Chapter 5Downstream and Tailwater Analysis
5.1 Purpose and scope
5.1.1 This chapter sets two checks that every regulated development and every public drainage project must pass.
- The downstream analysis (Clauses 5.3 to 5.5) confirms that the project does not make flooding worse below its outfall.
- The tailwater analysis (Clauses 5.6 to 5.13) sets the water level the system discharges into, including tide, storm surge, sea-level rise, river backwater and sand-bar closure. It also requires the system to cope when its outfall is closed.
5.1.2 This chapter applies to:
- (a) every site to which Chapter 4 applies;
- (b) every minor- and major-system drainage project under Chapter 6; and
- (c) every regional detention or tank restoration project under Clause 4.13 and Chapter 7.
5.1.3 Rainfall and joint-occurrence inputs come from Chapter 2, in particular Clauses 2.5.3 and 2.12. Hydrologic methods come from Chapter 3. Site release criteria come from Chapter 4. Hydraulic design of gates, culverts and pumps follows Chapter 9.
5.1.4 No tidal outfalls in Sikkim. Sikkim is landlocked and mountainous: it has no coast, no tide and no Coastal Regulation Zone. No outfall in the State discharges to the sea, a tidal creek or an estuary, so the provisions of this chapter that depend on tide, storm surge, sea-level rise or a river mouth do not apply in Sikkim: Clause 5.7 and Annex 5A, cases J1 to J3 of Table 5.2, the tidal lock windows of Clause 5.10.3, the seawater requirement of Clause 5.11.3(a) (gates and seats shall still be of corrosion-resistant materials, and shall resist abrasion by gravel, boulders and slide debris), and Clause 5.13. They are kept so that the clause numbers of this Manual match its other State editions. In Sikkim the receiving water is one of six kinds: a steep jhora (झोरा; a natural watercourse or ravine stream), into which most outfalls of the ridge towns fall freely from a slope; a river whose valley floor or terrace a town stands on, such as the Teesta at Rangpo, Singtam, Melli, Dikchu and Chungthang, the Rangit at Jorethang and Majitar and the Rongni Chu at Ranipool and Singtam, now on a bed that the flood of October 2023 raised by metres; the reservoir of a hydropower dam, or the reach of river below one; a glacial-lake outburst flood (GLOF) corridor, which is screened for siting and not used as a design tailwater; a pokhari (पोखरी; pond, lake or tank); or the Teesta and the Rangit where they leave the State; and:
- (a) its tailwater is set by Clauses 5.6 and 5.8, including Clause 5.8.5;
- (b) where Clauses 5.10 to 5.12, Form 5-1 or Chapter 6 refer to the J1 tailwater or the J1 tidal curve, the minor-system tailwater of Clause 5.6.2 or 5.8.5 applies, as a time series where the receiving level varies; where they refer to the J2 tailwater or to HAT + surge + SLA, the major-system tailwater applies: the design-AEP river level of Clause 5.8.4(b), or the major-system tailwater of Clause 5.8.5, whichever is higher at the outfall; and
- (c) the outfall-closed check of Clause 5.10 applies where an outfall is closed by a jhora in flood, a river, a reservoir, a pokhari or a receiving drain, with the locks and closures of Clause 5.8.5(a) to (f) in place of the tidal lock windows.
5.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Analysis point | A location on the downstream system where pre- and post-project conditions are compared (Clause 5.3.3). |
| Contributing catchment | The whole area draining to an analysis point, on and off site. |
| Major drain | A channel listed as a major drain in the basin plan or Annex 5B, or any river, WRD canal, the Rani Khola and the Roro Chu below Gangtok and the jhoras that feed them, the jhoras of Pakyong, Namchi, Ravangla, Gyalshing, Pelling, Soreng and the other ridge towns, every drain that discharges through a flap gate on the valley floors of Rangpo, Singtam, Melli, Majitar, Jorethang or Dikchu, any drain built or held by the Gangtok Municipal Corporation or another urban local body, GSCDL, the Roads and Bridges Department (PWD), NHIDCL, BRO, WRD, the Public Health Engineering Department (PHED) or the Rural Management and Development Department (RMDD) with an internal width of 1.0 m or more, and every jhora, khola or other natural channel that drains 8 ha or more, whether or not it has been trained, or a tidal creek. |
| Chart datum (CD) | The datum of the published tide tables and nautical charts, to which tidal heights are referred. |
| Mean sea level (MSL) | Average sea level over a long period at a tide gauge. |
| MHWS | Mean high water springs: the average of high waters at spring tides. |
| HAT | Highest astronomical tide: the highest level predicted under average meteorological conditions over a full tidal cycle (18.6 years). |
| Storm surge | The rise in sea level above the astronomical tide caused by wind and low pressure, mainly during cyclones. |
| Still-water level | Astronomical tide plus surge, excluding individual waves. |
| Sea-level allowance (SLA) | The allowance added to present-day tidal levels for sea-level rise over the design life (Clause 5.7.4). |
| Tailwater | The water level at the downstream end of a drain, outlet or storage. |
| Tide-lock | The condition in which the tailwater is at or above the upstream water level, so a gravity outfall cannot discharge. |
| Lock window | A period during which the outfall-closed check of Clause 5.10 sets gravity discharge to zero. |
| Sand bar | A bar of beach sand that partly or fully closes a river mouth or creek inlet. |
| Project datum | The levelling datum used on the project drawings. It must be tied to a Survey of India benchmark (Clause 5.7.2). |
5.3 Extent of the downstream analysis
5.3.1 The downstream analysis shall start at each site or project outfall. It shall continue downstream to the first of:
- (a) the point at which the project area is 10% or less of the contributing catchment;
- (b) the next tank, pokhari or other waterbody with a surplus weir or controlled outlet; or
- (c) the next major drain, or the sea.
The end point itself shall be analysed (Figure 5.1).
5.3.2 Where the analysis ends at a tank or pokhari under 5.3.1(b), it shall report:
- the change in the tank's maximum water level; and
- the change in surplus-weir discharge, for the AEPs and durations of Clause 5.4.3.
If the maximum water level rises, the analysis shall continue below the surplus weir to the next end point.
5.3.3 Analysis points shall be set at least at:
- (a) each site outfall;
- (b) each confluence with a drain or channel whose contributing catchment is at least half that of the receiving drain at that point;
- (c) each culvert, bridge or road crossing;
- (d) each location recorded as flood-prone by the local body, GMC, SSDMA or WRD; and
- (e) each building or road segment lying within the 1% AEP flood extent along the route. Representative points may be used where buildings are closely spaced.
5.3.4 Small sites. For sites of less than 0.5 ha, the Authority may accept a simplified downstream statement (Form 5-2) in place of the full analysis, where all of the following hold:
- the receiving public drain has documented capacity for its minor-system design flow (Chapter 6);
- no flood-prone location is recorded within 500 m downstream; and
- the site does not drain to a tidal or backwater-affected outfall.
Figure 5.1 — Extent of downstream analysis: analysis points A–D, the contributing area at each point, the 10% point, and the next pokhari or major drain as an alternative end point. Schematic; percentages are illustrative. Original drawing for this Manual, adapted from the ten-percent rule in the Georgia Stormwater Management Manual (2016, Vol. 2 §3.1.9) and KC APWA Section 5600 (2006, 5601.5).
Commentary. The 10% rule has established precedent. KC APWA 5600 (2006) required the downstream system to be analysed "to the point the development's land mass is less than 10% of the total watershed". The Georgia manual makes the ten-percent analysis a mandatory standard (GSMM 2016, Standard #8). The tank or major-drain end point has no direct precedent; this Manual adds it for Sikkim. In the ridge towns, where a colony's drain runs down a jhora to a khola, and the khola to a river far below, as Gangtok's drains run by its jhoras to the Roro Chu and the Rani Khola and on towards the Teesta, and on the Teesta itself, where a valley-floor town's outfall lies among the reservoirs and release reaches of the hydropower dams, the 10% point can lie many kilometres downstream, across several tanks. A tank with a working surplus weir changes the hydrograph completely, so the analysis is better ended there and the tank level reported. Clause 5.3.2 prevents that end point from hiding a rise in the tank level. The small-site statement (5.3.4) and its 500 m distance have no direct precedent and are set by this Manual.
5.4 What the analysis must check
5.4.1 Scenarios. Each analysis shall compare:
- (a) Existing: the present downstream system and present land use of the whole contributing catchment, with the project site at its pre-project state; and
- (b) With project: the same, with the project and all its controls (Chapter 4) in place.
Where the Authority's basin plan defines future land use, the Authority may also require:
- (c) Future: the catchment fully developed under the plan, all to Chapter 4 standards, with and without the project.
5.4.2 Quantities to be checked at every analysis point:
- (a) Capacity: peak flow against the capacity of every channel, pipe, culvert and crossing, for the minor-system AEP of that element (Chapter 6) and for 1% AEP;
- (b) Flood levels: 1% AEP maximum water level at buildings (at the lowest opening) and on roads (at the crown and at the deepest point);
- (c) Velocities: peak velocity for 50%, 10% and 1% AEP;
- (d) Timing of combined peaks: the hydrograph at each confluence, showing the time to peak of the project outflow and of the receiving drain; and
- (e) Duration of inundation: on roads and at buildings, the time above the Chapter 6 depth limits.
5.4.3 Storms. The analysis shall use:
- 50%, 10% and 1% AEP;
- the duration set of Clause 2.5.2, at least the durations that give the highest level at each analysis point (these will usually be longer than at the site); and
- the 24-, 48- and 72-hour storms in every case.
The AMC rule of Clause 2.11.4 applies. Areal reduction follows Clause 2.7, applied to the contributing catchment at each analysis point and never to the site storage.
5.4.4 Method. The analysis shall:
- use a hydrograph method that combines hydrographs at confluences (SWMM, HEC-HMS, or an equivalent);
- include a hydraulic model with backwater (SWMM dynamic wave, HEC-RAS, or equivalent) wherever tailwater or backwater affects any analysis point; and
- not use the Rational Method at any analysis point, because it cannot represent timing.
Off-site areas shall be modelled at their present land use. Upstream detention shall be included only where it is built, maintained and documented.
5.4.5 Tailwater. The downstream end of the model shall use the tailwater of Clauses 5.6 to 5.9 and the sand-bar condition of Clause 5.13 where applicable.
Commentary. Clause 5.4.2(d) exists because detention changes when the site's water arrives, not only how much arrives (Clause 4.16). A Colorado State University thesis and a Water (2016) optimisation study both found that delayed site releases can coincide with the main-stem peak and raise it. Georgia's manual states the result directly: some structural practices "fail to reduce discharge peaks to pre-development levels downstream" because of "peak flow timing and runoff volume effects" (GSMM 2016). The duration-of-inundation check (5.4.2(e)) matters in the valley-floor towns of Sikkim whose outfalls lie below a river held high for hours or days, on a bed that the flood of October 2023 raised by metres: the State says the raised Teesta bed "poses a heightened risk of flooding during the monsoon season" and that NH-10 along the river "has become prone to submergence and subsidence" (Project Prefeasibility Report annexed to the State's affidavit of 28 February 2026 to the National Green Tribunal), the highway was reported submerged by the Teesta in July 2025 (as reported), and at Toong Naga 155 households were "mandated for relocation" after the 2023 flood (PDNA, 2023, as quoted in the same report), although how long the water stood in any of these events was not found [TBC]. Detention that prolongs releases can lengthen that time even when it lowers the peak.
5.5 Acceptance criteria
5.5.1 The project is acceptable if, at every analysis point and for every AEP and duration of Clause 5.4.3, comparing "with project" to "existing":
- (a) the 1% AEP maximum water level does not rise by more than 10 mm at any habitable building, at any building's lowest opening, or on any road carriageway;
- (b) no building that is not flooded in the existing case is flooded with the project, and no building or road that meets the Chapter 6 freeboard or depth limits in the existing case fails them;
- (c) peak flow does not exceed the existing peak at the minor-system AEP of each element, or at 1% AEP;
- (d) peak velocity in lined channels stays within the permissible velocity for the lining (Chapter 6: 3.0 m/s maximum); and
- (e) in unlined or natural channels, peak velocity for 50% and 10% AEP does not increase by more than 10%, unless protection is provided under Chapter 9.
5.5.2 The duration of inundation under 5.4.2(e) shall be reported. The Authority may refuse a project that increases the duration of road closure on an arterial or emergency route.
5.5.3 Where the criteria are not met, the project shall do one or more of the following:
- (a) reduce release rates or increase storage (Chapter 4);
- (b) build downstream improvements, with the consent of the owner of the downstream system. These shall not transfer the problem further downstream, and shall be re-analysed under this chapter;
- (c) contribute to a regional facility under Clause 4.13; or
- (d) under Clause 5.5.4, change the release strategy.
5.5.4 Timing exception. Where the analysis shows that detention raises downstream levels because of timing, the Authority may vary the site release-rate criteria of Clause 4.5. This applies only where the site discharges within the lower tenth of the contributing catchment, directly to a major drain, tidal creek or the sea, and only on the following conditions:
- (a) the varied strategy meets 5.5.1;
- (b) the retention requirement (Clause 4.4) and WQv treatment (Chapter 8) are met in full; and
- (c) the outfall-closed check (Clause 5.10) is met.
Commentary. The 10 mm tolerance (5.5.1(a)) has no direct precedent. It is meant to be at or below the numerical precision of a typical one-dimensional model, so that "no increase" can be tested without arguing over rounding. The 10% velocity tolerance is likewise set by this Manual. The timing exception in 5.5.4 follows the Georgia manual, where the downstream analysis can show "that peak controls are not needed" and allow them to be waived (GSMM 2016, Standard #8). It is limited here to sites low in the catchment, which is where synchronisation with the main-stem peak is most likely (Water 2016, 8(7):290). It is not available above that, because the evidence on scale (Clause 4.16) shows that early release from many upstream sites raises peaks.
5.6 Tailwater: general and non-tidal outfalls
5.6.1 Every drain, outlet and storage shall be designed against a stated tailwater. A free outfall shall be assumed only where the outlet invert is above the maximum receiving water level for the case being checked.
5.6.2 Minor-system tailwater, non-tidal. The tailwater is the receiving system's water level at the time of the minor-system peak, from the downstream model. Where no model exists, use:
- for a receiving pipe, its obvert; or
- for a receiving open drain, its full-bank level less freeboard (Chapter 6).
5.6.3 Major-system tailwater, non-tidal. The tailwater is the receiving system's 1% AEP water level, unless Clause 5.8 allows a coincident lower level.
5.6.4 Tidal and backwater outfalls. Clauses 5.7 to 5.13 apply in addition.
5.6.5 Storage elements. Detention, tanks and pumped sumps shall be routed with a time-varying tailwater (Clause 4.6.6), not a constant level, wherever the tailwater varies with tide or with the receiving system's hydrograph.
5.7 Tidal tailwater: datums, surge and sea-level allowance
5.7.1 Design tailwater levels. For outfalls to the sea, tidal creeks, estuaries, backwaters and tidal reaches of rivers and canals:
Table 5.1 — Design tailwater levels for tidal outfalls
| Design case | Tailwater |
|---|---|
| Minor-system design (Chapter 6) | MHWS + SLA |
| Major-system design and storage design | HAT + surge + SLA, with the surge term defined in Clause 5.7.3 |
| Joint case (Clause 2.12(b)) | 1% AEP still-water level + SLA |
The SLA is +0.3 m minimum (Clause 5.7.4). The cases to be run are listed in Clause 5.9.
5.7.2 Sources and datums.
- (a) Tidal levels. MHWS, HAT and MSL shall be taken from the current edition of the Indian tide tables published by the National Hydrographic Office (NHO) or by the Survey of India, for the nearest standard or secondary port, or from the port authority's published tidal levels. The edition and port shall be stated.
- (b) Datum conversion. Tide-table heights are referred to chart datum. They shall be converted to the project datum through a documented connection between chart datum, the tide gauge zero and a Survey of India benchmark. The offset and its source shall be stated on Form 5-1.
- (c) Estuaries, creeks and canals. For outfalls inside estuaries, creeks, backwaters or tidal canals (for example the estuaries of the coastal States; there is none in Sikkim, Clause 5.1.4), tidal levels may differ from the open coast. Open-coast levels shall be used unless measured levels over at least one spring–neap cycle, or a calibrated hydrodynamic model, justify a different value. No reduction below open-coast levels shall be taken without such evidence.
- (d) Interim. Until Annex 5A is published, the designer shall obtain the values directly from the sources in (a) and record them.
5.7.3 Storm surge.
- (a) Major-system and storage design. The surge term in "HAT + surge" is the 10% AEP (10-yr) storm surge for the coastal segment, given in Annex 5A. The 1% AEP surge is used only in the joint case of Clause 2.12(b), with the 10-yr 48-hour storm. That keeps the two cases symmetric, so that a rare rainfall is never paired with a rare surge.
- (b) Joint case. The 1% AEP still-water level for Clause 2.12(b) is taken from Annex 5A.
- (c) Until Annex 5A is published, both values shall be taken from a site-specific study using INCOIS, IMD or NCCR surge hindcasts or return-level analyses. The study shall state its source, method and record length.
- (d) Wave set-up shall be added where the outfall faces the open sea without a protected entrance.
5.7.4 Sea-level allowance. The SLA shall be:
- (a) +0.3 m minimum for every element;
- (b) greater than 0.3 m where the State, a development authority or the Authority adopts a higher projection for the planning area; and
- (c) assessed for the design life of the element. For elements with a design life of more than 50 years, the designer shall report the effect of a sea-level rise of twice the SLA as a sensitivity run.
Figure 5.2 — Tidal outfall: flap gate, property non-return valve, and the design tailwater levels (MHWS + 0.3 m for the minor system; HAT + surge + 0.3 m for the major system), with a seasonal sand bar at the mouth. Schematic, not to scale. Original drawing for this Manual, adapted from the tidal tailwater table in MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, Table 6.2.
Commentary. CPHEEO (2019) Table 6.2 sets the design tailwater for coastal outfalls as:
- MHWN to MHWS for a minor storm (more frequent than 1 in 5 years);
- MHWS to HAT for a major storm; and
- "Effect of climate change: additional 0.3 m".
CPHEEO also says the joint probability of storm, tide and surge "should" be considered, with the state maritime board consulted. This Manual takes the upper end of each CPHEEO range, adds surge for the major system, and makes the joint case explicit (Clause 2.12). CPHEEO does not require surge to be added; this Manual adds it because the surge records of the coastal States showed why it is needed there; Sikkim has no coast, and the surge term does not arise in the State, whose outfalls fall freely to steep jhoras on the ridges or are held up by the Teesta, the Rangit and the Rongni Chu on the valley floors and by the reservoirs of the hydropower dams, not by the sea (Clause 5.8.5).
Indian tide tables have been published by the Survey of India since the nineteenth century (Survey of India, Tidal Predictions). Current Indian tidal predictions also appear in the NHO's tide tables. One port document describes the current edition as covering 95 Indian ports, based on NHO observations and on data from civil ports, NIO and INCOIS (Adani Ports, Dahej tide table 2025, citing NHO INP-12). INCOIS runs coastal tide gauges and issues storm-surge and swell-surge warnings. None of these is used for design in Sikkim, which has no coast, and Annex 5A is not prepared for the State (Clause 5.1.4).
5.8 Riverine backwater
5.8.1 Where it applies. Outfalls to rivers and canals whose water level in a storm can exceed the outfall invert shall be designed with riverine backwater. This includes:
- the jhoras of the ridge towns where an outfall's invert is below the jhora's design level, among them those of Gangtok to the Rani Khola and the Roro Chu, and those of Pakyong, Namchi, Ravangla, Gyalshing, Pelling and Soreng (Clause 5.8.5(a));
- the Teesta at Rangpo, Singtam, Melli, Dikchu, the riverside of Mangan and Chungthang, with the CWC sites at Khanitar and Melli; the Rangit at Jorethang and at the CWC site at Majitar; the Rongni Chu at Ranipool and at the CWC site at Singtam; and the Dik Chu at the CWC site at Bakcha (Clause 5.8.5(b));
- the reservoirs of the hydropower dams on the Teesta and its tributaries, among them Teesta-III at Chungthang, Teesta-V at Dikchu, Teesta-VI, Chuzachen, Dikchu, Rongnichu, Jorethang, Tashiding and Rangit-III, and the reach of river below each (Clauses 5.8.3 and 5.8.5(c));
- the Teesta from the South Lhonak lake through Chungthang, Mangan, Dikchu, Singtam, Rangpo and Melli to the State border, the Lachen Chu and the Lachung Chu, and every stream below a glacial lake listed as high-risk, as glacial-lake outburst flood (GLOF) corridors screened under Clause 2.3.6(i) (Clause 5.8.5(d));
- the Teesta below Melli and the Rangit's lower reach where they form or cross the State border (Clause 5.8.5(e));
- every pokhari that receives a town's drains (Clause 5.8.5(f));
- any drain or jhora of the Gangtok Municipal Corporation or another urban local body, GSCDL, the Roads and Bridges Department (PWD), NHIDCL, BRO, WRD, PHED or RMDD that receives storm water, and the river bank of every river scheduled under the Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 (Clause 5.8.5(g)); and
- elsewhere: any river or WRD channel listed in Annex 5B.
5.8.2 River levels. River water levels shall be taken from:
- (a) WRD design flood levels or recorded highest flood levels for the reach, where published; or
- (b) a hydraulic model (HEC-RAS or equivalent) of the river reach. The model shall use:
- the river design flood from a hydrograph method (Chapter 3), with continuous simulation where Chapter 3 requires it;
- the tidal boundary of Clause 5.7 at the mouth; and
- the sand-bar condition of Clause 5.13.
5.8.3 Reservoir and tank releases. Where a reservoir or tank upstream can release to the river (for example the Teesta-III dam at Chungthang, under restoration since the flood of October 2023, the Teesta-V dam of NHPC at Dikchu, Teesta-VI, Chuzachen, the Dikchu project, Rongnichu, Jorethang, Tashiding and Rangit-III), the river level shall include the release given by the reservoir's operating rule for the storm being checked. Where there is no published rule, it shall include the largest recorded release.
5.8.4 Coincidence of site storm and river flood. Unless a joint-probability study is accepted by the Authority, the more severe of the following governs:
- (a) the site design storm (AEP as required), with the river at its 10% AEP (10-yr) level; and
- (b) the site 10% AEP storm, with the river at its design-AEP level (1% AEP for the major system).
The two storms in each pair shall have the same duration and timing where they are generated by the same rainfall event.
5.8.5 Free outfalls to jhoras on the ridges, the valley-floor towns on the Teesta, Rangit and Rongni Chu, hydropower reservoirs and release reaches, GLOF corridors, the West Bengal reaches, pokharis, and consents and lines.
- (a) Jhoras on the ridges. For an outfall from a ridge or a slope to a jhora, directly or through a drain, down-drain or chute that ends in one, as in Gangtok with Tadong and Ranipool, Pakyong, Namchi, Ravangla, Gyalshing, Pelling, Soreng and the other ridge towns, and on every slope above a valley floor:
- No gauge, no level. No jhora in the State has a gauge or a published flood level [TBC]. The jhoras are steep and short, rise within minutes of a burst of rain and fall within hours of its end, and carry boulders, gravel, slide debris and, below the towns, sullage and garbage. Gangtok's jhoras drain to the Rani Khola and the Roro Chu, and those of the other ridge towns to the Rongni Chu, the Rangit and the Teesta. Most outfalls of the ridge towns fall freely to a jhora: there is no river tailwater for most of Gangtok, Pakyong, Namchi, Ravangla and Gyalshing (NEER reading).
- Free-outfall case. The design case is a free outfall with energy dissipation. The outfall shall end in an energy dissipator designed under Chapter 9, built into the bank of the jhora, and shall be reached from the town drain by a lined drain, chute, stepped channel or closed down-drain, so that no flow of the minor or major system is discharged onto an unprotected slope, fill, retaining wall or the land of a building below (Clause 6.3.6(j)). Where no jhora can be reached within the site or the public land beside it, the flow shall be carried in a closed conduit or lined drain to the nearest road drain or permanent drain that can take it, as regulation 25(iv) of the SBCR 1991 already requires of a building's plinth drain ("leading to the road side drain or to adjoining permanent drains or jhora"), through the land of another person only by a recorded easement or agreement, and not left at the foot of the slope (set by this Manual).
- Design level. Where the jhora can rise above the outfall invert, the tailwater for the major-system and storage cases shall be the higher of: (i) the 1% AEP level at the outfall from a study of the jhora, made with a hydrograph method of Chapter 3 for the whole catchment above the outfall, with the rainfall of its sub-area under Clause 2.3.6 (SK-B for Gangtok), the AMC of Clause 3.8.4 and the bulking factor of Clause 6.3.6(g) on the peak flow, and routed through a hydraulic model (Clause 5.8.2(b)) of the channel as surveyed, net of encroachment, silt, slide debris and solid waste, with the crossings downstream blocked as Clause 6.3.6(h) requires; and (ii) the highest flood level surveyed at the outfall from flood marks, such as debris lines, silt and scour marks and the accounts of residents, of a recorded storm, such as that of June 1997 at Gangtok, or a later storm, and from the records of the local body, the Sikkim State Disaster Management Authority (SSDMA) or the District Collector, with its source stated. No outfall to a jhora that can rise above its invert shall be designed without both items (set by this Manual).
- The jhora below the outfall. The designer shall also check the receiving jhora from the outfall to the next confluence with a jhora or khola of at least equal catchment, to a river, or to the upstream end of a reach trained to Clause 6.3.6(m), whichever comes first: that it carries the post-development 1% AEP flow of its whole catchment, with the bulking factor, within its banks and below the velocity limits of Chapter 9 for its bed and banks; that no bank or slope along that reach is in Mines and Geology stability zone 3, 4, 5 or 6, is sinking, landslide-prone or scarred by old landslides (SBCR 1991, reg. 35), or is undercut, without the geotechnical certificate of the hill rule of Clause 4.11; and that the increase in flow does not reach a road, a building, a dhara (धारा; a spring or spring spout) or a slide. Where the jhora fails any of these checks, the project shall reduce its peak and volume under Chapter 4, or train the reach to Clause 6.3.6(m) with the consent of its owner under item (g) (set by this Manual). This is the downstream check that s.187 of the Sikkim Municipalities Act, 2007 already makes a municipal duty, an outfall "in such manner as may not cause any nuisance, either by flooding any part of the municipal area or any area surrounding the outfall". The stability zone of the outfall and of the reach shall be stated on Form 5-1 and in the drain and jhora register (Clause 6.9).
- Bed level, scour and aggradation. The designer shall survey the bed of the jhora at the outfall and for at least 100 m upstream and downstream, and state the range within which the bed has moved, from past surveys, cross-sections, exposed foundations and pipes, and the records of the local body. The outfall invert, and the seat of any flap gate on it, shall stand at least 0.5 m above the highest bed level found in that range within 50 m downstream of the outfall, and the foundation of the outfall structure and its apron shall be taken below the scour depth computed under Chapter 9 (Clause 9.6) for the 1% AEP flow with the bulking factor (set by this Manual).
- Siting. An outfall shall be built into the bank and shall not project into the bed or the active channel, taken for this Manual as the land flooded once in 5 years (set by this Manual). It shall discharge in the direction of the stream's flow, with the bank protection that Chapter 9 requires, and no pipe, interceptor or chamber of the drainage system shall be laid along the bed of the jhora. No spoil or building material from the works shall be placed in "drains, gullies and jhoras" (SBCR 1991, reg. 22) or where a storm can carry it into one, and no excavation for an outfall shall be made in the period of the State's monsoon excavation ban (Chapter 10). No outfall shall discharge into or immediately above a dhara, within 15 m of one, or onto the recharge area above it (the spring rule of Chapter 8) (set by this Manual).
- Closed outfall. Where the outfall invert is below the design level of this item, the outfall-closed check of Clause 5.10 applies with a single lock that lasts for the duration of the design storm plus the jhora's recession, computed under item (i) for the coincident cases of Clause 5.8.4 for as long as the jhora stays above the invert, and not less than 24 hours; where the 48- and 72-hour storms of Clause 5.10.2 are run, the lock lasts for the whole storm (set by this Manual).
- (b) The valley-floor towns on the Teesta, Rangit and Rongni Chu. For an outfall on a valley floor or river terrace whose river can rise above the outfall invert, such as Rangpo, Singtam, Melli, Dikchu, the riverside of Mangan and Chungthang on the Teesta, Jorethang and Majitar on the Rangit, and Ranipool and Singtam on the Rongni Chu, and for any other outfall on land below the 1% AEP flood level of a river or on the river bed and terraces raised by the flood of October 2023 ("valley-floor land" in this Manual, sub-area SK-A and the valley floors of SK-B1), directly, through a flap gate or through a pumping station, or into a drain that itself discharges in one of those ways:
- A raised bed. The South Lhonak lake outburst and Teesta flood of 3–4 October 2023 left the Teesta on a new bed: it "has risen by an average of 7-8 meters", and NH-10 along the river "has become prone to submergence and subsidence" (PPR annexed to the State's affidavit of 28 February 2026 in OA 171/2023 before the National Green Tribunal); NHPC estimated the rise at about 7.44 m at TLDP-IV, 7.29 m at TLDP-III, 6.00 m at Teesta-V and 2.00 m at Teesta-VI (same affidavit). The State itself says the raised bed "poses a heightened risk of flooding during the monsoon season" (same affidavit). An outfall whose invert was set from a bed surveyed before October 2023 may now be buried, and every level based on a highest flood level read before that date needs a post-2023 survey (NEER reading).
- Gauges and levels. CWC's levels for the State's rivers are known for this Manual only from SANDRP's transcriptions of CWC data and from press reports (as reported), and no datum is stated for any of them [TBC]. They are: Khanitar on the Teesta (East), old highest flood level (HFL) 297.7 m (18 September 1974) and a new HFL of 298.4 m at 09:00 on 4 October 2023; Melli on the Teesta (Namchi district), warning level 226.0 m and danger level 227.0 m [TBC], old HFL 225.25 m, and an October 2023 peak given as 225.5 m (04:00, 4 October 2023) in SANDRP's text but as 228.0 m in a snippet of a CWC daily bulletin of 2024, seen only as a search snippet; SANDRP's own statement that the new level is "2.75 meter higher than the old HFL" does not agree with 225.25 m, and a press report that the river ran "nearly 3 metres above the Danger Level" does not agree with a danger level of 227.0 m and a peak of 228.0 m; Singtam on the Rongni Chu, danger level 355.09 m and HFL 356.09 m, undated; Majitar on the Rangit (Namchi district), HFL 279.29 m (17 October 1985); Ranipool on the Rongni Chu and Bakcha on the Dik Chu, active, with no HFL; and Rangpo, where no CWC level was found [TBC]. The upstream sites at Lachen, Rangma Range, Sankalang, Teesta-III and Teesta-V stopped recording between 22:00 and 23:00 on 3 October 2023 (all as reported). Every level used shall state its gauge, its date, its datum and its connection to the gauge datum of the named CWC site and to a Survey of India benchmark.
- Melli: the higher value for a check. Where a check level at Melli is needed, 228.0 m is used, and 225.5 m is recorded beside it on Form 5-1 (set by this Manual). The two readings cannot both be right, neither source was read in full, and the lower one is the one that its own source's arithmetic contradicts; a check level set on the lower of two unresolved readings could put an outfall below a level the river has already reached. The conflict is to be resolved from CWC's site record [TBC].
- Design level. The design tailwater at the outfall, for the major-system and storage cases (Clause 5.8.4(b)), shall be the higher of: (i) the highest recorded CWC level at the nearest site on the same river, with the October 2023 values above, transferred to the outfall with the water-surface slope of the flood that set it, from the gauge record or from a model; and (ii) the surveyed October 2023 flood mark at the outfall, from debris lines, silt and scour marks, damage records and the accounts of residents, with its source stated and tied to a Survey of India benchmark. Where neither exists, as at Rangpo, the design tailwater is the 1% AEP level at the outfall from a hydraulic model under Clause 5.8.2(b) run on the surveyed post-2023 bed, with the river design flood from a site study under Chapter 3 and the releases of item (c); and where such a model is made at any outfall, its result also applies where it is higher. No outfall on valley-floor land shall be designed without item (ii), or, where no flood mark can be found, without the model. The level of the nearest site downstream shall not be carried upstream (all set by this Manual). The 1% AEP rainfall flood is not the design flood for the trunk of the Teesta, and no level of this item protects against a cascade of the kind of October 2023 (item (d)).
- 10% AEP level. For the cases with the river at its 10% AEP level (Clause 5.8.4(a)), the level shall be taken from the same model or from a frequency analysis of the gauge record; until such an analysis is accepted, it is the danger level where one is reported (Melli 227.0 m, Singtam 355.09 m, as reported; datums [TBC]), and elsewhere the design level of this item (set by this Manual).
- Inverts above the post-2023 bed. The designer shall survey the river bed at the outfall and for at least 100 m upstream and downstream after October 2023, and state the range within which it has moved. The outfall invert, and the seat of any flap gate on it, shall stand at least 0.5 m above the highest surveyed post-2023 bed level within 50 m downstream of the outfall, and its foundation shall be taken below the scour depth computed under Chapter 9 (set by this Manual).
- Gates and owners. No flap-gated or pumped storm outfall was found in the State during research [TBC]. Every outfall whose invert is below the design level of this item shall have its own flap gate (Clause 5.11), and the designer shall name the body that will own, operate and maintain it, which is the owner of the drain in the drain and jhora register (Clause 6.9), and state its sill, the crest of any bank or wall it passes, and the river level at which it closes, all on the datum of this item.
- Two cases, and the lock. A valley-floor drain shall be checked for two cases: a short burst on the hillside above it with the river low and the drain as surveyed, net of silt, boulders, debris and encroachment; and a multi-day storm with the river at the design tailwater (Chapter 3). In the second case the tailwater at the outfall shall be the higher of the river level beyond the gate and the maximum level in the drain behind it, computed by routing the drain as a closed storage for as long as the river stands above the level behind it, with the inflow of the whole catchment that drains to it, the hill catchments above the valley floor included, its storage as surveyed in its present condition, and an outflow of no more than the pumping capacity that the operator confirms in writing is available in a storm, and in no case more than the installed capacity of the permanent pumps less the largest pump; portable pumps brought in for an event and capacity not commissioned shall not be counted. The outfall-closed check of Clause 5.10 applies with the river at the design tailwater for the whole of the 72-hour design storm of Clause 5.10.2, and the outfall closed, with no gravity discharge credited, for not less than 72 hours where a flap would shut (set by this Manual). No stage record of the Teesta, the Rangit or the Rongni Chu was analysed for this Manual; once a stage record of the nearest CWC site is obtained and analysed under Clause 5.10.6, it governs, and a longer lock shall be used where it shows the river above the outfall invert for longer. The lock covers every shorter storm, so that storage and pumping handle the full storm volume (Clause 5.9.4). Pumps (Clause 5.12) shall deliver against the design river level of this item, and every pump, panel and control shall remain operable with the river at that level (Clause 5.12.5). Any stored volume shall be pumped down to its starting level within 48 hours of the end of the storm, with the gate still closed (set by this Manual).
- Gate failure. Floor levels and pumped outfalls behind a flap gate shall also be checked for the gate jammed open by gravel, boulders or slide debris, with the drain filled to the river level beyond it, and for the gate buried by the bed.
- (c) Hydropower reservoirs and release reaches. For an outfall to the reservoir of a hydropower dam, directly or through a drain or jhora that ends in one, or to a reach of river below a dam:
- The dams. The State listed, in its affidavit of February 2026 to the National Green Tribunal, the Rongnichu project (113 MW, operational, run of the river); Teesta-III (1,200 MW, Chungthang), "Under restoration & first phase of wet commissioning is expected by 31st MAY 2026 through coffer dam", with no live storage in the first phase; Dikchu (96 MW); Chuzachen (110 MW, shut down, with restart from 15 February 2026); Jorethang (96 MW); Tashiding (97 MW); Teesta-VI (500 MW, expected in September 2029); and Rangit-III (60 MW). Teesta-III was listed as "non-operational since 4th Oct 2023" by the State's power department (as quoted), and its present status was not found [TBC]. Teesta-V (510 MW, NHPC; dam at Dikchu) is reported to have been restored, and the restoration of the Teesta-V dam at Dikchu and the Teesta-VI dam was reported to be under way in June 2025 (as reported). The Teesta Low Dam projects III and IV (TLDP-III, TLDP-IV) lie lower on the Teesta; their position in relation to the State border was not confirmed for this Manual [TBC], and where they lie across it the West Bengal edition governs (item (e)).
- Levels in writing. The operator's levels are data for the design, not an approval: the consents of item (g) still apply. No full reservoir level (FRL), maximum water level (MWL), spillway rating, datum or release rule was found for any dam in the State [TBC]. The tailwater for the major-system and storage cases shall be the reservoir's MWL as its operator states it in writing, or, where only the FRL is given, FRL plus the surcharge in its design flood, computed from the rating of its spillway with any gates operated only as the operator's written rule provides; where neither the MWL nor the surcharge has been given, or where the MWL is not above the FRL, the tailwater is FRL + 0.5 m. In every case it shall be not less than the highest level recorded at the reservoir. The minor-system tailwater is the FRL. The project's discharge shall be included in the level (Clauses 5.3.2 and 5.12.3) (set by this Manual).
- Until the operator gives them. Until the operator gives its levels in writing, an outfall in a reservoir reach has an unknown tailwater: it shall be sited above the surveyed October 2023 flood mark at the outfall, and where it cannot be, its tailwater is the higher of that flood mark, the highest water line surveyed on the shore and the crest of the spillway surveyed at the dam, each tied to a Survey of India benchmark, plus 0.5 m (set by this Manual) [TBC].
- Releases, not notices. No design shall rely on a notice or a warning of a release, on a reservoir being drawn down before a storm, or on a gate being opened early, late or partly: the release scenarios of this item govern (set by this Manual). A release from the Dikchu project in 2017 was reported to have come without warning (as reported); the High Court of Sikkim closed the case with the direction "that the hydropower projects in Sikkim shall ensure strict compliance of the safety guidelines" and that the authorities "undertake periodic inspection and review" (WP(PIL) 4/2017, judgment of 1 March 2021). No operating rule or release record of any dam, and no rule linking the operation of any dam to the drains above or below it, was found during research [TBC].
- Closed outfall. Where the outfall invert is below the design level of this item, the outfall shall be treated as closed for the whole of the 72-hour storm of Clause 5.10.2 and of every shorter storm (Clause 5.9.4), with storage and pumping handling the full storm volume, unless the operator's stage record shows the reservoir below the invert at the start of comparable storms and the Authority accepts it (set by this Manual). Every reservoir starts every design storm at its FRL (Clause 7.7.3); a catchment that drains to a reservoir or its backwater takes AMC III at any time of year (Clause 3.8.4); and the drawdown zone of a reservoir is part of the reservoir, in which no outfall structure, pumping station or storage shall be built without the operator's written agreement.
- Release reaches. For an outfall to a reach of river below a dam, in addition to the cases of Clause 5.8.4, the site design storm (each AEP required) and the 72-hour storm shall be run with the river at the level that results from the largest recorded release of the dams above, routed to the outfall, with the flow of the catchment below the dams as it occurred, and with the release placed before, during and after the site storm, and the lock of item (b) applies for not less than 72 hours (set by this Manual). No release record was obtained for any dam [TBC]. Until the operator states the largest recorded release and its duration, the release is the spillway design capacity, and until that is given, the 1% AEP inflow to the reservoir from a site study under Chapter 3, passed with no attenuation by the reservoir (set by this Manual) [TBC]. No attenuation by the storage of any reservoir shall be credited to the river below unless the operator's written rule commits that storage to flood control. The inflow of about 10,000 m³/s at Teesta-III in October 2023 against a spillway capacity of 7,500 m³/s, reported from the committee constituted by the National Dam Safety Authority (NDSA) (as reported), is recorded on Form 5-1 for an outfall below Chungthang; it is the cascade of item (d), not a design release. Every release reach is a hazard-first site under Clause 2.3.6(i).
- (d) GLOF corridors. For an outfall, a detention facility, a pumping station or an interception or treatment work on the path of a glacial-lake outburst flood: the Teesta from the South Lhonak lake through Chungthang, Mangan, Dikchu, Singtam, Rangpo and Melli to the State border; the Lachen Chu and the Lachung Chu; and every stream below a glacial lake that NDMA, the Science and Technology Department (nodal for GLOF studies and mitigation since Notification No. 10/Home/2025, 7 February 2025) or the Sikkim Commission on Glacial Hazards lists as high-risk:
- Screened, not sized. These corridors are screened under Clause 2.3.6(i), apart from rainfall design. No drain is sized for a GLOF, and no rainfall tailwater governs on the corridor: the design tailwater of an outfall to the trunk is that of item (b), and the GLOF decides where the asset may stand. NDMA has identified 40 high-risk glacial lakes in Sikkim, 16 of them very high-risk (State affidavit of 28 February 2026), 13 of the very high-risk lakes in Mangan district, 3 in Gyalshing district and 12 in the Lachen Chu watershed; "Shako Chho has habitations and Army establishments just 15 km downstream" (PPR, same affidavit). In the October 2023 flood the water outflow at the lake "peaked at 4.85 × 10⁴ m³ s⁻¹", with sediment of a further 1.03 × 10⁴ m³ s⁻¹, "equivalent to a return period exceeding 200 years"; at Chungthang the "discharge peaked at 5340 m³ s⁻¹ … within ~6 minutes", with a depth of 9 m and a velocity of 9 m/s; and GLOF peaks exceeded meteorological floods for about 50 km below the lake (Sattar et al., 2025). So the 1% AEP rainfall flood is not the design flood for the trunk, and no rainfall-based setback or level protects against the cascade (NEER reading).
- Cause disputed. The State's affidavit of 5 April 2024 attributed the flood "primarily to a cloudburst"; a committee constituted by the NDSA reportedly found that "all scientific data and satellite images from that period points to GLOF and not a cloudburst" (as reported); and Sattar et al. (2025) found 29–39 mm of rain over the lake from 28 September to 5 October in the ERA5 reanalysis, and a moraine collapse. This Manual takes no side; all the sources agree that the lake drained.
- Siting rule. Every drainage asset that this Manual governs on a GLOF corridor, among them detention storage, outfall structures, pumping stations and treatment and interception works, shall be sited above the October 2023 flood and aggradation level surveyed at the site, and outside the mapped GLOF path where a map exists, among them the GLOF evacuation maps prepared by SSDMA and the District Disaster Management Authorities with the participatory risk assessments of May 2024, where they cover the site [TBC]; and its outfall to the trunk shall meet item (b) (set by this Manual). Where an outfall must reach the river below that level, its structure shall be designed to be overtopped and buried without loss of the drain behind it, and nothing upstream of its flap gate shall be credited as storage below that level. No setback from a glacial lake or along a GLOF corridor exists in law (NEER reading); the "High-risk Zoning" of floodplains below glacial lakes in the PPR is a proposal, not a rule (Chapter 7).
- (e) The West Bengal reaches. The Teesta below Melli and the Rangit's lower reach form or cross the State border, and the West Bengal edition of this Manual governs those reaches. Its levels are named here only for that reason, from SANDRP's transcriptions of CWC data (as reported): Sevoke, HFL 147.3 m (12 October 1973) and 145 m on 4 October 2023; Coronation bridge, 156 m (1973) and 149.2 m on 4 October 2023; Domohani, HFL 89.3 m (4 October 1968); Singla Bazar on the Rangit, HFL 311 m (5 September 1980), inactive since 2021; and the Teesta barrage, whose release in October 2023 was reported as "more than 8000 m³/s" (as reported). None of them is a tailwater for any Sikkim town. For an outfall in Sikkim near the border, a level from that edition, or from a CWC site downstream transferred upstream, is a lower bound on the downstream boundary of the model of item (b), not the level at the outfall.
- (f) Pokharis as receiving storage. For an outfall to a pokhari, directly or through a drain or jhora that ends in one:
- Levels. No level on a stated datum, and no outlet or overflow level or stage–storage relation, was found for any pokhari in the State, and no pokhari that receives a town's drains was named in the sources [TBC]. Storm water shall not be discharged to a pokhari without the written consent of its custodian (Chapter 7) [TBC]. Until the custodian gives a level, the tailwater is the level at which the pokhari spills, from its outlet or overflow crest surveyed and tied to a Survey of India benchmark, plus the head over that crest needed to pass the 1% AEP inflow, and not less than the highest level recorded at it; the pokhari starts every design storm full to its outlet, and an outfall below the tailwater is closed for the whole storm (Clause 5.9.4) (set by this Manual).
- Storage first, not a detention pond. A pokhari is kept as storage under Chapter 7; no storage below its spill level is credited to a project, and no natural pokhari shall be converted into a detention pond. Every drain that discharges to a pokhari shall pass a debris and solid-waste trap and a sediment trap (Clause 6.3.6(f) and Chapter 8) before it reaches it, and no drain that carries sewage shall discharge to one (Clauses 6.3.6(e) and 8.9).
- No glacial lake. A glacial lake keeps its own name, even where the name contains "Pokhari" (Bhalay Pokhari, Doodh Pokhari), and is never a receiving waterbody or storage under this item: it is a hazard source under Clause 2.3.6(i) and Chapter 7, and no outfall shall be designed to one.
- (g) Consents and lines. No outfall structure, gate, pumping station or drain shall be built in the bed or bank of a river or jhora, or in a flood-protection work, without the consent of its owner under the drain and jhora register (Clause 6.9): for works in or on a river, that of WRD, whose procedure for such a consent was not found during research [TBC]; for any work in the river bank of a river in the Schedule of the Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988, that of the Forest Department, under whose control the river bank lies "as if it were a forest" (s.29(9)), unauthorised occupation of which is an offence (s.30); within a municipal area, that of the urban local body for its drains and jhoras, which vest in it where they lie on public land other than forest land and which it "shall protect … whether on a public land or on a private land" (Sikkim Municipalities Act, 2007, ss.172 and 189(1)), and which must provide a safe outfall (s.187); and for a road drain or culvert, that of the road's owner, the Roads and Bridges Department (PWD), NHIDCL or BRO. The operator of a reservoir gives its levels and release records under item (c); that is data, not an approval. A jhora outside municipal limits or on forest land has no named owner (NEER reading); the designer shall record that on Form 5-1 and in the register and obtain the consent of the landholder and, on forest land, of the Forest Department (set by this Manual). Where consent is given, the discharge shall not exceed the rate the consent allows; the tailwater is the higher of the channel's design water level as its owner states it in writing and its level in the coincident case of Clause 5.8.4, computed from all the storm water it receives and with its downstream boundary at the level of items (a) to (f); the channel shall be taken in its present condition, net of silt, boulders, slide debris, encroachment and solid waste and with its narrowest section as surveyed, and a widening, lining or training that has been proposed but not completed shall not be counted; and the outfall shall have a flap gate (Clause 5.11) where the design water level or the computed level is above the outfall invert. The designer shall also check the outfall against the lines that bind at the time of design (Chapter 7): the river bank of a scheduled river, "an area of sixty metres on either side of such river or area within high flood level mark, whichever is less" (1988 Act, s.29(1)), which is a maximum, not a minimum, and whose high-flood-level line has moved since October 2023; any closure of a river bank notified under s.32 of that Act; and any limits of a jhora notified by the State under s.173 of the Municipalities Act, of which none was found. No statute or regulation sets any line along a jhora: the 2021 stability zones ask only for training "with safe distance", which is not defined (NEER reading). No setback along the Teesta was found to have been notified after October 2023 (NEER reading). The Manual's own corridor (Clause 7.4) is a proposal of this Manual, wider than any line that binds on a jhora.
No pump, gate or dam operation that helps drainage, such as pumping a drain down before a storm, lowering a reservoir before a storm, closing a gate late or opening dam gates early, shall be assumed unless the operator's written records show it. Where the outfall invert is below the tailwater of this clause, the outfall shall have its own flap gate (Clause 5.11) and, where the outfall-closed check requires it, pumping (Clause 5.12), with the pumped volume included in the routing of the drain, the reservoir or the river (Clause 5.12.3). Pumping shall not be used to move water into a pokhari, a reservoir or another catchment without the consent of its custodian, or onto a slope.
Commentary. In large continental river basins, a site storm and a river flood are usually treated as roughly independent. That is the basis of tables of coincident frequencies such as FHWA HEC-22 Table 7.3. Sikkim's rivers break that assumption in two ways. The trunk flood need not come from local rain at all: on 3–4 October 2023 the Teesta rose to new highest levels at Khanitar and Melli (Clause 5.8.5(b)) after the South Lhonak lake drained, while the rain over the lake was 29–39 mm over eight days in the ERA5 reanalysis, with about 5 mm and 14 mm on 3 and 4 October (Sattar et al., 2025); the cause is disputed (Clause 5.8.5(d)). And the tributary floods and the town storms come together: in June 2024 rain over Mangan district brought landslides and floods on the tributaries, with 250 mm statewide in 1–13 June, "54% above the normal 162 mm", and the Sangkalang bridge collapsed (as reported); and the jhoras of a ridge town run full in the same hour as the khola (खोला; a river or large stream) below them. The two cannot be treated as independent, and a local storm can fall before, during or after the river peak. Clause 5.8.4 therefore pairs a design event on one side with a 10-yr event on the other, in the same way as Clause 2.12(b). This pairing has no direct precedent. It is more severe than an independence assumption would give.
Clause 5.8.3 reflects the hydropower dams on the Teesta and its tributaries, among them Teesta-III at Chungthang, Teesta-V at Dikchu, Teesta-VI, Chuzachen, Dikchu, Rongnichu, Jorethang, Tashiding and Rangit-III (State affidavit of February 2026 to the National Green Tribunal). In October 2023 they became a cascade: the flood destroyed the Teesta-III dam ("The 60 m high dam was destroyed"), and downstream dams were affected, among them Teesta-V and Teesta-VI and the Teesta Low Dam projects (Sattar et al., 2025, which names a "Teesta Low Dam VI", probably TLDP-IV (NEER reading)); NHPC estimated that the bed rose by about 6.00 m at Teesta-V and 2.00 m at Teesta-VI (PPR annexed to the State's affidavit of 28 February 2026). A committee constituted by the National Dam Safety Authority is reported to have put the inflow at Teesta-III at about 10,000 m³/s against a spillway capacity of 7,500 m³/s (as reported). Earlier, a release from the Dikchu project in 2017 was reported to have come without warning (as reported), and the High Court of Sikkim closed the public-interest case that followed with the direction "that the hydropower projects in Sikkim shall ensure strict compliance of the safety guidelines" and that the authorities "undertake periodic inspection and review" (WP(PIL) 4/2017, judgment of 1 March 2021); the National Green Tribunal sought data on all Teesta dams in January 2026 (OA 171/2023, order of 13 January 2026). No FRL, MWL, spillway rating, operating rule, release record or datum was obtained for any dam, and no rule linking their operation to the drains above or below them was found during research [TBC]. Until they are available, an outfall in a reservoir reach is sited above the October 2023 flood mark, and the spillway design capacity, or failing that the unattenuated 1% AEP inflow, applies as the release, with the flow of the catchment below the dam as it occurred in the same event (Clause 5.8.5(c)). The river levels used in this Manual come from SANDRP's transcriptions of CWC data; their datum and gauge zero are to be confirmed with CWC [TBC].
Clause 5.8.5 is set by this Manual. In Sikkim the tailwater at a town outfall is set not by the tide but by a jhora that no one gauges and whose bed moves, by a valley-floor river on a bed that a glacial-lake outburst raised by metres, or by a reservoir and the releases below its dam, and no document found during research gives a design level for any of them. No design standard for any town drain in the State was found: the Sikkim Building Construction Regulations, 1991 require a plinth drain "leading to the road side drain or to adjoining permanent drains or jhora" (reg. 25(iv)) but give no design storm, return period or runoff coefficient (Chapter 4); the drainage and landslip-protection projects of Gangtok's City Development Plan (2006) "were not taken up" (CAG, Report No. 3 of 2016); and no design storm was seen for the drainage and jhora-training works of GSCDL or for the stormwater drains of the ADB-funded Sikkim Integrated Urban Development Project (Chapter 6). The State has no floodplain zoning law, and no flood level has been published for any town (Chapter 7).
The first case is the free outfall to a jhora. Most outfalls of the ridge towns fall from a slope to a jhora, so item (a) is the general rule on the ridges. Its design case is a free outfall because there is no river tailwater there, but it does not stop at the outfall: the energy dissipator, the lined path to the jhora and the check of the jhora to the next confluence or trained reach are what keep the water off the slopes. The 2021 stability zones already treat a slope beside an "Untrained jhora/ erosional potential jhora" as unstable (zone 4), and s.187 of the Municipalities Act already makes the flooding of "any area surrounding the outfall" a municipal concern; item (a) turns both into a check that a designer can make. The check reach ends at the next confluence with a channel of at least equal catchment, at a river or at a trained reach, because there the project's flow is a small part of the whole or the channel has been built to carry it; it is a check of capacity and stability, not of level. The design level, where the jhora can rise above the invert, comes from a study and from flood marks, as for the ungauged hill streams of the mountain editions of this series, with the bulking and blockage of Clause 6.3.6; and the invert stands 0.5 m above the highest bed level surveyed downstream, a margin set by this Manual for the aggradation that a bouldery bed can show in a single storm. The lock is the storm and the jhora's recession, and not less than 24 hours, because the jhoras are small and fall within hours of the rain stopping, while the storms that fill them can last for days, as in October 1968 and June 2024 (as reported; Chapter 1); where the longer storms of Clause 5.10.2 are run, the lock lasts for all of them. Item (a) also keeps outfalls away from springs (dhara), the main source of water in rural Sikkim (Chapter 8).
The second is the valley floor. Item (b) is the interim valley-floor rule of this Manual. It takes the higher of the highest level CWC has recorded and the surveyed mark of October 2023, because those are the only two levels a designer can find, and because both may now understate the river: the bed rose by about 2 to 7.4 m along the trunk in that flood (NHPC's estimates), so a highest flood level recorded before 2023 stands on an older, lower bed, and the 2023 marks record a cascade, not a rainfall flood. A hydraulic model is required where neither level exists, as at Rangpo, and its result governs wherever it is higher. The Melli readings conflict; the check uses the higher, 228.0 m, because it is the one that SANDRP's own arithmetic ("2.75 meter higher" than 225.25 m) supports, and because a check that rests on the lower of two unresolved values can put an outfall below a level the river has already reached. Inverts are set above the surveyed post-2023 bed for the same reason. The lock is the whole 72-hour storm, and not less than 72 hours, because the rivers that fill the valley floors are fed by storms that last for days over a catchment of more than 10,000 km² (the Tista, 10,616.74 km², FER 2(a)); 250 mm fell statewide in 1–13 June 2024 (as reported), and the October storm of 1968 lasted four days (as reported). No stage record of the Teesta was analysed for this Manual, so the lock is a minimum, and a stage record, once obtained, governs. Flap gates are required wherever a river can close an outfall, and the owner of the gate is named because no gated storm outfall was found in the State and nobody yet holds one.
The third is the reservoir and its release reach. A reservoir at its full level passes its inflow over its spillway, and its level rises above FRL by whatever head the flood needs. Item (c) therefore follows the reservoir rule of the North-East hill editions of this series: the MWL, or FRL plus the design-flood surcharge, with an outfall below it treated as closed for the whole of the 72-hour storm. No FRL or MWL of any dam in the State was found, so until the operator gives them an outfall in a reservoir reach is sited above the October 2023 flood mark, and where it cannot be, it takes the surveyed shore line or spillway crest plus 0.5 m, the freeboard that this Manual uses for floor levels (Clause 6.11.1), as a floor and not as an estimate of the surcharge [TBC]. No release record was obtained either, so the spillway capacity, and failing that the unattenuated 1% AEP inflow, stands in for the largest release; that is conservative by design, because a tailwater set too low floods a reach, while one set too high only costs storage. Notices and warnings are not credited because a release from the Dikchu project in 2017 was reported to have come without one (as reported), and because the High Court's direction of 2021 is on the projects' safety, not on the levels of the drains below them.
The fourth is the GLOF corridor. Item (d) keeps the glacial-lake hazard out of the rainfall design and puts it into siting, because no drain can be sized for it: the October 2023 outflow at the lake was "equivalent to a return period exceeding 200 years", and at Chungthang the discharge peaked within about 6 minutes of the flood's arrival (Sattar et al., 2025), and water alone equalled "a 1–100 year meteorological flood at Chungthang" while the sediment made the total far higher (same work). The cause is disputed between the State's affidavit and the NDSA committee, and item (d) does not depend on it. Siting assets above the 2023 flood and aggradation level and outside a mapped GLOF path is the only rule that protects them; no setback for the cascade exists in law, and the Manual sets none of its own.
The fifth is the West Bengal reaches, the sixth the pokharis and the seventh the consents and lines. Item (e) names the Teesta's levels below Melli only to leave them to the edition that governs them, and makes them a lower bound on a model's boundary, not an outfall level. Item (f) treats a pokhari as storage that starts full, because no pokhari in the State has a published level, and keeps glacial lakes out of it, because a glacial lake is a hazard, not a store. Item (g) asks for the owner's consent and design level because a design that discharges to a channel cannot be checked without them, and because the drains belong to several bodies and no notification divides them (Chapter 6, Clause 6.9). The lines of item (g) decide where an outfall can be built, not its level: the 1988 Act's river bank is "sixty metres … or area within high flood level mark, whichever is less", so on an incised reach it can be a few metres wide; no line exists along a jhora; and the Manual's own corridor (Clause 7.4) is its proposal, not the law.
5.9 Joint-probability cases
5.9.1 Every element draining to a tidal or backwater-affected outfall shall be checked for the cases below. The most severe governs each design quantity: storage, water level, pipe size and pump capacity.
Table 5.2 — Joint-probability cases for tidal and riverine outfalls
| Case | Rainfall | Tailwater | Applies to | Basis |
|---|---|---|---|---|
| J1 | Minor-system design AEP, Tc to 24 h | MHWS + SLA (tidal curve) | Minor system | Clause 2.12(a); Clause 5.7.1 |
| J2 | 1% AEP, all durations of Clause 2.5.2 | HAT + surge + SLA | Major system, detention, tanks, pumped systems | Clause 5.7.1 |
| J3 | 10% AEP, 48 h | 1% AEP still-water level + SLA | Major system, detention, tanks, pumped systems | Clause 2.12(b) |
| J4 | Design AEP, 48 h (72 h reported) | Tidal curve per J1 with two 6 h lock windows (Clause 5.10) | All storage and every gated or tide-affected outfall | Clause 5.10 |
| R1 | Site design AEP | River at 10% AEP level | Riverine outfalls | Clause 5.8.4(a) |
| R2 | Site 10% AEP | River at design-AEP level | Riverine outfalls | Clause 5.8.4(b) |
5.9.2 For storage elements, the 48- and 72-hour storms shall be run with the J2 and J3 tailwaters (Clause 2.5.3).
5.9.3 For tidally influenced riverine outfalls, R1 and R2 shall be run with the river model's downstream boundary at the J1 tidal curve. The Authority may also require them at J2.
5.9.4 Where tailwater is constant at a level above the outfall invert for the whole storm, the case is treated as a fully closed outfall. Storage and pumps shall then handle the full storm volume.
Commentary. Clause 2.12 sets two joint cases. Case (a) is design rainfall with MHWS plus the sea-level allowance. Case (b) is the 10-yr, 48-hour storm with the 1% still-water level. This Manual adds HAT plus surge for major-system design (Clause 5.7.1). Case J2 combines these. J4 is the outfall-closed check, which tests the timing of tide against the storm rather than a single level. Rainfall and surge share a cyclone cause, so they cannot be treated as independent (Clause 2.12 commentary). These cases are simple surrogates, to be replaced when a statistical joint analysis of IMD rainfall and tide-gauge records is adopted.
5.10 Outfall-closed (tide-locked) storage check
5.10.1 Where it applies. The check applies to:
- every storage facility;
- every minor- and major-system element; and
- every pumped system
whose outfall invert is below HAT + surge + SLA, or which drains to a reach subject to tide-lock or sand-bar closure (Clause 5.13).
5.10.2 Storm. Use the 48-hour design storm built per Clause 2.9.2 (peak day last), at:
- the AEP of the element: 1% AEP for detention, tanks and the major system; the minor-system AEP for minor drains; and
- AMC III.
The 72-hour storm shall also be run and reported.
5.10.3 Lock windows. Unless a site study under 5.10.6 gives otherwise:
- (a) the outfall is closed for two consecutive lock windows of 6 hours each, centred on two consecutive high tides of the local tidal curve. For a semi-diurnal tide, the window starts are therefore about 12.4 hours apart.
- (b) During each lock window, gravity discharge is zero.
- (c) Between lock windows, gravity discharge is computed against the J1 tidal curve, including the head loss of the flap gate and any non-return valve.
- (d) The first lock window shall be placed so that it is centred on the peak 1-hour block of the final 24 hours of the storm. A second run with the first window starting at that peak block shall also be made. The more severe governs.
5.10.4 Requirement. Storage plus pumping (where provided) shall hold the inflow so that, throughout the check:
- (a) the maximum stage in any detention facility stays below its emergency spillway crest, so the spillway does not operate. Where the outfall-closed stage is higher than the 1% AEP maximum water level of the free-outfall design, it becomes the facility's 1% AEP maximum water level for Clause 4.9.3, and the spillway crest, freeboard and wall height are set from it;
- (b) the maximum stage in the minor and major systems meets the Chapter 6 limits: building floor levels, and street depths of no more than 150 mm at the crown and no more than 350 mm at the deepest point; and
- (c) no property connection surcharges above the lowest opening it serves, or a non-return valve is fitted under Clause 5.11.
In volume terms, over each lock window and the full storm:
V_inflow ≤ V_storage available + V_pumped + V_gravity (between locks)
This shall be demonstrated by routing, not by a single volume balance. The release from each facility after a lock window ends may exceed the release caps of Chapter 4, because the facility is emptying into a drain that has just reopened. That release shall be included in the downstream analysis (Clauses 5.4 and 5.9).
5.10.5 Drawdown after the storm. After the second lock window, the storage shall drain under the J1 tidal curve. The drawdown requirement of Clause 4.7 shall be met, with pumping where gravity cannot meet it (Clause 5.12).
5.10.6 Site study. A longer or shorter lock may be used where a site study gives a time series of still-water level for the design case. The study may use a calibrated hydrodynamic model, gauge records of past events, or a surge hindcast. Locks shorter than the default require the Authority's approval. A longer lock shall be used where:
- sand-bar closure (Clause 5.13) or river backwater (Clause 5.8) keeps the outfall closed for longer; or
- the gauge record shows tailwater above the outfall invert for more than 6 hours per tide in comparable past events.
Figure 5.3 — Outfall-closed check: 48-hour storm with the peak day last (Clause 2.9.2), tailwater of astronomical tide plus surge, two 6-hour design lock windows, and the resulting stage upstream of the flap gate. Illustrative — not design values. Original drawing for this Manual, adapted from the tidal tailwater and joint-probability concepts of MoHUA/CPHEEO Manual on Storm Water Drainage Systems (2019), Part A, §6.3.6.
Commentary. The outfall-closed check is the distinctive Sikkim requirement in this Manual. In Sikkim it applies where an outfall is shut not by the tide but by a jhora that has risen over the outlet or buried it in boulders, slide debris and waste, by the Teesta, the Rangit or the Rongni Chu held high on a valley floor, or by a reservoir at its full level or the releases below a dam. The storms that raise the rivers last for days: the October storm of 1968 brought four days of rain over Darjeeling and Sikkim, and 250 mm fell statewide in 1–13 June 2024 (both as reported); Gangtok's wettest month on record, June 1997, brought 1,281.3 mm (IMD). How long the Teesta stood above any outfall was not found, and no stage record was analysed for this Manual [TBC]. The jhoras of the ridge towns rise within minutes and fall within hours, but they can block an outlet with boulders and waste in a single storm. That is why Clause 5.8.5 replaces the two 6-hour windows described below with a lock of the storm and the jhora's recession, and not less than 24 hours, at a ridge-town outfall below its design level; the whole 72-hour storm, with the outfall closed for not less than 72 hours, on the valley floors; and not less than 72 hours on a release reach, with a closure for the whole storm below the design level of a reservoir or a pokhari. A rate rule cannot help when there is no outlet: an orificed basin behind a closed gate simply fills.
The default of two consecutive 6-hour locks has no direct precedent. It represents gravity outfalls failing to discharge for about half of each tidal cycle around the two high tides nearest the storm peak. Figure 5.3 shows why both windows matter. The first lock catches the storm peak. The second arrives before the storage has drained, so the stage rises again.
Placing the first window on the rainfall peak is deliberately unfavourable. Cyclone rainfall and surge share a cause, and Clause 2.12 already treats them as dependent. The check replaces neither the J2 and J3 level checks nor the downstream analysis; it adds a test of timing and volume.
5.11 Flap gates, tide gates and non-return valves
5.11.1 Where required. A flap gate, tide gate or equivalent non-return device is required on every outfall whose invert is below the 1% AEP still-water level (Clause 5.7.3). It is also required on outfalls into irrigation channels under Clause 5.8.5.
5.11.2 Hydraulics. The design shall include:
- the gate's head loss and opening head, from the manufacturer's certified head–discharge curve; and
- the reduction in effective outfall capacity when the gate is partly open.
Gates shall not be assumed to seal perfectly in the outfall-closed check unless they are tested.
5.11.3 Construction.
- (a) Gates, hinges and seats shall be of corrosion-resistant materials suitable for seawater (Clause 4.12.5).
- (b) The gate shall be set so that sand, silt or debris on the downstream side cannot hold it shut or open. Where the bed is mobile, the gate invert shall be raised above the bed, or the approach shall be protected.
- (c) A trash screen shall be provided upstream where the gate could be jammed by debris.
- (d) A stop-log slot or penstock shall be provided upstream for maintenance isolation on outfalls larger than 600 mm.
- (e) The gate chamber shall be accessible at all tides, with its access above HAT + surge + SLA.
5.11.4 Non-return valves on property connections. A non-return valve, or a backwater valve with an accessible cleaning eye, is required on every property drainage connection where the lowest opening served is below:
- the major-system tailwater (J2) at the point of connection; or
- the maximum stage in the outfall-closed check (Clause 5.10).
Basement drainage shall in addition be pumped to a level above both, with its own non-return valve.
5.11.5 Inspection. Gates and valves shall be inspected and operated:
- before 31 March each year;
- after every event in which they closed against a storm flow; and
- as set in the maintenance plan (Chapter 10).
Commentary. The requirement for gates below the 1% still-water level is set by this Manual. The construction details follow common coastal-drainage practice. A gate that is jammed open by debris lets the tide into the drain. A gate held shut by a sand bank turns a gravity outfall into a dead end. In Sikkim the outfalls do not cross a beach. Most of them fall freely to a jhora, and no flap-gated or pumped storm outfall was found in the State during research [TBC]; but the outfalls of the valley floors at Rangpo, Singtam, Melli, Majitar, Jorethang and Dikchu need flap gates under Clause 5.8.5(b), and there a gate jammed open by gravel, boulders or slide debris lets the river into the town's drains, and a gate buried by a rising bed turns the outfall into a dead end. The flood of October 2023 raised the Teesta's bed "by an average of 7-8 meters" (Project Prefeasibility Report annexed to the State's affidavit of 28 February 2026) and buried parts of Rangpo, "burying buildings and automobiles" (Sattar et al., 2025): a gate set on the old bed would now lie under it. Other outfall reaches lie below hydropower dams, where a release from the Dikchu project in 2017 was reported to have come without warning (as reported); no operating rule or release record of any dam was found, and no rule linking the operation of any dam to the levels of the drains above or below it [TBC]. The dams are held by their operators, while the drains that reach the rivers below them belong to the Gangtok Municipal Corporation and the other urban local bodies, the Roads and Bridges Department (PWD), NHIDCL and BRO, and the river banks of the scheduled rivers to the Forest Department, and no notification divides them (Clause 6.9). A gate and the drains behind it can therefore belong to different bodies, and the drain and jhora register of Clause 6.9 names the owner of each gate. The 31 March inspection date is set ahead of the monsoon.
5.12 Pumped outfalls
5.12.1 When required. Pumping shall be provided where gravity discharge cannot meet:
- the outfall-closed check of Clause 5.10;
- the drawdown requirement of Clause 4.7; or
- the J2 and J3 cases.
Pumping shall not be used where a gravity solution meets these requirements.
5.12.2 Capacity.
- (a) The duty pumps together, with the storage provided, shall pass every case of Clause 5.9 (including J4), demonstrated by routing.
- (b) Standby capacity at least equal to the largest duty pump shall be installed (duty + 1 standby as a minimum).
- (c) Pump capacity shall be stated at the static head for the J2 tailwater, not at mean tide.
5.12.3 Effect on the receiving water. Pumped discharge to a river, canal or creek shall be included in the river or creek level analysis of Clause 5.8. Pumping that raises the receiving water level above the acceptance criteria of Clause 5.5 elsewhere is not permitted.
5.12.4 Power supply. Pumping stations shall have either:
- two independent power supplies; or
- standby generation for 100% of the duty capacity, with on-site fuel for at least 72 hours of duty operation.
Changeover shall be automatic.
5.12.5 Flood immunity. Electrical panels, control equipment, generators and fuel storage shall be set above the higher of:
- the 1% AEP flood level + 0.5 m; and
- HAT + surge + SLA + 0.5 m.
Access to the station shall remain usable in the 1% AEP event.
5.12.6 Discharge arrangement. Rising mains shall discharge:
- over a level above the J2 tailwater; or
- through a non-return valve and a flap gate.
The arrangement shall prevent back-siphoning.
5.12.7 Controls and monitoring. Each station shall have:
- automatic level control;
- remote alarms for high level, pump failure and power failure, sent to the operator; and
- a level and run-time log kept for at least 5 years.
Wet wells shall be sized to keep pump starts within the manufacturer's limits.
5.12.8 Screens. Inlet screens shall be provided with a cleaning method that works during a storm (a mechanical rake, or duplicate screens).
5.12.9 Testing. Every pumped outfall shall be test-run at full duty, including on standby power, before 31 March each year. Private pumped systems shall be covered by a registered maintenance declaration (Chapter 10).
Commentary. Duty + standby, 72 hours of fuel and flood-immune electrics have no single direct precedent and are set by this Manual. The 72-hour fuel figure matches the longest mandatory design storm (Clause 2.5.2). A pump station that depends only on grid power can stop exactly when it is needed, because supply to flooded areas is often switched off for safety. Singapore's April 2025 amendments added annual maintenance declarations for pumped detention tanks (PUB Addendum No. 3). Clause 5.12.9 and Chapter 10 adopt the same approach. Clause 5.12.3 prevents pumping that simply moves water from one tide-locked drain into a tide-locked river.
5.13 Sand-bar closure of river mouths
5.13.1 Where it applies. This clause applies to outfalls into any river or creek whose mouth is subject to seasonal sand-bar closure. That includes the mouths of the coastal States (there is none in Sikkim: Clause 5.1.4), and any other mouth listed in Annex 5B.
5.13.2 Assumption at the start of the monsoon. The mouth shall be assumed closed by a bar at the start of the April–October season, at the crest level of the most recent pre-monsoon survey. This applies unless the Water Resources Department certifies that:
- a mouth-maintenance programme (dredging, bar cutting or training walls) has kept the mouth open at the start of each of the previous three monsoon seasons; and
- the programme is funded for the current season.
5.13.3 Tailwater with a closed mouth. With the mouth closed, the tailwater at the outfall shall be the higher of:
- (a) the tidal tailwater of Clause 5.7; and
- (b) the level in the river reach behind the bar, computed with the bar as a weir at its surveyed crest level. That level shall include the river flow of Clause 5.8 and the head needed to pass the flow over or through the bar.
5.13.4 No credit for emergency cutting. Bar cutting or breaching during the storm shall not be assumed in design, unless the Water Resources Department has a documented operating procedure, with equipment stationed for it. Where it does, the bar may be assumed lowered to the procedure's target level only after the time the procedure states.
5.13.5 Outfall-closed check. Where the closed-mouth level of 5.13.3(b) exceeds the outfall invert for longer than the default lock windows, the lock duration of Clause 5.10 shall be extended to that period.
Commentary. Sikkim has no coast and no river mouth, so Clause 5.13 does not apply in the State (Clause 5.1.4). Its nearest inland counterparts are the boulders, gravel, slide debris, silt and garbage that the jhoras leave at an outfall or a gate, and the bed that the Teesta raised in October 2023, which buried parts of Rangpo, "burying buildings and automobiles" (Sattar et al., 2025). Gangtok's waste agency is contracted for the "Clearing of Jhoras" and barred from dumping "along Footpath, Roadside and Jhoras" (GMC, Memo No. GMC/6727/III/2024/OL/01, 8 October 2024), and the building rule already forbids dumping spoil in "drains, gullies and jhoras" (SBCR 1991, reg. 22). A flap gate held open or shut by gravel, debris or waste, an outlet buried by a rising bed or left hanging by scour, or a gate that cannot be moved, turns a designed outfall into a dead end or a back-flow path. No rule linking the operation of any gate or dam in the State to the levels of the drains above or below it was found during research [TBC]. Clause 5.8.5 deals with both by setting outfalls above the surveyed range of bed movement and by giving no credit for a gate operation or a storage that the operator's records do not show. Clause 5.13.2 has no direct precedent. It puts the burden of proof on showing that the mouth is open rather than assuming it.
5.14 Documentation
Every project subject to this chapter shall submit a Downstream and Tailwater Report (Form 5-1). It shall contain:
- a plan of the analysis extent showing:
- the site;
- each analysis point with its contributing catchment area and the site's percentage of it; and
- the end point and the reason it was chosen (Clause 5.3);
- the model description:
- software and version;
- the network schematic, with survey sources for the drains and crossings;
- land use and CN for off-site areas;
- any upstream detention included; and
- calibration or validation evidence where available;
- for each analysis point, AEP and duration, the existing and with-project:
- peak flow;
- time to peak;
- maximum water level and velocity; and
- duration of inundation (Clause 5.4);
- the comparison against Clause 5.5, with each failure identified and the remedy adopted;
- the tailwater derivation:
- tide-table edition and port;
- MHWS, HAT and MSL relative to chart datum;
- the datum connection to the Survey of India benchmark and the project datum;
- surge source and value;
- SLA; and
- river levels and their sources (Clauses 5.6 to 5.8);
- the joint-case table of Clause 5.9 with results;
- the outfall-closed check (Clause 5.10):
- storm and lock alignment;
- stage hydrographs; and
- the volume balance for each lock window;
- a schedule of flap gates, tide gates and non-return valves, with certified head–discharge data (Clause 5.11);
- pumped outfall design, power supply, flood immunity and controls, where provided (Clause 5.12);
- the sand-bar assumption and supporting WRD certification, where relevant (Clause 5.13); and
- inspection and maintenance requirements for Chapter 10.
Small sites under Clause 5.3.4 shall submit Form 5-2 (Simplified Downstream Statement) instead.
References (chapter)
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §6.3.6 and Table 6.2 (coastal tailwater; +0.3 m climate allowance). https://web.archive.org/web/2024/https://mohua.gov.in/upload/uploadfiles/files/VolumeI-Part%20A-Engineering-Design.pdf
- MoHUA / CPHEEO (2013). Manual on Sewerage and Sewage Treatment Systems (pumping stations).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.5, ten-percent downstream analysis). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Vol. 1 (Standard #8) and Vol. 2 §3.1.9. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- MARC. The Evolution of Regional Stormwater Design Standards. https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Sattar, A. et al. (2025). The Sikkim flood of October 2023: Drivers, causes and impacts of a multihazard cascade. Science, doi:10.1126/science.ads2659 (accepted manuscript, White Rose eprint 224098: the outflow peaks at the lake and at Chungthang, the eroded volume, the burial of Rangpo, the ERA5 rainfall over the lake, the downstream dams affected).
- Government of Sikkim. Additional affidavit of Respondent 1 of 28 February 2026 in O.A. No. 171 of 2023 (EZ), National Green Tribunal, with the Project Prefeasibility Report "GLOF Risk Mitigation in Lhonak Valley, Sikkim" (the bed risen "by an average of 7-8 meters"; NH-10 "prone to submergence and subsidence"; NHPC's estimates of the bed rise at TLDP-IV, TLDP-III, Teesta-V and Teesta-VI; Toong Naga; the list and status of the hydropower projects; NDMA's 40 high-risk and 16 very high-risk glacial lakes; Shako Chho; "High-risk Zoning" as a proposal) and the PDNA summary, https://www.greentribunal.gov.in/sites/default/files/news_updates/Additional%20affidavit%20on%20behalf%20of%20R-1,%20State%20of%20Sikkim,%20page%201038-1178.pdf ; and the State's affidavit of 5 April 2024 in the same case (the flood attributed "primarily to a cloudburst").
- SANDRP. Transcriptions of CWC data for the Teesta basin sites (Khanitar, Melli, Singtam, Majitar, Ranipool, Bakcha, the upstream sites that stopped on 3 October 2023, and the West Bengal sites), as reported; the Melli reading of 228.0 m in a CWC daily bulletin of 2024 seen only as a search snippet; and press reports on Singtam's danger level (Deccan Herald) and on Melli on 4 October 2023 (EastMojo), as reported. The datum and gauge zero of each gauge are to be confirmed with CWC [TBC].
- Central Water Commission (1991). Flood Estimation Report for North Brahmaputra Subzone 2(a), NB/18/1991 (the Tista, 10,616.74 km², p. 29).
- High Court of Sikkim. WP(PIL) No. 4 of 2017, In re: Release of water from Dikchu Hydelpower Project, judgment of 1 March 2021, https://hcs.gov.in/hcs/hg_orders/202600000042017_37.pdf (read from a Wayback Machine copy); and the 2017 release as reported (Summit Times, 28 May 2017).
- ThePrint, 1 October 2024. "Sikkim govt, central panel split over what caused 2023 floods …" (the NDSA-constituted committee: GLOF, about 40 million m³, inflow about 10,000 m³/s against a 7,500 m³/s spillway; as reported), https://theprint.in/india/sikkim-govt-central-panel-split-over-what-caused-2023-floods-at-stake-is-rs-2500-cr-insurance-claim/2291910
- The Sikkim Municipalities Act, 2007 (Act 5 of 2007), as amended to 2026 (ss.2(24), 172, 173, 187, 189 and 193), https://prsindia.org/files/bills_acts/acts_states/sikkim/2007/2007SK5.pdf
- The Sikkim Forests, Water Courses and Road Reserve (Preservation and Protection) Act, 1988 (Act 6 of 1988), as amended by Act 8 of 2000 (ss.2(m), 29, 30, 32 and the Schedule), https://prsindia.org/files/bills_acts/acts_states/sikkim/1988/1988SK6.pdf
- The Sikkim Building Construction Regulations, 1991 (UD&HD Notification No. 29(202)UD&HD/90/295, 19 March 1991), as amended in 2000 and 2001 (regs. 22, 25(iv) and 35), read from a copy hosted by Sikkim Manipal University, https://smu.edu.in/img/content/dam/manipal/smu/IQAC/SDG/documents/BUILDING%20STANDARDS.pdf ; and Department of Mines and Geology Notification No. 17/DMG/20-21, 19 March 2021 (stability zones), read as Annexure R/2 to the State's counter-affidavit in O.A. No. 5 of 2022 (EZ), National Green Tribunal, https://www.greentribunal.gov.in/sites/default/files/news_updates/Counter%20Affidavit%20on%20behalf%20of%20R-,4,7,9%20in%20OA%205%20of%202022%20(EZ)%20(Dr.%20BINA%20BASNETT%20vs%20State%20of%20Sikkim%20&%20Ors.).pdf
- Gangtok Smart City Development Ltd. Reply affidavit in O.A. No. 38 of 2022 (EZ), National Green Tribunal ("landslides are caused mainly due to loose soil by spring water generated at natural Jhora"), https://www.greentribunal.gov.in/sites/default/files/news_updates/Reply%20Affidavit%20filed%20by%20R-2,%20GSCDL,%20page%20698-1006.pdf
- Government of Sikkim. Six-monthly report in O.A. No. 606 of 2018, National Green Tribunal (GMC's waste-agency contract, Memo No. GMC/6727/III/2024/OL/01, 8 October 2024), https://www.greentribunal.gov.in/sites/default/files/news_updates/SIX%20MONTHLY%20REPORT%20BY%20GOVT%20OF%20SIKKIM%20IN%20OA%20NO.%20606%20OF%202018%20FOR%20STATE%20OF%20SIKKIM%20(COMPLIANCE%20OF%20MSW%20MGT%20RULES,%202016%20AND%20OTHER%20ENVIRONMENTAL%20ISSUES).pdf ; and the State's affidavit of 19 December 2025 in E.A. No. 35 of 2023 in O.A. No. 673 of 2018 (the Zone III sewerage, "Pollution abatement of Rani chu through Ro-Ro Chu"), https://www.greentribunal.gov.in/sites/default/files/news_updates/AFFIDAVIT%20BY%20STATE%20OF%20SIKKIM%20IN%20EA%20NO.%2035%20of%202023%20IN%20OA%20NO.%20673%20of%202018%20News%20item%20published%20in%20the%20Hindu.pdf
- Comptroller and Auditor General of India. Report No. 3 of 2016 (Economic Sector, Sikkim), Chapter II (the Gangtok CDP's drainage and landslip works "not taken up"), https://www.cag.gov.in/uploads/download_audit_report/2017/Chapter_2_Economic_Sector_Sikkim_Report_No_3_of_2016.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012) (Gangtok's highest monthly total, June 1997).
- Press reports on the Mangan district storm of June 2024 (Business Standard, https://www.business-standard.com/india-news/heavy-rain-landslides-kill-6-in-indias-sikkim-2000-tourists-stranded-124061400418_1.html ; the statewide 250 mm of 1–13 June from a humanitarian situation report), on the October 1968 floods (https://en.wikipedia.org/wiki/1968_Sikkim_floods), on the Teesta barrage release of October 2023, and on the restoration of Teesta-V (all as reported).
- Survey of India. Tidal Predictions: Geodetic and Research Branch. https://www.geographyandyou.com/survey-of-india/tidal-predictions-geodetic-and-research-branch-survey-of-india
- GLOSS. India national report (tide-gauge network and datums). https://gloss-sealevel.org/gloss/gloss/sites/gloss/files/publications/documents/india_ge9.pdf
- Adani Ports (2025). Tide Table 2025, Dahej (notes on NHO INP-12 coverage and data sources). https://www.adaniports.com/-/media/Project/Ports/PortsAndTerminals/Dahej-Port/Marine-Documents/Tide-Table-2025-Dahej.pdf
- INCOIS. Storm-surge and swell-surge warning services. https://incois.gov.in/
- FHWA. HEC-22 Urban Drainage Design Manual (current edition), Table 7.3 (coincident frequencies).
- Purdue University JTRP (2023). Development of a Multiple Water Course Joint Probability Analysis Procedure for Indiana Watersheds, FHWA/IN/JTRP-2023/09. https://docs.lib.purdue.edu/jtrp/1820
- PUB Singapore (2025). Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
Annexes and forms
| Annex / Form | Content |
|---|---|
| 5A | Tidal datums (MSL, MHWS, HAT vs CD and Survey of India datum), surge allowances and 1% still-water levels by coastal segment |
| 5B | Major drains, riverine outfall reaches, and river mouths subject to sand-bar closure; map |
| 5C | Worked example: outfall-closed check for a hillside colony in Gangtok draining to a jhora |
| Form 5-1 | Downstream and Tailwater Report |
| Form 5-2 | Simplified Downstream Statement (small sites) |
Commentary. The drains of Sikkim's towns fail in places that site design does not see, and on the ridges the failure that matters most is not a flood. Gangtok, Pakyong, Namchi, Ravangla and Gyalshing stand on ridges and slopes of phyllite, schist and gneiss under thin soils and colluvium, and water put into those slopes moves them. The State's own building rule already grades sites by their jhoras: the stability zones of the Mines and Geology Department give zone 1 where the "Training of jhoras/drains have been completed and done properly (with safe distance)" and zone 4 where there is an "Untrained jhora/ erosional potential jhora", with "Gully erosion & collapse of jhora facing slope" (Notification No. 17/DMG/20-21, 19 March 2021). Gangtok Smart City Development Ltd (GSCDL) told the National Green Tribunal that "landslides are caused mainly due to loose soil by spring water generated at natural Jhora" (reply in OA 38/2022). So the first question at most outfalls on the ridges is not the level of the water below it but whether the water reaches a stable channel at all. The Sikkim Municipalities Act, 2007 already asks that question: the municipality shall provide "a safe and sufficient outfall … in such manner as may not cause any nuisance, either by flooding any part of the municipal area or any area surrounding the outfall" (s.187), and it makes a jhora a drain in law (s.2(24)). Gangtok's jhoras drain to the Rani Khola and the Roro Chu, a tributary system of the Teesta; none of them is gauged, and there is no river tailwater for most of the city or of the other ridge towns.
The valley floors are different. On the night of 3–4 October 2023 the South Lhonak glacial lake drained into the Teesta after a moraine collapse; the flood destroyed the Teesta-III dam at Chungthang, and at Rangpo, about 135 km downstream, it was "severely impacted by the debris, burying buildings and automobiles" (Sattar et al., 2025). The river bed "has risen by an average of 7-8 meters due to the accumulation of debris and silt from the flood" (the Project Prefeasibility Report (PPR) on GLOF risk mitigation in the Lhonak valley annexed to the State's affidavit to the National Green Tribunal, 28 February 2026). The cause of the event is disputed (Clause 5.8.5(d)). The Central Water Commission (CWC) set new highest flood levels on the Teesta on 4 October 2023 at Khanitar and at Melli, where two conflicting values are reported (Clause 5.8.5(b)), and no CWC level was found for Rangpo at all. Every flood level read before that night now stands on an older, lower bed. Below and between the hydropower dams the river is also an operator's: the High Court of Sikkim closed a public-interest case over a release from the Dikchu project with the direction "that the hydropower projects in Sikkim shall ensure strict compliance of the safety guidelines" (WP(PIL) 4/2017, 1 March 2021). And the outfalls belong to one body while the drains above them belong to others: the municipal drains and jhoras to the Gangtok Municipal Corporation (GMC) and the other urban local bodies, the river banks of the scheduled rivers to the Forest Department, the road drains to the Roads and Bridges Department (PWD), NHIDCL or BRO, the river works to the Water Resources Department (WRD), the reservoirs to their operators, and no notification divides them (Chapter 6, Clause 6.9). No document found during research sets a design level for any jhora, river or reservoir outfall in the State, or a design standard for any town drain. A detention tank that meets every release rate in Chapter 4 still fails if its overflow runs onto an unprotected slope, if the jhora below it cannot carry what it receives, or if the Teesta at Singtam stands above its outlet. This chapter makes these failure modes part of the design. Sikkim has no tidal outfall, so Clause 5.1.4 says which of the chapter's coastal provisions fall away and what takes their place.