Chapter 1Policy, Applicability and Adoption
1.1 Purpose and objectives
1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Sikkim. It applies to private development and to public works, as set out in Clause 1.5.
1.1.2 The Manual has the following objectives:
- (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
- (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
- (c) to size storage for the long-duration storms of the monsoon season, which in Sikkim begin with the pre-monsoon storms of April and May, when Gangtok recorded its highest day, 310.3 mm on 30 May 1975 (IMD), and Singhik 504.2 mm on 12 May 1981 (CWC, 2(a)), run through the south-west monsoon, when Gangtok received 1,281.3 mm in June 1997 (IMD), and end with the storms of October, falling for days on thin soils over rock and colluvium that the stability zones already record as wet, and filling the hydropower reservoirs on the Teesta and the Rangit, as well as for short-duration intensities;
- (d) to design outfalls for the jhoras (झोरा; natural watercourses or ravine streams), kholas (खोला; rivers or large streams), rivers and reservoirs into which the towns drain: the steep jhoras of the ridge towns, among them those of Gangtok to the Rani Khola and the Roro Chu, which rise within the hour and carry slide debris and garbage to free outfalls with no river tailwater; the Teesta, the Rangit and the Rongni Chu at the valley-floor towns of Rangpo, Singtam, Melli, Majitar and Jorethang, on a bed that the flood of October 2023 raised by metres; and the reservoirs and release reaches of the hydropower projects on the Teesta and the Rangit, held and released by their operators, while the glacial-lake outburst flood (GLOF) corridors are screened apart from rainfall design (Clause 2.3.6(i)), including the case where the outfall is closed;
- (e) to protect tanks (pokharis), marshes, rivers, supply channels and surplus courses as part of the drainage system;
- (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
- (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
- (h) to make sure that facilities, once built, are maintained and remain effective.
1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building regulations made by the Government under section 7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 for the notified areas of the State (the Sikkim Building Construction Regulations, 1991), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).
1.2 Stormwater management hierarchy
1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.
- Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
- Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
- Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
- Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).
1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.
1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.
Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).
Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Sikkim, the top two layers have a particular meaning. Much of the State's natural storage and supply lies in its springs. A dhara (धारा; a spring or spring spout; Turner's headword is धारो, "Spring of water", Turner, 1931, p. 328) is the main water source of rural Sikkim, where "about 80%" of households are reported to depend on springs and "half of the perennial springs have already dried up or have become seasonal" (as reported). The Rural Management and Development Department (RMDD) has run the Dhara Vikas springshed programme since 2008 (2010 in one source; as reported, conflict), and its spring counts differ by date and source: 704 springs mapped for rejuvenation (as reported) and "more than 2000 springs mapped on GIS platform" (RMDD presentation of 2018, as reported). The storage lies too in the jhoras and kholas of the ridges; in the State's pokharis (पोखरी; ponds, lakes or tanks; Turner's पोखरि, "Lake, pool, tank", p. 391), among them Khecheopalri (Khachoedpalri), reported to have become the State's first Ramsar site in February 2025 (as reported; its area is given in several conflicting figures, none of which is used here); in the flat benches of the ridges and the gravel terraces of the Teesta and Rangit valley floors; and, high in the north, in 320 glacial lakes (State affidavit before the NGT, 2026). A glacial lake keeps its own name, even where the name contains "Pokhari", as Bhalay Pokhari and Doodh Pokhari do: it is a hazard source under Clause 2.3.6(i) and Chapter 7, never storage, and no storage credit or tank clause of this Manual applies to it. The law protects little of this. The Sikkim Municipalities Act, 2007 makes a jhora "any natural watercourse, whether on a public land or on a private land" (s.163(b)), vests jhoras on public land other than forest land in the municipality (s.172(1)) and requires that "the Municipality shall protect any jhora, whether on a public land or on a private land, within the municipal area" (s.172(2)); the State may "specify the limits of any jhora, watercourse or channel within a municipal area" by notification (s.173), but no such notification was found. The Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 keeps a river bank of "sixty metres on either side of such river or area within high flood level mark, whichever is less" for the 103 rivers of its Schedule (s.29(1)), under the Forest Department (s.29(9)), and the River Rejuvenation Committee is "the Nodal Agency for all water bodies" (Order No. 205/GOS/F&ED/SECY of 21.01.2021). No statute or rule found protects springs or pokharis with a buffer, no floodplain zoning law was found, and no wetland of the State was found notified under rule 4 of the Wetlands (Conservation and Management) Rules, 2017. On the slopes the second layer, retain, is limited by the ground: water put into a slope near a jhora can move it, and GSCDL told the NGT that "landslides are caused mainly due to loose soil by spring water generated at natural Jhora" (GSCDL reply, NGT OA 38/2022), which is why Clause 4.11 allows infiltration only on tested ground and keeps it out of stability zones 3 to 6.
1.3 Legal basis and status
1.3.1 Notification. This Manual shall be given statutory effect by the Government of Sikkim through:
- (a) an amendment to the Sikkim Building Construction Regulations, 1991 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
- (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.
1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.
1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.
1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.
Commentary. In Sikkim the building rules are the Sikkim Building Construction Regulations, 1991 (SBCR 1991): UD&HD Notification No. 29(202)UD&HD/90/295 of 19 March 1991, made under section 7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 (Act 11 of 1985), as amended by the Sikkim Building Construction (Amendment) Regulations, 2000 and 2001 (No. GOS/UD&HD/6(294)2001 of 16 October 2001). The copy read for this Manual is one hosted by a third party, Sikkim Manipal University; the 2001 amendment was also read as a true copy annexed to the State's counter-affidavit before the NGT. A Sikkim Building Construction (Amendment) Regulation, 2022 was reportedly published on 12 April 2023 (as reported); its text was not read, and it may change what follows [TBC]. The regulations "shall extend to all the notified areas in Sikkim" (reg. 1(2)) and apply to State, Central, semi-government and private builders, Defence excepted; the 1985 Act requires permission for any construction in a notified area (s.7(1)), lets the Government make building regulations (s.7(2)) and demolish illegal works (s.8), and, since its amendment by Act 24 of 2022, punishes an offence with "such fine as may be notified from time to time", triable by the District Magistrate. Rural land outside the notified areas has no building permission under the regulations (NEER reading; the list of notified areas was not found [TBC]). Applications go to "the Secretary, UD&HD" (reg. 4); since 2017 building-plan approval inside Gangtok has been with the Town Planning Cell of the Gangtok Municipal Corporation (GMC), still under the 1991 regulations (GMC affidavit before the NGT; the transfer notification's number was not seen [TBC]). No "Gangtok Building Bye-laws" were found. The Sikkim Municipalities Act, 2007 has its own building-permit system, under which "No person shall undertake any building activity without obtaining" a permit (s.271), with rules that may cover "infrastructure in relation to building activity" (s.287); no rules under it were found, and whether GMC applies it beside the 1991 regulations is not clear (NEER reading). The Sikkim Town and Country Planning Act, 2024 (Act 10 of 2024, amended by Act 24 of 2025) would provide development plans with "proposals for water supply, drainage, sewage and solid waste disposal" and "proposals for flood control, land stability and sloped linked controls", but it comes into force only on a date to be notified (s.1(3)), and no commencement notification, rules, Board or development authority was found: it is enacted, not in force.
The regulations already tie a site's drainage to its approval, without numbers. The blue-print plan shows "drainage including connection to main outlet and the slopes of the roof" and the "sanitary/plumbing layout … drainage system … sewerage disposal system/septic tank and soak pit" (reg. 6); gutters and down pipes are "of such design and capacity that the water will neither spill out of them nor leak through them" and go to "the storm water plinth protection drain" (reg. 21); a "Pucca storm water/plinth protection drain" leads "to the road side drain or to adjoining permanent drains or jhora" (reg. 25(iv)); and "No occupation certificate shall be issued … if the drain has not been provided to main outlet/jhora" (reg. 13(iii)). Height is set by the six stability zones of the Mines and Geology Department (reg. 17(i), as substituted in 2001), whose parameters of 2021 grade each zone partly by its jhoras: zone 1 "Training of jhoras/drains have been completed and done properly (with safe distance)", zone 3 "Jhora training is required/annual maintenance of drain is necessary", zone 4 "Untrained jhora/ erosional potential jhora" (Notification No. 17/DMG/20-21 of 19.03.2021). The 2001 copy of the regulations gives zone 2 "1 ½" storeys and the 2021 notification 4½; this Manual cites the 2021 notification. The regulations set no storm-water volume, peak flow, detention, runoff coefficient, design storm or setback from a jhora or river, and they do not mandate rainwater harvesting: they ask only that at least 25 per cent of each roof be sloped "with rain water gutter" (reg. 6). The only statutory rainwater harvesting in the State is for buildings owned or occupied by the State Government and its bodies (Sikkim Municipalities Act, 2007, s.186), "in such manner as may be specified", and no manner has been specified, as far as found. Nor do the regulations, as read, set up a register of professionals: the Municipalities Act registers "Architects, Structural Engineers and Construction Engineers on Record" (ss.266–287), and where this Manual speaks of a person registered under the SBCR 1991, or of SBCR 1991 registration (Form 10A), that register or the Authority's recognition is meant (Clause 1.4) [TBC]. The Government may relax any provision (reg. 39, 2001), and has relaxed heights for a hospital (11 storeys), the State Secretariat (8 storeys) and a GSCDL car park (4 + 7 storeys, "subject to confirmation of a Geotechnical investigation and Report") (State and GMC affidavits before the NGT, 2022).
Clause 1.3.1 sets out how the Manual could be given effect; none of these steps has been taken. The State Government could amend the SBCR 1991 under section 7(2) of the 1985 Act, at regs. 6, 13(iii), 21, 25(iv) and 35, to make compliance with this Manual a condition of permission and of the occupation certificate (Clause 1.3.1(a); the model text is Annex 1D). The Mines and Geology Department could cite the Manual's jhora-training and catchment-drain standards in the conditions for reviewing a site's zone, which already ask for "Training of untrained Jhora" and "Proper channelization of surface runoff by providing catchment drains" to "natural waterways/Jhora". In place of the bye-laws of Clause 1.3.1(b), a municipality could act under the Municipalities Act: the State Government could notify jhora limits (s.173), the State Government or the Municipality could specify the manner of rainwater harvesting (s.186), and rules could be made on "infrastructure in relation to building activity" (s.287). Once the 2024 Act commences, development plans could carry the Manual's flood-sensitive catchments, corridors and regional facility sites. SSDMA could refer to it in district disaster management plans, and the departments could apply it to their own works (Clause 1.3.4). Where land is needed for a corridor or a regional facility, it is secured by agreement or donation, or reserved in a development plan once the 2024 Act commences; this Manual never takes or acquires land. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.
1.4 Definitions
1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).
| Term | Meaning in this Manual |
|---|---|
| Approving Authority (the Authority) | The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the competent authority for the area: in Gangtok, the Gangtok Municipal Corporation (GMC), which has approved building plans in its area under the Sikkim Building Construction Regulations, 1991 since 2017 (GMC affidavit before the NGT) and owns and protects its drains and jhoras under sections 172 and 187 of the Sikkim Municipalities Act, 2007; in another notified area, the Urban Development Department (UDD) or the urban local body that approves plans there (how approval is split between UDD and the urban local bodies outside Gangtok was not found [TBC]); for the bank of a river scheduled under the Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988, the Forest Department; for a public work, the department or agency that executes it (the Roads and Bridges Department / PWD, NHIDCL, BRO, WRD, PHED, RMDD, UDD or GSCDL); and on land outside every notified and municipal area, where the regulations give no building permission, none: there this Manual is guidance, except for public works and for any body that adopts it (NEER reading), or a department for its own works. |
| Applicant | The owner, developer or department that seeks approval, and its successors in title. |
| Development | Any building, layout, sub-division, road, paving or land-use change that requires approval under the Sikkim Building Construction Regulations, 1991 or that is executed as a public work. |
| Redevelopment | Development on a site where impervious cover already exists. |
| Land disturbance | Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5). |
| Impervious area | Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats. |
| New or replaced impervious area | Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced". |
| Retention | Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4). |
| Detention | Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4). |
| Rainwater harvesting (RWH) | Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it. |
| Minor system | Drains, pipes and inlets designed for the minor-system AEP of Chapter 6. |
| Major system | The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6). |
| Pre-development condition | Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3). |
| Flood-sensitive catchment | The catchments of Gangtok's jhoras to the Rani Khola and the Roro Chu; the Teesta valley floor in the corridor of the flood of October 2023, at Chungthang, Dikchu, Singtam, Rangpo and Melli, with Toong Naga; the Rangit at Jorethang and Majitar; the Rongni Chu at Ranipool and Singtam; Mangan town and the slopes of the North Sikkim road; Lachen and Chaten, and every catchment below a high-risk glacial lake; the hydropower reservoirs and release reaches (Teesta-III once restored, Teesta-V, Teesta-VI, the Teesta Low Dam III and IV projects, Chuzachen, Dikchu, Jorethang, Tashiding, Rongnichu and Rangit-III); the NH-10 corridor along the Teesta; Namchi; and Soreng, and any catchment the Authority notifies (Chapter 4; Annex 1B). |
| Waterbody | A river, stream, canal, tank (pokhari), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7). |
| Regional facility | A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4). |
| Tier A / Tier B authority | An Approving Authority classed under Clause 1.6. |
| Policy supplement | The set of adoptable alternative clauses in Clause 1.7 and Annex 1C. |
| Drainage report | The preliminary or final report required by Chapter 10. |
| Registered professional | A person registered under the Sikkim Building Construction Regulations, 1991 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6. |
| Compliance calculator | The State-issued tool for computing and reporting compliance (Clause 10.5). |
| Maintenance declaration | The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10). |
| Variance | Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10). |
| Waiver | Approval that a requirement does not apply to a site, on the grounds in Clause 1.10. |
| Notified | Published by the Government or the State Stormwater Technical Committee in the Sikkim Government Gazette. |
| Competent authority for the area | The body that grants permission for the site, or executes the work, under the instrument that applies there: in Gangtok, the Gangtok Municipal Corporation (GMC), which has approved building plans under the SBCR 1991 since 2017 and owns and protects its drains and jhoras (Sikkim Municipalities Act, 2007, ss.172 and 187); in another notified area, the Urban Development Department (UDD) or the urban local body that approves plans there [TBC: the split outside Gangtok was not found]; the Forest Department for the bank of a scheduled river under the Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988; and the executing department or agency for a public work (the Roads and Bridges Department / PWD, NHIDCL, BRO, WRD, PHED, RMDD, UDD or GSCDL). On land outside every notified and municipal area the SBCR 1991 give no building permission, and this Manual is guidance there, except for public works and for any body that adopts it (NEER reading). Where this Manual says "the Authority", the competent authority for the area is meant. |
| Notified area | An area notified by the Government to which the SBCR 1991 extend (reg. 1(2): "They shall extend to all the notified areas in Sikkim"), and in which no construction may begin without permission (Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985, s.7(1)). The list of notified areas was not found for this Manual [TBC]. |
| Jhora | Jhora (झोरा): a natural watercourse or ravine stream. In law, "any natural watercourse, whether on a public land or on a private land" (Sikkim Municipalities Act, 2007, s.163(b)), and a "drain" includes "a jhora or water-course of natural drainage line" (s.2(24)); "river" includes any "jhora" (1988 Act, s.2(m)). Turner gives झोरा "Ravine", marked as Darjeeling usage (Turner, 1931, p. 237). A jhora draining 8 ha or more is a natural channel under Chapter 7. |
| Trained jhora | A jhora whose channel, as built and maintained, meets the jhora-training standard of Clause 6.3.6(m): it carries the 1% AEP flow with bulking and the Manual's freeboard, with toe and bed protection, drop structures with energy dissipation, a debris basin or rack above every culvert and a maintenance access, without loss of the jhora's 1% AEP capacity (set by this Manual). It gives a number to the "Training of jhoras/drains … done properly (with safe distance)" of stability zone 1 (Mines and Geology Department, 2021); it is not a finding of that Department. |
| Stability zone | One of the six site-stability zones of the Mines and Geology Department, on which the SBCR 1991 set the height of a building (reg. 17(i), as substituted in 2001): zones 1 to 6, from 5½ storeys to "No construction", with the parameters of Notification No. 17/DMG/20-21 of 19.03.2021, which grade each zone partly by the state of its jhoras, its slope and its ground water ("Dry/nil" in zone 1 to "Flowing" in zones 5 and 6). The 2001 copy of the regulations reads "1 ½" storeys for zone 2 and the 2021 notification 4½; this Manual cites the 2021 notification. |
| GLOF corridor | The path of a glacial-lake outburst flood (GLOF): the Teesta from the South Lhonak lake through Chungthang, Mangan, Dikchu, Singtam, Rangpo and Melli to the State border, the Lachen Chu and the Lachung Chu, and every stream below a glacial lake listed as high-risk by NDMA, the Science and Technology Department or the Sikkim Commission on Glacial Hazards, as shown on a GLOF hazard or evacuation map where one exists [TBC]. A GLOF corridor is screened for siting under Clause 2.3.6(i); no drain is sized for a GLOF. |
| Registration (in Sikkim) | The SBCR 1991, as read for this Manual, set up no register of professionals. Where this Manual refers to a person registered under them, or to SBCR 1991 registration, it means a professional registered under Chapter XXXII of the Sikkim Municipalities Act, 2007, which registers "Architects, Structural Engineers and Construction Engineers on Record" (ss.266–287), or a professional the Authority recognises for the purpose until a register exists (set by this Manual) [TBC]. |
Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).
1.5 Applicability
1.5.1 Who is covered. This Manual applies to:
- (a) all development requiring planning permission, building permit or layout approval under the Sikkim Building Construction Regulations, 1991;
- (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
- (c) works executed by Central agencies or their contractors within Sikkim, to the extent that the Authority's approval or no-objection is required.
1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:
- (a) land disturbance of 0.1 ha or more; or
- (b) new or replaced impervious area of 500 m² or more.
1.5.3 RWH. The existing RWH mandate continues to apply under section 186 of the Sikkim Municipalities Act, 2007 to "every building owned or occupied by the State Government or a statutory body or a company or an institution owned or controlled by the State Government", "in such manner as may be specified by the State Government or the Municipality from time to time" (no manner has been specified, as far as found), and to no other building (the SBCR 1991 require no rainwater harvesting, only that at least 25 per cent of a roof be sloped "with rain water gutter", reg. 6), as now. This Manual does not change it.
1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:
- (a) no sewage connection to a storm drain (Chapter 8);
- (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
- (c) waterbody setbacks and the no-fill zone (Chapter 7); and
- (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).
1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.
1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.
1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.
1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:
- (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
- (b) linear road resurfacing that adds no impervious area.
Exempt development remains subject to the RWH mandate and to Clause 1.5.4.
1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.
Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.
Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:
- Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
- Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
- The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
- MBBL 2016 makes recharge mandatory for buildings over 500 m².
The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Sikkim plots are small and the cumulative effect of many small plots is what fills Gangtok's drains. For small buildings in Sikkim, the SBCR 1991 already ask every site to drain: roof gutters and down pipes go to "the storm water plinth protection drain" (reg. 21), the plinth drain leads "to the road side drain or to adjoining permanent drains or jhora" (reg. 25(iv)), and no occupation certificate is issued until the drain reaches "main outlet/jhora" (reg. 13(iii)). None of this sets a size, a volume or a release rate, so none of it limits what leaves the plot in a design storm, and a lined drain that sends every roof's water straight to a jhora sends it sooner and with more energy down a slope that the stability zones may already record as wet. The regulations also put sewage into the ground on every site without a sewer, in a septic tank and soak pit (regs. 6, 13(iii) and 25(i)), which on a wet slope puts water where the hill rule of Clause 4.11 keeps it out; this Manual does not override the regulation, puts no storm water into a soak pit, and recommends that no new soak pit be placed in stability zones 3 to 6 and that one on a slope of more than 10° be sited by a geotechnical engineer, downslope of buildings and cuts (set by this Manual), referring sewage to Clause 8.9. Clause 1.5.4(b) applies to every building whatever its size for these reasons. Outside the notified areas, where the regulations do not reach (reg. 1(2)), no building rule found reaches a small building, and this Manual is guidance only: a household, a village body or a public agency could use the small-site method of Chapter 4 and the hill rule of Clause 4.11 as guidance. A small building on a slope is where a soakaway can do most harm, and an Authority may make the hill rule of Clause 4.11 a condition of every permission in its area, whatever the size of the site (a recommendation of this Manual, not a requirement of Clause 1.5.4).
Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.
1.6 Tiered adoption
1.6.1 Tier A authorities. The following are Tier A:
- (a) the Gangtok Municipal Corporation (GMC), for its whole area; and
- (b) once a development plan under the Sikkim Town and Country Planning Act, 2024 (enacted in 2024 and amended in 2025, not yet commenced) is published for a planning area, every approving authority within that planning area, whichever has jurisdiction over a site (no such plan has been published).
1.6.2 Tier B authorities. All other Municipal Councils, Nagar Panchayats and other approving authorities under the regulations are Tier B.
1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:
Table 1.1 — Differences between Tier A and Tier B authorities
| Item | Tier A | Tier B |
|---|---|---|
| Performance criteria (Chapters 2–9) | Apply in full | Apply in full |
| Hydrologic method for storage | Hydrograph method (Chapter 3) | Hydrograph method, or the design-aid route of Clause 1.7 where eligible |
| Compliance calculator (Clause 10.5) | Required as a summary | Required; may be the sole calculation on the design-aid route |
| Policy supplement alternatives (Clause 1.7) | Only with State Stormwater Technical Committee concurrence | May be adopted by council resolution |
| Technical review | By the Authority | By the Authority, with UDD regional support or an empanelled reviewer (Clause 10.7) |
| Flood-sensitive catchment rule | Applies | Applies |
1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the area of the Gangtok Municipal Corporation or, once a development plan is published under the Sikkim Town and Country Planning Act, 2024 (enacted in 2024 and amended in 2025, not yet commenced), the planning area of that plan (none has been published), or is found by a post-event review (Clause 10.16) to need the full methods.
1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.
Commentary. Gangtok Municipal Corporation, with no drain inventory or drain design standard found, building-plan approval in its area under the SBCR 1991 since 2017 (GMC affidavit before the NGT), the State's only sewer network, whose plants treated 15.22 MLD in September 2025 against 18.33 MLD of sewage estimated for its area (State affidavit before the NGT, 19.12.2025), and the clearing of its jhoras let to its waste agency (GMC, 2024), and a small Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Gangtok.
1.7 Policy supplement: adoptable alternatives
1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.
1.7.2 The alternatives are:
Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5
| No. | Main-text requirement | Adoptable alternative | Eligibility |
|---|---|---|---|
| S-1 | Storage sized by hydrograph method (Chapter 3) | Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator | Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1) |
| S-2 | Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site | Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule | Any site outside flood-sensitive catchments |
| S-3 | Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) | Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 | Waterbodies with no mapped 1% AEP extent |
| S-4 | Downstream analysis by hydraulic model (Chapter 5) | Screening checklist of downstream capacity and known flooding, with a model only where the screen fails | Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall |
| S-5 | On-site detention | Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) | Where a basin plan has been notified |
1.7.3 Conditions on adoption.
- (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
- (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
- (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
- (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
- (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).
Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.
1.8 Relationship with other instruments
1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.
Table 1.3 — Relationship with other instruments
| Instrument | Relationship |
|---|---|
| the Sikkim Building Construction Regulations, 1991 (SBCR 1991; UD&HD Notification No. 29(202)UD&HD/90/295 of 19 March 1991, made under section 7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985), as amended by the Sikkim Building Construction (Amendment) Regulations, 2000 and 2001 (No. GOS/UD&HD/6(294)2001 of 16 October 2001); a further amendment of 2022, reportedly published on 12 April 2023, not read (as reported) [TBC] | Continue where they apply: in the notified areas (reg. 1(2)), with the Urban Development Department (UDD), and since 2017 the Gangtok Municipal Corporation in Gangtok, as the approving body. They require a site plan with the "position of sewer line, water main pipe line" (reg. 5(f)); a blue-print plan with "drainage including connection to main outlet and the slopes of the roof" and the septic tank and soak pit (reg. 6); roof gutters and down pipes to "the storm water plinth protection drain" (reg. 21); no spoil in "drains, gullies and jhoras", on a fine of ₹500 at least (reg. 22); a "Pucca storm water/plinth protection drain" to "the road side drain or to adjoining permanent drains or jhora" (reg. 25(iv)); no occupation certificate "if the drain has not been provided to main outlet/jhora" (reg. 13(iii)); and no allotment or regularisation in "any sinking area, landslide prone or in areas having scars of old landslides or in slope exceeding or around 70 (Seventy) degree" (reg. 35). They set no storm-water volume, peak flow, detention, runoff coefficient, design storm, rainwater-harvesting rule or setback from a jhora or river. The design criteria of Chapters 2–6, the hill, valley-floor and recharge rules of Clause 4.11 and the corridors of Chapter 7, whose Zone 1 is at least 15 m, are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the SBCR 1991 or a statute is stricter, it governs (Clause 1.3.3). |
| Site stability zones: Mines and Geology Department Notification No. 17/DMG/20-21 of 19.03.2021 (Sikkim Government Gazette Extraordinary No. 86, 06.04.2021), "In continuation with" the zones of the 2001 amendment (SBCR 1991, reg. 17(i)) | Continue. Zones 1 to 6 set building height from 5½ storeys to "No construction"; the 2001 copy of the regulations reads "1 ½" storeys for zone 2 and the 2021 notification 4½ (a conflict; this Manual cites the 2021 text). The zones are graded partly by jhora training (zone 1 "done properly (with safe distance)"; zone 3 "Jhora training is required"; zone 4 "Untrained jhora/ erosional potential jhora"), slope (zone 1 "<15°" to zones 5 and 6 ">45°") and ground water ("Dry/nil" to "Flowing"), and a site's zone may be reviewed after "Proper channelization of surface runoff by providing catchment drains … and connect it to natural waterways/Jhora". The zones are site classes for building height, not infiltration rules; this Manual uses them as such in Clause 4.11, forbids deliberate infiltration in zones 4 to 6 and requires a geotechnical certificate for it in zone 3, and gives numbers to "training" and "catchment drains" (Clause 6.3.6(m)). |
| Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 (Act 11 of 1985), as amended in 2000, 2001, 2007 and by Act 24 of 2022 | Continue. Prior permission for any construction in a notified area (s.7(1)); power to make building regulations (s.7(2)) and to demolish illegal works (s.8); penalty "such fine as may be notified from time to time", offences "triable by the District Magistrate" (2022). Its preamble records allotments that caused "encroachment of septic, water supply tanks … within the notified green belt and effecting and likely to cause land slides during monsoons". The route by which the regulations could be amended to give effect to this Manual (Clause 1.3.1(a)). |
| Sikkim Municipalities Act, 2007 (Act 5 of 2007), as amended up to Act 3 of 2026 and by Ordinance 5 of 2026 | Continue. A "drain" includes "a jhora or water-course of natural drainage line" (s.2(24)), and a jhora is "any natural watercourse, whether on a public land or on a private land" (s.163(b)); jhoras on public land other than forest land in a municipal area vest in the Municipality (s.172(1)), which "shall protect any jhora, whether on a public land or on a private land" (s.172(2)); the State may "specify the limits of any jhora, watercourse or channel within a municipal area" by notification (s.173; none found); rainwater harvesting is required in buildings owned or occupied by the State Government and its bodies, in a manner to be specified (s.186; none specified, as far as found); the Municipality provides "a safe and sufficient outfall … in such manner as may not cause any nuisance, either by flooding any part of the municipal area or any area surrounding the outfall" (s.187), and drains vest in "the Municipality, or the concerned Department, or organization, of the State Government, or the agency, as the case may be" (s.189(1)); sewage and rain water go in separate drains, the rain water to "the natural nullahs, khola-kholsas, jhoras, or storm water drainage" (s.193(b)); and Chapter XXXII sets up a building-permit system (ss.266–287) under which no drainage rules have been made. This Manual supplies the hydraulic meaning of "protect" and of a "safe and sufficient outfall" (Chapters 5–7). |
| Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 (Act 6 of 1988), as amended by Act 8 of 2000 | Continue. For the 103 rivers of its Schedule, from the Teesta and the Rangeet to the Khani Khola at Melli, the river bank is "an area of sixty metres on either side of such river or area within high flood level mark, whichever is less" (s.29(1)), under the Forest Department "as if it were a forest" (s.29(9)); its unauthorised occupation is an offence (s.30), and a river bank may be closed by notification (s.32). "Whichever is less" makes the line a maximum, not a minimum (NEER reading), and "river" includes "any stream, channel, jhora" (s.2(m)) though the 60 m applies only to the Schedule. Slip reserves (s.29(2)) are a hook for slope works. Where the statutory bank is wider than this Manual's Zone 1 it binds as well; where the flood mark lies nearer the channel, the Manual's corridor is stricter (Chapter 7). After October 2023 the high flood level itself has moved. |
| Sikkim Town and Country Planning Act, 2024 (Act 10 of 2024; Gazette Extraordinary No. 317, 15.06.2024), amended by Act 24 of 2025 (Gazette Extraordinary No. 13, 17.01.2026) | Enacted, not yet commenced: it comes into force on a date to be notified (s.1(3)), and no commencement notification, rules, Board or development authority was found. Once in force, its development plans would carry "proposals for water supply, drainage, sewage and solid waste disposal" and "proposals for flood control, land stability and sloped linked controls"; this Manual offers them its flood-sensitive catchments, corridors, 1% AEP extents and facility sites. It repeals the planning Acts of 1998 and 2007 (s.124); their status until it commences is not settled (NEER reading: a repeal takes effect when the repealing Act commences) [TBC]. |
| Monsoon notices of UD&HD and UDD: Notice No. 613/GOS/JCTP/UD&HD of 01.05.2019 (no earth excavation from 6 May to 30 September 2019) and Notice No. T(1689)/997 of 26.05.2020 (1 June to 30 September 2020); a ban from 1 May 2024, extended by 15 days (as reported) | Continue, as annual notices, not regulations. They stop "construction involving earth excavation works" and the issue of Construction Orders for the monsoon, and seize material "lying on the road setback or over drains". Drainage earthworks under this Manual are therefore finished before the ban, by the deadline of Chapter 10, and the notices are the hook for construction-phase sediment control (Chapter 8). |
| Official languages: Sikkim Official Languages Act, 1977 (Act 5 of 1977), as amended | Continue. "The Nepali, the Bhutia, the Lepcha and the Limbu languages" are the languages "for all official purposes of the State" (as amended in 1981), with other languages added later, the last being Bhujel (Act 16 of 2022). This Manual is published in English; a Nepali edition is to follow. Signs and depth markers are in Nepali and English, and in another official language of the State where the local body's own notices use it (front matter). |
| Floodplains, waterbodies, springs and private rainwater harvesting: no State law found; the Wetlands (Conservation and Management) Rules, 2017 | No floodplain zoning law, notified flood line, waterbody or spring protection law, or rainwater-harvesting rule for private buildings was found, and no wetland of the State was found notified under rule 4 of the 2017 Rules. The River Rejuvenation Committee is "the Nodal Agency for all water bodies" (Order No. 205/GOS/F&ED/SECY of 21.01.2021). No setback along the Teesta was found after October 2023; the "High-risk Zoning" of floodplains below glacial lakes in the State's Lhonak valley PPR is a proposal, not a rule. The corridors, spring rule and glacial-lake siting rule of Chapter 7 are this Manual's proposals. |
| Courts and tribunals: High Court of Sikkim, WP(PIL) 4/2017 (judgment of 01.03.2021), WP(PIL) 3/2023 (judgment of 07.12.2023), WP(PIL) 1/2024 (judgment of 15.05.2025) and the suo motu WP(PIL) 11/2026, In re Climate Justice in State of Sikkim (as reported); the NGT, OA 171/2023 (EZ), OA 5/2022 and 38/2022 (EZ), OA 673/2018 and OA 606/2018 | Directions to the parties, not rules of this Manual. The High Court directed "that the hydropower projects in Sikkim shall ensure strict compliance of the safety guidelines" and that authorities "undertake periodic inspection and review" (WP(PIL) 4/2017); in WP(PIL) 11/2026 the State is reported to have been asked to examine "land-use regulation, spatial planning, slope management, and drainage in ecologically and geologically fragile areas" (as reported; orders not read [TBC]). The NGT has recorded that "treated sewage is entering in to river/ rivulets/ jhoras and this is not permissible under the Water Act" (OA 606/2018, order of 04.07.2024, as quoted by the State), which the State answered with "No sewage is disposed off in the rivers or fast flowing water bodies"; both are stated in Chapter 8. A design under this Manual also meets any order that applies to its site. |
| Disaster Management Act, 2005; SSDMA, the District Disaster Management Authorities and the District Collectors; the Science and Technology Department as nodal department for GLOF (Notification No. 10/Home/2025 of 07.02.2025); the Sikkim Commission on Glacial Hazards (No. 73/Home/2024 of 11.09.2024) | Continue. GLOF corridors, landslide ground and release reaches are screened under Clause 2.3.6(i) from their maps and inventories where they exist [TBC]; this Manual sets no setback for the cascade and sites its own drainage assets above the October 2023 flood and aggradation level (Chapter 7). No urban-flood standard operating procedure of SSDMA was found [TBC]. |
| Environment (Protection) Act, 1986; Water (Prevention and Control of Pollution) Act, 1974; the Sikkim State Pollution Control Board (SSPCB) | Continue. Consents for sewage treatment plants and other discharges; Chapter 8 deals with sewage in storm drains and jhoras. |
| Terms of the Sikkim Integrated Urban Development Project (ADB 57230-001) and of GSCDL's drainage and jhora-training works | Apply to those works as their contracts say. No design storm, return period or runoff coefficient was seen in them; where a project's terms govern, the designer states on the submittal which governs (this Manual does not override a contract). |
| IRC:SP:42-2014, IRC:SP:48 (Hill Road Manual) and the practice of the Roads and Bridges Department / PWD, NHIDCL and BRO on hill-road drainage | Apply to road drainage where they do not conflict with Chapter 6; no road drain discharges onto an unprotected slope (Clause 6.3.6(k)). |
| CPHEEO Manual on Storm Water Drainage Systems (2019) | Engineering reference. This Manual sets higher return periods under Clause 1.3.2. |
| NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) | This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF. |
| NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 | Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create. |
| IRC:SP:42-2014 and IRC:SP:50-2013 | Apply to road drainage only where they do not conflict with Chapter 6. |
| MBBL 2016, Chapter 9 | Model for RWH and for the inspection regime in Chapter 10. |
Commentary. RWH in Sikkim is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the monsoon, because RWH sumps are usually full or the ground saturated by the time a June to September monsoon storm, such as those of 9 June 1997 at Gangtok and 25 September 2005 at Tadong, arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.
Sikkim is building drains and training jhoras, but without a design basis. The Gangtok City Development Plan of 2006 proposed works of ₹2,217 crore, among them "Drainage and Landslip Protection", but "Projects under Drainage, Landslip Protection, Traffic, Street Lighting, Tourism and Environment were not taken up" (CAG, Report No. 3 of 2016, para 2.3.9.2). Gangtok Smart City Development Ltd (GSCDL) has tendered "Construction of drainage and jhora training works" in Gangtok, of about ₹13.41 crore (as reported); the ADB's Sikkim Integrated Urban Development Project includes "Improving about 60 km roads in seven towns with junction improvements, improved pavement and stormwater drains", with infrastructure master plans for four towns other than Gangtok (ADB, 57230-001); and GMC has begun to refurbish the back drainage of MG Marg (as reported). None of the documents found states a design storm or a return period, and no development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.
The State's law holds some of the tools. The SBCR 1991 require a drain to "main outlet/jhora" before occupation (reg. 13(iii)) and ban spoil in jhoras (reg. 22); the stability zones of 2021 already make a site's buildability depend on whether its jhora is trained and its surface water carried off by catchment drains; the Sikkim Municipalities Act, 2007 makes the municipality protect every jhora in its area (s.172(2)), route rain water to jhoras or storm drains apart from sewage (s.193) and provide outfalls that do not cause "nuisance … by flooding … any area surrounding the outfall" (s.187); and the river bank of the 1988 Act keeps the scheduled rivers' edges under the Forest Department. None of them says how large a drain or a trained jhora must be, how much a site may release, or how far a building must stand from a jhora. This Manual supplies those numbers: the design rainfall of Chapter 2, the on-site controls of Chapter 4, the outfall rules of Chapter 5, the jhora-training standard of Clause 6.3.6(m) and the corridors of Chapter 7. It also adds a step that no Sikkim document takes: storage first. Every litre sent faster down a jhora arrives sooner, with more energy and more debris, on a slope that the 2021 zones already treat as unstable where the jhora is "untrained" or "erosional", and the jhoras end in a Teesta whose bed rose by metres in 2023 and whose valley-floor towns receive everything the ridge towns send.
Rainwater harvesting in Sikkim is a matter of supply, not flood control. The only statutory requirement is for buildings owned or occupied by the State Government and its bodies (Sikkim Municipalities Act, 2007, s.186), in a manner not yet specified as far as found, and a reply in the Rajya Sabha in 2019 listed Sikkim as "NA asked to take up rain water harvesting structure for Government buildings" (as quoted). Where this Manual credits harvested water, it does so as storage and reuse only (Clause 4.4.3), never as detention, because the tanks are full when the season's largest storms arrive.
1.9 Roles and responsibilities
1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.
Table 1.4 — Roles and responsibilities under this Manual
| Agency | Role under this Manual |
|---|---|
| Urban Development Department (UDD; formerly the Urban Development and Housing Department, UD&HD) | "The nodal department which undertakes planning and development in the notified areas" (State counter-affidavit before the NGT, 2022); issued the SBCR 1991, approves plans in notified areas outside Gangtok with the urban local bodies [TBC], issues the monsoon excavation notices and is the executing agency of the ADB's Sikkim Integrated Urban Development Project (ADB). Could propose the amendment of Clause 1.3.1(a) under section 7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985, design its drainage works to this Manual and give regional support to Tier B authorities (Table 1.1), if the Manual were adopted; once the Sikkim Town and Country Planning Act, 2024 commences, could carry its corridors and facility sites into development plans. |
| State Stormwater Technical Committee (Clause 1.3.2) | Would set the higher standards of Clause 1.3.2, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12). |
| Gangtok Municipal Corporation (GMC) | "A statutory body established under the Sikkim Municipalities Act, 2007"; has approved building plans in Gangtok under the SBCR 1991 since 2017 (GMC affidavit before the NGT); holds its drains and the jhoras on public non-forest land in its area and must protect every jhora there (ss.172, 189); lets the "Clearing of Jhoras" to its waste agency (GMC, 2024). Would be Tier A (Clause 1.6.1), review drainage reports, keep the drain and jhora register of Table 1.5 and publish its decisions, if the Manual were adopted. |
| The other urban local bodies: the Namchi Municipal Council and the Nagar Panchayats of Rangpo, Singtam, Mangan, Gyalshing, Nayabazar-Jorethang, Soreng and Pakyong (UDD Notification No. 06/UDD/2026; seven or nine bodies, as the sources differ) | Hold and protect the drains and jhoras of their areas under the Municipalities Act (ss.172, 187, 189, 193). Would be Tier B authorities (Clause 1.6.2) and keep drain and jhora registers, if the Manual were adopted; could act under the Act as Clause 1.3.1 describes. |
| Mines and Geology Department | Prepares the stability map on which building height rests (reg. 17) and notified the zone parameters of 2021, with their jhora and drainage conditions; advised against "any form of physical intervention on the moraine dam" at Shako Chho (State affidavit before the NGT, 2026). Could cite the jhora-training and catchment-drain standards of this Manual in its zone-review conditions. |
| Water Resources Department (WRD; formerly Irrigation and Flood Control) | Builds river and jhora works; nodal authority for the monitoring of NGT OA 673/2018 (Office Order No. 135A/CS/SKM/2022 of 09.12.2022) and monitors river water quality with CWC and SSPCB. Would supply river levels and flood marks for Chapter 5, train jhoras to Clause 6.3.6(m) and concur in works in or on a river. |
| Forest and Environment Department and its River Rejuvenation Committee | Hold the river banks of the 103 scheduled rivers "as if it were a forest" and the slip reserves (1988 Act, s.29); the River Rejuvenation Committee is "the Nodal Agency for all water bodies" (Order No. 205/GOS/F&ED/SECY of 21.01.2021). Would be the competent authority for works on a scheduled river's bank and keep the waterbody records of Chapter 7. |
| Public Health Engineering Department (PHED) | "The concern department for sewage management in the State" (State report before the NGT); runs Gangtok's sewers and treatment plants. Would receive the records of sewage found in storm drains and jhoras under Chapter 8. |
| Rural Management and Development Department (RMDD) | Supervises rural and peri-urban sewage (State report before the NGT) and runs the Dhara Vikas springshed programme (as reported). Would supply spring locations and recharge areas for the spring rule of Chapter 7, and train rural jhoras to this Manual. |
| Roads and Bridges Department / PWD, NHIDCL and BRO | Build and maintain the roads, their side drains and culverts, which in the hill towns are much of the minor drainage system; NH-10 runs along the Teesta. Would apply Chapter 6 to road drainage and never discharge onto an unprotected slope. |
| Gangtok Smart City Development Ltd (GSCDL) | Builds works in Gangtok under the Smart Cities Mission, among them drainage and jhora training (as reported). Would design them to this Manual, if it were adopted. |
| SSDMA, the Land Revenue and Disaster Management Department (LR&DMD), the District Collectors and the District Disaster Management Authorities | Prepare for and respond to floods, landslides and GLOFs and report their tolls; ran the GLOF participatory risk assessments of May 2024 and the State mock exercise of 17.11.2025; the PDNA of 2023 was SSDMA's, with NDMA (State affidavit before the NGT, 2026). Would supply the event records, maps and inventories used in the screening of Clause 2.3.6(i) and lead post-event reviews with the Authority (Clause 10.16). |
| Science and Technology Department; the Sikkim Commission on Glacial Hazards; the High-Level Steering Committee and Multi-disciplinary Task Force (Home Department Notifications No. 72/Home/2024 and 73/Home/2024 of 11.09.2024) | The Science and Technology Department is the nodal department for GLOF studies and mitigation (Notification No. 10/Home/2025 of 07.02.2025). Would supply the glacial-lake lists and GLOF hazard maps used in the screening of Clause 2.3.6(i). |
| Sikkim State Pollution Control Board (SSPCB) | Grants consents for sewage treatment plants and other discharges. Would receive the records of Chapter 8. |
| NHPC and the other hydropower operators (Teesta-III once restored, Teesta-V, Teesta-VI, the Teesta Low Dam projects, Chuzachen, Dikchu, Jorethang, Tashiding, Rongnichu, Rangit-III) | Operate the dams and their gates. Operators, not approving authorities: would supply reservoir levels, release records and release rules, which were not found [TBC], for Chapter 5 and the screening of Clause 2.3.6(i). |
| Central Water Commission (CWC), a body of the Union | Publishes the Flood Estimation Report for subzone 2(a) used in Chapters 2 and 3 and runs the level sites on the Teesta, the Rangit and the Rongni Chu. Would supply stage records and site sheets for Chapter 5. |
| IMD (Meteorological Centre Gangtok), and road and rail owners | IMD's stations at Gangtok (42299) and Tadong (22209) and the district network of its Gangtok centre supply the rainfall records of Chapter 2; Gangtok is the first data request of Clause 2.3.6(a). Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7). |
Commentary. Stormwater in Sikkim is split, first, by land. In the notified areas the SBCR 1991 apply, with UDD and, in Gangtok, the Gangtok Municipal Corporation (GMC) as approving bodies; in the municipal areas the Sikkim Municipalities Act, 2007 makes the urban local body the owner of the public drains and of the jhoras on public land other than forest land, and the protector of every jhora, public or private (s.172); the banks of the 103 scheduled rivers are Forest Department land (1988 Act, s.29(9)); and outside the notified and municipal areas no building rule found applies and no body is named as the owner of a jhora, on forest land or off it (NEER reading). How many urban local bodies there are is itself stated two ways: the State told the NGT on 19.12.2025 that "there are seven Urban Local Bodies (ULBs) in the State", while UDD's Notification No. 06/UDD/2026 of 23.04.2026 lists nine, the Gangtok Municipal Corporation, the Namchi Municipal Council and seven Nagar Panchayats, and UDD's web page lists seven and calls Namchi a "Municipal Corporation"; this Manual uses the 2026 notification's names. The split is then repeated among the bodies that drain the land: UDD, GSCDL and the ADB project build drains; the Roads and Bridges Department / PWD, NHIDCL and BRO build the road drains that are much of the minor system in the hill towns; WRD trains rivers and jhoras; PHED runs the sewers, and septic tanks serve the rest; RMDD works on springs and rural sewage; and the hydropower operators set the river below their dams. No notification divides the drains of any Sikkim town among their owners (NEER reading). Until the State issues such a rule [TBC], this Manual assigns the drainage elements as in Table 1.5, as Chapter 6 does for the drains themselves, and requires each town to keep a drain and jhora register giving every reach its owner under this split, its land status (municipal, Forest Department, private or road reserve) and its outfall (set by this Manual). The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers, and on private land it is put into effect by agreement or donation, not by acquisition.
Table 1.5 — Working assignment of drainage elements under this Manual
| Element | Assigned to |
|---|---|
| Municipal drains, and jhoras on public land other than forest land within a municipal area | The urban local body (Sikkim Municipalities Act, 2007, ss.172(1) and 189(1)); in Gangtok, GMC |
| Every jhora in a municipal area, public or private, for its protection | The urban local body (s.172(2)) |
| River banks of the 103 scheduled rivers | The Forest Department (1988 Act, s.29(9)) |
| Road drains | The road owner: the Roads and Bridges Department / PWD for State roads; NHIDCL or BRO for national highways (by inference) |
| Jhora training | The executing agency: GSCDL for Smart City works (as reported); WRD for river and jhora works; RMDD in rural areas |
| Sewers and sewage treatment plants; rural and peri-urban sewage | PHED; RMDD |
| Hydropower reservoirs and their gates | The operator (data, not approval) |
| Springs | No statutory owner (RMDD's Dhara Vikas works on them, as reported) |
| Jhoras outside municipal limits or on forest land | No named owner |
This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.
1.10 Variances and waivers
1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:
- (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
- (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.
1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Sikkim has no coast and no tidal reach, so no site in the State qualifies for this waiver. A site that drains to the Teesta, the Rangit or the Rongni Chu at a valley-floor town, to a hydropower reservoir or its release reach, or to any river in flood, is in the outfall-closed condition of Chapter 5 whenever the receiving water is high, and detention is not waived for it; nor is it waived for a site because it drains to a steep jhora, which carries every litre sent to it sooner, with more energy and more debris, to the slopes and the valley-floor towns below.
1.10.3 No variance or waiver. No variance or waiver shall be granted for:
- (a) a sewage connection to a storm drain;
- (b) the lowest habitable floor level of Chapter 6;
- (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
- (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.
1.10.4 Procedure.
- (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
- (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
- (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
- (d) A variance runs with the approval. It lapses if the approval lapses.
Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Sikkim no statute or regulation sets any line along a jhora, the one statutory river line found, the river bank of "sixty metres on either side of such river or area within high flood level mark, whichever is less" (Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988, s.29(1)), is a maximum that shrinks to the flood mark on an incised reach, the State's power to "specify the limits of any jhora" in a municipal area (Sikkim Municipalities Act, 2007, s.173) has not been used as far as found, and the stability-zone notification of 2021 asks only that jhoras be trained "with safe distance", undefined (Mines and Geology Department, 2021).
1.11 Transition provisions
1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).
1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.
1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.
1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.
1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.
Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).
1.12 Review and amendment
1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.
1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.
1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.
References (chapter)
- Government of Sikkim, Urban Development and Housing Department. Sikkim Building Construction Regulations, 1991, Notification No. 29(202)UD&HD/90/295 of 19 March 1991, as amended by the Sikkim Building Construction (Amendment) Regulations, 2000 (copy hosted by a third party, Sikkim Manipal University). https://smu.edu.in/img/content/dam/manipal/smu/IQAC/SDG/documents/BUILDING%20STANDARDS.pdf
- Government of Sikkim, UD&HD. Sikkim Building Construction (Amendment) Regulations, 2001, No. GOS/UD&HD/6(294)2001 of 16 October 2001 (read in the copy above and as Annexure R/1 to the State's counter-affidavit in NGT OA 5/2022 (EZ)).
- Sikkim Building Construction (Amendment) Regulation, 2022, reportedly published on 12 April 2023 (as summarised by TeamLease; text not read [TBC]). https://teamleaseregtech.com/updates/article/22995/sikkim-building-construction-amendment-regulation-2022/
- Government of Sikkim. Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985 (Act 11 of 1985), with Amendment Acts 16 of 2000, 8 of 2001, 6 of 2007 and 24 of 2022. https://prsindia.org/files/bills_acts/acts_states/sikkim/1985/1985SK11.pdf
- Government of Sikkim, Department of Mines and Geology. Notification No. 17/DMG/20-21 of 19.03.2021, site stability zonation parameters (Sikkim Government Gazette Extraordinary No. 86, 06.04.2021), read as Annexure R/2 to the State's counter-affidavit in NGT OA 5/2022 (EZ).
- Government of Sikkim. Sikkim Municipalities Act, 2007 (Act 5 of 2007), with amendments up to Act 3 of 2026. https://prsindia.org/files/bills_acts/acts_states/sikkim/2007/2007SK5.pdf ; Sikkim Municipalities (Amendment) Ordinance, 2026 (Ordinance 5 of 2026), Gazette Extraordinary No. 95, 20.03.2026. https://sikkim.gov.in/uploads//Notifications/Gazette_Num_95_74_20260502.pdf
- Government of Sikkim, Urban Development Department. Notification No. 06/UDD/2026 of 23.04.2026 (the nine urban local bodies). https://sikkim.gov.in/uploads//Notifications/Gazette_Num_158_74_20260502.pdf ; "Urban scenario" web page. https://www.sikkim.gov.in/departments/urban-dev-housing-department/urban-scenario
- Government of Sikkim. Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 (Act 6 of 1988), as amended by Act 8 of 2000. https://prsindia.org/files/bills_acts/acts_states/sikkim/1988/1988SK6.pdf
- Government of Sikkim. Sikkim Town and Country Planning Act, 2024 (Act 10 of 2024; Gazette Extraordinary No. 317, 15.06.2024), and (Amendment) Act, 2025 (Act 24 of 2025; Gazette Extraordinary No. 13, 17.01.2026); not yet commenced. https://prsindia.org/files/bills_acts/acts_states/sikkim/2024/Act10of2024SK.pdf
- Government of Sikkim. Sikkim Official Languages Act, 1977 (Act 5 of 1977), as amended, with the (Amendment) Act, 2022 (Act 16 of 2022). https://prsindia.org/files/bills_acts/acts_states/sikkim/1977/1977SK5.pdf
- UD&HD Notice No. 613/GOS/JCTP/UD&HD of 01.05.2019 and UDD Notice No. T(1689)/997 of 26.05.2020 (monsoon excavation bans), Annexure R/5 to the State's counter-affidavit in NGT OA 5/2022 (EZ); the 2024 extension (as reported).
- National Green Tribunal (EZ). OA 5/2022, Dr. Bina Basnett v. State of Sikkim & Ors.: counter-affidavits of the State (Respondents 1, 4, 7 and 9, 25.02.2022) and of GMC (Respondent 10); OA 38/2022, reply of GSCDL. https://www.greentribunal.gov.in/
- National Green Tribunal (EZ). OA 171/2023, additional affidavit of the State of Sikkim of 28.02.2026, with Home Department Notifications No. 72/Home/2024 and 73/Home/2024, Notification No. 10/Home/2025, the PPR "GLOF Risk Mitigation in Lhonak Valley, Sikkim" and the PDNA summary. https://www.greentribunal.gov.in/
- National Green Tribunal (PB). OA 673/2018, EA 35/2023: affidavit of the State of Sikkim of 19.12.2025, with the monthly progress report of September 2025, and the State's compliance report; OA 606/2018, six-monthly report of the State after the order of 04.07.2024. https://www.greentribunal.gov.in/
- High Court of Sikkim. WP(PIL) 4/2017, In re: Release of water from Dikchu Hydelpower Project, judgment of 01.03.2021; WP(PIL) 3/2023, Mani Kumar Subba v. State of Sikkim, judgment of 07.12.2023; WP(PIL) 1/2024, judgment of 15.05.2025. https://hcs.gov.in/
- High Court of Sikkim. WP(PIL) 11/2026, In re Climate Justice in State of Sikkim (as reported, LiveLaw, 17.09.2026 and November 2026; orders not read [TBC]).
- Comptroller and Auditor General of India. Report No. 3 of 2016 (Economic Sector, Government of Sikkim), Chapter II, Performance Audit of JNNURM. https://www.cag.gov.in/
- Turner, R.L. (1931). A Comparative and Etymological Dictionary of the Nepali Language (pp. 237, 328, 391), via the Digital South Asia Library. https://dsal.uchicago.edu/dictionaries/turner/
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §4.4.1.4 (Table 4.1 and notes).
- Kakkar, R. (CPHEEO) (2023). Understanding Urban Stormwater Management. CSE, Aug 2023.
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding.
- MoHUA (2016). Model Building Bye-Laws, Chapter 9.
- Lok Sabha Unstarred Question 1847, 30 Jul 2026 (MoHUA). https://sansad.in/getFile/lsapps/loksabhaquestions/annex/188/AU1847_x29brZ.pdf
- Sattar, A. et al. (2025). The Sikkim flood of October 2023: Drivers, causes and impacts of a multihazard cascade. Science. doi:10.1126/science.ads2659 (accepted manuscript).
- Sikkim State Disaster Management Authority with NDMA. Post Disaster Needs Assessment, Teesta flood of October 2023 (summary, field assessment 7–11 December 2023), Annexure R-6 to the State's affidavit in NGT OA 171/2023 (EZ), 28.02.2026.
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Gangtok (42299) and Tadong (22209). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Press and secondary reports of the floods and landslides of October 1968, June 1997, September 2011, 2017 (Dikchu), October 2023 (the cause and the toll), June 2024 (Mangan), May–June 2025 (Chaten) and July 2025 (NH-10), and of the NDSA committee of 2024 (ThePrint, 01.10.2024) (secondary sources).
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). APWA 5600 Manual Factsheet; APWA Stormwater Standards Supplement (7 Nov 2025). https://www.marc.org/document/apwa-stormwater-standards-supplement
- Mid-America Regional Council. The Evolution of Regional Stormwater Design Standards (presentation). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600, §5601.6 Waivers.
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed.
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management.
- Centre for Science and Environment (2023). Urban Stormwater Management (presentation).
- Asian Development Bank. Sikkim Integrated Urban Development Project (57230-001): Resettlement and Indigenous Peoples due-diligence report, Soreng sewerage (draft, December 2024, prepared by UDD). https://www.adb.org/sites/default/files/project-documents/57230/57230-001-sddr-en.pdf
- Gangtok City Development Plan (2006), as cited by CAG (Report No. 3 of 2016, para 2.3.9.2).
- Urban Development Department. Request for Proposal for a GIS-based Master Plan for the Namchi Planning Area (as listed on the Department's page); Sikkim Strategic Plan (2008) ("Long-Term Strategies: 2040"; as reported, not read [TBC]).
- Gangtok Smart City Development Ltd. Tenders for "Construction of drainage and jhora training works" (as reported; documents not read [TBC]).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 1A | List of Tier A authorities, with the boundary of the Gangtok Municipal Corporation and, once a development plan is published under the Sikkim Town and Country Planning Act, 2024 (not yet commenced), the boundary of its planning area |
| 1B | Maps of flood-sensitive catchments |
| 1C | Policy Supplement: text of alternatives S-1 to S-5 and model council resolution |
| 1D | Model SBCR 1991 amendment and model ULB bye-law |
| Form 1-1 | Applicability Determination |
| Form 1-2 | Variance / Waiver Request |
Commentary. Sikkim's floods come from three sources, often together, and its worst was not a rainfall flood. The first is the slide and debris of the ridge towns, where rain on thin soils over phyllite, schist and colluvium moves the slopes and the jhoras carry the debris down. In June 1997 landslides in Gangtok were reported to have killed 38 people (a single source, as reported; no official account found [TBC]), in a month in which Gangtok received 1,281.3 mm, its highest monthly total on record, with 223.8 mm on 9 June (IMD, Extremes). On 12–13 June 2024 rain and landslides in Mangan district killed 6 people in the first reports and 9 in a later one, stranded 1,200–2,000 tourists at Lachung and brought down the Sangkalang bridge, after about 250 mm had fallen over the State in 1–13 June, "54% above the normal 162 mm" (as reported; the tolls conflict, and no SSDMA toll or IMD station rainfall was found [TBC]); and at about 19:00 on 1 June 2025 a landslide struck the army camp at Chaten, near Lachen, after three days of rain in north Sikkim, with 3 dead and 6 missing (as reported). The 18 September 2011 earthquake (Mw 6.9) was reported to have killed 92 people by 23 September and between 97 and 116 in later totals (as reported; conflict); the landslides it set off were not researched for this Manual [TBC]. The second is the river flood of the valley floors. On 2–5 October 1968 four days of rain over the Darjeeling and Sikkim hills set off hundreds of landslides, washed away the Anderson Bridge at Teesta Bazar on 4 October and killed about 1,000 people in the region; a figure of "1,000 mm of rainfall in 52 hours" was attributed to a scientist in the press (all as reported; no Sikkim toll and no official account found), while IMD recorded 419.2 mm at Kalimpong on 5 October (IMD). In 2017 a release from the Dikchu hydropower project without warning was reported, and the High Court of Sikkim closed the public-interest litigation that followed with the direction "that the hydropower projects in Sikkim shall ensure strict compliance of the safety guidelines" (WP(PIL) 4/2017, judgment of 01.03.2021). In July 2025 the Teesta submerged NH-10 (as reported). The third is the glacial-lake outburst flood (GLOF). On the night of 3–4 October 2023 the South Lhonak lake drained into the Teesta after a moraine collapse at 22:12 IST, and the flood destroyed the 60 m dam of Teesta-III at Chungthang, damaged about 25,900 buildings and 31 major bridges and buried parts of Rangpo, about 135 km downstream, under debris (Sattar et al., 2025); the river bed "has risen by an average of 7-8 meters" (Lhonak valley PPR, annexed to the State's affidavit before the NGT, 28.02.2026). Its cause is disputed: the State's affidavit of 05.04.2024 attributed the flood "primarily to a cloudburst", a committee constituted by NDSA reported in June 2024 that "all scientific data and satellite images from that period points to GLOF and not a cloudburst" (as reported), and Sattar et al. (2025) found a moraine collapse with modest rain over the lake; this Manual takes no side and calls it the South Lhonak lake outburst and Teesta flood of 3–4 October 2023. Its toll is stated in two ways: 55 dead, 74 missing and over 7,025 displaced (SSDMA multi-stakeholder survey, as cited by Sattar et al., 2025), and 79 dead, 44 missing, 26 grievously injured, 5,665 evacuated and 7,025 in 30 relief camps, with 2,004 houses damaged and damage and loss of ₹1,480.07 crore (PDNA summary, SSDMA with NDMA, annexed to the State's affidavit before the NGT, 28.02.2026); press figures differ again (as reported). The PPR also lists an outburst of the Sangmya Meghu lake in August 2024. In September 2026 the High Court took up a suo motu public-interest litigation, In re Climate Justice in State of Sikkim (WP(PIL) 11/2026), in which the State is reported to have been asked to examine "land-use regulation, spatial planning, slope management, and drainage in ecologically and geologically fragile areas", and a later order urged early-warning systems for the 40 high-risk glacial lakes (as reported; the orders were not read [TBC]). No town in the State has a drainage design standard, and the 1991 regulations that govern building have no design storm, so this Manual sets the design rainfall for drains and screens the GLOF corridors and the Teesta valley floor apart, by siting rather than by drain size (Clause 2.3.6(i)).
In Sikkim neither the SBCR 1991 nor any other rule found requires rainwater harvesting of a private building: the regulations ask only that at least a quarter of each roof be sloped "with rain water gutter" (reg. 6), and the only statutory rainwater harvesting is in buildings owned or occupied by the State Government, its statutory bodies and the companies and institutions it owns or controls (Sikkim Municipalities Act, 2007, s.186).
No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Sikkim Building Construction Regulations, 1991 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.