Draft v1.0 prepared by NEER. Not adopted by the Government of Tripura, the TTAADC or any authority or local body, and has no legal force. About this draft

Chapter 11Basin and City Stormwater Master Plans


11.1 Purpose and scope

11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.

11.1.2 A BSMP shall:

  • (a) map flood hazard for the basin under existing and future conditions;
  • (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
  • (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
  • (d) reserve land for regional storage, pukur and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
  • (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
  • (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).

11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.

Commentary. Tripura's towns have a master plan, drainage projects and court-supervised works, but no published storm-drainage master plan with a design storm. The Master Plan for the Agartala Planning Area 2045 was declared final by the UDD on 24 February 2026 under s.53(1) of the Tripura Urban Planning and Development Act, 2018, for 238.57 km² covering the Agartala Municipal Corporation and 49 gram panchayats, with "statutory zoning and development control regulations" and sectoral infrastructure plans (as reported); its notification and text were not read, and whether it designates drainage reserves, flood zones or water-body buffers is not known [TBC]. TUDA notified Local Planning Areas adjacent to 20 cities and towns in November 2019, the first the "Agartala-Ranibazar-Jirania Local Planning Area" (excluding the ULB areas), bounded on the west by the international border (TUDA notification under s.52(1)); no master plan for any other town was found. Agartala's drainage is being built project by project. The ADB-funded Agartala City Urban Development Project (53262-001) provides 48.2 km of new or rehabilitated storm-water drains (initial environmental examination, draft of November 2020), on a loan reported as $61 million in 2021, and a later loan of $100 million with 55 km of storm-water drains was reported in a year not confirmed (both as reported); a Tripura Urban Livability Improvement Project (53276-003) of $181.28 million is listed as "Proposed" (ADB, as quoted). The Agartala Municipal Corporation and Agartala Smart City Ltd were reported to plan about 50 km of new storm drains, and a storm-water share of about ₹5–6 billion in an Agartala programme of about ₹12 billion, aiming to cut the city's drainage time "from one to two hours to about 15–30 minutes" (as reported); and in July 2026 a ₹1,000 crore Agartala flood-protection proposal of two embankments and three pumping stations was reported, to be "implemented in phases, depending on the availability of funds" (as reported). None of the documents read states a return period, design intensity, runoff coefficient or time of concentration, or sizes a drain against a river level; the project reports were not read [TBC]. Outside Agartala nothing was found. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by the UDD, TUDA, the Agartala Municipal Corporation, any Municipal Council or Nagar Panchayat, Agartala Smart City Ltd, PWD (WR), TDMA, the TTAADC, ADB or any other body, and it does not replace the plans and project reports they are preparing. A site-level manual cannot fix basin-level problems: lost tank storage, pukurs, dighis and lungas (lunga, Bengali লুঙ্গা: the land records' "Flat lands between tillas") filled for building, as reported at Barjala and Lanka Basti in Agartala, cuts in the tillas (tilla, Bengali টিলা: a hillock) and hill roads that silt the valley drains and slide in the rain, drains that are the sewers of towns in which sewers serve only Agartala's North Zone, and carry their sewage to the pukurs, the Haora and the Katakhal, outfalls that the Haora, the Katakhal and the other embanked rivers close for days, so that a town drains only as fast as its pumps run, rivers that leave the State for Bangladesh with no downstream level known, and channels split between the Agartala Municipal Corporation, Agartala Smart City Ltd, PWD (R&B), PWD (WR) and PWD (DWS), and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:

  • Denver's Mile High Flood District prepares major drainageway master plans that set regional facilities and release rates.
  • The Kansas City APWA criteria rest on regional watershed studies (MARC).
  • England's Surface Water Management Plans (Defra, Surface Water Management Plan Technical Guidance, 2010) set a phased method of preparation, risk assessment, options and implementation.
  • Malaysia's MSMA requires drainage master plans for urban areas.

This chapter adapts that method to Tripura, the first State of the series whose whole area lies outside every published CWC Flood Estimation Report and whose every river leaves the State for Bangladesh: to towns built on the lungas and flood plains of the valley floors, between the tillas and the north–south hill ranges; to Agartala, a saucer between the embanked Haora and the Katakhal that drains by pumps when they are high, and to Kailashahar, Belonia, Udaipur, Sonamura and Dharmanagar on rivers that cross the border with no Indian control downstream and no level data from across it; to the Gomati below the Dumbur reservoir, a release reach; to pukurs and dighis that hold the towns' storage and are being filled, and to lungas that are both the natural flow paths and the places where towns are built; to chharas (chhara, Bengali ছড়া: a stream) that bring down the silt of cut tillas and hill roads, and khals (khal, Bengali খাল: a canal or channel) that carry the towns' drains on to the rivers; to drains that are the sewers of towns in which sewers serve only part of one city; to rainfall that no CWC report covers, with a measured day, 49 cm at Bagafa on 22 August 2024 (IMD), above every estimate; to a water table near the surface across the valley floors, where infiltration is not credited; to embankment breach paths, landslide ground and the release reach, where no drain is the answer; to drains split among the Agartala Municipal Corporation, Agartala Smart City Ltd, PWD (R&B), PWD (WR) and PWD (DWS) with no order dividing them; and to the Sixth Schedule area of the TTAADC, about 68% of the State (as reported), where the TBR 2017 do not apply, so that a BSMP begins with the river and the hazard, not the storm alone (Clause 11.3.3).


11.2 Definitions

Term Meaning in this Manual
Basin The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3.
Basin Stormwater Master Plan (BSMP) The plan for one basin prepared under this chapter.
Lead Authority The body responsible for preparing a BSMP (Clause 11.4).
Level of service (LoS) The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6).
Flood hazard map A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario.
Regional facility A storage, conveyance or outfall work serving more than one development, identified in a BSMP.
Capital Improvement Programme (CIP) The ranked, costed list of works in a BSMP (Clause 11.8.4).

11.3 Planning unit: the basin, not the ward

11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.

11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.

11.3.3 No basin delineation has been published for any Tripura town; the drainage project reports for Agartala were not read [TBC]. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:

  • Agartala, central saucer and Akhaura canal: the Central zone of the Greater Agartala Planning Area, between the Haora embankment on the south and the Katakhal on the north, the erstwhile area of the Corporation, whose centre lies lower than the rest of the city (ADB, initial environmental examination, 2020), with its channels, among them the Bangeshwar Gang, the Debta Gang, the Nagichara and the Kalapani Charra, and the Akhaura canal, which serves the central area along the Akhaura road and flows on to Bangladesh (ADB, 2020); modelled with the design rainfall of sub-area TR-A (Clause 2.3.6(c)), the flood pumps with their discharge pipelines to the Haora and the Katakhal, and the case of local rain with the outfalls shut as a design case (Clause 5.8.5(b)), with the drains that carry sewage in the 1D network;
  • Agartala, the Katakhal: the North zone and the channel to the Katakhal double-barrel sluice near Bhuturia, run by PWD (WR) (as quoted), with the Kalapania Khal; the Katakhal has no gauge, so its levels come from surveyed flood marks, and until they are surveyed the Haora level is used at its outfalls (Clause 5.8.5(b)); the treatment plants being built on its banks, 10 MLD at Ranjit Nagar, 15 MLD at Abhaynagar Bridge and 1.5 MLD at Astabal Bridge, and 5 MLD at Joypur on the Kalapania Khal, all fed by intercepting drains (State affidavit to the National Green Tribunal, 6 July 2026), are shown with their interception points;
  • Agartala, the Haora: the whole catchment of the Haora, 46 km long and 414 km², which rises in the Baramura range, flows west through the Agartala–Sonamura valley and enters Bangladesh near Agartala (CGWB, aquifer mapping report for West Tripura) and is "the only source of surface water for Greater Agartala" (ADB, 2020), its upper catchment in sub-area TR-E under Clause 2.3.6(c); the South zone; the flood-plain localities mapped by PWD (WR), Khayerpur, Kashipur, Baldakhal, Aralia, Jogendranagar and Joynagar (Dashamighat) (State affidavit to the National Green Tribunal in O.A. No. 673 of 2018; map, return period and status not known [TBC]), and Chandrapur, flooded in August 2026 (as reported); the 8 MLD treatment plant being built on the Haora bank, which the Tribunal found on flood plain (order of 13 April 2026, as quoted); and the Haora at the CWC Haora site, design level 12.42 m (22 August 2024, as reported; datum not stated), as the boundary, with the other published levels stated;
  • Kailashahar on the Manu: the town behind the Manu embankment, 16.8 km of which was reported raised in 2025 (as reported), with its outfalls and any pumps, once surveyed [TBC], the Manu at Kailashahar (CWC), danger level 25.34 m and 25.95 m on 13 June 2018 (as reported; the State press figures of 24.00 m and 23.05 m stated as a conflict), as the boundary, the record check of Clause 2.3.6(h) (377.2 mm at 1% AEP within 25 km) and the river's run north into Bangladesh;
  • Belonia on the Muhuri: the town behind the Muhuri embankment (7.47 km of works reported in 2025), with the Muhuri at Belonia, 18.81 m on 22 August 2024 against the 16.98 m of 1983 (as reported), as the boundary and the 490 mm record floor of sub-area TR-D1 (Clause 2.3.6(h));
  • Udaipur, Amarpur and Sonamura on the Gomati: the towns on the release reach below the Dumbur reservoir, with the Gomati at Udaipur, 22.05 m against an extreme danger level of 22.00 m on 21 August 2024 (State gauge), the Gumti at Amarpur, 32.74 m (22 July 1993), and the Gumti at Sonamura, danger level 12.5 m and 14.43 m (23 July 1993) (as reported), as boundaries, and the largest recorded release, or the spillway capacity of 481.38 m³/s until the operator gives one, as the release case (Clause 5.8.5(d)); at Udaipur, the pukurs and dighis of the town, among them Kalyan Sagar at Matabari, kept as storage, not drawn down;
  • Dharmanagar on the Juri: the town on the Juri, with the Juri at Nutan Bazar, 20.66 m on 22 August 2024 against the 20.435 m of 15 May 1984 (as reported), as the boundary;
  • Khowai and Teliamura on the Khowai: the towns on the Khowai, with the Khowai at Khowai, 28.005 m (24 June 2004, as reported), as the boundary, and the governing cell of sub-area TR-B, since NIH-DHAARA's cell at Khowai town is empty (Clause 2.3.6(c));
  • Kamalpur on the Dhalai: with the Dhalai at Kamalpur, 33.85 m (15 May 1984, as reported), as the boundary, and the governing cell of sub-area TR-B1;
  • Santirbazar, Bagafa and Sabroom: the towns of the Muhuri–Feni south, with the landslides of August 2024 at Gardang near Santirbazar (as reported) mapped, the Feni a border river whose CWC site at Sabroom was not reporting in 2024 (as reported), and the 490 mm record floor of sub-area TR-D1;
  • Hill-range corridors: the drains and culverts of NH-8 through the Atharamura and Longtharai ranges and of NH-108B and NH-208, whose blocked culverts the High Court recorded (WP(C)(PIL) No. 06 of 2026), with the tilla cuts and landslide ground above them mapped and the hazard-first rule below; and
  • Rudrasagar: the catchment of the Rudrasagar lake at Neermahal, a Ramsar site, 6,052 ha as cited by the Forest Department, with no new storm drain into it without the interception of Clause 8.9 and the lake's level as the High Court has watched it (WP(C)(PIL) No. 05 of 2017, as reported) as the boundary.

Hazard first (set by this Manual). On the landslide ground of the tilla cuts and the hill ranges, in the breach path or leakage path of an embankment, on the Gomati below the Dumbur reservoir, on the active flood plains, "the present-day flood-prone belts fringing the rivers" (CGWB), on filled ponds and lunga fills (TBR 2017, r.32) and on the border reaches with no downstream control, the BSMP begins with a hazard screening (Clause 2.3.6(i)), made with TDMA's hazard pages and the State Disaster Management Plan [TBC], PWD (WR)'s flood-plain localities on the Haora and its records of its embankments, sluices and breaches, GSI's landslide maps where they exist [TBC] and the Natural Hazard Prone Areas of r.2(44) of the TBR 2017 once a Development Plan maps them, and states whether each part of the basin lies in the path of the hazard. The scale is large: the rains of August 2024 were reported to have opened 2,032 landslip locations, and landslides killed seven members of two families at Gardang near Santirbazar and three at Debipur, the Dumbur reservoir released water on 21 August 2024 for the first time "since 1993" by the district's account, which the power minister denied (all as reported, a conflict), and the Haora embankment at Agartala needed 6 km of leakage repairs (as reported). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a breach, a debris flow or a landslide. The other ULBs define their basins in the first BSMP that covers them. Where CWC, PWD (WR), a master plan, the operator of the Dumbur reservoir or a court has a high flood level, a gate-closing level, a flood line or an operating rule for a dam, sluice or pumping station, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.

Basin Stormwater Master Plan (BSMP) — process and links to site design 1. Basin set-up Delineate by basin, not ward (Cl. 11.3) Lead Authority + partners 2. Data DEM, drains, tanks, river levels, flood marks (Cl. 11.5) 3. Model 1D–2D, 24–72 h storms, river, continuous sim. calibrate to past floods 4. Gap vs LoS Scenarios: existing, future ± site controls, climate (Cl. 11.6–11.7) 5. Options Restore tanks first, then regional storage, conveyance, outfalls 6. Outputs (Cl. 11.8.4) — approved by State Stormwater Technical Committee • Flood hazard maps 10% / 1% / 0.2% AEP • Flood-sensitive catchments, basin release rates • Regional facility sites and fee-in-lieu rate • Capital Improvement Programme, ranked • Pre-monsoon maintenance programme • Monitoring network • Open data + public map viewer • Annual report, pre-monsoon Land-use plan Statutory master plan: reserve storage sites, flow paths, hazard zoning (Cl. 11.9) Site design Ch 4 release rates, regional detention and fee-in-lieu (Cl. 4.13, 4.5.6) Floors and setbacks 1% AEP future-with-plan map sets floor levels (Ch 6) and setbacks (Ch 7) Public works CIP funds: ULB, State, Union; O&M and desilting (Ch 10) Review every 10 yr, after a >1% AEP event, or plan revision (Cl. 11.11)

Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.

Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Tripura a single channel passes through many hands, and every river crosses the international border on its way to the sea. The Haora rises in the Baramura range and runs 46 km through the Agartala–Sonamura valley into Bangladesh, draining 414 km² (CGWB, aquifer mapping report for West Tripura); in Agartala the city is divided by it and the Katakhal into a North zone, north of the Katakhal, a Central zone between the Haora embankment and the Katakhal, and a South zone, south of the Haora, and the Haora and the Katakhal are the city's "two major drainage channels draining flood water to Bangladesh" (ADB, initial environmental examination, 2020), with the Akhaura canal serving the centre and flowing on to Bangladesh as well. The planning boundaries do not follow the water: the Master Plan for the Agartala Planning Area 2045 covers 238.57 km², the Corporation and 49 gram panchayats (as reported), wider than the Corporation's own area, given as 76.5 km² or 92 km² (as reported, a conflict), and the Agartala–Ranibazar–Jirania Local Planning Area of 2019 lies outside the ULB areas, bounded on the west by the international border (TUDA notification). No order assigns the Haora, the Katakhal or the Akhaura canal to one owner (this Manual's reading of the record): the channels and drains vest in the Municipality "unless the State Government otherwise directs by a notification" (Tripura Municipal Act, 1994, s.91); PWD (WR) holds the embankments and the Katakhal sluice and has mapped the Haora's flood-plain localities; Agartala Smart City Ltd has built storm drains, flood pumps and works on the Akhaura canal and the Katakhal; PWD (R&B) holds the road drains and PWD (DWS) the pump houses and, with the UDD, the treatment plants (CAG; State affidavits to the National Green Tribunal); and the State has reported the Haora's polluted stretch as "Agartala to Champaknagar" while CPCB lists it as "Agartala to Bishramganj", a conflict over one river. Upstream, about 68% of the State lies in the area of the TTAADC (as reported), where the Municipal Act and the TBR 2017 do not apply (s.1(2)); which reaches of each basin lie in it has not been mapped [TBC]. This clause makes the basin the planning unit, so that one model carries each channel from its head in the hills, across the boundaries of the Corporation, the Planning Area and the council area, to the river and the border, through every sluice and pump, whoever owns each reach.


11.4 Who prepares, and when

11.4.1 Lead Authority.

  • For the basins of the Agartala Planning Area (the area of the Master Plan for the Agartala Planning Area 2045, 238.57 km², as reported): the Agartala Municipal Corporation, in which the public drains, tanks and water courses vest and which must provide "a safe and sufficient out-fall" (Tripura Municipal Act, 1994, ss.91 and 156(1)), jointly with TUDA, which prepares the Master Plan, gives building permission in the Local Planning Areas and for large projects (TBR 2017, r.13(3)) and whose functions include the "development of water bodies or open spaces" (Tripura Urban Planning and Development Act, 2018); the BSMP is taken into the Master Plan and its zoning regulations (Clause 11.9). For the other towns: the Municipal Council or Nagar Panchayat, jointly with TUDA in the town's Local Planning Area. Each role is the one the body would have if the Manual were adopted. Where a basin extends beyond the ULB's limits or the Planning Area, the other local bodies and Gram Panchayats in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
  • No order dividing the drains and channels among the Corporation, Agartala Smart City Ltd and the departments was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: PWD (WR) for the rivers, the embankments and the sluices in them, among them the Katakhal double-barrel sluice, and the flood-plain mapping of the Haora; the Agartala Municipal Corporation and the other ULBs for the municipal drains, the channels and the flood pumps they run; Agartala Smart City Ltd for the works it builds until they are handed over; PWD (R&B) for the road drains, and NHIDCL for those of the national highways in its charge; PWD (DWS), with the UDD, for the pump houses and treatment plants in its charge; and the Wetland Authority of Tripura for a notified wetland and Rudrasagar. Each town keeps the drain register of Chapters 1 and 6, which gives every reach its owner.
  • TDMA, with the District Disaster Management Authority, for the flood, embankment-breach, release-reach and landslide hazards that a BSMP must show (Clause 11.3.3).
  • In the other ULBs and Tier B bodies, the Lead Authority is named by the UDD. In the area of the TTAADC, the Lead Authority is the District Council or the authority it designates, only where the Council has made a regulation or resolved that this Manual applies (none has). Basins draining to a common river reach or sluice may be grouped into one district-level plan.

PWD (WR) shall also be a partner in every BSMP whose outfall passes through one of its embankments or sluices; TDMA and the District Magistrate and Collector shall be consulted on every BSMP; the Revenue Department on every BSMP that proposes works on land recorded as a pukur, dighi, beel or other water body; the Department of Science, Technology and Environment and TSPCB on every BSMP that proposes works on a drain that carries sewage, among them the drains intercepted for the treatment plants on the Haora and the Katakhal; the Forest Department and the Wetland Authority of Tripura on every BSMP whose basin drains to Rudrasagar or another wetland; the operator of the Gumti hydel project at Dumbur on every BSMP whose outfall lies on the Gomati below it; and CWC, for the levels at its sites, on every BSMP whose boundary is a river it gauges. Because every river leaves the State for Bangladesh, no downstream authority can be a partner, and the BSMP states that the level across the border is unknown (Clause 5.8.5(c)).

PWD (Water Resources) shall be a partner in every BSMP that includes a river, canal or tank under its control.

11.4.2 When a BSMP is required.

  • (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
  • (b) A BSMP is required before:
    • any regional detention or fee-in-lieu is accepted under Clause 4.13;
    • a fee held under Clause 4.5.6.3 is spent; and
    • a basin-specific release rate is applied under Clause 11.8.3.
  • (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.

11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.


11.5 Data and surveys

11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:

Table 11.1 — Minimum data and surveys for a BSMP

Data Minimum requirement
Terrain Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum
Drain network Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm
Waterbodies Survey of every tank, pukur, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment
Rivers and canals Cross-sections at no more than 200 m spacing and at every structure
Outfalls, rivers, embankments, sluices and pumps The datum of every level named; outfall invert levels against the warning, danger and high flood levels of the receiving river at the nearest CWC site (for example the Haora at Agartala, danger level 10.70 m and high flood level 12.42 m, and the Manu at Kailashahar, 25.34 m and 25.95 m; CWC levels as transcribed by SANDRP or reported in the press, with the datum not stated) and its recorded peaks, with any State gauge, such as the Haora at Jahar Bridge (danger level 10.50 m, as reported), kept as a separate series and any conflict between published values stated; embankment crest levels and the location of every sluice and flap gate in the embankments of PWD (WR), among them the Katakhal double-barrel sluice, with its sill, gate type, closing level and operating rule; the flood pumps and pumping stations on the outfalls, with their installed and working capacities, discharge pipelines, sump volumes and standby power (the design capacity of none was found [TBC]); the levels of the Katakhal and the Akhaura canal, which have no gauge, by survey; the stage–storage of every pukur, dighi and lunga storage that receives the outfall, starting full to its outlet; past breaches and leaks of the embankments and the land they flooded; the release records of the Dumbur reservoir where it sets the receiving level; and, at every border reach, the statement that no downstream level is known
Rainfall and levels All available rain gauges (IMD, through its Meteorological Centre Agartala, with its two stations in Extremes, Agartala (A) (42724) and Kailashahar (A) (42618), and the stations named in its press releases of August 2024, among them Agartala Aero, Met Agartala (ARG/AWS), Teliamura ARG, Bagafa and Bagafa AWS, Belonia and Belonia ARG, KVK South, KVK Dhalai and Gandacherra AWS; the rain gauges at CWC's river sites, among them Sonamura Mohanbhog, Gajaria, Amarpur, Belonia, Manughat, Kailashahar, Kumarghat, Nutanbazar and Kadamtala; the State's automatic rain gauges, among them the DM Office and Secretariat gauges in Agartala (owners, logging intervals and archives [TBC]); the rain and level sensors of the Agartala Municipal Corporation's Integrated Command and Control Centre (as reported); and the ten automatic rain gauges that IMD is to add in Agartala and other urban areas (TDMA's monsoon checklist of 2026, as quoted) [TBC]) and water-level records, including those for the 22 August 2024 (Agartala Aero 23 cm in the 24 hours to 08:30 IST on 22 August, IMD, with the Haora at the CWC Haora site at 12.42 m the same day, as reported, in the State's flood of record, whose largest measured day was 49 cm at Bagafa, IMD), 17–19 June 2022 (the Agartala urban flood, with about 200 mm in 3 hours by the Mayor's account and 145 mm or 155 mm in 24 hours in other reports, a conflict, all as reported, no IMD hourly value found, and the Haora at 10.82–10.85 m at Jahar Bridge against a danger level of 10.50 m and at 10.72 m at the CWC site against 10.70 m, as reported), 31 May 2025 (about 200 mm in 3 hours at Agartala by the account of the Mayor and officials, with one death in a manhole, as reported; no IMD hourly value found), 13 June 2018 at Kailashahar (the Manu at 25.95 m at the CWC site, 0.16 m above its high flood level of 1993, and about 21,000 people homeless in the town, as reported; no hourly town rainfall found) and 22–24 August 2026 (Chandrapur, Baldakhal and Aralia in Agartala flooded, and the Haora at 10.72 m at 08:00 on 24 August against a danger level of 10.70 m, as reported; no rainfall value found) events
Flood evidence Surveyed flood marks and mapped flood extents from past events, including public reports
Land use Existing land use and imperviousness; future land use from the statutory master plan
Soils and groundwater HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones
Sewer interaction Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots

Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the lungas and flood plains of the valley floors, in Agartala's central saucer between the Haora embankment and the Katakhal, where the ground falls from 25–30 m to about 8 m (ADB, initial environmental examination, 2020), behind the embankments of Kailashahar, Belonia and the other embanked towns and on the pukur, dighi and beel margins, where slopes are gentle, the rivers back up and a closed sluice ponds the land behind it, and where a raised road, an embankment or a filled pond can turn an overflow from one part of a town to another, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 22 August 2024 (Agartala Aero 23 cm in the 24 hours to 08:30 IST on 22 August, IMD, with the Haora at the CWC Haora site at 12.42 m the same day, as reported, in the State's flood of record, whose largest measured day was 49 cm at Bagafa, IMD), 17–19 June 2022 (the Agartala urban flood, with about 200 mm in 3 hours by the Mayor's account and 145 mm or 155 mm in 24 hours in other reports, a conflict, all as reported, no IMD hourly value found, and the Haora at 10.82–10.85 m at Jahar Bridge against a danger level of 10.50 m and at 10.72 m at the CWC site against 10.70 m, as reported), 31 May 2025 (about 200 mm in 3 hours at Agartala by the account of the Mayor and officials, with one death in a manhole, as reported; no IMD hourly value found), 13 June 2018 at Kailashahar (the Manu at 25.95 m at the CWC site, 0.16 m above its high flood level of 1993, and about 21,000 people homeless in the town, as reported; no hourly town rainfall found) and 22–24 August 2026 (Chandrapur, Baldakhal and Aralia in Agartala flooded, and the Haora at 10.72 m at 08:00 on 24 August against a danger level of 10.70 m, as reported; no rainfall value found) events are the best calibration data Tripura has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.


11.6 Levels of service

11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.

Table 11.2 — Minimum levels of service

Element Minimum level of service
Minor system The design AEP of Chapter 6 (Table 6.1)
Habitable buildings No flooding above floor level in the 1% AEP (100-yr) event
Critical facilities (hospitals, emergency services, substations, water and sewage plants) No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event
Evacuation routes and arterial roads Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event
Ponding drain time Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event
Tank and pukur storage No net loss of flood storage below the MWL in the basin, measured against the earliest available survey
Outfalls Functioning under the joint and outfall-closed cases of Chapter 5

Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Tripura has no irrigation tank cascades; its storage is in the pukurs and dighis of its towns and villages, the palace and temple tanks, the beels of the valley floors and the Dumbur reservoir. The land records already count them: the Revenue Department's classes of land include পুকুর "Tank/Pond", পুকুরপাড় "Bank of tank", দীঘি "Large tank", দীঘিরপাড় "Bank of large tank", ডোবা "Ditch", বিল "Watery land" and হাওর "Big watery land" (Diversion of Land Rules, 2025, Appendix-I), so the pukurs, dighis and their banks can be counted plot by plot. The losses are reported, not surveyed: ponds filled for housing at Barjala and Lanka Basti in Agartala (as reported), ponds filled and banks walled at Kalyan Sagar, Matabari, where the High Court ordered 110 m of cement embankment demolished (WP(C)(PIL) No. 2 of 2014, as cited), the encroachment of Agartala's water bodies that the High Court took up in 2017 (as cited), and a water body at Gol Bazar filled, which the Tripura Human Rights Commission took up in 2025 (as reported). Against them, the Mayor reported about 65 water bodies cleaned and developed under city schemes, the State told the National Green Tribunal in 2020 that 180 urban water bodies on government land had been identified and 30 prioritised (as reported), and Agartala Smart City Ltd has projects at the Ujjayanta palace lakes and the MBB College lake (as cited). Rudrasagar at Neermahal is the State's Ramsar site, no. 1572, of 240 ha, designated on 8 November 2005 by the Ramsar listing or "officially designated" on 29 February 2007 by the Forest Department, a conflict, with a catchment of 6,052 ha (as cited); the CAG found ring roads built there without the Wetland Authority's permission, which "reduced the water level" (Audit Report for the year 2021-22). The Wetland Authority of Tripura was constituted by notification No. F.17(54)/For-Dev/WATIL/2017/24661-686 of 5 September 2018 and reconstituted in 2022 (as cited). The Dumbur reservoir is not a Ramsar site, and its water spread is given as 4,500 ha originally and 3,049.3 ha by 2012 (ICAR study) or about 41 km² (as reported). No inventory of Agartala's pukurs and dighis, and no survey of the stage–storage of any pukur, dighi or beel in a town, was found [TBC]; the palace-era and temple tanks are counted as existing storage with heritage and fisheries constraints, not as detention to be drawn down.


11.7 Modelling and scenarios

11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:

  • the minor system;
  • the major (overland) system;
  • rivers, canals and tanks; and
  • the outfalls.

Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.

11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.

11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.

11.7.4 Scenarios. Each BSMP shall model at least:

  • (a) Existing: existing land use, network, tanks and outfalls;
  • (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
  • (c) Future, controlled: future land use with the site controls of Chapter 4;
  • (d) Future, with plan: scenario (c) plus the works of the CIP; and
  • (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Tripura has been adopted with a design factor; the State Action Plan on Climate Change (2017) and its second version for 2021–2030 were not read [TBC], and are reported to have "only a few sentences on floods and landslides" (as quoted by SANDRP); the block-level vulnerability assessment of 2022 by the Climate Change Cell of the Department of Science, Technology and Environment was not read [TBC]; a study at NIT Agartala with CMIP6 models finds days of 100 mm or more becoming "more frequent" in 2025–2054 (EGU abstract, 2026), and CSTEP (2022) projects more heavy-rainfall events in almost all districts of the North East (as reported); and Bagafa's 49 cm in 24 hours on 22 August 2024 (IMD) exceeds every NIH-DHAARA 100-year cell in the State, which is a reason to keep the factors, not to reduce them; and on the tilla slopes and hill ranges, on the Gomati below the Dumbur reservoir and behind the embankments the hazard screening of Clause 11.3.3 is made in every scenario.

11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 22 August 2024 (Agartala Aero 23 cm in the 24 hours to 08:30 IST on 22 August, IMD, with the Haora at the CWC Haora site at 12.42 m the same day, as reported, in the State's flood of record, whose largest measured day was 49 cm at Bagafa, IMD), 17–19 June 2022 (the Agartala urban flood, with about 200 mm in 3 hours by the Mayor's account and 145 mm or 155 mm in 24 hours in other reports, a conflict, all as reported, no IMD hourly value found, and the Haora at 10.82–10.85 m at Jahar Bridge against a danger level of 10.50 m and at 10.72 m at the CWC site against 10.70 m, as reported), 31 May 2025 (about 200 mm in 3 hours at Agartala by the account of the Mayor and officials, with one death in a manhole, as reported; no IMD hourly value found), 13 June 2018 at Kailashahar (the Manu at 25.95 m at the CWC site, 0.16 m above its high flood level of 1993, and about 21,000 people homeless in the town, as reported; no hourly town rainfall found) and 22–24 August 2026 (Chandrapur, Baldakhal and Aralia in Agartala flooded, and the Haora at 10.72 m at 08:00 on 24 August against a danger level of 10.70 m, as reported; no rainfall value found) events where data exist.

Figure 11.2 — BSMP model schematic Schematic plan of a basin model: design rainfall over sub-catchments; a pukur and a dighi in cascade with an outflow khal; a 1D drain network linked to a 2D surface grid; a chhara, khal and nala reach with an inter-basin link; an outfall with a sluice, a flap gate and pumps; and a river stage boundary behind an embankment sluice, with the gate closed when the river is high and the outfall pumped. Numbered notes on the right explain each element. BSMP model: elements required by Clause 11.7 (schematic, not to scale) River behind embankment 1 S1 S2 S3 2 Pukur Dighi start level start level 3 2D surface 5 4 Chhara, khal and nala (1D) 6 Inter-basin link Gate Pumps 7 8 1 Design rainfall Ch. 2 storms incl. 24, 48, 72 h; 50%, 10%, 1%, 0.2% AEP; areal reduction (Cl. 2.7.3, 11.7.2) 2 Sub-catchments Runoff by Ch. 3 methods; land use for each scenario (a)–(e) of Cl. 11.7.4 3 Pukurs and dighis Surveyed FTL, MWL, stage–storage, sluices, surplus weirs (Cl. 11.5.1); start level from continuous run (Cl. 3.13.5, 11.7.3) 4 1D drain network Minor system: drains, pipes, culverts with surveyed inverts and silt (Cl. 11.5.1) 5 2D surface Major (overland) system on the DEM, 0.15 m RMSE or better; exchange with 1D at inlets and manholes 6 Chharas, khals and nalas (1D) Sections ≤ 200 m apart and at every structure; diversions between basins mapped (Cl. 11.3.2) 7 Outfall Sluices, flap gates and pumps; joint and outfall-closed cases of Ch. 5 8 Downstream boundary River stage behind an embankment sluice (gate closed when the river is high) and pumped outfall, per Ch. 5 Calibrate and validate with at least two major past flood events where data exist (Cl. 11.7.5).

Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and pukurs with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.

Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).


11.8 Options, outputs and the Capital Improvement Programme

11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:

  1. Protect and restore storage: pukurs, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
  2. Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
  3. Conveyance upgrades to drains, canals and culverts;
  4. Outfall works: sluices, flap gates and penstocks on the outfalls through the embankments of the Haora, the Manu, the Muhuri, the Gomati and the other rivers, with the storage and pumping behind them sized for the outfall-closed durations of Chapter 5, among them the Katakhal double-barrel sluice, the flood pumps that lift Agartala's water by pipeline to the Haora and the Katakhal, and the three pumping stations proposed for Agartala in July 2026 (as reported); standby power and fuel for the whole closure; screens and silt traps where drains that carry sewage, plastic and garbage enter a pump sump, a gate or a pukur; silt traps and debris racks at the tilla foot and the hill–lunga break, where chharas enter the towns; the interception and screening of dry-weather flow before every outfall to a pukur, a dighi, the Haora, the Katakhal or the Akhaura canal (Chapter 8, Clause 8.9); and the operating rules of the sluices of PWD (WR), agreed with PWD (WR);
  5. Property-level protection where works cannot reach the level of service; and
  6. Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Agartala, CWC level forecasts for the Manu at Kailashahar and the Gumti at Sonamura and its monitoring of the Haora and the other rivers against their warning and danger levels (as reported; the Kailashahar site was reported inactive in 2024), the alerts of TDMA and the District Disaster Management Authorities, the rain and level sensors of the Agartala Municipal Corporation's Integrated Command and Control Centre (as reported), level gauges with alarms at the Katakhal sluice, on the Akhaura canal and at the flood pumps of Agartala, where none was found, and warnings before releases from the Dumbur reservoir, whose release rules and warning procedures were not found [TBC]), flood-hazard zoning, emergency planning and public information.

11.8.2 Option assessment. Each option shall be assessed for:

  • reduction in flood risk (buildings and people flooded; expected annual damage);
  • capital and 30-year maintenance cost;
  • land required;
  • effect on groundwater recharge, which is not a design objective in Tripura, where the stage of extraction is 9.48% and every assessment unit Safe (CGWB, State compilation of 2025, as quoted), and which is credited only on tested, flat tilla tops (Clause 4.11, tilla rule), waterlogging where the water table lies within 2 m of the surface, as it does across much of the valley floors after the monsoon (0.22–6.64 m below ground in West Tripura in November 2017; CGWB), the stability of tilla slopes, cuts and the hill ranges, where water put into fill or weathered rock raises the pore pressure, and the iron-rich shallow groundwater, with up to 4.99 ppm of iron, which clogs infiltration media (Chapter 8);
  • effect on downstream basins and the receiving river, khal or chhara; and
  • who benefits.

11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.

11.8.4 Outputs. Each BSMP shall produce:

  • (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
  • (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
  • (c) regional facility sites, with storage volumes, land needs and the sites they serve;
  • (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
  • (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
  • (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
  • (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.

Commentary. Restoring storage comes first because Tripura's town outfalls are closed for days when the rivers are high, and the storage left is in pukurs, dighis and lungas that the towns are filling. When the Haora and the Katakhal run higher than Agartala, "Several pumps have been provided to lift the water out of the city" (ADB, initial environmental examination, 2020), and the city can then drain only as fast as its 18 flood pumps of up to 900,000 L/h each, about 4.5 m³/s together by this Manual's arithmetic, and 6 diesel pumps run (as reported; their working capacity was not found [TBC]); every cubic metre that cannot be pumped must be stored. The storm of 19–24 August 2024 ran for six days, with the Haora's peak on 22 August (as reported), so Chapter 5 keeps the gates shut for the 72-hour storm and, where no stage record exists, a further 72 hours, with the receiving pukurs, dighis and lunga storage full to their outlets at the start (Clause 5.8.5). The lungas are the natural flow paths of the valley floors and the places where the towns are built and the ponds filled, and the TBR 2017 already bar the filling of any "pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts" except by the Local Body with the State's prior approval (r.9(3)), and treat a site on a "recently filled up … pond, lake, marshy" soil with caution (r.32). On the valley floors, where the water table is near the surface in the monsoon, storage means a lined pond or a pukur kept at its outlet level, never a pond that soaks into the ground (Clause 4.11, lunga rule); the storage that r.110 of the TBR 2017 asks for on every plinth of 200 m² or more, credited as Clause 4.11 allows, and the detention of Chapter 4 are the first of it. Conveyance upgrades on their own move water faster to an outfall that the Haora, the Katakhal or another river in flood closes at its sluice for days, to a pukur or lunga storage that a closed sluice holds full, or to an outfall limited by the capacity of its pumps, as in Agartala's central saucer, where 18 flood pumps of up to 900,000 L/h each, about 4.5 m³/s together by this Manual's arithmetic, and 6 diesel pumps were reported in 2024 to lift the city's water to the Haora and the Katakhal (as reported; their working capacity and the flow the drains bring to them were not found [TBC]). Groundwater in Tripura calls for storage and restraint, not recharge. It is not short: the stage of extraction was 9.48% in the assessment of 2024, with every assessment unit Safe, and 9.92% in 2023 (CGWB and RBI tables, as quoted). It is shallow: in West Tripura the dug wells stood 1.63–10.30 m below ground in March 2017 and 0.22–6.64 m in November 2017 (CGWB, aquifer mapping report for West Tripura), and in South and North Tripura 0.90–5.10 m and 1.20–4.37 m after the monsoon in 2008 data (CGWB district profiles, as quoted); in Agartala "The ground water table being very high" (ADB, initial environmental examination, 2020), and "Within a few hours most of the rainwater goes as run off and finally enters Bangladesh" (CGWB). Its quality limits what can be put into it: shallow groundwater carries iron of 0.00–4.99 ppm, "due to the ferruginous nature of Tipam sandstones" (CGWB), which clogs infiltration media. The TBR 2017 nonetheless make groundwater recharge mandatory on plots of more than 500 m² and list recharge pits, trenches, wells and shafts among the techniques (r.110(5)), and no State groundwater Act or authority was found [TBC]. The recharge structures of r.110 therefore sit in saturated ground on the lungas for much of the season they are meant to serve, and Clause 4.11 replaces them there with storage. This is why waterlogging, recharge only on the ground that can take it (Clause 4.11, tilla rule), the stability of tilla slopes and cuts and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.


11.9 Integration with land-use planning

11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plan for the Agartala Planning Area 2045 and its zoning and development control regulations under the Tripura Urban Planning and Development Act, 2018 (s.53), and the plans of the other Local Planning Areas notified under s.52 once they are made; the Natural Hazard Prone Areas that r.2(44) of the TBR 2017 asks the Development Plans to identify "through local surveys"; in the area of the TTAADC, the plans and rules of the District Council, if the Council adopts the Manual; and the layouts and buildings permitted under them. In particular:

  • (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
  • (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
  • (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
  • (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.

11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.

Commentary. Tripura draws its water lines in its Building Rules, and has no flood-plain zoning law. The TBR 2017 bar the filling of any "canal, pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts", except where the Local Body, with the State's prior approval and for reasons recorded in writing, allows a canal, pond, stream, river or "flood plain area to be filled up" (r.9(3)); regulate, but do not forbid, building "in the zone of river (within 15 metres from river bank) or other water fronts of large water bodies (more than 1000 acres)", with a height of 5.00 m (6.50 m on stilts), a length of 20.00 m along the water, a gap of 50.00 m between buildings and a covered area of 200.00 m² (r.9(4)); require the owner of a site within 5.00 m of a tank to keep the building's drainage out of it (r.4(1)(e)); and in the ULBs of the hill areas forbid a site "within five meters in any direction of the outside edge of such water courses" (r.90(1)(i)), the only no-build distance from a watercourse in the rules, and ask for protective works within 5.0 m of a tank, reservoir, jhora, spring, water source or natural drain and where a site is within 30 m of a jhora (r.90(1)(m)). The rules define neither "river bank" nor "outside edge" (this Manual's reading). The "Natural Hazard Prone Areas" of r.2(44) include the "flood prone areas in river plains" of CWC's Flood Atlas of India and areas flooded by "heavy intensity rains, inadequate drainage, etc. as identified through local surveys in the Development Plan of the area"; the plinth is to be at least 60 cm above the crest of the road (r.55); and a site on a "recently filled up … pond, lake, marshy" soil may be restricted or refused (r.32). PWD (WR) has mapped flood-plain localities on the Haora at Khayerpur, Kashipur, Baldakhal, Aralia, Jogendranagar and Joynagar (Dashamighat) for the National Green Tribunal, with the map, return period and status not known [TBC]. The DST&E's guidelines for the protection of lakes, ponds and water bodies, notified after the High Court's order in WP(C)(PIL) No. 2 of 2014 (as cited), were not read, a direction against construction "within 75 Mtrs. of the end of the lake" is of unverified source and scope, and the zoning regulations of the Master Plan 2045 were not read [TBC]; none of them is treated here as a rule. No flood-plain zoning Act or Bill of Tripura was found, and a Union press report says only four States have one (as reported). Where a rule of the TBR 2017 or a Master Plan line governs, it applies; this Manual adds the hydraulic corridor and setback zones of Chapter 7, with a Zone 1 of at least 15 m from the top of bank on every natural channel draining 8 ha or more, rivers, chharas, khals and lunga flow paths alike, and round every pukur, dighi and beel, and a Zone 2 to the 1% AEP extent plus 10 m, the line that reaches furthest from the water governing, as this Manual's proposal. Zone 1 is a no-build zone, so it is stricter than r.9(4) everywhere and than the 5 m of r.90(1)(i), and it adds a corridor round tanks and along chharas and lungas where the rules set only a drainage duty or protective works (Chapter 7); it applies to new development and redevelopment, and Zone 1 land that is private is reserved in the Master Plan or secured by agreement, not taken. A BSMP gives the Master Plan the 1% AEP drainage-flood map and the buffer widths of Chapter 7 as an input to the hazard surveys of r.2(44), not as a notification under it. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the TBR 2017 already exclude water bodies from the area counted as park (r.9(2)), require public open spaces above 500 m² to have "arrangements for complete utilization and capture of storm water" (r.110(4)), ask for permeable materials on all open parking in group housing (r.110) and set landscaping of 1.0–7.5% of plots above 150 m² (r.113, 2022), but allow a ground coverage of 70% for every use and 100% on some industrial and commercial plots (r.46(1) and r.51(2), 2025) and set no detention or peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one, and on the lungas and flood plains, where the water table is near the surface in the monsoon, it is a shallow lined storage that drains to the outfall, never an infiltration basin (Clause 4.11, lunga rule). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.


11.10 Consultation and publication

11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.

11.10.2 After approval, the following shall be published as open data:

  • the model files;
  • the flood hazard maps;
  • the data of Clause 11.5.1, except security-sensitive asset details; and
  • the CIP.

They shall also be shown on a public map viewer.

Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.


11.11 Approval, review and reporting

11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.

11.11.2 Review. Each BSMP shall be reviewed:

  • every 10 years;
  • within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
  • when the statutory land-use plan is revised.

11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:

  • CIP progress;
  • the fee-in-lieu ledger (Clause 4.13.4);
  • maintenance completed; and
  • any flooding against the levels of service.

11.12 Interim arrangements

11.12.1 Until a BSMP is approved for a basin:

  • (a) all site criteria of Chapters 4 to 8 apply in full;
  • (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
  • (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
  • (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.

References (chapter)

  • Government of Tripura, Urban Development Department. Master Plan for the Agartala Planning Area 2045, declared final on 24 February 2026 under s.53(1) of the Tripura Urban Planning and Development Act, 2018 (as reported; notification and text not read [TBC]); and TUDA notification No. F2(15)-TUDA/TECH/2019(P) under s.52(1), November 2019 (Local Planning Areas adjacent to 20 cities and towns). http://web.archive.org/web/20240521223656/https://udd.tripura.gov.in/sites/default/files/2024-05/Local%20Planning%20Areas%20Notification..pdf
  • Tripura Urban Planning and Development Act, 2018 (Tripura Act No. 12 of 2018): ss.52, 53 and 163. https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/Urban%20Planning%20and%20Development%20Act,%20Tripura,%202018.pdf
  • Tripura Municipal Act, 1994, as amended to 7 May 2025: ss.1(2), 91, 156–166 and 233. https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/Municipal%20Act,%20Tripura,%201994.pdf
  • Asian Development Bank (2020). Agartala City Urban Development Project (53262-001): initial environmental examination (draft, November 2020) (city zones, saucer, drains, pumps, the Haora and the Katakhal, 48.2 km of drains). https://www.adb.org/sites/default/files/project-documents/53262/53262-001-iee-en_6.pdf
  • Central Ground Water Board, North Eastern Region. Aquifer Mapping and Management Plan of West Tripura District (NAQUIM, AAP 2017-18) (landforms, rivers and catchments, depth to water, iron, recharge). http://web.archive.org/web/20221212020843/https://cgwb.gov.in/AQM/NAQUIM_REPORT/Tripura/NAQUIM%20Report-West%20Tripura.pdf
  • National Green Tribunal. O.A. No. 606 of 2018, affidavit of the Government of Tripura filed 6 July 2026 (sewers, treatment plants, interception of drains); O.A. No. 673 of 2018, affidavit of the State of Tripura in E.A. No. 35 of 2023 (the Haora, its drains and flood-plain localities). https://www.greentribunal.gov.in/
  • Comptroller and Auditor General of India. Audit Reports for the years 2019-20, 2021-22 and 2022-23 (Government of Tripura). https://cag.gov.in/
  • Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
  • Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
  • Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
  • Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
  • Government of Tripura, Urban Development Department. Tripura Building Rules, 2017, as amended to the Fifth Amendment, 2025 (citation in Chapter 10): rules 2(44), 4(1)(e), 9(2)–(4), 32, 55, 90(1)(i) and (m), 110 and 113.
  • Government of Tripura, Revenue Department. Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025 (Gazette Extraordinary No. 1072, 3 June 2025), as amended on 6 March 2026 (Gazette Extraordinary No. 2026350): Appendix-I, classification of land.
  • Ramsar Convention. Rudrasagar Lake, site no. 1572, information sheet (as cited); and Forest Department, Government of Tripura, Rudrasagar page and the constitution of the Wetland Authority of Tripura, No. F.17(54)/For-Dev/WATIL/2017/24661-686 of 5 September 2018 (as cited).
  • High Court of Tripura. WP(C)(PIL) No. 2 of 2014, Bibash Ch. Saha v. State of Tripura (as cited); WP(C)(PIL) No. 05 of 2017 (Rudrasagar; as reported); WP(C)(PIL) No. 06 of 2026, judgment of 8 September 2026.
  • National Green Tribunal. O.A. No. 325 of 2015, Tripura's report of 26 May 2020 on urban water bodies (as reported).
  • Indian Journal of Fisheries (ICAR). Study of the Dumbur reservoir (water spread). https://epubs.icar.org.in/index.php/IJF/article/download/38686/22160/488756
  • South Asia Network on Dams, Rivers and People (2018, 2024). Transcriptions of CWC site data for Tripura and of IMD district rainfall for August 2024. https://sandrp.in/2024/08/23/august-2024-tripura-floods-questions-over-disaster-management/
  • Indian Masterminds, India Today NE, NewKerala, NE Now, Construction World, The NewsMill, Northeast Today, EastMojo, Tripuranet, Deccan Herald and other sources (2014–2026). Reports of the Master Plan 2045, the ADB loans and the drainage programme, the flood pumps, the ₹1,000 crore proposal, the Katakhal cleaning, the embankment programme, the filling of ponds, the Rudrasagar case and the floods and landslides of 2024 and 2026 (secondary sources).

Annexes and forms

Annex / Form Content
11A BSMP terms of reference template
11B Basin lists and boundaries for Tier A bodies
11C Depth–damage curves for Tripura building types
11D BSMP data and model publication standard
Form 11-1 Annual implementation report