Chapter 1Policy, Applicability and Adoption
1.1 Purpose and objectives
1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Tripura. It applies to private development and to public works, as set out in Clause 1.5.
1.1.2 The Manual has the following objectives:
- (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
- (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
- (c) to size storage for the long-duration storms of the monsoon season, which bring several hundred millimetres in a day (377.2 mm at Kailashahar on 6 June 1993 and 49 cm at Bagafa on 22 August 2024, IMD) and fall for days on valley floors already saturated, while the rivers stand high behind their embankments and the sluices and pumps of the embanked towns are shut, from the pre-monsoon storms of April and May to the October storms about the withdrawal of the south-west monsoon, as well as for short-duration intensities;
- (d) to design outfalls for the rivers into which the towns drain, every one of which flows on into Bangladesh with no Indian control downstream and no level data from across the border, and which in the monsoon stand above the towns behind their embankments, so that many outfalls pass through sluices and pumps that work only when the river is low: the Haora and the Katakhal round the saucer of central Agartala, where flood pumps lift the water over the embankments when the rivers are high; the Manu at Kailashahar, the Juri at Dharmanagar, the Khowai at Khowai and Teliamura, the Dhalai at Kamalpur and the Muhuri at Belonia; the Gomati below the Dumbur reservoir, into whose reach through Amarpur, Udaipur and Sonamura the reservoir releases floods; the pukurs, dighis and lungas that store a town's water while its outfall is shut; and the chharas (hill streams) that come down from the tillas and the hill ranges and rise within the hour, including the case where the outfall is closed;
- (e) to protect tanks (pukurs), marshes, rivers, supply channels and surplus courses as part of the drainage system;
- (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
- (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
- (h) to make sure that facilities, once built, are maintained and remain effective.
1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building rules made by the Urban Development Department under section 274 read with section 118 of the Tripura Municipal Act, 1994 (the Tripura Building Rules 2017), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).
1.2 Stormwater management hierarchy
1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.
- Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
- Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
- Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
- Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).
1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.
1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.
Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).
Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Tripura, the top two layers have a particular meaning. Much of the State's natural storage lies in its pukurs and dighis, among them the palace-era and temple tanks of Agartala and Udaipur; in its beels (natural low wetlands, "Watery land" in the land records) and haors ("Big watery land"); in the lungas, the flat valley floors between the tillas that carry the water of the valleys to the rivers; in Rudrasagar, a Ramsar site (No. 1572, 240 ha, designated 8 November 2005 by the Ramsar record and "officially designated" on 29 February 2007 by the Forest Department, as quoted; conflict); and in the Dumbur reservoir, which is not a Ramsar site. No pond inventory of Agartala was found; the State reported 180 urban water bodies on government land, of which 30 had been prioritised for restoration (2020, as reported), and about 65 water bodies have been cleaned and developed in Agartala (as reported). The law protects some of this. The TBR 2017 bar the filling of any "canal, pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts" except by the Local Body with the State Government's prior approval for recorded reasons (r.9(3)), and the land records class the pukur ("Tank/Pond"), its bank (pukurpar, "Bank of tank"), the dighi ("Large tank") and its bank as land classes of their own (Diversion of Land Rules, 2025, Appendix-I). The ponds are being lost all the same: ponds have been filled for housing in Barjala and Lanka Basti (as reported), and the High Court found local bodies allowing ponds to be filled and walls built on their banks at Kalyan Sagar, Matabari (WP(C)(PIL) No. 2 of 2014, as cited). Since 6 March 2026 a change in the classification of land is made by online self-declaration, with post-facto revocation within 30 working days, and the procedure that applied to water bodies in 2025 was omitted; whether section 20 of the Tripura Land Revenue and Land Reforms Act, 1960 still bars their diversion was not established for this Manual [TBC]. On the valley floors the second layer changes. Groundwater is shallow: in West Tripura the dug wells read 1.63–10.30 m below ground in March 2017 and 0.22–6.64 m in November 2017, and the shallow water carries iron of up to 4.99 ppm from "the ferruginous nature of Tipam sandstones" (CGWB, West Tripura), which clogs infiltration media (NEER reading); under Agartala "The ground water table being very high" (ADB, IEE, 2020). A soakaway or recharge pit on a lunga floor therefore sits in saturated ground when the storm comes. This Manual bars deliberate infiltration on lunga floors and recent flood plains, below the 1% AEP flood level, inside embankment-protected land that ponds when its sluices close or its pumps stop, on pukur, dighi, beel and haor margins, on filled ponds and lunga fills and wherever the seasonal high water table is less than 2.0 m below ground (Clause 4.11, lunga rule); allows it, after testing, on flat tilla tops and benches with a deep water table (Clause 4.11, tilla rule); and bars it on tilla slopes, cut faces and the hill ranges without a geotechnical certificate (Clause 4.11, hill rule) (all set by this Manual). Groundwater is not short: the stage of extraction is 9.48%, with every assessment unit Safe (Ground Water Resource Assessment 2024, as quoted by CGWB), so rainwater harvesting on most sites is storage for reuse, not recharge. Losing the pukurs and lungas cannot be offset by pipes, and a town that drains through a closed sluice has nothing but its pukurs, dighis and lungas to hold the water until the river falls or the pumps empty it.
1.3 Legal basis and status
1.3.1 Notification. This Manual shall be given statutory effect by the Government of Tripura through:
- (a) an amendment to the Tripura Building Rules 2017 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
- (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.
1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.
1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.
1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.
Commentary. In Tripura the building rules are the Tripura Building Rules, 2017 (UDD notification No. F.2(316)-UDD/GL/TCPO/2009 (Part-I)/371 of 10 November 2017, as cited in the UDD's BRAP-2019 document; the 2017 gazette was not read [TBC]), as amended by the Tripura Building (Amendment) Rules, 2019 (No. F.2(466)-UDD/GL/TCPO/2018/599-627, 19 February 2019; Gazette Extraordinary No. 482, 25 February 2019), the (Second Amendment) Rules, 2020 (dated 15 February 2020, Gazette 24 February 2020; number garbled in the copy read [TBC]), the (3rd Amendment) Rules, 2022 (No. F.01(24)-TUDA/Estt/2022/4902-30, 29 November 2022; Gazette 2 December 2022), the (Fourth Amendment) Rules, 2024 (No. F.1(23)-TUDA/ESTT/2024/66, 15 January 2025; Gazette No. 95, 17 January 2025) and the (Fifth Amendment) Rules, 2025 (F.No.2(466)-UDD/GL/TCPO/2018(P-V)/4009-20, 4 July 2025; Gazette No. 1294, 5 July 2025), made under section 274 read with section 118 of the Tripura Municipal Act, 1994. No sixth amendment was found up to November 2026. The rules replace the Tripura Building Rules, 2004 (r.1(4)), and apply "to buildings in the Urban Local Bodies (ULBs) in Tripura" (r.1(2)), to which the amendment of 2019 added "and Planning Areas" and the Tripura Urban Planning and Development Act, 2018 (Tripura Act No. 12 of 2018) as an "Act" of the rules. The building permit and the occupancy certificate are given by the Agartala Municipal Corporation, a Municipal Council or a Nagar Panchayat, and by TUDA "within the Notified Local Planning Area" and for buildings or townships of 50 or more flats or a project area of one acre or more inside a ULB area (r.13(3), as inserted in 2020). Since the Fifth Amendment of 2025, low- and very-low-risk buildings are permitted through an empanelled professional's self-certification "on a trust-based approach" (r.13(3)), their occupancy certificate is issued by that professional (r.34), and inspection is waived but for a random 10% to 15% of applications (r.34(9)). The TBR 2017 carry drainage hooks: the site shall be "capable of being well-drained" and not lower than its approach road (r.4(1)(b), (c)); within 5.00 m of a tank the owner shall prevent drainage from the building passing into it (r.4(1)(e)); the site plan shows the means of drainage and the "natural drainage channel/jhora" (r.5(1)(k), (p)); "No canal, pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts shall be filled up" except by the Local Body with the State Government's prior approval for recorded reasons (r.9(3)); in the "zone of river (within 15 metres from river bank)" a building is limited in height, length and covered area (r.9(4)), a regulated zone, not a no-build line; the plans include "the house drainage plan, and site drainage plan up to nearest Nagar Panchayat or Municipality or natural outfall" (r.14); the plinth is at least 60 cm (r.55); basements keep surface drainage out and have pumping arranged (r.66); the hill ULBs of Part X (rr.88–101) keep sites five metres from water courses (r.90(1)(i)) and drain them by lined drains that "shall not be connected with any drain carrying sullage water or sewage" (r.99); and rainwater harvesting is required for buildings of 200 m² plinth and more (r.110). They set no design storm, return period, release rate or detention volume, and no rule found in them limits peak runoff or asks for storm-water detention (NEER reading). The route of Clause 1.3.1(a) therefore runs through an amendment to the Tripura Building Rules 2017 by the UDD under section 274 read with section 118 of the Tripura Municipal Act, 1994, which the UDD, the department that makes them, could prepare. It reaches only the ULB areas and the Local Planning Areas. Outside them, the Manual reaches development only through public works (Clause 1.5.1(b)) and through any body that adopts it. The Tripura Municipal Act, 1994 "extends to the whole of the State of Tripura except the areas under the Tripura Tribal Areas Autonomous District" (s.1(2)), and its "District Council" is the Tripura Tribal Areas Autonomous District Council (s.2(10)); the TBR 2017 are made under that Act, so they do not apply in the council area, about 68% of the State (as reported), which is under the Sixth Schedule to the Constitution. No building or land-development regulation of the TTAADC was found [TBC]; the instruments made for the council area that were found (the TTAADC Act, 1979, the Village Committee Act, 1994 and its Rules of 2006, and two trade and money-lending regulations) do not concern building or drainage (index titles; NEER reading). A dispute over a proposed Bisramganj Nagar Panchayat on council land was unresolved in 2026 (as reported). In the council area the Manual could take effect only through the District Council, by a regulation of its own or a resolution that the Manual applies (Annex 1D). This Manual is a draft; neither the Government of Tripura, the UDD, TUDA, the Agartala Municipal Corporation, any other ULB, the TTAADC nor any other authority has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.
1.4 Definitions
1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).
| Term | Meaning in this Manual |
|---|---|
| Approving Authority (the Authority) | The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the competent authority for the area: in a ULB area, the Agartala Municipal Corporation, a Municipal Council or a Nagar Panchayat for the building permit and the occupancy certificate under the Tripura Building Rules, 2017, and for its own drains and works under the Tripura Municipal Act, 1994 (ss.91 and 156–166); in a notified Local Planning Area, and for a building or township of 50 or more flats or of one acre or more inside a ULB area, TUDA (TBR 2017, r.13(3), as inserted in 2020); for filling any canal, pond, water body, wetland, jhora, stream, drain or culvert, the Local Body with the prior approval of the State Government (r.9(3)); for diverting a water body as land, the District Magistrate and Collector under the Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025 (the procedure since their amendment of 6 March 2026 not established [TBC]); for any work that cuts, crosses or discharges through an embankment or sluice, PWD (WR) as its owner (no statute found [TBC]); for a notified wetland, the Wetland Authority of Tripura under the Wetlands (Conservation and Management) Rules, 2017; in a rural area outside the council area and outside every Local Planning Area, the Gram Panchayat (Tripura Panchayats Act, 1993, not read for this Manual; the TBR 2017 do not apply there); and, in the area of the Tripura Tribal Areas Autonomous District Council (TTAADC), the District Council or the authority it designates, only where the Council has made a regulation or resolved that this Manual applies (none has), or a department for its own works. |
| Applicant | The owner, developer or department that seeks approval, and its successors in title. |
| Development | Any building, layout, sub-division, road, paving or land-use change that requires approval under the Tripura Building Rules 2017 or that is executed as a public work. |
| Redevelopment | Development on a site where impervious cover already exists. |
| Land disturbance | Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5). |
| Impervious area | Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats. |
| New or replaced impervious area | Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced". |
| Retention | Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4). |
| Detention | Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4). |
| Rainwater harvesting (RWH) | Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it. |
| Minor system | Drains, pipes and inlets designed for the minor-system AEP of Chapter 6. |
| Major system | The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6). |
| Pre-development condition | Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3). |
| Flood-sensitive catchment | The catchments of Agartala's central saucer between the Haora embankment and the Katakhal, with the Akhaura canal; of the Katakhal basin and its sluice; of the Haora flood-plain-zone localities and Chandrapur; of Kailashahar on the Manu; of Belonia on the Muhuri; of Udaipur, Amarpur and Sonamura on the Gomati below the Dumbur reservoir; of Dharmanagar on the Juri; of Khowai and Teliamura on the Khowai; of Kamalpur on the Dhalai; of Santirbazar, Bagafa and Sabroom in the south; and of the hill-range corridors of NH-8, NH-108B and NH-208, and any catchment the Authority notifies (Chapter 4; Annex 1B). |
| Waterbody | A river, stream, canal, tank (pukur), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7). |
| Regional facility | A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4). |
| Tier A / Tier B authority | An Approving Authority classed under Clause 1.6. |
| Policy supplement | The set of adoptable alternative clauses in Clause 1.7 and Annex 1C. |
| Drainage report | The preliminary or final report required by Chapter 10. |
| Registered professional | A person registered under the Tripura Building Rules 2017 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6. |
| Compliance calculator | The State-issued tool for computing and reporting compliance (Clause 10.5). |
| Maintenance declaration | The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10). |
| Variance | Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10). |
| Waiver | Approval that a requirement does not apply to a site, on the grounds in Clause 1.10. |
| Notified | Published by the Government or the State Stormwater Technical Committee in the Tripura Gazette. |
| Competent authority for the area | The body that grants permission for the site, or consents to the work, under the instrument that applies there: in a ULB area, the Agartala Municipal Corporation, a Municipal Council or a Nagar Panchayat for the building permit and the occupancy certificate under the Tripura Building Rules, 2017, and for its own drains and works under the Tripura Municipal Act, 1994 (ss.91 and 156–166); in a notified Local Planning Area, and for a building or township of 50 or more flats or of one acre or more inside a ULB area, TUDA (TBR 2017, r.13(3), as inserted in 2020); for filling any canal, pond, water body, wetland, jhora, stream, drain or culvert, the Local Body with the prior approval of the State Government (r.9(3)); for diverting a water body as land, the District Magistrate and Collector under the Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025 (the procedure since their amendment of 6 March 2026 not established [TBC]); for any work that cuts, crosses or discharges through an embankment or sluice, PWD (WR) as its owner (no statute found [TBC]); for a notified wetland, the Wetland Authority of Tripura under the Wetlands (Conservation and Management) Rules, 2017; in a rural area outside the council area and outside every Local Planning Area, the Gram Panchayat (Tripura Panchayats Act, 1993, not read for this Manual; the TBR 2017 do not apply there); and, in the area of the Tripura Tribal Areas Autonomous District Council (TTAADC), the District Council or the authority it designates, only where the Council has made a regulation or resolved that this Manual applies (none has). Where this Manual says "the Authority", the competent authority for the area is meant. |
| Building permit; occupancy certificate; self-certification | The building permission and the occupancy certificate given under the Tripura Building Rules, 2017 by the Agartala Municipal Corporation, a Municipal Council or a Nagar Panchayat, or by TUDA in a Local Planning Area and for the large projects of r.13(3). Since the Fifth Amendment of 2025 a low- or very-low-risk building is permitted through an empanelled professional's "Self-Certification Proforma … on a trust-based approach" (r.13(3)); its occupancy certificate is issued by that professional (Form H1, r.34); and "Inspection for self-certified buildings is hereby waived", with 10% to 15% of applications selected at random (r.34(9)). For such a building the drainage report and certificates of this Manual sit with the empanelled professional (Chapter 10). |
| Local Planning Area; Planning Area; Master Plan 2045 | A planning area declared under section 52 of the Tripura Urban Planning and Development Act, 2018. TUDA notified Local Planning Areas adjacent to 20 cities and towns in November 2019 (No. F2(15)-TUDA/TECH/2019(P)), the first being the Agartala-Ranibazar-Jirania Local Planning Area, outside the ULB area. The Master Plan for the Agartala Planning Area 2045 was declared final by the UDD on 24 February 2026 under section 53(1), for 238.57 km², the Agartala Municipal Corporation and 49 gram panchayats (as reported); its notification number and text were not read [TBC]. The Planning Area is wider than the Corporation's area. |
| Tripura Tribal Areas Autonomous District; District Council | The area of the TTAADC under the Sixth Schedule to the Constitution, "nearly sixty-eight per cent of Tripura's territory" (as reported). The Tripura Municipal Act, 1994 "extends to the whole of the State of Tripura except the areas under the Tripura Tribal Areas Autonomous District" (s.1(2)), and the TBR 2017 are made under that Act, so neither applies there. No building or land-development regulation of the Council was found [TBC]. This Manual reaches the council area only through the District Council. |
| Tilla; lunga; chhara | Tilla (Bengali টিলা, "Hillock"): the low, dissected terrace uplands of every valley, 10–30 m high (CGWB). Lunga (Bengali লুঙ্গা, "Flat lands between tillas"): the flat valley floor between them, CGWB's "low lands ('loonga') of Holocene terrace", which is the natural flow path and the land on which towns are built and ponds are filled. Chhara (Bengali ছড়া, "Streams"): a hill stream or small natural channel; the TBR 2017 call a hill stream a jhora. The glosses are the land classes of Appendix-I of the Diversion of Land Rules, 2025. A chhara or lunga flow path draining 8 ha or more is a natural channel under Chapter 7. |
| Embankment (bandh); sluice | A river or pond embankment, bandh (Bengali বাঁধ, "Embankment" in the land records), with its sluices, flap gates and pumps. PWD (WR) builds and holds the flood embankments and the Katakhal double-barrel sluice (as quoted). No Tripura statute on embankments or drainage was found [TBC]; this Manual treats PWD (WR) as the owner whose consent a work through an embankment or sluice needs. |
| Khas land; land records | Land of the Government (khas land), and land recorded by district, sub-division, revenue circle and mouza (the online Form-1 of 2026 lists "District / Sub-Division / Revenue Circle"; mouza and plot numbers [TBC]). Where this Manual reserves a drainage corridor, an easement or a regional facility site on private land, it is reserved in the Master Plan or secured by agreement, not taken (set by this Manual); in the TTAADC area land is held under the Council's land law [TBC: not researched]. |
Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).
1.5 Applicability
1.5.1 Who is covered. This Manual applies to:
- (a) all development requiring planning permission, building permit or layout approval under the Tripura Building Rules 2017;
- (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
- (c) works executed by Central agencies or their contractors within Tripura, to the extent that the Authority's approval or no-objection is required.
1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:
- (a) land disturbance of 0.1 ha or more; or
- (b) new or replaced impervious area of 500 m² or more.
1.5.3 RWH. The existing RWH mandate continues to apply under rule 110 of the TBR 2017, in the ULB areas and Local Planning Areas to which the rules apply, to every building of plinth area 200 m² or more, to group housing, public, semi-public and industrial buildings of all sizes and to commercial and mixed-use buildings of 50 m² or more, with permeable materials for all open parking in group housing, the capture of storm water in public open spaces above 500 m², groundwater recharge on plots of more than 500 m² (r.110(5)), and inspection before the completion certificate, as now. This Manual does not change it.
1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:
- (a) no sewage connection to a storm drain (Chapter 8);
- (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
- (c) waterbody setbacks and the no-fill zone (Chapter 7); and
- (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).
1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.
1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.
1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.
1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:
- (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
- (b) linear road resurfacing that adds no impervious area.
Exempt development remains subject to the RWH mandate and to Clause 1.5.4.
1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.
Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.
Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:
- Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
- Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
- The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
- MBBL 2016 makes recharge mandatory for buildings over 500 m².
The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Tripura plots are small and the cumulative effect of many small plots is what fills Agartala's drains. For small buildings in Tripura, the TBR 2017 reach every building of 200 m² plinth or more in the ULB areas and Local Planning Areas with rainwater harvesting, "with emphasis on both storage and reuse" for plotted housing, and require groundwater recharge on plots of more than 500 m² (r.110, r.110(5)); they place the plinth so that the drainage of the site is assured and "in no case … at a height less than 60 centimeters" (r.55), and require roof water to be carried by "sufficient rain-water pipes", which the ULB may require to be connected to a drain (r.57). None of these sets a design storm or a storage volume, so none of it yet limits what leaves the plot in a design storm; Chapter 4 supplies the calculation. The recharge structures of r.110, pits, trenches and wells, on a lunga floor or a recent flood plain with the water table near the surface, are recharge devices in saturated ground: this Manual states the conflict with its lunga rule (Clause 4.11, lunga rule) and requires storage in their place there, and the applicant seeks the ULB's relaxation of the recharge requirement; the Manual does not override the rule. Clause 1.5.4(b) applies to every building whatever its size, because the plinth of r.55 is set by the crest of the road and not by any flood level, and no "highest flood level" has been fixed for any town [TBC]; a small house on a lunga or behind an embankment is where a floor level does most good. Since 2025 a small, low-risk building is permitted and certified by an empanelled professional, with inspection only at random (r.13(3), r.34(9)), so the drainage checks of this Manual for such a building rest with that professional (Chapter 10). An Authority may make the lunga rule, the tilla rule and the hill rule of Clause 4.11 a condition of every building permit in its area, whatever the size of the site (a recommendation of this Manual, not a requirement of Clause 1.5.4). In the TTAADC area, and in rural areas outside the Local Planning Areas, small buildings follow no State building rule that this Manual can reach.
Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.
1.6 Tiered adoption
1.6.1 Tier A authorities. The following are Tier A:
- (a) the Agartala Municipal Corporation; and
- (b) TUDA, within the Agartala Planning Area of the Master Plan 2045 (238.57 km², the Corporation's area and 49 gram panchayats, as reported) and the Agartala-Ranibazar-Jirania Local Planning Area notified by TUDA in November 2019, as those areas are notified from time to time, the Corporation or TUDA being Tier A wherever it has jurisdiction over a site.
1.6.2 Tier B authorities. All other Municipal Councils and Nagar Panchayats, and TUDA in their Local Planning Areas are Tier B.
1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:
Table 1.1 — Differences between Tier A and Tier B authorities
| Item | Tier A | Tier B |
|---|---|---|
| Performance criteria (Chapters 2–9) | Apply in full | Apply in full |
| Hydrologic method for storage | Hydrograph method (Chapter 3) | Hydrograph method, or the design-aid route of Clause 1.7 where eligible |
| Compliance calculator (Clause 10.5) | Required as a summary | Required; may be the sole calculation on the design-aid route |
| Policy supplement alternatives (Clause 1.7) | Only with State Stormwater Technical Committee concurrence | May be adopted by council resolution |
| Technical review | By the Authority | By the Authority, with UDD regional support or an empanelled reviewer (Clause 10.7) |
| Flood-sensitive catchment rule | Applies | Applies |
1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the Agartala Planning Area of the Master Plan 2045 or a notified Local Planning Area, or is found by a post-event review (Clause 10.16) to need the full methods.
1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.
Commentary. Agartala Municipal Corporation, with a central city in a saucer between the embanked Haora and the Katakhal, which floods "During normal rainfall of about 3 to 4 hours" (ADB, IEE, 2020) and is drained by 18 flood pumps and 6 diesel pumps when the rivers are high (2024, as reported), drains and canals whose blockage by plastic waste causes "frequent water logging" (CAG, 2022-23), sewers in its North Zone only (State affidavit to the NGT, 2026) and capital works built mostly by others, 98 per cent of the major AMRUT works by the UDD and PWD (DWS) "and only a few minor works" by the Corporation (CAG, 2019-20), and a small Nagar Panchayat with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Agartala.
1.7 Policy supplement: adoptable alternatives
1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.
1.7.2 The alternatives are:
Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5
| No. | Main-text requirement | Adoptable alternative | Eligibility |
|---|---|---|---|
| S-1 | Storage sized by hydrograph method (Chapter 3) | Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator | Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1) |
| S-2 | Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site | Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule | Any site outside flood-sensitive catchments |
| S-3 | Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) | Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 | Waterbodies with no mapped 1% AEP extent |
| S-4 | Downstream analysis by hydraulic model (Chapter 5) | Screening checklist of downstream capacity and known flooding, with a model only where the screen fails | Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall |
| S-5 | On-site detention | Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) | Where a basin plan has been notified |
1.7.3 Conditions on adoption.
- (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
- (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
- (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
- (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
- (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).
Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.
1.8 Relationship with other instruments
1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.
Table 1.3 — Relationship with other instruments
| Instrument | Relationship |
|---|---|
| Tripura Municipal Act, 1994, as amended up to the Ninth Amendment (7 May 2025) (High Court of Tripura, consolidated text) | Continue. It "extends to the whole of the State of Tripura except the areas under the Tripura Tribal Areas Autonomous District" (s.1(2)); the Agartala Municipal Corporation, the Municipal Councils and the Nagar Panchayats are constituted under it, and there is no separate Act for the Corporation. It defines a "Municipal drain" as "a drain vested in the Municipality" and a "Watercourse" as including "any river, stream or channel" (s.2); vests "all public tanks, streams, reservoirs, and wells" and "all public sewers, drains, channels, tunnels, culverts and water courses in, alongside, or under any street" in the Municipality "unless the State Government otherwise directs by a notification" (s.91); requires it to "provide and maintain a system of drainage or sewerage as well as a safe and sufficient out-fall in or outside the Municipal area" (s.156(1)), with power to hand trunk sewers, treatment plants and pumping stations to a Government agency with the State's approval (s.156(2)); to cleanse and flush drains (s.157); to drain "sudden waterlogging" across private land without prior notice (s.160, proviso); to permit private connections in writing (s.161) and demolish unauthorised ones (s.162); to "require separate provisions to be made for drainage of sewage and other offensive matters as distinct from rain-water" (s.164); and lets the State hand inefficient works to another agency (s.165). No tank may be made without the Municipality's permission (s.232, fine up to ₹2,000); owners must deal with water that "is or is likely to become a breeding place of mosquitoes" (s.233) and keep private tanks free of "pollution by surface drainage" (s.234(1)). Sections 156 and 164 are the hooks for the outfall and separation rules of Chapters 5 and 8, and s.233 for drain-down times (NEER reading). |
| The Tripura Building Rules, 2017 (UDD notification No. F.2(316)-UDD/GL/TCPO/2009 (Part-I)/371 of 10 November 2017, as cited in the UDD's BRAP-2019 document; the 2017 gazette was not read [TBC]), as amended by the Tripura Building (Amendment) Rules, 2019 (No. F.2(466)-UDD/GL/TCPO/2018/599-627, 19 February 2019; Gazette Extraordinary No. 482, 25 February 2019), the (Second Amendment) Rules, 2020 (dated 15 February 2020, Gazette 24 February 2020; number garbled in the copy read [TBC]), the (3rd Amendment) Rules, 2022 (No. F.01(24)-TUDA/Estt/2022/4902-30, 29 November 2022; Gazette 2 December 2022), the (Fourth Amendment) Rules, 2024 (No. F.1(23)-TUDA/ESTT/2024/66, 15 January 2025; Gazette No. 95, 17 January 2025) and the (Fifth Amendment) Rules, 2025 (F.No.2(466)-UDD/GL/TCPO/2018(P-V)/4009-20, 4 July 2025; Gazette No. 1294, 5 July 2025), made under section 274 read with section 118 of the Tripura Municipal Act, 1994; the original rules read in the UDD's copy and the consolidated texts to the Fourth and Fifth Amendments (High Court of Tripura); no sixth amendment found to November 2026 | Continue. They apply to "buildings in the Urban Local Bodies (ULBs) in Tripura" and, since 2019, the Planning Areas (r.1(2)), and not in the TTAADC area, to which the parent Act does not extend; they replace the Tripura Building Rules, 2004 (r.1(4)) and defer to the latest National Building Code and Indian Standards for what they do not cover (r.3A). They define a "drain" to include a culvert, ditch or channel for carrying off "rain water or subsoil waters" (r.2(22)) and "Natural Hazard Prone Areas" to include flood-prone areas of the CWC Flood Atlas and areas flooded by "heavy intensity rains, inadequate drainage, etc. as identified through local surveys in the Development Plan" (r.2(44)); require a site "capable of being well-drained" and not lower than its approach road, and drainage kept out of any tank within 5.00 m (r.4(1)(b), (c), (e)); show drainage and the "natural drainage channel/jhora" on the site plan (r.5(1)(k), (p)); bar the filling of any "canal, pond, water body, wetland, river lets, jhora, water source, natural spring, streams, drains, culverts" except by the Local Body with the State Government's prior approval for recorded reasons, which may also allow a "flood plain area to be filled up" (r.9(3)); limit buildings in the "zone of river (within 15 metres from river bank)" or on the front of a water body of more than 1,000 acres to 5.00 m in height (6.50 m on stilts), 20.00 m in length, 200.00 m² of cover and 50.00 m apart (r.9(4)), a regulated zone, not a no-build setback; keep abandoned brickfield pits as water bodies (r.9(5)); require pucca drains in sub-divisions (r.10(2)(f)); ask for "the house drainage plan, and site drainage plan up to nearest Nagar Panchayat or Municipality or natural outfall" and a roof drainage plan (r.14), now through an online single window (r.14(1), 2025); allow a soil test, a height limit or refusal on "recently filled up … pond, lake, marshy" land (r.32); require notice before drains are covered (r.38, Form I); set ground coverage at up to 70% for every use and 100% for some industrial and commercial plots (r.46(1), r.51(2), 2025) and landscaping of 1.0% to 7.5% of plots above 150 m² (r.113, 2022); set the plinth at not less than 60 cm above the crest of the road (r.55) and roof drainage by rain-water pipes (r.57); keep surface drainage out of basements and require pumping where needed, with the basement ceiling 0.8–1.2 m above the front road (r.66(5), (6)(b), (6)(h)); and, in the hill ULBs of Part X (rr.88–101; which ULBs these are is not listed [TBC]), require a slope-stability certificate on slopes of 30° and more (r.90(1)(f)), bar sites within 200 m of a sinking or slip zone or on "high water table and fully saturated soil" (r.90(1)(h)), keep sites "five meters in any direction of the outside edge of such water courses" (r.90(1)(i)), the only no-build distance from a watercourse in the rules, require protective works within 5.0 m of a tank, jhora or natural drain and within 30 m of a jhora (r.90(1)(m)), and require slopes "not less than 1 : 60" round buildings and surface-water drains that "shall not be connected with any drain carrying sullage water or sewage" (r.99). Since 2025 low-risk buildings are self-certified by empanelled professionals, with inspection of 10% to 15% at random (r.13(3), r.34(9)). They set no design storm, release rate, detention volume or storm-water volume (NEER reading). The design criteria of Chapters 2–6, the lunga, tilla and hill rules of Clause 4.11 and the corridors of Chapter 7, whose Zone 1 is a no-build strip of at least 15 m and so stricter than r.9(4) and r.90(1)(i), are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the TBR 2017, a Master Plan or a statute are stricter, they govern (Clause 1.3.3). |
| Rainwater harvesting: TBR 2017, r.110 | Continue unchanged. "All building having plinth area not less than 200 sq.m., while submitting the building plans for sanction, shall mandatorily include the complete proposal of rainwater harvesting"; group housing, public, semi-public and industrial buildings of all sizes and commercial and mixed-use buildings of 50 m² and above are listed; in group housing "Concrete paving to be avoided and permeable materials are to be used for all open parking spaces"; public open spaces above 500 m² "shall have arrangements for complete utilization and capture of storm water"; groundwater recharge "should be made mandatory" on plots of more than 500 m² (r.110(5)), by recharge pits, trenches, wells and shafts of stated sizes; each ULB constitutes a Rainwater Harvesting Cell and inspects the structures before the completion certificate, every year above 1,000 m² and at random (10%) below (r.110(6)). The 200 m² threshold replaced the 300 m² of the 2004 rules (as reported). No storage volume, roof-area rate or infiltration test is set (NEER reading). This Manual counts stored water against its retention requirement only as reuse (Clause 4.4.3), never as detention. Where the lunga rule or the hill rule of Clause 4.11 bars the recharge structures of r.110, the two conflict: this Manual requires storage in their place, and the applicant seeks the ULB's relaxation; the Manual does not override the rule. |
| Tripura Urban Planning and Development Act, 2018 (Tripura Act No. 12 of 2018); the notification of Local Planning Areas under section 52(1) (No. F2(15)-TUDA/TECH/2019(P), November 2019); the Master Plan for the Agartala Planning Area 2045 | Continue. The Act constitutes the Tripura Urban Planning and Development Board, chaired by the Chief Minister, and TUDA, whose functions include the "development of water bodies or open spaces" and Master Plans; Planning Areas are declared under s.52 and Master Plans made under s.53(1); and s.163 repeals the Tripura Town and Country Planning Act, 1975 (Tripura Act No. 4 of 1976), deeming orders under it issued under the new Act. TUDA notified "Local Planning Areas adjacent to 20 Cities/Towns of Tripura" in November 2019 (the day is illegible in the copy read), the first being the Agartala-Ranibazar-Jirania Local Planning Area, bounded on the west by the "International border with Bangladesh". The Master Plan for the Agartala Planning Area 2045, a GIS-based plan for 238.57 km² taking in the Agartala Municipal Corporation and 49 gram panchayats, with "statutory zoning and development control regulations", was declared final by the UDD on 24 February 2026 under s.53(1) (as reported); its notification number, text, zoning regulations and any water-body, river or drainage buffers were not read [TBC]. Master Plans would show the flood-sensitive catchments, drainage reserves and regional facility sites of this Manual (Chapter 11). |
| Tripura Land Revenue and Land Reforms Act, 1960 (43 of 1960) (as cited); the Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025 (Revenue Department No. F.4(05)-RCC/2025, 2 June 2025; Gazette Extraordinary No. 1072, 3 June 2025), made under sections 20 and 98 of the Act, as amended by the (First Amendment) Rules, 2026 (6 March 2026; Gazette Extraordinary No. 2026350); the Revenue Department's "Guidelines on Diversion of Water Bodies" (April 2022, as quoted) | Apply as amended. The 2025 rules made the "Diversion of water body to any other purpose" a diversion of land (r.2(iii)) and required for it a recommendation of a district or sub-divisional committee of DST&E, a no-objection certificate of the Fire and Emergency Service and the recommendation of the State Level Advisory Committee, with the District Magistrate and Collector deciding (r.4(v), r.7). The amendment of 6 March 2026 substituted rule 3 with "Self certification for change of classification of land" online, subject to section 20(4) of the Act, and rule 4 with revocation within thirty working days of a diversion made in contravention of section 20(3) and (4), and omitted rules 6 to 10. Read literally, the water-body procedure of 2025 no longer stands; whether section 20 of the Act still bars the diversion of a water body was not established for this Manual, and the current procedure is not stated here [TBC]. In 2022 the Department found "no specific guidelines in the TLR & LR Act & Rules in respect of diversion of water bodies" (as quoted). Appendix-I of the 2025 rules classes the pukur ("Tank/Pond"), its bank ("Bank of tank"), the dighi ("Large tank"), the beel ("Watery land"), the haor ("Big watery land"), the chhara ("Streams"), the lunga ("Flat lands between tillas") and the bandh ("Embankment") as land, the hook for counting and protecting their storage under Chapter 7. |
| Tripura Official Language Act, 1964 (Act No. 5 of 1964), as amended by Act No. 8 of 1979 (as quoted); Law Department notification No. F.12(1)-LAW/88(Shadow), 29 April 1999 | Continue. Bengali and Kokborok (written "Kok-Borak" in the Act and "Kok Borok" in the notification) are the languages for the official purposes of the State from 1 May 1999, and English "may continue to be used" (s.2). The Manual's rule for signs is in the front matter. |
| Wetlands (Conservation and Management) Rules, 2017; the Wetland Authority of Tripura (No. F.17(54)/For-Dev/WATIL/2017/24661-686, 05.09.2018, reconstituted on 04.04.2022 and 18.06.2022, as quoted); Rudrasagar (Ramsar site No. 1572) | Continue. Rudrasagar, 240 ha with a catchment of 6,052 ha, was designated on 8 November 2005 by the Ramsar record and "officially designated" on 29 February 2007 by the Forest Department (as quoted; conflict); the CAG found ring roads built in it without the Wetland Authority's permission, which "reduced the water level" (CAG, 2021-22). The Dumbur reservoir is not a Ramsar site. The pukurs, dighis, beels and other water bodies are governed by Chapter 7. |
| Department of Science, Technology and Environment: "Statutory Guidelines for protection and preservation of lakes, ponds and water bodies in Tripura" (reported as notified after WP(C)(PIL) No. 2 of 2014; not read [TBC]); a direction on construction near a lake (source and scope unverified) | Not used as rules. The guidelines were not read and no buffer is taken from them; the direction that "no construction is raised within 75 Mtrs. of the end of the lake" is of unverified source and scope and is not a rule (as quoted). The statutory lines are those of the TBR 2017, r.4(1)(e), r.9(3), r.9(4) and r.90(1)(i) and (m). |
| Floodplain zoning, groundwater and water bodies: no Act | No flood-plain zoning Act, groundwater Act or water-body Act of Tripura was found (the High Court's index of 166 State Acts; NEER reading). The "Natural Hazard Prone Areas" of r.2(44), to be identified "through local surveys in the Development Plan", r.9(3) and r.9(4) and the zoning of the Master Plan 2045 are the nearest hooks; PWD (WR)'s map of the flood-plain zone of the Haora, prepared for the NGT, has no known legal status [TBC]. The 1% AEP maps of Chapters 6 and 7 are offered as an input to the surveys of r.2(44), not as a notification. Groundwater is little used (stage of extraction 9.48%, every unit Safe; GWRA 2024, as quoted), so recharge is not a design objective of this Manual (Clause 4.11). |
| Embankments and drainage: no statute | No Tripura Act on embankments or drainage was found [TBC]. PWD (WR) holds the flood embankments, reported as 154.41 km and as 134.55 km (conflict), and the Katakhal double-barrel sluice, and this Manual treats it as the owner whose consent a work that cuts, crosses or discharges through an embankment or sluice needs (Chapter 5). No setback distance from an embankment was found [TBC]. |
| High Court of Tripura: WP(C)(PIL) No. 2 of 2014, Bibash Ch. Saha v. State of Tripura (as cited, copy dated 16.08.2016); the order of 28.06.2017 on the encroachment of water bodies in Agartala (case number unconfirmed, as quoted); WP(C)(PIL) No. 05 of 2017 (Rudrasagar, as reported); WP(C)(PIL) No. 06 of 2026 (NH-108B and NH-208, judgment of 08.09.2026) | Apply where they bind; they are court directions, not design standards. In PIL 2/2014 the Court found ponds filled and walls built on their banks at Kalyan Sagar, Matabari, ordered 110 m of cement embankment to be demolished and the State to notify a guideline on protecting water bodies within six months; in 2017 it took a zone-wise affidavit of the Corporation on encroached water bodies; in PIL 05/2017 it took up the level of Rudrasagar (a minimum level of 11 m RL is reported); and in PIL 06/2026 it recorded "No proper drainage system … water logging everywhere" and culverts blocked "by silt, vegetation, debris" on the national highways, and called for bi-weekly reports by NHIDCL, an audit by the Border Roads Organisation by 30.01.2027 and an inquiry by the Union by 1.12.2026. None sets a setback or a design storm. The Tripura Human Rights Commission took up the filling of a water body at Gol Bazar in 2025 (as reported). |
| National Green Tribunal: OA 673/2018 (polluted river stretches; State affidavit and CPCB report); OA 606/2018 (solid and liquid waste; State affidavit of 06.07.2026 on the order of 13.04.2026); OA 325/2015 (water bodies; State report of 26 May 2020, as reported) | Apply where they bind. In OA 673/2018 six Priority V stretches of 2018 were reduced to one, the Haora at Dashamighat, which is to be a "Model River" with in-situ treatment of five drains, and the State said "Partial drainage system is present in Agartala Municipal Corporation"; the stretch is given as "Agartala to Champaknagar" by the State and "Agartala to Bishramganj" by CPCB (conflict). In OA 606/2018 the tribunal's point, as quoted in the State's affidavit, is that "storm water drains are being tapped and taken to STPs which is not legal", and its order of 13.04.2026 found two treatment plants near or on the flood plain that "may lead to flooding of the STP and flowing of untreated sewage in the river during the monsoon". Sewage in storm drains is dealt with in Chapter 8 (Clause 8.9). |
| Environment (Protection) Act, 1986; Water (Prevention and Control of Pollution) Act, 1974; the Tripura State Pollution Control Board | Continue. Chapter 8 governs sewage in storm drains. |
| Disaster Management Act, 2005; TDMA, the Revenue Department, the District Magistrates and Collectors and the District Disaster Management Authorities | Continue. TDMA's State Disaster Management Plan 2024-25 was not read [TBC]; its monsoon checklist of 2026 lists "urban drain de-silting" without a date (as quoted), and no order of the State fixing a date for pre-monsoon desilting was found; the works calendar of Chapter 10 sets this Manual's dates, beginning with 31 March, for drains, sluice gates, flap gates and pumps. PWD (WR)'s calendar for embankment works remains its own. |
| IRC:SP:42-2014, IRC:SP:48 (Hill Road Manual) and the practice of PWD (R&B) and NHIDCL on road drainage on the tillas and the hill ranges | Apply to road drainage, cross-referenced from Chapter 6, where they do not conflict with it; the drainage clauses of IRC:SP:48 were not read for this Manual [TBC]. |
| CPHEEO Manual on Storm Water Drainage Systems (2019) | Engineering reference. This Manual sets higher return periods under Clause 1.3.2. |
| NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) | This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF. |
| NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 | Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create. |
| IRC:SP:42-2014 and IRC:SP:50-2013 | Apply to road drainage only where they do not conflict with Chapter 6. |
| MBBL 2016, Chapter 9 | Model for RWH and for the inspection regime in Chapter 10. |
Commentary. RWH in Tripura is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the monsoon, because RWH sumps are usually full or the ground saturated by the time a June to August monsoon storm, such as those of June and July 1993 and August 2024, arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.
Tripura is spending on Agartala's drains, but with no stated design basis. The ADB's Agartala City Urban Development Project (53262-001) includes 48.2 km of new or rehabilitated storm-water drains (ADB, IEE, 2020), on a loan of $61 million in 2021 (as reported); a later ADB loan of $100 million with 55 km of storm-water drains is reported, its year unconfirmed (as reported), and a Tripura Urban Livability Improvement Project (53276-003) of $181.28 million is listed as "Proposed" (ADB, as quoted). The Corporation sent the ADB a storm-water proposal, reported as about ₹5–6 billion of an Agartala programme of about ₹12 billion, whose aim is to cut drainage time "from one to two hours to about 15–30 minutes" (as reported). Agartala Smart City Ltd has built storm drains, flood pumps and works on the Akhaura canal and the Katakhal, with "6 new flood pumps" in 2025 among projects worth "over Rs 844 crores" (as reported); a 650 m embankment on the Haora was built and the Katakhal cleaned in March 2026, and a proposal of ₹1,000 crore for two protective embankments and three more pumping stations, to be "implemented in phases, depending on the availability of funds", was reported in July 2026 (as reported). About 50 km of new drains are planned by the Corporation and Agartala Smart City Ltd (as reported). None of the documents found states a design return period, design intensity or runoff coefficient for any of these works, and no development-control condition stops new plots in the same catchments from using up the capacity they create. Linking Chapters 4–5 to approvals closes that gap.
The State's law holds many of the tools. The TBR 2017 bar the filling of ponds, jhoras, streams and drains without the State's approval (r.9(3)), regulate building within 15 m of a river bank (r.9(4)), ask for a site drainage plan "up to nearest … natural outfall" (r.14), keep hill sites five metres from water courses and their surface-water drains apart from sewage (r.90(1)(i), r.99), and require rainwater harvesting (r.110). The Tripura Municipal Act, 1994 vests "all public tanks, streams, reservoirs, and wells" and "all public sewers, drains, channels, tunnels, culverts and water courses in, alongside, or under any street" in the Municipality (s.91), makes it "provide and maintain a system of drainage or sewerage as well as a safe and sufficient out-fall in or outside the Municipal area" (s.156(1)), lets it drain "sudden waterlogging" across private land without notice (s.160), require "separate provisions … for drainage of sewage and other offensive matters as distinct from rain-water" (s.164) and act where water accumulation "is or is likely to become a breeding place of mosquitoes" (s.233). The Diversion of Land Rules class the pukur, the dighi and their banks as land; the Wetlands Rules, 2017 and the Wetland Authority of Tripura cover notified wetlands. The courts and tribunals have acted too: the High Court on pond filling at Kalyan Sagar (WP(C)(PIL) No. 2 of 2014), on Rudrasagar (WP(C)(PIL) No. 05 of 2017) and on the drains and culverts of NH-108B and NH-208 (WP(C)(PIL) No. 06 of 2026), and the National Green Tribunal on the Haora (OA 673/2018) and on sewage in storm drains (OA 606/2018), where the tribunal's point, as quoted in the State's affidavit, is that "storm water drains are being tapped and taken to STPs which is not legal". The CAG has audited solid waste in the towns, sand mining that "caused weakening of river embankment", the Rudrasagar ring roads and the Corporation's role in AMRUT; no CAG audit of flood control, embankments, Smart City works or storm drainage was found. What the law lacks is a design standard. None of these instruments says which storm a drain must carry, how much storage a paved plot removes, how long a sluice may be assumed closed or where a flood line lies; no floodplain zoning law, water-body Act or groundwater Act exists in the State, and the zoning regulations of the Master Plan for the Agartala Planning Area 2045 were not read [TBC]. This Manual's checks are framed as part of the building permit and the occupancy certificate given by the competent authority for the area, not as a separate no-objection certificate. The Manual is offered as a technical companion to these instruments, to the orders of the courts and to the drainage works of the towns: it supplies the design storm, release rates, storage volumes, tailwater and outfall-closed cases, infiltration rules and corridors they do not set, as a proposal for the Government, the TTAADC and the other authorities to consider. Neither the UDD, TUDA, the Agartala Municipal Corporation, any Municipal Council or Nagar Panchayat, PWD (WR), the TTAADC nor any other body has adopted it.
1.9 Roles and responsibilities
1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.
Table 1.4 — Roles and responsibilities under this Manual
| Agency | Role under this Manual |
|---|---|
| Urban Development Department (UDD) and its Town and Country Planning Organisation (TCPO) | The UDD makes the TBR 2017 under section 274 read with section 118 of the Tripura Municipal Act, 1994 (its file series is "UDD/GL/TCPO"), oversees the urban local bodies, carries out AMRUT works with PWD (DWS) and is the executing agency of the ADB's Agartala project (as reported); it declared the Master Plan for the Agartala Planning Area 2045 final on 24 February 2026 (as reported). If the Manual were adopted, the UDD would prepare the amendment of Clause 1.3.1(a) and the model bye-law of Clause 1.3.1(b), and give regional support to Tier B authorities (Table 1.1). |
| Tripura Urban Planning and Development Authority (TUDA) and the Tripura Urban Planning and Development Board | Constituted under the Tripura Urban Planning and Development Act, 2018 (the Board chaired by the Chief Minister, the Authority by the Minister-in-charge of Urban Development); prepares Master Plans and gives building permission and occupancy certificates in the notified Local Planning Areas and for buildings or townships of 50 or more flats or one acre or more inside a ULB area (r.13(3)); its functions include the "development of water bodies or open spaces". If the Manual were adopted, it would require the drainage report of Chapter 10 with each permission it grants, and could write drainage reserves, lunga and pukur protection and buffers along the Haora into the zoning regulations of the Master Plan 2045 and the layouts of the Local Planning Areas (Chapter 11). |
| State Stormwater Technical Committee (Clause 1.3.2) | Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12). |
| Agartala Municipal Corporation, the Municipal Councils and the Nagar Panchayats | Constituted under the Tripura Municipal Act, 1994 (the Corporation upgraded from a Municipal Council in January 2014, as reported; 19 other ULBs); give the building permit and the occupancy certificate under the TBR 2017 and hold the drains, tanks and water courses vested in them (s.91), with the duty to provide drainage and "a safe and sufficient out-fall" (s.156(1)) and the powers of ss.157–166. The Corporation desilts its drains every year, runs the flood pumps of the central city and an Integrated Command and Control Centre with rain and level sensors (as reported). Would apply this Manual at the building permit and the occupancy certificate and to their own works, keep the drain register of their area, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15). |
| Agartala Smart City Ltd (ASCL) | Builds storm drains, flood pumps, works on the Akhaura canal and the Katakhal, the Ujjayanta and MBB College lakes, the 8 MLD treatment plant at the Akhaura ICP and the in-situ treatment of five drains to the Haora (as reported; as quoted). Would design its drainage works to this Manual from the dates of Clause 1.11 and hand them over with their records (Clause 10.14). |
| Public Works Department (Water Resources) (PWD (WR)) | Builds and maintains the "flood protection embankments and anti-erosion work", the irrigation works and the Katakhal double-barrel sluice near Bhuturia, and has mapped the flood-plain zone of the Haora (as quoted). No Tripura statute on embankments or drainage was found [TBC]. Would set outfall, sluice and embankment-crossing conditions as the owner of those works, supply sluice sills, closing levels and operating rules for Chapter 5, and apply this Manual to its drainage works. Its calendar for embankment works remains its own; the dates of Chapter 10 cover the drains, sluice gates, flap gates and pumps of the drainage system. |
| PWD (Roads and Buildings) and NHIDCL | PWD (R&B) builds "Major roads and drains" (CAG, 2019-20); NHIDCL is the agency for NH-108B and NH-208 before the High Court (WP(C)(PIL) No. 06 of 2026). Would apply Chapter 6 and the hill-road rules to their roads and never discharge a road drain onto an unprotected slope. |
| PWD (Drinking Water and Sanitation) | Carries out water-supply and AMRUT works and, with the UDD, the drainage pump houses and sewage treatment plants (as quoted; CAG, 2019-20). Would keep sewage out of storm drains as the sewers are built (Chapter 8) and design pump houses to Chapters 5 and 9. |
| Revenue Department and the District Magistrates and Collectors; the State Level Advisory Committee | Keep the land records (district, sub-division, revenue circle and mouza) and the land classes of the Diversion of Land Rules, 2025; the Revenue Department is the nodal department for disaster management (as quoted). Since the amendment of 6 March 2026 a change of classification is made by online self-declaration, which the Competent Authority may revoke within 30 working days; how a water body is diverted under the amended rules was not established [TBC]. Would refer to this Manual in decisions on water bodies. |
| Department of Science, Technology and Environment (DST&E), its water-body committees and the Tripura State Pollution Control Board (TSPCB) | DST&E reports a notified "Statutory Guidelines for protection and preservation of lakes, ponds and water bodies in Tripura" (not read; no buffer is taken from it [TBC]), runs the State and sub-divisional monitoring committees and the River Rejuvenation Committee; TSPCB gives consents and monitors the Haora at Dashamighat (as quoted; CPCB). Would be consulted before a pukur or water body is used for storage or as an outfall (Chapter 7) and receive the records of sewage found in storm drains (Chapter 8). |
| Forest Department and the Wetland Authority of Tripura | The Wetland Authority (No. F.17(54)/For-Dev/WATIL/2017/24661-686, 05.09.2018, reconstituted in 2022, as quoted) administers the Wetlands (Conservation and Management) Rules, 2017; Rudrasagar is managed by the Fisheries Department by the Ramsar record and by the Forest Department by the State's page (as quoted; conflict). Would be the competent authority for the area for a notified wetland and be consulted before one is used for storage or as an outfall (Chapter 7). |
| TDMA and the District Disaster Management Authorities | TDMA, chaired by the Chief Minister, issued the State Disaster Management Plan 2024-25 and a monsoon checklist of 2026 with "urban drain de-silting", sluice gates and 42 vulnerable embankment points (as quoted; as reported). Would supply the flood and landslide inventories used in the screening of Clause 2.3.6(i) and lead post-event reviews with the Authority (Clause 10.16). |
| Tripura Tribal Areas Autonomous District Council (TTAADC) | Governs the Tripura Tribal Areas Autonomous District under the Sixth Schedule to the Constitution, "nearly sixty-eight per cent of Tripura's territory" (as reported), to which the Tripura Municipal Act, 1994, and so the TBR 2017, do not extend (s.1(2)); no building or land-development regulation of the Council was found [TBC]. The Manual has no force in the council area unless the Council adopts it. The Council could adopt it by a regulation of its own or by resolution; if it did, it, or the authority it designated, would be the competent authority for the area. |
| Operator of the Dumbur reservoir (the Gumti hydel project; TSECL, as reported) and NEEPCO | Operate the reservoir and its gates, whose release on 21 August 2024 is reported and denied (as reported; conflict); full reservoir level 93.55 m, "danger level" 94 m and spillway capacity 481.38 m³/s (as reported). Would supply reservoir levels, release rules and release records for Chapter 5 and the screening of Clause 2.3.6(i), and give warnings of releases in writing and by siren or SMS. |
| Central Water Commission (CWC), a body of the Union | Publishes the Flood Estimation Reports (none for subzone 2(c), in which Tripura lies by elimination) and runs 12 river sites in Tripura, 2 of them for level forecasting (2018, as reported). Would supply river stage records with their datum for Chapter 5 and confirm the subzone of the State and whether any study for subzone 2(c) exists. |
| Central Ground Water Board (CGWB), North Eastern Region, State Unit Office Agartala, a body of the Union | Holds the observation wells and published the aquifer map of West Tripura (NAQUIM). Would supply groundwater levels and quality for Clause 4.11 and Chapter 8; no State observation-well network was found [TBC]. |
| IMD (Meteorological Centre Agartala), and road, rail and other owners | IMD's stations supply the rainfall records of Chapter 2; Agartala (A) (42724) and Kailashahar (A) (42618) are the first data requests of Clause 2.3.6(a). Other owners of roads, railways and their drains would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7). |
Commentary. Stormwater in Tripura is split, first, by the river. The towns drain through sluices and pumps at embankments that PWD (WR) holds, into rivers that leave the State, so the body that holds a town's drains is not the body that decides when its outfall opens, and no one in India controls the river below it. It is split, second, by the Sixth Schedule: the Tripura Municipal Act, 1994 and the TBR 2017 reach the ULB areas and the Local Planning Areas, and not the TTAADC area, about 68% of the State (as reported), where no building regulation was found. And it is split, third, among the bodies that build Agartala's drains. The Act vests the public drains, tanks and water courses in the Corporation (s.91) and makes it provide "a safe and sufficient out-fall" (s.156(1)), but the capital works are built by others: 98 per cent of the major AMRUT works by the UDD and PWD (DWS), "and only a few minor works" by the Corporation, with no tripartite agreement (CAG, 2019-20); the major roads and drains by PWD (R&B) (CAG); storm drains, flood pumps and the Akhaura canal and Katakhal works by Agartala Smart City Ltd; the embankments, the Katakhal sluice and the flood-plain mapping by PWD (WR); and the pump houses and treatment plants by PWD (DWS) with the UDD (as quoted; as reported). The Agartala Planning Area of the Master Plan 2045, 238.57 km², is also wider than the Corporation's area (as reported). The Katakhal shows why the split matters. It is at once the northern trunk drain of the city, the receiver of three treatment plants that are to be fed by intercepting its drains (State affidavit to the NGT, 2026), and a channel whose outfall PWD (WR)'s sluice closes against the river. No order was found that allocates the Akhaura canal, the Katakhal, the Haora embankments or the sluices to one owner, or that hands any drainage work over under section 156(2) or section 165 of the Act (NEER reading) [TBC]. Until the State issues such an order, this Manual assigns the drainage elements as in Table 1.5, as Chapter 6 does for the drains themselves, and recommends that each town keep a drain register giving every reach its owner, its land status (khas or government land, private land, or Council land), whether it is a vested municipal drain, an embankment drain or sluice, or a natural chhara (Bengali ছড়া, "Streams") or lunga, and its outfall (set by this Manual). The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers, and on private land it is put into effect by reservation in the Master Plan or by agreement, not by acquisition.
Table 1.5 — Working assignment of drainage elements under this Manual
| Element | Assigned to |
|---|---|
| Municipal drains, public tanks, streams and water courses in a ULB area | The ULB, and in Agartala the Agartala Municipal Corporation (Tripura Municipal Act, 1994: vesting s.91, "unless the State Government otherwise directs by a notification"; drainage and "safe and sufficient out-fall" s.156(1); cleansing s.157; connections by written permission s.161; demolition of unauthorised drains s.162; separation of sewage from rain-water s.164; encroachment s.166) |
| Capital drainage works in Agartala, built by others: AMRUT works; storm drains, flood pumps and the Akhaura canal and Katakhal works; the Ujjayanta and MBB College lakes; the ADB's 48.2 km of drains | Built by the UDD and PWD (DWS) (AMRUT, 98%, CAG, 2019-20), Agartala Smart City Ltd and the ADB project; maintained by the Agartala Municipal Corporation unless handed over under s.156(2) or s.165 [TBC] |
| Major roads and their drains; the drains of NH-108B and NH-208 | PWD (R&B) (CAG); NHIDCL (WP(C)(PIL) No. 06 of 2026) |
| River embankments, sluices (among them the Katakhal double-barrel sluice), anti-erosion works and flood-plain mapping | PWD (WR) (no statute found [TBC]) |
| Drainage pump houses and sewage treatment plants | PWD (DWS) with the UDD |
| Drains in the TTAADC area | The District Council or the body it designates [TBC] |
No formal allocation order was found. This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.
1.10 Variances and waivers
1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:
- (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
- (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.
1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Tripura has no coast and no tidal reach, so no site in the State qualifies for this waiver. A site that drains to a river through an embankment sluice, to a pukur, dighi or lunga behind a closed outfall, to a pumped outfall such as those of central Agartala, to a river that leaves the State with no downstream control, or to the Gomati below the Dumbur reservoir, is in the outfall-closed condition of Chapter 5 whenever the receiving water is high, and detention is not waived for it; nor is it waived for a site because it drains to a large river.
1.10.3 No variance or waiver. No variance or waiver shall be granted for:
- (a) a sewage connection to a storm drain;
- (b) the lowest habitable floor level of Chapter 6;
- (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
- (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.
1.10.4 Procedure.
- (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
- (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
- (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
- (d) A variance runs with the approval. It lapses if the approval lapses.
Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Tripura ponds have been filled for housing in Barjala and Lanka Basti in Agartala (as reported); local bodies allowed ponds to be filled and walls to be built on their banks at Kalyan Sagar, Matabari, until the High Court ordered the State to notify a water-body guideline and 110 m of cement embankment to be demolished (WP(C)(PIL) No. 2 of 2014, as cited); ring roads were built in Rudrasagar, a Ramsar site, without the Wetland Authority's permission, which "reduced the water level" (CAG, 2021-22); and the State Human Rights Commission took up the filling of a water body at Gol Bazar in 2025 (as reported).
1.11 Transition provisions
1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).
1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.
1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.
1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.
1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.
Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).
1.12 Review and amendment
1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.
1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.
1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.
References (chapter)
- Government of Tripura, Urban Development Department. Tripura Building Rules, 2017 (notification No. F.2(316)-UDD/GL/TCPO/2009 (Part-I)/371 of 10 November 2017, as cited in the UDD's BRAP-2019 document [TBC]; the UDD's copy, Wayback Machine capture of 24 May 2024), as amended by the (Amendment) Rules, 2019, the (Second Amendment) Rules, 2020, the (3rd Amendment) Rules, 2022, the (Fourth Amendment) Rules, 2024 and the (Fifth Amendment) Rules, 2025 (consolidated texts to the Fourth Amendment, 17.01.2025, and the Fifth Amendment, 05.07.2025, High Court of Tripura). https://thc.nic.in/Tripura%20State%20Lagislation%20Rules/Building%20Rules,%20Tripura,%20%202017%20(As%20Amended%20upto%205th%20Amendment%20dt.%2005.07.2025).pdf
- Government of Tripura, Urban Development Department. Supporting documents, Uniform Building Code (BRAP-2019) (Wayback Machine capture of 24 May 2024). https://udd.tripura.gov.in/sites/default/files/2024-05/Uniform%20Building%20Code_0.pdf
- Government of Tripura. Tripura Municipal Act, 1994, as amended up to the Ninth Amendment, 07.05.2025 (High Court of Tripura). https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/Municipal%20Act,%20Tripura,%201994.pdf
- Government of Tripura. Tripura Urban Planning and Development Act, 2018 (Tripura Act No. 12 of 2018). https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/Urban%20Planning%20and%20Development%20Act,%20Tripura,%202018.pdf
- Tripura Urban Planning and Development Authority. Notification of Local Planning Areas under section 52(1), No. F2(15)-TUDA/TECH/2019(P), November 2019 (Wayback Machine capture of 21 May 2024). https://udd.tripura.gov.in/sites/default/files/2024-05/Local%20Planning%20Areas%20Notification..pdf
- Government of Tripura, Revenue Department. Tripura Land Revenue and Land Reforms (Diversion of Land) Rules, 2025, No. F.4(05)-RCC/2025 of 2 June 2025 (Gazette Extraordinary No. 1072, 3 June 2025), with the (First Amendment) Rules, 2026, of 6 March 2026 (Gazette Extraordinary No. 2026350) (page images). https://thc.nic.in/Tripura%20State%20Lagislation%20Rules/Land%20Revenue%20&%20Land%20Reforms%20(Diversion%20of%20Land)%20Rules,Tripura,%202025.pdf
- Government of Tripura. Tripura Official Language Act, 1964 (Act No. 5 of 1964), as amended, with Law Department notification No. F.12(1)-LAW/88(Shadow) of 29 April 1999. https://thc.nic.in/Tripura%20State%20Lagislation%20Acts/The%20Tripura%20Official%20Language%20Act,%201964..pdf
- High Court of Tripura. WP(C)(PIL) No. 06 of 2026, judgment of 08.09.2026. https://www.livelaw.in/pdf_upload/2026/09/09/union-of-india-tripura-hc-699203.pdf
- High Court of Tripura. WP(C)(PIL) No. 2 of 2014, Bibash Ch. Saha v. State of Tripura (third-party copy dated 16.08.2016, as cited). https://www.casemine.com/judgement/in/58f70f25e4b09df07d76ea5f
- National Green Tribunal. OA 673/2018, State of Tripura affidavit and CPCB report in EA 35/2023; OA 606/2018, affidavit of the Government of Tripura filed 06.07.2026 and the earlier action-taken report. https://www.greentribunal.gov.in/
- Comptroller and Auditor General of India. Audit Report for the year 2022-23 (Government of Tripura), Chapter II, performance audit of solid waste management in urban areas, and Chapter III, sand mining; Audit Report for 2021-22, Chapter III, para 3.6 (Rudrasagar); Audit Report for 2019-20, Chapter II, performance audit of the 74th Amendment (report numbers not given on the pages read). https://cag.gov.in/
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (the Haora at Dashamighat). https://dste.py.gov.in/ppcc/pdf/Laboratory/PRS-2025.pdf
- Central Ground Water Board, North Eastern Region. Aquifer Mapping and Management Plan of West Tripura District (NAQUIM, AAP 2017-18) (Wayback Machine capture of 12 Dec 2022); Ground Water Resource Assessment 2024, State compilation (as quoted). https://cgwb.gov.in/
- Ramsar Convention. Rudrasagar Lake, Ramsar Information Sheet, site No. 1572 (as quoted). https://rsis.ramsar.org/ris/1572
- Government of Tripura, Forest Department. Rudrasagar and the Wetland Authority of Tripura (as quoted). https://forest.tripura.gov.in/node/49
- Department of Science, Technology and Environment, Tripura. Indicative action plan citing the Statutory Guidelines for water bodies, and a direction on construction near a lake (as quoted; not read). https://dste.tripura.gov.in/
- Indian Roads Congress. IRC:SP:48, Hill Road Manual (drainage clauses not read [TBC]).
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §4.4.1.4 (Table 4.1 and notes).
- Kakkar, R. (CPHEEO) (2023). Understanding Urban Stormwater Management. CSE, Aug 2023.
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding.
- MoHUA (2016). Model Building Bye-Laws, Chapter 9.
- Lok Sabha Unstarred Question 1847, 30 Jul 2026 (MoHUA). https://sansad.in/getFile/lsapps/loksabhaquestions/annex/188/AU1847_x29brZ.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Agartala (A) (42724) and Kailashahar (A) (42618). https://imdpune.gov.in/library/public/EXTREMES%20OF%20TEMPERATURE%20and%20RAINFALL%20upto%202012.pdf
- India Meteorological Department. National press releases of 20 and 22 August 2024, Annexure I (station rainfall in Tripura). https://internal.imd.gov.in/press_release/20240822_pr_3166.pdf
- Lok Sabha debates, 22 August 1983 (the floods of 3–5 August 1983; as quoted). https://eparlib.sansad.in/bitstream/123456789/831484/1/07_XII_22-08-1983_p195_p200_PII.pdf
- Lok Sabha Unstarred Question 1192 (the toll of August 2024 as found by the Inter-Ministerial Central Team; as quoted). https://eparlib.sansad.in/bitstream/123456789/2984067/1/AU1192_EAHWv4.pdf
- South Asia Network on Dams, Rivers and People (2018 and 2024). Overview of CWC's flood monitoring and forecasting in North East India; August 2024 Tripura floods; June 2018 floods (transcriptions of CWC and IMD data; secondary sources). https://sandrp.in/2024/08/23/august-2024-tripura-floods-questions-over-disaster-management/
- Dartmouth Flood Observatory. Event 2004-096 (June–July 2004; as reported). https://floodobservatory.colorado.edu/2004096.html
- Press reports of the floods of 2017, 2018, June 2022, Cyclone Remal (May 2024), August 2024, 31 May–1 June 2025 and 22–24 August 2026, the landslides of 2018 and 2024, the Dumbur release of 21 August 2024 and the losses and assistance of 2024–2025 (secondary sources).
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). APWA 5600 Manual Factsheet; APWA Stormwater Standards Supplement (7 Nov 2025). https://www.marc.org/document/apwa-stormwater-standards-supplement
- Mid-America Regional Council. The Evolution of Regional Stormwater Design Standards (presentation). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600, §5601.6 Waivers.
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed.
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management.
- Centre for Science and Environment (2023). Urban Stormwater Management (presentation).
- Asian Development Bank (2020). Agartala City Urban Development Project (53262-001): Initial Environmental Examination (draft, November 2020), prepared by the PMU, Agartala Smart City Ltd. https://www.adb.org/sites/default/files/project-documents/53262/53262-001-iee-en_6.pdf
- Asian Development Bank. Tripura Urban Livability Improvement Project (53276-003), project listing ("Proposed"; as quoted). https://www.adb.org/
- Government of Tripura, Urban Development Department. Master Plan for the Agartala Planning Area 2045 (declared final on 24 February 2026, as reported; notification number and text not read [TBC]).
- Agartala Smart City Ltd. Initial Environmental Examination, Smart roads, Part A (not read [TBC]); project lists of storm drains, flood pumps and lake works (as quoted). https://agartalasmartcity.tripura.gov.in/
- Press reports of the Agartala drainage proposal to the ADB, the Smart City projects of 2025, the Haora embankment and Katakhal works of March 2026 and the ₹1,000 crore flood-protection proposal of July 2026 (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 1A | List of Tier A authorities, with the boundaries of the Agartala Municipal Corporation, of the Agartala Planning Area of the Master Plan 2045 and of the Agartala-Ranibazar-Jirania Local Planning Area |
| 1B | Maps of flood-sensitive catchments |
| 1C | Policy Supplement: text of alternatives S-1 to S-5 and model council resolution |
| 1D | Model TBR 2017 amendment and model ULB bye-law |
| Form 1-1 | Applicability Determination |
| Form 1-2 | Variance / Waiver Request |
Commentary. Tripura's floods come from four sources, often together. The first is the river. Every river of the State leaves it for Bangladesh, and the towns lie on the valley floors beside them, many behind embankments (bandh, Bengali বাঁধ, "Embankment" in the land records), whose length PWD (WR) gives as 154.41 km, with 98.00 km of anti-erosion works protecting 28,000 ha, and as 41 embankments of 134.55 km on another page (dates unknown, as quoted; conflict). The benchmark is the flood of 3–5 August 1983, when heavy rain caused "serious devastation", about thirty people died, around five lakh were affected and the road link to the north (NH-8) was cut by "over 60 breaches", with losses of ₹10 crore (Lok Sabha debates, as quoted); the Muhuri at Belonia reached 16.98 m on 4 August 1983, a level that stood until 2024 (CWC data as transcribed by SANDRP). The highest levels of the other CWC sites date the floods since: 15 May 1984 on the Dhalai at Kamalpur and the Juri at Nutan Bazar, before the monsoon; 7 June 1993 on the Manu at Kailashahar and Kumarghat and 22–23 July 1993 on the Gumti at Amarpur and Sonamura, the storms that set the IMD records at Kailashahar (377.2 mm on 6 June) and Agartala (257.2 mm on 22 July) (IMD, Extremes), for which no casualty figures were found; and 24 June 2004 on the Haora, the Burima at Gajaria and the Khowai, in floods that displaced about 90,000 people and killed 3 (as reported). Flash floods in May 2018 killed 6, and on 13 June 2018 the Manu at Kailashahar rose to 25.95 m, 16 cm above its level of 1993, leaving about 21,000 people homeless in Kailashahar and about 40,000 in relief camps, reported as 173, 189 or 224 camps (as reported; conflict), with about 3 deaths.
The second is drainage congestion. Central Agartala "is located at a lower level than other areas giving it the appearance of a saucer", between the Haora embankment to the south and the Katakhal to the north; "During normal rainfall of about 3 to 4 hours, the central part of Agartala gets flooded", and when the rivers are high "Several pumps have been provided to lift the water out of the city" (ADB, IEE, 2020). The Corporation runs 18 flood pumps of up to 900,000 litres an hour each and 6 diesel pumps, which lift water by pipeline to the Katakhal and the Haora (2024, as reported). The towns are built on the lungas (lunga, Bengali লুঙ্গা, "Flat lands between tillas" in the land records), the valley floors that are the natural flow paths, and ponds there have been filled for housing (as reported). On 11 August 2017 the Haora reached 12.4 m and "incessant rain & waterlogging paralyses normal life" (as reported). On 17–19 June 2022 the Haora stood above its danger level (10.82–10.85 m at the Jahar Bridge gauge against 10.50 m; 10.72 m at the CWC site against 10.70 m), West Tripura recorded 155 mm in 24 hours (145 mm in another report; conflict), the Mayor spoke of about 200 mm in 3 hours, 2,057 families, more than 10,000 people, were in 39 camps (1,623 families and 7,109 people in another report; conflict), and one person drowned at Jirania (all as reported). On the night of 31 May 2025 "around 200 mm in just three hours" was reported at Agartala, a man died in a manhole, and about 1,300 families were in camps after 48 hours of rain (as reported; no IMD hourly value found). On 22–24 August 2026 Chandrapur, Baldakhal and Aralia flooded while the Haora stood at 10.72 m against its danger level of 10.70 m (as reported; no rainfall value found).
The third is the great storm. On 19–24 August 2024 a low over Bangladesh brought the State's flood of record in most basins, "worst since 1983" in official words (as reported). Bagafa recorded 49 cm in the 24 hours to 0830 IST on 22 August, and Belonia 32 cm and Amarpur 31 cm in the 24 hours to 20 August (IMD, press releases); South Tripura district received 644.5 mm over 20–22 August (IMD district data as transcribed by SANDRP). The Muhuri at Belonia rose to 18.81 m, the Juri at Nutan Bazar to 20.66 m and the Haora at Agartala to 12.42 m, new highest levels, and the Gomati at Udaipur passed its extreme danger level (CWC data as transcribed by SANDRP; as reported). The gates of the Dumbur reservoir were opened on 21 August, the first release since 1993 by one account, while the power minister denied that a gate had opened (as reported; conflict). About 17 lakh people were affected and 1.25 lakh ha of crops damaged (as reported). The toll is given as 36 by the Inter-Ministerial Central Team (Lok Sabha Unstarred Question 1192, as quoted) and as about 38 by the Chief Minister in the Assembly (as reported), after 24 and 31 at earlier dates. The preliminary estimate of losses was ₹14,247 crore, with a package of ₹564 crore, and the State's memorandum of 13 September 2024 sought ₹7,080.55 crore from the National Disaster Response Fund: a loss estimate and a request for assistance, not two estimates of one thing; ₹288.93 crore of further assistance followed in February 2025 (as reported; as quoted). Cyclone Remal had brought 252.4 mm in 24 hours to Unakoti district on 27–28 May 2024 (district value, as reported).
The fourth is the slope. The tilla uplands (tilla, Bengali টিলা, "Hillock") are cut for roads and houses, and the national highways cross the hill ranges: landslides were reported at 17 locations in June 2018, 11 of them in Khowai district, and at 2,032 locations in August 2024, when 7 people died at Gardang near Santirbazar and 3 at Debipur (as reported). In a petition it took up of its own motion on 7 July 2026, the High Court of Tripura recorded on NH-108B and NH-208 "No proper drainage system … water logging everywhere; RCC drain hole blocked with mud, vegetation; Earthen drain damage & blocked", with culverts blocked "by silt, vegetation, debris", and called for reports, an audit and an inquiry (WP(C)(PIL) No. 06 of 2026, judgment of 08.09.2026).
Missing design makes all four worse. No design storm, return period or drain standard was found in any document of the State's towns: the ADB's report on Agartala (2020), the State's filings before the NGT and the news reports give no storm-drain return period, design intensity, runoff coefficient or time of concentration, and the ADB's drainage upgrade for Agartala aims to cut drainage time "from one to two hours to about 15–30 minutes" (as reported; its DPR was not read [TBC]). The CAG found "frequent water logging of different areas due to blockage of drains and canals by plastic waste" (CAG, 2022-23). The drains are also the sewers: Agartala's sewer network serves only its North Zone, and its treatment plants are fed by intercepting drains (State affidavit to the NGT, 2026). The TBR 2017 bar the filling of ponds, jhoras and streams, regulate building within 15 m of a river bank and set a plinth of at least 60 cm, but set no design storm, release rate or storage method, and in the TTAADC area, about 68% of the State (as reported), they do not apply at all. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix; the closed outfall of the second source is the design case of Chapter 5, not an exception; and the breaches, flood plains and slides are answered by the siting, setback and floor-level rules of Chapters 2, 6 and 7, because no drain is sized to carry a river through a breach.
No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Tripura Building Rules 2017 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.