Draft v1.0 prepared by NEER. Not adopted by the Government of the Union Territory of Jammu and Kashmir or the Administration of the Union Territory of Ladakh, and has no legal force. About this draft

Annexes to Chapter 7Waterbodies, Lakes, Marshes (Nambals) and Talabs (Ponds) and Setbacks

These annexes support Chapter 7. They give the inventory field specification, the fixed-width setback table, a template operating rule, the desilting and restoration specification, a glossary of Kashmiri and Urdu waterbody terms, and the three forms that Clause 7.15 requires. Where an annex cannot yet be completed it says so and gives the rule to use in the meantime. The forms are draft forms; the template and model text are for consideration by a competent authority and are not in force.


Annex 7A — Statewide waterbody GIS layer and inventory fields

Supports Clauses 7.3.1, 7.3.3 and 7.3.5 of Chapter 7.

To be prepared. This annex will contain the statewide GIS layer of waterbodies required by Clause 7.3.1, prepared by each Authority with I&FC and the Revenue Department. It needs the Revenue records and village maps of the Revenue Department, in which rivers, khads, nallahs, khuls, talabs, nambals and land covered by water are recorded, and in which drainage land in Jammu is largely recorded as Gair Mumkin Khad and marsh or grassland as nambal, rakh or kahcharai, classes that record the land, not its hydraulic extent; the "approximate location and size of any water body, flood affected areas and contours at an interval of 0.3m" that clause 2.6(b)(xi) of UBBL-2021 requires on the site plan of a sloping site, and the certificate of the registered technical person that the site is clear of drains and water bodies; the land use maps and buffer tables of the Srinagar Master Plan 2035 (Tables 8-2 to 8-4) and the Jammu Master Plan 2032 (§7.3.3), and the flood zonation of I&FC used in the Srinagar Master Plan (125 km² undevelopable and 136.50 km² vulnerable in the Srinagar planning area); the drains, nallahs and dewatering stations in the records of SMC, JMC, UEED and the other urban local bodies; I&FC's records of the rivers, khads, embankments, the flood spill channel and the city channels, and of its gauges; LCMA's records of Dal and Nigeen and WUCMA's of Wular; the boundaries of the five Ramsar sites, of the seven Wildlife Conservation Reserves and of any wetland notified under the Wetlands (Conservation and Management) Rules, 2017; NHPC's and JKSPDC's records of reservoir levels and acquired land; and the lists of wetlands, encroachments and water bodies filed before the High Court of Jammu & Kashmir and Ladakh and the National Green Tribunal, such as the 27 wetlands of more than 1 ha outside forests listed in 2026; the I&FC and Halqa Panchayat tank registers with FTL and MWL; surveyed levels on a common datum; the ISRO National Wetland Inventory and Assessment (NRSC); Survey of India topographic maps; and any list of waterbodies published under court directions. Until it is published, each Applicant identifies waterbodies from all the sources of Clause 7.3.3, with the larger extent governing, and records them on the Waterbody Sheet (Form 7-1).

The field specification below is complete. It is written so that every field the chapter asks for (Clause 7.3.1(a) to (g)) has a defined name, type and source, and so that the same fields can be filled from a project's Form 7-1.

7A.1 Layers

  • WB_POLY — one polygon per waterbody: the Revenue record boundary (Clause 7.3.1(c)).
  • WB_FTL — the surveyed FTL contour (tanks, lakes, ponds) or top of bank (channels), as a polygon or line.
  • WB_MWL — the MWL contour of each tank, as a polygon.
  • WB_FLOOD — the 1% AEP flood extent, where mapped (Clause 7.3.1(f)), with the floodway where delineated (Clause 7.6.1).
  • WB_STRUCT — points for surplus weirs, sluices, regulators, inlets and drain outfalls.
  • WB_LINK — lines for supply channels, surplus courses and the links between tanks in a cascade (Clause 7.3.1(e)).
  • WB_ENCR — polygons of known encroachments, each with the date recorded (Clause 7.3.1(g)).
  • WB_SETBACK — Zone 1 and Zone 2 polygons (Clause 7.4), derived from the layers above.

All layers shall carry the waterbody identifier (WB_ID) so that they can be joined. All levels shall be stated to one datum (Clause 7.3.5), named in the layer metadata.

Table 7A.1 — Attribute fields of the waterbody inventory (WB_POLY)

Field Type Unit / domain Required Content Clause
WB_ID Text District code + serial Yes Unique identifier, never reused 7.3.1
WB_NAME Text — Yes Name as in Revenue and I&FC records, with local name 7.3.1(a)
WB_NAME_UR Text Urdu script Yes Name in Urdu 7.3.1(a)
WB_TYPE Code Table 7A.2 Yes Waterbody type 7.2, 7.3.1(a)
SURVEY_NOS Text Village, survey and subdivision numbers Yes Revenue survey numbers of the waterbody 7.3.1(a)
VILLAGE Text — Yes Revenue village, tehsil and district 7.3.1(a)
CUSTODIAN Code Table 7A.2 Yes Custodian body 7.3.1(b)
AREA_REC Number ha Yes Area within the Revenue record boundary 7.3.1(c)
AREA_FTL Number ha Tanks Waterspread at FTL, surveyed 7.2, 7.3.1(d)
FTL Number m (datum) Tanks Full tank level 7.3.1(d)
MWL Number m (datum) Tanks Maximum water level (Clause 7.2 definition) 7.3.1(d)
MWL_BASIS Code I&FC record / 1% AEP computed Tanks Which value governs MWL 7.2
TBL Number m (datum) Tanks Top bund level, lowest point 7.3.1(d)
WEIR_CREST Number m (datum) Tanks Surplus weir crest level 7.3.1(d)
WEIR_LEN Number m Tanks Surplus weir crest length 7.3.1(d)
WEIR_TYPE Text — Tanks Surplus weir type (for example fixed crest, with shutters or falling boards) 7.3.1(d)
SLUICE_N Integer — Tanks Number of sluices; details in WB_STRUCT 7.3.1(d)
SUPPLY_CH Text WB_ID(s) Tanks Supply channel(s) feeding the tank 7.3.1(d)
SURPLUS_CS Text WB_ID(s) Tanks Surplus course(s) leaving the tank 7.3.1(d)
UPSTR_WB Text WB_ID(s) Cascades Upstream tank(s) in the cascade 7.3.1(e)
DNSTR_WB Text WB_ID Cascades Downstream tank, river, drain or sea outfall 7.3.1(e)
CATCH_AREA Number ha Channels Drainage area at the downstream end of the reach (for the 8 ha trigger of Clause 7.4.1(b) and Table 7.1) 7.4.1
DATUM Text — Yes Datum of all levels; conversion from any older I&FC datum 7.3.5
LEVEL_DATE Date — Tanks Date of the level survey 7.7.1(a)
SSC_DATE Date — Tanks Date of the latest stage–storage survey 7.7.1(b)
FLOOD_SRC Code Adopted map / site study / none Yes Source of the 1% AEP extent 7.3.4
FLOODWAY Code Delineated / whole 1% extent / below MWL Yes Basis of the floodway 7.6.1
ENCR_KNOWN Code Yes / No Yes Known encroachment; details in WB_ENCR 7.3.1(g)
CREDITED Code Yes / No Tanks Storage counted under Clause 7.7, with the scheme reference 7.7.1
WETLAND Code Notified / listed / other Wetlands Status under Clause 7.12.1 7.12.1
SOURCES Text — Yes Sources used, from the list in Clause 7.3.3(a) to (e) 7.3.3
UPDATED Date — Yes Date of the last edit, and by whom 7.3.1

Table 7A.2 — Code lists

Code list Values Clause
WB_TYPE River; khad (seasonal torrent); nallah (natural or artificial drainage channel); kol (stream or canal); city channel or flood spill channel; canal; kuhl or zamindari khul (irrigation channel); lake or sar (with its gated or open outlet); nambal (marsh) or flood basin; talab (pond or tank; Kandi pond); reservoir or barrage pond (with its drawdown zone); spring (nag or cashma) and its recharge area; wetland (Ramsar site, Wildlife Conservation Reserve or other); glacial or moraine-dammed lake; supply channel; surplus course 7.2
CUSTODIAN SMC, JMC, Municipal Council or Municipal Committee (Municipal Acts, 2000 [TBC]); UEED (with its Sewerage and Drainage Division (West) Jammu); Town Drainage (SMC or DULBK); I&FC (division; rivers, khads, nallahs, embankments, flood spill channel, city channels, canals and khuls); LCMA (Dal–Nigeen); WUCMA (Wular); Wildlife Department (Wildlife Conservation Reserve); Forest Department; PW (R&B) or NHAI (road drains and culverts); NHPC, JKSPDC or other dam operator; SDA, JDA, J&K Housing Board, Smart City SPV or developer (until handed over); State Government through the Deputy Commissioner or Tehsildar; Halqa Panchayat; Jammu and Kashmir Wetland Authority (wetland); private owner; other (name) 7.3.1(b)
Structure (WB_STRUCT) Surplus weir; sluice; regulator; inlet; drain outfall; gross pollutant trap; crossing 7.3.1(d), 7.10
Encroachment (WB_ENCR) Building; fill; road; wall; dumping; cultivation; other — each with date recorded, area (m²) and source 7.3.1(g), 7.13

Table 7A.3 — Attribute fields of structures (WB_STRUCT)

Field Type Unit Content Clause
STR_ID Text — Unique identifier 7.3.1(d)
WB_ID Text — Waterbody served 7.3.1(d)
STR_TYPE Code Table 7A.2 Structure type 7.3.1(d)
CREST_SILL Number m (datum) Weir crest or sluice sill level 7.7.1(a)
LENGTH_SIZE Text m Weir crest length, or sluice opening size 7.7.1(a)
GATED Code Yes / No Controllable outlet (needed for a flood cushion, Clause 7.8.2(a)) 7.8.2
CONDITION Code Serviceable / defective Result of the latest pre-monsoon inspection, with date 7.7.1(d), 7.14.4

Annex 7B — Fixed-width setback table (alternative S-3, with Annex 1C)

Supports Clauses 7.3.4, 7.4.3, 7.4.6 and 7.4.7 of Chapter 7, and alternative S-3 of the Policy Supplement (Annex 1C).

7B.1 When the table may be used

The fixed-width setback may be used only where all of the following apply:

  • (a) the Authority has not adopted a 1% AEP flood extent map for the waterbody (Clause 7.3.4);
  • (b) Clause 7.3.4 does not require the Applicant to determine the 1% AEP extent by a hydraulic study: the site is not in a flood-sensitive catchment, is not a site of 1 ha or more adjoining a waterbody, and the Authority has not asked for a study; and
  • (c) the waterbody is one to which setbacks apply (Clause 7.4.1): any recorded or found waterbody, and any natural channel draining 8 ha or more at the site.

Where an Authority adopts alternative S-3 under Clause 1.7, the table below is the S-3 table. Clause 1.7.3(e) provides for the S-3 table to be issued by the State Stormwater Technical Committee. Until it is issued, the values are those of Clause 7.4.6, repeated here without change.

Table 7B.1 — Fixed-width setback by waterbody class (alternative S-3)

Waterbody class Drainage area at the site Total setback (Zone 1 + Zone 2) Of which Zone 1 Measured from
Channel, small 8 ha to 65 ha 25 m 15 m Top of bank (Clause 7.4.3)
Channel, medium 65 ha to 20 km² 40 m 15 m Top of bank
Channel, large, and rivers More than 20 km² 50 m 20 m Top of bank
Tank, lake or pond Any MWL contour + 25 m To the MWL contour, and not less than 15 m from FTL FTL contour (Zone 1); MWL contour (total)
Marsh, estuary or backwater Any As notified by the Authority, and not less than 50 m 15 m The waterbody boundary of Clause 7.13.1

Values from Clause 7.4.6 (Table 7.1). Zone 2 is the total setback less Zone 1.

7B.2 Rules of application

  • (a) Measurement. Measure horizontally on plan, outward from the boundary of Clause 7.13.1: the larger of the Revenue record boundary and the surveyed FTL (or top of bank). Where FTL and top of bank both apply, use whichever gives the wider zone (Clause 7.4.3).
  • (b) Drainage area. For a channel, use the drainage area at the downstream end of the reach that adjoins the site. Where a reach crosses a class limit within the site, apply the wider setback to the whole reach within the site.
  • (c) Both banks. The setback applies on each bank of a channel and all round a tank, lake, pond or marsh.
  • (d) Minimum set by this Manual. Zone 1 is never less than 15 m (Clause 7.4.7). A wider statutory or approval setback governs for the uses it restricts (Clause 7.4.5).
  • (e) Stricter of the two. Where a hydraulic study is made voluntarily, the setback is the wider of Table 7B.1 and Clauses 7.4.3 and 7.4.4.
  • (f) Record. The basis of the setback (fixed width) shall be stated on the Waterbody Sheet (Form 7-1) and in the approval (Clause 7.4, Disclosure).
  • (g) Review. The table shall be reviewed within 2 years of the Authority adopting 1% AEP flood maps (Clause 7.16.1).

7B.3 Source of the channel widths

The channel widths were set by this Manual with reference to the 2006 Kansas City APWA default stream buffers, rounded up and floored at the 15 m minimum (Clause 7.4.6, commentary). The source values, as cited in the chapter, are:

Table 7B.2 — Source buffers cited in Clause 7.4.6 (KC APWA 5600, 2006, §5605.3)

Drainage area (source, acres) Approximate SI equivalent Source buffer
Less than 40 ac Less than 16 ha 40 ft (12 m)
40–160 ac 16–65 ha 60 ft (18 m)
160–5,000 ac 65 ha – 20 km² 100 ft (30 m)
More than 5,000 ac More than 20 km² 120 ft (37 m)

The 65 ha and 20 km² class limits in Table 7B.1 are the SI equivalents of 160 ac and 5,000 ac. The 8 ha lower limit is the 20-acre trigger of APWA 2025.01 (Clause 7.4.1(b)).


Annex 7C — Template tank operating rule, with flood cushion

Supports Clauses 7.7.1(c), 7.7.3, 7.8 and 7.14.4 of Chapter 7.

Model text for consideration by a competent authority. Not in force. For tanks under I&FC control, the operating rule is I&FC's rule (Clause 7.8.4); this template sets out the content that Clause 7.8 asks for, so that the custodian's rule can be checked against it. Text in square brackets is to be completed for each tank.

7C.1 Identification

  1. Tank: [name, WB_ID of Annex 7A, village, tehsil, district].
  2. Custodian: [I&FC division / ULB / Halqa Panchayat / other].
  3. Cascade position: upstream tank(s) [ ]; downstream tank, river or drain [ ].
  4. Datum: [ ]. Surveyed levels (Clause 7.7.1(a)), date of survey [ ]: FTL [ ] m; MWL [ ] m; TBL (lowest point) [ ] m; surplus weir crest [ ] m, length [ ] m; sluice sills [ ] m.
  5. Stage–storage curve (Clause 7.7.1(b)): survey date [ ]; attached as Schedule 1.
  6. Controllable outlets (Clause 7.8.2(a)): [gated sluice / regulator / none]; capacity at FTL [ ] m³/s.

7C.2 Purposes and priority

  1. The tank serves [irrigation of a command area of [ ] ha / drinking water supply / recharge / flood storage]. Irrigation and water supply remain primary unless the custodian records otherwise (Clause 7.8.2(d)).

7C.3 Levels and dates through the year (Clause 7.8.1(a))

  1. The tank shall be operated to the levels in Table 7C.1.

Table 7C.1 — Rule levels by period (to be completed for each tank)

Period Target level (m) Upper limit (m) Lower limit (m) Purpose
[1 Jan – date] [ ] FTL [ ] Holding for irrigation / supply
[date – start of cushion period] [ ] FTL [ ] Holding
[Flood-cushion period, if any] Cushion level [ ] Cushion level [ ] [ ] Flood cushion (Clause 7.8.2)
[End of cushion period – 31 Dec] [ ] FTL [ ] Refilling
  1. Where no flood cushion is adopted, the starting level for design is FTL (Clause 7.7.3) and the row for the cushion period is deleted.

7C.4 Flood cushion (Clause 7.8.2)

  1. Cushion level: [ ] m, which is [ ] m below FTL, giving a cushion volume of [ ] m³ from Schedule 1.
  2. Dates: the cushion applies from [ ] to [ ].
  3. Drawdown: the tank can be drawn down from FTL to the cushion level through [outlet] in [ ] hours, with a release not exceeding the maximum release rate of paragraph 18.
  4. Reliability: continuous simulation (Clause 3.13) over the record [years] shows that the cushion is available at the start of a design storm in [ ]% of SW monsoon seasons, which shall be at least 90%. The simulation report is Schedule 2.
  5. Yield: the custodian accepts the loss of irrigation or supply yield stated in Schedule 3 [and the compensation recorded there].
  6. Where the tank has no controllable outlet, this section does not apply and no flood cushion is assumed (Clause 7.8.3).

7C.5 Releases (Clause 7.8.1(b) to (d))

  1. Sluice and regulator settings at each level: Table 7C.2.
  2. Operator: the sluices and regulators are operated by [post]. A release above [ ] m³/s may be ordered only by [post], or, in an emergency, by [post].
  3. Maximum release rate: [ ] m³/s. This rate, added to the flow from the downstream catchment, does not flood buildings downstream (Schedule 4 gives the downstream check).
  4. No person shall cut, lower or breach the bund or surplus weir except under the custodian's emergency procedure (Clause 7.14.5).

Table 7C.2 — Outlet settings by level (to be completed for each tank)

Tank level (m) Sluice 1 Sluice 2 Regulator Expected outflow (m³/s) Notes
Below cushion level [ ] [ ] [ ] [ ]
Cushion level to FTL [ ] [ ] [ ] [ ]
FTL (weir begins to spill) [ ] [ ] [ ] [ ]
Above FTL to MWL [ ] [ ] [ ] [ ] Check freeboard to TBL (Clause 7.7.4(b))

7C.6 Forecasts, warnings and communication (Clause 7.8.1(e) and (f))

  1. The triggers and actions are in Table 7C.3.
  2. Before any release under this rule, the operator shall inform the ULBs and the district administration downstream, and residents by the means stated in Schedule 5, at least [ ] hours before the release where the forecast allows.

Table 7C.3 — Triggers and actions (to be completed for each tank)

Trigger Source Action By whom
IMD district heavy-rainfall warning for the catchment IMD Read gauges [ ] hourly; check outlets are free; confirm the tank is at or below its rule level [ ]
IMD or J&K SDMA red alert IMD, J&K SDMA Begin releases needed to reach the rule level, within the maximum release rate; notify downstream bodies (paragraph 21) [ ]
City forecast system warning, where available [ ] [ ] [ ]
Tank level reaches FTL Gauge Record outflow hourly; inspect bund and weir [ ]
Tank level reaches [MWL − [ ] m] Gauge Emergency procedure; warning to the breach area of any emergency action plan (Clause 7.14.3(c)) [ ]

7C.7 Records and review (Clause 7.8.1(g))

  1. During the SW monsoon (15 June to 31 October) the operator shall record daily: the tank level, every release (time, rate and duration), and every gate setting. Outside the SW monsoon, records shall be kept [weekly].
  2. Records shall be kept with the O&M plan (Chapter 10) and given to the Authority on request.
  3. The tank shall be inspected before the SW monsoon (by 31 May) and after every heavy-rainfall event (Clause 7.14.4).
  4. This rule shall be reviewed after any event in which the tank surplused at a level above [ ] m, after any change to the weir, sluices or bund (Clause 7.7.6), and in any case with the review of the Manual.

Schedules: 1 stage–storage curve; 2 continuous simulation report; 3 yield and compensation; 4 downstream check of the maximum release; 5 communication list.


Annex 7D — Desilting and restoration specification

Supports Clauses 7.7.1(b), 7.9 and 7.14.4 of Chapter 7.

This specification applies to every desilting, restoration or deepening of a tank, pond or other waterbody under Clause 7.9. Values are those of Chapter 7. Where the chapter does not set a value, it is marked "to be confirmed in design" and shall be stated in the works design.

7D.1 Pre-works survey (Clause 7.9.1)

  • (a) Topographic and bathymetric survey of the waterspread, foreshore (to the MWL contour), bund, surplus weir and sluices, levelled to the datum of Clause 7.3.5. Survey grid and point density: to be confirmed in design.
  • (b) Original bed level found by test pits or augering on a grid (grid spacing to be confirmed in design), and from historical records where available. Each pit log shall show the silt thickness, the level of the original bed, and any clay or silt layer below it.
  • (c) Silt testing where the tank receives urban runoff or sewage: samples from the pits of (b), tested for heavy metals and other contaminants before disposal is planned. The parameters and limits shall be those the Jammu and Kashmir Pollution Control Committee (JKPCC) directs.
  • (d) Structures: condition of the bund (seepage, slips, cracks, animal burrows, trees), surplus weir and sluices, as in Clause 7.14.4.
  • (e) Existing stage–storage curve from the survey of (a).

7D.2 Limits of excavation (Clauses 7.9.2 and 7.9.3)

  • (a) Desilting removes accumulated sediment down to the original bed level of 7D.1(b), and no deeper.
  • (b) Deepening below the original bed only with a hydrogeological report showing each of Clause 7.9.3(a) to (c).
  • (c) Storage created below the lowest sluice sill is not flood storage, and shall not be shown as such in the revised stage–storage curve.
  • (d) Excavation shall stay clear of the bund toe by a distance to be confirmed in design, so that the bund's stability is not reduced.

7D.3 Edges and safety (Clause 7.9.4)

Where the public has access to the edge:

  • (a) side slopes no steeper than 1V:4H from 0.5 m above FTL down to 1.2 m below FTL; or
  • (b) a level safety bench at least 3 m wide, between 0.3 m and 0.5 m below FTL; and
  • (c) no isolated deep pit or vertical cut left in the bed. Borrow pits shall be regraded to the bed.

7D.4 Storage not reduced (Clause 7.9.5)

  • (a) Islands, walkways, bund widening into the waterspread, ring roads, parking, buildings and lake-front platforms within the waterspread or foreshore are lost storage.
  • (b) Lost storage shall be offset by compensatory storage at equivalent levels, band by band, using Form 7-3.

7D.5 Silt handling and disposal (Clause 7.9.6)

  • (a) Desilted material shall not be placed within the setback, on the bund (except approved bund strengthening), or on any flood path.
  • (b) Contaminated silt shall be disposed of as the Jammu and Kashmir Pollution Control Committee (JKPCC) directs.
  • (c) Haul routes and temporary stockpiles shall meet the construction erosion and sediment control rules of Clause 8.12, including stockpiles outside Zone 1.

7D.6 Inlets (Clause 7.9.7)

Every inlet that brings urban runoff shall have a sediment forebay, a constructed wetland inlet zone or a gross pollutant trap, designed under Chapter 8 (Annex 8D).

7D.7 Timing (Clause 7.9.8)

Desilting shall be complete, and the waterbody made safe, by 31 May. No excavation shall be left open, and no sluice or weir left dismantled, during the SW monsoon.

7D.8 Completion records

  • (a) As-built survey and revised stage–storage curve. The curve is the one that Clause 7.7.1(b) requires "after the last desilting".
  • (b) Volume removed, its disposal site, and the silt test results.
  • (c) Photographs of the bund, weir, sluices and inlet works.
  • (d) Update of the inventory record (Annex 7A: SSC_DATE, LEVEL_DATE, CONDITION).

Table 7D.1 — Hold points for desilting and restoration works

Hold point Check Clause
1. Before excavation Pre-works survey, pit logs, silt tests, and hydrogeological report if deepening 7.9.1, 7.9.3
2. Original bed reached Levels checked against pit logs; no excavation below the original bed unless approved 7.9.2
3. Edges formed Side slopes or safety bench as 7D.3 7.9.4
4. Inlet works Forebay, wetland inlet zone or GPT built 7.9.7
5. Completion (by 31 May) As-built survey, stage–storage curve, silt disposal record 7.9.8, 7.7.1(b)

Annex 7E — Glossary of Kashmiri and Urdu waterbody terms and regional variants

Supports Clause 7.2 and Clause 7.3 of Chapter 7.

The terms below are Kashmiri and Urdu words, with the Jammu usage of the instruments, for waterbodies, springs, channels and land in Jammu and Kashmir. Many of them appear in the names of lakes, marshes, springs and places (Hokersar, Brari Nambal, Kokernag, Tsunth Kol, Rani Talab). The name used in the Revenue, I&FC, LCMA, WUCMA or municipal record for each waterbody should be recorded in the inventory (Annex 7A) alongside the Manual's term. A meaning is given below only where it was confirmed in G. A. Grierson, A Dictionary of the Kashmiri Language (1916–1932), or in J. T. Platts, A Dictionary of Urdu, Classical Hindi, and English (1884), both as served by the Digital South Asia Library, with the page shown there, or in a Jammu and Kashmir statute, bye-law or plan. Three cautions apply. Grierson gives Kashmiri headwords in Roman and in the Kashmiri form of Devanagari, and gives a Perso-Arabic spelling only for words borrowed from Persian or Arabic (such as cashma, hōz and talab); no Perso-Arabic spelling is given here for a Kashmiri word unless a dictionary gives it, and the Kashmiri Perso-Arabic spellings of nāg, kŏl, sar and nambal are to be supplied by an editor. No Dogri dictionary was consulted, so the Jammu terms (khad, kuhl, talab) are given in the sense the Jammu Master Plan 2032 and UBBL-2021 use them, and their Dogri forms are to be checked. Meanings are the dictionaries' English glosses, and modern usage may be narrower or wider. Every term whose meaning or regional use was not confirmed is in Table 7E.4. The list is to be extended by the State Stormwater Technical Committee, with modern Revenue, I&FC and municipal usage and with a Dogri dictionary.

The Manual's term for a pond or tank in Jammu and Kashmir is talab (तालाब; تالاب; Kashmiri talāv): it is the word the Union Territory's own instruments use ("Talav" and "talab, village tanks" in UBBL-2021; "talabs" in the Jammu Master Plan 2032), it is found with the pond or tank sense in both the Kashmiri and the Urdu dictionary, and it names places in Jammu (Rani Talab, Talab Tillo). Because Kashmiri talab (طلب) is a different word meaning "pay, wages, salary" (Grierson, p. 1000), it is always written with its script or glossed on first use as "talab (pond or tank)". Natural waterbodies keep their own words in names: sar (lake), nambal (marsh) and nāg (spring); and an engineered detention basin is never called a talab, sar, nambal or nag: it is a detention pond, with the local word in brackets where that helps.

Table 7E.1 — Waterbodies

Term Meaning Source of the term Manual term (Clause 7.2)
तालाब / تالاب (tālāb); Kashmiri तलाव् (talāv) Platts: "Pond, pool, tank, reservoir of water ( = talāʼo; cf. tāl)"; Grierson: talāv, "an artificial pond, a tank". UBBL-2021: "water body, pond and Talav"; "talab, village tanks" (clause 7.12(c)); Jammu Master Plan 2032: "talabs" Platts, p. 306; Grierson, p. 1003; UBBL-2021; JMP 2032 Talab (pond or tank), see the definitions after Clause 7.2
सर् (sar) "a lake, a large sheet of water" (Grierson, sar 1); saras, "a lake, pool, pond" Grierson, pp. 928 and 938 A lake, in names only (Hokersar, Khushalsar, Gilsar, Mansar, Surinsar, Budsar); a lake for this chapter
डल् (ḍal) "a lake; N. of a large lake near Śrīnagar" (Grierson, ḍal 1); Ḍal-darwāza, "the Ḍal gate, the flood-gate of the Ḍal lake. When the Jihlam … is low, the gates remain open; but when the river rises to a certain height, they automatically close, thus preventing inundation of the land round the lake". Not the same word as Grierson's dal 1 and dal 2 (a leaf; pounding) Grierson, p. 210 The name Dal only; Dal Gate is the lake's outlet under Clause 7.8
नंबल् (nambal) "a grass-grown lake, a lake choked by vegetation, a shallow lake, a marsh, swamp"; nambala-syomu, "the silt of a marsh"; nambali-boṭhu, "the edge, bank, or margin of a marsh" Grierson, p. 637 Nambal (marsh; flood-absorption marsh), see the definitions after Clause 7.2; a wetland under Clause 7.12
होज़् / حوض (hōz) "a reservoir, cistern, pond, pool, tank, vat, trough, basin of a fountain" Grierson, p. 368 A built cistern or pool; a talab for this chapter where it holds water
ल्यम्ब् (lĕmb) "the mud at the bottom of standing or running water, sediment …; land in which springs occur" Grierson, p. 524 Spring-fed wet land; optional, always glossed

Table 7E.2 — Springs, streams and channels

Term Meaning Source of the term Manual term (Clause 7.2)
नाग् (nāg) Grierson, nāg 2: "a snake, esp. a fabulous serpent-demon … In Kashmīr, they are the deities of springs …; a fountain, a spring of water"; nāga-wuziñ, "the steady perpetual flow of water from a spring". Platts gives ناگ only the sense of a snake Grierson, p. 624; Platts, p. 1116 Spring (nag), as in Kokernag and Verinag, see the definitions after Clause 7.2
چشمه (cashma) "a spring, source, fountain" (Grierson); Cashma Shāhī, "N. of a fountain on the northern shore of the Śrīnagar city lake"; Platts, ćashma: "A spring, source, fount; a fountain; — spectacles" Grierson, p. 177; Platts, p. 434 Spring (cashma), see the definitions after Clause 7.2
क्वल् (kŏl) Grierson, kŏl 2: "a river, a stream, a brook …; an artificial stream, canal, irrigation channel"; kŏla-boṭhu, "the bank of a river"; kŏla-ganḍ, "stopping the flow of water through an irrigation channel". Not Platts's kūl (کول, "bank … a pool, pond, lake"), a different word Grierson, p. 437; Platts, p. 863 Kol (stream or canal), as in the Tsunth Kol, see the definitions after Clause 7.2
नाल / نالا (nāla; nālā) Grierson, nāla 1: "an artificial watercourse, a channel, a canal (esp. when forming a boundary between two pieces of land)"; Platts, nālā: "A watercourse; channel …, a ravine; a rivulet, brook, canal; a drain, gutter". UBBL-2021: "Nallas" (clause 5.2.5); the master plans: "Nallah" Grierson, p. 633; Platts, p. 1117; UBBL-2021; SMP 2035; JMP 2032 Nallah (natural or artificial drainage channel)
खड्ड (khaḍḍ; khad) Jammu usage: "ravines, locally called Khads are transformed into gushing torrents" (JMP 2032, §2.4); "any other river/khad" (UBBL-2021, clause 7.12(b)). Grierson's khŏḍ is "a pit, a hole dug in the ground; a ditch" and Platts's khaḍḍā "Pit, cavity, hollow", with no stream sense JMP 2032; UBBL-2021; Grierson, p. 392; Platts, p. 873 Khad (seasonal torrent or ravine stream), see the definitions after Clause 7.2; always glossed
कूहल (kuhl); khul An irrigation channel. The Water Resources Act, 2010 counts "zamindari khuls" among its hydraulic works; Grierson has no kuhul headword (his kúl is a spelling of kŏl 2) Water Resources Act, 2010, section 2 [TBC]; Grierson, p. 437 Kuhl or khul (irrigation channel), see the definitions after Clause 7.2; always glossed

Table 7E.3 — Land and Revenue classes

Term Meaning Source of the term Use in this Manual
Gair Mumkin Khad (also "Ghir Mumkin Khad") A Revenue class of drainage land in Jammu, covering "more than thirty percent of the JDA land" JMP 2032, §§2.4 and 12.2.3 A Revenue class only, glossed as land recorded as uncultivable stream-bed; its hydraulic extent is the functional khad (definitions after Clause 7.2)
رکهہ (rakh) Platts: "A preserve (for grass, or game, &c.), a grassy wood". Official usage: "Wetlands Reserves (Game Reserves and State Rakhs)" (Wildlife Department, 2024); names such as Rakh-e-Arth, Rakhi Shalbug and Rakh-e-Gund Aksha. Grierson's rakh headwords have no water sense Platts, p. 597; Wildlife Department, 2024; SMP 2035 Rakh (reserved wetland or grassland), in names only; not used as a generic term for a marsh

Table 7E.4 — Terms not yet verified

These terms or senses are in use but were not confirmed in a dictionary during research for this Manual. They shall not be used in a record or a drawing as defined terms until verified.

Term Reported meaning or use Status
kahcharai Land recorded as grazing land (Kahcharai Act, Svt. 2011) The Act was not read; dictionary meaning not checked; used in this Manual only as a Revenue class
ghair-mumkin "Impossible", that is, land that cannot be cultivated Dictionary meaning not checked; the gloss in Table 7E.3 is this Manual's
Dogri forms of talab, khad, kuhl and nallah, and other Dogri waterbody words Regional words and spellings of the Jammu division No Dogri dictionary was consulted
Kashmiri Perso-Arabic spellings of nāg, kŏl, sar and nambal Spellings for signs and records in Urdu script Not given by Grierson; to be supplied by an editor

The Manual uses the terms in the last column of Tables 7E.1 and 7E.2, the land terms of Table 7E.3, and the Jammu and Kashmir terms defined after Clause 7.2.


Form 7-1 — Waterbody Sheet

Supports Clauses 7.3.2, 7.4 and 7.15(1) of Chapter 7.

Draft form — Jammu and Kashmir Stormwater Design Manual, Draft v1.0. One sheet per waterbody. Attach the plan of Clause 7.3.2 at 1:1,000 or larger.

Table 7F.1 — Form 7-1, Section A: Project and waterbody

No. Field Entry Clause
A1 Project name and Authority file number ______ —
A2 Waterbody name (English and Urdu) and inventory ID (Annex 7A), if any ______ 7.3.1
A3 Waterbody type (Clause 7.2) ______ 7.2
A4 Position: within the site / within 100 m of the site boundary / downstream within the Chapter 5 extent ______ 7.3.2
A5 Survey numbers and village ______ 7.3.1(a)
A6 Custodian ______ 7.3.1(b)
A7 Sources checked (tick): Revenue records and village maps (Gair Mumkin Khad, nambal, rakh, kahcharai), UBBL-2021 site plan (water bodies, flood areas, 0.3 m contours), SMP 2035 and JMP 2032 buffers and land use, I&FC flood zonation, channel and gauge records, SMC, JMC and UEED drain and dewatering-station records, LCMA and WUCMA records, Ramsar, conservation-reserve and wetland boundaries, dam-operator records, High Court and NGT lists ☐; I&FC / Halqa Panchayat registers ☐; Authority inventory or court list ☐; historical maps and imagery, including NWIA ☐; site survey ☐ ______ 7.3.3
A8 Where sources conflict: which extent governs (the larger) ______ 7.3.3
A9 Datum of all levels, and conversion from any I&FC datum ______ 7.3.5

Table 7F.2 — Form 7-1, Section B: Levels and features

No. Field Entry Clause
B1 FTL (tanks, lakes, ponds) or top of bank (channels), m ______ 7.2
B2 MWL (tanks), m, and basis (I&FC record or 1% AEP computed) ______ 7.2
B3 TBL, lowest point (tanks), m ______ 7.3.1(d)
B4 1% AEP flood level, m, and source (adopted map / hydraulic study / not available) ______ 7.3.4
B5 Drainage area at the site (channels), ha ______ 7.4.1(b)
B6 Supply channels, surplus courses, sluices and surplus weirs shown on plan (yes / no) ______ 7.3.2
B7 Known encroachments, with date recorded ______ 7.3.1(g)

Table 7F.3 — Form 7-1, Section C: Setback

No. Field Entry Clause
C1 Basis of setback: mapped extent / hydraulic study / fixed width (Annex 7B) ______ 7.15(1)
C2 Is a hydraulic study required under Clause 7.3.4 (a) / (b) / (c)? ______ 7.3.4
C3 Floodway outer edge, m from FTL or top of bank, and how delineated ______ 7.6.1
C4 Zone 1 width, m (greatest of 15 m, floodway edge, MWL contour) ______ 7.4.3
C5 Zone 2 width, m (to 1% AEP extent + 10 m, or 10 m) ______ 7.4.4
C6 Wider statutory or approval setback, if any, and its source ______ 7.4.5
C7 Setback applied: Manual standard / a wider statutory, plan, court or approval line: UBBL-2021, clause 7.12(b), 50 m (major rivers and any other river or khad), 30 m (lakes) or 20 m (unlisted rivulets, tributaries, minor canals and watercourses) from the edge of the bank; clause 5.2.5, 30 m green buffer from the highest water level along nallahs and rivers; a buffer of the Srinagar Master Plan 2035 (Tables 8-2 and 8-3; 100 m round an unlisted wetland reserve, §8.2.3) or of the Jammu Master Plan 2032 (§7.3.3, from Full Tank Level; its 15 m and 5 m khad lines are overridden by clause 7.12 where the bye-laws apply); the High Court's 200 m round Dal and, as reported, round Wular, and the 200 m round Nigeen applied by LAWDA (as quoted); the boundary of a Ramsar site, a Wildlife Conservation Reserve or a notified wetland; an I&FC line under the Water Resources Act, 2010; a flood basin notified under Part VI of that Act or a flood plain zone under the Flood Plain Zones Act, 2005 (none notified); or other (state which) ______ 7.4, Disclosure
C8 Uses proposed in Zone 1 and Zone 2, and the custodian's NOC for any work in Zone 1 ______ 7.5, 7.15(5)
C9 Fill proposed in the flood fringe (yes / no); if yes, Form 7-3 attached ______ 7.6.3
C10 Zone 1 marker positions shown (not more than 30 m apart) ______ 7.13.4

Table 7F.4 — Form 7-1, Section D: Prepared by

Field Entry
Name, registration and empanelment number (Clause 10.6) ______
Signature and date ______
Licensed surveyor for the levels (name, licence number) ______

Form 7-2 — Tank Storage Credit Sheet

Supports Clauses 7.7, 7.8, 7.11, 7.14 and 7.15(4) of Chapter 7.

Draft form — Jammu and Kashmir Stormwater Design Manual, Draft v1.0. One sheet per tank whose storage is counted. Storage that fails any item in Section B shall not be counted (Clause 7.7.1).

Table 7F.5 — Form 7-2, Section A: Tank and scheme

No. Field Entry Clause
A1 Tank name and inventory ID (Annex 7A); custodian ______ 7.3.1
A2 Scheme in which storage is counted: basin plan / regional facility / fee-in-lieu (S-5) ______ 7.7.1, 7.11
A3 Cascade modelled: uppermost tank ______ to outfall ______ ______ 7.7.2
A4 Datum ______ 7.3.5

Table 7F.6 — Form 7-2, Section B: Conditions for counting storage

No. Condition Date / reference Met (yes / no) Clause
B1 FTL, MWL, TBL, weir crest and length, sluice sills surveyed within the previous 5 years ______ ______ 7.7.1(a)
B2 Stage–storage curve from a bathymetric and topographic survey within 5 years or after the last desilting, whichever is later ______ ______ 7.7.1(b)
B3 Documented operating rule agreed with the custodian (Annex 7C) ______ ______ 7.7.1(c), 7.8
B4 Weir, sluices and bund under an O&M plan; latest pre-monsoon inspection found them serviceable ______ ______ 7.7.1(d), 7.14.4
B5 Custodian's written concurrence ______ ______ 7.7.1(e)

Table 7F.7 — Form 7-2, Section C: Levels and creditable volume

No. Item Value Clause
C1 Starting level: FTL, or cushion level under a rule meeting Clause 7.8.2, m ______ 7.7.3
C2 If a cushion is used: controllable outlet (type) and drawdown time, h ______ 7.8.2(a)
C3 If a cushion is used: reliability from continuous simulation, % of SW monsoon seasons (≥ 90%) ______ 7.8.2(c)
C4 Computed maximum level, 1% AEP inflow with climate factor routed through the cascade, m ______ 7.7.4
C5 MWL, m; is C4 ≤ MWL? ______ 7.7.4(a)
C6 Freeboard C4 to TBL, m; I&FC freeboard standard, m; met? ______ 7.7.4(b)
C7 Storage between C1 and C4, from the stage–storage curve, m³ ______ 7.7.5
C8 Volume already committed to another facility or scheme, m³ ______ 7.7.5
C9 Creditable volume = C7 − C8, m³ ______ 7.7.5
C10 Register entry under Clause 10.17 (fee-in-lieu storage) ______ 7.11.2(d)

Table 7F.8 — Form 7-2, Section D: Bund safety

No. Item Entry Clause
D1 Specified dam under the Dam Safety Act, 2021? Height, crest length, capacity, maximum flood discharge ______ 7.14.1
D2 Hazard class: high / low ______ 7.14.2
D3 High hazard: weir passes 1% AEP at MWL with freeboard; 0.2% AEP check without overtopping ______ 7.14.3(a)
D4 High hazard: breach analysis and emergency action plan (references) ______ 7.14.3(b), (c)
D5 High hazard: independent check under Clause 10.6 (name) ______ 7.14.3(d)

Table 7F.9 — Form 7-2, Section E: Signatures

Role Name and designation Signature and date
Designer (Clause 10.6) ______ ______
Independent checker, where Clause 7.14.3(d) applies ______ ______
Custodian's concurrence (Clause 7.7.1(e)) ______ ______

Form 7-3 — Compensatory Storage Calculation (by elevation band)

Supports Clauses 7.6.3 to 7.6.5, 7.9.5 and 7.15(3) of Chapter 7.

Draft form — Jammu and Kashmir Stormwater Design Manual, Draft v1.0.

Method

  1. Fix the lower limit: the normal water level of the waterbody, or the 50% AEP (2-yr) level where higher (Clause 7.6.4(b)).
  2. Fix the upper limit: the 1% AEP flood level (with the climate factor).
  3. Divide the range into bands of not more than 0.3 m. The top band may be thinner.
  4. For each level z at a band boundary, measure on plan:
    • A_fill(z): the area of the fill footprint where existing ground is below z; and
    • A_cut(z): the area of the excavation where finished ground is below z and existing ground was above z (new flooded area).
  5. For each band, by the average end-area method: V = (A(z_bottom) + A(z_top)) / 2 × band thickness. Do this for fill (volume lost) and for excavation (volume gained).
  6. Check each band: volume gained ≥ volume lost. A surplus in one band does not make up a shortfall in another (Clause 7.6.4(b)).
  7. Check the other conditions of Clause 7.6.4(c) to (f) in Section C.

Figure 7.2 in Chapter 7 shows the method.

Table 7F.10 — Form 7-3, Section A: Levels

No. Field Entry Clause
A1 Waterbody, reach, and inventory ID ______ 7.6.4(c)
A2 Normal water level, m; 50% AEP level, m; lower limit (the higher), m ______ 7.6.4(b)
A3 1% AEP flood level with climate factor, m (upper limit) ______ 7.6.4(b)
A4 Band thickness, m (≤ 0.3) and number of bands ______ 7.6.4(b)
A5 Datum ______ 7.3.5

Table 7F.11 — Form 7-3, Section B: Band-by-band balance

Band From (m) To (m) A_fill bottom (m²) A_fill top (m²) Volume lost (m³) A_cut bottom (m²) A_cut top (m²) Volume gained (m³) Gained ≥ lost?
1 ______ ______ ______ ______ ______ ______ ______ ______ ______
2 ______ ______ ______ ______ ______ ______ ______ ______ ______
3 ______ ______ ______ ______ ______ ______ ______ ______ ______
4 ______ ______ ______ ______ ______ ______ ______ ______ ______
Total ______ ______

Add rows as needed.

Table 7F.12 — Form 7-3, Section C: Other conditions

No. Condition Met (yes / no) and evidence Clause
C1 Fill is in the flood fringe, not the floodway, and for a permitted use ______ 7.6.2, 7.6.3
C2 Excavation is in the same reach of the same waterbody, hydraulically connected, and not further downstream than the fill ______ 7.6.4(c)
C3 Excavation drains by gravity as the flood recedes; no pumping; no permanent pool below normal water level ______ 7.6.4(d)
C4 Excavation built before, or at the same time as, the fill ______ 7.6.4(e)
C5 Covenant or handover so that it is never filled (reference) ______ 7.6.4(f)
C6 Not counted as detention or retention under Chapter 4 ______ 7.6.5
C7 Signature of designer (Clause 10.6) and date ______ 10.6

Worked example

Illustrative — not design values. A site in the flood fringe of a channel needs a fill pad for a permitted Zone 2 use (Clause 7.5.2). The inputs are assumed.

  • Normal water level 10.00 m; 50% AEP level 9.80 m. Lower limit = 10.00 m (the higher).
  • 1% AEP flood level 11.20 m. Range 1.20 m, so four bands of 0.30 m.
  • The fill footprint is 1,600 m². Existing ground across the footprint rises evenly from 10.00 m to 11.20 m, so the area of footprint below each level is: 0 m² at 10.00 m; 400 m² at 10.30 m; 800 m² at 10.60 m; 1,200 m² at 10.90 m; 1,600 m² at 11.20 m.
  • The excavation is a graded cut beside the channel, with its floor at 10.00 m. The new flooded area below each level (first trial) is: 300 m² at 10.00 m; 900 m² at 10.30 m; 1,100 m² at 10.60 m; 1,500 m² at 10.90 m; 1,500 m² at 11.20 m.

Step 1 — volume lost, band by band (V = average area × 0.3 m):

  • Band 1: (0 + 400) / 2 × 0.3 = 60 m³
  • Band 2: (400 + 800) / 2 × 0.3 = 180 m³
  • Band 3: (800 + 1,200) / 2 × 0.3 = 300 m³
  • Band 4: (1,200 + 1,600) / 2 × 0.3 = 420 m³
  • Total: 960 m³

Step 2 — volume gained, first trial:

Table 7F.13 — Worked example: first trial (illustrative)

Band From (m) To (m) Volume lost (m³) A_cut bottom (m²) A_cut top (m²) Volume gained (m³) Gained ≥ lost?
1 10.00 10.30 60 300 900 180 Yes
2 10.30 10.60 180 900 1,100 300 Yes
3 10.60 10.90 300 1,100 1,500 390 Yes
4 10.90 11.20 420 1,500 1,500 450 Yes
Total 960 1,320

Every band passes. Note that a simple total balance would hide a failure if, for example, the cut were made deeper and narrower: suppose the designer instead offers a cut with new flooded areas of 1,400 m² at 10.00 m, 1,400 m² at 10.30 m, 1,000 m² at 10.60 m, 600 m² at 10.90 m and 200 m² at 11.20 m.

Table 7F.14 — Worked example: deeper, narrower cut (illustrative)

Band From (m) To (m) Volume lost (m³) A_cut bottom (m²) A_cut top (m²) Volume gained (m³) Gained ≥ lost?
1 10.00 10.30 60 1,400 1,400 420 Yes
2 10.30 10.60 180 1,400 1,000 360 Yes
3 10.60 10.90 300 1,000 600 240 No
4 10.90 11.20 420 600 200 120 No
Total 960 1,140

The total gained (1,140 m³) exceeds the total lost (960 m³), but bands 3 and 4 are short by 60 m³ and 300 m³. The surplus low down cannot be counted against them: the low storage fills early in every flood and is not available when the fill takes away storage near the peak. This design fails Clause 7.6.4(b) and must be regraded so that the upper bands gain at least as much as they lose, as in the first trial.