Chapter 10Submittals, Review, Operation & Maintenance and Enforcement


10.1 Purpose and scope

10.1.1 This chapter sets out how compliance with this Manual is shown, checked, built, kept working and enforced. It covers:

  • (a) the submittal stages and their contents (Clauses 10.3–10.4);
  • (b) the compliance calculator (Clause 10.5);
  • (c) professional certification and review (Clauses 10.6–10.7);
  • (d) construction inspection and as-built certification (Clauses 10.8–10.9);
  • (e) maintenance declarations, O&M plans, inspection and access (Clauses 10.10–10.13);
  • (f) handover of public assets (Clause 10.14);
  • (g) enforcement (Clause 10.15); and
  • (h) monitoring, post-event review and data publication (Clauses 10.16–10.17).

10.1.2 This chapter applies to every development and public work to which Chapters 4 and 5 apply under Clause 1.5.2. Clauses 10.3.1 (Stage 0), 10.15 and 10.17 also apply to development that is subject only to Clause 1.5.4.

Commentary. A criterion that is not checked at approval, built as approved, and maintained afterwards has no effect. In Jammu and Kashmir the failure is one of missing criteria, of drains that have not kept up with the towns, and of statutory routes that have never been used. No document of H&UDD, the Jal Shakti Department, SMC, JMC, UEED or a Smart City company stating a design return period, intensity or runoff coefficient for the storm drains of any town was found (Chapter 11), and Jammu's own master plan records that roadside drains serve as its storm drains and that only 20% of its roads have them (Jammu Master Plan 2032, §5.1.3). The approval route shapes this chapter. Building permission in the urban local bodies and development authorities follows UBBL-2021, adopted body by body on a common text (the original H&UDD notification was not found [TBC]) and amended by H&UDD under s.395(d) of the J&K Municipal Corporation Act 2000 and s.202 of the J&K Municipal Act 2000 (S.O. 304 of 1 December 2025; a draft of 9 September 2026 cites s.397 instead, as reported). S.O. 304 moved approvals online: plans are auto-scrutinised against the master plan and the bye-laws, rainwater harvesting among the parameters; an application not decided in 15 days is deemed rejected; and the no-objections of the Revenue Department, PHE, PDD, PWD, Sewerage & Drainage, JDA, SDA, LCMA, the Town Planning Organisations, the Forest Department, NHAI, the Pollution Control Board and I&FC, among others, are given online. The bye-laws already ask for much of what a drainage submittal needs: a site plan showing "the approximate location and size of any water body, flood affected areas and contours at an interval of 0.3m in case of the site which has a slope more than 1:20" (cl. 2.6(b)(xi)); a service plan with the rainwater-harvesting system (cl. 2.6(d)); a certificate of the registered technical person (RTP) that "the site is clear from any provisions related to water supply, electric lines, sewers and drains, water bodies" (cl. 2.18); a complete rainwater-harvesting proposal for every plot of 100 m² or more (cl. 10.1); and inspection of the rainwater-harvesting structures "before issuing Completion Certificates or NOCs for service connections", with 100% annual checks above 1,000 m² (cl. 10.6). Building near an irrigation or hydraulic work needs the prior permission of I&FC, which also controls the bed and banks of every water source, city channel and flood spill channel (Water Resources (Regulation and Management) Act 2010, ss.66 and 81; section numbers to be confirmed against an official copy [TBC]). The ULBs run their drains under the J&K Municipal Corporation Act 2000 and the J&K Municipal Act 2000, whose drain sections were not read [TBC]. No rule asks for a drainage report, limits peak runoff, requires on-site detention, sets a "zero runoff" condition or regulates the flooding of basements, and the only flood-related level in the bye-laws is the plinth, not less than 45 cm (cl. 6.1) with the ground floor finished 300 mm above the centre of the road (Table 5-9), which the Manual's flood-level rule of Chapter 6 exceeds. Every stormwater item in this chapter is therefore written so that the architect, engineer or RTP on record can certify it on Forms 1-1, 2-1, 10-2 and 10-3, and the Authority can check it with the OBPS submission, alongside the site plan and the rainwater-harvesting proposal that the bye-laws already require; through the online no-objections of I&FC (outfalls, levels and the flood check), Sewerage & Drainage (connections), LCMA (the Dal–Nigeen catchment) and the Pollution Control Board, which S.O. 304 already routes; and at completion, when cl. 10.6 already calls for an inspection. This chapter is the process.


10.2 Definitions

Term Meaning in this chapter
Submittal A set of documents lodged with the Authority at one of the stages of Clause 10.3.
Drainage report The preliminary (Stage 1) or final (Stage 2) report required by Clause 10.4.
Stormwater facility Any retention, detention, water quality, conveyance, pumping, gate or outfall element required by this Manual, public or private.
Hold point A construction stage at which work shall not proceed until the Authority or the certifying professional has inspected it (Clause 10.8).
As-built certificate The certificate of Clause 10.9 that the facility was built as approved and performs as designed.
Owner The person or body responsible for a facility under its maintenance declaration, or the ULB for a handed-over asset.
O&M plan The operation and maintenance plan of Clause 10.11.
Facility register The public register of facilities of Clause 10.17.

Other terms are defined in Clause 1.4.


10.3 Submittal stages

10.3.1 Submittals shall be made in the following stages, linked to the approval steps of the Jammu and Kashmir Unified Building Bye-Laws 2021 (Table 10.1):

Table 10.1 — Submittal stages and linked approvals

Stage Submittal When Linked approval
0 Pre-application meeting and Form 1-1 (Applicability Determination) Before the planning permission or layout application None (advisory record)
1 Preliminary drainage report With the planning permission or layout application Planning permission / layout approval
2 Final drainage design Before building permit, or before commencement where the permit is issued with the planning permission Building permit / commencement
3 Construction inspections at hold points During construction None (records filed)
4 As-built certificate and verification tests Before the completion certificate Completion / occupancy certificate
5 Maintenance declaration registered, or handover of public assets Before or with the completion certificate Completion certificate; asset acceptance
6 Annual declarations and inspection reports Every year after completion Continuing compliance

10.3.2 Stage 0 is mandatory for:

  • (a) sites of 2 ha or more;
  • (b) sites in a flood-sensitive catchment;
  • (c) sites proposing a variance, waiver, regional facility or fee-in-lieu; and
  • (d) sites draining to a tidal outfall or adjoining a waterbody.

For other sites, Stage 0 is optional, and Form 1-1 is lodged with Stage 1.

10.3.3 Combined stages. For sites of less than 1 ha outside flood-sensitive catchments, the Authority may accept Stages 1 and 2 as one submittal.

10.3.4 Public works. For a public work, Stage 1 is the drainage section of the DPR and Stage 2 is the drainage section of the tender drawings. The sanctioning authority shall not sanction or tender the work until the relevant stage has been reviewed under Clause 10.7.

10.3.5 Changes after approval. Any change that alters impervious area, levels, storage, outlet or outfall after Stage 2 shall be resubmitted, with the compliance calculator re-run, before the change is built.

Figure 10.1 — Submittal, review and approval workflow Two columns: applicant stages 0 to 6 on the left, Approving Authority actions and approval gates on the right. Stages 1 and 2 can be returned with comments for resubmittal. Stage 6 repeats every year. Applicant / certifying professional Approving Authority Stage 0 — Pre-application Form 1-1 Applicability Determination Confirms applicability; advises Mandatory: ≥ 2 ha, flood-sensitive, waterbody Stage 1 — Preliminary drainage report Forms 2-1, 10-1, 10-2, 10-3 comments Check 5 days; review 15 (resubmit 10) → Planning permission / layout Stage 2 — Final drainage design Models, GIS, draft O&M plan, Form 10-3 comments Review 15 working days (resubmit 10) → Building permit / commencement Stage 3 — Construction Hold-point inspections, Form 10-4 Notified of key hold points (3 working days); may attend Stage 4 — As-built certification Survey, re-run, drawdown tests, Form 10-5 Accepts as-built certificate → Completion certificate Stage 5 — Maintenance declaration Form 10-6, or handover with Form 10-8 Enters facility / asset register → Public asset accepted Stage 6 — Every year, pre-monsoon Form 10-7 annual declaration Inspects; enforces (Clause 10.15) Publishes register (Clause 10.17) yearly Approval gate (accent text) Returned with comments; resubmit Periods in working days (Clause 10.7)

Figure 10.1 — Submittal, review and approval workflow (Clauses 10.3–10.10). Original drawing for this Manual.

Commentary. The stages follow the APWA 5600 sequence of preliminary and final stormwater studies, construction inspection and maintenance agreements (APWA 5600, 2006, §5608 and §5609), mapped onto the UBBL-2021 steps a Jammu and Kashmir applicant already follows. Linking Stage 4 to the completion certificate copies the MBBL 2016 RWH model, which requires inspection before the completion certificate (MBBL 2016, §9.6). The 2 ha and 1 ha limits in Clauses 10.3.2 and 10.3.3 have no direct precedent and are set by this Manual.


10.4 Required contents and checklists

10.4.1 Preliminary drainage report (Stage 1). The report shall contain at least:

  • (a) Form 1-1 and, where applicable, Form 1-2 (Variance / Waiver Request);
  • (b) a site plan with existing and proposed levels, impervious areas, and the catchment boundaries draining to and through the site;
  • (c) soils (HSG), the seasonal high groundwater table, and infiltration test results or a test plan (Chapter 3);
  • (d) the Design Rainfall Sheet (Form 2-1), completed as Clause 2.13 requires;
  • (e) the pre-development condition and hydrologic method (Chapter 3);
  • (f) how the hierarchy of Clause 1.2 has been applied: areas preserved, retention method, detention concept and conveyance;
  • (g) preliminary retention, water quality and detention volumes, and release rates, from the compliance calculator (Clause 10.5);
  • (h) the downstream extent and tailwater case (Chapter 5);
  • (i) waterbodies, setbacks and the 1% AEP level (Chapters 6 and 7); and
  • (j) the land reserved for facilities and maintenance access (Clause 10.13).

10.4.2 Final drainage design (Stage 2). The final design shall contain, in addition to updated Stage 1 contents:

  • (a) the final calculations for every storage duration of Clause 2.5.2 and every AEP required by Chapter 4, including the outfall-closed check of Chapter 5;
  • (b) stage–storage–discharge tables for each facility, and the emergency spillway design (Chapter 4);
  • (c) hydraulic design of conveyance elements, inlets and structures (Chapters 6 and 9);
  • (d) the water quality design and the first-flush or gross pollutant trap where required (Chapter 8);
  • (e) construction drawings, details and specifications of every facility;
  • (f) the construction sequence, including protection of retention and infiltration areas from sediment and compaction (Clause 10.8.3);
  • (g) the hold-point schedule (Clause 10.8);
  • (h) the draft O&M plan (Clause 10.11) and draft maintenance declaration (Clause 10.10);
  • (i) the model input files and the GIS data of Clause 10.4.4; and
  • (j) the certificates of Clause 10.6.

10.4.3 Checklist. Each submittal shall include the Drainage Report Checklist (Form 10-1), showing for each item of Clauses 10.4.1–10.4.2 the page or sheet where it is addressed, or the reason it does not apply. The Authority shall not start technical review of a submittal without a completed Form 10-1.

10.4.4 Digital submittal.

  • (a) Reports and drawings shall be submitted as searchable PDF.
  • (b) Hydrologic and hydraulic models shall be submitted in their native, runnable format (for example SWMM .inp, HEC-HMS or HEC-RAS project files), with the version of the software used.
  • (c) Facilities, outfalls, flow paths and catchment boundaries shall be submitted as GIS data (GeoPackage or shapefile) in WGS 84 (EPSG:4326) or the applicable UTM zone (43N, EPSG:32643, which covers the whole Union Territory, from about 73.75° E at Karnah to about 76.78° E in Kishtwar district, with no exception; to be confirmed against the Survey of India boundary), with attributes as listed in Annex 10B.
  • (d) Levels shall be stated relative to a named vertical datum. The relationship to the river datums of the CWC gauges on the Jhelum, the Chenab, the Tawi and the Lidder, the zeros of the I&FC staff gauges read in feet (stated once I&FC publishes them, and never assumed), the lake and reservoir levels of LCMA, WUCMA, I&FC, JKSPDC, NHPC and the other operators, and the flood marks surveyed on ungauged khads and nallahs used in Chapter 5 shall be stated.

10.4.5 Summary of forms used in submittals (Table 10.2):

Table 10.2 — Forms used in submittals

Form Title Stage
1-1 Applicability Determination 0 or 1
1-2 Variance / Waiver Request 1
2-1 Design Rainfall Sheet 1, 2
10-1 Drainage Report Checklist 1, 2
10-2 Compliance Calculator Summary 1, 2, 4
10-3 Professional Design Certificate 1, 2
10-4 Hold-Point Inspection Record 3
10-5 As-built Certificate 4
10-6 Maintenance Declaration 5
10-7 Annual Maintenance Declaration and Inspection Report 6
10-8 Asset Handover Certificate 5

Commentary. Runnable models and GIS data cost the applicant little and let the Authority check the work, and later build a city-wide picture of private storage. Jammu and Kashmir has no notified design return period or design storm for its urban drains, and no document of H&UDD, SMC, JMC, UEED, I&FC or a Smart City company stating a return period, a runoff coefficient or a drain standard was found. The drainage master plan and project report for 767 km² of Srinagar prepared by Egis India, for "a stormwater drainage system that is separate from the sewage system" and modelled in SewerGEMS, publishes no return period, intensity or runoff coefficient (Bentley case study, 2023, as reported); the World Bank's Jhelum and Tawi Flood Recovery Project designed its roads and bridges to the guidelines of the Indian Roads Congress and states no drainage return period (2015); the Srinagar Master Plan 2035 sets benchmarks of 100% coverage and zero waterlogging without a design storm (§13.3); and Jammu's storm-water project report was still to be prepared after its master plan was approved (Jammu Master Plan 2032, §11.1.3). The rainfall studies do not supply one either: IMD's national IDF study (Das et al., 2022) has panels for Srinagar and Jammu, but both repeat a generic curve, about 109 mm/h for one hour at 100 years against the 32–40 mm recorded in an hour at Srinagar, and are not used; and the IDF equation published for Kupwara (Dar et al., 2016) does not reproduce its own tabulated intensities and is not used. The bursts on record are modest, 62 mm in an hour at the Gulmarg self-recording gauge on 9 September 1980 and 32 mm at Srinagar on 28 August 1975 (CWC Flood Estimation Report, zone 7), and 35 mm in an hour and 101 mm in three hours at the Kawa AWS in Udhampur on 6 September 2014 (Ray et al., 2015), but the 24-hour falls are not: 380 mm at Jammu and 630 mm at Udhampur IAF in the 24 hours to 08:30 IST on 27 August 2025 (IMD), against a previous Jammu record of 299.2 mm (31 July 1961; IMD), and Srinagar's city centre was waterlogged after 26.4 mm on 1 August 2019 (as reported). The Union Territory's design values are therefore those of the CWC Flood Estimation Report for zone 7 (Western Himalayas), which covers all of it, with the interim provisions of Chapter 2, including the 24-hour record check that raises the 1% AEP depth near Jammu to 380 mm (Clause 2.3.6(h)), and each submission must state its own design basis. Form 2-1 and Form 10-2 ensure that every design states its inputs.


10.5 Compliance calculator

10.5.1 The State Stormwater Technical Committee shall issue and maintain a compliance calculator: a version-controlled spreadsheet or web tool that, for a given site:

  • (a) applies the applicability tests of Clause 1.5;
  • (b) computes the retention volume from the Annex 2E depth, and the water quality volume (Chapter 8);
  • (c) applies the credits for preserved areas and retained volume against detention (Chapter 4);
  • (d) on the design-aid route (Clause 1.7, S-1), gives retention and detention volumes from the unit-storage tables;
  • (e) on alternative S-2, gives the permissible site discharge for each AEP; and
  • (f) produces the Compliance Calculator Summary (Form 10-2).

10.5.2 Use.

  • (a) Every Stage 1, 2 and 4 submittal shall include Form 10-2 from the current version of the calculator.
  • (b) On the design-aid route, the calculator may be the only storage calculation.
  • (c) Outside the design-aid route, the calculator is a summary and a screening check. It does not replace the hydrograph analysis of Chapter 3. Where a model result differs from the calculator screen by more than the tolerance stated in the calculator guide, the report shall explain why.

10.5.3 Version control. The calculator shall record its version in every output. A new version applies to new submittals 6 months after release, in line with Clause 2.14.2. A submittal shall use one version throughout Stages 1 to 4, unless the Applicant elects a later one.

10.5.4 Openness. The calculator, its user guide, and the source of every table in it shall be published free of charge.

Commentary. The Mid-America Regional Council issued a Compliance Calculator (.xlsm) and a Calculator Start-Up Guide with APWA 5600 Version 2025.01, together with a site activity plan template and the Policy Supplement (MARC stormwater management page, 2025). The calculator turns a layered standard with credits into one consistent set of numbers that a reviewer can check quickly. Singapore achieves a similar effect with a much simpler rule: a single allowable C value of 0.55 for 10-yr storms up to 4 h, applied by formula (PUB Code of Practice, cl. 7.1.5). A Jammu and Kashmir calculator serves Tier B authorities in particular, where it may be the whole calculation.


10.6 Professional certification

10.6.1 Who may sign. Drainage reports and designs shall be prepared and signed by a registered professional (Clause 1.4) competent in hydrology and hydraulics. For any of the following, the signatory shall be a civil engineer empanelled as a Stormwater Design Professional by the Authority or H&UDD:

  • (a) Tier A sites of 1 ha or more;
  • (b) any site in a flood-sensitive catchment;
  • (c) any facility with an embankment, or a high-hazard basin checked for the 0.2% AEP (Chapter 4); and
  • (d) any pumped facility, tide gate or regional facility.

10.6.2 Empanelment criteria shall be issued by H&UDD and shall include a civil engineering degree, relevant experience in drainage design, and completion of a training course on this Manual.

10.6.3 Certificate. The signatory shall complete the Professional Design Certificate (Form 10-3), certifying that:

  • (a) the design complies with this Manual, except for variances listed and approved;
  • (b) the rainfall, soils and tailwater inputs are as recorded in Forms 2-1 and 10-2; and
  • (c) the models submitted reproduce the results reported.

10.6.4 Independent check. Facilities under Clause 10.6.1(c) and (d) shall be checked by a second empanelled professional who is independent of the designer. That professional shall sign Form 10-3 as checker.

10.6.5 False certification. A false or negligent certificate is an offence under Clause 10.15.

Commentary. Singapore requires that its ABC Waters design features used for peak control be endorsed by an ABC Waters Professional who is also a Professional Engineer (Civil) (PUB Detention Tank Guide, 2024). India has no statutory register of professional engineers comparable to Singapore's, so this clause uses the UBBL-2021 registration and adds empanelment for the higher-risk cases. The 1 ha limit is set by this Manual.


10.7 Review procedure and timelines

10.7.1 Completeness check. The Authority shall check each submittal against Form 10-1 within 5 working days and either accept it for review or return it with a list of missing items.

10.7.2 Technical review. The Authority shall complete technical review and issue approval, conditional approval or a single consolidated list of comments within:

  • (a) 15 working days of acceptance for a first submittal; and
  • (b) 10 working days of acceptance for a resubmittal.

10.7.3 No new comments. On resubmittal, the Authority shall not raise new comments on matters that were unchanged and not commented on in the earlier review, unless the matter affects safety.

10.7.4 Review capacity. A Tier B authority, or a Tier A authority for overflow work, may use an empanelled reviewer from the H&UDD list. The empanelled reviewer shall not have worked on the same site. The Authority remains the decision-maker.

10.7.5 Concurrent clearances. Where the permission of I&FC under the Jammu and Kashmir Water Resources (Regulation and Management) Act 2010 for a building in the vicinity of an irrigation or hydraulic work (s.66) or for a work on, or a discharge to, the bed or banks of a river, nallah or other water source, a city channel, the flood spill channel or an embankment (s.81; section numbers to be confirmed against an official copy [TBC]), given as its online no-objection under S.O. 304 of 1 December 2025, the no-objection of Sewerage & Drainage (UEED) for a connection to a public drain or sewer, of LCMA for a site in the Dal–Nigeen catchment or of WUCMA for one that drains to Wular, of the Pollution Control Board (JKPCC) and of SDA or JDA in their areas, the permission of SMC, JMC or the Municipal Council or Committee to connect to a municipal drain or to build over one (J&K Municipal Corporation Act 2000 and J&K Municipal Act 2000, whose drain sections were not read [TBC]), the consent of PW (R&B) or NHAI for a discharge to a side drain or culvert of one of their roads, the views of the J&K Wetland Authority or the Wildlife Department for a work in or next to a Ramsar site or wetland conservation reserve, such as Wular, Hokersar, Hygam, Shallabugh or Surinsar–Mansar, the consent of JKSPDC, NHPC or another operator for a work that drains to its reservoir, the consent of the body that owns or runs the receiving drain where that body is not the Authority (for example Srinagar Smart City Ltd or Jammu Smart City Ltd until its drains are handed over), or another agency's concurrence is required (Chapter 7), the Authority shall forward the submittal on the day it is accepted for review, and the review periods shall run concurrently.

10.7.6 Fit with permit timelines. The periods in Clauses 10.7.1–10.7.2 run within, and do not extend, the overall time limits for planning permission and building permits set by the Government.

10.7.7 Reasons. Every refusal or condition shall state the clause of this Manual on which it is based.

Commentary. The review periods have no direct precedent and are set by this Manual. A single consolidated comment list and the "no new comments" rule follow common good practice for engineering review.


10.8 Construction inspection

10.8.1 Hold points. The approved hold-point schedule (Form 10-4) shall include at least:

  • (a) the excavated base of each retention, infiltration and detention facility, before any media, liner or structure is placed;
  • (b) the outlet structure, orifice and trash screen, before backfill or before the facility is first allowed to fill;
  • (c) the infiltration tests of Clause 10.9.3;
  • (d) the outfall, flap or tide gate and non-return valve, before the downstream connection is made; and
  • (e) pumps and controls, at commissioning.

10.8.2 Each hold point shall be inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs. For sites under Clause 10.6.1, the Authority shall be given at least 3 working days' notice of hold points (a) and (b), and may attend.

10.8.3 Protection during construction.

  • (a) Retention and infiltration areas shall be fenced off from construction traffic and stockpiles.
  • (b) Infiltration facilities shall not be brought into service until the area draining to them is stabilised.
  • (c) Sediment shall be removed from any facility used for temporary sediment control before the as-built survey.

Figure 10.2 — Construction hold points from approval to handover Vertical timeline from Stage 2 approval through construction, verification tests and as-built certification to the maintenance declaration or asset handover. Diamonds mark hold points (a) to (e) of Clause 10.8.1; each step shows the form used. Construction hold points: approval to as-built and handover (not to scale in time) Hold point: work stops until inspected and recorded Other required step Stage 2 Approval Stage 3 Construction Stage 4 Tests and as-built Stage 5 Declaration or handover Final design approved; hold-point schedule set Schedule of hold points approved with the design (Cl. 10.4.2(g), 10.8.1) Form 10-4 (schedule) Protect retention and infiltration areas Fenced off from traffic and stockpiles (Cl. 10.8.3(a)) (a) Excavated base of each facility Retention, infiltration, detention: before media, liner or structure Form 10-4 3-day notice * (b) Outlet structure, orifice, trash screen Before backfill, or before the facility is first allowed to fill Form 10-4 3-day notice * (d) Outfall, flap or tide gate, non-return valve Before the downstream connection is made Form 10-4 (e) Pumps and controls At commissioning Form 10-4 Area stabilised; temporary sediment removed Infiltration not in service until stabilised (Cl. 10.8.3(b), (c)) (c) Verification tests Infiltration retention empties within 72 h; pumps at duty point; gates open and seal (Cl. 10.9.3) Form 10-4 As-built survey and re-run; certificate accepted Licensed surveyor; calculator and model re-run; then completion certificate (Cl. 10.9) Forms 10-5, 10-2 Private facility: maintenance declaration Registered to run with the land; owner and successors bound (Cl. 10.10) Form 10-6 Public asset: handover to the ULB Cleaned, inspected inside, land or easement transferred; defects liability for at least one full monsoon season (Cl. 10.14) Form 10-8 * Notice: for sites under Clause 10.6.1 the Authority is given at least 3 working days’ notice of hold points (a) and (b), and may attend. Every hold point is inspected by the certifying professional and recorded on Form 10-4 with dated, geotagged photographs (Cl. 10.8.2).

Figure 10.2 — Construction hold points from approval to as-built certification and handover, with the form used at each step (Clauses 10.8–10.10 and 10.14). Hold points are lettered as in Clause 10.8.1. Original drawing for this Manual, adapted from the construction-inspection and maintenance-agreement sequence of APWA Section 5600 (2006), §5608.

Commentary. Infiltration facilities fail most often in construction, when they are compacted or filled with silt before they ever operate. Hold points (a) and (c) target that failure. The 3-day notice is set by this Manual.


10.9 As-built certification

10.9.1 Before the completion certificate is issued, the certifying professional shall submit the As-built Certificate (Form 10-5) with:

  • (a) an as-built survey by a licensed surveyor of each facility's levels, storage volume, outlet dimensions and inverts, and the outfall;
  • (b) a re-run of the compliance calculator, and of the model where one was used, with as-built values;
  • (c) the completed hold-point records (Form 10-4); and
  • (d) the final O&M plan and the executed maintenance declaration or handover documents (Clauses 10.10 and 10.14).

10.9.2 Acceptance. The as-built facility is accepted where:

  • (a) the as-built storage volume at each design level is not less than the volume required by Chapter 4;
  • (b) the outlet dimensions and inverts match the approved design; and
  • (c) the re-run shows compliance with every criterion of Chapters 4 and 5.

Any deviation shall be corrected, or re-certified as compliant under Clause 10.3.5.

10.9.3 Verification tests. Every retention facility that relies on infiltration shall be tested after construction to show that it empties within 72 hours, as Chapter 4 requires. Pumped facilities shall be tested at their design duty point. Tide gates and non-return valves shall be shown to open and seal.

10.9.4 The Authority shall not issue the completion certificate until Form 10-5 is accepted.

Commentary. The 72-hour retention drawdown is the criterion of Chapter 4. This Manual requires it to be tested after construction, rather than relying on pre-construction tests alone, because compaction during construction can cut infiltration rates far below the design values.


10.10 Maintenance declarations and covenants

10.10.1 Declaration. The owner of every private stormwater facility shall execute a Maintenance Declaration (Form 10-6) before the completion certificate is issued. The declaration shall:

  • (a) identify each facility, its location and the approved O&M plan;
  • (b) bind the owner and successors in title to operate, inspect and maintain the facility under the O&M plan;
  • (c) grant the Authority a right of entry to inspect, and to carry out works in default under Clause 10.15;
  • (d) prohibit removal, filling, covering, reduction or change of use of the facility without the Authority's approval; and
  • (e) be registered so that it runs with the land and is disclosed to purchasers.

10.10.2 Multi-owner developments. For apartments, layouts and gated communities, the declaration shall name the association or body responsible after handover by the developer. The developer remains responsible until that body is legally constituted and has accepted the declaration in writing.

10.10.3 Annual declaration. Every owner of a facility in a Tier A area, and of any pumped facility, tide gate or regional facility anywhere, shall submit an Annual Maintenance Declaration and Inspection Report (Form 10-7) by 31 May each year. The report shall be signed by the owner and, for facilities under Clause 10.6.1(c) and (d), by an empanelled professional. It shall state that the pre-monsoon inspection of Clause 10.12 has been done and any defects corrected.

10.10.4 Transfer. On sale or transfer, the seller shall disclose the declaration and the latest Form 10-7. The purchaser takes on the obligations from the date of transfer.

Commentary. Singapore requires owners of pumped detention systems to file yearly declarations and documents with PUB (PUB Detention Tank Guide, citing Code of Practice §13.2). Addendum No. 3 to the Code of Practice (16 Apr 2025) introduced annual maintenance declarations for flood barriers and pumped detention tanks, following amendments to the Sewerage and Drainage Act. APWA 5600 (2006, §5608) required easements and maintenance provisions for detention facilities. A registered declaration matters in Jammu and Kashmir because detention tanks under podiums and in basements are easy to convert to parking or storage once the building is occupied. The 31 May date is set by this Manual to fall before the south-west monsoon (June–September), when most Jammu and Kashmir extreme rainfall occurs.


10.11 O&M plans

10.11.1 Every stormwater facility shall have an O&M plan, approved at Stage 2 and finalised at Stage 4. The plan shall include:

  • (a) an inventory and a plan drawing of each facility, with design levels, volumes and outlet details;
  • (b) routine tasks and their frequency: inspection, debris and sediment removal, vegetation care, screen cleaning;
  • (c) the trigger for sediment removal, stated as a depth or a percentage of design volume;
  • (d) inspection checklists matching Form 10-7;
  • (e) for pumped systems, gates and valves: the operating rules, test schedule, standby power, and actions on a cyclone or heavy-rainfall warning;
  • (f) actions to prevent standing water and mosquito breeding, consistent with the drawdown times of Chapter 4;
  • (g) safety measures for confined spaces, deep water and public access;
  • (h) access routes and equipment needed (Clause 10.13);
  • (i) an annual cost estimate and who pays it; and
  • (j) the records to be kept, and for how long.

10.11.2 Public facilities. For facilities owned by a ULB or department, the O&M plan shall be included in the asset register (Clause 10.14.3) and funded in the annual maintenance budget.

Commentary. Jammu and Kashmir has no dated UT or municipal order fixing pre-monsoon desilting. JMC's practice is known from the press: a first phase of desilting "before the end of June" (2017), 191 nallahs and 143 deep drains to be cleaned before the monsoon (2020), and a round-the-clock drive on 29 major nallahs on 18 July 2026; in Srinagar the Divisional Commissioner directed SMC to "start de-silting work of drains … immediately" in August 2018, and SMC ran a city-wide de-watering drive after the snowfall and snowmelt of January 2026 (all as reported); the Srinagar Master Plan 2035 asks only for "periodical desilting". The drains are run by several hands: UEED, whose mandate is "planning, designing and construction of works of sewerage and drainage in urban areas", with the Town Drainage wings of SMC and of the Directorate of Urban Local Bodies Kashmir in Srinagar (Srinagar Master Plan 2035, §13.3) and its Sewerage and Drainage Division (West) within JMC's limits in Jammu; SMC, JMC and the Municipal Councils and Committees for the municipal drains; I&FC for the rivers, nallahs, embankments, the flood spill channel and the city channels; LCMA for Dal and Nigeen and WUCMA for Wular; PW (R&B) and NHAI for the road drains and culverts; and the Smart City companies of Srinagar and Jammu for the drains they build. Srinagar's dewatering stations have been rebuilt by projects rather than run by a rule: about 56 were to be rehabilitated under the Jhelum and Tawi Flood Recovery Project (2015), and 49 upgrades were reported financed under it (as reported). The gates that matter most are run by rules made for other purposes: Baglihar, run by JKSPDC, opened all its spillways on 1 August 2025; Salal, run by NHPC, opens its gates monthly in the monsoon to flush sediment and opened all of them on 12 August 2025; and Ranjit Sagar on the Ravi reached its full reservoir level on 27 August 2025 (all as reported); the Dal Gate closes by itself when the Jhelum rises (Grierson). No operating rule for any flap gate, lock or pumping station in a town of Jammu and Kashmir, linking it to a river stage, a dam release or a rainfall warning, was found in the public domain; the nearest are the flood-declaration and danger stages that I&FC announces on its feet gauges. Every gate and pump in this Manual needs a written rule for what happens when a warning is issued.


10.12 Inspection frequencies

10.12.1 Owner inspections. Owners shall inspect facilities at least as set out in Table 10.3:

Table 10.3 — Minimum owner inspection frequencies

Facility type Routine Pre-monsoon (by 31 May) After a heavy-rainfall event
Retention / infiltration (soakaways, trenches, bioretention, permeable paving) Every 6 months Yes Yes
Surface detention basin or multi-use open space area Every 6 months Yes Yes
Underground or podium detention tank, gravity outlet Every 6 months Yes Yes
Pumped detention, pumps and controls Monthly test run Yes, with full duty test Yes
Flap / tide gate, non-return valve Every 3 months Yes, with seal test Yes
Gross pollutant trap / first-flush device Every 3 months Yes Yes
Private drains and inlets Every 6 months Yes —

A heavy-rainfall event, for this Clause, is a day on which the nearest approved gauge records rainfall at or above the IMD "heavy rainfall" category, or a day for which a red alert is issued for the district. In Jammu and Kashmir, the pre-monsoon inspection of flap gates, penstocks, non-return valves, debris racks, sediment traps, debris basins, culvert inlets and pumped facilities, including every dewatering station of Srinagar and of the other embanked towns of the Kashmir valley floor, the Dal Gate, and the gates on outfalls that the Jhelum, the Tawi, the Chenab or a lake can close, with the desilting and the clearance of boulders, debris and muck from every drain, inlet, rack, trap, basin and culvert and the pump duty and gate seal tests, shall be completed by 31 May; inlets, trash and debris racks, culverts, outfall gates and pumped facilities, with their standby generators and fuel, shall be certified ready by 15 June, before the normal onset of 28 June at Jammu (the monsoon was declared on 13 June in 2021, as reported), with every gate on an outfall to a river or lake operated through its full travel. Pumps, their standby power and the gates shall then be kept on standby, with the monthly test run, until 31 October, after the normal withdrawal of 21 September at Jammu and the withdrawal from most of the Union Territory by 1 October, because storms come after it, as at Jammu (160.0 mm) and Basohli (229 mm) in October 1955, and at an outfall to the Jhelum, the Tawi or the Chenab until the river at the governing gauge has fallen below its flood-declaration or danger stage and the gravity outfalls have reopened, if that is later. On the Kashmir valley floor (sub-area JK-C of Annex 2A), where most rain falls with the western disturbances of December to April and snowmelt follows, inlets, gratings and outfalls shall in addition be cleared of snow, ice and sediment, and every pumping station given a full duty test, by 15 March; the pumps shall be on standby from 1 March to 31 October, and on call in winter whenever snow melts; and every public drain, inlet, outfall and pump sump shall be cleared a second time by 15 August, before the late-August and September storms that brought the floods of 1992, 2014 and 2025. In the hill towns of sub-areas JK-B, JK-B1 and JK-D, and on every drain with an undeveloped hill catchment, every public drain, inlet, debris rack, sediment trap, debris basin and culvert shall be cleared a second time, of the sediment, slide debris and muck of the monsoon, by 31 October. In towns above about 1,500 m, inlets, gratings, catch-water drains and culvert entrances shall be kept clear of snow and ice from December to March, and checked after every snowfall and every winter storm.

10.12.2 Authority inspections. The Authority shall inspect:

  • (a) every facility on a site of 1,000 m² or more, or under Clause 10.6.1(c) or (d), at least once every 2 years, and every year in a flood-sensitive catchment; and
  • (b) a random sample of at least 10% of other facilities each year.

10.12.3 The results of Authority inspections shall be entered in the facility register (Clause 10.17).

Figure 10.3 — Maintenance cycle and responsibility A one-year strip from January to December showing the two rainfall regimes of Jammu and Kashmir: the south-west monsoon of the Jammu division (normal onset 28 June, with the early onset of 13 June 2021 shaded lightly, normal withdrawal 21 September, and withdrawal from most of the Union Territory by 1 October shaded lightly), and the western disturbances of December to April that bring most of the Kashmir valley's rain, peaking in February in the Pir Panjal and in March in the valley, with snowmelt from March to May. Lanes show the seasons; routine inspections; the UT-wide works (desilting and debris clearance with the pre-monsoon inspection and the Form 10-7 declaration by 31 May, inlets, debris racks, culverts, gates and pumps certified ready by 15 June, standby to 31 October); the additional works on the Kashmir valley floor (post-winter clearance of snow and ice and a pump duty test by 15 March, pumps on standby from 1 March to 31 October, a second clearance by 15 August); the hill-town works (inlets kept clear of snow and ice from December to March above about 1,500 m, a post-monsoon debris clearance by 31 October); inspections after heavy rainfall; and Authority inspections. Boxes below show who is responsible: the owner, the ULB and the Authority. Maintenance cycle and responsibility (Clauses 10.10–10.12, 10.14) Western disturbances: Kashmir valley and Pir Panjal W. dist. SW monsoon (Jammu) Early Late Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 15 Mar 31 May 15 Jun 15 Aug 31 Oct Seasons two rainfall regimes Western disturbances Dec–Apr (peak Feb in the Pir Panjal, Mar in Kashmir); snowmelt Mar–May; SW monsoon 28 Jun–21 Sep (Jammu) Routine Monthly: pump test run (continues through the standby period) Every 3 months: gates, valves, GPTs Every 6 months: retention, detention, drains Works readiness, standby UT-wide: by 31 May desilting and debris clearance, inspection, pump and gate tests; by 15 Jun all ready; standby to 31 Oct JK-C valley floor: by 15 Mar snow and ice cleared, pump duty test; pumps on standby 1 Mar–31 Oct; second clearance by 15 Aug Hill towns: above ≈1,500 m, snow and ice Dec–Mar; post-monsoon debris clearance by 31 Oct (JK-B, JK-B1, JK-D) After heavy rain After each day at or above IMD “heavy rainfall”, or a district red alert (in any month, including winter and March storms) Annual declaration Form 10-7 Form 10-7 lodged by 31 May: Tier A facilities; pumped, gate and regional facilities anywhere Authority Every 2 years (yearly if flood-sensitive) for sites ≥ 1,000 m² or Cl. 10.6.1(c), (d); 10% sample of others → register (Cl. 10.17) Who is responsible Owner — private facility Maintenance declaration, Form 10-6; binds successors in title (Cl. 10.10.1) Layouts and apartments: the association; the developer until it accepts (Cl. 10.10.2) Inspects; lodges Form 10-7 ULB — handed-over public asset Accepted with Form 10-8 (Cl. 10.14) O&M plan in the asset register, funded in the annual budget (Cl. 10.11.2) Developer liable for defects and routine maintenance, ≥ one monsoon to 31 Oct (10.14.2) Authority Inspects and records results in the facility register (Cl. 10.12.2–10.12.3) Enforces: notice, penalty, works in default with cost recovered (Cl. 10.15) Publishes the register (Cl. 10.17) Tick positions are illustrative; only 15 March, 31 May, 15 June, 15 August and 31 October are fixed (set by this Manual). Jammu: normal onset 28 June, withdrawal 21 September; most of J&K clear by 1 October (IMD); early onset 13 June 2021 (as reported). Srinagar is wettest in March, Banihal, Batote and Bhaderwah in February; snowmelt Mar–May; storms also in October (Jammu, Basohli, 1955).

Figure 10.3 — Annual maintenance cycle and who is responsible: routine, pre-monsoon (by 31 May) and post-event inspections, the annual declaration (Form 10-7) and Authority inspections (Clauses 10.10–10.12 and 10.14). Original drawing for this Manual. The timing follows the south-west monsoon (June–September); tick positions within the year are illustrative.

Commentary. The split in Clause 10.12.2 follows the MBBL 2016 inspection regime for RWH, which requires 100% monitoring of buildings over 1,000 m² and a 10% random check below that (MBBL 2016, §9.6). The inspection intervals in Table 10.3 are set by this Manual. The dates are set by this Manual for a Union Territory with two rainfall regimes. The 31 May deadline is set for the onset of the south-west monsoon in the Jammu division at the end of June: the normal onset at Jammu is 28 June and the normal withdrawal 21 September (IMD normals from 2020), the monsoon covering most of Jammu and Kashmir by 30 June and withdrawing from most of it by 1 October (IMD), but it was declared on 13 June in 2021 (as reported), and heavy falls come in June, among them 147.9 mm at Katra on 30 June 2017 and 120.0 mm at Banihal on 21 June 1996 (IMD; Jammu's June record is 92.3 mm on the Meteorological Centre's page and 114.8 mm in IMD's Extremes, a conflict). Inlets, racks, culverts, gates and pumps must in addition be certified ready by 15 June, about two weeks before the normal onset. Pumps and gates are kept on standby to 31 October (Figure 10.3), because storms come after the withdrawal, as at Jammu (160.0 mm) on 5 October 1955 and Basohli (229 mm) on 14 October 1955 (IMD; CWC Flood Estimation Report, zone 7), and because the pumps of the Kashmir valley floor are needed until the Jhelum falls, a later date than the storms of the Jammu division alone would need. The Kashmir valley needs more. Srinagar receives 697.5 mm a year, only 30% of it in June–September, and is wettest in March (IMD normals 1991–2020); the Flood Estimation Report found that it receives "only 28% of the annual rainfall during south west monsoon season as against over 55% in the months of December - April in association with western disturbances"; Gulmarg, Qazigund, Kupwara, Kokernag and Pahalgam are wettest in March, and Banihal, Batote and Bhaderwah in February; Srinagar's largest 24-hour fall, 147.8 mm, came on 31 January 1930, Gulmarg's 293.4 mm on 20 February 1967, and Katra's 261.9 mm with 145.2 mm at Jammu on 13 March 2007 (IMD); the water table of the valley is shallowest in May, after the winter rain and snow (CGWB); and SMC had to dewater the city after the snowmelt of January 2026 (as reported). The valley floor is therefore cleared of snow, ice and sediment, and its pumps given a full duty test, by 15 March, ahead of the March–April maximum and the snowmelt, with the pumps on standby from 1 March to 31 October. NDMA (2010) sets 31 March for pre-monsoon desilting nationally; this Manual allows until 31 May UT-wide so that dry-season work can be finished, and sets 15 March on the valley floor, where the wet season begins earlier. The largest floods of both divisions came in September, when monsoon moisture met a western trough (1988, 1992, 2014), and the largest 24-hour falls of the Jammu division in late August (1996, 1997, 2025), so the valley's drains, inlets and pump sumps are cleared a second time by 15 August. Hill drains fill with sediment, slide debris and muck during the monsoon, so in the hill towns of sub-areas JK-B, JK-B1 and JK-D a second clearance is made by 31 October; and above about 1,500 m inlets are kept clear of snow and ice from December to March. No dated UT or municipal order fixing any of these dates was found, and JMC's practice of finishing desilting before the end of June (as reported) is later than this Manual's. The reporting year runs from 1 June to 31 May, so that each year's declaration covers one full monsoon and one full winter. The post-event inspections of Table 10.3 cover storms at any time of year.


10.13 Maintenance access

10.13.1 Every facility shall have permanent access for inspection and maintenance, shown on the approved drawings and protected by the maintenance declaration or, for public facilities, by an easement or land transfer.

10.13.2 Surface facilities. Basins, ponds and open channels shall have a vehicle access route to the inlet, the outlet and the base, and a maintenance strip along at least one side. Ramps into basins shall be suitable for the plant needed to remove sediment.

10.13.3 Underground facilities. Tanks shall have:

  • (a) an access opening over the inlet, the outlet and each chamber;
  • (b) fixed ladders or steps, and ventilation for confined-space entry;
  • (c) a sump or low point for sediment removal; and
  • (d) headroom sufficient for manual cleaning.

10.13.4 Outlets. Orifices and screens shall be reachable for cleaning without entering a full facility.

10.13.5 Access routes shall not be built over, fenced off or used for parking in a way that prevents access.

Commentary. APWA 5600 (2006, §5608) required a 15-ft (about 4.5 m) maintenance access strip for detention facilities. Plot sizes in Srinagar, Jammu and the other cities and towns of Jammu and Kashmir make a fixed width hard to apply to every site, so this Manual sets functional requirements. Annex 10C covers maintenance access dimensions.


10.14 Handover of public assets to the ULB

10.14.1 Drains, roads, open space facilities, regional facilities and other stormwater assets that a developer builds for transfer to a ULB shall be handed over only when:

  • (a) the as-built certificate (Clause 10.9) has been accepted;
  • (b) the facility has been cleaned, and pipes and culverts have been inspected internally (for example by CCTV or manual entry), with the record handed over;
  • (c) the land, or an easement over it, has been transferred to the ULB;
  • (d) the O&M plan, drawings, GIS data and warranties have been handed over; and
  • (e) the Asset Handover Certificate (Form 10-8) has been signed by both parties.

10.14.2 Defects liability. The developer shall remain responsible for defects and for routine maintenance for a defects liability period that includes at least one full monsoon season, from 15 June to 31 October, after handover. The ULB may hold a security deposit for this period.

10.14.3 Asset register. On acceptance, the ULB shall enter the asset in its GIS drainage asset register and in the facility register of Clause 10.17.

10.14.4 Private facilities. A private facility remains the owner's responsibility under its maintenance declaration unless the ULB formally accepts it under this Clause.

Commentary. NDMA (2010) calls for a GIS inventory of drains. Requiring the developer's GIS data at handover builds that inventory as the city grows, at no cost to the ULB. The defects period spans one monsoon because many defects in Jammu and Kashmir drainage show up only in the first SW monsoon.


10.15 Enforcement

10.15.1 Offences. The following are contraventions of this Manual:

  • (a) building without an approved drainage design where one is required;
  • (b) building a facility other than as approved;
  • (c) removing, filling, covering, reducing or changing the use of a facility without approval;
  • (d) failing to maintain a facility, or to submit Form 10-7;
  • (e) a sewage connection to a storm drain;
  • (f) building or filling in a waterbody setback or no-fill zone (Chapter 7);
  • (g) obstructing a natural drainage path or major-system flow path; and
  • (h) false or negligent certification.

10.15.2 Graduated response. The Authority shall respond in the following order, moving to a later step where an earlier one fails or where the contravention is serious (Table 10.4):

Table 10.4 — Graduated enforcement response

Step Action
1 Written notice stating the contravention, the clause breached, the remedy and a compliance period.
2 Stop-work order, or withholding of the completion certificate, for development not yet complete.
3 Penalty under the applicable Act or rules.
4 Works in default by the Authority, with the cost recovered from the owner.
5 Disconnection of the private drain connection to the public system, where this causes no hazard to others.
6 Report of the certifying professional to the registering authority, and suspension from the empanelled list.

10.15.3 Immediate action. Where a contravention puts life or property at risk during a monsoon, the Authority may carry out works in default at once and recover the cost later.

10.15.4 Security deposits. For sites under Clause 10.6.1, the Authority may require a security deposit or bank guarantee, released after the as-built certificate is accepted, to cover works in default.

10.15.5 Record. Every notice and action under this Clause shall be entered in the facility register.

Commentary. Penalties are referred to generically. This Manual cannot itself create offences or fines, and the powers come from the Acts under which the Jammu and Kashmir Unified Building Bye-Laws 2021 are made and from the municipal Acts. The graduated steps are set by this Manual. In Jammu and Kashmir the High Court has become the working regulator of the Jhelum and its water bodies. In the cases on the floods of 2014 it held that "A duty is cast upon the Chief Engineer and other statutory authorities to ensure removal of all encroachments from the banks of River Jhelum along its entire course" (24 November 2014), directed a committee under the Divisional Commissioner to ensure "that the original width of the river Jhelum is restored" and the statutory authorities under the Water Resources Act 2010 to remove all encroachments, declaring that "the Court is Custodia Legis of river Jhelum and other water bodies" (24 February 2015), directed the Deputy Commissioners "to ensure that no construction of any kind is raised near the water bodies" (10 June 2016) and ordered the demarcation of the wetland reserves (2017); in its order of 29 May 2024 it asked for affidavits of compliance on the encroachments removed and the utilisation of the central assistance (Environmental Policy Group v. Union of India, PIL 8/2017 with PIL 2/2014 and PIL 18/2018). Around Dal it has kept a bar on construction within 200 m of the lake since 19 July 2002 (PIL 159/2002, as quoted; a judgment of 30 October 2025 is reported to keep it, text not read), and in November 2020 it barred construction within 200 m of Wular (as reported). The National Green Tribunal supervises Dal (O.A. No. 504 of 2024), Brari Nambal (O.A. No. 190 of 2025), the valley's wetlands (O.A. No. 239 of 2024, where on 13 November 2026 it found areas taken from the revenue records "insufficient" and asked for the area on the ground, as reported), the Jhelum and the Chenab (O.A. No. 413 of 2025), the land sinking at Pernote (O.A. No. 642 of 2024) and Thathri (O.A. No. 93 of 2023). The statutes carry powers that are little used: the Water Resources (Regulation and Management) Act 2010 lets the Government prohibit obstructions to irrigation and flood-control works, and its Executive Engineers remove them and recover the cost (ss.52–53), bars waste in channels (s.73), vests the bed and banks of all water sources in I&FC (s.81) and punishes construction that changes the behaviour of a water source or stands on an embankment with fines of up to ₹5,000 for a first offence, ₹10,000 for a second and then up to one year in prison or ₹15,000 or both (s.168) (section numbers assigned from a title index, to be confirmed [TBC]); but no flood basin has been found declared under its Part VI, the Flood Plain Zones Act 2005 has not been found brought into force, and the flood zonation maps to which UBBL-2021 defers (cl. 7.12(a)) have not been found notified, so no flood-zoning restriction can yet be enforced on the ground. Building rules are enforced under the J&K Municipal Corporation Act 2000 and the J&K Municipal Act 2000, under which UBBL-2021 are made (their penalty sections were not read [TBC]), and the bye-laws leave the incentives and penalties for rainwater harvesting to be framed locally (cl. 10.6). The CAG found that the flood spill channel had silted from 17,000 to 4,000 cusecs, that two schemes to restore the Jhelum's capacity had treated 68–81% of their lengths and excavated 43–84% of their volumes, and that "Had the two schemes been progressed and implemented as per the approved DPRs, the impact of the floods of September 2014 may have been mitigated", and that the State Disaster Management Authority had met only once in 2010–15 (Report No. 4 of 2016); and in its audit of the Prime Minister's Development Package it found "a significant shortfall of targets in terms of dredging" in Phase I of the Comprehensive Plan for Flood Management of the Jhelum, with "Critical areas of the FSC" still under excavation (year ended March 2019, published 2021). This shows that a rule without routine enforcement does little, and that where the Government has not drawn a line on the ground the courts have. Professional accountability (step 6) is often more effective than fines on owners, because it acts on the person who signs the design.


10.16 Monitoring and post-event review

10.16.1 Monitoring network. Tier A authorities shall maintain, or have access to, recording rain gauges and water-level gauges at their main outfalls and regional facilities. Data shall be archived at intervals of 15 minutes or less.

10.16.2 Event reports. After any event that floods buildings within a ULB area, the ULB shall prepare a short event report within 3 months, recording:

  • (a) rainfall at the nearest approved gauges, by duration, compared with the design depths of Chapter 2;
  • (b) the level of the receiving river at the governing gauge, named, with its datum: on the Jhelum the CWC levels in metres at Khanabal, Sangam, Ram Munshi Bagh and Safapora and the I&FC readings in feet at Sangam, Ram Munshi Bagh and Asham, kept as two separate series and never converted one into the other until I&FC publishes its gauge zeros; on the Tawi the CWC level at Sidhra and the I&FC gauges at Jammu and Udhampur; on the Chenab the levels at Akhnoor; and, for an ungauged khad or nallah and for every river reach outside the CWC sites, the flood marks surveyed after the event and the boulders, debris and muck deposited at crossings; the level of the receiving lake, nambal or reservoir (Dal, Anchar, Wular, Salal, Baglihar, the Tawi barrage) as its manager records it, on a named datum; the times at which each gravity outfall, the Dal Gate and the outlet of each lake closed and reopened; the state of every flap gate, penstock, debris rack, sediment trap, debris basin and pumping station on the outfall and on the drain upstream of it, with the volume of debris removed from each, the hours each pump ran, the number of mobile pumps deployed and where, and any loss of power or fuel; and the gate openings and releases of any dam or barrage that set the receiving level, such as Baglihar, Salal or the Tawi barrage;
  • (c) flooded locations, depths and durations, with flood marks surveyed where possible;
  • (d) the performance of public and inspected private facilities, including any blocked outlets, failed pumps or closed gates; and
  • (e) recommended actions.

10.16.3 Post-event review. Where an event exceeds the 1% AEP 24-hour or 72-hour design depth at two or more approved gauges in the State (Clause 2.14.1), J&K SDMA, with the State Stormwater Technical Committee, shall lead a post-event review within 12 months. It shall assess whether the criteria of this Manual were adequate, and shall feed into the review of Clause 1.12.

10.16.4 Facility performance sampling. The Authority shall, at least every 5 years, monitor a sample of private retention and detention facilities through a monsoon, to test whether they perform as designed.

Commentary. The post-event trigger is the review trigger already set in Clause 2.14.1. Jammu and Kashmir's floods have been audited and litigated more than they have been reviewed. The CAG's audit of disaster management recorded that the rain of 28 August to 10 September 2014 caused floods in Srinagar and the Jammu division in which 304 people died (Jammu 217, Kashmir 87), 2,40,004 houses were damaged and crops were lost on about 4,91,967 ha (Report No. 4 of 2016); other counts give 277 or 284 deaths and more than 1.6 lakh structures damaged (Malik, 2021; H&UDD reply in the Legislative Assembly, February 2026, as reported), and these conflicts are not resolved. In Srinagar 262 km², 34% of the planning area, was under water (Srinagar Master Plan 2035, §4.2), up to 16 ft deep and for up to 25 days in places (as reported); the Jhelum carried about 1,15,218 cusecs at Sangam and 72,585 cusecs at Ram Munshi Bagh (Malik, 2021), against a channel capacity of about 31,800 and 27,000 cusecs before the works that followed (I&FC, as reported). The locations and dates of the embankment breaches, the duration of dewatering and the number of pumps that ran were not found. In 2025 the Jammu division had the largest 24-hour falls on record, 380 mm at Jammu and 630 mm at Udhampur IAF on 26–27 August (IMD), the Tawi set a new high flood level at Sidhra, the cloudburst at Chasoti on 14 August killed more than 60 people and the landslide on the route to Vaishno Devi on 26 August between 30 and 35, and more than 110 people were reported dead across the Union Territory in two weeks (all as reported; the counts differ). The CAG also found the Jhelum's dredging under the Prime Minister's Development Package behind its targets (2021), and the Government told the Legislative Assembly in 2026 that the safe discharge of the Jhelum in the Srinagar reach had risen from about 31,800 to 41,000 cusecs after Phase I of the Comprehensive Plan (as reported). No review of any flood in a town of Jammu and Kashmir, no record of flood extents, depths or durations kept by any ULB or by J&K SDMA, and no official toll for 2022 or 2025 was found; the Ramban flash flood of 2025 and the floods of September 1992 were not researched in detail. NDMA (2010) called for automatic rain gauges at "1 in every 4 sq km" in Class I, II and III cities. Clause 10.16.1 asks only for gauges where they serve design and review. The report and sampling intervals are set by this Manual.


10.17 Data publication

10.17.1 Each Authority shall publish, on a public website, and update at least quarterly:

  • (a) a facility register: location, type, design volume, release rate, owner, date of as-built acceptance, and the latest inspection result for every facility approved under this Manual;
  • (b) a summary of each approved drainage report, with Forms 2-1 and 10-2;
  • (c) the register of variances and waivers (Clause 1.10);
  • (d) the alternatives adopted under the Policy Supplement (Clause 1.7);
  • (e) enforcement actions (Clause 10.15.5); and
  • (f) event reports and post-event reviews (Clause 10.16).

10.17.2 The State Stormwater Technical Committee shall publish the compliance calculator, all Annexes, the flood-sensitive catchment maps and the State-level summary of facility registers as open data.

10.17.3 Personal data other than the name of a corporate owner or association shall not be published. Security-sensitive details of critical infrastructure may be withheld, with the reason recorded.

10.17.4 Published data shall be machine-readable (for example CSV and GeoPackage) and released under the Government Open Data Licence – India or an equivalent open licence.

Commentary. Transparency is a design criterion in its own right here. Some of Jammu and Kashmir's drainage records are public: UBBL-2021 as gazetted on 24 December 2021 and S.O. 304 of 2025, on the H&UDD and OBPS portals; the Srinagar Master Plan 2035 and the Jammu Master Plan 2032; the Reorganisation Act 2019 and the Water Resources Act 2010; the High Court's order of 29 May 2024 in the Jhelum cases; the reports of JKPCC and the Forest, Ecology and Environment Department to the National Green Tribunal on Dal, the wetlands, the Jhelum and the Chenab, and Pernote, with the note of the Geological Survey of India on Pernote; the CAG's audits; IMD's press releases and the station pages of the Meteorological Centre Srinagar; CGWB's groundwater reports; and MoEFCC's list of Ramsar sites. Much else could not be found in the public domain: the original H&UDD notification of UBBL-2021, the text of S.O. 58 of 2026 and the annexure of the draft amendments of September 2026; the texts of SRO 160 of 2019 and SRO 90 of 2017; the drain sections of the municipal Acts; the design basis of the Egis drainage master plan for Srinagar and of any Smart City drain; Jammu's storm-water project report; the flood zonation maps of I&FC to which UBBL-2021 defers, and any notification under the Flood Plain Zones Act 2005 or Part VI of the Water Resources Act 2010; the zeros of the I&FC feet gauges and the datum of CWC's levels; the operating rule of the Dal Gate and the datum of the Dal gauge; the pool level of the Tawi barrage and the operating rules of the Union Territory's dams; J&K SDMA's procedures for urban floods; the gauge records of 2014; and a list of the dewatering stations of Srinagar, with their capacities and the river stages at which their gravity gates shut. Publishing inputs and facility records lets the public, researchers and other agencies check that the city's growing stock of private storage actually exists. The open-format requirement is set by this Manual.


10.18 Review of this chapter

10.18.1 This chapter shall be reviewed with the Manual under Clause 1.12. The forms and the compliance calculator may be revised by the State Stormwater Technical Committee between reviews, under Clause 10.5.3.


References (chapter)

Annexes and forms

Annex / Form Content
10A Compliance calculator and user guide
10B GIS data specification and attribute schema
10C Maintenance access dimensions
10D Model O&M plans by facility type
10E Empanelment criteria for Stormwater Design Professionals and reviewers
Form 10-1 Drainage Report Checklist
Form 10-2 Compliance Calculator Summary
Form 10-3 Professional Design Certificate
Form 10-4 Hold-Point Inspection Record
Form 10-5 As-built Certificate
Form 10-6 Maintenance Declaration
Form 10-7 Annual Maintenance Declaration and Inspection Report
Form 10-8 Asset Handover Certificate
Form 2-1 Design Rainfall Sheet (Chapter 2)