Draft v1.0 prepared by NEER. Not adopted by the Government of Arunachal Pradesh or any authority, local body or community, and has no legal force. About this draft

Chapter 4Site Runoff Control: Retention and Detention


4.1 Purpose and scope

4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:

  • (a) the order in which runoff-control measures are to be applied (Clause 4.3);
  • (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
  • (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
  • (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
  • (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
  • (f) regional detention and fee-in-lieu (Clause 4.13);
  • (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
  • (h) public safety (Clause 4.15).

4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (the "complete proposal of rainwater harvesting" that every building on a plot of 100 m² must include in its plans for sanction under clause 9.1 and Annexure E of the Arunachal Pradesh Building Bye-Laws, 2019 (APBBL 2019), with the provisions of Table 9.1 by building type, ground water recharge for buildings on plots of 500 m² and more under clause 9.7, and the "complete utilization and capture of storm water" asked of public open spaces of more than 500 m² under clause 9.6; none sets a volume, and all are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.

4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.

Commentary. No Indian national rule or Arunachal Pradesh rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". No Arunachal Pradesh document found sets a design storm, a return period, a runoff coefficient or a time of concentration for any drain. The building rules are the Arunachal Pradesh Building Bye-Laws, 2019 (Department of Town Planning and ULBs, Government of Arunachal Pradesh) (APBBL 2019), which "shall extent to whole of Arunachal Pradesh with effect from the date of notification" (2.1) and are applicable "for a period of FIVE years after which they shall be reviewed. Till such time the reviewed building byelaws are notified, these building byelaws will continue to be in force" (2.2). Their "Authority" is "The Director/Chief Town Planner of Town Planning & Urban Local Body", "till an executing authority is notified" (def. 12). The "Gazette Notification" page of the copy read is blank, so the notification number, date and gazette reference were not found [TBC]; the bye-laws are named as the State's "Building bye-laws" by s.2(c) of the Arunachal Pradesh Fire and Emergency Services Act, 2026 (Act No. 12 of 2026), and the Online Building Permission System launched on 30 July 2025 is reported to be customised to them (as reported). An "Arunachal Pradesh Building Bye-Law 2010" is listed as notified on the Town Planning portal (as summarised) but was not read, and the hill-site clause of the 2009 "FINAL DRAFT" of the bye-laws ("location of landslide prone areas", "diversion of the natural flow of water coming from uphill side") is not in the 2019 text, although the report of the ICR Master Plan 2031 reproduces it; it is not cited here as in force. The drainage provisions that can be found protect the building and the drain line, not the catchment. The site plan shows "Any existing physical features such as well, drains" (2.10.1(j)) and the "Distance from Nallah/Stream as per the notified rules/norms" and the "Distance from Disaster Prone Area as per norms set by Disaster Management Authority" (2.10.1(e) and (f)), but no such rules or norms were found (NEER reading); a certificate of supervision of drainage and sanitary works accompanies the notice (2.10.10); a retaining wall on a sloping side stands at least 0.60 m from the building (2.10.2(a)); the norms for hill towns are "only indicative" (3.2); the plinth is "so located with respect to the surrounding ground level that adequate drainage of the site is assured" and "not less than 300 mm" (4.2.1.1); "Under no circumstances shall effluent from a septic tank be allowed into an open channel drain or body of water without adequate treatment" (4.16.2(c)); "The Authority may require rain-water pipes to be connected to a drain or sewer" (4.19.1.1); earth cutting needs a permission valid for six months, cuts are not more than 3 m high, a clear setback of 2.5 m is kept from the property line on the upper terrace, the owner clears debris "from site or drain to suitable/safer place", a retaining or breast wall follows "immediately", and "Earth cutting permission shall not be granted if the average slope of the topography is more than 30%. And the site will be declared as not fit for construction except for plantation", with a penalty of one lakh rupees for unapproved cutting and a recommendation to cancel the land allotment (4.39(4), (5), (8), (11) and (14)); every building on a plot of 100 m² includes "the complete proposal of rainwater harvesting" (9.1; Commentary to Clause 4.11); public open spaces of more than 500 m² "shall have arrangements for complete utilization and capture of storm water", including "Artificial or natural Storage of storm water runoff from larger sites" (9.6); and on sites of 5,000 m² of built-up area and more, "The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water" and the unpaved area is not less than 20% of the recreational open space (Table 14.1). The bye-laws define a Jhot as "A strip of land permanently left open for drainage purposes" (def. 69), with no width, and include among natural hazard prone areas those flooded by "back flow in drains, inadequate drainage, etc. as identified through local surveys in the development plan of the area". They set no stream, spring or drain setback by number, no flood plinth above 300 mm and no runoff limit, and none of these provisions sets a design storm, a release rate, a detention volume or an overflow path. The site plan of 2.10.1, the roof-water connection of 4.19.1.1, the storage of storm water on large open spaces of 9.6 and the natural drains of Table 14.1 are the hooks for this chapter. The municipal Acts make drainage a duty of the local body: a Municipality "shall … construct and maintain drains and sewers, and provide a safe and sufficient outfall … for … proper discharge of storm-water and sewage … in such manner as may not cause any nuisance, whether by flooding" (Arunachal Pradesh Municipal Act, 2007, s.194), and public drains vest in it "Notwithstanding anything contained in any other law" (s.102); in Itanagar "the maintenance and cleaning of drains and drainage works" is an obligatory function of the Corporation (Arunachal Pradesh Municipal Corporation Act, 2019, s.60(a)), public drains and sewage disposal works vest in it (s.200), and no one may discharge "foul water into a drain provided for surface water" where separate drains exist (s.203). The Master Plan of Itanagar Capital Region-2031, approved on 3 June 2022 under s.24 of the Arunachal Pradesh Urban and Country Planning Act, 2007, finds that "no scheme or work for storm water drains is under execution", that the drains are "not engineered", and that "Most of the surface water and sewerage gets mixed up resulting in storm water drains being used as sewers"; it proposes a new drainage network for Itanagar and Naharlagun designed on "topography of the region and flow gradient" (Maps 28–30), with no design storm, return period or runoff coefficient (report, titled "Draft"; whether the approved text differs was not checked [TBC]). A "GIS based Integrated Drainage Master Plan and DPR for Itanagar Capital City" was put out for expressions of interest in October 2017 (65 km², horizon year 2038; no return period stated), and a drainage plan by a consultant was reviewed by the Chief Minister in June 2021 (as reported); its adoption was not found. No master plan or drainage plan for Pasighat was found [TBC]. No highest flood level published by a local authority exists for any town [TBC], and the bye-laws' plinth is 300 mm; this Manual supplies the method (surveyed flood marks, the CWC levels where a site exists, or the modelled 1% AEP level, Chapter 5). There is no Sixth Schedule area in the State, and Article 371H does not protect land (as quoted); but customary rights are recognised in the Arunachal Pradesh (Land Settlement and Records) Act, 2000, much land near the towns is held by communities, clans and individuals, and the beds of streams and nallahs are Government property only where they are "not the property of any person or community" (s.9(1)). So this chapter applies as a condition of building permission and layout approval wherever the bye-laws apply, which is the whole State (2.1); for a household or a community building on its own land without a permission it is guidance, and its small-site method (Clause 4.14) and the hill rule of Clause 4.11 are offered as such (Chapter 1).

The State's planning law is being rewritten around storage. The Arunachal Pradesh Urban and Country Planning (Amendment) Ordinance, 2025 (Ordinance No. 5 of 2025) defines a "sponge city" as "an area that acts like a sponge, soaking up and retaining water during rain and storms and releasing it slowly", and lets the Government "prepare policy documents for … Sponge City … Risk Informed master Plan" (new s.71(2)(za)); it also lets a Town Planning Scheme provide for "the filling-up or reclamation of low-lying, swampy or unhealthy area, or levelling-up of land". An amending Bill was reported passed by the Legislative Assembly on 9 March 2026 (as reported); its Act number and final text were not found [TBC], so none of these provisions is cited here as enacted law. This Manual's storage-first rules, on-site detention under this chapter, ponds and low land kept as storage, and release at pre-development rates (Chapters 4, 7 and 11), are an engineering form of that definition, and the Manual could be offered as technical input to such a policy document; it is not one, and no policy document under s.71(2)(za) was found. Storage matters here for three reasons: (i) the capital's outfalls back up when the Dikrong carries the releases of the Pare dam, so that water sent faster from the colonies fills the nallahs of Naharlagun, Nirjuli and Doimukh sooner when the river is high; (ii) the outfalls of Pasighat and Tezu back up from the Siang and the Lohit, whose stage is set upstream; and (iii) water sent downstream faster reaches the Assam reaches below the State, on the Ranganadi and the Subansiri below the projects, where the Assam edition governs. Where a Town Planning Scheme fills or reclaims low-lying or swampy land, the compensatory storage of Clause 7.6.4 (Chapter 7) applies to it.

No design basis is in use. The State Action Plan on Climate Change (draft, 2011) budgets "Storm water draining in twenty six urban settlements" at Rs 15,000.0 million with no design criteria; a storm-water drainage project for Itanagar had its foundation stone laid in June 2018 (as reported) and IMC is reported to have sought funds for a 64 km integrated drainage system (as reported), with no design basis seen; Smart City storm-water works in Itanagar and Pasighat are reported, with "improperly constructed drainage systems" noted at Pasighat (as reported), but their DPRs were not read [TBC]; and the bye-laws refer to Part 9 of the National Building Code 2005 for plumbing and drainage (4.19.1.3, 4.33.1), which does not size storm drains for a catchment (NEER reading). The illustrative example of Clause 4.6.7 and Annex 4C, set at a hillside colony in Itanagar draining to the Senki, uses invented 24-hour depths of 110, 200 and 350 mm for the 2-, 10- and 100-yr storms; they are not design values. In the capital region the design depths are those of Clause 2.3.6(c)(ii), 205 mm at 10% AEP and 290 mm at 1% AEP before the climate factor of Clause 2.8 (319 mm with it), so the example's 350 mm lies above the design value and below NIH-DHAARA's 528 mm for the Itanagar cell, which this Manual does not use for design (Clause 2.3.6(m)).

Basements are regulated only against surface water: "Adequate arrangements shall be made such that surface drainage does not enter the basement", and "The walls and floors of the basement shall be watertight" (APBBL 2019, 4.10.4(d) and (e)); no basement rule on flood levels was found. This Manual therefore adds its own requirements for every basement: no detention storage in a habitable basement (Clause 4.10.1); the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4); and no basement in Zone 2 (Clause 7.5.2). In the flood-sensitive catchments of Clause 4.5.3.2, in any catchment notified under Clause 4.5.4, and on the valley-floor, flood-plain and pond-margin land of Clause 4.12.1, it recommends that no basement be permitted where the 1% AEP flood level stands above the surrounding ground; where one is permitted on a valley floor it is watertight, as the bye-laws already require, and checked for flotation with the design groundwater level at ground level (Clause 4.12.3); and wherever a basement or lower floor is cut into a slope, it shall carry the geotechnical certificate of the hill rule of Clause 4.11, with the water behind its walls drained to a lined drain and not to the ground (all set by this Manual). For a sloping site, this chapter also supplies what clause 4.39 of the bye-laws leaves open: runoff from the catchment above the site and above every cut shall be intercepted and carried round the building in the design storms of Chapter 6, and every flow from the site shall discharge to a lined drain or a stable natural channel through an energy dissipator, never onto an unprotected slope, a cut face or fill; where the ground falls steeply, the drain is stepped. These are the Manual's proposals, not rules of the APBBL 2019. This chapter is written so that it can supply, as a technical companion to the APBBL 2019 and to their five-year review (2.2), to the municipal Acts, to the ICR Master Plan 2031 and its proposed drainage network, and to the public works of the State's departments, the design storm, release rates and storage volumes that they leave open, and so that the Manual's corridor can be offered as the "norms" that 2.10.1(e) refers to; a competent authority could adopt it for those purposes, but none has. In practice the storm drains of the towns carry sewage: "City sewerage is discharged into open drains. The hilly terrain means limited scope for u/g sewer network" (report); "no ULB is treating sewage. Even the state capital, Itanagar-Naharlagun, lacks a sewage treatment facility" (observations quoted in the State's affidavit in NGT OA 606/2018, 2025); and the Senki at Chandranagar, upstream of the Pachin, is listed among polluted river stretches (CPCB, 2025) (Clause 8.9). Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.


4.2 Definitions

Term Meaning in this Manual
Retention Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall.
Retention depth The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E).
Required retention volume (RRV) The runoff volume from the retention depth over the post-development site (Clause 4.4.2).
Detention Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5.
Retention credit The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume.
Permissible site discharge (PSD) The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha.
Site storage requirement (SSR) The detention storage required per hectare of site under the simplified method of Clause 4.14.
Multi-stage outlet An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2).
Drawdown time Time from the peak stored volume until the stated fraction of that volume has been released.
Emergency spillway A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment.
Freeboard Vertical distance between the maximum design water level and the embankment crest or other critical level.
Flood-sensitive catchment A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4.
Authority The approving authority under Chapter 1 (the competent authority for the area: in the area of the Itanagar Municipal Corporation (IMC), the Corporation for its own drains and connections (ss.60, 200 and 203 of the Arunachal Pradesh Municipal Corporation Act, 2019) and the Authority under the APBBL 2019 (the Director/Chief Town Planner, or the executing authority once notified, with its Building Permission Committee) for the building permit and the earth-cutting permission (4.39); in the Pasighat municipal area, the Pasighat Municipal Council for its drains (ss.102, 194 and 196 of the Arunachal Pradesh Municipal Act, 2007) and for building sanction (ss.340–343, through its Municipal Building Committee); in a Local Planning Area, the Local Planning Authority (the Itanagar Planning Authority in the Itanagar Capital Region) for layouts and the master plan under the Arunachal Pradesh Urban and Country Planning Act, 2007; elsewhere, the Authority under the APBBL 2019; for a public work, the department or agency that executes it (Urban Affairs, PWD, PWD (Highways), WRD, PHED or a Smart City company); WRD for any work in or on a river; and on community or clan land, the owners or the community by agreement, for whom this Manual is guidance unless a permission or plan carries it, as applicable).
Tier A / Tier B Adoption tiers defined in Chapter 1. Tier A: the Itanagar Municipal Corporation (IMC), and every approving authority within the area of the Master Plan of Itanagar Capital Region-2031 (Itanagar, Naharlagun, Nirjuli, Doimukh and Banderdewa), that is, the Itanagar Planning Authority for layouts and the Authority under the APBBL 2019 for building permits, whichever has jurisdiction over a site. Tier B: urban local bodies, Local Planning Authorities and other authorities under the bye-laws.

4.3 Order of measures

4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:

  1. Preserve. Keep existing waterbodies, ponds, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
  2. Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
  3. Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
  4. Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).

4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.

Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.


4.4 Retention

4.4.1 Requirement

The site shall retain the RRV. Retention shall be achieved by one or more of the following:

  • infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
  • rainwater reuse that is drawn down by a demonstrated non-potable demand;
  • green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.

The limits of Clause 4.4.4 apply.

4.4.2 Computation of the RRV

RRV (m³) = 10 × Q_R × A

where:

  • Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
  • A (ha) is the area of the site that drains to the outfall.

Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.

The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.

Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.

4.4.3 Verification

Retention by infiltration shall be supported by:

  • (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
  • (b) a design infiltration rate of no more than half of the measured rate; and
  • (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).

Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.

Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.

4.4.4 Limits on retention

4.4.4.1 Infiltration practices shall not be used:

  • where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
  • on contaminated land;
  • within the setbacks from foundations, wells and septic systems set in Chapter 8; or
  • on fill, unless tested after placement.

4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.

4.4.5 Drawdown of retention

Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.

4.4.6 Retention credit: definition and computation

4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.

4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:

  • (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
  • (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
  • (c) once it is full, route its overflow to the detention facility; and
  • (d) size the detention for the residual hydrograph.

The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.

4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:

V_credit = C_R × RRV_provided

where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.

4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.

Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Arunachal Pradesh, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.

The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).

This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).

4.4.7 Preservation credit

Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:

  • they are protected by a registered covenant or dedication; and
  • their runoff is not concentrated onto impervious surfaces.

This lowers both the RRV and the detention required. No other preservation credit applies.


4.5 Release-rate criteria

4.5.1 General

4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.

4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.

4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.

4.5.2 Standard catchments

For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:

Q_post(T, d) ≤ 0.9 × Q_pre(T, d)

4.5.3 Flood-sensitive catchments

4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:

Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).

Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).

4.5.3.2 The flood-sensitive catchments are:

  • (a) The Senki through Itanagar: the land of Itanagar that drains to the Senki, including the reach of the Senki View culvert washed away in September 2018 (as reported) and the stretch "Senki at Chandranagar, Itanagar (u/s of Pachin)" listed by CPCB in 2025, down to its confluence with the Pachin;
  • (b) The Pachin through Itanagar–Naharlagun: the land that drains to the Pachin, with its flood plain, palaeochannels and swampy land, down to its confluence with the Dikrong near Nirjuli;
  • (c) The Dikrong at Naharlagun, Nirjuli and Doimukh, with Papu Nallah: the land that drains to the Dikrong below the Pare dam and the outfall of the Ranganadi project's tailrace, including Papu Nallah and the other nallahs of Naharlagun, Nirjuli and Doimukh;
  • (d) The NH-415 corridor from Itanagar to Naharlagun: the land that drains to and across NH-415, with Energy Park, Bank Tinali, Niti Vihar and Abo Tani Colony and the drains of the Bage Tinali–Naharlagun road (as reported);
  • (e) The Modirijo and Donyi Polo catchments: the land of Itanagar and Naharlagun that drains through Modirijo and Donyi Polo, flooded in September 2018 (as reported);
  • (f) Pasighat on the Siang: the land of Pasighat that drains to the Siang and its side channels on the river's outburst reach, including Jarkong near the airfield, and the Mebo villages downstream, where erosion is reported (as reported);
  • (g) Tezu on the Lohit: the land of Tezu that drains to the Lohit and its side channels;
  • (h) Namsai and Miao on the Noa-Dihing: the land of Namsai and Miao that drains to the Noa-Dihing;
  • (i) Roing on the Dibang: the land of Roing that drains to the Dibang and to the streams that cross its fan;
  • (j) The Ranganadi reach at Yazali: the land at Yazali that drains to the Ranganadi and its side streams below the Ranganadi project, including the Poosa / NEEPCO colony flooded on 24 June 2025 or 2026 (the reports conflict; as reported);
  • (k) The glacial-lake and outburst reaches of Tawang and Dibang Valley: the land of any settlement in Tawang or Dibang Valley district that lies on the path of a glacial lake listed as high-risk by NDMA (as reported), as found by the outburst screening of Clause 2.3.6(i); and
  • (l) any catchment notified under Clause 4.5.4.

The boundaries shall be those mapped in Annex 4A.

4.5.4 Notification of further flood-sensitive catchments

4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:

  • (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
  • (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
  • (c) an outfall that is backed up by the Dikrong carrying the releases of the Pare dam and the tailrace of the Ranganadi project, as the nallahs of Naharlagun, Nirjuli and Doimukh are, or by the Siang, the Lohit or the Noa-Dihing at Pasighat, Tezu or Namsai, or that discharges to a reservoir held near its full level or to a release reach below a dam, or that is buried or blocked by the boulders, slope debris and garbage of a hill stream or a nallah, for part of the monsoon season (Chapter 5);
  • (d) loss of more than a quarter of the mapped tank and pond storage in the catchment since the earliest available survey; or
  • (e) a basin master plan that relies on limiting site discharge.

4.5.4.2 The procedure shall be:

  1. The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
  2. The State-level technical committee constituted under Chapter 1 reviews the note.
  3. The draft notification and map are published for public comment for at least 60 days.
  4. The Government notifies the catchment and the map is added to Annex 4A.
  5. The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.

4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.

Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The capital-region entries follow its rivers, nallahs and spine road. Itanagar's drains run to nallahs and to the Senki and the Pachin, and Naharlagun's to the Dikrong; the storm water drainage system "consists of natural drainage system (Nallah) and major drains", the drains are "not engineered … open drains or kutcha drains without any flow gradient", "There is no proper storm water network for the overall town area", "With only 3.7% storm drains along main roads, drainage was marked as a key area of focus", and "rivers like Pachin flowing through densely populated areas had become a waste disposal site" (Master Plan of Itanagar Capital Region-2031, report). In the floods of 2017 the "land protection wall of several nallahs and rivulets" was badly damaged and NH-415 was closed during flash floods, with traffic diverted via Papu Nallah and Jullang Road (report). About 14 September 2018 cloudburst floods in the Modirijo and Donyi Polo areas killed three people, with at least four missing (later reports give up to seven dead; the tolls conflict), damaged more than 90 houses, washed away the Senki View culvert and the Press Colony bridge, and were joined by a landslide from "the dumping area of NH 415" (as reported). On 23 June 2024, 40 mm in two hours ("As per IMD, the rainfall recorded today was 40 mm between 10:30 am and 12:30 pm", the secretary of the State Disaster Management Authority, who added that IMD "confirmed there was no incident of cloudburst") inundated at least 66 houses in Itanagar and Naharlagun, destroyed one house, damaged NH-415 between the two towns, flooded Energy Park and brought a landslide at Niti Vihar and damage in Abo Tani Colony (as reported); a reported "cloudburst" of about 28 July 2024 submerged NH-415 and flooded homes near Energy Park and Bank Tinali (as reported; its date and the June event's are not to be merged). The drains along the Bage Tinali–Naharlagun road are reported to be "too shallow and narrow" and clogged with earth-cutting debris, and an inspection recommended de-silting "upto the Dikrong river" (as reported). The Senki at Chandranagar, upstream of the Pachin, is one of four stretches in the State first listed as polluted by CPCB in 2025, at Priority V (BOD 3.2 mg/L) (CPCB, 2025); the Pachin itself is not listed. Below Doimukh the Dikrong carries the releases of the Pare dam, whose peak was reported as 1,310 m³/s on 31 May 2025, and the 1999 flood is the local benchmark from Jampa to Doimukh (as reported); the Ranganadi project's tailrace also enters it (as reported). No State gauge level for the Senki, the Pachin or the Dikrong was found, and there is no CWC site on them [TBC]. The Pasighat, Tezu and Namsai entries follow the main stems and their CWC sites: the Siang at Passighat, with a highest flood level of 157.54 m on 11 June 2000, 3.58 m above its danger level, from the Yigong outburst in Tibet; the Lohit at Tezu, highest level 192.14 m (16 July 1996); and the Noa-Dihing at Namsai (highest level 146.6 m, 31 August 1974) and at Miao (241.57 m, 9 July 2004) (CWC tables as transcribed by SANDRP); erosion is reported at Jarkong near the Pasighat airfield in 2024 and in the Mebo villages of Seram, Kongkul, Namsing, Gadum-I/II and Mer (as reported). The Roing entry follows the Dibang, on which there is no CWC site; its stretch at Roing is the third of the four CPCB stretches (BOD 3.6 mg/L) (CPCB, 2025). The Yazali entry follows the flash flood of 24 June at the Poosa / NEEPCO colony in Keyi Panyor, from a side stream of about 17 km² while "the main river stayed in its channel": 1 dead and 4 missing, and about 18 quarters or about 50 houses washed away, with 73 mm in 24 hours, mostly in three hours (as reported; Down To Earth places it in 2026 and EastMojo dates its photographs to 2025, and the years conflict); the CWC site on the Ranganadi at Yazali records a highest level of 623.1 m (14 June 2008) (as transcribed by SANDRP). The glacial-lake entry follows NDMA's 27 high-risk glacial lakes in the State, 6 of them in Tawang district and 16 in Dibang Valley, with Kurung Kumey, Shi Yomi and Anjaw holding the rest (as reported). Ziro, Daporijo, Aalo, Seppa, Bomdila, Khonsa, Changlang and Bhalukpong, and the NH-13 corridor between Bana and Seppa, where a landslide swept a vehicle off the road on 30 May 2025 and killed seven (as reported), are candidates for notification under Clause 4.5.4. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.

4.5.5 Minimum outlet and short-duration 2-yr checks

4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.

4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:

  • size the low-flow orifice as the smallest opening that meets Clause 4.7; and
  • report the resulting 2-yr exceedance for those durations.

The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.

Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).

4.5.6 Constrained redevelopment sites

4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:

  • (a) the existing site is at least 60% impervious, as surveyed before demolition;
  • (b) the site is 1 ha or less; and
  • (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.

New development on undeveloped land is never eligible.

4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:

  • (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
  • (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
  • (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).

4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:

  • (a) paid into the ring-fenced account of the basin in which the site lies;
  • (b) spent only on regional detention or on restoring pond or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
  • (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.

Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with WRD agreement.

4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.

Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as the localities along NH-415 in Itanagar and Naharlagun that flood when the drains and nallahs block, among them Energy Park, Bank Tinali, Niti Vihar and Abo Tani Colony (as reported), there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.


4.6 Detention sizing procedure

4.6.1 Method

Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.

4.6.2 Steps

  1. Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
  2. Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
  3. Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
  4. Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 1 May to 15 October in sub-areas AR-A, AR-A1, AR-C and AR-C1, from 1 April to 31 October in AR-B, from 1 June to 15 October in AR-D and AR-E, and from 1 April to 31 October on land below the 1% AEP level of a river, stream or nallah, on the Pachin and Dikrong palaeochannels and swamps, on pond margins and where the seasonal high water table is within 2 m of ground, at all times in catchments draining to a reservoir, its backwater or a release reach below a dam (Pare, Ranganadi, Kameng, Lower Subansiri), and at other sites and times after a 5-day total of more than 53 mm, AMC II otherwise).
  5. Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
  6. Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
  7. Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
  8. Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
  9. Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
  10. Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
  11. Size the emergency spillway and set freeboard (Clause 4.9).
  12. Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).

4.6.3 Storms to be routed

Every facility shall be routed for the full matrix:

Table 4.1 — Design storms to be routed for detention sizing

AEP Durations (h) AMC
50% (2-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h
10% (10-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h
1% (100-yr) 1, 2, 3, 6, 12, 24, 48, 72 II for ≤ 6 h; III for ≥ 12 h

The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.

4.6.4 Initial conditions

Each run shall start with:

  • detention storage empty, down to the invert of the lowest outlet;
  • any permanent pool full;
  • retention practices empty, except as limited by Clause 4.11; and
  • RWH storage full (Clause 4.11).

The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.

4.6.5 Multi-stage outlet design

4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:

  • Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
  • Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
  • Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
  • Emergency spillway: separate from the primary outlet (Clause 4.9).

Stages may be combined where routing shows that every cap is met.

4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).

4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.

4.6.6 Tailwater on the outlet

The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:

  • for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
  • for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).

Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.

4.6.7 Illustrative example

Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a hillside colony in Itanagar draining to the Senki. They are not NIH-DHAARA values and must not be used for design.

Inputs:

  • Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
  • Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
  • Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
  • 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
  • Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
  • Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
  • Storage: vertical-walled, 2,500 m² plan area.
  • Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
    • Stage 1: 170 mm orifice at the invert.
    • Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
    • Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.

Results (discharges in L/s; storage in m³):

Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)

Duration (h) 2-yr pre 2-yr post, detained 10-yr pre 10-yr post, detained 100-yr post, uncontrolled 100-yr post, detained 100-yr storage used 10-yr drawdown, 50% blocked (h)
1 4 15 51 28 922 42 1,426 31.3
2 14 20 84 34 961 79 1,911 32.1
3 19 22 104 37 981 139 1,999 32.8
6 32 25 150 41 1,010 194 2,154 34.2
12 127 30 302 46 1,074 276 2,512 39.0
24 149 32 327 49 1,081 320 2,766 45.3
48 173 34 349 82 1,087 343 2,913 44.8
72 180 34 356 84 1,089 343 2,911 44.7

How to read it:

  • 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
  • 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
  • Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
  • Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
  • Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.

The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.

2026-11-01T10:14:56.974241 image/svg+xml Matplotlib v3.9.4, https://matplotlib.org/ 0 5 10 15 20 25 30 35 40 Time from start of 24 h design storm (h) 0 200 400 600 800 1000 1200 Discharge (L/s) Release cap = max pre-development 10-yr peak over all durations (356 L/s) Uncontrolled peak 1081 L/s Detained: peak later and flatter, recession prolonged (volume unchanged) Illustrative — not design values. 2 ha site, 24 h storm, AMC III, mixed-frequency rule Post-development 1% AEP (100-yr), uncontrolled Post-development 1% AEP (100-yr), detained Pre-development 10% AEP (10-yr)

Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).

Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).


4.7 Drawdown

4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.

4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).

4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).

4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.

Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Arunachal Pradesh storage must hold multi-day volumes. It is still short enough that a basin filled by one monsoon depression will have most of its volume back before the next, which in June 2024, when Itanagar had 40 mm in two hours on 23 June (IMD, as quoted by the State Disaster Management Authority) and 52.0 mm by 12:30 on 27 June (IMD special bulletin, as summarised), and late May and early June 2025, when the landslides of 30 May between Bana and Seppa were followed by statewide floods to 7 June (as reported), followed within days.


4.8 Outlet structures

4.8.1 General. Primary outlets shall be:

  • unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
  • accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
  • built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).

4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.

4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:

  • have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
  • have a clear open area at least 10 times the area of the opening it protects;
  • be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
  • be removable or hinged for cleaning; and
  • for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.

4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).

4.8.5 Outlet barrels. Outlet barrels through embankments shall:

  • be at least 300 mm in diameter (Chapter 6);
  • have watertight joints;
  • have a filter diaphragm or seepage collars over the length within the embankment; and
  • have an energy-dissipating outfall (Chapter 9).

4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.

Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.

Figure 4.2 — Detention storage stack and multi-stage outlet (schematic) Schematic cross-section of a detention basin showing stacked storage zones (permanent pool, water quality volume, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and a multi-stage riser outlet with trash rack, anti-vortex plate, outlet barrel and emergency spillway. Not to scale. Storage stack and multi-stage outlet — schematic section, not to scale Embankment crest Max level, spillway flowing (outlet blocked) Emergency spillway crest 1% AEP (100-yr) max water level 10% AEP (10-yr) max water level 50% AEP (2-yr) max water level Top of water quality volume (WQv) Permanent pool (wet basin only) Basin floor / pool bottom Spillway surcharge (Clause 4.9) 100-yr detention zone 10-yr detention zone 2-yr / channel-protection zone WQv — 24–48 h release (Ch 8) Permanent pool / retention Freeboard ≥ 0.3 m Spillway crest (offset in plan) 1 2 3 4 5 6 7 Key 1 Stage 1 low-flow orifice (≥ 50 mm, Clause 4.8.2) — releases WQv over 24–48 h 2 Stage 1 second orifice — with 1, controls 50% AEP (2-yr) release 3 Stage 2 orifice or weir slot — controls 10% AEP (10-yr) release 4 Stage 3 riser crest / overflow grate with anti-vortex plate — controls 1% AEP (100-yr) release 5 Trash rack enclosing all openings (Clause 4.8.3) 6 Seepage collar or filter diaphragm on outlet barrel 7 Outlet barrel, energy dissipation and outfall apron Levels and zone thicknesses are diagrammatic only.

Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).


4.9 Emergency spillway, freeboard and embankment safety

4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:

  • with the primary outlet assumed fully blocked;
  • with the facility full to the spillway crest at the start of the storm; and
  • with at least 0.3 m freeboard from the maximum water level to the embankment crest.

4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:

  • endanger life;
  • flood a habitable building or critical facility; or
  • close an arterial road.

High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.

4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.

4.9.4 Spillway location. The spillway shall be:

  • on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
  • discharging to the 1% AEP overland flow path of Chapter 6; and
  • placed so that its flow does not reach a building.

4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.

4.9.6 Embankments.

  • (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
  • (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
  • (c) Embankments shall have:
    • a crest width of at least 3 m;
    • compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
    • no trees or large shrubs.
  • (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.

4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.

Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.


4.10 Facility types

4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.

4.10.2 Underground tanks and vaults.

  • (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
  • (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
  • (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
  • (d) The tank shall be ventilated.
  • (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
  • (f) Flotation and groundwater ingress shall be checked under Clause 4.12.

4.10.3 Rooftop detention.

  • (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
  • (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
  • (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.

4.10.4 Podium and landscape-deck detention.

  • (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
  • (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.

4.10.5 Parking-lot detention.

  • (a) It is permitted only on surface parking. Ponding depth shall not exceed:
    • 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
    • zero on accessible routes, ramps and pedestrian crossings; and
    • zero in the 10% AEP storm on fire-tender access routes.
  • (b) Signs shall warn that the area floods.
  • (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).

4.10.6 Multi-use detention (parks, playfields, open space reservation).

  • (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
  • (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
  • (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
  • (d) The depth and slope limits of Clause 4.15 apply.
  • (e) Play equipment and seating shall be placed above the 10% AEP level.

4.10.7 Ponds and wet basins.

  • (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
  • (b) Only storage above the permanent pool counts as detention.

Commentary.

  • The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
  • The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
  • Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
  • Using open space for multi-use detention fits what the APBBL 2019 already ask of a site and of open land: public open spaces of more than 500 m² "shall have arrangements for complete utilization and capture of storm water", including "Artificial or natural Storage of storm water runoff from larger sites" (9.6); on large sites "The unpaved area shall be more than or equal to 20% of the recreational open spaces" (Table 14.1); and group housing avoids concrete paving, with "permeable materials … for all open parking spaces" (Table 9.1). None of these sets a volume or a release rate (NEER reading). On the tested terrace sands of the Naharlagun–Nirjuli–Doimukh valley and on the coarse bhabar fan heads, on flat ground outside the floodplain rule, a detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires, and can also infiltrate under Clause 4.11 (recharge rule). Everywhere else the position is different. Below the 1% AEP flood level, on the Pachin and Dikrong palaeochannels and swamps and wherever the seasonal high water table is within 2 m of ground, a basin in the open space holds groundwater and backwater, not storm water, so detention there is in lined, watertight storage (Clause 4.11, floodplain rule). Ground on a natural slope of more than 10°, Siwalik shale, a terrace held up by a retaining wall, land within twice the height of a cut or wall downslope of it, colluvium, slope debris and fill, and mapped landslide ground are not to be used for ponding, because water held there soaks into the slope (Clause 4.11, hill rule); the bye-laws already refuse earth cutting where the average slope exceeds 30% and declare such a site "not fit for construction except for plantation" (APBBL 2019, 4.39(14)). On such sites, detention is provided in lined tanks, open or closed, with an orifice outlet and an overflow to a lined drain, on rooftops and podiums under 4.10.3 and 4.10.4, or on a level open space only where it stands on rock or on ground that the geotechnical certificate of the hill rule covers; an excavated pond or basin on a slope is not accepted, and paving there is laid on a lined or non-exfiltrating base with an underdrain. Three kinds of land are not open space for this purpose. A pond, lake or spring on the land is preserved under step 1 of Clause 4.3.1; a pond is modelled as a water surface (Clause 3.3.2(e)) that starts at its outlet level (Clause 3.12.5), so only its flood storage above that level can count, and only as Chapter 7 allows; a natural pond keeps its own description and is never turned into a detention pond, and neither is a lake, a spring pool or a reservoir; Ganga Lake in the Itanagar Wildlife Sanctuary is a lake, not storage. The corridor of Chapter 7 along streams and nallahs and round ponds and springs is flood land already: water reaches it first, so it is not counted as detention for the development beside it; no statute sets such a line, and the "Distance from Nallah/Stream as per the notified rules/norms" of the bye-laws' site plan (2.10.1(e)) refers to norms that were not found, while the Jhot, "A strip of land permanently left open for drainage purposes" (def. 69), has no width. And land kept open on purpose, such as a spring-recharge area above a town's or village's intake (Clause 4.11; Chapter 7), is not graded or paved for detention. Where open space is used for detention, the signs and depth markers of Clause 4.15.5 are in English and the local language, that is, the language in local use in the ward or village, as the local body or the village authority uses for its own public notices (set by this Manual), because a sign must be readable by the people it warns.

4.11 Rainwater harvesting versus detention accounting

4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.

4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.

4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:

  • (a) the detention zone lies wholly above the RWH overflow level;
  • (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
  • (c) no pump, valve or user action can hold water in the detention zone; and
  • (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.

Only the volume between the RWH overflow level and the detention overflow level counts as detention.

4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the monsoon season.

4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of clauses 9.1 and 9.5–9.8, Table 9.1 and Annexure E of the APBBL 2019, any rainwater harvesting provision of a master plan or layout approved under the Arunachal Pradesh Urban and Country Planning Act, 2007, any condition of a building permission, or any rainwater harvesting rule or direction of an approving authority.

Commentary. Rainwater harvesting in Arunachal Pradesh is required by one instrument, which does not size it. "All buildings having a plot size of 100 sqm while submitting the building plans for sanction shall mandatorily include the complete proposal of rainwater harvesting"; the system comprises the roof catchment, gutters, down pipes, "Rain water/ Storm water drains", a filter chamber, "Storage Tanks/ Pits/ Sumps" and "Ground Water recharge structures like pit, trench, tube well or combination of above structure" (APBBL 2019, 9.1). Table 9.1 sets the provisions by building type: plotted houses of 100 m² and more build a harvesting structure "with emphasis on both storage & reuse"; group housing, public, commercial and industrial buildings of all plot sizes build one too, with recharge pits or wells, and group housing avoids concrete paving, with "permeable materials … for all open parking spaces". "Recharging of ground water should be made mandatory … for all types of buildings, including Group Housing Societies having a plot area 500 sqm and above", and for parks, parking, plazas and playgrounds (9.7); public open spaces of more than 500 m² "shall have arrangements for complete utilization and capture of storm water" (9.6); and the Authority "shall constitute a Rainwater Harvesting Cell", inspect the structures before issuing completion certificates, monitor every building above 1,000 m² with annual physical verification and the rest by a 10% random survey (9.8). Annexure E makes harvesting mandatory on plots of 100 m² and more (1.1), not below (1.4), lets the Authority "impose a levy for the failure … to provide or to maintain" it (1.7), and asks that structures be placed so as "not to endanger the stability of building or earthwork" (2.2.2). The bye-laws say that "Rainwater can be harvested to the extent of 55,000 liters per 100sq. meters area per year from rooftops" (9.1), but none of these provisions gives a storage volume, a roof-area rate, a drawdown or an infiltration test (NEER reading). This Manual therefore sets a sizing rule for credit: RWH storage shall hold at least 25 L per m² of roof area (about 25 mm of rain over the roof). This is set by this Manual. It is the value of the other North-East editions of this series, raised from the 20 L per m² of the mountain editions because the storms that matter here come on wet ground, often on several days running: at Doimukh the mean May rainfall is 505.9 mm and the June mean 762.8 mm (NERIST series, as given by Dabral et al., 2016). A larger minimum was weighed and not adopted, for two reasons: the credit under Clause 4.4 depends on how fast a continuous use empties the tank, not on how much rain falls, so a larger minimum adds cost on every plot without adding credit; and the 100 m² trigger of 9.1 reaches small plots on steep ground, where a larger tank is harder to place safely. A larger tank is always allowed and is credited in the same way, up to the volume that the stated use empties within 72 hours. The rule makes the bye-laws' requirement measurable; it does not replace it. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:

  • An RWH tank under clause 9.1 is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2), because in the monsoon season it is full after the first heavy rain. A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
  • An RWH tank counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing or washing, demonstrated under Clause 4.4.3; watering a garden is not a continuous use in the monsoon season. The tank is then modelled under Clause 4.4.6 like any other retention practice. Outside the recharge ground below, storage and reuse is the way retention is provided, and the 25 L per m² is the first part of it.
  • Recharge pits, trenches, shafts and wells count as retention only where they meet Clause 4.11.4 and the recharge rule below: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume.
  • Hill rule. No deliberate infiltration practice (soakaway, soak or percolation pit, recharge pit, shaft or well, infiltration trench, or permeable paving with an exfiltrating base) shall be built or credited: on natural ground sloping more than 10°; on Siwalik shale, at any slope; on colluvium, slope debris or fill, whatever its slope; in a mapped landslide zone; above a landslide scarp; or upslope of a cut slope or retaining wall within twice the height of the cut or wall — unless a geotechnical certificate by a qualified geotechnical engineer or engineering geologist shows that the added water will not destabilise the slope. On such sites roof runoff goes to rainwater storage of at least 25 L per m² of roof, with overflow to a lined drain, stepped where the ground falls steeply, that discharges through a silt trap and an energy dissipator to a stable natural channel, never onto an unprotected slope. The rule applies in sub-areas AR-C1, AR-D and AR-E of Annex 2A, on the hill rim of AR-A and AR-A1, and on any natural slope of more than 10° anywhere. The APBBL 2019 are its hooks: the earth-cutting rules of 4.39, with the 3 m limit on the height of a cut (4.39(4)), the 2.5 m setback from the property line on the upper terrace (4.39(5)), the duty to clear debris "from site or drain to suitable/safer place" (4.39(8)) and to build a retaining or breast wall "immediately" (4.39(11)), and "Earth cutting permission shall not be granted if the average slope of the topography is more than 30%. And the site will be declared as not fit for construction except for plantation" (4.39(14)); the 0.60 m between a retaining wall and the building (2.10.2(a)); the existing drains on the site plan (2.10.1(j)); and Annexure E's requirement that harvesting structures not "endanger the stability of building or earthwork" (2.2.2). The 30% of 4.39(14), about 17°, is a limit on earth cutting, not an infiltration rule: a slope that may be cut can still be destabilised by water put into it, so the hill rule applies from 10°. Where an earth-cutting permission or a geotechnical report is required, it shall also state whether the site's drainage, storage and any infiltration add water to the slope. On these sites, retention is provided by storage and reuse, and detention by lined tanks, not by ponds or basins on the slope (Commentary to Clause 4.10). The 1.0 m groundwater separation of Clause 4.4.3 does not make an infiltration practice acceptable on a slope: perched water and pore pressure in a slope are the hazard, not the depth to the water table.
  • Septic dispersion on slopes. "A sub- soil dispersion system shall not be closer than 18 m from any source of drinking water, such as well", and not closer than 6 m to the nearest habitable building (APBBL 2019, 4.16.1). On a slope or on shale a dispersion trench or soak pit puts water into the ground that the hill rule protects. This Manual does not override the bye-law, which also keeps septic effluent out of the open drains (4.16.2(c)). It states the conflict and recommends that, on a natural slope of more than 10° or on shale, a dispersion trench or soak pit be sited by a geotechnical engineer, downslope of buildings, cuts and retaining walls and outside the recharge area of any spring (set by this Manual); sewage and septage are dealt with under Clause 8.9.
  • Floodplain rule. No deliberate infiltration practice (soakaway, soak or percolation pit, recharge pit, shaft or well, infiltration trench, or permeable paving with an exfiltrating base) shall be built or credited, on the valley floor of sub-area AR-A and in sub-areas AR-B and AR-C: on land below the 1% AEP flood level of the Dikrong, the Pachin, the Senki, the Siang, the Lohit, the Dibang or the Noa-Dihing or of a nallah; on the palaeochannels and swampy land of the Pachin and Dikrong flood plains; on the margins of a pond (its Zone 1 and Zone 2 under Chapter 7); on flood-plain silts and swamps (HSG C or D, Clause 3.7.2); or wherever the seasonal high water table, the highest level from April to November, is less than 2.0 m below ground. The last condition alone may be set aside where a piezometer record of at least one full April–November season shows that the water table stays at least 2.0 m below ground and at least 1.0 m below the base of the practice (Clauses 4.11.4 and 4.12); the others may not, because a flood or a backed-up nallah puts water over the practice whatever the water table does. On such land roof runoff goes to storage under the RWH credit rule above, and detention is provided in lined, watertight storage, checked for flotation with the design groundwater level at ground level (Clauses 4.12.1 to 4.12.3). The evidence is the CGWB's: 1–5 m below ground in the semi-consolidated formations of Papum Pare and 2–4 m before the monsoon and 2–5 m after it in the Dikrong valley; 1.50–11.13 m in East Siang; 3.58 m and 3.52 m in Lohit in 2008; 2.62–5.50 m in the dug wells of Bhalukpong in the lean period (district booklets); and 15 of the 27 State stations at 0–2 m below ground in August 2025 (water-level bulletin, as summarised) (Commentary to Clause 3.10).
  • Recharge rule. Recharge is not a design objective in Arunachal Pradesh: groundwater is not short, and the stage of extraction is 0.39% (CGWB, 2024, as summarised). Deliberate recharge is allowed only on tested ground outside the hill and floodplain rules: the sandy terrace and valley-fill soils of the Naharlagun–Nirjuli–Doimukh valley, where NERIST's field test at Doimukh found 95.19% sand and a double-ring infiltration rate falling from 12 cm/h to a basic rate of 1 cm/h after 250–300 minutes (Dabral et al., 2016); and the coarse bhabar fan heads above the water table, where the "Siwalik group is the recharge zone" and the piedmont plain "is highly permeable" (CGWB, East Siang district booklet) and "The Bhabar is mostly composed of boulders" (Lohit district booklet), away from scarps and avulsion channels. It is allowed there only after a field infiltration test, where the seasonal high water table stands at least 2.0 m below ground and with the separation of Clause 4.12, and through a silt trap, a filter and a first-flush diverter ahead of the recharge structure. Iron is the main quality issue in the State's groundwater (Papum Pare springs 0.14–0.78 mg/L; East Siang and Changlang flagged; CGWB district booklets), so no recharge structure shall be placed within 30 m of a dug well or spring used for drinking water (set by this Manual). Everywhere else rainwater harvesting is storage and reuse.
  • Where the bye-laws require recharge on a forbidden site. Clause 9.7 makes ground water recharge mandatory for buildings on plots of 500 m² and more and for parks, parking, plazas and playgrounds, and Table 9.1 asks for recharge pits or wells on public, commercial and industrial sites. On a site where the hill rule or the floodplain rule forbids infiltration, this Manual does not override the bye-law. It states the conflict plainly: on such a site the Manual requires storage and reuse in place of recharge, with the overflow to a lined drain, and the applicant seeks the Authority's relaxation of any recharge element of the plan, citing this rule and, where one is required, the geotechnical report. Until the Authority relaxes it, the bye-law stands, and a recharge structure built on such a site earns no credit under this Manual.
  • Springs. Springs supply many hill settlements: in Papum Pare they discharge 0.43–2 L/s before the monsoon and 0.02–2.4 L/s after it, "most of the springs become dry during dry season", and in the northern hills of East Siang springs are the only source (CGWB district booklets); springs were not otherwise researched for this Manual, and no spring inventory or statute was found [TBC]. The Municipal Corporation Act vests "all public streams, springs and works for the supply, storage and distribution of water" in the Corporation. In the recharge area of a spring above a town's or a village's intake, where it has been mapped, no surface shall be paved except for access, no road or parking runoff shall be led into the ground, and no infiltration facility, soak pit or septic tank shall be placed; and drains, cuts and fills shall not intercept the flow to a spring or bury its outlet (the spring rule of Chapter 7, set by this Manual).
  • Polluted runoff. Runoff from fuel stations, workshops, industrial premises and the like, and from any drain or nallah that carries sewage, as most of the capital's drains do ("storm water drains being used as sewers", Master Plan of Itanagar Capital Region-2031, report), shall not be recharged; road and parking runoff shall be recharged, where the recharge rule allows it at all, only through a surface practice with a filter, such as a vegetated basin or trench, never directly into a bore or well (Chapter 8). The bye-laws already ask that recharge structures in industrial areas be kept "away from sewer lines, septic tanks, soak pits, landfill and other sources of contamination" (Table 9.1).

In the hills, water put into the ground does not stay where it is put. The capital lies on Siwalik sandstone, shale and boulder beds whose slopes are "covered by residual soil or slope debris" (CGWB, Papum Pare district booklet), in Earthquake Zone V with "5 fault lines in the city" (Master Plan of Itanagar Capital Region-2031, report). The Laptap landslide in Toru circle of Papum Pare killed 14 people on 11 July 2017 after three days of rain (14 to 16 in different reports; as reported), and earth cutting along NH-415 was blamed for a mudslide near the Donyi Polo airport (as reported). On the valley floors, a recharge pit can sit in the water table in the monsoon season, and in the monsoon season an RWH tank is full after the first heavy rain. Treating RWH as detention would therefore credit storage that does not exist when it is needed. That is why this Manual assumes RWH tanks are full at the start of every storm. Applying the assumption to every season keeps one simple rule. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives. The 25 L per m² sizing rule, the hill rule, the floodplain rule, the recharge rule, the recommendation on septic dispersion, the treatment of the recharge conflict of 9.7, the spring rule and the polluted-runoff rule are set by this Manual. No Arunachal Pradesh source sets a slope or distance threshold for infiltration: the bye-laws' slope number, 30%, governs earth cutting, and a threshold of 15% considered for this Manual is not used. The 10° limit is set by this Manual, as in the mountain editions of this series, because a slope that can carry a building can still be destabilised by water put into it; the shale condition is set by this Manual because the Siwalik shales underlie the capital's slopes and the slides of its hills; and the distance of twice the height of a cut or wall is set by this Manual as a precaution, pending guidance from a geotechnical study for the State [TBC].


4.12 High-groundwater and sandy coastal sites

4.12.1 Design groundwater level. Each site in the valley floor of the capital region, where the CGWB records water levels of 2–4 m below ground before the monsoon and 2–5 m after it in the Dikrong valley and 1–5 m in the semi-consolidated formations of Papum Pare (Papum Pare district booklet), with the palaeochannels and swampy land of the Pachin and Dikrong flood plains; the flood plains and fan toes of the Siang at Pasighat (1.50–11.13 m, East Siang district booklet), the Lohit at Tezu (3.58 m before and 3.52 m after the monsoon of 2008, Lohit district booklet), the Dibang at Roing and the Noa-Dihing at Namsai and Miao; the dug-well ground of Bhalukpong (2.62–5.50 m in the lean period, West Kameng district booklet); the land beside the capital's nallahs; the margins of ponds, swamps and reservoirs; and hill sites with perched water or springs, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the monsoon, from:

  • (a) site piezometer readings over at least one full April–November season; or
  • (b) where (a) is not available, the higher of the CGWB or WRD record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, stream, nallah, pond or reservoir, including the backwater of the Dikrong below the Pare dam in a Naharlagun or Doimukh nallah and of the Siang, Lohit or Noa-Dihing at a Pasighat, Tezu or Namsai outfall.

For the flotation check of 4.12.3 at sites in the Dikrong and Pachin flood plains of the capital region, with their palaeochannels and swamps, the Siang, Lohit and Noa-Dihing flood plains at Pasighat, Tezu and Namsai, land below the 1% AEP flood level of those rivers, and the pond and swamp margins, where (a) is not available, the DGWL shall be taken as existing ground level.

4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:

  • (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
  • (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.

4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:

  • with the facility empty;
  • with groundwater at the DGWL; and
  • for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.

The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.

4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.

4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.

4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.

Commentary. Arunachal Pradesh is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the State, and no saline groundwater was reported in the assessments read for this Manual [TBC]. Iron is the main quality issue: spring water in Papum Pare carries 0.14–0.78 mg/L, and iron is flagged in East Siang and Changlang (CGWB district booklets); and "The soils in the valley areas are sandy loamy in texture with high acidic content" (CGWB, Papum Pare district booklet). Wherever a site test shows iron-rich or acid groundwater, the exposure provisions of 4.12.5 apply to concrete and metal parts as if the groundwater were aggressive, with the exposure class set from the test (set by this Manual). Groundwater lies at two kinds of depth. On the valley floors it is shallow: 1–5 m below ground in the semi-consolidated formations of Papum Pare and 2–4 m before the monsoon and 2–5 m after it in the Dikrong valley (Papum Pare district booklet), 1.50–11.13 m in East Siang, 3.58 m and 3.52 m in Lohit in 2008, and 2.62–5.50 m in the dug wells of Bhalukpong in the lean period (district booklets), with 15 of the 27 State stations at 0–2 m below ground in August 2025 (CGWB, North Eastern Region water-level bulletin, as summarised), and the water higher still beside the Dikrong, the Pachin, the Siang, the Lohit and the Noa-Dihing in flood and beside the nallahs when they back up. In the hills it is deeper, but perched water and springs occur in the slopes. The Pachin and Dikrong flood plains with their palaeochannels and swamps, the main-stem flood plains and fan toes at Pasighat, Roing, Tezu and Namsai, the land beside the nallahs, the pond, swamp and reservoir margins, and hill sites with perched water or springs are the wet cases. There an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when a river in flood, a backed-up nallah, a pond at its outlet level or a reservoir near its full level raises the water table beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, stream, nallah, pond or reservoir where that is higher than the well record, and on the Dikrong and Pachin flood plains, on the Siang, Lohit and Noa-Dihing flood plains at Pasighat, Tezu and Namsai, below the 1% AEP flood level of those rivers and on the pond and swamp margins it is taken as existing ground level for the flotation check unless piezometers show otherwise. On a hill site, a deep tank is not preferred even where groundwater is deep, because a leaking tank on a slope is an infiltration practice by another name: storage on a slope, on shale or on slope debris shall be lined and watertight, and its leakage and overflow taken to a lined drain (Clause 4.11). The April–November monitoring season of 4.12.1(a) is set by this Manual to cover the Manual's monsoon season of 1 April to 31 October, whose pre-monsoon storms can raise the water table in April and May, and the post-monsoon high after the withdrawal in mid-October; a reading taken in March understates the design level. The observation wells are those of the CGWB, North Eastern Region; no State observation-well network was found, and the role this Manual gives WRD as the State's groundwater agency is set by this Manual pending a State network [TBC]. No monsoon water-table depths for individual town sites in Itanagar, Naharlagun, Pasighat or the other towns, and no map of the seasonal high water table, were obtained [TBC]. The factor of 1.2, the 0.5 m allowance, the "ground level" default for the valley floors, the flood plains and the pond, swamp and reservoir margins, and the exposure rule for iron-rich or acid groundwater have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Arunachal Pradesh were found during research.


4.13 Regional detention and fee-in-lieu

4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:

  • (a) a regional detention facility identified in the plan; or
  • (b) a fee-in-lieu paid toward restoration of pond or tank storage identified in the plan.

4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:

  • (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
  • (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
  • (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the monsoon. Storage below FTL that is held for irrigation or supply through April to October shall not be credited.
  • (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
  • (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
  • (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.

4.13.3 Fee. The fee-in-lieu shall be computed as:

Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)

The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.

4.13.4 Ledger. The Authority shall keep a public ledger of:

  • detention volume credited to each regional facility;
  • volume delivered; and
  • fees received and spent.

Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.

Arunachal Pradesh has no tank or pond Act, and no pond, lake or reservoir in or near its towns was found to be operated for flood control under a documented rule. The first Water Bodies Census counted 993 water bodies in the State, 893 rural and 100 urban, with none reported encroached (as summarised from an answer in the Rajya Sabha); the Forest Department's truthing lists 1,127 wetlands of more than 2.25 ha, 944 of them high-altitude lakes and only 2 tanks or ponds, with 6 in Papum Pare district (Department of Environment, Forest and Climate Change); Glaw Lake in Lohit district is reported as the State's first Ramsar site, announced on 3 August 2026 (as reported); and no wetland notified under rule 4 of the Wetlands (Conservation and Management) Rules 2017 was found [TBC]. The bye-laws ask every urban local body and Planning Authority "to identify, demarcate, protect and maintain the water bodies that come under their jurisdiction" and prepare a list (APBBL 2019, Annexure E 1.8); no such list was found [TBC]. The State's regional storage near its towns is of four kinds: the reservoirs above the Pare, Ranganadi and Kameng dams of NEEPCO and the Lower Subansiri dam of NHPC; the few small ponds and swamps of the valley floors, among them the ponds that the capital's drains and sewage reach (Master Plan of Itanagar Capital Region-2031, report); the lakes, such as Ganga Lake in the Itanagar Wildlife Sanctuary; and the low land of the Pachin and Dikrong flood plains and of the main-stem flood plains at Pasighat, Tezu and Namsai, which no floodplain law protects (none was found). Four points follow:

  • A pond on the record may not be a working pond, and a lake is not a detention basin. No inventory of the ponds within the municipal areas or the ICR Master Plan 2031 area, with their beds, rims and outlets, was found [TBC]. A pond is credited only after a survey shows its bed, rim and outlet, and only for the storage above its outlet level; a natural pond keeps its own description and is never turned into a detention pond, and neither is a lake, a spring pool or a reservoir; engineered storage is called a detention pond. Ganga Lake is a lake in a sanctuary and is never counted as detention. A spring-recharge area is not storage for detention (Commentary to Clause 4.11). Where a pond is used as storage, the dry-weather flow of the drains that reach it is intercepted before it (Clause 8.9), because the capital's drains carry sewage: "storm water drains being used as sewers" (report).
  • A reservoir is not spare capacity for a site. The reservoirs are held for power through the season, their releases are set by the operators for the whole river, and their storage below the starting level of Clause 3.12.5 is not credited (Clause 4.13.2(c)); storm water spilled to a reservoir, or to the reach below a dam, can be relied on only with the written agreement of the operator for a stated flow and level. NEEPCO and NHPC are the operators whose data the design needs, not approving authorities.
  • A pond or check dam in the bed of a hill stream or a nallah is not regional detention unless it is designed for debris and garbage. The hill streams carry boulders and slope debris in every large storm, and the capital's drains are "chocked with the solid wastes" (report); such a facility is credited only for the storage left after the sediment and debris volume of Chapter 6, with a debris rack or trap at its inlet, a geotechnical check of its bund and abutments, its failure path mapped, and a maintenance budget for clearing it after each large storm (Chapters 9 and 10). A regional facility on a slope is also subject to the hill rule, and one on a valley floor to the floodplain rule, of Clause 4.11; in a snow-fed or glaciated catchment no storage is credited without the site study of the Commentary to Clause 3.7.
  • No notification divides drains between owners [TBC]. Until one is made, this Manual follows the working split of Chapter 1 and the Commentary to Clause 6.9: public drains, sewers, culverts and watercourses in or under streets, and public streams and springs, as IMC's in its area (Arunachal Pradesh Municipal Corporation Act, 2019, s.200; s.60(a); s.203) and the Pasighat Municipal Council's in its area (Arunachal Pradesh Municipal Act, 2007, ss.47(1)(a)(ii), 102, 194 and 196); storm drains, sewerage and septage works built by the Department of Urban Affairs and the Smart City companies as theirs until handed over in writing to the urban local body; roadside drains, culverts and scuppers on State roads and NH-415 as PWD's and PWD (Highways)'; rivers, their beds and banks and anti-erosion works as WRD's; water supply as PHED's (not researched [TBC]); the dams, reservoirs and release reaches of NEEPCO and NHPC as theirs, as operators; and drains on community or clan land outside an urban local body as the community's, with no statutory owner. Each town keeps a drain register giving every reach its owner, its land status (community, clan, individual, municipal or Government land), whether it carries sewage or septic overflow, and its outfall (set by this Manual). This is the Manual's working split, not a statutory one; where land is community, clan or private land, a drainage corridor or easement is secured by agreement with the owners or the community, by donation or purchase, or by reservation in a plan, never taken.

The first point is the basis of condition 4.13.2(c) in Arunachal Pradesh. A pond gives flood storage only above its outlet level, unless a notified operating rule commits it to be lowered before the monsoon season. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.


4.14 Simplified methods for small sites

4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.

4.14.2 Method.

  1. Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
  2. Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
  3. Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
  4. Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
  5. Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
  6. Complete Form 4-2 (Tier B site sheet).

Table 4.3 — Tier B permissible site discharge and site storage requirement (template)

Zone (Annex 2A) HSG Imperviousness PSD 2-yr (L/s/ha) PSD 100-yr (L/s/ha), standard PSD 100-yr (L/s/ha), flood-sensitive SSR (m³/ha), standard SSR (m³/ha), flood-sensitive
AR-Z1 Western foothills: AR-A Itanagar capital region (Itanagar–Naharlagun–Nirjuli–Doimukh–Banderdewa) A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
AR-Z1 Western foothills: AR-A1 Western foothills (Bhalukpong–Seijosa–Kimin–Yazali) A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
AR-Z2 Eastern foothills: AR-B Siang–Dibang–Lohit foothills (Pasighat–Ruksin–Likabali–Roing–Tezu) A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
AR-Z3 South-east: AR-C Noa-Dihing plain (Namsai–Chowkham–Bordumsa–Miao) A / B / C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
AR-Z3 South-east: AR-C1 Patkai hills (Changlang–Jairampur–Deomali–Khonsa–Longding) C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
AR-Z4 Hills and high ranges: AR-D Middle hills (Ziro–Daporijo–Aalo–Seppa–Basar–Yingkiong) C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]
AR-Z4 Hills and high ranges: AR-E High ranges (Tawang–Bomdila–Dirang–Mechuka–Anini–Hayuliang) C / D 50% / 70% / 90% [TBC] [TBC] [TBC] [TBC] [TBC]

Worked example (illustrative — not design values).

A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:

  • PSD 100-yr = 356 / 2.0 = 178 L/s/ha
  • SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
  • PSD 2-yr ≈ 17 L/s/ha

Then:

  • Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
  • 100-yr release: 178 × 0.4 = 71 L/s.
  • 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
  • Layout options:
    • a 400 m² underground tank 1.5 m deep; or
    • 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
    • Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
  • RWH sumps are additional, and are assumed full (Clause 4.11).

Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.

4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:

  • (a) the site counts tank or waterbody storage in its design (Chapter 7);
  • (b) any part of the site lies within a waterbody setback (Chapter 7); or
  • (c) the site drains to a tank cascade whose storage is counted in a downstream design.

The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.

4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:

Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A

where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.

Table 4.3A — Fixed release coefficients (provisional)

Hydrologic soil group C_10 C_2
A (sandy, well drained) 0.05 0.02
B 0.08 0.03
C 0.15 0.08
D (clay, poorly drained) 0.25 0.15

Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).

4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):

V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]

V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]

where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).

4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.

4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.

Figure 4.3 — Fixed-coefficient route: release caps, storage by the mass-curve method and two-stage outlet (schematic) Schematic. Left: cumulative inflow volume against storm duration for the 1% and 50% AEP storms, with straight release lines 1.8 x Q_cap x d; the storage is the largest vertical gap. Right: two-stage outlet. Not to scale. Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3–4.14.7) — schematic, not to scale 0 12 24 36 48 60 72 Storm duration d (h) Volume (m³) V_100 = largest gap V_2 = largest gap 1% AEP inflow 10·C_v·P_100(d)·A Release line 1.8·Q_cap,10·d 50% AEP inflow 10·C_v·P_2(d)·A Release line 1.8·Q_cap,2·d Dots: durations of Clause 2.5.2 (1, 2, 3, 6, 12, 24, 48, 72 h). Pervious C ≥ 0.50 for d ≥ 12 h. Two-stage outlet (Clause 4.14.6) Top of V Top of V_2 Overflow / spillway (Clause 4.9) Upper orifice or weir: total release ≤ Q_cap,10 at top of V Low-flow orifice (≥ 50 mm): passes Q_cap,2 at top of V_2 Retention (Clause 4.4) is provided in addition; no retention credit (Clause 4.14.7) Q_cap,10 = 2.78 × C_10 × i_10 × A ; Q_cap,2 = 2.78 × C_2 × i_2 × A ; (L/s; A in ha; i in mm/h) C_10, C_2 from Table 4.3A by soil group; i_10, i_2 for a 15-minute duration with the climate factor (Clause 2.8) V = max(V_100, V_2); V_T = max over d of [ 10 × C_v × P_T(d) × A − 1.8 × Q_cap × d ] (m³) ; 1.8 = 3.6 × 0.5 (average release of half the cap)

Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).

Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the foothills round Itanagar, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.

The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.


4.15 Safety, fencing and multi-use

4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):

  • (a) maximum depth in the 10% AEP storm: 0.45 m;
  • (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
  • (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
  • (d) no vertical drop greater than 0.3 m within the storage area or at its edge.

4.15.2 Wet basins. Permanent pools shall have:

  • a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
  • an emergent planting fringe that deters entry.

4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:

  • has a vertical wall or headwall drop greater than 0.6 m;
  • exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
  • contains an outlet structure with an opening larger than 300 mm that is not grated.

4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.

4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in the local language and English stating that the area floods during rain, and a depth marker at the deepest point.

4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.

4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.

Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.


4.16 Basis: why peak matching alone fails

Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.

  1. Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
  2. Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
  3. Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
  4. Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
  5. Closed outfalls. In Arunachal Pradesh the governing failure takes three forms. On the valley floor of the capital region it is a river that backs up into the nallahs: Naharlagun's drains run to the Dikrong (Master Plan of Itanagar Capital Region-2031, report), and below Doimukh the Dikrong carries the releases of the Pare dam, reported at a peak of 1,310 m³/s on 31 May 2025 (as reported), and the tailrace of the Ranganadi project, so the nallahs of Naharlagun, Nirjuli and Doimukh cannot empty while the operator releases and the river is high. At the foothill towns it is a main stem whose stage is set far upstream: the CWC level of the Siang at Passighat reached 157.54 m on 11 June 2000, 3.58 m above its danger level, when the Yigong landslide dam breached in Tibet (as transcribed by SANDRP), a stage that local rain did not cause and that no drain at Pasighat can discharge against; the Lohit at Tezu and the Noa-Dihing at Namsai stand in the same way above their towns' outfalls when they are high. No gate or flap gate on any town outfall was found [TBC], and no stage record of how long the Dikrong, the Siang, the Lohit or the Noa-Dihing stays above a town's outfalls was obtained [TBC]. Everywhere in the hills the outfall can also be closed by debris and garbage: hill streams rise within minutes and carry boulders, slope debris and solid waste that bury outfalls and block culverts, as in September 2018, when the Senki View culvert and the Press Colony bridge in Itanagar were washed away (as reported), and the capital's drains are "chocked with the solid wastes" with "heavy silting" (report). No document was found that sets a design river level for any outfall; Chapter 5 sets the design level and the closure to be assumed (Clause 5.8.5), and Chapters 6 and 9 the debris and blockage allowances. A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.

The response in this Manual is layered:

  • release below pre-development (Clause 4.5);
  • retain the frequent storms (Clause 4.4);
  • route long monsoon storms (Clause 4.6.3);
  • prefer regional storage in the pond system (Clause 4.13); and
  • check downstream and at the outfall (Chapter 5).

Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.


4.17 Submittal requirements

Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:

  1. the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
  2. the evidence for the order of measures under Clause 4.3.1;
  3. the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
  4. the retention credit computation (Clause 4.4.6);
  5. the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
  6. a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
  7. stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
  8. the drawdown calculation (Clause 4.7);
  9. outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
  10. the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
  11. the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
  12. the design groundwater level and flotation check (Clause 4.12);
  13. the downstream and tailwater report (Chapter 5, Form 5-1); and
  14. the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).

Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.


References (chapter)

Annexes and forms

Annex / Form Content
4A Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map
4B Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A)
4C Worked example (Tier A) with full routing tables
Form 4-1 Site Runoff Control Report
Form 4-2 Tier B Site Sheet
Form 4-3 Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7)