Draft v1.0 prepared by NEER. Not adopted by the Government of Tripura, the TTAADC or any authority or local body, and has no legal force. About this draft

Chapter 6Minor and Major Drainage Systems


6.1 Purpose and scope

6.1.1 This chapter sets the level of service and the hydraulic criteria for the conveyance system that carries runoff from a development, a road or a public drainage scheme to a receiving waterway, tank or outfall. It covers:

  • (a) the dual drainage concept: a minor system and a major system (Clause 6.3);
  • (b) design return periods by land use and road class (Clause 6.4);
  • (c) street hydraulics: spread, depth and flow hazard (Clause 6.5);
  • (d) inlets, including clogging (Clause 6.6);
  • (e) pipes and open and covered drains (Clause 6.7);
  • (f) hydraulic grade line analysis (Clause 6.8);
  • (g) overland flow paths, ponding at sags and building floor levels (Clauses 6.9 to 6.11);
  • (h) culverts and road crossings (Clause 6.12); and
  • (i) Tripura construction-practice requirements for covered drains, silt, solid waste, utilities and desilting access (Clause 6.13).

6.1.2 The detailed hydraulic design of individual structures (culverts, channels, energy dissipators, screens, pumps, gates, manholes) is in Chapter 9. Rainfall is in Chapter 2, runoff methods in Chapter 3, on-site storage in Chapter 4, tailwater in Chapter 5, waterbodies in Chapter 7 and water quality in Chapter 8.

6.1.3 This chapter applies to all public drains, all roads with kerbs or roadside drains, and all private drainage systems in developments that meet the applicability thresholds of Chapter 1. In Tier B local bodies, the simplified procedures and design aids referred to in Chapter 1 may be used for elements serving ≤ 16 ha, but the criteria of this chapter still apply.

Commentary. Tripura's drains were not designed against any State or municipal standard: none was found during research, and no document found gives a design return period, runoff coefficient or drain size for any town (Clause 2.3.6(o)). The ADB found that "Although GAPA has numerous storm water drains and two major rivers flowing through it, the city suffers from recurrent flood problems. During normal rainfall of about 3 to 4 hours, the central part of Agartala gets flooded", that "Most of the main drains are masonry-lined, but the feeder drains are earth-lined and in a poor condition with silt and vegetation choking them" (ADB IEE, 2020), and its Agartala project provides 48.2 km of new or rehabilitated drains (ADB IEE, 2020); the State told the NGT that a "Partial drainage system is present in Agartala Municipal Corporation" (State affidavit in O.A. No. 673 of 2018), and about 50 km of new drains were reported planned by the Agartala Municipal Corporation and Agartala Smart City Ltd (as reported). Nothing was found for the drains of the other towns [TBC]. The drains also work in a setting that the plains editions of this Manual meet only in part. They run on lungas (Bengali লুঙ্গা: the flat valley land between low hills — the land records' "Flat lands between tillas"), the natural flow paths of the valleys, where towns are built and ponds filled; they take the runoff and silt of the tillas (Bengali টিলা: a low hill or hillock — the land records' "Hillock"), "10 – 30 m high mounds with gullies in between them" (CGWB NAQUIM, West Tripura), and of chharas (Bengali ছড়া: a stream — the land records' "Streams") from the hill ranges; they end at sluices in embankments, or bandhs (Bengali বাঁধ: an embankment — the land records' "Embankment"), behind rivers that stand above the town, in khals (Bengali খাল: a canal or channel — the land records' "Khal") such as the Katakhal and the Akhaura canal that cross into Bangladesh, and in pukurs and dighis; and they carry the towns' sewage, because Agartala's sewers serve only its North Zone and no other town has any (State affidavit to the NGT, July 2026). And they are divided among owners: the drains vest in the Municipality (Tripura Municipal Act, 1994, s.91), but in Agartala the UDD and PWD (DWS) carry out 98% of the AMRUT works "and only a few minor works" are the Corporation's (CAG, Audit Report 2019-20), PWD (R&B) builds the major roads and drains, Agartala Smart City Ltd the new storm drains and flood pumps, PWD (WR) the embankments and the Katakhal sluice, and NHIDCL the national-highway drains on NH-108B and NH-208, with no formal allocation among them (see the Commentary to Clause 6.9). Fixing the rainfall (Chapter 2) is only half the answer. The other half is a second, surface-level system that carries the flows the pipes cannot, without flooding buildings. That is the dual drainage concept of this chapter, taken from Kansas City Metro APWA Section 5600 (5601.8, Levels of Service), which requires every element to have a 1% AEP overflow path.


6.2 Definitions

Term Meaning in this Manual
Minor system Inlets, pipes, covered drains and open drains that carry runoff up to the minor design AEP of Table 6.1 without surcharge above the limits of Clause 6.8.
Major system The surface flow paths (streets, overland flow paths, open channels, floodways and storage) that carry flow above the capacity of the minor system, up to the 1% AEP (100-yr) event.
Overland flow path A defined surface route, in public land or a recorded easement, that carries major-system flow to a receiving waterway.
Spread (T) Width of flow in the gutter and carriageway, measured from the face of the kerb.
Sag A low point on a road or flow path from which water can leave only through an inlet or by ponding to an overflow level. A trapped sag has no surface overflow route.
Clogging factor The fraction of an inlet's clean hydraulic capacity assumed lost to debris (Clause 6.6.3).
Hydraulic grade line (HGL) The line joining the free-surface levels in a conduit system, or the piezometric levels where the system is under pressure.
Covered drain A rectangular drain, usually beside a road, closed by cast-in-situ or precast cover slabs that form a footpath.
Sediment allowance The depth or area of a drain or pipe assumed filled with silt when its design capacity is computed (Clause 6.7.8).
Check event An AEP rarer than the design AEP at which the combined minor and major system must still meet the limits of Table 6.2.
High-density area An area notified as such by the approving authority under Clause 6.4.4.
Class I area An urban local body with a population of 1 lakh or more (the CPHEEO definition).

6.3 The dual drainage concept

6.3.1 Every drainage system shall be designed as two systems that work together:

  • (a) a minor system that carries the minor design flow of Table 6.1 below ground or in drains, keeping streets usable and spread within Table 6.2; and
  • (b) a major system that carries all flow above the minor-system capacity, up to the 1% AEP (100-yr) flow, on the surface without entering buildings and within the depth and hazard limits of Clause 6.5.

6.3.2 Every element has a 1% path. Every inlet, sag, pipe, drain, culvert and storage element shall have an identified 1% AEP overland flow path to a receiving waterway, tank or outfall. The path shall be shown on the drainage plan (Clause 6.15).

6.3.3 Major-system design flow. The major system at any point shall carry the 1% AEP peak flow less the minor-system capacity at that point. The minor-system capacity used in this subtraction is the capacity of the inlets after the clogging factors of Clause 6.6.3, or the pipe capacity, whichever is less. At sags and at any location used to set building floor levels, the major system shall also be checked with the minor system fully blocked (Clause 6.10.3).

6.3.4 Rainfall and method. Design flows shall use the rainfall of Chapter 2 (including the climate factor of Clause 2.8) and the methods of Chapter 3:

  • (a) the Rational Method only for catchments ≤ 16 ha and a single conveyance element. It shall not be used to accumulate flows down a network whose total catchment exceeds 16 ha;
  • (b) a hydrograph method with hydraulic routing (for example SWMM, HEC-HMS with a hydraulic model, or an equivalent 1D/2D model) for networks above 16 ha and for any network with storage, pumping or a tidal outfall;
  • (c) a minimum time of concentration of 10 minutes.

6.3.5 No transfer between catchments. Neither the minor nor the major system shall divert flow from one natural catchment to another unless the approving authority accepts a catchment-wide study showing no adverse effect.

6.3.6 Drains that carry sewage, and tilla and hill drains. No town in Tripura has a full sewerage system: Agartala's sewers serve only its North Zone, and the other 19 ULBs treat none of their sewage (State affidavit to the NGT in O.A. No. 606 of 2018, 6 July 2026). So the public drain that receives storm water from a site or a public drainage project normally also carries sewage and sullage (Clause 8.9); and on the tillas and in the hill ranges the drains also carry silt, sand and debris. This chapter applies to the storm-water system up to the point of connection and to every public drain, with the following additions (all set by this Manual).

Items (a) to (e) apply wherever the receiving drain carries dry-weather flow of sewage or sullage, whatever its owner calls it:

  • (a) Separation on site. Storm water and sewage shall be collected in separate systems within the site, each with its own last inspection chamber at the site boundary, so that the storm-water system can be connected to a separate public storm drain, without rework on the site, when one is built or when the sewers of the area are commissioned. Where the Authority allows only one connection to the receiving drain, the two systems shall meet only in a final chamber after both inspection chambers. The Municipality's existing power to "require separate provisions to be made for drainage of sewage and other offensive matters as distinct from rain-water and other unpolluted sub-soil water" (Tripura Municipal Act, 1994, s.164), its written permission for every connection (s.161), and, in the ULBs in the hill areas, the rule that drains for surface water "shall not be connected with any drain carrying sullage water or sewage" (TBR 2017, r.99(2)(d)) are the hooks for this item. Clause 6.13.7 applies to every storm drain within the site.
  • (b) No rise in the peak inflow. A development to which Chapter 4 applies shall meet Chapter 4 at each connection to a drain that carries sewage, as at any other site outfall (Clause 4.5.1.3). A development below the thresholds of Clause 1.5.2 shall not raise the peak inflow above that of the site before the development: where it adds impervious area, the roof water of the added area shall pass through a rainwater harvesting or storage tank with a controlled overflow before it reaches the connection.
  • (c) Tailwater and backflow. The HGL of Clause 6.8 shall be started from the level in the receiving drain at the connection in the coincident event, taken from the owner's model where one exists and otherwise at the drain's obvert or top of bank (Clause 5.6.2). Where the receiving drain ends at a river-locked or pumped outfall, the outfall-closed check of Clause 5.10 applies with the lock of Clause 5.8.5(a), and in Agartala's central saucer with the pumps of Clause 5.8.5(b). A non-return valve (Clause 6.8.8) shall be fitted on every connection, storm or foul, to a drain that carries sewage wherever the lowest drainage fitting or opening it serves is below the cover or bank level of the receiving drain at the connection.
  • (d) Capacity, velocity, access and odour. A public drain that carries sewage shall be designed as a combined channel until the sewers of its area are connected: its storm capacity used in Clause 6.3.3 shall be the capacity left after its dry-weather flow, measured or estimated from the population served; it shall reach the minimum velocity of Clause 6.7.3(a) at its dry-weather flow, or have a low-flow channel in its invert that does, so that sewage solids do not settle between storms; where it is covered, it shall have the access openings of Clause 6.13.2, with covers and vents placed so that odour does not reach homes and footpaths; and it shall be cleanable by machine from those openings, without anyone entering it. Flow above its storm capacity, or above what the inlets admit, shall be carried on the surface by the major system (Clauses 6.3.2 and 6.9), and floor levels shall be set under Clause 6.11 with the drain surcharged.
  • (e) Interception and screens before outfalls; separation planned by the Authority. Every public drain that carries sewage shall have dry-weather-flow interception and a screen before its outfall to a pukur, a dighi, a beel, the Haora, the Katakhal, the Akhaura canal, the Kalapania Khal or a channel that drains to Rudrasagar, designed under Clause 8.9. The interception shall be sized on the dry-weather flow, with a defined bypass for monsoon flows, so that it does not reduce the drain's storm capacity and so that storm flows are kept out of the sewage treatment plants that the interception feeds; the screen shall be sized for the plastic and solid waste that the drain carries. No new storm drain shall be brought to a pukur, a dighi or the catchment of Rudrasagar without that treatment. The Authority shall identify in its master plan (Chapter 11) the areas where a separate public storm drain is feasible, among them the sewered North Zone of Agartala as its connections are made, and elsewhere the storage that will hold back the combined peak; where a separate public storm drain is available at the site boundary, the site's storm-water system shall be connected to it and not to the drain that carries sewage. The Conveyance Design Report (Form 6-1) shall state whether each receiving drain carries sewage, whether it is intercepted to a sewage treatment plant, the source of that information, and how items (a) to (e) are met.

Items (f) to (m) apply to every element of the minor and major systems that receives runoff from a tilla or hill catchment, which in this Manual means land in sub-area TR-E of Annex 2A (the Baramura, Atharamura, Longtharai, Sakhan and Jampui ranges and the hill faces above the valley towns), the tilla slopes and cut faces of every valley (Clause 4.11 (tilla rule) and (hill rule)), any catchment whose natural ground slopes more than 10% on average, and every chhara that comes down from the tillas or the hill ranges:

  • (f) Debris racks and traps. Every inlet, drain or pipe entrance and culvert that receives flow from 1 ha or more of unbuilt tilla or hill land (forest, bamboo, scrub, cultivated or bare slope, a cut tilla, a quarry or a cut slope), or from a chhara whatever its catchment, shall have a debris rack or a debris trap upstream of it, designed under Chapter 9 (Clause 9.8), with machine access and a stable place to stockpile what it catches, which shall not be a slope, a chhara, a lunga floor or a pukur margin. With 50% of the rack blocked, the element it protects shall still pass its design flow, and the overflow route shall not send the flow onto a building or an unprotected slope. Racks and traps shall be cleared by 31 March, again by 31 May after the April–May storms, and after the season by 15 November (Chapter 10). The volume of a debris basin is to be set in Chapter 9 [TBC].
  • (g) Bulking factor. The design flow of every channel, drain, pipe, culvert and crossing that receives flow from a tilla or hill catchment shall be the clear-water peak flow of Chapter 3 multiplied by a bulking factor of 1.25, for the minor design flow, the check event and the 1% AEP flow; elsewhere the factor is 1.0. The factor applies to capacity, freeboard and velocity; it does not apply to the runoff volume used for storage (Chapter 4). A larger factor shall be used where a sediment study of the catchment gives one. A catchment that the screening of Clause 2.3.6(i) shows to be prone to landslides, or that drains a mapped slide, a cut tilla face that has failed or a channel-shift path, is not designed by a bulking factor: no building, outfall, pumping station or storage shall be placed in that path, and the drains are designed for the bulked flow only [TBC].
  • (h) Blockage. The blockage check of Clause 6.12.4 shall assume 50% of the inlet area blocked for every culvert and pipe entrance with a span or diameter below 3.0 m, and 20% for larger ones, whether or not a debris rack is provided. Grate inlets keep the clogging factor of Table 6.5, and kerb openings on grade take the sag value of 20%.
  • (i) Sediment and minimum velocity. Drains and pipes that receive flow from a tilla or hill catchment shall reach a velocity of at least 1.0 m/s at the minor design flow, in place of the minimum of Clause 6.7.3(a). Where the gradient does not allow it, a sediment trap shall be provided upstream and the sediment allowance of Clause 6.7.8 doubled (Clause 6.7.4).
  • (j) Steep drains and steep streets. Where the gradient of a drain gives a velocity above the limits of Clause 6.7.3(b), or a Froude number above 0.8, at the design flow, the drain shall be a lined chute, a stepped channel or a series of drop structures designed under Chapter 9 for the bulked flow of item (g), with the freeboard of Table 6.7 for steep channels and an energy dissipator at every change to a flatter gradient and at the outlet. On a street steeper than 5%, grate-only inlets shall not be used, and inlets shall be placed by the calculation of Clause 6.6.4 with the bypass flows of a steep gutter; on a street steeper than 10%, the flow shall be intercepted by transverse grated channels or kerb inlets at a spacing that keeps the street flow within the limits of Table 6.3 in the check and 1% AEP events, and where the 1% AEP flow cannot be kept within those limits, the excess shall be carried in a lined side channel or stepped drain and the street, unless it is a notified evacuation route, is treated as closed in that event. Steps and footpaths that carry flow shall have a lined side channel.
  • (k) Hill roads as the minor system. On every road and street in a tilla or hill catchment as this clause defines it, the drainage of a road is the minor system for the land above it as well as for the road. Every such road and street shall have, as works of the road's owner, PWD (R&B), NHIDCL, the Municipality or the District Council: (i) a lined catch-water drain above every cut slope where the land above drains towards the road, discharging to a natural channel or a cross-drainage work and not over the cut; (ii) lined side drains on the hill side (IRC:SP:42-2014, cl. 8.5.1); (iii) a cross-drainage work at every chhara and stream, and culverts or scuppers at intervals such that no side drain exceeds its capacity at the design AEP of Table 6.1 with the factors of items (g) and (h); (iv) at the outlet of every scupper, culvert and side drain on the valley side, a lined chute, cascade or pipe carrying the flow to a stable natural channel or a public drain, with an energy dissipator, so that road runoff is never discharged onto an unprotected slope, fill, retaining wall or the land of a building below, by PWD (R&B), NHIDCL or any other owner of a road; (v) culverts of at least the size of Clause 6.12.5, designed under Clause 6.12 and not less than IRC:SP:42-2014 cl. 7.1.4 requires for the road, kept clear of silt, vegetation and debris after every heavy-rainfall day and on the dates of item (f); where the drainage provisions of IRC:SP:48-1998, the Hill Road Manual, which were not read for this Manual [TBC], are stricter than this item, they apply; and (vi) no spoil or excavated material from the construction, widening or maintenance of the road, or from tilla or hill cutting beside it, placed in or beside a chhara, a lunga floor or another line of natural drainage, or on a slope from which a storm can carry it into one.
  • (l) Sloping sites and tilla cutting. On a site where the land above drains towards a building, its cut or its retaining wall, the runoff of that land shall be intercepted above them by a lined diversion drain sized for the minor design flow of Table 6.1 from the land above it, with the factors of items (g) and (h), with a 1% AEP flow path that does not pass through or against the building. The space between a building and the cut or retaining wall above it shall be paved or lined and drained so that water does not stand against the building or soak into the foot of the cut, and both shall discharge to a public drain or a stable natural channel as item (k)(iv) requires, not onto the slope below. Roof and paved-area runoff on such a site follows the tilla rule or the hill rule of Clause 4.11. These items give a design standard to what the Tripura Building Rules 2017 already ask of the ULBs in the hill areas: "diversion of the natural flow of water coming from uphill side of the building away from the foundation" (r.91(r)); a drainage system that carries the water of the site and of "the hillside above" to "main drains or natural streams/jhoras without stagnation, avoiding any possibility of erosion, slope failure" (r.99(1)(c)); slopes "not less than 1 : 60" all round a building and the uphill flow diverted "through suitable lined or unlined drains" (r.99(2)(a) and (b)); an impervious apron "not less than 0.75 m. wide" (r.99(2)(l)); breast and retaining walls with weep holes and filters (r.100); a soil test and slope-stability certificate on slopes of 30° and above (r.90(1)(f)); and no site within 200 m of "a sinking or probable slip zone" (r.90(1)(h)). The rules do not list which ULBs are in the hill areas [TBC], and they do not extend to tilla land outside Part X or to the TTAADC area, where this item applies on its own.
  • (m) The tilla foot, the hill–lunga break, silt and waste. Where a chhara, a gully of the tilla uplands or a drain that receives one reaches the lunga floor or flatter ground, a silt trap designed under Chapter 9 (Clause 9.8) shall be provided above the point where the gradient falls, at every tilla foot that drains 1 ha or more of tilla land to a public drain, with machine access and a stockpile place that is not a chhara, a lunga floor, a pukur margin or a slope, sized for the sediment of item (i) and cleared on the dates of item (f) and after every heavy-rainfall day (Chapter 10). No spoil from tilla or hill cutting and no construction and demolition waste shall be placed where a storm can carry it into a drain, a chhara, a lunga or a pukur; placing it in a chhara, a stream or a drain is a filling that r.9(3) of the TBR 2017 already bars without the State's prior approval. A trap or screen placed in a stream shall not raise its 1% AEP level at any outfall (Clause 5.8.5(f)) and shall be designed to be overtopped without damage. A trap is not a treatment work: dry-weather flow is intercepted under item (e) and Clause 8.9.

Commentary. The CPHEEO (2019) manual defines major and minor systems in its glossary but gives no return period for the major system. APWA 5600 (2006, 5601.8) requires the system to convey the 1% peak and, where in-system capacity is less, an overflow system to carry the remainder. Clause 6.3.3 subtracts only the clogged inlet capacity, not the full pipe capacity, because in practice the pipes cannot take more water than the inlets admit. The fully-blocked check at sags has no direct precedent; this Manual sets it because of the Agartala experience that drains under footpaths are often silted or blocked by solid waste when the heaviest rain arrives (CPHEEO 2019 Part A, Ch 1 and 2, Figures 1.2 and 2.1 on solid waste dumping in drains). The prohibition on inter-catchment transfer follows the DID Malaysia 2008 submission checklist, which prohibits inter-catchment diversion. Clause 6.3.6 is set by this Manual for Tripura, and it has two parts because the State's drains fail in two ways that the criteria of this chapter, which assume clear storm water on gentle ground, do not see. The first is sewage. The State generates 82.4 MLD of sewage against 17.4 MLD of treatment capacity, and Agartala alone 61.0 MLD; its 103.6 km of sewers, "with 4011 nos. household connection", run "only in the North Zone"; and its sewage treatment plants, the one at Akhaura and the 39.5 MLD under construction, "are designed to be connected through Interception & Diversion of Drains" (State affidavit to the NGT in O.A. No. 606 of 2018, 6 July 2026; the State gave the Central Monitoring Committee a figure of 227.43 MLD in August 2025, which conflicts). The tribunal's concern, as the State's affidavit quotes it, is that "storm water drains are being tapped and taken to STPs which is not legal. If surface drains are used as open conduit, then storm water flows should have separate conveyance system. Sewage and storm water mixing particularly during monsoon will not only upset functioning of STP but, will also lead overflow of untreated sewage"; and two of the plants stand near or on flood plain, where flooding may lead to "flowing of untreated sewage in the river during the monsoon" (NGT order of 13 April 2026, as quoted in the same affidavit). The law already allows the separation that item (a) asks of each site: the Municipality may "require separate provisions to be made for drainage of sewage and other offensive matters as distinct from rain-water" (Tripura Municipal Act, 1994, s.164), and in the hill ULBs surface-water drains "shall not be connected with any drain carrying sullage water or sewage" (TBR 2017, r.99(2)(d)). Items (a) to (e) follow the combined-sewer rules of the plains editions of this series and of the neighbouring North-East edition: a site keeps its storm water separate up to the boundary, so that the town can separate its system street by street as sewers are connected without going back into every plot; a development does not add to the peak of a drain that carries sewage; a non-return valve guards every connection, because what comes back up a surcharged drain is sewage; the drain is designed as the combined channel it is, with its capacity taken net of its dry-weather flow and a low-flow channel so that sewage solids do not settle in it between storms; and the outfall to a pukur, the Haora, the Katakhal or the Akhaura canal is intercepted and screened. Item (e) sizes the interception on dry-weather flow with a monsoon bypass because that is the tribunal's own point: an interception that takes storm flow upsets the plant and overflows untreated, and one that is sized for storm flow takes the drain's capacity. The screens are there because the CAG found that, with no wire nets on the drains, "solid waste or plastic waste reached to the river" and that "there is frequent water logging of different areas due to blockage of drains and canals by plastic waste" (CAG, Audit Report for the year 2022-23). Separation itself is for the Authority to plan, not for each site.

The second is the tillas and the hills. The tilla uplands are "10 – 30 m high mounds with gullies in between them" (CGWB NAQUIM, West Tripura), and they are cut for building and fill; the lungas between them are the valleys' flow paths, so the silt of every cut runs onto the lunga floor and into its drains. The slopes fail: 2,032 landslip locations were reported in August 2024, with deaths at Gardang near Santirbazar and at Debipur, and 17 in June 2018, 11 of them in Khowai district (all as reported). The roads through the hill ranges carry the same load: inspections for the High Court found on NH-108B and NH-208 "No proper drainage system … water logging everywhere; RCC drain hole blocked with mud, vegetation; Earthen drain damage & blocked", with culverts blocked "by silt, vegetation, debris" chainage by chainage (WP(C)(PIL) No. 06 of 2026, judgment of 8 September 2026, para 44). That is why item (m) puts a silt trap at every tilla foot and at the hill–lunga break, and item (k)(v) keeps culverts clear. No Tripura allowance for debris, bulking or blockage was found during research [TBC], and no Indian guidance on bulking factors, debris racks or debris basins [TBC], so each number in items (f) to (m) is the interim value of the hill and mountain editions of this series, with the same reasons. The 1 ha trigger for a debris rack reflects the few minutes' time of concentration on tilla and hill slopes. The bulking factor of 1.25 is the factor for a flow that carries a fifth of its volume as sediment (bulking factor = 1 / (1 − sediment fraction by volume)), about the most that a drain can carry and still behave as a water flood; a flow with more behaves as a debris flow, which no drain can be sized for, so item (g) keeps buildings and outfalls out of its path. The 3.0 m limit in item (h) doubles the core's 1.5 m because bamboo, timber, stones and waste block openings that leaves alone do not. The 1.0 m/s minimum in item (i) replaces the 0.6 m/s of CPHEEO, which is based on carrying fine sand of 0.09 mm, because tilla and hill drains carry coarser sand and gravel. IRC:SP:42-2014 (cl. 8.5.1) already treats hill roads differently, with lined side drains and culverts "at closer intervals compared to those in plain areas", and item (k) keeps road runoff off unprotected slopes because water discharged onto a slope raises its pore pressure (Clause 4.11). Part X of the Tripura Building Rules 2017 already reaches towards these rules in the hill ULBs without numbers; items (l) and (m) give them design standards of this Manual's own, and apply them also on the tillas of the plains ULBs and outside the rules' extent. The clause deals with sewage, silt and debris at the drain; it does not ask for the concrete channelisation of the chharas and lungas, whose capacity has been lost to filling and encroachment, not to roughness.


6.4 Design return periods

6.4.1 The minor system, roads and crossings shall be designed for the AEPs of Table 6.1. Where both a land-use row and a road-class row apply to an element, the rarer AEP (longer return period) governs.

Table 6.1 — Design AEPs for conveyance (matches Clause 2.4)

Element Design AEP (return period) Check event Basis
Minor system: Agartala core and other high-density areas 10% (10-yr) 1% (100-yr) overland path This Manual (see Commentary)
Minor system: other Class I areas 20% (5-yr) 1% overland path This Manual; CPHEEO Table 4.1
Minor system: other areas 50% (2-yr) 1% overland path This Manual; CPHEEO Table 4.1
Arterial road drainage and crossings 2% (50-yr) for arterials that are notified evacuation or emergency routes; 4% (25-yr) for other arterials Next higher AEP: 1% for a 2% design; 2% for a 4% design This Manual (25–50-yr); split set by this Manual
Collector road drainage and crossings 4% (25-yr) 2% (50-yr) This Manual
Local road drainage and crossings 10% (10-yr) 4% (25-yr) This Manual
Road underpasses and other trapped sags on public roads 2% (50-yr) 1% (100-yr) This Manual (Clause 6.10.5)
Airports, railway stations, power stations and other critical infrastructure 1% (100-yr) in Class I areas; 2% (50-yr) elsewhere — CPHEEO 2019 Table 4.1
Major (overland) system, every element 1% (100-yr) — This Manual
Building floor levels 1% level + 0.5 m freeboard — This Manual (Clause 6.11)

6.4.2 Check events. At the check event of Table 6.1, the combined minor and major system shall carry the check-event flow within the 1% AEP limits of Table 6.2 and without water entering any building. The 1% overland path requirement of Clause 6.3.2 applies in addition to the check event.

6.4.3 Higher standards. An approving authority may adopt a rarer AEP for any element, including through the high-powered committee route in Note 2 of CPHEEO Table 4.1. It shall not adopt a more frequent AEP than Table 6.1.

6.4.4 High-density areas. The approving authority shall notify, by map, the high-density areas to which the 10% AEP minor-system standard applies. Until it does, the 10% AEP standard applies to:

  • (a) in Agartala, the Central Zone between the Haora embankment and the Katakhal, the erstwhile municipal area and the city's saucer (ADB IEE, 2020); the localities that the sources name for flooding, Chandrapur, Baldakhal and Aralia (August 2026, as reported); the Haora flood-plain-zone localities that PWD (WR) has mapped, Khayerpur, Kashipur, Baldakhal, Aralia, Jogendranagar and Joynagar (Dashamighat) (State affidavit to the NGT in O.A. No. 673 of 2018); and any central business district or transit-oriented development zone with the base FAR of 7 under TBR 2017, r.50(6)(a); with the boundary of each to be confirmed by the Agartala Municipal Corporation and TUDA under the Master Plan for the Agartala Planning Area 2045, whose text was not read [TBC];
  • (b) in every Municipal Council and Nagar Panchayat area and every Local Planning Area, the area that the applicable Master Plan or development plan identifies as the core area, old town or central business district, and the main market of a town [TBC]; and
  • (c) any area in a Tier A body where the master plan permits a floor space index above the base value for the zone.

6.4.5 Retrofit. Where an existing drain cannot practicably be enlarged to the Table 6.1 AEP, the shortfall shall be made good by upstream storage (Chapter 4), regional storage (Chapter 7) or an improved major-system path. The approving authority shall record the residual level of service.

Commentary. The values in Table 6.1 match the Clause 2.4 summary and add rows for underpasses and critical infrastructure. They exceed the CPHEEO (2019) national advisory minimums of 5-yr for Class I cities and 2-yr elsewhere (CPHEEO Part A, Table 4.1). Note 2 of that table allows a State committee to adopt higher values. The 10-yr tier for high-density areas follows Gupta (IIT Bombay), who recommends "1 in 10 year for residential-high density", and Malaysia's MSMA 2, which uses 10-yr minor and 100-yr major systems for link houses, apartments, commercial and industrial land. The road values resolve a conflict in Indian codes. IRC:SP:50-2013 recommends 1–2 years for urban road drains. IRC:SP:42-2014 suggests 25 years for urban roadside drains and a check flood at the next higher return period. APWA 5600 (2006) uses 50-yr for arterial, 25-yr for collector and 10-yr for residential street crossings. Table 6.1 adopts the APWA tiers and the IRC:SP:42 check-flood concept. Splitting arterials into 50-yr evacuation routes and 25-yr others has no direct precedent and is set by this Manual. The 50-yr standard for underpasses is likewise set by this Manual, because an underpass is a trapped sag where the failure mode is deep water on a live carriageway. The default high-density areas in Clause 6.4.4 are set by this Manual and apply until the approving authority notifies a map.


6.5 Street hydraulics: spread, depth and flow hazard

6.5.1 Gutter flow. Flow in a triangular kerb-and-gutter section shall be computed with the modified Manning (Izzard) equation:

Q = (Ku / n) · Sx^(5/3) · SL^(1/2) · T^(8/3)

where Q is the gutter flow (m³/s), Ku = 0.376 (SI), n is the Manning roughness of the gutter (Table 6.6), Sx is the cross slope (m/m), SL is the longitudinal slope (m/m) and T is the spread (m). Composite and depressed gutter sections shall be analysed by the methods of FHWA HEC-22 (4th edition, 2024).

6.5.2 Spread and depth limits. Street flow shall not exceed the limits of Table 6.2.

Table 6.2 — Street flow limits

Road class Minor design event (Table 6.1) Check event and 1% AEP event
Arterial Spread shall leave at least one through lane in each direction clear of water. No flow across the crown. Depth ≤ 150 mm at the crown and ≤ 350 mm at the deepest point; hazard limits of Clause 6.5.3
Collector Spread T ≤ 3 m. No flow across the crown except at a sag intersection. As above
Local Spread T ≤ 3 m. Flow shall not overtop the kerb. As above
All classes, at intersections Cross-flow over the crown ≤ 0.03 m³/s at sag intersections and superelevation transitions; none at mid-block sags. As above

6.5.3 Flow hazard limits. In the check event and the 1% AEP event, the product of depth (D, m) and velocity (V, m/s) of street and overland flow shall not exceed the limits of Table 6.3.

Table 6.3 — Flow hazard limits for streets and overland flow paths

Location Required hazard class (Table 6.4) Limits
Carriageways of all roads H2 or better D·V ≤ 0.6 m²/s; D ≤ 0.35 m (Table 6.2); V ≤ 2.0 m/s
Footpaths, pedestrian crossings, school, hospital and transit-stop frontages H1 D·V ≤ 0.3 m²/s; D ≤ 0.3 m; V ≤ 2.0 m/s
Notified evacuation and emergency routes H1 D·V ≤ 0.3 m²/s; D ≤ 0.3 m; V ≤ 2.0 m/s
Overland flow paths in public open space or easements, away from roads H3 or better, with warning signs D·V ≤ 0.6 m²/s; D ≤ 1.2 m; V ≤ 2.0 m/s

Table 6.4 — Combined flood hazard vulnerability classes (reproduced for reference)

Class Description D·V limit (m²/s) Depth limit D (m) Velocity limit V (m/s)
H1 Generally safe for vehicles, people and buildings ≤ 0.3 0.3 2.0
H2 Unsafe for small vehicles ≤ 0.6 0.5 2.0
H3 Unsafe for vehicles, children and the elderly ≤ 0.6 1.2 2.0
H4 Unsafe for vehicles and people ≤ 1.0 2.0 2.0
H5 Unsafe for vehicles and people; buildings vulnerable to structural damage ≤ 4.0 4.0 4.0
H6 Unsafe for vehicles and people; all buildings vulnerable to failure > 4.0 — —

Source: AIDR Guideline 7-3, Technical flood risk management guideline: Flood hazard (2014), Tables 1 and 2, modelled after Smith and Wasko (2012).

6.5.4 Depth and velocity for Clause 6.5.3 shall be taken from the gutter-flow calculation for simple sections, or from a 1D or 2D hydraulic model where flow leaves the kerb-and-gutter section.

Dual drainage street cross-section Minor and major (dual) drainage in a kerbed street: section (not to scale) 1% AEP water level Road boundary Road boundary Footpath Plinth Building Lowest habitable floor and openings ≥ 0.5 m freeboard above 1% level Building Crown ≤ 150 mm at crown (1% AEP) ≤ 350 mm at deepest point (1% AEP) Minor-event spread T (≤ 3 m on local streets; one lane clear on arterials) Kerb inlet with silt sump Minor-system pipe: design AEP per Table 6.1; HGL ≥ 0.3 m below inlet rim (Clause 6.8) Major system: the street carries flow above pipe capacity along its length, up to the 1% AEP flow Minor (design) event flow 1% AEP (major) event Limit set by this Manual Silt sump Vertical scale exaggerated. Values are the Chapter 6 criteria (Clauses 6.5, 6.8 and 6.11).

Figure 6.1 — Minor and major drainage in a kerbed street. Original drawing for this Manual, adapted from Kansas City Metro APWA, Section 5600 (2006, 5601.8) and FHWA, HEC-22 Urban Drainage Design Manual (4th ed., 2024).

Commentary. The Izzard form of Manning's equation with Ku = 0.376 is used both in FHWA HEC-22 and in the CPHEEO (2019) manual (Part A, Example 5.5, where the constant is written Kc = 0.376). The arterial spread rule (one lane clear) and the 3 m spread for local and collector streets are close to the APWA 5600 (2006, 5604.2) limit of 12 ft (3.66 m) from the back of kerb in each outside lane. The cross-flow limit of 0.03 m³/s is the SI equivalent of the APWA limit of 1.0 cfs at intersection sumps and superelevation transitions, with no cross-flow at mid-block sumps. The 150 mm and 350 mm depth limits are close to the APWA 5600 limits for 1% overflow at road crossings (7 in, about 180 mm, at the crown; 14 in, about 360 mm, at the deepest point). Mumbai's criterion of no flooding above 15 cm (IRC:SP:50-2013, §6.4.1) is a local precedent for the 150 mm crown value.

The hazard classes of Table 6.4 are the combined hazard curves published by the Australian Institute for Disaster Resilience (AIDR Guideline 7-3, 2014), which are modelled after Smith and Wasko (2012). Requiring H2 or better on carriageways means the 1% depth limit of 350 mm (Table 6.2) governs the depth, and the D·V product controls fast, shallow flow on steep streets. H2 is described as "unsafe for small vehicles". Two-wheelers are the dominant vehicles on Tripura streets, so the 1% event must be treated as a road-closure event on all roads except notified evacuation routes, which must meet H1. The assignment of hazard classes to locations in Table 6.3 has no direct precedent and is set by this Manual.


6.6 Inlets

6.6.1 Inlet types. Inlets may be kerb-opening inlets, grate inlets, combination inlets (a grate with a kerb opening) or slotted and trench drains. On public streets:

  • (a) kerb-opening or combination inlets shall be used, unless the approving authority accepts grate-only inlets for a specific location;
  • (b) inlet openings shall be set at road level, with a gutter depression where practicable, so that water is not held on the carriageway by a raised kerb or footpath;
  • (c) grates in carriageways, cycle lanes and footpaths shall be of a bicycle- and pedestrian-safe pattern (Chapter 9, Clause 9.11).

6.6.2 Inlet capacity. The clean capacity of inlets on grade and in sags shall be computed by the methods of FHWA HEC-22 (4th edition, 2024), or from tested ratings published by the manufacturer for the exact grate and kerb-opening geometry. The empirical kerb-inlet equations of CPHEEO (2019) Part A §5.6.2 may be used as a cross-check only.

6.6.3 Clogging factors. The design capacity of every inlet shall be its clean capacity reduced by the clogging factors of Table 6.5:

Table 6.5 — Inlet clogging factors (share of clean capacity assumed lost)

Inlet type On grade In a sag
Grate 50% 50%
Kerb opening 10% 20%
Combination Apply the grate and kerb factors to each part separately Apply the grate and kerb factors to each part separately

Design capacity = (1 − clogging factor) × clean capacity.

6.6.4 Inlet spacing. Inlets shall be located by a sequential calculation that starts at the top of each gutter run. At each inlet, the intercepted flow is computed, and the bypass flow is added to the gutter flow arriving at the next inlet. Spacing shall be such that the spread limits of Table 6.2 are met everywhere in the minor design event. In addition:

  • (a) inlet spacing shall not exceed 30 m on kerbed roads, whatever the calculation gives;
  • (b) inlets shall be provided at every sag, immediately upstream of pedestrian crossings and intersections, upstream of bridge decks and superelevation transitions, and at the end of every gutter run;
  • (c) bypass flow from the last inlet of a run shall not be passed onto a road of a higher class or into private land.

6.6.5 Sag inlets. At a sag on a kerbed road:

  • (a) the sag inlet's design capacity (after clogging) shall be not less than the total minor design flow arriving at the sag;
  • (b) flanking inlets shall be placed on each side of a sag on any road where ponding could spread beyond the Table 6.2 limits, and at every underpass;
  • (c) the ponding at the sag shall comply with Clause 6.10.

6.6.6 Inlet connections. The pipe connecting an inlet to the main drain shall have a diameter of at least 300 mm and shall be laid at a gradient that gives at least 0.9 m/s at the inlet's design flow.

6.6.7 Silt sumps. Every inlet chamber on a public road shall have a silt sump at least 300 mm deep below the invert of its outlet pipe, accessible for cleaning from the surface.

Inlet spacing, spread and clogging plan Gutter spread, inlet interception and clogging: plan (not to scale) Footpath Kerb Crown / lane line Spread limit T(max), Clause 6.5 Longitudinal grade Inlet on grade: intercepts Qi = E·Q; the bypass flow goes to the next inlet Inlet spacing: set so that T ≤ T(max) Sag: main inlet plus flanking inlets; ponding limit and overflow path (Clause 6.10) Clogging factors (share of clean capacity lost), Clause 6.6 Inlet type On grade Sag Grate 50% 50% Kerb opening 10% 20% Combination Each part as above Each part as above Gutter flow spread (minor event) Ponding at sag Assumed clogged portion Kerb opening

Figure 6.2 — Gutter spread, inlet interception and clogging. Original drawing for this Manual, adapted from FHWA, HEC-22 Urban Drainage Design Manual (3rd ed., 2009; 4th ed., 2024) and CPHEEO, Manual on Storm Water Drainage Systems (2019).

Commentary. The clogging factors are more severe than the APWA 5600 (2006, 5604.2) rating of sump inlets at 80% of theoretical capacity (a 20% reduction), because grates in Tripura streets are routinely blinded by plastic and leaves. CPHEEO (2019) Part A shows solid waste dumped in drains as a primary cause of drain failure (Figures 1.2 and 2.1). APWA 5600 (2006) allows only kerb-opening inlets on public streets; Clause 6.6.1(a) is less strict because combination inlets are useful on flat roads. No standard inlet, kerb-channel or covered-drain detail of PWD (R&B), of the Agartala Municipal Corporation, of Agartala Smart City Ltd or of any other local body in the State was found during research [TBC]; the Tripura Building Rules 2017 ask only for "the house drainage plan, and site drainage plan up to nearest Nagar Panchayat or Municipality or natural outfall" (TBR 2017, r.14) and, in a sub-division, "drainage facilities with pucca drain ensuing drainage of each individual plot … leading to existing public drain or natural drainage channels" (r.10(2)(f)). The 30 m maximum spacing and the treatment of combination inlets in Table 6.5 have no direct precedent and are set by this Manual. Roads on the lunga floors and flood plains of Tripura's valleys, and in Agartala's flat central saucer, are very flat, which shortens the calculated spacing anyway; on the steep roads of the hill ranges and through tilla cuts, gutter flow runs fast and passes inlets by, which Clause 6.3.6(j) deals with. A fixed cap stops a single blocked inlet from leaving a long dry gutter run. The 300 mm silt sump is set by this Manual. It matches the 0.3 m sump shown on the CPHEEO catch-basin detail (CPHEEO 2019, Figure 5.9).


6.7 Pipes and open and covered drains

6.7.1 Uniform flow. Pipe and drain capacity shall be computed with Manning's equation:

V = (1/n) · R^(2/3) · S^(1/2); Q = A · V

where V is the mean velocity (m/s), n is the Manning roughness (Table 6.6), R is the hydraulic radius (m), S is the friction slope (m/m), A is the flow area (m²) and Q is the discharge (m³/s). Where backwater from a tailwater, a junction or a structure affects the water level, a gradually varied flow (standard step) or hydraulic network model shall be used, and the HGL requirements of Clause 6.8 apply.

6.7.2 Manning roughness. Design values of n shall be taken from Table 6.6. For concrete pipes and masonry or concrete drains, the design value shall be not less than the "fair" or "rough" condition value listed, to allow for sediment, biofilm and ageing.

Table 6.6 — Manning's n for design (from CPHEEO 2019)

Material Condition n (CPHEEO) Minimum design n in this Manual
Cement concrete pipe (collar joints) Good / fair 0.013 / 0.015 0.015
Spun concrete pipe (RCC, PSC) with S/S joints Manufacturer's design value 0.011 0.013
HDPE / uPVC pipe — 0.010 0.011
Plastic (smooth), asbestos cement — 0.011 0.011
Concrete drain, steel trowelled / wood trowelled — 0.014 / 0.015 0.015
Sand and cement plaster — 0.015 0.015
Brick masonry Good / rough 0.015 / 0.017 0.017
Masonry Bad condition 0.020 0.020
Rubble set in cement — 0.017 0.017
Earth channel Regular, good / ordinary 0.020 / 0.025 0.025
Earth channel With stones and weeds / poor 0.030 / 0.035 0.035
Earth channel Partly obstructed by debris or weeds 0.050 0.050
Gutter: concrete — 0.013 0.013
Gutter: hot-mix asphalt — 0.015 0.015
Gutter: sprayed seal — 0.018 0.018

Source of the CPHEEO column: CPHEEO (2019) Part A, Table 5.1 (itself from the CPHEEO Manual on Sewerage and Sewage Treatment Systems, 2013) and Table 5.8 (gutters).

6.7.3 Velocity limits. At the minor design flow:

  • (a) minimum (self-cleansing) velocity: 0.6 m/s in open and covered drains and 0.9 m/s in pipes;
  • (b) maximum velocity: 3.0 m/s in lined drains and in pipes, unless the drain or pipe is designed as a chute under Chapter 9. CPHEEO permits up to 6.0 m/s in plastic or plastic-lined pipes in hilly regions; this may be used in the hill settlements of the Jampui hills (Vangmun), Gandacherra and Chhamanu, in any ULB in the hill areas under Part X of the Tripura Building Rules 2017 (which the rules do not list [TBC]) and other hill towns with the approving authority's agreement;
  • (c) maximum velocity in unlined and vegetated channels: Chapter 9, Table 9.2;
  • (d) the Froude number of flow in open and covered drains shall not exceed 0.8 at the design flow, unless the drain is designed for supercritical flow under Chapter 9.

6.7.4 Gradient. Each pipe and drain shall be laid at a gradient that achieves Clause 6.7.3(a). Where flat terrain or a fixed outfall level makes this impossible, the designer shall:

  • (a) report the velocity achieved;
  • (b) double the sediment allowance of Clause 6.7.8; and
  • (c) provide access for mechanical desilting at the spacing of Clause 6.13.2.

6.7.5 Pipe flow condition. Pipes shall be sized so that the minor design flow does not exceed the pipe-full capacity. The greater discharge that a circular pipe carries at about 0.95 of its depth shall not be relied on.

6.7.6 Minimum sizes.

  • (a) Pipes: 300 mm internal diameter; 450 mm for public mains.
  • (b) Open drains: bed width 0.3 m.
  • (c) Covered public drains (drains closed by cover slabs): clear internal width 0.6 m and clear internal depth 0.6 m.

6.7.7 Cover to pipes. Pipes shall have at least 0.6 m of cover to finished level, and at least 0.9 m under carriageways unless a structural design for the traffic load is submitted. Where the seasonal high groundwater table is within 1 m of the pipe crown, the pipe shall be checked for flotation with the pipe empty (CPHEEO 2019, Table 11.2) and anchored where necessary.

6.7.8 Sediment allowance. The design capacity of open drains, covered drains and pipes of 600 mm diameter or more shall be computed with the following depth of sediment at the invert:

  • (a) open and covered drains: the greater of 75 mm and 10% of the clear internal depth;
  • (b) pipes of 600 mm diameter or more: 5% of the internal diameter;
  • (c) pipes below 600 mm: no allowance, but Clause 6.7.3(a) shall be met.

The Manning n for the reduced section shall be that of the drain material in Table 6.6.

6.7.9 Freeboard in open and covered drains. At the minor design flow, the water surface (computed with the sediment allowance) shall be below the top of the drain wall, or below the soffit of the cover slab in a covered drain, by at least the freeboard of Table 6.7.

Table 6.7 — Minimum freeboard in open and covered drains

Drain Minimum freeboard Source
Bed width up to 300 mm 100 mm CPHEEO 2019 Table 5.3 (from IRC:SP:50-2013)
Bed width 300–900 mm 150 mm CPHEEO 2019 Table 5.3
Bed width 900–1,500 mm 300 mm CPHEEO 2019 Table 5.3
Wider drains and engineered channels, Q < 3 m³/s 450 mm CPHEEO 2019 Table 5.12 (from IS 7784 (Part 1): 1993)
Q 3 to < 30 m³/s 600 mm As above
Q 30 to < 300 m³/s 900 mm As above
Q 300 to < 3,000 m³/s 1,200 mm As above
Q ≥ 3,000 m³/s 1,500 mm As above
Any roadside drain Not less than 150 mm IRC:SP:42-2014
Steep (supercritical) channels Equal to the flow depth CPHEEO 2019 §5.3.2

At bends, the freeboard shall be measured from the water level on the outside of the bend, including the superelevation Δy = V²T / (2 g rc), where T is the top width and rc the centreline radius (CPHEEO 2019, Eq. 5.29).

6.7.10 Bends and junctions.

  • (a) The centreline radius of a bend in a drain shall be at least 3 times the drain width (CPHEEO 2019 §5.3.3). In engineered channels it shall be at least 2 times the top width and not less than 30 m (CPHEEO 2019 Table 5.11).
  • (b) Where drains meet, a junction sump shall be provided with an internal width of at least twice the width of the outgoing drain. Incoming drains shall enter at less than a right angle to the outgoing flow, and the outgoing invert shall be below the sump floor so that water does not stand in the sump (CPHEEO 2019 §5.3.4).

6.7.11 Manholes and access chambers on pipes. Manholes shall be provided at every junction, change of size, alignment or gradient, and at the head of every pipe. Spacing on straight runs shall not exceed Table 6.8.

Table 6.8 — Maximum spacing of manholes on straight pipe runs

Pipe diameter Maximum spacing
300–600 mm 40 m
700–1,000 mm 100 m
1,050–1,400 mm 150 m
1,500 mm and above 300 m

Source: CPHEEO 2019 Table 11.5. Manhole sizes, drops and covers: Chapter 9, Clause 9.12.

Open and covered drain sections Drain sections: freeboard, sediment allowance and access (not to scale) (a) Open lined drain (b) Covered roadside drain Design water surface Edge protection (Clause 6.13.8) Freeboard (Table 6.7) Sediment allowance: capacity is computed above this level (Clause 6.7.8) Bed width B ≥ 0.3 m (open drain) Carriageway Removable cover panel with lifting recess Slab Kerb inlet opening at road level, with silt sump (Cl. 6.13) Design water surface Freeboard to soffit No utility pipe or cable may cross through the flow area or freeboard (Clause 6.13.6) Clear width ≥ 0.6 m for covered public drains (Clause 6.7.6) Design flow Sediment allowance

Figure 6.3 — Drain sections: freeboard, sediment allowance and access. Original drawing for this Manual, adapted from CPHEEO, Manual on Storm Water Drainage Systems (2019), Tables 5.3 and 5.12, and IRC:SP:50-2013.

Commentary. The n values are those of CPHEEO (2019) Table 5.1. The higher minimum design values have no direct precedent; this Manual sets them because CPHEEO notes that the 0.011 value for spun pipes "may be taken as given by the manufacturer". That is a clean-pipe value, and Tripura drains carry heavy silt and solid waste. The 0.6 m/s minimum velocity is CPHEEO's (Table 5.2), based on carrying 0.09 mm sand (§5.3.1). The 0.9 m/s value for pipes is stricter, because a silted pipe cannot be cleaned as easily as an open drain. The 3.0 m/s maximum is from CPHEEO Table 5.2 (WPCF/ASCE 1982). The Froude limit of 0.8 is from CPHEEO §5.3, which advises avoiding critical flow because the water surface becomes unstable.

The 0.6 m × 0.6 m minimum for covered drains has no direct precedent and is set by this Manual. A covered drain narrower than this cannot be desilted by hand or by small machines through a cover opening, and silted, inaccessible drains were a recurring finding after the Agartala floods of 17–19 June 2022 and of 31 May–1 June 2025, when a man died in a manhole (as reported), in a city whose "feeder drains are earth-lined and in a poor condition with silt and vegetation choking them" (ADB IEE, 2020) and where the CAG found "frequent water logging of different areas due to blockage of drains and canals by plastic waste" (CAG, Audit Report for the year 2022-23), and on NH-108B and NH-208, where inspections for the High Court found an "RCC drain hole blocked with mud, vegetation" and culverts blocked "by silt, vegetation, debris" (WP(C)(PIL) No. 06 of 2026, judgment of 8 September 2026). The 0.6 m minimum cover is the value used in the CPHEEO (2019) worked pipe-design computation sheet (Part A, Chapter 5). The 0.9 m cover under carriageways is set by this Manual.

The sediment allowance values (75 mm or 10% for drains, 5% for large pipes) are set by this Manual. No Indian standard sets a sediment allowance for design. Agartala's experience is that drains run partly full of silt for much of the year, so a capacity computed for a clean section overstates the real capacity.

The CPHEEO freeboard table (Table 5.3) prints the first row as "Beyond 300 mm bed width". Read with the second row ("Beyond 300 mm & up to 900 mm"), the first row must mean "up to 300 mm"; Table 6.7 is written that way. The CPHEEO manhole spacing table (Table 11.5) gives overlapping ranges (700–1,050 mm and 1,000–1,400 mm); Table 6.8 removes the overlap by assigning 1,050 mm to the 150 m class.


6.8 Hydraulic grade line

6.8.1 HGL analysis. For every pipe and covered-drain network, the designer shall compute the HGL for the minor design event and for the check event, starting at the outfall and working upstream. The analysis shall include friction losses and losses at junctions, manholes, bends, inlets, outlets and gates.

6.8.2 Starting water level. The starting (tailwater) level at the outfall shall be the higher of:

  • (a) the tailwater level of Chapter 5: mean high water springs (MHWS) plus the sea-level allowance of +0.3 m for minor-system design at tidal outfalls, and the level in the receiving drain, river or tank for the coincident event at other outfalls; and
  • (b) the level computed at the outlet pipe from the critical depth and the pipe diameter, (dc + D)/2, where the receiving water is lower.

6.8.3 Minor-event limit. In the minor design event, the HGL shall be at least 0.3 m below the rim of every inlet and the cover level of every manhole and access chamber.

6.8.4 Check-event and 1% limit. In the check event and the 1% AEP event, the HGL may rise above the inlet rims. Water that leaves the minor system shall then be carried by the major system within the limits of Table 6.2 and shall not enter any building. Manholes that can surcharge above ground in these events shall have bolted or locked covers (Chapter 9, Clause 9.12).

6.8.5 Structure losses. Losses at manholes and junctions shall be computed by the energy-based access-hole method of FHWA HEC-22 (2009 or 2024 edition), or by an equivalent method in an approved hydraulic model. A simplified loss-coefficient method (h = K V²/2g) with coefficients from HEC-22 may be used for Tier B networks below 16 ha.

6.8.6 Invert and soffit levels. Where pipe size increases at a manhole, the soffits (crowns) of the incoming and outgoing pipes shall be matched, or the outgoing soffit set lower. The outgoing invert shall not be higher than the lowest incoming invert. Vertical drops in manholes shall follow Chapter 9, Clause 9.12.

6.8.7 Gates and valves. The head loss through flap gates and non-return valves in the open position shall be included in the HGL (Chapter 9, Clause 9.10).

6.8.8 Private connections. Building drainage that connects to a public drain whose 1% HGL is above the building's lowest drainage fitting shall have a non-return valve.

Commentary. The 0.3 m clearance between the minor-event HGL and the inlet rim is set by this Manual. It keeps a margin for losses that a model underestimates, and it stops water from bubbling out of inlets in the event the system is designed for. In Tripura most town drains end at a sluice in an embankment, behind which the river stands higher than the drain in a flood, at a pumped outfall, or in a pukur, dighi or lunga that is already full (Clause 5.8.5). Agartala's centre lies "at a lower level than other areas giving it the appearance of a saucer", and its worst floods come when "the waters in the Haora and Katakhal Rivers" are "higher than the city", so that "Several pumps have been provided to lift the water out of the city" (ADB IEE, 2020). The Haora's highest level at the CWC Haora site is reported as 12.42 m (22 August 2024) against a danger level of 10.70 m (as reported, datum not stated (TBC)), and the river stood above that danger level in June 2022 and in August 2026 (as reported). No design level for any outfall in the State was found during research. A drain whose HGL is started from a free outfall, or computed one length at a time without the river, the closed sluice, the pumps or the full pukur at its end, fails in exactly that way. An HGL computed from the outfall, with the tidal tailwater of Chapter 5, exposes those errors at design stage. The MHWS plus 0.3 m starting level is from CPHEEO (2019) Table 6.2. The access-hole method is described in HEC-22 from the 2009 edition onward.


6.9 Major system: overland flow paths, easements and drainage reserves

6.9.1 Streets as the primary major system. Streets shall be graded so that the 1% AEP major-system flow is carried along the road reserve to a receiving waterway without being trapped, except at sags designed under Clause 6.10.

6.9.2 Overland flow paths outside streets. Where a major-system path leaves the road reserve, it shall be:

  • (a) in public land, in the open space of a layout, or in an easement recorded on the layout approval and the title;
  • (b) at least as wide as the 1% AEP flow top width plus 0.5 m on each side, and not less than 3.0 m;
  • (c) kept free of buildings, compound walls, fences, fill, stored materials and planting that would obstruct flow;
  • (d) graded to a continuous fall with no sag that lacks an outlet; and
  • (e) within the hazard limits of Table 6.3.

6.9.3 Compound walls. A compound wall or fence shall not be built across a mapped overland flow path. Where a wall must cross one, it shall have openings with a total area that passes the 1% AEP flow with a 50% blockage, without raising the upstream water level above the limits of this chapter.

6.9.4 Access along open drains. Open drains with a top width of 2 m or more shall have a maintenance access strip at least 3.5 m wide along one bank, connected to a public road at intervals of not more than 500 m.

6.9.5 Supply channels, surplus courses and tanks. Tank supply channels and surplus courses are part of the major system and shall be protected under Chapter 7.

6.9.6 Drainage reserves. A drainage reserve is a strip of land, including the drain, kept free of buildings so that the drain can be maintained, widened and used as a flood path. A drainage reserve shall be provided:

  • (a) along every public drain or channel with an internal width of 1.0 m or more that runs through or along a layout or site being developed or redeveloped;
  • (b) along every drain or channel shown in an adopted Basin Stormwater Master Plan (Chapter 11), at the width of the future drain in that plan; and
  • (c) along every new public drain with an internal width of 1.0 m or more built by a public body.

6.9.7 Width. The reserve shall be not less than the width in Table 6.9, measured from the drain's internal width W. The width is based on the required drain size (for a planned drain, the size in the master plan), not the existing size. Where the access strip of Clause 6.9.4 is wider than the margin in Table 6.9, the wider governs.

Table 6.9 — Minimum drainage reserve width (adopted from PUB Singapore)

Internal width of drain, W Open drain Closed (covered) drain
1.0 m to 1.2 m 3.0 m W + 0.6 m
more than 1.2 m to 3.0 m W + 2.6 m W + 1.6 m
more than 3.0 m to 4.5 m W + 3.5 m W + 1.6 m
more than 4.5 m to 6.0 m W + 4.5 m W + 3.0 m
more than 6.0 m to 9.0 m W + 6.0 m W + 3.0 m
more than 9.0 m to 25.0 m W + 7.5 m W + 3.0 m
more than 25.0 m W + 12.0 m W + 3.0 m

For an open drain, the larger part of the margin shall be on the side used for maintenance access.

6.9.8 Use and protection.

  • (a) The reserve shall be shown as a separate plot on the layout or site plan and transferred to the Approving Authority free of cost, as roads and open space reservations are. Where the drain is a PWD (WR) channel, the reserve is transferred to PWD (WR).
  • (b) No building, compound wall, fence, ramp, step, fill or other structure shall be built in the reserve. Compound walls and boundary fences shall stand outside it.
  • (c) The access strip in the reserve shall be level and continuous, and connected to a public road. Bollards or posts and chains may be used at entrances to keep out vehicles other than maintenance vehicles.
  • (d) Where the reserve is not fenced off, its edge shall be marked with concrete markers at not more than 50 m spacing.
  • (e) Services shall cross under the drain, with at least 1.0 m clearance below the invert, or over it on an approved structure. Services shall not run along the reserve inside the drain section.
  • (f) A structure within 2 m of the edge of the reserve shall be designed to remain stable when the drain is excavated to 1.0 m below its invert. The design shall be signed by a qualified structural engineer.
  • (g) The reserve counts toward the site's open space requirements only where the Approving Authority's rules allow it; it does not reduce any setback required by Chapter 7.

Drainage reserve: open drain cross-section Drainage reserve along an open drain (cross-section, schematic, not to scale) No-structure zone: the whole reserve (Clause 6.9.8(b)) no building, compound wall, fence, ramp, step or fill W (internal width) Access strip: level, continuous, linked to a public road; bollards or posts and chains at entrances (6.9.8(c)) Compound wall outside the reserve (6.9.8(b)) Building and compound wall outside the reserve Reserve width: not less than Table 6.9, from the required drain size (Clause 6.9.7) smaller margin larger margin, maintenance side (6.9.7) 2 m Structure within 2 m of the reserve edge: stable with the drain excavated 1.0 m below its invert; signed by a structural engineer (6.9.8(f)) 1.0 m below invert ≥ 1.0 m clear below invert for services crossing under the drain (6.9.8(e)) Service pipe or duct, crossing in a sleeve Concrete markers at ≤ 50 m where not fenced (6.9.8(d)) No-structure zone 2 m stability-check zone Future excavation, 1.0 m below invert

Figure 6.4 — Drainage reserve along an open drain: reserve width from Table 6.9, no-structure zone, access strip on the maintenance side, the 1.0 m service clearance below the invert and the 2 m stability-check zone (Clauses 6.9.6 to 6.9.8). Original drawing for this Manual, adapted from PUB Singapore, Code of Practice on Surface Water Drainage (7th ed., with Addendum No. 3, 2025), clauses 5.1, 5.3, 9.6 and 9.7 and Appendix 1.

Commentary. Drainage reserves follow Singapore, where "the width of a drainage reserve is based on the required drain size" and the reserve is set aside as a separate plot, "kept free of all encumbrances" (PUB Code of Practice on Surface Water Drainage, 7th ed. with Addendum No. 3, 2025, cl. 1.1). Table 6.9 reproduces PUB's Appendix 1 widths. Clauses 6.9.8(b) to (f) follow PUB clauses 5.1 (no structure within a drain or drainage reserve), 5.3 and 5.3.1 (stability for excavation 1.0 m below the invert; engineer's calculations within 2 m of the reserve), 9.6 (level, continuous access, with bollards or posts and chains) and 9.7 (markers at a maximum of 50 m). The 1.0 m clearance for services crossing under a drain is from PUB's development-plan guidance. In Tripura, buildings and compound walls are often built up to the edge of a drain, so it cannot be widened or desilted by machine. Reserving the land when a plot is developed or redeveloped is the cheapest time to secure it, because widening later needs land acquisition. Basing the width on the master-plan drain size (6.9.6(b)) protects the land a future drain will need. Tripura has statutory lines along rivers and round tanks, but no reserve width along a drain, no no-build setback from a river in the plains, and no flood-plain zoning law. The lines are those of the Tripura Building Rules 2017: no "canal, pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts shall be filled up", except where the Local Body, with the prior approval of the State Government and for reasons recorded in writing, allows a canal, pond, rivulet, stream, river or "flood plain area to be filled up" (TBR 2017, r.9(3)); "In the case of a building in the zone of river (within 15 metres from river bank) or other water fronts of large water bodies (more than 1000 acres)", a building may be no more than 5.00 m high (6.50 m on stilts, the stilts not more than 3.00 m and not walled up), no more than 20.00 m long along the water, at least 50.00 m from the next and no more than 200.00 m² in covered area (r.9(4)), which is a regulated zone, not a no-build line; within 5.00 m of a tank the owner shall prevent drainage from the building passing into it (r.4(1)(e)), which is a drainage rule, not a setback; and in the ULBs in the hill areas no site may be "within five meters in any direction of the outside edge of such water courses" (r.90(1)(i)), the only no-build distance from a watercourse in the rules, with protective works within 5.0 m of a tank, reservoir, jhora or spring, water source or natural drain and where the site is within 30 m of a jhora (r.90(1)(m)). The site plan shall show the "natural drainage channel/jhora" (r.5(1)(p)), a sub-division needs a pucca drain to each plot leading to a public drain or natural drainage channel (r.10(2)(f)), and a notice in Form I is required before drains are covered (r.38). The Municipality holds "all public tanks, streams, reservoirs" and "all public sewers, drains, channels, tunnels, culverts and water courses in, alongside, or under any street" (Tripura Municipal Act, 1994, s.91), and may demolish an unauthorised drain and act against encroachment of its drains (ss.162 and 166). The rules do not define "river bank" or "outside edge of water course" (NEER reading). The DST&E's "Statutory Guidelines for protection and preservation of lakes, ponds and water bodies in Tripura" (as cited) were not read and give no line here, a direction against construction "within 75 Mtrs. of the end of the lake" is of unverified source and scope and is not a rule, and the buffers, if any, of the Master Plan for the Agartala Planning Area 2045 were not read [TBC]. Tripura has no flood-plain zoning law: the rules' "Natural Hazard Prone Areas" include flood-prone areas in river plains shown in the Flood Atlas of India of CWC and areas flooded by "heavy intensity rains, inadequate drainage, etc. as identified through local surveys in the Development Plan" (r.2(44)), and PWD (WR) has mapped flood-plain-zone localities on the Haora for the NGT (map, return period and status not known). None of these gives a reserve width along a chhara, khal or town drain. For this Manual, as its own proposal and not as the meaning of the rules, the bank of a channel is its top of bank, and the edge of a pukur, dighi or beel is the higher of its full level and its monsoon water line (Chapter 7); every chhara, khal, lunga flow path and other natural channel that drains 8 ha or more is a natural channel under Clause 7.4.1(b), whoever maintains it and whether or not it is lined, piped or covered (all set by this Manual). This Manual therefore gives the reserve a width, as its own proposal and not as a statutory width: a hydraulic corridor made up of the reserve of Table 6.9, based on the drain size needed to carry the design flow, with the bulking factor of Clause 6.3.6(g) on tilla and hill land (Clause 6.9.7), the access strip of Clause 6.9.4 on the access bank, and, along every natural channel that drains 8 ha or more and round every pukur, dighi and beel that this Manual covers, the setbacks of Clause 7.4, with a Zone 1 of not less than 15 m from top of bank (or from the full level of a pukur, dighi or beel) and a Zone 2 to the 1% AEP extent plus 10 m, whichever line is wider governing; where a rule, the Master Plan or a court sets a wider line, that line applies for as long as it binds, and the widest governs (Clause 7.4.5). Three reference lines are compared (Chapter 7): the rules' "river bank", "outside edge" of a water course or side of a tank, with the rules' distance; the top of bank or full level, with Zone 1; and the 1% AEP extent, with 10 m. Zone 1 is no-build, so the corridor is stricter than r.9(4) everywhere, because r.9(4) allows buildings within 15 m of a river bank, capped in height, length and cover; it is three times the 5 m of r.90(1)(i) in the hill ULBs; and it adds a corridor round tanks and along chharas, khals and lungas where the rules set only a drainage duty (r.4(1)(e)) or protective works (r.90(1)(m)). It applies to new development and redevelopment approved under this Manual, not to existing buildings, and Clause 7.4.7 allows no variance below it. Zone 1 land and reserve land that is private is reserved in the Master Plan or secured by agreement with the owner, recorded on the layout approval and in the land records by district, sub-division, revenue circle and mouza, and not taken; where it is so secured, the transfer of Clause 6.9.8(a) is made by that recorded agreement rather than by a transfer of title; in the TTAADC area it is secured only through the District Council, whose land law was not researched [TBC] (set by this Manual). The corridor should be shown in the Master Plan for the Agartala Planning Area 2045 and in the plans of the Local Planning Areas as land kept free along drainage lines, and checked at the building permit, where the plans already have to show "the house drainage plan, and site drainage plan up to nearest Nagar Panchayat or Municipality or natural outfall" (r.14), and at the self-certification of a low-risk building by its empanelled professional (r.13(3), 2025), rather than made a new NOC.

The reserve matters because the drains of Tripura's towns are divided among owners, and no rule divides them. In law the drains are the Municipality's: s.91 of the Tripura Municipal Act, 1994 vests "all public sewers, drains, channels, tunnels, culverts and water courses in, alongside, or under any street" in it "unless the State Government otherwise directs by a notification", and s.156(1) makes it "provide and maintain a system of drainage or sewerage as well as a safe and sufficient out-fall in or outside the Municipal area", with power to hand trunk sewers, treatment plants and pumping stations to a Government agency (s.156(2)), to cleanse its drains (s.157), to drain sudden waterlogging across private land without prior notice (s.160), to permit connections in writing (s.161), to demolish unauthorised drains (s.162) and to require separate drainage of sewage (s.164), and with the State able to hand inefficient drainage works to another agency (s.165). In practice the capital works are built by others. In Agartala the major AMRUT works "(98 per cent)" are "being implemented by the UDD and State PWD (DWS)", with "only a few minor works" by the Corporation and no tripartite agreement, and PWD (R&B) builds the major roads and drains (CAG, Audit Report 2019-20); Agartala Smart City Ltd builds storm drains and flood pumps, the Ujjayanta and MBB College lakes, the Akhaura canal and Katakhal works and the Akhaura sewage treatment plant (as reported and as cited); PWD (WR) holds the river embankments, the Katakhal sluice and the Haora flood-plain mapping; PWD (DWS) the drainage pump houses and, with the UDD, the sewage treatment plants (as cited); and NHIDCL the drains of the national highways in the High Court's PIL 06/2026. No formal allocation order, and no notification under s.91, s.156(2) or s.165, was found (NEER reading). For the purposes of this Manual, and until the State issues an allocation [TBC], the drains are assigned as follows: the municipal drains, public tanks, streams and water courses of a ULB to the Municipality (ss.91 and 156–166 of the 1994 Act), in Agartala the Agartala Municipal Corporation; capital drainage works built in Agartala by the UDD, PWD (DWS), Agartala Smart City Ltd or under the ADB project, to their builder until they are handed over to the Corporation in writing, and then to the Corporation; major roads and their drains to PWD (R&B), and the national-highway drains it builds to NHIDCL; river embankments, sluices, anti-erosion works and flood-plain mapping, the Katakhal double-barrel sluice among them, to PWD (WR); drainage pump houses and sewage treatment plants to PWD (DWS) with the UDD; and, in the TTAADC area, the drains to the District Council or the body it designates [TBC] (set by this Manual). Each town shall keep a drain register that gives every reach its owner under this assignment, its land status (khas or other government land, private land, or Council land), whether it is a vested municipal drain, an embankment drain or sluice of PWD (WR), or a natural chhara, khal or lunga flow path, whether it carries sewage and is intercepted to a sewage treatment plant, and its outfall (set by this Manual). Under Clause 6.9.8(a), the reserve along a channel assigned to PWD (WR) is transferred to, or secured for, PWD (WR). Where a channel's status is disputed, the corridor follows the channel and not its name: Agartala's khals are at once storm drains, carriers of sewage, embankment drains behind a PWD (WR) sluice and border reaches to Bangladesh. No approved city drainage master plan with a design return period was found for any town in the State. A drain sized to fit the land left beside it cannot be enlarged, which is why the reserve is based on the required size. Until a Basin Stormwater Master Plan is adopted (Clause 6.9.6(b)), the required drain size of Clause 6.9.7 is the size computed by the designer under this chapter. This Manual does not prescribe a lined or an unlined section, except where Clause 6.3.6(j) and Chapter 9 require lining on steep gradients. It requires the section to meet the velocity limits of Clause 6.7.3 and Chapter 9, and a reserve wide enough for an unlined or vegetated section is a reserve that keeps both options open.

Commentary. Requirements 6.9.2(b)–(e), 6.9.3 and 6.9.4 have no direct precedent and are set by this Manual. Compound walls around individual plots are almost universal in Tripura and are one of the most common ways that overland flow paths get blocked. The 50% blockage assumption for wall openings is set to match the grate clogging factor of Clause 6.6.3. The 3.5 m access width is set by this Manual, sized for a small excavator or desilting vehicle. For comparison, APWA 5600 (2006, 5608.4) requires a 15 ft (about 4.6 m) maintenance access strip for detention facilities.


6.10 Ponding at sags and low points

6.10.1 Minor event. At every sag, the minor design flow shall be removed by inlets (after clogging) with ponded spread within Table 6.2.

6.10.2 1% AEP event. At every sag:

  • (a) the ponded depth shall not exceed 350 mm at the deepest point of the carriageway;
  • (b) a surface overflow route shall be provided (for example over a lowered kerb and footpath into a designated overland flow path), so that the ponding level cannot rise above the overflow level; and
  • (c) building floor levels around the sag shall comply with Clause 6.11.

6.10.3 Fully-blocked check. At sags, the 1% AEP ponding level shall also be computed with the minor system fully blocked and all flow leaving by the surface overflow route. Floor levels around the sag shall be set from the higher of the two ponding levels.

6.10.4 Trapped sags. Where a sag has no surface overflow route, the inlets and conduits (after clogging) shall carry the 1% AEP flow, and the approving authority shall agree the arrangement.

6.10.5 Road underpasses. Underpasses and other trapped sags on public roads shall:

  • (a) be drained by a minor system (with pumping under Chapter 9, Clause 9.9, where gravity drainage is not possible) designed for the 2% AEP (50-yr) flow, checked at the 1% AEP flow;
  • (b) have flanking inlets at both approaches to intercept flow before it reaches the low point;
  • (c) be protected from inflow from surrounding streets by raised approach crests where practicable; and
  • (d) have depth markers and automatic warning or closure signals that operate at 150 mm depth on the carriageway.

Commentary. The fully-blocked check, the trapped-sag rule and the underpass requirements have no direct precedent and are set by this Manual. No record of a flooded road underpass in Tripura was found during research [TBC]. The roads already act as the major system: in August 2026 Chandrapur, Baldakhal and Aralia in Agartala were flooded (as reported); in Agartala's flood of 31 May–1 June 2025 a man died in a manhole (as reported); and inspections for the High Court on NH-108B and NH-208 found "No proper drainage system … water logging everywhere" (WP(C)(PIL) No. 06 of 2026). Clause 6.10.5(d) links the 150 mm crown depth limit of Table 6.2 to the point at which traffic should stop.


6.11 Building floor levels

6.11.1 The lowest habitable floor, and every opening through which water could enter a building (doors, ventilators, basement ramps, lift pits and service entries), shall be at least 0.5 m above the 1% AEP flood level.

6.11.2 The 1% AEP flood level is the highest of:

  • (a) the 1% AEP major-system water level in the street or overland flow path next to the building (Clauses 6.9 and 6.10, including the fully-blocked check at sags);
  • (b) the 1% AEP flood level of any river, channel, tank or waterbody (Chapter 7); and
  • (c) the 1% AEP level with the tailwater of Chapter 5; and
  • (d) where the Approving Authority has adopted a 1% AEP flood depth map under Clause 7.3.4, the ground level at the plot plus the mapped 1% AEP depth.

6.11.3 Default where no level has been computed. For a plot below the Chapter 1 thresholds, or where no 1% AEP level has been computed for the plot, the lowest habitable floor and openings shall be at least the higher of:

  • (a) 0.65 m above the highest crown level of the road on which the plot fronts; and
  • (b) where an adopted 1% AEP flood depth map covers the plot, the ground level plus the mapped 1% AEP depth plus 0.5 m.

The Approving Authority may adopt a regional map, such as a State-approved map or a published national map of modelled 1% AEP flood depth (for example the India Flood Atlas), until a local study replaces it. A map that does not model storm surge shall not be used in place of Clause 6.11.6.

6.11.4 Basements. The crest of every basement ramp and the sill of every basement opening shall meet Clause 6.11.1. Basement drainage shall be pumped to the surface drain through a non-return valve.

6.11.5 Services. Electrical panels, transformers, standby generators, lift machinery and pumps that serve a building shall meet Clause 6.11.1.

6.11.6 Coastal band. The coastal band is the land within 500 m landward of the High Tide Line along the sea front, as defined by the CRZ Notification, 2019, with the High Tide Line as demarcated in the approved Coastal Zone Management Plan. Where the Survey of India Hazard Line lies further inland than 500 m, the band extends to the Hazard Line. Within the coastal band, in addition to Clauses 6.11.1 to 6.11.5:

  • (a) the lowest habitable floor and every opening shall also be at least 0.5 m above the coastal flood level, which is the 1% AEP still-water level (Clause 5.7.3(b), Annex 5A) plus twice the sea-level allowance of Clause 5.7.4 (so at least 0.6 m), because buildings have a design life of more than 50 years (Clause 5.7.4(c));
  • (b) where the plot fronts the open beach, the coastal flood level shall include wave set-up from a site study;
  • (c) no habitable room, electrical service room or plant listed in Clause 6.11.5 shall be placed in a basement; and
  • (d) every basement opening, ramp crest and ventilation opening shall meet Clause 6.11.6(a).

Clause 6.11.6 does not authorise any construction that the CRZ Notification prohibits. Where both apply, the stricter governs.

Coastal band floor level Coastal band: minimum floor level and extent of the band (schematic, not to scale) (a) Level stack for the lowest habitable floor (Clause 6.11.6(a), (b)) (b) Extent of the band (plan) Datum Ground + 2 × sea-level allowance (Clause 5.7.4), so at least 0.6 m + wave set-up from a site study, where the plot fronts the open beach (6.11.6(b)) + 0.5 m freeboard (6.11.6(a)) 1% AEP still-water level (Clause 5.7.3(b), Annex 5A) Coastal flood level Lowest habitable floor and every opening at or above No habitable room, electrical room or listed plant in a basement (6.11.6(c)) Clauses 6.11.1 to 6.11.5 (1% AEP level + 0.5 m, and the defaults of 6.11.3) also apply; the higher floor level governs. CRZ prohibitions are not relaxed. Sea 500 m landward of HTL High Tide Line (HTL), as in the approved CZMP (CRZ Notification, 2019) 500 m line Hazard Line (Survey of India) Coastal band: to 500 m from HTL, or to the Hazard Line where it lies further inland (Clause 6.11.6)

Figure 6.5 — Coastal band: the minimum floor level built up from the 1% AEP still-water level, twice the sea-level allowance, wave set-up where the plot fronts the open beach and 0.5 m freeboard; and the extent of the band, to 500 m from the High Tide Line or to the Hazard Line where it lies further inland (Clause 6.11.6). Original drawing for this Manual, adapted from the CRZ Notification, 2019 (para 1(i) and Annexure IV) and PUB Singapore, Code of Practice on Surface Water Drainage (7th ed.), cl. 2.1.1.

Commentary. The 0.5 m freeboard above the 1% AEP level follows the DID Malaysia 2008 checklist (platform and lowest floor at 100-yr ARI + 0.5 m). It is more than the APWA 5600 (2006, 5601.8 A2) requirement of 1 ft (about 0.3 m) above the 1% stage. The 0.65 m default in Clause 6.11.3 is derived from the other limits of this chapter, not separately sourced: the 1% water level at the crown may be up to 150 mm (Table 6.2), plus the 0.5 m freeboard. It has no direct precedent and applies to plots where no flood level exists. URDPFI (2015) also links minimum plinth levels to flood frequency in its flood-plain zoning, which is covered in Chapter 7.

Clause 6.11.3(b) lets a small plot use a mapped 1% AEP depth where no local study exists, instead of guessing from the road level alone. Modelled national maps are coarse (about 30 m), and most model rainfall and river flooding but not storm surge, which is why 6.11.3 keeps the road-crown check and Clause 6.11.6 sets a separate coastal rule.

The coastal band of Clause 6.11.6 uses the 500 m line of the CRZ Notification, 2019 (G.S.R. 37(E), para 1(i): "the land area from High Tide Line ... to 500 meters on the landward side"), because every coastal authority already maps it and it needs no new survey. The Hazard Line, demarcated by the Survey of India to show the extent of flooding and shoreline change, extends the band where it lies further inland (CRZ Notification, 2019, Annexure IV). The band takes the coastal level from the joint-case still-water level of Chapter 5 rather than from the rainfall map. The higher standard reflects the setting: a coastal flood rises with the sea, cannot be drained while the tide is up, and will rise further with the sea. Singapore takes the same approach with a fixed minimum platform level of 4.0 m above datum on its southern coast and 4.5 m on its northern coast, whatever the rainfall flood level (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 2.1.1). Each coastal State's tide and surge levels vary too much along its coast for one fixed level, so this Manual uses the computed still-water level instead. Using twice the sea-level allowance applies the sensitivity case of Clause 5.7.4(c) as the design case, because a building, unlike a drain, cannot easily be raised later. The basement restriction in 6.11.6(c) is set by this Manual: a basement in the coastal band fills from the sea as well as from rain, and cannot be pumped out to a tide-locked outfall. Tripura has no coast, no High Tide Line and no Coastal Regulation Zone, so the coastal band is empty in the State and Clause 6.11.6 does not apply there. Clauses 6.11.3 and 6.11.4 matter instead. The Tripura Building Rules 2017 set the plinth "so located with respect to the crest of the road level that adequate drainage of the site … assured and it shall in no case be at a height less than 60 centimeters", inner courtyards at least 15 cm above the centre of the nearest street, and a plinth of not less than 15 cm where parking is on the ground floor (TBR 2017, r.55); they allow no kitchen, bathroom or water closet in a basement unless "there is no chance of back flow and flooding of sewerage", with drainage and pumping plans (r.66(5)), require every basement to keep surface drainage out, to have pumping and to have water-tight walls and floors (r.66(6)(b) and (c)), and since 2025 set the basement ceiling between 0.8 m and 1.2 m above the average road level on the front of the building (r.66(6)(h)); and on recently filled pond, lake or marshy land the Mayor or Chairperson may seek a soil test, restrict the height or refuse the building (r.32). No rule in the State fixes a highest flood level to build to, and no flood-plain zoning law exists. For this Manual, the level is the 1% AEP flood level of Clause 6.11.2 at the site, computed with the river-locked, pumped and breach cases of Clause 5.8.5, or, where none has been computed, the highest flood level surveyed from flood marks with its source stated, and the floor levels of Clause 6.11.1, 0.5 m above the 1% AEP level, govern where they are higher than the plinth of r.55 (set by this Manual). Behind an embankment the level is that of the ponded area with its sluices closed and its pumps at their confirmed capacity, and for a breach, the river level beyond the embankment (Clause 5.8.5(a) and (b)): Agartala's central saucer lies between the Haora embankment and the Katakhal, with ground from 25–30 m down to 8 m (ADB IEE, 2020), below the Haora's reported highest level of 12.42 m (as reported, datum not stated (TBC)). Clause 6.11.3, which sets the lowest habitable floor and every opening 0.65 m above the road crown where no flood level has been computed, and Clause 6.11.4, which applies the same level, or 0.5 m above the 1% AEP flood level, to the crest of every basement ramp and the sill of every basement opening, are set by this Manual and add to the rules; where the rules refuse a basement or a building, the refusal governs. On a hill or tilla site the road crown is not always the right reference: a building below a road takes the road's runoff, so Clause 6.11.2(a) sets its floor and openings from the 1% AEP level of the flow path past it, with the uphill diversion of Clause 6.3.6(l) in place, and a floor or basement cut into a slope also needs the geotechnical certificate of the hill rule of Clause 4.11. Along the rivers, chharas, khals and lunga flow paths and round the pukurs and dighis, the lines of Chapter 7 also apply.


6.12 Culverts and road crossings

6.12.1 Design AEP. A culvert or bridge that carries a road over a drain or waterway shall pass the design AEP flow of Table 6.1 for that road class without overtopping the road, and with the headwater limits of Chapter 9, Clause 9.4. Where the waterway is a State highway or national highway crossing, the design AEP shall also be not less than that of IRC:SP:42-2014 §7.1.4 for the span. The rarer AEP governs.

6.12.2 Check event and 1% AEP. At the check event and at the 1% AEP event, the crossing and the road together shall pass the flow:

  • (a) with overtopping depth ≤ 150 mm at the road crown and ≤ 350 mm at the deepest point of the road;
  • (b) within the hazard limits of Table 6.3;
  • (c) with no overtopping at all of arterial roads that are notified evacuation routes; and
  • (d) without raising the 1% AEP flood level at any upstream building or property boundary above the level for the existing condition, unless the affected owners and the approving authority agree.

6.12.3 Where overtopping is not permitted. Overtopping in the 1% AEP event is permitted only where the structure span is less than 6 m and the 1% AEP peak flow is not more than 7 m³/s, unless a guard rail is installed downstream of the overtopping section. Otherwise, the crossing shall pass the 1% AEP flow without overtopping.

6.12.4 Blockage check. The 1% AEP check shall be repeated with a blocked inlet:

  • (a) 50% of the inlet area blocked for culverts with a span or diameter below 1.5 m; and
  • (b) 20% blocked for larger culverts.

The results of this check shall meet Clause 6.12.2(a) and (d).

6.12.5 Minimum size. Culverts under public roads shall be at least 900 mm in diameter, or 900 mm × 900 mm for box culverts.

6.12.6 Hydraulic design. Culvert hydraulics, including inlet and outlet control, tailwater, road overtopping and outlet protection, shall follow Chapter 9, Clauses 9.4 and 9.6.

Commentary. The design AEPs are those of Table 6.1. The overtopping limits are the street-depth limits of Table 6.2. The span and flow threshold in Clause 6.12.3 is the SI conversion of APWA 5600 (2006): overtopping allowed only where the structure span is under 20 ft and the 1% peak is 250 cfs or less, unless a downstream guard fence is installed. IRC:SP:42-2014 (§7.1.4) sets 25-yr for NH/SH culverts up to 2 m span and 50-yr for 2–6 m spans. The blockage percentages in Clause 6.12.4 and the 900 mm minimum size have no direct precedent and are set by this Manual. The 50% value matches the grate clogging factor.


6.13 Tripura construction-practice requirements

6.13.1 Covered roadside drains. Where a roadside drain is covered by slabs that form a footpath:

  • (a) it shall be designed as an open channel with the freeboard of Table 6.7 measured to the soffit of the cover slab, and its HGL shall meet Clause 6.8 measured to the footpath and inlet levels;
  • (b) road runoff shall enter through openings in the drain wall at road level (Clause 6.6.1(b)), each with a silt sump (Clause 6.6.7), at the spacing of Clause 6.6.4;
  • (c) footpath runoff shall enter through slots or grated openings in the cover, not by ponding on the footpath; and
  • (d) the clear section shall meet Clause 6.7.6(c).

6.13.2 Removable covers and access openings. Covered drains shall have:

  • (a) removable cover panels at not more than 10 m centres, each at least 0.6 m long and spanning the full clear width, with recessed lifting points, liftable by two workers or by a hand-operated lifting device, and flush with the footpath;
  • (b) access chambers with a clear opening of at least 0.6 m × 0.6 m at every junction, bend and change of section, and at not more than 30 m centres on straight runs; and
  • (c) covers rated for the traffic or pedestrian load at their location (Chapter 9, Clause 9.11).

6.13.3 Silt traps. In addition to the inlet sumps of Clause 6.6.7, silt trap chambers shall be provided:

  • (a) upstream of every culvert under an arterial road;
  • (b) upstream of every pump station and detention facility; and
  • (c) at every outfall to a tank, river or other waterbody (with the gross pollutant trap required by Chapter 8).

Each silt trap shall be sized to hold the sediment expected between scheduled cleanings, using the sediment yield in Annex 6B, and shall be reachable by a desilting vehicle.

6.13.4 Garbage and gross pollutant screens. Screens shall be provided where an open drain enters a covered drain, a pipe or a culvert, and at outfalls under Chapter 8. Each screen shall:

  • (a) be designed under Chapter 9, Clause 9.8;
  • (b) have a bypass or overflow, so that a fully blinded screen does not flood properties or the road beyond the limits of this chapter; and
  • (c) be checked hydraulically with 50% of its area blocked.

6.13.5 No building over drains. No structure other than an approved crossing or a removable cover shall be built over a public drain. Shop frontages, ramps and steps that cross a drain shall be removable or shall leave access openings that meet Clause 6.13.2.

6.13.6 Utilities. No water main, sewer, power or telecom cable, gas pipe or duct shall be laid along, or pass through, the flow area or freeboard of any drain. A utility that must cross a drain shall:

  • (a) cross above the cover soffit or below the drain invert, inside a sleeve; and
  • (b) be shown on the drainage plan with its level.

Where an existing utility crossing obstructs a drain, its area shall be deducted from the drain section, with a 50% blockage allowance for the debris it traps, until the utility is relocated. The utility owner shall relocate it when the drain is rebuilt.

6.13.7 Sewage. No sewage connection is permitted to a storm drain (Chapter 8). Covered drains shall be built with sealed joints where they run next to sewers.

6.13.8 Edge protection. Open drains deeper than 1.0 m beside a footpath, a carriageway or a public open space shall have railings or barriers. Open drains of any depth shall not be left uncovered across a footpath.

6.13.9 As-built levels. The as-built invert levels of every public drain, pipe and manhole shall be surveyed and submitted (Chapter 10). Inverts shall be within ±15 mm of design. An HGL re-check shall be submitted where they are not.

6.13.10 Desilting. Public drains shall be desilted before the monsoon season each year, as set out in Chapter 10.

Commentary. Clause 6.13 has no direct precedent; this Manual sets it on the basis of Tripura practice. Most urban drains in the State are covered roadside drains under footpaths. They are often built with continuous cast-in-situ slabs and few openings, so they cannot be cleaned and fill with silt and solid waste within a season. CPHEEO (2019) notes that uncovered channels "are prone to the dumping of garbage" (Part A, Ch 2), which is why the drains are covered. Covering without access openings simply moves the problem out of sight. NDMA (2010) recommends that pre-monsoon desilting be complete by 31 March. In Tripura that date is also the start of the wet season. The south-west monsoon's normal onset over the State is about 5 June, inferred from two press reports of the Meteorological Centre Agartala's dates (7 June 2026 "two days later than its normal" and 26 May 2025 "10 days before its normal date", as reported; NEER reading), while another report gives 10 June (as reported); the conflict stands until IMD's revised normals are read [TBC], and no withdrawal date for Tripura was found [TBC]. But the storms come earlier: Kailashahar's wettest months on record are May (1,175.0 mm, May 1991) and April (1,012.8 mm, April 1977), its April 24-hour record is 257.1 mm (19 April 2004) and its May record 231.2 mm (3 May 1993), and Agartala's April record is 198.0 mm (11 April 2007) (IMD Extremes); the Dhalai at Kamalpur and the Juri at Nutan Bazar set their highest levels on 15 May 1984 (CWC levels as reported); Cyclone Remal brought 252.4 mm to Unakoti district in 24 hours on 27–28 May 2024 (district value, as reported); and the ADB IEE, citing the district disaster management plan, records storms "during April & May and during October & November in terms of Kalbaisakhi" (ADB IEE, 2020). Storms also come outside the season: Agartala 142.2 mm on 19 February 1993 and Kailashahar 112.4 mm on 25 March 1994; Agartala 183.6 mm on 11 October 1989 and Kailashahar 182.0 mm on 9 October 1986; Agartala 104.6 mm on 9 November 1955 and Kailashahar 104.2 mm on 10 November 1986 (IMD Extremes). No order with a completion date for desilting town drains was found during research [TBC]: the Agartala Municipal Corporation desilts every year, with "super sucker" machines (as reported), PWD (WR) runs a pre-monsoon programme of embankment works (as reported), and TDMA's monsoon checklist of 2026 includes "urban drain de-silting" (as quoted), all without a date. So Clause 6.13.10 refers to the monsoon season as this Manual defines it, 1 April to 31 October, and Chapter 10 requires the desilting of drains, khals, chharas and channels and the clearance of inlets, silt traps and screens to be complete by 31 March, with sluice gates, flap gates, pumps and standby power certified ready and test-run on the same date (Clauses 5.11.5 and 5.12.9); a mid-season clearance of inlets, silt traps, screens and tilla-foot traps by 31 May, after the April–May storms and before the south-west monsoon sets in; standby from 1 April to 31 October; and a post-season clearance of silt and debris, with a survey of silt depths, by 15 November. The research behind this Manual suggested testing pumps and gates by 15 April; that date is not used, because the April storms come before it (Agartala 198.0 mm on 11 April 2007). These dates are set by this Manual, and are those of the neighbouring North-East editions. Tripura's towns have no snow regime.

Building over drains is already restrained in law. A Municipality may demolish an unauthorised drain into a municipal drain or water course at the owner's cost and act against the encroachment of municipal drains (Tripura Municipal Act, 1994, ss.162 and 166); a notice in Form I is required before drains are covered (TBR 2017, r.38); and in the ULBs in the hill areas "except with the written permission of the ULB no covered drain shall be constructed and no existing open drain shall be covered in" and "no building shall be placed over any drain" (r.99(2)(e) and (f)). Natural chharas, khals and lunga flow paths are open channels with a drainage reserve (Clause 6.9), and should not be covered, decked or built over. Where a drain is covered, Clause 6.13.2 applies to it in full; where it is open beside a footpath or a carriageway, Clause 6.13.8 applies: in Agartala's flood of 31 May–1 June 2025 a man died in a manhole (as reported).

Clause 6.13.7 is not yet the practice, and in Tripura it cannot be until sewers exist. Agartala's sewers, 103.6 km "with 4011 nos. household connection", are "only in the North Zone"; the Akhaura plant and every sewage treatment plant under construction "are designed to be connected through Interception & Diversion of Drains", which Agartala Smart City Ltd describes as "a temporary measure till the conveyance system is laid"; and the other 19 ULBs treat none of their sewage (State affidavit to the NGT in O.A. No. 606 of 2018, 6 July 2026). In 2020 the ADB IEE recorded that "Agartala city is not covered by an underground sewerage system at present" (ADB IEE, 2020); the North Zone network is recorded by 2026. Clause 6.3.6(a) to (e) sets how a drain that carries sewage is designed meanwhile, and Clause 8.9 how dry-weather flow in storm drains is surveyed and intercepted until the connections are removed, including the rule that interception shall not reduce the capacity of the drain (Clause 8.9.5(b)).

The 10 m and 30 m spacings and the ±15 mm tolerance have no direct precedent and are set by this Manual. Clause 6.13.6 responds to the common sight of water mains and cables running through drains. Each one traps debris and reduces the section. Mechanical cleaning through cover openings, rather than manual entry, is assumed throughout, consistent with the Prohibition of Employment as Manual Scavengers and their Rehabilitation Act, 2013.


6.14 Outfalls

6.14.1 Outfalls shall be designed for the tailwater conditions of Chapter 5. Outfalls below the 1% AEP still-water level shall have flap or tide gates or non-return valves (Chapter 5 and Chapter 9, Clause 9.10).

6.14.2 Outfall protection and energy dissipation shall be designed under Chapter 9, Clause 9.6. Outfalls to tanks and waterbodies shall also meet Chapters 7 and 8.


6.15 Submittal requirements

Every conveyance submittal shall include a Conveyance Design Report (Form 6-1) containing:

  1. a catchment plan showing sub-catchments, the minor system, inlet locations and the major-system overland flow paths for the 1% AEP event (Clause 6.3.2);
  2. the land-use and road-class AEP adopted for each element (Table 6.1), and the high-density area status;
  3. design flows, with the rainfall sheet of Chapter 2 and the method of Chapter 3;
  4. gutter spread, depth and D·V checks for the minor, check and 1% events (Tables 6.2 and 6.3);
  5. an inlet schedule with clean capacity, clogging factor, design capacity and bypass flow (Clause 6.6);
  6. pipe and drain design tables with n, velocity, sediment allowance and freeboard (Clause 6.7);
  7. HGL profiles for the minor and check events, with the tailwater used (Clause 6.8);
  8. sag ponding levels, including the fully-blocked check (Clause 6.10);
  9. a floor-level schedule for every building (Clause 6.11);
  10. culvert and crossing calculations (Clause 6.12 and Chapter 9); and
  11. a utilities-crossing schedule and access-opening layout for covered drains (Clause 6.13).

References (chapter)

Annexes and forms

Annex / Form Content
6A Standard inlet types for Tripura with capacity curves (on grade and sag)
6B Sediment yield for silt-trap sizing and calibration of the sediment allowance
6C Standard drawings: covered roadside drain with removable covers, access chamber, inlet with silt sump
Form 6-1 Conveyance Design Report checklist