Annexes to Chapter 11Basin and City Stormwater Master Plans
These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.
Annex 11A — BSMP terms of reference template
Supports Clauses 11.1 to 11.12 of Chapter 11.
Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.
11A.1 Background and purpose
- The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Tripura Stormwater Design Manual.
- The BSMP shall (Clause 11.1.2):
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service for each part of the drainage system;
- (c) identify, cost and rank the works, storage and land needed to reach that level of service;
- (d) identify land to be reserved in the statutory land-use plan for regional storage, pukur and tank restoration and major flow paths;
- (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
- (f) recommend catchments for notification as flood-sensitive.
- The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).
11A.2 Client, partners and study area
- Client: [Lead Authority] (Clause 11.4.1).
- Partners: PWD (WR), wherever the basin includes a river, canal or tank under its control, and [other local bodies, TUDA or UDD, TDMA] (Clause 11.4.1).
- Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
- Links to other basins: [for example the receiving river, khal or chhara corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).
11A.3 Team
- The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
- The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.
11A.4 Tasks
Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.
Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):
- (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
- (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
- (c) waterbodies: every tank, pukur, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
- (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
- (e) outfalls, rivers and embankments: outfall invert levels, on a named datum, against the warning, danger and high flood levels of the receiving river at the nearest CWC site and its recorded peaks, with any State gauge kept as a separate series and any conflict between published values stated; embankment crest levels; the sluices and flap gates in the embankments, among them the Katakhal double-barrel sluice, with their sills, gate types, closing levels and operating rules; the flood pumps and pumping stations on the outfalls, with their installed and working capacities, discharge pipelines, sump volumes and standby power; the levels of the ungauged Katakhal and Akhaura canal by survey; the stage–storage of the receiving pukurs, dighis and lunga storage; past breaches and leaks of the embankments; the release records of the Dumbur reservoir; and, at every border reach, the statement that no downstream level is known;
- (f) rainfall and water levels: all available records (IMD, through its Meteorological Centre Agartala, with its two stations in Extremes, Agartala (A) (42724) and Kailashahar (A) (42618), and the stations named in its press releases of August 2024, among them Agartala Aero, Met Agartala (ARG/AWS), Teliamura ARG, Bagafa and Bagafa AWS, Belonia and Belonia ARG, KVK South, KVK Dhalai and Gandacherra AWS; the rain gauges at CWC's river sites, among them Sonamura Mohanbhog, Gajaria, Amarpur, Belonia, Manughat, Kailashahar, Kumarghat, Nutanbazar and Kadamtala; the State's automatic rain gauges, among them the DM Office and Secretariat gauges in Agartala (owners, logging intervals and archives [TBC]); the rain and level sensors of the Agartala Municipal Corporation's Integrated Command and Control Centre (as reported); and the ten automatic rain gauges that IMD is to add in Agartala and other urban areas (TDMA's monsoon checklist of 2026, as quoted) [TBC]), including the 22 August 2024 (Agartala Aero 23 cm in the 24 hours to 08:30 IST on 22 August, IMD, with the Haora at the CWC Haora site at 12.42 m the same day, as reported, in the State's flood of record, whose largest measured day was 49 cm at Bagafa, IMD), 17–19 June 2022 (the Agartala urban flood, with about 200 mm in 3 hours by the Mayor's account and 145 mm or 155 mm in 24 hours in other reports, a conflict, all as reported, no IMD hourly value found, and the Haora at 10.82–10.85 m at Jahar Bridge against a danger level of 10.50 m and at 10.72 m at the CWC site against 10.70 m, as reported), 31 May 2025 (about 200 mm in 3 hours at Agartala by the account of the Mayor and officials, with one death in a manhole, as reported; no IMD hourly value found), 13 June 2018 at Kailashahar (the Manu at 25.95 m at the CWC site, 0.16 m above its high flood level of 1993, and about 21,000 people homeless in the town, as reported; no hourly town rainfall found) and 22–24 August 2026 (Chandrapur, Baldakhal and Aralia in Agartala flooded, and the Haora at 10.72 m at 08:00 on 24 August against a danger level of 10.70 m, as reported; no rainfall value found) events;
- (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
- (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
- (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
- (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.
Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.
Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).
Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the 22 August 2024 (Agartala Aero 23 cm in the 24 hours to 08:30 IST on 22 August, IMD, with the Haora at the CWC Haora site at 12.42 m the same day, as reported, in the State's flood of record, whose largest measured day was 49 cm at Bagafa, IMD), 17–19 June 2022 (the Agartala urban flood, with about 200 mm in 3 hours by the Mayor's account and 145 mm or 155 mm in 24 hours in other reports, a conflict, all as reported, no IMD hourly value found, and the Haora at 10.82–10.85 m at Jahar Bridge against a danger level of 10.50 m and at 10.72 m at the CWC site against 10.70 m, as reported), 31 May 2025 (about 200 mm in 3 hours at Agartala by the account of the Mayor and officials, with one death in a manhole, as reported; no IMD hourly value found), 13 June 2018 at Kailashahar (the Manu at 25.95 m at the CWC site, 0.16 m above its high flood level of 1993, and about 21,000 people homeless in the town, as reported; no hourly town rainfall found) and 22–24 August 2026 (Chandrapur, Baldakhal and Aralia in Agartala flooded, and the Haora at 10.72 m at 08:00 on 24 August against a danger level of 10.70 m, as reported; no rainfall value found) events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.
Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).
Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.
Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on groundwater recharge, which is not a design objective in Tripura, where the stage of extraction is 9.48% and every assessment unit Safe (CGWB, State compilation of 2025, as quoted), and which is credited only on tested, flat tilla tops (Clause 4.11, tilla rule), waterlogging where the water table lies within 2 m of the surface, as it does across much of the valley floors after the monsoon (0.22–6.64 m below ground in West Tripura in November 2017; CGWB), the stability of tilla slopes, cuts and the hill ranges, where water put into fill or weathered rock raises the pore pressure, and the iron-rich shallow groundwater, with up to 4.99 ppm of iron, which clogs infiltration media; effect on downstream basins and the receiving river, khal or chhara; and who benefits.
Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).
Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).
Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).
Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.
Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.
Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).
11A.5 Deliverables
Table 11A.1 — Deliverables
| No. | Deliverable | Task | Due (months from start) |
|---|---|---|---|
| D1 | Inception report, data inventory and survey plan | 1 | [ ] |
| D2 | Data report and data sets (Annex 11D) | 2 | [ ] |
| D3 | Model build report and model files | 3 | [ ] |
| D4 | Calibration and validation report | 4 | [ ] |
| D5 | Scenario results, hazard maps and level-of-service assessment | 5, 6 | [ ] |
| D6 | Options report, with basin inputs for site design | 7, 8 | [ ] |
| D7 | Draft BSMP with draft CIP, for consultation | 9–12 | [ ] |
| D8 | Final BSMP, consultation log, approval package and open-data release | 13 | [ ] |
11A.6 Ownership and publication
All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.
Annex 11B — Basin lists and boundaries for Tier A bodies
Supports Clauses 11.3 and 11.4 of Chapter 11.
To be prepared. This annex will contain the list of basins for every Tier A body, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs the list of Tier A bodies (Annex 1A), a DEM of the accuracy of Clause 11.5.1, flown again over the lungas, flood plains and tilla cuts after any large flood or landslide, the drain network of every drain-owning body (the Agartala Municipal Corporation and the other ULBs, Agartala Smart City Ltd, PWD (R&B), NHIDCL, PWD (WR) and PWD (DWS)), the drain register of each town giving every reach its owner, its land status (khas or government, private or Council land) and whether it is a vested municipal drain, an embankment drain or sluice, or a natural chhara or lunga, the embankments of PWD (WR) with every sluice, its sill, closing level and operating rule, the flood pumps and pumping stations on the outfalls with their working capacities, the pukurs, dighis and beels with their stage–storage and outlet levels and their land classes in the Revenue Department's records, the interception points of the drains that feed the treatment plants, the release reach below the Dumbur reservoir, the embankment breach and leakage paths, and the landslide and flood hazards mapped by TDMA, GSI and PWD (WR) (other likely sources: Survey of India, CWC, CGWB, the Master Plan 2045 maps, the land records by district, sub-division, revenue circle and mouza, and the TTAADC's land records [TBC]). No basin map of any Tripura town was found. Until the annex is published, the basins of Agartala (the central saucer and the Akhaura canal; the Katakhal; the Haora), Kailashahar, Belonia, Udaipur, Amarpur and Sonamura, Dharmanagar, Khowai and Teliamura, Kamalpur, Santirbazar, Bagafa and Sabroom, the hill-range corridors and Rudrasagar named in Clause 11.3.3 are at least those named there; other Tier A bodies define their basins in their first BSMP (Clause 11.3.3); on landslide ground, in breach paths, on the release reach and on the active flood plains the hazard screening of Clause 11.3.3 comes first; and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP.
Table 11B.1 — Basins named in Clause 11.3.3 (provisional)
| Tier A body or area | Basin | Note from Chapter 11 |
|---|---|---|
| Agartala Planning Area (Agartala Municipal Corporation, TUDA) | Central saucer between the Haora embankment and the Katakhal, with the Akhaura canal | Sub-area TR-A (Clause 2.3.6(c)); local rain with the outfalls shut a design case (Clause 5.8.5(b)); flood pumps and pipelines; drains that carry sewage in the 1D network |
| Agartala Planning Area (as above) | Katakhal to the double-barrel sluice, with the Kalapania Khal | No gauge: surveyed flood marks, the Haora level until surveyed [TBC]; interception points of the treatment plants on its banks |
| Agartala Planning Area (as above) | Haora, 414 km², from the Baramura range to the border | Upper catchment in TR-E; PWD (WR) flood-plain localities and Chandrapur; Haora at the CWC Haora site, 12.42 m, as boundary (datum not stated) |
| Kailashahar | Town behind the Manu embankment | Outfalls once surveyed [TBC]; Manu at Kailashahar (CWC) as boundary, with the conflicting danger levels stated; record check of Clause 2.3.6(h) |
| Belonia | Town behind the Muhuri embankment | Muhuri at Belonia, 18.81 m (2024), as boundary; TR-D1 record floor of 490 mm |
| Udaipur, Amarpur, Sonamura | Towns on the Gomati below the Dumbur reservoir | Largest recorded release, or spillway capacity, as boundary (Clause 5.8.5(d)); State and CWC gauges stated separately; tanks kept as storage |
| Dharmanagar | Town on the Juri | Juri at Nutan Bazar, 20.66 m (2024), as boundary |
| Khowai, Teliamura | Towns on the Khowai | Khowai at Khowai, 28.005 m (2004), as boundary; governing cell of TR-B |
| Kamalpur | Town on the Dhalai | Dhalai at Kamalpur, 33.85 m (1984), as boundary; governing cell of TR-B1 |
| Santirbazar, Bagafa, Sabroom | Towns of the Muhuri–Feni south | Landslide ground mapped; Feni a border river with no working gauge reported; TR-D1 record floor |
| Hill-range corridors | NH-8, NH-108B and NH-208 through the ranges | Hazard screening first; culverts and silt traps (Clause 6.3.6(k) and (m)) |
| Rudrasagar | Catchment of the Ramsar lake at Neermahal | No new storm drain into it without interception (Clause 8.9); lake level as boundary |
| Other Tier A bodies and ULBs | To be defined in the first BSMP | Clause 11.3.3 |
Table 11B.2 — Attributes of the basin boundary layer (layout)
| Field | Type | Content |
|---|---|---|
| BASIN_ID | Text | Basin identifier |
| NAME_EN, NAME_BN | Text | Basin name in English and Bengali |
| TIER_A | Text | Tier A body or bodies in the basin |
| OUTFALL | Text | Outfall to the sea, river or major waterbody (Clause 11.2) |
| AREA_KM2 | Real | Basin area, km² |
| LEAD_AUTH | Text | Lead Authority (Clause 11.4.1) |
| PARTNERS | Text | Partners, including PWD (WR) where it applies |
| LINKS | Text | Diversions to and from other basins (Clause 11.3.2) |
| BSMP_STAT | Text | None / in preparation / draft published / approved |
| BSMP_DATE | Date | Date of approval of the current BSMP |
| REVIEW_DUE | Date | Date of the next review (Clause 11.11.2) |
Annex 11C — Depth–damage curves for Tripura building types
Supports Clause 11.8.2 of Chapter 11.
To be prepared. This annex will contain depth–damage curves for the main building types of Tripura cities, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the 22 August 2024 (Agartala Aero 23 cm in the 24 hours to 08:30 IST on 22 August, IMD, with the Haora at the CWC Haora site at 12.42 m the same day, as reported, in the State's flood of record, whose largest measured day was 49 cm at Bagafa, IMD), 17–19 June 2022 (the Agartala urban flood, with about 200 mm in 3 hours by the Mayor's account and 145 mm or 155 mm in 24 hours in other reports, a conflict, all as reported, no IMD hourly value found, and the Haora at 10.82–10.85 m at Jahar Bridge against a danger level of 10.50 m and at 10.72 m at the CWC site against 10.70 m, as reported), 31 May 2025 (about 200 mm in 3 hours at Agartala by the account of the Mayor and officials, with one death in a manhole, as reported; no IMD hourly value found), 13 June 2018 at Kailashahar (the Manu at 25.95 m at the CWC site, 0.16 m above its high flood level of 1993, and about 21,000 people homeless in the town, as reported; no hourly town rainfall found) and 22–24 August 2026 (Chandrapur, Baldakhal and Aralia in Agartala flooded, and the Haora at 10.72 m at 08:00 on 24 August against a danger level of 10.70 m, as reported; no rainfall value found) floods (Revenue Department and TDMA damage assessments, insurers), and replacement costs (Public Works Department schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.
Table 11C.1 — Depth–damage curve (layout, one table per building type)
| Depth of water above floor level (m) | 0 | 0.25 | 0.5 | 1.0 | 1.5 | 2.0 | 3.0 |
|---|---|---|---|---|---|---|---|
| Structure damage (% of replacement cost) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Contents damage (% of contents value) | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Building type, source and year of costs | ______ |
11C.1 Use in option assessment
Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:
EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))
The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.
Annex 11D — BSMP data and model publication standard
Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.
11D.1 What is published, and when
Table 11D.1 — Items to be published
| Item | Format | At draft (Clause 11.10.1) | At approval (Clause 11.10.2) |
|---|---|---|---|
| BSMP report, with the level-of-service assessment and options | Searchable PDF | Yes | Yes, final |
| Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) | GeoTIFF rasters; extents also as GeoPackage polygons | Yes | Yes |
| Capital Improvement Programme | CSV and PDF | Draft | Yes |
| Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate | GeoPackage and CSV | Yes | Yes |
| Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, river, khal, pukur and embankment levels, sluices and pumping stations, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) | GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) | Summary | Yes, except security-sensitive asset details |
| Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log | Native format, zipped | No | Yes |
| Calibration and validation report | Searchable PDF | Yes | Yes |
| Consultation log of comments and responses | PDF or CSV | — | Yes |
11D.2 Formats and references
- (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
- (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 river datums of the CWC level-forecasting and level-monitoring sites on the Haora, the Gumti (Gomati), the Manu, the Khowai, the Dhalai, the Juri, the Muhuri and the Burima (not stated in any source found [TBC]), of the State gauges, such as the gauge at Jahar Bridge on the Haora and those at Udaipur and Amarpur on the Gomati, of the embankment crests, sluice sills and gate-closing levels of PWD (WR), of the levels of the Dumbur reservoir (full reservoir level given as 93.55 m, as reported, on a datum not stated), and of the flood marks surveyed on the Katakhal, the Akhaura canal and the other ungauged channels, streams, ponds and tanks shall be stated in every data set that carries levels.
- (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
- (d) Hazard map files shall be named
<basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for examplehaora_d_1_depth.tif. - (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.
11D.3 Metadata
Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.
11D.4 Withholding and personal data
- (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
- (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.
11D.5 Licence, viewer and versions
- (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
- (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
- (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
- (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).
Form 11-1 — Annual implementation report
Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.
Draft form — Tripura Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each monsoon season, by 31 March (Clause 11.11.3).
Table 11F.1 — Form 11-1, Section A: Basin and plan
| No. | Field | Entry |
|---|---|---|
| A1 | Basin; Lead Authority; partners | ______ |
| A2 | BSMP version and date of approval | ______ |
| A3 | Reporting year (1 April to 31 March) | ______ |
| A4 | Date of publication (by 31 March) and web address | ______ |
Table 11F.2 — Form 11-1, Section B: CIP progress
| CIP rank | Work | Agency | Cost in CIP (₹) | Spent this year (₹) | Spent to date (₹) | Status | Expected completion |
|---|---|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| ______ | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)
| Regional facility or tank | Volume credited to sites (m³) | Volume delivered (m³) | Fees received (₹) | Fees spent (₹) | Fees held, with year received |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
| Basin total: volume owed and delivered | ______ | ______ | ______ | ______ | ______ |
Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))
| No. | Item | Planned | Done | Date completed |
|---|---|---|---|---|
| D1 | Desilting of drains and canals (length, km; volume, m³) | ______ | ______ | ______ |
| D2 | Tank and pukur desilting and restoration (tanks, number; storage restored, m³) | ______ | ______ | ______ |
| D3 | Gate tests (number of gates) | ______ | ______ | ______ |
| D4 | Pump station duty tests (number of stations) | ______ | ______ | ______ |
| D5 | Tank operating rules reviewed with the custodian (number) | ______ | ______ | ______ |
| D6 | Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) | ______ | ______ | ______ |
Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service
| Event (dates) | Rainfall compared with the design depths (Clause 10.16.2(a)) | Level-of-service element (Table 11.2) | Location | Met (yes / no) | Event report reference (Clause 10.16.2) |
|---|---|---|---|---|---|
| ______ | ______ | ______ | ______ | ______ | ______ |
Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off
| No. | Field | Entry |
|---|---|---|
| F1 | Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) | ______ |
| F2 | Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) | ______ |
| F3 | Next 10-year review due (date) | ______ |
| F4 | Officer of the Lead Authority: name, designation, signature, date | ______ |