Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, pond and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any Arunachal Pradesh town. For the urban areas where the evidence identifies them, the basins are at least the following, in the order of the flood-sensitive catchments of Clause 4.5.3.2:
- Itanagar, Senki: the catchment of the Senki through Itanagar to its confluence with the Pachin, with the lift intake of the town's supply, CPCB's monitored stretch at Chandranagar and the Senki View culvert washed away in September 2018 shown, the drain register marking the reaches that carry sewage and the reaches on community, clan or private land, and surveyed flood marks and the 1% AEP level with its sediment, debris and bulking as the boundary, since the river has no gauge;
- Itanagar and Naharlagun, Pachin: the catchment of the Pachin through Itanagar and Naharlagun to the Dikrong near Nirjuli, with its palaeochannels and swampy land mapped and the Dikrong's level at the confluence, from the model of the Dikrong reach below, as the boundary;
- Naharlagun, Nirjuli and Doimukh, Dikrong and Papu Nallah: the catchments that drain to the Dikrong below the Pare dam, Papu Nallah among them, with the outfalls as outfall-closed cases under the interim design tailwater of Clause 5.8.5(a), both failure cases modelled (the river low with the nallahs blocked, and the river high with the Pare release and the Ranganadi tailrace backing up the outfalls), and the surveyed flood marks of 1999, 2017, September 2018, 2024 and May–June 2025;
- NH-415, Itanagar to Naharlagun: the catchments that cross NH-415, with Energy Park, Bank Tinali, Niti Vihar, Abo Tani Colony and the drains of the Bage Tinali–Naharlagun road (as reported), the closures of 2017 and the slides and earth-cutting sites along the road mapped;
- Modirijo and Donyi Polo: the catchments of the streams that flooded Modirijo and Donyi Polo in September 2018, within the basins of the Senki and the Pachin (this Manual's reading [TBC]), with the Press Colony bridge and the landslide from "the dumping area of NH 415" (as reported) mapped, under the hazard-first rule below;
- Pasighat, Siang: the catchments of the town that drain to the Siang and its side channels, with the CWC danger level (153.96 m) as the design boundary and the highest flood level (157.54 m, 11 June 2000) as the check (Clause 5.8.5(c)), the erosion at Jarkong and the Mebo villages (as reported) and the bhabar fan and its avulsion channels mapped;
- Tezu, Lohit: the catchments of the town that drain to the Lohit, with the CWC highest flood level at Tezu (192.14 m, 16 July 1996) as the boundary until a danger level is given [TBC], and the fan and its channels mapped;
- Namsai and Miao, Noa-Dihing: the catchments of the two towns that drain to the Noa-Dihing, with the CWC levels at Namsai (danger level 145.8 m, highest flood level 146.6 m) and Miao (highest flood level 241.57 m) as the boundaries (Clause 5.8.5(c));
- Roing, Dibang: the catchments of the town that drain to the Dibang, which has no CWC site, with the 1% AEP level from a hydraulic model and the surveyed flood marks as the boundary;
- Yazali, Ranganadi: the catchments of Yazali and the NEEPCO colony at Poosa on the reach of the Ranganadi at Yazali, where the flood of 24 June (2025 or 2026, a conflict) came from a side stream of about 17 km² while the main river stayed in its channel (as reported), so the side streams are modelled as hill streams (Clause 5.8.5(b)) and the Ranganadi's release as the boundary (Clause 5.8.5(d)); and
- Tawang and Dibang Valley, glacial-lake and outburst reaches: the town catchments below the glacial lakes that NDMA lists as high-risk, 6 in Tawang and 16 in Dibang Valley among the State's 27 (as reported), under the hazard-first rule below.
Hazard first on landslide ground, the outburst reaches and the release reaches (set by this Manual). On the hazard-first sites of Clause 2.3.6(i), which include the landslide ground on Siwalik sandstone, shale and boulder beds, colluvium, slope debris and fill, the earth-cutting sites along NH-415, the bhabar fans and avulsion corridors at Pasighat, Ruksin, Roing, Tezu, Namsai, Bhalukpong and Banderdewa, the main stems of the Siang, Dibang, Lohit, Subansiri, Kameng and Tawang Chu, the glacial lakes and the release reaches below the Pare, Ranganadi, Kameng and Lower Subansiri projects, and in every basin below one of them, the BSMP begins with a hazard screening for landslides, debris flows, flash floods, outbursts and dam releases, made with NDMA's list of glacial lakes, CWC's monitoring of glacial lakes and the hazard maps of APSDMA and the District Disaster Management Authorities where they exist [TBC], and the operators' release reaches [TBC], and in snow-fed and glaciated catchments uses site-specific hydrology in place of a CWC report, which neither report supplies (Clause 2.3.6(b) and (i)). The outburst of the Yigong landslide dam in Tibet on 10–11 June 2000 is the check event for Pasighat: it gave the CWC highest flood level of 157.54 m, 3.58 m above the danger level (as reported), and "a recorded rise of 5.5 m at the Pasighat gauge, 462 km downstream" (a peer-reviewed analysis, as summarised); it lies outside the design storm, and its stage governs siting, floor levels and the screening, not the size of a drain. The ground moves more than the design storm here: 14 people died at Laptap on 11 July 2017 (14 to 16 by other counts) and at least 3 in the Modirijo and Donyi Polo floods of September 2018, and the Siang ran turbid at 425 NTU at Pasighat on 27 November 2017 after landslide dams formed in Tibet (all as reported). The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow, a landslide or an outburst. Other Tier A bodies and the Tier B local bodies define their basins in the first BSMP that covers them. Where a master plan, a Town Planning Scheme, NEEPCO, NHPC, WRD, CWC or a court has a flood level, a reservoir level, a line or an operating rule for a dam or gate, the BSMP shall take its boundary conditions from it and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Arunachal Pradesh a single stream passes through many hands, and through land held in several ways, on its way to a river. In the capital the Senki runs through Itanagar to the Pachin, and supplies 7 MLD of the town's water by lift (Master Plan of Itanagar Capital Region-2031, report); the Pachin "passes through most of the area before it debouches to Dikrang river near Nirjuli" (a CGWB document, as summarised); Naharlagun drains to the Dikrong, whose flood plain, with the Pachin's, carries palaeochannels and swampy land (CGWB, Papum Pare district booklet), and Papu Nallah is a named channel of Naharlagun; and below Doimukh the Dikrong carries the releases of the Pare dam and the tailrace of the Ranganadi project. The three rivers are at once storm drains and sewers: the master plan finds "storm water drains being used as sewers", the Senki at Chandranagar, upstream of the Pachin, is in CPCB's Priority V (2025), and the National Green Tribunal has kept O.A. No. 94/2020/EZ on the Senki, the Pachin and the Dikrong open since November 2020, asking whether two sewage treatment plants would suffice "across the entire stretch of 145 Kms" (as reported). The capital's land is held in several ways at once. The municipal area of the Itanagar Municipal Corporation (Itanagar, Naharlagun, Nirjuli and Banderdewa) and the Itanagar Capital Region of the master plan, which adds Doimukh, are not the Deputy Commissioner's district of the Itanagar Capital Complex; much land near the towns is held by communities, clans and individuals, and the beds of rivers, streams, nallahs, lakes and tanks are the Government's only where they "are not the property of any person or community" (Arunachal Pradesh (Land Settlement and Records) Act, 2000, s.9(1)); so a stream that crosses the capital crosses municipal land, community and clan land, private land and Government land. In Pasighat the town drains to the Siang and its side channels, on whose banks erosion has reached Jarkong near the airfield and the villages of Mebo (as reported), and Tezu, Namsai and Roing drain to the Lohit, the Noa-Dihing and the Dibang. The drains vest in IMC and in the Pasighat Municipal Council (Arunachal Pradesh Municipal Corporation Act, 2019, s.200; Arunachal Pradesh Municipal Act, 2007, s.102), the road drains are PWD's or PWD (Highways)'s, the rivers WRD's, the reservoirs and release reaches NEEPCO's and NHPC's to operate, and the drains on community land outside a ULB the community's. Below them the main stems leave the State: the Siang, the Lohit, the Subansiri, the Ranganadi and the Kameng flow on across the State border, where other plans govern. No rule divides the natural streams from the municipal drains, and no notification divides the drains among their owners (this Manual's reading). This clause makes the basin the planning unit, so that one model carries each stream and nallah from its head on the ridge to the river or reservoir whoever owns each reach, so that a drain register gives every reach an owner, a land status (community, clan, individual, municipal or Government land) and an outfall, and so that the sewage it carries is separated before it reaches the river or a pond (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of the Itanagar Capital Region (Itanagar, Naharlagun, Nirjuli, Doimukh and Banderdewa): the Itanagar Municipal Corporation (IMC), in which the public drains, streams and springs within its limits vest (Arunachal Pradesh Municipal Corporation Act, 2019, s.200), jointly with the Department of Urban Affairs (Town Planning wing), which issues the building bye-laws and prepared the master plan, and the Itanagar Planning Authority, the Local Planning Authority for the region under the Arunachal Pradesh Urban and Country Planning Act, 2007, into whose master plan, layouts and Town Planning Schemes the BSMP is taken (Clause 11.9). Each role is the one the body would have if the Manual were adopted. The Smart City company is a partner for its works until they are handed over. For the basins of Pasighat: the Pasighat Municipal Council, in which the public drains vest (Arunachal Pradesh Municipal Act, 2007, ss.102, 194 and 196), with the Department of Urban Affairs. Where a basin extends beyond a local body's limits, the communities and clans whose land it crosses and the other local bodies and Local Planning Authorities in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1); on community or clan land the BSMP is guidance unless the owners or the community agree to it or a permission or plan carries it.
- No notification dividing the natural streams from the municipal drains, or the drains among their owners, was found; until one is made, this Manual assigns the reaches within each BSMP as follows, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: the Water Resources Department (WRD) for the rivers, their beds and banks, and the anti-erosion works, among them the Dikrong, the Siang, the Lohit, the Noa-Dihing and the Dibang; IMC and the Pasighat Municipal Council for the public drains, streams and springs vested in them; the Department of Urban Affairs and the Smart City companies for the storm drains, sewerage and septage works they have built, until handed over in writing; PWD and PWD (Highways) for the side drains, catch-water drains and culverts of State roads and of NH-415 and the other national highways, with the slide debris and spoil of their works; PHED for water supply [TBC]; NEEPCO and NHPC as the operators of the Pare, Ranganadi, Kameng and Lower Subansiri projects, whose levels and releases a BSMP needs as data, not as approving authorities; the community for the drains on community or clan land outside a ULB, if it adopts the Manual; and the Arunachal Pradesh State Disaster Management Authority (APSDMA), with the District Disaster Management Authorities, for the mapping of landslide, flood, debris and outburst hazards that a BSMP must show.
- In the other towns, which are Tier B: the Lead Authority is named by the Department of Urban Affairs, if the Manual is adopted. Basins draining to a common river reach or reservoir may be grouped into one district-level plan.
APSDMA and the Deputy Commissioner shall be consulted on every BSMP; NEEPCO or NHPC on every BSMP whose basin drains to one of their reservoirs or to the reach below its dam; the Arunachal Pradesh State Pollution Control Board (APSPCB) on every BSMP that proposes works on a drain or stream that carries sewage, among them the Senki, the Pachin and the Dikrong; the owners, communities and clans on every BSMP that crosses their land or needs it for a corridor, storage or outfall, which is secured by agreement, donation, purchase or reservation in a plan, never taken; and, for a basin whose outfall lies on a river that flows on across the State border, the water resources department downstream, through WRD.
The Water Resources Department (WRD) shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, pond, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, rivers, streams, nallahs, ponds and reservoirs | The datum of every level named; outfall invert levels against a surveyed level of the receiving river at the outfall; for the Siang at Pasighat, the Noa-Dihing at Namsai and the Lohit at Tezu, the CWC danger level and highest flood level (as transcribed by SANDRP, as reported) on CWC's datum once stated [TBC], with the Pasighat HFL of 11 June 2000 marked as an outburst stage from Tibet; for the Senki, the Pachin and the Dikrong in the capital and the Dibang at Roing, which have no CWC site, surveyed flood marks (on the Dikrong those of 1999, 2017, September 2018, 2024 and May–June 2025) and any local gauge kept as a separate series; for the hill streams and nallahs, surveyed flood marks, the debris and garbage lines of past floods and the 1% AEP flood level with its sediment, debris and bulking; for outfalls on the release reaches of the Pare, Ranganadi, Kameng and Lower Subansiri projects, the levels, spillway and gate data and release records of NEEPCO and NHPC on a named datum, naming which is used [TBC]; ponds at their surveyed spill levels; the glacial lakes, landslide dams and debris fans above the basin, from NDMA's list and CWC's monitoring, and the landslide and flood hazards from the inventories of APSDMA and the District Disaster Management Authorities where they exist [TBC]; and the flap gates, penstocks, debris racks, screens, silt traps, debris basins and any pumping stations on the outfalls, with their capacities and operating rules |
| Rainfall and levels | All available rain gauges (IMD, including the network reported by the Meteorological Centre Itanagar, whose automatic weather stations and rain gauges were not listed in any source found [TBC], and the IMD stations at Pasighat (42220), Tezu (01203), Ziro (42312, printed "Zero") and Hayuliang (01212, rain records 1971–1985); the daily gauge of NERIST at Doimukh (1988–2012); the State ordinary gauges used in the CWC Flood Estimation Report for subzone 2(a), which are not named on the pages read [TBC]; the CWC sites on the Siang, the Noa-Dihing, the Lohit, the Subansiri and the Ranganadi; the rain and reservoir records of NEEPCO and NHPC at the Pare, Ranganadi, Kameng and Lower Subansiri projects [TBC]; and any gauges or sensors kept by the Itanagar Municipal Corporation, the Pasighat Municipal Council, the Smart City companies, WRD and the Arunachal Pradesh State Disaster Management Authority (APSDMA) [TBC]) and water-level records, including those for the September 2018 (the Modirijo and Donyi Polo floods in Itanagar–Naharlagun on or about 14 September, with 3 dead and at least 4 missing in early reports and up to 7 dead in later ones, a conflict, the Senki View culvert and the Press Colony bridge washed away, as reported, and no rainfall value found), 23 June 2024 (Itanagar and Naharlagun, with 66 houses inundated, as reported, and 40 mm between 10:30 and 12:30 "As per IMD", as quoted from the secretary of the State's disaster management authority, who said that IMD "confirmed there was no incident of cloudburst"), July 2024 (the reported Itanagar "cloudburst" of about 28 July, with NH-415 submerged and homes near Energy Park and Bank Tinali flooded, as reported, its date in conflict between dateline and publication and kept apart from 23 June, and no rainfall value found), late May to 7 June 2025 (the statewide floods and landslides, with 12 dead by one count and 9 to 11 by others, a conflict, and a peak release of 1,310 m³/s from the Pare dam on 31 May, all as reported, with only press values of rain), 24 June 2025 or 2026 (the Poosa / NEEPCO colony flood at Yazali, dated 2026 by one report and 2025 by another, a conflict, with 73 mm in 24 hours, mostly in 3 hours, as reported) and the 2017 monsoon (the capital's floods that damaged the protection walls of nallahs and closed NH-415, recorded in the Master Plan of Itanagar Capital Region-2031, with no rainfall value found) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the valley floor of Naharlagun, Nirjuli and Doimukh along the Dikrong and the Pachin, with their palaeochannels and swampy land, on the bhabar fans and flood plains of Pasighat, Ruksin, Roing, Tezu and Namsai, where the rivers back up into the drains and the channels can shift, on the release reaches below the dams, and on pond margins and the few flat benches of the hill towns, where a raised road, a dumped fill or a low wall can turn an overflow from one side of a valley floor to the other, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The September 2018 (the Modirijo and Donyi Polo floods in Itanagar–Naharlagun on or about 14 September, with 3 dead and at least 4 missing in early reports and up to 7 dead in later ones, a conflict, the Senki View culvert and the Press Colony bridge washed away, as reported, and no rainfall value found), 23 June 2024 (Itanagar and Naharlagun, with 66 houses inundated, as reported, and 40 mm between 10:30 and 12:30 "As per IMD", as quoted from the secretary of the State's disaster management authority, who said that IMD "confirmed there was no incident of cloudburst"), July 2024 (the reported Itanagar "cloudburst" of about 28 July, with NH-415 submerged and homes near Energy Park and Bank Tinali flooded, as reported, its date in conflict between dateline and publication and kept apart from 23 June, and no rainfall value found), late May to 7 June 2025 (the statewide floods and landslides, with 12 dead by one count and 9 to 11 by others, a conflict, and a peak release of 1,310 m³/s from the Pare dam on 31 May, all as reported, with only press values of rain), 24 June 2025 or 2026 (the Poosa / NEEPCO colony flood at Yazali, dated 2026 by one report and 2025 by another, a conflict, with 73 mm in 24 hours, mostly in 3 hours, as reported) and the 2017 monsoon (the capital's floods that damaged the protection walls of nallahs and closed NH-415, recorded in the Master Plan of Itanagar Capital Region-2031, with no rainfall value found) events are the best calibration data Arunachal Pradesh has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and pond storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but not measured. Arunachal Pradesh's storage is in its ponds, swamps and low land on the valley floors, its lakes and its reservoirs more than in tanks; it has no irrigation tank cascades, so the tank clauses of this chapter apply to ponds, lakes and any impounded water. The Forest Department's truthing lists 1,127 wetlands of 2.25 ha or more in 19 districts, 944 of them high-altitude lakes, 24 aquaculture ponds, 12 ox-bow lakes, 8 waterlogged areas, 3 lakes, 2 tanks or ponds, 1 reservoir and 1 paddy field, with 130 entries found to be shadows and boundaries demarcated for 997; only 6 are in Papum Pare. The first census of water bodies counted 993 in the State, 893 rural and 100 urban, with none reported encroached (a Rajya Sabha answer, as summarised). Ganga Lake (Gyakar Sinyi), in the Itanagar Wildlife Sanctuary about 6 km from Itanagar, faces encroachment and earth-cutting pressure (as reported); it is a lake in a sanctuary, not storage, and is never counted as detention. Glaw Lake in Lohit district was announced as the State's first Ramsar site on 3 August 2026 (as reported). No wetland notified under Rule 4 of the Wetlands Rules, 2017 was found. The master plan records that sewage is "drained to open or vacant land as well as into ponds" and that "The natural water bodies such as ponds and streams are getting polluted", and the bye-laws ask every urban local body and planning authority to "identify, demarcate, protect and maintain the water bodies that come under their jurisdiction" and prepare a list (APBBL 2019, Annexure E, 1.8), but no such list was found. Town Planning Schemes may provide for "the filling-up or reclamation of low-lying, swampy or unhealthy area, or levelling-up of land" (Ordinance No. 5 of 2025), the main statutory risk to ponds, swamps and paddy-field storage in Itanagar–Naharlagun and Pasighat, to which the compensatory storage of Clause 7.6.4 applies. No survey of the storage of any pond, or of the low land and flood plain inside any town, was found.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Arunachal Pradesh has been adopted with a design factor; the State Action Plan on Climate Change (draft, July 2011) projects annual rainfall 5% to 15% lower in the 2030s and 25% to 35% higher by the 2080s, with the pre-monsoon the exception to the decrease of the 2030s, and gives no factor for extreme rainfall or for intensity–duration–frequency relations (a press summary places the decrease in the 2050s, a conflict); the plan reports "spatial variability in rainfall trend (increasing as well as decreasing trend)"; a researcher is reported to find declining totals with more frequent high-intensity events (as reported; no paper seen), which is a reason to keep the factors, not to reduce them, while the Meteorological Centre Itanagar is reported to say that one season is not enough to show a trend (as reported); NIH-DHAARA's projected depths are not used; and on the hazard-first sites of Clause 2.3.6(i), the outburst reaches of the main stems among them, the hazard screening of Clause 11.3.3 is made in every scenario.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the September 2018 (the Modirijo and Donyi Polo floods in Itanagar–Naharlagun on or about 14 September, with 3 dead and at least 4 missing in early reports and up to 7 dead in later ones, a conflict, the Senki View culvert and the Press Colony bridge washed away, as reported, and no rainfall value found), 23 June 2024 (Itanagar and Naharlagun, with 66 houses inundated, as reported, and 40 mm between 10:30 and 12:30 "As per IMD", as quoted from the secretary of the State's disaster management authority, who said that IMD "confirmed there was no incident of cloudburst"), July 2024 (the reported Itanagar "cloudburst" of about 28 July, with NH-415 submerged and homes near Energy Park and Bank Tinali flooded, as reported, its date in conflict between dateline and publication and kept apart from 23 June, and no rainfall value found), late May to 7 June 2025 (the statewide floods and landslides, with 12 dead by one count and 9 to 11 by others, a conflict, and a peak release of 1,310 m³/s from the Pare dam on 31 May, all as reported, with only press values of rain), 24 June 2025 or 2026 (the Poosa / NEEPCO colony flood at Yazali, dated 2026 by one report and 2025 by another, a conflict, with 73 mm in 24 hours, mostly in 3 hours, as reported) and the 2017 monsoon (the capital's floods that damaged the protection walls of nallahs and closed NH-415, recorded in the Master Plan of Itanagar Capital Region-2031, with no rainfall value found) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and ponds with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: ponds, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: flap gates on the outfalls of the nallahs and drains of Naharlagun, Nirjuli and Doimukh to the Dikrong and of the town drains of Pasighat, Tezu, Namsai and Roing to the main stems, where a river in flood can close an outfall, with storage behind them, and pumping only where the outfall-closed check of Chapter 5 shows that storage alone cannot serve, since no pumping station on a storm drain was found in the State [TBC]; screens, debris racks and silt traps at the mouths of the nallahs and where the hill streams leave the hills for a valley floor or a fan; debris racks, silt traps and debris basins above the culverts of the hill rim of the capital, of NH-415 and of the other hill roads, with ramps for the machines that empty them; drop structures, chutes, energy dissipators and protected outfalls where steep drains reach a stream or nallah, never an unprotected slope; the interception and screening of dry-weather flow before the outfalls to the Senki, the Pachin and the Dikrong and to the main stems at Pasighat, Tezu, Namsai and Roing, and before any pond used as storage (Chapter 8, Clause 8.9); and release scenarios, agreed with NEEPCO and NHPC, for the drains on the reaches below the Pare, Ranganadi, Kameng and Lower Subansiri projects;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Itanagar, CWC level forecasts for the Siang at Pasighat and the Noa-Dihing at Namsai, warnings of releases from the Pare, Ranganadi, Kameng and Lower Subansiri projects under protocols agreed with NEEPCO and NHPC [TBC], level gauges with alarms on the Senki, the Pachin and the Dikrong in the capital, which have no published gauge today, alerts of outbursts on the Siang from upstream in Tibet and from the glacial lakes that NDMA lists, and the alerts of APSDMA and the District Disaster Management Authorities), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on the springs and streams that supply the hill towns and villages, which in Papum Pare discharge 0.43–2 litres a second before the monsoon and of which "most of the springs become dry during dry season" (CGWB), and their recharge areas above the intakes, which this Manual keeps free of paving and of infiltrated road runoff, the stability of hill slopes on Siwalik shale, colluvium, slope debris and fill, where water put into the ground raises the pore pressure, recharge on the tested sandy terrace and valley-fill soils of the Naharlagun–Nirjuli–Doimukh valley and on the coarse bhabar fan heads, the only ground where it is allowed, and not within 30 m of a dug well or spring used for drinking water (Clause 4.11, recharge rule), although groundwater is not short (stage of extraction 0.39%, CGWB 2024, as summarised), the shallow water table of the valley floors and flood plains, and the quality of the groundwater, which carries iron (0.14–0.78 mg/L in the springs of Papum Pare, CGWB), and of the streams, nallahs, ponds and reservoirs that the runoff reaches (Chapter 8);
- effect on downstream basins and the receiving river, stream, nallah, pond or reservoir; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because the outfalls of the capital's valley floor and of the main-stem towns are closed or limited in the wettest hours, and because the storage left is in ponds, swamps and low land that a Town Planning Scheme may reclaim (Ordinance No. 5 of 2025). The State's planning law is itself being rewritten around storage: Ordinance No. 5 of 2025 defines a "sponge city" as "an area that acts like a sponge, soaking up and retaining water during rain and storms and releasing it slowly" and lets the Government "prepare policy documents for … Sponge City … Risk Informed master Plan" (new s.71(2)(za)); an amending Bill was reported passed on 9 March 2026 (as reported), and its Act number and final text were not found [TBC], so whether that power stands in the amended Act is not known; and no policy document under it was found. The bye-laws already ask for "Artificial or natural Storage of storm water runoff from larger sites" (APBBL 2019, 9.6) and an unpaved area of at least 20% of the recreational open spaces of large projects (Table 14.1). The Master Plan of Itanagar Capital Region-2031, by contrast, proposes a drainage network designed on the "topography of the region and flow gradient", that is, conveyance. This Manual's storage-first rules, on-site detention, ponds and low land kept as storage, and release at pre-development rates (Chapters 4, 7 and 11), are an engineering form of the Ordinance's definition, and the Manual could be offered as technical input to such a policy document; it is not one, and it does not criticise the master plan, which was written for land use. Storage matters here for three reasons. First, the capital's outfalls back up when the Dikrong carries the Pare releases and the Ranganadi tailrace, so removing water faster fills the nallahs sooner when the river is high (Clause 5.8.5(a)). Second, the drains of Pasighat, Tezu and Namsai back up from the Siang, the Lohit and the Noa-Dihing, whose level is set upstream (Clause 5.8.5(c)). Third, water sent downstream faster reaches the reaches across the State border, on the Ranganadi and the Subansiri below the projects, where other plans govern. In the hills storage means a lined tank or a terrace, never a pond that soaks into the ground (Clause 4.11, hill rule); the rainwater storage of at least 25 litres per m² of roof that Clause 4.11 sets, where the bye-laws require harvesting without a volume (APBBL 2019, 9.1), is the first of it, and it also serves the towns when the springs run low in the dry months. Conveyance upgrades on their own move water faster to a nallah outfall that the Dikrong may close when it carries the Pare releases, to a main-stem outfall at Pasighat, Tezu or Namsai whose level is set upstream, to a hill stream whose bed and banks shift with the gravel, slide debris and garbage it carries, to a release reach whose level the dam's releases set, or to the villages and the reaches downstream across the State border. Groundwater in Arunachal Pradesh calls for storage and restraint, not recharge. The State draws little of what it has, with a stage of extraction of 0.39% (CGWB, 2024, as summarised), although the State Action Plan on Climate Change (draft, 2011) reports growing demand on groundwater in the foothill districts as surface sources decline; no State observation-well network was found, and the wells reported are CGWB's [TBC]. In the hills water put into the ground can do harm: Papum Pare "is underlain mostly by Siwalik group of rocks", its hill slopes are covered by residual soil or slope debris, and "The entire older metamorphic formation of Paleozoic is overthrusted over the Younger Tertiary Siwaliks" (CGWB, Papum Pare district booklet), so on Siwalik shale, colluvium, slope debris and fill infiltration raises the pore pressure on slopes that slide. On the valley floors and fans the ground is different but the water is near the surface: the Dikrong valley's water stood 2–4 m below ground before the monsoon and 2–5 m after it, the semi-consolidated formations of Papum Pare 1–5 m, East Siang 1.50–11.13 m, Lohit about 3.5 m (2008) and the dug wells of Bhalukpong 2.62–5.50 m in the lean period (CGWB district booklets), and 15 of the State's 27 stations stood within 2 m of the surface in August 2025 (CGWB, as summarised). In East Siang the "Gondwana group acts as a run off zone while Siwalik group is the recharge zone" and the piedmont plain "is highly permeable", and in Lohit "The Bhabar is mostly composed of boulders while flood plain is composed of fine sand and silt" (CGWB); at Doimukh NERIST measured infiltration falling from 12 cm/h to a basic rate of 1 cm/h after 250–300 minutes on a soil of 95.19% sand (Dabral et al., 2016). Iron is the main quality issue, 0.14–0.78 mg/L in the springs of Papum Pare and flagged in East Siang and Changlang (CGWB). The springs matter more than the wells: in Papum Pare they discharge 0.43–2 litres a second before the monsoon and 0.02–2.4 after it, and "most of the springs become dry during dry season", while in the northern hills of East Siang springs are the only source (CGWB); the Municipal Corporation Act vests "all public streams, springs and works for the supply … of water" in the Corporation, but no spring inventory was found and springs were not researched for this Manual [TBC]. The capital's supply comes from the Senki by lift (7 MLD) and from the Poma (11 MLD) and the Niorch (7 MLD) by gravity (Master Plan of Itanagar Capital Region-2031, report), and the Poma pipeline broke in the floods of June 2025 (as reported). This is why springs and their recharge areas, slope stability, recharge only on the tested sandy terrace soils of the Naharlagun–Nirjuli–Doimukh valley and the coarse bhabar fan heads (Clause 4.11, recharge rule), the shallow water table and groundwater quality are all assessment criteria, and why rainwater harvesting here means storage and reuse. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the Master Plan of Itanagar Capital Region-2031, approved under section 24 of the Arunachal Pradesh Urban and Country Planning Act, 2007, and the master plans of the other Local Planning Areas once any is approved; the layouts approved under that Act (APBBL 2019, 2.10.3); the Town Planning Schemes that Ordinance No. 5 of 2025 provides for, in whatever form the amending Act takes [TBC]; the APBBL 2019, which apply to the whole State; and the buildings permitted under them; on community or clan land outside any of these, the BSMP is guidance for the owners or the community unless they take it up. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Arunachal Pradesh draws no water line in law. No statute or bye-law found sets a numerical setback from a stream, nallah, spring, pond or drain, and no floodplain zoning law or Bill was found (this Manual's reading). What exists is a reference without a number: the site plan must show the "Distance from Nallah/Stream as per the notified rules/norms" and the "Distance from Disaster Prone Area as per norms set by Disaster Management Authority" (APBBL 2019, 2.10.1(e) and (f)), and no such rules or norms were found. The bye-laws also define a Jhot, "A strip of land permanently left open for drainage purposes", which "is not to be used as an access way or a street and is not to be included as a part of setbacks" (definition 69), without a width; ask large projects to keep "The inlet and outlet point of natural drain system … with adequate size of channel for ensuring unrestricted flow of water" (Table 14.1); list "sacred groves, hills, hillocks, water bodies (and the areas adjoining the same)" as natural features to be "listed in notification(s) … / identified in Master Plan" (Chapter 12); and count as flood-prone the areas "flooded under conditions of heavy intensity rains, inundation in depressions, back flow in drains, inadequate drainage, etc. as identified through local surveys in the development plan of the area" (definition of a natural hazard prone area). The plinth is "not less than 300 mm" above the surrounding ground (4.2.1.1), and no high flood level fixed by any local authority was found for any town [TBC]. The master plan's 30 m green buffers line its new 30, 45 and 60 m roads, not its streams (Master Plan of Itanagar Capital Region-2031, report). Town Planning Schemes may provide for "the filling-up or reclamation of low-lying, swampy or unhealthy area, or levelling-up of land" (Ordinance No. 5 of 2025), which can remove the storage this chapter relies on. Much land near the towns is held by communities, clans and individuals, and stream and nallah beds on it are not the Government's (Arunachal Pradesh (Land Settlement and Records) Act, 2000, s.9(1)). Where a master-plan line or a Town Planning Scheme governs, it applies; elsewhere the hydraulic corridor and setback zones of Chapter 7 apply as this Manual's proposal, with a Zone 1 of at least 15 m from the top of bank on every channel draining 8 ha or more, including the capital's nallahs, the Senki, the Pachin and the Dikrong, and round every pond and spring the Manual covers, and a Zone 2 to the 1% AEP extent plus 10 m, whichever is wider; the 15 m is offered as the "norms" to which 2.10.1(e) refers, which the State could notify, and it applies to new development and redevelopment approved under this Manual, not to existing buildings. The corridor is a condition of building permission and layout approval wherever the bye-laws apply, which is the whole State (2.1), and a recommendation for works on community land outside any permission; Zone 1 land that is community, clan or private land is secured by agreement with the owners or the community, by donation, by purchase, or by reservation in a master plan, layout or Town Planning Scheme, never taken by this Manual; where the State decides that land must be obtained compulsorily, the Arunachal Pradesh Municipal Act, 2007 routes it through the "Land of Acquisition Act, 1894" (as printed) and allows "other methods of land assembly including the use of transferable development rights" (s.104), and this Manual states that route and does not invoke it. A BSMP gives the master plans, the Town Planning Schemes and the local surveys of the bye-laws' flood-prone definition the 1% AEP drainage-flood map and the buffer widths of Chapter 7 that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because the APBBL 2019 already require public open spaces of more than 500 m² to have "arrangements for complete utilization and capture of storm water", including "Artificial or natural Storage of storm water runoff from larger sites" (9.6), require on large projects an unpaved area of at least 20% of the recreational open spaces and the inlet and outlet of the natural drain system "maintained with adequate size of channel for ensuring unrestricted flow of water" (Table 14.1), and define a Jhot, "A strip of land permanently left open for drainage purposes" (definition 69), and Ordinance No. 5 of 2025 defines a "sponge city" as "an area that acts like a sponge, soaking up and retaining water during rain and storms and releasing it slowly", but no rule sets a detention volume or a peak-runoff limit; storage placed in a layout's open space builds on these, and because that land still serves as open space, the storage must stay usable as one, and on a hill slope or on shale it is a lined tank or a shallow terrace, never an infiltration basin (Clause 4.11, hill rule). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each monsoon (by 31 March). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Directorate of Town Planning. Draft Master Plan Report for Itanagar Capital Region, GIS Based Master Plan under AMRUT Scheme (drainage 13.10, Maps 28–30; sewerage 13.11), and notice of approval of the Master Plan of Itanagar Capital Region-2031 (Form-II, File No. TP-ULB-21011/3/2021-DirTPULB [E-31358], 30 June 2022; approval of 3 June 2022). https://web.archive.org/web/20250428180542/https://arunachaltp.nic.in/sites/default/files/Report%20IMP2031.pdf
- Department of Town Planning and ULBs. Expression of interest, Preparation of GIS based Integrated Drainage Master Plan and DPR for Itanagar Capital City (File No. DTP/MP-76/2015-16, 31 October 2017). https://web.archive.org/web/20180713211942/http://arunachaltp.nic.in/docs/tender/EOI-%20Drainage%20Master%20Plan.pdf
- The Arunachal Pradesh Urban and Country Planning Act, 2007 (Act No. 3 of 2008), ss.24 and 29, and the Arunachal Pradesh Urban and Country Planning (Amendment) Ordinance, 2025 (Ordinance No. 5 of 2025), new s.71(2)(za) and the provisions on Town Planning Schemes. https://prsindia.org/files/bills_acts/bills_states/arunachal-pradesh/2025/Ord5of2025AR.pdf
- The Arunachal Pradesh Municipal Corporation Act, 2019 (Act No. 8 of 2019), ss.60, 200 and 203; and the Arunachal Pradesh Municipal Act, 2007 (Act No. 4 of 2008), ss.102, 104, 194 and 196. https://prsindia.org/files/bills_acts/acts_states/arunachal-pradesh/2019/Act%208%20of%202019%20Arunachal%20Pradesh.pdf
- The Arunachal Pradesh (Land Settlement and Records) Act, 2000 (Act No. 10 of 2000), s.9(1). https://faolex.fao.org/docs/pdf/ind193861.pdf
- Central Ground Water Board, North Eastern Region. Ground Water Information Booklets, Papum Pare, East Siang, Lohit, West Kameng and Changlang districts; and the assessment of 2024 and the water-level bulletin of August 2025 (as summarised).
- Dabral, P.P., Kumar, A. and Tana, G. (2016). Determination of surface drainage coefficient – a case study of Doimukh (Arunachal Pradesh), India. Agricultural Engineering International: CIGR Journal 18(4), 1–10.
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Government of Arunachal Pradesh, Department of Town Planning and ULBs. Arunachal Pradesh Building Bye-Laws, 2019: 2.10.1, 4.2.1.1, 9.6, Chapter 12, Table 14.1, definitions 69 and natural hazard prone area, and Annexure E. https://web.archive.org/web/20201120074900/http://arunachaltp.nic.in/sites/default/files/APBuildingByelaws2019.pdf
- Department of Environment, Forest and Climate Change, Government of Arunachal Pradesh. Status of Truthing and Boundary Demarcation of Wetland of Arunachal Pradesh (undated). https://arunachalforests.gov.in/
- Central Pollution Control Board (2025). Polluted River Stretches for Restoration of Water Quality (the Senki at Chandranagar, Itanagar, Priority V).
- Government of Arunachal Pradesh. Arunachal Pradesh State Action Plan on Climate Change (draft, July 2011).
- South Asia Network on Dams, Rivers and People (2019). Overview of CWC's flood forecasting sites 2019: North East India (transcriptions of CWC site data; secondary source). https://sandrp.in/
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): Pasighat (42220), Tezu (01203), Ziro (42312) and Hayuliang (01212).
- The Arunachal Times, EastMojo, The Sentinel, Eastern Sentinel, NE Now, India Today NE, Down To Earth, The Wire and PTI (2017–2026). Reports of the drainage plan reviewed in 2021, the twin-city master plan, the Town Planning Schemes Bill, the Pare dam's releases, the Siang's outburst and turbidity events, the glacial lakes, the water bodies census and the floods and landslides of 2017–2026 (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Arunachal Pradesh building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Arunachal Pradesh has a statutory master plan for its capital, a drainage master plan tendered and drafted but not found adopted, and no storm-drainage master plan with a design storm anywhere. The Master Plan of Itanagar Capital Region-2031, covering Itanagar, Naharlagun, Nirjuli, Doimukh and Banderdewa, was approved under section 24 of the Arunachal Pradesh Urban and Country Planning Act, 2007 on 3 June 2022 (notice of approval of 30 June 2022), and is described as the "first city of the country to be notified as GIS-based master plan of AMRUT Mission" (a Union official, as quoted); the report read is titled "Draft", and whether the approved text differs was not checked [TBC]. Its diagnosis is plain: "the storm water drainage system consists of natural drainage system (Nallah) and major drains", "no scheme or work for storm water drains is under execution", "There is no proper storm water network for the overall town area", the drains are "not engineered … open drains or kutcha drains without any flow gradient", "With only 3.7% storm drains along main roads, drainage was marked as a key area of focus", and "rivers like Pachin flowing through densely populated areas had become a waste disposal site". It proposes a "new drainage network … in the Itanagar and Naharlagun regions taking into consideration of the topography of the region and flow gradient" (Maps 28–30) and one sewage treatment plant of 4 MLD, also given as 3.9 MLD, near the Dikrong, but states no design storm, return period or runoff coefficient (this Manual's reading of the text). Its "2289 mm" of annual rain and "170 rainy days" are the plan's own words, with no source given. The Department of Town Planning and ULBs invited expressions of interest on 31 October 2017 for a "GIS based Integrated Drainage Master Plan and DPR for Itanagar Capital City" over 65 km², with a horizon year of 2038 and no return period stated; a plan prepared by En-Geo Consultancy and Research Centre was reviewed by the Chief Minister in June 2021, who asked for "a GIS-based and scientifically approved drainage master plan" with trial sectors in Itanagar and Naharlagun; the Itanagar Municipal Corporation (IMC) sought central funds for a 64 km integrated drainage system; and a master plan for the twin capital cities was announced in August 2024, its relation to the plan of 2022 unclear (all as reported). The adoption of none of these drainage plans was found. No master plan or drainage plan for Pasighat was found [TBC]. The State Action Plan on Climate Change (draft, 2011) budgets Rs 15,000.0 million for "Storm water draining in twenty six urban settlements" without criteria. Ordinance No. 5 of 2025 adds Town Planning Schemes to the Urban and Country Planning Act, whose contents include "drainage, inclusive of sewerage, surface or sub-soil drainage and sewage disposal" and "the filling-up or reclamation of low-lying, swampy or unhealthy area, or levelling-up of land"; the Cabinet approved schemes for 47 urban centres and the Assembly passed an amending Bill on 9 March 2026 (as reported), whose Act number and final text were not found [TBC]. The reclamation clause is the main statutory risk to ponds, swamps and low land kept as storage in Itanagar–Naharlagun and Pasighat (this Manual's reading), and the compensatory storage of Clause 7.6.4 applies to such reclamation. No published document sets a design return period for the storm-drain network of any Arunachal Pradesh town. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by the Department of Urban Affairs, the Itanagar Planning Authority, IMC, the Pasighat Municipal Council, any village authority or community, the Water Resources Department (WRD), the Arunachal Pradesh State Disaster Management Authority (APSDMA), NEEPCO, NHPC or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, nallahs narrowed by encroachment and earth-cutting spoil and choked with garbage, which flood the colonies of Itanagar and Naharlagun both when they block and when the Dikrong backs up into them, slopes that rain, open drains and blocked culverts saturate until they slide, culverts that debris washes out, as at Senki View in September 2018 (as reported), drains that carry untreated sewage to the Senki, the Pachin and the Dikrong, reaches below the Pare and Ranganadi projects whose level the releases set, main-stem outfalls at Pasighat, Tezu and Namsai whose level is set upstream, at Pasighat by outbursts in Tibet, and single streams split between a Municipal Corporation or Council, PWD, WRD and the communities and clans whose land they cross, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Arunachal Pradesh, the seventh North-East edition of this series and its first State with neither a Sixth Schedule area nor constitutional protection of land: to a foothill capital on Siwalik sandstone and shale that slides, whose hill rim drains through steep nallahs to the Senki and the Pachin and whose valley floor at Naharlagun, Nirjuli and Doimukh drains to a Dikrong that carries the releases of the Pare dam; to foothill towns, Pasighat, Tezu, Namsai and Roing, on bhabar fans and flood plains of main stems whose level is set upstream, at Pasighat by outbursts in Tibet; to hill and high-range towns, Ziro, Bomdila, Tawang, Seppa, Daporijo and Aalo among them, where water put into the slope moves the ground and snow lies in winter; to glacial lakes that NDMA lists as high-risk; to rainfall that the national products barely cover, a CWC subzone whose isopluvials stop at the foothills, a capital whose only frequency analysis, from NERIST's gauge at Doimukh, reads about one contour above the plate, and a gridded product that doubles the foothill values; to drains that carry the towns' untreated sewage; to a statewide building rule, the APBBL 2019, with the strongest slope rule of the North-East editions but no number for the distance from a nallah; to a statutory GIS master plan for the capital that diagnoses the drains but sets no design storm; to land held largely by communities, clans and individuals, so that land for a drain or a corridor is secured by agreement, donation, purchase or reservation in a plan, never taken; to a planning law being rewritten around Town Planning Schemes and a "sponge city"; and to a wet season that begins with the April storms of the east and the May rain of the foothills, so that on landslide ground, on the outburst reaches and below the dams a BSMP begins with the hazard, not the storm (Clause 11.3.3).