Annexes to Chapter 2Design Rainfall and Design Storms
These annexes support Chapter 2. Annexes 2A to 2E will hold the statewide rainfall tables that Chapter 2 refers to: the benchmark checks and zone map, sub-daily ratios, grid-to-point factors, temporal patterns and retention depths. Each needs analysis of NIH-DHAARA and IMD records that has not yet been done for this Manual, so each is marked "To be prepared" and gives its intended layout and the rule to use until it is published (Clause 1.11.5). Form 2-1 is a draft form for the Design Rainfall Sheet that every hydrologic submittal must include (Clause 2.13). The Manual is a draft; it is not adopted by any government or agency.
Annex 2A — NIH-DHAARA vs IMD station and IMD gridded checks at benchmark points; zone map
Supports Clauses 2.3.1 to 2.3.5 of Chapter 2.
To be prepared. This annex will compare, at benchmark points across the State, the NIH-DHAARA design depths with frequency analyses of long IMD daily station records and of IMD gridded daily data (converted to point values with Annex 2C), for 24 hours and longer and for the AEPs of Table 2.1. It will also contain the map of rainfall zones used by Annexes 2B, 2C and 2E and by the Tier B tables of Chapter 4. It needs NIH-DHAARA values at the benchmark coordinates (NIH), IMD daily and recording-gauge station records and IMD gridded rainfall (IMD), State rain-gauge records (the district rain gauges whose readings IMD tabulates for the Union Territory, the gauges of I&FC, and the gauges of JKSPDC and NHPC at their dams [TBC]), and district and basin boundaries (Survey of India, I&FC). Until it is published, design depths are taken from NIH-DHAARA under Clause 2.3.1, the cross-checks of Clause 2.3.3 are reported on Form 2-1, and the zone of a site is the one agreed with the Authority and recorded on Form 2-1.
Table 2A.1 — Benchmark comparison of design depths (layout)
| Benchmark point | IMD station ID | Latitude, longitude | Years of record | Duration (h) | AEP | NIH-DHAARA (mm) | IMD station analysis (mm) | IMD gridded, point value (mm) | NIH-DHAARA / IMD station | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 24 | ||||||||||
| 48 | ||||||||||
| 72 |
2A.1 The zone names below are the working names used in the Tier B table template of Chapter 4 (Clause 4.14.2). Their boundaries, and whether further zones are needed, are to be set by the analysis of this annex.
Table 2A.2 — Rainfall zones (layout)
| Zone (working name) | Extent (districts, basins) | Representative stations | Notes |
|---|---|---|---|
| JK-Z1 Jammu plains | The plains of the Jammu division south of the Siwalik front, from Akhnoor to Lakhanpur, with the Kandi fans below the hills and the Sirowal below the spring line, in CWC zone 7, Western Himalayas, which covers the whole Union Territory with no part in subzone 1(e) (Clause 2.3.6(b)); south-monsoon regime; catchments that cross a zone line take the higher zone value | Jammu (42056; daily record from 1910) and Jammu Airport; Katra (from 1980) for the front; the district rain gauges of Kathua and Samba; no recording gauge of the zone-7 report | Annual normal 1,401.9 mm at Jammu, 77% in June–September (IMD, normals 1991–2020). FER zone 7 50-yr 24-h about 240–280 mm at Jammu and Akhnoor and about 240 mm at R.S. Pura, Bishnah and Samba; Kathua and Hiranagar not resolved (240–320 mm). NIH-DHAARA 50-yr 24-h 327–411 mm (cross-check only). Records: Jammu 380 mm (27 Aug 2025), 299.2 mm (31 Jul 1961) and 270.4 mm (25 Sep 1988) (IMD) |
| JK-Z1 Jammu plains: JK-A Jammu plains, Kandi and Sirowal (Jammu–R.S. Pura–Akhnoor–Samba–Kathua) | Jammu, Gangyal, Bari Brahmana, Nagrota, R.S. Pura, Bishnah, Arnia, Akhnoor, Khour, Samba, Vijaypur, Kathua, Hiranagar and Lakhanpur; boundaries [TBC] | Jammu (42056) and Jammu Airport; Kathua and Samba (district gauges); Akhnoor (FER Annex 4.3) | FER zone 7 50-yr 24-h about 240–280 mm at Jammu and Akhnoor, 100-yr about 240–280 mm; zone-7 ratios, which give about 102–119 mm in 1 hour at 50 years at Jammu, a depth never measured there (no recording gauge of Jammu was used by the zone-7 report). Record check (Clause 2.3.6(h)): Jammu's 380 mm of 27 Aug 2025 counts and sets the 1% AEP 24-h depth at 380 mm, and the 2% AEP at not less than 340 mm, within 25 km of the Jammu gauge, which takes in Jammu city, Nagrota, Gangyal, Bari Brahmana, R.S. Pura, Bishnah and Akhnoor (NEER reading of distances); Akhnoor 249 mm (25 Sep 1917, FER) excluded until its gauge's record is confirmed [TBC]. NIH-DHAARA 50-yr 24-h 334 mm at Jammu, 343 mm at Akhnoor, 327 mm at R.S. Pura, 351 mm at Samba and 411 mm at Kathua (cross-check only; Clause 2.3.6(m)). Kandi: boulder-gravel fans, water 7–30 m below ground (to 84 m), transmissivity 21–1,197 m²/day at Jammu and 692–2,613 m²/day at Kathua, the preferred recharge zone; Sirowal: finer, water 2–5 m below ground, waterlogging and flowing wells (Hiranagar, Rajpura, Jangi Chak, Airwan, Nagri) (CGWB). Jammu, Samba and Kathua "Safe" in every assessment of 2017–2024 (CGWB). Receiving waters: the Tawi (Sidhra, highest level 321.1 m, 26 Aug 2025; the Tawi barrage, pool level [TBC]); the Chenab at Akhnoor (highest level 324.29 m, 10 Sep 1992); the Ujh, the Basantar, the Devak and the khads of the Kandi; the Ravi and Ranjit Sagar for Kathua; the Tawi, the Basantar, the Ujh and the Chenab cross into Pakistan within about 10–30 km of the towns |
| JK-Z2 Pir Panjal–Chenab hills | The Siwalik, Murree and Lesser Himalayan hills of the Jammu division, from Poonch and Rajouri across Reasi and Udhampur to Ramban, Banihal and the Chenab valley at Doda and Kishtwar, in CWC zone 7 (Clause 2.3.6(b)); monsoon regime on the outer hills, with western-disturbance maxima in February on the Pir Panjal; catchments that cross a zone line take the higher zone value | Batote (from 1977), Banihal (42045; from 1961), Katra (from 1980), Bhaderwah (from 1977); Udhampur IAF (period of record [TBC]); Kawa automatic weather station (Udhampur); the district gauges of Rajouri, Poonch, Reasi, Ramban, Doda and Kishtwar | Gauge normals 2,151.1 mm at Katra, 1,529.0 mm at Batote, 1,364.8 mm at Banihal and 1,227.9 mm at Bhaderwah (IMD, normals 1991–2020). FER zone 7 50-yr 24-h from about 160–200 mm at Poonch and Kishtwar to 240–280 mm at Udhampur, Katra and Banihal and 280–320 mm at Reasi, with a closed cell of more than 320 mm at Mahore–Gulabgarh. Records exceed or reach the plates on the outer front: Batote 316.2 mm and Katra 292.4 mm (25 Sep 1988) (IMD); Udhampur IAF 63 cm (27 Aug 2025, IMD), excluded under Clause 2.3.6(h) [TBC]. Murree and Siwalik "alternating layers of permeable sandstone and weak impermeable clay" (GSI, 2024); subsidence at Pernote, Thathri and Duksar |
| JK-Z2 Pir Panjal–Chenab hills: JK-B Outer and middle hills (Udhampur–Katra–Reasi–Rajouri–Poonch–Ramban–Banihal) | Udhampur, Ramnagar, Chenani, Katra, Reasi, Mahore–Gulabgarh, Rajouri, Sunderbani, Nowshera, Poonch, Surankote, Mendhar, Ramban, Batote, Banihal, Billawar, Basohli and Bani; boundaries [TBC] | Katra; Batote; Banihal (42045); Udhampur IAF and the Kawa automatic weather station; Rajouri and Poonch (district gauges) | FER zone 7 50-yr 24-h about 240–280 mm at Udhampur, Katra, Rajouri, Ramban, Batote and Banihal, 280–320 mm at Reasi (a closed cell of more than 320 mm at Mahore–Gulabgarh, taken under Clause 2.3.6(c) as the contour plus one interval) and about 160–200 mm at Poonch; 100-yr about 280–320 mm on the front; zone-7 ratios. Record check (Clause 2.3.6(h)): Batote 316.2 mm and Katra 292.4 mm (25 Sep 1988) count and raise the 1% AEP 24-h depth within 25 km of their gauges wherever the plate reading at the site is lower, for example at Udhampur, about 20 km from Katra, where the 100-yr plate reads about 280 mm (NEER reading of distance); Banihal 205.6 mm (28 Aug 1997) lies below its plate. Excluded [TBC]: Udhampur IAF 63 cm (27 Aug 2025), the gauge's period of record not being in any IMD table read, reported on Form 2-1 beside the design depth as the stress case of the sub-area, about 2.3 times the 100-yr plate; Gulabgarh 371 mm (14 Sep 1906, FER), two places of that name; Poonch 268 mm (31 Aug 1928, FER), gauge period not confirmed. 48- and 72-hour records: Katra 488.6 mm and 698.6 mm (September 2014) (Clause 2.3.6(e)). Recording-gauge hours: Kawa 35 mm in 1 hour and 101 mm in 3 hours (6 Sep 2014). Basohli, Bani and the Sewa lie on the edge of the closed cell over the Ravi hills; the Sewa HE project (383 km², Kathua district) is the one catchment of the zone-7 unit hydrograph in Jammu and Kashmir. Receiving waters: the Tawi at Udhampur (gauge of I&FC: alert 15 ft, danger 20 ft, also given as 17 ft, as reported) and Kishanpur Manwal (442.65 m, 2025); the Chenab and the reaches of Salal (full reservoir level 487.68 m) and Baglihar (840 m), whose gate and flushing operations may since 2025 come without notice downstream (as reported); the khads of the Trikuta, Rajouri and Poonch hills |
| JK-Z2 Pir Panjal–Chenab hills: JK-B1 Inner Chenab hills (Doda–Kishtwar–Bhaderwah) | Doda, Thathri, Bhaderwah, Kishtwar and the lower Paddar valley; boundaries [TBC] | Bhaderwah (from 1977); Doda and Kishtwar (district gauges); the CWC sites at Prem Nagar (Doda) and Gulabgarh (Paddar) | FER zone 7 50-yr 24-h about 200–240 mm at Doda and Bhaderwah and about 160–200 mm at Kishtwar; zone-7 ratios. Records: Bhaderwah 164.4 mm (26 Sep 1988) in one IMD table and 170.2 mm (5 Sep 1995) in another, both below the plate. Cloudbursts at Dachhan (28 Jul 2021) and Chasoti (14 Aug 2025), both unmeasured (as reported). Subsidence at Thathri Nai Basti (2023), where a committee before the NGT found no planned drainage (as reported). Receiving waters: the Chenab (Prem Nagar, 902.56 m in 2025), the Neeru Nallah (1,075.33 m) and the Kalnai (932.7 m), all above their highest levels in 2025 (CWC data as transcribed by SANDRP); Dul Hasti, Ratle and Pakal Dul. Debris-flow and subsidence mapping govern siting (Chapters 6 and 7) |
| JK-Z3 Kashmir valley | The floor of the Kashmir valley, with its Karewa tablelands, from Qazigund and Anantnag to Baramulla, Sopore, Bandipora and Kupwara, in CWC zone 7 (Clause 2.3.6(b)); western-disturbance and snowmelt regime, with September storms; an embanked Jhelum; catchments that cross a zone line take the higher zone value | Srinagar (42027; daily record from 1901), with the recording gauge used by the zone-7 report; Qazigund (42044; from 1962); Kokernag (from 1978); Kupwara (from 1977); the Srinagar and Rambagh automatic weather stations | Annual normal 697.5 mm at Srinagar, 30% in June–September, wettest month March (IMD, normals 1991–2020). FER zone 7 plates: a closed low over Srinagar (25-yr less than 100 mm, 50-yr less than 120 mm, 100-yr less than 160 mm), about 120–160 mm at Baramulla and Sopore and about 160–200 mm at Kupwara and Anantnag at 50 years. Records: Srinagar 147.8 mm (31 Jan 1930); Qazigund 206.0 mm (5 Sep 2014) (IMD) |
| JK-Z3 Kashmir valley: JK-C Kashmir valley floor and Karewas (Srinagar–Anantnag–Pampore–Sopore–Baramulla–Kupwara) | Srinagar (the SMC and SDA area), Ganderbal, Budgam, Pampore, Pulwama, Awantipora, Anantnag, Bijbehara, Kulgam, Shopian, Qazigund, Sopore, Baramulla, Bandipora, Sumbal, Kupwara and Handwara; Uri and the Jhelum gorge below Baramulla, which the research for this Manual did not place, take the rainfall of JK-C with the hill rules of JK-B (Clauses 4.11 and 6.3.6) [TBC]; boundaries [TBC] | Srinagar (42027) and its recording gauge; Qazigund (42044); Kokernag; Kupwara; the automatic weather stations at Srinagar, Rambagh and Anantnag | FER zone 7 24-h at Srinagar read under Clause 2.3.6(c) as the enclosing contour of the closed low: 100 mm at 25 years, 120 mm at 50 years and 160 mm at 100 years; about 120–160 mm at 50 years at Baramulla, Sopore and Uri, about 160 mm at Anantnag, 160–200 mm at Kupwara and 200–240 mm at Qazigund. Zone-7 ratios, which give less than 51 mm in 1 hour at 50 years at Srinagar against its recorded 32 mm (recording gauge, 28 Aug 1975) and about 40 mm (1970–2005, as quoted). Records: Srinagar 147.8 mm (31 Jan 1930), below the 100-yr reading of 160 mm; Qazigund 206.0 mm (5 Sep 2014), below its 100-yr reading of about 240–280 mm; Anantnag 180 mm and Kokernag 149.5 mm (4–5 Sep 2014) (IMD; Ray et al., 2015); Srinagar's own fall of 3–6 Sep 2014 was only about 140–152 mm. Two design cases and the river-stage rule of Clause 2.3.6(g). Alluvium, Gurti clay and Nambal peat on the valley floor, with the water table 0–2 m below ground over the central and south-western valley and flowing wells on both sides of the Jhelum; Upper Karewa of low permeability with perched water, Lower Karewa moderately permeable; CGWB: in Srinagar "there is no scope for artificial recharge to ground water". Receiving waters: the Jhelum behind its embankments (CWC: Ram Munshi Bagh danger level 1,585.48 m, highest level 1,588.99 m, 8 Sep 2014; Sangam danger level 1,590.88 m, highest 1,595 m, 4 Sep 2014; Khanabal 1,595.43 m, 3 Sep 2025; Safapora danger level 1,579.66 m, highest 1,582.1 m; CWC data as transcribed by SANDRP); the gauges of I&FC in feet (Ram Munshi Bagh flood declaration 18 ft, danger 21 ft, as reported; zeros not published); the flood spill channel and the city channels; the Dal (Dal Gate; Nallah Amir Khan), Nigeen, Anchar and Wular (danger 1,578 m, as reported); the marshes of Hokersar, Narkara and Shallabugh. Srinagar drains through pumping stations, 89 in 2019 and 104 permanent dewatering stations in 2026 (as reported) |
| JK-Z4 High mountains | The high Pir Panjal and Great Himalaya above the valley and the Chenab hills, with snow-fed and glacier catchments that the zone-7 report excludes (Clause 2.3.6(i)); western-disturbance snow and rain on snow; hazard-first, with mandatory GLOF, landslide-lake, debris-flow and avalanche screening; catchments that cross a zone line take the higher zone value | Gulmarg (42026; from 1901), with the recording gauge used by the zone-7 report; Pahalgam (from 1978); Sonemarg (FER Annex 4.3); the automatic weather station below the Amarnath cave; the CWC site at Ganeshpura on the Lidder | Gauge normals 1,449.2 mm at Gulmarg (26% in June–September) and 1,273.5 mm at Pahalgam, wettest month March (IMD, normals 1991–2020). FER zone 7 50-yr 24-h about 120–160 mm at Gulmarg and Pahalgam and about 200–240 mm at Sonamarg and Gurez, inside a closed high over Sonamarg. Winter records: Gulmarg 293.4 mm (20 Feb 1967) and 270.3 mm (27 Jan 1957) (IMD); Sonemarg 300 mm (27 Feb 1936, CWC, zone 7, Annex 4.3), all excluded under Clause 2.3.6(h) until IMD states whether they are rain or snow measured as water [TBC] |
| JK-Z4 High mountains: JK-D High mountains and snow-fed catchments (Gulmarg–Pahalgam–Sonamarg–Gurez–Paddar; hazard-first) | Gulmarg, Tangmarg, Pahalgam, Aru, Sonamarg, Gurez, Tulail, Machil, Keran, Karnah, the Warwan valley, Paddar, upper Kishtwar (Marwah), Kokernag–Daksum, Bani–Sarthal and the Amarnath yatra route, and every catchment elsewhere with permanent snow or a glacier; all in UTM zone 43N; boundaries [TBC] | Gulmarg (42026) and its recording gauge; Pahalgam; the Amarnath cave automatic weather station | Zone-7 relations not used for snow-fed catchments; site-specific hydrology and a GLOF, landslide-lake, debris-flow and avalanche screening (Clause 2.3.6(i)); for local catchments below the snow, Clause 2.3.6(c) to (h) apply, with the 1-hour floor of 62 mm of Clause 2.3.6(g)(i). Recording-gauge maxima at Gulmarg: 62 mm in 1 hour and 99 mm in 24 hours (9–10 Sep 1980) (CWC, zone 7, Annex 4.4); Amarnath cave 25 mm in 1 hour (8 Jul 2022), not a cloudburst (MoES). Thin soils over rock and moraine, frozen in winter. Events not driven by rain at the gauges: the flood at the Amarnath cave (8 Jul 2022) and the Chasoti cloudburst (14 Aug 2025) (as reported). Receiving waters: the Sind, the Lidder (Ganeshpura), the Kishanganga at Gurez, the Warwan and the Marusudar, and the Chenab headwaters from Lahaul through Paddar |
Annex 2B — Sub-daily ratios P(t)/P(24h) by zone: NIH-DHAARA (hourly-based) vs the one-third rule
Supports Clauses 2.6.1 to 2.6.4 of Chapter 2.
To be prepared. This annex will tabulate, for each zone of Annex 2A, the ratios of the t-hour to the 24-hour design depth from NIH-DHAARA, which are derived from hourly records, against the ratios implied by IMD Das et al. (2022) and by the one-third rule. It needs NIH-DHAARA depths for each duration at representative points in each zone (NIH), IMD recording-gauge data and the IDF values of Das et al. (2022) (IMD). Until it is published, sub-daily depths are read directly from NIH-DHAARA or an approved station IDF (Clause 2.6.1). Where only daily depths are available, the ratios used are those agreed with the Authority, which in Jammu and Kashmir are those of Clause 2.3.6: the CWC Flood Estimation Report ratios for zone 7 in Table 2B.1, in every sub-area, with the 1-hour floor of 62 mm of Clause 2.3.6(g)(i) in sub-area JK-D, applied to the 24-hour depth before the record check of Clause 2.3.6(h) (Clause 2.6.2), and are recorded on Form 2-1. The one-third rule is not used (Clause 2.6.4).
2B.1 The first row of Table 2B.1 gives the ratios of the one-third rule P(t) = P(24)·(t/24)^(1/3), for comparison only. The 1, 3, 6 and 12 h values are those stated in the commentary to Clause 2.6; the 2 h value is computed from the same formula. The rule shall not be used for design unless this annex confirms it for the zone concerned (Clause 2.6.4).
Table 2B.1 — Ratios P(t)/P(24h) by zone (layout)
| Zone | Source | 1 h | 2 h | 3 h | 6 h | 12 h | 24 h |
|---|---|---|---|---|---|---|---|
| All (reference only, not for design) | One-third rule | 0.35 | 0.44 | 0.50 | 0.63 | 0.79 | 1.00 |
| JK-Z1 (JK-A Jammu plains, Kandi and Sirowal), JK-Z2 (JK-B Outer and middle hills; JK-B1 Inner Chenab hills), JK-Z3 (JK-C Kashmir valley floor and Karewas) and JK-Z4 (the local catchments of JK-D below the snow) | CWC FER zone 7, 10-yr basis, nine recording gauges (interim design ratios, Clause 2.3.6(f); 2-h value interpolated on logarithmic axes; no exception in any sub-area) | 0.425 | 0.600 | 0.725 | 0.845 | 1.00 | |
| JK-Z4 (JK-D), 10% AEP and rarer | 1-hour floor of Clause 2.3.6(g)(i), set by this Manual: not less than 62 mm, the largest hour of the Gulmarg recording gauge (9 Sep 1980), not a ratio | ||||||
| JK-Z3 (JK-C): Srinagar | CWC FER zone 7, Annex 4.4: recording-gauge maxima as ratios to the 24-h maximum of the same record (separate storms: 1 to 12 h on 28 Aug 1975, 24 h on 16–17 May 1975; comparison only) | 0.48 | 0.81 | 0.96 | 0.99 | 1.00 | |
| JK-Z4 (JK-D): Gulmarg | CWC FER zone 7, Annex 4.4: recording-gauge maxima of 9–10 Sep 1980 (comparison only) | 0.63 | 0.64 | 0.66 | 0.85 | 1.00 | |
| JK-Z2 (JK-B): Kawa (Udhampur) | Automatic weather station, storm of 5–6 Sep 2014: 35 mm in 1 hour and 101 mm in 3 hours against 260 mm in the 24 hours to 08:30 on 6 Sep (Ray et al., 2015; a long storm; comparison only) | 0.13 | 0.39 | 1.00 | |||
| All sub-areas (22 town cells) | NIH-DHAARA (IMDAA), 50-yr 1-h / 24-h, queried 13 Nov 2026: 0.10–0.18 in the hill cells (Ramban 0.10; Udhampur and Katra 0.18), 0.20–0.21 on the valley floor and 0.21–0.27 in the Jammu plains, Rajouri and Poonch (not used, Clause 2.3.6(m)) | 0.10–0.27 | 1.00 |
2B.2 Depths from fixed observation windows are converted to true-interval depths with the factors of Clause 2.6.3, repeated in Table 2B.2. They are the standard WMO (Hershfield) values and are not provisional.
Table 2B.2 — Fixed-interval adjustment factors (Clause 2.6.3)
| Number of fixed observation intervals in the duration | Factor |
|---|---|
| 1 | 1.13 |
| 2 | 1.04 |
| 3–4 | 1.02 |
Annex 2C — Grid-to-point factors
Supports Clauses 2.7.1 and 2.7.4 of Chapter 2.
To be prepared. This annex will give the factors that convert grid-average design depths (for example from 0.25° cells) to point depths, by zone, duration and AEP. It needs paired frequency analyses of IMD gridded rainfall and of the IMD and State gauges inside each cell (IMD, I&FC, and the district rain gauges of the Union Territory whose records IMD tabulates [TBC]), the benchmark points of Annex 2A, and a stated method for deriving the factors. Until it is published, design depths are taken as point values from NIH-DHAARA or an approved station IDF (Clauses 2.3.1 and 2.3.2). Grid-average values are not used as design depths unless a conversion agreed with the Authority is recorded on Form 2-1 (Clause 1.11.5).
2C.1 The commentary to Clause 2.7 shows why the factors matter. In Jammu and Kashmir NIH-DHAARA, whose values come from a reanalysis grid of about 12 km, was queried at 22 town cells for this Manual (13 November 2026): its 24-hour depths are close to the plates at Srinagar (140 mm at 50 years) and above them across the Jammu division (334 mm at Jammu, 388 mm at Udhampur and 411 mm at Kathua at 50 years, against about 240–280 mm on the plates), while its 1-hour depths are only 0.10–0.16 of the 24-hour depths in the hill cells and 0.21–0.27 in the plains (NIH-DHAARA; NEER reading). The district totals that IMD publishes after a storm show the size of the gap between an area value and a point: in 4–10 September 2014 the Srinagar district total was 148.0 mm, while the gauge at Qazigund, about 60 km away, recorded 599.8 mm in four days (Ray et al., 2015). Across the Pir Panjal the gauge normals change two- to three-fold within a few tens of kilometres, from 697.5 mm a year at Srinagar to 1,364.8 mm at Banihal and 2,151.1 mm at Katra (IMD, normals 1991–2020). Values of this kind are grid- or area-average values and need these factors before any use as point depths; under Clause 2.3.6 they are not used as design depths in Jammu and Kashmir until this annex and Annex 2A are published, NIH-DHAARA's 24-hour depths are used only as a cross-check in sub-area JK-A, and its 1-hour depths are not used at all (Clause 2.3.6(m)).
Table 2C.1 — Grid-to-point factors (layout)
| Zone | Grid product and cell size | Duration (h) | AEP | Factor (point / grid) | Stations used | Years of record |
|---|---|---|---|---|---|---|
| 24 | ||||||
| 48 | ||||||
| 72 |
Annex 2D — Jammu and Kashmir temporal patterns (Huff curves)
Supports Clauses 2.9.3 and 2.9.4 of Chapter 2, and Clause 11.7.3 of Chapter 11.
To be prepared. This annex will give dimensionless time-distribution (mass) curves of Jammu and Kashmir storms, in the form introduced by Huff (1967), by zone, storm-duration class and quartile, at stated probability levels. It needs storm hyetographs from recording gauges and automatic weather stations (IMD, its automatic weather stations and automatic rain gauges in the Union Territory, under the Meteorological Centre Srinagar, among them those at Srinagar, Rambagh, Jammu Aero, Udhampur IAF, Kawa, Pahalgam, Govindpur and the Amarnath cave, and any recording gauges of I&FC, J&K SDMA and the Smart City companies of Srinagar and Jammu [TBC]), separated into independent storms by a stated rule, and the storms recorded by the recording gauges of the CWC zone-7 report at Srinagar (16–17 May and 28 August 1975) and Gulmarg (9–10 September 1980), the storm of 3–7 September 2014 as recorded at the automatic weather stations at Kawa, Anantnag, Govindpur, Pahalgam, Srinagar and Rambagh, the Srinagar storm of 1 August 2019, the Amarnath storm of 8 July 2022 and the Jammu and Udhampur storm of 26–27 August 2025 among them. Until it is published, design storms use the alternating-block pattern of Clause 2.9.1 and the 48- and 72-hour pattern of Clause 2.9.2; for catchments of 25–5,000 km², the CWC Flood Estimation Report curves may be used with a sensitivity run under Clause 2.9.1 (Clause 2.9.4). SCS Type distributions are not used (Clause 2.9.3). For the disaggregation of daily records in continuous simulation (Clause 11.7.3), the method is agreed with the Authority and recorded (Clause 1.11.5).
Table 2D.1 — Cumulative fraction of storm depth against cumulative fraction of storm time (layout, one table per zone, duration class and quartile)
| Fraction of storm time | 0 | 0.1 | 0.2 | 0.3 | 0.4 | 0.5 | 0.6 | 0.7 | 0.8 | 0.9 | 1.0 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 10% probability curve | 0 | 1.0 | |||||||||
| 50% probability curve | 0 | 1.0 | |||||||||
| 90% probability curve | 0 | 1.0 |
2D.1 Each table shall state the zone, the duration class, the quartile (the quarter of the storm in which most rain fell), the number of storms analysed and the period of record.
Reference: Huff, F.A. (1967). Time distribution of rainfall in heavy storms. Water Resources Research 3(4), 1007–1019.
Annex 2E — Retention percentile depths by zone
Supports Clauses 2.8.3 and 2.10.1 to 2.10.2 of Chapter 2, Clause 4.4 of Chapter 4 and Chapter 8.
To be prepared. This annex will give, for each zone of Annex 2A, the retention design depth P_R: the 24-hour rainfall depth not exceeded on 90% of days with rain (≥ 2.5 mm) in the long-term record (Clause 2.10.1). It needs long daily records at stations in each zone (IMD, I&FC, and the district rain gauges of the Union Territory whose records IMD tabulates [TBC]) and IMD gridded data with the factors of Annex 2C where stations are sparse. Until it is published, P_R is computed by the definition of Clause 2.10.1 from the long-term daily record of a station agreed with the Authority, by the steps in 2E.1, and recorded on Form 2-1 (Clause 1.11.5).
2E.1 Computing P_R from a daily record.
- Take the daily (24-hour) rainfall series of the station for its full record.
- Keep only the days with rain of 2.5 mm or more (wet days).
- Rank the wet-day depths and take the depth not exceeded on 90% of them (the 90th percentile).
- Do not apply the climate factor (Clause 2.8.3) or the fixed-interval factor; P_R is a statistic of everyday rainfall, not an AEP design depth.
- Record the station, the period of record, the number of wet days and P_R on Form 2-1.
Table 2E.1 — Retention depth P_R by zone (layout)
| Zone | Stations or grid cells used | Period of record | Number of wet days (≥ 2.5 mm) | P_R, 90th percentile (mm) | Issued on |
|---|---|---|---|---|---|
| JK-Z1 Jammu plains | |||||
| JK-Z2 Pir Panjal–Chenab hills | |||||
| JK-Z3 Kashmir valley | |||||
| JK-Z4 High mountains |
Form 2-1 — Design Rainfall Sheet
Supports Clauses 2.3 to 2.13 of Chapter 2, and Clause 10.4.1(d) of Chapter 10.
Draft form — Jammu and Kashmir Stormwater Design Manual, Draft v1.0. One sheet for each hydrologic submittal. The steps follow Figure 2.3 of Chapter 2.
Table 2F.1 — Form 2-1: site, source and storms
| No. | Item (clause) | Entry |
|---|---|---|
| A. Site (Clause 2.13, item 1) | ||
| A1 | Project and site | ______ |
| A2 | Site coordinates (latitude, longitude, decimal degrees) | ______ |
| A3 | Rainfall zone (Annex 2A, or as agreed with the Authority) | ______ |
| A4 | Contributing catchment area (km²) (Clause 2.7) | ______ |
| A5 | Design life: more than 25 years / temporary works, 5 years or less (Clause 2.8.2) | ______ |
| A6 | Outfall under tidal or river backwater influence: Yes / No (Clauses 2.5.3, 2.12) | ______ |
| B. Source (Clauses 2.3, 2.3.5; item 2) | ||
| B1 | NIH-DHAARA: version or access date | ______ |
| B2 | Coordinates queried | ______ |
| B3 | Screenshot or export of the values extracted attached: reference | ______ |
| B4 | Station IDF used (Clause 2.3.2): No / Yes — station, ID, distance from site (km) | ______ |
| B5 | Station IDF: years of recording-gauge data (30 or more); published or approved by | ______ |
| B6 | Station IDF: change of terrain or coastal exposure between gauge and site: None / describe | ______ |
| C. AEPs and durations (Clauses 2.4, 2.5) | ||
| C1 | Elements designed and their AEPs (Table 2.1) | ______ |
| C2 | Conveyance: Tc and design duration (not less than 10 min) (Clause 2.5.1) | ______ |
| C3 | Storage: durations checked from {1, 2, 3, 6, 12, 24, 48, 72 h}; 24, 48 and 72 h included (Clause 2.5.2) | ______ |
| C4 | Critical duration found for each storage element | ______ |
| D. Conversions | ||
| D1 | Sub-daily depths: read directly / from Annex 2B ratios / from ratios agreed with the Authority (Clauses 2.6.1, 2.6.2) | ______ |
| D2 | Fixed-interval factor applied: none (true-interval source) / 1.13 / 1.04 / 1.02 (Clause 2.6.3) | ______ |
| D3 | Grid-to-point factor: not needed (point source) / Annex 2C / agreed value (Clause 2.7.1) | ______ |
| D4 | ARF: 1.0 (10 km² or less; single-site storage) / CWC curve / interpolated (Clauses 2.7.2–2.7.4) | ______ |
| D5 | Climate factor: 1.20 (≤ 6 h) and 1.10 (> 6–72 h) / 1.0 temporary works / projected depths under Clause 2.8.4 | ______ |
| E. Cross-checks (Clause 2.3.3; item 4) | ||
| E1 | IMD Das et al. (2022) values for 1–24 h: reported in Table 2F.2 | ______ |
| E2 | CWC zone 7 24-hour point value, catchments of 25–5,000 km²: subzone used | ______ |
| E3 | CWC floor governs for any AEP: No / Yes — AEPs | ______ |
| F. Retention depth (Clause 2.10) | ||
| F1 | P_R (mm) and source: Annex 2E zone value / computed under Annex 2E, 2E.1 — station and period | ______ |
| F2 | No climate factor applied to P_R (Clause 2.8.3): confirmed | ______ |
| G. Design storms (Clauses 2.9, 2.11, 2.12; items 5 and 6) | ||
| G1 | Storms up to 24 h: alternating block, peak at 50%; time step (≤ Tc/3 and ≤ 15 min) | ______ |
| G2 | 48 and 72 h storms: built under Clause 2.9.2 (Table 2F.3) | ______ |
| G3 | Other pattern used: none / Annex 2D / CWC FER with sensitivity run (Clauses 2.9.3, 2.9.4) | ______ |
| G4 | Hyetographs attached as a table and a plot for each design storm: reference | ______ |
| G5 | AMC: III for every design storm of 1 March–31 May on the Kashmir valley floor (JK-C), and there at any time while the Jhelum is at or above flood-declaration level at Sangam or Ram Munshi Bagh; III for every design storm of 1 July–30 September on the Sirowal and valley-floor alluvium of JK-A and in JK-B and JK-B1; III at any time in JK-D and in catchments draining to a reservoir, barrage pond or backwater or to Dal, Anchar or Wular; at any other site or time (including the Kandi and the Karewas), III for a storm that follows or contains a 5-day total of more than 53 mm; II otherwise (Clause 2.11.4) | ______ |
| G6 | Pre-development condition: greenfield, open land in good condition for the mapped HSG (Clause 2.11.5) | ______ |
| G7 | Release criterion: standard, Q_post ≤ 0.9 × Q_pre (Clause 2.11.2) / flood-sensitive, mixed-frequency rule (Clause 2.11.3) | ______ |
| G8 | Tailwater joint cases run (Clause 2.12): case (a) MHWS + sea-level allowance; case (b) 10% AEP 48 h storm with 1% AEP still-water level + sea-level allowance; governing case | ______ |
| H. Prepared by | ||
| H1 | I confirm that the values above are those extracted and used in the submittal. Name, registration number, signature, date | ______ |
Design depth = source depth × fixed-interval factor × grid-to-point factor × ARF × climate factor. Where the design depth is lower than the CWC floor for the same AEP, the floor is adopted (Clause 2.3.3).
Table 2F.2 — Form 2-1: depth table (Clause 2.13, item 3)
| AEP (T-yr) | Duration | Source depth (mm) | Fixed-interval factor | Grid-to-point factor | ARF | Climate factor | Design depth (mm) | IMD Das et al. (2022) (mm) | CWC floor (mm) | Adopted depth (mm) |
|---|---|---|---|---|---|---|---|---|---|---|
Table 2F.3 — Form 2-1: 48- and 72-hour storm construction (Clause 2.9.2)
| AEP (T-yr) | Duration (h) | Total design depth (mm) | 24 h design depth, final 24 h (mm) | Remainder (mm) | Hours before the final 24 h | Uniform intensity before the final 24 h (mm/h) |
|---|---|---|---|---|---|---|
| 48 | 24 | |||||
| 72 | 48 |