Chapter 10Submittals, Review, Operation & Maintenance and Enforcement
10.1 Purpose and scope
10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:
- (a) the submittal stages and their contents (Clauses 10.3–10.4);
- (b) the compliance calculator (Clause 10.5);
- (c) professional certification and review (Clauses 10.6–10.7);
- (d) construction inspection and as-built certification (Clauses 10.8–10.9);
- (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
- (f) handover of public assets (Clause 10.14);
- (g) enforcement (Clause 10.15); and
- (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).
10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.
10.2 Definitions
| Term | Meaning in this chapter |
|---|---|
| Submittal | A set of documents lodged with the Authority at one of the stages of Clause 10.3. |
| Drainage report | The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4. |
| Stormwater facility | Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private. |
| Hold point | A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8). |
| As-built certificate | The certificate of Clause 10.9 that the facility was built as approved and performs as designed. |
| Owner | The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset. |
| O&M plan | The operation and maintenance plan of Clause 10.11. |
| Facility register | The public register of facilities of Clause 10.17. |
Other terms are defined in Clause 1.4.
10.3 Submittal stages
10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Tripura Building Rules 2017 (Table 10.1):
Table 10.1 — Submittal stages and linked approvals
| Stage | Submittal | When | Linked approval |
|---|---|---|---|
| 0 | Pre-application meeting and Form 1-1 (Applicability Determination) | Before the planning permission or layout application | None (advisory record) |
| 1 | Preliminary drainage report | With the planning permission or layout application | Planning permission / layout approval |
| 2 | Final drainage design | Before building permit, or before commencement where the permit is issued with the planning permission | Building permit / commencement |
| 3 | Construction inspections at hold points | During construction | None (records filed) |
| 4 | As-built certificate and verification tests | Before the completion certificate | Completion / occupancy certificate |
| 5 | Maintenance declaration registered, or handover of public assets | Before or with the completion certificate | Completion certificate; asset acceptance |
| 6 | Annual declarations and inspection reports | Every year after completion | Continuing compliance |
10.3.2 Stage 0 is mandatory for:
- (a) sites of 2 ha or more;
- (b) sites in a flood-sensitive catchment;
- (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
- (d) sites draining to a tidal outfall or adjoining a waterbody.
For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.
10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.
10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.
10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.
Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.
Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the TBR 2017 steps a Tripura applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.
10.4 Required contents and checklists
10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:
- (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
- (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
- (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
- (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
- (e) the pre-development condition and hydrologic method (Chapter 3);
- (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
- (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
- (h) the downstream extent and tailwater case (Chapter 5);
- (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
- (j) the land reserved for facilities and maintenance access (Clause 10.13).
10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:
- (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
- (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
- (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
- (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
- (e) construction drawings, details and specifications of every facility;
- (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
- (g) the hold-point schedule (Clause 10.8);
- (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
- (i) the model input files and the GIS data of Clause 10.4.4; and
- (j) the certificates of Clause 10.6.
10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.
10.4.4 Digital submittal.
- (a) Reports and drawings shall be submitted as searchable PDF.
- (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
- (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for the whole State, which lies between about 22°56′ and 24°32′ N and 91°09′ and 92°20′ E, as quoted from State pages, inside zone 46N's 90°–96° E; Agartala is given at 91°30′ E or 91°17′ E, a conflict, both in 46N; every project uses 46N for all its layers), with attributes as listed in Annex 10B.
- (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC level-forecasting and level-monitoring sites on the Haora, the Gumti (Gomati), the Manu, the Khowai, the Dhalai, the Juri, the Muhuri and the Burima (not stated in any source found [TBC]), of the State gauges, such as the gauge at Jahar Bridge on the Haora and those at Udaipur and Amarpur on the Gomati, of the embankment crests, sluice sills and gate-closing levels of PWD (WR), of the levels of the Dumbur reservoir (full reservoir level given as 93.55 m, as reported, on a datum not stated), and of the flood marks surveyed on the Katakhal, the Akhaura canal and the other ungauged channels, streams, ponds and tanks used in Chapter 5 shall be stated.
10.4.5 Summary of forms used in submittals (Table 10.2):
Table 10.2 — Forms used in submittals
| Form | Title | Stage |
|---|---|---|
| 1-1 | Applicability Determination | 0 or 1 |
| 1-2 | Variance / Waiver Request | 1 |
| 2-1 | Design Rainfall Sheet | 1, 2 |
| 10-1 | Drainage Report Checklist | 1, 2 |
| 10-2 | Compliance Calculator Summary | 1, 2, 4 |
| 10-3 | Professional Design Certificate | 1, 2 |
| 10-4 | Hold-Point Inspection Record | 3 |
| 10-5 | As-built Certificate | 4 |
| 10-6 | Maintenance Declaration | 5 |
| 10-7 | Annual Maintenance Declaration and Inspection Report | 6 |
| 10-8 | Asset Handover Certificate | 5 |
Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Tripura has no notified design return period or design storm for its urban drains. No document found, among them the ADB-funded Agartala City Urban Development Project's initial environmental examination (project 53262-001, draft of November 2020), the State's filings before the National Green Tribunal and the press, states a return period, design intensity, runoff coefficient or time of concentration for any Tripura drain; the TBR 2017 defer to "the latest edition of National Building Code and other relevant Indian Standards" for what they do not cover (r.3A), and roads follow IRC:SP:42-2014 and IRC:SP:48. ADB's drainage upgrade for Agartala is reported to aim to cut the time the city takes to drain "from one to two hours to about 15–30 minutes" (as reported); its project report was not read [TBC]. The rainfall studies do not supply a design storm either. No intensity–duration–frequency relation with published constants was found for any Tripura station; IMD's national study (Das et al., 2022) prints no panel for any Tripura station, and its North-East panels, all for stations outside Tripura, are not used; and no CWC Flood Estimation Report covers any part of the State, which by elimination lies in subzone 2(c), "Barak and others", for which CWC has published no report (this Manual's reading [TBC]). IMD's Extremes holds two Tripura stations, Agartala (A), whose largest day is 257.2 mm (22 July 1993), and Kailashahar (A), 377.2 mm (6 June 1993). The storms on record exceed the estimates: Bagafa (IMD) recorded 49 cm in the 24 hours to 08:30 IST on 22 August 2024 (IMD press release, Annexure I), more than every NIH-DHAARA 100-year 24-hour depth in the State, the largest of which is 435.1 mm at Sabroom, and Belonia's 32 cm and Amarpur's 31 cm on 20 August 2024 exceed their cells' 50-year depths; the claims of "about 200 mm in 3 hours" at Agartala on 17–19 June 2022 and 31 May 2025 are press reports with no IMD value behind them (as reported). The State's design values are therefore those of Chapter 2: NIH-DHAARA as modified by Clause 2.3.6, raised to the governing cell of the site's sub-area (Clause 2.3.6(c)), with the 2(a) ratio as a lower bound on the short durations (Clause 2.3.6(f)), the short-storm floors of Clause 2.3.6(g) and the zone-bounded record check of Clause 2.3.6(h), which sets 490 mm at 1% AEP in sub-area TR-D1; and each submission must state its own design basis on Form 2-1. Form 2-1 and Form 10-2 ensure that every design states its inputs.
10.5 Compliance calculator
10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:
- (a) applies the applicability tests of Clause 1.5;
- (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
- (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
- (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
- (e) on alternative S-2, gives the permissible site discharge for each AEP; and
- (f) produces the Compliance Calculator Summary (Form 10-2).
10.5.2 Use.
- (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
- (b) On the design-aid route, the calculator may be the only storage calculation.
- (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.
10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.
10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.
Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Tripura calculator serves Tier B authorities in particular, where it may be the whole calculation.
10.6 Professional certification
10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or UDD:
- (a) Tier A sites of 1 ha or more;
- (b) any site in a flood-sensitive catchment;
- (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
- (d) any pumped facility, tide gate or regional facility.
10.6.2 Empanelment criteria shall be issued by UDD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.
10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:
- (a) the design complies with this Manual, except for variances listed and approved;
- (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
- (c) the models submitted reproduce the results reported.
10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.
10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.
Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the TBR 2017 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.
10.7 Review procedure and timelines
10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.
10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:
- (a) 15 working days of acceptance for a first submittal; and
- (b) 10 working days of acceptance for a resubmittal.
10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.
10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the UDD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.
10.7.5 Concurrent clearances. Where the consent of PWD (WR), as owner, for any work that cuts, crosses, alters or discharges through an embankment, sluice or flood-protection work in its charge, or for a work on a river in its charge (no Tripura embankment or drainage statute was found, so the consent is the owner's [TBC]), the written permission of the Municipality to connect a private drain to a municipal drain (Tripura Municipal Act, 1994, s.161), the prior approval of the State Government under which the Local Body may allow a canal, pond, water body, wetland, jhora, stream, drain or culvert to be filled (TBR 2017, r.9(3)), the decision of the District Magistrate and Collector on a change in the classification of land recorded as a water body under the Diversion of Land Rules, 2025 (the procedure after their amendment of 6 March 2026 was not established [TBC]), the permission of the Wetland Authority of Tripura for a work in or draining to a notified wetland or Rudrasagar, a Ramsar site (the CAG faulted ring roads built there without it, Audit Report for the year 2021-22), the consent of PWD (R&B) or NHIDCL for a discharge to a side drain or culvert of one of their roads, the consent of TSPCB for a discharge that carries effluent, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (in Agartala, the Agartala Municipal Corporation, Agartala Smart City Ltd, PWD (R&B), PWD (WR) or PWD (DWS)), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.
10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.
10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.
Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.
10.8 Construction inspection
10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:
- (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
- (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
- (c) the infiltration tests of Clause 10.9.3;
- (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
- (e) pumps and controls, at commissioning.
10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.
10.8.3 Protection during construction.
- (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
- (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
- (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.
Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.
Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.
10.9 As-built certification
10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:
- (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
- (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
- (c) the completed hold-point records (Form 10-4); and
- (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).
10.9.2 Acceptance. The as-built facility is accepted where:
- (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
- (b) the outlet dimensions and inverts match the approved design; and
- (c) the re-run shows compliance with every criterion of Chapters 4 and 5.
Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.
10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.
10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.
Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.
10.10 Maintenance declarations and covenants
10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:
- (a) identify each facility, its location and the approved O&M plan;
- (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
- (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
- (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
- (e) be registered so that it runs with the land and is disclosed to purchasers.
10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.
10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.
10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.
Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Tripura because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Tripura extreme rainfall occurs.
10.11 O&M plans
10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:
- (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
- (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
- (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
- (d) inspection checklists matching Form 10-7;
- (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
- (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
- (g) safety measures for confined spaces, deep water and public access;
- (h) access routes and equipment needed (Clause 10.13);
- (i) an annual cost estimate and who pays it; and
- (j) the records to be kept, and for how long.
10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.
Commentary. Tripura has no dated State or municipal order fixing pre-monsoon desilting. The Agartala Municipal Corporation desilts its drains every year, ward by ward and with mechanised "super sucker" machines, under a flood strategy it dates to 2018 (as reported); PWD (WR) runs a pre-monsoon programme of embankment works, of ₹150 crore on 44 embankments on 12 rivers in 2025 (as reported), and cleaned the Katakhal and built a 650-m embankment on the Haora in March 2026, with the Corporation and Agartala Smart City Ltd (as reported); and TDMA's checklist for the monsoon of 2026 includes "urban drain de-silting", sluice gates and 42 vulnerable embankment points (as quoted) — none with a date. The drains are run by several hands, and no order divides them: the drains, tanks and water courses vest in the Municipality "unless the State Government otherwise directs by a notification" (Tripura Municipal Act, 1994, s.91), which must have them "cleansed, flushed and emptied from time to time" (s.157) and may, in "sudden waterlogging", drain water across private land "without prior service of any notice" (s.160); the UDD and PWD (DWS) built the AMRUT works and PWD (R&B) the major road drains (CAG, Audit Report for the year 2019-20); Agartala Smart City Ltd built storm drains and flood pumps; and PWD (WR) holds the embankments and the Katakhal double-barrel sluice. The flood pumps of Agartala, 18 flood pumps and 6 diesel pumps in August 2024, discharge by pipeline to the Katakhal and the Haora, and the Corporation watches the city through an Integrated Command and Control Centre with rain and level sensors (as reported); no operating rule for the pumps or for the Katakhal sluice, linking them to a river stage or a rainfall warning, was found [TBC]. Sewage shares the drains: Agartala's treatment plants are fed by interception and diversion of drains, "a temporary measure till the conveyance system is laid" (Agartala Smart City Ltd, in the State affidavit to the National Green Tribunal, 6 July 2026), so the pukurs and channels that hold storm water mixed with sewage need their own operating rules. The Dumbur reservoir upstream of Udaipur and Sonamura is operated for power, and its release rules and warning procedures were not found [TBC]. No operating rule for any sluice, flap gate or pumping station in a Tripura town, linking it to a river stage, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.
10.12 Inspection frequencies
10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:
Table 10.3 — Minimum owner inspection frequencies
| Facility type | Routine | Pre-monsoon (by 31 March) | After a heavy-rainfall event |
|---|---|---|---|
| Retention / infiltration (soakaways, trenches, bioretention, permeable paving) | Every 6 months | Yes | Yes |
| Surface detention basin or multi-use open space area | Every 6 months | Yes | Yes |
| Underground or podium detention tank, gravity outlet | Every 6 months | Yes | Yes |
| Pumped detention, pumps and controls | Monthly test run | Yes, with full duty test | Yes |
| Flap / tide gate, non-return valve | Every 3 months | Yes, with seal test | Yes |
| Gross pollutant trap / first-flush device | Every 3 months | Yes | Yes |
| Private drains and inlets | Every 6 months | Yes | — |
A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Tripura, the pre-monsoon inspection of sluice gates, flap gates, non-return valves, screens, silt traps and pumped facilities, including the Katakhal sluice, the gates and flood pumps on Agartala's outfalls to the Haora and the Katakhal and the gates and pumps on every outfall through an embankment of PWD (WR), with the desilting of every drain, nala (Bengali নালা: a water channel), khal (Bengali খাল: a canal or channel) and chhara (Bengali ছড়া: a stream), the clearance of inlets, silt traps, screens and the silt traps at the foot of every tilla (Bengali টিলা: a hillock), and the pump duty and gate seal tests, shall be completed by 31 March; sluice gates, flap gates and pumped facilities, with their standby power and fuel, shall be certified ready on the same date, with every gate on an outfall to a river operated through its full travel, by or with PWD (WR) where the gate is in its charge, because the season of this Manual begins on 1 April and the storms of April and May are among the State's largest. Pumps, their standby power, gates and screens shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall to a river until the river at the governing CWC site has fallen below its danger level and the gates have been reopened, if that is later. Inlets, silt traps, screens and tilla-foot traps shall be cleared again by 31 May, of the silt, plastic and debris of the April and May storms, before the south-west monsoon arrives, and every public drain, nala, khal and chhara, inlet, trap and screen in every town shall be cleared of the silt and debris of the season, and its silt depths surveyed, by 15 November.
10.12.2 Authority inspections. The Authority shall inspect:
- (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
- (b) a random sample of at least 10% of other facilities each year.
10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).
Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.
Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October, and its first two months bring some of the State's largest storms: Kailashahar's wettest month on record is May (1,175.0 mm in 1991) and its next is April (1,012.8 mm in 1977); its April 24-hour record is 257.1 mm (19 April 2004) and its May record 231.2 mm (3 May 1993); and Agartala's April record is 198.0 mm (11 April 2007), with a wettest May of 723.8 mm (1984) (IMD, Extremes). The rivers rise with them: the Dhalai at Kamalpur and the Juri at Nutan Bazar set their high flood levels, 33.85 m and 20.435 m, on 15 May 1984 (CWC levels as transcribed by SANDRP, as reported); Cyclone Remal brought 252.4 mm to Unakoti, 248.3 mm to Dhalai and 242 mm to North Tripura district in 24 hours on 27–28 May 2024 (district values, as reported); and Agartala flooded on 31 May–1 June 2025 (as reported). ADB's initial environmental examination for Agartala, citing the district disaster management plan of 2016-17, records cyclones "during April & May and during October & November in terms of Kalbaisakhi" (wording as printed) and a summer that "starts from middle of March" (2020). NDMA (2010) sets 31 March for pre-monsoon desilting nationally, and this Manual keeps that date. One date applies statewide, the same as in the neighbouring North-East editions of this series, because the Manu, the Juri and the Longai run north into the same Kushiyara plain as the Barak valley, and one calendar keeps catchments that cross a border on one cycle of inspection (set by this Manual). No Tripura order fixes a date for drains: the Agartala Municipal Corporation desilts every year, PWD (WR) runs a pre-monsoon programme of embankment works and TDMA's checklist for the monsoon of 2026 includes "urban drain de-silting", none with a date (as reported or as quoted); PWD (WR)'s programme is for its embankments, while this Manual's 31 March covers the drains, sluice gates, flap gates and pumps of the drainage system. The research for this edition suggested testing pumps and gates by 15 April; that date is not used, because the April storms come before it (Agartala 198.0 mm on 11 April 2007), and this Manual therefore takes 31 March for desilting, the clearance of inlets, silt traps and screens, the pre-monsoon inspection, the annual declaration and the readiness of gates, pumps and standby power, with no later readiness date. The south-west monsoon arrives about the first week of June: its normal onset over Tripura is about 5 June, inferred from two reports of the Meteorological Centre Agartala's dates, 7 June 2026 "two days later than its normal" and 26 May 2025 "10 days before its normal date", while another report gives "June 10" (all as reported, a conflict; IMD's revised normals were not read [TBC]). Inlets, silt traps, screens and tilla-foot traps are therefore cleared again by 31 May, after the April and May storms and before the onset. The date of the monsoon's withdrawal from Tripura was not obtained [TBC] (over the North East it was reported "close to its normal date" on 15 October 2026), but storms continue to the end of October: Agartala 183.6 mm (11 October 1989) and Kailashahar 182.0 mm (9 October 1986) (IMD); pumps, gates and screens are therefore kept on standby to 31 October (Figure 10.3). Large falls also come outside the season: Agartala 142.2 mm on 19 February 1993 and 98.6 mm on 1 March 1960, Kailashahar 112.4 mm on 25 March 1994, and Agartala 104.6 mm on 9 November 1955 and Kailashahar 104.2 mm on 10 November 1986 (IMD); and the drains fill with silt during the season, so every town clears its drains a second time, and surveys their silt depths, by 15 November. December to February is the works window. The post-event inspections of Table 10.3 cover storms at any time of year. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.
10.13 Maintenance access
10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.
10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.
10.13.3 Underground facilities. Tanks shall have:
- (a) an access opening over the inlet, the outlet and each chamber;
- (b) fixed ladders or steps, and ventilation for confined-space entry;
- (c) a sump or low point for sediment removal; and
- (d) headroom sufficient for manual cleaning.
10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.
10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.
Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Tripura cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.
10.14 Handover of public assets to the ULB
10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:
- (a) the as-built certificate (Clause 10.9) has been accepted;
- (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
- (c) the land, or an easement over it, has been transferred to the ULB;
- (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
- (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.
10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.
10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.
10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.
Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Tripura drainage show up only in the first monsoon.
10.15 Enforcement
10.15.1 Offences. The following are contraventions of this Manual:
- (a) building without an approved drainage design where one is required;
- (b) building a facility other than as approved;
- (c) removing, filling, covering, reducing or changing the use of a facility without approval;
- (d) failing to maintain a facility, or to submit Form 10-7;
- (e) a sewage connection to a storm drain;
- (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
- (g) obstructing a natural drainage path or major-system flow path; and
- (h) false or negligent certification.
10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):
Table 10.4 — Graduated enforcement response
| Step | Action |
|---|---|
| 1 | Written notice stating the contravention, the clause breached, the remedy and a compliance period. |
| 2 | Stop-work order, or withholding of the completion certificate, for development not yet complete. |
| 3 | Penalty under the applicable Act or rules. |
| 4 | Works in default by the Authority, with the cost recovered from the owner. |
| 5 | Disconnection of the private drain connection to the public system, where this causes no hazard to others. |
| 6 | Report of the certifying professional to the registering authority, and suspension from the empanelled list. |
10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.
10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.
10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.
Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Tripura Building Rules 2017 are made and from the municipal Acts. The graduated steps are set by this Manual. In Tripura the courts, the National Green Tribunal and the CAG have become the working regulators of drains and water bodies. The High Court of Tripura, in its suo motu WP(C)(PIL) No. 06 of 2026 on NH-108B and NH-208, recorded the District Legal Services Authority's finding of "No proper drainage system … water logging everywhere" and "culvert block by silt, vegetation, debris", and directed NHIDCL to report every two weeks, a BRO audit by 30 January 2027 and a Union inquiry by 1 December 2026 (judgment of 8 September 2026); in WP(C)(PIL) No. 2 of 2014 (Bibash Ch. Saha v. State of Tripura), on ponds filled and walled at Kalyan Sagar, Matabari, it directed the State to notify a guideline on protecting water bodies within six months and 110 m of cement embankment to be demolished (as cited from a third-party copy dated 16 August 2016); in an order of 28 June 2017 it took up the encroachment of Agartala's water bodies on a zone-wise affidavit of the Agartala Municipal Corporation (case number unconfirmed, as cited); and in suo motu WP(C)(PIL) No. 05 of 2017 it has watched the level of Rudrasagar (as reported). The Tribunal has dealt with the Haora as a polluted river stretch, now the State's only listed stretch, with in-situ treatment of five drains (O.A. No. 673 of 2018), the State's water bodies, of which 180 urban water bodies were identified and 30 prioritised (O.A. No. 325 of 2015, State report of 26 May 2020, as reported), and the sewage gap, where storm drains tapped to feed treatment plants are quoted as "not legal" and two plants were found on or near flood plain, where they "may lead to flooding of the STP and flowing of untreated sewage in the river during the monsoon" (O.A. No. 606 of 2018, order of 13 April 2026, as quoted in the State affidavit of 6 July 2026). The statutes reach drains and tanks but carry small penalties. Under the Tripura Municipal Act, 1994 a private drain may join a municipal drain only with the Municipality's written permission (s.161), an unauthorised drain into a municipal drain or water course may be demolished at the owner's cost (s.162), the Municipality may require "separate provisions … for drainage of sewage and other offensive matters as distinct from rain-water" (s.164), encroachment on municipal drains is dealt with under s.166, and a well or tank made "without the permission of the Municipality" may be filled up or demolished, with a fine of up to ₹2,000 (s.232), a nominal sum by today's values. The TBR 2017 bar the filling of any "canal, pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts" except by the Local Body with the State's prior approval for reasons recorded in writing (r.9(3)), and their self-certification route of 2025 waives inspection for low-risk buildings, with 10–15% of applications "randomly selected" (r.34(9)), so a false certificate is found only by that sample or by a flood. The Diversion of Land Rules, 2025, as amended on 6 March 2026, let a change in the classification of land be made by online self-declaration and revoked by the Competent Authority "within thirty working days" if made in contravention of s.20(3) and (4) of the Tripura Land Revenue and Land Reforms Act, 1960 (rules 3 and 4, as substituted); whether s.20 still bars the diversion of a water body was not established, and this Manual does not state the current procedure [TBC]. No embankment or drainage statute, and so no offence of cutting an embankment or operating a sluice, was found [TBC]. The CAG found drains without wire nets letting plastic waste reach the Haora and the Katakhal, with "frequent water logging … due to blockage of drains and canals by plastic waste" (Audit Report for the year 2022-23), ring roads built in Rudrasagar, a Ramsar site, without the Wetland Authority's permission, which "reduced the water level" (2021-22), ₹3.09 crore spent unfruitfully on the Kashari Cherra minor irrigation earth dam, eroded by heavy rain in September 2017 (2022-23), and the AMRUT works of Agartala implemented almost entirely by the UDD and PWD (DWS) rather than the Corporation (2019-20); no CAG audit of flood control, embankments, Agartala Smart City Ltd or storm drainage was found. This shows that a rule without routine enforcement does little, and that where the State has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.
10.16 Monitoring and post-event review
10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.
10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:
- (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
- (b) the stage of the receiving river (the Haora, the Gomati, the Manu, the Muhuri, the Juri, the Khowai or another) at the nearest CWC site, against its warning, danger and high flood levels, and, where it is gauged, at the outfall and inside the embankment, each on a named datum, with any reading of a State gauge, such as the Haora at Jahar Bridge or the Gomati at Udaipur, kept apart from the CWC levels; the level in the Katakhal, the Akhaura canal and any other ungauged khal, from a staff gauge where one exists or from surveyed flood marks; the times at which each sluice and flap gate on the outfall and on the drain upstream of it closed and reopened, among them the Katakhal sluice, the level in the receiving pukur, dighi or lunga storage, the hours each flood pump ran and the river it discharged to, any loss of power and the fuel used; any breach, leak or overtopping of an embankment, with its time and the level the water reached inside it; and the releases from the Dumbur reservoir that set the level of the Gomati, with the times of the warnings given;
- (c) flooded locations, depths and durations, with flood marks surveyed where possible;
- (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
- (e) recommended actions.
10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), TDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.
10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.
Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Tripura's floods have been counted more often than they have been reviewed, and the counts conflict. The floods of 19–24 August 2024, the State's flood of record in most basins and reported as the worst since 1983, killed 36 by the count of the Inter-Ministerial Central Team (as cited in a Lok Sabha answer) or about 38 by the Chief Minister's account in the Assembly, after earlier counts of 24 and 31; about 17 lakh people were affected, the number of relief camps rose from 450 to 822 as the days passed, and 2,032 landslip locations were reported (all as reported). The State put its preliminary losses at ₹14,247 crore and sought ₹7,080.55 crore of assistance from the National Disaster Response Fund in its memorandum of 13 September 2024 — a loss estimate and a request for assistance, not two estimates of one thing (as reported). On the night of 31 May 2025 a man died in a manhole in Agartala and about 1,300 families went to camps in West Tripura (as reported); the Agartala flood of 17–19 June 2022 sent 2,057 families, more than 10,000 people, to 39 camps by one account and 1,623 families, 7,109 people, by another, a conflict (as reported); and in June 2018 about 21,000 people were left homeless in Kailashahar when the Manu rose above its high flood level, with 173, 189 or 224 camps given in different reports (as reported). The benchmark is still the flood of 3–5 August 1983, with "about thirty" deaths and "around five lakh" people affected (Lok Sabha debates, as quoted). TDMA's final report on 2024 was not obtained [TBC]. No review of any flood in a Tripura town, and no record of flood extents, depths or durations kept by the Agartala Municipal Corporation, another ULB or TDMA, was found. The rainfall record shows why reviews need more than one gauge: on 20 August 2024 co-located gauges disagreed, Belonia 32 cm against Belonia ARG 25 cm and Belonia CWC 15 cm, Bagafa 38 cm against Bagafa AWS 13 cm, and Amarpur 31 cm against Amarpur CWC 27 cm (IMD press release, Annexure I), so every value in a review names its gauge. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.
10.17 Data publication
10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:
- (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
- (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
- (c) the register of variances and waivers (Clause 1.10);
- (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
- (e) enforcement actions (Clause 10.15.5); and
- (f) event reports and post-event reviews (Clause 10.16).
10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.
10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.
10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.
Commentary. Transparency is a design criterion in its own right here. Much of Tripura's drainage record is public: the TBR 2017 as amended to the Fifth Amendment of 2025, the Tripura Municipal Act, 1994, the Tripura Urban Planning and Development Act, 2018, the Diversion of Land Rules, 2025 with their amendment of 2026 and the Official Language Act, 1964, in the High Court of Tripura's library of State legislation; the High Court's judgment in WP(C)(PIL) No. 06 of 2026; the State's affidavits and CPCB's reports before the National Green Tribunal; the CAG's audit reports for 2019-20, 2021-22 and 2022-23; ADB's initial environmental examinations for the Agartala City Urban Development Project; CGWB's aquifer mapping report for West Tripura; IMD's station extremes and its press releases of August 2024; and the TUDA notification of the Local Planning Areas of 2019. Several of these were read only from archived or third-party copies, because the State's websites refused connections while this edition was prepared. Much else could not be found in the public domain: the text, notification and zoning regulations of the Master Plan for the Agartala Planning Area 2045; the original gazette of the TBR 2017 and the number of their Second Amendment; any drainage master plan or project report with a design storm, from the Agartala Municipal Corporation, Agartala Smart City Ltd, ADB or PWD (WR), including the ₹1,000 crore flood-protection proposal of 2026; the capacity of Agartala's flood pumps and the hydraulics of the Katakhal and the Akhaura canal; an inventory of PWD (WR)'s embankments and sluices with their sills and operating rules; CWC's site sheets and gauge datums; the release rules of the Dumbur reservoir; the DST&E's guidelines for the protection of lakes, ponds and water bodies; s.20 of the Land Revenue and Land Reforms Act as now amended; any building or land-development regulation of the TTAADC; an inventory of Agartala's pukurs and dighis; the archives of the State's and the Corporation's rain gauges; and TDMA's final report on the floods of 2024. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.
10.18 Review of this chapter
10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.
References (chapter)
- Government of Tripura, Urban Development Department. Tripura Building Rules, 2017 (UDD notification No. F.2(316)-UDD/GL/TCPO/2009 (Part-I)/371 of 10 November 2017, as cited in UDD's BRAP-2019 document; the 2017 gazette was not read [TBC]), as amended by the Tripura Building (Amendment) Rules, 2019 (No. F.2(466)-UDD/GL/TCPO/2018/599-627, 19 February 2019; Gazette Extraordinary No. 482, 25 February 2019), the (Second Amendment) Rules, 2020 (dated 15 February 2020, Gazette 24 February 2020; number garbled in the copy read [TBC]), the (3rd Amendment) Rules, 2022 (No. F.01(24)-TUDA/Estt/2022/4902-30, 29 November 2022; Gazette 2 December 2022), the (Fourth Amendment) Rules, 2024 (No. F.1(23)-TUDA/ESTT/2024/66, 15 January 2025; Gazette No. 95, 17 January 2025) and the (Fifth Amendment) Rules, 2025 (F.No.2(466)-UDD/GL/TCPO/2018(P-V)/4009-20, 4 July 2025; Gazette No. 1294, 5 July 2025), made under section 274 read with section 118 of the Tripura Municipal Act, 1994: rules 1, 3A, 4, 5(1)(k) and (p), 9(2)–(4), 13(3), 14, 14(1), 16, 17, 32, 34, 34(9), 38, 46, 51(2), 55, 57, 66, 88–101 (Part X), 110 and 113. https://thc.nic.in/Tripura%20State%20Lagislation%20Rules/Building%20Rules,%20Tripura,%20%202017%20(As%20Amended%20upto%205th%20Amendment%20dt.%2005.07.2025).pdf
- Tripura Municipal Act, 1994, as amended to the Ninth Amendment (7 May 2025): ss.1(2), 2, 91, 156–166, 232–235. https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/Municipal%20Act,%20Tripura,%201994.pdf
- Tripura Urban Planning and Development Act, 2018 (Tripura Act No. 12 of 2018): ss.52, 53 and 163; and TUDA notification No. F2(15)-TUDA/TECH/2019(P) under s.52(1), November 2019, declaring Local Planning Areas adjacent to 20 cities and towns. https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/Urban%20Planning%20and%20Development%20Act,%20Tripura,%202018.pdf
- Government of Tripura, Revenue Department. Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025, No. F.4(05)-RCC/2025, 2 June 2025 (Gazette Extraordinary No. 1072, 3 June 2025), as amended by the (First Amendment) Rules, 2026 (6 March 2026; Gazette Extraordinary No. 2026350): rules 2, 3, 4 and Appendix-I. https://thc.nic.in/Tripura%20State%20Lagislation%20Rules/Land%20Revenue%20&%20Land%20Reforms%20(Diversion%20of%20Land)%20Rules,Tripura,%202025.pdf
- Comptroller and Auditor General of India. Audit Report for the year 2019-20 (Government of Tripura), Chapter II, performance audit on the implementation of the 74th Constitutional Amendment, para 2.2.8.4(i); Audit Report for the year 2021-22, Chapter III, para 3.6 (Rudrasagar); Audit Report for the year 2022-23, Chapter II, performance audit on solid waste management in the urban areas of Tripura, and Chapter III (sand mining; the Kashari Cherra earth dam) (report numbers not given on the pages read). https://cag.gov.in/
- Asian Development Bank (2020). Agartala City Urban Development Project (53262-001): initial environmental examination (draft, November 2020), prepared by Agartala Smart City Ltd. https://www.adb.org/sites/default/files/project-documents/53262/53262-001-iee-en_6.pdf
- Central Ground Water Board, North Eastern Region. Aquifer Mapping and Management Plan of West Tripura District (NAQUIM, AAP 2017-18). http://web.archive.org/web/20221212020843/https://cgwb.gov.in/AQM/NAQUIM_REPORT/Tripura/NAQUIM%20Report-West%20Tripura.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012), Agartala (A) and Kailashahar (A); and press releases of 20 and 22 August 2024, Annexure I (station rainfall, Tripura). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- Das, S.K. et al. (2022). Isopluvial analysis and intensity–duration–frequency curves for different cities in India. MAUSAM 73(4), 887–898. https://metnet.imd.gov.in/docs/mausamdocs/173412_F.pdf
- Central Water Commission (2000). Flood Estimation Report for South Brahmaputra Subzone 2(b) (Revised), Report No. SB-2(b)/R-4/44/99 (extent, Annexure 1.1 and corrigendum); and (1991) Flood Estimation Report for North Brahmaputra Subzone 2(a), Report No. NB/18/1991 (ratios).
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities, §5608 (easements, maintenance, submittals) and §5609 (plan requirements). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). Stormwater management page: 2025 Stormwater Standards Manual, Compliance Calculator, Calculator Start-Up Guide, Policy Supplement. https://www.marc.org/environment/environment-plans/stormwater-management
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed. https://info.corenet.gov.sg/docs/default-source/pub-circulars/pub-circular_cop-7th-ed-addendum-no-3_16-apr-2025.pdf?sfvrsn=5a2c1e1a_2
- PUB Singapore (2024). On-site Stormwater Detention Tank Technical Guide. https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- PUB Singapore (11 Nov 2024). Amendments to Sewerage and Drainage Act (press release). https://www.pub.gov.sg/Resources/News-Room/PressReleases/2024/11/Amendments-to-Sewerage-and-Drainage-Act
- MoHUA (2016). Model Building Bye-Laws, Chapter 9, §9.6. https://web.archive.org/web/2022/https://mohua.gov.in/upload/uploadfiles/files/MBBL.pdf
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding. https://sdma.goa.gov.in/sites/default/files/2022-05/management_urban_flooding.pdf
- High Court of Tripura. WP(C)(PIL) No. 06 of 2026 (suo motu; NH-108B and NH-208), judgment of 8 September 2026. https://www.livelaw.in/pdf_upload/2026/09/09/union-of-india-tripura-hc-699203.pdf
- High Court of Tripura. WP(C)(PIL) No. 2 of 2014, Bibash Ch. Saha v. State of Tripura (as cited from a third-party copy dated 16 August 2016); order of 28 June 2017 on the encroachment of water bodies in Agartala (case number unconfirmed, as cited); WP(C)(PIL) No. 05 of 2017 (suo motu; Rudrasagar; as reported).
- National Green Tribunal. O.A. No. 606 of 2018: affidavit of the Government of Tripura filed 6 July 2026, and the earlier action-taken report of 2020; O.A. No. 673 of 2018: affidavit of the State of Tripura and report of CPCB in E.A. No. 35 of 2023; O.A. No. 325 of 2015: Tripura's report of 26 May 2020 (as reported). https://www.greentribunal.gov.in/
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (Haora at Dashamighat).
- Lok Sabha. Debates of 22 August 1983 (floods of 3–5 August 1983, as quoted); and Unstarred Question No. 1192 (deaths in the floods of August 2024, as cited).
- Tripura Disaster Management Authority. Checklist for the monsoon of 2026 (as quoted) and State Disaster Management Plan 2024-25 (draft, as cited).
- South Asia Network on Dams, Rivers and People (2018, 2024). Overview of CWC's flood monitoring and forecasting in North East India (5 August 2018) and "August 2024 Tripura floods" (23 August 2024) (transcriptions of CWC site data and IMD district data). https://sandrp.in/2024/08/23/august-2024-tripura-floods-questions-over-disaster-management/
- Indian Masterminds, India Today NE, The Week (PTI), Deccan Herald, Down To Earth, EastMojo, Northeast Herald, Tripura Times, Morung Express, Business Standard, Scroll and other sources (2017–2026). Reports of Agartala's flood pumps and desilting, the Katakhal cleaning and the Haora embankment, the ₹1,000 crore proposal, the embankment programme of 2025, the onset of the monsoon and the floods of 2018, 2022, 2024, 2025 and 2026 (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 10A | Compliance calculator and user guide |
| 10B | GIS data specification and attribute schema |
| 10C | Maintenance access dimensions |
| 10D | Model O&M plans by facility type |
| 10E | Empanelment criteria for Stormwater Design Professionals and reviewers |
| Form 10-1 | Drainage Report Checklist |
| Form 10-2 | Compliance Calculator Summary |
| Form 10-3 | Professional Design Certificate |
| Form 10-4 | Hold-Point Inspection Record |
| Form 10-5 | As-built Certificate |
| Form 10-6 | Maintenance Declaration |
| Form 10-7 | Annual Maintenance Declaration and Inspection Report |
| Form 10-8 | Asset Handover Certificate |
| Form 2-1 | Design Rainfall Sheet (Chapter 2) |
Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Tripura the failure is one of missing criteria, of drains split among many hands and of a permit route that now relies on self-certification. No document of the Urban Development Department (UDD), the Tripura Urban Planning and Development Authority (TUDA), the Agartala Municipal Corporation, any other ULB, Agartala Smart City Ltd, PWD (R&B) or PWD (WR) stating a design return period, intensity or runoff coefficient for the storm drains of any town was found. The drains vest in the Municipality, which "shall provide and maintain a system of drainage or sewerage as well as a safe and sufficient out-fall" (Tripura Municipal Act, 1994, ss.91 and 156(1)), but the works are built by others: in Agartala the major AMRUT works "(98 per cent)" were implemented "by the UDD and State PWD (DWS) and only a few minor works … by AMC", with no tripartite agreement, and PWD (R&B) builds the major roads and their drains (CAG, Audit Report for the year 2019-20); Agartala Smart City Ltd builds storm drains, flood pumps and the works on the Akhaura canal and the Katakhal, and PWD (WR) the embankments and the Katakhal sluice; no order allocating the drains among them was found. The approval route shapes this chapter. The TBR 2017 apply in the ULBs and, since 2019, in the Local Planning Areas; TUDA gives the building permission and occupancy certificate in a notified Local Planning Area and for a building or township of 50 or more flats or of one acre or more inside a ULB (r.13(3), as inserted in 2020), and the ULB elsewhere. Applications go through a "unified digital platform / online single window system having application tracking facility" (r.14(1), as substituted in 2025). The plans already carry much of what a drainage submittal needs: the site plan shows "the means of drainage of the proposed building leading to existing public drains or drainage channels" and the "natural drainage channel/jhora" (r.5(1)(k) and (p)); the building plans show "the house drainage plan, and site drainage plan up to nearest Nagar Panchayat or Municipality or natural outfall" and "the roof plan indicating the drainage and slope of the terrace", and the specification "the manner in which roof and house drainage and the surface drainage of the site will be disposed of" (r.14); a basement with a kitchen, bath or water closet needs "Detailed plans showing arrangement for drainage including pumping system" (r.66(5)); a plot of 200 m² of plinth or more needs "the complete proposal of rainwater harvesting" (r.110); a site on a "recently filled up … pond, lake, marshy" soil may be asked for a soil test, restricted or refused (r.32); and notice in Form I precedes the covering of a drain (r.38). Since the Fifth Amendment of 2025, low- and very-low-risk buildings are permitted on a "Self-Certification Proforma" by an empanelled professional, "on a trust-based approach" (r.13(3)); their occupancy certificate is issued within 7 working days by that professional in Form H1 (r.34); and "Inspection for self-certified buildings is hereby waived. However, 10% to 15% of total applications shall be randomly selected" (r.34(9)). Rainwater-harvesting structures are inspected "before issuing Completion Certificates" (r.110(6)(ii)). A private drain joins a municipal drain only "after obtaining the written permission of the Municipality" (Tripura Municipal Act, 1994, s.161). An outfall through an embankment or sluice needs the consent of PWD (WR) as its owner, since no embankment or drainage statute was found [TBC]; a notified wetland, the Wetland Authority of Tripura; and the filling of any canal, pond, water body, wetland, jhora, stream, drain or culvert, the Local Body with the prior approval of the State Government (r.9(3)). The TBR 2017 are made under the Municipal Act, which "extends to the whole of the State of Tripura except the areas under the Tripura Tribal Areas Autonomous District" (s.1(2)), so they do not apply in the council area, about 68% of the State (as reported), and no building or land-development regulation of the TTAADC was found [TBC]. No rule asks for a drainage report, limits peak runoff, requires on-site detention or sets a design storm, and the "site drainage plan up to nearest … natural outfall" has no method to follow. Every stormwater item in this chapter is therefore written so that the professional who signs the drawings can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the competent authority for the area can check it with the drawings the TBR 2017 already require. Where a building is self-certified, the Manual's submittal and its certificate sit with that empanelled professional, as the permit and Form H1 do, and the Authority's check is the random selection of r.34(9) and the inspections of Clause 10.12, not a review before the permit; for every other building the site drainage plan of r.14 carries the Stage 1 and 2 submittals, the basement drainage plan of r.66 the pumped and gated items, the inspection of r.110(6)(ii) the Stage 4 check at the completion certificate, and the permission of s.161 the connection to the public drain, with the consent of PWD (WR) for any outfall through an embankment or sluice. This chapter is the process.