Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Arunachal Pradesh the failure is one of missing criteria, not of a missing building rule, and of land that no permission reaches. No document stating a design return period, intensity or runoff coefficient for the storm drains of any town was found. The building rule is the Arunachal Pradesh Building Bye-Laws, 2019 (Department of Town Planning and ULBs, Government of Arunachal Pradesh), now under the Department of Urban Affairs (Town Planning wing); their notification number, date and gazette reference are not in the copy read, whose "Gazette Notification" page is blank [TBC]. They "extent to whole of Arunachal Pradesh" (2.1), apply for five years and stay in force until reviewed bye-laws are notified (2.2), and are named as the State's building bye-laws by section 2(c) of the Arunachal Pradesh Fire and Emergency Services Act, 2026 (Act No. 12 of 2026); no amendment was found, and whether the review due from 2024 has begun is not known [TBC]. Their "Authority" is the Director/Chief Town Planner of Town Planning and Urban Local Bodies "till an executing authority is notified" (definition 12), and the "Act" under which they work is the Arunachal Pradesh Municipal Act, 2007 (Act No. 4 of 2008) and the Arunachal Pradesh Urban and Country Planning Act, 2007 (Act No. 3 of 2008). An "Arunachal Pradesh Building Bye-Law 2010" is listed as notified on the Town Planning portal (as summarised) but was not read and is not cited here as the current rule, and the hill-site clause of the 2009 final draft of the bye-laws, which asked for "location of landslide prone areas" and the "diversion of the natural flow of water coming from uphill side" on the site plan, is not in the 2019 text, although the Itanagar master plan's report reproduces it. The Online Building Permission System, launched on 30 July 2025, was "customised" to the bye-laws and processes all permits online (as reported), so the drainage checklist of Form 10-1 would have to be built into it. The bye-laws already ask for much of what a drainage submittal needs, and this chapter hooks into them. The site plan shows "Any existing physical features such as well, drains, trees" (2.10.1(j)), the "Distance from Nallah/Stream as per the notified rules/norms" and the "Distance from Disaster Prone Area as per norms set by Disaster Management Authority" (2.10.1(e) and (f)), and no such rules or norms were found: the drainage sheet of Stage 2 goes with the site plan, and the corridor of Chapter 7, which this Manual offers as the norms that 2.10.1(e) refers to and which the State could notify, is drawn on it. A "certificate of supervision and execution of drainage/sanitary works" in Appendix 'A-3' accompanies the notice (2.10.10): the as-built certificate of Stage 4 (Form 10-5) goes with it. The Authority grants planning permission within 30 days of an application (2.14.1(a)) and, for residential schemes, a completion is "deemed to approved by the Authority for occupation" if nothing is communicated within 30 days of the notice of completion (2.17), so the drainage review must fit inside those periods: the 5 working days of the completeness check and the 15 of the first review (Clause 10.7) come to about four calendar weeks, which fit only if the drainage report is complete and lodged with the building application, and the Stage 4 inspection must be made inside the 30 days of 2.17 (this Manual's reading of Clause 10.7.6). Earth cutting needs its own permission, valid for six months, with written notice before work starts (4.39(1)–(2)); a cut may not exceed 3 m, a clear 2.5 m is kept from the property line on the upper terrace, the owner must clear "soil/debris from site or drain", a retaining or breast wall follows "immediately", and no permission is given where "the average slope of the topography is more than 30%" (4.39(4), (5), (8), (11) and (14)): the slope-drainage conditions of this Manual (catch drains, toe drains, silt traps and no infiltration above a cut, Clause 4.11, hill rule) are attached to that permission. Rainwater harvesting is required on plots of 100 m² and more (9.1), and recharge "should be made mandatory" on plots of 500 m² and more (9.7), its structures are inspected before the completion certificate by the Authority's Rainwater Harvesting Cell (9.8), and a levy may be imposed for failing to provide or maintain them (Annexure E, 1.7): the storage of Clause 4.11 is shown on the same plans and inspected at the same visit. The Building Permission Committee recommends the cancellation of a land allotment for unapproved cutting (4.39(14)). The bye-laws do register professionals: "Registration of Professionals" (6.3.6) refers to Appendix 'E', "Registration: Qualifications and Competence of Professionals", and every professional's qualifications are as given there (2.14.5), so the "APBBL 2019 registration" of Clause 10.6.1's commentary and the "APBBL 2019 registration number" of Form 10-3 read as written. A layout is approved under the Urban and Country Planning Act (2.10.3), whose Local Planning Authority, the Itanagar Planning Authority in the Itanagar Capital Region, grants permission for development (s.29), and Ordinance No. 5 of 2025 adds Town Planning Schemes whose contents include "drainage, inclusive of sewerage, surface or sub-soil drainage and sewage disposal" and "the filling-up or reclamation of low-lying, swampy or unhealthy area"; an amending Bill was reported passed on 9 March 2026 (as reported), and its Act number and final text were not found [TBC]. In the Pasighat municipal area a building is sanctioned by the Municipal Building Committee (Arunachal Pradesh Municipal Act, 2007, ss.340–343), and in the area of the Itanagar Municipal Corporation (IMC) a private drain is connected to a drain of the Corporation on application, with no "foul water into a drain provided for surface water" where separate drains exist (Arunachal Pradesh Municipal Corporation Act, 2019, s.203). Land is the other hook. The State has no Sixth Schedule area, and Article 371H gives the Governor a special responsibility for law and order without protecting customary law or land (as quoted); the Arunachal Pradesh (Land Settlement and Records) Act, 2000 (Act No. 10 of 2000) incorporates "customary rights on the land", defines a "community" to include "a clan, sub-clan, kindred", and vests the beds of rivers, streams, nallahs, lakes and tanks in the Government only where they "are not the property of any person or community" (s.9(1)); individual titles came with an amendment of 2018 (s.1A, as reported), and much land near the towns is held by communities, clans and individuals. So the land that a drain, corridor, storage or outfall needs is secured by agreement with the owners or the community, by donation, by purchase, or by reservation in a master plan, layout or Town Planning Scheme, and never taken by this Manual; where the State decides that land must be obtained compulsorily, the Municipal Act routes it through the "Land of Acquisition Act, 1894" (as printed) and allows "other methods of land assembly including the use of transferable development rights" (s.104), and this Manual states that route and does not invoke it. On community or clan land outside any permission this chapter is guidance for the owners or the community. One field of the forms reads differently here: the "survey numbers, village, circle" of Form 10-6, because much customary land has no survey number in any State record, so the village, the circle and the description of the land in the owner's or community's record, or the title issued under s.1A where one exists, are entered (this Manual's reading). Every stormwater item in this chapter is therefore written so that the registered professional can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the site plan of 2.10.1, the earth-cutting permission of 4.39, the supervision certificate of 2.10.10 and the rainwater harvesting plans of Chapter 9, within the 30 days of 2.14.1 and 2.17, and at completion. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Arunachal Pradesh Building Bye-Laws, 2019 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the APBBL 2019 steps an Arunachal Pradesh applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (46N for a project area west of 96° E, which is most of the State, including Itanagar, Pasighat, Roing, Namsai and Anini, and 47N for a project area wholly east of 96° E, which includes Tezu (about 96.16° E), Miao, Wakro, Hayuliang (about 96.54° E) and Anjaw district; a project area uses one zone, and one that crosses 96° E uses the zone that holds most of it and states the conversion (set by this Manual); the State's eastern limit is given as about 96°30′ E in some sources and 97°30′ E in others (as reported), a conflict to be confirmed against Survey of India maps [TBC], and Namsai, Roing and Anini lie within about 15 km of 96° E (this Manual's reading)), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC sites on the Siang at Pasighat, the Noa-Dihing at Namsai and the Lohit at Tezu (levels as transcribed by SANDRP, on a datum not stated [TBC]), of any gauge or staff gauge on the Senki, the Pachin and the Dikrong in the capital and on the Dibang at Roing (none with a published datum was found [TBC]), of the reservoir and release levels of the Pare, Ranganadi, Kameng and Lower Subansiri projects (not found on a named datum [TBC]), and of the flood marks surveyed on ungauged streams, nallahs and ponds used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Arunachal Pradesh has no design return period, design storm, runoff coefficient, time-of-concentration rule or drain standard for the storm drains of any town, and none was found in any document of the Department of Urban Affairs, the Itanagar Municipal Corporation, the Pasighat Municipal Council, the Smart City companies, PWD or the Water Resources Department. The APBBL 2019 refer to Part 9 of the National Building Code (2005) for plumbing and drainage (4.19.1.3 and 4.33.1); road drains follow the practice of the Indian Roads Congress, which this Manual did not research. The Master Plan of Itanagar Capital Region-2031 proposes a "new drainage network … in the Itanagar and Naharlagun regions taking into consideration of the topography of the region and flow gradient" (Maps 28–30), with no design storm, return period or runoff coefficient; the expression of interest of 31 October 2017 for a "GIS based Integrated Drainage Master Plan and DPR for Itanagar Capital City" (65 km², horizon year 2038) states no return period; a GIS-based drainage plan for the capital prepared by En-Geo Consultancy and Research Centre was reviewed by the Chief Minister in June 2021, the foundation stone of a storm-water drainage and seepage-management project for Itanagar was laid in June 2018, and a SWMM 5.2 study of Itanagar's C-Sector has been posted as a preprint (all as reported or as summarised), and the design basis of none of them was seen. The State Action Plan on Climate Change (draft, 2011) budgets "Storm water draining in twenty six urban settlements" at Rs 15,000.0 million without criteria. The rainfall studies do not supply a design storm either. No intensity–duration–frequency relation with constants was found for any Arunachal Pradesh station; IMD's national study (Das et al., 2022) has no Arunachal Pradesh panel; IMD's Extremes lists Pasighat, Tezu, Ziro and Hayuliang and no gauge in the capital, and its Pasighat record of 652.2 mm on 5 October 1988 is 1.37 times the station's next day and is to be confirmed by IMD [TBC]; NERIST's daily gauge at Doimukh (1988–2012) gives 210.39 mm in a day at 25 years (Dabral et al., 2016), about one contour above Plate 8 of the CWC Flood Estimation Report for subzone 2(a) at Itanagar; and the 2(a) plates draw their isopluvials only along the foothills, so that every hill and high-range town lies inside the subzone but beyond its last contour. The State's design values are therefore those of Chapter 2: the capital-region table from the Doimukh gauge in sub-area AR-A (Clause 2.3.6(c)(ii)), the 2(a) or 2(b) plates, the higher where both draw a contour, with floors, in AR-A1, AR-B, AR-C and AR-C1 (Clause 2.3.6(c)(i)), the floors of Clause 2.3.6(c)(iii) in the middle hills and high ranges of AR-D and AR-E, the Pasighat and Tezu records as floors within 25 km of their gauges (Clause 2.3.6(h)), and site-specific values with an outburst screening in snow-fed and glaciated catchments (Clause 2.3.6(i)); NIH-DHAARA is reported for comparison only; and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). An Arunachal Pradesh calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or Urban Affairs:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by Urban Affairs and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the APBBL 2019 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the Urban Affairs list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the approval of the Water Resources Department (WRD) for a work in or on a river, or for an outfall to a river or an anti-erosion work in its charge, among them the Dikrong, the Siang, the Lohit and the Noa-Dihing, the permission of the Itanagar Municipal Corporation (IMC) to connect a drain to a drain of the Corporation (Arunachal Pradesh Municipal Corporation Act, 2019, s.203) or the consent of the Pasighat Municipal Council for a drain vested in it (Arunachal Pradesh Municipal Act, 2007, ss.102 and 196), the agreement of the owner, the community or the clan for a drain, corridor, storage or outfall on its land, the consent of PWD or PWD (Highways) for a discharge to a side drain, catch-water drain or culvert of one of their roads, NH-415 among them, the consent of the Arunachal Pradesh State Pollution Control Board (APSPCB) for a discharge that carries effluent, and the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example the Department of Urban Affairs or a Smart City company for a drain it has built and not yet handed over to the ULB), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 March each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Arunachal Pradesh because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 March date is set by this Manual to fall before the monsoon season (April–October), when most Arunachal Pradesh extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Arunachal Pradesh has no dated State or municipal order fixing pre-monsoon desilting, and none was found for the capital; the Department of Disaster Management's daily situation reports run through the season (as reported). The Master Plan of Itanagar Capital Region-2031 finds that "Regular cleaning of drains is not taking place and hence heavy silting happens" and that the drains are "chocked with the solid wastes", and an inspection of the Bage Tinali–Naharlagun road found its drains clogged by earth-cutting debris and recommended de-silting "upto the Dikrong river" (as reported). The drains are run by many hands, and no notification divides them (this Manual's reading): the Itanagar Municipal Corporation for the public drains, sewers, culverts and watercourses in or under its streets and the public streams and springs vested in it (Arunachal Pradesh Municipal Corporation Act, 2019, s.200, with the obligatory "maintenance and cleaning of drains and drainage works" of s.60(a)); the Pasighat Municipal Council for the drains vested in it (Arunachal Pradesh Municipal Act, 2007, ss.102, 194 and 196); the Department of Urban Affairs, a works department with a Chief Engineer and 28 divisions, and the Itanagar and Pasighat Smart City companies for the storm drains, sewerage and septage works they build, until they hand them over; PWD and PWD (Highways) for the drains and culverts of State roads and of NH-415, the spine from Itanagar to Naharlagun (as reported); WRD for the rivers and anti-erosion works, among them the Siang schemes at Mebo (as reported); PHED for water supply, which this Manual did not research [TBC]; and, on community or clan land outside a ULB, the community itself, with no statutory owner. The Pasighat Smart City company's "Storm Water Drainage Project" was criticised by the local Member of Parliament for "improperly constructed drainage systems" (as reported). The septage plant at Chimpu, reported as 100 KLD in one account and "1 MLD" in another (a conflict), and the Naharlagun sewage treatment plant, still under construction in 2025 and possibly to be converted into a septage plant (minutes of 11 April 2025 in the State's affidavit to the National Green Tribunal), need their own maintenance, and their screens trap the same garbage as the storm drains. The large gated structures are run by rules made for another purpose: NEEPCO operates the Pare, Ranganadi and Kameng projects and NHPC the Lower Subansiri project for power, NEEPCO issues monsoon advisories on releases from the Pare dam (as reported), and no release protocol or warning threshold was found for any of them [TBC]. No operating rule for any gate or pumping station in an Arunachal Pradesh town, linking it to a river level, a dam release or a rainfall warning, was found in the public domain. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 March) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Arunachal Pradesh, the pre-monsoon inspection of flap gates, penstocks, non-return valves, debris racks, screens, silt traps, debris basins, culvert inlets and any pumped facility, including the gates, where any exist, on the outfalls of the nallahs and drains of Naharlagun, Nirjuli and Doimukh to the Dikrong, on the outfalls of the town drains of Pasighat, Tezu, Namsai and Roing to the Siang, the Lohit, the Noa-Dihing and the Dibang, and on outfalls to a reservoir or its release reach, with the desilting of every drain, nallah and channel, the clearance of inlets, culverts, racks, silt traps and slide debris, and the pump duty and gate seal tests, shall be completed by 31 March, with earthworks and cut slopes stabilised and their retaining or breast walls built (APBBL 2019, 4.39(11)) by the same date; gates, flap gates and any pumped facilities, with their standby power, shall be certified ready on the same date, with every gate on an outfall to a river or reservoir operated through its full travel, because the season of this Manual begins on 1 April and the April storms of the east and the May rain of the foothills follow at once. Gates, pumps, their standby power and racks shall then be kept on standby, with the monthly test run, from 1 April to 31 October, and at an outfall on a release reach until the operator's releases have ended, if that is later. Inlets, culverts, debris racks, silt traps and the mouths of the nallahs shall be cleared again by 15 May, of the silt, slide debris and garbage of the April and early-May storms, before the storms of the last ten days of May, and every public drain, nallah, inlet, rack, trap, basin and culvert in every town shall be cleared of the silt, slide debris and garbage of the season by 15 November, after the October storms of the east. In the towns of the high ranges where snow lies in winter, inlets, culverts and racks shall be kept clear of snow and ice from December to March; where snow or frozen ground prevents the desilting before 31 March, it shall be done in the 15 November clearance and a snowmelt clearance of inlets, culverts and racks shall follow by 30 April, and the declaration of 31 March shall state what was done and what waits for the snowmelt. WRD's own works on rivers and anti-erosion works keep WRD's calendar.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December. The monsoon season of this Manual, 1 April to 31 October, is bracketed: the pre-monsoon months of April and May, with their storms, the south-west monsoon from its normal onset at Itanagar on 5 June to its withdrawal on 14 October, and the late part of October after the withdrawal, when storms still reach the east. December to February is marked as the dry works window, and March and November as months with storms outside the season. Lanes show routine inspections; the desilting of drains and nallahs, the clearance of inlets, culverts, racks, silt traps and slide debris, the pre-monsoon inspection, the readiness of gates, flap gates and any pumps and the Form 10-7 declaration, all by 31 March; in the high ranges, inlets, culverts and racks kept clear of snow and ice from December to March, with a snowmelt clearance by 30 April where snow prevents the March works; standby of gates, pumps and racks from 1 April to 31 October; a mid-season clearance by 15 May, before the late-May storms; a post-season clearance by 15 November; inspections after heavy rainfall in any month; the reporting year from 1 April to 31 March; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Monsoon season of this Manual: 1 Apr–31 Oct Dry: works window Dry Storms Storms Pre-monsoon storms South-west monsoon, 5 Jun–14 Oct Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 31 Mar 30 Apr snowmelt, high ranges 15 May 31 Oct 15 Nov Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Pre-monsoon readiness, standby By 31 Mar: drains and nallahs desilted; inlets, culverts, racks, traps and slide debris cleared; inspection; gates and pumps ready. 1 Apr–31 Oct: standby. By 15 May: inlets, culverts, racks, traps and nallah mouths cleared again. By 15 Nov: post-season clearance. High ranges: inlets, culverts and racks kept clear of snow and ice Dec–Mar; snowmelt clearance by 30 Apr where snow delays the March works. After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including the storms of March, November and February) Annual declaration Form 10-7 Form 10-7 by 31 Mar, closing the reporting year (1 Apr–31 Mar): Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one season, 1 Apr–31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 31 March, 30 April (high ranges), 15 May, 31 October and 15 November are fixed (set by this Manual). December–February is the works window. Doimukh monthly means: April 227.7 mm, May 505.9 mm, June 762.8 mm (Dabral et al., 2016). South-west monsoon at Itanagar: normal onset 5 June, withdrawal 14 October (IMD normals, 2020, as summarised). Late-May storms: Bomdila 190 mm on 29 May 2024 (IMD, as summarised). October storms in the east: Hayuliang 280.0 mm and Tezu 222.0 mm on 3–4 October 1979. Outside the season: Pasighat 137.6 mm on 4 February 1961 (both IMD). Snow lies in winter in the high ranges (SAPCC).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 March) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the monsoon season (April–October); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The 31 March deadline is set by this Manual for a wet season that begins before the south-west monsoon. In this Manual the monsoon season runs from 1 April to 31 October: the pre-monsoon months of April and May, and the south-west monsoon from its normal onset at Itanagar on 5 June (4 June before) to its withdrawal on 14 October (IMD, new normal dates of onset and withdrawal, 2020, as summarised; no Pasighat date was found). The monsoon in IMD's sense does not begin in April; the season of this Manual does, for four reasons. First, the pre-monsoon months are wet: at Doimukh the monthly means are 227.7 mm in April, 505.9 mm in May and 762.8 mm in June, the wettest month, and March to May bring 846.5 mm, 24.0% of the year's 3,531.8 mm (NERIST series, Dabral et al., 2016, citing Dabral et al., 2006); over the State, March to May bring 23.4% of 2,818 mm (IMD gridded data for 1971–2005, as given in the State Action Plan on Climate Change, draft, 2011), which notes that "The state receives rainfall over a period of 8 to 9 months excepting in winter"; and in West Kameng the "rainy season starts from April and continues up to November" (CGWB). Second, the east has large April and May falls: 278.5 mm at Hayuliang on 24 April 1980, 234.4 mm at Pasighat on 29 May 1948 and 181.4 mm at Tezu on 21 May 1978, with monthly totals of 1,087.9 mm at Tezu in April 2010 and 1,367.0 mm at Hayuliang in April 1975 (IMD, Extremes). Third, cut slopes and earthworks must be finished and stabilised before that rain, since the bye-laws ask for a retaining or breast wall "immediately" after earth cutting (APBBL 2019, 4.39(11)). And NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual keeps that date, as the other North-East editions of this series do. No Arunachal Pradesh order fixing a date for desilting was found. The research suggested tiered dates, 31 March in the foothill towns, 15 April in the mid-hill towns and 31 May in the high towns, with a post-monsoon check by 30 September; they are not used, because one calendar keeps the North East on one date, because 31 May falls inside the storms of the last ten days of May, and because 30 September falls before the October storms of the east. December to February is the works window. This Manual therefore takes 31 March for the desilting of drains, nallahs and channels, the clearance of inlets, culverts, racks, silt traps and slide debris, the pre-monsoon inspection, the annual declaration, the BSMP annual report, the stabilisation of completed earthworks and cut slopes, and the readiness of gates, flap gates and any pumps, with no later readiness date. WRD's own works on rivers and anti-erosion works keep WRD's calendar. The damaging pre-monsoon storms come in the last ten days of May: the remnants of cyclone Remal brought 190 mm at Bomdila, 120 mm at Miao and 70 mm at Namsai in the 24 hours to 29 May 2024 (IMD bulletin, as summarised); on 30 May 2025 a landslide swept a vehicle off NH-13 between Bana and Seppa, killing seven people, and the Pare dam passed a peak of 1,310 m³/s on 31 May 2025 (both as reported). A second clearance due by 31 May, the date of the Assam edition and of the plateau edition to the west, would fall inside those storms, so inlets, culverts, racks, silt traps and the mouths of the nallahs are cleared again by 15 May, as in the adjoining edition to the south and the edition to its south, after the April storms and before the late-May cluster. Storms continue after the withdrawal, and the largest come in the east: 280.0 mm at Hayuliang on 3 October 1979 and 222.0 mm at Tezu on 4 October 1979, Pasighat's October monthly record of 1,207.9 mm in 1979, and its 652.2 mm of 5 October 1988, a record this Manual keeps under Clause 2.3.6(h) until IMD confirms or withdraws it (IMD, Extremes); gates, pumps and racks are therefore kept on standby to 31 October (Figure 10.3), and every town clears its drains a second time by 15 November. Storms also come outside the season, 137.6 mm at Pasighat on 4 February 1961 and 122.6 mm at Hayuliang on 16 February 1973 (IMD, Extremes), and Ziro's record of 150.7 mm on 4 February 1974, which this Manual treats as suspect (Chapter 2), while November to February bring 142.68 mm, 4.0% of the year, at Doimukh (Dabral et al., 2016); design statistics use annual maxima from all months, and the post-event inspections of Table 10.3 cover storms at any time of year. In the high ranges "Higher regions experience snow fall during winter" (State Action Plan on Climate Change, draft, 2011), and Tawang has "occasional rainfall/snowfall during winter" (CGWB), with snow in Tawang, upper West Kameng, the upper Subansiri, Mechuka and the Dibang and Lohit ranges; the calendar is not split, as the mountain editions of this series kept one statewide date: in the towns where snow lies, inlets, culverts and racks are kept clear of snow and ice from December to March, the desilting that snow or frozen ground prevents before 31 March is done in the 15 November clearance, and a snowmelt clearance of inlets, culverts and racks follows by 30 April. The research's 31 May for the high towns is not used, because the late-May storms reach the high ranges too, as at Bomdila on 29 May 2024. The reporting year runs from 1 April to 31 March, so that the annual declaration of 31 March closes it.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Arunachal Pradesh cities make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 1 April to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Arunachal Pradesh drainage show up only in the first monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Arunachal Pradesh Building Bye-Laws, 2019 were issued and from the municipal Acts. The graduated steps are set by this Manual. In Arunachal Pradesh the bye-laws carry real penalties for slopes and for rainwater harvesting, the municipal Acts give the local bodies a duty over their drains, and the National Green Tribunal has begun to act on the rivers; nothing yet acts on a drain that is built too small. The APBBL 2019 refuse earth-cutting permission where "the average slope of the topography is more than 30%", and "If formation cutting is under taken without obtaining approval … an amount of One Lakh shall be charged as penalty further, Building Permission Committee shall recommend to the Govt. of AP for cancellation of land allotment" (4.39(14)); they require the Authority to "constitute a Rainwater Harvesting Cell which will be responsible for enforcement and monitoring" and to inspect rainwater harvesting structures "before issuing Completion Certificates" (9.8(a)–(b)), let it "impose a levy for the failure of the owner … to provide or to maintain" them (Annexure E, 1.7), make it punishable "as per section 35" of the Urban and Country Planning Act to let polluted or waste water into a recharge pit, and withhold occupancy certificates without "satisfactory proof of compliance" (Annexure E, 8, 9.1 and 9.2); they let the Authority revoke a permit for false statements or for building against the bye-laws or the sanctioned plan (2.14.4), take action against unauthorised development "which may include demolition of unauthorized works, sealing of premises, prosecution and criminal proceeding" (2.14.7), and debar or blacklist an architect, engineer, supervisor or plumber who has deviated from professional conduct or made a false statement, after a show-cause notice (2.14.6; 17.8). Under the Arunachal Pradesh Urban and Country Planning Act, 2007, development without permission or against its conditions is punishable "with a fine which may extend to twenty thousand rupees" and up to five hundred rupees a day while it continues (s.35), the Local Planning Authority may within four years require unauthorised development to be removed or brought into conformity (s.36), and an applicant aggrieved by a refusal or a condition may appeal to the State Government or the State Urban and Country Planning Board (s.30), the section to which the bye-laws send appeals against debarment (17.8(iii)); they send appeals against a refused occupancy certificate to "section 34 (1)" (17.11(iii)), which in the Act read is the power to revoke or modify a permission, so that cross-reference is to be confirmed [TBC]. The Arunachal Pradesh Municipal Corporation Act, 2019 makes "the maintenance and cleaning of drains and drainage works" an obligatory function of the Corporation (s.60(a)), vests its public drains in it (s.200) and forbids foul water in a drain provided for surface water where separate drains exist (s.203); the Arunachal Pradesh Municipal Act, 2007 requires a Municipality to "construct and maintain drains and sewers, and provide a safe and sufficient outfall" for storm water "in such manner as may not cause any nuisance, whether by flooding" (s.194), although a Municipality may "decide not to take up, or postpone" a core function (s.47(2)). The audits show what happens without enforcement: three PMGSY road projects costing ₹47.70 crore were taken up "without provision of drain", and "₹46.15 crore on construction of 49 Km roads wherein no drains were constructed" was spent, against the scheme's rule that a drainage plan be prepared for each rural road project, findings the Government accepted at the exit conference in June 2023 (CAG, Audit Report for the year ended 31 March 2023); no CAG audit of the Smart Cities, of drainage by the urban local bodies, of AMRUT storm drains or of the State's disaster management authority was found. The Tribunal and the court supervise what the rules leave open: in O.A. No. 94/2020/EZ, on the Senki, the Pachin and the Dikrong, the National Green Tribunal directed on 5 January 2023 that "no untreated sewage or treated sewage be allowed to enter into the waterbody", with quarterly monitoring by the Arunachal Pradesh State Pollution Control Board, and on 8 April 2025 asked the State and the Itanagar Municipal Corporation to file counter-affidavits on faecal sludge treatment (as summarised); in O.A. No. 606 of 2018 the amicus curiae recorded on 20 March 2026 the "complete absence of functional sewage treatment systems" in Itanagar–Naharlagun; and the Gauhati High Court, Itanagar Bench, directed the Corporation to fine littering in PIL 21/2021 and PWD (Highways) to repair the Itanagar–Jullang–Naharlagun–Nirjuli road in 2024 (both as reported). No order on the capital's drains, earth cutting or landslides was found. On community or clan land outside any permission, the owners or the community decide; this Manual does not bind them unless a permission or a plan carries it. This shows that a rule without routine enforcement does little, and that the step that acts on the professional who signs, which the bye-laws already provide for, is the one most likely to work. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river at the nearest gauge with a named datum, which for the Siang at Pasighat, the Noa-Dihing at Namsai and the Lohit at Tezu means the CWC site, with CWC's datum stated [TBC], and for the Senki, the Pachin and the Dikrong in the capital and the Dibang at Roing a staff gauge set up and levelled for the purpose, since none with a published datum was found [TBC], or the level of the receiving pond, with any reading published in the press kept apart and never mixed with CWC levels; for an ungauged stream or nallah, which includes the streams that flooded Modirijo and Donyi Polo in September 2018 and Papu Nallah, the flood marks surveyed after the event and the gravel, slide debris and garbage deposited at crossings, racks and culverts; the state of every flap gate, penstock, debris rack, screen, silt trap, debris basin and pumping station on the outfall and on the drain upstream of it, with the volume of debris and garbage removed from each, the hours each pump ran and any loss of power; and the gate openings, inflows and releases of the Pare, Ranganadi, Kameng or Lower Subansiri project where they set the receiving level, with the times of any warning the operator gave;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), APSDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Arunachal Pradesh's floods and landslides have been counted more often than they have been reviewed, and the counts conflict. The Modirijo and Donyi Polo floods of about 14 September 2018 killed 3 people with at least 4 missing in early reports and up to 7 in later ones, and damaged more than 90 houses (as reported). The landslide at Laptap in Papum Pare on 11 July 2017 killed 14 people by one count and 14 to 16 by others, at about 13:30 or about 15:30 in different reports (as reported). In Itanagar the storm of 23 June 2024 inundated at least 66 houses, while the reported "cloudburst" of about 28 July 2024 submerged NH-415 and led to seven relief camps; the two are separate events, and the date of the second is in conflict between its dateline and its publication (as reported). The statewide floods and landslides from late May to 7 June 2025 killed 12 people with one missing and affected 33,200 people in 215 villages of 24 districts by the count of the State Emergency Operation Centre, against 9, 10 and 11 dead and 156 villages in other reports (as reported). The Poosa / NEEPCO colony flood at Yazali on 24 June is dated 2026 by one report and 2025 by another (as reported). The Department of Disaster Management counted 173 landslides, 104 floods, 80 heavy-rainfall events and 8 flash floods in the 2026 season to 20 July, with 15 deaths, 4 of them in flash floods (as quoted). The Yigong outburst of June 2000 is said to have killed 30 people in one account and more than 100, counting the reaches downstream, in others (as reported). The official tolls of the State's disaster management authority for these events were not found [TBC]. For most of these events no gauge value was published: no IMD rainfall series for any of them is in the research, only an IMD bulletin as summarised (190 mm at Bomdila on 29 May 2024), values quoted by officials (40 mm between 10:30 and 12:30 on 23 June 2024) and press values (73 mm in 24 hours at the Poosa colony); no rainfall was published for Laptap. No review of any flood in an Arunachal Pradesh town, and no record of flood extents, depths or durations kept by the Itanagar Municipal Corporation, the Pasighat Municipal Council or any District Disaster Management Authority, was found. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Arunachal Pradesh's drainage record is public: the APBBL 2019, the Urban and Country Planning Act, 2007, the Municipal Act, 2007, the municipal-area notifications of Itanagar and Pasighat, the Master Plan of Itanagar Capital Region-2031 with its notice of approval, and the drainage expression of interest of 2017, all through archived copies of the Town Planning portal; the Municipal Corporation Act, 2019, the Fire and Emergency Services Act, 2026 and Ordinance No. 5 of 2025 through PRS; the Land Settlement and Records Act, 2000 through FAOLEX; the State's affidavit to the National Green Tribunal and the amicus curiae's observations; CPCB's list of polluted river stretches (2025); the CAG's audit of PMGSY roads; the Forest Department's report on the truthing of wetlands; the CGWB district booklets; NERIST's Doimukh rainfall study; and IMD's station extremes. Much else could not be found in the public domain: the notification of the APBBL 2019 and the "notified rules/norms" for the distance from a nallah or stream to which they refer; the notification constituting the Itanagar Municipal Corporation; the final text of the amendment to the Urban and Country Planning Act; the integrated drainage master plan for the capital and its design basis; the design basis of the AMRUT and Smart City drains; any gauge level or datum on the Senki, the Pachin or the Dikrong; CWC's datum for its Arunachal Pradesh sites; the release protocols and levels of the Pare, Ranganadi, Kameng and Lower Subansiri projects on a named datum; the station list and hourly archive of the Meteorological Centre Itanagar; IMD's ruling on the Pasighat record of 1988; the official tolls of the State's disaster management authority; a master plan or drainage plan for Pasighat; and an inventory of the gates, racks, screens and culverts of any town. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate