Chapter 11Basin and City Stormwater Master Plans
11.1 Purpose and scope
11.1.1 Chapters 2 to 10 control one project at a time. This chapter sets the requirements for the plan that ties those projects together: the Basin Stormwater Master Plan (BSMP). A BSMP is prepared for each drainage basin of a city or urban area. A city's set of BSMPs makes up its City Stormwater Master Plan.
11.1.2 A BSMP shall:
- (a) map flood hazard for the basin under existing and future conditions;
- (b) set the level of service each part of the drainage system must achieve (Clause 11.6);
- (c) identify the works, storage and land needed to reach that level of service, and rank them (Clauses 11.7 and 11.8);
- (d) reserve land for regional storage, talab and tank restoration, and major flow paths in the statutory land-use plan (Clause 11.9);
- (e) set the basin-specific inputs that site designs under Chapter 4 depend on: regional facilities, the fee-in-lieu unit rate, and any basin release rate stricter than Chapter 4 (Clause 11.8.3); and
- (f) recommend catchments for notification as flood-sensitive (Clause 4.5.4).
11.1.3 Relationship to site design. Site criteria (Chapters 4 to 8) apply whether or not a BSMP exists. A BSMP may make the site criteria stricter for its basin. It shall not relax them, except through the regional detention and fee-in-lieu routes of Clauses 4.13 and 4.5.6.
11.2 Definitions
| Term | Meaning in this Manual |
|---|---|
| Basin | The land draining to one outfall to the sea, a river, or a major waterbody, as delineated under Clause 11.3. |
| Basin Stormwater Master Plan (BSMP) | The plan for one basin prepared under this chapter. |
| Lead Authority | The body responsible for preparing a BSMP (Clause 11.4). |
| Level of service (LoS) | The flood performance a part of the drainage system must achieve, expressed as an AEP and an outcome (Clause 11.6). |
| Flood hazard map | A map of flood extent, depth, velocity and hazard class (H1–H6, Chapter 6) for a stated AEP and scenario. |
| Regional facility | A storage, conveyance or outfall work serving more than one development, identified in a BSMP. |
| Capital Improvement Programme (CIP) | The ranked, costed list of works in a BSMP (Clause 11.8.4). |
11.3 Planning unit: the basin, not the ward
11.3.1 BSMPs shall be prepared by hydrological basin, not by ward, zone or local-body boundary. Where a basin crosses local-body boundaries, one BSMP shall cover the whole basin.
11.3.2 Basin boundaries shall be delineated from the digital elevation model of Clause 11.5.2, checked against the drain network, road embankments, canals and tank supply channels. Diversions between basins, whether by canal, drain or surplus course, shall be mapped and represented in the model.
11.3.3 No basin delineation has been published for any town in Jammu and Kashmir. For the urban areas where the evidence identifies them, the basins are at least the following, grouped under the flood-sensitive catchments of Clause 4.5.3.2:
- Srinagar, Dal catchment and Telbal: the catchments that drain to Dal and Nigeen, among them the Telbal Nallah from Dachigam and the Mearkh Shah, Bota Koul and Pishpow nallahs, with the Dal Gate and Nallah Amir Khan as controlled outlets, the chain from Nigeen through Gilsar and Khushalsar to Anchar in the 1D network, the lake at its level with the gate shut as the boundary condition [TBC: level and datum], and the sewage inflows from Telbal and Lal Bazar shown;
- Srinagar, the city behind the Jhelum embankments: the three drainage zones of the Srinagar drainage master plan, with every drainage scheme, gravity outfall and dewatering station in the model, its sump levels and the stage at which its gate shuts, and the Jhelum at Ram Munshi Bagh as the boundary (Clause 5.8.5(a)), the outfall-closed case of Clause 5.10 a design case;
- Srinagar west and north, the flood-basin chain: the catchments that drain to the flood spill channel and to the flood-absorption marshes west and north of the city, Rakh-e-Gund Aksha, Hokersar, Nambal Narkur (Narkara), Shallabugh and Rakh-e-Arth, with the Lelhar–Lasjan floodplain that the master plan proposes to protect (not notified) mapped;
- Doodhganga: the catchment of the Doodhganga, with the Sukhnag, draining to Hokersar and the Jhelum, with the high flood level set at Kralpora in 2025 (1,594.3 m, as reported) as a boundary;
- Sindh–Anchar: the catchments that drain through the Sindh Nallah to Anchar, Shallabugh and the Haran forest and on to the Jhelum below Srinagar, with the drains that reach Anchar from Dal through Khushalsar;
- Anantnag–Bijbehara–Pampore, upper Jhelum: the catchments of the towns and of the tributaries of the master plan's watershed list, the Lidder, Veshaw, Brengi, Sandran, Rambiara, Arpath, Rumshi, Veth and Arizal, with the Jhelum at Khanabal and Sangam as the boundary;
- Sopore–Baramulla–Sumbal–Bandipora, lower Jhelum and Wular: the catchments that drain to the Jhelum below Srinagar and to Wular, with Safapora and the Wular level (1,578 m, as reported) as the boundary and the outlet at Ningli as a control;
- Jammu, the Tawi and its khads: the catchments that drain to the Tawi, the Devak and the Basantar and through the Balol, Thather and Bhalwal khads and the other khads of the Jammu planning area, with the land recorded as Gair Mumkin Khad mapped against the functional khad, the Tawi at Sidhra (high flood level 321.1 m, 2025) and the Tawi barrage [TBC] as the boundary, and the localities flooded in 2025 and 2026 checked;
- Kathua–Hiranagar and Samba: the catchments that drain to the Ujh and the Ravi, with Ranjit Sagar's level as the Ravi boundary, and to the Basantar;
- R.S. Pura–Bishnah–Arnia, Sirowal: the flat, waterlogged catchments of the Sirowal, whose drains reach rivers that cross into Pakistan within 10–30 km, so that the level beyond the border is unknown and the flood-mark profile of the reach is the boundary;
- Akhnoor, Chenab: the catchments of the town, with Akhnoor's high flood level (324.29 m, 1992) and the releases of Salal as the boundary;
- Udhampur and Katra: the catchments on the Tawi and the Devak at Udhampur, with the I&FC gauge at Udhampur, and the nallahs of Katra, with debris racks and basins at the foot of the hills and the 1% AEP level with debris as the boundary; and
- the hill towns of the Chenab valley, Ramban–Batote–Banihal and Doda–Thathri–Kishtwar: the catchments of each town and of every nallah that crosses it, with the subsidence and sliding zones of Pernote, Duksar and Thathri mapped, surveyed flood marks where CWC has no site, and the levels and releases of Baglihar, Dul Hasti and Ratle where they set the river below the town.
Hazard first in the high mountains (set by this Manual). In sub-area JK-D (High mountains and snow-fed catchments; Gulmarg–Pahalgam–Sonamarg–Gurez–Paddar) of Annex 2A, and in any basin with a glacier, a glacial lake or a mapped debris-flow fan above it, the BSMP begins with a hazard screening for glacial-lake outbursts, debris flows, landslide dams and cloudburst floods, made with J&K SDMA, and uses site-specific hydrology in place of the zone-7 report (Clause 2.3.6(i)). The cloudburst at Chasoti on the Machail Mata yatra route on 14 August 2025, where more than 60 people were reported killed, and the flood at the Amarnath cave on 8 July 2022, where 16 were reported killed, came from storms that no gauge measured at a cloudburst rate, down channels that no drain could have carried; the Chenab's headwaters, the Marusudar and the Warwan carry snowmelt and the risk of outbursts towards Kishtwar, Doda and the Chenab reservoirs. The hazard zones are shown on the 1% AEP map, no drain, storage or pumping station is sited in them, and no work in the CIP is sized to carry a debris flow or an outburst. Other local bodies, among them those of Anantnag, Baramulla, Sopore, Kathua and Udhampur, shall define their basins in the first BSMP that covers them. Where CWC, I&FC, LCMA, WUCMA, a dam operator, a master plan or a court has a high flood level, a lake or reservoir level, a flood line or an operating rule for a gate, dam, barrage or pumping station, the BSMP shall take its boundary conditions from it, naming the gauge and its datum, and show those levels against its own 1% AEP map.
Figure 11.1 — Basin Stormwater Master Plan process and its links to site design. Original drawing for this Manual. The phase structure is adapted from Defra, Surface Water Management Plan Technical Guidance (2010), and Mile High Flood District master planning practice.
Commentary. Water does not follow ward boundaries. A ward-by-ward drain plan can pass the problem to the next ward, and to the next local body. In Jammu and Kashmir a single nallah passes through many hands on its way to a river. In Srinagar the Telbal Nallah carries the runoff of Dachigam and the untreated sewage of Telbal into Dal (JKPCC, 2024); the lake is managed by LCMA, and its outlets drain through the Dal Gate to the Tsunth Kol and the Jhelum and through Nallah Amir Khan to Nigeen, Khushalsar and Anchar; the city's drains are planned and built by UEED and run by the Town Drainage wings of SMC and of the Directorate of Urban Local Bodies Kashmir; the banks of the Jhelum, its embankments, the flood spill channel and the city channels are I&FC's (Water Resources Act 2010, s.81); and Hokersar, Shallabugh and Hygam, which take the overflow, are wetland conservation reserves of the Wildlife Department. In Jammu the roadside drains carry runoff and raw effluent to the Tawi (Jammu Master Plan 2032, §5.1.3), the khads are recorded by the Revenue Department as Gair Mumkin Khad, whose "true Khad" is to be fixed with I&FC (§12.2.3), and the Sewerage and Drainage Division (West) of UEED works only within JMC's limits. No rule divides the khads and natural nallahs from the municipal drains (as this Manual reads the record); the nearest is the Act's vesting in I&FC of the bed and banks of every water source. This clause makes the basin the planning unit, so that one model carries each nallah and khad from its head in the hills to the river, whoever owns each reach, and so that the sewage it carries is separated before it reaches a lake (Chapter 8, Clause 8.9.5).
11.4 Who prepares, and when
11.4.1 Lead Authority.
- For the basins of Srinagar: SMC, jointly with UEED, which plans, designs and builds the city's drainage schemes and dewatering stations, and with SDA in the Srinagar Local Planning Area, into whose master plan the BSMP is taken (Clause 11.9); for the basins of Jammu: JMC, jointly with the Sewerage and Drainage Division (West) of UEED and with JDA in the Jammu Local Planning Area; either Municipal Corporation may prepare the plan as H&UDD directs, with the Town Planning Organisation of Kashmir or Jammu. Where a basin extends beyond the Corporation or the local planning area, the other local bodies, the Halqa Panchayats and the planning authorities in the basin are partners, and one BSMP covers the whole basin (Clause 11.3.1).
- No order dividing the khads and natural nallahs from the municipal drains, or the drains of the local bodies from the rivers, lakes and channels, was found; until one is made, this Manual assigns the reaches within each BSMP as in Table 1.5, each body being Lead Authority for the reaches and works it owns or runs and for the parts of the CIP on them: I&FC for the Jhelum, the Tawi, the Chenab, the Ravi, the Ujh, the Basantar, the Devak and the other rivers, for the beds and banks of the nallahs and khads, for the embankments, the flood spill channel and any supplementary channel, for the city channels such as the Tsunth Kol and the Padshahi Canal, and for the canals and zamindari khuls; UEED with the Town Drainage wings of SMC and of the Directorate of Urban Local Bodies Kashmir for Srinagar's drainage schemes, drains and dewatering stations, JMC with UEED within JMC's limits in Jammu, and the Municipal Councils and Municipal Committees for the drains within their limits; PW (R&B) for the side drains, catch-water drains and culverts of its roads, including the hill roads, and NHAI for the national highways; LCMA for Dal and Nigeen and the drains it holds in their catchment, WUCMA for Wular and its feeder channels, and the Wildlife Department for the wetland conservation reserves, with the J&K Wetland Authority under the Wetlands Rules 2017; SDA, JDA, the J&K Housing Board, the Smart City companies of Srinagar and Jammu and colony developers for the drains of their works and schemes, until handed over in writing; NHPC for Salal and Dul Hasti, JKSPDC for Baglihar and the operator of Ranjit Sagar for their reservoir levels and releases; UEED for the sewers and treatment plants whose effluent reaches the drains (Clause 8.9); the Revenue Department for the records of Gair Mumkin Khad, nambal, rakh and kahcharai land; and J&K SDMA for the mapping of the landslide, cloudburst, debris-flow and glacial-lake hazards that a BSMP must show.
- In Tier B bodies: the Lead Authority is named by H&UDD. Basins draining to a common river reach or lake may be grouped into one district-level plan.
J&K SDMA and the Deputy Commissioner shall be consulted on every BSMP, and the Geological Survey of India wherever a basin includes a mapped subsidence or sliding zone, such as Pernote, Duksar or Thathri; LCMA, WUCMA or the Wildlife Department on every BSMP whose basin drains to Dal, Nigeen, Wular, a Ramsar site or a wetland conservation reserve; JKPCC on every BSMP that proposes works on a drain or nallah that carries sewage, among them the drains to Dal and the stretches that CPCB lists as polluted (the Chunt Kol, the Jhelum below the Vishav, the Tawi, the Basantar and the Devak); NHPC, JKSPDC or the dam operator on every BSMP whose basin drains to a reservoir or to a river below a dam; and, for a basin whose outfall lies on the Ravi, shared with Punjab, that State's water resources department, through I&FC. For a basin whose outfall lies on a river that crosses into Pakistan, the BSMP states that the level beyond the border is not monitored.
The Irrigation and Flood Control (I&FC) wing of the Jal Shakti Department shall be a partner in every BSMP that includes a river, canal or tank under its control.
11.4.2 When a BSMP is required.
- (a) Every Tier A body shall approve BSMPs covering its whole area within 3 years of this Manual taking effect.
- (b) A BSMP is required before:
- any regional detention or fee-in-lieu is accepted under Clause 4.13;
- a fee held under Clause 4.5.6.3 is spent; and
- a basin-specific release rate is applied under Clause 11.8.3.
- (c) A Tier B body shall prepare a BSMP where its Lead Authority, or the State Stormwater Technical Committee, finds recurrent flooding of buildings or arterial roads.
11.4.3 Preparation. BSMPs shall be prepared by, or under the direction of, an engineer empanelled as a Stormwater Design Professional (Chapter 10) with experience in basin-scale modelling.
11.5 Data and surveys
11.5.1 Each BSMP shall assemble and publish (Clause 11.10) the data in Table 11.1:
Table 11.1 — Minimum data and surveys for a BSMP
| Data | Minimum requirement |
|---|---|
| Terrain | Digital elevation model from LiDAR or photogrammetry, with vertical accuracy of 0.15 m RMSE or better in urban areas, tied to the Survey of India datum |
| Drain network | Inventory of all public drains, culverts and outfalls with invert levels, sizes, condition and silt depth; private drains above 600 mm |
| Waterbodies | Survey of every tank, talab, pond and marsh under Chapter 7: FTL, MWL, bund level, stage–storage, sluices, surplus weirs, supply channels, encroachment |
| Rivers and canals | Cross-sections at no more than 200 m spacing and at every structure |
| Outfalls, rivers, khads, lakes and reservoirs | The datum of every level named; outfall invert levels against the levels of the receiving river at the nearest CWC site and its recorded peaks (on the Jhelum the danger and high flood levels at Sangam, 1,590.88 m and 1,595.7 m or 1,595 m, at Ram Munshi Bagh, 1,585.48 m and 1,589.65 m or 1,588.99 m (the lists of 2018 and 2022 differ, and the higher governs until CWC confirms one), and at Safapora, 1,579.66 m and 1,582.1 m, with 1,595.43 m at Khanabal in 2025; on the Tawi at Sidhra the high flood level of 321.1 m of 2025, and on the Chenab at Akhnoor 324.29 m of 1992; CWC levels as transcribed by SANDRP, as reported), with the I&FC readings in feet at Sangam, Ram Munshi Bagh, Asham, Akhnoor and on the Tawi kept as a separate series and never converted until I&FC publishes its gauge zeros; the stage at which each gravity outfall closes, and the duty points, sump levels, start levels and standby power of every pumping station (lists of UEED and SMC [TBC]); for the ungauged khads and nallahs and every river reach outside the CWC sites, surveyed flood marks, the debris lines of 2014 and 2025 and the 1% AEP flood level with its sediment and debris; for outfalls to lakes and nambals, the outlet levels and gate rules of Dal (the Dal Gate and Nallah Amir Khan), Nigeen, Anchar, Wular (danger level 1,578 m, as reported) and the other lakes, from LCMA, WUCMA or I&FC, on a named datum [TBC]; for outfalls to reservoirs and barrage ponds, the maximum water level, full reservoir level and spillway and gate data from JKSPDC, NHPC or the operator (Baglihar 840 m; Salal 487.68 m; Ranjit Sagar 527.91 m or 527.13 m, a conflict; the Tawi barrage [TBC]), with their release records; the capacity of the Jhelum and the flood spill channel by reach (the channel was designed for 17,000 cusecs and carried 4,000 in 2014, CAG); the debris-flow fans, landslide and subsidence zones and glacial lakes above the basin, from J&K SDMA and the Geological Survey of India where mapped; and the flap gates, penstocks, debris racks, sediment traps and pumping stations on the outfalls, with their capacities and operating rules |
| Rainfall and levels | All available rain gauges (IMD, including its observatories and stations at Srinagar, Jammu and Jammu Airport, Udhampur IAF, Katra, Qazigund, Banihal, Batote, Bhaderwah, Kokernag, Pahalgam, Gulmarg and Kupwara, the automatic weather stations reported by the Meteorological Centre Srinagar, among them Kawa (Udhampur), Rambagh and Srinagar, and its gauges at Kathua, Samba, Rajouri, Poonch, Anantnag, Baramulla, Doda and Kishtwar; the self-recording gauges at Srinagar and Gulmarg used for the CWC Flood Estimation Report for zone 7; the river gauges of CWC and the staff gauges of I&FC; the rain and reservoir records of JKSPDC at Baglihar and of NHPC at Salal and Dul Hasti; and any gauges kept by SMC, JMC, the Smart City companies, J&K SDMA and the Jal Shakti Department) and water-level records, including those for the 3–10 September 2014 (599.8 mm at Qazigund in the four days to 6 September and 698.6 mm at Katra in 72 hours, Ray et al., 2015; the Jhelum at Ram Munshi Bagh at its high flood level on 8 September, 1,588.99 m or 1,589.65 m in CWC's lists of 2022 and 2018, as transcribed by SANDRP; 262 km², 34% of the Srinagar planning area, flooded), 26–27 August 2025 (380 mm at Jammu and 630 mm at Udhampur IAF in the 24 hours to 08:30 IST on 27 August, IMD, with the Tawi at Sidhra at a new high flood level of 321.1 m, as reported), 1 August 2019 (Lal Chowk, Budshah Chowk, Residence Road, M A Road and the Exhibition Grounds in Srinagar waterlogged after 26.4 mm, as reported), 7–10 September 1992 (the Chenab at Akhnoor at its high flood level of 324.29 m on 10 September, CWC as transcribed by SANDRP, and 61 ft on the I&FC gauge, as reported) and 25 September 1988 (316.2 mm at Batote, 292.4 mm at Katra and 270.4 mm at Jammu, IMD) events |
| Flood evidence | Surveyed flood marks and mapped flood extents from past events, including public reports |
| Land use | Existing land use and imperviousness; future land use from the statutory master plan |
| Soils and groundwater | HSG map (Annex 3A); seasonal high groundwater; aquifer and recharge zones |
| Sewer interaction | Known sewage cross-connections, dry-weather flow in drains, and solid-waste hotspots |
Commentary. The 0.15 m accuracy has no direct precedent; this Manual sets it because on the Kashmir valley floor, where Srinagar and the other embanked towns lie on flat ground below the Jhelum in flood, and where water stood up to 16 ft deep for up to 25 days in places in 2014 (as reported), on the Sirowal of the Jammu plains, where slopes are gentle and the water table is near the surface, and on the Kandi fans and khad terraces of Jammu, Samba and Kathua, where a raised road, a fill or a low wall can turn the overflow of a khad from one side of a fan to the other, a small error in ground level moves the flood edge a long way, and the 1% extent from the BSMP sets floor levels (Chapter 6) and setbacks (Chapter 7). Past flood marks matter as much as models. The 3–10 September 2014 (599.8 mm at Qazigund in the four days to 6 September and 698.6 mm at Katra in 72 hours, Ray et al., 2015; the Jhelum at Ram Munshi Bagh at its high flood level on 8 September, 1,588.99 m or 1,589.65 m in CWC's lists of 2022 and 2018, as transcribed by SANDRP; 262 km², 34% of the Srinagar planning area, flooded), 26–27 August 2025 (380 mm at Jammu and 630 mm at Udhampur IAF in the 24 hours to 08:30 IST on 27 August, IMD, with the Tawi at Sidhra at a new high flood level of 321.1 m, as reported), 1 August 2019 (Lal Chowk, Budshah Chowk, Residence Road, M A Road and the Exhibition Grounds in Srinagar waterlogged after 26.4 mm, as reported), 7–10 September 1992 (the Chenab at Akhnoor at its high flood level of 324.29 m on 10 September, CWC as transcribed by SANDRP, and 61 ft on the I&FC gauge, as reported) and 25 September 1988 (316.2 mm at Batote, 292.4 mm at Katra and 270.4 mm at Jammu, IMD) events are the best calibration data Jammu and Kashmir has, and much of the evidence is held in photographs, news reports and residents' records that should be collected before it is lost.
11.6 Levels of service
11.6.1 Each BSMP shall adopt the following minimum levels of service. A BSMP may adopt stricter levels.
Table 11.2 — Minimum levels of service
| Element | Minimum level of service |
|---|---|
| Minor system | The design AEP of Chapter 6 (Table 6.1) |
| Habitable buildings | No flooding above floor level in the 1% AEP (100-yr) event |
| Critical facilities (hospitals, emergency services, substations, water and sewage plants) | No flooding of the facility in the 0.2% AEP (500-yr) event; access road passable in the 1% AEP event |
| Evacuation routes and arterial roads | Passable (hazard class H2 or better, Chapter 6) in the 1% AEP event |
| Ponding drain time | Surface water cleared from roads within 6 hours after rain ends in the 10% AEP (10-yr) event |
| Tank and talab storage | No net loss of flood storage below the MWL in the basin, measured against the earliest available survey |
| Outfalls | Functioning under the joint and outfall-closed cases of Chapter 5 |
Commentary. The building and road levels repeat Chapter 6, so that the basin plan and the site designs aim at the same outcome. The 0.2% AEP for critical facilities, the 6-hour ponding drain time and the no-net-loss rule for tank storage have no direct precedent and are set by this Manual. The drain time reflects what residents notice most after a storm. The no-net-loss rule reflects a loss of storage that has been reported but rarely measured. Jammu and Kashmir's storage is in its lakes and nambals more than in tanks. Wular (18,900 ha, designated in 1990), Hokera or Hokersar (1,375 ha, 2005), Surinsar–Mansar (350 ha, 2005), Hygam (802 ha, 2022) and Shallabugh (1,675 ha, 2022) are its Ramsar sites (MoEFCC, 31 January 2024; WUCMA gives Wular's area as 13,000 ha and the Wildlife Department Hygam's as 7.62 km², conflicts); Dal covers 20.37 km² in a catchment of about 314 km² (2024); and the wetlands of the Kashmir valley were put at about 42,661 ha in 755 water bodies (as quoted by the National Green Tribunal). Seven wetlands, Hokersar, Shallabugh, Hygam, Freshkoori, Kranchoo, Chatlam and Manibugh, have been game reserves since Order No. 710-C of 17 July 1945 and are now wildlife conservation reserves; the J&K Wetland Authority was constituted on 25 November 2020, but no wetland had been notified under Rule 4 of the Wetlands Rules 2017 by September 2024, and the brief document for Wular approved for notification in 2022 has not been found notified. In the Jammu plains the storage is in the 365 ponds of the Kandi, 249 in Jammu and 116 in Kathua district, of which 165 are perennial (CGWB), and in the talabs (तालाब; تالاب; Kashmiri talāv; pond or tank) that the Jammu Master Plan 2032 would revive for recharge, while its old town talabs are lost. The losses are visible on the ground and in the records: on 13 November 2026 the National Green Tribunal found the wetland areas taken from revenue records "insufficient" and asked for the area that exists on the ground (as reported), and a rakh near Baramulla was reported "not existing on the spot" (as reported). No survey of the flood-storage volume of any lake, nambal or talab, or of any floodplain inside a ULB, was found.
11.7 Modelling and scenarios
11.7.1 Model. Each BSMP shall use a coupled 1D–2D hydraulic model of:
- the minor system;
- the major (overland) system;
- rivers, canals and tanks; and
- the outfalls.
Methods shall follow Chapter 3. Tidal and river boundaries shall follow Chapter 5.
11.7.2 Design storms. The model shall be run for the design storms of Chapter 2, including the 24-, 48- and 72-hour storms, for at least the 50%, 10%, 1% and 0.2% AEPs. Areal reduction shall be applied under Clause 2.7.3.
11.7.3 Continuous simulation. Basins with tank cascades shall also be run by continuous simulation (Clause 3.13), using the full IMD gridded daily record where available and at least 30 years, disaggregated by the temporal patterns of Annex 2D. This shows how full the tanks are when the design storms arrive, and how often heavy rain coincides with a closed outfall. The two-step approach of Clause 3.13.5 may be used: a simplified storage model is run for the whole record, and the coupled 1D–2D model of Clause 11.7.1 is run only for the design storms, starting from the tank levels the continuous run gives. A continuous run of the full 1D–2D model is not required.
11.7.4 Scenarios. Each BSMP shall model at least:
- (a) Existing: existing land use, network, tanks and outfalls;
- (b) Future, uncontrolled: future land use under the statutory master plan, with no site controls;
- (c) Future, controlled: future land use with the site controls of Chapter 4;
- (d) Future, with plan: scenario (c) plus the works of the CIP; and
- (e) Climate: scenarios (a) and (d), with the climate factors of Clause 2.8, used unchanged: no projection of heavy rainfall for Jammu and Kashmir has been adopted with a design factor; the State Action Plan on Climate Change (2012) projects rainfall intensity rising by 1–2 mm/day and annual rainfall by 5% to 13%, and by up to 50% in parts, by the 2030s, without a design factor, and a revised plan is reported in draft (2026, as reported); observed trends are mixed, with annual and spring rainfall falling at several valley stations (Zaz et al., 2019) and a slight rise in Srinagar's extreme indices (Dar et al., 2021); and in the Jammu division the storms already on record, 380 mm at Jammu on 27 August 2025 among them, exceed the zone-7 design depths before any factor is applied, so that the larger correction there is to the base value (Clause 2.3.6(h)), which is a reason to keep the factors, not to reduce them; in snow-fed basins of sub-area JK-D the climate scenario adds no rainfall factor, and the glacial-lake, debris-flow and landslide-dam hazards of Clause 11.3.3 are mapped instead.
11.7.5 Calibration. The model shall be calibrated and validated under Clause 3.15, using at least two of the 3–10 September 2014 (599.8 mm at Qazigund in the four days to 6 September and 698.6 mm at Katra in 72 hours, Ray et al., 2015; the Jhelum at Ram Munshi Bagh at its high flood level on 8 September, 1,588.99 m or 1,589.65 m in CWC's lists of 2022 and 2018, as transcribed by SANDRP; 262 km², 34% of the Srinagar planning area, flooded), 26–27 August 2025 (380 mm at Jammu and 630 mm at Udhampur IAF in the 24 hours to 08:30 IST on 27 August, IMD, with the Tawi at Sidhra at a new high flood level of 321.1 m, as reported), 1 August 2019 (Lal Chowk, Budshah Chowk, Residence Road, M A Road and the Exhibition Grounds in Srinagar waterlogged after 26.4 mm, as reported), 7–10 September 1992 (the Chenab at Akhnoor at its high flood level of 324.29 m on 10 September, CWC as transcribed by SANDRP, and 61 ft on the I&FC gauge, as reported) and 25 September 1988 (316.2 mm at Batote, 292.4 mm at Katra and 270.4 mm at Jammu, IMD) events where data exist.
Figure 11.2 — Elements of the BSMP model required by Clause 11.7: sub-catchments, the 1D drain and channel network, the 2D surface, tanks and talabs with starting levels from continuous simulation, and the tidal or river boundary at the outfall (schematic, not to scale). Original drawing for this Manual, adapted from common coupled 1D–2D urban flood modelling practice.
Commentary. Scenario (b) against scenario (c) shows what the site rules achieve on their own. Scenario (d) shows what the public works add. This comparison is also the evidence base for notifying flood-sensitive catchments (Clause 4.5.4) and for setting a stricter basin release rate (Clause 11.8.3).
11.8 Options, outputs and the Capital Improvement Programme
11.8.1 Options hierarchy. Options shall be considered in the following order, the basin-scale form of the hierarchy in Clause 1.2:
- Protect and restore storage: talabs, tanks, marshes and floodplains, including desilting to the original bed and recovering encroached area (Chapter 7);
- Regional retention and detention, sited by modelling so that releases do not coincide with the main-stem peak (Clause 4.13);
- Conveyance upgrades to drains, canals and culverts;
- Outfall works: flap gates, penstocks and pumping stations on the outfalls of Srinagar and the other embanked towns of the Kashmir valley floor to the Jhelum, the flood spill channel and the lakes, with their duty points, standby power and storage sized together for the outfall-closed case, and with every dewatering station, permanent or mobile, entered on the drain register; gates, with storage or pumping behind them, on the outfalls of Jammu to the Tawi, of Akhnoor to the Chenab, of Kathua to the Ujh and of Samba to the Basantar where a river in flood can close them; debris racks, sediment traps and debris basins where the khads of the Kandi and the nallahs of the hill towns enter the built-up area, with ramps for the machines that empty them, and the removal of muck dumped in the khads and nallahs; drop structures, chutes, energy dissipators and protected outfalls where steep drains reach a khad or river, never an unprotected slope; sediment traps, screens and the interception of dry-weather flow before every outfall to Dal, Nigeen, Anchar, Wular and the flood-absorption marshes, and the separation of sewage before the outfalls to the Jhelum, the Chunt Kol and the Tawi; and the operating rules of the Dal Gate and of the regulating gates planned at Hokersar (as reported), and the release rules of Baglihar, Salal and the Tawi barrage, agreed with I&FC, LCMA, JKSPDC and NHPC;
- Property-level protection where works cannot reach the level of service; and
- Non-structural measures: flood warning (for example IMD district rainfall warnings and nowcasts issued by the Meteorological Centre Srinagar, the CWC flood forecasts for the Jhelum at Khanabal, Sangam, Ram Munshi Bagh and Safapora and its level monitoring on the Tawi at Jammu and the Chenab at Akhnoor, the flood-declaration and danger stages that I&FC announces on its gauges, notice of releases from Baglihar, Salal, Dul Hasti and the Tawi barrage to the towns downstream, and the emergency operation centres of J&K SDMA and the districts), flood-hazard zoning, emergency planning and public information.
11.8.2 Option assessment. Each option shall be assessed for:
- reduction in flood risk (buildings and people flooded; expected annual damage);
- capital and 30-year maintenance cost;
- land required;
- effect on groundwater recharge on the Kandi fans of Jammu, Samba and Kathua, the preferred recharge zone, from whose groundwater Jammu is supplied (the three districts were Safe in every assessment from 2017 to 2024, CGWB), the waterlogging of the Sirowal and of the Kashmir valley floor, where the water table stands 0–2 m below the ground and wells flow on both sides of the Jhelum, so that recharge there adds to flooding (in Srinagar "there is no scope for artificial recharge", CGWB), the stability of hill slopes, where water put into the ground raises the pore pressure, as at Pernote in 2024 and Thathri in 2023, the springs that feed the lakes and towns and the ponds of the Kandi, the zamindari khuls that carry hill runoff, and the quality of the groundwater, in which nitrate exceeded 45 mg/L in 9.2% of the samples of 2024 (CGWB), and of the lakes, nambals and rivers that the runoff reaches (Chapter 8);
- effect on downstream basins and the receiving river, khad, nallah, lake, nambal, flood spill channel or canal; and
- who benefits.
11.8.3 Basin release rates. Where scenario (c) does not meet the level of service, the BSMP may set a basin-specific permissible site discharge (m³/s/ha) stricter than Chapter 4, by AEP and sub-catchment. The rate takes effect under the notification procedure of Clause 4.5.4.
11.8.4 Outputs. Each BSMP shall produce:
- (a) flood hazard maps (extent, depth, velocity, hazard class) for the 10%, 1% and 0.2% AEPs, existing and future-with-plan. The 1% AEP future-with-plan map becomes the reference map for floor levels (Chapter 6) and setbacks (Chapter 7);
- (b) recommended flood-sensitive catchments and any basin release rates (Clauses 4.5.4 and 11.8.3);
- (c) regional facility sites, with storage volumes, land needs and the sites they serve;
- (d) the fee-in-lieu unit rate for the basin (Clause 4.13.3);
- (e) the Capital Improvement Programme: works ranked by risk reduction per rupee, with cost, phasing and agency;
- (f) a pre-monsoon maintenance programme: desilting, gate and pump testing, and tank operating rules (Chapter 10); and
- (g) monitoring needs: new rain gauges, level sensors and flood-mark survey points.
Commentary. Restoring storage comes first because the outfalls of the Kashmir valley floor are closed in the wettest weeks, and because the storage that once took the Jhelum's floods is in lakes and marshes that the towns have filled. The Srinagar Master Plan 2035 records that its predecessor of 1971–91 "triggered growth … mostly in low lying areas, wetlands and flood absorption basins adjacent to Flood Spill Channel", and that the wetlands to the south, west and north-west "have been acting as flood retention basins"; Hokersar has shrunk from 18.75 km² to about 13 km² and is said to have lost nearly half of its flood storage, Wular from 157.74 km² in 1911 to 86.71 km² in 2007, and 37% of Narkara has been built over (all as reported); and the flood spill channel had silted from 17,000 to 4,000 cusecs by 2014 (CAG). In 2014 34% of the Srinagar planning area was flooded. Pumps alone cannot replace that storage: the 104 permanent dewatering stations reported in 2026 lift about 65 m³/s from about 767 km², some 0.3 mm of runoff an hour (this Manual's reading). In Jammu the khads are the storage and the flow paths, and they "hold greater importance in safeguarding the city from flash floods" (Jammu Master Plan 2032, §2.4), while most of the city's old talabs, Rani Talab, Talab Khatikan and Talab Tillo among them, survive only as names. On the valley floor storage means surface storage that drains to the pumps, never a pond that soaks into ground already saturated, on a hill slope a lined tank or a terrace (Clause 8.8.1), and the rainwater-harvesting proposal that UBBL-2021 requires on every plot of 100 m² or more is the first of it. The storms are large for drains with no stated design basis: 380 mm fell at Jammu in the 24 hours to 27 August 2025 (IMD). Conveyance upgrades on their own move water faster to an outfall that the Jhelum in flood closes, as in September 2014, to a lake or nambal whose outlet the river can shut, to a khad whose bed and banks shift with the boulders and muck it carries, or to an outfall limited by the capacity of its gate or pumping station, which across Srinagar is about 2,300 cusecs, some 65 m³/s, for a drainage area of about 767 km² (as reported; about 0.3 mm of runoff an hour, this Manual's reading). Groundwater in Jammu and Kashmir calls for recharge on the Kandi fans and for restraint everywhere else. All 149 assessment units of the Union Territory were Safe in 2024, at a stage of extraction of 22.28%; Srinagar Urban had been Semi-critical at 73.85% in 2022; and Jammu, Samba and Kathua, whose towns draw on groundwater, have been Safe in every assessment from 2017 to 2024 (CGWB). The boulder gravels of the Kandi, with water 7–30 m below the ground, are "a very good medium for the recharge", while the finer Sirowal below the spring line has water at 2–5 m, waterlogging and flowing wells (CGWB). On the Kashmir valley floor the water stood 0–2 m below the ground over the central and south-western valley, artesian wells flow on both sides of the Jhelum, and in Srinagar "there is no scope for artificial recharge to ground water" (CGWB), so recharge there only adds to flooding. On the hill slopes water put into the ground can bring them down: at Pernote the Geological Survey of India found that runoff entering cracks "may have developed the pore pressure" (2024). Springs (nāg) feed the lakes and towns of the valley, and the Kandi holds 365 ponds, 165 of them perennial (CGWB). Nitrate exceeded 45 mg/L in 9.2% of the samples of 2024, in Baramulla, Jammu, Kathua, Kupwara, Rajouri and Samba (CGWB). The Water Resources Act 2010 lets the Government notify areas where extraction is controlled (ss.111–112), and none has been found notified, and its rainwater-harvesting power is advisory (s.122). This is why recharge, slope stability, springs, waterlogging and groundwater quality are all assessment criteria. This Manual ranks projects by risk reduction per rupee so that limited budgets go first where most people are protected.
11.9 Integration with land-use planning
11.9.1 An approved BSMP shall be incorporated into the statutory land-use plan: the master plans of the local planning areas notified under the Jammu and Kashmir Development Act 1970, among them the Srinagar Master Plan 2035 and the Jammu Master Plan 2032 and its revision, with their zonal development plans and regulations and UBBL-2021; the conservation plans of LCMA for Dal and Nigeen and of WUCMA for Wular; and the layouts and buildings permitted under them. In particular:
- (a) regional facility sites, restored tank flood storage, and major flow paths shall be reserved in the plan;
- (b) the 1% AEP hazard map shall be shown, and Chapter 7 setbacks applied to it;
- (c) land in hazard classes H5–H6 in the 1% AEP event shall not be zoned for new habitable development; and
- (d) the open space of layouts within a basin should be located, where possible, to form part of the major flow paths or regional storage shown in the BSMP.
11.9.2 Where a land-use plan is revised before a BSMP is approved, the planning authority shall use the best available flood mapping and record the BSMP as pending.
Commentary. Jammu and Kashmir draws its watercourse lines from three reference lines, and no drainage-flood line. UBBL-2021 bars development within 50 m of the edge of the bank of the Chenab, the Jhelum, the Tawi, the Ravi, the Ujh "or any other river/khad", 30 m of the listed lakes, among them Mansar, Surinsar, Wular, Nigeen and Manasbal, and 20 m of unlisted rivulets and canals, "or as per building regulation whichever is more" (cl. 7.12(b)), and keeps a green buffer of at least 30 m "from the highest water level" along nallahs and rivers (cl. 5.2.5); the Srinagar Master Plan 2035 sets lake, nallah and wetland buffers from the edge, from 20 m to 200 m (Tables 8-2 and 8-3; 100 m for unlisted wetland reserves, §8.2.3), and records 125 km² of its planning area as undevelopable and 136.50 km² as vulnerable on the flood zonation of I&FC (§4.2); the Jammu Master Plan 2032 sets its buffers from the Full Tank Level, 50 m (30 m in built-up areas) on the Tawi, the Devak and the Basantar, 15 m on the Balol, Thather and Bhalwal khads and 5 m elsewhere (§7.3.3), lines that UBBL's 50 m overrides where the bye-laws apply; and the High Court holds 200 m around Dal (2002, as quoted) and Wular (2020, as reported). Building in flood-prone areas is left to I&FC "or the flood zonation maps notified by the department from time to time" (UBBL-2021, cl. 7.12(a)), none of which has been found. The Flood Plain Zones Act 2005 has not been found brought into force, and no flood basin has been found declared under Part VI of the Water Resources Act 2010. The Jammu Master Plan proposes to release land recorded as Gair Mumkin Khad, more than 30% of JDA's land, outside the "true Khad" to be fixed with I&FC (§12.2.3); this Manual requires any release to follow a hydraulic study of the functional khad at the 1% AEP flow with its sediment bulking (set by this Manual). These are watercourse lines, not drainage-flood lines: where a flood basin is notified under Part VI of the Act its restrictions govern; until then the mapped design flood line of Chapter 7 applies (set by this Manual), the widest of the statutory lines governs, and the hydraulic corridor and setback zones of Chapter 7, with a Zone 1 of at least 15 m, apply only where nothing wider binds, as this Manual's proposal. A BSMP gives the master plans the 1% AEP drainage-flood map, including the khads and nallahs that no plan yet covers, and the buffer widths of Chapter 7, that they need. Using open space land as storage or flow path has no direct precedent; this Manual adopts it because UBBL-2021 already requires public open spaces of more than 500 m² to capture and use their storm water (cl. 10.4), recharge in parks, parking areas, plazas and playgrounds (cl. 10.5) and permeable paving for the open parking of group housing (Table 10-1), and the Srinagar Master Plan 2035 asks for detention and retention as source controls under its stormwater performance standard (§13.3), but no rule sets a detention volume or a peak-runoff limit; storage placed in a layout's open space builds on these duties, and because that land still serves as open space, the storage must stay usable as one; on the Kashmir valley floor it is shallow surface storage that drains to the outfall or the pumps, never an infiltration basin, and on a hill slope it is a lined tank or a shallow terrace (Clause 8.8.1). Placing it on the flow path costs the developer nothing extra and gives the basin storage it would otherwise have to buy.
11.10 Consultation and publication
11.10.1 A draft BSMP shall be published for public comment for at least 60 days, with public meetings in each affected local body.
11.10.2 After approval, the following shall be published as open data:
- the model files;
- the flood hazard maps;
- the data of Clause 11.5.1, except security-sensitive asset details; and
- the CIP.
They shall also be shown on a public map viewer.
Commentary. Publishing the maps lets buyers, lenders, insurers and residents see flood hazard before they build or buy. Publishing the model lets designers use the same boundary conditions as the Authority, so site designs and the basin plan stay consistent. This matches the publication approach of Chapter 10.
11.11 Approval, review and reporting
11.11.1 Approval. BSMPs shall be approved by the State Stormwater Technical Committee (Chapter 1), after review of the model and of the public comments.
11.11.2 Review. Each BSMP shall be reviewed:
- every 10 years;
- within 2 years of an event exceeding the 1% AEP design depth in the basin (Clause 2.14); and
- when the statutory land-use plan is revised.
11.11.3 Annual report. The Lead Authority shall publish an annual implementation report before each SW monsoon (by 31 May). The report shall show:
- CIP progress;
- the fee-in-lieu ledger (Clause 4.13.4);
- maintenance completed; and
- any flooding against the levels of service.
11.12 Interim arrangements
11.12.1 Until a BSMP is approved for a basin:
- (a) all site criteria of Chapters 4 to 8 apply in full;
- (b) regional detention and fee-in-lieu under Clause 4.13 are not available, except the holding of fees under Clause 4.5.6.3;
- (c) floor levels and setbacks use the best available mapping, and the methods of Chapters 6 and 7 where no mapping exists; and
- (d) public drain projects shall include a basin-level check that their outfall and downstream reaches can take the design flow under the Chapter 5 tailwater cases.
References (chapter)
- Central Ground Water Board. Dynamic Ground Water Resources, Jammu and Kashmir, 2022 and 2024 (stage of extraction; assessment units); Ground Water Year Book, Jammu and Kashmir, 2021–22 (depth to water); aquifer mapping (NAQUIM) reports for the Kashmir valley and the Jammu plains (Kandi and Sirowal; Kandi ponds); and the district booklet for Srinagar ("no scope for artificial recharge").
- Town Planning Organisation Kashmir (2019). Srinagar Master Plan 2035, §§4.2, 8.2–8.4, 13.3 and 14.4.4.2, Tables 8-2 to 8-4 and 12-4 to 12-5. https://huddobps.jk.gov.in/Srinagar_Master_Plan_2035.pdf
- Jammu Master Plan 2032, §§2.4, 5.1.3, 7.3.2–7.3.3, 11.1 and 12.2.3. https://huddobps.jk.gov.in/JMP2032.pdf
- Jammu and Kashmir Pollution Control Committee. Report in O.A. No. 504 of 2024 before the National Green Tribunal, 14 August 2024 (Dal: catchment, outlets, sewage, STPs, houseboats).
- Geological Survey of India (2024). Note on preliminary geological assessment of the landslide at Pernote, Ramban, 25 April 2024, annexed to JKPCC's compliance report in O.A. No. 642 of 2024.
- Defra (2010). Surface Water Management Plan Technical Guidance. Department for Environment, Food and Rural Affairs, London.
- Mile High Flood District (Denver). Master planning programme and Urban Storm Drainage Criteria Manual.
- Mid-America Regional Council (2025). APWA Stormwater Standards Supplement; KC Metro APWA Section 5600, Version 2025.01.
- Department of Irrigation and Drainage Malaysia (2012). Urban Stormwater Management Manual for Malaysia (MSMA), 2nd ed.
- Comptroller and Auditor General of India. Report No. 4 of 2016, Performance Audit of Disaster Management in the State of Jammu and Kashmir, §2.1.4 (flood spill channel; Jhelum schemes); and Audit Report on the Prime Minister's Development Package for the year ended 31 March 2019 (2021), chapter VI (Comprehensive Plan for Flood Management of the Jhelum, Phase I).
- Jammu and Kashmir Unified Building Bye-Laws, 2021, cls. 5.2.5 and 7.12 and chapter 10; Jammu and Kashmir Water Resources (Regulation and Management) Act, 2010, ss.75–81 and 111–122 (section numbers to be confirmed); Jammu and Kashmir Flood Plain Zones (Regulation and Development) Act, 2005, s.1(3).
- High Court of Jammu and Kashmir and Ladakh. PIL 8/2017 with PIL 2/2014 and PIL 18/2018, order of 29 May 2024; PIL 159/2002 (Dal; 200 m, as quoted and reported).
- National Green Tribunal. O.A. No. 239 of 2024 (wetlands of Kashmir), report of the Forest, Ecology and Environment Department of 9 September 2024 (Wetland Authority; Wular; wildlife conservation reserves) and order of 13 November 2026 (as reported). https://www.greentribunal.gov.in/
- Ministry of Environment, Forest and Climate Change, 80 Ramsar sites of India (31 January 2024). https://moef.gov.in/uploads/2024/03/80-Ramsar-sites-of-India-31-01-2024.pdf
- Government of Jammu and Kashmir (2012). State Action Plan on Climate Change (final report). Zaz, Romshoo et al. (2019), Atmospheric Chemistry and Physics 19, 15–37; Dar et al. (2021), Srinagar extreme-rainfall indices.
- Bentley Systems (2023). Case study: drainage master plan and detailed project report for the stormwater drainage system of Srinagar city (Egis India) (secondary source).
- Kashmir Life, Greater Kashmir, Daily Excelsior and Kashmir Reader (2020–2026). Reports of Srinagar's dewatering stations and drainage network (H&UDD reply in the Legislative Assembly, 12 February 2026), the Jhelum Comprehensive Plan and the Hokersar gates, the shrinking of Hokersar, Wular and Narkara, and the Jammu drainage projects (secondary sources).
Annexes and forms
| Annex / Form | Content |
|---|---|
| 11A | BSMP terms of reference template |
| 11B | Basin lists and boundaries for Tier A bodies |
| 11C | Depth–damage curves for Jammu and Kashmir building types |
| 11D | BSMP data and model publication standard |
| Form 11-1 | Annual implementation report |
Commentary. Jammu and Kashmir's cities have drainage plans, schemes and benchmarks, but no published storm-drainage master plan with a design storm. In Srinagar the master plan commits the city to "stormwater performance standards … with 100% coverage and zero incidence of waterlogging", recommends source controls that "store stormwater onsite and release it at a controlled rate", and divides the city into the three drainage zones of the "Drainage Master Plan of Srinagar City", with about 50 drainage schemes, 118,663 m of primary and secondary drains and 89 drainage pumping stations, but it gives no return period, runoff coefficient or intensity (Srinagar Master Plan 2035, §13.3); the drainage master plan and project report that Egis India prepared for 767 km² of the city, "separate from the sewage system", has not been published with its design basis (as reported). For the Jhelum the same plan proposes the watershed mapping of the Lidder, Veshaw, Brengi, Sandran, Rambiara, Arpath, Rumshi, Veth, Sindh, Arizal and Doodhganga, records that "A supplementary Flood Spill Channel from Dogripora to Wullar, designed for 55,000 Cusecs has been conceived by Department of Irrigation and Flood Control", aims at a river capacity of 55,000 cusecs "with 25,000 cusecs to be diverted through the Flood Spill Channel", and envisages the demarcation of the 25-year flood plain from Lelhar to Lasjan, to be notified "as Protected Natural Flood Absorption Basin" (§14.4.4.2); this is a proposal of the plan, and no such notification has been found. The 25-year flood plain is the only design-flood frequency found in any planning text of the Union Territory, and it is a planning line, not a drain-design storm. The Comprehensive Plan for Flood Management Works on the Jhelum was taken up in two phases, Phase I of ₹399.29 crore and Phase II of ₹5,411.54 crore, of which Part A, ₹1,623.43 crore, was approved in 2022, with regulating gates at Hokersar (as reported); the CAG found Phase I's dredging well short of its targets (2021). In Jammu the master plan records that roadside drains serve as storm drains, that only 20% of roads have them, covering about 40% of the city, and that "Storm water drains carry considerable quantities of raw and untreated effluents" (Jammu Master Plan 2032, §5.1.3); it asks that a storm-water project report be prepared "immediately after the approval of this Master Plan" (§11.1.3), and none was found; only the names and costs of single drains, such as the Digiana–Gangyal storm drain, were seen (as reported). No published document sets a design return period for the storm-drain network of any town in Jammu and Kashmir. This chapter supplies the design storm, levels of service, storage and buffer criteria that such a plan needs, with the design storms of Chapter 2 and the levels of service of Clause 11.6; it has not been adopted by H&UDD, the Jal Shakti Department (I&FC), SMC, JMC, SDA, JDA, UEED, LCMA, WUCMA, J&K SDMA or any other body. A site-level manual cannot fix basin-level problems: lost tank storage, lakes, nambals and flood-absorption marshes built over on the valley floor, city drains that close against the Jhelum and empty only by pumps, as Srinagar's did in September 2014, khads narrowed by building and by the release of Gair Mumkin Khad land in Jammu, slopes that open drains and sewage pipes saturate, as at Thathri and Pernote, drains that carry sewage into Dal, the Jhelum and the Tawi, and single drains split between a Municipal Corporation, UEED, I&FC, LCMA, PW (R&B) and a Smart City company, and drains that are adequate on their own but overload the next reach. Comparable manuals pair site criteria with basin planning:
This chapter adapts that method to Jammu and Kashmir, the third mountain edition in the series and its first with two rainfall regimes and a valley-floor city behind river embankments: to Srinagar and the other towns of the Kashmir valley floor, flat, with the water table 0–2 m below the ground, whose drains close against the Jhelum in flood and then empty only by pumps, and whose flood storage lies in lakes and nambals, Dal, Anchar, Hokersar, Narkara and Wular among them, into which the towns have grown since the plan of 1971–91 (Srinagar Master Plan 2035); to Jammu and the towns of the Kandi and the Sirowal, whose khads cross boulder fans to the Tawi, the Chenab, the Ujh and the Basantar and are narrowed by building and by the release of land recorded as Gair Mumkin Khad; to the hill towns of the Pir Panjal and the Chenab, Udhampur, Ramban, Doda and Kishtwar among them, where water put into the ground moves the ground, as at Pernote and Thathri; to drains run by SMC, JMC, UEED, I&FC, LCMA, PW (R&B) and Smart City companies, beside nallahs and khads that no rule assigns; to a Union Territory with flood-zoning statutes that have never been used, building bye-laws with wide watercourse buffers but no drainage standard, and master plans with benchmarks but no design storm; to the western disturbances and snowmelt of the Kashmir valley and the monsoon of the Jammu division, whose largest floods both came in September; and to storms that outrun the design maps, 380 mm at Jammu and 630 mm at Udhampur in the 24 hours to 27 August 2025 (IMD), and cloudbursts and debris flows, as at Chasoti in 2025, that no drain can carry, so that in the high mountains a BSMP begins with the hazard, not the storm (Clause 11.3.3).