Chapter 1Policy, Applicability and Adoption
1.1 Purpose and objectives
1.1.1 This Manual sets the minimum standards for the planning, design, construction, operation and maintenance of stormwater systems in Jammu and Kashmir. It applies to private development and to public works, as set out in Clause 1.5.
1.1.2 The Manual has the following objectives:
- (a) to make stormwater management a condition of development approval, so that new development and redevelopment do not increase flood peaks or runoff volumes downstream;
- (b) to retain frequent rainfall on site, so that groundwater recharge is sustained and pollutant loads are reduced;
- (c) to size storage for the long-duration storms of the south-west monsoon in the Jammu division, often joined by a western trough, as in September 1988, 1992 and 2014 and August 2025, and the multi-day western-disturbance storms and snowmelt of the Kashmir valley from December to May, which fall on soils, springs and water tables already wet, on lakes and marshes held at their outlets and on rivers already in flood, as well as for short-duration intensities;
- (d) to design outfalls for the stage of the Jhelum, held above Srinagar and the valley towns by its embankments, which shuts their gravity outfalls at its flood-declaration stage and leaves Srinagar to drain by pumps; the Tawi, the Chenab, the Ujh, the Basantar and the khads of the Jammu plains and hills, which rise within hours and carry boulders and debris; the levels of the Dal, Nigeen, Anchar and Wular and of the marshes at their gated or silted outlets; and the levels of Salal, Baglihar, Ranjit Sagar and the Tawi barrage, held and released by their operators, including the case where the outfall is closed;
- (e) to protect tanks (talabs), marshes, rivers, supply channels and surplus courses as part of the drainage system;
- (f) to give every element of the drainage network a safe overland path for the 1% AEP (100-yr) storm;
- (g) to make design inputs, approvals and facility records public, so that designs can be checked and repeated; and
- (h) to make sure that facilities, once built, are maintained and remain effective.
1.1.3 This Manual does not replace the rainwater harvesting (RWH) mandate, the building bye-laws notified under the Jammu and Kashmir Municipal Corporation Act, 2000 and the Jammu and Kashmir Municipal Act, 2000 (the Jammu and Kashmir Unified Building Bye-Laws 2021), or the statutes on waterbodies. It adds runoff control requirements to them (Clause 1.8).
1.2 Stormwater management hierarchy
1.2.1 Every development to which Chapter 4 applies shall consider stormwater measures in the following order. A designer shall not use a lower measure in place of a higher one that is practicable on the site.
- Preserve — keep or restore natural drainage features, tanks, wetlands, permeable soils, trees and overland flow paths (Chapter 7).
- Retain — hold the runoff from the retention depth of Annex 2E on site, by infiltration, reuse or evapotranspiration (Chapters 4 and 8).
- Detain — store larger storms temporarily and release them at or below the rates in Chapter 4, checked against downstream and tailwater conditions (Chapters 4 and 5).
- Convey — carry the remaining flow safely in the minor system, and the 1% AEP flow in the major system (Chapters 6 and 9).
1.2.2 Maintenance underlies all four measures. A measure that cannot be maintained by its owner under Chapter 10 shall not be credited.
1.2.3 Credits from higher measures reduce the requirements of lower ones. Preserved areas and retained volume reduce detention storage as set out in Chapter 4.
Figure 1.1 — Stormwater management hierarchy: preserve, retain, detain, convey, with maintenance underlying each measure. Original drawing for this Manual, adapted from Mid-America Regional Council / Kansas City Metro Chapter APWA, "Layers of Stormwater Management", APWA 5600 Manual Factsheet, 2025 (concept).
Commentary. The order follows the "layers" of Kansas City Metro APWA Section 5600, Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet, 2025). The same logic is behind Georgia's runoff-reduction standard and CSE's "attenuate and infiltrate first" principle (CSE, 2023). For Jammu and Kashmir, the top two layers have a particular meaning, and it differs between the Union Territory's three kinds of ground. Much of its natural storage lies in the lakes and marshes of the Kashmir valley: the Dal (20.37 km²) and Nigeen, which drain through the Dal Gate and the Nallah Amir Khan to Gilsar, Khushalsar and Anchar; the marshes (nambal (नंबल्; a grass-grown, shallow lake or marsh)) of Hokersar, Narkara, Shallabugh and the Rakh-e-Arth flood basin on the west and north of Srinagar, which the Srinagar Master Plan 2035 says "have been acting as flood retention basins"; and Wular, the valley's flood basin. Five of them are Ramsar sites: Wular (18,900 ha, 1990), Surinsar–Mansar (350 ha) and Hokera (Hokersar) (1,375 ha), both of 2005, and Hygam (802 ha) and Shallabugh (1,675 ha), both of 2022 (MoEFCC, list of Ramsar sites). Much has been lost: Hokersar has shrunk from 18.75 km² to about 13 km² and is reported to have "lost nearly half of its flood storage", Wular from 157.74 km² to 86.71 km², and 37% of Narkara has been built over (as reported). In the Jammu division the storage lies in the Kandi, the boulder-gravel fans below the Siwaliks that the Central Ground Water Board calls "a very good medium for the recharge", in its 365 Kandi ponds (249 in Jammu district and 116 in Kathua), in the khads (खड्ड; seasonal hill torrents or ravine streams) that cross it, and in the old talabs of Jammu (Rani Talab, Talab Tillo), most of which survive only as names; and across the Union Territory in its springs (nāg (नाग्; spring), as at Kokernag, Verinag and Achabal). The law protects some of this. The UBBL-2021 keep development 50 m from the major rivers and khads, 30 m from the listed lakes and 20 m from rivulets and canals, measured from the edge of the bank (cl. 7.12(b)), and 30 m from the highest water level along nallahs and rivers (cl. 5.2.5); the master plans add buffers of up to 200 m round Anchar and Hokersar; the High Court keeps construction 200 m from the Dal; the Water Resources (Regulation and Management) Act, 2010 places the bed and banks of every water source under I&FC; and seven wetlands have been reserves since 1945. The statutory flood-zoning routes, flood basins under that Act and flood plain zones under the Flood Plain Zones Act, 2005, have not been used. The second layer changes with the ground, and this Manual flags three regimes. On the valley floor, where the water table stands 0–2 m below the surface and wells flow on both sides of the Jhelum, retention is storage and reuse, not infiltration, and no infiltration is credited (CGWB: in Srinagar "there is no scope for artificial recharge to ground water"). In the Kandi, infiltration is the preferred measure, with pre-treatment and protection of Jammu's groundwater supply. In the hills, water put into the slope moves the slope, as at Pernote in Ramban in 2024 and Thathri in Doda in 2023, so this Manual bars deliberate infiltration on natural slopes of more than 10°, on the clay–sandstone sequences of the Murree and Siwalik hills and in mapped subsidence or sliding zones, unless a geotechnical certificate allows it (Clause 4.11, set by this Manual). Losing the marshes and the Kandi cannot be offset by pipes, and on the valley floor the pumps can only empty what the marshes once held.
1.3 Legal basis and status
1.3.1 Notification. This Manual shall be given statutory effect by the Government of Jammu and Kashmir through:
- (a) an amendment to the Jammu and Kashmir Unified Building Bye-Laws 2021 that makes compliance with this Manual a condition of planning permission, building permit, layout approval and completion certificate, for development to which Clause 1.5 applies; and
- (b) bye-laws or standing orders of each urban local body (ULB), adopting the Manual for works executed or approved by that ULB, including the ULB's own drains and roads.
1.3.2 Higher State standards. The design return periods and performance criteria of this Manual exceed the national advisory minimums of the CPHEEO Manual on Storm Water Drainage Systems (2019). The State shall constitute, by notification, a high-powered committee (the State Stormwater Technical Committee, Clause 1.9) to adopt these higher standards. This is the route that CPHEEO (2019) provides for higher return periods.
1.3.3 Precedence. Within its scope, this Manual governs where it is stricter than CPHEEO (2019), IRC:SP:42-2014, IRC:SP:50-2013 or any departmental standard. Where a statute or statutory rule sets a stricter requirement (for example a waterbody setback), the statute governs.
1.3.4 Design-practice standard for public works. Departments and ULBs that procure drainage, road or waterbody works shall require compliance with this Manual in detailed project reports (DPRs) and contracts, from the dates in Clause 1.11.
Commentary. In Jammu and Kashmir the building rules are the Jammu and Kashmir Unified Building Bye-Laws 2021 (UBBL-2021), one set of bye-laws for "all urban local bodies, urban development authorities and metropolitan regional development authorities" of the Union Territory (cl. 2.1), read with the master plan of the area (cl. 1.1, 2.2). This Manual read them as published in the J&K Official Gazette, Extraordinary, Vol. 134, No. 39-4, of 24 December 2021 (the copy of the Jammu Municipal Corporation). They appear to have been adopted body by body on a common text: the Doda Municipal Council adopted them on 21 October 2021 under section 204 of the Jammu and Kashmir Municipal Act, 2000 (as quoted); the original notification of H&UDD was not found [TBC]. They were amended by the notification of JMC gazetted on 9 March 2022, by S.O. 304 of 1 December 2025, which H&UDD issued under section 395(d) of the Jammu and Kashmir Municipal Corporation Act, 2000 and section 202 of the Jammu and Kashmir Municipal Act, 2000, and by S.O. 58 of 26 February 2026 (listed; text not read [TBC]); a further draft of 9 September 2026, published under section 397 of the Corporation Act, was reported (as reported). The two sections cited for the same power, 395(d) and 397, are both stated here; which one the final amendments rest on is to be confirmed [TBC]. S.O. 304 moved approvals to online auto-scrutiny, which checks rainwater harvesting, with deemed rejection after 15 days and online no-objection certificates from, among others, Sewerage & Drainage, the Lake Conservation and Management Authority (LCMA), the Pollution Control Board and the Irrigation and Flood Control Department (I&FC), and a "WATERBODY USE_NEGATIVE LIST" that bars permanent structures in a waterbody use. The bye-laws ask for a site plan that shows "any water body, flood affected areas and contours at an interval of 0.3m" where the slope is more than 1:20 (cl. 2.6(b)(xi)), and a certificate of the registered technical person that the site is clear of drains and water bodies (cl. 2.18); bar development in "water body, pond and Talav" land; keep a green buffer along nallahs and rivers of "minimum 30 m from the highest water level … whichever is more" (cl. 5.2.5); leave building in flood areas to I&FC "or the flood zonation maps notified by the department from time to time" (cl. 7.12(a)), of which none was found; and keep development 50 m from the edge of the bank of the listed rivers, among them the Chenab, the Jhelum, the Tawi, the Ravi and the Ujh, "or any other river/khad", 30 m from the listed lakes, among them Mansar, Surinsar, Wular, Nigeen and Manasbal, and 20 m from unlisted rivulets and the Ranbir and Sindh canals, "or as per building regulation whichever is more" (cl. 7.12(b)). They require sloping roofs in snowfall areas and let the Authority require roof water to be piped to a drain (cl. 6.20), and set a plinth of not less than 45 cm (cl. 6.1) and a ground-floor finish 300 mm above the centre line of the road (Table 5-9); the research for this Manual read each provision in a different part of the text, so both are cited, and the 1% AEP level plus 0.5 m of Clause 1.5.4(b) is stricter than either. Chapter 10 makes a rainwater harvesting proposal mandatory on plots of 100 m² or more. The bye-laws set no design storm, return period, release rate, detention volume or storage volume, no "zero runoff" rule, no basement flood rule and no rule on infiltration on slopes. The route of Clause 1.3.1(a) therefore runs through an amendment of the UBBL-2021 notified by H&UDD, and through the regulations of the master plans under the Jammu and Kashmir Development Act, 1970. This Manual is a draft; neither the Government nor any authority has adopted it. MoHUA told Parliament in July 2026 that urban flooding "falls under the purview of the State Governments and the ULBs" and listed the CPHEEO manual among "advisory guidelines" (Lok Sabha AU1847). The State therefore needs no central approval to adopt higher standards. CPHEEO's Note 2 to Table 4.1 (§4.4.1.4) allows "a high powered committee constituted by State/UT Government through a notification" to adopt higher return periods. Clause 1.3.2 uses that route so that higher standards are on record for centrally funded schemes.
1.4 Definitions
1.4.1 The following terms apply throughout this Manual. Chapter-specific terms are defined in each chapter (for example Clause 2.2).
| Term | Meaning in this Manual |
|---|---|
| Approving Authority (the Authority) | The body that grants planning permission, building permit or layout approval for a development, or that sanctions a public work: the Building Permit Issuing Authority under UBBL-2021 in whose area the site lies: the Srinagar or Jammu Municipal Corporation, a Municipal Council or Municipal Committee, or a Development Authority under the Jammu and Kashmir Development Act, 1970, such as SDA or JDA, in its area, acting with the no-objection certificates routed through the online system of S.O. 304 of 2025, among them those of I&FC, Sewerage & Drainage and LCMA (the division of these powers between the bodies, and the bodies that grant permission outside urban areas, are to be confirmed [TBC]), or a department for its own works. |
| Applicant | The owner, developer or department that seeks approval, and its successors in title. |
| Development | Any building, layout, sub-division, road, paving or land-use change that requires approval under the Jammu and Kashmir Unified Building Bye-Laws 2021 or that is executed as a public work. |
| Redevelopment | Development on a site where impervious cover already exists. |
| Land disturbance | Clearing, grading, excavation, filling or paving of land, measured in plan area over the whole of a common plan of development (Clause 1.5.5). |
| Impervious area | Roofs, paving, compacted gravel, decks and other surfaces that prevent infiltration. Permeable paving designed to Chapter 8 is counted as pervious only for the area it treats. |
| New or replaced impervious area | Impervious area created, or removed and rebuilt down to the subgrade, by the development. Resurfacing that leaves the base in place is not "replaced". |
| Retention | Permanent removal of runoff from the drainage system on site, by infiltration, reuse or evapotranspiration (Chapter 4). |
| Detention | Temporary storage of runoff with a controlled outlet, emptied after the storm (Chapter 4). |
| Rainwater harvesting (RWH) | Collection of rainfall for supply or recharge under the RWH mandate. RWH storage is not detention unless Chapter 4 allows it. |
| Minor system | Drains, pipes and inlets designed for the minor-system AEP of Chapter 6. |
| Major system | The overland and floodway path that carries the 1% AEP (100-yr) flow (Chapter 6). |
| Pre-development condition | Greenfield: open land in good condition for the mapped hydrologic soil group. Existing impervious cover is not counted (Chapter 3). |
| Flood-sensitive catchment | The catchments of Srinagar behind the Jhelum embankments, with the Dal–Nigeen catchment and the low land of the west-bank flood basins from Lelhar and Lasjan to Rakh-e-Arth, Narkara and Hokersar; the land of Anantnag, Bijbehara and Pampore that drains to the upper Jhelum; the land of Sopore, Baramulla, Sumbal and Bandipora that drains to the lower Jhelum, Wular and the flood spill channel; the land of Jammu that drains to the Tawi and to its khads; the land of Kathua and Hiranagar that drains to the Ujh and the Ravi, and of Samba that drains to the Basantar; the land of R.S. Pura, Bishnah and Arnia in the Sirowal; the land of Akhnoor that drains to the Chenab; the land of Udhampur that drains to the Tawi and the Devak, and of Katra; and the land of the hill towns of the Chenab valley, Ramban, Batote, Banihal, Doda, Thathri and Kishtwar, and any catchment the Authority notifies (Chapter 4; Annex 1B). |
| Waterbody | A river, stream, canal, tank (talab), lake, pond, marsh, supply channel or surplus course, whether perennial or seasonal (Chapter 7). |
| Regional facility | A detention, retention or tank storage facility serving more than one development, built or restored under a basin plan (Chapter 4). |
| Tier A / Tier B authority | An Approving Authority classed under Clause 1.6. |
| Policy supplement | The set of adoptable alternative clauses in Clause 1.7 and Annex 1C. |
| Drainage report | The preliminary or final report required by Chapter 10. |
| Registered professional | A person registered under the Jammu and Kashmir Unified Building Bye-Laws 2021 to prepare and sign the relevant plans, with any further qualification required by Clause 10.6. |
| Compliance calculator | The State-issued tool for computing and reporting compliance (Clause 10.5). |
| Maintenance declaration | The registered undertaking by an owner to maintain a stormwater facility (Clause 10.10). |
| Variance | Approval to depart from a numeric requirement, with equivalent performance shown (Clause 1.10). |
| Waiver | Approval that a requirement does not apply to a site, on the grounds in Clause 1.10. |
| Notified | Published by the Government or the State Stormwater Technical Committee in the Jammu and Kashmir Official Gazette. |
| State | The Union Territory of Jammu and Kashmir. Jammu and Kashmir has been a Union territory with a Legislative Assembly since 31 October 2019 (Jammu and Kashmir Reorganisation Act, 2019; article 239A applies under section 13), not a State; "State" is used in this Manual as in section 3(58)(b) of the General Clauses Act, 1897, under which a State includes a Union territory. The usage is one of convenience and does not change who holds any power. The Legislative Assembly may make laws on any matter of the State List except public order and police (section 32), so land, local government, water, drainage and building regulation lie with the Union Territory. The Union Territory of Ladakh, a separate Union territory since 31 October 2019, is not part of the State in this Manual and is covered only by Supplement S01; figures published before that date for the former State include Ladakh and are not used for the Union Territory. |
| State Government, Government | The Government of the Union Territory of Jammu and Kashmir: the Lieutenant Governor acting on the aid and advice of the Council of Ministers, except where he acts in his discretion (section 53), with executive action expressed in his name (section 55(2)), and its departments, among them H&UDD and the Jal Shakti Department. Bodies of the Union that act in the Union Territory, among them CWC, CGWB, IMD, NHAI and NHPC, are named as such and are not part of the State Government. |
Commentary. "Replaced" impervious area is defined to the subgrade so that redevelopment of a fully paved site is captured, while routine resurfacing is not. This follows the approach of the APWA 5600 (2025.01) redevelopment triggers (MARC Supplement, 2025).
1.5 Applicability
1.5.1 Who is covered. This Manual applies to:
- (a) all development requiring planning permission, building permit or layout approval under the Jammu and Kashmir Unified Building Bye-Laws 2021;
- (b) all drainage, road, bridge, culvert, waterbody and flood-mitigation works executed by a ULB, a State department, a board, or a State undertaking; and
- (c) works executed by Central agencies or their contractors within Jammu and Kashmir, to the extent that the Authority's approval or no-objection is required.
1.5.2 Retention and detention threshold. Chapters 4 and 5 (retention, detention, downstream and tailwater analysis) apply to any development that, over the common plan of development, involves:
- (a) land disturbance of 0.1 ha or more; or
- (b) new or replaced impervious area of 500 m² or more.
1.5.3 RWH. The existing RWH mandate continues to apply under Chapter 10 of UBBL-2021 to every building on a plot of 100 m² or more, as a complete rainwater harvesting proposal with storage and recharge structures but no storage volume (cl. 10.1), with recharge mandatory for buildings and group housing on plots of more than 500 m² (cl. 10.5), the capture of storm water mandatory in public open spaces of more than 500 m² (cl. 10.4) and every structure inspected before the completion certificate or a service connection (cl. 10.6); the Srinagar Master Plan 2035 makes storage mandatory only for plots of 1,000 m² or more and group housing (reg. 1-7-13), and the stricter threshold of the bye-laws applies, as now. This Manual does not change it.
1.5.4 Provisions that apply at every size. The following apply to all development under Clause 1.5.1, whatever its size, unless exempted by Clause 1.5.8:
- (a) no sewage connection to a storm drain (Chapter 8);
- (b) lowest habitable floor and openings at or above the 1% AEP level plus 0.5 m, where a 1% AEP level is mapped or determinable (Chapter 6);
- (c) waterbody setbacks and the no-fill zone (Chapter 7); and
- (d) no obstruction of a natural drainage path or major-system flow path (Chapter 6).
1.5.5 Common plan of development. The thresholds of Clause 1.5.2 apply to the total area of a development, including all phases, plots and sub-divisions under one layout approval or one ownership at the date of application. A development shall not be divided to avoid the thresholds.
1.5.6 Redevelopment. For redevelopment, the thresholds apply to new plus replaced impervious area. Retention and detention apply to the whole of the new and replaced impervious area, and the pre-development condition is greenfield (Clause 1.4). Where greenfield control cannot be achieved on a constrained redevelopment site, the relief route of Clause 4.5.6 applies: a minimum on-site cut of 50% from existing peaks, with the shortfall paid as fee-in-lieu into basin storage.
1.5.7 Linear public works. For roads, widening and other linear works, the impervious area threshold applies to the added impervious area within each drainage catchment crossed. Retention and detention shall be provided within the right of way, or in a regional facility under Chapter 4, where the right of way cannot hold them.
1.5.8 Exemptions. The following are exempt from Chapters 4 and 5:
- (a) a single dwelling on its own plot, where the thresholds of Clause 1.5.2 are not met; and
- (b) linear road resurfacing that adds no impervious area.
Exempt development remains subject to the RWH mandate and to Clause 1.5.4.
1.5.9 Applicability determination. The Applicant shall record the applicability decision on Form 1-1 (Applicability Determination) with the first submittal under Chapter 10. The Authority may confirm or correct it at the pre-application stage.
Figure 1.2 — Applicability decision flowchart for Clause 1.5. Original drawing for this Manual.
Commentary. The thresholds have no single direct precedent; they are set by this Manual. Precedents span a wide range:
- Singapore controls peak runoff from developments of 0.2 ha or more (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5).
- Malaysia's 2008 DID checklist used on-site detention for sites up to 0.1 ha and community ponds above that.
- The APWA 5600 (2025.01) Policy Supplement offers alternative triggers of ¼ acre (about 0.1 ha) disturbed, or 1 acre (about 0.4 ha) with 10,000 sq ft (about 930 m²) impervious, and warns agencies not to exceed a 1-acre trigger.
- MBBL 2016 makes recharge mandatory for buildings over 500 m².
The 0.1 ha / 500 m² trigger sits at the strict end of these, because typical Jammu and Kashmir plots are small and the cumulative effect of many small plots is what fills Srinagar's drains. For small buildings in Jammu and Kashmir, Chapter 10 of the UBBL-2021 already reaches every plot of 100 m² or more: the plans must include "the complete proposal of rainwater harvesting" (cl. 10.1), and the structures are inspected before the completion certificate or a service connection (cl. 10.6). The bye-laws set no storage volume, and the only figure they give, that "55,000 litres per 100 sq. m. area per Year" can be harvested from rooftops, describes a yield, about 550 mm a year (NEER reading), not a tank. That is a supply measure, and none of it limits what leaves the plot in a design storm. The Srinagar Master Plan 2035 makes storage mandatory only for plots of 1,000 m² or more and group housing (reg. 1-7-13); the UBBL-2021, which are later and apply across the Union Territory, set the stricter threshold of 100 m², and this Manual applies that one. Clause 1.5.4(b) applies to every building whatever its size, because no bye-law asks a small building to stand above the water: the UBBL-2021 set a plinth of 45 cm and a ground-floor finish 300 mm above the road, not a level above the flood. The same rainwater harvesting proposal does different things on the Union Territory's three kinds of ground, and an Authority may make the matching rule of this Manual a condition of every building permit in its area, whatever the size of the site (a recommendation of this Manual, not a requirement of Clause 1.5.4): on the alluvium, Gurti clay and Nambal peat of the Kashmir valley floor, where the water table is within 2 m of the surface and wells flow, it is storage and reuse, with no soakaway or recharge pit; in the Kandi of the Jammu plains it may be recharge, with the protections of Chapter 8; and on a hill slope, as at Thathri in Doda, where a committee before the NGT found no planned drainage on the subsiding slope and sewage piped to the roadside drains below it (as reported), it is storage with an overflow to a lined drain, never a soak pit (Clause 4.11).
Clause 1.5.4(b) has no direct precedent; this Manual sets it because floor levels are the cheapest protection a building can have, and it would be perverse to protect only large developments. Where no 1% AEP level is mapped, Chapter 6 gives the method for small sites.
1.6 Tiered adoption
1.6.1 Tier A authorities. The following are Tier A:
- (a) Srinagar Municipal Corporation (SMC) and the Jammu Municipal Corporation (JMC), constituted under the Jammu and Kashmir Municipal Corporation Act, 2000;
- (b) every Approving Authority within the Srinagar Local Planning Area, the local area of the Srinagar Master Plan 2035 notified under the Jammu and Kashmir Development Act, 1970 (SRO-429 of 21 October 2014), as that area is notified from time to time, including the Srinagar Development Authority (SDA), SMC and the Municipal Councils and Committees in that area; and
- (c) every Approving Authority within the Jammu Local Planning Area, the local area of the Jammu Master Plan 2032 notified under the Jammu and Kashmir Development Act, 1970, as that area is notified from time to time, including the Jammu Development Authority (JDA), JMC and the Municipal Councils and Committees in that area.
1.6.2 Tier B authorities. All other Municipal Councils and Municipal Committees are Tier B.
1.6.3 What differs between tiers. All criteria of this Manual apply in both tiers. The tiers differ only in method and review:
Table 1.1 — Differences between Tier A and Tier B authorities
| Item | Tier A | Tier B |
|---|---|---|
| Performance criteria (Chapters 2–9) | Apply in full | Apply in full |
| Hydrologic method for storage | Hydrograph method (Chapter 3) | Hydrograph method, or the design-aid route of Clause 1.7 where eligible |
| Compliance calculator (Clause 10.5) | Required as a summary | Required; may be the sole calculation on the design-aid route |
| Policy supplement alternatives (Clause 1.7) | Only with State Stormwater Technical Committee concurrence | May be adopted by council resolution |
| Technical review | By the Authority | By the Authority, with H&UDD regional support or an empanelled reviewer (Clause 10.7) |
| Flood-sensitive catchment rule | Applies | Applies |
1.6.4 Moving between tiers. A Tier B authority may opt into Tier A by council resolution. The Government may notify a Tier B authority as Tier A when it becomes a Corporation, joins the local planning area of the Srinagar Master Plan 2035 or the Jammu Master Plan 2032 under the Jammu and Kashmir Development Act, 1970, or is found by a post-event review (Clause 10.16) to need the full methods.
1.6.5 Flood-sensitive catchments override tier. In a flood-sensitive catchment, whatever the tier, the alternatives of Clause 1.7 are available only as Table 1.2 allows: S-1 (the design-aid route) for sites of 0.5 ha or less (Clause 4.14.1), and S-5 fee-in-lieu where a basin plan has been notified (Clause 1.10.3(d)). S-2, S-3 and S-4 are not available.
Commentary. Srinagar Municipal Corporation, with its Town Drainage wing, with UEED and the Town Drainage of the Directorate of Urban Local Bodies Kashmir beside it, about 119 km of primary and secondary storm drains and 89 drainage pumping stations counted in 2019 (Srinagar Master Plan 2035), and 104 permanent dewatering stations and 281 mobile units reported in 2026 (as reported), and a small hill Municipal Committee with one assistant engineer cannot be asked to review the same hydrograph models. The Kansas City solution was to keep one regional standard and publish adoptable alternatives for the most contested criteria, so that smaller agencies can "opt down" without leaving the standard (MARC Supplement, Nov 2025). The tiers here keep the performance criteria the same in both tiers and vary only the method, so that a building in a Tier B town is protected to the same level as one in Srinagar.
1.7 Policy supplement: adoptable alternatives
1.7.1 The Government shall publish, with this Manual, a Policy Supplement (Annex 1C) of alternative clauses. An Approving Authority may adopt one or more alternatives under the conditions in Clause 1.7.3.
1.7.2 The alternatives are:
Table 1.2 — Policy supplement: adoptable alternatives S-1 to S-5
| No. | Main-text requirement | Adoptable alternative | Eligibility |
|---|---|---|---|
| S-1 | Storage sized by hydrograph method (Chapter 3) | Design-aid route: retention and detention volumes taken from the unit-storage tables (m³ per ha, by rainfall zone, soil group and impervious fraction) in Annex 4 and the compliance calculator | Sites ≤ 2 ha outside flood-sensitive catchments; ≤ 0.5 ha within them (as Clause 4.14.1) |
| S-2 | Release rate Q_post(T) ≤ 0.9 × Q_pre(T), computed for the site | Permissible site discharge (PSD): a tabulated unit-area release rate (m³/s/ha) by zone and AEP, derived from the 0.9 × Q_pre rule | Any site outside flood-sensitive catchments |
| S-3 | Waterbody setback extended to the mapped 1% AEP flood extent plus margin (Chapter 7) | Fixed-width setback table by waterbody class, where no 1% AEP extent is mapped. Never less than the Zone 1 minimum of Clause 7.4.7 | Waterbodies with no mapped 1% AEP extent |
| S-4 | Downstream analysis by hydraulic model (Chapter 5) | Screening checklist of downstream capacity and known flooding, with a model only where the screen fails | Sites < 1 ha, outside flood-sensitive catchments, not discharging to a tidal outfall |
| S-5 | On-site detention | Fee-in-lieu toward a regional facility or restored tank storage in a master-planned basin (Chapter 4) | Where a basin plan has been notified |
1.7.3 Conditions on adoption.
- (a) An alternative shall not lower any criterion below the values of this Manual. S-1 and S-2 are simplified methods for meeting the same criterion. They are not lower criteria.
- (b) A Tier B authority adopts an alternative by council resolution, sent to the State Stormwater Technical Committee within 30 days. A Tier A authority needs the Committee's concurrence before adoption.
- (c) The adopted alternatives shall be published on the Authority's website and in the register of Clause 10.17.
- (d) Retention (Annex 2E depth) cannot be replaced by any alternative, except where fee-in-lieu under S-5 funds equivalent retention in the same basin.
- (e) The tables for S-1, S-2 and S-3 shall be issued by the State Stormwater Technical Committee, and reviewed with Chapter 2 (Clause 2.14).
Commentary. The supplement follows the model of the APWA 5600 (2025.01) Policy Supplement, which gives alternatives for the four most contested criteria (applicability, Rational Method limits, stream setback trigger, and Zone 2 setback width). Two of those map onto S-3 and onto the applicability threshold of Clause 1.5.2. Alternative S-3 copies the APWA answer to the same problem: the 1% AEP extent is not mapped for small drainage areas, so a fixed-width table is offered. S-2 follows the Kansas City 2011 shift from "match existing" to fixed unit-area release rates. Local agencies preferred a set rate because existing conditions were hard to determine consistently (MARC Evolution deck). It also reflects the Sydney Water permissible site discharge (PSD) method. The 2 ha / 0.5 ha limits for S-1 (matching Clause 4.14.1) and the 1 ha limit for S-4 have no direct precedent; they are set by this Manual.
1.8 Relationship with other instruments
1.8.1 This Manual shall be applied together with the instruments below. Where they overlap, Clause 1.3.3 governs.
Table 1.3 — Relationship with other instruments
| Instrument | Relationship |
|---|---|
| Jammu and Kashmir Reorganisation Act, 2019 (No. 34 of 2019): section 13 (article 239A applies), section 32 (legislative power), sections 53 and 55 (aid and advice; rules of business; executive action in the name of the Lieutenant Governor) and the Fifth Schedule, Table 4 (State Acts that remain in force); the Transaction of Business Rules as amended in 2024 (as reported) | Continue; they decide who could adopt this Manual. The Legislative Assembly may make laws on any matter of the State List "except … 'Public Order' and 'Police'" (s.32(1)), so land, local government, water, drainage and building regulation lie with the Government of the Union Territory, acting on the aid and advice of its Council of Ministers except where the Lieutenant Governor acts in his discretion (s.53); executive action is expressed in the Lieutenant Governor's name (s.55(2)). The amendment of the Business Rules reported in 2024 does not list any of the subjects of this Manual (as reported; NEER reading), and revised rules are reported to be pending (as reported, unverified). The Fifth Schedule continues the Development Act 1970, the Flood Plain Zones Act 2005, the Land Revenue Act Svt. 1996, the Municipal Act 2000, the Municipal Corporation Act 2000, the Town Planning Act 1963, the Water Resources Act 2010, the Common Lands Act 1956, the Control of Building Operations Act 1988, the Kahcharai Act Svt. 2011 and the Prevention of Ribbon Development Act Svt. 2007. |
| the Jammu and Kashmir Unified Building Bye-Laws 2021 (UBBL-2021), J&K Official Gazette, Extraordinary, Vol. 134, No. 39-4, 24 December 2021 (read), as amended by the JMC notification gazetted on 9 March 2022 (read), S.O. 304 of 1 December 2025 (read) and S.O. 58 of 26 February 2026 (listed; not read [TBC]); draft amendments of 9 September 2026 (as reported) | Continue. They keep development 50 m from the edge of the bank of the Chenab, the Jhelum, the Tawi, the Ravi, the Ujh "or any other river/khad", 30 m from Mansar, Surinsar, Wular, Nigeen, Manasbal "and other lakes" and 20 m from unlisted rivulets, tributaries and canals, among them the Ranbir and Sindh canals, "or as per building regulation whichever is more" (cl. 7.12(b)); keep a green buffer along nallahs and rivers of at least 30 m "from the highest water level" (cl. 5.2.5); leave the distance from a talab or village tank to the Authority (cl. 7.12(c)); leave flood areas to I&FC "or the flood zonation maps notified by the department from time to time" (cl. 7.12(a)), none of which was found; bar development in "water body, pond and Talav" land; require the site plan to show water bodies, flood-affected areas and 0.3 m contours on slopes steeper than 1:20 (cl. 2.6(b)(xi)); and route the no-objection certificates of I&FC, Sewerage & Drainage, LCMA and the Pollution Control Board through online scrutiny (S.O. 304). The list of major watercourses in cl. 7.12(b) also names a river that does not flow through the Union Territory; this Manual applies the clause to the rivers of the Union Territory it names and to "any other river/khad". The bye-laws set no design storm, release rate, detention volume, storage volume, basement flood rule or rule on infiltration on slopes. The design criteria of Chapters 2–6, the outfall-closed and infiltration rules of Chapters 4, 5 and 8, and the hydraulic corridor of Chapter 7, whose Zone 1 is at least 15 m and which applies only where no wider statutory line binds, are this Manual's proposals; they are not statutory values, and no authority has adopted them. Where the bye-laws, a master plan, a statute or a court order are stricter, they govern (Clause 1.3.3). |
| Rainwater harvesting: UBBL-2021, Chapter 10; Srinagar Master Plan 2035, regulation 1-7-13; Water Resources (Regulation and Management) Act, 2010, section 122 [section number to be confirmed] | Continue unchanged. Chapter 10 makes a complete rainwater harvesting proposal mandatory for every building on a plot of 100 m² or more (cl. 10.1), recharge mandatory for buildings and group housing on plots of more than 500 m² (cl. 10.5) and the capture of storm water mandatory in public open spaces of more than 500 m² (cl. 10.4), asks for permeable paving of the open parking of group housing (Table 10-1), bars contaminated water from recharge structures in industrial areas, and has every structure inspected before the completion certificate or a service connection, with an annual check of every building above 1,000 m² (cl. 10.6); it sets no storage volume. The master plan's regulation makes storage mandatory only for plots of 1,000 m² or more and group housing; both are cited, and the stricter 100 m² of the bye-laws applies. Section 122 of the Act of 2010 lets the regulatory authority advise the Government on areas where rooftop harvesting should be mandatory; it is advisory and not self-executing. This Manual counts the storage of Chapter 10 against its retention requirement only as reuse (Clause 4.4.3), never as detention, and on the Kashmir valley floor and on hill slopes only as storage, never as recharge (Clause 4.11). |
| Jammu and Kashmir Development Act, 1970 (Act XIX of 1970); the Srinagar Master Plan 2035 (SRO 160 of 7 March 2019, as quoted) and the Jammu Master Plan 2032 (SRO 90 of 3 March 2017, as quoted, amended by S.O. 243 of 2022 and S.O. 19 of 2024, as listed); the Development Authorities, LCMA (renamed from LAWDA on 3 November 2021, as reported) and WUCMA (2012) | Continue. The Srinagar plan records that 34% of its planning area, 262 km², was flooded in 2014, that I&FC's flood zonation puts 125 km² in undevelopable and 136.50 km² in flood-vulnerable categories (§4.2), and sets buffers round the Dal and Nigeen (50–100 m), Anchar (200 m on three sides, 30 m on the east), Hokersar (200 m south and west, 50 m east and north), Nambal Narkur (100 m), the Telbal and Sind nallahs (50 m) and the Doodhganga, the Nallah Amir Khan and other small water bodies (20 m), with 100 m round unlisted wetland reserves (Tables 8-2 and 8-3; §8.2.3); its §13.3 sets "stormwater performance standards" of full coverage and no waterlogging without a return period, and its §14.4.4.2 proposes, without having notified it, that the 25-year floodplain from Lelhar to Lasjan be a "Protected Natural Flood Absorption Basin". The Jammu plan sets buffers from the Full Tank Level of 50 m (30 m in built-up areas) on the Tawi, the Devak and the Basantar, 15 m on the Balol, Thather and Bhalwal khads and 5 m elsewhere (§7.3.3), and proposes that land recorded as "Gair Mumkin Khad", more than 30% of JDA's land, be reduced to the "true Khad" fixed with I&FC (§12.2.3). The buffers are measured from three different lines (the edge, the highest water level and the Full Tank Level); Chapter 7 maps each onto its design flood line, and the widest governs. This Manual requires any release of khad land to follow a hydraulic study of the functional khad at the AEP of Chapter 7 (set by this Manual). Master plans would show the flood-sensitive catchments, drainage reserves and regional facility sites of this Manual (Chapter 11). |
| Jammu and Kashmir Municipal Corporation Act, 2000 (Act XXI of 2000) and Jammu and Kashmir Municipal Act, 2000 (Act XX of 2000) | Continue. They are the parent Acts of the UBBL-2021: S.O. 304 cites section 395(d) of the Corporation Act and section 202 of the Municipal Act, the draft of September 2026 section 397 of the Corporation Act, and the Doda Municipal Council adopted the bye-laws under section 204 of the Municipal Act (as quoted); which sections govern is to be confirmed [TBC]. Their drainage sections, on the vesting of drains, connections and building over drains, were not read for this Manual [TBC]. |
| Jammu and Kashmir Water Resources (Regulation and Management) Act, 2010 (Act XXI of 2010) and its Rules of 2011 (section numbers were assigned from a title index and are to be confirmed against an official copy [TBC]) | Continue, and apply where a water source, embankment or channel is concerned. The Act defines "drainage works" to exclude works for sewage (s.2(l)), a "flood basin" as "the area which is required for carrying the flow of the floods" (s.2(s)), and a "water source" to include any "nallah, canal, spring, pond, lake" (s.2(zze)); bans encroachment on water bodies (s.4(zw)); prohibits obstructions (ss.52–53) and provides for drainage schemes (s.54); requires permission to build in the vicinity of an irrigation or hydraulic work (s.66); bars waste in channels (s.73); provides for flood basins to be declared after survey, objections and notification, with restrictions on the use of land (Part VI, ss.75–79), of which none was found notified; and places "the bed and banks of all water sources … city channels and flood spill channels" under I&FC (s.81). Every outfall to a river, nallah, flood spill channel or city channel needs I&FC's consent under this Manual (Chapter 5). Where a flood basin is notified under Part VI, its restrictions govern; until then the mapped design flood line of Chapter 7 applies (set by this Manual). |
| Jammu and Kashmir Flood Plain Zones (Regulation and Development) Act, 2005 (Act XVII of 2005) | Not in force: the Act comes into force on a date to be notified (s.1(3)), and no such notification was found [TBC]. No flood plain zone or flood zonation map is notified under it. Its "flood zone", the area needed "to carry the flow of the maximum probable floods" (s.2(d)), is not the 1% AEP line of this Manual. Where the Act is brought into force and a zone declared, its restrictions govern. |
| Wetlands (Conservation and Management) Rules, 2017; the Jammu and Kashmir Wetland Authority (constituted on 25 November 2020; the number of the notification is uncertain in the copy read); the Wildlife (Protection) Act, 1972 (in force in the Union Territory from 31 October 2019) and the wetland conservation reserves of Order No. 710-C of 17 July 1945; Ramsar sites Wular (18,900 ha, 1990), Surinsar–Mansar (350 ha) and Hokera (1,375 ha) (2005), Hygam (802 ha) and Shallabugh (1,675 ha) (2022) | Continue. No wetland of the Union Territory had been notified under rule 4 of the Rules by September 2024; the Wetland Authority approved the brief document of Wular "for Notification" on 3 August 2022, and a plan of 2021 to declare Wular, Dal, Nigeen, Sanasar, Manasbal and Purmandal "Protected Wetlands" was reported (as reported), neither confirmed as notified. The seven wetland reserves are held by the Wildlife Department. The NGT has called the revenue-record areas of 27 wetlands of more than 1 ha "insufficient" and asked for their extent on the ground (OA 239/2024, order of 13 November 2026, as reported). The lakes and wetlands are governed by Chapter 7. |
| High Court of Jammu and Kashmir and Ladakh: PIL 8/2017 with PIL 2/2014 and PIL 18/2018, Environmental Policy Group v. Union of India (order of 29 May 2024, reciting the orders of 24 November 2014, 24 February 2015 and 10 June 2016); PIL 159/2002 (the Dal; order of 19 July 2002, as quoted; later orders as reported); the order on Wular of November 2020 (as reported) | Apply as court directions where they bind. The Court has directed the removal of encroachments from the banks of the Jhelum "along its entire course", ordered that "the original width of the river Jhelum is restored", described itself as "Custodia Legis of river Jhelum and other water bodies", and directed the Deputy Commissioners to ensure that "no construction of any kind is raised near the water bodies". It has kept a 200 m no-construction zone round the Dal since 2002 (as quoted; the judgment of 30 October 2025 is reported to keep it [TBC]), and is reported to have ordered 200 m round Wular in November 2020 (as reported); LCMA has applied 200 m round Nigeen (2021, as quoted). These are court directions, not rules of this Manual; Chapter 7 applies the widest line that binds. |
| National Green Tribunal: OA 504/2024 (the Dal), OA 190/2025 (Brari Nambal), OA 239/2024 (the wetlands of Kashmir), OA 413/2025 (the Jhelum and the Chenab), OA 642/2024 (land sinking) and OA 93/2023 (Thathri) | Apply where they bind. JKPCC reported in OA 504/2024 that Srinagar generates 193.34 MLD of sewage against 62.01 MLD of treatment capacity (32.07%), and that "Untreated sewage gets entry into the Dal Lake from areas like Telbal, Lalbazar" (14 August 2024); CPCB's list of polluted river stretches of October 2025 includes the Chunt Kol (Priority III), the Jhelum from the Vishav confluence to Baramulla and the Tawi from the Tawi Bridge to the Balol Nallah (Priority IV), and the Basantar, the Devak, the Gawkadal stretch and the Lidder (Priority V) (JKPCC, OA 413/2025). The GSI note on Pernote filed in OA 642/2024 recommends "diverting the surface runoff away" and lining the drains of the affected slope. Sewage in storm drains is dealt with in Chapter 8, and slopes in Chapters 4 and 6. |
| Jammu and Kashmir Land Revenue Act, Svt. 1996; the Kahcharai Act, Svt. 2011; the Common Lands (Regulation) Act, 1956 | Continue (texts not read [TBC]). Much of Jammu's drainage land is recorded as "Gair Mumkin Khad" (land recorded as uncultivable stream bed), and the Kashmir marshes as nambal and rakh (a reserved wetland or grassland, a word used in names); the recorded class and the surveyed extent diverge, and this Manual's register records both (Chapter 7). |
| Disaster Management Act, 2005; J&K SDMA and the District Disaster Management Authorities | Continue. No urban flood plan or standard operating procedure of J&K SDMA was read for this Manual [TBC], and no order found fixes a date for desilting; the works calendar of Chapter 10 sets this Manual's dates. |
| IRC:SP:42-2014 and IRC:SP:48, Hill Road Manual, and the practice of the PW (R&B) Department on road drainage | Apply to the drainage of roads and hill roads, cross-referenced from Chapter 6, where they do not conflict with it; the World Bank's flood recovery project designed its roads and bridges "per the guidelines of the Indian Roads Congress" (JTFRP, 2015); the drainage clauses of IRC:SP:48 were not read for this Manual [TBC]. |
| CPHEEO Manual on Storm Water Drainage Systems (2019) | Engineering reference. This Manual sets higher return periods under Clause 1.3.2. |
| NDMA Guidelines on Management of Urban Flooding (2010) and MoHUA SOP (2017) | This Manual puts into effect the NDMA directives on catchment-based design, detention and retention, waterbody protection and climate-adjusted IDF. |
| NDMA Urban Flood Risk Management Programme (UFRMP) and AMRUT 2.0 | Works funded under these programmes shall comply with this Manual. The development controls of Chapters 4–5 protect the capacity those works create. |
| IRC:SP:42-2014 and IRC:SP:50-2013 | Apply to road drainage only where they do not conflict with Chapter 6. |
| MBBL 2016, Chapter 9 | Model for RWH and for the inspection regime in Chapter 10. |
Commentary. RWH in Jammu and Kashmir is framed as a water supply and recharge measure. It works well for that purpose. It cannot, however, be relied on for flood control in the SW monsoon, because RWH sumps are usually full or the ground saturated by the time a late-August or September storm, such as those of September 2014 and August 2025, arrives after weeks of rain. The Manual therefore keeps harvest volume and attenuation volume apart, while letting recharge count as retention where it truly removes water from the system.
Jammu and Kashmir is spending on its drains and its rivers, but without a design basis. After the floods of 2014 the World Bank's Jhelum and Tawi Flood Recovery Project ($250 million, approved in 2015 and extended to 31 August 2026) took up the rehabilitation of about 56 of Srinagar's storm water pumping stations (JTFRP, 2015; as reported); a drainage master plan and DPR for 767 km² of Srinagar, modelled as "a … stormwater drainage system that is separate from the sewage system", was prepared by a consultant (as reported); ten drainage projects of the Srinagar Smart City and a storm network of about 650 km were reported to the Assembly in 2026 (as reported); and the Comprehensive Plan for Flood Management Works on the Jhelum spent ₹399.29 crore on its first phase, while ₹1,623.43 crore of a second phase of ₹5,411.54 crore, with regulatory gates at Hokersar, was approved in 2022 (as reported). In Jammu, storm drains such as the Digiana–Gangyal drain were sanctioned as named projects (as quoted), and the Jammu Master Plan 2032 asks for a storm-water DPR "immediately after the approval of this Master Plan" (§11.1.3). None of the documents found states a design storm, return period or runoff coefficient. No development-control condition stops new plots in the same catchments from using up the capacity such works create. Linking Chapters 4–5 to approvals closes that gap.
The Union Territory's law holds more of the tools than most States of the series. The UBBL-2021 set the widest statutory waterway buffers found in the series (NEER reading), 50, 30 and 20 m from the edge of the bank and 30 m from the highest water level, and make a rainwater harvesting proposal mandatory from plots of 100 m²; the Water Resources (Regulation and Management) Act, 2010 puts "the bed and banks of all water sources … city channels and flood spill channels" under I&FC and provides for flood basins to be declared and their use restricted (Part VI); the Flood Plain Zones (Regulation and Development) Act, 2005 provides for flood plain zoning; the Srinagar Master Plan 2035 sets "stormwater performance standards" of full coverage and no waterlogging and asks for detention and retention "source controls"; and the High Court, as "Custodia Legis of river Jhelum and other water bodies", has ordered the original width of the Jhelum restored and no construction near water bodies (PIL 8/2017, orders of 2015 and 2016, as recalled in the order of 29 May 2024). What the law lacks is the design standard and the use of its own flood routes. None of these instruments says how large a drain must be, which storm it must carry, how long a Srinagar sump must hold the city's runoff when the Jhelum closes its gates, how much water a hill site may put into its slope, or how much storage a paved plot removes; the Flood Plain Zones Act has not been brought into force, no flood basin has been declared under the Act of 2010, and the "flood zonation maps" to which the UBBL-2021 defer have not been found notified [TBC]. This Manual's checks are framed as part of the building permission and the online no-objection certificates of the UBBL-2021 (S.O. 304) and of the master plans, not as a separate certificate. This Manual is offered as a technical companion to these instruments, to the orders of the High Court, and to the drainage and flood works: it supplies the design storm, outfall-closed storage, hill-site drainage, infiltration and buffer numbers they do not set, as a proposal that a competent authority (for example H&UDD for building approvals, or the Jal Shakti Department for river and flood-basin matters) could adopt. Neither H&UDD, the Jal Shakti Department nor any other body has adopted it.
1.9 Roles and responsibilities
1.9.1 The responsibilities below apply under this Manual. They do not change any agency's statutory powers.
Table 1.4 — Roles and responsibilities under this Manual
| Agency | Role under this Manual |
|---|---|
| Housing and Urban Development Department (H&UDD), with the Town Planning Organisations of Kashmir and Jammu | Issues amendments to the UBBL-2021 (S.O. 304 of 1 December 2025), prepares the master plans of the local planning areas, among them the Srinagar Master Plan 2035 and the Jammu Master Plan 2032, under the Jammu and Kashmir Development Act, 1970, and administers the Municipal Corporations, Councils and Committees, the Development Authorities, UEED and LCMA. Would prepare the amendment of Clause 1.3.1(a) if the Manual were adopted, show flood-sensitive catchments, drainage reserves and regional facility sites in the master plans (Chapter 11), and, through the Town Planning Organisations, give regional support to Tier B authorities (Table 1.1). |
| Jal Shakti Department: Irrigation and Flood Control (I&FC), with its Kashmir and Jammu wings, and Public Health Engineering (PHE) | I&FC controls "the bed and banks of all water sources … city channels and flood spill channels" and the embankments (Water Resources (Regulation and Management) Act, 2010, section 81 [section number to be confirmed]), reads the river gauges in feet at Sangam, Ram Munshi Bagh, Asham, Akhnoor and on the Tawi, issues flood declarations, and is a no-objection authority for building permission (S.O. 304); PHE runs the water supply and registers bore wells. Would supply river levels, gauge zeros and flood marks for Chapter 5, consent to every outfall to a river, nallah, flood spill channel or city channel, approve the site-specific hydrology of Clause 2.3.6(i), apply this Manual to its drainage and flood works, and, as the route for flood basins under Part VI of the Act of 2010, map them with Chapter 7's flood line in mind. |
| State Stormwater Technical Committee (Clause 1.3.2) | Would adopt higher standards, issue Annexes, tables and the compliance calculator, concur with Tier A alternatives, decide variances referred to it and review the Manual (Clause 1.12). |
| Srinagar Municipal Corporation (SMC) and the Jammu Municipal Corporation (JMC); the Municipal Councils and Municipal Committees | Grant building permission as Building Permit Issuing Authorities under the UBBL-2021 and hold and clean the drains vested in them under the Jammu and Kashmir Municipal Corporation Act, 2000 and the Jammu and Kashmir Municipal Act, 2000 (drainage sections not read [TBC]); SMC runs the Town Drainage wing and the dewatering of Srinagar with UEED, and JMC the desilting of Jammu's nallahs. Would apply this Manual to their works, receive handed-over assets (Clause 10.14), and inspect and enforce (Clauses 10.12–10.15). |
| Urban Environmental Engineering Department (UEED); Town Drainage of SMC and of the Directorate of Urban Local Bodies Kashmir | UEED's mandate is "planning, designing and construction of works of sewerage and drainage in urban areas" (Srinagar Master Plan 2035, §13.3); its Sewerage and Drainage Division (West) works within the limits of JMC. With the Town Drainage wings it builds and runs Srinagar's drains and pumping stations, 89 in 2019 (Srinagar Master Plan 2035) and 104 permanent dewatering stations in 2026 (as reported). Would keep the register of drains and pumping stations with their sump levels and the river stage at which each gravity gate shuts (Chapters 5 and 9), and design its drains, pumps and sewers to this Manual, keeping sewage out of the storm drains (Chapter 8). |
| Srinagar Development Authority (SDA), Jammu Development Authority (JDA) and the other Development Authorities under the Jammu and Kashmir Development Act, 1970 | Plan and grant permission in their areas and are no-objection authorities under S.O. 304; JDA holds the Nazool and State land along Jammu's water bodies and would receive land released from the "Gair Mumkin Khad" class (Jammu Master Plan 2032, §§12.2.3–12.2.4). Would require the drainage report of Chapter 10 with each application or scheme, and release no khad land without the hydraulic study of Chapter 7. |
| Lake Conservation and Management Authority (LCMA, formerly LAWDA) and Wular Conservation and Management Authority (WUCMA) | LCMA manages the Dal and Nigeen and their catchment and is a no-objection authority under S.O. 304; WUCMA, constituted in 2012 under the Jammu and Kashmir Development Act, 1970, manages Wular and its feeder channels. Would consent to every outfall to the lakes and to Wular, with the sediment and dry-weather-flow interception of Chapter 8, and supply lake and outlet levels for Chapter 5. |
| Srinagar and Jammu Smart City companies | Build drains under the Smart Cities Mission and hand them to the Municipal Corporation. Would design them to this Manual from the dates of Clause 1.11. |
| Public Works (R&B) Department and the National Highways Authority of India (NHAI) | Build and maintain roads with their side drains, catch-water drains and culverts, which in the hill towns, and in Jammu, where "the road side drains serve as storm water drains" (Jammu Master Plan 2032, §5.1.3), are much of the minor drainage system. Would apply Chapter 6 and the hill-road rules to them, and discharge no road drain onto an unprotected slope. |
| Jammu and Kashmir State Disaster Management Authority (J&K SDMA), the District Disaster Management Authorities, and the Jammu and Kashmir Economic Reconstruction Agency (JKERA) | J&K SDMA met only once in 2010–15 (CAG, 2016); no urban flood plan or standard operating procedure of it was read for this Manual [TBC]. JKERA runs the Jhelum and Tawi Flood Recovery Project. Would supply the hazard, landslide and subsidence maps used in the screening of Clause 2.3.6(i) and the hill rules, and lead post-event reviews with the Authority (Clause 10.16). |
| Forest, Ecology and Environment Department, with the Jammu and Kashmir Wetland Authority (constituted on 25 November 2020) and the Wildlife Department | The Wetland Authority applies the Wetlands Rules, 2017; no wetland of the Union Territory had been notified under rule 4 by September 2024. The Wildlife Department holds Hokersar, Shallabugh, Hygam, Freshkoori, Kranchoo, Chatlam and Manibugh as wetland conservation reserves, notified by Order No. 710-C of 17 July 1945. Their consent would be needed before a wetland or Ramsar site is used for storage or an outfall (Chapter 7). |
| Jammu and Kashmir Pollution Control Committee (JKPCC) | Monitors rivers, lakes and treatment plants and reports to the NGT (OA 504/2024, OA 413/2025). Would receive the records of sewage found in storm drains under Chapter 8. |
| Revenue Department and the Deputy Commissioners | The revenue records show the rivers, nallahs, khads, nambals and rakhs, much of Jammu's drainage land as "Gair Mumkin Khad", and the common and kahcharai land; the Deputy Commissioners were directed by the High Court to ensure that "no construction of any kind is raised near the water bodies" (order of 10 June 2016, as recalled in 2024). Would record drainage reserves and the surveyed extent of waterbodies, beside their revenue class, in the land records. |
| JKSPDC, NHPC and the other dam operators | Operate Baglihar (JKSPDC), Salal and Dul Hasti (NHPC) and the other dams on the Chenab; Ranjit Sagar, on the Ravi below Kathua and Basohli, is operated from Punjab. Would supply reservoir levels, gate and flushing schedules and release records for Chapter 5. |
| Central Water Commission (CWC), a body of the Union | Publishes the Flood Estimation Report for zone 7 used in Chapters 2 and 3 and runs the river sites at Khanabal, Sangam, Ram Munshi Bagh, Safapora, Akhnoor, Ganeshpura and Sidhra. Would supply river stage records, warning and danger levels, datums and forecasts for Chapter 5. |
| Central Ground Water Board (CGWB), North Western Himalayan Region, Jammu, a body of the Union | Assesses the groundwater of the Union Territory (stage of extraction 22.28% in 2024, all 149 units "Safe") and holds the observation wells. Would supply groundwater levels and quality, and the shallow and artesian levels of the valley floor, with the Jal Shakti Department. |
| IMD (Meteorological Centre Srinagar), and road and rail owners (PW (R&B), NHAI, Indian Railways) | IMD's stations supply the rainfall records of Chapter 2. Road and rail owners would apply this Manual to road drainage (Chapter 6), culverts and linear works (Clause 1.5.7). |
Commentary. Stormwater in Jammu and Kashmir is split between H&UDD, through the UBBL-2021, the master plans and the Development Authorities; the Municipal Corporations, Councils and Committees, through the drains vested in them; UEED and the Town Drainage wings, through the drains, sewers and pumping stations of Srinagar and the sewerage of Jammu; I&FC, through the rivers, nallahs, khads, embankments, flood spill channel and city channels, under section 81 of the Water Resources (Regulation and Management) Act, 2010 [section number to be confirmed]; LCMA and WUCMA, through the Dal, Nigeen and Wular; the PW (R&B) Department and NHAI, through the road drains; the dam operators, through the reservoirs of the Chenab and the Ravi; and the High Court, which treats itself as "Custodia Legis of river Jhelum and other water bodies". Srinagar shows why the split matters. A drain in the city may be built by UEED, cleaned by SMC's Town Drainage, emptied over the embankment by a pumping station run by either, and discharged into the Jhelum, the flood spill channel or a city channel whose bed and banks are I&FC's, or into the Dal, which is LCMA's; and it carries sewage, because the city could treat 32% of its sewage in 2024 (JKPCC, 2024). In Jammu the drains are largely the side drains of roads, which cover about 40% of the city, and the khads into which they run are recorded in the revenue records as "Gair Mumkin Khad" land that the Jammu Master Plan 2032 proposes to release in part (§§5.1.3, 12.2.3). The Municipal Acts of 2000 are understood to vest public drains in the local bodies (drainage sections not read [TBC]), but no rule or order found divides the drains, nallahs and khads between the bodies concerned [TBC]. Until such a rule is made, this Manual assigns the drainage elements as in Table 1.5, as Chapter 6 does for the drains themselves, and recommends that each town keep a register of its drains, nallahs, pumping stations and outfalls with an owner for each reach. The assignment is this Manual's working split for applying its clauses; it does not change any agency's powers.
Table 1.5 — Working assignment of drainage elements under this Manual
| Element | Assigned to |
|---|---|
| Rivers (the Jhelum, the Tawi, the Chenab, the Ravi, the Ujh, the Basantar, the Devak and the others), nallahs and khads, with their beds and banks; the embankments; the flood spill channel and any supplementary channel; the city channels, such as the Tsunth Kol and the Padshahi Canal; canals and kuhls (कूहल; gravity irrigation channels; the "zamindari khuls" of the Act of 2010) | I&FC; within municipal limits the Municipal Corporation, Council or Committee desilts and clears the nallahs it cleans now; the land remains with its recorded owner |
| Drainage schemes, drains and dewatering (pumping) stations of Srinagar | UEED for planning, design and construction, and the Town Drainage wings of SMC and of the Directorate of Urban Local Bodies Kashmir for operation and maintenance, each reach and station on the register of drains |
| Drains of Jammu within the limits of JMC | JMC and the Sewerage and Drainage Division (West) of UEED; UEED's schemes at Bhathindi, outside the limits of JMC, with UEED until they are rationalised |
| Drains of the other towns | The Municipal Council or Municipal Committee concerned |
| Road drains, catch-water drains and culverts of roads | The PW (R&B) Department for its roads; NHAI for national highways |
| The Dal and Nigeen and the drains that LCMA holds in its area; Wular and its feeder channels; the wetland conservation reserves; wetlands under the Wetlands Rules, 2017 | LCMA; WUCMA; the Wildlife Department; the Jammu and Kashmir Wetland Authority |
| Drains and storage of SDA, JDA, the Jammu and Kashmir Housing Board, the Smart City companies of Srinagar and Jammu, and colony developers, until handed over in writing | The body that built them |
| Reservoirs, their gates and releases, and their drawdown land | NHPC (Salal, Dul Hasti; Pakal Dul through its joint venture); JKSPDC (Baglihar); the operator of Ranjit Sagar |
| Sewers, the interception of sewage from drains and nallahs, and sewage treatment plants (Clause 8.9) | UEED |
| Records of drainage land (Gair Mumkin Khad, nambal, rakh, kahcharai) | The Revenue Department |
This Manual names departments and authorities as the statutes, orders and records name them. A manual that names one owner for each task does not fix institutions by itself, but it removes ambiguity about who signs what.
1.10 Variances and waivers
1.10.1 Variance. The Authority may grant a variance from a numeric requirement where the Applicant shows, through a report certified under Clause 10.6, that:
- (a) compliance is impracticable because of site conditions such as a high groundwater table, contaminated soil, rock, or a site area too small for the required facility; and
- (b) the proposed alternative gives equal or better performance at the downstream point of Chapter 5, or the shortfall is made up by fee-in-lieu or off-site works in the same catchment.
1.10.2 Waiver. The Authority may waive Chapter 4 detention requirements (not retention) where a hydraulic analysis certified under Clause 10.6 shows that the site discharges directly to the sea, or to a tidal reach with no flood-prone property downstream, and that undetained flow does not worsen the outfall-closed condition of Chapter 5. Jammu and Kashmir has no coast and no tidal reach, so no site in the Union Territory qualifies for this waiver. A site that drains to the Jhelum, the flood spill channel or a city channel through a gate, or only by pumping, as in Srinagar and the embanked towns of the valley, to a lake held by its outlet, such as the Dal or Wular, or to a reservoir or barrage pond, such as Salal, Baglihar or the Tawi barrage, is in the outfall-closed condition of Chapter 5 whenever the receiving water is high, and detention is not waived for it; nor is it waived for a site because it drains to a steep khad or nallah or down a hill slope.
1.10.3 No variance or waiver. No variance or waiver shall be granted for:
- (a) a sewage connection to a storm drain;
- (b) the lowest habitable floor level of Chapter 6;
- (c) any reduction of a waterbody setback below the Zone 1 minimum of Clause 7.4.7, or any fill or construction in the no-fill zone of Chapter 7; or
- (d) the retention requirement in a flood-sensitive catchment, except by fee-in-lieu under Clause 1.7.
1.10.4 Procedure.
- (a) The request shall be made on Form 1-2 (Variance / Waiver Request) with the preliminary drainage report.
- (b) A Tier B authority shall refer any variance on a site of 1 ha or more to the State Stormwater Technical Committee.
- (c) A decision shall state its reasons and any conditions, and shall be entered in the public register of Clause 10.17.
- (d) A variance runs with the approval. It lapses if the approval lapses.
Commentary. The 2006 APWA 5600 included a waivers section (5601.6), and Georgia allows waivers where downstream analysis shows a peak control is unnecessary. The waiver of Clause 1.10.2 is narrow: on a tidal coast, undetained flow can help by passing through before the tide closes the outfall, but only an analysis can show that. This Manual requires every decision to be published because publication deters case-by-case erosion of the standard; in Jammu and Kashmir the Srinagar Master Plan 2035 records that the plan of 1971–91 "triggered growth in west and southwest directions of Srinagar mostly in low lying areas, wetlands and flood absorption basins adjacent to Flood Spill Channel", the Jammu Master Plan 2032 that the drainage channels "have fallen prey to the accelerated urban growth", and the High Court has had to order encroachments removed from the banks of the Jhelum and "the original width of the river Jhelum" restored (PIL 8/2017, orders of 2014 and 2015, as recalled in 2024).
1.11 Transition provisions
1.11.1 Effective date. This Manual takes effect for new applications 6 months after notification (the effective date).
1.11.2 Applications in process. An application filed complete before the effective date may be decided under the rules in force when it was filed, if a decision is issued within 12 months of the effective date. Otherwise, this Manual applies.
1.11.3 Phased start for Tier B. In Tier B authorities, Chapters 4 and 5 apply from 24 months after notification, except in flood-sensitive catchments, where they apply from the effective date.
1.11.4 Public works. DPRs sanctioned before the effective date may proceed as sanctioned. Any DPR revised or re-tendered after the effective date shall comply. Departments shall report non-compliant works in progress to the State Stormwater Technical Committee within 12 months.
1.11.5 Before the annexes are issued. Until an annex referred to in this Manual is issued, the Applicant shall use the method stated in the clause, with values agreed with the Authority and recorded in the drainage report.
Commentary. The 6-month lead time matches the lead time for NIH-DHAARA updates in Clause 2.14.2. Singapore gave a similar interval for its 2025 detention addendum (issued 16 Apr 2025, applied from 1 Oct 2025). The 12- and 24-month periods are set by this Manual to let Tier B authorities train staff and to let the State issue the design-aid tables (Clause 1.7).
1.12 Review and amendment
1.12.1 The State Stormwater Technical Committee shall review this Manual every 10 years, and after any event that exceeds the 1% AEP design depth as set out in Clause 2.14.1.
1.12.2 Amendments shall be notified in the Gazette, published with a change log, and take effect 6 months after notification unless the notification states otherwise.
1.12.3 Any person may propose an amendment to the Committee. Proposals and the Committee's decisions shall be published.
References (chapter)
- Government of India. The Jammu and Kashmir Reorganisation Act, 2019 (No. 34 of 2019), sections 13, 32, 53 and 55 and the Fifth Schedule, Table 4 (Gazette of India copy). https://faolex.fao.org/docs/pdf/IND227546.pdf
- Ministry of Home Affairs. Transaction of Business of the Government of Union Territory of Jammu and Kashmir (Second Amendment) Rules, 2024, as reported (Greater Kashmir, 12–13 July 2024; G.S.R. number not found [TBC]).
- General Clauses Act, 1897, section 3(58).
- Jammu Municipal Corporation. Jammu and Kashmir Unified Building Bye-Laws, 2021, J&K Official Gazette, Extraordinary, Vol. 134, No. 39-4, Part III, 24 December 2021 (clauses 1.1, 2.1, 2.6, 2.18, 5.2.1.7, 5.2.5, 6.1, 6.20, 7.12, Table 5-9 and Chapter 10 read). https://huddobps.jk.gov.in/JMCUBYL.pdf
- Jammu Municipal Corporation. Notification of amendments to the Unified Building Bye-Laws, J&K Official Gazette, Vol. 134, No. 49-3, 9 March 2022. https://jmc.jk.gov.in/adminjmcpanel/noticefiles/2142022372181344.pdf
- Housing and Urban Development Department. S.O. 304 of 1 December 2025 (amendments to UBBL-2021: online auto-scrutiny, no-objection certificates, negative lists). https://obps.jk.gov.in/BPAMSClient/seConfigFiles/Downloads/SO%20304%20DT%2001.12.2025.pdf ; S.O. 58 of 26 February 2026 (listed; not read [TBC]); draft amendments of 9 September 2026 (as reported, Daily Excelsior).
- Jammu and Kashmir Municipal Corporation Act, 2000 (Act XXI of 2000) and Jammu and Kashmir Municipal Act, 2000 (Act XX of 2000) (sections cited in S.O. 304 and the draft of 2026; drainage sections not read [TBC]).
- Jammu and Kashmir Development Act, 1970 (Act XIX of 1970).
- Jammu and Kashmir Water Resources (Regulation and Management) Act, 2010 (Act XXI of 2010), with the Rules of 2011 (as quoted); section numbers from the title index of lawgist.in, to be confirmed against an official copy [TBC]. https://jklaw.nic.in/jklawData/StaActs/Water%20Resources%20(Regulation%20and%20Management)%20Act,%202010.pdf
- Jammu and Kashmir Flood Plain Zones (Regulation and Development) Act, 2005 (Act XVII of 2005), sections 1–4 read. https://indianemployees.com/acts-rules/details/jammu-and-kashmir-flood-plain-zones-regulation-and-development-act-2005
- Ministry of Environment, Forest and Climate Change. Wetlands (Conservation and Management) Rules, 2017; List of 80 Ramsar sites of India, 31 January 2024. https://moef.gov.in/uploads/2024/03/80-Ramsar-sites-of-India-31-01-2024.pdf
- Forest, Ecology and Environment Department, Jammu and Kashmir. Report in NGT OA 239/2024 of 9 September 2024, with the replies of the Wildlife Department and WUCMA (the Wetland Authority; Order No. 710-C of 17 July 1945). https://www.greentribunal.gov.in/sites/default/files/news_updates/REPORT%20BY%20FOREST%20DEPTT.%20JAMMU%20&%20KASHMIR%20IN%20OA%20239%20OF%202024%20IN%20News%20item%20titled%20What%20Challenge%20Are%20Kashmiri%20Wetlands%20Facing.pdf
- High Court of Jammu and Kashmir and Ladakh. Environmental Policy Group v. Union of India, PIL 8/2017 with PIL 2/2014 and PIL 18/2018, order of 29 May 2024. https://livelaw.in/pdf_upload/pil-8-of-2017-544110.pdf ; Syed Iqbal Tahir Geelani v. State, PIL 159/2002 (the Dal), order of 19 July 2002 (as quoted) and later orders (as reported; judgment of 30 October 2025 not read [TBC]); order on Wular of November 2020 (as reported, Kashmir Reader, 6 November 2020).
- Jammu and Kashmir Pollution Control Committee. Response in NGT OA 504/2024 of 14 August 2024 (sewage of Srinagar and the Dal); report in NGT OA 413/2025 of March 2026, with the CPCB list of Polluted River Stretches for Restoration of Water Quality, October 2025; compliance report in NGT OA 642/2024 of 13 September 2024.
- National Green Tribunal. OA 239/2024 with OA 237/2026, order of 13 November 2026 (as reported, Daily Excelsior); OA 190/2025 and OA 93/2023 (as reported).
- Comptroller and Auditor General of India. Report No. 4 of 2016, Performance Audit of Disaster Management in the State of Jammu and Kashmir. https://cag.gov.in/webroot/uploads/download_audit_report/2017/Report_No.4_of_2016_-_Performance_Audit_of_Disaster_Management_in_the_State_of_Jammu_and_Kashmir_Government_of_Jammu_and_Kashmir.pdf ; Audit Report on the Prime Minister's Development Package for the year ended 31 March 2019, Chapter VI (2021; report number not on the chapter read). https://cag.gov.in/uploads/download_audit_report/2021/chap_6-061af2ebc7e35d9.21045816.pdf
- Central Ground Water Board. Aquifer mapping (NAQUIM) reports for the Kashmir valley (March 2017) and the outer plains of the Jammu province; Ground Water Year Book 2021-22; Dynamic Ground Water Resources of Jammu and Kashmir, 2022 and 2024.
- Indian Roads Congress. IRC:SP:42-2014, Guidelines on Road Drainage; IRC:SP:48, Hill Road Manual (drainage clauses not read [TBC]).
- Grierson, G.A. A Dictionary of the Kashmiri Language (Asiatic Society of Bengal, 1916–1932), DSAL edition; Platts, J.T. (1884). A Dictionary of Urdū, Classical Hindī, and English, DSAL edition (local terms; no Dogri dictionary was consulted). https://dsal.uchicago.edu/dictionaries/grierson
- Press reports of the renaming of LAWDA as LCMA (3 November 2021), the allocation of portfolios (October 2024), the Business Rules (2024–2026) and the hearing of September 2025 in PIL 8/2017 (secondary sources). https://www.greaterkashmir.com/ ; https://www.dailyexcelsior.com/
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A, §4.4.1.4 (Table 4.1 and notes).
- Kakkar, R. (CPHEEO) (2023). Understanding Urban Stormwater Management. CSE, Aug 2023.
- National Disaster Management Authority (2010). National Guidelines on Management of Urban Flooding.
- MoHUA (2016). Model Building Bye-Laws, Chapter 9.
- Lok Sabha Unstarred Question 1847, 30 Jul 2026 (MoHUA). https://sansad.in/getFile/lsapps/loksabhaquestions/annex/188/AU1847_x29brZ.pdf
- India Meteorological Department. Extremes of Temperature and Rainfall for Indian Stations (up to 2012): monthly, seasonal and annual 24-hour records and data periods for the eleven stations of Jammu and Kashmir. https://mausam.imd.gov.in/bengaluru/mcdata/Extremes.pdf
- India Meteorological Department. Press release of 27 August 2025, Annexure I (24-hour rainfall to 08:30 IST: Jammu 38 cm, Udhampur IAF 63 cm). https://mausam.imd.gov.in/Forecast/marquee_data/Press%20Release%2027-08-2025.pdf
- Ray, Bhan & Bandopadhyay (IMD) (2015). Current Science 109(3), 580–591 (the rainfall of September 2014 in Jammu and Kashmir; title not recorded [TBC]). https://www.currentscience.ac.in/Volumes/109/03/0580.pdf
- Malik (2021). Natural Hazards 110(3), 1911–1929 (the floods of 2014 in the Kashmir valley; title not recorded [TBC]). https://pmc.ncbi.nlm.nih.gov/articles/PMC8424175
- Ministry of Earth Sciences. Reply to Lok Sabha Starred Question *158, 27 July 2022 (the cloudburst definition and the Amarnath event of 8 July 2022). http://web.archive.org/web/20250528021810/https://moes.gov.in/sites/default/files/LS-in-English-158-27-7-2022.pdf
- Geological Survey of India (2024). Note on Preliminary Geological Assessment of Landslide at Pernote, Ramban, annexed to the compliance report of JKPCC before the NGT in OA 642/2024 (13 September 2024).
- Central Water Commission. Flood monitoring sites and highest flood levels in Jammu and Kashmir, as transcribed by SANDRP (2018, 2022 and 2025; no CWC bulletin was read for this Manual, and the datum is to be confirmed [TBC]). https://sandrp.in/
- Press reports of the floods of 1893, 1902–03, 1957 and 1959, the September 1992 floods, the Amarnath flood of 2022, the Chasoti cloudburst, the Vaishno Devi landslide and the Jammu and Udhampur rain of August 2025, the waterlogging of Srinagar on 1 August 2019 and of Jammu in 2025 and 2026, and the Thathri subsidence of 2023 (secondary sources). https://kashmirlife.net/ ; https://www.theweek.in/
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01.
- Mid-America Regional Council (2025). APWA 5600 Manual Factsheet; APWA Stormwater Standards Supplement (7 Nov 2025). https://www.marc.org/document/apwa-stormwater-standards-supplement
- Mid-America Regional Council. The Evolution of Regional Stormwater Design Standards (presentation). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Kansas City Metro Chapter APWA (2006). Section 5600, §5601.6 Waivers.
- PUB Singapore (2018, with Addendum No. 3 of 16 Apr 2025). Code of Practice on Surface Water Drainage, 7th ed.
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management.
- Centre for Science and Environment (2023). Urban Stormwater Management (presentation).
- Town Planning Organisation Kashmir (2019). Srinagar Master Plan 2035 (February 2019; notified by SRO 160 of 7 March 2019, as quoted; local area notified by SRO-429 of 21 October 2014): §4.2, Tables 8-2 to 8-4, §8.2.3, §8.4, §§13.3 and 14.4.4.2, and regulation 1-7-13. https://huddobps.jk.gov.in/Srinagar_Master_Plan_2035.pdf
- Jammu Development Authority / Town Planning Organisation Jammu. Jammu Master Plan 2032 (notified by SRO 90 of 3 March 2017, as quoted; amended by S.O. 243 of 2022 and S.O. 19 of 2024, as listed; revision reported pending): §§2.4, 5.1.3, 7.3.2, 7.3.3, 11.1.3 and 12.2.3. https://huddobps.jk.gov.in/JMP2032.pdf
- World Bank. Jhelum and Tawi Flood Recovery Project (P154990): Integrated Safeguards Data Sheet and draft Environmental and Social Management Framework (April 2015). https://ewsdata.rightsindevelopment.org/files/documents/90/WB-P154990_JSbE55j.pdf
- Bentley Systems (2023). Case study: Preparation of Drainage Master Plan and Detailed Project Report for Stormwater Drainage System in Srinagar City (vendor case study; secondary source). https://www.bentley.com/en/esdg/preparation-of-drainage-master-plan-and-detailed-project-report-for-stormwater-drainage-system-in-srinagar-city-jammu-and-kashmir/
- Housing and Urban Development Department. Reply in the Legislative Assembly on Srinagar's drainage network and dewatering stations, 12 February 2026, as reported by Kashmir Life (secondary source). https://kashmirlife.net/srinagar-completes-10-drainage-projects-650-kilometre-storm-network-backed-by-104-permanent-dewatering-stations-425018/
Annexes and forms
| Annex / Form | Content |
|---|---|
| 1A | List of Tier A authorities, with the boundaries of the Municipal Corporations and of the local planning areas of Srinagar and Jammu notified under the Jammu and Kashmir Development Act, 1970 |
| 1B | Maps of flood-sensitive catchments |
| 1C | Policy Supplement: text of alternatives S-1 to S-5 and model council resolution |
| 1D | Model UBBL-2021 amendment and model ULB bye-law |
| Form 1-1 | Applicability Determination |
| Form 1-2 | Variance / Waiver Request |
Commentary. Jammu and Kashmir's floods come from four sources, and the two divisions of the Union Territory meet them differently. The first is the Jhelum in the Kashmir valley, held above Srinagar and the valley towns by its embankments. In September 2014, when monsoon moisture met a western trough, Qazigund received 599.8 mm in four days and Katra 698.6 mm in three, while Srinagar's own gauges recorded only about 140–152 mm over 3–6 September (Ray et al., 2015): the city flooded from the river, through breaches of the embankments, not from its own rain. The Jhelum reached its highest levels at Sangam and Ram Munshi Bagh (1,588.99 m on 8 September 2014 at Ram Munshi Bagh in one CWC list and 1,589.65 m in another; CWC data as transcribed by SANDRP), and almost 34% of the Srinagar planning area, 262 km², was under water (Srinagar Master Plan 2035, §4.2), in places up to 16 feet deep and for up to 25 days (Malik, 2021). The record of that flood is in conflict: the Comptroller and Auditor General counted 304 deaths (217 in the Jammu division and 87 in Kashmir) and 2,40,004 houses damaged (CAG, Report No. 4 of 2016), a study counts 277 deaths (Malik, 2021) and the press 284 (as reported), and the Government told the Assembly in 2026 of more than 1.6 lakh structures damaged (as reported); the breach locations have not been found [TBC]. The Comptroller and Auditor General found that the flood spill channel built after the great flood of 1902 or 1903 (the sources differ) for 17,000 cusecs could carry only 4,000, and that the floods "may have been mitigated" had two flood schemes been carried out as approved (CAG, 2016). The Jhelum has flooded the valley before: in 1893, in 1902 or 1903, and in 1957 and July 1959, when it was reported to have stood at "30.25 feet" on a gauge that is not named (as reported). The second is the storm of the outer hills of the Jammu division. In the 24 hours to 08:30 on 27 August 2025 IMD recorded 38 cm at Jammu and 63 cm at Udhampur IAF (IMD, press release of 27 August 2025); the Tawi at Sidhra rose to 321.1 m, 2.25 m above its highest level of 2014 (CWC data as transcribed by SANDRP); and more than 110 people died in the Union Territory in two weeks (as reported). Earlier storms on the same front, in September 1988 (Batote 316.2 mm and Katra 292.4 mm in a day), August 1996 and 1997, and September 1992, when the Chenab at Akhnoor rose to 61 ft on the gauge of I&FC and to its highest level of 324.29 m (CWC data as transcribed by SANDRP; as reported), show that it is not new (IMD). The third, as in the other mountain editions of the series, is the cloudburst, the debris flow and unstable ground: on 8 July 2022 a flood at the Amarnath cave killed 16 people although the gauge 50 m below the cave recorded 25 mm in the hour, which "does not satisfy the criteria for cloud burst" (MoES; as reported); on 14 August 2025 a cloudburst at Chasoti in Kishtwar killed more than 60 pilgrims on the Machail route, and on 26 August 2025 a landslide on the Vaishno Devi route above Katra killed 30 to 35, by differing counts; no gauge measured the burst at Chasoti (as reported); and at Thathri in Doda (2023) and Pernote in Ramban (2024) houses cracked where water from the surface entered the slope (GSI, 2024; as reported). The fourth is the town drainage that fails in a fall that is not extreme: on 1 August 2019, 26.4 mm of rain left Lal Chowk, Budshah Chowk, Residence Road, M A Road and the Exhibition Grounds in Srinagar under water (as reported), Jammu's colonies from Gangyal to Trikuta Nagar and Nanak Nagar flooded in 2025 and 2026 (as reported), and in both cities the drains carry sewage: Srinagar could treat 32% of its sewage in 2024 (JKPCC, 2024), and the Jammu Master Plan 2032 records that its "Storm water drains carry considerable quantities of raw and untreated effluents".
Missing design makes all four worse. No design storm, return period or drain standard was found for the drains of any town in the Union Territory, and Srinagar's drains end at pumping stations, 89 counted in 2019 (Srinagar Master Plan 2035) and 104 permanent dewatering stations of about 2,300 cusecs reported in 2026 (as reported), which together could empty the 767 km² of the city's drainage plan at only about 0.3 mm of rain an hour once the river closes the gravity outfalls (NEER reading). The UBBL-2021 control setbacks, plinths and rainwater harvesting, not runoff. Objectives (b) to (e) address the storage, outfall and building-level failures, which a drain-sizing manual alone cannot fix; the first source is answered by the outfall-closed rules of Chapter 5 and the floodplain rules of Chapter 7, and the third by the siting, screening and debris rules of Chapters 2, 6 and 7, because no drain is sized to carry a debris flow or a river that has left its embankments.
No national instrument requires on-site detention. CPHEEO (2019) is advisory and describes peak control only as typical practice. NDMA (2010) says detention and retention "will" be included but gives no sizing rule. MBBL 2016 and the Jammu and Kashmir Unified Building Bye-Laws 2021 mandate RWH only. Objective (a) is therefore the main new step this Manual takes.