Draft v1.0 prepared by NEER. Not adopted by the Government of Arunachal Pradesh or any authority, local body or community, and has no legal force. About this draft

Annexes to Chapter 11Basin and City Stormwater Master Plans

These annexes support Chapter 11. They give a terms of reference template for a Basin Stormwater Master Plan (BSMP), the layout of the basin list and boundary layer, the layout and method for depth–damage curves, the standard for publishing BSMP data and models, and the annual implementation report form. Annexes 11B and 11C need data that are not yet available; they say so and give the rule to use in the meantime. The template and the form are a model and a draft form for consideration by a competent authority, and are not in force.


Annex 11A — BSMP terms of reference template

Supports Clauses 11.1 to 11.12 of Chapter 11.

Model text for consideration by a competent authority. Not in force. The Lead Authority adapts this template for each basin. Items in "[ ]" are for the Lead Authority to complete. Clause references are to this Manual, which the consultant shall follow in full.

11A.1 Background and purpose

  1. The [Lead Authority] intends to prepare a Basin Stormwater Master Plan for the [name] basin under Chapter 11 of the Arunachal Pradesh Stormwater Design Manual.
  2. The BSMP shall (Clause 11.1.2):
    • (a) map flood hazard for the basin under existing and future conditions;
    • (b) set the level of service for each part of the drainage system;
    • (c) identify, cost and rank the works, storage and land needed to reach that level of service;
    • (d) identify land to be reserved in the statutory land-use plan for regional storage, pond and tank restoration and major flow paths;
    • (e) set the basin inputs for site design: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4; and
    • (f) recommend catchments for notification as flood-sensitive.
  3. The BSMP may make the site criteria of Chapters 4 to 8 stricter for the basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6 (Clause 11.1.3).

11A.2 Client, partners and study area

  1. Client: [Lead Authority] (Clause 11.4.1).
  2. Partners: WRD, wherever the basin includes a river, canal or tank under its control, and [other local bodies, the Itanagar Planning Authority or Urban Affairs, APSDMA] (Clause 11.4.1).
  3. Study area: the whole of the [name] basin, draining to [outfall], as delineated under Clause 11.3, including the parts outside the client's limits (Clause 11.3.1). The provisional boundary is in [Annex 11B / attached map]. The consultant shall confirm it in Task 2.
  4. Links to other basins: [for example the receiving river, stream, nallah, pond or reservoir corridor]. Diversions between basins by canal, drain or surplus course shall be mapped and represented in the model (Clause 11.3.2).

11A.3 Team

  1. The study shall be led by an engineer empanelled as a Stormwater Design Professional with the basin modelling endorsement of Annex 10E (Clause 11.4.3).
  2. The team shall include at least: [a hydrologist; a hydraulic modeller; a coastal or tidal specialist where the basin has a tidal outfall; a GIS and survey lead; a planner; a cost engineer; a community engagement lead]. The client sets the minimum qualifications and experience of each.

11A.4 Tasks

Task 1 — Inception. Review existing studies, data and projects in the basin. Prepare a data inventory against Table 11.1, a gap list, a survey plan, a consultation plan, and the work programme. Deliver the inception report.

Task 2 — Data and surveys. Assemble, survey where missing, and quality-check every item of Table 11.1 (Clause 11.5.1):

  • (a) terrain: DEM from LiDAR or photogrammetry with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum, with the accuracy test reported;
  • (b) drain network: every public drain, culvert and outfall, with invert levels, sizes, condition and silt depth; private drains above 600 mm;
  • (c) waterbodies: every tank, pond, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels and encroachment, in the fields of Annex 7A;
  • (d) rivers and canals: cross-sections at no more than 200 m spacing and at every structure;
  • (e) outfalls, rivers, streams, nallahs, ponds and reservoirs: outfall invert levels, on a named datum, against a surveyed level of the receiving river at the outfall, with the CWC danger level and highest flood level for the Siang at Pasighat, the Noa-Dihing at Namsai and the Lohit at Tezu on CWC's datum once stated [TBC] and the Pasighat HFL marked as an outburst stage, surveyed flood marks for the Senki, the Pachin, the Dikrong and the Dibang, which have no CWC site in the towns, any local gauge kept as a separate series and any conflict between published values stated; for ungauged hill streams and nallahs, surveyed flood marks and the 1% AEP level with its sediment, debris and bulking; for outfalls on release reaches, the operator's levels, spillway and gate data and release records, and ponds at their surveyed spill levels; the glacial lakes, landslide dams, debris fans and landslide hazards above the basin; and flap gates, penstocks, debris racks, screens, silt traps, debris basins and any pumping stations on the outfalls, with their capacities and operating rules;
  • (f) rainfall and water levels: all available records (IMD, including the network reported by the Meteorological Centre Itanagar, whose automatic weather stations and rain gauges were not listed in any source found [TBC], and the IMD stations at Pasighat (42220), Tezu (01203), Ziro (42312, printed "Zero") and Hayuliang (01212, rain records 1971–1985); the daily gauge of NERIST at Doimukh (1988–2012); the State ordinary gauges used in the CWC Flood Estimation Report for subzone 2(a), which are not named on the pages read [TBC]; the CWC sites on the Siang, the Noa-Dihing, the Lohit, the Subansiri and the Ranganadi; the rain and reservoir records of NEEPCO and NHPC at the Pare, Ranganadi, Kameng and Lower Subansiri projects [TBC]; and any gauges or sensors kept by the Itanagar Municipal Corporation, the Pasighat Municipal Council, the Smart City companies, WRD and the Arunachal Pradesh State Disaster Management Authority (APSDMA) [TBC]), including the September 2018 (the Modirijo and Donyi Polo floods in Itanagar–Naharlagun on or about 14 September, with 3 dead and at least 4 missing in early reports and up to 7 dead in later ones, a conflict, the Senki View culvert and the Press Colony bridge washed away, as reported, and no rainfall value found), 23 June 2024 (Itanagar and Naharlagun, with 66 houses inundated, as reported, and 40 mm between 10:30 and 12:30 "As per IMD", as quoted from the secretary of the State's disaster management authority, who said that IMD "confirmed there was no incident of cloudburst"), July 2024 (the reported Itanagar "cloudburst" of about 28 July, with NH-415 submerged and homes near Energy Park and Bank Tinali flooded, as reported, its date in conflict between dateline and publication and kept apart from 23 June, and no rainfall value found), late May to 7 June 2025 (the statewide floods and landslides, with 12 dead by one count and 9 to 11 by others, a conflict, and a peak release of 1,310 m³/s from the Pare dam on 31 May, all as reported, with only press values of rain), 24 June 2025 or 2026 (the Poosa / NEEPCO colony flood at Yazali, dated 2026 by one report and 2025 by another, a conflict, with 73 mm in 24 hours, mostly in 3 hours, as reported) and the 2017 monsoon (the capital's floods that damaged the protection walls of nallahs and closed NH-415, recorded in the Master Plan of Itanagar Capital Region-2031, with no rainfall value found) events;
  • (g) flood evidence: surveyed flood marks and mapped extents of past events, including public reports, photographs and residents' records;
  • (h) land use: existing land use and imperviousness; future land use from the statutory master plan;
  • (i) soils and groundwater: HSG map (Annex 3A or Clause 3.7.2), seasonal high groundwater, aquifer and recharge zones; and
  • (j) sewer interaction: known cross-connections, dry-weather flow in drains, solid-waste hotspots.

Confirm the basin boundary and the inter-basin diversions (Clause 11.3.2). Deliver the data report and the data in the formats of Annex 11D.

Task 3 — Model build. Build a coupled 1D–2D hydraulic model of the minor system, the major (overland) system, rivers, canals and tanks, and the outfalls (Clause 11.7.1; Figure 11.2). Use the methods of Chapter 3 and the tidal and river boundaries of Chapter 5. Run the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs, with areal reduction under Clause 2.7.3 (Clause 11.7.2). Where the basin has tank cascades, run continuous simulation under Clause 3.13 with the full IMD gridded daily record where available, and at least 30 years, disaggregated by the temporal patterns of Annex 2D. The two-step approach of Clause 3.13.5 may be used: starting tank levels and antecedent conditions from the continuous run are passed to the design-storm runs (Clause 11.7.3).

Task 4 — Calibration and validation. Calibrate and validate the model under Clause 3.15, using at least two of the September 2018 (the Modirijo and Donyi Polo floods in Itanagar–Naharlagun on or about 14 September, with 3 dead and at least 4 missing in early reports and up to 7 dead in later ones, a conflict, the Senki View culvert and the Press Colony bridge washed away, as reported, and no rainfall value found), 23 June 2024 (Itanagar and Naharlagun, with 66 houses inundated, as reported, and 40 mm between 10:30 and 12:30 "As per IMD", as quoted from the secretary of the State's disaster management authority, who said that IMD "confirmed there was no incident of cloudburst"), July 2024 (the reported Itanagar "cloudburst" of about 28 July, with NH-415 submerged and homes near Energy Park and Bank Tinali flooded, as reported, its date in conflict between dateline and publication and kept apart from 23 June, and no rainfall value found), late May to 7 June 2025 (the statewide floods and landslides, with 12 dead by one count and 9 to 11 by others, a conflict, and a peak release of 1,310 m³/s from the Pare dam on 31 May, all as reported, with only press values of rain), 24 June 2025 or 2026 (the Poosa / NEEPCO colony flood at Yazali, dated 2026 by one report and 2025 by another, a conflict, with 73 mm in 24 hours, mostly in 3 hours, as reported) and the 2017 monsoon (the capital's floods that damaged the protection walls of nallahs and closed NH-415, recorded in the Master Plan of Itanagar Capital Region-2031, with no rainfall value found) events where data exist (Clause 11.7.5). Report the performance measures of Clause 3.15.4 and the reasonableness check of Clause 3.15.6.

Task 5 — Scenarios and hazard maps. Model the scenarios of Clause 11.7.4: (a) existing; (b) future, uncontrolled; (c) future, controlled; (d) future, with plan; and (e) climate, applied to (a) and (d). Produce flood hazard maps of extent, depth, velocity and hazard class (H1–H6, Chapter 6) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan (Clause 11.8.4(a)).

Task 6 — Level-of-service assessment. Compare scenarios (a), (c) and (d) with the levels of service of Table 11.2 and any stricter levels the client adopts (Clause 11.6.1). Map every shortfall.

Task 7 — Options. Develop options in the order of Clause 11.8.1: protect and restore storage; regional retention and detention, sited by modelling; conveyance; outfall works; property-level protection; non-structural measures. Assess each option for the criteria of Clause 11.8.2: reduction in flood risk (buildings and people flooded, and expected annual damage using Annex 11C); capital and 30-year maintenance cost; land required; effect on the springs and streams that supply the hill towns and villages, which in Papum Pare discharge 0.43–2 litres a second before the monsoon and of which "most of the springs become dry during dry season" (CGWB), and their recharge areas above the intakes, which this Manual keeps free of paving and of infiltrated road runoff, the stability of hill slopes on Siwalik shale, colluvium, slope debris and fill, where water put into the ground raises the pore pressure, recharge on the tested sandy terrace and valley-fill soils of the Naharlagun–Nirjuli–Doimukh valley and on the coarse bhabar fan heads, the only ground where it is allowed, and not within 30 m of a dug well or spring used for drinking water (Clause 4.11, recharge rule), although groundwater is not short (stage of extraction 0.39%, CGWB 2024, as summarised), the shallow water table of the valley floors and flood plains, and the quality of the groundwater, which carries iron (0.14–0.78 mg/L in the springs of Papum Pare, CGWB), and of the streams, nallahs, ponds and reservoirs that the runoff reaches; effect on downstream basins and the receiving river, stream, nallah, pond or reservoir; and who benefits.

Task 8 — Basin inputs for site design. Where scenario (c) does not meet the level of service, propose basin release rates (m³/s/ha) by AEP and sub-catchment (Clause 11.8.3). Recommend catchments for notification as flood-sensitive, with the evidence of Clause 4.5.4.1. Identify regional facility sites, with storage volumes, land needs and the sites they serve, and compute the fee-in-lieu unit rate, including land, construction and 10 years of maintenance (Clauses 4.13.3, 11.8.4(c), (d)).

Task 9 — Capital Improvement Programme. Rank the works by risk reduction per rupee, with cost, phasing and responsible agency (Clause 11.8.4(e)).

Task 10 — Maintenance and monitoring. Prepare the pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Clause 11.8.4(f); Chapters 7 and 10). Specify monitoring needs: new rain gauges, level sensors and flood-mark survey points (Clause 11.8.4(g); Clause 10.16.1).

Task 11 — Land-use integration. Prepare the material for the statutory land-use plan required by Clause 11.9.1: sites to be reserved; the 1% AEP hazard map with the Chapter 7 setbacks; land in hazard classes H5–H6 in the 1% AEP event; and open space locations that can form part of flow paths or regional storage.

Task 12 — Consultation. Publish the draft BSMP for public comment for at least 60 days, with public meetings in each affected local body (Clause 11.10.1). Keep a log of comments and responses.

Task 13 — Final BSMP and publication. Revise the BSMP after consultation. Prepare the package for approval by the State Stormwater Technical Committee, including the model for review (Clause 11.11.1). Publish the data, models, maps and CIP under Annex 11D (Clause 11.10.2).

11A.5 Deliverables

Table 11A.1 — Deliverables

No. Deliverable Task Due (months from start)
D1 Inception report, data inventory and survey plan 1 [ ]
D2 Data report and data sets (Annex 11D) 2 [ ]
D3 Model build report and model files 3 [ ]
D4 Calibration and validation report 4 [ ]
D5 Scenario results, hazard maps and level-of-service assessment 5, 6 [ ]
D6 Options report, with basin inputs for site design 7, 8 [ ]
D7 Draft BSMP with draft CIP, for consultation 9–12 [ ]
D8 Final BSMP, consultation log, approval package and open-data release 13 [ ]

11A.6 Ownership and publication

All data, models, maps and reports produced under these terms are owned by the Lead Authority and shall be published under Annex 11D. The consultant shall not use any software licence, data licence or format that prevents publication, or that prevents a third party from re-running the model with the stated software version.


Annex 11B — Basin lists and boundaries for Tier A bodies

Supports Clauses 11.3 and 11.4 of Chapter 11.

To be prepared. This annex will contain the list of basins for every Tier A body, with a GIS layer of basin boundaries delineated under Clause 11.3.2. It needs the list of Tier A bodies (Annex 1A), a DEM of the accuracy of Clause 11.5.1, flown again over the valley floor of Naharlagun, Nirjuli and Doimukh, the fans of Pasighat, Tezu, Namsai and Roing, the release reaches and the slide-prone slopes after any large flood, landslide or outburst, the drain network of every drain-owning body (the Itanagar Municipal Corporation, the Pasighat Municipal Council and the other local bodies, the Department of Urban Affairs and the Smart City companies for the drains they have built and not handed over, PWD and PWD (Highways), and the communities for the drains on their land), a drain register giving every reach its owner, its land status (community, clan, individual, municipal or Government land), whether it carries sewage or septic overflow, and its outfall, the rivers and anti-erosion works of WRD, the reservoirs and release reaches with the levels, spillway, gates and release records of NEEPCO and NHPC on a stated datum, the CWC sites with their datum, the ponds with their spill levels, the springs and their recharge areas above the town intakes, the glacial lakes that NDMA lists, and the landslide, debris, flood and outburst hazards mapped by the State's disaster management authority and the District Disaster Management Authorities (other likely sources: Survey of India, CWC, CGWB, NIH, the master plan's maps and the Forest Department's wetland truthing). No basin map of any Arunachal Pradesh town was found. Until the annex is published, the basins of the capital (the Senki; the Pachin; the Dikrong with Papu Nallah; the NH-415 corridor; Modirijo and Donyi Polo), of Pasighat on the Siang, Tezu on the Lohit, Namsai and Miao on the Noa-Dihing, Roing on the Dibang, Yazali on the Ranganadi, and the glacial-lake and outburst reaches of Tawang and Dibang Valley, named in Clause 11.3.3, are at least those named there; other Tier A bodies define their basins in their first BSMP (Clause 11.3.3); on the hazard-first sites of Clause 2.3.6(i) the hazard screening of Clause 11.3.3 comes first; and the interim arrangements of Clause 11.12 apply in every basin without an approved BSMP.

Table 11B.1 — Basins named in Clause 11.3.3 (provisional)

Tier A body or area Basin Note from Chapter 11
Itanagar (Itanagar Municipal Corporation, with Urban Affairs and the Itanagar Planning Authority; communities for their land, if adopted) Catchment of the Senki through Itanagar to the Pachin Senki View culvert (2018) and the lift intake shown; reaches carrying sewage and reaches on community, clan or private land marked; surveyed flood marks and 1% AEP level with debris and bulking as boundary
Itanagar and Naharlagun (as above) Catchment of the Pachin to the Dikrong near Nirjuli Palaeochannels and swampy land mapped; Dikrong level at the confluence as boundary
Naharlagun, Nirjuli and Doimukh (as above) Catchments draining to the Dikrong below the Pare dam, with Papu Nallah Outfall-closed cases under the interim design tailwater (Clause 5.8.5(a)); river low and river high with the Pare release both modelled; flood marks of 1999–2025
NH-415, Itanagar to Naharlagun Catchments crossing NH-415 Energy Park, Bank Tinali, Niti Vihar, Abo Tani Colony and earth-cutting sites mapped
Itanagar (as above) Modirijo and Donyi Polo catchments Press Colony bridge and the NH-415 dumping area mapped; hazard screening first
Pasighat (Pasighat Municipal Council, with Urban Affairs; Tier B, flood-sensitive) Catchments draining to the Siang and its side channels CWC danger level 153.96 m as design and HFL 157.54 m as check (Clause 5.8.5(c)); Yigong 2000 as the check event; erosion and fan channels mapped
Tezu Catchments draining to the Lohit CWC HFL 192.14 m as boundary until a danger level is given [TBC]
Namsai and Miao Catchments draining to the Noa-Dihing CWC levels at Namsai and Miao as boundaries
Roing Catchments draining to the Dibang No CWC site; 1% AEP model and surveyed flood marks as boundary
Yazali Side streams on the Ranganadi reach at Yazali Side streams as hill streams (Clause 5.8.5(b)); Ranganadi release as boundary (Clause 5.8.5(d)); hazard screening first
Tawang and Dibang Valley Town catchments below NDMA's high-risk glacial lakes Outburst screening first (Clause 2.3.6(i))
Other local bodies (Tier B) To be defined in the first BSMP Clause 11.3.3

Table 11B.2 — Attributes of the basin boundary layer (layout)

Field Type Content
BASIN_ID Text Basin identifier
NAME_EN, NAME_LOC Text Basin name in English and the local language
TIER_A Text Tier A body or bodies in the basin
OUTFALL Text Outfall to the sea, river or major waterbody (Clause 11.2)
AREA_KM2 Real Basin area, km²
LEAD_AUTH Text Lead Authority (Clause 11.4.1)
PARTNERS Text Partners, including WRD where it applies
LINKS Text Diversions to and from other basins (Clause 11.3.2)
BSMP_STAT Text None / in preparation / draft published / approved
BSMP_DATE Date Date of approval of the current BSMP
REVIEW_DUE Date Date of the next review (Clause 11.11.2)

Annex 11C — Depth–damage curves for Arunachal Pradesh building types

Supports Clause 11.8.2 of Chapter 11.

To be prepared. This annex will contain depth–damage curves for the main building types of Arunachal Pradesh cities, for structure and contents, for use in computing expected annual damage under Clause 11.8.2. It needs a building-type classification and building stock data (Census housing tables, property-tax records, Lead Authority GIS), damage surveys and claims from the September 2018 (the Modirijo and Donyi Polo floods in Itanagar–Naharlagun on or about 14 September, with 3 dead and at least 4 missing in early reports and up to 7 dead in later ones, a conflict, the Senki View culvert and the Press Colony bridge washed away, as reported, and no rainfall value found), 23 June 2024 (Itanagar and Naharlagun, with 66 houses inundated, as reported, and 40 mm between 10:30 and 12:30 "As per IMD", as quoted from the secretary of the State's disaster management authority, who said that IMD "confirmed there was no incident of cloudburst"), July 2024 (the reported Itanagar "cloudburst" of about 28 July, with NH-415 submerged and homes near Energy Park and Bank Tinali flooded, as reported, its date in conflict between dateline and publication and kept apart from 23 June, and no rainfall value found), late May to 7 June 2025 (the statewide floods and landslides, with 12 dead by one count and 9 to 11 by others, a conflict, and a peak release of 1,310 m³/s from the Pare dam on 31 May, all as reported, with only press values of rain), 24 June 2025 or 2026 (the Poosa / NEEPCO colony flood at Yazali, dated 2026 by one report and 2025 by another, a conflict, with 73 mm in 24 hours, mostly in 3 hours, as reported) and the 2017 monsoon (the capital's floods that damaged the protection walls of nallahs and closed NH-415, recorded in the Master Plan of Itanagar Capital Region-2031, with no rainfall value found) floods (land revenue offices of the Deputy Commissioners and APSDMA damage assessments, insurers), and replacement costs (Public Works Department schedules of rates). Until it is published, each BSMP shall state the depth–damage relations it uses and their source, and shall report the reduction in buildings and people flooded for every option (Clause 11.8.2), which does not depend on the curves.

Table 11C.1 — Depth–damage curve (layout, one table per building type)

Depth of water above floor level (m) 0 0.25 0.5 1.0 1.5 2.0 3.0
Structure damage (% of replacement cost) ______ ______ ______ ______ ______ ______ ______
Contents damage (% of contents value) ______ ______ ______ ______ ______ ______ ______
Building type, source and year of costs ______

11C.1 Use in option assessment

Expected annual damage (EAD) is computed for each scenario from the damages at the modelled AEPs. With damages D_1, D_2, … at annual exceedance probabilities P_1 > P_2 > …, using at least the 50%, 10%, 1% and 0.2% AEP results of Clause 11.7.2:

EAD ≈ Σ ½ × (D_i + D_(i+1)) × (P_i − P_(i+1))

The reduction in EAD between scenario (c) and scenario (d), or between options, is the risk-reduction benefit used to rank works per rupee (Clause 11.8.4(e)). The BSMP shall state how damages beyond the 0.2% AEP and below the 50% AEP were treated.


Annex 11D — BSMP data and model publication standard

Supports Clauses 11.5.1 and 11.10 of Chapter 11, and Clause 10.17 of Chapter 10.

11D.1 What is published, and when

Table 11D.1 — Items to be published

Item Format At draft (Clause 11.10.1) At approval (Clause 11.10.2)
BSMP report, with the level-of-service assessment and options Searchable PDF Yes Yes, final
Flood hazard maps: extent, depth, velocity, hazard class, for each AEP and scenario of Clause 11.8.4(a) GeoTIFF rasters; extents also as GeoPackage polygons Yes Yes
Capital Improvement Programme CSV and PDF Draft Yes
Basin release rates, recommended flood-sensitive catchments, regional facility sites, fee-in-lieu unit rate GeoPackage and CSV Yes Yes
Data of Table 11.1 (terrain, drains, waterbodies, cross-sections, river, nallah, pond and reservoir levels, outburst, slope and debris hazards and outfall structures, rainfall and levels, flood evidence, land use, soils and groundwater, sewer interaction) GeoTIFF (terrain); GeoPackage (features); CSV (tables and time series) Summary Yes, except security-sensitive asset details
Model files: native, runnable, with all boundary-condition, rainfall and control files, the software name and version, and a run log Native format, zipped No Yes
Calibration and validation report Searchable PDF Yes Yes
Consultation log of comments and responses PDF or CSV — Yes

11D.2 Formats and references

  • (a) Raster data shall be GeoTIFF, preferably cloud-optimised, with the cell size stated. Vector data shall be GeoPackage. Tables and time series shall be CSV in UTF-8, with a header row and units in the column names.
  • (b) Horizontal and vertical references shall be as in Annex 10B.1(b) and (c). The vertical datum and its relationship to the Chapter 5 river datums of the CWC sites on the Siang at Pasighat, the Noa-Dihing at Namsai and the Lohit at Tezu (levels as transcribed by SANDRP, on a datum not stated [TBC]), of any gauge or staff gauge on the Senki, the Pachin and the Dikrong in the capital and on the Dibang at Roing (none with a published datum was found [TBC]), of the reservoir and release levels of the Pare, Ranganadi, Kameng and Lower Subansiri projects (not found on a named datum [TBC]), and of the flood marks surveyed on ungauged streams, nallahs and ponds shall be stated in every data set that carries levels.
  • (c) Times shall be in Indian Standard Time, written as ISO 8601 (yyyy-mm-ddThh:mm+05:30). Units shall be SI.
  • (d) Hazard map files shall be named <basin>_<scenario>_<AEP>_<variable>.tif, where scenario is a to e of Clause 11.7.4, AEP is written as 50, 10, 1 or 0p2, and variable is depth, velocity, hazard or extent; for example senki_d_1_depth.tif.
  • (e) Waterbody data shall use the fields of Annex 7A. Facility and outfall data shall use the fields of Annex 10B.

11D.3 Metadata

Every published data set shall carry: title; description; Lead Authority; source and method; date of capture; accuracy (for the DEM, the measured vertical RMSE); horizontal and vertical reference; scenario and AEP, where relevant; BSMP version; licence; and a contact.

11D.4 Withholding and personal data

  • (a) Security-sensitive details of critical assets may be withheld, with the reason recorded and published (Clauses 10.17.3, 11.10.2). The flood hazard maps and the model shall still be published; only the sensitive attributes are removed.
  • (b) Personal data shall not be published (Clause 10.17.3). Flood evidence collected from residents shall be published without names or contact details unless the person consents.

11D.5 Licence, viewer and versions

  • (a) Published data and models shall be released under the Government Open Data Licence – India or an equivalent open licence (Clause 10.17.4).
  • (b) The hazard maps, regional facility sites and CIP shall also be shown on a public map viewer (Clause 11.10.2).
  • (c) Each approved BSMP shall carry a version number and date. Superseded versions shall stay available, marked as superseded, so that designs approved under them can be checked.
  • (d) The published model package shall allow a third party with the stated software version to reproduce the published results. Designers may use its boundary conditions for site designs in the basin (Clause 11.10, Commentary).

Form 11-1 — Annual implementation report

Supports Clause 11.11.3 of Chapter 11, with Clauses 4.5.6.3 and 4.13.4 of Chapter 4.

Draft form — Arunachal Pradesh Stormwater Design Manual, Draft v1.0. Published by the Lead Authority for each basin with an approved BSMP before each monsoon season, by 31 March (Clause 11.11.3).

Table 11F.1 — Form 11-1, Section A: Basin and plan

No. Field Entry
A1 Basin; Lead Authority; partners ______
A2 BSMP version and date of approval ______
A3 Reporting year (1 April to 31 March) ______
A4 Date of publication (by 31 March) and web address ______

Table 11F.2 — Form 11-1, Section B: CIP progress

CIP rank Work Agency Cost in CIP (₹) Spent this year (₹) Spent to date (₹) Status Expected completion
______ ______ ______ ______ ______ ______ ______ ______
______ ______ ______ ______ ______ ______ ______ ______

Table 11F.3 — Form 11-1, Section C: Fee-in-lieu ledger (Clauses 4.5.6.3(c) and 4.13.4)

Regional facility or tank Volume credited to sites (m³) Volume delivered (m³) Fees received (₹) Fees spent (₹) Fees held, with year received
______ ______ ______ ______ ______ ______
Basin total: volume owed and delivered ______ ______ ______ ______ ______

Table 11F.4 — Form 11-1, Section D: Maintenance completed (Clause 11.8.4(f))

No. Item Planned Done Date completed
D1 Desilting of drains and canals (length, km; volume, m³) ______ ______ ______
D2 Tank and pond desilting and restoration (tanks, number; storage restored, m³) ______ ______ ______
D3 Gate tests (number of gates) ______ ______ ______
D4 Pump station duty tests (number of stations) ______ ______ ______
D5 Tank operating rules reviewed with the custodian (number) ______ ______ ______
D6 Monitoring added: rain gauges, level sensors, flood-mark points (Clause 11.8.4(g)) ______ ______ ______

Table 11F.5 — Form 11-1, Section E: Flooding against the levels of service

Event (dates) Rainfall compared with the design depths (Clause 10.16.2(a)) Level-of-service element (Table 11.2) Location Met (yes / no) Event report reference (Clause 10.16.2)
______ ______ ______ ______ ______ ______

Table 11F.6 — Form 11-1, Section F: Review triggers and sign-off

No. Field Entry
F1 Event exceeding the 1% AEP design depth in the basin this year (yes / no). If yes, review due within 2 years (Clause 11.11.2) ______
F2 Statutory land-use plan revised this year (yes / no) (Clause 11.11.2) ______
F3 Next 10-year review due (date) ______
F4 Officer of the Lead Authority: name, designation, signature, date ______