Annexes to Chapter 7Waterbodies, Ponds (Pukurs) and Setbacks
These annexes support Chapter 7. They give the inventory field specification, the fixed-width setback table, a template operating rule, the desilting and restoration specification, a glossary of Bengali waterbody terms, and the three forms that Clause 7.15 requires. Where an annex cannot yet be completed it says so and gives the rule to use in the meantime. The forms are draft forms; the template and model text are for consideration by a competent authority and are not in force.
Annex 7A — Statewide waterbody GIS layer and inventory fields
Supports Clauses 7.3.1, 7.3.3 and 7.3.5 of Chapter 7.
To be prepared. This annex will contain the statewide GIS layer of waterbodies required by Clause 7.3.1, prepared by each Authority with PWD (WR) and the Revenue Department. It needs the land records of the Revenue Department, kept by district, sub-division, revenue circle and mouza (the plot numbering was not confirmed [TBC]), with each plot's land class under Appendix-I of the Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025, among them pukur ("Tank/Pond"), pukurpar ("Bank of tank"), dighi ("Large tank"), dighirpar ("Bank of large tank"), doba ("Ditch"), beel ("Watery land"), haor ("Big watery land"), chhara ("Streams"), lunga ("Flat lands between tillas"), khal ("Khal"), nala ("Water channel") and bandh ("Embankment"), including government (khas) land recorded as water; the list of 180 urban water bodies on government land that the ULBs geo-tagged for the National Green Tribunal in 2020, of which 30 were prioritised (as reported); the Agartala Municipal Corporation's zone-wise affidavit on the encroachment of water bodies before the High Court of Tripura (2017, as cited); PWD (WR)'s records of its embankments, sluices and anti-erosion works and its mapping of the Haora flood-plain zones; the land-use maps of the Master Plan for the Agartala Planning Area 2045 (text not read [TBC]) and the layouts of the Local Planning Areas; the records of the Wetland Authority of Tripura for Rudrasagar; in the TTAADC area, the land records of the District Council (not researched [TBC]); and each town's drain register (Chapter 6); the PWD (WR) and Gram Panchayat or Village Committee tank registers with FTL and MWL; surveyed levels on a common datum; the ISRO National Wetland Inventory and Assessment (NRSC); Survey of India topographic maps; and any list of waterbodies published under court directions. Until it is published, each Applicant identifies waterbodies from all the sources of Clause 7.3.3, with the larger extent governing, and records them on the Waterbody Sheet (Form 7-1).
The field specification below is complete. It is written so that every field the chapter asks for (Clause 7.3.1(a) to (g)) has a defined name, type and source, and so that the same fields can be filled from a project's Form 7-1.
7A.1 Layers
- WB_POLY — one polygon per waterbody: the Revenue record boundary (Clause 7.3.1(c)).
- WB_FTL — the surveyed FTL contour (tanks, lakes, ponds) or top of bank (channels), as a polygon or line.
- WB_MWL — the MWL contour of each tank, as a polygon.
- WB_FLOOD — the 1% AEP flood extent, where mapped (Clause 7.3.1(f)), with the floodway where delineated (Clause 7.6.1).
- WB_STRUCT — points for surplus weirs, sluices, regulators, inlets and drain outfalls.
- WB_LINK — lines for supply channels, surplus courses and the links between tanks in a cascade (Clause 7.3.1(e)).
- WB_ENCR — polygons of known encroachments, each with the date recorded (Clause 7.3.1(g)).
- WB_SETBACK — Zone 1 and Zone 2 polygons (Clause 7.4), derived from the layers above.
All layers shall carry the waterbody identifier (WB_ID) so that they can be joined. All levels shall be stated to one datum (Clause 7.3.5), named in the layer metadata.
Table 7A.1 — Attribute fields of the waterbody inventory (WB_POLY)
| Field | Type | Unit / domain | Required | Content | Clause |
|---|---|---|---|---|---|
| WB_ID | Text | District code + serial | Yes | Unique identifier, never reused | 7.3.1 |
| WB_NAME | Text | — | Yes | Name as in Revenue and PWD (WR) records, with local name | 7.3.1(a) |
| WB_NAME_BN | Text | Bengali script | Yes | Name in Bengali | 7.3.1(a) |
| WB_TYPE | Code | Table 7A.2 | Yes | Waterbody type | 7.2, 7.3.1(a) |
| SURVEY_NOS | Text | Village, survey and subdivision numbers | Yes | Revenue survey numbers of the waterbody | 7.3.1(a) |
| VILLAGE | Text | — | Yes | Revenue village, revenue circle and district | 7.3.1(a) |
| CUSTODIAN | Code | Table 7A.2 | Yes | Custodian body | 7.3.1(b) |
| AREA_REC | Number | ha | Yes | Area within the Revenue record boundary | 7.3.1(c) |
| AREA_FTL | Number | ha | Tanks | Waterspread at FTL, surveyed | 7.2, 7.3.1(d) |
| FTL | Number | m (datum) | Tanks | Full tank level | 7.3.1(d) |
| MWL | Number | m (datum) | Tanks | Maximum water level (Clause 7.2 definition) | 7.3.1(d) |
| MWL_BASIS | Code | PWD (WR) record / 1% AEP computed | Tanks | Which value governs MWL | 7.2 |
| TBL | Number | m (datum) | Tanks | Top bund level, lowest point | 7.3.1(d) |
| WEIR_CREST | Number | m (datum) | Tanks | Surplus weir crest level | 7.3.1(d) |
| WEIR_LEN | Number | m | Tanks | Surplus weir crest length | 7.3.1(d) |
| WEIR_TYPE | Text | — | Tanks | Surplus weir type (for example fixed crest, with shutters or falling boards) | 7.3.1(d) |
| SLUICE_N | Integer | — | Tanks | Number of sluices; details in WB_STRUCT | 7.3.1(d) |
| SUPPLY_CH | Text | WB_ID(s) | Tanks | Supply channel(s) feeding the tank | 7.3.1(d) |
| SURPLUS_CS | Text | WB_ID(s) | Tanks | Surplus course(s) leaving the tank | 7.3.1(d) |
| UPSTR_WB | Text | WB_ID(s) | Cascades | Upstream tank(s) in the cascade | 7.3.1(e) |
| DNSTR_WB | Text | WB_ID | Cascades | Downstream tank, river, drain or sea outfall | 7.3.1(e) |
| CATCH_AREA | Number | ha | Channels | Drainage area at the downstream end of the reach (for the 8 ha trigger of Clause 7.4.1(b) and Table 7.1) | 7.4.1 |
| DATUM | Text | — | Yes | Datum of all levels; conversion from any older PWD (WR) datum | 7.3.5 |
| LEVEL_DATE | Date | — | Tanks | Date of the level survey | 7.7.1(a) |
| SSC_DATE | Date | — | Tanks | Date of the latest stage–storage survey | 7.7.1(b) |
| FLOOD_SRC | Code | Adopted map / site study / none | Yes | Source of the 1% AEP extent | 7.3.4 |
| FLOODWAY | Code | Delineated / whole 1% extent / below MWL | Yes | Basis of the floodway | 7.6.1 |
| ENCR_KNOWN | Code | Yes / No | Yes | Known encroachment; details in WB_ENCR | 7.3.1(g) |
| CREDITED | Code | Yes / No | Tanks | Storage counted under Clause 7.7, with the scheme reference | 7.7.1 |
| WETLAND | Code | Notified / listed / other | Wetlands | Status under Clause 7.12.1 | 7.12.1 |
| SOURCES | Text | — | Yes | Sources used, from the list in Clause 7.3.3(a) to (e) | 7.3.3 |
| UPDATED | Date | — | Yes | Date of the last edit, and by whom | 7.3.1 |
Table 7A.2 — Code lists
| Code list | Values | Clause |
|---|---|---|
| WB_TYPE | River (nadi); khal (canal or channel); chhara (stream); nala, doba (ditch) or drain; lunga flow path; pukur (tank or pond); dighi (large tank); beel or haor (natural wetland); marsh or swamp (dhepa, utla); ponded area behind an embankment (with its sluice); reservoir; retention pond or basin; brick-field pit kept as a water body (TBR 2017, r.9(5)); supply channel; surplus course | 7.2 |
| CUSTODIAN | Agartala Municipal Corporation (TMA 1994, s.91); other Municipal Council or Nagar Panchayat (s.91); Agartala Smart City Ltd (works not handed over); TUDA (LPA layouts); PWD (WR) (embankment, sluice, anti-erosion work, minor-irrigation dam); PWD (R&B) or NHIDCL (road drains and culverts); PWD (DWS) (pump house, STP); Dumbur reservoir operator; Forest Department or Fisheries Department (Rudrasagar); Revenue Department (khas land); Gram Panchayat or Village Committee; religious institution; private owner; District Council, TTAADC area [TBC]; Wetland Authority of Tripura (notified wetland); other (name) | 7.3.1(b) |
| Structure (WB_STRUCT) | Surplus weir; sluice; regulator; inlet; drain outfall; gross pollutant trap; crossing | 7.3.1(d), 7.10 |
| Encroachment (WB_ENCR) | Building; fill; road; wall; dumping; cultivation; other — each with date recorded, area (m²) and source | 7.3.1(g), 7.13 |
Table 7A.3 — Attribute fields of structures (WB_STRUCT)
| Field | Type | Unit | Content | Clause |
|---|---|---|---|---|
| STR_ID | Text | — | Unique identifier | 7.3.1(d) |
| WB_ID | Text | — | Waterbody served | 7.3.1(d) |
| STR_TYPE | Code | Table 7A.2 | Structure type | 7.3.1(d) |
| CREST_SILL | Number | m (datum) | Weir crest or sluice sill level | 7.7.1(a) |
| LENGTH_SIZE | Text | m | Weir crest length, or sluice opening size | 7.7.1(a) |
| GATED | Code | Yes / No | Controllable outlet (needed for a flood cushion, Clause 7.8.2(a)) | 7.8.2 |
| CONDITION | Code | Serviceable / defective | Result of the latest pre-monsoon inspection, with date | 7.7.1(d), 7.14.4 |
Annex 7B — Fixed-width setback table (alternative S-3, with Annex 1C)
Supports Clauses 7.3.4, 7.4.3, 7.4.6 and 7.4.7 of Chapter 7, and alternative S-3 of the Policy Supplement (Annex 1C).
7B.1 When the table may be used
The fixed-width setback may be used only where all of the following apply:
- (a) the Authority has not adopted a 1% AEP flood extent map for the waterbody (Clause 7.3.4);
- (b) Clause 7.3.4 does not require the Applicant to determine the 1% AEP extent by a hydraulic study: the site is not in a flood-sensitive catchment, is not a site of 1 ha or more adjoining a waterbody, and the Authority has not asked for a study; and
- (c) the waterbody is one to which setbacks apply (Clause 7.4.1): any recorded or found waterbody, and any natural channel draining 8 ha or more at the site.
Where an Authority adopts alternative S-3 under Clause 1.7, the table below is the S-3 table. Clause 1.7.3(e) provides for the S-3 table to be issued by the State Stormwater Technical Committee. Until it is issued, the values are those of Clause 7.4.6, repeated here without change.
Table 7B.1 — Fixed-width setback by waterbody class (alternative S-3)
| Waterbody class | Drainage area at the site | Total setback (Zone 1 + Zone 2) | Of which Zone 1 | Measured from |
|---|---|---|---|---|
| Channel, small | 8 ha to 65 ha | 25 m | 15 m | Top of bank (Clause 7.4.3) |
| Channel, medium | 65 ha to 20 km² | 40 m | 15 m | Top of bank |
| Channel, large, and rivers | More than 20 km² | 50 m | 20 m | Top of bank |
| Tank, lake or pond | Any | MWL contour + 25 m | To the MWL contour, and not less than 15 m from FTL | FTL contour (Zone 1); MWL contour (total) |
| Marsh, estuary or backwater | Any | As notified by the Authority, and not less than 50 m | 15 m | The waterbody boundary of Clause 7.13.1 |
Values from Clause 7.4.6 (Table 7.1). Zone 2 is the total setback less Zone 1.
7B.2 Rules of application
- (a) Measurement. Measure horizontally on plan, outward from the boundary of Clause 7.13.1: the larger of the Revenue record boundary and the surveyed FTL (or top of bank). Where FTL and top of bank both apply, use whichever gives the wider zone (Clause 7.4.3).
- (b) Drainage area. For a channel, use the drainage area at the downstream end of the reach that adjoins the site. Where a reach crosses a class limit within the site, apply the wider setback to the whole reach within the site.
- (c) Both banks. The setback applies on each bank of a channel and all round a tank, lake, pond or marsh.
- (d) Minimum set by this Manual. Zone 1 is never less than 15 m (Clause 7.4.7). A wider statutory or approval setback governs for the uses it restricts (Clause 7.4.5).
- (e) Stricter of the two. Where a hydraulic study is made voluntarily, the setback is the wider of Table 7B.1 and Clauses 7.4.3 and 7.4.4.
- (f) Record. The basis of the setback (fixed width) shall be stated on the Waterbody Sheet (Form 7-1) and in the approval (Clause 7.4, Disclosure).
- (g) Review. The table shall be reviewed within 2 years of the Authority adopting 1% AEP flood maps (Clause 7.16.1).
7B.3 Source of the channel widths
The channel widths were set by this Manual with reference to the 2006 Kansas City APWA default stream buffers, rounded up and floored at the 15 m minimum (Clause 7.4.6, commentary). The source values, as cited in the chapter, are:
Table 7B.2 — Source buffers cited in Clause 7.4.6 (KC APWA 5600, 2006, §5605.3)
| Drainage area (source, acres) | Approximate SI equivalent | Source buffer |
|---|---|---|
| Less than 40 ac | Less than 16 ha | 40 ft (12 m) |
| 40–160 ac | 16–65 ha | 60 ft (18 m) |
| 160–5,000 ac | 65 ha – 20 km² | 100 ft (30 m) |
| More than 5,000 ac | More than 20 km² | 120 ft (37 m) |
The 65 ha and 20 km² class limits in Table 7B.1 are the SI equivalents of 160 ac and 5,000 ac. The 8 ha lower limit is the 20-acre trigger of APWA 2025.01 (Clause 7.4.1(b)).
Annex 7C — Template tank operating rule, with flood cushion
Supports Clauses 7.7.1(c), 7.7.3, 7.8 and 7.14.4 of Chapter 7.
Model text for consideration by a competent authority. Not in force. For tanks under PWD (WR) control, the operating rule is PWD (WR)'s rule (Clause 7.8.4); this template sets out the content that Clause 7.8 asks for, so that the custodian's rule can be checked against it. Text in square brackets is to be completed for each tank.
7C.1 Identification
- Tank: [name, WB_ID of Annex 7A, village, revenue circle, district].
- Custodian: [PWD (WR) division / ULB / Gram Panchayat or Village Committee / other].
- Cascade position: upstream tank(s) [ ]; downstream tank, river or drain [ ].
- Datum: [ ]. Surveyed levels (Clause 7.7.1(a)), date of survey [ ]: FTL [ ] m; MWL [ ] m; TBL (lowest point) [ ] m; surplus weir crest [ ] m, length [ ] m; sluice sills [ ] m.
- Stage–storage curve (Clause 7.7.1(b)): survey date [ ]; attached as Schedule 1.
- Controllable outlets (Clause 7.8.2(a)): [gated sluice / regulator / none]; capacity at FTL [ ] m³/s.
7C.2 Purposes and priority
- The tank serves [irrigation of a command area of [ ] ha / drinking water supply / recharge / flood storage]. Irrigation and water supply remain primary unless the custodian records otherwise (Clause 7.8.2(d)).
7C.3 Levels and dates through the year (Clause 7.8.1(a))
- The tank shall be operated to the levels in Table 7C.1.
Table 7C.1 — Rule levels by period (to be completed for each tank)
| Period | Target level (m) | Upper limit (m) | Lower limit (m) | Purpose |
|---|---|---|---|---|
| [1 Jan – date] | [ ] | FTL | [ ] | Holding for irrigation / supply |
| [date – start of cushion period] | [ ] | FTL | [ ] | Holding |
| [Flood-cushion period, if any] | Cushion level [ ] | Cushion level [ ] | [ ] | Flood cushion (Clause 7.8.2) |
| [End of cushion period – 31 Dec] | [ ] | FTL | [ ] | Refilling |
- Where no flood cushion is adopted, the starting level for design is FTL (Clause 7.7.3) and the row for the cushion period is deleted.
7C.4 Flood cushion (Clause 7.8.2)
- Cushion level: [ ] m, which is [ ] m below FTL, giving a cushion volume of [ ] m³ from Schedule 1.
- Dates: the cushion applies from [ ] to [ ].
- Drawdown: the tank can be drawn down from FTL to the cushion level through [outlet] in [ ] hours, with a release not exceeding the maximum release rate of paragraph 18.
- Reliability: continuous simulation (Clause 3.13) over the record [years] shows that the cushion is available at the start of a design storm in [ ]% of monsoon seasons, which shall be at least 90%. The simulation report is Schedule 2.
- Yield: the custodian accepts the loss of irrigation or supply yield stated in Schedule 3 [and the compensation recorded there].
- Where the tank has no controllable outlet, this section does not apply and no flood cushion is assumed (Clause 7.8.3).
7C.5 Releases (Clause 7.8.1(b) to (d))
- Sluice and regulator settings at each level: Table 7C.2.
- Operator: the sluices and regulators are operated by [post]. A release above [ ] m³/s may be ordered only by [post], or, in an emergency, by [post].
- Maximum release rate: [ ] m³/s. This rate, added to the flow from the downstream catchment, does not flood buildings downstream (Schedule 4 gives the downstream check).
- No person shall cut, lower or breach the bund or surplus weir except under the custodian's emergency procedure (Clause 7.14.5).
Table 7C.2 — Outlet settings by level (to be completed for each tank)
| Tank level (m) | Sluice 1 | Sluice 2 | Regulator | Expected outflow (m³/s) | Notes |
|---|---|---|---|---|---|
| Below cushion level | [ ] | [ ] | [ ] | [ ] | |
| Cushion level to FTL | [ ] | [ ] | [ ] | [ ] | |
| FTL (weir begins to spill) | [ ] | [ ] | [ ] | [ ] | |
| Above FTL to MWL | [ ] | [ ] | [ ] | [ ] | Check freeboard to TBL (Clause 7.7.4(b)) |
7C.6 Forecasts, warnings and communication (Clause 7.8.1(e) and (f))
- The triggers and actions are in Table 7C.3.
- Before any release under this rule, the operator shall inform the ULBs and the district administration downstream, and residents by the means stated in Schedule 5, at least [ ] hours before the release where the forecast allows.
Table 7C.3 — Triggers and actions (to be completed for each tank)
| Trigger | Source | Action | By whom |
|---|---|---|---|
| IMD district heavy-rainfall warning for the catchment | IMD | Read gauges [ ] hourly; check outlets are free; confirm the tank is at or below its rule level | [ ] |
| IMD or TDMA red alert | IMD, TDMA | Begin releases needed to reach the rule level, within the maximum release rate; notify downstream bodies (paragraph 21) | [ ] |
| City forecast system warning, where available | [ ] | [ ] | [ ] |
| Tank level reaches FTL | Gauge | Record outflow hourly; inspect bund and weir | [ ] |
| Tank level reaches [MWL − [ ] m] | Gauge | Emergency procedure; warning to the breach area of any emergency action plan (Clause 7.14.3(c)) | [ ] |
7C.7 Records and review (Clause 7.8.1(g))
- During the monsoon (1 April to 31 October) the operator shall record daily: the tank level, every release (time, rate and duration), and every gate setting. Outside the monsoon, records shall be kept [weekly].
- Records shall be kept with the O&M plan (Chapter 10) and given to the Authority on request.
- The tank shall be inspected before the monsoon (by 31 March) and after every heavy-rainfall event (Clause 7.14.4).
- This rule shall be reviewed after any event in which the tank surplused at a level above [ ] m, after any change to the weir, sluices or bund (Clause 7.7.6), and in any case with the review of the Manual.
Schedules: 1 stage–storage curve; 2 continuous simulation report; 3 yield and compensation; 4 downstream check of the maximum release; 5 communication list.
Annex 7D — Desilting and restoration specification
Supports Clauses 7.7.1(b), 7.9 and 7.14.4 of Chapter 7.
This specification applies to every desilting, restoration or deepening of a tank, pond or other waterbody under Clause 7.9. Values are those of Chapter 7. Where the chapter does not set a value, it is marked "to be confirmed in design" and shall be stated in the works design.
7D.1 Pre-works survey (Clause 7.9.1)
- (a) Topographic and bathymetric survey of the waterspread, foreshore (to the MWL contour), bund, surplus weir and sluices, levelled to the datum of Clause 7.3.5. Survey grid and point density: to be confirmed in design.
- (b) Original bed level found by test pits or augering on a grid (grid spacing to be confirmed in design), and from historical records where available. Each pit log shall show the silt thickness, the level of the original bed, and any clay or silt layer below it.
- (c) Silt testing where the tank receives urban runoff or sewage: samples from the pits of (b), tested for heavy metals and other contaminants before disposal is planned. The parameters and limits shall be those the Tripura State Pollution Control Board (TSPCB) directs.
- (d) Structures: condition of the bund (seepage, slips, cracks, animal burrows, trees), surplus weir and sluices, as in Clause 7.14.4.
- (e) Existing stage–storage curve from the survey of (a).
7D.2 Limits of excavation (Clauses 7.9.2 and 7.9.3)
- (a) Desilting removes accumulated sediment down to the original bed level of 7D.1(b), and no deeper.
- (b) Deepening below the original bed only with a hydrogeological report showing each of Clause 7.9.3(a) to (c).
- (c) Storage created below the lowest sluice sill is not flood storage, and shall not be shown as such in the revised stage–storage curve.
- (d) Excavation shall stay clear of the bund toe by a distance to be confirmed in design, so that the bund's stability is not reduced.
7D.3 Edges and safety (Clause 7.9.4)
Where the public has access to the edge:
- (a) side slopes no steeper than 1V:4H from 0.5 m above FTL down to 1.2 m below FTL; or
- (b) a level safety bench at least 3 m wide, between 0.3 m and 0.5 m below FTL; and
- (c) no isolated deep pit or vertical cut left in the bed. Borrow pits shall be regraded to the bed.
7D.4 Storage not reduced (Clause 7.9.5)
- (a) Islands, walkways, bund widening into the waterspread, ring roads, parking, buildings and lake-front platforms within the waterspread or foreshore are lost storage.
- (b) Lost storage shall be offset by compensatory storage at equivalent levels, band by band, using Form 7-3.
7D.5 Silt handling and disposal (Clause 7.9.6)
- (a) Desilted material shall not be placed within the setback, on the bund (except approved bund strengthening), or on any flood path.
- (b) Contaminated silt shall be disposed of as the Tripura State Pollution Control Board (TSPCB) directs.
- (c) Haul routes and temporary stockpiles shall meet the construction erosion and sediment control rules of Clause 8.12, including stockpiles outside Zone 1.
7D.6 Inlets (Clause 7.9.7)
Every inlet that brings urban runoff shall have a sediment forebay, a constructed wetland inlet zone or a gross pollutant trap, designed under Chapter 8 (Annex 8D).
7D.7 Timing (Clause 7.9.8)
Desilting shall be complete, and the waterbody made safe, by 31 March. No excavation shall be left open, and no sluice or weir left dismantled, during the monsoon.
7D.8 Completion records
- (a) As-built survey and revised stage–storage curve. The curve is the one that Clause 7.7.1(b) requires "after the last desilting".
- (b) Volume removed, its disposal site, and the silt test results.
- (c) Photographs of the bund, weir, sluices and inlet works.
- (d) Update of the inventory record (Annex 7A: SSC_DATE, LEVEL_DATE, CONDITION).
Table 7D.1 — Hold points for desilting and restoration works
| Hold point | Check | Clause |
|---|---|---|
| 1. Before excavation | Pre-works survey, pit logs, silt tests, and hydrogeological report if deepening | 7.9.1, 7.9.3 |
| 2. Original bed reached | Levels checked against pit logs; no excavation below the original bed unless approved | 7.9.2 |
| 3. Edges formed | Side slopes or safety bench as 7D.3 | 7.9.4 |
| 4. Inlet works | Forebay, wetland inlet zone or GPT built | 7.9.7 |
| 5. Completion (by 31 March) | As-built survey, stage–storage curve, silt disposal record | 7.9.8, 7.7.1(b) |
Annex 7E — Glossary of Bengali waterbody terms and regional variants
Supports Clause 7.2 and Clause 7.3 of Chapter 7.
The terms below are the Bengali words for waterbodies, channels, embankments and land that Tripura's land records use, with a few that appear in place names, the Building Rules and the dictionary. Their primary source is the State's own gazette: Appendix-I, "Classification of land for Agricultural purpose", of the Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025 (Tripura Gazette Extraordinary No. 1072, 3 June 2025; "App-I", with its item number), which gives each Bengali class with an official English gloss. Meanings are also given, where found, from S. Biswas, Samsad Bengali-English Dictionary, as served by the Digital South Asia Library (edition not confirmed; "Biswas", with its print page). The Bengali script is the gazette's. The name used in the land records, a municipal record or PWD (WR)'s records for each waterbody should be recorded in the inventory (Annex 7A) alongside the Manual's term. Two cautions apply. Roman spellings vary (for example beel and bil, lunga and loonga, Katakhal and Kathakhal), and modern usage may be narrower or wider than the gazette's and the dictionary's English glosses. Terms whose meaning or use was not confirmed, and terms this Manual avoids, are in Table 7E.4. The list is to be extended by the State Stormwater Technical Committee, with modern land-record, PWD (WR) and municipal usage and the terms of Kokborok and the other languages in use in the State.
The Manual's term for a dug tank or pond is pukur, written on first use as "pukur (Bengali পুকুর: a tank or pond — the land records' 'Tank/Pond'; plural pukurs)", and its term for a large tank is dighi, written on first use as "dighi (Bengali দীঘি: a large tank)". Pukur is the gazetted land class "Tank/Pond" in the rules that control the diversion of water bodies, and the dictionary gives it the engineering verbs of the tank (পুকুর কাটা, "to excavate a pond"; পুকুর ঝালানো, "to dredge a tank"); dighi has its own class, "Large tank". Bengali marks the plural with -gulo or -guli, not with an ending of this kind, so the English plural pukurs is a convention of this Manual. Engineered storage built under this Manual is a detention pond, never a pukur, and a natural wetland is never called a pukur. A doba is recorded in Tripura as a "Ditch", never as a pond. The Building Rules call a hill stream a jhora; this Manual keeps that word when it quotes the rules and writes chhara elsewhere.
Table 7E.1 — Waterbodies and wet land
| Bengali term | Meaning (source) | Manual term (Clause 7.2) |
|---|---|---|
| পুকুর (pukur) | "Tank/Pond" (App-I, 9); "n. a pond, a tank, a pool"; পুকুর কাটা "v. to excavate a pond"; পুকুর ঝালানো "v. to dredge a tank" (Biswas, p. 653) | Pukur (tank or pond), see the definitions after Clause 7.2 |
| পুকুরপাড় (pukurpar) | "Bank of tank" (App-I, 10) | Bank of a pukur; in Zone 1 (definitions after Clause 7.2) |
| দীঘি, দিঘি (dighi) | "Large tank" (App-I, 14); "n. a large and deep tank or pond" (Biswas, pp. 499, 501) | Dighi (large tank) |
| দীঘিরপাড় (dighirpar) | "Bank of large tank" (App-I, 31) | Bank of a dighi; in Zone 1 |
| ডোবা (doba) | "Ditch" (App-I, 11); "n. a pit full of water; a small pool of water" (Biswas, p. 436) | Doba (ditch); never a pukur |
| বিল (bil; beel) | "Watery land" (App-I, 13); "… a fen; a marsh" (Biswas, p. 770) | Beel (natural wetland), see the definitions after Clause 7.2 |
| হাওর (haor) | "Big watery land" (App-I, 12); "n. an extensive marsh or quagmire or fen" (Biswas, p. 1050, as হাওড়) | Haor (large natural wetland) |
| ঢেপা (dhepa) | "Marshy land" (App-I, 21) | Marsh (Clause 7.12) |
| উতলা (utla) | "Swampy land" (App-I, 23) | Marsh or swamp (Clause 7.12) |
| জলা (jala) | "n. a marsh, a bog"; ~জমি, "wetlands" (Biswas, p. 395) | Marsh; not a land class in App-I |
| বালুরচর (balurchar) | "Sandy land bed" (App-I, 22) | Sand bar within a river (part of the waterbody) |
Table 7E.2 — Streams, channels, drains and wells
| Bengali term | Meaning (source) | Manual term (Clause 7.2) |
|---|---|---|
| নদী (nadi) | "River" (App-I, 33) | River |
| ছড়া (chhara) | "Streams" (App-I, 35); the dictionary gives the word no stream sense (Biswas, p. 374) | Chhara (stream), see the definitions after Clause 7.2; cite the gazette |
| খাল (khal) | "Khal" (App-I, 34); "n. a canal; a strait; a channel …" (Biswas, p. 281) | Khal (canal or channel), as in the Katakhal and the Kalapania Khal |
| নালা (nala) | "Water channel" (App-I, 7); "n. a duct; a drain; a canal; a wayside gutter" (Biswas, p. 567) | Nala (water channel) |
| ড্রেন (drain) | "Drain in Municipal area" (App-I, 8) | Drain (the gazette uses the English loan) |
| নর্দমা (nardama) | "n. a drain; a gutter; a sewer" (Biswas, p. 558) | Drain (minor system); colloquial |
| ঝোরা (jhora) | The Building Rules' word for a hill stream ("natural drainage channel/jhora", "streams/jhoras", rr.5, 90 and 99); "n. a cascade, a waterfall, a fountain" (Biswas, p. 418) | Used only when quoting the rules; otherwise chhara |
| ইন্দারা (indara); কুয়া (kua) | "Pucca well"; "Kachha well" (App-I, 19 and 20) | Well (Clause 8.11) |
Table 7E.3 — Land and embankments
| Bengali term | Meaning (source) | Use in this Manual |
|---|---|---|
| লুঙ্গা (lunga) | "Flat lands between tillas" (App-I, 5); not in Biswas; the CGWB writes "loonga" | Lunga (valley floor between tillas) and its flow path, see the definitions after Clause 7.2 |
| টিলা (tilla) | "Hillock" (App-I, 15); "n. a mound, a hillock, a knoll, a hummock" (Biswas, p. 424) | Tilla (low hill or terrace upland) |
| বাঁধ (bandh) | "Embankment" (App-I, 30); "n. a dam; a breakwater … (geog.) a dyke" (Biswas, p. 735) | Bandh: the term for a river or pond embankment |
Kokborok. Kokborok is an official language of the State with Bengali (Tripura Official Language Act, 1964, as amended in 1979; in force for official purposes from 1 May 1999). Its script is disputed between Roman and Bengali (as reported), and this Manual takes no side: it gives the Kokborok words it found only in the phonetic (IPA) forms of a linguistic study of the Debbarma dialect (Brahma, 2022, Himalayan Linguistics 21(2), Tables 9–10, citing B. Debbarma's Concise Kokborok-English-Bengali Dictionary, 2001, which was not read). Their Roman and Bengali spellings were not confirmed [TBC], so they are given for reference only and are not used as defined terms: tɯi "water"; tɯɪma "river"; tɯɪsluŋ "canal"; tɯɪsuŋ "riverbank"; tɯɪtɔɾ "flood"; tɯɪwaɾ "large pond, lake", the nearest Kokborok word to pukur and dighi; and tɯɪmuk "fountain". Kokborok names such as Saidra for the Haora and Twijilikma for Rudrasagar (both as reported) are recorded in the WB_NAME field of Annex 7A with a note.
Table 7E.4 — Terms avoided or not yet verified
These terms or senses are in use or have been proposed but were not confirmed during research for this Manual, or are avoided because they mislead. They shall not be used in a record or a drawing as defined terms.
| Term | Reported meaning or use | Status |
|---|---|---|
| ডোবা (doba) as "pond" | In some Bengali usage a small pool, grouped with tanks | Avoided in that sense: Tripura's land records class it as "Ditch" |
| ছড়া (chhara) from the dictionary | Biswas gives "rhyme; string; bunch" and no stream sense | Not cited; the gazette's "Streams" is the source |
| Katakhal as "cut canal" | A reading of the name | Not used: the etymology is not verified |
| hachuk | Kokborok "hill", from Wiktionary only | Not used |
| Kokborok words in Roman or Bengali script | Spellings of the IPA forms above | Not confirmed [TBC] |
| Terms in the other languages of the State | — | Not researched for this Manual [TBC] |
The Manual uses the terms in the last column of Tables 7E.1 to 7E.3 and the Tripura terms defined after Clause 7.2.
Form 7-1 — Waterbody Sheet
Supports Clauses 7.3.2, 7.4 and 7.15(1) of Chapter 7.
Draft form — Tripura Stormwater Design Manual, Draft v1.0. One sheet per waterbody. Attach the plan of Clause 7.3.2 at 1:1,000 or larger.
Table 7F.1 — Form 7-1, Section A: Project and waterbody
| No. | Field | Entry | Clause |
|---|---|---|---|
| A1 | Project name and Authority file number | ______ | — |
| A2 | Waterbody name (English and Bengali) and inventory ID (Annex 7A), if any | ______ | 7.3.1 |
| A3 | Waterbody type (Clause 7.2) | ______ | 7.2 |
| A4 | Position: within the site / within 100 m of the site boundary / downstream within the Chapter 5 extent | ______ | 7.3.2 |
| A5 | Survey numbers and village | ______ | 7.3.1(a) |
| A6 | Custodian | ______ | 7.3.1(b) |
| A7 | Sources checked (tick): Revenue Department land records (district, sub-division, revenue circle, mouza; Appendix-I land class), the 2020 list of 180 urban water bodies, Master Plan 2045 and LPA maps, PWD (WR) embankment and sluice records and Haora flood-plain-zone map, TTAADC records [TBC], drain register ☐; PWD (WR) / Gram Panchayat or Village Committee registers ☐; Authority inventory or court list ☐; historical maps and imagery, including NWIA ☐; site survey ☐ | ______ | 7.3.3 |
| A8 | Where sources conflict: which extent governs (the larger) | ______ | 7.3.3 |
| A9 | Datum of all levels, and conversion from any PWD (WR) datum | ______ | 7.3.5 |
Table 7F.2 — Form 7-1, Section B: Levels and features
| No. | Field | Entry | Clause |
|---|---|---|---|
| B1 | FTL (tanks, lakes, ponds) or top of bank (channels), m | ______ | 7.2 |
| B2 | MWL (tanks), m, and basis (PWD (WR) record or 1% AEP computed) | ______ | 7.2 |
| B3 | TBL, lowest point (tanks), m | ______ | 7.3.1(d) |
| B4 | 1% AEP flood level, m, and source (adopted map / hydraulic study / not available) | ______ | 7.3.4 |
| B5 | Drainage area at the site (channels), ha | ______ | 7.4.1(b) |
| B6 | Supply channels, surplus courses, sluices and surplus weirs shown on plan (yes / no) | ______ | 7.3.2 |
| B7 | Known encroachments, with date recorded | ______ | 7.3.1(g) |
Table 7F.3 — Form 7-1, Section C: Setback
| No. | Field | Entry | Clause |
|---|---|---|---|
| C1 | Basis of setback: mapped extent / hydraulic study / fixed width (Annex 7B) | ______ | 7.15(1) |
| C2 | Is a hydraulic study required under Clause 7.3.4 (a) / (b) / (c)? | ______ | 7.3.4 |
| C3 | Floodway outer edge, m from FTL or top of bank, and how delineated | ______ | 7.6.1 |
| C4 | Zone 1 width, m (greatest of 15 m, floodway edge, MWL contour) | ______ | 7.4.3 |
| C5 | Zone 2 width, m (to 1% AEP extent + 10 m, or 10 m) | ______ | 7.4.4 |
| C6 | Wider statutory or approval setback, if any, and its source | ______ | 7.4.5 |
| C7 | Setback applied: Manual standard / a wider statutory, plan or approval line: the r.9(4) "zone of river" of the TBR 2017 (15 m from the river bank; a regulated zone, not a no-build line, stated and never governing alone); in a hill ULB, the 5 m of r.90(1)(i) and the protective works of r.90(1)(m) (narrower than Zone 1, stated, never governing alone); a zoning or development control line of the Master Plan for the Agartala Planning Area 2045 or another Master Plan (not read [TBC]); a condition of the Local Body's approval under r.9(3) or of a decision under the Diversion of Land Rules; a PWD (WR) condition at an embankment or sluice; the boundary of Rudrasagar or of a wetland notified under the 2017 Rules; a court or Tribunal line; or other (state which) | ______ | 7.4, Disclosure |
| C8 | Uses proposed in Zone 1 and Zone 2, and the custodian's NOC for any work in Zone 1 | ______ | 7.5, 7.15(5) |
| C9 | Fill proposed in the flood fringe (yes / no); if yes, Form 7-3 attached | ______ | 7.6.3 |
| C10 | Zone 1 marker positions shown (not more than 30 m apart) | ______ | 7.13.4 |
Table 7F.4 — Form 7-1, Section D: Prepared by
| Field | Entry |
|---|---|
| Name, registration and empanelment number (Clause 10.6) | ______ |
| Signature and date | ______ |
| Licensed surveyor for the levels (name, licence number) | ______ |
Form 7-2 — Tank Storage Credit Sheet
Supports Clauses 7.7, 7.8, 7.11, 7.14 and 7.15(4) of Chapter 7.
Draft form — Tripura Stormwater Design Manual, Draft v1.0. One sheet per tank whose storage is counted. Storage that fails any item in Section B shall not be counted (Clause 7.7.1).
Table 7F.5 — Form 7-2, Section A: Tank and scheme
| No. | Field | Entry | Clause |
|---|---|---|---|
| A1 | Tank name and inventory ID (Annex 7A); custodian | ______ | 7.3.1 |
| A2 | Scheme in which storage is counted: basin plan / regional facility / fee-in-lieu (S-5) | ______ | 7.7.1, 7.11 |
| A3 | Cascade modelled: uppermost tank ______ to outfall ______ | ______ | 7.7.2 |
| A4 | Datum | ______ | 7.3.5 |
Table 7F.6 — Form 7-2, Section B: Conditions for counting storage
| No. | Condition | Date / reference | Met (yes / no) | Clause |
|---|---|---|---|---|
| B1 | FTL, MWL, TBL, weir crest and length, sluice sills surveyed within the previous 5 years | ______ | ______ | 7.7.1(a) |
| B2 | Stage–storage curve from a bathymetric and topographic survey within 5 years or after the last desilting, whichever is later | ______ | ______ | 7.7.1(b) |
| B3 | Documented operating rule agreed with the custodian (Annex 7C) | ______ | ______ | 7.7.1(c), 7.8 |
| B4 | Weir, sluices and bund under an O&M plan; latest pre-monsoon inspection found them serviceable | ______ | ______ | 7.7.1(d), 7.14.4 |
| B5 | Custodian's written concurrence | ______ | ______ | 7.7.1(e) |
Table 7F.7 — Form 7-2, Section C: Levels and creditable volume
| No. | Item | Value | Clause |
|---|---|---|---|
| C1 | Starting level: FTL, or cushion level under a rule meeting Clause 7.8.2, m | ______ | 7.7.3 |
| C2 | If a cushion is used: controllable outlet (type) and drawdown time, h | ______ | 7.8.2(a) |
| C3 | If a cushion is used: reliability from continuous simulation, % of monsoon seasons (≥ 90%) | ______ | 7.8.2(c) |
| C4 | Computed maximum level, 1% AEP inflow with climate factor routed through the cascade, m | ______ | 7.7.4 |
| C5 | MWL, m; is C4 ≤ MWL? | ______ | 7.7.4(a) |
| C6 | Freeboard C4 to TBL, m; PWD (WR) freeboard standard, m; met? | ______ | 7.7.4(b) |
| C7 | Storage between C1 and C4, from the stage–storage curve, m³ | ______ | 7.7.5 |
| C8 | Volume already committed to another facility or scheme, m³ | ______ | 7.7.5 |
| C9 | Creditable volume = C7 − C8, m³ | ______ | 7.7.5 |
| C10 | Register entry under Clause 10.17 (fee-in-lieu storage) | ______ | 7.11.2(d) |
Table 7F.8 — Form 7-2, Section D: Bund safety
| No. | Item | Entry | Clause |
|---|---|---|---|
| D1 | Specified dam under the Dam Safety Act, 2021? Height, crest length, capacity, maximum flood discharge | ______ | 7.14.1 |
| D2 | Hazard class: high / low | ______ | 7.14.2 |
| D3 | High hazard: weir passes 1% AEP at MWL with freeboard; 0.2% AEP check without overtopping | ______ | 7.14.3(a) |
| D4 | High hazard: breach analysis and emergency action plan (references) | ______ | 7.14.3(b), (c) |
| D5 | High hazard: independent check under Clause 10.6 (name) | ______ | 7.14.3(d) |
Table 7F.9 — Form 7-2, Section E: Signatures
| Role | Name and designation | Signature and date |
|---|---|---|
| Designer (Clause 10.6) | ______ | ______ |
| Independent checker, where Clause 7.14.3(d) applies | ______ | ______ |
| Custodian's concurrence (Clause 7.7.1(e)) | ______ | ______ |
Form 7-3 — Compensatory Storage Calculation (by elevation band)
Supports Clauses 7.6.3 to 7.6.5, 7.9.5 and 7.15(3) of Chapter 7.
Draft form — Tripura Stormwater Design Manual, Draft v1.0.
Method
- Fix the lower limit: the normal water level of the waterbody, or the 50% AEP (2-yr) level where higher (Clause 7.6.4(b)).
- Fix the upper limit: the 1% AEP flood level (with the climate factor).
- Divide the range into bands of not more than 0.3 m. The top band may be thinner.
- For each level z at a band boundary, measure on plan:
- A_fill(z): the area of the fill footprint where existing ground is below z; and
- A_cut(z): the area of the excavation where finished ground is below z and existing ground was above z (new flooded area).
- For each band, by the average end-area method: V = (A(z_bottom) + A(z_top)) / 2 × band thickness. Do this for fill (volume lost) and for excavation (volume gained).
- Check each band: volume gained ≥ volume lost. A surplus in one band does not make up a shortfall in another (Clause 7.6.4(b)).
- Check the other conditions of Clause 7.6.4(c) to (f) in Section C.
Figure 7.2 in Chapter 7 shows the method.
Table 7F.10 — Form 7-3, Section A: Levels
| No. | Field | Entry | Clause |
|---|---|---|---|
| A1 | Waterbody, reach, and inventory ID | ______ | 7.6.4(c) |
| A2 | Normal water level, m; 50% AEP level, m; lower limit (the higher), m | ______ | 7.6.4(b) |
| A3 | 1% AEP flood level with climate factor, m (upper limit) | ______ | 7.6.4(b) |
| A4 | Band thickness, m (≤ 0.3) and number of bands | ______ | 7.6.4(b) |
| A5 | Datum | ______ | 7.3.5 |
Table 7F.11 — Form 7-3, Section B: Band-by-band balance
| Band | From (m) | To (m) | A_fill bottom (m²) | A_fill top (m²) | Volume lost (m³) | A_cut bottom (m²) | A_cut top (m²) | Volume gained (m³) | Gained ≥ lost? |
|---|---|---|---|---|---|---|---|---|---|
| 1 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| 2 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| 3 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| 4 | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Total | ______ | ______ |
Add rows as needed.
Table 7F.12 — Form 7-3, Section C: Other conditions
| No. | Condition | Met (yes / no) and evidence | Clause |
|---|---|---|---|
| C1 | Fill is in the flood fringe, not the floodway, and for a permitted use | ______ | 7.6.2, 7.6.3 |
| C2 | Excavation is in the same reach of the same waterbody, hydraulically connected, and not further downstream than the fill | ______ | 7.6.4(c) |
| C3 | Excavation drains by gravity as the flood recedes; no pumping; no permanent pool below normal water level | ______ | 7.6.4(d) |
| C4 | Excavation built before, or at the same time as, the fill | ______ | 7.6.4(e) |
| C5 | Covenant or handover so that it is never filled (reference) | ______ | 7.6.4(f) |
| C6 | Not counted as detention or retention under Chapter 4 | ______ | 7.6.5 |
| C7 | Signature of designer (Clause 10.6) and date | ______ | 10.6 |
Worked example
Illustrative — not design values. A site in the flood fringe of a channel needs a fill pad for a permitted Zone 2 use (Clause 7.5.2). The inputs are assumed.
- Normal water level 10.00 m; 50% AEP level 9.80 m. Lower limit = 10.00 m (the higher).
- 1% AEP flood level 11.20 m. Range 1.20 m, so four bands of 0.30 m.
- The fill footprint is 1,600 m². Existing ground across the footprint rises evenly from 10.00 m to 11.20 m, so the area of footprint below each level is: 0 m² at 10.00 m; 400 m² at 10.30 m; 800 m² at 10.60 m; 1,200 m² at 10.90 m; 1,600 m² at 11.20 m.
- The excavation is a graded cut beside the channel, with its floor at 10.00 m. The new flooded area below each level (first trial) is: 300 m² at 10.00 m; 900 m² at 10.30 m; 1,100 m² at 10.60 m; 1,500 m² at 10.90 m; 1,500 m² at 11.20 m.
Step 1 — volume lost, band by band (V = average area × 0.3 m):
- Band 1: (0 + 400) / 2 × 0.3 = 60 m³
- Band 2: (400 + 800) / 2 × 0.3 = 180 m³
- Band 3: (800 + 1,200) / 2 × 0.3 = 300 m³
- Band 4: (1,200 + 1,600) / 2 × 0.3 = 420 m³
- Total: 960 m³
Step 2 — volume gained, first trial:
Table 7F.13 — Worked example: first trial (illustrative)
| Band | From (m) | To (m) | Volume lost (m³) | A_cut bottom (m²) | A_cut top (m²) | Volume gained (m³) | Gained ≥ lost? |
|---|---|---|---|---|---|---|---|
| 1 | 10.00 | 10.30 | 60 | 300 | 900 | 180 | Yes |
| 2 | 10.30 | 10.60 | 180 | 900 | 1,100 | 300 | Yes |
| 3 | 10.60 | 10.90 | 300 | 1,100 | 1,500 | 390 | Yes |
| 4 | 10.90 | 11.20 | 420 | 1,500 | 1,500 | 450 | Yes |
| Total | 960 | 1,320 |
Every band passes. Note that a simple total balance would hide a failure if, for example, the cut were made deeper and narrower: suppose the designer instead offers a cut with new flooded areas of 1,400 m² at 10.00 m, 1,400 m² at 10.30 m, 1,000 m² at 10.60 m, 600 m² at 10.90 m and 200 m² at 11.20 m.
Table 7F.14 — Worked example: deeper, narrower cut (illustrative)
| Band | From (m) | To (m) | Volume lost (m³) | A_cut bottom (m²) | A_cut top (m²) | Volume gained (m³) | Gained ≥ lost? |
|---|---|---|---|---|---|---|---|
| 1 | 10.00 | 10.30 | 60 | 1,400 | 1,400 | 420 | Yes |
| 2 | 10.30 | 10.60 | 180 | 1,400 | 1,000 | 360 | Yes |
| 3 | 10.60 | 10.90 | 300 | 1,000 | 600 | 240 | No |
| 4 | 10.90 | 11.20 | 420 | 600 | 200 | 120 | No |
| Total | 960 | 1,140 |
The total gained (1,140 m³) exceeds the total lost (960 m³), but bands 3 and 4 are short by 60 m³ and 300 m³. The surplus low down cannot be counted against them: the low storage fills early in every flood and is not available when the fill takes away storage near the peak. This design fails Clause 7.6.4(b) and must be regraded so that the upper bands gain at least as much as they lose, as in the first trial.