Draft v1.0 prepared by NEER. Not adopted by the Government of Sikkim or any authority or local body, and has no legal force. About this draft

Chapter 4Site Runoff Control: Retention and Detention


4.1 Purpose and scope

4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:

  • (a) the order in which runoff-control measures are to be applied (Clause 4.3);
  • (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
  • (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
  • (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
  • (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
  • (f) regional detention and fee-in-lieu (Clause 4.13);
  • (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
  • (h) public safety (Clause 4.15).

4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of section 186 of the Sikkim Municipalities Act, 2007 (a rainwater harvesting structure in every building owned or occupied by the State Government, a statutory body or a company or institution owned or controlled by the State Government, "in such manner as may be specified by the State Government or the Municipality from time to time"; no such manner has been specified as far as found, no rule requires rainwater harvesting in a private building, and the Commentary to Clause 4.11 discusses both) continues to apply to every building it covers, whether or not this chapter applies.

4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.

Commentary. No Indian national rule or Sikkim rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". No Sikkim document found sets a design storm, a return period, a runoff coefficient or a time of concentration for any drain. The building rules are the Sikkim Building Construction Regulations, 1991 (SBCR 1991; Urban Development and Housing Department (UD&HD) Notification No. 29(202)UD&HD/90/295 of 19 March 1991, made under section 7(2) of the Sikkim Allotment of House Sites and Construction of Building (Regulation and Control) Act, 1985), as amended by the Sikkim Building Construction (Amendment) Regulations, 2000 and 2001 (No. GOS/UD&HD/6(294)2001 of 16 October 2001). They "extend to all the notified areas in Sikkim" (reg. 1(2)); applications go to the Secretary of the department, now the Urban Development Department (UDD) (reg. 4), and inside Gangtok building-plan approval passed to the Town Planning Cell of the Gangtok Municipal Corporation (GMC) in 2017, still under the 1991 Regulations (GMC's counter-affidavit before the National Green Tribunal (NGT) in OA 5/2022 (EZ); the transfer notification was not seen [TBC]). Rural land outside the notified areas has no building permission under them (NEER reading; the list of notified areas was not found [TBC]). A Sikkim Building Construction (Amendment) Regulation, 2022 was reportedly published on 12 April 2023 (as reported); it was not read, and it may change what follows [TBC]. The drainage provisions that can be found protect the building, the road and the drain line, not the catchment. The site plan shows the "position of sewer line, water main pipe line, electricity line" (reg. 5(f)), and the blue-print plan the "drainage including connection to main outlet and the slopes of the roof" and the "sanitary/plumbing layout … drainage system … sewerage disposal system/septic tank and soak pit" (reg. 6); at least 25 per cent of the roof is "sloped gabled of traditional roofing … with rain water gutter" (reg. 6); gutters and down pipes are "of such design and capacity that the water will neither spill out of them nor leak through them", connected "to the storm water plinth protection drain of the building" (reg. 21); a "Pucca storm water/plinth protection drain shall be provided leading to the road side drain or to adjoining permanent drains or jhora to drain off the surface water" (reg. 25(iv)), the jhora (झोरा) being a natural watercourse or ravine stream; "No occupation certificate shall be issued … if the drain has not been provided to main outlet/jhora or if the septic tank/soak pit has not been properly built/connected/ventilated" (reg. 13(iii)); dumping of spoil on "Public Street, road, drains, gullies and jhoras" is prohibited, with a fine of ₹500 at least (reg. 22), and a security of ₹5,000 is held against spoil and damage to the road "including drainage system" (Form III, cl. 15); and no allotment is made "in any sinking area, landslide prone or in areas having scars of old landslides or in slope exceeding or around 70 (Seventy) degree" (reg. 35). Setbacks are measured from the road (27 feet from the centre of the road, and 10 feet "or as indicated in approved Master Plan of the area", reg. 18); there is no setback from a jhora or a khola (खोला; a river or large stream). None of these sets a design storm, a release rate, a detention volume or an overflow path. Height is set by the stability zones of the Mines and Geology Department (reg. 17(i), as substituted in 2001), whose parameters of 2021 grade each zone partly by the state of its jhoras, from zone 1, where the "Training of jhoras/drains have been completed and done properly (with safe distance)", to zone 4, with an "Untrained jhora/ erosional potential jhora", and make "Proper channelization of surface runoff by providing catchment drains especially during the rainy seasons and connect it to natural waterways/Jhora" a condition for reviewing a site's zone (Notification No. 17/DMG/20-21, 19 March 2021). Regulations 6, 13(iii), 21 and 25(iv) and the 2021 condition on catchment drains are the only hooks for this chapter; reg. 39 (2001) lets the Government relax any provision, and the State relaxed the height of a car park of Gangtok Smart City Development Ltd (GSCDL) "subject to confirmation of a Geotechnical investigation and Report" (GMC's counter-affidavit), which shows how a technical condition can be attached. The Sikkim Municipalities Act, 2007 treats a jhora as a drain ("a jhora or water-course of natural drainage line", s.2(24)) and as "any natural watercourse, whether on a public land or on a private land" (s.163(b)); a jhora on public land other than forest land within a municipal area vests in the Municipality (s.172(1)), and "the Municipality shall protect any jhora, whether on a public land or on a private land, within the municipal area" (s.172(2)); the State may "specify the limits of any jhora, watercourse or channel within a municipal area" by notification (s.173), and none has been found; the Municipality shall "provide a safe and sufficient outfall … in such manner as may not cause any nuisance, either by flooding any part of the municipal area or any area surrounding the outfall" (s.187); and rain water shall go in "an entirely separate drain" and "be connected with the natural nullahs, khola-kholsas, jhoras, or storm water drainage" (s.193). Chapter XXXII of the Act sets up a building-permit system ("No person shall undertake any building activity without obtaining" a permit, s.271) with rules that may cover "infrastructure in relation to building activity" (s.287), but no such rules were found, and whether GMC applies that system or the 1991 Regulations is not clear (NEER reading). The Sikkim Town and Country Planning Act, 2024 (Act 10 of 2024), enacted in 2024 and amended in 2025, not yet commenced, would require development plans with "proposals for water supply, drainage, sewage and solid waste disposal" and "proposals for flood control, land stability and sloped linked controls"; no commencement notification, Board or plan under it was found. The State's annual notices that ban "construction involving earth excavation" in the monsoon (6 May–30 September 2019; 1 June–30 September 2020) are the hook for construction-phase sediment control (Chapter 8). No published highest flood level exists for any Sikkim town [TBC], and the 1991 Regulations have no flood plinth; this Manual supplies the method (surveyed flood marks, the surveyed mark of the flood of October 2023 or the modelled 1% AEP level, Chapter 5).

No design basis is in use. GSCDL has tendered "Construction of drainage and jhora training works" in Gangtok, for about ₹13.41 crore (as reported); the Sikkim Integrated Urban Development Project of the Asian Development Bank (ADB), with UDD as executing agency, includes "Improving about 60 km roads in seven towns with junction improvements, improved pavement and stormwater drains" and infrastructure master plans for four towns other than Gangtok (ADB, due-diligence report of December 2024); and the drainage and landslip works of the Gangtok City Development Plan of 2006 "were not taken up" (CAG, Report No. 3 of 2016, para 2.3.9.2). No return period, rainfall source or runoff coefficient was seen for any of them. These works convey water; this Manual adds storage first. It requires on-site detention under this chapter, and keeps pokharis (पोखरी; pond, lake or tank), wetlands and flat benches as storage first (Chapters 4, 7 and 11), for three reasons: (i) every litre sent faster down a jhora arrives sooner, with more energy and more debris, on a slope that the 2021 stability zones already treat as unstable where a jhora is "untrained" or "erosional"; (ii) the jhoras end in a Teesta whose bed rose "by an average of 7-8 meters" in October 2023 (State Government's pre-project report on GLOF risk mitigation in the Lhonak valley, 2026), and whose valley-floor towns, Singtam, Rangpo and Melli, receive everything the ridge towns send; and (iii) section 187 of the Municipalities Act already makes the flooding of "any area surrounding the outfall" a matter of municipal duty. Where a project's own terms govern a design, the designer states on the submittal which governs; the Manual does not override a contract.

Basements are not regulated for flooding: no basement rule that addresses flooding was found in the SBCR 1991 read for this Manual [TBC]. This Manual therefore adds its own requirements for every basement: no detention storage in a habitable basement (Clause 4.10.1); the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4); and no basement in Zone 2 (Clause 7.5.2). In the flood-sensitive catchments of Clause 4.5.3.2, in any catchment notified under Clause 4.5.4, and on the valley-floor land of Clause 4.12.1, it recommends that no basement be permitted where the 1% AEP flood level, or on the Teesta valley floor the surveyed mark of the flood of October 2023, stands above the surrounding ground; where one is permitted on the valley floor it is watertight and checked for flotation with the design groundwater level at ground level (Clause 4.12.3); and wherever a basement or lower floor is cut into a slope, it shall carry the geotechnical certificate of the hill rule of Clause 4.11, with the water behind its walls drained to a lined drain and not to the ground (all set by this Manual). For a sloping site, this chapter also supplies what regulations 21 and 25(iv) leave open: runoff from the catchment above the site shall be intercepted and carried round the building in the design storms of Chapter 6, and every flow from the site shall discharge to a lined drain, the road drain or a trained jhora through an energy dissipator, never onto an unprotected slope or into fill (Clause 6.3.6(l)). These are the Manual's proposals, not rules of the SBCR 1991. This chapter is written so that it can supply, as a technical companion to the SBCR 1991, the stability-zone conditions of 2021, the Municipalities Act and, once the 2024 Act commences, its development plans, the design storm, release rates and storage volumes that they leave open; a competent authority could adopt it for that purpose, but none has. In practice the storm drains of most towns carry sewage effluent: every building treats its sewage "in septic tanks built within the site" unless a public sewer is available (reg. 25(i)–(ii)); Gangtok's sewage treatment plants treated 15.22 MLD in September 2025 against an estimated urban sewage generation of 29.51 MLD in the State (State Government's affidavit of 19 December 2025 in NGT (PB) OA 673/2018); in Soreng "most of the houses have adopted the practice of onsite disposal by constructing septic tank/soak pits with effluent discharging into open surface drains" (ADB, due-diligence report of December 2024); and the NGT recorded in its order of 4 July 2024 that "treated sewage is entering in to river/ rivulets/ jhoras and this is not permissible under the Water Act", to which the State replied that "No sewage is disposed off in the rivers or fast flowing water bodies" (both as quoted in the State's report in NGT (PB) OA 606/2018) (Clause 8.9). Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sullage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.


4.2 Definitions

Term Meaning in this Manual
Retention Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall.
Retention depth The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E).
Required retention volume (RRV) The runoff volume from the retention depth over the post-development site (Clause 4.4.2).
Detention Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5.
Retention credit The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume.
Permissible site discharge (PSD) The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha.
Site storage requirement (SSR) The detention storage required per hectare of site under the simplified method of Clause 4.14.
Multi-stage outlet An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2).
Drawdown time Time from the peak stored volume until the stated fraction of that volume has been released.
Emergency spillway A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment.
Freeboard Vertical distance between the maximum design water level and the embankment crest or other critical level.
Flood-sensitive catchment A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4.
Authority The approving authority under Chapter 1 (the competent authority for the area: in Gangtok, the Gangtok Municipal Corporation (GMC), which has approved building plans under the SBCR 1991 since 2017 and owns and protects its drains and jhoras under sections 172 and 187 of the Sikkim Municipalities Act, 2007; in another notified area, the Urban Development Department (UDD) or the urban local body that approves plans there (how approval is split between UDD and the urban local bodies outside Gangtok was not found [TBC]); for a scheduled river's bank under the Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988, the Forest Department; for a public work, the department or agency that executes it (the Roads and Bridges Department / PWD, NHIDCL, BRO, WRD, PHED, RMDD, UDD or GSCDL); and on land outside every notified and municipal area, where the SBCR 1991 give no building permission, none, so that there this Manual is guidance, except for public works and for any body that adopts it, as applicable).
Tier A / Tier B Adoption tiers defined in Chapter 1. Tier A: the Gangtok Municipal Corporation (GMC), for its whole area, and, once a development plan under the Sikkim Town and Country Planning Act, 2024 (enacted in 2024 and amended in 2025, not yet commenced) is published for a planning area, every approving authority within that planning area, whichever has jurisdiction over a site (no such plan has been published). Tier B: Municipal Councils, Nagar Panchayats and other approving authorities under the regulations.

4.3 Order of measures

4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:

  1. Preserve. Keep existing waterbodies, pokharis, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
  2. Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
  3. Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
  4. Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).

4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.

Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.


4.4 Retention

4.4.1 Requirement

The site shall retain the RRV. Retention shall be achieved by one or more of the following:

  • infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
  • rainwater reuse that is drawn down by a demonstrated non-potable demand;
  • green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.

The limits of Clause 4.4.4 apply.

4.4.2 Computation of the RRV

RRV (m³) = 10 × Q_R × A

where:

  • Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
  • A (ha) is the area of the site that drains to the outfall.

Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.

The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.

Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.

4.4.3 Verification

Retention by infiltration shall be supported by:

  • (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
  • (b) a design infiltration rate of no more than half of the measured rate; and
  • (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).

Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.

Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.

4.4.4 Limits on retention

4.4.4.1 Infiltration practices shall not be used:

  • where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
  • on contaminated land;
  • within the setbacks from foundations, wells and septic systems set in Chapter 8; or
  • on fill, unless tested after placement.

4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.

4.4.5 Drawdown of retention

Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.

4.4.6 Retention credit: definition and computation

4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.

4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:

  • (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
  • (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
  • (c) once it is full, route its overflow to the detention facility; and
  • (d) size the detention for the residual hydrograph.

The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.

4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:

V_credit = C_R × RRV_provided

where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.

4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.

Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Sikkim, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.

The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).

This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).

4.4.7 Preservation credit

Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:

  • they are protected by a registered covenant or dedication; and
  • their runoff is not concentrated onto impervious surfaces.

This lowers both the RRV and the detention required. No other preservation credit applies.


4.5 Release-rate criteria

4.5.1 General

4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.

4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.

4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.

4.5.2 Standard catchments

For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:

Q_post(T, d) ≤ 0.9 × Q_pre(T, d)

4.5.3 Flood-sensitive catchments

4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:

Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).

Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).

4.5.3.2 The flood-sensitive catchments are:

  • (a) Gangtok's jhoras to the Rani Khola and the Roro Chu: the catchments of the jhoras of Gangtok, with Tadong and Ranipool, that drain to the Rani Khola and the Roro Chu, including the named jhoras of the city's waterbody network (as reported) and the slide-prone wards above them [TBC];
  • (b) The Teesta valley floor in the October 2023 corridor: the land of Chungthang, Dikchu, Singtam, Rangpo and Melli, with Toong Naga, that drains to the Teesta at or below the level of the flood of October 2023 and of the river bed it raised, and every jhora and side stream that falls to that land;
  • (c) The Rangit at Jorethang and Majitar: the land of Jorethang (Nayabazar-Jorethang) and Majitar that drains to the Rangit;
  • (d) The Rongni Chu at Ranipool and Singtam: the land of Ranipool and Singtam that drains to the Rongni Chu, above its confluence with the Teesta;
  • (e) Mangan town and the slopes of the North Sikkim road: the land of Mangan town and the catchments of the jhoras that cross the North Sikkim road in Mangan district, where the rain and landslides of June 2024 struck;
  • (f) Lachen and Chaten, and every catchment below a high-risk glacial lake: the land of Lachen and of Chaten, where the landslide of 1 June 2025 struck, and every catchment that drains from a glacial lake listed as high-risk or very high-risk, down to its confluence with the Teesta;
  • (g) The hydropower reservoirs and release reaches: the land that drains to the reservoirs of Teesta-III (once restored), Teesta-V, Teesta-VI, the Teesta Low Dam III and IV projects, Chuzachen, Dikchu, Jorethang, Tashiding, Rongnichu and Rangit-III, below or near their starting levels of Clause 3.12.5, and the land along the reaches below their dams;
  • (h) The NH-10 corridor along the Teesta: the land that drains to NH-10 and its drains where the highway runs along the Teesta;
  • (i) Namchi: the land of the Namchi Municipal Council area and of its jhoras;
  • (j) Soreng: the land of the Soreng Nagar Panchayat area and of its jhoras; and
  • (k) any catchment notified under Clause 4.5.4.

The boundaries shall be those mapped in Annex 4A.

4.5.4 Notification of further flood-sensitive catchments

4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:

  • (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
  • (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
  • (c) an outfall that is held up by the Teesta, the Rangit or the Rongni Chu in flood, such as the outfalls of Singtam, Rangpo, Melli, Majitar and Jorethang, where the flood of October 2023 raised the river bed by metres, or by a hydropower reservoir held near its full level or a release from a dam upstream, or that is buried or blocked by the boulders, slide debris and garbage of a jhora, for part of the monsoon season (Chapter 5);
  • (d) loss of more than a quarter of the mapped tank and pokhari storage in the catchment since the earliest available survey; or
  • (e) a basin master plan that relies on limiting site discharge.

4.5.4.2 The procedure shall be:

  1. The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
  2. The State-level technical committee constituted under Chapter 1 reviews the note.
  3. The draft notification and map are published for public comment for at least 60 days.
  4. The Government notifies the catchment and the map is added to Annex 4A.
  5. The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.

4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.

Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The Gangtok entry follows the city's jhoras to its two receiving streams, the Rani Khola and the Roro Chu: Gangtok's 24-hour record is 310.3 mm (30 May 1975), its wettest month on record is June 1997 (1,281.3 mm, with 223.8 mm on 9 June), and in that month landslides were reported to have killed 38 people in the city (as reported, from a single source; no official account was found [TBC]) (IMD Extremes); the city's waterbody network lists named jhoras, such as the Goshkhan and Hospital jhoras (ICLEI, as reported); GMC has its waste agency clear the jhoras and bars dumping "along Footpath, Roadside and Jhoras" (Memo No. GMC/6727/III/2024/OL/01, 8 October 2024); and the Zone III sewerage of Gangtok is described as "Pollution abatement of Rani chu through Ro-Ro Chu" (State Government's report of September 2025 to the NGT). Which wards stand on slide-prone ground was not found [TBC]. The Teesta valley-floor entry follows the corridor of 3–4 October 2023, when the South Lhonak glacial lake drained into the Teesta after a moraine collapse: at Chungthang "discharge peaked at 5340 m³ s⁻¹ … within ~6 minutes", with a depth of 9 m and a velocity of 9 m/s, the 60 m high Teesta-III dam was destroyed, and Rangpo, about 135 km downstream, was "severely impacted by the debris, burying buildings and automobiles" (Sattar et al., 2025). The cause is disputed: the State's affidavit of 5 April 2024 before the NGT attributed the flood "primarily to a cloudburst", while a committee constituted by the National Dam Safety Authority found a lake outburst (as reported) and Sattar et al. found 29–39 mm of rain over the lake from 28 September to 5 October in the ERA5 reanalysis, and no cloudburst near the lake; this Manual takes no side. The toll is also stated two ways: 55 dead and 74 missing (SSDMA's multi-stakeholder survey, as cited by Sattar et al.), and 79 dead and 44 missing (the post-disaster needs assessment of SSDMA with the National Disaster Management Authority (NDMA), annexed to the State's affidavit of 28 February 2026). The river bed rose "by an average of 7-8 meters", NH-10 "has become prone to submergence and subsidence", and at Toong Naga 155 households "have been mandated for relocation" (State Government's pre-project report, 2026). The Rangit entry follows its valley floor: the CWC site at Majitar has a highest level of 279.29 m (17 October 1985; as reported), and the land chosen for the Jorethang sewage works was "fully flooded during monsoon" (CAG, Report No. 3 of 2016). The Rongni Chu entry follows the river through Ranipool, where the CWC site has no published highest level, to Singtam, where it has a danger level of 355.09 m and a highest level of 356.09 m (as reported), and where the flood of October 2023 damaged the sewage treatment plant (State Government's compliance report to the NGT). The Mangan entry follows the rain and landslides of 12–13 June 2024 in Mangan district, in which 6 people were reported killed in the first reports and 9 in a later one (as reported; the figures conflict), between 1,200 and 2,000 tourists were stranded at Lachung and the Sangkalang bridge collapsed, after about 250 mm of rain across the State in 1–13 June, "54% above the normal 162 mm" (as reported); no station rainfall for Mangan was found [TBC]. The Lachen entry follows the landslide of about 19:00 on 1 June 2025 at the army camp at Chaten near Lachen, in which 3 people were killed and 6 were missing and after which 1,678 tourists were evacuated from Lachung and Chungthang (as reported), and the glacial lakes above: NDMA "has identified 40 high-risk glacial lakes in Sikkim, out of which 16 are classified as very high risk" (13 in Mangan district and 3 in Gyalshing district; 12 in the Lachen Chu watershed), and "Shako Chho has habitations and Army establishments just 15 km downstream" (State Government's affidavit of 28 February 2026). These catchments are screened under Clause 2.3.6(i); no drain is sized for a lake outburst. The reservoir entry follows the hydropower reaches: Teesta-III was destroyed in 2023, the High Court of Sikkim closed WP(PIL) 4/2017, which followed a release from the Dikchu project in 2017 without warning (as reported), with the direction "that the hydropower projects in Sikkim shall ensure strict compliance of the safety guidelines" and that the authorities "undertake periodic inspection and review" (judgment of 1 March 2021), and a committee constituted by the National Dam Safety Authority reported an inflow of about 10,000 m³/s at Teesta-III against a spillway capacity of 7,500 m³/s (as reported); no full or maximum level or release rule was found for any reservoir [TBC]. The NH-10 entry follows the highway along the Teesta, which was submerged by the river in July 2025 (as reported) and whose drainage, damaged by the railway works, the High Court warned IRCON to correct in June 2025 (as reported). The Namchi entry follows a ridge town on the southern slopes, where the 2(a) plates read higher than at Gangtok (Clause 2.3.6(c)(i)) and whose sewerage "has remained stalled since the year 2013" (State Government's affidavit of 19 December 2025), so that its drains carry septic effluent to its jhoras. The Soreng entry follows the town where "most of the houses" discharge septic effluent "into open surface drains", and "untreated wastewater into the open storm water drains ultimately discharging into the farmland / water bodies" (ADB, due-diligence report of December 2024); its plate value was not read [TBC]. Pakyong, Gyalshing (Geyzing), Ravangla and Pelling are candidates for notification under Clause 4.5.4, and a notification of jhora limits under section 173 of the Municipalities Act, or the flood-control proposals of a development plan once the 2024 Act commences, would be evidence for it. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.

4.5.5 Minimum outlet and short-duration 2-yr checks

4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.

4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:

  • size the low-flow orifice as the smallest opening that meets Clause 4.7; and
  • report the resulting 2-yr exceedance for those durations.

The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.

Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).

4.5.6 Constrained redevelopment sites

4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:

  • (a) the existing site is at least 60% impervious, as surveyed before demolition;
  • (b) the site is 1 ha or less; and
  • (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.

New development on undeveloped land is never eligible.

4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:

  • (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
  • (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
  • (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).

4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:

  • (a) paid into the ring-fenced account of the basin in which the site lies;
  • (b) spent only on regional detention or on restoring pokhari or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
  • (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.

Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with WRD agreement.

4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.

Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as central Gangtok round MG Marg (as reported), or the town centres of Namchi, Jorethang and Rangpo [TBC], there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.


4.6 Detention sizing procedure

4.6.1 Method

Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.

4.6.2 Steps

  1. Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
  2. Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
  3. Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
  4. Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 1 May to 30 September in every sub-area, from 1 April to 31 October on valley-floor land below the 1% AEP flood level, on the 2023 aggradation zone, where the seasonal high water table is within 2 m and in stability zones 3 to 6, at all times in catchments draining to a hydropower reservoir, its backwater, a release reach below a dam or a river reach above its CWC warning level, and at other sites and times after a 5-day total of more than 53 mm, AMC II otherwise).
  5. Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
  6. Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
  7. Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
  8. Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
  9. Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
  10. Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
  11. Size the emergency spillway and set freeboard (Clause 4.9).
  12. Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).

4.6.3 Storms to be routed

Every facility shall be routed for the full matrix:

Table 4.1 — Design storms to be routed for detention sizing

AEP Durations (h) AMC
50% (2-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h
10% (10-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h
1% (100-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h

The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.

4.6.4 Initial conditions

Each run shall start with:

  • detention storage empty, down to the invert of the lowest outlet;
  • any permanent pool full;
  • retention practices empty, except as limited by Clause 4.11; and
  • RWH storage full (Clause 4.11).

The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.

4.6.5 Multi-stage outlet design

4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:

  • Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
  • Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
  • Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
  • Emergency spillway: separate from the primary outlet (Clause 4.9).

Stages may be combined where routing shows that every cap is met.

4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).

4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.

4.6.6 Tailwater on the outlet

The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:

  • for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
  • for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).

Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.

4.6.7 Illustrative example

Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a hillside colony in Gangtok draining to a jhora. They are not NIH-DHAARA values and must not be used for design.

Inputs:

  • Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
  • Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
  • Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
  • 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
  • Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
  • Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
  • Storage: vertical-walled, 2,500 m² plan area.
  • Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
    • Stage 1: 170 mm orifice at the invert.
    • Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
    • Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.

Results (discharges in L/s; storage in m³):

Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)

Duration (h) 2-yr pre 2-yr post, detained 10-yr pre 10-yr post, detained 100-yr post, uncontrolled 100-yr post, detained 100-yr storage used 10-yr drawdown, 50% blocked (h)
1 4 15 51 28 922 42 1,426 31.3
2 14 20 84 34 961 79 1,911 32.1
3 19 22 104 37 981 139 1,999 32.8
6 32 25 150 41 1,010 194 2,154 34.2
12 127 30 302 46 1,074 276 2,512 39.0
24 149 32 327 49 1,081 320 2,766 45.3
48 173 34 349 82 1,087 343 2,913 44.8
72 180 34 356 84 1,089 343 2,911 44.7

How to read it:

  • 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
  • 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
  • Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
  • Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
  • Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.

The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.

2026-11-01T10:14:56.974241 image/svg+xml Matplotlib v3.9.4, https://matplotlib.org/ 0 5 10 15 20 25 30 35 40 Time from start of 24 h design storm (h) 0 200 400 600 800 1000 1200 Discharge (L/s) Release cap = max pre-development 10-yr peak over all durations (356 L/s) Uncontrolled peak 1081 L/s Detained: peak later and flatter, recession prolonged (volume unchanged) Illustrative — not design values. 2 ha site, 24 h storm, AMC III, mixed-frequency rule Post-development 1% AEP (100-yr), uncontrolled Post-development 1% AEP (100-yr), detained Pre-development 10% AEP (10-yr)

Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).

Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).


4.7 Drawdown

4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.

4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).

4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).

4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.

Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Sikkim storage must hold multi-day volumes. It is still short enough that a basin filled by one monsoon depression will have most of its volume back before the next, which in June 1997, when Gangtok's 223.8 mm of 9 June fell in a month of 1,281.3 mm, its wettest on record (IMD Extremes), and June 2024, when about 250 mm fell across the State in 1–13 June before and during the rain of 12–13 June in Mangan district (as reported) followed within days.


4.8 Outlet structures

4.8.1 General. Primary outlets shall be:

  • unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
  • accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
  • built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).

4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.

4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:

  • have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
  • have a clear open area at least 10 times the area of the opening it protects;
  • be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
  • be removable or hinged for cleaning; and
  • for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.

4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).

4.8.5 Outlet barrels. Outlet barrels through embankments shall:

  • be at least 300 mm in diameter (Chapter 6);
  • have watertight joints;
  • have a filter diaphragm or seepage collars over the length within the embankment; and
  • have an energy-dissipating outfall (Chapter 9).

4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.

Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.

Figure 4.2 — Detention storage stack and multi-stage outlet (schematic) Schematic cross-section of a detention basin showing stacked storage zones (permanent pool, water quality volume, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and a multi-stage riser outlet with trash rack, anti-vortex plate, outlet barrel and emergency spillway. Not to scale. Storage stack and multi-stage outlet — schematic section, not to scale Embankment crest Max level, spillway flowing (outlet blocked) Emergency spillway crest 1% AEP (100-yr) max water level 10% AEP (10-yr) max water level 50% AEP (2-yr) max water level Top of water quality volume (WQv) Permanent pool (wet basin only) Basin floor / pool bottom Spillway surcharge (Clause 4.9) 100-yr detention zone 10-yr detention zone 2-yr / channel-protection zone WQv — 24–48 h release (Ch 8) Permanent pool / retention Freeboard ≥ 0.3 m Spillway crest (offset in plan) 1 2 3 4 5 6 7 Key 1 Stage 1 low-flow orifice (≥ 50 mm, Clause 4.8.2) — releases WQv over 24–48 h 2 Stage 1 second orifice — with 1, controls 50% AEP (2-yr) release 3 Stage 2 orifice or weir slot — controls 10% AEP (10-yr) release 4 Stage 3 riser crest / overflow grate with anti-vortex plate — controls 1% AEP (100-yr) release 5 Trash rack enclosing all openings (Clause 4.8.3) 6 Seepage collar or filter diaphragm on outlet barrel 7 Outlet barrel, energy dissipation and outfall apron Levels and zone thicknesses are diagrammatic only.

Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).


4.9 Emergency spillway, freeboard and embankment safety

4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:

  • with the primary outlet assumed fully blocked;
  • with the facility full to the spillway crest at the start of the storm; and
  • with at least 0.3 m freeboard from the maximum water level to the embankment crest.

4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:

  • endanger life;
  • flood a habitable building or critical facility; or
  • close an arterial road.

High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.

4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.

4.9.4 Spillway location. The spillway shall be:

  • on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
  • discharging to the 1% AEP overland flow path of Chapter 6; and
  • placed so that its flow does not reach a building.

4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.

4.9.6 Embankments.

  • (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
  • (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
  • (c) Embankments shall have:
    • a crest width of at least 3 m;
    • compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
    • no trees or large shrubs.
  • (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.

4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.

Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.


4.10 Facility types

4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.

4.10.2 Underground tanks and vaults.

  • (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
  • (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
  • (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
  • (d) The tank shall be ventilated.
  • (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
  • (f) Flotation and groundwater ingress shall be checked under Clause 4.12.

4.10.3 Rooftop detention.

  • (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
  • (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
  • (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.

4.10.4 Podium and landscape-deck detention.

  • (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
  • (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.

4.10.5 Parking-lot detention.

  • (a) It is permitted only on surface parking. Ponding depth shall not exceed:
    • 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
    • zero on accessible routes, ramps and pedestrian crossings; and
    • zero in the 10% AEP storm on fire-tender access routes.
  • (b) Signs shall warn that the area floods.
  • (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).

4.10.6 Multi-use detention (parks, playfields, open space reservation).

  • (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
  • (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
  • (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
  • (d) The depth and slope limits of Clause 4.15 apply.
  • (e) Play equipment and seating shall be placed above the 10% AEP level.

4.10.7 Ponds and wet basins.

  • (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
  • (b) Only storage above the permanent pool counts as detention.

Commentary.

  • The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
  • The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
  • Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
  • Using open space for multi-use detention fits what the SBCR 1991 already ask of a site, a front setback of 10 feet "or as indicated in approved Master Plan of the area" and an open area of 5 feet (reg. 18), but the regulations set no share of the plot as soft cover or permeable ground (NEER reading). On the tested river-terrace gravels of sub-area SK-A above the 1% AEP flood level and outside the ground raised in October 2023, on flat ground, a detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires, and can also infiltrate under Clause 4.11 (recharge rule). Everywhere else the position is different. Ground on a natural slope of more than 10°, a terrace held up by a retaining wall, land within twice the height of a cut or wall downslope of it, colluvium, fill and slide debris, land in stability zones 3 to 6, and land that is sinking or landslide prone (reg. 35) are not to be used for ponding, because water held there soaks into the slope (Clause 4.11, hill rule); and valley-floor land below the 1% AEP flood level, the river bed and terraces raised in 2023 and land where the seasonal high water table is within 2 m are not to be used for unlined ponding, because there the river and the water table fill the storage first (Clause 4.11, valley-floor rule). On such sites, detention is provided in lined tanks, open or closed, with an orifice outlet and an overflow to a lined drain, on rooftops and podiums under 4.10.3 and 4.10.4, or on a level open space only where it stands on rock or on ground that the geotechnical certificate of the hill rule covers; an excavated pond or basin on a slope is not accepted, and any permeable paving there is laid on a lined or non-exfiltrating base with an underdrain. Four kinds of land are not open space for this purpose. A pokhari or a dhara (धारा; a spring or spring spout) on the land is preserved under step 1 of Clause 4.3.1; a pokhari is modelled as a water surface (Clause 3.3.2(e)) that starts at its spill level (Clause 3.12.5), so only its flood storage above that level can count, and only as Chapter 7 allows; and a natural or community pokhari is never turned into a detention pond. The bank of a scheduled river, which the Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 places under the Forest Department "as if it were a forest" (s.29(9)), and the Manual's corridor of Chapter 7 along every jhora and khola are flood land already: water reaches them first, so they are not counted as detention for the development beside them. And land kept open on purpose, such as a slip reserve notified for stabilisation under section 29(2) of the 1988 Act, the notified green belt of the 1985 Act (s.2(f)), or a spring-recharge area above a town's or village's intake (the spring rule of Clause 8.8.1), is not graded or paved for detention. The signs and depth markers of Clause 4.15.5, and the flood-warning signs of 4.10.5(b), are in Nepali and English; where the local body's own public notices also use another official language of the State, such as Bhutia, Lepcha or Limbu, the signs carry that language too, because a sign must be readable by the people it warns (set by this Manual).

4.11 Rainwater harvesting versus detention accounting

4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.

4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.

4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:

  • (a) the detention zone lies wholly above the RWH overflow level;
  • (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
  • (c) no pump, valve or user action can hold water in the detention zone; and
  • (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.

Only the volume between the RWH overflow level and the detention overflow level counts as detention.

4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the monsoon season.

4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of section 186 of the Sikkim Municipalities Act, 2007 and any manner of rainwater harvesting that the State Government or a Municipality specifies under it, any condition of a building permission, or any rainwater harvesting rule or direction of an approving authority (no rainwater harvesting rule for private buildings was found).

Commentary. Rainwater harvesting in Sikkim is required by one provision, which reaches only public buildings and does not size it. Section 186 of the Sikkim Municipalities Act, 2007 reads: "In every building owned or occupied by the State Government or a statutory body or a company or an institution owned or controlled by the State Government, rain water harvesting structure shall be provided in such manner as may be specified by the State Government or the Municipality from time to time." No such manner has been specified as far as found (NEER reading). A reply in the Rajya Sabha in 2019 lists Sikkim as "NA asked to take up rain water harvesting structure for Government buildings" (as quoted), and GSCDL has sought expressions of interest for a rainwater harvesting project in Gangtok (as reported). The SBCR 1991 require no rainwater harvesting: their only roof-water provisions are that at least 25 per cent of the roof is sloped "with rain water gutter" (reg. 6) and that gutters and down pipes carry the water to the plinth drain (reg. 21). A gutter is not storage. No rule requires rainwater harvesting in a private building (NEER reading). In Sikkim rainwater harvesting is storage and reuse, not recharge: "about 80%" of rural Sikkim is reported to depend on springs, and "half of the perennial springs have already dried up or have become seasonal" (as reported). This Manual therefore sets three infiltration rules and one sizing rule for credit (all set by this Manual), and credits rainwater storage as follows:

  • An RWH tank provided under section 186, or provided voluntarily, is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2), because in the monsoon season it is full after the first heavy rain. A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
  • RWH credit rule. Because section 186 sets no volume, and no rule sets one for a private building, RWH storage shall hold at least 25 L per m² of roof area (about 25 mm of rain over the roof) to earn credit under this Manual. The value is the North-East value of this series; the 20 L per m² of the mountain editions is the precedent, raised because Sikkim's towns and villages depend on springs that run low in the dry months. It counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing or washing, demonstrated under Clause 4.4.3; watering a garden is not a continuous use in the monsoon season. The tank is then modelled under Clause 4.4.6 like any other retention practice; it is assumed full at the start of every monsoon design storm and is never counted as detention. For a building that section 186 covers, the rule makes the section measurable; for a private building it is a condition of this Manual wherever the Manual applies, not a statutory duty. A larger tank is always allowed. On hill-rule ground, which is most of the State, storage and reuse is the way retention is provided, and the 25 L per m² is the first part of it.
  • Recharge pits, trenches, shafts and wells count as retention only where they meet Clause 4.11.4 and the recharge rule below: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume. The recharge rule's 2.0 m separation is stricter than Clause 4.11.4's 1.0 m, and both apply.
  • Hill rule. In sub-areas SK-B, SK-B1 and SK-C of Annex 2A, and on every natural slope of more than 10° in sub-area SK-A, no deliberate infiltration practice (soakaway, soak pit for storm water, recharge pit, shaft or well, infiltration trench, or permeable paving with an exfiltrating base) shall be built or credited: on natural ground sloping more than 10°; on colluvium, fill or slide debris, whatever its slope; in stability zones 3 to 6 of the Mines and Geology Department's Notification No. 17/DMG/20-21 of 19 March 2021; in any area that is sinking, landslide prone or has scars of old landslides (SBCR 1991, reg. 35); or upslope of a cut slope or retaining wall within twice the height of the cut or wall — unless a geotechnical certificate by a qualified geotechnical engineer or engineering geologist shows that the added water will not destabilise the slope; and in stability zones 4 to 6 not at all, whatever certificate is offered. On such sites roof runoff goes to rainwater storage under the credit rule above, with overflow by a lined, stepped drain through a silt trap and an energy dissipator to a trained jhora or the road drain, never onto an unprotected slope. The ground gives the reason. On steep terrain groundwater emerges "as seepages and springs wherever the land surface intersects local ground water body" (CGWB, as quoted); the 2021 notification records the ground of zone 3 as "Wet", of zone 4 as "Dripping" and of zones 5 and 6 as "Flowing", and judges zone 4 "Not suitable for habitation unless immediate protective measures"; and GSCDL told the NGT that "landslides are caused mainly due to loose soil by spring water generated at natural Jhora", and was advised to channel the groundwater it met through "multiple drains connecting to nearby Jhoras" (reply affidavit in NGT OA 38/2022). Water put into such a slope does not recharge an aquifer; it raises the pore pressure in the slope. The rainfall thresholds proposed for landslide warning in Sikkim, I = 43.26 D^−0.78 for the State and I = 100 D^−0.92 for Gangtok (I in mm/day, D in days; Landslides, 2019, as summarised), show how little rain over a few days the slopes can take; they are cited here as commentary only and are not used for design. The landslides of Gangtok in June 1997, in which 38 people were reported killed (as reported, single source), came in the wettest month of Gangtok's record (1,281.3 mm, IMD Extremes). The hooks are in the building rules and the zone notification: gutters and down pipes "of such design and capacity that the water will neither spill out of them nor leak through them" (reg. 21); a "Pucca storm water/plinth protection drain … leading to the road side drain or to adjoining permanent drains or jhora" (reg. 25(iv)); no occupation certificate "if the drain has not been provided to main outlet/jhora" (reg. 13(iii)); no allotment on sinking or landslide-prone land (reg. 35); and the zone-review condition of "Proper channelization of surface runoff by providing catchment drains especially during the rainy seasons and connect it to natural waterways/Jhora which also improves the stability of the area due to reduced erosions and percolation of water" (2021). On these sites retention is provided by storage and reuse, and detention by lined tanks, not by ponds or basins on the slope (Commentary to Clause 4.10). The 1.0 m groundwater separation of Clause 4.4.3 does not make an infiltration practice acceptable on a slope: perched water and pore pressure in a slope are the hazard, not the depth to the water table.
  • The septic soak pit: a conflict, stated. Regulation 25(i) has every building treat its sewage "in septic tanks built within the site", and regulations 6 and 13(iii) require the septic tank and soak pit to be shown on the plan and properly built before occupation. On a wet slope that soak pit puts water into the ground that the hill rule protects. This Manual does not override the regulations, which govern sewage, not storm water. It states the conflict plainly: no storm water, roof water or sullage is put into a soak pit under this Manual, and a soak pit earns no infiltration credit. It recommends that no new soak pit be placed in stability zones 3 to 6, and that one on a slope of more than 10° be sited by a geotechnical engineer, downslope of buildings and cuts (set by this Manual, as in the mountain editions of this series); where a soak pit falls on hill-rule ground, the conflict is recorded on the site submission, and the sewage itself is dealt with under Clause 8.9.
  • Valley-floor rule. In sub-area SK-A, no deliberate infiltration practice shall be built or credited on land below the 1% AEP flood level of the Teesta, the Rangit, the Rongni Chu or another river; on the river bed and terraces raised by the flood of October 2023; on the margins of a pokhari or reservoir (its Zone 1 and Zone 2 under Chapter 7); or wherever the seasonal high water table, the highest level from April to November, is less than 2.0 m below ground. On such land roof runoff goes to storage, and detention is provided in lined storage, checked for flotation with the design groundwater level at ground level (Clause 4.12.1). The ground gives the reason: the terraces at Rangpo, Melli and Jorethang are gravels with a high water table in the monsoon season (NEER reading), and no depth to water has been measured on any of them [TBC]; the land chosen for the Jorethang sewage works was "fully flooded during monsoon" (CAG, Report No. 3 of 2016); and the State itself says that the raised bed of the Teesta "poses a heightened risk of flooding during the monsoon season" (pre-project report, 2026).
  • Recharge rule. Recharge is not a design objective in Sikkim. Deliberate recharge is allowed only on tested river-terrace gravels of sub-area SK-A above the 1% AEP flood level and outside the zone raised by the flood of October 2023, and on benches of 10° or less in stability zone 1 that a geotechnical certificate shows to be stable; there it needs a silt trap, a filter and a first-flush diverter ahead of the structure, a field infiltration test, a seasonal high water table at least 2.0 m below ground and the separation of Clauses 4.11.4 and 4.12. Groundwater in the State is "largely in disconnected localized pockets and in deeper fracture zones" (CGWB, as quoted), and no CGWB depth or extraction figure for Sikkim was read for this Manual [TBC]. Everywhere else rainwater harvesting is storage and reuse.
  • Springs (dhara). A dhara is protected under the spring rule of Clause 8.8.1: no storm outfall, soakaway or drain discharge within 15 m of it, no storm water routed into or immediately above it, no drain, cut or fill that intercepts, buries or crosses its outlet, and no paving and no infiltration of road runoff in the recharge area above a town's or village's intake (set by this Manual). Springshed recharge, such as the trenches and ponds of the Dhara Vikas programme of the Rural Management and Development Department (RMDD), is a water-supply programme, not a stormwater credit: this Manual credits none of it, and allows recharge works of that kind under its rules only where the geology is mapped and the slope is stable, never above a known slide, a road cut or a building. That condition is a limit on where water may be put into a slope, not a judgement of the programme. A dhara is never used as storage.
  • Polluted runoff. Runoff from fuel stations, workshops, quarries and the like, and from any drain that carries sewage or septic effluent, as many of the drains of the towns do (Commentary to Clause 4.1), shall not be recharged; road and parking runoff shall be recharged, where the recharge rule allows it at all, only through a surface practice with a filter, such as a vegetated basin or trench, never directly into a pit, bore or well (Chapter 8).

On the ridges, water put into the ground goes into the slope, and on the valley floors it meets a water table that the river raises. In the monsoon season an RWH tank is full after the first heavy rain. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH tanks are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives. The 25 L per m² credit rule, the hill rule, the valley-floor rule, the recharge rule, the treatment of the soak-pit conflict and the polluted-runoff rule are set by this Manual. No Sikkim source sets a slope threshold for infiltration: the "around 70" degrees of reg. 35 is a limit on allotment, and the slope bands of the 2021 stability zones (zone 1 "<15°", zone 2 16–25°, zone 3 26–35°, zone 4 36–45°, zones 5 and 6 more than 45°) are site classes for building height, not infiltration rules. The 10° limit is set by this Manual, as in the mountain editions of this series, well below those slopes, because a slope that can carry a building can still be destabilised by water put into it; zones 3 to 6 need a certificate because the 2021 notification already records their ground as wet, dripping or flowing; zones 4 to 6 are excluded with no certificate, as the highest landslide-hazard zones are in another North-East hill edition of this series, because the notification judges zone 4 unsuitable for habitation without immediate protective measures and allows no construction in zone 6; and the distance of twice the height of a cut or wall is set by this Manual as a precaution, pending guidance from a geotechnical study for the State [TBC].


4.12 High-groundwater and sandy coastal sites

4.12.1 Design groundwater level. Each site in the valley floors and river terraces of the Teesta, the Rangit and the Rongni Chu in sub-area SK-A (at Rangpo, Singtam, Melli, Majitar and Jorethang), land below the 1% AEP flood level of a river and the river bed and terraces raised by the flood of October 2023, the margins of the pokharis and of the hydropower reservoirs and their backwaters, the seepage zones below springs (dhara) on the slopes, and the ground of stability zones 3 to 6, which the Mines and Geology Department's notification of 2021 records as "Wet", "Dripping" or "Flowing", or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the monsoon, from:

  • (a) site piezometer readings over at least one full April–November season; or
  • (b) where (a) is not available, the higher of the CGWB or WRD record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, khola, jhora, pokhari or reservoir, including the Teesta or the Rangit at a valley-floor town.

For the flotation check of 4.12.3 at sites in the Teesta and Rangit valley floors and river terraces (at Rangpo, Singtam, Melli, Majitar and Jorethang), land below the 1% AEP flood level or on the river bed raised by the flood of October 2023, the pokhari and reservoir margins, and the seepage zones below springs (dhara) on slopes, where (a) is not available, the DGWL shall be taken as existing ground level.

4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:

  • (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
  • (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.

4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:

  • with the facility empty;
  • with groundwater at the DGWL; and
  • for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.

The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.

4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.

4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.

4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.

Commentary. Sikkim is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3 and the saline exposure of 4.12.5, do not apply in the State, and no saline or aggressive groundwater was reported in the sources read for this Manual [TBC]. Groundwater is "largely in disconnected localized pockets and in deeper fracture zones", and "springs are the main source" (CGWB, as quoted); no CGWB depth to water or observation-well record for Sikkim was read, because the CGWB's Sikkim reports could not be reached, and no State observation-well network was found [TBC]. This Manual names WRD as the State agency for the observation-well records of 4.12.1(b), because WRD is the State's department for rivers and jhora works and monitors river water with CWC and the State Pollution Control Board (set by this Manual); until it keeps such records, the CGWB well, site piezometers and trial pits are the only sources. The wet cases are the valley floors and river terraces of the Teesta, the Rangit and the Rongni Chu at Rangpo, Singtam, Melli, Majitar and Jorethang, gravels with a high water table in the monsoon season (NEER reading); the river bed and terraces raised by the flood of October 2023; the margins of pokharis and of the hydropower reservoirs; the seepage zones below springs (dhara) on the slopes; and the ground of stability zones 3 to 6, which the Mines and Geology Department's notification of 2021 records as "Wet", "Dripping" or "Flowing". There an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when a river in flood, a reservoir at its full level or a pokhari at its spill level raises the water table beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, khola, jhora, pokhari or reservoir where that is higher than the well record, and on the valley floors, the raised bed and terraces, the waterbody margins and the seepage zones it is taken as existing ground level for the flotation check unless piezometers show otherwise. On a hill site a deep tank is not preferred even where groundwater is deep, because a leaking tank on a slope is an infiltration practice by another name: storage on a slope shall be lined and watertight, and its leakage and overflow taken to a lined drain (Clause 4.11, hill rule). The April–November monitoring season of 4.12.1(a) is set by this Manual to cover the Manual's monsoon season of 1 April to 31 October, whose pre-monsoon storms of April and May can raise the water table early, and the high after the season ends; a reading taken in March understates the design level. No monsoon water-table depth for any town site in Sikkim, and no map of the seasonal high water table, was obtained [TBC]. The factor of 1.2, the 0.5 m allowance and the "ground level" default for the valley floors, the raised bed, the waterbody margins and the seepage zones have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Sikkim were found during research.


4.13 Regional detention and fee-in-lieu

4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:

  • (a) a regional detention facility identified in the plan; or
  • (b) a fee-in-lieu paid toward restoration of pokhari or tank storage identified in the plan.

4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:

  • (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
  • (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
  • (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the monsoon. Storage below FTL that is held for irrigation or supply through April to October shall not be credited.
  • (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
  • (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
  • (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.

4.13.3 Fee. The fee-in-lieu shall be computed as:

Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)

The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.

4.13.4 Ledger. The Authority shall keep a public ledger of:

  • detention volume credited to each regional facility;
  • volume delivered; and
  • fees received and spent.

Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.

Sikkim has no tank or lake Act, and no pokhari, lake or reservoir in its towns was found to be operated for flood control under a documented rule. The River Rejuvenation Committee of the Forest and Environment Department has been "notified as the Nodal Agency for all water bodies" (Order No. 205/GOS/F&ED/SECY, 21 January 2021), but no State Wetland Authority notification and no wetland notified under rule 4 of the Wetlands (Conservation and Management) Rules, 2017 were found [TBC]; Khecheopalri lake became the State's first Ramsar site in February 2025 (as reported), and the published figures for its area conflict, so none is given here. The State's regional storage is of five kinds: the reservoirs of the hydropower projects on the Teesta and the Rangit; the lakes of the hills, such as Khecheopalri and Tsomgo, which are sacred and visited sites rather than flood storage (as reported); the pokharis of the towns and villages; the springs (dhara) that supply most villages; and the river floodplains, which no law zones. Glacial lakes are not among them: the State counts 320 (pre-project report annexed to its affidavit of 28 February 2026), a study of 2024 counts 232 larger than 0.01 km² (as summarised) and an older count gives 266 (as reported), the counts differing with the date and scope of the inventory, and they are hazard sources under Clause 2.3.6(i) and Chapter 7, never storage. Four points follow:

  • A pokhari on the record may not be a working pokhari, and a pokhari in the hills is not a detention basin. No inventory of the pokharis, lakes and springs within the municipal areas, with their beds, rims and outlets, was found [TBC]. A pokhari or lake is credited only after a survey shows its bed, rim and outlet, and only for the storage above its spill level; a natural, community or sacred pokhari or lake is never turned into a detention pond, and engineered storage is called a detention pond. A spring-recharge area is not storage for detention (Commentary to Clause 4.11).
  • The reservoirs are not spare capacity for a site. They are held for power, no full level, maximum level or release rule was found for any of them [TBC], their releases are set by their operators for the whole river, and in October 2023 the flood came down through them, destroying the dam of Teesta-III and filling the reaches below with debris (Sattar et al., 2025). Their storage below full level is not credited (Clause 4.13.2(c)), and storm water spilled to a reservoir, or to a reach below a dam, can be relied on only with the written agreement of the operator, for a stated flow and level.
  • A pond or check dam in the bed of a jhora is not regional detention unless it is designed for debris and garbage. The jhoras carry boulders, slide debris and waste in every large storm; the 2021 stability zones grade sites by whether their jhoras are trained, and GMC contracts for "Clearing of Jhoras"; such a facility is credited only for the storage left after the sediment and debris volume of Chapter 6, with a debris rack or trap at its inlet, a geotechnical check of its bund and abutments, its failure path mapped, and a maintenance budget for clearing it after each large storm (Clause 6.3.6; Chapters 9 and 10). A regional facility on a slope is also subject to the hill rule of Clause 4.11, and one on a valley floor to its valley-floor rule; in sub-area SK-C, and in any catchment below a glacial lake, no regional storage is credited without the site-specific study of Clause 2.3.6(i).
  • No notification divides the drains of any Sikkim town among their owners (NEER reading). Until one is made, this Manual follows the working split of Chapter 1: municipal drains, and jhoras on public land other than forest land within a municipal area, as the urban local body's (Municipalities Act ss.172(1) and 189(1)), with every jhora in the municipal area, public or private, under its duty to protect (s.172(2)); the river banks of the 103 scheduled rivers as the Forest Department's (1988 Act, s.29(9)); road drains as the road owner's (the Roads and Bridges Department (PWD) for State roads, and NHIDCL or BRO for national highways, by inference); jhora training as the executing agency's (GSCDL for Smart City works, as reported; WRD for river and jhora works; RMDD in rural areas); sewers and sewage treatment plants as PHED's, and rural and peri-urban sewage as RMDD's; the hydropower reservoirs and their gates as the operators'; springs with no statutory owner, although RMDD's Dhara Vikas programme works on them (as reported); and jhoras outside municipal limits or on forest land with no named owner. Each town keeps a drain and jhora register giving every reach its owner, its land status (municipal, Forest Department, private or road reserve) and its outfall (Chapter 6). This is the Manual's working split, not a statutory one; where land is private, a drainage corridor or easement is secured by agreement or donation, never taken.

The first point is the basis of condition 4.13.2(c) in Sikkim. A pokhari or lake gives flood storage only above its spill level, unless a notified operating rule commits it to be lowered before the monsoon season. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.


4.14 Simplified methods for small sites

4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.

4.14.2 Method.

  1. Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
  2. Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
  3. Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
  4. Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
  5. Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
  6. Complete Form 4-2 (Tier B site sheet).

Table 4.3 — Tier B permissible site discharge and site storage requirement (template)

Zone (Annex 2A) HSG Imperviousness PSD 2-yr (L/s/ha) PSD 100-yr (L/s/ha), standard PSD 100-yr (L/s/ha), flood-sensitive SSR (m³/ha), standard SSR (m³/ha), flood-sensitive
SK-Z1 Southern hills and valleys: SK-A Lower valleys (Rangpo–Singtam–Melli–Jorethang), at the depths of Clause 2.3.6(c)(i) A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
SK-Z1 Southern hills and valleys: SK-B Ridge towns (Gangtok–Pakyong–Namchi–Gyalshing), at the depths of Clause 2.3.6(c)(i) after the record check of Clause 2.3.6(h) C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
SK-Z2 North Sikkim: SK-B1 Middle Teesta valley (Dikchu–Mangan–Singhik–Chungthang), at the floor of Clause 2.3.6(c)(ii); where a station fit replaces the floor, Clause 4.6 applies C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
SK-Z2 North Sikkim: SK-C High valleys (Lachen–Lachung–Thangu) — — Not tabulated: Clause 4.6 applies (Clause 2.3.6(c)(iii) and (i)) — — — —

Worked example (illustrative — not design values).

A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:

  • PSD 100-yr = 356 / 2.0 = 178 L/s/ha
  • SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
  • PSD 2-yr ≈ 17 L/s/ha

Then:

  • Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
  • 100-yr release: 178 × 0.4 = 71 L/s.
  • 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
  • Layout options:
    • a 400 m² underground tank 1.5 m deep; or
    • 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
    • Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
  • RWH sumps are additional, and are assumed full (Clause 4.11).

Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.

4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:

  • (a) the site counts tank or waterbody storage in its design (Chapter 7);
  • (b) any part of the site lies within a waterbody setback (Chapter 7); or
  • (c) the site drains to a tank cascade whose storage is counted in a downstream design.

The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.

4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:

Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A

where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.

Table 4.3A — Fixed release coefficients (provisional)

Hydrologic soil group C_10 C_2
A (sandy, well drained) 0.05 0.02
B 0.08 0.03
C 0.15 0.08
D (clay, poorly drained) 0.25 0.15

Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).

4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):

V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]

V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]

where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).

4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.

4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.

Figure 4.3 — Fixed-coefficient route: release caps, storage by the mass-curve method and two-stage outlet (schematic) Schematic. Left: cumulative inflow volume against storm duration for the 1% and 50% AEP storms, with straight release lines 1.8 x Q_cap x d; the storage is the largest vertical gap. Right: two-stage outlet. Not to scale. Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3–4.14.7) — schematic, not to scale 0 12 24 36 48 60 72 Storm duration d (h) Volume (m³) V_100 = largest gap V_2 = largest gap 1% AEP inflow 10·C_v·P_100(d)·A Release line 1.8·Q_cap,10·d 50% AEP inflow 10·C_v·P_2(d)·A Release line 1.8·Q_cap,2·d Dots: durations of Clause 2.5.2 (1, 2, 3, 6, 12, 24, 48, 72 h). Pervious C ≥ 0.50 for d ≥ 12 h. Two-stage outlet (Clause 4.14.6) Top of V Top of V_2 Overflow / spillway (Clause 4.9) Upper orifice or weir: total release ≤ Q_cap,10 at top of V Low-flow orifice (≥ 50 mm): passes Q_cap,2 at top of V_2 Retention (Clause 4.4) is provided in addition; no retention credit (Clause 4.14.7) Q_cap,10 = 2.78 × C_10 × i_10 × A ; Q_cap,2 = 2.78 × C_2 × i_2 × A ; (L/s; A in ha; i in mm/h) C_10, C_2 from Table 4.3A by soil group; i_10, i_2 for a 15-minute duration with the climate factor (Clause 2.8) V = max(V_100, V_2); V_T = max over d of [ 10 × C_v × P_T(d) × A − 1.8 × Q_cap × d ] (m³) ; 1.8 = 3.6 × 0.5 (average release of half the cap)

Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).

Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the ridge towns round Gangtok, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.

The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.


4.15 Safety, fencing and multi-use

4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):

  • (a) maximum depth in the 10% AEP storm: 0.45 m;
  • (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
  • (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
  • (d) no vertical drop greater than 0.3 m within the storage area or at its edge.

4.15.2 Wet basins. Permanent pools shall have:

  • a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
  • an emergent planting fringe that deters entry.

4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:

  • has a vertical wall or headwall drop greater than 0.6 m;
  • exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
  • contains an outlet structure with an opening larger than 300 mm that is not grated.

4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.

4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Nepali and English stating that the area floods during rain, and a depth marker at the deepest point.

4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.

4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.

Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.


4.16 Basis: why peak matching alone fails

Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.

  1. Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
  2. Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
  3. Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
  4. Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
  5. Closed outfalls. In Sikkim the governing failure takes three forms. On the valley floors of the Teesta, the Rangit and the Rongni Chu it is a river that stands above the town's outfalls for hours or days: the Teesta at Khanitar reached a new highest level of 298.4 m on 4 October 2023, and at Melli a peak given as 225.5 m in one transcription and 228.0 m in a CWC bulletin, against a danger level of 227.0 m (as reported; the two peaks conflict), and the flood raised the bed itself by metres, so that an outfall set from the old bed may now be buried (State Government's pre-project report, 2026). On the reservoirs and below the dams it is volume with no outlet: the Teesta and Rangit reservoirs are held for power, no level or release rule for any of them was found [TBC], and a release from the Dikchu project in 2017 came without warning (as reported); when a reservoir is high, every drain below it discharges to a water surface that cannot fall until the operator releases. Everywhere in the hills the outfall can also be closed by debris and garbage: the jhoras rise within minutes and carry boulders, slide debris and waste that bury outfalls and block culverts; GMC's waste contract makes its agency responsible for "Clearing of Jhoras", and the SBCR 1991 forbid spoil in "drains, gullies and jhoras" (reg. 22). A flood such as the South Lhonak lake outburst and Teesta flood of 3–4 October 2023 is not an outfall-closed case to be designed for: no drain is sized for it, and the Manual deals with it by siting (Clause 2.3.6(i); Clause 5.8.5(d)). No hourly record of how long any river, reservoir or pokhari in Sikkim stays above a town's outfalls was obtained [TBC], and no document was found that sets a design river level for an outfall; Chapter 5 sets the design level and the closure to be assumed (Clause 5.8.5), and Chapters 6 and 9 the debris and blockage allowances. A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.

The response in this Manual is layered:

  • release below pre-development (Clause 4.5);
  • retain the frequent storms (Clause 4.4);
  • route long monsoon storms (Clause 4.6.3);
  • prefer regional storage in the pokhari system (Clause 4.13); and
  • check downstream and at the outfall (Chapter 5).

Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.


4.17 Submittal requirements

Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:

  1. the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
  2. the evidence for the order of measures under Clause 4.3.1;
  3. the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
  4. the retention credit computation (Clause 4.4.6);
  5. the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
  6. a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
  7. stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
  8. the drawdown calculation (Clause 4.7);
  9. outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
  10. the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
  11. the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
  12. the design groundwater level and flotation check (Clause 4.12);
  13. the downstream and tailwater report (Chapter 5, Form 5-1); and
  14. the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).

Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.


References (chapter)

Annexes and forms

Annex / Form Content
4A Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map
4B Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A)
4C Worked example (Tier A) with full routing tables
Form 4-1 Site Runoff Control Report
Form 4-2 Tier B Site Sheet
Form 4-3 Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7)