municipality for a work on, or a discharge to, a municipal drain or a jhora that vests in it or that it must protect (Sikkim Municipalities Act, 2007, ss.172, 187 and 189), the consent of the Roads and Bridges Department (PWD), NHIDCL or BRO for a discharge to a side drain, catch-water drain or culvert of one of their roads, the reservoir levels and release records, in writing, of NHPC or the other operator for a work that drains to its reservoir or to the reach below its dam (operator data, not an approval; Clause 5.8.5(g)), the consent of the Sikkim State Pollution Control Board (SSPCB) for a discharge that carries effluent, the views of the Mines and Geology Department where a work forms part of the review of a site's stability zone (Notification No. 17/DMG/20-21, 19 March 2021), and the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example Gangtok Smart City Development Ltd (GSCDL) or PHED for a drain or sewer it has built and not yet handed over), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Sikkim because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Sikkim extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Sikkim has no dated State or municipal order fixing a date for desilting drains or clearing jhoras; the only fixed dates are those of the monsoon excavation ban, which UDD issues as an annual notice (UD&HD Notice No. 613/GOS/JCTP/UD&HD of 1 May 2019; UDD Notice No. T(1689)/997 of 26 May 2020), not as a regulation. The drains are run by several hands, and no notification divides them (Chapter 6): the Municipality for its drains and for the jhoras on public land other than forest land within its area, which vest in it, and for the protection of every jhora in that area, public or private (Sikkim Municipalities Act, 2007, ss.172 and 189); the Forest Department for the river banks of the 103 scheduled rivers (1988 Act, s.29(9)); the Roads and Bridges Department (PWD) for the drains of State roads, and NHIDCL and BRO for those of the national highways (this Manual's reading); GSCDL, WRD and the Rural Management and Development Department (RMDD) for the jhoras they train (as reported); PHED for the sewers and treatment plants ("the concern department for sewage management in the State"); and no one for the jhoras outside municipal limits or on forest land, which have no named owner. Maintenance is let by contract: the GMC's waste agency is responsible for the "Clearing of Jhoras" and barred from dumping "along Footpath, Roadside and Jhoras" (Memo No. GMC/6727/III/2024/OL/01, 8 October 2024), and GSCDL's jhora-training works (as reported) will need their own maintenance once handed over. The gates that matter most are run by rules made for other purposes: the hydropower reservoirs are operated for power, no release rule, full reservoir level or maximum water level was found for any of them [TBC], and the High Court closed its case on a release from the Dikchu project in 2017, reported to have come without warning, with a direction that the projects "shall ensure strict compliance of the safety guidelines" and that the authorities "undertake periodic inspection and review" (WP(PIL) 4/2017, 1 March 2021). Warning of the largest hazard rests with other bodies: the Science and Technology Department is the nodal department for GLOF studies and mitigation (Notification No. 10/Home/2025, 7 February 2025), SSDMA and the District Disaster Management Authorities ran participatory risk assessments with GLOF evacuation maps in May 2024 and a State mock exercise on 17 November 2025 (State affidavit to the National Green Tribunal, 28 February 2026), and no operating procedure for urban floods was read [TBC]. No operating rule for any flap gate, sluice or pumping station in a Sikkim town, linking it to a river level, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 March) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Sikkim, the pre-monsoon inspection of flap gates, penstocks, non-return valves, debris racks, debris basins, silt traps, culvert inlets and any pumped facility, including the gates, where any exist, on the outfalls of the valley-floor towns that the Teesta, the Rangit or the Rongni Chu can close and on outfalls to a hydropower reservoir or its release reach, with the desilting of every drain and jhora channel, the clearance of inlets, culverts, racks, debris basins, silt traps and slide debris, the clearance of plinth drains and catchment drains, the inspection and clearance of the weep holes and subsurface drains of retaining walls, and the pump duty and gate seal tests, shall be completed by 31 March, with completed earthworks and cut slopes stabilised by the same date; flap gates and any pumped facilities, with their standby power, shall be certified ready on the same date, with every gate on an outfall to a river or reservoir operated through its full travel, because the season of this Manual begins on 1 April and the storms of April and May are among the State's largest. Flap gates, racks and any pumps shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to a hydropower reservoir or to a reach below a dam until the operator's releases have ended, if that is later. Drains, jhora channels, racks, culvert inlets and debris basins shall be cleared again by 30 April, of the silt, debris and slide material of the April storms, before May, the month of the State's largest recorded 24-hour falls, and every public drain, jhora channel, inlet, rack, trap, basin and culvert in every town shall be cleared of the silt, debris and slide material of the season by 15 November, with a survey of the cut slopes, retaining walls and trained jhoras above them. In sub-area SK-C, and at any site above about 2,500 m, where snow or frost prevents the works in March, the pre-season works shall be completed by 30 April and the mid-season clearance by 31 May, with the reason recorded on Form 10-7; inlets, gratings, culverts and drains shall be cleared of snow and ice after every snowfall from December to March; and the post-season clearance shall be completed by 31 October, before the first snow. WRD's own works on rivers keep WRD's calendar.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December. The monsoon season of this Manual, 1 April to 31 October, is bracketed: the pre-monsoon storms of April and May, with the two largest 24-hour falls on record in May (Singhik, 12 May 1981; Gangtok, 30 May 1975), and the south-west monsoon from June, for which no IMD normal onset or withdrawal date for Sikkim was found, so none is drawn. December to February is marked as the dry works window, and March and November as outside the season, with storms marked there. Lanes show routine inspections; desilting of drains and jhora channels, the clearance of inlets, culverts, racks, debris basins and slide debris, plinth and catchment drains, weep holes and subsurface drains, the pre-monsoon inspection, the readiness of flap gates and any pumps and the Form 10-7 declaration, all by 31 March; standby from 1 April to 31 October; a mid-season clearance by 30 April; a post-season clearance and slope survey by 15 November; inspections after heavy rainfall in any month; the reporting year from 1 April to 31 March; the State's monsoon ban on earth excavation, by annual notice, from early May or June to September; the regime for sites above about 2,500 m, with pre-season works by 30 April, the mid-season clearance by 31 May, the post-season clearance by 31 October and snow and ice cleared from December to March; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Monsoon season of this Manual: 1 Apr–31 Oct Dry: works window Dry: works Outside Outside Pre-monsoon storms South-west monsoon Oct storms Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 Mar 30 Apr 31 Oct 15 Nov Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 Mar: drains and jhora channels desilted; inlets, racks, debris basins, slide debris, catchment drains, weep holes cleared; inspection; gates and pumps ready. 1 Apr–31 Oct: standby. By 30 Apr: mid-season clearance. By 15 Nov: clearance, slope survey. After heavy rain After each day at or above IMD “heavy rainfall” or a district red alert, in any month (red: the May records; orange: outside the season) Annual declaration Form 10-7 Form 10-7 by 31 Mar, closing the reporting year (1 Apr–31 Mar): Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Notice; high sites ban; above ≈2,500 m Earth excavation and Construction Orders stopped by annual notice, from early May or June to September (drain earthworks done before) Above ≈2,500 m (SK-C): snow and ice cleared Dec–Mar; if snow stops March works, 30 Apr and 31 May; post-season by 31 Oct Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one season, 1 Apr–31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 March, 30 April, 31 October and 15 November (above about 2,500 m, also 31 May) are fixed (set by this Manual). Pre-monsoon storms: Gangtok normals 296.9 mm in April, 496.4 mm in May (IMD). 24-hour records: Singhik 504.2 mm, 12 May 1981; Gangtok 310.3 mm, 30 May 1975. South-west monsoon: IMD’s normal onset and withdrawal dates for Sikkim were not found, so none is drawn. October storms: 1968, 1996 and 2023. Outside the season: Gangtok 72.0 mm on 27 March 2008 and 96.0 mm on 11 November 1995 (IMD). December–February is the dry works window. Excavation ban: 6 May–30 September 2019 and 1 June–30 September 2020 (UD&HD and UDD notices); from 1 May, extended by 15 days, in 2024 (as reported).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins in April. In this Manual the monsoon season runs from 1 April to 31 October: the pre-monsoon storms of April and May and the south-west monsoon. IMD's normal dates of onset and withdrawal for Sikkim were not found [TBC], and the monsoon in IMD's sense is not said here to begin in April; the season of this Manual does, for four reasons. Gangtok's rain rises steeply from April: its normals for 1981–2010 are 126.4 mm in March, 296.9 mm in April on 15.2 rainy days, with 10.7 days of thunder, 496.4 mm in May on 20.1 rainy days, 609.8 mm in June, 626.3 mm in July, 565.9 mm in August, 438.7 mm in September and 173.4 mm in October (IMD, M.O. Gangtok), and March to May bring 919.7 mm, 26% of the year (sum computed for this Manual); its highest April total is 687.8 mm (1974) and its highest May total 951.7 mm (1996) (IMD, Extremes). The largest 24-hour falls on record are pre-monsoon: Gangtok's 310.3 mm on 30 May 1975, its record for 1958–2012 (IMD), and Singhik's 504.2 mm on 12 May 1981 (CWC Flood Estimation Report for subzone 2(a), Table 7). The State already treats May as the start of the season for earthworks: its notices ban "construction involving earth excavation" and stop Construction Orders each monsoon, from 6 May to 30 September in 2019 and from 1 June to 30 September in 2020 (UD&HD Notice No. 613/GOS/JCTP/UD&HD; UDD Notice No. T(1689)/997), in 2024 from 1 May, extended by 15 days (as reported), and the State told the National Green Tribunal that the monsoon "starts around the month of May or June and continues till September" (counter-affidavit in O.A. No. 5 of 2022); drainage earthworks must therefore be finished before the ban, and the April storms argue for March. And NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual keeps that date, as the other North-East editions of this series do, while the CWC Flood Estimation Report for subzone 2(a) finds that "The south-west monsoon and cyclonic storm causes the rainfall in the subzone from May to October". No Sikkim order fixing a date for clearing drains or jhoras was found. The research's own suggestion, desilting complete by 30 April, is not used as the deadline, because it would put the desilting into April's 297 mm on 15 rainy days; the 31 May and 15 June dates of the mountain editions of this series, set for a monsoon that begins in late June, are not used either, because Sikkim's wet season and records begin in April and May. December to February is the works window, and in North Sikkim above about 2,500 m snow and frost limit it. This Manual therefore takes 31 March for the desilting of drains and jhora channels, the clearance of inlets, culverts, racks, debris basins, silt traps and slide debris, the clearance of plinth drains and catchment drains, the inspection and clearance of the weep holes and subsurface drains of retaining walls, the pre-monsoon inspection, the annual declaration, the BSMP annual report, the stabilisation of completed earthworks and cut slopes, and the readiness of flap gates and any pumps, with no later readiness date; WRD's own works on rivers keep WRD's calendar. The research's 30 April becomes instead the date of the mid-season clearance. Drains, jhora channels, racks, culvert inlets and debris basins are cleared again by 30 April, after the April storms and before May, the month of both the Gangtok and the Singhik records. One other North-East edition of this series uses the same date; the rest clear a second time by 31 May or by 15 May, but here the largest falls on record come in May, on 12 May at Singhik and 30 May at Gangtok, so a clearance due by 15 May or 31 May could come after them. Storms continue into October: Gangtok recorded 201.0 mm on 3 October 1996 (IMD), the regional storm of 2–5 October 1968 brought hundreds of landslides in Darjeeling and Sikkim (as reported), and the flood of 3–4 October 2023 came down the Teesta, so flap gates, racks and any pumps are kept on standby to 31 October (Figure 10.3). Storms also come outside the season, 96.0 mm at Gangtok on 11 November 1995 and 72.0 mm on 27 March 2008 (IMD); design statistics use annual maxima from all months, the drains and jhoras fill with silt, debris and slide material during the season, and every town clears its drains a second time, and surveys its cut slopes, retaining walls and trained jhoras, by 15 November. In sub-area SK-C and at any site above about 2,500 m, where snow or frost prevents the works in March, the pre-season works are due by 30 April and the mid-season clearance by 31 May, with the reason recorded on Form 10-7, snow and ice are cleared from inlets, culverts and drains after every snowfall from December to March, and the post-season clearance is due by 31 October, before the first snow, as the mountain editions of this series do for their high towns (set by this Manual; no snow-day statistics or snow lines by valley were found [TBC]; Gangtok itself has occasional snow, with a January minimum of −2.2 °C in 1956, IMD). The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Sikkim towns make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Sikkim drainage show up only in the first monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Sikkim Building Construction Regulations, 1991 were made and from the municipal Acts. The graduated steps are set by this Manual. In Sikkim the statutes give the building authority strong powers over unauthorised works and weak, unstated penalties, and the High Court and the National Green Tribunal have begun to act where the rules do not. The Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 lets the Government demolish works built without permission in a notified area (s.8) and act against unsafe structures (s.9); since its amendment of 2022 (Act 24 of 2022) its penalty is "such fine as may be notified from time to time" (s.11) and its offences are "triable by the District Magistrate" (s.12), and no notified fine was found [TBC]. The Sikkim Building Construction Regulations, 1991 count as "Unauthorized Construction" even "a protective wall, fence of any type etc." built without permission in the notified area or a road reserve (reg. 3(1)(h)), fine the dumping of spoil on "drains, gullies and jhoras" ₹500 at least (reg. 22), refuse an electricity, sewerage or water connection or a trade licence to an unauthorised building (reg. 34), and hold Form III's security of ₹5,000 against spoil and damage to the drainage (cl. 15); the monsoon notices add that building material "lying on the road setback or over drains" will be "seized and auctioned" and that a violator is "solely responsible for any loss of life and property" (UD&HD Notice No. 613/GOS/JCTP/UD&HD, 1 May 2019). The Sikkim Municipalities Act, 2007 puts the duty on the Municipality, which must provide "a safe and sufficient outfall" that does not cause "any nuisance, either by flooding any part of the municipal area or any area surrounding the outfall" (s.187), must protect every jhora in its area, public or private (s.172(2)), and must keep sewage and rain water in separate drains, the rain water "connected with the natural nullahs, khola-kholsas, jhoras, or storm water drainage" (s.193); the State may notify the limits of a jhora (s.173), and none has been notified as far as found. The Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 makes the unauthorised occupation of a river bank, slip reserve or road reserve an offence (s.30) and lets the Government close one by notification (s.32). The audits show how works fail without a design basis or follow-through: of the ₹2,217 crore proposed in Gangtok's City Development Plan of 2006, project reports for only seven projects (₹153.02 crore) were approved, and "Projects under Drainage, Landslip Protection, Traffic, Street Lighting, Tourism and Environment were not taken up"; at Melli the households "had constructed their own septic tank … and were reluctant to connect" to the new treatment plant; and Jorethang's sewerage was incomplete "for want of land", the land chosen being "fully flooded during monsoon" (CAG, Report No. 3 of 2016, performance audit of JNNURM); no audit of storm drainage, flood works, GSCDL or the response to the flood of 2023 was found. The courts and the Tribunal supervise what the rules leave open. Before the National Green Tribunal the State reported that "the establishment of sewerage systems for Namchi Town and Jorethang Town has remained stalled since the year 2013 and 2015 respectively" (affidavit of 19 December 2025 in O.A. No. 673 of 2018), and the Tribunal recorded that treated sewage entering "river/ rivulets/ jhoras" is "not permissible under the Water Act" (O.A. No. 606 of 2018, order of 4 July 2024, as quoted by the State), which the State disputes; it has also sought data on all the Teesta dams after the breach at Chungthang (O.A. No. 171 of 2023, order of 13 January 2026). The High Court directed the hydropower projects to "ensure strict compliance of the safety guidelines" (WP(PIL) 4/2017, 1 March 2021), warned IRCON to correct its damage to the drainage of NH-10 (June 2025, as reported), and in its suo motu case In re Climate Justice in State of Sikkim (WP(PIL) 11/2026) is reported to have asked the State to examine "land-use regulation, spatial planning, slope management, and drainage in ecologically and geologically fragile areas" and urged early-warning systems for the 40 high-risk glacial lakes, with a hearing listed for 18 November 2026 (as reported; the orders were not read). This shows that a rule without routine enforcement does little, and that where no rule draws a line beside a jhora or a river, the courts have begun to ask the State to look at drainage and slopes. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river at the nearest CWC level-monitoring site, where there is one (Khanitar or Melli on the Teesta, Singtam on the Rongni Chu or Majitar on the Rangit; none was found for Rangpo), each on a named datum, with any reading of a local gauge or a press report kept apart from the CWC levels, and the flood marks surveyed at the outfall and compared with the flood mark of October 2023 and with the river bed surveyed after it; for an ungauged khola or jhora, the Rani Khola and the Roro Chu in Gangtok among them, the flood marks surveyed after the event and the boulders, spoil, slide debris and garbage deposited at crossings, racks and culverts; the state of every flap gate, debris rack, debris basin, silt trap, check dam and pumping station on the outfall and on the drain upstream of it, with the volume of debris and garbage removed from each and the hours any pump ran; the slides, slope failures and blocked catchment drains, jhoras and weep holes in the catchment of the outfall, located on the stability zones of the Mines and Geology Department; and the gate openings and releases of any hydropower dam that sets the receiving level, with the times of any warning its operator gave;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), SSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Sikkim's floods and landslides have been counted more often than they have been reviewed, and the counts conflict. For the South Lhonak lake outburst and Teesta flood of 3–4 October 2023 the post-disaster needs assessment of SSDMA with NDMA (field assessment 7–11 December 2023) gives 79 dead and 44 missing, 2,004 houses damaged, 33 bridges damaged, 13 of them major, and damage and loss of ₹1,480.07 crore, with a recovery need of ₹2,192.59 crore (summary annexed to the State's affidavit to the National Green Tribunal of 28 February 2026), while the SSDMA survey cited by Sattar et al. (2025) gives 55 dead and 74 missing, and the press other figures (as reported); its cause is disputed too, the State's affidavit of 5 April 2024 attributing it "primarily to a cloudburst" and the committee constituted by NDSA finding, as reported, that "all scientific data and satellite images from that period points to GLOF and not a cloudburst", while Sattar et al. found a moraine collapse into the lake with modest rain, 29–39 mm over eight days in ERA5. This Manual takes no side. The Gangtok landslides of June 1997 are given as 38 deaths by a single unofficial source (as reported); the rain and landslides of 12–13 June 2024 in Mangan district killed 6 by early reports and 9 by a later account (as reported); the slide at the army camp at Chaten near Lachen on 1 June 2025 left 3 dead and 6 missing (as reported); and the earthquake of 18 September 2011 is given as 92 deaths by the count of 23 September and 97 to 116 in later totals (as reported). No official account of the regional storm of 2–5 October 1968 in Sikkim, of June 1997, or of SSDMA's final tolls for 2024 and 2025 was found [TBC], and for none of these events was an IMD station rainfall found except Gangtok's 223.8 mm on 9 June 1997. No review of any flood in a Sikkim town, and no record of flood extents, depths or durations kept by any urban local body or SSDMA, was found; the State's own reconstruction of the flood of 2023 rests on the needs assessment and the project proposal for the Lhonak valley, not on a drainage review. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Much of Sikkim's drainage record is public: the Sikkim Building Construction Regulations, 1991 with their amendments of 2000 and 2001 (in a copy held by a third-party host); the Acts of 1985, 1988 and 2007 and the Sikkim Town and Country Planning Act, 2024 as consolidated by PRS; the stability-zone notification of 2021 and the monsoon notices of 2019 and 2020, annexed to the State's affidavits before the National Green Tribunal; the Gazette notifications of 2026 on the urban local bodies; the State's affidavits of 2024 to 2026 on the flood of 2023, with the project proposal for the Lhonak valley and the summary of the post-disaster needs assessment, and on sewage and the rivers, with the monthly progress report of September 2025; the High Court's judgments on the Dikchu release and on the petitions after the flood; the CAG's audit of JNNURM in Gangtok; the ADB due-diligence report for Soreng; IMD's station extremes and Gangtok normals; and Sattar et al. (2025) on the cascade of 2023. Much else could not be found in the public domain: the text of the Sikkim Building Construction (Amendment) Regulation, 2022; the list of notified areas; the notification of 2017 that gave building-plan approval in Gangtok to the GMC, and any rules under Chapter XXXII of the Municipalities Act; any notification of jhora limits under section 173; the commencement of the 2024 Act, its rules and its Board; the design basis of any storm drain or jhora-training work, including GSCDL's works and the road drains of SIUDP; any drainage master plan or notified master plan for Gangtok; CWC's site sheets and gauge datums, and any level at Rangpo; the full reservoir levels, maximum water levels and release rules of every hydropower dam; the report of the committee constituted by NDSA on the flood of 2023; SSDMA's official tolls for 2024 and 2025 and its procedures for urban floods; the High Court's orders in its climate-justice case of 2026; and an inventory of the gates, racks, debris basins and traps of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

  • Government of Sikkim, Urban Development and Housing Department. Sikkim Building Construction Regulations, 1991, Notification No. 29(202)UD&HD/90/295 of 19 March 1991, under s.7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985, as amended by the Sikkim Building Construction (Amendment) Regulations, 2000 and 2001 (No. GOS/UD&HD/6(294)2001 of 16 October 2001): regs. 1(2), 3(1)(g)–(h), 4–6, 9(i), 13(iii), 17, 18, 21, 22, 25, 34, 35 and 39; Forms I–III. Copy held by a third-party host (Sikkim Manipal University). https://smu.edu.in/img/content/dam/manipal/smu/IQAC/SDG/documents/BUILDING%20STANDARDS.pdf. The Sikkim Building Construction (Amendment) Regulation, 2022, reported as published on 12 April 2023, was not read.
  • Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 (Act 11 of 1985), as amended by Acts 16 of 2000, 8 of 2001, 6 of 2007 and 24 of 2022: ss.7, 8, 9, 11 and 12. https://prsindia.org/files/bills_acts/acts_states/sikkim/1985/1985SK11.pdf
  • Government of Sikkim, Department of Mines and Geology. Notification No. 17/DMG/20-21 of 19 March 2021 (Sikkim Government Gazette Extraordinary No. 86, 6 April 2021): site stability zonation parameters and conditions for review; read as Annexure R/2 to the State's counter-affidavit in O.A. No. 5 of 2022 (EZ) before the National Green Tribunal.
  • Sikkim Municipalities Act, 2007 (Act 5 of 2007), as amended to Act 3 of 2026: ss.2(24), 163(b), 172, 173, 186, 187, 189, 193, 266–287 (Chapter XXXII). https://prsindia.org/files/bills_acts/acts_states/sikkim/2007/2007SK5.pdf
  • Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 (Act 6 of 1988), as amended by Act 8 of 2000: ss.2(m), 29, 30 and 32. https://prsindia.org/files/bills_acts/acts_states/sikkim/1988/1988SK6.pdf
  • Sikkim Town and Country Planning Act, 2024 (Act 10 of 2024), as amended by Act 24 of 2025; not yet commenced (s.1(3)). https://prsindia.org/files/bills_acts/acts_states/sikkim/2024/Act10of2024SK.pdf
  • Government of Sikkim, Urban Development and Housing Department. Notice No. 613/GOS/JCTP/UD&HD of 1 May 2019; Urban Development Department, Notice No. T(1689)/997 of 26 May 2020 (monsoon bans on earth excavation and Construction Orders); Annexure R/5 to the State's counter-affidavit in O.A. No. 5 of 2022 (EZ).
  • National Green Tribunal (Eastern Zone). O.A. No. 5 of 2022, Dr. Bina Basnett v. State of Sikkim and Others: counter-affidavits of the State and of the Gangtok Municipal Corporation (2022); and O.A. No. 38 of 2022, reply affidavit of GSCDL. https://www.greentribunal.gov.in/
  • Government of Sikkim. Additional affidavit of 28 February 2026 in O.A. No. 171 of 2023 (EZ) before the National Green Tribunal, with the Home Department's notifications, the project proposal GLOF Risk Mitigation in Lhonak Valley, Sikkim and the summary of the post-disaster needs assessment of 2023. https://www.greentribunal.gov.in/
  • Government of Sikkim. Affidavit of 19 December 2025 in E.A. No. 35 of 2023 in O.A. No. 673 of 2018, with the monthly progress report of September 2025; and six-monthly report in O.A. No. 606 of 2018 (sewage; the Tribunal's order of 4 July 2024 as quoted; the GMC's waste-agency contract). https://www.greentribunal.gov.in/
  • Comptroller and Auditor General of India. Report No. 3 of 2016 (Economic Sector, Government of Sikkim), Chapter II, performance audit of JNNURM, para 2.3.9.2. https://www.cag.gov.in/uploads/download_audit_report/2017/Chapter_2_Economic_Sector_Sikkim_Report_No_3_of_2016.pdf
  • India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Gangtok (42299) and Tadong (22209); and Mean monthly meteorological parameters of Gangtok, 1981–2010. https://mausam.imd.gov.in/gangtok/mcdata/climatology_gangtok.pdf
  • Central Water Commission (1991). Flood Estimation Report for North Brahmaputra Subzone 2(a), Report No. NB/18/1991 (Table 7; Plates 8–10; rainfall season).
  • Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
  • Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
  • Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
  • PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
  • PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
  • PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
  • MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
  • National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
  • High Court of Sikkim. In re: Release of water from Dikchu Hydelpower Project, WP(PIL) No. 4 of 2017, judgment of 1 March 2021; Mani Kumar Subba v. State of Sikkim, WP(PIL) No. 3 of 2023, judgment of 7 December 2023. https://hcs.gov.in/
  • Sattar, A. et al. (2025). The Sikkim flood of October 2023: drivers, causes and impacts of a multihazard cascade. Science, doi:10.1126/science.ads2659 (accepted manuscript).
  • Asian Development Bank. Sikkim Integrated Urban Development Project (57230-001), resettlement and indigenous peoples due-diligence report for Soreng sewerage, December 2024, prepared by the Urban Development Department. https://www.adb.org/sites/default/files/project-documents/57230/57230-001-sddr-en.pdf
  • Wangsu, M., Isaac, R.K. and Tirkey, N. (2022). Development of rainfall-intensity-duration-frequency (IDF) curves for Ranikhola watershed, Gangtok, India. Journal of Soil and Water Conservation (abstract only; cited to show that no gauge-based Gangtok IDF exists).
  • Das, S.K. et al. (2022). Isopluvial analysis and intensity–duration–frequency curves for different cities in India. MAUSAM 73(4), 887–898 (no Sikkim panel).
  • Indian Roads Congress (2014). IRC:SP:42-2014, Guidelines on Road Drainage; and IRC:SP:48, Hill Road Manual.
  • South Asia Network on Dams, Rivers and People. Transcriptions of CWC site data for the Teesta basin, including the levels of 4 October 2023 (secondary source).
  • Sikkim Express, LiveLaw, Bar & Bench, ThePrint, EastMojo, Scroll, Business Standard, Republic World and other news sources (2017–2026). Reports of the Dikchu release of 2017, GSCDL's jhora-training tenders, the extension of the excavation ban in 2024, the NH-10 drainage case, the High Court's climate-justice case, the NDSA committee's findings, and the events of 1997, 2024 and 2025 (secondary sources).

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)