Chapter 4Site Runoff Control: Retention and Detention
4.1 Purpose and scope
4.1.1 This chapter sets the performance standard that every regulated development shall meet for runoff leaving the site. It covers:
- (a) the order in which runoff-control measures are to be applied (Clause 4.3);
- (b) retention of frequent rainfall, and how retained volume is credited against detention (Clause 4.4);
- (c) release-rate criteria for standard and flood-sensitive catchments (Clause 4.5);
- (d) the procedure for sizing detention storage and outlets (Clauses 4.6 to 4.9);
- (e) facility types, rainwater harvesting (RWH) accounting, and high-groundwater sites (Clauses 4.10 to 4.12);
- (f) regional detention and fee-in-lieu (Clause 4.13);
- (g) simplified methods for small sites: the Tier B tables and the fixed-coefficient route (Clause 4.14); and
- (h) public safety (Clause 4.15).
4.1.2 This chapter applies to land disturbance of 0.1 ha or more, or new or replaced impervious area of 500 m² or more, as set in Chapter 1. Single dwellings below that threshold, and road resurfacing that adds no impervious area, are exempt. The existing RWH mandate of the building rules (the complete rainwater harvesting proposal that chapter 10 of UBBL-2021 makes mandatory for every building on a plot of 100 m² or more, with recharge for buildings on plots of more than 500 m² and inspection before a completion certificate or service connection is issued; the rules are discussed in the Commentary to Clause 4.11) continues to apply to every building it covers, whether or not this chapter applies.
4.1.3 Rainfall inputs come from Chapter 2. Hydrologic methods come from Chapter 3. Tailwater, downstream analysis and the outfall-closed check come from Chapter 5. Water quality volume (WQv) treatment comes from Chapter 8. Where this chapter and those chapters overlap, the more stringent requirement governs.
4.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Retention | Permanent removal of runoff from the surface drainage system by infiltration, evapotranspiration or reuse, so that the water never reaches the outfall. |
| Retention depth | The 90th percentile wet-day 24-hour rainfall depth for the site's zone (Clause 2.10, Annex 2E). |
| Required retention volume (RRV) | The runoff volume from the retention depth over the post-development site (Clause 4.4.2). |
| Detention | Temporary storage of runoff, released through a controlled outlet at a rate set by Clause 4.5. |
| Retention credit | The reduction in required detention storage that results from retention practices, determined by routing under Clause 4.4.6. It is not the same as the retained volume. |
| Permissible site discharge (PSD) | The maximum rate at which a site may discharge for a stated AEP, in L/s or L/s/ha. |
| Site storage requirement (SSR) | The detention storage required per hectare of site under the simplified method of Clause 4.14. |
| Multi-stage outlet | An outlet structure with separate openings at different levels, each controlling a different AEP (Figure 4.2). |
| Drawdown time | Time from the peak stored volume until the stated fraction of that volume has been released. |
| Emergency spillway | A secondary overflow that passes flows above the primary outlet capacity, or all flow when the primary outlet is blocked, without overtopping the embankment. |
| Freeboard | Vertical distance between the maximum design water level and the embankment crest or other critical level. |
| Flood-sensitive catchment | A catchment listed in Clause 4.5.3 or notified under Clause 4.5.4. |
| Authority | The approving authority under Chapter 1 (the building permit issuing authority under UBBL-2021, that is the Srinagar or Jammu Municipal Corporation, a Municipal Council or Municipal Committee, or a Development Authority under the Jammu and Kashmir Development Act 1970, such as SDA or JDA, in its area, acting through the online building permission system of S.O. 304 of 1 December 2025, as applicable). |
| Tier A / Tier B | Adoption tiers defined in Chapter 1. Tier A: the Srinagar Municipal Corporation (SMC), with the Srinagar Development Authority (SDA), in the Srinagar Local Planning Area; and the Jammu Municipal Corporation (JMC), with the Jammu Development Authority (JDA), in the Jammu Local Planning Area. Tier B: Municipal Councils and Municipal Committees. |
4.3 Order of measures
4.3.1 Every site runoff-control design shall apply measures in the following order, and shall document in the submittal why each earlier step could not do more:
- Preserve. Keep existing waterbodies, talabs, natural drainage lines, wetlands, and permeable soils and vegetation. Avoid fill in flood storage (Chapter 7).
- Retain. Retain the RRV on site by infiltration, reuse or evapotranspiration (Clause 4.4).
- Detain. Detain the remaining runoff so that the release-rate criteria of Clause 4.5 are met for every design storm and duration (Clauses 4.6 to 4.9).
- Convey. Convey the 1% AEP (100-yr) flow safely through the site to the receiving system on a defined overland path (Chapter 6), and check the receiving system downstream (Chapter 5).
4.3.2 Preservation and retention reduce the detention required (Clauses 4.4.6 and 4.4.7). They do not relieve the site of the release-rate criteria of Clause 4.5 or of the downstream analysis of Chapter 5.
Commentary. This order follows the "layers of stormwater management" adopted in the Kansas City Metro APWA Section 5600 Version 2025.01: preserve or restore, retain, detain, convey, maintain (MARC factsheet; MARC Supplement, Nov 2025). Maintenance is the fifth layer and is set in Chapter 10. The 2025.01 manual credits retention and natural-area preservation against detention size (MARC Supplement, Nov 2025). Clause 4.4.6 adopts that credit, and defines it so that it cannot be claimed twice.
4.4 Retention
4.4.1 Requirement
The site shall retain the RRV. Retention shall be achieved by one or more of the following:
- infiltration practices (soakaways, infiltration trenches, permeable pavement with an infiltration base, bioretention);
- rainwater reuse that is drawn down by a demonstrated non-potable demand;
- green roofs and landscape areas that do not drain to the outfall in the retention-depth storm.
The limits of Clause 4.4.4 apply.
4.4.2 Computation of the RRV
RRV (m³) = 10 × Q_R × A
where:
- Q_R (mm) is the runoff depth from the retention depth P_R (Annex 2E). It is computed with the SCS-CN method for the post-development cover of each sub-area, at AMC II, with Ia = 0.2S (Chapter 3); and
- A (ha) is the area of the site that drains to the outfall.
Q_R shall be computed for each sub-area separately and summed. An area-weighted CN shall not be used where impervious and pervious areas differ by more than 20 CN points.
The volumetric method RRV = 10 × P_R × Rv × A, with Rv = 0.05 + 0.009 × I (I = percent impervious), may be used for sites under 0.5 ha and under the Tier B method.
Commentary. The Rv formula is the one used in the KC water quality volume (MARC BMP Manual 2012). It is simple to review for small sites. The SCS-CN form is required for larger sites so that the retention computation uses the same runoff model as the detention routing. That keeps the credit computation of Clause 4.4.6 consistent.
4.4.3 Verification
Retention by infiltration shall be supported by:
- (a) site infiltration tests at the location and depth of each practice, at the frequency set in Chapter 8;
- (b) a design infiltration rate of no more than half of the measured rate; and
- (c) groundwater evidence showing the seasonal high groundwater table at least 1.0 m below the base of the practice (Chapter 8).
Retention by reuse shall be supported by a demand calculation showing that the RRV is drawn down within 72 hours by a continuous non-potable use, such as toilet flushing, cooling or irrigation.
Commentary. The factor of 2 on measured infiltration rate has no direct precedent; this Manual sets it to allow for clogging and for the difference between a test pit and a full-scale practice. Chapter 8 may set a different factor; if it does, Chapter 8 governs.
4.4.4 Limits on retention
4.4.4.1 Infiltration practices shall not be used:
- where the seasonal high groundwater table is less than 1.0 m below the base (Chapter 8);
- on contaminated land;
- within the setbacks from foundations, wells and septic systems set in Chapter 8; or
- on fill, unless tested after placement.
4.4.4.2 Where the RRV cannot be fully retained, the shortfall shall be stated in the submittal. The shortfall shall be treated as WQv under Chapter 8 and shall get no retention credit.
4.4.5 Drawdown of retention
Retention storage shall be emptied by infiltration or reuse within 72 hours of the end of the retention-depth storm, verified by the tests of Clause 4.4.3.
4.4.6 Retention credit: definition and computation
4.4.6.1 What the credit is. The retention credit is the reduction in required detention storage that results when the retention practices are included in the post-development routing. It is computed. It is not assumed equal to the RRV.
4.4.6.2 Tier A method (routing). For each design storm and duration of Clause 4.6.3:
- (a) model each retention practice explicitly as a storage that is empty at the start of the storm, unless Clause 4.11 says otherwise;
- (b) let the practice fill from the front of the storm, and let it lose water during the storm only at the design infiltration or reuse rate of Clause 4.4.3;
- (c) once it is full, route its overflow to the detention facility; and
- (d) size the detention for the residual hydrograph.
The required detention storage is the largest storage over all storms and durations. The credit is the difference between that storage and the storage required with no retention. No further deduction shall be made.
4.4.6.3 Tier B method (simplified). The detention storage required by Clause 4.14 may be reduced by:
V_credit = C_R × RRV_provided
where C_R is the retention credit factor from Annex 4B for the zone, soil group and drawdown rate. Until Annex 4B is published, C_R = 0.
4.4.6.4 Retention that is not verified under Clause 4.4.3 gets no credit.
Commentary. "Credited against detention" (APWA 5600 2025.01) can be read in two ways. One reading subtracts the retained volume from the detention volume, cubic metre for cubic metre. The other routes the storms with retention in place and sees what detention is still needed. The two readings give very different answers in Jammu and Kashmir, because the mandatory 48- and 72-hour storms (Clause 2.5.2) fill any retention practice on the first day, long before the peak arrives on the last day (Clause 2.9.2). Unless the practice keeps infiltrating during the storm, it is full at the peak and does nothing to reduce the peak storage.
The illustrative example in Clause 4.6.7 shows the size of the effect. A 2 ha site with 552 m³ of retention (no infiltration during the storm) needs 138 m³ less detention for the 24-hour storm. That is a credit of about a quarter of the retained volume. For the 48- and 72-hour storms, which govern, the credit is close to zero. Subtracting the retained volume directly would have under-sized the detention by about 545 m³ (about 19%).
This Manual therefore defines the credit as the result of routing. Retention on fast-draining sandy soils, which keeps infiltrating through a multi-day storm, will earn a real credit. Retention that only fills will earn little. Both outcomes are physically correct. Setting C_R = 0 until Annex 4B exists is a safe default for Tier B, not a judgement that retention has no value: retention is still required for water quality and recharge (Chapter 8).
4.4.7 Preservation credit
Areas of the site that are permanently preserved in natural cover may be modelled at their pre-development CN in the post-development condition, provided that:
- they are protected by a registered covenant or dedication; and
- their runoff is not concentrated onto impervious surfaces.
This lowers both the RRV and the detention required. No other preservation credit applies.
4.5 Release-rate criteria
4.5.1 General
4.5.1.1 Peak discharge from the site shall be computed by a hydrograph method (Chapter 3) for the pre-development and post-development conditions with identical design storms (Clause 2.11.1). The Rational Method shall not be used for any part of storage sizing.
4.5.1.2 Pre-development is greenfield: open land in good condition for the mapped HSG. Existing impervious cover is not counted (Clause 2.11.5, Chapter 3). This applies to redevelopment as well, subject only to the constrained-redevelopment route of Clause 4.5.6.
4.5.1.3 The criteria apply at each point where runoff leaves the site. Where a site drains to more than one outfall, the criteria apply to each outfall for the area draining to it. Runoff shall not be diverted between catchments.
4.5.2 Standard catchments
For each of the 50%, 10% and 1% AEP (2-, 10- and 100-yr) storms, and for every duration in {1, 2, 3, 6, 12, 24, 48, 72 h}:
Q_post(T, d) ≤ 0.9 × Q_pre(T, d)
4.5.3 Flood-sensitive catchments
4.5.3.1 In the catchments listed below, the mixed-frequency rule of Clause 2.11.3 applies, for every duration in Clause 2.5.2:
Q_post(1% AEP, 100-yr) ≤ Q_pre(10% AEP, 10-yr), and Q_post(50% AEP, 2-yr) ≤ Q_pre(50% AEP, 2-yr).
Each cap is the pre-development peak at the duration that maximises it: the 10-yr peak for the 100-yr check, and the 2-yr peak for the 2-yr check. The cap applies to every post-development duration (Clause 2.11.3).
4.5.3.2 The flood-sensitive catchments are:
- (a) Srinagar behind the Jhelum embankments: the land of the SMC and SDA areas that drains to the Jhelum, the flood spill channel and the city channels through gated or pumped outfalls, including the catchment of Dal and Nigeen and the low land of the west-bank flood basins, from Lelhar and Lasjan to Rakh-e-Arth, Narkara and Hokersar;
- (b) Anantnag–Bijbehara–Pampore on the upper Jhelum: the land of Anantnag, Bijbehara and Pampore and of the other towns on the valley floor above Srinagar that drains to the Jhelum between Sangam and Srinagar and to the nallahs that join it there;
- (c) Sopore–Baramulla–Sumbal–Bandipora on the lower Jhelum and Wular: the land of Sopore, Baramulla, Sumbal and Bandipora that drains to the Jhelum below Srinagar, to Wular or to the flood spill channel;
- (d) Jammu's khads and the Tawi: the land of the JMC and JDA areas that drains to the Tawi and to its khads, among them the Balol, Thather and Bhalwal khads, including land recorded as Gair Mumkin Khad and the localities flooded in August 2025;
- (e) Kathua–Hiranagar on the Ujh and the Ravi, and Samba on the Basantar: the land of Kathua, Hiranagar and Samba that drains to the Ujh, the Ravi, the Basantar and their khads;
- (f) R.S. Pura–Bishnah–Arnia in the Sirowal: the land of R.S. Pura, Bishnah, Arnia and the other towns of the Sirowal that drains across waterlogged, flat land towards the international border;
- (g) Akhnoor on the Chenab: the land of Akhnoor that drains to the Chenab below the Salal reservoir;
- (h) Udhampur on the Tawi and the Devak, and Katra: the land of Udhampur that drains to the Tawi and the Devak, and of Katra that drains to the khads below it;
- (i) Hill towns of the Chenab valley: the land of Ramban, Batote, Banihal, Doda, Thathri and Kishtwar that drains to the Chenab and its tributaries or lies on the slopes of the subsidence and sliding zones of Pernote, Duksar and Thathri Nai Basti (Commentary to Clause 4.11); and
- (j) any catchment notified under Clause 4.5.4.
The boundaries shall be those mapped in Annex 4A.
4.5.4 Notification of further flood-sensitive catchments
4.5.4.1 The Authority may propose that a catchment be notified as flood-sensitive where one or more of the following is documented:
- (a) buildings or arterial roads flooded in an event of 1% AEP or more frequent, on at least two occasions in the previous 20 years;
- (b) receiving drains or channels with capacity below the 10% AEP flow under existing conditions;
- (c) an outfall that is held up by a river, lake or reservoir in flood, such as the Jhelum behind the embankments of Srinagar, Anantnag–Bijbehara, Pampore, Sopore and Baramulla, where the gravity outfalls are shut from flood-declaration stage and the town drains only by pumps, Wular below Sopore, Sumbal and Bandipora, Dal and Anchar when the river shuts their outlets, the Tawi at Jammu and Udhampur, the Chenab at Akhnoor, or the Salal, Baglihar or Ranjit Sagar reservoir, or that is buried or blocked by the debris of a khad or nallah, for part of the SW monsoon or of the spring snowmelt (Chapter 5);
- (d) loss of more than a quarter of the mapped tank and talab storage in the catchment since the earliest available survey; or
- (e) a basin master plan that relies on limiting site discharge.
4.5.4.2 The procedure shall be:
- The Authority prepares a technical note with the catchment boundary in GIS form and the evidence for 4.5.4.1.
- The State-level technical committee constituted under Chapter 1 reviews the note.
- The draft notification and map are published for public comment for at least 60 days.
- The Government notifies the catchment and the map is added to Annex 4A.
- The rule applies to applications received 6 months or more after notification. Applications received earlier are assessed under Clause 4.5.2.
4.5.4.3 A notified catchment may be de-notified only by the same procedure, and only after a basin study shows that the downstream system meets Chapter 5 with all development under Clause 4.5.2.
Commentary. The 0.9 factor is derived from the Denver (MHFD) analysis. In that analysis, ten basins each releasing 100% of the historic 100-yr peak still produced 106% of the historic peak at the outlet; releasing 90% at each gave 97% (UDFCD Full Spectrum Detention Release Rate Memorandum, 2012). The mixed-frequency rule has no direct precedent; the nearest is the Malaysian DID (2008) checklist, which required post-development 2-, 10-, 50- and 100-yr peaks below the pre-development 2-yr peak. The specific "100-yr post ≤ 10-yr pre" form appears in a New Berlin, Wisconsin planning discussion (not an adopted rule). The Srinagar entry follows the river and the pumps. In September 2014 about 34% of the Srinagar planning area, 262 km², was under water (Srinagar Master Plan 2035); the flood came down the Jhelum, which passed about 72,585 cusecs at Ram Munshi Bagh and set the CWC site's highest level of 1,588.99 m on 8 September, while the city's own gauges recorded only about 140–152 mm over the storm (Malik, 2021; CWC, as transcribed by SANDRP; Ray et al., 2015). The flood spill channel that carries the river round the city had been built for 17,000 cusecs after the flood of the early 1900s and had silted to 4,000 cusecs, and the CAG found that the impact of the floods "may have been mitigated" had two channel schemes been carried out as approved (CAG Report No. 4 of 2016). The city drains by pumps whenever the river is high: the master plan counts about 89 drainage pumping stations (38 lift, 21 gravity, 30 lift-cum-gravity) on about 119 km of primary and secondary drains (Srinagar Master Plan 2035, February 2019), and H&UDD told the Legislative Assembly in February 2026 of 104 permanent dewatering stations of about 2,300 cusecs, 281 mobile units and about 650 km of drains (as reported). About 2,300 cusecs, roughly 65 m³/s, over the 767 km² of the drainage master plan is about 0.3 mm of rain an hour (NEER's arithmetic), so when the river shuts the gravity outfalls the city drains only by storage and pumps. The city centre, Lal Chowk, Budshah Chowk, Residence Road, M A Road and the Exhibition Grounds, was waterlogged after 26.4 mm on 1 August 2019 (as reported). The master plan sets "stormwater performance standards" of 100% coverage and zero waterlogging, and it records that the wetlands to the south, west and north-west of the city "have been acting as flood retention basins", while the plan of 1971–91 drew growth into "low lying areas, wetlands and flood absorption basins" (Srinagar Master Plan 2035). The Anantnag–Bijbehara–Pampore entry follows the upper Jhelum, whose CWC site at Sangam has a danger level of 1,590.88 m and a highest level of 1,595 m from 4 September 2014, and at Khanabal a highest level of 1,595.43 m set on 3 September 2025 (CWC, as transcribed by SANDRP); in 2014 the river at Sangam exceeded 115,000 cusecs (Romshoo et al., 2018), and Qazigund recorded 206 mm in a day and 599.8 mm over 3–6 September (IMD; Ray et al., 2015); wells flow over much of Anantnag district (NAQUIM, Kashmir Valley). The Sopore–Baramulla–Sumbal–Bandipora entry follows the lower Jhelum and Wular: the CWC site at Safapora has a danger level of 1,579.66 m and a highest level of 1,582.1 m (2014), Wular's danger level is reported as 1,578 m, and the lake has shrunk from 157.74 km² in 1911 to 86.71 km² in 2007 (as reported), with less room for the floods it absorbs; 81.8% of Baramulla's observation wells stood within 2 m of the surface in May 2021 (CGWB). The Jammu entry follows the Tawi and its khads, which the master plan says are "transformed into gushing torrents" in the rains; Jammu recorded 380 mm in the 24 hours to 08:30 IST on 27 August 2025 (IMD), the Tawi at Sidhra rose to a new highest level of 321.1 m on 26 August 2025 (CWC, as transcribed by SANDRP), and land recorded as "Gair Mumkin Khad", more than 30% of the JDA's land, is proposed for release once the "true Khad" is fixed with I&FC (Jammu Master Plan 2032, §12.2.3). Roadside drains serve as the city's storm drains and cover only about 40% of it, and its storm-water DPR was still to be prepared (same plan, §§5.1.3 and 11.1.3). The Kathua–Hiranagar–Samba entry follows the Ujh, the Ravi and the Basantar: I&FC's levels for the Ujh at Panjtirthi are reported as 48,000 and 88,000 cusecs (as reported), the Basantar at Samba is in the most polluted priority of the CPCB list (October 2025), and more than half of Kathua's wells flow (NAQUIM, Outer Plains of Jammu Province). The R.S. Pura–Bishnah–Arnia entry follows the Sirowal, where water stands two to five metres below ground, waterlogging occurs towards its south-western extremity and the drains run towards the international border, beyond which their tailwater is not monitored (NAQUIM; Chapter 5). The Akhnoor entry follows the Chenab, whose CWC site at Akhnoor holds its highest level of 324.29 m from 10 September 1992; I&FC reported its gauge at 43 ft on 3 September 2025 against a danger level of 35 ft and a peak of 61 ft in 1992 (as reported), and the river below Salal carries the reservoir's desilting and flood releases (Chapter 5). The Udhampur and Katra entry follows the outer-hill front, where the plates of the CWC report are most exceeded: Udhampur IAF recorded 630 mm in the 24 hours to 08:30 IST on 27 August 2025 (IMD), and Katra 292.4 mm on 25 September 1988 and 698.6 mm in 72 hours in September 2014 (IMD; Ray et al., 2015); the Devak at Udhampur is in the most polluted priority of the CPCB list (October 2025), and the landslide of 26 August 2025 on the route above Katra was reported to have killed 30–35 people (as reported). The hill-town entry follows the Chenab valley, where the GSI found that "ingress of surface runoff through these cracks may have developed the pore pressure" at Pernote in April 2024 (GSI note, 2024), the NGT's committee at Thathri Nai Basti in 2023 found "unplanned PVC pipes for the purpose of sewerage disposal to the road side drainage downslope" (as reported), and JKPCC lists Duksar in Ramban as prone to land sinking (JKPCC, 2024). Kupwara, Ganderbal, Pulwama, Shopian, Kulgam, Rajouri, Poonch, Reasi, Bhaderwah and Bani are candidates for notification under Clause 4.5.4. No flood basin has been declared under Part VI of the Jammu and Kashmir Water Resources (Regulation and Management) Act 2010, and no flood plain zone under the Jammu and Kashmir Flood Plain Zones (Regulation and Development) Act 2005, which is not in force (Commentary to Clause 4.1), so the list has no entry for notified floodplain reaches. The notification triggers in 4.5.4.1 have no direct precedent and are set by this Manual. The 6-month lead time follows the update rule of Clause 2.14.2. Clause 4.16 explains why releases below pre-development are needed at all.
4.5.5 Minimum outlet and short-duration 2-yr checks
4.5.5.1 Where the PSD for any AEP and duration is less than the discharge of a 50 mm orifice (Clause 4.8.2) at the corresponding stage, the 50 mm orifice is deemed to comply for that AEP and duration.
4.5.5.2 Where meeting the 2-yr criterion at a duration of 3 hours or less would require a low-flow orifice so small that the drawdown requirement of Clause 4.7 cannot be met, the designer shall:
- size the low-flow orifice as the smallest opening that meets Clause 4.7; and
- report the resulting 2-yr exceedance for those durations.
The Authority may accept the design if the exceedance is below the discharge of the 50 mm orifice at the 2-yr stage, or if the downstream analysis of Chapter 5 shows no adverse effect.
Commentary. Under AMC II, a greenfield site produces almost no runoff in a 1- or 2-hour, 2-yr storm, because most of the rain is lost to initial abstraction. A pre-development peak of a few litres per second, compared duration by duration, then forces a very small low-flow orifice. That orifice cannot release the 10-yr volume within 48 hours. Checked as if it were outside a flood-sensitive catchment, the illustrative example of Clause 4.6.7 would need a low-flow orifice of about 75 mm to match the 1-hour, 2-yr pre-development peak. 90% drawdown of the 10-yr volume would then take about 84 hours even with a clean orifice, against the 48-hour limit. The 170 mm orifice that meets drawdown with 50% blockage exceeds the 1-hour, 2-yr pre-development peak by about 11 L/s. Clause 4.5.5.2 resolves that conflict in favour of drawdown, because a basin that is still partly full when the next SW monsoon storm arrives fails in the event that matters more. KC APWA 5600 (2006) used a 75 mm (3 in) minimum orifice with trash racks. This Manual sets a 50 mm minimum (Clause 4.8.2).
4.5.6 Constrained redevelopment sites
4.5.6.1 Eligibility. The relief route of this clause is available only for redevelopment where all of the following hold:
- (a) the existing site is at least 60% impervious, as surveyed before demolition;
- (b) the site is 1 ha or less; and
- (c) the designer shows, in a Constraint Statement submitted with Form 4-1, that the greenfield criteria of Clauses 4.5.2 or 4.5.3 cannot be met on the site. The statement must show that every storage option of Clause 4.10 has been assessed: rooftop and podium storage, tanks under parking or landscape, permeable paving with sub-base storage, and landscape depressions. It must also give the storage each option can provide.
New development on undeveloped land is never eligible.
4.5.6.2 Minimum on-site performance. An eligible site shall provide all of the following on site:
- (a) the full retention volume (Clause 4.4) and the WQv treatment (Chapter 8), with no relief;
- (b) post-development peak discharge no more than 50% of the existing-condition peak for the 50%, 10% and 1% AEP storms, at each duration of Clause 2.5.2. The existing condition is modelled under Clause 3.3.4; and
- (c) no increase in the 1% AEP water level at any building or road downstream (Chapter 5).
4.5.6.3 Shortfall. The shortfall is the detention storage required to meet the greenfield criteria (Clause 4.6) minus the storage provided on site under 4.5.6.2. The applicant shall pay for the shortfall as a fee-in-lieu at the unit rate of Clause 4.13.3. The fee shall be:
- (a) paid into the ring-fenced account of the basin in which the site lies;
- (b) spent only on regional detention or on restoring talab or tank flood storage identified in the basin stormwater master plan (Chapter 11); and
- (c) recorded in the public ledger of Clause 4.13.4, which shall show the volume owed and the volume delivered in each basin.
Where no basin master plan has yet been approved, the fee shall be held for up to 5 years. If no plan is approved in that time, it shall be spent on restoring tank flood storage in the same basin, with I&FC agreement.
4.5.6.4 Flood-sensitive catchments. In the catchments of Clause 4.5.3, the route is available under the same conditions. The Authority may, however, refuse it where the downstream analysis of Chapter 5 shows existing flooding of buildings in the 10% AEP event within the analysis extent.
Commentary. Greenfield is the target for all redevelopment, because a dense city only reduces its runoff as it rebuilds. On small, fully built plots in areas such as Lal Chowk, Budshah Chowk and the old city of Srinagar, the old city of Jammu round Lakhdata Bazar, or the old towns of Anantnag, Baramulla and Sopore, there is often no space for the full greenfield storage. A rule that cannot be met invites variances and non-compliance, which help no one downstream. This clause follows the approach of the UK Non-statutory Technical Standards for Sustainable Drainage (Defra, 2015, S2–S3). For previously developed sites, those standards require peak runoff "as close as reasonably practicable to the greenfield runoff rate" and never above the pre-redevelopment rate. The fixed 50% minimum reduction has no direct precedent; this Manual sets it to give reviewers a clear number in place of a "reasonably practicable" judgement. The fee-in-lieu turns the shortfall into regional storage in the same basin, so the basin still receives greenfield-equivalent control in total. Retention and water quality get no relief, because they are small volumes that almost every site can hold.
4.6 Detention sizing procedure
4.6.1 Method
Detention shall be sized by hydrograph routing through the stage–storage–discharge relationship of the facility, by level-pool (Modified Puls) or an equivalent numerical method (SWMM, HEC-HMS). Fixed-ratio and Rational-based storage formulae shall not be used. The simplified methods of Clause 4.14 (the Tier B tables and the fixed-coefficient route) are the only exceptions.
4.6.2 Steps
- Delineate the site and sub-areas. Map HSG and confirm by testing (Chapter 3).
- Extract design rainfall for 50%, 10% and 1% AEP and every duration in Clause 2.5.2, with the climate factor (Chapter 2, Form 2-1).
- Build design hyetographs: alternating block for ≤ 24 h; the "peak day last" pattern for 48 and 72 h (Clause 2.9).
- Compute pre-development hydrographs (greenfield CN; AMC III for storms of every duration from 1 March to 31 May on the Kashmir valley floor (sub-area JK-C) and there whenever the Jhelum is at or above flood-declaration level, from 1 July to 30 September on the Sirowal and valley-floor alluvium of sub-area JK-A and in sub-areas JK-B and JK-B1, at all times in sub-area JK-D and in catchments draining to a reservoir, barrage pond or backwater or to a lake whose outlet the river can close (Dal, Anchar, Wular), and at other sites and times, including the Kandi and the Karewas, after a 5-day total of more than 53 mm, AMC II otherwise).
- Compute the release caps for each AEP and duration under Clause 4.5.2 or 4.5.3.
- Compute post-development hydrographs with the same storms and AMC, including retention practices (Clause 4.4.6).
- Choose a trial facility geometry (stage–storage) and a multi-stage outlet (Clause 4.6.5).
- Route every storm and duration. Use a time step of no more than 5 minutes, and no more than Tc/3 of the post-development catchment.
- Check every release against its cap, and check drawdown (Clause 4.7). Adjust the outlet and storage and repeat.
- Check the tailwater condition of Clause 4.6.6 and the downstream analysis of Chapter 5.
- Size the emergency spillway and set freeboard (Clause 4.9).
- Report the governing storm for storage, for each outlet stage, and for the spillway (Clause 4.17).
4.6.3 Storms to be routed
Every facility shall be routed for the full matrix:
Table 4.1 — Design storms to be routed for detention sizing
| AEP | Durations (h) | AMC |
|---|---|---|
| 50% (2-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 10% (10-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
| 1% (100-yr) | 1, 2, 3, 6, 12, 24, 48, 72 | II for ≤ 6 h; III for ≥ 12 h |
The 24-, 48- and 72-hour runs are mandatory whatever the critical-duration result (Clause 2.5.2). Where Ia = 0.05S sensitivity is required by Chapter 3, it shall be run for the governing storage case.
4.6.4 Initial conditions
Each run shall start with:
- detention storage empty, down to the invert of the lowest outlet;
- any permanent pool full;
- retention practices empty, except as limited by Clause 4.11; and
- RWH storage full (Clause 4.11).
The 48- and 72-hour storms already contain their antecedent rain, so no further pre-filling is applied.
4.6.5 Multi-stage outlet design
4.6.5.1 The outlet shall have a separate control for each criterion, normally stacked as in Figure 4.2:
- Stage 1, at the invert: the low-flow orifice. It releases the WQv over 24–48 h (Chapter 8) and controls the 2-yr release.
- Stage 2: an orifice or slot set at or near the maximum 2-yr level. It controls the 10-yr release.
- Stage 3: a weir, riser crest or larger orifice set at or near the maximum 10-yr level. It controls the 100-yr release.
- Emergency spillway: separate from the primary outlet (Clause 4.9).
Stages may be combined where routing shows that every cap is met.
4.6.5.2 Orifices shall be computed with a discharge coefficient of 0.60 unless a rated device is used. Weirs shall use a coefficient appropriate to their shape. Submerged-outlet and tailwater effects shall be included (Clause 4.6.6).
4.6.5.3 Vortex flow controls and other proprietary devices may be used where the supplier provides a certified head–discharge curve and the minimum clear opening is at least 50 mm.
4.6.6 Tailwater on the outlet
The outlet shall be routed against the tailwater of the receiving system, not free outfall, wherever the receiving water level can rise above the outlet invert. The tailwater shall be:
- for a receiving drain: its water level in the same storm, from the Chapter 5 analysis or, for Tier B, the drain obvert;
- for tidal or backwater-affected outfalls: the levels and joint cases of Clause 2.12 and Chapter 5, including the outfall-closed check (Clause 5.10).
Where tailwater governs, a flap gate shall be fitted to the outlet (Clause 5.11). The storage below the tailwater level shall not be counted as available unless the routing includes the gate closure.
4.6.7 Illustrative example
Illustrative — not design values. This example shows the procedure and the sizes it produces. The inputs are invented to be plausible for a colony draining to a khad in Jammu. They are not NIH-DHAARA values and must not be used for design.
Inputs:
- Site: 2.0 ha, flood-sensitive catchment (Clause 4.5.3).
- Land cover: pre-development all pervious, CN 70. Post-development as two sub-areas (Clause 3.9.2): 1.57 ha of directly connected impervious surface at CN 98, never converted for AMC, and 0.43 ha of pervious open space at CN 70, on the same soil as pre-development; the area-weighted CN at AMC II is 92. For storms of 12 h and longer the pervious CN only is converted to AMC III: CN_III = 23·CN / (10 + 0.13·CN) = 84.3 (Clause 3.8.4).
- Time of concentration (Tc): 45 min pre-development, 15 min post-development (used for both sub-areas). SCS triangular unit hydrograph; 5-minute time step.
- 24-h depths: 110, 200 and 350 mm for 2-, 10- and 100-yr (the same 10- and 100-yr values as Clause 2.11).
- Shorter durations: P(t) = P24·(t/24)^0.40, an assumed ratio set and not Annex 2B.
- Longer durations: 48-h and 72-h depths taken as 1.25 and 1.40 × P24, laid out per Clause 2.9.2.
- Storage: vertical-walled, 2,500 m² plan area.
- Outlet, sized so that drawdown is met with the low-flow orifice 50% blocked (Clause 4.8.3). Annex 4C shows the trial outlet that failed this check.
- Stage 1: 170 mm orifice at the invert.
- Stage 2: 460 mm orifice with its invert 0.53 m above the floor.
- Stage 3: none needed, because the 100-yr cap is met by Stages 1 and 2.
Results (discharges in L/s; storage in m³):
Table 4.2 — Illustrative example: peak discharges and storage used, by duration (Illustrative — not design values)
| Duration (h) | 2-yr pre | 2-yr post, detained | 10-yr pre | 10-yr post, detained | 100-yr post, uncontrolled | 100-yr post, detained | 100-yr storage used | 10-yr drawdown, 50% blocked (h) |
|---|---|---|---|---|---|---|---|---|
| 1 | 4 | 15 | 51 | 28 | 922 | 42 | 1,426 | 31.3 |
| 2 | 14 | 20 | 84 | 34 | 961 | 79 | 1,911 | 32.1 |
| 3 | 19 | 22 | 104 | 37 | 981 | 139 | 1,999 | 32.8 |
| 6 | 32 | 25 | 150 | 41 | 1,010 | 194 | 2,154 | 34.2 |
| 12 | 127 | 30 | 302 | 46 | 1,074 | 276 | 2,512 | 39.0 |
| 24 | 149 | 32 | 327 | 49 | 1,081 | 320 | 2,766 | 45.3 |
| 48 | 173 | 34 | 349 | 82 | 1,087 | 343 | 2,913 | 44.8 |
| 72 | 180 | 34 | 356 | 84 | 1,089 | 343 | 2,911 | 44.7 |
How to read it:
- 100-yr cap. The cap is the largest pre-development 10-yr peak, 356 L/s (72 h). Every 100-yr detained peak is at or below it; the largest is 343 L/s.
- 2-yr cap. The site is flood-sensitive, so the 2-yr cap is the largest pre-development 2-yr peak, 180 L/s (72 h; Clause 4.5.3.1). The largest 2-yr detained peak is 34 L/s. At 1, 2 and 3 hours the detained 2-yr peak is above the pre-development peak of the same duration (15 against 4 L/s, 20 against 14 L/s, and 22 against 19 L/s). That comparison is not required here. It would be for a site under Clause 4.5.2, and Clause 4.5.5.2 would then apply.
- Governing storage. Storage is governed by the 48- and 72-hour storms: 2,913 m³, which is 0.146 m³ per m² of site, at a maximum depth of 1.17 m. A design that checked only the critical-duration peak storm (1–3 h here) would have provided about 2,000 m³, roughly two-thirds of what is needed.
- Drawdown. With the low-flow orifice 50% blocked (Clause 4.8.3), 90% of the 10-yr storage drains in at most 45.3 h (the 24-hour storm), within the 48 hours of Clause 4.7. A 120 mm orifice would drain it in about 42 h when clean but 54 to 75 h when half blocked, so it fails. Annex 4C shows that trial and the routing step by step.
- Retention credit. With an illustrative retention depth of 40 mm, RRV = 552 m³, computed for each sub-area (Clause 3.9.4). Modelled as filling from the start of the storm with no infiltration during it, the retention reduces the 24-hour storage by 138 m³ and the 48- and 72-hour storage by 7 m³ or less. The credit under Clause 4.4.6 is therefore effectively zero for this site.
The order of magnitude, about 0.15 m³ per m² of site, is consistent with the indication in Clause 2.11.
Figure 4.1 — Pre-development 10-yr, post-development 100-yr uncontrolled and detained hydrographs for the 24-hour storm of the illustrative example (Clause 4.6.7). Illustrative — not design values. Original drawing for this Manual, adapted from the pre/post-development hydrograph concept in MARC/KC APWA Section 5600 and the Georgia Stormwater Management Manual (2016).
Commentary. Figure 4.1 shows what detention does and does not do. It cuts and delays the peak. It does not reduce the volume: the area under the detained curve equals the area under the uncontrolled curve, more than twice the pre-development 10-yr volume. The extra volume leaves the site over many hours after the storm. That prolonged release can coincide with the peak of the larger catchment downstream (Clause 4.16), and it must still drain when the outfall is tide-locked (Chapter 5).
4.7 Drawdown
4.7.1 Detention. At least 90% of the maximum volume stored in the 10% AEP (10-yr) storm of each duration shall be released within 48 hours of the time of maximum storage, by gravity, with the tailwater of Clause 4.6.6.
4.7.2 Water quality volume. The WQv shall be released over not less than 24 hours and not more than 48 hours (Chapter 8).
4.7.3 Retention. Retention storage shall be emptied within 72 hours by infiltration or reuse (Clause 4.4.5).
4.7.4 Tidal outfalls. Where gravity drawdown is prevented by tide for part of each cycle, the 48-hour limit applies with the tidal tailwater modelled. Where it cannot be met by gravity, pumped drawdown shall be provided under Clause 5.12.
Commentary. KC APWA 5600 (2006) required dry basins to release at least 80% of storage within 24 hours of the inflow peak and to empty within 72 hours. Singapore PUB requires detention to be restored within 4 hours. The 48-hour, 90% rule is longer than PUB's because Jammu and Kashmir storage must hold multi-day volumes. It is still short enough that a basin filled by one SW monsoon depression will have most of its volume back before the next, which in late August and early September 2014, when heavy rain fell between 28 August and 10 September (CAG Report No. 4 of 2016), and August 2025, when the storms of 14, 16–17 and 26–27 August struck the Jammu division within two weeks (IMD; as reported) followed within days.
4.8 Outlet structures
4.8.1 General. Primary outlets shall be:
- unattended, with no moving parts, valves or pumps, except where Clause 5.12 permits pumped drawdown;
- accessible for inspection and cleaning from the surface without confined-space entry, where practicable; and
- built of durable materials. In coastal areas these shall be corrosion-resistant (Clause 4.12.5).
4.8.2 Minimum orifice. No control orifice shall be smaller than 50 mm in diameter, or 50 mm in least dimension for a slot.
4.8.3 Trash racks and screens. Every orifice and weir shall be protected by a trash rack or screen. The rack shall:
- have a clear bar spacing no greater than half the smallest opening it protects, and not less than 25 mm;
- have a clear open area at least 10 times the area of the opening it protects;
- be inclined, or set as a cage around the riser, so that debris rises with the water and does not pin against the bars;
- be removable or hinged for cleaning; and
- for routing, be assumed 50% blocked at the low-flow orifice when checking drawdown.
4.8.4 Anti-vortex devices. Riser crests and orifices that may run under more than 1.5 times their diameter of head shall have an anti-vortex plate or hood (Figure 4.2).
4.8.5 Outlet barrels. Outlet barrels through embankments shall:
- be at least 300 mm in diameter (Chapter 6);
- have watertight joints;
- have a filter diaphragm or seepage collars over the length within the embankment; and
- have an energy-dissipating outfall (Chapter 9).
4.8.6 Isolation. Facilities serving more than 1 ha shall have a means of isolating the outlet for maintenance, such as a stop-log slot or penstock. In normal service it shall be left fully open.
Commentary. The 50 mm minimum is smaller than the 75 mm (3 in) of KC APWA 5600 (2006), so the trash-rack requirements are correspondingly stricter. The ratios in 4.8.3 (bar spacing at half the opening, open area 10 times the opening, 50% blockage for the drawdown check) have no direct precedent and are set by this Manual. The blockage factor matches the 50% grate clogging factor for sag inlets in Chapter 6. Indian urban drains carry heavy loads of solid waste, so a low-flow orifice without an effective rack will block within one season.
Figure 4.2 — Detention storage stack (permanent pool, WQv, 2-yr, 10-yr and 100-yr zones, spillway surcharge and freeboard) and multi-stage riser outlet. Schematic, not to scale. Original drawing for this Manual, adapted from the multi-stage outlet and storage-zone concepts in MARC/KC APWA Section 5600 (2006, 2025.01) and the Mile High Flood District Urban Storm Drainage Criteria Manual, Volume 2 (full-spectrum detention).
4.9 Emergency spillway, freeboard and embankment safety
4.9.1 Spillway capacity. Every detention facility formed wholly or partly by an embankment, or whose overflow would reach buildings, shall have an emergency spillway that passes the 1% AEP (100-yr) peak inflow:
- with the primary outlet assumed fully blocked;
- with the facility full to the spillway crest at the start of the storm; and
- with at least 0.3 m freeboard from the maximum water level to the embankment crest.
4.9.2 High-hazard facilities. A facility is high-hazard if its failure or overflow could:
- endanger life;
- flood a habitable building or critical facility; or
- close an arterial road.
High-hazard facilities shall also be checked for the 0.2% AEP (500-yr) peak inflow under the conditions of 4.9.1, with the embankment not overtopped.
4.9.3 Spillway crest. The spillway crest shall be at or above the 1% AEP maximum water level from routing with the primary outlet working. The recommended clearance is 0.15 m.
4.9.4 Spillway location. The spillway shall be:
- on natural ground or a reinforced section, not on fill, unless protected against erosion for the full design flow;
- discharging to the 1% AEP overland flow path of Chapter 6; and
- placed so that its flow does not reach a building.
4.9.5 Underground and enclosed facilities. Tanks, vaults and podium storage shall have an overflow route that operates when the outlet is blocked. The route shall carry the 1% AEP inflow to the overland path without surcharging any building, basement or lift pit.
4.9.6 Embankments.
- (a) Embankments more than 2 m high (measured from the downstream toe to the crest) shall be designed by a qualified geotechnical engineer. The design shall include stability, seepage and settlement analysis.
- (b) Side slopes shall be no steeper than 3H:1V on any face that is mown or accessible to the public. Slopes shall be flatter where Clause 4.15 requires.
- (c) Embankments shall have:
- a crest width of at least 3 m;
- compacted, engineered fill with a core or cut-off where required by the seepage analysis; and
- no trees or large shrubs.
- (d) An embankment structure that falls within the Dam Safety Act, 2021 is subject to that Act in addition to this Manual.
4.9.7 Excavated facilities. Facilities wholly below the surrounding ground, with no embankment, need not meet 4.9.6. They shall still meet 4.9.1, with the overflow route treated as the spillway.
Commentary. The spillway criterion (1% inflow, outlet blocked, basin full, 0.3 m freeboard; 0.2% for high hazard) follows the KC APWA 5600 (2006) rule: the spillway passes the 1% storm with 1 ft (0.3 m) freeboard to the top of the dam, assuming zero storage and a clogged primary outlet, with the crest at least 0.5 ft (0.15 m) above the 1% maximum water surface. KC designed dams above 10 ft (3 m) to SCS TR-60 Class C. The 2 m embankment trigger, the 3H:1V slope (KC wet ponds), and the 3 m crest width have no direct precedent and are set by this Manual.
4.10 Facility types
4.10.1 General. Any storage that meets Clauses 4.5 to 4.9 may be used. Surface storage that is visible and can be inspected without confined-space entry is preferred. Storage shall not be placed in a habitable basement or in any space whose flooding would endanger life.
4.10.2 Underground tanks and vaults.
- (a) Gravity outlet is required where the receiving drain allows it. Pumped outlets are permitted only under Clause 5.12, with a registered maintenance declaration (Chapter 10).
- (b) Access openings shall be provided over the outlet chamber and over every inlet. In tanks over 500 m², they shall be no more than 30 m apart.
- (c) The floor shall fall at least 1% to a sump at the outlet, with a sediment pocket below the low-flow orifice invert.
- (d) The tank shall be ventilated.
- (e) Inlets shall pass through a silt trap or gross pollutant trap (Chapter 8).
- (f) Flotation and groundwater ingress shall be checked under Clause 4.12.
4.10.3 Rooftop detention.
- (a) It is permitted on flat roofs designed for the full ponded load with the outlet blocked. The ponding depth shall not exceed 150 mm unless a structural engineer certifies a greater depth.
- (b) Each roof outlet shall have a flow-control ring or weir with a certified rating, and every roof area shall have at least one overflow scupper, independent of the controlled outlets, that passes the 1% AEP inflow.
- (c) Roofs used for RWH collection may also provide rooftop detention. The detained volume is released through the control, not into the RWH sump.
4.10.4 Podium and landscape-deck detention.
- (a) It is permitted above ground level or above a basement car park, provided the structure is designed for full saturation and ponding, and waterproofed.
- (b) The release, overflow and safety rules for rooftop detention (4.10.3) apply.
4.10.5 Parking-lot detention.
- (a) It is permitted only on surface parking. Ponding depth shall not exceed:
- 200 mm in the 10% AEP storm and 300 mm in the 1% AEP storm at any parking bay;
- zero on accessible routes, ramps and pedestrian crossings; and
- zero in the 10% AEP storm on fire-tender access routes.
- (b) Signs shall warn that the area floods.
- (c) Ponding shall not reach a building wall unless the wall is waterproofed above the 1% level plus freeboard (Chapter 6).
4.10.6 Multi-use detention (parks, playfields, open space reservation).
- (a) Open space land may be used for detention, provided its primary use remains available in at least the 50% AEP storm.
- (b) The storage areas shall be graded to drain fully within the times of Clause 4.7.
- (c) A low-flow channel or underdrain shall carry dry-weather and frequent flows, so that the park is not waterlogged.
- (d) The depth and slope limits of Clause 4.15 apply.
- (e) Play equipment and seating shall be placed above the 10% AEP level.
4.10.7 Ponds and wet basins.
- (a) A permanent pool shall be at least 1.2 m deep over most of its area to discourage weed growth and mosquito breeding, with a vegetated safety bench at the edge (Clause 4.15).
- (b) Only storage above the permanent pool counts as detention.
Commentary.
- The rooftop depth (150 mm) and parking depths (200 and 300 mm) have no direct precedent. This Manual sets them so that a blocked outlet is noticed before it becomes dangerous.
- The 1.2 m pool depth equals the 4 ft minimum permanent pool of KC APWA 5600 (2006). This Manual adopts it mainly for weed and mosquito control.
- Pumped detention tanks need maintenance declarations in Singapore (PUB Addendum No. 3, April 2025). This Manual adopts the same approach through Chapter 10.
- Using open space for multi-use detention fits UBBL-2021, under which public open spaces of more than 500 m² shall have "arrangements for complete utilization and capture of storm water" and "Artificial or natural Storage of storm water runoff from larger sites" (cl. 10.4), group housing shall use permeable materials for its open parking (Table 10-1), and the Conservation Green Zone along nallahs and rivers allows only roads, parking, plantation and sit-outs (cl. 5.2.5). On the Kandi fans, a detention area graded into the open space below the level of the road keeps it pervious and usable, which is what 4.10.6 requires, and can also infiltrate under the Kandi recharge rule of Clause 4.11. On the floor of the Kashmir valley and on the Sirowal the position is different. Ground there is wet, the water table may stand within a metre of the surface in spring, and the town's outfalls may be shut by the river for days; a depressed open space stays wet, cannot infiltrate (valley-floor rule, Clause 4.11) and may hold groundwater as well as storm water, so its storage below the design groundwater level is not counted (Clause 4.12.2), and its outlet is designed for the outfall-closed case of Chapter 5. On a hill site, ground on a natural slope of more than 10°, a terrace held up by a retaining wall, land within twice the height of a cut or wall downslope of it, and land in a subsidence or sliding zone are not to be used for ponding, because water held there soaks into the slope (hill infiltration rule, Clause 4.11). On such sites, detention is provided in lined tanks, open or closed, with an orifice outlet and an overflow to a lined drain, on rooftops and podiums under 4.10.3 and 4.10.4, or on a level open space only where it stands on rock or on ground that the geotechnical certificate of Clause 4.11 covers; an excavated pond or basin on a slope is not accepted. Four kinds of land are not open space for this purpose. A lake, nambal, talab, spring or kuhl on the land is preserved under step 1 of Clause 4.3.1; a lake or talab is modelled as a water surface (Clause 3.3.2(e)) that starts at its outlet or spill level (Clause 3.12.5), so only its flood storage above that level can count, and only as Chapter 7 allows, and a kuhl or other irrigation channel is a hydraulic work under the Jammu and Kashmir Water Resources (Regulation and Management) Act 2010 that may not be obstructed or fouled. The buffers of clauses 5.2.5 and 7.12 of UBBL-2021, of the Srinagar Master Plan 2035 (Tables 8-2 and 8-3) and of the Jammu Master Plan 2032 (§7.3.3), the 200 m round Dal and Wular that the High Court has held (Chapter 7), and land that the I&FC flood zonation of the Srinagar Master Plan treats as undevelopable are flood or waterbody land already. Land in the hydraulic corridor of a khad, nallah, lake or river under Chapter 7, and land recorded as Gair Mumkin Khad until the functional khad has been mapped (Commentary to Clause 4.1), is corridor or flood land: water reaches it first, so it is not counted as detention for the development beside it (Chapter 7). And land kept open on purpose, such as the wetland reserves, the proposed flood-absorption basin from Lelhar to Lasjan, the green Zabarwan hills above Srinagar or a mapped spring-recharge area, is not graded or paved for detention.
4.11 Rainwater harvesting versus detention accounting
4.11.1 No double counting. RWH storage (sumps, tanks, recharge pits and wells provided under the RWH mandate) shall not be counted as detention.
4.11.2 RWH sumps assumed full. For all routing under this chapter, RWH sumps and tanks shall be assumed full at the start of every storm, in every season. Their overflow shall be routed to the detention facility, or directly to the outfall if it bypasses detention. In the latter case the bypass flow counts against the PSD.
4.11.3 Combined tanks. A single tank may provide both RWH and detention only if:
- (a) the detention zone lies wholly above the RWH overflow level;
- (b) the detention zone is drained by its own gravity control orifice set at the RWH overflow level, meeting Clauses 4.7 and 4.8;
- (c) no pump, valve or user action can hold water in the detention zone; and
- (d) the two zones and the orifice level are shown on the drawings and in the maintenance declaration.
Only the volume between the RWH overflow level and the detention overflow level counts as detention.
4.11.4 Recharge structures. Recharge pits, trenches, shafts and wells may count as retention (not detention) if they meet Clauses 4.4.3 to 4.4.5. In particular, the seasonal high groundwater table shall be at least 1.0 m below their base. In the routing they are treated under Clause 4.4.6 with the groundwater level for the SW monsoon season.
4.11.5 RWH remains mandatory. Nothing in this chapter reduces the RWH requirement of chapter 10 of UBBL-2021 (as amended), regulation 1-7-13 of the Srinagar Master Plan 2035 where it applies, any measure notified on the advice of the Authority under the Jammu and Kashmir Water Resources (Regulation and Management) Act 2010, the guidelines of the Central Ground Water Authority where they apply, any condition of a building permission, or any rainwater harvesting rule or direction of an approving authority.
Commentary. RWH in Jammu and Kashmir rests on chapter 10 of UBBL-2021, which "gives the mandatory requirements of water conservation", with methods "adopted from NBC, 2016". "All buildings having a plot size of 100 sq.m. Or more, while submitting the building plans for sanction, shall mandatorily include the complete proposal of rainwater harvesting", whose components include storm-water drains, a filter chamber, storage and "Ground Water recharge structures like pit, trench, tube well" (cl. 10.1); plotted houses place the "emphasis on both storage and reuse", group housing shall use permeable materials "for all open parking spaces" and show its storm drainage, harvesting structure and recharge well, and in industrial areas contaminated water shall not be injected into recharge structures (Table 10-1); public open spaces of more than 500 m² shall capture their storm water (cl. 10.4); recharge is mandatory for buildings and group housing on plots of more than 500 m² (cl. 10.5); and an RWH Cell inspects the structures "before issuing Completion Certificates or NOCs for service connections" and verifies every building above 1,000 m² each year (cl. 10.6). Since S.O. 304 of 1 December 2025 the online scrutiny of plans checks rainwater harvesting. The chapter sets no storage volume: its only figure, that "Rainwater can be harvested to the extent of 55,000 litres per 100 sq. m. area per Year from rooftops", is a description, about 550 mm a year (NEER's arithmetic), not a size. The Srinagar Master Plan 2035 makes "storage of rainwater" mandatory only for plots of 1,000 m² and above and for all group housing (reg. 1-7-13). The two conflict; this Manual cites both and applies the stricter, the 100 m² threshold of UBBL-2021, which is the later rule and applies throughout the Union Territory, and never the master plan's figure alone. The Jammu and Kashmir Water Resources (Regulation and Management) Act 2010 adds only an advisory power: the Authority "may advise the Government" to identify areas where rooftop rainwater harvesting should be made mandatory, and no such area was found to have been notified [TBC]. To give the UBBL proposal a size against which credit can be given, this Manual sets a minimum RWH storage of 20 litres per m² of roof, about 20 mm of rain over the roof (set by this Manual, on the precedent of Appendix 6 of the Himachal Pradesh Town and Country Planning Rules 2014, which requires that volume for every roof in that State's planning areas), with a filter and first-flush diverter ahead of it and its overflow taken to the site's detention facility or drain. The figure is a floor for credit, not a cap on what an owner may store. This Manual credits these structures against its own retention requirement (Clause 4.4) as follows:
- An RWH tank is RWH storage. It is not detention (Clause 4.11.1), and it is assumed full at the start of every storm (Clause 4.11.2), because in the SW monsoon it is full after the first heavy rain, and in the Kashmir valley it is full through the wet spring. A tank may also provide detention only if it is built as a combined tank under Clause 4.11.3, with a detention zone above its RWH overflow level that drains through its own orifice; only that zone counts.
- An RWH tank counts toward the retention requirement of Clause 4.4 only to the extent that it is emptied within 72 hours by a continuous non-potable use, such as toilet flushing or washing, demonstrated under Clause 4.4.3; watering a garden is not a continuous use in the SW monsoon or in the Kashmir spring. The tank is then modelled under Clause 4.4.6 like any other retention practice. Where infiltration is barred, as on the valley floor and on hill sites, this storage and reuse is the way retention is provided.
- Recharge pits, trenches, shafts and wells count as retention only where they meet Clause 4.11.4: they are credited only to the extent that they drain within 72 hours at half the rate measured in a site test (Clauses 4.4.3 and 4.4.5), with their base at least 1.0 m above the seasonal high water table, and the credit is found by routing under Clause 4.4.6, not by deducting their volume. They are also subject to the three rules below, which decide where an infiltration practice may be built at all.
- Valley-floor rule. No deliberate infiltration practice (soakaway, soak pit, recharge pit, shaft or well, infiltration trench, or permeable paving with an exfiltrating base) shall be built or credited, and no infiltration credit shall be given, on the alluvium, Gurti clay and Nambal peat of the floor of the Kashmir valley in sub-area JK-C, whatever depth to water a single reading shows, or on the Sirowal, the river terraces and floodplains and the lake, nambal, talab and reservoir margins anywhere in the Union Territory wherever the seasonal high water table is within 2 m of the surface or wells nearby flow; such ground is HSG D (Clause 3.7.2). There the rainwater harvesting of UBBL-2021 is storage and reuse, not recharge, and the recharge structures listed in its chapter 10 are not built; detention is lined and sized for the outfall-closed case and the pump capacity of Chapter 5; and the flotation check takes the design groundwater level at ground level (Clause 4.12.1) and, where wells nearby flow, at the artesian head. Permeable paving required by Table 10-1 of UBBL-2021 for open parking is built there with a lined or impermeable base and an underdrain to the detention facility. On the Upper Karewa tablelands of Budgam, Pulwama, Pampore and the airport plateau, small infiltration practices may be built only after a site test, and only where the hill infiltration rule does not apply, and outlets that run down a Karewa scarp shall be lined or stepped and protected against erosion; on the Lower Karewa infiltration is decided case by case on a site test.
- Kandi recharge rule. The boulder-gravel fans and khad beds of the Kandi belt, north of Jammu, round Nagrota and Samba and in the north of Kathua and Hiranagar, are the preferred recharge zone of the Union Territory. There retention shall be provided by recharge before reuse or detention wherever site tests allow, through a silt trap, a filter and a first-flush diverter ahead of the recharge structure, with the base of every practice at least 0.6 m above the post-monsoon water level and at least 1.0 m above the seasonal high water table (Clauses 4.4.3 and 4.11.4). Every recharge bore or shaft requires a hydrogeologist's check of the target zone that reports its nitrate before it is credited; no recharge bore or shaft shall be built within the protection zone of a public supply well, for which no Jammu and Kashmir distance was found [TBC]; and road, parking, industrial and sewage-carrying runoff shall not be put into a bore or shaft. The Kandi ponds are kept and, where they have been lost or silted, revived as recharge talabs, as the Jammu Master Plan 2032 proposes. The rule stops at the spring line: the Sirowal below it falls under the valley-floor rule.
- Hill infiltration rule. No deliberate infiltration practice (soakaway, soak pit, recharge pit, shaft or well, infiltration trench, or permeable paving with an exfiltrating base) shall be built or credited: on natural ground sloping more than 10°; on the Murree and Siwalik sequences of sandstone and clay of the hills; in a mapped subsidence or sliding zone, including Thathri Nai Basti in Doda, Pernote and Duksar in Ramban and any area that JKPCC lists as prone to land sinking, such as those of Budgam district; on colluvium, slide debris or moraine, whatever its slope; or upslope of a cut slope or retaining wall within a distance of twice the height of the cut or wall — unless a geotechnical certificate by a qualified geotechnical engineer or engineering geologist shows that the added water will not destabilise the slope. On such sites roof runoff goes to the rainwater storage of this Commentary (at least 20 L per m² of roof), with overflow to a lined drain that discharges through a sediment trap to a stable natural channel, never onto an unprotected slope, and sewage is never discharged to a roadside drain or onto a slope. The rule applies in sub-areas JK-B, JK-B1 and JK-D and on the slopes of sub-areas JK-A and JK-C, such as the Siwalik hills above the Kandi, the Karewa scarps and the hills round Srinagar. On these sites retention is provided by storage and reuse, and detention by lined tanks, not by ponds or basins on the slope (Commentary to Clause 4.10). The 1.0 m groundwater separation of Clause 4.4.3 does not make an infiltration practice acceptable on a slope: perched water and pore pressure in a slope are the hazard, not the depth to the water table.
- Springs. Kashmir's springs, the nāg and cashma, feed lakes and towns, and Dal has springs within its own basin (JKPCC, 2024); the Water Resources Act 2010 counts springs as water sources and "spring ponds, spring channels" as hydraulic works, but no Jammu and Kashmir rule found keeps construction or infiltration back from a spring [TBC]. In the recharge area of a spring, where it has been mapped, only clean roof runoff, passed through a filter, may be infiltrated, and only where the three rules allow; road and parking runoff shall not be infiltrated, the area shall not be paved, and no runoff that may be polluted shall be infiltrated upslope of a spring.
- Industrial and polluted runoff. UBBL-2021 bars contaminated water from recharge structures in industrial areas (Table 10-1). Runoff from industrial premises, fuel stations, workshops and the like, as in the industrial estates of Jammu, Samba and Kathua, shall not be recharged, and untreated runoff shall not be put into a bore or shaft anywhere (Chapter 8).
- Everywhere, road and parking runoff shall be recharged only through a surface infiltration practice with a filter, such as a vegetated basin or trench, never directly into a bore or well, and runoff from a nallah or khad that carries sewage, as many of Jammu's and Srinagar's drains do (Commentary to Clause 4.1), shall not be recharged at all.
The three rules follow the ground. On the floor of the Kashmir valley water stands 0–2 m below ground over the central and south-western parts and wells flow on both sides of the Jhelum, with piezometric levels "between 2 m agl and 12 m bgl" (NAQUIM, Kashmir Valley), and the CGWB says of Srinagar district that "As depth to water level in the district is shallow there is no scope for artificial recharge to ground water" (CGWB, Srinagar district booklet). A recharge pit there sits in the water table for much of the year. The 2 m threshold of the valley-floor rule, wider than the 1 m used for some valley floors elsewhere in the series, is set by this Manual because a practice whose base must stand 1.0 m above the seasonal high water table (Clause 4.4.3) has no working depth where that level is within 2 m, and because artesian heads up to 2 m above ground make a shallow reading unsafe as a guide. Groundwater is not short in the Union Territory: all 149 assessment units were safe in 2024, with a stage of extraction of 22.28% (CGWB, GWRA 2024), and Jammu, Samba and Kathua districts have been safe in every assessment from 2017 to 2024, so recharge is preferred on the Kandi because the ground takes it, not because the aquifer is stressed. The Kandi is "underlain by boulder, gravel, which acts as a very good medium for the recharge", with water 7–30 m below ground over most of the belt (NAQUIM, Outer Plains of Jammu Province), and the water supply of Jammu city is drawn from groundwater, for which the CGWB asks for "proper well head protection measures"; nitrate above 45 mg/L was found in 9.2% of the samples of 2024, among them samples from Jammu, Kathua and Samba districts (CGWB, Ground Water Year Book 2021–22; CGWB leaflet on the ground water resources and quality of Jammu and Kashmir, 2024). In the hills water put into the ground does not stay where it is put. At Pernote in Ramban, where about 35 houses were damaged in April 2024, the GSI found that "During rains the ingress of surface runoff through these cracks may have developed the pore pressure, thus inducing the instability in the slope", in "alternating layers of permeable sandstone and weak impermeable clay", and recommended "Proper measures for diverting the surface runoff away from the affected/active part of the slope", that "Drains present in the affected slope should be lined/trained" and "No new construction" (GSI note, 2024); the district committee asked that drains be "properly lined and maintained and the domestic sewage be channelised" (JKPCC, 2024). At Thathri Nai Basti in Doda, where houses cracked in early 2023 after heavy rain in late January, the NGT's committee found "no retaining wall with weep holes, or planned drainage or sewage disposal structures" and sewage piped "to the road side drainage downslope" (as reported). Treating RWH as detention would credit storage that does not exist when it is needed, which is why this Manual assumes RWH tanks are full at the start of every storm, in every season. The combined-tank provision (4.11.3) lets an owner build one structure, as long as the detention part is empty when the storm arrives. The 20 L per m² storage, the valley-floor rule, the Kandi recharge rule, the hill infiltration rule, the spring rules, the industrial-runoff and pre-treatment rules and the road-runoff rule are set by this Manual. No Jammu and Kashmir source sets a slope or distance threshold for infiltration; the 10° limit is set by this Manual, as in the other mountain editions of the series, because a slope that can carry a building can still be destabilised by water put into it, and the distance of twice the height of a cut or wall is set as a precaution, pending guidance from a geotechnical study for the Union Territory [TBC].
4.12 High-groundwater and sandy coastal sites
4.12.1 Design groundwater level. Each site in the floor of the Kashmir valley, on its alluvium, Gurti clay and Nambal peat, in and around Srinagar, Anantnag–Bijbehara, Pampore, Sopore, Baramulla, Sumbal and Bandipora, the Sirowal of the Jammu plains round R.S. Pura, Bishnah, Arnia and Hiranagar, the floodplains and low terraces of the Jhelum, the Tawi, the Chenab, the Ujh, the Basantar, the Ravi and the khads, the margins of Dal, Nigeen, Anchar, Wular, Manasbal, Hokersar and the other lakes and nambals, of Mansar and Surinsar and of the Kandi ponds and talabs, the margins and backwaters of the Salal, Baglihar and Dul Hasti reservoirs and of the Tawi barrage pond, and hill sites with perched water, such as Thathri Nai Basti, Pernote and Duksar, or any area where the groundwater table lies within 3 m of the surface at any time of year shall establish a design groundwater level (DGWL) for the facility. The DGWL is the seasonal high level during or after the SW monsoon, from:
- (a) site piezometer readings over at least one full March–November season; or
- (b) where (a) is not available, the higher of the CGWB or Jal Shakti Department (PHE) record for the nearest observation well, plus 0.5 m, and the design flood level of any adjacent river, khad, nallah, lake, nambal, talab or reservoir.
For the flotation check of 4.12.3 at sites in the alluvium, Gurti clay and Nambal peat of the Kashmir valley floor, the Sirowal belt of the Jammu plains, the river terraces and floodplains, and the lake, nambal and reservoir margins, where (a) is not available, the DGWL shall be taken as existing ground level.
4.12.2 Lined storage. Where the DGWL is less than 1.0 m below the base of a storage facility:
- (a) the facility shall be watertight (lined or of watertight concrete), and no infiltration credit applies (Clause 4.4.4); or
- (b) if unlined, the volume below the DGWL shall not be counted as detention, and groundwater inflow shall be added to the routed inflow.
4.12.3 Uplift and flotation. Every below-ground tank, vault, lined pond or chamber shall be checked for flotation:
- with the facility empty;
- with groundwater at the DGWL; and
- for coastal sites, with groundwater also at the major-system tailwater level of Chapter 5, where that is higher.
The factor of safety against uplift, counting only permanent dead loads and ignoring wall friction unless supported by geotechnical design, shall be at least 1.2. Anchoring by ballast, toe extensions or tension piles may be used.
4.12.4 Shallow and above-ground storage preferred. On sites where the DGWL is within 1.5 m of ground, storage should be provided above ground where possible: rooftop, podium, landscape or surface storage. Deep tanks should be avoided.
4.12.5 Durability. Concrete and metal parts in contact with saline or brackish groundwater or tidal water shall be designed for the exposure class appropriate to coastal conditions under IS 456:2000. Outlet fittings, trash racks and gates shall be of stainless steel, HDPE, FRP or another corrosion-resistant material.
4.12.6 Sandy soils with deep groundwater. Where the DGWL is 1.0 m or more below the base, infiltration retention in sandy soils is encouraged. The design infiltration rate of Clause 4.4.3 applies, and the Chapter 8 requirements on pollution of shallow aquifers shall be met.
Commentary. Jammu and Kashmir is landlocked, so the coastal provisions of this clause, the tidal water levels of 4.12.1 and 4.12.3, do not apply in the Union Territory, and no saline groundwater was reported in the assessments read for this Manual [TBC], so the exposure provisions of 4.12.5 apply only where a test at the site shows it. Groundwater lies at three kinds of depth. On the Kandi fans of the Jammu plains it is deep: 7–30 m below ground over most of the belt and up to 84 m in the deeper aquifers, 5.24 m at Supwal to 65.0 m at Pangiari in Jammu district, and in Kathua district generally more than 18 m (NAQUIM, Outer Plains of Jammu Province). On the floor of the Kashmir valley, on the Sirowal and near the trunk streams it is shallow: 0–2 m below ground over the central and south-western valley in November 2014 (NAQUIM, Kashmir Valley), within 2 m in 81.8% of Baramulla's observation wells in May 2021 (CGWB, Ground Water Year Book 2021–22), 1.50–2.50 m after the monsoon in Srinagar district (CGWB, Srinagar district booklet), and mostly two to five metres in the Sirowal; and it stands above ground in the wells that flow under artesian pressure on both sides of the Jhelum, at heads up to 2 m above ground and 2.50 m at Charsoo in Anantnag district, and in the Sirowal of Kathua district, where more than half the wells flow at heads from a metre to more than 9 m above ground (NAQUIM, Kashmir Valley; CGWB, Anantnag district booklet; NAQUIM, Outer Plains of Jammu Province). In the hills it occurs in fractures, weathered rock and debris and is perched in places, as at Pernote, where "the water table is shallow" and springs flow from the slope (GSI note, 2024), and on the Upper Karewa, where "Perched water bodies are encountered" (NAQUIM, Kashmir Valley). The valley floor, the Sirowal, the floodplains and low terraces of the rivers and khads, the margins of the lakes, nambals, talabs and reservoirs, and hill sites with perched water are the wet cases. There an unlined tank fills with groundwater before the storm, and an empty lined tank can float, especially when the Jhelum in flood, a lake whose gate the river has shut, a reservoir at its full level or a talab at its spill level raises the water table beside it. The design groundwater level of 4.12.1(b) therefore takes the design flood level of the adjacent river, khad, nallah, lake, nambal, talab or reservoir where that is higher than the well record, and on the valley floor, the Sirowal, the river terraces and floodplains and the lake, nambal and reservoir margins it is taken as existing ground level for the flotation check unless piezometers show otherwise. Where wells near the site flow under artesian pressure, as along the Jhelum and in the Sirowal of Kathua district, the tank shall also be checked for uplift with the groundwater at the artesian head measured in the nearest flowing well, which may stand several metres above ground; a deep tank shall not be built there at all unless that check is met. On a hill site a deep tank is not preferred even where groundwater is deep, because a leaking tank on a slope is an infiltration practice by another name: storage on a slope shall be lined and watertight, and its leakage and overflow taken to a lined drain (hill infiltration rule, Clause 4.11). The March–November monitoring season of 4.12.1(a) is set by this Manual to cover both groundwater years of the Union Territory: on the floor of the Kashmir valley levels are shallowest in May, after winter rain, snowfall and snowmelt (NAQUIM, Kashmir Valley), and in the Jammu division they rise with the SW monsoon of June–September and its after-flow; a reading taken only in the SW monsoon understates the design level in the valley, and one taken only in spring understates it in the plains. No water-table depths for individual town sites in Srinagar, Anantnag, Sopore, Baramulla, R.S. Pura or Kathua, and no map of the seasonal high water table of the valley floor or the Sirowal, were obtained [TBC]; the only Srinagar well in the 2021–22 year book is at Regal Chowk. The factor of 1.2, the 0.5 m allowance, the "ground level" default for the valley floor, the Sirowal, the river terraces and floodplains and the lake, nambal and reservoir margins, and the artesian-head check have no direct precedent; this Manual sets them because no published site-scale seasonal groundwater depths for Jammu and Kashmir were found during research.
4.13 Regional detention and fee-in-lieu
4.13.1 Where permitted. In a basin covered by a Basin Stormwater Master Plan approved under Chapter 11, a development may meet all or part of its detention requirement through:
- (a) a regional detention facility identified in the plan; or
- (b) a fee-in-lieu paid toward restoration of talab or tank storage identified in the plan.
4.13.2 Conditions. Regional detention or fee-in-lieu shall be accepted only where:
- (a) the regional facility or restored tank is operational, or is funded and scheduled to be operational within 3 years. Until then, interim on-site detention is required.
- (b) the conveyance from the site to the facility carries the 1% AEP post-development flow without increasing water levels at buildings or roads between them (Chapter 5);
- (c) the storage credited at a tank is the flood storage only. This is the volume between full tank level (FTL) and the maximum water level the bund and surplus weir can safely hold, plus any volume below FTL that a notified operating rule commits to empty before the SW monsoon. Storage below FTL that is held for irrigation or supply through June to September shall not be credited.
- (d) the tank meets Chapter 7: surveyed FTL, a documented operating rule, and a maintained surplus weir;
- (e) the site still provides retention (Clause 4.4) and WQv treatment (Chapter 8) on site; and
- (f) in flood-sensitive catchments, the regional facility meets the mixed-frequency rule for its whole contributing area.
4.13.3 Fee. The fee-in-lieu shall be computed as:
Fee = (detention volume required on site under Clause 4.6, m³) × (unit rate, ₹/m³, notified by the Authority)
The unit rate shall include land, construction and 10 years of maintenance. Fees shall be held in a ring-fenced basin account and spent only on the facilities named in the plan.
4.13.4 Ledger. The Authority shall keep a public ledger of:
- detention volume credited to each regional facility;
- volume delivered; and
- fees received and spent.
Commentary. The Malaysian DID (2008) checklist favoured community ponds over on-site detention for sites above 0.1 ha. Studies of on-site detention show that its benefit depends on location and fades with distance downstream (Colorado State University thesis; McEnroe for Kansas City), and that a pond low in the catchment can synchronise with the main-stem peak (Water 2016). Regional storage therefore has to be sited by basin modelling, not simply aggregated.
Jammu and Kashmir has no tank or lake Act. Its lakes are managed by authorities set up under the Jammu and Kashmir Development Act 1970: Dal and Nigeen by the Lake Conservation and Management Authority (LCMA, formerly LAWDA; renamed in November 2021, as reported) and Wular and its feeder channels by the Wular Conservation and Management Authority (WUCMA, 2012). The Jammu and Kashmir Wetland Authority was constituted on 25 November 2020 under the Wetlands (Conservation and Management) Rules 2017, but as of September 2024 no wetland had been notified under rule 4 of those Rules, although the Authority had approved the brief document of Wular "for Notification" (Forest, Ecology and Environment Department, report of 9 September 2024 in NGT O.A. 239/2024). Seven wetlands, Hokersar, Shallabugh, Hygam, Freshkoori, Kranchoo, Chatlam and Manibugh, are wildlife conservation reserves under orders of 1945 (same report). The Union Territory has five Ramsar sites: Wular (18,900 ha, 1990), Surinsar–Mansar (350 ha) and Hokera (Hokersar, 1,375 ha) (both 2005), and Hygam (802 ha) and Shallabugh (1,675 ha) (both 2022) (MoEFCC, list of Ramsar sites, 31 January 2024). No lake, nambal or reservoir in the towns was found to be operated for flood control under a documented rule for the towns' benefit. The Union Territory's regional storage is of six kinds: the lakes, Dal and Nigeen behind the Dal Gate, Anchar, Manasbal and Wular in the Kashmir valley and Mansar and Surinsar near Jammu; the nambals and flood basins of the Jhelum, Hokersar, Narkara, Shallabugh, Rakh-e-Arth, Haran and the low land from Lelhar to Lasjan, which hold the river's floods; the reservoirs, Salal and Dul Hasti (NHPC), Baglihar (JKSPDC), Ranjit Sagar on the Ravi and the new barrage pond on the Tawi at Jammu; the Kandi ponds and the talabs of Jammu, most of which survive only as names; the springs; and the kuhls and canals, from the Ranbir canal to the zamindari khuls. Five points follow:
- A lake or nambal on the record may not be a working one, and a nambal is the river's storage, not the town's. Hokersar has shrunk from 18.75 km² to about 13 km² and is reported to have "lost nearly half of its flood storage capacity", Wular from 157.74 km² in 1911 to 86.71 km² in 2007, and 37% of Narkara has been built over (as reported); no flood-storage volume was found for any valley wetland [TBC]. A lake or nambal is credited only after a survey shows its bed, rim and outlet, and only for the storage above its outlet or spill level (Clause 3.12.5). The flood basins that fill from the Jhelum are not credited to any site, because they are full when the river is high, which is when the town's outfalls are shut; a site that drains to them provides its full detention on site.
- Dal and Nigeen are not spare capacity for their catchment. Their outlets are shut when the Jhelum rises (Commentary to Clause 3.10), untreated sewage "gets entry into the Dal Lake from areas like Telbal, Lalbazar", and about 910 houseboats discharge into Dal and Nigeen (JKPCC, 2024). Storm water may be discharged to them only with LCMA's consent, through a sediment trap and with the dry-weather flow intercepted (Clause 8.9), and no credit is given for their storage.
- The reservoirs are not spare capacity either. They are held for power through the SW monsoon and the snowmelt, Salal's gates are opened at least once a month in the monsoon for desilting (as reported), their releases are set by their operators for the whole river and, since April 2025, may not be announced (as reported); their storage below full level is not credited (Clause 4.13.2(c)), and storm water spilled to a reservoir, or to a river below one, can be relied on only with the written agreement of the operator, NHPC, JKSPDC, the operator of Ranjit Sagar or I&FC for the Tawi barrage, for a stated flow and level.
- A pond or check dam in the bed of a khad or nallah is not regional detention unless it is designed for debris. The khads of the Kandi and the hills carry boulders, sediment and muck in every large storm, and muck dumping was reported to have worsened the floods of August 2025 on the Chenab and the Tawi (SANDRP, as reported); such a facility is credited only for the storage left after the sediment and debris volume of Chapter 6, with a debris rack or trap at its inlet, a geotechnical check of its bund and abutments, its failure path mapped, and a maintenance budget for clearing it after each large storm (Chapters 9 and 10). A Kandi pond revived as a recharge talab under Clause 4.11 is credited as retention only to the extent that it drains within 72 hours under Clause 4.4. A regional facility on a hill slope is also subject to the hill infiltration rule of Clause 4.11. A kuhl, canal or city channel is not regional detention: a storm drain that crosses or discharges to one does so only with the consent of I&FC, through a screen and a sediment trap, because the control of "the bed and banks of all water sources … city channels and flood spill channels" lies with I&FC and depositing waste in a channel is barred by the Water Resources Act 2010 (section numbers to be confirmed [TBC]).
- No rule dividing natural streams from municipal drains was found [TBC]. Until one is made, this Manual follows the working assignment of Chapter 1: the rivers, nallahs and khads, with their beds, banks and embankments, the flood spill channel, the city channels, canals and khuls as I&FC's, with the municipal body desilting and clearing within its limits the nallahs it cleans now; in Srinagar, the drainage schemes, drains and dewatering stations as UEED's to plan, design and build and as the Town Drainage wings' of SMC and of the Directorate of Urban Local Bodies Kashmir to run; in Jammu, the drains within JMC's limits as JMC's and the UEED Sewerage and Drainage Division (West) Jammu's; in the other towns, the Municipal Council's or Municipal Committee's; road drains and culverts as PW (R&B)'s, and on national highways NHAI's; Dal, Nigeen and the drains in LCMA's area as LCMA's, Wular and its feeder channels as WUCMA's, and the wetland conservation reserves as the Wildlife Department's; drains built by SDA, JDA, the Housing Board, a Smart City company or a colony developer as the builder's until handed over in writing; the reservoirs and their drawdown land as their operators'; and sewers as UEED's (Commentary to Clause 6.9). This is the Manual's working assignment, not a statutory one.
The first point is the basis of condition 4.13.2(c) in Jammu and Kashmir. A lake, nambal or talab gives flood storage only above its outlet or spill level, unless a notified operating rule commits it to be lowered before the SW monsoon or, in the Kashmir valley, before the spring snowmelt. The 3-year operational limit and the 10-year maintenance allowance have no direct precedent and are set by this Manual.
4.14 Simplified methods for small sites
4.14.1 Applicability. Tier B local bodies may permit the simplified method for sites of 2 ha or less outside flood-sensitive catchments. In flood-sensitive catchments, it may be used for sites of 0.5 ha or less. All other sites shall use Clause 4.6. Until Table 4.3 (Annex 4B) is published, all Tier B sites shall also use Clause 4.6.
4.14.2 Method.
- Read the PSD (L/s/ha) and SSR (m³/ha) for the site's zone, HSG and post-development imperviousness from Table 4.3 (Annex 4B).
- Required storage: V = SSR × A − V_credit (Clause 4.4.6.3).
- Permissible discharges: Q_PSD,T = PSD_T × A for the 2-yr and 100-yr stages.
- Select the low-flow orifice and upper control from the standard outlet table in Annex 4B (orifice sizes for the PSD at the stated depths), subject to the 50 mm minimum.
- Provide a spillway or overflow under Clause 4.9, the RWH accounting of Clause 4.11, and the safety provisions of Clause 4.15.
- Complete Form 4-2 (Tier B site sheet).
Table 4.3 — Tier B permissible site discharge and site storage requirement (template)
| Zone (Annex 2A) | HSG | Imperviousness | PSD 2-yr (L/s/ha) | PSD 100-yr (L/s/ha), standard | PSD 100-yr (L/s/ha), flood-sensitive | SSR (m³/ha), standard | SSR (m³/ha), flood-sensitive |
|---|---|---|---|---|---|---|---|
| JK-Z1 Jammu plains: JK-A Jammu plains, Kandi and Sirowal (Jammu–R.S. Pura–Akhnoor–Samba–Kathua) | A / B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| JK-Z2 Pir Panjal–Chenab hills: JK-B Outer and middle hills (Udhampur–Katra–Reasi–Rajouri–Poonch–Ramban–Banihal) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| JK-Z2 Pir Panjal–Chenab hills: JK-B1 Inner Chenab hills (Doda–Kishtwar–Bhaderwah) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| JK-Z3 Kashmir valley: JK-C Kashmir valley floor and Karewas (Srinagar–Anantnag–Pampore–Sopore–Baramulla–Kupwara) | B / C / D | 50% / 70% / 90% | [TBC] | [TBC] | [TBC] | [TBC] | [TBC] |
| JK-Z4 High mountains: JK-D High mountains and snow-fed catchments (Gulmarg–Pahalgam–Sonamarg–Gurez–Paddar; hazard-first) | — | — | Not tabulated: Clause 4.6 applies (Clause 2.3.6(i)) | — | — | — | — |
Worked example (illustrative — not design values).
A 0.4 ha residential layout in a Tier B Municipality, in a flood-sensitive catchment, with about 80% directly connected impervious area (area-weighted post-development CN about 92). Suppose Table 4.3 had been computed and gave the per-hectare equivalent of the Clause 4.6.7 example:
- PSD 100-yr = 356 / 2.0 = 178 L/s/ha
- SSR = 2,913 / 2.0 ≈ 1,460 m³/ha
- PSD 2-yr ≈ 17 L/s/ha
Then:
- Storage: V = 1,460 × 0.4 = 584 m³. C_R = 0, so there is no retention credit.
- 100-yr release: 178 × 0.4 = 71 L/s.
- 2-yr release: 17 × 0.4 = 7 L/s. At about 1 m head this needs a low-flow orifice of about 60 mm, above the 50 mm minimum (Clause 4.8.2).
- Layout options:
- a 400 m² underground tank 1.5 m deep; or
- 250 m² of podium storage at 0.3 m (75 m³) plus a 350 m² tank 1.5 m deep (525 m³).
- Rooftop storage at 150 mm over 1,200 m² of roof (180 m³) could replace part of the tank.
- RWH sumps are additional, and are assumed full (Clause 4.11).
Commentary. Australian councils use permissible site discharge and site storage requirement tables in the same way (Sydney Water OSD guide; the Upper Parramatta River Catchment Trust handbook listed SSR of about 455 m³/ha). The illustrative SSR here, about 1,460 m³/ha, is much larger. That is the expected effect of combining a mixed-frequency cap with mandatory 48–72-hour storms at AMC III. MSMA 2 in Malaysia offers a similar simplified OSD method for sites under 5 ha. The MARC policy supplement offers smaller Kansas City municipalities adoptable alternatives within the regional standard; Clause 4.14 follows that model for Tier B.
4.14.3 Fixed-coefficient route. As an alternative to Clauses 4.6 and 4.14.2, the designer of any site of 1 ha or less, under any Approving Authority and in any catchment, may size detention by Clauses 4.14.4 to 4.14.7. The route shall not be used where:
- (a) the site counts tank or waterbody storage in its design (Chapter 7);
- (b) any part of the site lies within a waterbody setback (Chapter 7); or
- (c) the site drains to a tank cascade whose storage is counted in a downstream design.
The route sets the release caps by fixed coefficients and does not need Table 4.3. It may therefore be used before Annex 4B is published. Retention (Clause 4.4), drawdown (Clause 4.7), outlets (Clause 4.8), the spillway (Clause 4.9), the downstream and tailwater checks (Chapter 5) and water quality (Chapter 8) still apply.
4.14.4 Release caps. Two caps apply at each point where runoff leaves the site:
Q_cap,10 = 2.78 × C_10 × i_10 × A and Q_cap,2 = 2.78 × C_2 × i_2 × A
where Q_cap is in L/s; A is the site area (ha); i_10 and i_2 are the 10% AEP (10-yr) and 50% AEP (2-yr) rainfall intensities (mm/h) for a 15-minute duration at the site, from the sources of Chapter 2, with the climate factor of Clause 2.8; and C_10 and C_2 are the fixed coefficients of Table 4.3A for the site's hydrologic soil group (Clause 3.7). For a site with more than one soil group, the coefficients are area-weighted.
Table 4.3A — Fixed release coefficients (provisional)
| Hydrologic soil group | C_10 | C_2 |
|---|---|---|
| A (sandy, well drained) | 0.05 | 0.02 |
| B | 0.08 | 0.03 |
| C | 0.15 | 0.08 |
| D (clay, poorly drained) | 0.25 | 0.15 |
Q_cap,10 is the maximum release for every storm up to and including the 1% AEP (100-yr) storm, in every catchment. Q_cap,2 is the maximum release for the 50% AEP (2-yr) storm. Where a cap is smaller than the discharge of a 50 mm orifice at the corresponding stage, the 50 mm orifice is deemed to comply (Clause 4.5.5.1).
4.14.5 Storage. The detention storage V (m³) is the larger of V_100 and V_2, each the largest over the durations d of Clause 2.5.2 (1 to 72 hours):
V_100 = max over d of [ 10 × C_v × P_100(d) × A − 1.8 × Q_cap,10 × d ]
V_2 = max over d of [ 10 × C_v × P_2(d) × A − 1.8 × Q_cap,2 × d ]
where P_100(d) and P_2(d) are the 1% and 50% AEP rainfall depths (mm) for duration d (hours), with the climate factor; and C_v is the post-development volumetric coefficient: the composite C of Table 3.2 (upper half of each range), multiplied by Cf of Table 3.3 for the 1% AEP. For durations of 12 hours or more, C for every pervious surface shall be taken as not less than 0.50. The factor 1.8 assumes an average release of half the cap over the storm (3.6 × 0.5).
4.14.6 Outlet. The outlet shall be a two-stage control: a low-flow orifice that passes Q_cap,2 when the storage holding V_2 is full, and an upper orifice or weir that limits the total release to Q_cap,10 at the top of V. The outlet table of Annex 4B may be used once it is published.
4.14.7 Retention. The retention volume of Clause 4.4 is provided in addition to V. No retention credit (Clause 4.4.6) is taken under this route.
Figure 4.3 — Fixed-coefficient route for sites of 1 ha or less (Clauses 4.14.3 to 4.14.7): the release caps Q_cap,10 and Q_cap,2 from Table 4.3A; the storage V as the largest gap, over the durations of Clause 2.5.2, between the cumulative inflow 10·C_v·P(d)·A and the release line 1.8·Q_cap·d, for the 1% and 50% AEP storms; and the two-stage outlet that passes Q_cap,2 at the top of V_2 and Q_cap,10 at the top of V. Schematic, not to scale. Original drawing for this Manual, adapted from the rainfall mass-curve (inflow minus outflow) storage concept and the single-coefficient peak cap of the PUB Code of Practice on Surface Water Drainage, 7th ed. (cl. 7.1.5).
Commentary. The fixed-coefficient route follows Singapore, which caps the peak runoff from every development of 0.2 ha or more with one runoff coefficient, C = 0.55, applied to the 10-yr storm (PUB Code of Practice on Surface Water Drainage, 7th ed., cl. 7.1.5, Addendum No. 3, 2025). It is quick to apply and quick to check: the cap needs only the site area, the soil group and two intensities. PUB's 0.55 is not used here, because Singapore's baseline is the existing urban drainage system, while this Manual's baseline is greenfield land (Clause 4.5.1.2). The coefficients of Table 4.3A are set by this Manual from the greenfield curve numbers of Clause 3.3 (CN 39, 61, 74 and 80 for soil groups A to D). They are the ratios of runoff to rainfall that those curve numbers give for 1-hour depths typical of the Jammu plains and the Kandi belt, rounded down. They are therefore provisional. The State Stormwater Technical Committee shall confirm or revise them against NIH-DHAARA values for each zone when it issues Annex 4B.
The route is deliberately stricter than the full method, so that simplicity costs the developer storage rather than costing the people downstream. The 100-yr release is held to about the greenfield 10-yr peak everywhere, which is the flood-sensitive rule of Clause 4.5.3; the storage assumes the outlet releases only half the cap on average; pervious ground is assumed wet in long storms; and no retention credit is taken. A designer who wants a smaller tank can use the full method of Clause 4.6. The storage formula is the rainfall-mass (inflow minus outflow) method. Clause 3.4.2 otherwise forbids rainfall-based peak methods for storage, because they ignore the shape of the hydrograph; this route is a stated exception because its conservative assumptions cover that error for small sites, and the 24- to 72-hour durations are always checked.
4.15 Safety, fencing and multi-use
4.15.1 Depth limits for publicly accessible storage. Where the public has access to a storage area (parks, playfields, open space, school grounds):
- (a) maximum depth in the 10% AEP storm: 0.45 m;
- (b) maximum depth in the 1% AEP storm: 1.2 m, except in a fenced zone under 4.15.3;
- (c) side slopes: no steeper than 4H:1V, with at least a quarter of the perimeter at 6H:1V or flatter for escape; and
- (d) no vertical drop greater than 0.3 m within the storage area or at its edge.
4.15.2 Wet basins. Permanent pools shall have:
- a safety bench at least 3 m wide, no more than 0.3 m below the normal water level; and
- an emergent planting fringe that deters entry.
4.15.3 Fencing. A fence at least 1.2 m high, of a non-climbable design with a lockable gate, is required around any part of a storage that:
- has a vertical wall or headwall drop greater than 0.6 m;
- exceeds 1.2 m depth in the 1% AEP storm with slopes steeper than 4H:1V; or
- contains an outlet structure with an opening larger than 300 mm that is not grated.
4.15.4 Outlets. Every inlet and outlet opening larger than 300 mm accessible to the public shall be fitted with a grate or rack. The grate shall be designed so that a person pinned against it can escape: low approach velocity, inclined, with a large open area.
4.15.5 Signs and depth markers. Every publicly accessible storage shall have signs in Urdu and English stating that the area floods during rain, and a depth marker at the deepest point.
4.15.6 Confined spaces. Underground tanks shall have lockable covers. They shall be marked as confined spaces, and the maintenance declaration (Chapter 10) shall state the entry procedure.
4.15.7 Vector control. Dry storage shall drain completely (Clause 4.7) and have no low points that pond for more than 72 hours. Wet basins shall meet Clause 4.10.7.
Commentary. The numeric limits in Clause 4.15 have no single direct precedent. They are drawn from common international practice, for example KC APWA 5600 (2006), which required at least a quarter of a dry-pond perimeter at 5:1 or flatter, a 20 ft (6 m) clearance from property lines and a 15 ft (4.6 m) maintenance strip. They are made somewhat stricter here because multi-use storage on open space land and in schools will be used by children during the monsoon. Standing water in dry basins is a mosquito-breeding risk, so complete drainage (Clause 4.15.7) is a public-health requirement, not an amenity.
4.16 Basis: why peak matching alone fails
Commentary. This section has no requirements. It records why this chapter requires release below pre-development rates, retention, long-duration checks and a downstream analysis, rather than simple peak matching.
- Timing. Detention lowers a site's peak but stretches its hydrograph (Figure 4.1). Downstream, the stretched releases from many sites overlap with each other and with the main-stem peak. In Denver's study, ten basins each releasing 100% of the historic 100-yr peak produced 106% of the historic peak at the outlet. Only releasing 90% at each site brought it to 97% (UDFCD memo, 2012). A Colorado State University thesis found that location-blind on-site detention "can actually increase peak flows above post-development peaks". An optimisation study found that a downstream pond performed worse than upstream ponds because its outflow synchronised with the main stem (Water 2016, 8(7):290).
- Volume. Detention does not remove volume. In the illustrative example, the post-development 100-yr storm produces about three times the runoff volume of the pre-development 10-yr storm (Clause 2.11). Only retention, or storage that empties to somewhere other than the receiving drain, reduces volume.
- Scale. Kansas City modelling (McEnroe, 2005) found that uniform 3 cfs/ac control reduced Q100 by 36% in a 200-ac watershed. With the same control everywhere, Q100 still rose by 40% at 14 sq mi, and the benefit faded beyond about 1–2 sq mi. The KC committee concluded that "'match existing' can harm streams" (MARC Evolution deck). Georgia makes a ten-percent downstream analysis mandatory for the same reason: "Due to peak flow timing and runoff volume effects, some structural practices fail to reduce discharge peaks to pre-development levels downstream" (GSMM 2016).
- Design-storm dependence. An Australian study of 20 real on-site detention systems found that designs using even ten temporal patterns "cannot reliably produce an OSD system design that will always be effective" under real rainfall (Water Science and Engineering, 2019). This is why Clause 4.6.3 routes the full duration matrix rather than one critical storm.
- Closed outfalls. In Jammu and Kashmir, the governing failure takes two forms. On the floor of the Kashmir valley it is volume with no outlet while the Jhelum is high. Srinagar, Anantnag–Bijbehara, Pampore, Sopore and Baramulla lie behind the river's embankments, and their gravity outfalls are shut from the time the river reaches flood-declaration stage, 18 ft on the I&FC gauge at Ram Munshi Bagh (as reported); in September 2014 the CWC site there rose to 1,588.99 m on 8 September, 3.51 m above its danger level of 1,585.48 m (CWC, as transcribed by SANDRP from the 2022 list; the 2018 list gives 1,589.65 m), the river broke its embankments and parts of the city stayed under water for up to 25 days (Malik, 2021). Whenever the river shuts the outfalls the city drains only by its pumps, about 2,300 cusecs from 104 permanent dewatering stations in 2026 (as reported), or about 0.3 mm an hour over the 767 km² of the drainage master plan (NEER's arithmetic), and by the storage in its drains, low land and lakes; Dal and Nigeen are shut off from the river by the same rise. Even a small storm floods the city centre, as 26.4 mm did on 1 August 2019 (as reported). In the hills and on the Kandi the outfall is closed in a different way: by debris. The khads and nallahs rise fast after a burst and carry boulders, sediment, wood and muck that bury outfalls, block culverts and choke the drains behind them; muck dumping was reported to have worsened the floods of August 2025 on the Chenab and the Tawi (SANDRP, as reported), and at Thathri Nai Basti sewage pipes discharged to the roadside drains downslope (as reported). No hourly record of how long the Jhelum stays above a town's outfalls was obtained [TBC], the I&FC gauges read in feet on zeros that are not published, and no document was found that sets a design river level for an outfall; Chapter 5 sets the design level, the closure to be assumed and its duration, and Chapters 6 and 9 the debris and blockage allowances. A perfectly orificed basin behind a closed outfall simply fills. No release-rate rule can fix that; it is handled by the outfall-closed check of Chapter 5.
The response in this Manual is layered:
- release below pre-development (Clause 4.5);
- retain the frequent storms (Clause 4.4);
- route long SW monsoon storms (Clause 4.6.3);
- prefer regional storage in the talab system (Clause 4.13); and
- check downstream and at the outfall (Chapter 5).
Kansas City's own history shows the price. On a test site, peak matching needed 3.0 ac-ft of storage and the 2011 comprehensive criteria needed 4.9 ac-ft (MARC Evolution deck). Over-detention costs more storage. That is the cost of protecting the catchment rather than only the site boundary.
4.17 Submittal requirements
Every site runoff-control submittal shall include a Site Runoff Control Report (Form 4-1) containing:
- the Design Rainfall Sheet (Form 2-1) and the hydrology inputs (Chapter 3);
- the evidence for the order of measures under Clause 4.3.1;
- the RRV computation, infiltration tests, groundwater evidence and drawdown calculation (Clause 4.4);
- the retention credit computation (Clause 4.4.6);
- the release-rate criterion applied, standard or flood-sensitive, with the Annex 4A map extract (Clause 4.5);
- a results table in the format of Clause 4.6.7 for every AEP and duration, with the governing case highlighted;
- stage–storage and stage–discharge tables and plots, and inflow/outflow hydrographs for the governing cases;
- the drawdown calculation (Clause 4.7);
- outlet details, including orifice sizes and levels, trash racks and anti-vortex devices (Clause 4.8);
- the spillway or overflow calculation, freeboard and hazard classification, and the geotechnical report where required (Clause 4.9);
- the RWH and detention accounting, with tank sections showing zone levels (Clause 4.11);
- the design groundwater level and flotation check (Clause 4.12);
- the downstream and tailwater report (Chapter 5, Form 5-1); and
- the safety provisions (Clause 4.15) and the draft maintenance declaration (Chapter 10).
Tier B sites using Clause 4.14.2 shall submit Form 4-2 in place of items 6 and 7. Sites using the fixed-coefficient route (Clause 4.14.3) shall submit Form 4-3 in place of items 6 and 7.
References (chapter)
- Kansas City Metro Chapter APWA (2025). Section 5600 Storm Drainage Systems and Facilities, Version 2025.01 (approved 10 Dec 2025). https://kcmetro.apwa.org/wp-content/uploads/sites/23/2026/01/APWA-Section-5600_Storm-Drainage-Systems-Facilities.pdf
- Mid-America Regional Council (2025). APWA 5600 Stormwater Standards Policy Supplement (7 Nov 2025); APWA 5600 Manual factsheet. https://www.marc.org/document/apwa-stormwater-standards-supplement ; https://www.marc.org/document/apwa-5600-manual-factsheet
- Kansas City Metro Chapter APWA (2006). Section 5600 Storm Drainage Systems and Facilities (5601.8, 5608.4). https://www.kcwater.us/wp-content/uploads/2020/08/Design-Criteria-%E2%80%93-Section-5600-%E2%80%93-Storm-Drainage-Systems-and-Facilities.pdf
- MARC / APWA (2012). Manual of Best Management Practices for Stormwater Quality. https://www.marc.org/sites/default/files/2022-05/Best_Management_Practices_for_Stormwater_Quality.pdf
- MARC. The Evolution of Regional Stormwater Design Standards (presentation; McEnroe 2005 results). https://www.marc2.org/Assets/Environment/WQEC/The_Evolution_of_Regional_Strormwater_Design_Standards.pdf
- Atlanta Regional Commission / Georgia EPD (2016). Georgia Stormwater Management Manual, Volume 1. https://documents.atlantaregional.com/gastormwater/GSMM_2016%20EDITION_FINAL_V1.pdf
- Urban Drainage and Flood Control District (now MHFD) (2012). Full Spectrum Detention Release Rate Memorandum. https://mhfd.specialdistrict.org/files/23cb85ce8/UDFCD_Full_Spectrum_Detention_Release_Rate_Memorandum.pdf
- Mile High Flood District. Urban Storm Drainage Criteria Manual, Volume 2 (Storage).
- Department of Irrigation and Drainage Malaysia (2008). Submission Checklist for Stormwater Management. https://www.water.gov.my/jps/resources/auto%20download%20images/5844dfbba8fc1.pdf
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- PUB Singapore (2024). On-site Detention Tank Technical Guide, Rev. 3; Code of Practice on Surface Water Drainage, 7th ed., Addendum No. 3 (16 Apr 2025). https://www.pub.gov.sg/-/media/PUB/PDF/detentionTank.pdf
- Sydney Water (2020). On-site Stormwater Detention Guide (SW201). https://www.sydneywater.com.au/content/dam/sydneywater/documents/on-site-stormwater-detention-guide.pdf
- Upper Parramatta River Catchment Trust (2005). On-site Stormwater Detention Handbook, 4th ed.
- "On-site stormwater detention for Australian development projects: does it meet frequent flow management objectives?" Water Science and Engineering (2019). https://www.sciencedirect.com/science/article/pii/S1674237019300213
- Optimisation of urban detention (2016). Water 8(7):290. https://doi.org/10.3390/w8070290
- Colorado State University. Spatially Dependent On-Site Detention Policies (thesis). https://mountainscholar.org/bitstreams/f4dbec4e-a44f-4933-8d54-a097e741f44a/download
- Forest, Ecology and Environment Department, Jammu and Kashmir. Report of 9 September 2024 in NGT O.A. 239/2024, with the replies of the Wildlife Department and WUCMA (constitution of the Jammu and Kashmir Wetland Authority on 25 November 2020; status of the Wular brief document; Order No. 710-C of 17 July 1945 on the wetland reserves).
- Ministry of Environment, Forest and Climate Change (2024). List of 80 Ramsar sites of India, 31 January 2024. https://moef.gov.in/uploads/2024/03/80-Ramsar-sites-of-India-31-01-2024.pdf
- Jammu and Kashmir Pollution Control Committee (2024). Response of 14 August 2024 in NGT O.A. 504/2024 (Dal Lake: catchment, outlets, sewage and houseboats).
- Central Ground Water Board. Aquifer Mapping in Outer Plains of Jammu Province (the Kandi ponds, citing NIH, 2000).
- Reports on LCMA (renaming of LAWDA, November 2021), the shrinking of Hokersar, Wular and Narkara, the Tawi barrage, the Salal and Baglihar releases and muck dumping in the floods of August 2025 (Kashmir News Service; Greater Kashmir; Scroll; Dialogue Earth; SANDRP; The Tribune).
- MoHUA / CPHEEO (2019). Manual on Storm Water Drainage Systems, Part A (§8.5).
- Jammu and Kashmir Unified Building Bye-Laws, 2021, J&K Official Gazette, Extraordinary, Vol. 134, No. 39-4, Part III, 24 December 2021 (Municipal Corporation, Jammu, October 2021), cls. 2.6, 2.18, 5.2.1.7, 5.2.5, 6.1, 6.20 and 7.12, Table 5-9 and chapter 10 (Table 10-1; cls. 10.1, 10.4–10.6). https://huddobps.jk.gov.in/JMCUBYL.pdf
- Jammu Municipal Corporation, notification of amendments to the Unified Building Bye-Laws, J&K Official Gazette, Vol. 134, No. 49-3, 9 March 2022; Housing and Urban Development Department, S.O. 304 of 1 December 2025 (online auto-scrutiny, NOCs and negative lists). https://obps.jk.gov.in/BPAMSClient/seConfigFiles/Downloads/SO%20304%20DT%2001.12.2025.pdf ; S.O. 58 of 26 February 2026 and the draft amendments of 9 September 2026 (as listed and as reported; not read).
- Town Planning Organisation Kashmir (2019). Srinagar Master Plan 2035, February 2019, §§4.2, 8.2–8.4, 12–13.3 and 14.4.4.2, Tables 8-2 to 8-4 and 12-4 to 12-5, regulation 1-7-13. https://huddobps.jk.gov.in/Srinagar_Master_Plan_2035.pdf
- Jammu Master Plan 2032, §§2.4, 5.1.3, 7.3.2–7.3.3, 8, 11.1 and 12.2.3–12.2.4. https://huddobps.jk.gov.in/JMP2032.pdf
- Jammu and Kashmir Water Resources (Regulation and Management) Act, 2010 (Act No. XXI of 2010), Part VI and the sections on the control of bed and banks, the deposit of waste in channels and rainwater harvesting (section numbers from a title index, to be confirmed against an official copy). https://jklaw.nic.in/jklawData/StaActs/Water%20Resources%20(Regulation%20and%20Management)%20Act,%202010.pdf
- Jammu and Kashmir Flood Plain Zones (Regulation and Development) Act, 2005 (Act No. XVII of 2005), ss.1–4.
- Jammu and Kashmir Reorganisation Act, 2019 (No. 34 of 2019), Fifth Schedule, Table 4 (continuance of the Acts above).
- High Court of Jammu and Kashmir and Ladakh. PIL 8/2017 with PIL 2/2014 and PIL 18/2018, Environmental Policy Group v. Union of India, order of 29 May 2024 (with the orders of 24 November 2014, 24 February 2015 and 10 June 2016 that it recalls). https://livelaw.in/pdf_upload/pil-8-of-2017-544110.pdf
- Comptroller and Auditor General of India (2016). Report No. 4 of 2016, Performance Audit of Disaster Management in the State of Jammu and Kashmir (§§2.1.4 and 5.1).
- Geological Survey of India (2024). Note on Preliminary Geological Assessment of Landslide at Pernote, and the DPCC Ramban site report, annexed to the compliance report of JKPCC of 13 September 2024 in NGT O.A. 642/2024.
- Jammu and Kashmir Pollution Control Committee (2024). Response of 14 August 2024 in NGT O.A. 504/2024 (sewage generation and treatment in Srinagar; Dal and Nigeen); report of March 2026 in NGT O.A. 413/2025, with the CPCB list of polluted river stretches (October 2025).
- Central Ground Water Board, North Western Himalayan Region, Jammu. Aquifer Mapping & Management Plan of Kashmir Valley (March 2017); Aquifer Mapping in Outer Plains of Jammu Province; Ground Water Year Book 2021–22, Jammu & Kashmir; Ground Water Information Booklets for Srinagar and Anantnag districts; Dynamic Ground Water Resources & Ground Water Quality of Jammu & Kashmir, leaflet, 2024.
- World Bank. Jhelum and Tawi Flood Recovery Project (P154990), Integrated Safeguards Data Sheet and draft Environmental and Social Management Framework (April 2015).
- Reports on the Srinagar drainage master plan and DPR (Bentley case study, 8 December 2023), the H&UDD reply in the Legislative Assembly on Srinagar's dewatering stations (Kashmir Life, 12 February 2026), the waterlogging of Srinagar on 1 August 2019, the Thathri subsidence and the NGT committee's findings (Down To Earth, 2023), the I&FC gauge stages on the Jhelum, the Chenab and the Ujh, and the floods of August 2025 (SANDRP; Greater Kashmir; Kashmir Life; The Tribune).
- Bureau of Indian Standards. IS 456:2000 Plain and Reinforced Concrete — Code of Practice.
- Government of India. Dam Safety Act, 2021.
- Chow, V.T., Maidment, D.R. and Mays, L.W. (1988). Applied Hydrology. McGraw-Hill (AMC conversion).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 4A | Flood-sensitive catchment boundaries (GIS); shallow-groundwater zone map |
| 4B | Tier B tables: PSD and SSR (Table 4.3), retention credit factor C_R, standard outlet sizes; confirmed fixed release coefficients (Table 4.3A) |
| 4C | Worked example (Tier A) with full routing tables |
| Form 4-1 | Site Runoff Control Report |
| Form 4-2 | Tier B Site Sheet |
| Form 4-3 | Fixed-coefficient Route Sheet (Clauses 4.14.3 to 4.14.7) |
Commentary. No Indian national rule or Jammu and Kashmir rule found during research for this Manual limits the rate of discharge from a site, and none requires on-site detention or "zero run-off". No Jammu and Kashmir document found sets a design storm, runoff coefficient, time of concentration, minimum size or freeboard for any drain: the drainage master plan and DPR for Srinagar prepared by Egis India covers "a 767-square-kilometer stormwater drainage system that is separate from the sewage system", modelled in SewerGEMS, but publishes no design basis (vendor case study, as reported); the World Bank's Jhelum and Tawi Flood Recovery Project designs its roads and bridges to the guidelines of the Indian Roads Congress and states no drainage return period (JTFRP project documents, 2015); and Jammu's storm-water DPR was to be prepared "immediately after the approval" of its master plan (Jammu Master Plan 2032, §11.1.3), and none was found. The building rules are the Jammu and Kashmir Unified Building Bye-Laws 2021 (UBBL-2021), published in the J&K Official Gazette, Extraordinary, Vol. 134, No. 39-4, on 24 December 2021 in the copy of the Jammu Municipal Corporation, and adopted body by body on a common text (the Doda Municipal Council's notification of 21 October 2021, as quoted); the original H&UDD notification was not found [TBC]. They have been amended by a JMC notification of 9 March 2022, by H&UDD's S.O. 304 of 1 December 2025, issued under section 395(d) of the Jammu and Kashmir Municipal Corporation Act 2000 and section 202 of the Jammu and Kashmir Municipal Act 2000, which brought in online auto-scrutiny of plans, including their rainwater harvesting, deemed rejection after 15 days, online NOCs from departments that include Sewerage & Drainage, LCMA, the Pollution Control Board and I&FC, and a "WATERBODY USE_NEGATIVE LIST", and by S.O. 58 of 26 February 2026 (as listed); a further draft of 9 September 2026 was reported to be issued under section 397 of the Corporation Act (as reported). Neither S.O. 58 nor the 2026 draft was read [TBC]. The drainage provisions that can be found protect the building and the watercourse, not the catchment. The site plan shall show "the approximate location and size of any water body, flood affected areas and contours at an interval of 0.3m in case of the site which has a slope more than 1:20" (cl. 2.6(b)(xi)); the registered technical person certifies that the site is clear of drains and water bodies (cl. 2.18); "No development shall be permitted in area designated for water body, pond and Talav"; the green buffer along nallahs and rivers is "minimum 30 m from the highest water level" or wider where a plan or the water law provides (cl. 5.2.5); building in areas "vulnerable to floods/flash floods" is regulated by I&FC "or the flood zonation maps notified by the department from time to time" (cl. 7.12(a)), of which none was found; no development is allowed within 50 m of the edge of the bank of the major rivers and khads, 30 m of the listed lakes, among them Mansar, Surinsar, Wular, Nigeen and Manasbal, and 20 m of other rivulets and of the Ranbir and Sindh canals, "or as per building regulation whichever is more" (cl. 7.12(b)), with talabs and village tanks "as may be prescribed" by the building permit issuing authority (cl. 7.12(c)); and roofs slope in snowfall areas, the Authority "may require rainwater pipes to be connected to a drain", and "No rainwater from the roof shall be drained in the adjoining property" (cl. 6.20). For floor levels UBBL-2021 sets the plinth at not less than 45 cm (cl. 6.1) and the ground-floor finish 300 mm above the centre line of the road (Table 5-9); this Manual reads them as two minimums that both apply, and its own floor-level rule, based on the design flood level and freeboard (Clause 6.11), is stricter than either. Rooftop rainwater harvesting is mandatory under chapter 10 (Commentary to Clause 4.11). None of these sets a design storm, a release rate, a detention volume or an overflow path. The master plans go no further. The Srinagar Master Plan 2035 (Town Planning Organisation Kashmir, February 2019) "asserts to work as per the stormwater performance standards effectively with 100% coverage and zero incidence of waterlogging" and describes "source controls" that "store and slowly release stormwater" (detention) or "dispose of stormwater onsite" (retention), but gives no return period, runoff coefficient or intensity (§13.3). The Jammu Master Plan 2032 records that "the road side drains serve as storm water drains", that 20% of the roads have side drains covering about 40% of the city (§5.1.3), and that land recorded as "Gair Mumkin Khad" covers more than 30% of the JDA's land and is to be reduced to the "true Khad", the functional drainage channel fixed with I&FC, with "adequate buffer zones along all the drainage channels in accordance with the size, importance, and expected discharge" (§12.2.3). This Manual requires that no such land be released until a hydraulic study of the khad has mapped the 1% AEP flow, bulked for sediment and debris under Chapter 6, with the corridor of Chapter 7 (set by this Manual). The Union Territory has two statutory routes to flood zoning, and neither has been used. The Jammu and Kashmir Flood Plain Zones (Regulation and Development) Act 2005 comes into force only on a date the Government notifies (s.1(3)), and no such notification was found, so the Act is not in force; its "flood zone" is the area needed to carry "the maximum probable floods" (s.2(d)), which is not the 1% AEP line. Part VI of the Jammu and Kashmir Water Resources (Regulation and Management) Act 2010 lets the Government declare a flood basin after survey, objections and notification, and no flood basin has been declared; the Act places "the bed and banks of all water sources … city channels and flood spill channels" under I&FC, so every outfall to them needs I&FC's consent, and its rainwater harvesting provision is advice to the Government, not a rule that binds an owner (the section numbers of the copy read were assigned from an index and are to be confirmed against an official copy [TBC]). Where a flood basin is declared under Part VI, or a flood plain zone notified under the 2005 Act, its restrictions will govern; until then the mapped design flood line of Chapter 7 applies (set by this Manual). The drain sections of the Municipal Corporation Act and the Municipal Act 2000 were not read [TBC]. The High Court of Jammu and Kashmir and Ladakh, as "Custodia Legis of river Jhelum and other water bodies", has directed the removal of encroachments from the Jhelum's banks so that "the original width of the river Jhelum is restored" and that "no construction of any kind is raised near the water bodies" (PIL 8/2017 with PIL 2/2014 and PIL 18/2018, order of 29 May 2024, recalling the orders of 2014–2016); these are court directions, and Chapter 7 states the lake buffers the Court has set. Basements are regulated for their size, not for flooding: they lie within the building envelope, their height is limited and none may be put to habitable use (cl. 5.2.1.7); no rule found restricts basements in low-lying or flood-prone land, sets a level for a basement ramp or opening, or keeps surface water or groundwater out of a basement. This Manual therefore adds its own requirements for every basement: no detention storage in a habitable basement (Clause 4.10.1); the crest of every basement ramp and the sill of every basement opening at least 0.5 m above the 1% AEP flood level, with basement drainage pumped to the surface drain through a non-return valve (Clauses 6.11.1 and 6.11.4); and no basement in Zone 2 (Clause 7.5.2). In the flood-sensitive catchments of Clause 4.5.3.2, in any catchment notified under Clause 4.5.4, and on the valley-floor, Sirowal, floodplain, lake-margin and reservoir-margin land of Clause 4.12.1, it recommends that no basement be permitted where the 1% AEP flood level stands above the surrounding ground. On the floor of the Kashmir valley a basement shall also be watertight and checked for flotation with groundwater at ground level (Clause 4.12.1), and where wells nearby flow, at the artesian head measured in the nearest flowing well; its pumps shall discharge above the level that the receiving drain reaches while the Jhelum holds its outfall shut, because in Srinagar that drain may itself drain only by pumps. In the hills a basement cut into a slope shall carry the geotechnical certificate of the hill infiltration rule of Clause 4.11, with the water behind its walls drained to a lined drain and not to the ground. For a sloping site, this chapter also supplies what the building rules leave open and what the GSI recommended at Pernote, "diverting the surface runoff away" from the slope and lining the drains on it (GSI note, 2024): runoff from the catchment above the site shall be intercepted and carried round the building in the design storms of Chapter 6, and every flow from the site shall discharge to a lined drain or a stable natural channel, never onto an unprotected slope or into the overburden. These are the Manual's proposals, not rules of UBBL-2021. This chapter is written so that it can supply, as a technical companion to UBBL-2021, the master plans and the Municipal Acts, the design storm, release rates and storage volumes that they leave open; it has not been adopted for either purpose. A competent authority, such as H&UDD for building approvals or the Jal Shakti Department for river and flood-basin matters, could adopt it. In practice many of the Union Territory's urban drains carry sewage: Srinagar generated about 193.34 MLD of sewage against 62.01 MLD of treatment capacity (32.07%) in 2024, untreated sewage "gets entry into the Dal Lake from areas like Telbal, Lalbazar", and about 910 houseboats discharge into Dal and Nigeen (JKPCC, 2024); in Jammu "Storm water drains carry considerable quantities of raw and untreated effluents" and the BOD of 90% of the city's drains is that of "weak to strong domestic sewage" (Jammu Master Plan 2032, §5.1.3); and the CPCB lists the Chunt Kol in Srinagar, the Jhelum below the Vishav confluence to Baramulla, the Tawi from Tawi Bridge to the Balol Nallah, the Basantar at Samba, the Devak at Udhampur, Gawkadal and the Lidder among the polluted river stretches (October 2025) (Clause 8.9). Retention and detention apply in full on every site whatever the drain carries: every litre a site releases at the peak of a storm takes up capacity in a drain that is already part-filled with sewage, and in Srinagar capacity at a pump that may already be running. The CPHEEO (2019) manual describes limiting outflow to the pre-development peak as typical practice, but it uses no "shall" and names no storm frequencies (CPHEEO Part A §8.5.1). This chapter turns that description into a development-control requirement.